![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
P J HANLYREFERENCE: 0554-2000
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 10 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY
MANAGEMENT ACT 1997
| Number of Scheme: | 20213 |
| Name of Scheme: | Chermside Villas |
| Address of Scheme: | PO Box 466 TOOWONG QLD 4066 |
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Kimwood Pty Ltd, the owner of lot 32
I hereby order that the
application for an order that the body corporate accept responsibility for
repairs of structural problems to the building
of villa 32/2 Nye Street,
Chermside, and cover for water damage, is
dismissed.
STATEMENT OF ADJUDICATOR’S REASONS FOR
DECISION - REF 0554-2000
“Chermside Villas” CTS
20213
The applicant, Kimwood Pty Ltd, the owner of lot 32, has sought the
following order of an adjudicator under the Body Corporate and Community
Management Act 1997 (the Act), quote –
That the body corporate accept responsibility for repairs of structural
problems to the building of villa 32/2 Nye Street, Chermside
and also cover for
water damage.
Section 223(1) of the Act provides that an adjudicator
may make an order that is just and equitable in the circumstances (including
a
declaratory order) to resolve a dispute, in the context of a community titles
scheme, about –
a) a claimed or anticipated contravention of the Act or the community management statement; orb) the exercise of rights or powers, or the performance of duties, under this Act or the community management statement; or
c) a claimed or anticipated contravention of the terms, or the termination of, or the exercise of rights or powers under the terms of, or the performance of duties under the terms of an engagement contract or an authorisation contract.
An order may require a person to act, or prohibit a
person from acting, in a way stated in the order (section 223(2)). An
adjudicator’s order may contain ancillary or consequential provisions the
adjudicator considers necessary or appropriate
(section
230(1)).
In the supporting grounds, the applicant states that a
ruling is sought from this office as it is believed that the body corporate
should be responsible for the damage under sections 128 and 129 of the Act. The
applicant has attached a structural engineer’s
report dated 1 September
2000, and various photographs of the damaged brick pier supporting the
roof.
The body corporate committee and the body corporate manager were
invited to respond to the application. On 7 February 2001 the body
corporate
manager advised that, as an adjudicator had already dismissed a similar
application to the present application, the committee
did not intend to lodge a
submission in this matter, but would, instead, just await the
adjudicator’s order.
2nI note the conclusions expressed in the
structural engineer’s report, and in particular his view that
“the core of the pier is not
filled by grout as shown on structural plans and as is required by the good
building practice.
This reduces substantially the ability of the pier to resist
the lateral load” and “(w)e believe that construction of
footing on deep fill together with reactive clays is a principal cause of
footing failure.” The engineer also expressed the view that a change
in moisture content is also a main factor that affects ground (and foundation)
movement. The engineer observed that part of the site adjacent to the damaged
pier is not well drained and is water logged from
time to time.
The
scheme registered as a group titles plan (now a standard format plan) on 1
November 1991. The original developer was Capa-Laba
Pty Ltd. The body
corporate is comprised of all of the owners of lots in the scheme. The body
corporate has certain responsibilities
under the Act to maintain common property
and body corporate assets (section 114 of the Act and section 109 of the
Standard Module).
It is clear from the engineer’s report that the
problems associated with the applicants’ lot have been caused by the
failure
to fill the core of the pier with grout, as shown on the structural
plans, and by constructing the footings on deep fill with reactive
clays,
thereby allowing for settlement of the building. The engineer’s report
also identifies the poor drainage of the site
as another important factor
affecting ground and foundation movement. However, the body corporate had no
control over the construction
of the lot, and the photographs provided to me
show that the area of poor drainage is on the applicant’s lot, and not on
common
property. I am satisfied that the body corporate is not responsible for
the damage which has been caused to the applicants’
lot. I have therefore
dismissed the application.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2001/77.html