![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 13 July 2007
REFERENCE: 0018-2004B
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
16553
|
|
Name of Scheme:
|
Villa Estoril
|
|
Address of Scheme:
|
102 Indooroopilly Road TARINGA QLD 4068
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Donald Robert Richards, the owner of lot 4
|
I hereby order that the order dated 30 June 2004 staying the
implementation of the order made by Adjudicator R A Meek on 13 May 2004 shall be
revoked
at midday on 14 July 2004 subject to the applicant Donald Robert
Richards being afforded a reasonable opportunity, prior to midday
on 14 July
2004, to cause his authorised agent to inspect the intended work to be carried
out on the gutters by means of access through
lot 3 and lot 5.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0018-2004B
"Villa Estoril" CTS 16553
The original application in this matter was made by Donald Robert Richards.
A final order determining that application was made on
13 May 2004 by
Adjudicator R A Meek. The applicant lodged an appeal against that order in the
District Court on 24 June 2004. On
25 June 2004, the
applicant/appellant’s solicitors requested a stay of the order made on 13
May 2004. On 30 June 2004 the
order was stayed on certain conditions.
On
2 July 2004 the body corporate’s solicitors (Herdlaw) requested that the
stay be revoked on the following basis:
1. The balance of convenience is in favour of the body corporate being able to perform the repair for these reasons
a. The damage being sustained to unit 3 is in excess of the cost of proceeding with the repair
b. The body corporate is clearly in breach of its duty to maintain common property, which has resulted in damage to the lot. The lot owners have now notified that they will be pursuing the body corporate for substantial damages.
c. There is an extremely dangerous situation caused to the electrical wiring in the building by water penetration.
2. The grounds for granting the stay have not been properly considered in accordance with the principles applied by courts or tribunals in granting stays. There has been no examination or consideration of the merits of the appeal. We submit that a close examination of the grounds of the appeal will reveal that they have not been properly formulated and do not disclose valid grounds for appeal.
On 5 July 2004 the solicitors acting
on behalf of the owners of lot 3 (Deacons) similarly requested that the stay be
revoked. The
basis for the request was outlined as follows:
The general rule is that an applicant for a stay must demonstrate some good reason why the general rule that an appeal does not operate as a stay should be departed from Croney v Nand [1999] 2QdR 342; Berry v Green (unreported, CA (Qld) 07/09/99).
We submit that the balance of convenience overwhelmingly favours the lifting of the stay so that the source of the water damage can be removed and our clients’ unit can be repaired.
There would not appear to be any reason why photographs could not be taken of the allegedly defective work, or an inspection undertaken by an appropriately qualified expert should Mr Richards choose to engage one to give evidence in whatever proceedings he contemplates pursuing in respect of the allegedly defective work.
Our clients are innocent third parties, are not involved in, and have not
contributed to, the matters which Mr Richards complains
of. Our clients are now
informed that the situation with respect to water penetration of their unit is
now "potentially dangerous".
In this regard, we enclose an email from Geoff
Morrison, an electrician, to our client dated 1 July 2004.
On 13 July
2004 I conducted a teleconference with the following parties:
• Mr Robert Herd – Herdlaw, the solicitor for the body corporate
• Mr Steven Forrest – Deacons, the solicitor for the owners of lot 3, Mr and Mrs Saunders. Mr Saunders was present with Mr Forrest during the teleconference
• Ms Jacqueline Wheeler – Baker Lawyers, the solicitor for the applicant/appellant
During the course of the teleconference
(which was suspended for a short time to allow certain further enquiries to be
made by Mr
Herd and Ms Wheeler) I was advised by Mr Saunders that, contrary to
the belief expressed by Mr Douglas, (the body corporate secretary),
during an
earlier teleconference on 30 June 2004, the problem of water penetration into
lot 3 has not been completely resolved by
the laying of the new roof membrane.
I was further advised by Mr Forrest that the cost of the work stayed by
the order of 30 June 2004 is $875.00 and sharing the cost
will incur a liability
for each owner in the sum of $175.00. Mr Forrest stated that it was absurd that
the applicant/appellant’s
desire to relieve himself of the payment of such
an insignificant amount of money could form the basis for the staying of work
which
has significant ramifications for the owners of lot 3 and, ultimately, the
body corporate. Mr Forrest reiterated that the allegedly
defective work could
be photographed and a report could be prepared for use at a later time if
necessary. Mr Forrest also pointed
out that the major cause of the water
penetration into lot 3 has been, and continues to be, the blocked box gutters,
and not the
failed roof membrane.
Mr Herd pointed out that the body
corporate has an obligation to maintain common property in good condition, and
that the failure
to carry out the work exposes the body corporate to potential
liability, particularly in light of the evidence from Mr Morrison that
the
electrical wiring in lot 3 is now in a dangerous state as a result of the water
penetration, which itself is only continuing
to occur because the work has not
been completed. Mr Herd stated that at the very least the applicant/appellant
should be required
to give an undertaking to the body corporate that he will
indemnify it in respect of any on-going damage which might be caused by
the
incompletion of the work.
Ms Wheeler advised that the applicant/appellant
would welcome the opportunity to inspect and photograph the subject areas as
suggested
by Mr Forrest, but that he has in the past been denied access to do
so. Mr Forrest stated that neither of the owners of lots 3 and
5 was prepared
to allow the applicant/appellant to have access to their lots because of his
behaviour on previous occasions. However,
they were prepared to allow an
independent third party nominated by the applicant/appellant to have access to
the subject areas so
as to take photographs and prepare a report.
At
this point, the teleconference was adjourned.
Upon resumption, I was
advised by Mr Herd that the tiler is expected to complete the tiling on lot
5’s balcony on 14 July 2004,
and that, if the stay were to be lifted, the
builder would expect to be able to commence work on the box gutters on 14 July
2004,
particularly if there were any further threat of rain.
Ms Wheeler
advised me that the applicant/appellant was arranging for a builder to inspect
the subject areas on the morning of 14 July
2004, and, further, that he
understood that under no circumstances would he be allowed to accompany the
builder for the inspection.
Ms Wheeler further advised that the
applicant/appellant did not consider it necessary in the circumstances to give
any undertaking
to the body corporate.
Since making my decision to stay
the order on 30 June 2004 additional evidence has come to light.
Firstly, I was advised by the applicant/appellant during the
teleconference on 30 June 2004 that part of the work he wished to have
stayed
involved the demolition of a wall. I was of the view that if that wall were
defective as alleged, then its demolition would
make any later attempt to
determine what, if any, defects were present almost impossible. I have now been
advised that the work
does not involve demolition of any wall.
Secondly,
I have now been informed that the major cause of the water penetration into lot
3 is the blocked box gutter (this is confirmed
by the report dated 7 November
2003 from Eurocom Projects Pty Ltd and the report dated 28 November 2003 from
Building Certification
of Australia Pty Ltd.). Accordingly, I accept that the
laying of the new roof membrane will not have completely resolved the problem
of
water penetration into lot 3.
Thirdly, I have been informed that the
continuing water penetration into lot 3 has created a potentially dangerous
situation in relation
to the electrical wiring.
Fourthly, the owners of
lots 3 and 5 have agreed to allow the applicant/appellant’s agent to gain
access to their lots for the
purposes of taking photographs and preparing a
report on the allegedly defective gutters for use in any subsequent proceedings
that
the applicant/appellant might commence if his appeal were to be successful.
On this basis I am not persuaded that there will be any
disadvantage to the
applicant/appellant if the remaining work is completed. On the other hand, I
consider that there is the potential
for considerable disadvantage to the owners
of lot 3 if the water penetration into their lot is allowed to continue. There
is also
considerable potential liability for the body corporate, particularly in
relation to public safety.
Section 291(2)(c)(i) of the Act permits
me to revoke or amend a stay. I am therefore satisfied that the stay of order
made by me on 30 June 2004 should
be revoked as from midday on 14 July 2004,
subject to the condition that prior to that deadline the applicant/appellant
shall be
afforded a reasonable opportunity to cause his authorised agent to
inspect the intended work to be carried out on the gutters by
means of access
through lot 3 and lot 5.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2004/671.html