![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 17 May 2005
REFERENCE: 0772-2002
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY
MANAGEMENT ACT 1997
|
Number of Scheme:
|
15022
|
|
Name of Scheme:
|
Tobermory
|
|
Address of Scheme:
|
216 The Esplanade BURLEIGH HEADS QLD 4220
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Paul ROGERS, as a co-owner of Lot 5,
I hereby order that the tender by All
Areas Bathroom Renovations, principal and licensee Peter Stuart Wilson, dated 1
November 2002 for the amount
of $9,580 (adjusted for any reasonable increase in
price in line with this type of work generally), must be accepted by the body
corporate and the work carried out as soon as possible.
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0772-2002
"Tobermory" CTS 15022
The applicant, Paul Rogers of Lot 5, has sought the following orders of
an adjudicator under the Body Corporate and Community Management Act 1997
("the Act") -
"That the quotation submitted by All Areas Bathrooms in the amount of $10,780 less $1,200 for work required by others, be accepted to enable Adjudicator’s Order dated 0313-2001(sic) to be complied with."
JURISDICTION:
This is a dispute
between an owner (the applicant Rogers) and other owners (the respondents: Gwen
Dixon, the owner of Lot 4; Hepron
Pty Ltd, the owner of Lot 1 (directors Neil
Dixon and Linda Dixon); and Hepron Pty Ltd and Palcourt Pty Ltd (directors as
for Hepron
Pty Ltd), the co-owners of Lot 6, concerning the engagement of a
service provider by the body corporate to carry out waterproofing
work to the
deck of Lot 4 to prevent water penetration into the garages of Lots 1, 2 and 4
below, as determined in Order 313-2001
of 27 September 2001. This is a matter
falling within the disputes resolution provisions of the legislation (see
sections 227, 228 and 276 of the Act) however there are two jurisdictional
issues that I need to address before continuing in determining this
application.
Firstly, the applicant wrongly attributes Order 313-2001 to
Mr Mobley of this office: I was the adjudicator who determined the order
(Mobley
completed the administrative task of signing
the accompanying letter). I
mention that because there is a rule, called the
functus officio rule,
which prevents an adjudicator (or court) from dealing again with a matter which
the adjudicator (or court) had already finally
determined. The question arising
here is whether the subject dispute as to how the repairs should be carried out
and who should
carry them out, is really a matter of enforcement of Order
313-2001 to be actioned by the respondents in the Magistrates Court under
section 288 of the Act. After consideration of the matter, I am of the view
that I am able to proceed as the dispute concerns the scope and
manner of the
necessary repair work, rather than mere non-compliance with the
order.
Secondly, the respondents Neil and Linda Dixon have made a written
complaint to the relevant government minister alleging incompetence
and/or a
possible personal interest by a staff member of this office, in delaying
this application being determined. They have made an analogous reference to the
shorter
time taken to determine a previous order, Order 322-2003. I can only
say that adjudicators randomly take up files on a chronological
basis after they
have been administratively processed
by the office (collated, submissions
sought, notices sent, etc). Currently,
files are taking in the vicinity of six
months to be
determined, as is the case with this application. The causes of
delays are
a matter or resources and large increases in applications
caused
mainly by the rising levels of unit ownership in community title
schemes. The
time taken to determine applications has varied
over the years in accordance
with the fluctuating level of resources
and applications. I can state that I
have no personal knowledge
of, or relationship with, any of the owners in the
scheme, and this
matter will be dealt with solely on its facts and no other
basis.
If anything, in Order 313-2001 my determination was against the
body
corporate and favourable to the respondents, however that was merely the result
of the
application of the relevant law and,
as with this application, persons
and interests play no part.
For the above reasons, I know of no
jurisdictional bar why I should not continue to determine this matter.
General powers of an Adjudicator in making an order:
Section 276(1) provides that an adjudicator may make an order that is just and equitable in the circumstances (including a declaratory order) to resolve a dispute, in the context of a community titles scheme, about –
a) a claimed or anticipated contravention of the Act or the community management statement; or b) the exercise of rights or powers, or the performance of duties, under this Act or the community management statement; or c) a claimed or anticipated contractual matter about – (i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or (ii) the authorisation of a person as a letting agent for a community titles scheme.
An order may require a person to act, or prohibit a person from acting, in a
way stated in the order (section 276(2) of the Act).
An adjudicator’s
order may contain ancillary or consequential provisions the adjudicator
considers necessary or appropriate
(section 284(1) of the
Act).
APPLICATION AND SUBMISSIONS:
In accordance with
section 243 of the Act, a copy of the application was provided to the
respondents and to all other owners, with an invitation to respond to the
matter
of
dispute raised in the application. All of the respondents representing Lots
1, 4 and 6 (Gwen Dixon, and Neil and Linda
Dixon for
Hepron Pty Ltd and Palcourt
Pty Ltd), made a joint submission. The applicant Rogers viewed the submission
and subsequently
lodged
a written reply (see sections 246 and 244 of the Act
respectively).
The brief facts of the matter are as follows.
In
early 2001, the body corporate made application for an adjudicator to determine:
the cause of water penetration from the Lot 4
deck into the garages for Lots 1,
2 and 4 underneath, and the outside walls; how the problem could be rectified;
and who is responsible
for the necessary repair and rectification work. The
following order was made by me for that application –
I hereby order that, within two (2) months of the date of this order the body corporate shall engage a suitably qualified person to inspect and report on the most effective way to –
1. prevent water entering the garages of Lots 1, 2 and 4 from the deck of Lot 4.
2. drain storm water from the deck of Lot 4 to prevent further damage to the garage doors and their fixtures and fittings and the common property walls.
3. prevent water seeping from the garden beds constructed on the deck of Lot 4 to prevent further damage to the common property walls.
I further order that within a further two (2) months, the body corporate must at its cost engage appropriately qualified tradespersons to carry out the work recommended in the reports on matters 1 and 2 above, with the work to be commenced and continued so as to be completed within a reasonable time but no later than six (6) months from the date of this order.
I further order that within a further two (2) months, the owner of Lot 4 must at her cost engage appropriately qualified tradespersons to carry out the work recommended in the reports on 3 above, with the work to be commenced and continued so as to be completed within a reasonable time but no later than six (6) months from the date of this order.
Obviously the time periods set in the order were
never met, though Gwen Dixon has since removed the garden beds, and the repairs
to
the deck have not be carried out.
The applicant broadly states the
position as follows. The applicant (and apparently the other two owners of Lots
2 and 3) says that
the delays are the fault of the respondents who act and vote
as a group (Gwen Dixon is reportedly the mother of Neil Dixon). Quotes
were
initially obtained from Frank Milla Homes and Evanspalm and the latter, the
cheaper, was acceptable to the applicant and the
owners of Lots 2 and 3 ("the
applicant’s group"). However the respondents objected to Evanspalm on the
grounds that it was
not licensed to do the necessary work. A letter from the
Building Services Authority dated 15 February 2000 stating that the work
envisaged did not require a licensed person, was rejected by the respondents.
The applicant’s group then sought acceptance
of the alternative quote by
Millaa Homes but Neil Dixon, who is a builder, refused this also, allegedly on
the basis that the quote
raised "vagaries and technical construction and
legal flaws". The Body Corporate Manager (D Watkins) then asked Dixon to
list out what he thought should be done to remedy the problem, which he
subsequently did and referred to as a "Scope of Work". A copy of that document
was provided to owners and forms part of the application
attachments. The
applicant subsequently obtained a quote from All Areas Bathroom Renovations,
after showing its principal, Peter
Wilson, Dixon’s "Scope of Work".
Wilson said that some of the items listed were not necessary for rectifying the
water seepage
problem, and gave a quote of $10,780 on this basis. Dixon then
objected on the grounds that All Areas Bathroom Renovations is not
licensed for
the work and it would be illegal to accept an unlicensed contractor. In
summary, the applicant believes that he and the owners of Lots 2 and 3 have
acted properly in trying to have the problem resolved
but the respondents
(especially Neil Dixon) have been unreasonable in their demands and have
frustrated their attempts to have the
problem rectified in a reasonable manner
by a qualified person – he rejects the allegation by Dixon that he has
acted in an incompetent manner. He also states that some contractors
approached did not want Dixon instructing them in the work while others were
reluctant to quote.
The respondent’s position is that the body
corporate having been found to be responsible for the work, then it should do
the
work properly in accordance with the standards set out in Dixon’s
"scope of work" and he estimates the work will cost between
$12,500 and $15,000
if done correctly. The tenders by Evanspalm and Frank Milla (Miller?) Homes
were for much less than this; Dixon
found that Evanspalm had no licence (though
the QBSA said none was required for the type of work) and the other’s
tender was,
as referred to above by the applicant, Due to vagaries and
technical construction and legal flaws contained within this quote acceptance of
quote was not forthcoming. Dixon states that after this, he prepared the
"scope of work" due to the technical illiteracy of fellow unit holders and
uncertainty as to work that was going to be undertaken. After receiving the
quote from All Areas Bathroom Renovations, Dixon was unable to find any license
for the principal Peter Wilson.
The respondents complain that it is now over
1.5 years since the relevant order was made and believe that the applicant
should be
responsible for the cost increases in tender prices as they are a
result of his incompetency and laid back approach.
DETERMINATION:
"Tobermory" was registered as a building
units plan (now termed a building format plan) and comprises six
residential lots. It is regulated by the Body Corporate and Community
Management (Standard Module) Regulation 1997 ("the Standard Module").
The original licence number given for Peter Wilson, the principal of All
areas Bathroom Renovations, was incorrect, and the correct
one is 64205. A
search of this number on the QBSA website at the date of this order, shows
Wilson to have an active licence to contract
with the public in the following
three areas –
• Building Restricted Renovations – Wet Areas.
• Building Restricted to Renovations, Repairs and Maintenance.
• Waterproofing Application.
From the evidence
before me it appears that Wilson is suitably licensed, and therefore suitably
qualified, to carry out the type of
work that is required to remedy the water
leaking problem subject of Order 313-2001. I note that the concluding objection
of the
respondents in their submission was, The reason that no agreement can
be reached is due to the unlicensed contractors being nominated by the Chairman
(the applicant) to undertake the subject remedial work, which has now
been met with the information that Wilson is indeed licensed. However, I have
also noted the comments of the applicant
concerning Wilson’s statement to
him that all of Dixon’s "scope of work" was not necessary, and I assume
that Dixon,
if not all the respondents, are not happy with this
view.
However, if Wilson is licensed to carry out wet area renovations,
general building repairs, and waterproofing applications, then,
on the face of
it, his assertion that he is able to carry out the work appears correct. Too
much time has been wasted already in
getting the matter to this stage, and it
should proceed as soon as possible to prevent further price
escalations.
I note that the "scope of work" stipulates replacement tiles
@ $28.50 a sq metre. I am unaware of the value of the present tiles,
however
the rule in such work is that the owner cannot expect to be put in a better
position than before the repairs by way of either
a better quality fitting,
tile, etc, or additional items except as are necessary for the repair. If the
respondents want a more
expensive tile (or other item) then they must pay the
difference between the replacement cost and the preferred item cost.
I
have also noted the comment that there has been less leakage into the garage of
Lot 2 since the removal of the gardens and pot plants
on Lot 4 (Gwen
Dixon).
In the circumstances, I have allowed the order by the applicant
Rogers for All Areas Bathroom Renovations to carry out the repairs
at a cost of
$10,780 – 1,200 = $9,580. I have not included in my order any authority
for Neil Dixon to supervise or instruct
the contractor in regard to the work.
Wilson is licensed and therefore presumably competent in his work and should be
allowed to
work without having to respond to another person, even though Dixon
is a builder himself. The proof of the work will be in its function
and finish.
As the tender was given on 1 November 2002 some 8 months ago, it is likely that
the price will have increased since –
I have included a provision that if
the increase is reasonably in line with that generally in the type of repairs,
then the work
can proceed on the authority of the order.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2003/31.html