![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 30 September 2005
REFERENCE: 0623-2003
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY
MANAGEMENT ACT 1997
|
Number of Scheme:
|
20903
|
|
Name of Scheme:
|
Ballymore Heights Villas
|
|
Address of Scheme:
|
41 Scott Road HERSTON QLD 4006
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by: Christine Frances CLAYTON, as the owner of Lot 8; and Ewan Cameron MACKENZIE and Alison MACKENZIE, as the co-owners of Lot 9,
|
I hereby order that within three (3) months of the date of this
order, the owners of Lot 8 and Lot 9 must carry out such work as is necessary to
waterproof the courtyard and garden bed areas of their respective lots, at their
own cost, to prevent water penetration through to
the supporting framework
underneath, including as recommended in Items 1 and 2 of the Mullins Consulting
Pty Ltd engineering report
of 6 March 2003 the removal of the bed and courtyard
paver bricks, cleaning of the slab, screeding to provide adequate fall and other
works to provide efficient drainage, and application of the designated
waterproofing membrane.
I further order that in respect of Items 3 and 7, the cost of the works must be apportioned between the body corporate, the owner of Lot 8 and the owner of Lot 9, according to the cost of the actual work done on the common property, Lot 8 and Lot 9 respectively, except that the body corporate is wholly responsible for the construction of the earth spoon drain described in Item 7. I further order that in respect to Items 4, 5, 6, 13, 14, 15, and 16 the body corporate is solely responsible for the cost of the works, to be levied on all owners in the normal manner in proportion to their respective contribution schedule lot entitlements. I further order that in respect to Items 8, 9, 10, 11, and 12 the cost of the works is to be borne equally by the body corporate (but excluding any contribution by the owners of Lot 8 or 9) in a half-share, and the owners of Lots 8 and 9 jointly in the other half-share. I further order that the body corporate secretary must forward a copy of this order and the accompanying reasons to all lot owners. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0623-2003
"Ballymore Heights Villas" CTS
20903
The applicants, Christine Clayton of Lot 8, and Ewan and Alison Mackenzie
of Lot 9, have sought the following order of an adjudicator
under the Body
Corporate and Community Management Act 1997 ("the Act") -
"The owners of Units 8 & 9 would like a ruling on who is responsible for the costs of work items 1 and 2 in the attached documentation."
JURISDICTION:
The applicant
owners are seeking a declaratory order as to whether they (for their respective
lots) or the body corporate are responsible
for the costs of rectification work
recommended in Items 1 and 2 of an engineering report compiled by Mullins
Consulting Pty Ltd,
Civil Structural Engineering Consultants of Indooroopilly.
A declaratory order sought under section 227(1)(b) concerning owners and their
body corporate is a "dispute" under section 227(2) of the Act; it is also
a dispute falling within sections 228(1)(b) and 276(1)(b) of the Act giving
jurisdiction to determine the application.
General powers of an
Adjudicator in making an order:
Section 276(1) provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory order) to
resolve a dispute, in the context of a
community titles scheme, about –
a) a claimed or anticipated contravention of the Act or the community management statement; or b) the exercise of rights or powers, or the performance of duties, under this Act or the community management statement; or c) a claimed or anticipated contractual matter about –
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles scheme.
An order may require a person to act, or
prohibit a person from acting, in a way stated in the order (section 276(2) of
the Act).
An adjudicator’s order may contain ancillary or consequential
provisions the adjudicator considers necessary or appropriate
(section 284(1) of
the Act).
APPLICATION AND SUBMISSIONS:
Under section 243 of
the Act, a copy of the application was provided to the respondent body corporate
(committee) and the other owners, with an invitation
to
respond to the matter of
dispute raised in the application. Submissions were received from George Moore
of Lots 5 and 6, and
Pamela
Champion of Lot 3. No submission was received from
the committee. The applicants did not view the submissions and therefore
did
not lodge a written reply to them (see sections 246 and 244 of the Act
respectively).
This is one of two applications for the scheme both of
which concern the same question as to cost responsibility for rectification
work, the other being Application 690-2003 lodged by Elizabeth Finney, Sheue
Ooi, and Catherine Curry as owners of Lots 1, 2 and
4 respectively. They are
seeking a declaration as to the responsibility for the works set out in Items 7
to 13 of the same engineering
report, though have also sought an additional
order against the owners of Lots 8 and 9 to rectify the water seepage problem in
their
courtyard areas.
As both applications concern recommendations by
Mullins Consulting Pty Ltd, (later set out in dot form as Appendix 2
"Specification
for Remedial Work" based on the report recommendations)
(hereafter "the report"), there is a large degree of commonality in the
history, facts and grounds relied on by both parties in their respective
applications.
I assume this is why neither applicant made submissions to the
other’s application. In the circumstances, and as this was
the first
application lodged, I shall set out the history and facts of the situation in
these reasons and aspects of the law bearing
on maintenance responsibility, and
adopt them in my reasons to the second application by quoting the relevant
areas.
In 1998 after the steel structure supporting the suspended
concrete slabs for Lots 8 and 9 and part of the common property driveway
area
was seen to show signs of corrosion from water penetration, the body corporate
committee engaged a service provider, Opat, to
carry out certain rust prevention
treatment. An inspection by Bill Finney (father of the owner of Lot 1,
Elizabeth Finney) of the
structure and the treatment work, found the work
unsatisfactory in remedying the corrosion.
At a committee meeting on 7
November 2002 it was resolved that a structural engineer be commissioned to
report on the status of the
supporting structure and the remedial work
necessary. As a result, on 2 January and again on 30 January 2003 Peter Mullins
of Mullins
Consulting Pty Ltd, with Bill Finney, carried out an inspection and
engineering survey of the structure and other areas of the scheme.
The report
is the result of that survey, setting out the problems and 16 recommendations to
rectify the problems; tenders for the
recommended work were obtained from three
builders, Eggert & Leighton, Roof & Building Service and Mainline
Technologies.
Owners have a copy of the report and should be generally aware of
the problems. I will set out the main problems here and deal
with each in more
detail when determining maintenance responsibility for each area.
To
assist in my understanding of the problem, on 25 March 2003 I carried out an
inspection of the relevant scheme areas in the company
of Bill Finney, Pamela
Champion of Lot 3 (representing the applicants for Application 690-2003),
Christine Clayton of Lot 8 and Alison
MacKenzie of Lot 9.
The buildings
which comprise Lots 8 and 9 are wholly supported by a framework of metal posts,
supporting metal beams and Bondek sheets
in which the floor concrete slabs have
been set. The posts are bolted to concrete pads set into the ground. The
pebble-coat slabs
which form the driveway area (hereafter "the driveway
area") lying between Lots 5, 6 and 7 and the courtyard areas (and garages)
of Lots 8 and 9, are similarly supported by a system of metal
posts, beams, and
Bondek. The posts under the driveway area slab and the posts under Lots 8 and 9
have some common connecting framework.
Extensive corrosion is evident in
many parts of the steel framework with significant corrosion under the garden
beds situated at the
southern end of the two courtyards (Lots 8 and 9),
particularly under the block-wall behind (southern end) the garden beds (see
page
12 of report), and under the brick wall which separates both courtyards
from the indented garage entrance (hereafter "the garage entrance"). At
the time of the survey on 30 January, water was seen leaking down from under the
length of the garden bed for Lot 8 (presumably
it had been watered earlier) and
was wetting the supporting Bondek and slab, and continued for several hours (see
page 2).
Many post base-plates and the securing bolts and nuts are
corroded from water ponding in the hollows dug to take the concrete pads.
A
large part of the water causing this damage comes from rainwater flowing down
the eastern side of the scheme land, coming from
the front and some off the
driveway area slab, and then flowing diagonally under Lots 8 and 9. There is
some flow of rainwater from
the driveway area (which slopes from Lots 5, 6 and 7
down to the courtyards of Lots 8 and 9) to the box spoon drain situated before
the garden beds and the other box drain situated at the base of the indented
garage entrance (just outside the garage doors for Lots
8 and 9). The report
shows that the drains are not adequate to capture the water flow. There is also
some seepage through the driveway
area slab joints.
The above sets out
the major problems and some probable causes – each of the problem areas
will be addressed separately under
the following heading, with reference to the
items of work recommended in the report.
DETERMINATION:
"Ballymore Heights Villas" was registered as a
group titles plan (now termed a standard format plan) on 12 July 1988 and
comprises 9 residential lots. It is regulated by the Body Corporate and
Community Management (Standard Module) Regulation 1997 ("the Standard
Module").
This application seeks orders concerning Items 1 and 2 of the
report, however as the problems relating to all of the other recommended
rectification items (ie Items 3 to 16) are intertwined, and Application 690-2003
puts Items 7 to 13, in issue, I intend to deal with
all of the problems in the
one statement of reasons. This will mean that there will be common statements
of reason for both applications,
and orders, with the reasons here merely
adopted by quoting in the reasons to the other order. This is a commonsense
approach and
it will not deprive any party from their rights of appeal.
(NOTE: I would comment here that at the end of my inspection of the site on 25 March I stated that I would be making decisions by order in respect to Items 1 and 2, but in respect to the remaining items of work which includes the contentious area of framework corrosion as the result of water penetration from both common property and the relevant lots, I would be providing certain information to assist owners reach their own assessment of apportionment of responsibility. Upon examining the scope of the work and the legislative issues involved, I believe it best that I make the apportionment by order. This will avoid any misunderstanding of the law involved and also any ill-feeling that may arise from having to make difficult money decisions regarding oneself and one’s neighbour. Ms Champion did say at the time that the applicants she represented thought an order would be made on all matters, perhaps expressing the thoughts that I have followed in making my order).
There are two types of community titles schemes in Queensland. A standard
format plan (group title plan) is a subdivision of land
and therefore owners of
lots have ownership of the land comprised within their lot boundaries which
usually includes a building sited
within the lot, as is the case with Ballymore
Heights Villas. Ownership is similar to that of a normal freehold block of land
as
the lot owner owns the land beneath and the air above. This is in contrast
to the alternative type of community title scheme, a
building format plan
(formerly "building units plan"), where owners only own to the centre-point of
the floor, walls and ceiling
of that part of the building that comprises their
lot. The external surface of the building, the roof and the foundations are
therefore
common property under a building format plan.
In Ballymore
Heights Villas, owners own their building completely (and to the centre-point of
the common wall where lot buildings
are adjacent), including the roof and the
foundations and ground underneath. In the case of Lots 8 and 9 the "ground
underneath"
includes all of the supporting structure (posts, beams, Bentok,
slab) situated directly under their lot building as well as the ground
surface
and underneath that surface.
Generally, the maintenance responsibility
for common property (and body corporate assets) falls on the body corporate and
the maintenance
responsibility for a lot falls on the lot owner. Common
property is defined as scheme land other than lots (see section 10 of the Act)
but is extended by section 20 to include certain utility infrastructure (the
significance of this will be seen later).
In respect to the division of
maintenance responsibilities in a standard format plan, the respective
responsibilities of the body
corporate and owners are set out in the legislation
as follows –
In regard to owners, section 120 of the Standard
Module states –
120 Obligations of owners and occupiers.
(1) An occupier of a lot included in the scheme must keep the parts of the lot readily observable from another lot or common property in a clean and tidy condition. (2) The owner of a lot included in the scheme must maintain the lot in good condition. (3) The owner’s obligation under subsection (2) to maintain the lot in good condition does not apply to a part of the lot the body corporate is required under this regulation to maintain in good condition. (4) The owner of a lot included in the scheme must maintain the utility infrastructure within the boundaries of the lot, and not part of common property, in good condition and, if it is in need of replacement, must replace it. (5) This section applies only to a lot that is not a community titles scheme.
Subsection(2) sets the general rule;
the lot owner must maintain their lot in good condition. This means that the
owners of Lot 8
and 9 are prima facie responsible for the maintenance of
their lots which includes their lot building, the courtyard, the garden bed and
the supporting
structure items (post, beams etc) underneath. I have qualified
the responsibility because there are two issues here that alter that
strict
responsibility. I will deal with these two issues separately under the first
issue I shall also discuss the body corporate’s
general maintenance
responsibility.
THE FIRST ISSUE is in respect to certain utility
infrastructure that have a shared purpose with at least one other lot owner, in
particular the box
drain situated at the end of the indented garage entrance
(see part Item 4) and pipe hangers supporting various pipes under the lots (see
Item 14). These matters are those referred to as exceptions in subsections
120(3) and (4) above, however I shall discuss the maintenance responsibility for
these items in the following examination of body
corporate maintenance
responsibilities.
In regard to the body corporate, section 109(1) of the
Standard Module states –
109 Duties of body corporate about common property.
(1) The body corporate must maintain the common property in good condition, including, to the extent that common property is structural in nature, in a structurally sound condition.
The reference to
"structural common property" would include, for example, the structural frame
work under the driveway area (being
part of common property), but not the
structure under Lots 8 and 9 (being part of the respective lots). As well as
the general duty
under section 109, the body corporate has a separate and
specific maintenance responsibility under section 20 of the Act regarding
certain utility infrastructure (pipes, wires, etc) which provides
–
20 Utility infrastructure as common property
(1) Common property for a community titles scheme includes all utility infrastructure forming part of scheme land, except utility infrastructure--
a) solely related to supplying utility services to a lot; and
b) within the boundaries of the lot (according to the way the boundaries of the lot are defined in the plan of subdivision under which the lot is created); and
c) located other than within a boundary structure for the lot.
(2) However, common property does not include utility infrastructure positioned within common property if--
a) its positioning is the subject of an agreement to which the original owner or the body corporate is a party; and
b) under the agreement, ownership of the utility infrastructure does not pass to the original owner or body corporate.
Example of utility infrastructure for subsection (2)--
Cable television wires positioned in the service shaft of a multistorey building that is scheme land for a community titles scheme, if the wires remain in the ownership of a cable television provider.
(3) In this section--
"boundary structure",
for a lot included in a community titles scheme, means a floor, wall or ceiling,
other than a false ceiling, in which is located
the boundary of the lot with
another lot or common property.
Under Schedule 6 Dictionary to the
Act, "utility infrastructure" includes cables, wires, pipes,
sewers, drains...by which lots ... are supplied with utility services.
The term "utility services" is defined as including ...sewer system,
drainage. Accordingly, although the drain at the northern end of the garage
entrance is actually sited under the eaves of Lots 8 and 9 ("the relevant
lots"), and therefore presumably inside the boundary of their lot (if it is
not it is a body corporate responsibility anyway), the drain
services both lots
and therefore under section 20(1)(a) is not an exception and therefore is the
responsibility of the body corporate to maintain. Similarly, there are a number
of stormwater
pipes positioned (by pipe hangers affixed to the underside of the
slab) under both lots that service the scheme generally; like the
drain, under
section 20 these are also the responsibility of the body
corporate.
Accordingly, the work described in Item 4 for the
rectification of both box drains, and the work described in Item 14 for the
replacement
of nine stormwater pipe hangers, are both wholly the responsibility
of the body corporate.
Before moving on to the second issue that
impacts on the strict liability of the relevant owners under section 120 of the
Standard Module, I will consider the remaining report items that do not concern
the supporting structure under the relevant
lots. Thus far I have found that
Items 4 and 14 are the responsibility of the body corporate, however for
completeness I shall also
include them in the list but with only a reference to
the reasons set out above determining responsibility.
Items 1 and
2 concern the courtyards and garden beds of the relevant lots, these are
clearly part of the respective owner’s lot and therefore
under section
120(2) are the responsibility of the owners to maintain. The areas do not
include any common utility infrastructure that would displace
owner’s
responsibility in favour of the body corporate.
However, while the
relevant owners have the responsibility to rectify the courtyards and garden
beds so that there is no further water
penetration through to the slab and
structure below (which incidentally also answers the second order sought in
Application 690-2003),
they need not necessarily follow all of the remedial work
as set out in the report. That is, where the report talks of removing
and
replacing the existing paver bricks in the courtyards, and sealing the garden
bed and replacing the soil and shrubs, the owners
may wish to lay new tiles and
to do away with the garden beds altogether and instead extend the courtyard. Of
course the By-law
10(f) controls in a limited manner renovations to lots
(whereas lot buildings are more strictly controlled), I cannot see why the
body
corporate would not give consent to such changes, or indeed to replacing the
lattice work fence now sited on top of the boundary
block wall forming the
southern edge of the garden beds. In effect, though the owners of Lots 8 and 9
are wholly responsible for
waterproofing their courtyard area, and must carry
out the work as soon as possible, there is an opportunity to, in today’s
reality parlance, "make-over" their respective courtyard
areas.
Accordingly, in respect to the orders sought by the relevant
owners in Application 623-2003, I will not be merely ordering that they
are
responsible to both pay for and implement the recommendations in Items 1 and 2,
but will phrase the order such that both are
responsible for having done at
their own expense all that is necessary for the waterproofing of their
respective courtyards including
the garden bed areas. This will include the
cleaning of the area, screeding to provide proper fall, rectification of the
drainage
system and the application of the recommended membrane, but will allow
for the owners to make whatever changes to the area that they
wish and is
approved by the body corporate.
Item 3 concerns the
installation of lengths of 25mm angle aluminium under the edge of the slab (on
both sides of the slab) so as to prevent
water flowing over the slab edge and
back under the slab to wet the supporting metal beam causing corrosion over
time. This is an
example of a simple, low-cost procedure that by its omission
at the time of construction has caused unnecessary damage; along with
the
omission of membranes in the garden beds, wrongly placed drainage pipes, lack of
drainage fall, post base-plates set below ground
level, etc., it is indicative
of poor workmanship.
The installation cannot be regarded as coming within
the ambit of those items of utility infrastructure set out in the Schedule 6
Dictionary for the body corporate to assume responsibility. Therefore, the cost
($801) must be apportioned according to where the
work is carried out and the
extent of the work – the installation will need to follow all of the
suspended slab area and therefore
will need to be apportioned between the body
corporate for the driveway area, and the respective owners for their lot areas.
An
easy and reasonably accurate method is to apportion according to the length
of the installation and my order is to this effect.
Item 4
– already determined as a body corporate
responsibility.
Item 5 concerns waterproofing the joints in the
slabs which comprise the suspended driveway area between Lots 5, 6 & 7, and
Lots 8 &
9. It involves grinding out the joints (between slabs, and between
slabs and buildings), cleaning and sealing (cost $1,462). This
concerns only
common property and therefore is the responsibility of the body
corporate.
Item 6 concerns the construction of a box drain to
capture rainwater draining down the eastern side of the building (including
run-off from
the driveway area slab) to prevent it from overflowing under Lots 8
and 9 where it has contributed to the ponding around the posts
and the corrosion
of the base plates and bolts over time. (I will be referring to this damage
when discussing the second issue).
This "cut-off" drain which is to be
constructed in reinforced concrete, will be on common property to remedy a
common property problem
and is therefore at the cost of the body corporate
($2,409).
Item 7 concerns the lowering of the ground level around
the metal posts under the driveway area and the relevant lots. The
responsibility
for this cost will be shared between the body corporate and the
relevant owners according to the proportion of work done in respect
to that area
under the common property driveway area and the respective lot. This may result
in a difference in cost apportionments
between Lots 8 and 9. From my
observation, the main work will be in the area under the relevant lots. The
spoon drain that needs
to be constructed which is to service both lots (with or
without servicing the common property as well) will fall into that category
of
utility infrastructure for which the body corporate has responsibility. In
summary, the body corporate is responsible for the
levelling work on common
property and for the construction of the spoon drain; and the relevant owners
are responsible for the cost
of the levelling work actually carried out on their
respective lots.
Items 8, 9, 10, 11 and 12 - see SECOND
ISSUE later.
Item 13 concerns the fixing of angle
iron to outside posts so as to support the bottom of the large wooden lattice
panels that are fixed to
the sides and back of the suspended slabs. The lattice
panels look slightly untidy because of their age and the fact that they are
unsupported at the base. It appears that no allowance has been made in the
quote of $3,841 for the replacement of any panel. A
large part of the cost here
is undoubtedly because of the need for scaffolding.
While it is true that
the lattice panels are fixed to the side of the slabs of the relevant lots, the
purpose of the lattice is as
a decorative feature to hide the supporting
structure both under the driveway area and the relevant lots, and the pipes
(stormwater,
waste and sewerage) suspended amongst the supporting structure or
against the block wall under the boundaries of Lots 5, 6 and 7.
Accordingly,
the lattice can be regarded as performing a function for the scheme as a whole
in contributing to the overall presentation
of the scheme building. There is
also the fine distinction that the lattice is affixed at the boundary of the
relevant lots and
common property and, more correctly just over the common
property, and therefore should be a responsibility of the body corporate
in any
case. It is my view that in the circumstances the body corporate should wholly
bear the responsibility here.
Item 14 – already
determined as a responsibility of the body corporate.
Item 15 concerns stairs that are fixed to the side of the
driveway entrance area and are part of the common property. The body corporate
is wholly responsible for this item ($1,053).
Item 16 concerns the
repair and stabilisation of the handrail fixed to the eastern side of the
driveway entrance slab. It is part of the
common property and wholly the
responsibility of the body corporate ($923).
THE SECOND ISSUE
that impacts on the strict liability of the relevant owners under section
120 of the Standard Module to repair all on their lot (eg supporting framework),
concerns the issue of negligence. Simply put, it could
be argued by the
relevant owners that the failure by the body corporate to carry out certain
remedial measures (eg sealing the slab
gaps, ensuring drains worked properly)
under its duty to maintain the common property, has contributed, unintentionally
but carelessly,
to the damage caused to the supporting structure of their lots.
Such an action needs to be argued in the civil court – it
is not a matter
that I can determine in this jurisdiction.
However, section 276(1) of the
Act provides that an adjudicator "may make an order that is just and
equitable in the circumstances (including a declaratory order) to resolve a
dispute in the context
of a community titles scheme about...the performance of
duties under this Act." That is, I have discretion to make a determination
of a dispute that is just and equitable in the circumstances; that allows
me to take all matters into account, including any breach of duty under the Act
that has caused damage. The legislation
provides an avenue of appeal to the
District Court on a question of law (see section 289) if an "aggrieved
person" (applicants, lot owners affected, owners who made submissions) is
dissatisfied with the order.
The remaining items to be
determined, Items 8 to 12, all concern damage to the supporting structure under
the relevant lots (lot property)
and the driveway area (common property),
comprising the steel posts (including base plates), the steel beams, the Bondek
sheets,
and minor steel components and fixing bolts etc. The major item is Item
8 costing $6,090 with Items 9 to 12 totalling $1,253. Item
8 is for the
cleaning of all steel work (including sandblasting), application of rust
inhibitor and application of membranes as set
out in the Mullins Consulting
report. Item 10 is to cut back corroded Bondek; Item 12 is to paint all cleaned
steelwork with silicate
and silver steel paint.
Item 9 is a special case;
it is costed at $176 which is for the removal of a number of bricks from the
triangular portion of the brick
wall dividing Lot 8 from the garage entrance, to
be able to examine the extent of the corrosion to the steel beam (angle) the
wall
rests on. A structural engineer (presumably Mullins) needs to be present
to determine what remedial action is necessary. There
may or may not be a
further cost involved here. If there is a future cost, then it should be funded
in the same manner as set out
in the order to this application.
In
regard to the damage covered in the other items (Items 8, 10, 11 and 12), my
views on responsibility, based largely on opinion
expressed in the report and my
observations to an extent, is as follows.
The scheme buildings are now
nearly 16 years old and it would appear that the water seepage and resulting
corrosion problems have
been occurring all that time as most seepage is related
to the manner of construction and design, for example, lack of drainage,
lack of
or inadequate waterproofing membranes, inadequately sealed joints, omitted or
inadequate soil removal, etc.
The courtyards and the garden beds of the
relevant lots have no proper waterproofing membrane, or proper drainage (see
prior comments)
and this has allowed water to leak down into the supporting
structure underneath causing corrosion, over time, to the framework of
steel
posts, beams, Bondek and other steel items (angle iron, fixing bolts etc). In
regard to the damage to the beams and Bondek
under the relevant lots, this is
significant damage, especially under the garden beds and the southern block wall
of the garden bed
(see page 12 of report). While water from rain and watering
of the garden has obviously seeped down, there is also the inadequacy
of the box
drain in front of the garden beds on the driveway area (see prior comments).
Water not captured by the drain would hit
the side of the garden bed wall
resulting in some water entering into the block wall and later leaking down into
the framework. As
commented under "Application and Submissions" in
respect of this area, "At the time of the survey on 30 January, water was
seen leaking down from under the length of the garden bed for Lot 8 (presumably
it had been watered earlier) and was wetting the supporting Bondek and slab, and
continued for several hours (see page 2)."
Also commented on under
"Application and Submissions" there is significant corrosion under the
brick wall which separates both courtyards from the indented garage
entrance. The water causing this damage would be from the (lot) courtyards
and from the (common property) garage entrance, with water entering
the
framework underneath through the brick wall and the joint between the two
areas.
Again under "Application and Submissions", I have commented
on water flow from the eastern side of the scheme and off the driveway area slab
flowing under the driveway area
and the relevant lots area, ponding in the post
hollows causing corrosion of the steel posts and base-plates. This work, which
in
my view the body corporate (more precisely the builder at the outset) could
have avoided with proper drains to prevent the flow of
water under the suspended
slab, is included in Item 8 along with the cleaning and treatment of all
corroded steel work. However,
in respect of the cleaning of the posts and
base-plates under the relevant lots, this does not mean that the body corporate
is wholly
responsible – the relevant owners are not separate persons to
the body corporate as, for example, is the case between two neighbours,
but are
part of the body corporate; as well, they have a duty to maintain their lot,
including the posts, and therefore a responsibility
to check their building for
damage (the rust is quite evident in most parts of the framework) and take steps
to prevent further damage,
including notifying the body corporate of the
drainage problem.
Apportionment: From the above comments it should
be apparent to owners that, while the owners of Lots 8 and 9 have total
responsibility for rectifying
their courtyards, and the body corporate has total
responsibility for certain other rectification work, there are areas of work
recommended
that will have to be apportioned according to the actual work done
on the common property or lot (see Items 3 and 7) or, in the case
of Items 8 to
13, there needs to be an apportionment between the body corporate and the
relevant owners based on an assessment of
the source of the water penetration
and damage. It would be a difficult exercise to determine the extent the water
from the various
sources contributed to the damage; perhaps an expert in the
area (hydraulic engineer or hydrographer) could set up instruments to
measure
flow over time, but this would be expensive, delay the rectification work,
measure future not past flow and in the end the
result would have to evaluated
and accepted by the parties. It is my view that the responsibility of the
relevant owners to rectify
the framework on their lots should be reduced to the
extent that they together contribute half the cost and the body corporate
(without
any contribution by the relevant owners for these Items 8 to 12 only)
contribute the other half.
I making this decision I have been
mindful that where the body corporate has a responsibility to fund works, the
relevant owners will
also be sharing in that cost through their normal
contributions based on contribution lot entitlements, where their contribution
is 8/55 compared to 4 owners with 6/55 lot entitlements (Lots 1 to 4), and the
remaining 3 owners (Lots 5 to 7) with 5/55.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2004/176.html