![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 17 May 2005
REFERENCE: 0441-2003
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
24652
|
|
Name of Scheme:
|
Grosvenor Apartments - Brisbane
|
|
Address of Scheme:
|
PO Box 7972 BUNDALL QLD 9726
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by the Body Corporate for Grosvenor Apartments - Brisbane, CTS 24652
|
I hereby order that the application for an
order that the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652
be restrained and an
injunction hereby granted restraining the owners from
installing, causing to be installed or placing upon any part of the lot hard
flooring for a period to be ordered by the adjudicator or until further order in
accordance with section 279(2) of the Body Corporate and Community Management
Act 1997 (Qld), is dismissed.
I further order that the owners of lot 53 shall, within 14 days of the date of this order and at their cost, have the Floor Impact Isolation Class of the installed flooring determined by a field test conducted by an accredited acoustic consultant approved by the committee and provide a copy of the consultant’s report to the committee and to the Office of the Commissioner for Body Corporate and Community Management. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION -
REF 0441-2003
"Grosvenor Apartments - Brisbane" CTS
24652
The applicant, the body corporate for Grosvenor Apartments – Brisbane, has sought an interim order of an adjudicator under the Body Corporate and Community Management Act 1997 (the Act) as follows:
1. That the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652 be restrained and an injunction hereby granted restraining the owners from installing, causing to be installed or placing upon any part of the lot hard flooring for a period to be ordered by the adjudicator or until further order in accordance with section 279(2) of the Body Corporate and Community Management Act 1997 (Qld). 2. That the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652 remove the works from the lot in accordance with by-law 22.5(e) of the scheme in the event that the owners install, cause to be installed or place in or upon any part of the lot hard flooring in contravention of the scheme (sic).
The applicant also sought final orders in
similar terms.
Section 276(1) of the Act provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory
order) to resolve a dispute, in the context of a
community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
Section
279(1) of the Act allows an adjudicator to make an interim order if
satisfied, on reasonable grounds, that an interim order is necessary
because of
the nature or urgency of the circumstances of the application.
In the
supporting grounds, the applicant referred to the relevant by-law, provided a
chronology of events, and stated that it had
been informed that notwithstanding
the body corporate committee having refused, on or about 29 January 2003, the
request by the owners
of lot 53 to install hard flooring in their lot, such
flooring was scheduled to be installed on 27 June 2003.
The application
was received in the Commissioner’s office mid afternoon on 27 June 2003.
On 30 June 2003, the applicant’s
solicitors forwarded a copy of the flying
minute, evidencing the committee’s authorisation for the lodgement of the
application.
The Commissioner has referred the application to me pursuant to
section 247 of the Act, to consider whether an interim order should be
made.
On 30 June 2003, a member of the Commissioner’s staff
arranged a teleconference at 9.30am on 1 July 2003 between the applicant’s
solicitors, and the solicitors for the respondents, the owners of lot 53.
I conducted the teleconference as scheduled. Mr Mark Peacock, a partner
of Hopgood Ganim Lawyers, represented the applicant body
corporate. Mr David
Jenkins, a partner of Nicol Robinson Halletts Lawyers, represented the owners of
lot 53, Robert Anthony Hines
and Margaret Patricia Walker. Although the
respondents had not been formally invited by the Commissioner to respond to the
application,
prior to lodging the application on 27 June 2003 Mr Peacock had
provided Mr Jenkins with a copy of the application, and had also
arranged for a
letter to be placed under the door of the respondents’ lot, when his
various attempts to contact Mr Hines earlier
that same day had been
unsuccessful. The letter dated 27 June 2003 placed Mr Hines on notice that an
application was to be made
to the Commissioner’s office for an order that
the installation works cease. During the course of the teleconference, Mr
Jenkins
advised me that Mr Hines was absent from Brisbane on holiday. I
requested that Mr Jenkins ascertain the progress of the installation.
The
teleconference was reconvened on 1 July 2003 at 2.30pm, at which time Mr Jenkins
advised me that the installation was 80% complete.
There was also
considerable discussion between Mr Peacock and Mr Jenkins concerning by-law 22.5
and whether the respondents had obtained
approval for the installation of the
floors.
Mr Peacock’s instructions were that approval had not been
obtained, which of course precipitated the application, and in support
of that
argument, Mr Peacock relied upon the flying minute appearing as annexure 3 in
the material.
Mr Jenkins relied upon a statement provided by Mr Hines,
in which he stated that he had been advised by the body corporate manager
and
later, certain members of the committee, that the installation of timber
flooring would not be a problem as long as it complied
with the requirements of
the body corporate by-laws, and satisfied the noise benchmarks.
At this
time, I am primarily concerned with the application for an interim order. In
any consideration of an application that seeks
the making of an interim order,
it is necessary to determine whether, because of the nature or urgency of the
circumstances relating
to the application, an interim order is in fact necessary
or appropriate.
The examples included in the Act under section
279(1) are suggestive of the usual circumstances where an interim order
might be made. Both examples are in the nature of injunctive relief.
Whilst
the range of matters that might be the subject of an interim order is not
capable of definition, the applicant does need
to establish that the
circumstances of the application warrant the making of an interim
order.
An interim order will not be made, or will be refused, in
circumstances where the only urgency relates to the applicant’s desire
to
resolve or expedite the matters in dispute, or where the nature of the
circumstances are such that the matter is not capable of
being dealt with in the
context of an interim order. Again, it is not possible to define these
circumstances.
However, given that an interim order may be made ex parte
(ie. without reference to, or submission from, the respondent named in the
matter), then as a guide, where the circumstances or matters in dispute include
matters or allegations not capable of expeditious,
and objective consideration,
then the request for an interim order may be refused. It is a matter for an
adjudicator to determine
in respect of each application.
It is common
ground that the respondents have not obtained written approval for the
installation of their flooring. However, the
installation was 80% complete on 1
July 2003. Mr Jenkins submitted that, on the balance of convenience, the work
should be allowed
to continue, so that acoustic testing on the installed floor,
as envisaged by by-law 22.5(b)(ii), can be carried out. Mr Jenkins
stated that
his clients are well aware of their responsibility under by-law 22.5(b)(iii),
but are confident that the flooring will
achieve the performance specification
set out in by-law 22.5(b)(i).
Mr Peacock’s view was that as the
respondents had not obtained approval for the installation, then an order should
be made suspending
the works, otherwise the authority of the body corporate
committee would be completely undermined, and any owner who just chose to
flout
the by-laws would essentially do so with impunity.
I do not propose to
make any finding at this stage as to whether the respondents were justified in
assuming they had committee approval
in principle, for the installation of the
flooring. I note that Mr Hines referred to his various conversations with
certain members
of the committee and the body corporate manager. No doubt the
specific content of these conversations will be detailed further in
later
material.
In my view an order suspending the works would do no more
than create a most unsatisfactory hiatus. The acoustic testing could not
be
carried out on a completed floor, and the lot would be uninhabitable in its
present state. To require the respondents to remove
the flooring at this stage
would prevent them from demonstrating that the flooring did in fact meet the
noise benchmarks. The respondents
are apparently aware of the consequences
should the benchmarks not be met. Furthermore, the body corporate is not
disadvantaged
by my decision not to suspend the works, as its remedies are still
available in final orders.
I intend therefore to dismiss the application
for an interim order suspending the works. I do, however, intend to order that
the
acoustic testing be carried out and a report on that testing be provided to
the body corporate and to this office within 14 days
of the date of this order.
At that time, the application for final orders shall be further
considered.
REFERENCE: 0441A-2003
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
24652
|
|
Name of Scheme:
|
Grosvenor Apartments - Brisbane
|
|
Address of Scheme:
|
PO Box 7972 BUNDALL QLD 9726
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by the Body Corporate for Grosvenor Apartments - Brisbane, CTS 24652
I hereby order that the owners of lot 53, Grosvenor Apartments
– Brisbane CTS 24652 shall arrange for Dynamic Timber Floors to remove
skirting
boards in lot 53 on Friday 10 October 2003 for the purpose of
conducting a visual inspection, and, if indicated, remediation work,
and
thereafter acoustics testing.
I further order that in the event
that the acoustics testing meets the FIIC performance levels set out in the
by-laws the owners of lot 53 will make
contact with Ron Rumble Pty Ltd with a
view to having the tests verified either on Friday 10 October 2003 or as soon as
practicable
thereafter.
I further order that in the event that
the acoustic testing does not meet the FIIC performance levels set out in the
by-laws, then the owners of
lot 53 shall, by 5.00pm on Tuesday 14 October 2003,
produce a report from Dynamic Timber Floors and/or its acoustics engineer, Mr
Roger Hawkins, setting out what further remediation work and testing is proposed
for the consideration of the adjudicator and the
applicant.
I further
order that in the event that objection is raised by the applicant to the
further proposal a teleconference between the parties shall be
held on Wednesday
15 October 2003 at 2.00pm.
I further order that in the event that
no objection is raised by the applicant to the further proposal, the work and
further acoustics testing shall
be completed within 14 days from the date of the
report.
I further order that in the event that the further
acoustics testing meets the FIIC performance levels set out in the by-laws the
owners of lot 53
will make contact with Ron Rumble Pty Ltd with a view to having
the tests verified as soon as practicable after the completion of
the work.
I further order that in the event that Ron Rumble Pty Ltd
confirms that the timber flooring then meets the FIIC performance levels set out
in the
by-laws this application shall be at an end.
STATEMENT OF
ADJUDICATOR’S REASONS FOR DECISION - REF
0441-2003
"Grosvenor Apartments - Brisbane" CTS
24652
The applicant, the body corporate for Grosvenor Apartments – Brisbane, has sought an interim order of an adjudicator under the Body Corporate and Community Management Act 1997 (the Act) as follows:
3. That the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652 be restrained and an injunction hereby granted restraining the owners from installing, causing to be installed or placing upon any part of the lot hard flooring for a period to be ordered by the adjudicator or until further order in accordance with section 279(2) of the Body Corporate and Community Management Act 1997 (Qld). 4. That the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652 remove the works from the lot in accordance with by-law 22.5(e) of the scheme in the event that the owners install, cause to be installed or place in or upon any part of the lot hard flooring in contravention of the scheme (sic).
The applicant also sought final orders in
similar terms.
On 4 July 2003, I made the following interim order:
I hereby order that the application for an order that the owners of lot 53, Grosvenor Apartments – Brisbane CTS 24652 be restrained and an injunction hereby granted restraining the owners from installing, causing to be installed or placing upon any part of the lot hard flooring for a period to be ordered by the adjudicator or until further order in accordance with section 279(2) of the Body Corporate and Community Management Act 1997 (Qld), is dismissed.
I further order that the owners of lot 53 shall, within 14
days of the date of this order and at their cost, have the Floor Impact
Isolation Class
of the installed flooring determined by a field test conducted
by an accredited acoustic consultant approved by the committee and
provide a
copy of the consultant’s report to the committee and to the Office
of the Commissioner for Body Corporate and Community Management.
The
installation of the timber flooring has subsequently been completed, and
acoustic testing has revealed that it does not presently
meet the FIIC
performance levels required in the by-laws.
On 6 October 2003 I
conducted a meeting between the parties, their legal representatives and two
acoustic engineers, Mr Ron Rumble
and Mr Roger Hawkins and the technician who
conducted the acoustic testing for Ron Rumble Pty Ltd. It was agreed that
further interim
orders would be made to facilitate the timely completion of
remediation work required to be undertaken on the timber flooring.
The
chairperson of the body corporate, Mr Dart, advised the parties that the owner
of the lot below the respondents’ lot, Ms
Hopkins, had instructed him that
she would make her lot available on 10 October 2003 between 9.00am and 5.00pm to
enable further
acoustic testing to be carried out.
I have made further
interim orders as agreed.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2003/8.html