![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 5 July 2005
REFERENCE: 0557-2004
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
14193
|
|
Name of Scheme:
|
Galileo Tower
|
|
Address of Scheme:
|
12 Mullen Street HAMILTON Q 4007
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Andrew James MACKENZIE, owner of Lot 4; Marie Yvonne DAWSON, owner of Lot
5; IGNATATUS PTY LTD (J Gorman), owner of Lot 3; CRATBURN
PTY LTD (H Lithgo, E
Meixner), owner of Lots 1 and 2; Timothy Caesar LOWNE, owner of Lot 6; and
Yvonne Muriel Renee McCOMB, owner
of Lot 9,
|
I hereby order that the application for the following order
–
"To rule that the renovations and repairs work proposed in Motion 2 and
Motion 3 be carried out and levies struck. Motions refer
to EGM of
12/8/04,"
is dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0557-2004
"Galileo Tower" CTS 14193
The applicants, Andrew Mackenzie of Lot 4 and 6 other owners, have sought the
following order of an adjudicator under the Body Corporate and Community
Management Act 1997 ("the Act") -
"To rule that the renovations and repairs work proposed in Motion 2 and
Motion 3 be carried out and levies struck. Motions refer
to EGM of
12/8/04."
JURISDICTION:
This is a dispute between a
number of owners (the applicants) and the body corporate (the respondent)
concerning the failure of a
special resolution for certain renovation works to
be carried out to the scheme building and the supervision of that work, at an
extraordinary general meeting of the body corporate held on 12 August 2004.
This is a matter that falls within the dispute resolution
provisions of the
legislation (see sections 227, 228 and 276 of the Act) and may be
determined by a departmental adjudicator.
General powers of an
Adjudicator in making an order:
Section 276(1) of the Act provides that an adjudicator may make an order that is just and equitable in the circumstances (including a declaratory order) to resolve a dispute, in the context of a community titles scheme, about –
a) a claimed or anticipated contravention of the Act or the community management statement; or b) the exercise of rights or powers, or the performance of duties, under this Act or the community management statement; or c) a claimed or anticipated contractual matter about – (i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or (ii) the authorisation of a person as a letting agent for a community titles scheme.
An order may require a person to act, or prohibit a person from acting, in a
way stated in the order (section 276(2) of the Act). An
adjudicator’s order may contain ancillary or consequential provisions the
adjudicator considers necessary
or appropriate
(section 284(1) of the
Act).
APPLICATION AND SUBMISSIONS:
In accordance with
section 243 of the Act, a copy of the application was served on the
respondent body corporate (committee) which was also required to serve copies
(first
8 pages and balance on demand) on all other lot owners, along with a copy
of the department’s notice inviting the committee
and each other owner to
make a written submission on the dispute raised in the
application.
Submissions were received from P Spottiswood of Lot 11,
James Dawes of Lot 12, and Mahoney Lawyers for Carmford Pty Ltd, Brezville
Pty
Ltd and Peachbroom Pty Ltd (P Hollis) of Lots 7, 8 and 10 respectively, all
opposing the application.
The applicants inspected the submissions and
subsequently lodged a reply to those submissions (see sections 244 and
246 of the Act).
This is one of three applications for this scheme
that concern repairs and renovations to various parts of the common property,
the
others being Application No’s. 701-2004 and 717-2004. Given the
commonality of disputes in the three applications, I shall
determine them
together and orders for all three with be issued together. The reasons for all
three orders should be read together
and copies of all three have been sent to
all applicants, respondents and parties making a submission to any of the three
applications.
The broad facts of the common dispute are as
follows.
The building is now over 30 years old and parts of the common
property are in need of repair, some repairs being of more pressing
concern than
others. Owners are facing the same decisions that as other owners in other,
similar buildings; that is, whether to
merely repair items or replace them with
a modern equivalent, or some combination of both. In regard to machinery items
such as
the elevator subject of this application, the decision includes whether
to take advantage of new technology which may offer a smoother
ride, be more
reliable, stave off future repairs for a much longer period, etc (see later).
The decisions include questions of cost,
the availability of replacement parts,
the ability of some owners to pay, how does the benefit fall on owners, a
prioritisation of
repairs, expert guidance in identifying necessary repairs,
whether renovation costs will be reflected in added value to lots, and
how the
different options must be resolved.
The owners have been considering
these questions for some time. The applications and the outcomes of the
extraordinary general meeting
held on 12 August 2004 ("the meeting") show that
owners have varying opinions on what should be done. There is reference to a
"Master
Plan" being decided on by the body corporate in general meeting in 2000
which was to be prepared setting out details for refurbishment
(repairs and
improvements) of the building. The body corporate engaged Norman Disney Young,
Consulting Engineers, ("NDY") to review
the existing lift equipment; it
subsequently produced a "Lift Condition Report" dated 18 July 2003,
recommending certain changes to the lift. Also around that time, the body
corporate engaged Leary and Partners,
Building Surveyor ("Leary"), to identify
building defects and make repair recommendations. Leary subsequently carried
out an inspection
of the building and produced a report titled "Defects &
Occupational Health & Safety Report" dated 27 August 2003 setting out
details of the defect, the recommended repair, a prioritisation of the repairs,
and a rough cost
of the repair.
The meeting was held for owners to votes
on various repairs and replacements. The first motion following confirmation of
minutes,
Motion 2, is a "motion with alternatives", comprising a
principal motion and two alternative motions containing tenders by Milson
Projects Pty Ltd ($479,358) and James Trowse
Constructions Pty Ltd ($498,724)
respectively. The cost per owner (all have equal lot entitlements) is around
$33,000 (see section 42B of the Standard Module). The principal motion
was put as a special resolution in recognition of the improvements it contained
(see
section 113 of the Standard Module). The motion failed and
Application 557-2004 lodged by 7 owners is for an order to give effect to the
motion – while the grounds
do not specifically say that the opposing votes
were unreasonable, that is easily inferred from their words and I have proceeded
on that basis. The application also seeks a similar order for Motion 3 which is
the appointment of a supervisor over the renovation
works contained in Motion 2
– of course its fate will be decided by the order in respect to Motion
2.
The initial order sought in Application 717-2004 (by three related
companies which each own a lot) was directly contrary to 557-2004
in that it
sought Motions 2 and 3 remain as defeated motions. The applicants later made a
change by adding to the application, permitted
under section 245 of the
Act but which required the submission process be restarted in respect to the
additional matters. The additional orders sought
was in
effect seeking the
invalidation of all of the motions passed at the meeting that related to
building works, namely resolutions
in
respect of Motions 4, 5, 6, 7, 8, 9, 10,
11, 13, and 14.
The orders sought under this application (Application
701-2004, is for the invalidation of the resolutions passed in respect of
Motions
4 (the lift), 11 (the garage doors) and 12 (the hot water systems). I
have dealt in some depth with these particular resolutions
in my Statement of
Reasons to the interim order and I will be dealing specifically with them under
"Determination" which follows.
Apart from Motion 2 (which was put
as a special resolution), the determination of whether resolutions passed should
stand or fall
depends on whether the subject matter of each motion should be
properly characterised as merely a repair, in which case an ordinary
resolution
is sufficient, or (assuming the cost is above the legislative threshold of
$3,600 (12 @ $300 per lot) or alternatively
is under the threshold amount but is
part of a project of improvements that are in excess of the value) is an
improvement, in which
case section 113 requires a special resolution.
All of the other motions were resolved by ordinary resolution, presumably on the
basis that the committee
considered all of them were repairs and not
improvements, or if an improvement’s cost was under the threshold amount
then they
were not part of a project over the threshold amount.
I
have broadly set out the facts of the matter and the orders sought under the
three applications.
I might say at this point that in my Statement of
Reasons to the interim order I made the following comment in respect of this and
the other two applications –
"While I am ready to deal with the applications in time, perhaps the owners might think a better outcome will be achieved if they were to strive for a negotiated outcome encompassing all of the intended and suggested works, rather than fight each other through the adjudication system and later perhaps through the District Court on appeal. It may be more timely and effective (cost and otherwise) in this instance, to engage a trained mediator for the purpose. In any case, that is a matter for owners to decide."
I
thought it may have been possible with the benefit of the comments and
references I made in the interim orders to this and 717-2004,
that owners might
have been able to negotiate a suitable compromise outcome and call a further
meeting to formalise that outcome.
That obviously did not happen.
DETERMINATION:
"Galileo Tower" was registered as a
building units plan (now termed a building format plan) on September 1973
and comprises 12 lots. It is regulated by the Body Corporate and Community
Management (Standard Module) Regulation 1997 ("the Standard
Module").
There is an important preliminary point I need to make
concerning an adjudicator’s jurisdiction to make such an order as the
applicants are seeking, namely an order to give effect to a failed motion for
the body corporate to carry out improvements to the
common property.
The
principal motion to Motion 2 was put as requiring a special resolution in
recognition of the improvements for which it sought
approval (see section 113
of the Standard Module). The cost per owner (all have equal lot
entitlements) is a large sum of around $33,000 (see section 42B of the
Standard Module).
The legislation does not prevent owners from agreeing
to spend such large sums as proposed by Motion 2 on refurbishing the scheme
building, but it sets a cost threshold for a higher level of resolution to apply
(special resolution) in recognition of the varying
needs and desires of owners,
and their financial means. This contrasts with the position of the legislation
concerning necessary
maintenance (repairs and replacement) where no such
threshold applies (except to require 2 or more tenders). Owners have no option
but to contribute to the cost of necessary repairs whatever the cost may be.
But, and rightly so, they do have a right to block
any change to the building
that is in the nature of an improvement.
That is what has occurred here
in Motion 2 failing. What then are the respective powers of an adjudicator to
give effect to failing
motions concerning improvements. Item 10 of Schedule
5 to the Act provides that adjudicators may give effect to a failed motion
that requires a "resolution without dissent" to pass, on
grounds that
the
opposition was "in the circumstances unreasonable". Item 17 provides
that an adjudicator can give effect to a failed motion for an owner to make
improvements for the benefit of their lot (special
resolution) though no grounds
are mentioned, however I would suggest that unreasonableness is
implied.
But in regard to improvements by the body corporate to common
property, such as Motion 2, section 113(1)(c) of the Standard Module
provides that an adjudicator may give effect to a failed motion where the
adjudicator "decides the improvements are reasonably necessary for the
health, safety or security of persons who use the common property". While I
leave open the point that the wide powers given an adjudicator under section
276 of the Act may not be limited by this provision in all circumstances, I
consider that there must be exceptional circumstances for
an adjudicator
to give
effect to such a motion. At the least the standard should be that of "in the
circumstances unreasonable" as in Item 17, though I suggest it should be a
high level of unreasonableness.
The circumstances surrounding Motion 2 do
not involve substantive issues of health, safety or security, though the
applicants have not identified and sought to argue this provision. However, for
example, the applicants have generally
argued that the balcony railings are
corroded and the glass cracked, severely on some balconies. The Leary report
identifies the
damaged mountings need repair though the committee motion takes
the remedy beyond this work. Leary has also identified other instances
requiring immediate repair, and repair within a short period.
Clearly
there are defects that need to be addressed promptly, however I am not satisfied
that the dissenting votes are unreasonable
such that improvements catering for
those defects to be remedied should be given effect to by an order. However,
unless the body
corporate is able to gain prompt support for one or more of its
improvement work proposals, then it will need to make the repairs
necessary for
those defects identified by Leary as being urgent or near urgent (ie repair
within 6 months), without the remedy being
part of an improvement.
In the
circumstances I have dismissed the application to give effect to Motion 2 and
Motion 3.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/152.html