![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 30 September 2005
REFERENCE: 0472-2004
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
27344
|
|
Name of Scheme:
|
Whalewatch Ocean Beach Resort
|
|
Address of Scheme:
|
7 - 15 Samarinda Drive, POINT LOOKOUT QLD 4183
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Krackob Pty Ltd, the owner of lot 22
|
I hereby order that within 1 month of the date of this order the
body corporate shall pay to the applicant, Krackob Pty Ltd, the sum of $511.89,
being 60% of the amount expended by the applicant in plumbing expenses relating
to a blocked drain which was properly the responsibility
of the body corporate
to maintain.
I further order that the application for the remaining orders is dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0472-2004
"Whalewatch Ocean Beach Resort" CTS
27344
ORDERS SOUGHT
The applicant, Krackob Pty Ltd, has sought orders
of an adjudicator under the Body Corporate and Community Management Act
1997 (the Act) as follows:
1. Recognition of all or lesser of blocked drain costs of $853.15 incurred by Krackob Pty Ltd from 31/12/99 to 03/01/01 as a cost of body corporate Whalewatch.
2. Recognition of payment by Krackob Pty Ltd of (1) as an advance on body corporate levies.
3. Withholding of $1,000.00 payment of levy fees in January 2004 in light of (1) to be considered as reasonable and not attract penalties.
4. Refund of amount in (1) now that $1000.00 payment offer made on 16/07/04 as full settlement.
5. Refund in (4) to attract interest.
6. Krackob Pty Ltd be entitled to reimbursement of reasonable costs should body corporate Whalewatch be found lacking in duty of care to Krackob Pty Ltd.
7. Establish precedent for any such future outlays.
8. Both body corporate Whalewatch and Body Corporate Services be made fully aware of any failure in their duty of care (if any) to Krackob Pty Ltd.
JURISDICTION
The application evidences
a dispute between an owner of a lot included in a community titles scheme and
the body corporate for the
scheme (section 227(1)(b) of the
Act).
Section 276(1) of the Act provides that an adjudicator may
make an order that is just and equitable in the circumstances (including a
declaratory
order) to resolve a dispute, in the context of a community titles
scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
SCHEME
DETAILS
Whalewatch Ocean Beach Resort was established as a building
format plan on 4 October 1999 and comprises 40 lots. It is regulated
by the
Body Corporate and Community Management (Accommodation Module) Regulation
1997 (Accommodation Module).
BACKGROUND
The applicant
provided a chronology of events, which has been supplied to the respondent body
corporate and all owners. I do not
propose to set out that detail again.
Suffice to say, the applicant experienced drainage problems (manifesting as a
blocked kitchen
sink) from late December 1999 to early January 2001. The
applicant engaged a plumber, Mr Garry MacFarlane, who carried out work
on 6
separate occasions in an effort to unblock the sink. The applicant stated, in a
letter dated 9 January 2004 to the body corporate
manager, that "on all
occasions the body corporate manager was kept informed and he accepted the
reports as a basis to put before the committee
for reimbursement." The
applicant did not claim to have obtained actual body corporate approval prior to
having the work carried out by Mr MacFarlane.
In a submission lodged on
behalf of the body corporate committee, the chairperson stated, in part, as
follows:
"The problems of drains blocked in the complex by building debris on the
handover of the properties to the owners was a common one
which affected other
units including my own. The builder of the complex has subsequently gone into
liquidation. This is a matter
that should have been taken up at the time with
the builder or the BSA but now exceeds the time limits for claiming from the
BSA.
To my knowledge the body corporate has not reimbursed any other unit
holders in relation to defects related to the building of the
site. I consider
it would be unfair for present owners to have to bear costs back-dated from this
time particularly given that many
of the units have recently changed hands and
the new unit owners would be expected to bear the cost through their body
corporate
for something that occurred almost five years ago."
The
chairperson also rejected the applicant’s action in withholding his levies
as an offset against the amount claimed for plumbing
costs.
DETERMINATION
I note that the body corporate
committee considered the applicant’s claim for reimbursement of plumbing
expenses at a meeting
held on 30 December 2003. The committee rejected the
claim on the basis that the blockage occurred within the applicant’s
lot.
On 19 November 2004 I spoke by telephone with Mr Garry MacFarlane,
the plumber engaged by the applicant. Mr MacFarlane advised me
that he could
recall doing work on a kitchen sink in this scheme. He advised me that
initially he attempted to unblock the sink
locally (within the lot). He said
that on each occasion it appeared that the blockage had been cleared, but as
time went by and
he was recalled on several occasions he decided that the
blockage had to be within the main line. He explained that finally he used
a
sewer machine, which has a lead of approximately 30 metres. He said that after
the machine had travelled about 5-10 metres, it
encountered a significant
blockage (well outside the applicant’s lot). I note from Mr
MacFarlane’s invoice (No 85) dated
30 November 2000 that he put the
machine down the line several times and also put down liquid cleaner "to eat
concrete". Ultimately the blockage was cleared. Mr Macfarlane was of the
view that the blockage was caused by the builder’s debris.
Under
section 108 of the Accommodation Module the body corporate is responsible
for maintaining common property in good condition. Section 20 of the Act
extends the definition of common property to include utility infrastructure,
which, unless falling within the exceptions
detailed in section 20(1)(a), (b)
and (c), is also required to be maintained by the body corporate. In this
instance, I accept the plumber’s advice that the blockage
occurred outside
of the applicant’s lot in the main drainage line, and therefore the
utility infrastructure did not fall within
the exceptions.
Accordingly,
under normal circumstances, the body corporate would have been responsible for
the whole of the costs of clearing the
blockage. I note the chairperson’s
comments about the builder. However, once the building was completed, and the
scheme had
been established upon registration of the plan, the body corporate
assumed its responsibility notwithstanding that there might have
been some
redress against the builder for a certain period of time.
However, of
more concern in this instance is that owners do not have the right to
unilaterally proceed with work which is the responsibility
of the body
corporate, and then necessarily expect to receive reimbursement at a later date.
Firstly, the body corporate did not
authorize the work before it was carried
out. It was immaterial that the body corporate manager might have been
receiving "reports" from the applicant. The body corporate manager did
not have the power to authorize work on behalf of the body corporate. Only the
body corporate committee could authorize such work, (assuming it fell within the
committee’s spending limit), otherwise it
would have to have been
authorized by owners in general meeting.
Secondly, by proceeding with
the work as it did the applicant deprived the body corporate of the opportunity
to select a contractor
of its choice, perhaps at a more competitive price.
Perhaps too the body corporate’s contractor might have decided to use
the
sewer machine at an earlier time than Mr MacFarlane did, such that the problem
was finally resolved with fewer visits and accordingly
for a lesser
cost.
In its letter dated 9 January 2004 to the body corporate manager
the applicant stated that it "was left no choice but to address the urgent
nature of the health problem by taking action and instructing a plumber to
inspect and
report and proceed with our (the applicant and Ray White)
approval to fix the problem" because "the body corporate was unable to
act immediately". In the absence of any documented approach to the body
corporate by the applicant prior to the work being carried out, I am not
persuaded
that the body corporate was unable to act immediately. In my view
there is insufficient evidence that the matter was so urgent that
proper
approval could not have been sought. A committee meeting could have been called
after giving 7 days’ notice, and, in
the case of a genuine emergency, the
committee could have voted outside a formal meeting under section 33 of
the Accommodation Module.
Notwithstanding my reservations about the
applicant’s actions, I consider that the body corporate should not be
completely relieved
of responsibility for the plumbing costs, given that the
plumber confirmed that the blockage was ultimately discovered to be in the
main
line. I have therefore decided that the body corporate should reimburse the
applicant 60% of the costs expended by it. I have
only allowed this amount for
the reasons outlined above. I do not propose to allow interest on this amount,
and in any event it
is arguable that even if I were so minded that I do not have
power to do so.
I shall now consider the applicant’s decision to
withhold $1,000.00 of its levies in an attempt to obtain some "positive"
action from the body corporate committee.
Levy contributions are payable
by owners at pre-determined levels and intervals to enable the body corporate to
function in an orderly
fashion and attend to payment of accounts as and when
they fall due. It would create financial havoc for the body corporate if every
owner who thought they might have a claim against the body corporate were to
withhold payment of all or part of their levies by way
of offset without first
having to establish the validity of their claim.
Section 94 of
the Accommodation Module provides:
94 Notice of contribution payable [SM, s 96]
(1) At least 30 days before the payment of a contribution, or instalment
of a contribution, is required, the body corporate must give the owner of
each lot written notice of--
(a) the total amount of the contribution levied on the owner; and
(b) the amount of the contribution, or instalment of contribution, of
which payment is currently required; and
(c) the date (the "date for payment") on or before which the
contribution, or instalment of contribution, must be paid; and
(d) any discount to which the owner is entitled for payment of the
contribution, or instalment of contribution, by the date for
payment; and
(e) any penalty to which the owner is liable for each month payment
is in arrears; and
(f) if the owner is in arrears in payment of a contribution or
penalty--the arrears.
(2) The written notice under subsection (1) may also include notice
about an amount payable by a lot owner to the body corporate for--
(a) a specially contracted service enjoyed by the owner; or
(b) an exclusive use or special right over common property enjoyed
by the owner.
(3) A written notice under this section may be served on a lot owner at
the lot owner’s address for service, or in the way directed by the
lot owner.
Section 96 of the Accommodation Module
provides:
96 Penalties for late payment [SM, s 98]
(1) The body corporate may, by ordinary resolution, fix a penalty to be
paid by owners of lots if a contribution, or instalment of contribution, is not
received by the body corporate by the date for payment fixed in notices of
contribution given to the owners.
(2) The penalty must consist of simple interest at a stated rate (of not
more than 2.5%) for each month the contribution or instalment is in arrears.
Example--
Suppose that--
• a contribution of $400 is payable in 4 instalments of $100 and the body
corporate has fixed a penalty interest rate of 2% per month
• an account requiring payment of an instalment of $100 by 31 March is given
to the owner of a lot
• the instalment is not paid until 27 June.
In this case, the instalment has been in arrears for 2 months and a penalty of $4 is
payable.
Section 97 of the Accommodation Module provides:
97 Payment and recovery of body corporate debts [SM, s 99]
(1) If a contribution or contribution instalment is not paid by the date for
payment, the body corporate may recover each of the following amounts as
a debt--
(a) the amount of the contribution or instalment;
(b) any penalty for not paying the contribution or instalment;
(c) any costs ("recovery costs") reasonably incurred by the body
corporate in recovering the amount.
(2) If the amount of a contribution or contribution instalment has been
outstanding for 2 years, the body corporate must, within 2 months from the
end of the 2 year period, start proceedings to recover the amount.
(3) A liability to pay a body corporate debt in relation to a lot is
enforceable jointly and severally against each of the following persons--
(a) a person who was the owner of the lot when the debt became
payable;
(b) a person (including a mortgagee in possession) who becomes an
owner of the lot before the debt is paid.
(4) If there are 2 or more co-owners of a lot, the co-owners are jointly
and severally liable to pay a body corporate debt in relation to the lot.
(5) If an owner is liable for a contribution or a contribution instalment,
and a penalty, an amount paid by the owner must be paid--
(a) first, towards the penalty; and
(b) second, in reduction of the outstanding contribution or
instalment; and
(c) third, towards any recovery costs for the debt.
(6) If the body corporate is satisfied there are special reasons for
allowing a discount of a contribution, or waiving a penalty or liability for
recovery costs, the body corporate may allow the discount, or waive the
penalty or costs in whole or part.
The body corporate was
within its rights to impose a penalty on the applicant when the applicant failed
to pay its levy contribution
in full for the January 2004 quarter. Subsequent
debits for penalties and interest followed that event and they should stand. I
have therefore dismissed the remainder of the application.
In closing I
note that there does appear to have been a significant delay before the body
corporate advised the applicant that it
did not propose to reimburse the claimed
expenses. Whilst I can see from the chronology of events that there were a
number of issues
preoccupying the body corporate (the liquidation of the
building company, a change of body corporate manager, adjustments of budgets
to
address deficit) the body corporate should ensure in future that owners’
correspondence receives prompt attention.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2004/588.html