![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 17 May 2005
REFERENCE: 0012-2003
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY
MANAGEMENT ACT 1997
|
Number of Scheme:
|
30554
|
|
Name of Scheme:
|
27 Aberleigh Road
|
|
Address of Scheme:
|
27 Aberleigh Road, HERSTON QLD 4006
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Jun Wang, the Owner of lot 1
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0012-2003
"27 Aberleigh Road" CTS 30554
The applicant, Jun Wang, has sought an order of an adjudicator under the Body
Corporate and Community Management Act 1997 (the Act)
that the body corporate
fence a large excavation within the exclusive use area allocated to lot 1, to
make it safe, and,
further,
that the body corporate request the developer to
flatten the ground with soil within the same exclusive use area where subsidence
has occurred.
Section 276(1) of the Act provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory
order) to resolve a dispute, in the context of a
community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
The applicant
contends that an excavated area within the exclusive use area allocated to his
lot is unsafe in its present state.
He states that the excavation is about
670mm below the ground and is surrounded by vertical timbers. I note that the
applicant purchased
his lot in October 2002, shortly after the plan registered.
He would therefore have been aware of the existence of the excavated
area when
he purchased. I would have thought that the time to make an objection to the
area, if he considered it to be dangerous,
would have been prior to the
settlement of his contract. He also expresses concern that an area on the back
and side of the building
where water pipes were laid by the developer has now
settled, leaving the ground surface 200mm or more lower than the rest of the
ground. The applicant believes that ultimately the building might be at risk if
further soil erosion occurs near the timber wall
adjacent to the
building.
The body corporate committee and the other two owners were
invited to respond to the application. No submissions were received.
However,
a member of the Commissioner’s staff spoke with the body corporate manager
shortly after the period for submissions
had closed, and the body corporate
manager stated that the other owners did not really understand the orders being
sought by the
applicant, and would leave the decision up to the adjudicator.
The body corporate manager also stated that the applicant is the
only one of the
owners who attends body corporate meetings.
The by-laws for this scheme
are contained in the community management statement recorded at the time of
registration of the scheme,
on 3 September 2002. By-law 12 provides that each
lot has an exclusive use area allocated to it, and that each owner is
responsible
for the maintenance and operating costs for that exclusive use
area.
The applicant believes that the fence, which he is seeking to have
constructed around the excavated area, is an improvement to common
property and
not maintenance, so that it should fall within the body corporate’s
responsibility for payment. The applicant
is correct in identifying the fence
as an improvement to the common property, however, as the applicant is the only
person who has
the use and enjoyment of the area (hence the exclusive use
by-law), then he must bear the cost of any fence which he wishes to construct.
In addition, prior to undertaking the construction, he must seek body corporate
approval (section 114 of the Standard Module) by way of a special
resolution at a general meeting, unless the fence falls within the category of a
minor
improvement and meets the other criteria in section 114(2). I do
not propose to make the order sought by the applicant in respect of this
area.
I have a different view in relation to the soil subsidence,
however. The storm water and water pipes form part of the utility
infrastructure,
for which the body corporate is responsible, unless the
exceptions in section 20(1) of the Act apply, which they do not in this
instance. The applicant’s right to the use and enjoyment of the area does
not,
in my view, extend his obligation for maintenance and operating costs to
include such issues. If the developer has failed to properly
fill and compact
the area where the pipes have been laid, and subsidence has occurred, then the
body corporate should remedy the
problem. It is then a matter for the body
corporate to determine if it will, in turn pursue the developer. I have ordered
accordingly.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2003/1.html