![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 5 July 2005
REFERENCE: 0231-2004
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
13545
|
|
Name of Scheme:
|
Pine Court Lodge
|
|
Address of Scheme:
|
1371 Gold Coast Highway PALM BEACH QLD 4221
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Stephen Baddiley, the owner of lot 3
|
I hereby order that within 6 weeks of the date of this order, the
body corporate for Pine Court Lodge shall pay to the owner of lot 3, Stephen
Baddiley
the amount of $615 being in satisfaction of its liability for
responsibility for water penetration to lot 3, excluding the cost of
repair of
the bathroom ducting.
I further order that within 6 weeks of the date of this order, the owner of lot 7, Grant Barrett shall pay to the owner of lot 3, Stephen Baddiley the amount of $307.50 being in satisfaction of its liability for responsibility for water penetration to lot 3, excluding the cost of repair of the bathroom ducting. I further order that within 6 weeks of the date of this order, the body corporate for Pine Court Lodge shall obtain a quotation or quotations for the repair by reinstatement of the ducting concealing the pipe work in the bathroom of lot 3. Thereafter the body corporate shall select a contractor to undertake the necessary reinstatement work to the bathroom of lot 3. I further order that the owner of lot 3, Stephen Baddiley shall allow the body corporate reasonable access to his lot to allow for quotes to be obtained, and for the repairs to be undertaken. I further order that on completion of the work and payment of the contractor by the body corporate, the body corporate shall be entitled to invoice – • the owner of lot 3, Stephen Baddiley, 10% of the cost to the body corporate of reinstating the ducting in the bathroom of lot 3; and such
amounts shall be paid by those owners respectively within one month of the date
of the invoice sent by the body corporate.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0231-2004
"Pine Court Lodge" CTS 13545
The applicant, Stephen Baddiley, the owner of lot 3 has sought the following order of an adjudicator under the Body Corporate and Community Management Act 1997 (the Act) quote –
An order that the owner of lot 7 carry out repairs to the leaking shower in lot 7 which is causing water damage to lot 3, and further damages in an amount of $2500 to cover the cost of repair work to the lot 3 caused by water damage.
Section 276(1) of the Act provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory
order) to resolve a dispute, in the context of a
community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
The scheme is
a subdivision of 8 lots recorded under a building unit plan (now a building
format plan) of subdivision. The regulation
module applying to the scheme is the
Standard Module.
This dispute concerns alleged water penetration to the
applicant’s lot from lot 7 above, now owned by Grant Barrett (Barrett),
the responsibility for repair of that damage and compensation for repairs. It is
not disputed by any of the parties that water penetration
did occur to the
applicant’s lot 3 causing damage.
Section 281 of the Act
provides:
281 Order to repair damage or reimburse amount paid for carrying out repairs
(1) If the adjudicator is satisfied that the applicant has suffered damage to property because of a contravention of this Act or the community management statement, the adjudicator may order the person who the adjudicator believes, on reasonable grounds, to be responsible for the contravention--
(a) to carry out stated repairs, or have stated repairs carried out, to the damaged property; or
(b) to pay the applicant an amount fixed by the adjudicator as reimbursement for repairs carried out to the property by the applicant.
Example--
A waterproofing membrane in the roof of a building in the scheme leaks and there is damage to wallpaper and carpets in a lot included in the scheme. The membrane is part of the common property and the leak results from a failure on the part of the body corporate to maintain it in good order and condition, the adjudicator could, on application of the lot’s owner, order the body corporate to have the damage repaired or to pay an appropriate amount as reimbursement for amounts incurred by the owner in repairing the property.
(2) The order can not be made if--
(a) for an order under subsection (1)(a)--the cost of carrying out the repairs is more than $75 000; or
(b) for an order made under subsection (1)(b)--the amount fixed by the adjudicator would be more than $10 000.
The investigation
of this dispute has been lengthy. Due to the lack of clear information or
evidence of the source and location of
the water leak, responsibility has been
difficult to determine. In addition to the application and submission process,
investigation
by myself has included two teleconferences, numerous telephone
attendances by this office, a further report being provided by one
of the
parties, and finally, a physical inspection of both units, and a meeting with
both parties (on Wednesday 19 January 2005)
to clarify several aspects of this
dispute.
The actual fact of the water penetration to the
applicant’s lot was confirmed in a report provided with the original
application.
The report, by John Butler of Domestic & Commercial Building
Inspections dated 4 March 2004 stated in part:
During the inspection, unit 7 owner ... invited an inspection of unit 7, bathroom, the undersigned directed the bath be part filled with water and de plugged whilst the under side inspected at unit 3, during the draining of unit 7, bath, a flow of water escaped from the P trap under unit 7, onto timber ductwork in unit 3, it was found a fitting was loose and leaking.
Conclusion:
It is apparent water is / was leaking from the P trap of unit 7 into the partical (sic) ducting enclosure for the plumbing to unit 7, and causing damage, it is also apparent water from unit 7 has ingressed the kitchen ceiling ... The evidence is there for anyone to see that a large section of ducting and cupboards have been damaged by water, and that water ingressed unit 3 from unit 7. ...
I have the benefit of a lengthy submission from the body corporate. That submission has much detail of the history of the dispute, and particularly of the actions of the previous owner which are alleged to have been generally unhelpful. The owner of lot 7 at the time the dispute first arose has since sold the unit to Barrett. The evidence suggests that Barrett is or at least was the partner of the original owner at that time, and was aware of the on going dispute regarding water penetration to lot 3. The body corporate submission suggests that the cause of the water penetration to lot 3 is "that with time, the tile grouting dries out. The main problem occurs when this happens where the ceramic tiles meet the bath. The seal is no longer water proof and shower water can pass down between the wall and the rim of the bath. ... The body corporate has no fixed policy on what should be done other than water should not run down to the unit below and any damage caused to be paid for by the culprit".
It is noted that this analysis of the problem is completely different
from the conclusion in the report by Butler. That report concludes
that the
problem was "a fitting was loose and leaking".
Section 120 of the
standard module provides that the owner of a lot must maintain the lot in good
condition. Section 120 of the standard
module further provides –
(4) The owner of a lot included in the scheme must maintain the utility infrastructure within the boundaries of the lot, and not part of common property, in good condition and, if it is in need of replacement, must replace it.
The relevance of this section will become apparent.
There is also a substantial submission in response to the dispute from Barrett. He states in part:
... in the last year of owning the unit Camille had 2 plumbers come to the unit and replace all the tap washers and silicone around the taps and bath. Camille also had workers from Tech 2000 come to the unit who coated the tiles with a water proof silicone and also siliconed around the taps in the shower, so I can’t see how she had been negligent in fixing the leak.
... the area were it was supposedly leaking was in fact an area of common property because the pipe work was in a concealed bulkhead below my bathroom and in his bathroom. ...
The water damage in unit 3 is directly below the drain pipe below the shower, the damage has been made to the chipboard bulkhead which is over 30 years old and is also directly above Stephen’s shower. I think that damage to the bulkhead could also be caused by steam coming from Stephen’s shower and lack of ventilation in his bathroom. When the building inspector came to the unit’s I was there with him, when we turned the shower on in unit 7 there was no signs of any water escaping from the shower into the unit below. When the bath in unit 7 was filled on release of the water you could see a tiny amount of water nothing more than drops escaping from one of the pipes, the building inspector tightened the fitting and there was no more leaks. ...
From this submission, it is noted that a third possible
cause or source of water penetration is suggested: namely lack of ventilation
and simply wear and tear due to the age of the building and presumably, lack of
maintenance. Barrett attributes these causes to the
applicant as owner of the
lot.
I will add at this point that the further report which I required to
be provided by Barrett was of no benefit whatsoever, in that
it did not seek to
determine the cause or source of the leak, but merely concluded that "no water
pipes or drainage pipes were found
to be damaged or leaking".
Given the
difficulty in determining the cause or source of the leak, and the lack of
information regarding the actual location of
pipes etc, and also determining the
level of actual damage occasioned to the applicant’s lot of which little
detail had been
provided, I determined to undertake an inspection of the scheme,
and to meet with the parties. This occurred on Wednesday 19 January
2005 and was
of considerable assistance in determining many aspects of the dispute.
The most significant aspect of this inspection was to understand the
location of the pipes. All the pipes / drains for Barrett’s
lot 7 are,
after breaching the slab concrete floor between lots 3 and 7, located within lot
3. This includes waste water pipes and
sewerage pipes. Certain of these pipes
then connect with pipes servicing lot 3 and others do not. The pipes then
continue through
the concrete slab floor of lot 3 into a garage. In particular,
it is relevant to note that the P trap referred to in the Butler report
and said
to be leaking when tested, is located wholly within lot 3. The effect of the
pipes for lot 7 being located within lot 3
is that the pipes are utility
infrastructure which does not fall within the exception set out in section 20 of
the Act, and consequently,
are deemed to be common property of the scheme. Under
section 109 of the standard module, the body corporate is responsible to
maintain
the common property of the parcel in good condition. Effectively, this
means that the body corporate is responsible for the repair
of the pipes, since
under section 20 of the Act, the pipes are utility infrastructure deemed to be
common property.
The evidence before me does not establish categorically
one single cause or source of the water leak. It may in fact be that the cause
and source of the leak was multiple. That it was both the failure of tile grout
and bathroom sealants as well as a leak in the actual
waste water pipe at the
location of the P trap.
In addition to this, it also appears that there
must have been some other form of leak within lot 7 itself where water escaped
because
of the fact that there are some areas on the ceiling of lot 3 which have
been affected by water. There are at least two areas of
water penetration
resulting in discolouration of the ceiling of the applicant’s lot; the
first is in the south west corner
of the applicant’s bathroom, and the
second in the south east corner of the applicant’s kitchen. This second
water penetration
is shown in the photos provided with the Butler report (photo
01) and referred to in the statement quoted above.
Whilst the owner of
lot 7 (Barrett) is not responsible for the pipes servicing his lot, he is
responsible to ensure that his lot is
generally waterproof. Given that the
ceiling of the applicant’s lot show’s discolouration, then I suggest
that this evidences
some escape of water from Barrett’s lot other than
simply through the leaking P trap identified in the Butler report. Finally,
given that all the pipework at least was located entirely within the
applicant’s lot, and not accessible or observable by any
other owner or
the body corporate, that perhaps the owner had a responsibility to act earlier.
For example, what was indicated to
me at the inspection was that the water from
the P trap was stopped simply by the tightening of a fitting associated with the
P trap.
Certainly it was not within the ability of Barrett to even be aware of,
let alone repair, a leak occurring within lot 3. Although
after being informed
of such leak, perhaps the then owner of that lot should have taken a more
conciliatory approach to the resolution
of the problem.
In the
circumstances, I conclude that all three parties (the applicant, the owner of
lot 7 (Barrett) and the body corporate) bear
some responsibility for the water
leaks and consequent damage to lot 3. I intend to apportion responsibility on
the following percentage
basis:
• The owner of lot 3 (Baddiley) 10%
• The owner of lot 7 (Barrett) 30%
• The body corporate 60%
Whilst this apportionment
is somewhat arbitrary, I conclude that it fairly and reasonably apportions
responsibility based on what
appears to me to be multiple causes / sources of
water penetration to the applicant’s lot.
I now turn to consider
the question of the extent of the damage and what is required. Generally, whilst
I acknowledge that there has
been some damage to the applicant’s lot, I
conclude from the inspection that this damage was not extensive. I note that the
applicant has sought "an amount of $2500 to cover the cost of repair work to the
lot 3 caused by water damage". The first issue is
whether the water leak has in
fact been stopped. My questions of the applicant at the inspection appeared to
confirm that this was
the case, although he reasonably expressed concerns that a
leak might re-occur in the future. I understand from statements in
Barrett’s
submission, and also statements made by him at the inspection,
that Barrett is in the process of or about to renovation both his
bathroom and
parts of his kitchen. In his submission, he states –
... what this dispute is solved I am going to replace my bathroom and have it fully waterproofed as there is no chance of any leakage ...
If this is done, then presumably it will reduce the risk
of water penetration from lot 7, at least that which is attributable simply
to
lack of or failure of proper or effective waterproofing.
As part of his
application, the applicant has provided copies of certain invoices and quotes
for repair work. These include:
• A fee for the Butler report (paid by the applicant) $475
• A quote for the supply and installation of cabinets in the kitchen $2035
• A quote for the "demolition, removal and disposal of water damaged drainage pipe ducting to the bathroom" and "supply of all materials and labour necessary to restore the ducting to the original condition" $1850
The expense of the Butler report is a given.
The quote for the kitchen however is for a replacement kitchen, or at least
cabinets.
At the inspection, the state of, and damage done to, the kitchen was
considered. I conclude that the damage done was limited and
more in the nature
of aesthetic. For example, the only real visible evidence of damage was to the
chipboard base or plinth on which
the kitchen cupboards stand. Further damage
was visible to the rear wall of the kitchen when a large draw was removed.
However this
damage was not apparent otherwise. In other respects, the kitchen
was and remained in good condition. I certainly did not conclude
that the
kitchen required replacement due to the water penetration, and that the
applicant’s choosing to replace the kitchen
cupboards was a matter of
choice on his part rather than necessity. The maximum I am prepared to allow
for repairs to the kitchen
is $400.
The final expense is the $1850 for
the reinstatement of the bathroom ducting. This quote does appear to me to be
excessive. The necessary
materials would not be considerable, and even allowing
$350 for materials, this leaves $1500 for labour. A carpenter at $40 per hour
would not take 37.5 hours to construct the new ducting work. As well, the quote
includes "demolition, removal and disposal" which
has already been done.
In the circumstances, I intend to order that the body corporate, who
will be the largest contributor to the cost of repairs, obtain
quotes for the
repair of the bathroom ducting, and accept the quote which it considers to be
the most reasonable.
What is not mentioned here, but was raised by the
applicant at the inspection was the replacement of tiles on the kitchen floor.
There
was an area of perhaps 2 square metres where tiles had lifted. The
applicant states that this had occurred due to the fact of the
water penetration
to the lot causing them to become drummy. No quote was provided in respect of
this expense. From recent personal
experience of tiling, I suggest that tiles
can be purchased for perhaps $30 - $40 and laid for a similar amount. At two
square metres,
I am prepared to allow a figure of say $150 for the tiling.
I calculate the amounts to be as follows:
The butler
report 475
Kitchen 400
Tiling 150
Total 1025
Body
Corporate (60% of $1025) $615
Barrett – Lot 7 (30% of
$1025) $307.50
Baddiley – lot 3 (10% of $1025) $102.50
These
figures are independent of the cost of the repair of the ducting in the
applicant’s bathroom, which when the quotes are
available, and one chosen,
the cost to each party should be calculated on the same basis as set out (namely
60/30/10 to the Body
corporate/ Barrett/ Baddiley respectively).
I have
ordered to this effect. Obviously it is for the body corporate to organise the
quotes for the bathroom ducting, and to liaise
with Baddiley regarding access
for quotes and also to undertake repair work. The body corporate should pay the
account for this work,
and then seek contribution from Barrett and Baddiley for
their shares.
As for all other items, I intend to order that the Body
Corporate and Barrett shall pay to Baddiley, within 6 weeks of the date of
this
order, the amounts set out respectively, in satisfaction of the other claims. It
is then for Baddiley to undertake the repairs
when he chooses.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/33.html