![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 19 July 2006
REFERENCE: 0194-2005
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
7590
|
|
Name of Scheme:
|
Hossegor
|
|
Address of Scheme:
|
14 Rivera Street MIAMI QLD 4220
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Helen Maree Montgomery, the Owner(s) of lot 4
|
I hereby order that in relation to the application seeking an order
that pavers installed on common property by the Respondents (Debra and Francis
Taylor – owners of Lot 1) be removed in this matter that the Body
Corporate will approve their installation within 6 months
of the date of this
order conditional upon them having been installed by a qualified tradesperson.
I order further that if the above
condition is not complied with then the pavers
will be lifted and the area returned to its original condition by 1 April 2006.
I
order further that the costs associated with complying with this order will be
paid for by the Respondents.
I order further that in relation to the application seeking an order that the cat cage installed by the Respondents be removed that the Respondents remove the cat cage within 6 months of the date of this order unless approval is given by the Body Corporate before the final date for compliance with this order. I order further that in relation to the application to remove the Respondents cat that the Body Corporate will approve the keeping of this one cat only by the Respondents within their lot only and not on any part of the common property within 6 months of the date of this order. I order further that in relation to the application regarding payment of the extra expense of treating for Redback Spiders that each lot owner is to pay the cost (between $20 and $30) above the pest treatment costs as agreed at the AGM. I order further that in relation to the application seeking evidence of approval of the installation of the roof on the Respondents pergola I order that the Body Corporate approve the installation of the roof within 6 months of the date of this order conditional upon it having been installed by a qualified tradesperson. I order further that if this condition is not complied with that the roof is to be removed by 1 April 2006. I order further that the costs associated with complying with this order will be paid for by the Respondents. I order further that all other orders sought in this application are dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0194-2005
"Hossegor" CTS 7590
The applicant has sought the following orders of an adjudicator under the
Body Corporate and Community Management Act 1997 ("the Act") -
1. Remove bamboo structure on common property; 2. Remove pavers on common property; 3. Remove the pet cage on common property; 4. Restore the termite barrier interfered with by extension to interior/exterior wall; 5. Remove cat; 6. Provide evidence of council permit for pergola roof; 7. Obtain body corporate approval for changes to exterior walls/common property; 8. Provide evidence of the integrity of the concrete slab after changes to extensions; 9. Detailed identification of any changes to common property that occurred as a result of extensions; 10. Provide evidence regarding the effects of stability of the building as a result of repositioning of interior/exterior ground floor walls; 11. Provide clarification of any changes made to common property eg front doors.
Jurisdiction:
This is a
dispute between an owner (Helen Montgomery - the Applicant) and other owners
(Debra and Francis Taylor – the Respondents)
of lots in the Hossegor
Community Titles Scheme concerning the nature and extent of renovations made to
their lot and common property.
This is a matter that falls within the dispute
resolution provisions of the legislation (see sections 227, 228 and 276 of the
Act).
Section 276(1) of the Act provides that an adjudicator may
make an order that is just and equitable in the circumstances (including a
declaratory
order) to
resolve a dispute, in the context of a community titles
scheme, about –
a) a claimed or anticipated contravention of the Act or the community management statement; or b) the exercise of rights or powers, or the performance of duties, under this Act or the community management statement; or c) a claimed or anticipated contractual matter about – (i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or (ii) the authorisation of a person as a letting agent for a community titles scheme.
An order may require a person to act, or
prohibit a person from acting, in a way stated in the order (section
276(2) of the Act). An adjudicator’s order may contain ancillary or
consequential provisions the adjudicator considers necessary
or appropriate
(section 284(1) of the Act).
Application and
Submissions:
Under section 243 of the Act, a copy of the
application was provided to the Respondents and all other owners within the
scheme with an invitation to
them to respond
to the matters raised in the
application. The Respondents have provided a submission to the
application.
The brief facts of the matter are as follows. The Applicant
alleges numerous breaches of the Act, regulation module and by-laws applicable
to the scheme principally as a result of renovations done by the Respondents to
their lot
and improvements to the common property.
To resolve these matters the
Applicant seeks 12 different orders which are listed above.
I propose to
outline each issue, outline
the allegations from the Applicant and reply by the
Respondents and thereafter make my
determination on each issue.
Determination:
"Hossegor" was established as a building
units plan (now termed a building format plan) in 1987. Having been
established under the
Building Units and Group Titles Act 1980, under the
transitional provisions of the (new) Act it became subject to the provisions of
the (new) Act upon its commencement.
A new community management statement was
lodged in 2000 which brought the scheme under the regulation of
the Body
Corporate and Community Management (Standard Module) Regulation 1997 ("the
Standard Module"). Despite these legislative changes the by-laws applicable to
the Hosseger scheme remain those as provided
in Schedule 3 of the Building
Units and Group Titles Act 1980.
The Applicant has raised the
following issues:
Bamboo structure on common property
The
Applicant alleges that the Respondents have installed a bamboo structure on the
front fence line which is on the common property
of the scheme. The Applicant
alleges further that the installation was without Body Corporate
approval.
The Respondents advise that they had installed a bamboo
structure to give them some privacy. They go on and advise that the structure
has now been removed. They make no comment regarding its location being on
common property or otherwise. I do note that they do
not specifically deny this
aspect of the allegation.
As the bamboo structure no longer appears to
be in place I can see no reason to make the order as sought. I will however
make the
comment that if an improvement is made to common property then it is
usual that Body Corporate approval is first obtained (see section 159 of
the Act and section 114 of the Standard Module). To do otherwise may
result in legal action being taken against the offending lot owner and the
imposition
of significant costs in the form of legal fees, rectification costs
etc.
Accordingly I will make no order regarding this
aspect of the application.
Remove pavers on common
property
The Applicant alleges that late in 2004 the Respondents
installed pavers onto common property without Body Corporate approval. The
Applicant has provided a photograph of the subject area which appears to be
about 16 square meters in area.
The Respondents acknowledge the
presence of the ‘new’ paved area and state that this area was
previously ‘grassed’.
The Respondents advise that the grass did not
grow well because of the surrounding trees. They do not deny the allegation
that
Body Corporate approval was not given prior to the installation of the
pavers.
I accept that the Respondents have installed the pavers without
the prior approval of the Body Corporate (as required in By-law 4
of the
Community Management Statement, section 159 of the Act and section
114 of the Standard Module). I also accept that the subject area would be
shaded by the surrounding trees and therefore difficult keep
grass growing on.
In determining what order I will make regarding this matter it is
relevant to note that common property is property owned by all owners
and
managed on their behalf by the Body Corporate. Therefore it is important to
consider the nature of the unauthorised improvements
and their
‘value’ to all lot owners collectively.
As the improvements
have already been completed to order their removal would be counter- productive
to all lot owners and occupiers
within the scheme generally. Therefore I will
order that the Body Corporate approve their installation within 6 months of the
date
of this order conditional upon them having been installed by a qualified
tradesperson. I would expect that if this condition is
not complied with that
the pavers will be lifted and the area returned to its original condition or a
qualified tradesperson would
be engaged to reinstall the pavers. I will also
order that the costs associated with these works will be borne by the
Respondents.
Remove the pet cage on common property
The Applicant alleges that the Respondents constructed a large pet cage (cat
enclosure). The Applicant alleges that the cage was
installed without Body
Corporate approval on common property. The Applicant states that the timber
construction is of concern because
of the ongoing problems with termites in the
area. The Applicant points out that regular pest inspections identify the
necessity
to remove timber which is termite susceptible being in contact with
the ground and the building. The Applicant also alleges that
the cage is highly
visible from the street. To this end the Applicant has provided photographs of
the cage taken from a location
next to some rubbish bins. I note that the
Applicant has only just recently taken issue with the cage.
The
Respondents do not deny that the cage is on common property or that they did not
receive approval from the Body Corporate before
its installation. They say that
the cage is constructed of treated timber which is termite resistant. The
Respondents have provided
photographs of the cage as seen from the street.
I am unable to clearly identify the cage in the photographs provided by
the Respondents. The cage appears to blend in with the surrounding
foliage etc.
I do not believe its installation detracts from the amenity of the scheme
however by its nature the cage limits access
to this area of the common property
as a thoroughfare or simply its use by other lot owners or occupiers. As
mentioned above common
property is property owned by all owners and managed on
their behalf by the Body Corporate.
Free access to all areas of common
property is a right that all lot owners and occupiers must enjoy and accordingly
I will make an
order that the cage be removed as correct Body Corporate approval
has not been secured. If the Respondents wish to seek the necessary
approvals
them they will need to seek approval in accordance with section 114 of
the Standard Module. I will order that the Respondents remove the cat cage that
is located on common property within 6 months
of the date of this order.
Remove cat
The Applicant alleges that
the Respondents brought a cat into the scheme without the requisite Body
Corporate approval in 1997. The
Applicant alleges that the Respondents cat died
and they acquired a second cat from a former neighbour. The Applicant alleges
that
the Respondents were advised of the need to seek Body Corporate approval to
keep an animal but despite this have never sought the
required approval. The
keeping of any animal within the scheme is subject to By-law 11 (Keeping of
animals) which requires written
consent to keep an animal in a lot or on common
property.
The Respondents admit that they have a cat which was
acquired from an animal refuge but deny cat ownership when they moved into the
scheme. The Respondents say that the presence of the cat has not been a
‘secret’ and that all other owners have known
about the cat for a
significant period of time. The Respondents advise that the presence of the cat
has never been the subject of
any complaint to their knowledge. This is no
doubt due to the Respondents ‘vigilance’ and level of care provided
to
the cat.
Considering the length of time the cat has been ‘in
residence’ and not the subject of significant complaint I will order
that
the Body Corporate approve the keeping of this one cat only by the Respondents
within their lot only and not on common property.
This approval is to be given
within 6 months of the date of this order. To be very clear my order relates to
the one cat currently
in residence. It does not provide a precedent for the
Respondents to acquire a further (second) cat or another in the future without
the prior written approval of the Body Corporate. Any further applications to
the Body Corporate will have to be dealt with on their
merits and may be
refused.
In the event that Body Corporate approval is given for the
installation of a cat cage (as referred to above in the discussions re
the
installation of the cat cage) then necessarily the Body Corporate is to approve
the cats’ presence on common property in
the cage only.
Pest control
The Applicant alleges that a pest treatment
for spiders (at a cost of $70-80 per lot) was performed on the say so of one of
the Respondents
(in particular Francis Taylor). This treatment had not been
approved however a cockroach treatment had been previously approved
at the AGM
at a cost of $50 per lot. The Respondent raises the issue that this is an
example of the unilateral decision making that
goes on in the scheme and how
little regard is had for usual body corporate approval processes.
The
Respondents state that a cockroach treatment had been approved (at the recent
AGM) and for convenience the lot owners agreed to
be charged $50 each for the
service payable when they were levied other payment to other funds administered
by the Body Corporate.
However during the treatment Redback Spiders were
discovered. The Respondents (Francis Taylor) made an effort to contact other
lot owners however only spoke with the occupier of one lot regarding the matter
who agreed that the spider treatment should proceed.
The Respondents advise
that another issue considered was the presence of young children in the scheme.
For these reasons a decision
was made to treat for the spiders without reference
to the usual approval process. The Respondents suggest that this approach was
only sensible considering the possible consequences to some occupiers of a
bite.
In addressing this matter it is important to clearly identify in
what context the initial pest treatment was ‘approved’
at the AGM.
The treatment appears to be as per section 119 of the Standard Module, an
‘agreement to supply services by the body corporate’. Such
agreements typically include ‘bulk’
pest control treatments for lot
owners. Not all lot owners need be included in agreements of this sort if they
choose not to be.
Accordingly they would attend to the matter themselves at
their own expense.
The actions of the Respondents (Francis Taylor) were
reasonable in the circumstances. The cost of having to do the work done at a
subsequent visit, the clear urgency and possible life threatening consequences
to all lot owners (and occupiers and casual visitors)
and efforts to raise the
matter with other lot owners are all matters that I have taken into account. I
therefore believe that the
extra treatment and associated expense incurred by
each lot owner is reasonable. The just and equitable order that must follow is
that each lot owner is to pay the extra cost of the Redback Spider
treatment.
Renovations
The balance of the issues raised by
the Applicant relate to the renovations done by the Respondents. The Applicant
alleges generally
that neither the Body Corporate or local government approval
have been given for these works.
The renovations and associated
issues are:
• Remodelled their kitchen, bathroom and toilet;
• Installed a roof onto the pergola;
• Enclosed their garage (walls and new doors);
• The structural integrity of the scheme building may have been affected by the movement of an internal wall;
• Disturbed the chemical termite barrier.
The
Respondents have provided an extensive reply to these allegations. I will deal
with their reply under the following headings.
Renovations - Kitchen,
bathroom and toilet
The Respondents advise that they did renovate
the kitchen, bathroom and toilet in their lot but did not move any walls
internally
or externally. The Respondents also advise that the toilet was not
moved.
Internal renovations of the sort discussed above do not
generally require Body Corporate approval. There is nothing in the by-laws
applicable to the scheme, the Act or Standard Module which requires approval for
these types of renovations. Whether there are local
government approvals that
are
required to be given is not a matter I have jurisdiction to consider. The
enforcement of local government
regulations is a matter
for the relevant local
authority.
Accordingly I will make no order regarding this aspect of the
application.
Renovations – Roof on pergola
The Respondents admit that they have caused a roof to be installed onto
the pergola as was done to other units in the scheme. The
Respondents admit
that they did not receive the necessary Body Corporate or local government
approval to undertake this work. They
explain that they are now seeking local
government approval and will seek Body Corporate approval in due
course.
The pergola is of course common property and is the property of
all owners within the scheme and managed on their behalf by the Body
Corporate.
The installation of the roof on any pergola within the scheme would require the
necessary Body Corporate approval in
accordance with section 159 of the
Act and section 114 of the Standard Module and By-law 5.
As the
roof is now in place it would be unreasonable to order its removal. Therefore I
will order that the Body Corporate approve
the installation of the roof within 6
months of the date of this order conditional upon it having been installed by a
qualified tradesperson.
I would expect that if this condition is not complied
with that the roof be removed or a qualified tradesperson be engaged to
reinstall
it. I will also order that the costs associated with these works be
borne by the Respondents.
Renovation (enclosure) of garage and
structural integrity of scheme building
The Respondents state that
during the process of organising the renovations to the kitchen, bathroom and
toilet they became aware
of the limitations that they had to operate under (i.e.
they could not extend or improve common property without approval). This
caused
them to reconsider their original plans to extend their living space. It was
decided to enclose the garage to achieve their
objective. The respondents
advise that these renovations did not affect any structural elements of the
scheme building.
Internal renovations of the sort discussed above
generally do not require Body Corporate approval. There is nothing in the
by-laws
applicable to the scheme, the Act or Standard Module which requires
approval for this type of renovation. Whether there are local
government
regulations that are
required to be complied with is a matter I do not have
jurisdiction to deal with. The enforcement
of these regulations is a matter
for
the relevant local government.
Accordingly I will make no order
regarding this aspect of the application.
Renovations - Chemical
termite barrier
The Respondents advise that, as far as the integrity
of the chemical termite barrier is concerned that no alterations were made to
the existing floor slab or walls and therefore no damage was done to the
integrity of the chemical termite barrier that is in place.
The Respondents
admit that they have enclosed their garage which brought the new garage walls
down into close vicinity of the ground
however they did seek professional advice
on how to minimise the chances of termite invasion and have implemented this
advice.
Accordingly I will make no order regarding this aspect of the
application.
External door
The Applicant also seeks
clarification of the ‘changes to common property’ in particular the
front door to unit 1. Although
I believe that the common property issues are
mostly addressed in the body of this decision I will comment on the front door
situation.
Pursuant to section 109 of the Standard Module a front
entrance door which separates a lot from common property is the responsibility
of the Body Corporate.
Therefore if a lot owner wishes to change their front
door then the necessary approvals must be given. As no specific orders are
sought by the Applicant and on the advice that the doors have not been changed
to date I can see no reason why any order need be
made regarding this aspect of
the application.
Accordingly I will make no order regarding this aspect
of the application.
Annual budgets and Statement of income and
expenditure
I will now turn to the issue of the budgets as raised by
the Applicant. The Applicants concern in raising the financial records is
unclear. The Respondents have provided no specific comments on this issue
either. I am therefore at a disadvantage in dealing with
this matter as there
is insufficient information provided for me to identify any clear breaches of
the legislation. Accordingly
I will make no orders on this issue.
I
will make the general comment that it is critical that accounts of this nature
are accurate in all respects and can be readily explained
when questions are put
to the Body Corporate Manager. Part 7 of the Standard Module deals with the
financial management (including the keeping and presentation of specific
records) of a community
titles scheme. It may be prudent for the Body Corporate
Manager at this time to inform all owners of the nature of the issue raised
and
be available to explain any issue or question that may arise from owners.
Accordingly I will make no order regarding this aspect of the
application.
Conduct of Applicant
It is alleged that the
Applicant is attempting to take steps to remove the current Body Corporate
Manager from their appointed role
unilaterally. The Respondents express some
concern about this and the Body Corporate Manager has already replied to the
Applicant
regarding this situation. I have considered all materials provided in
this matter and are unable to find any issue which I can address
by way of
making any order involving the Body Corporate Manager. I will however advise
generally that a body corporate manager is
engaged to provide body corporate
services to the scheme and should not be subject to unnecessary interference
without good reason.
Accordingly I will make no order regarding this
aspect of the application.
Comments about the
application
It is apparent from the application and the reply
provided by the Respondents that all parties have been placed in difficult
situations
on occasions in trying to ‘keep the peace’ yet achieve
their desired outcomes. Regretfully sometimes misunderstandings
can cause
considerable problems which I believe may be the root of a number of the issues
raised in the application. I make this
statement on the basis that a good
number of the issues raised were resolved simply by sharing information. I will
also make the
general observation that community titles living necessarily
requires concessions by all parties and I would encourage all parties
to accept
that this type of approach is required more often than not. Unreasonably
blocking motions which are properly brought
for no good reason will just cause
future problems.
I will say that I concur with the Applicant’s
general approach of trying to ensure that the scheme is run in accordance with
the legislation as much as is possible. The legislation, despite its
complexities in some areas, provides a system that facilitates
an equitable
approach to managing community titles schemes. This is why all parties involved
in community titles living should make
themselves fully aware of the processes
required under the legislation. A ready source of information is of course the
Information
Service a service provided by the Office of the Commissioner for
Body Corporate which provides free information and general advice
to any person.
I would encourage all parties to consider using this resource.
Orders:
In resolving this dispute I make the following
orders:
I hereby order that in relation to the application seeking an
order that pavers installed on common property by the Respondents (Debra
and
Francis Taylor – owners of Lot 1) be removed in this matter that the Body
Corporate will approve their installation within
6 months of the date of this
order conditional upon them having been installed by a qualified tradesperson.
I order further that
if the above condition is not complied with then the pavers
will be lifted and the area returned to its original condition by 1 April
2006.
I order further that the costs associated with complying with this order will be
paid for by the Respondents.
I order further that in relation to the
application seeking an order that the cat cage installed by the Respondents be
removed that
the Respondents remove the cat cage within 6 months of the date of
this order unless approval is given by the Body Corporate before
the final date
for compliance with this order.
I order further that in relation to
the application to remove the Respondents cat that the Body Corporate will
approve the keeping
of this one cat only by the Respondents within their lot
only and not on any part of the common property within 6 months of the date
of
this order.
I order further that in relation to the application
regarding payment of the extra expense of treating for Redback Spiders that each
lot owner is to pay the cost (between $20 and $30) above the pest treatment
costs as agreed at the AGM.
I order further that in relation to the
application seeking evidence of approval of the installation of the roof on the
Respondents
pergola I order that the Body Corporate approve the installation of
the roof within 6 months of the date of this order conditional
upon it having
been installed by a qualified tradesperson. I order further that if this
condition is not complied with that the
roof is to be removed by 1 April 2006.
I order further that the costs associated with complying with this order will be
paid for
by the Respondents.
I order further that all other orders
sought in this application are dismissed.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/409.html