![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 5 July 2005
REFERENCE: 0834-2004
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
10241
|
|
Name of Scheme:
|
Carool
|
|
Address of Scheme:
|
5 Eden Avenue RAINBOW BAY QLD 4225
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Ann WILLIAMS, as the owner of Lot 1,
|
I hereby order that the application for the following interim order
-
"We seek to have the unannounced temporary barricades and signage removed from the west side driveway which currently prevents total access into or out of the basement (under town houses only) car park by each of the three townhouse owners and visitors," is dismissed.
I further order that the body corporate committee must immediately take steps to put reasonable and appropriate signage and safety barricades in place in accordance with the written recommendations of Ian Rickard, Consulting Engineer, in his second report dated 21 December 2004, and must ensure that they stay in place, pending the final order in determination of this application. I further order that the committee must provide a copy of the reports of Ian Rickard and of Ray Griffiths, builder, to the owners of Lots 1, 2 and 3 if they have not already been supplied to them, and further must advise these same owners of the signage and safety barricades it considers necessary to meet the recommendations. I further order that this interim order has effect for a period of three (3) months from the date of this order. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0834-2004
"Carool" CTS 10241
The applicant, Ann Williams of Lot 1, has sought the following order of
an adjudicator under the Body Corporate and Community Management Act 1997
("the Act") -
"We seek to have the unannounced temporary barricades and signage removed from the west side driveway which currently prevents total access into or out of the basement (under town houses only) car park by each of the three townhouse owners and visitors."
(We the townhouse owners were never involved in, informed of, view reports (technical or otherwise) or otherwise notified of the works, investigations or other actions that led to or initiated the current actions, directives or orders. We were simply awoken at approximately 0600 this morning to be advised by the supervisor representing Romano constructions (also member of the Carool Management Committee) that this work had been ordered. Now we are denied access to the car park.)
[Adjudicator’s Note: The above comments, though included by the applicant as part of the order sought, should properly be regarded as part of the supporting grounds.]
The applicant has also made
application for interim orders in identical terms to the final order set out
above, and this order is
a determination of this
application.
JURISDICTION:
This is a dispute between an
owner (the applicant Ann Williams), and the body corporate (the respondent),
concerning action authorised
by the body corporate committee to erect signs and
barricades that interfere with the use by owners of the townhouse lots, being
Lots 1, 2 and 3, of their respective garages. The signs and barricades were
erected upon the expert advice of an engineer and builder
that the brickwork
mortar and metal ties incorporated in the western exterior wall of the townhouse
building were defective and the
area needed to be cordoned off because of the
danger of falling bricks. This is a matter that falls within the dispute
resolution
provisions of the legislation (see sections 227, 228 and 276
of the Act) and may be dealt with by a departmental adjudicator.
Section 279 of the Act provides that an adjudicator may make an
interim order if satisfied, on reasonable grounds, that an interim order is
necessary
because
of the nature or urgency of the circumstances to which the
application relates. An adjudicator’s order may contain
ancillary
or
consequential provisions the adjudicator considers necessary or appropriate
(section 284 of the Act).
APPLICATION and
SUBMISSIONS:
Under section 243 of the Act, a copy of the
application was provided to the respondent body corporate (committee) with an
invitation to respond by
written submission
to the matters raised in the
application. The committee subsequently submitted a response, including copies
of
relevant documents,
opposing the order sought by the applicant.
The
applicant appears to be the spokesperson for the other two "townhouse" owners,
namely John Utz of Lot 2 and Jacquelyn and Wayne
Stevens of Lot 3, though she is
the only person nominated and signing as the applicant.
The applicant
Williams states that, though the signage and barricades directly affect the
townhouse owners, they have "...never been involved in, informed of, view
reports (technical or otherwise) or otherwise notified of the works,
investigations,
or other actions..." Her complaint is against the body
corporate committee which, she says, has initiated actions that have seriously
disadvantaged
the townhouse owners in not being able to access their garages.
They state that on 23 December 2004 a representative of Romano Constructions
(affiliated with an owner and committee member, Bap Romano) informed her at her
door that the driveway to the townhouse car park
area was to be blocked and
scaffolding erected at the western (townhouse) boundary of the scheme. She
states that the Body Corporate
Manager, Mark Purtell of Strata Title Management,
had no knowledge of the building report being relied on by the committee, or of
the works, and enquiries to the chairperson, Chris Boyle, were
ignored.
The applicant has attached copies of emails between David
Williams, a committee member (and the applicant’s spouse), and the
Resident Manager, Phillip Roddy, including one dated 22 December 2004 reporting
how he (Williams) had argued with the committee that
the townhouse owners had
initiated their own "review of the state of the brickwork and had developed
two strategies to deal with the problem" but the committee had chosen to act
without reference to them.
The applicant also attached as part of her
grounds, a copy of a report dated 10 June 2004 by Charlie Ferguson of RK
Building Inspections
on the state of the building, who concluded that it had no
major defects. The report, however, does say in respect of the brickwork,
"Mortar is very sandy (Not enough cement used in construction – contact
bricklayer for advice)", though does go on to say, "Basically a strong
building with some maintenance issues, i.e., Roof, replacement of external
timbers, paint damage, etc."
The committee
states that it first became aware of the problem on 12 November 2004. It
was discussed at an extraordinary general meeting on 17 November
2004 by David
Williams, from whom the committee became aware of the comments by Ferguson
regarding as possible mortar problem. As
a result of this information, at its
meeting on 12 December the committee authorised Bap Romano to investigate the
problem. The
following two reports, copies of which have been supplied with the
committee submission, were subsequently obtained.
Ian Rickard, Consulting
Engineer, carried out a site inspection on 18 November (I note this was carried
out before the committee’s
authorisation) followed by a further inspection
on 20 December. The initial report found that the mortar had eroded and could
be
easily raked out. It also contained an opinion, which could only be verified
by an invasive inspection of the brickwork, that the
holding ties embedded in
the mortar may have rusted because of the state of the mortar.
At the
second inspection by Rickard, the brickwork was inspected in three locations and
it was found that the metal ties had in fact
deteriorated – the locations
were in a sheltered position and more exposed brickwork could be assumed to be
in a worse condition.
The report conclusion reads –
"It is imperative that rectification work is carried out on this building and that the external skin of brickwork is totally removed and rebuilt with stainless steel ties, epoxied into the inner skin of brickwork and mortared into the new external brick skin.
As this work cannot be carried out immediately it is imperative that steps are immediately taken to safeguard people from injury from potentially falling bricks.
Access to this area should be closed off immediately and if you require to maintain this access then a safety canopy should be erected to withstand the failure of the brick walls above to protect the people under.
IN relation to the driveway to the carpark this should be cordoned off and if access to the carpark is required then people should be advised of the potential failure of the wall and proceed at their own risk."
The
second report obtained by the committee was from Ray Griffiths, a licensed
builder, who also carried out an inspection on 18 November
followed by a further
one on 20 December, both in company with Ian Rickard and Romano. That is, on
both occasions both Rickard and
Griffiths carried out joint inspections though
they submitted separate reports – a committee member(s) were present at
the
inspection. There was also a subsequent teleconference between Rickard,
Griffiths, Romano and Chris Boyle, chairperson, on the findings
of the
inspection.
In the "Opinion" section of his report, Griffiths
states (in bold type) the following –
"Accordingly, I believe there could be some considerable risk to the occupants and the public from falling bricks if my suspicions are confirmed by Mr Rickard.
There is however obvious and unqualified risk of falling bricks from the capping bricks to the ends of the walls regardless of any other considerations regarding the cavity ties and something must be done to ensure public safety in this regard even if nothing else is considered.
Therefore I strongly advise steps be immediately taken to make the site safe by immediately closing the affected areas to the occupants and public at least while other means are investigated and installed for protection purposes."
The committee has also submitted a copy of an
email from Tony Wheeler, Area Manager for CGU Insurance Australia Group,
commenting
on the body corporate public liability insurance, which states in
part -
"It is the responsibility of the property owner, in this case the body corporate, to take all reasonable precautions to prevent any property damage or personal injury occurring on the property.
The body corporate is now aware of the potential for damage or injury to occur due to the reasons outlined in the engineers report and therefore, has an obligation under the policy to prevent access to all affected areas so damage or injury does not occur.
If the body corporate does not take any action to prevent access to the dangerous areas and make people aware of the situation by signage etc, there is the potential that a claim should it occur, may not be met."
The committee has made further comments on the
application material, however it is not necessary that I review them here in
order
to reach a decision in the application for an interim order. The only
comment I will make is that the committee has reported that
Roddy was asked by
the committee to advise the townhouse owners of the committee’s findings
and decision. Also, the committee
submits that barricades and signage were
removed by unknown persons on 23 December.
DETERMINATION:
"Carool" was registered as a building units
plan (now termed a building format plan) on 31 May 1982 and comprises 35
lots with a two-building configuration, one comprising 3 "townhouses" (Lots 1 to
3) and the other
a high-rise tower of 32 lots (Lots 4 to 35). It is regulated
by the Body Corporate and Community Management (Accommodation Module)
Regulation 1997 ("the Accommodation Module").
In this order I am
concerned solely with the determination of the application for an interim order.
This application was submitted on 24 December 2004 but submissions did
not close until 14 January. In view of the situation of the
body corporate I am
making this interim order without further delay. I would stress that it is only
an interim order (in the nature
of an injunction) that has effect for the period
given in the order (which may be extended if necessary).
It would appear
that the townhouse owners have not been properly advised by the committee of the
findings and recommendations of the
engineer and builder it engaged. The
arrangement to have the Resident Manager verbally advise them was not
appropriate in view of
the serious impact the safety works were to have.
However, the fact that the townhouse owners engaged a builder (Ferguson) to
inspect
their building as early as June 2004 means that a problem was at least
suspected by one or more of them.
xxxxxx
In any case, regardless of what
may have been the state of knowledge of the various parties (which will probably
be clearer in making
the final order), the findings and recommendations of both
the engineer Rickard and the builder Griffiths, are clear and unequivocal
in
having the body corporate take positive steps to protect both owners and the
public from failing brickwork. I know that the report
by Ferguson does not make
the same urgent recommendations, but it does say that the crumbling mortar
should be inspected.
As if the reports are not enough to require the body
corporate to act promptly in protecting its members against possible claims for
personal injury (note that owners have unlimited liability for the debts of the
body corporate, including any damages claim against
it successful in the
courts), the warning by the body corporate insurer makes clear that the
committee has a duty to act promptly
to erect the safety signage and
barriers.
My order is not only to dismiss the application, but in light
of the information that the signage and barricades were removed and
may possibly
still be removed, to require the body corporate to act in compliance with the
recommendations of the experts.
This is the only safe course to follow;
if it is found in further investigations, namely by further engineering and
building reports
that are persuasive evidence in reaching a different
conclusions, then the final order to this application will reflect that further
evidence.
I can understand the annoyance of the townhouse owners in
losing access to their garages and perhaps the body corporate could assist
in
allowing owners to find temporary parking elsewhere in the scheme, if that is
possible. The suggestion by the engineer that owners
and others could continue
to use the unsafe areas by offering to assume the risk is fraught with legal
danger. Such an undertaking
will not protect the body corporate against claims
by visitors, tradespersons, and even the owners themselves. The body corporate
should seek its own private legal advice on this point before any such
arrangement or exemption is given.
I am satisfied that an interim
order is necessary because of the possible consequences of injury to residents
or members of the public
from falling bricks; these are urgent circumstances
warranting immediate action. I have therefore issued an interim order until
such time as the matter is further investigated, including a further submission
to the final order, and perhaps a site inspection
or teleconference with the
parties. In that respect I note in the submission of the committee that it is
considering obtaining a
second engineering opinion and if obtained a copy should
be included with the committee’s submission.
Section 279(2) of the
Act provides –
279 Interim orders in context of adjudication
(2) An interim order--
(a) has effect for a period (not longer than 1 year) stated in the order; and
(b) may be extended, varied, renewed or cancelled by the adjudicator until a final order is made; and
(c) may be cancelled by a later order made by the adjudicator; and
(d) if it does not lapse or is not cancelled earlier, lapses when--
(i) the application is withdrawn; or
(ii) the commissioner gives the person who made the application a written notice under section 241 rejecting the application; or
(iii) a final order is made by an adjudicator to whom the application is referred.
In my order I have
provided that the interim order has effect for a period of three months. All
parties should be aware of this section
and its effect on the interim order. In
particular, it is the responsibility of the applicant to request an extension to
the interim
order period should it become necessary, as this office will not
automatically renew an interim order.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/29.html