![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 30 September 2005
REFERENCE: 0685-2003
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY
MANAGEMENT ACT 1997
|
Number of Scheme:
|
1592
|
|
Name of Scheme:
|
The Bay Apartments
|
|
Address of Scheme:
|
43 The Strand NORTH WARD Q 4810
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Michael O’Dea, the co-owner of lot 14
|
I hereby order that the application by Michael O’Dea, the
co-owner of lot 14 for several orders that
voting papers being allowed in
...
is dismissed.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0685-2003
"The Bay Apartments" CTS 1592
The applicant, Michael O’Dea has sought the following orders of an
adjudicator under the Body Corporate and Community Management Act 1997
(the Act) quote –
1. Orders requested:That the 6 voting papers rejected by the chair at the EGM be accepted and counted and that the count be amended to reflect the votes of these papers.
2. Alternatively that:The 6 voting papers rejected by the chair at the EGM be accepted from item 4 (the item that was being counted when the papers were rejected)
3. Alternatively that:The 6 voting papers rejected by the chair at the EGM be accepted as submitted before the recommencement of the meeting after the chair had adjourned the meeting. At the time of adjournment motion 4 was being tallied. This makes the request that the voting papers be valid and counted from motion 4 onwards when the meeting was restarted.
4. If orders 1, 2, 3 above rejected, then the order below is requested:That the EGM declared invalid on the grounds that the date had passed for the EGM to be held on the adjudicators orders which was made on the 3rd June 2003 and stated that the EGM had to be held no later than 3 months from the 3rd June 2003 bringing it to final date of 3rd September 2003, making it outside the adjudicators orders by 1 month and 7 days.
These orders are requested aside from above orders:
5. That a penalty be levied to Gribbins Realty (Body Corporate Group) and Linda Payne (Body Corporate Manager for acting outside the power vested by chairing the meeting. These was unconscionable conduct resulting in undue influence being used to stop the voting papers being allowed in ...
6. That a penalty be levied to Linda Payne, the body corporate manager for not acting impartial, honestly, fairly and professionally whilst carrying out her duties as representative of the Body Corporate Group.
7. That the single letter from John Gribbins, dated 19th September be ruled as deliberately misleading on the grounds that paragraph 5 which starts with the work "working" infers that $84.00 per unit is all that is required to satisfy payment for work that has been earmarked as needed in the EGM paper.
8. It should be ordered that complete clarification by John Gribbin Realty be made to all owners in the Bay Apartments, making it clear that the funds required to be paid by owners is between $3024.00 and $3864.00.
9. That motion 12, Agreement to special levy on the EGM of 10th October be struck out as "out of order" on the grounds that the committee had submitted that the motion to be put to the owners of the Bay Apartments was to be levied as three distinct payments but when the papers came out it had been changed by R. Petherbridge (Chairperson) without consultation with committee members to show the special levy as a single payment.
10. It is argued that this should have been added as an extra motion and called it motion 13 and the original motion should have remained.
(Note that the above numbering is not the
applicant’s system of numbering. However, for ease of reference, I have
varied the
numbering, as the applicant’s references to numerous orders
sought numbered 1 and 2 would cause confusion).
Section 276(1) of
the Act provides that an adjudicator may make an order that is just and
equitable in the circumstances (including a declaratory
order) to resolve a
dispute, in the context of a community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
Interim
order
The applicant had previously sought an interim order be granted
stopping any act to further pursue any action in relation to any of the
motions voted on at the EGM on the 10th October 2003 until a decision
by the Adjudicator is given and specifically that It is believed that the
removal of the bicycle enclosure (motion 4) will be dismantled almost
immediately, thus asking that this is
an "urgent application" for a hold on
work.
On 31 October, 2003, the following interim order was made,
quote -
I hereby order that resolution 5 purportedly carried by the body corporate of the Bay Apartments at the EGM held on 10 October 2003 shall not be implemented or otherwise put into effect, until a final order to this application is made, this application is withdrawn, or this order is of no effect through operation of law.
In my reasons for my
interim order, I reasoned as follows -
The meeting in question was an EGM of the body corporate held on 10 October 2003. Motions 2, 3 and 4 are headed "Bicycle Enclosure", and motion 5 "Removal of Bicycle Enclosure". Thereafter the motions listed deal with other matters, including motions 8 to 11 which deal with certain maintenance items, and finally motion 12, headed "Agreement to a special levy". It is noted that the minutes refer to all the above motions as having been carried.
Motion 4 specifically resolved that the body corporate, in resolving the problems arising from the construction of the bicycle enclosure shall not leave the owner of lot 14 (or any other unit owner) in a situation of continuing disadvantage.
Motion 5 provides that the body corporate authorise the committee and the managing agent to organise the removal of the bicycle enclosure and the restitution of lot 14’s car space and adjacent visitor parking space. This motion was carried by 7 votes in favour to 4 against).
The essence of the applicant’s argument is that he was incorrectly denied the right to submit 6 voting papers. Assuming that the 6 voting papers in question all voted "no" to each of the motions 4 to 12, the only motions which would not have been carried on the numbers are motions 4, 5 and 11. Given this outcome, I am not prepared to order as an interim order that the implementation of all resolutions be put on hold pending a final resolution of the dispute. If such an order is to be made, it will be restricted to motions 4, 5 and 11.
In respect of motion 11, I note that it and motion 10 are described as "special resolutions". Given that the motions appear to relate to maintenance items, I do not see why they would not simply be ordinary resolutions. The deficiency I do notice however with these two motions is the failure of the body corporate to submit two quotes. This is a requirement of section 104 of the legislation, where a proposal involves spending over the limit for major spending. However, in respect of both motions, I note that the motions themselves provide that alternative quotes will be provided to choose between before the work is initiated and the work will not be initiated until the body corporate has chosen between alternate quotes. Given these qualifications, then I do not intend to place motion 11 on hold, as it is little more than an information motion in my view. It is not a motion which can be proceeded with at this time in any event.
Motion 5 however can be implemented by removal of the bicycle enclosure. Given the dispute regarding the non-acceptance of the 6 voting papers, I intend to order that resolution 5 shall not be implemented or otherwise put into effect, until a final order to this application is made, this application is withdrawn, or this order is of no effect through operation of law. The question of the acceptance of the 6 voting papers in question will be considered in my final order. Whilst I intend to place motion 5 on hold, I do not intend to similarly order in respect of motion 4, although the effect of the non-implementation of motion 5 may cause "continuing disadvantage" to the owner of lot 14 in any event. I cannot avoid this, but any disadvantage which can be avoided in the interim, should be so avoided.
For the benefit of all parties to this dispute, I have reproduced the relevant section of the standard module dealing with voting, quote -
51 Exercise of vote at general meetings
(1) A voter for a general meeting may vote on a motion personally, by proxy or by casting a written vote.
(2) A written vote is cast by completing the voting papers as required by the accompanying instructions and giving them to the secretary (personally, by post or by facsimile) before the start of the meeting.
(3) A written vote on a motion may be withdrawn by a voter at any time before the result of the motion is declared, except that an owner’s written vote cannot be withdrawn by a person voting as the proxy of the owner.
In an appeal of an order of an adjudicator, specifically on the question of the meaning of "personally" as used in section 51 of the standard module, Judge Robin Q.C. of the District Court stated, quote -
[at paragraph 16] ... (Counsel for the Appellant, Ms Cull) says, and I am inclined to agree, that it must be the same person, namely, the voter. She says, and again I agree, having regard to the contents of Mr Beattie’s speech, among other things, that this is a "consumer protection" provision which is designed to protect all lot owners by creating an assurance that every written vote cast is a sincere and honest expression of the voter’s views, as authenticated by the voter’s taking the trouble personally to give the voting paper to the secretary if the alternative modes of transmission are not resorted to. That state of assurance, the argument runs, cannot be reached where some intermediary is interposed, who is the one who in the event gives a voting paper to the secretary. ...
[at paragraph 19 ... A voter who wishes to have a written vote counted would be wise to comply strictly with s.51(2); doubtless, shortcuts will be taken in emergency situations which may lead to further elicitation by adjudicators or judges. I think, at the least, that what the provision requires is a person commitment by the voter to his or its vote to the extent of personal and particular steps being taken in relation to that voting paper to get it to the secretary in a way that indicates to the secretary the voter’s personal, considered imprimatur and implies a warranty to the secretary that the vote is an enthusiastic, free and genuine one.
I have quoted the above passages as the matters contained therein bear heavily in my view on certain of the issues I will need to address in the final order. In their submission to the final order, I suggest all parties will need to address the considerations raised by the judge in respect of the requirements of section 51 of the standard module.
Subsequent to the
making of the interim order, and clearly in light of such interim order, the
applicant has amended the final orders
sought by him in the following terms,
quote –
(Referring to the contents of the interim order) There is persuasive argument in this material to abandon our argument to have the voting papers counted, however this does not excuse the lateness of the EGM (approximately some 6 weeks late) and no extension of time sought or granted.
Therefore we make the Alternative Order argument of lateness of EGM our number one request and on these grounds would argue that all motions should be subject to the "interim order" on the grounds that if found to be in our favour, then none of the motions put forward on the 10th October 2003 will be valid. It should now be noted that we make the Orders of 1, 2 or 3 our secondary orders and should only be visited on failure of finding the EGM to be not our of order for failure to observe time limitations and therefore invalid.
The applicant actually requested that the terms of the
interim order be "revisited" and be "placed on all 12 motions presented at
the
EGM. In respect of this request, the applicant was referred to his rights of
appeal.
Whilst the applicant has requested that his original first three
orders sought now be relegated to secondary orders, and that his
original
secondary order be accorded first priority, I nevertheless intend to deal with
the orders in their original order, as I
consider it convenient to do so.
Determination
Orders sought 1, 2 and 3
The
applicant was correct to suspect as he did the "persuasive" nature of the
material which I referred to in the reasons for the
interim order. Given the
District Court authority for the interpretation of section 51, I conclude that
it is impossible for the
applicant to succeed in any of the first three orders
sought by him in the alternative. The delivery of 6 written votes (including
5
for other owners) by the applicant after the meeting had commenced clearly
contravenes at least two requirements in section 51(2);
namely that an owner
give their voted to the secretary, either personally, by post or by facsimile,
and further, that the vote be
given to the secretary before the start of the
meeting. I consider that the 6 written voting papers sought by the applicant to
be
included in the count of votes in respect of motions, are invalid and of no
effect. I intend to dismiss the first three orders sought
by the applicant for
this reason.
Order sought 4
The applicant next seeks that
the EGM be declared invalid on the grounds that the date had passed for the
EGM to be held on the adjudicators orders which was made on the 3rd
June 2003 and stated that the EGM had to be held no later than 3 months from the
3rd June 2003. The applicant calculates that the meeting ordered
to be held was in fact held some 1 month and 7 days out of time.
I
acknowledge that the EGM required to be held pursuant to my previous order was
held out of time. The question is whether the entire
meeting should now be
invalidated for this reason.
The first consideration is that the failure
to hold the meeting in the time period stipulated is an enforcement issue. This
office
does not act to enforce its orders in any way. Rather, the Act provides
to owners or aggrieved persons mechanism for enforcement
of orders made by
adjudicators. (see Part 10 Enforcement of Adjudicator’s Orders, Ss. 286 to
288).
Notwithstanding this I am prepared to further consider the issue.
The question arises: what will be achieved by invalidating the meeting
for this
reason. The applicant does not address this question. In my view, the effect on
the body corporate will be a negative or
adverse one. The body corporate has
convened a meeting ordered by an earlier adjudication, however it did so
belatedly. I conclude
that it is in the interests of the body corporate that the
meeting was held, rather than not held. The failure to comply with the
time
limitation imposed by me is in these specific circumstances, of no particular
concern to me.
Now I intend to consider the reason for the delay. In a
submission, the chairperson, Rolf Petherbridge has explained that
–
The decision to defer the EGM I made in order to enable it to deal also with other imminent and urgent matters. I made it jointly as applicant for the order and as chair of the body corporate, believing it to be in the body corporate’s best interests and was supported in doing so by the committee. The reason for the delay was explained to the owners (email 17 September 2003 3:38 pm attached) ...
The chairperson sent an email to
the body corporate manager requesting that the contents of the email be included
in the papers for
the EGM in question. In part the email states –
Most of you would be aware that we proposed to hold an EGM by Sept. 3 as required by the Adjudicator’s Order sent out to each of you earlier. AT that time, responding to concerns voiced at the previous EGM, owners were provided with two alternate quotes for the production of an architect’s condition report on the building. The majority (8 to 2) favoured Ralph Power Associate quote, and before the EGM could be called for Sept 3, their David Derbyshire had provided us with his completed report. It raised a number of urgent issues which demanded our attention. I made the decision that it was reasonable, and in the body corporate’s best interest, to defer the EGM for a short time to enable us to deal with all of these issues at one meeting.
The explanation provided by the chairperson to all
owners for the delay in convening the meeting appear to me to be reasonable
justification
for such delay. I note that the applicant has not adduced any
evidence to show than any owner objected to the delay in the convening
of the
meeting. As well, submissions were sought from all owners regarding the
application and no owner has written stating that
they objected to the delay in
the convening of the meeting, or that it caused them to be disadvantaged or
otherwise affected.
Finally, I turn to the actions of the applicant in
regard to this aspect. At all times, in his grounds, the applicant seeks to
evidence
his actions in having the 6 voting papers accepted. He did not press
the point regarding the meeting being out of time. I consider
it clear that if
the six voting papers tendered by the applicant had been accepted, the applicant
would not be objecting to the timing
of the meeting as he now does. It is clear
that the applicant’s interest in the meeting was in having his six voting
papers
accepted. Once it was made reasonably clear to the applicant this would
not happen due to the requirements of section 51, then the
applicant’s
tack changed considerably. It was at this time that the applicant sought to
elevate the issue of delay to "our
number one request". In my view the
applicant’s motives are very transparent, and self serving. Upon realising
that he would
fail on his first line of argument, he then sought to change tack.
For the reasons I have set out, I refuse to order in terms as sought by
the applicant that the meeting be invalidated for the reason
that it was
convened out of time.
Orders sought 5, 6, 7 and 8
Orders
sought 5, 6, 7 and 8 seek penalties be imposed and other orders imposed against
the body corporate manager, John Gribbins Realty
and certain officers or
employees thereof.
The first point to make is that this office has no
power or jurisdiction to impose a "penalty". An adjudicator can make an order
that
certain action be undertaken, but cannot order the imposition of a penalty
in respect of an alleged contravention of the legislation.
Secondly, the
applicant is seeking orders be made against the appointed body corporate
manager, and officers or employees of that
firm. An adjudicator has power to
make an order in respect of a dispute. Section 227 of the Act defines a dispute.
No part of that
definition including a reference to a dispute which may arise
between an individual owner and a body corporate manager appointed
for the
scheme. Only a body corporate for a scheme may be in dispute with a body
corporate manager (see section 227(1)(c)). I conclude
that the orders sought by
the applicant numbered 5, 6, 7 and 8 are beyond power of an adjudicator to make,
and are dismissed for
this reason.
However, in dismissing the
application for orders sought 5, 6, 7 and 8 I will make the observation that the
determination of these
orders, if within jurisdiction, would have depended
significantly on the credibility of the parties, and the veracity of their
various
allegations. The information presented by the applicant as to the events
of the meeting differ markedly from the version of events
provided in
submissions by both the chairperson and the body corporate manager, Linda Payne.
I consider that the applicant would
have had some difficulty in my view in
establishing the accuracy of many of his explanations of events at the meeting.
In my view, the applicant’s version lacks conviction, is not
corroborated by others, tends to be self serving and fails to explain
certain
aspects (for example, the alleged taking of the voting papers by the applicant).
The applicant simply does not refer to this
aspect. Did it not occur? If it did
occur, and at least two others have stated clearly that it did, why does the
applicant not refer
to the event. Is it that perhaps the event is somewhat hard
to explain in a way consistent with the applicant’s version of
events.
Does it perhaps tend to show that the applicant might perhaps not have acted in
an entirely reasonable manner during the
meeting as he clearly sought to suggest
in his material? The answers to these questions are known only by the parties,
but my point
is that in my view, the evidence opposing the application was more
consistent and persuasive than that provided in it.
Orders sought 9
and 10
Finally the applicant has sought an order that motion 12
considered at the meeting be struck out as "out of order" on the grounds
that
the committee had submitted that the motion to be put to the owners was to be
levied as three distinct payments but when the
papers came out it had been
changed by R. Petherbridge (Chairperson) without consultation with committee
members to show the special
levy as a single payment.
In support of this,
the applicant has provided a document annexed Exhibit 3 which he suggests is
proof of a committee determination
to propose the motion contemplating the
special as being levied in three equal payments on three different dates.
However, I do not
consider the document to be evidence of a committee resolution
to this effect. I suggest that minutes of a committee meeting where
this was
resolved would evidence this, not an unidentified document containing a list of
motions. There is no evidence on the fact
of this document that the committee
has adopted or resolved that these motions be proposed at the general meeting to
be convened.
The chairperson has made a submission in response. He
states –
That motion 12 was a budgetary motion proposed by myself in my capacity as an individual owner, and in the absence of agreement by the committee, was made clear to all owners in the meeting papers. My decision to resort to this solution to an apparent impasse was communicated to the committee secretary the same date it was made (email 17 September 2003 ... )
The
email, which went to all owners as part of the meeting notice and agenda,
includes the following paragraph –
The EGM agenda, as well as including motion authorising these works, including a motion to fund these works through a special levy at near minimum notice. The current sinking fund balance (less than $12000) is not sufficient to provide for these works. This motion would normally be proposed by the committee but is not in this case. In discussions with the other committee office bearers I have tried to get agreement on how and when these funds should be raised and when these works should be scheduled. Thus far these attempts have been fruitless and, in order to avoid any further delay in the holding of the EGM and the initiation of these works, I have decided to put use my rights as an owner to propose a motion funding these works – a motion which does so outright at the earliest opportunity.
This explanation to all
owners does more than simply explain that the motion is submitted by the
chairperson as an owner and not by
the committee; it also suggests a deadlock or
impasse by the committee in this aspect. This is contrary to what the applicant
has
suggested. As I have already stated, the applicant has not evidenced to me
that the committee did resolve to propose the motion in
the manner he
suggested.
In all the circumstances, I consider that there was no
invalidity in the manner in which the motion was put to owners. Moreover, the
motion was resolved in the affirmative by 10 votes in favour with one against.
As I have already acknowledged in the interim order,
even the six votes held by
the applicant, assuming a "no" vote against motion 12, would not have defeated
the motion. The body corporate
in general meeting has determined by majority
resolution to collect the levy in one amount, rather than 3. In the
circumstances,
I intend to dismiss the applicant’s application in respect
of motion 12. I conclude the resolution taken in respect of motion
12 at the EGM
held on 10 October, 2003 to be valid and enforceable.
I note that this
determination has implications for the entitlement of owners to vote at the
forthcoming AGM proposed for 31 March,
2004. I suggest that owners who have not
yet paid the contribution required by motion 12 do so immediately in order to
ensure their
voting entitlements at the forthcoming AGM.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2004/169.html