![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 12 September 2007
REFERENCE: 0440-2002
ORDER OF AN ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
6537
|
|
Name of Scheme:
|
Trinity Place
|
|
Address of Scheme:
|
1 James Street BEENLEIGH Q 4207
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Hysten Pty Ltd, the Owner of Lot 1 and Lot 2:
I hereby order that the application for
the following adjudicator’s orders:
"1. That the Respondent pay the Applicant the sum of $7,968.60 being the cost of installation of an air- conditioning unit to service Lot 2 in the scheme.2. The Respondent remove the constructions on the common property adjacent to the entrance of Lot 5 in BUP 8761 where such construction has encroached upon the common property of the Scheme.
3. The Respondent
remove all improvements to the exterior of the building and reinstate the
exterior of the building as far as possible
to its original
condition."
is dismissed under section 270(1)(b) of the
Body Corporate and Community Management Act 1997 on the basis that the
matters in dispute should be dealt with in a court or tribunal of competent
jurisdiction.
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION
- REF 0440-2002
"Trinity Place" CTS 6537
1. Orders sought
The Applicant, the Owner of Lots 1
and 2, has sought the following adjudicator’s orders under the Body
Corporate and Community Management Act 1997 ("the Act"), quote-
"1. That the Respondent pay the Applicant the sum of $7,968.60 being the cost of installation of an air-conditioning unit to service Lot 2 in the scheme.2. The Respondent remove the constructions on the common property adjacent to the entrance of Lot 5 in BUP 8761 where such construction has encroached upon the common property of the Scheme.
3. The Respondent remove all improvements to the exterior of the building and reinstate the exterior of the building as far as possible to its original condition."
The Applicant has identified Big C
Investments Pty Ltd, the Owner of Lots 5 and 6, as the Respondent to the
application.
Section 276(1) of the Act provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory order) to
resolve a dispute, in the context of a
community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
2. Scheme details
The "Trinity Place" community titles
scheme was originally created under building units plan of subdivision 8761,
which was registered
on 8 November 1988. Lot 4, and some common property of the
scheme, formed the subject of a building units plan of re-subdivision
registered
on 27 June 1990. The scheme currently consists of 5 lots (Lots 1, 2, 3, 5 and
6) and common property. The building is
currently used for commercial
purposes.
A new community management statement was recorded for "Trinity
Place" on 19 October 1998, and indicates that the Body Corporate and
Community Management (Commercial Module) Regulation 1997 ("the Commercial
Module") applies to the scheme.
3. Application details
This is one of two closely related
dispute resolution applications concerning the "Trinity Place" Body Corporate
currently before
this Office. While the other application (reference number
0584-2002) will be the subject of its own order and statement of reasons,
at the
request of the parties, I have decided to deal with both matters concurrently on
the basis that similar issues are raised
in both applications.
This
application (0440-2002) was made on 23 July 2002. On 28 August 2002, the
Commissioner for Body Corporate and Community Management
("the Commissioner")
invited the Committee for the Body Corporate, and the Respondent, to make a
written submission about the application.
The Respondent provided a written
submission about the application under cover of a letter dated 16 September
2002.
In accordance with the then section 196 of the Act (recently
renumbered as section 246), the Applicant requested and was provided with
a copy of the Respondent’s submission. The Applicant has provided a
written
response to the submission.
On 14 October 2002, the Commissioner
made an initial case management recommendation that the application should be
the subject of
departmental adjudication.
Section 271 of the Act
provides adjudicators with particular powers to investigate dispute resolution
applications. On 3 June 2003 and pursuant to those
powers, I conducted an
inspection of the scheme land and met with Mr Douglas McGregor (representing the
Applicant), and Mr John Gould
of Compass Legal Solutions and Mr Mark Seabrook
(both representing the Respondent).
I had three main purposes for my
inspection of scheme land and meeting with the parties. Firstly I wished to see
the improvements
and alterations that are the subject of the application.
Secondly, I wished to raise with parties the possibility of mutually acceptable
outcomes to the matter in dispute. Finally, I wished to discuss with the
parties and attempt to reconcile the significant inconsistencies
between the
parties’ versions of events as presented in the written material.
Regrettably, Mr McGregor decided to withdraw
from the meeting prior to these
outcomes being achieved in any meaningful way.
4. Determination
After carefully reviewing the material provided by the parties concerning this application, and following my meeting with the parties, I have decided that this application should be dismissed pursuant to section 270(1)(b) of the Act. Section 270(1)(b) provides that an adjudicator may make an order dismissing a dispute resolution application if "the adjudicator is satisfied the dispute should be dealt with in a court or tribunal of competent jurisdiction." Section 270(2) of the Act goes on to state that an adjudicator may make an order in these terms without investigating the detail of the application, or before an investigation has ended.
As will be outlined in more detail below, the parties to this application
have presented significantly inconsistent versions of a
range of key events and
aspects of the matters in dispute. It seems to me that resolving these issues
requires an assessment of
the credit of the parties, and perhaps the
presentation of evidence by witnesses. In my opinion, the most equitable way of
gathering
and assessing this information will be via the presentation of
evidence on oath, with a facility for cross examination.
While the
legislation provides adjudicators with certain investigative powers pursuant to
section 271 of the Act, including the power to require parties to provide
information in the form of a statutory declaration (section
271(1)(a)(iii)), adjudicators are not empowered to conduct hearings where
evidence is presented on oath, and where parties have an opportunity to
cross-examine witnesses. In my view, the significant inconsistencies between
the parties recollections and versions of relevant
events can best be determined
in a forum where parties can present information, and be questioned, orally. I
consider that it is
unlikely that these matters can be effectively resolved by
way of written statutory declarations.
I have also had regard to the
seriousness of the relief sought by the Applicant. As will be outlined in more
detail below, the Applicant
is seeking reimbursement of almost $8,000 for the
installation of an air-conditioning unit. In addition, the Applicant is seeking
the removal of improvements and alterations to the building made by the
Respondent, which I understand cost around $120,000 (as indicated
by the
Respondent at our meeting). In my opinion, the seriousness of the relief sought
in the application warrants the evidence
being as effectively tested as
possible.
As a result, I do not consider that I am in a position to
fairly and equitably determine the key issues raised in this application.
I wish to emphasise that my decision to dismiss this application
pursuant to section 270(1)(b) of the Act is not based on my views on the
merits of the application, but on my view of the most equitable way of
determining the matters in
dispute. However, notwithstanding the above, I will
make some brief comments regarding the key issues in dispute.
4.1 Air conditioning unit
The Applicant alleges that the Respondent caused an air conditioning unit
servicing Lot 2 to be removed, without the Applicant’s
consent. The
Applicant states that while this air conditioning unit was located on common
property, it was the property of the Applicant,
installed with the prior
approval of the Body Corporate. The Applicant considers that the Respondent
should reimburse it for costs
of purchasing and installing a new air
conditioning unit amounting to $7,968.60.
In its submission, the
Respondent states that it was advised by an air conditioning technician that the
air conditioning unit in question
was inoperable. The Respondent also states
that it caused the air conditioning unit to be removed, and placed on the
footpath for
some time before it was ultimately disposed of.
On the basis
of the submissions, I consider that the Applicant has a strong claim for
reimbursement of at least some of the costs
of purchase and installation of a
new air conditioning unit. Regardless of whether the unit was defective, it
seems most improper
for a lot owner to remove and dispose of a lawfully
installed asset of another lot owner without the person’s knowledge or
consent.
However, notwithstanding the above, while the
Applicant’s representative maintained at our meeting that the Applicant
had no
prior knowledge of the removal of the air conditioning unit, the
Respondent’s representatives indicated that the builder who
carried out
the renovation work described below had walked around the site with the
Applicant outlining the proposed improvements.
If I understand it correctly,
the Respondent believes that the builder discussed the issue of the removal of
the air conditioning
unit with the Applicant’s nominee prior to the air
conditioning unit being removed, and as a result the Applicant was well
aware of
the proposed removal of the unit prior to the work being carried
out.
This issue is one of the inconsistencies described above, and a
matter that I consider can only be properly resolved through a formal
questioning of parties, and perhaps by calling the builder to present evidence
on oath about the extent and content of discussions
that he had with the
Applicant’s nominee prior to the removal of the air conditioning
unit.
4.2 Encroachment on common property outside of Lot 5 and other improvements to common property
The remaining two orders sought by the Applicant concern alterations and
improvements to the scheme land carried out by the Respondent.
The first matter
concerns an area of common property on Level B of the building, between Lots 5
and 6. I understand that the Respondent
has made significant alterations to
this area, which the Applicant considers may impact on the Body
Corporate’s insurance,
and ability to access common property utility
infrastructure. I would comment that in my opinion, the alterations effectively
incorporate
this area of common property into Lots 5 and 6, and I note that the
Respondent wishes to resurvey the building with a view to formally
incorporating
the area into Lot 5 or Lot 6.
In addition, I understand that the
Respondent has carried out other significant renovations to the external
surfaces of the building,
some of which form part of the common property for the
scheme. As mentioned above, one of the Respondent’s representatives
indicated that the renovations cost approximately $120,000.
The
Applicant alleges that the renovations were carried out without the approval of
the Body Corporate, and is seeking an order that
the alterations be removed, and
the common property reinstated to its previous condition.
The Respondent
argues that the improvements enhance the value of the building and should
remain. More importantly, the Respondent
alleges in its submission (and at our
meeting) that the improvements were carried out with both the knowledge, and
consent of the
Applicant. The Respondent alleges that the builder who carried
out the work walked around the site with the Applicant explaining
in detail the
proposed work. In addition, and if I understand them correctly, the
Respondent’s representatives indicated that
the Applicant agreed to paint
the exterior of the ground floor lots in a colour matching the improvements
proposed by the Respondent.
Clearly, the consent of the Applicant to the
improvements is a key aspect of resolving this application, and should be
equitably determined
before any order is made requiring the renovations to be
removed. For the reasons outlined above, I do not consider that I have
the
power to effectively and equitably assess the evidence in order to make a
reasonable determination on the issue.
5. Conclusion
For
the reasons outlined above, I have dismissed this application under section
270(1)(b) of the Act.
However, in my opinion, some of the issues
have the potential to be effectively resolved between the parties through
negotiation,
or perhaps mediation. For example, while I am not advocating that
lot owners make alterations to common property without body corporate
approval,
if the renovations genuinely add value to the scheme land benefiting all owners,
there could be some way of addressing
the Applicant’s safety and insurance
concerns without requiring the removal of all of the renovations.
Similarly, while the area between Lots 5 and 6 forms part of the common
property for the scheme, it seems to me that this area is
of little use of any
other lot owners. The Body Corporate could consider an arrangement such as
allocating this area for the exclusive
use of the owner of Lot 5 or 6, provided
appropriate arrangements were put in place for affected utility infrastructure
and access
to the lots. I consider that it would be reasonable for the Body
Corporate to be compensated for approving the allocation, and note
that
section 103(1) of the Commercial Module contemplates exclusive use
by-laws imposing conditions, such as the owner with the benefit of the exclusive
use by-law making a payment or periodic payments to the body
corporate.
While the above is certainly not intended to be an exhaustive
list of possible solutions for the "Trinity Place" Body Corporate, it
seems to
me that there are potential mutual benefits for the parties in making genuine
attempts to resolve some of these matters
internally, prior to pursuing a
judicial determination of the matters. This is entirely consistent with the
secondary objects of
the Act, which contemplate self-management as an inherent
aspect of community titles schemes (section 4(a)).
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2003/569.html