You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2011 >>
[2011] NSWSC 2
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Dargham v Kovacevic [2011] NSWSC 2 (31 January 2011)
Last Updated: 16 June 2011
|
Case Title:
|
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
22, 23, 24, 25 February, 27, 28, 29, 30 April,
28, 31 May, 1, 3, 4 June 2010
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
Before:
|
|
|
|
|
Decision:
|
1. Judgment for the first defendant against the
plaintiff. 2. The plaintiff's claim against the second defendant is
dismissed. 3. Judgment for the plaintiff against the third defendant in the
sum of $206,382.11. 4. Declare the first cross defendant on the first cross
claim is liable to indemnify the first cross claimant in respect of his
liability
in these proceedings. 5. Judgment for the third cross defendant on
the first cross claim. 6. All questions of costs are reserved pending
written submissions by the parties. Such submissions to be served by 4.00pm on
14 February
2011 with replies by 4.00 pm on 28 February 2011.
|
|
|
|
Catchwords:
|
Common law - personal injury - construction site
accident - liability for subcontractor - damages - insurance.
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
|
Parties:
|
Fadi Dargham (Plaintiff) Radovan Kovacevic (1st
Defendant/Cross Claimant (Second Cross Claim)) Nutalab Construction Pty
Limited (2nd Defendant) Sibin Djuric (3rd Defendant/Cross Claimant (First
Cross Claim)) Mechanical and Construction Insurance Pty Limited t/as Mecon
Insurance (1st Cross Defendant (First Cross Claim)/Cross Defendant (Second
Cross
Claim) Jabbour James Marroun (2nd Cross Defendant (First Cross
Claim)) Nathanael Celik (3rd Cross Defendant (First Cross Claim))
|
|
|
|
Representation
|
|
|
|
|
D.E. Baran (Plaintiff) A. Kostopoulos (1st
Defendant/Cross Claimant (Second Cross Claim)) S. Torrington (3rd
Defendant/Cross Claimant (First Cross Claim)) R. Sweet (3rd Cross Defendant
(First Cross Claim)) J.C. Sheller (1st Cross Defendant (First Cross
Claim)/Cross Defendant (Second Cross Claim)
|
|
|
|
- Solicitors:
|
Stephen Smart & Associates
(Plaintiff) Russell C. Byrnes (1st Defendant/Cross Claimant (Second Cross
Claim)) Carneys Lawyers (3rd Defendant/Cross Claimant (First Cross
Claim)) Stojanovic Solicitors (3rd Cross Defendant (First Cross
Claim)) William Roberts Lawyers (1st Cross Defendant (First Cross
Claim)/Cross Defendant (Second Cross Claim)
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
JUDGMENT
Introduction
- On
4 July 2005 the plaintiff, then aged 24, sustained personal injury when, whilst
working on a construction site at Strathfield,
NSW, he fell down an unguarded
stairwell void.
- The
plaintiff, in his statement of claim filed on 2 July 2008, asserted he had been
working as a subcontractor on the site and sought
damages for his injuries from
the defendants who were, respectively:
(a) the first defendant -
Radovan Kovacevic, who was sued as the builder/head contractor;
(b) the second defendant - Nutalab Construction Pty Limited, the first
defendant's company, which was sued in the alternative as the
head contractor.
This company took no part in the proceedings as it was in liquidation;
(c) the third defendant - Sibin Djuric, who was sued as an owner/occupier of
the site and as principal.
- It
was alleged in the statement of claim that the first and third defendants each
owed a duty of care to the plaintiff which they
breached. No breaches of
statutory duty were relied upon.
- The
first and third defendants denied liability to the plaintiff. The third
defendant, but not the first defendant, alleged the plaintiff's
injuries were
caused or contributed to by his own negligence.
- The
third defendant cross claimed against three cross defendants, namely:
(a) the first cross defendant - Mechanical and Construction
Insurance Pty Limited ("Mecon"). Indemnity was sought from Mecon under
a
Contract Works Policy. It denied liability to indemnify under the policy;
(b) the second cross defendant - Jabbour Marroun. He was sued in contract
and/or negligence as a subcontract carpenter engaged by
the third defendant to
do certain work on the site. The third defendant did not prosecute the cross
claim against Mr Marroun as he
was bankrupt. The third defendant filed a notice
of discontinuance in respect of the cross claim against Mr Marroun on 4 October
2010;
(c) the third cross defendant - Nathanael Celik. Mr Celik was a subcontract
carpenter engaged by Mr Marroun to work on the site. It
was alleged he
negligently exercised a supervisory role. The third defendant sought indemnity
or contribution from the third cross
defendant in the event he was found liable
to the plaintiff. The third cross defendant denied liability to the third
defendant.
- The
first defendant cross claimed against Mecon seeking indemnity under the Contract
Works Policy. Mecon denied liability to indemnify
the first defendant.
- The
third defendant did not cross claim against the first defendant nor did the
first defendant cross claim against the third defendant.
- There
was no agreement as to the damages which the plaintiff would be entitled to
recover in the event he established liability.
- It
was common ground the plaintiff was entitled to and did receive workers'
compensation payments from Mr Marroun in respect of the
subject injury - see
Workplace Injury Management and Workers Compensation Act 1998 (WIM), Sch
1 cl 2.
Background
- The
construction site was owned by the third defendant with others. Five two-storey
townhouses were being built upon the site. The
site was fenced and entry to it
was by a padlocked gate in the fence, the key to which was held by the third
defendant.
- The
plaintiff had been engaged as a subcontract labourer by Mr Marroun from about
February 2005. Mr Marroun had contracted with the
third defendant to erect the
timber framework and roofing timbers for the townhouses. In June 2005 the
plaintiff commenced to work
on the site as part of a team of subcontractors
engaged by Mr Marroun (the "Pearl Design team"). The members of the team were Mr
Celik, two carpenters, two apprentice carpenters (who were directly employed by
Mr Marroun) and one labourer (the plaintiff).
- At
the time of injury the framework for the townhouses had been erected and roofing
timbers were being put in place. The plaintiff
was working in townhouse No. 1.
The particleboard floor of the second storey of townhouse No. 1 was in place but
there was a void
in the floor where the stairway was to be completed. The size
of the opening of the void was variously estimated from 4 metres x
4 metres to 2
metres x 2 metres. The opening of the void had been partially covered by a piece
of plywood and a plank. The extent
of the cover was variously estimated at 20
percent of the total void to one-third. There was no fence around the void to
prevent
a person from falling in. On the day of injury the plaintiff and other
members of the Pearl Design team were required to work in
the vicinity of the
void. No work was being done on the void at the time of injury but the concrete
steps were in place in the void
and they were from time to time used for access
between the first and second floors.
- The
plaintiff commenced work at about 7.00 am on the day of injury. He fell into the
void at about 7.30 am, falling between 2.5 metres
and 4.1 metres. He landed in a
sitting position on the corner of a concrete step.
- The
plaintiff was conveyed by ambulance from the accident site to Westmead Hospital
where he was treated and allowed to leave after
a few hours.
- The
above facts are either common ground or are not the subject of any real dispute.
I accept them.
The circumstances of injury
- The
plaintiff gave evidence that on the morning of his injury he was required to
pass 6 x 2 wooden rafters weighing approximately
40 kilos to another worker in
the vicinity of the void. He was required to do that work standing on the
exposed floor of the second
level of the townhouse, which floor was moist with
morning dew.
- He
said in his evidence-in-chief:
" At 7 o'clock in the morning I
arrived to work. We prepared all the tools, prepared everything that was going
to go get everything
ready, and we got the power saws out and the nail guns and
everything and we started cutting getting the rafters, which are timbers
that
run across to hold the roof tiles up, and I cut the first piece of timber and as
I was on my way to pass it to Mr Celik I lost
control, I slipped with my right
foot where I lost control and had to step on a piece [of] plywood that was
covering the void which
was the stairwell which gave way and where I fell down."
- The
plaintiff said later in his evidence:
"Q. When your foot slipped
and you came into contact with the area where the void was otherwise situated,
did your did your foot come
into contact with the part of the covered void which
is where the plank is or on the other part?
A. The part of where the plank was covering.
Q. Where the plank was covering?
A. Yes.
Q. Are you able to say what happened to that plank as you came into contact
with the plywood covering the void?
A. To what I remember it just gave way. It slipped, gave way and I just found
myself on the stairs with a lot of pain.
Q. Can you describe what actually physically happened to the plywood as you
went down?
A. I'm not a hundred per cent sure if it snapped, slipped, I just remember
falling."
- No
witness gave evidence of seeing the plaintiff fall though there was ample
evidence of him laying injured at the bottom of the void.
- The
plaintiff's version of the accident was challenged in cross examination, to my
mind, unsuccessfully. I accept the injury occurred
generally in the manner
stated by the plaintiff in his evidence.
Liability
- The
initial issue is whether the circumstances of injury attract liability to any of
the parties. This issue is to be determined in
circumstances where the evidence
is frequently conflicting, the credibility of a number of witnesses,
particularly the first and
third defendants, who were admitted liars, is
dubious, and recollection of events is often poor.
The liability
of the first defendant
- The
first defendant is, by trade, a bricklayer/builder. He has worked as such for
many years. He was a director of the second defendant.
The second defendant was
sued in the alternative. Apart from erecting its sign on the site, it appears to
have had no active role
in this matter. As the claim against it has not been
pressed, it is unnecessary to further consider its role, if any.
- A
builder's licence was held by the first defendant. He signed the building
contract with the third defendant in his own name. The
building contract was in
a standard form. It nominated the third defendant as the owner and the first
defendant as the builder. It
provided that the first defendant would have
exclusive and uninterrupted possession of and access to the site for the
performance
of the work, would complete the works shown in the drawings and
described in the specifications and that the third defendant would
pay to the
first defendant the cost of the works plus the fee payable under the contract.
That fee was five percent of the cost of
works (the cost of the works was of the
order of $800,000). The first defendant was to be reimbursed at the rate of $40
per hour
for work done by himself and his employees and subcontractors.
- Prima
facie, by reason of the contract, the first defendant was the builder and had
all the rights, liabilities and responsibilities
of that role. There was also
documentary evidence of an improvement notice issued by a Workcover inspector
alleging a breach by the
first defendant, a record of a tool box talk purported
to have been given by the first defendant on 27 March 2005 and a safe work
methods summary alleged to have been prepared and signed by the first defendant.
Consistently with this, following the injury to
the plaintiff, the first
defendant gave a statement to the Workcover investigators in which he admitted
he was the builder in charge
of the site. He pleaded guilty to charges arising
out of the injury to the plaintiff.
- However,
the first defendant gave evidence in these proceedings that though he had signed
the building contract he did not proceed
with it from the beginning. He said he
was not given possession of the site nor was he given a copy of the plans and
specifications.
He did no work on the site and visited it only on three, four or
five occasions for the purpose of obtaining money from the third
defendant. He
said the third defendant paid him $20,000 or $30,000 for nothing. He had no role
and no involvement in the job. He
initially said the third defendant had engaged
him solely to enable the third defendant to get home warranty insurance .
He later appeared to resile from that, saying that "he didn't mean it". The
allegation had not been put by the first defendant's counsel
to the third
defendant when initially cross examining him. It was later put and denied by the
third defendant though at one stage
he said he did employ the first defendant
for his licence. The first defendant said his statement to the Workcover
investigator in
relation to the injury to the plaintiff consisted essentially of
lies told for the purpose of protecting the third defendant.
- There
was some support for the first defendant's assertion that he played no active
role on the site as none of the witnesses who
had worked on the site and who
gave evidence knew the first defendant or had seen him on the site; there was
affidavit evidence that
between November 2004 and early 2007 the first defendant
had been renovating a property at Vaucluse pursuant to a building contract
dated
3 November 2004. The deponent was overseas at the time of the hearing and could
not be cross examined upon her affidavit in
which she said the first defendant
had told her "he had to also attend another building site during the same
period, the location
of which I am not aware of and as a result he was at my
site between three to four days a week during the entire time renovations
were
carried out on my property." The improvement notice previously referred to named
the third defendant as the contact and the
person upon whom the notice was
served. Although it was alleged that the first defendant was in breach, he
denied that he had seen
the notice prior to the plaintiff's injury; the first
defendant denied conducting a tool box talk, asserting that the record of the
tool box talk on 27 March 2005 had not been written by him save for the names of
Mr Djukic and Mr Bencul which were the last names
on the document. No
satisfactory explanation for this was forthcoming and Messrs Bencul and Djukic,
when called both denied ever
working on the site. The third defendant alleged
that Mr Bencul and Mr Djukic had worked on the site, but I reject this evidence
in the light of the evidence given by Messrs Bencul and Djukic. It may well be
that the additional names were added in order to meet
possible criticism from
the Workcover investigators investigating the injury to the plaintiff. The safe
work method statement was
prepared by the third defendant and signed by the
first defendant subsequent to the injury to the plaintiff. The document was
prepared
as part of the response to the Workcover investigation.
- Moreover,
the third defendant gave evidence that though he gave the first defendant a copy
of the plans and specifications, the first
defendant did not carry out physical
work on the site but would generally visit the site once or twice per week to
inspect progress
and advise the third defendant as to the works. These visits
generally occurred outside of normal site working hours when the tradesmen
were
absent. The third defendant also made telephone calls to the first defendant
seeking advice as to the works from time to time.
He did not dispute that he
paid the first defendant $20,000-30,000 which, he said, was for the services
outlined above.
- It
is apparent from the third defendant's evidence in these proceedings, if
believed, that the first defendant was not required to
perform all, or indeed
most, of the duties and functions of a building contractor. The selection and
payment of subcontractors, the
negotiating of terms of subcontract, the
coordination on site of the various trades and the day to day attendance at and
supervision
of the site were carried out by the third defendant.
- Whilst
I accept that the signed building contract did not represent the actual
arrangements between the first and third defendants,
I do not accept that the
first defendant had no role or involvement. I prefer and accept the evidence of
the third defendant as to
the first defendant's involvement. It appears to be
consistent with the first defendant having commitments elsewhere and fitting
in
the subject job around it. It explains why telephone records record some 17
calls between the third defendant and the first defendant
during the building
work and why the third defendant contacted the first defendant and he attended
on the day or the day following
the injury. It is consistent with the receipt
for the payment of money which referred to the provision of advice. It explains
why
the first defendant was not seen on the site by the tradesmen who gave
evidence and why the third defendant would pay $20-30,000
to him. It would be
sensible to have a qualified person checking that the job was being done
properly particularly where the principal
lacked the appropriate expertise and
the townhouses were to be occupied by the third defendant, family members and
friends.
- In
my opinion, the first defendant was, in fact, engaged for the limited role of
ensuring, as far as reasonably practicable, that
the townhouses were constructed
in a proper and workmanlike manner.
- In
my opinion, whether the building contract was wholly abandoned as the first
defendant submits or was varied as the third defendant
submits does not matter.
In either event, the first defendant owed no duty to the plaintiff. This is
because there was no evidence
or no acceptable evidence that the first
defendant:
(a) hired any employees or subcontractors;
(b) took possession of the construction site;
(c) controlled or managed the construction site;
(d) was the entrepreneur or the occupier of the site;
(e) was required to give advice as to site safety to the third defendant;
(f) gave any advice to the third defendant as to site safety;
(g) was responsible for day to day directions to subcontractors;
(h) had any dealings with the tradesmen on site;
(i) was aware or ought to have been aware that the void was not fenced;
(j) knew or ought to have known that the void had been partially covered
and/or that the cover was inadequate;
(k) was relied upon for advice by the tradesmen on site.
- Accordingly,
there will be judgment for the first defendant on the plaintiff's claim.
The liability of the third defendant
- The
third defendant was an aircraft mechanic. He had no qualifications as a builder
though he had been previously involved in a development
project. He, together
with others, was the owner and occupier of the site.
- The
third defendant's evidence initially was that he would attend the site when not
working as an mechanic and open and close the
gates. He would check people
coming onto the site and would engage contractors to work on the site. He had no
other involvement and,
in particular, did no building work himself.
- The
third defendant, later in his evidence, explained that he selected the
contractors with the advice of the first defendant, but
conducted all of the
financial dealings with them as the first defendant had a gambling problem (the
first defendant agreed he was
a gambler). Acting on the advice of the first
defendant, he would give directions, if necessary, to the subcontractors about
the
job and on one occasion had required the timber in the bathroom to be
removed and replaced as it was inappropriate. He conceded he
did safety checks
of the site most days and that when required by Mr Marroun to provide additional
scaffolding he arranged for this
to be done by a firm of scaffolding
subcontractors.
- There
was evidence from members of the Pearl Design team that during the period they
were on site the third defendant was there every
day, though not necessarily for
the whole of the day, would confer with Messrs Marroun and Celik and
occasionally issue instructions
to other members of the team. None of the
witnesses observed the third defendant do any physical work on the site. He
admitted in
his insurance claim form that he was partly to blame for the
plaintiff's injury but he did not say why he reached this conclusion.
- The
duty of care owed by a principal to an independent contractor was reviewed by
the High Court in Leighton Contractors Pty Limited v Fox [2009] HCA 35;
(2009) 83 ALJR 1086. There the High Court held (at [48]) that the relationship
between principal and independent contractor was not one which, of itself,
gave
rise to a common law duty of care much less to the special duties resting on an
employer to ensure that care was taken. However,
in some circumstances a duty
will be owed by the principal to use reasonable care to ensure that a system of
work for one or more
independent contractors is safe ( Fox [20]).
- The
High Court in Fox at [20] (see also [62]) affirmed that the circumstances
in which such a duty was owed were those explained by Brennan J in Stevens v
Brodribb Sawmilling Co Pty Limited [1986] HCA 1; (1986) 160 CLR 16 at 47-48,
namely:
"An entrepreneur who organises an activity involving a risk
of injury to those engaged in it is under a duty to use reasonable care
in
organising the activity to avoid or minimise that risk, and that duty is imposed
whether or not the entrepreneur is under a further
duty of care to servants
employed by him to carry out that activity. The entrepreneur's duty arises
simply because he is creating
the risk and his duty is more limited than the
duty owed by an employer to an employee. The duty to use reasonable care in
organising
an activity does not import a duty to avoid any risk of injury; it
imports a duty to use reasonable care to avoid unnecessary risks
of injury and
to minimise other risks of injury. It does not import a duty to retain control
of working systems if it is reasonable
to engage the services of independent
contractors who are competent themselves to control their system of work without
supervision
by the entrepreneur. The circumstances may make it necessary for the
entrepreneur to retain and exercise a supervisory power or to
prescribe the
respective areas of responsibility of independent contractors if confusion about
those areas involves a risk of injury.
But once the activity has been organised
and its operation is in the hands of independent contractors, liability for
negligence by
them within the area of their responsibility is not borne
vicariously by the entrepreneur. If there is no failure to take reasonable
care
in the employment of independent contractors competent to control their own
systems of work, or in not retaining a supervisory
power or in leaving undefined
the contractors' respective areas of responsibility, the entrepreneur is not
liable for damage caused
merely by a negligent failure of an independent
contractor to adopt or follow a safe system of work either within his area of
responsibility
or in an area of shared responsibility."
- In
addition to the duty owed as principal to an independent contractor, the
principal, if the occupier of the construction site, also
owes a duty, as
occupier, to persons coming on to the site to use reasonable care to avoid
physical injury to them ( Fox at [48]).
- A
principal may also, under the general law, be vicariously liable to an
independent contractor for injury negligently inflicted by
the principal's
employees or for the tortious acts of independent contractors who the principal
has directly authorised.
- The
third defendant, in my opinion, was an entrepreneur who organised an activity
which created a risk. The circumstances, it would
seem from the evidence,
involved some uncertainty as to whose duty it was to guard against any danger
created by the existence of
the stairwell void. Accordingly, in accordance with
the principles in Fox , the circumstances made it necessary for the
entrepreneur to retain and exercise the supervisory power or to prescribe the
respective
areas of responsibility of independent contractors.
- Four
matters combined to cause injury to the plaintiff, namely:
(a) the
existence of the void;
(b) the inability of the partial cover to withstand the weight of the
plaintiff and his load;
(c) the dewy nature of the flooring which caused him to lose his footing;
(d) the absence of a fence to prevent entry to the void.
- The
third defendant was aware of the presence of the void, as was Mr Celic. Mr Celik
gave evidence that he asked the third defendant
to cover the void and the third
defendant said he would do so. The plaintiff sought to corroborate this
evidence. He said he was
present within earshot when the conversation took
place.
- The
third defendant denies any such conversation took place. His evidence initially
was that Mr Celik had agreed to cover the void
but later he said "Mr Marroun
told me Celik will put on the cover, but Celik didn't tell me he will do this."
Mr Marroun denied this
conversation.
- The
plaintiff and Mr Celik gave evidence the third defendant placed the partial
cover over the void but neither observed this occur.
It was merely an
assumption.
- The
third defendant denied he placed the partial cover over the void. He asserted Mr
Celik had done so but he had not observed this
occur. He said he looked at the
cover when it was in place but did not make any decision as to its adequacy for
the safety of workers
on the site as Mr Marroun told him it would be good
enough. This conversation was denied by Mr Marroun.
- I
am unable to determine who agreed to construct the cover, who did construct it
and whether any express assurances as to its adequacy
were given. I did not find
the evidence of any of the relevant witnesses satisfactory and I am unable to
determine where, on balance,
the truth lies. I have borne in mind that the third
defendant is not a carpenter or scaffolder, there was evidence he had done no
physical work on the site and there were no other contractors on the site. It
was at least a real possibility that if the third defendant
undertook to cover
the void he would have asked the Pearl Design team to perform the task.
- Both
Mr Celic and the third defendant were aware prior to the plaintiff's fall that
the partial cover was in position. Mr Zouein,
a subcontract carpenter engaged by
Mr Marroun to work on the site, gave evidence he told Mr Celic the cover was
"not right" and there
should be a handrail. He said the third defendant was
there at the time and he said to the third defendant that "this didn't look
right and someone is going to get hurt sooner or later, being me or someone
else, anyone." He said he couldn't tell whether the third
defendant said
anything in response. This evidence was somewhat uncertain, particularly that
part of it which concerned the third
defendant. Mr Zouein said he thought the
third defendant was present but then proceeded to give evidence of a definite
conversation
with the third defendant though he said he had no recollection of
any response by the third defendant. In cross examination he conceded
that when
asked by a work inspector whether he had any concerns about the safety of the
job prior to the injury to the plaintiff
he replied "No, not really". He
conceded his memory may have misled him. I do not accept Mr Zouein's evidence as
to the conversations
with Mr Celik and the third defendant as I am not satisfied
as to the reliability of his recollection.
- The
provision of a partial cover, even if solidly affixed and capable of
withstanding the weight of a man and his load, nevertheless
left the remainder
of the void as a danger. This could be guarded against by the provision of a
fence, and reasonable care required
that this should be done. There was evidence
that the steps in the void were used to gain access to the second floor but
there was
no evidence that this would have rendered it impractical to place the
fence around the stairwell void. Such a fence was placed in
position following
the fall. I infer the void was only partially covered in order to permit the use
of the stairs as a means of access
to the second floor. Subsequent events show
that the cover either was not adequately affixed or was incapable of bearing the
necessary
weight. However, this was not apparent to the third defendant prior to
the plaintiff's fall.
- In
my opinion, the third defendant owed a duty to the plaintiff both as occupier
and pursuant to the principles in Fox . A protective fence around the
perimeter of the void would have prevented the plaintiff's injury. In my
opinion, reasonable care
required that such a fence should have been placed and
maintained in position prior to the plaintiff's injury. The third defendant,
in
my opinion, was negligent in failing to provide such a fence or ensure that it
was provided.
- There
was reference to safe work method statements and similar documents. However,
those documents only came into existence after
the plaintiff's fall and there
was no evidence of reliance upon them.
- The
third defendant submitted the risk of falling into the void was obvious and he
had no duty to warn the plaintiff of the risk -
Civil Liability Act 2002
("CLA"), s 5F-H. The plaintiff conceded he was well aware of the void and the
fact that he could fall into it. No warning of this was required.
This, however,
does not obviate the third defendant's liability to the plaintiff for the
injuries sustained in the circumstances
of this case.
- There
will be judgment for the plaintiff against the third defendant.
The liability of Mr Marroun
- Mr
Marroun was a qualified carpenter. He was licensed as such under the Home
Building Act 1989. Mr Marroun traded under the name Pearl Design and
Construction. He later incorporated the business as Pearl Design and
Construction
Pty Limited. Mr Marroun gave evidence that the incorporation
occurred after the injury to the plaintiff. He contracted with the third
defendant for the erection of the timber frame and roof timbers of the
development. He engaged a number of independent contractors
to carry out the
work he had contracted to perform. He denied he was a partner with Mr Celik or
that they shared the profits of this
job contrary to an allegation by the third
defendant that he had been told by Mr Marroun that Mr Marroun and Mr Celik were
co-owners
and partners.
- The
plaintiff did not sue Mr Marroun as he had failed to establish a permanent
impairment of at least 15 percent, which was a prerequisite
to obtaining an
award of damages against Mr Marroun (s 151H(1) Workers Compensation Act
1987). The third defendant did not pursue his cross claim against Mr Marroun
as Mr Marroun was bankrupt.
- Mr
Marroun was on the site only on limited occasions. He was not on site at the
time of the injury to the plaintiff.
- Mr
Marroun accepted he owed a duty to provide a safe system of work for those
engaged as part of the Pearl Design team. He recognised
the danger of the void.
He agreed that the void could have been adequately fenced for under $400. He
gave evidence the timber would
cost $20 and he could have constructed the fence
in five minutes though it may take an inexperienced person about one hour, in
which
event the labour costs may be in the order of $100. Mr Marroun owed a duty
of care in accordance with Fox to ensure that a safe place and system of
work was provided, and it was not. However, as Mr Marroun was not sued by the
plaintiff
and the cross claim against him by the third defendant was not
pursued, his involvement is relevant only to the application of s151Z(2).
The liability of Mr Celik
- The
third cross defendant, Mr Celik, was a qualified carpenter. He had allowed his
licence under the Home Building Act 1989 to lapse as he was working under
Mr Marroun and had the benefit of his licence. He agreed he was "the supervisor"
of the Pearl Design
team.
- He
stated that his role as supervisor of the Pearl Design team was to ensure that
the scope of works were properly carried out. He
was not responsible for the
safety of the members of the team.
- Mr
Celik recognised the existence of the danger posed by the void to people working
in the area. He gave evidence he requested the
third defendant to remove the
danger. This was not done. He warned the team to be careful when working near
the void. He did this
15 minutes before the accident occurred.
- Mr
Celik took no steps to put up a fence or to adequately cover the void as, he
said:
(a) the area would be used by other trades and the obligation
to take precautions therefore was on those responsible for the whole
site;
(b) he owed no duty of care to the members of the Pearl Design team;
(c) it would be difficult, costly and time consuming to do this work and he
had no authority to do it as it was not part of the scope
of works.
- The
crucial issue, in my opinion, is whether Mr Celik assumed responsibility for the
safety of the independent contractors engaged
by Mr Marroun. In the absence of
him accepting such a role I do not consider that he can be seen as owing the
plaintiff a relevant
duty of care.
- Mr
Celik subcontracted to Mr Marroun at an hourly rate as did the other
subcontractors in the team. The contract for the work in which
the plaintiff was
engaged when injured was between Mr Marroun and the third defendant. Mr Celik
was not a party to that contract.
He was not a principal, he did not engage or
employ the plaintiff. He was not, I find, a partner of Mr Marroun or entitled to
share
in any profit arising from the work undertaken by Mr Marroun.
- Mr
Celik gave evidence he did not undertake to be responsible for the safety of the
members of the team. This was confirmed by Mr
Marroun, who told the Workcover
investigator that Mr Celik was employed by him to supervise the work done by the
men and to ensure
that it was properly carried out. He did not undertake a
responsibility for the safety of the men engaged by Mr Marroun. Mr Marroun
confirmed this in his evidence in these proceedings. He did not give evidence
that he had delegated his duty to the plaintiff to
Mr Celik.
- It
is true Mr Celik did warn the team of the void but this was in the context of
the members of the team voluntarily warning each
other of a perceived common
danger pursuant to concern for one's fellow workers, not pursuant to a legal
duty to do so. Nor was the
making of a request by Mr Celik to the third
defendant (if such was made) other than as a reminder to the third defendant to
perform
a duty which Mr Celik contended the third defendant owed to all persons
on the site.
- In
my opinion, Mr Celik did not owe a duty of care to the plaintiff.
- If
I am in error in that conclusion, it would occasion no different result. If Mr
Celik was liable to a member of the Pearl Design
team, it would be because
performance of the duty owed by Mr Marroun to the team member had been delegated
to Mr Celik.
- The
only claim against Mr Celik is that brought by the third defendant for
contribution. No contribution would be recoverable from
Mr Celik by the third
defendant by reason of the application of s151Z(2) which would operate to limit
the entitlement of the third
defendant to the deduction in the verdict resulting
from the operation of the section.
Contributory negligence
- The
third defendant alleged that any injury suffered by the plaintiff was caused or
contributed to by the negligence of the plaintiff,
which it particularised as
follows:
"(a) Failing to keep a proper lookout.
(b) Failing to comply with reasonable directions by Jabbour Marroun or in the
alternate by Nathan Celic.
(c) The Plaintiff failed to comply with the Site Management Plan advised to
him by Mr Marroun and/or Mr Celic.
(d) The Plaintiff failed to comply with the Safe Work Method Statement issued
to him by Mr Marroun.
(e) The Plaintiff failed to comply with a direction that workers not walk
across stair voids where materials were being hoisted over
beams placed across
the void.
(f) Despite being directed by Mr Marroun and Mr Celic to walk around the
void, walking across the hoisting beam.
(g) Stepping on sheets of timber which a reasonable person should know would
not support him.
(h) Walking in and being in an area despite being instructed by Mr Celic not
to walk in that area.
(i) Failing to dry water from the area he was working around."
- Counsel
for the third defendant submitted that, if the plaintiff succeeded against his
client, an apportionment for contributory negligence
in the order of 75 percent
was appropriate.
- The
plaintiff conceded he had a responsibility, as a subcontractor, to take care for
his own safety. He conceded that he knew the
void was there, as he had seen it
uncovered approximately four days before injury and subsequently partly covered
on the day of the
injury. He knew that it posed a danger of injury if he fell
into it, knew that he had to be wary of the danger and had been so warned
some
15 minutes before the accident.
- However,
the plaintiff's injury was not caused by a deliberate voluntary act on his part
of stepping onto the cover but by his involuntary
reaction resulting from
slipping on the floor. There is also an absence of proof of the factual
underpinning of a number of the particulars,
eg it was not established that a
reasonable person would know the cover would not support him, that the plaintiff
could effectively
dry the dew from the floor area and so on. The onus of
establishing contributory negligence lies with the third defendant. In my
opinion, that onus has not been discharged. There will be no deduction for
contributory negligence.
Section 151Z(2) of the Workers
Compensation Act 1987
- Section
151Z(2) of the Workers Compensation Act 1987 provides relevantly:
(2) If, in respect of an injury to a worker for which compensation
is payable under this Act:
(a) the worker takes or is entitled to take proceedings independently of this
Act to recover damages from a person other than the
worker's employer, and
(b) the worker also takes or is entitled to take proceedings independently of
this Act to recover damages from that employer,
the following provisions have effect:
(c) the damages that may be recovered from the person by the worker in
proceedings referred to in paragraph (a) are to be reduced
by the amount by
which the contribution which the person would (but for this Part) be entitled to
recover from the employer as a
joint tortfeasor or otherwise exceeds the amount
of the contribution recoverable,
(d) the amount of the contribution that the person is entitled to recover
from the employer as a joint tortfeasor or otherwise is
to be determined as if
the whole of the damages were assessed in accordance with provisions of Division
3 as to the award of damages..."
- (a)
The third defendant and Mr Marroun were in breach of the duty of care owed by
each to the plaintiff;
(b) the injuries sustained by the plaintiff
in the fall did not result in a degree of permanent impairment of the plaintiff
that was
at least 15%;
(c) accordingly no damages could be awarded against
Mr Marroun - s151H of the Workers Compensation Act 1987 ;
(d) the
amount of contribution that the third defendant was entitled to recover from Mr
Marroun as a joint tortfeasor pursuant to
s151Z(2)(d) was to be determined at
nil;
(e) the damages recoverable by the plaintiff from the third defendant
were to be reduced by:
"...the amount by which the contribution which the person would (but for this
part) be entitled to recover from the employer as a
joint tortfeasor."
- The
apportionment of damages between joint tortfeasors involves:
"...a
comparison both of culpability, that is, of the degree of departure from the
standard of care of the reasonable man, and of
the relative importance of the
acts of the parties in causing the damage ... it is the whole conduct of each
negligent party in relation
to the circumstances of the accident which must be
subject to comparative examination." - James Hardie and Coy Pty Limited v
Roberts [1999] NSWCA 314; (1999) 47 NSWLR 425 at 446 [90]."
- In
my opinion, the comparative examination of the culpability and relevant
importance of the acts of the parties leads to the conclusion
that the amount of
contribution should be assessed at 25 percent. I have reached that conclusion as
it seems to me the void was a
potential risk to all persons coming onto the
second floor of the site and thus the principal/occupier should bear a greater
responsibility
to that of a subcontractor with responsibilities only to the
limited number of persons who were working under his control.
Damages
- The
plaintiff was born in Australia in August 1980. He obtained his School
Certificate. On leaving school he worked for Franklins
and Woolworths, each in
the fruit and vegetable department for about 18 months each. He then worked for
about a year for a spring
water supplier. He told Mr Hawkins, a vocational
psychologist qualified on his behalf, that "from 2001-2005 he described himself
as 'a young hoon'". He was on unemployment benefit and only worked occasionally
during this period in jobs such as labouring. He
had no prior accidents,
injuries or disabilities. The plaintiff claimed he had been active in a number
of sports, though he told
Dr Panjiratan that prior to this injury he was not
involved in any sport. Dr Breit recorded a history his sporting activities
ceased
when he started work.
- The
plaintiff said he did one or two short courses at TAFE but it is unclear if he
completed these. He married in 2004 and in February
2005 the first of his two
children was born. He commenced work with Mr Marroun in 2005. He said he had
intended to continue work
as he had a child to support and he proposed to obtain
trade qualifications as a carpenter.
- The
plaintiff gave evidence that he suffered extreme pain when he fell. He said that
for the first month or so after the injury he
could not bend at all. He had to
stay upright the whole time or lie on his stomach. He could not sit at all. He
was virtually on
the couch in the bedroom the whole time. His wife did
everything for him, getting him up and off the couch, assisting with going
to
the toilet, showering, getting dressed etc. He took pain medication which at
times gave relief and at other times did not. After
three months he was walking
better but still had a lot of pain in the leg, arm and neck and was still pretty
much on the couch. He
still required assistance from his wife. Gradually he was
able to do more things but a year after injury he was still, he said, in
too
much pain to resume work. Essentially he managed his own treatment using hot
baths and creams. He continues this regime to the
present time. He, on
occasions, will take Cerebrex and he continues to see his general practitioner,
Dr Hanna. The injury has had
an emotional effect on him in that, he said, it has
taken a lot out of his life.
- The
plaintiff was certified unfit for work by Dr Hanna, until 23 November 2005 when
he certified him fit for suitable duties, working
four hours per day five days
per week. Certificates to 24 March 2006 from Dr Hanna were tendered in evidence.
The certificates from
23 November 2005 to 24 March 2006 all marked the plaintiff
fit for suitable duties save for a week commencing 23 February 2006 when
he was
certified unfit due to an exacerbation. No certificates, reports or notes from
Dr Hanna later than 24 March 2006 were tendered
nor was he called to give
evidence.
- The
plaintiff did not return to work when certified fit for suitable duties by Dr
Hanna.
- In
April 2006 the workers' compensation insurer requested the plaintiff to resume
work with Mr Marroun but he refused because of Mr
Marroun's attitude toward him
since being required to pay workers compensation. Mr Marroun was not examined or
cross examined as
to this matter and I accept there was an unsatisfactory
relationship between them at that time. The plaintiff said he looked for
light
work in this period but was unsuccessful. In September 2007 the plaintiff
commenced to work two to three days per week doing
light work for Mr Celik. This
lasted for six to eight months. He said he was paid $300 per week. After ceasing
work with Mr Celik
the plaintiff did not seek any employment. He did not take
any courses. In February 2009 he commenced a business as a handyman with
another
man. The latter does the heavier work. He receives $200-300 net per week from
this work. The business is expanding. He has
noticed improvement in his physical
ability. He considers there are many jobs he could do, his restriction being
only on heavy lifting.
- The
plaintiff gave a history to doctors that x-rays at the hospital following the
fall revealed a fracture of the coccyx. However,
the hospital x-ray report
stated: "SACRUM (lat) No retro or antero listhesis is seen at the L5/S1 level.
No obvious displaced fracture
is evident however AP is required to assess for
possible fracture." Subsequent radiological reports were as follows:
29 July 2005 - x-ray of the lumbo sacral spine:
"There is a normal lumbar lordotic curve. No muscle spasm, spondylolisthesis
or Parr's defect noted. The sacrum and sacroiliac joints
are normal."
29 July 2005 - CT scan of the lumbar spine:
"The L3 to the coccyx was scanned with scans parallel to the disc spaces.
The lumbar spine is normal with no bony injury, disc bulge or spinal
stenosis. The sacrum is normal and no obvious sacral coccygeal
fracture was
defined in the films available."
18 November 2005 - MRI scan of whole spine:
"No evidence of central canal stenosis, disc bulge/protrusion or foraminal
narrowing in cervical or thoracic spine."
29 July 2006 - CT scan of lumbar spine showed:
"The sacrum is normal and no obvious sacral or coccygeal fracture was defined
in the films available.
31 July 2008 - MRI scan of cervical spine:
"All the cervical intervertebral discs are of normal size and appearance and
of normal signal intensity and there is no evidence of
any cervical disc bulge
or protrusion. There is a small central disc bulge at the T2/3 level and this
indents the anterior margin
of the thecal sac and reaches back to the spinal
cord just to the left of the midline. It does not cause any significant
compression
of the spinal cord. No other abnormalities are demonstrated in the
MRI of the cervical spine. The cervical spinal cord has been visualised
between
the craniocervical junction and T5 and shows no abnormality.
Comment: Small T2/3 disc bulge."
31 July 2008 - MRI scan of lumbar spine:
"There is no evidence of any disc degeneration and disc bulging or disc
protrusion. Normal MRI scan of the lumbar spine."
- The
plaintiff relied particularly upon the reports of Dr Ellis, an orthopaedic
surgeon, and Dr Teoh, a psychiatrist. These doctors
were qualified on behalf of
the plaintiff. Dr Ellis in his latest report dated 18 August 2008 concluded the
plaintiff sustained musculo
ligamentous contusion, aggravation of degenerative
changes in his back and neck with referred pain and deficit in the left lower
limb. Consequent upon the neck injury there were secondary effects in his left
upper limb with referred pain and neurological deficit.
Dr Ellis considered the
plaintiff was unable to return to work though there had been improvements since
the last assessment in February
2006. Dr Ellis considered there was no evidence
of psychosomatic illness and rehabilitation assistance and assessment should be
provided
in an attempt to retrain the plaintiff in alternative lighter work as
it was unlikely he would return to his previous employment
as a builder's
labourer.
- Dr
Teoh, in his report dated 27 October 2008, concluded that the plaintiff's
presentation was consistent with the diagnosis of an
adjustment disorder with
depressed mood. He considered the psychiatric condition was caused by the
plaintiff's chronic pain and physical
disability and that he could benefit from
pain management and counselling.
- The
defendants relied particularly upon a report of Dr Bodel dated 3 August 2009. Dr
Bodel, an orthopaedic specialist, concluded that
an x-ray of the sacrum
available to him indicated there was no obvious fracture in that region. He
considered the plaintiff had suffered
a soft tissue injury to the
sacro-coccygeal region and the lumbo-sacral region and a soft tissue injury to
the neck. He concluded
the plaintiff should have quite a good prognosis for
these injuries. He was at a loss to understand the level of ongoing complaint
at
this stage four years after injury. He considered that the plaintiff would have
some ongoing intermittent symptoms in the neck
and the back but should be
capable of a wide range of physical activities on the basis of his current
complaints and that he should
be capable of his pre-injury style of work. He
considered the plaintiff's motivation for a return to work must be somewhat
questionable
as he had no clinical sign of major physical impediment which would
prevent him from a graded reintroduction to appropriately modified
work. Over a
three to four month period, he should be able to upgrade to his pre-injury level
of work. He noted that the difference
between the report of Dr Ellis and his
assessment was that Dr Ellis found clinical evidence of nerve root involvement
or radiculopathy
in either arm or either leg and Dr Bodel could find no such
evidence on clinical testing.
- Dr
Bodel's opinion was consistent with that of Dr Panjiratan who, in his report of
25 January 2006, reported:
"Mr Dargham has an unusual pain
response. He is very stiff all over and walks awkwardly. It appears as if the
injury occurred only
last week. I cannot explain this...The recovery time has
exceeded expected time frames but the worker is still not capable of returning
to work...He should have recovered within a few weeks of the fracture."
(I
note Dr Panjiratan did not have x-rays or radiological reports before him at
examination and accepted the plaintiff's history of
a fracture.)
- I
prefer the opinion of Dr Bodel which appears more consistent with the
radiological picture which provides no evidence of a fracture
or pre-existing
degenerative changes. I note the psychological condition commented upon by Mr
Teoh is dependent upon the plaintiff's
physical condition.
- In
the course of the hearing some evidence was provisionally admitted subject to
submissions as to admissibility being made in final
addresses. Most of these
matters resolved themselves during the hearing and were not the subject of
specific submissions in addresses.
One matter provisionally admitted was a
medical certificate and report by Dr Breit dated 14 September 2006 issued
pursuant to an
assessment under Pt7 of WIM. These documents were tendered by
counsel for the third defendant and objected to by the plaintiff's
counsel, the
primary objection being "that effectively it's not an expert's report where the
code of conduct is adopted". Counsel
for the third defendant submitted the code
of conduct was inapplicable as the certificate and report were outside the
provisions
of UCPR 31.18 and 31.23. However, in his final address counsel for
the plaintiff did not refer to this issue but instead relied upon
the assessment
contained therein as "not an insignificant whole person impairment", such that
the Court could not dismiss him as
a man not injured. In these circumstances,
and as I would have determined the "primary objection" in favour of the third
defendant,
I have treated the certificate and report as admitted into evidence.
I note also that two matters the subject of provisional admission,
namely what
would the first defendant have done if responsible for safety on the site, was
admissible against the first defendant
only but, in the light of my findings, it
now has no relevance, and the third defendant's evidence that he was not
licensed to do
building work was admissible.
- Dr
Breit, on 14 September 2006, reported radiology reports do not confirm a
fracture, there was no evidence of a radiculopathy, that
the stiff manner in
which he held his spine was inconsistent with the physical examination but he
had scalene muscle tenderness and
tightness which was not something that one can
feign. Despite his complaints of extraordinary levels of back pain he does have
an
asymmetrical loss of movement and therefore an assessment of both areas for
impairment is appropriate.
- Reports
of a physiotherapist from the Vocational Capacity Centre dated August 2009
concluded:
"Results of this assessment indicate that Mr Dargham is
physically capable of sedentary, semi-sedentary and light manual work tasks.
He
did not demonstrate the capability to perform his pre-injury occupation as a
builders labourer."
Apparently the plaintiff gave a history he had not worked since the injury.
The report also indicated the plaintiff's maximum capability
level may not have
been adequately observed on certain tests. I do not attach any significant
weight to this report or other reports
of this nature.
- Plaintiff's
counsel prepared a schedule in which he outlined the claims which were pressed
on behalf of the plaintiff. The schedule
and the response of the first and third
defendants is set out hereunder in tabular form.
|
Plaintiff
|
|
1st Defendant
|
3rd Defendant
|
|
Non Economic Loss
- 40% of most extreme case
|
$189,400.00
|
30% most extreme case -$142,050.00
|
$40,000.00
|
|
Past Economic Loss - Taking the average of the pre-accident earnings
$713.00 per week x 5 years thus $185,380 less 1 year of earnings
@$300.00 per
week to take into account the business presently conducted by the plaintiff and
the earnings from working with Mr Celik
which equates to $15,600.00 thus =
|
$169,780.00
|
$30,000.00
|
$32,088.00
|
|
Future Economic Loss - Taking the average between the weekly figure for the
past of $713.00 per week and an average of the likely
figures for the future
which is $963.00 @ 100% of $838.00 per week less an ongoing residual earning
capacity of $300.00 per week,
therefore an ongoing loss of $538.00 per week for
10 years less 15% thus =
|
$188,819.00
|
$100 per week for the next 10 years (less 15% vicissitudes), but say with
adjustments -$50,000.00
|
Future economic buffer
$25,000.00
|
|
Past and Future Lost Superannuation Contributions
No claim made as subcontractor
|
$0.00
|
Nil
|
|
|
Past Gratuitous Domestic Assistance
For the first 26 weeks @ 3 hours per day, 7 days per week @ $20.00 per hour
=
|
$10,920.00
|
|
|
|
Thereafter 1 hour per day @ $23.00 per hour, 7 days per week x 234 weeks
=
|
$37,674.00
|
$10,000.00
|
Nil
|
|
Future Gratuitous Domestic Assistance - @ 1 hour per day x 7 days per week
for the next 10 years @ $23.00 per hour which equates to
$161.00 per week x
multiplier 412.9
|
$66,476.00
|
$5,000.00
|
|
|
Future Treatment Counselling, General Practitioner consultations,
Orthopaedic Specialist reviews, creams and medication =
|
$25,000.00
|
$5,000.00
|
Pharmacy & analgesics - $5,000.00 Rehab & pain management
$10,000.00
|
|
Fox v Wood
|
$730.000
|
$730.00
|
|
|
Past Out of Pocket Expenses
|
$7,366.14
|
$7,366.14
|
|
- I
assess damages as follows.
Non economic loss
- In
my opinion, the plaintiff, as a result of the fall, suffered soft tissue
injuries to the sacro-coccygeal, lumbo sacral and neck
regions. These injuries
occasioned him significant pain and marked disability for about three months.
The pain and disability gradually
decreased thereafter and by 23 November 2005
he was fit to resume limited part time work though he continued to have some
ongoing
symptoms, the effect of which was exacerbated, to some degree, by an
adjustment disorder and depressed mood. The plaintiff has no
clinical findings
of major physical impediment and, in the opinion of Dr Bodel in August 2009,
would have been able to upgrade to
his pre-injury level of work after three or
four months of a gradual return to work.
- In
my opinion, the effects of the injury had largely subsided by December 2009 and
no future problems resulting from the injury are
to be anticipated though the
plaintiff may have some intermittent low level pain for some time to come.
- The
maximum amount of damages that may be awarded for non economic loss (s 16 of the
CLA) is $500,500. In my opinion, the appropriate assessment for non economic
loss is 30 percent. The award on this head of
damages is accordingly $115,000.
Past economic loss
- There
was evidence from Mr Marroun and Mr Celic that the plaintiff was a competent
labourer. He was being paid $25 per hour gross
at the time of injury. He
normally worked a 40 hour week. He did not dispute that for the period he was
working for Mr Marroun his
gross salary was a little over $12,000, from which he
claimed expenses of $5000, leaving him with a net figure before tax of $7000,
or
about $400 per week.
- The
plaintiff's employment record for the four years prior to being engaged by Mr
Marroun was unimpressive. I accept the plaintiff's
attitude towards work may
have changed as a result of the birth of his first child. However, it is likely
that his employment with
Mr Marroun may have come to an end by the time of Mr
Marroun bankruptcy and the plaintiff may have encountered some difficulty
obtaining
employment at the same level of remuneration. There is also the
possibility that he may have had an increase in salary at some time
during that
period. In my opinion, it would be reasonable to calculate the past economic
loss until 2 April 2008 on the basis that,
but for injury, the plaintiff would
have averaged earnings after expenses of $600 net per week and thereafter $700
net.
- I
would assess the plaintiff's damages for past economic loss as follows:
|
4 July 2005 - 23 November 2005: Plaintiff totally incapacitated for
work. $600 net per week for 20 weeks =
|
$12,000
|
|
24 November 2005 - 24 March 2006: The plaintiff was certified fit to
work four hours per day, five days per week with lifting limited to four
kilograms, sitting to
half an hour and no frequent bending. The plaintiff did
not work during this period. In my opinion, the restrictions on the plaintiff's
work capacity were such that it was improbable he could obtain any employment
and for present purposes his loss should be calculated
at $600 net per week,
ie
|
$10,800
|
|
25 March 2006 - 1 September 2007: The plaintiff had a capacity for
suitable light work during this period but refused employment with Mr Marroun
which was offered to
him and did not obtain other employment. The refusal to
work for Mr Marroun appears to have had a basis in the relationship between
the
two men. I would allow the plaintiff loss of wages for this period of $600 net
per week as his fitness for work was still quite
limited, ie
|
$45,000
|
2 September 2007 - 1 April 2008: The plaintiff was employed in light
duties by Mr Celik at $300 net per week approximately. I allow a loss of $300
net per week for
the period, ie
|
$9,000
|
|
2 April 2008 - 1 February 2009 The plaintiff ceased working with Mr Celik.
He did not look for work or attend any courses. The plaintiff
had a capacity to
work which I assess, if exercised, would have earned him approximately $500 net
per week. I assess his earnings
but for injury would by this time have risen to,
say, $700 net per week. However, he lacked formal job qualifications and may not
have been able to fall back upon heavy work which might otherwise have been
available to him. I assess his loss at $300 net per week
for this period,
ie
|
$13,200
|
|
2 February 2009 - 31 December 2009: The plaintiff commenced his
handyman business earning approximately $300 net per week. During this period he
had a higher earning
capacity than $300 net per week but it is reasonable to
allow him actual loss as it was necessary to take time to establish the
business.
The plaintiff stated that he preferred to open his own business rather
than seeking employment elsewhere. I allow the plaintiff a
loss of $400 net per
week for this period, ie
|
$19,200
|
|
1 January 2010 to 31 January 2011 I find the plaintiff's capacity to
earn in his handyman business or in other suitable employment is $600 net per
week. I allow a loss
of $100 net per week for the period, ie approximately
|
$5,600:
|
- For
past economic loss, I allow the sum of $114,800
Future economic
loss
- In
my opinion, the plaintiff is now virtually able to do all forms of work which he
would have been able to do had he not sustained
the subject injury. I allow a
small buffer against the possibility some minor intermittent limitation may
still exist. For this I
allow $25,000.
Past gratuitous care
- The
plaintiff and his wife gave evidence as to assistance provided to the plaintiff
by his wife as a result of the injury. They gave
evidence that the plaintiff
required a high level of assistance during the first three months. The
plaintiff's wife assessed the
time spent as being in the order of two to three
hours per day. During the period of three to six months following injury, the
amount
of care afforded was in the order of approximately one hour per day.
- The
plaintiff also asserted he had assisted around the house with jobs prior to his
injury. He said this occupied four to five hours
per week and his wife has had
to do those jobs since his injury. This assertion is contrary to the history
recorded by Dr Panjiratan
in his report dated 25 January 2006 where he recorded
"[The plaintiff] stated that his wife does everything at home and did prior
to
the injury." Dr Breit recorded a history that his wife does all the household
duties and continues to do so. The plaintiff, when
questioned as to this, said
he did not recollect if he told the doctor that but conceded it was a
possibility. It is unnecessary
to pursue this matter further as no claim is
pressed in this regard.
- Section
15 of the Act provides relevantly:
"(3) Further, no damages may be
awarded to a claimant for gratuitous attendant care services unless the services
are provided (or
to be provided):
(a) for at least 6 hours per week, and
(b) for a period of at least 6 consecutive months."
- In
Hill v Forrester [2010] NSWCA 170 the Court of Appeal held a party
"is not entitled to recover damages in respect of any period during
which the gratuitous services were not provided (or are not to
be provided) to
him for at least six hours per week."
- I
find the plaintiff required gratuitous attendant care services throughout the
six month period commencing 4 July 2005. I allow compensation,
as claimed by the
plaintiff, for past assistance at $20 per hour for three hours per day for three
months from 4 July 2005 and at
$20 per hour for the following three months at
one hour per day. This allowance totals $7280.
- The
plaintiff has claimed care at the rate of one hour per day seven days per week
from that date until a date ten years in the future.
In my opinion, after the
first six months had expired, the plaintiff's need was less than six hours per
week and has continued to
reduce until, as the plaintiff conceded in cross
examination, nowadays he does not need any help. In these circumstances, the
plaintiff's
claim after the first six months must be rejected pursuant to
s15(3)(a) of the Act.
Future treatment
- The
plaintiff at present treats himself using a cream supplied by a friend who is a
pharmacist, occasionally takes painkillers, occasionally
visits his general
practitioner, Dr Hanna. I allow for future treatment the sum of $5000.
Fox v Wood
- This
head of damage is agreed at $730.
Past out of pocket expenses
- This
head of damage is agreed at $7366.14.
- I
assess total damages as follows:
Non economic loss
$115,000.00
Past economic loss 114,800.00
Future economic loss 25,000.00
Past gratuitous care 7,280.00
Future gratuitous care Nil
Future treatment 5,000.00
Fox v Wood 730.00
Past out of pocket expenses 7366.14
$275,176.14
Less 25 percent employer's liability $206,382.11
Insurance
The policy provisions
- It
was common ground that the first and third defendants were insured under a
Contract Works Policy with Mecon.
- The
relevant insuring provisions of the policy were as follows:
"5.00
In accordance with the terms, exclusions and conditions of the Policy MECON will
provide Indemnity for all amounts which you
become legally liable to pay in
compensation of Personal Injury or Property Loss that happens within the
Territorial Limits during
the Period of Insurance as a result of an Occurrence
which arises in connection with your Business.
With MECON's prior written permission, and included within the applicable
limits of indemnity, MECON will also pay:
5.01 legal charges, expenses and costs incurred by you."
- It
was common ground that subject to the application of General Condition 10.08,
the policy would indemnify the first and third defendants
in respect of their
liability, if any, to the plaintiff.
- The
conditions relied upon by the insurer to refuse indemnity under the policy were
in the following terms:
"GENERAL CONDITIONS
10.00 Each condition reflects a reasonable requirement of you as a condition
or precedent to receiving insurance under the Policy.
If you fail to observe
these conditions, and such failure increases MECON's exposure to a claim or
directly or indirectly exacerbates
or causes loss, damage or legal liability,
MECON may reduce, or avoid paying, any claim submitted by you.
...
10.08 Risk Management
Without exception, you and your Employees must:
(a) fully comply with manufacturer's instructions
(b) fully comply with all legal requirements and relevant work place
authority regulations regarding safety, and maintenance of property,
including
but not limited to observance of the Occupational Health and Safety Act
applicable in your State, and,
(c) ensure that any safety devices (including, but not limited to, load
movement and overload indicators), where fitted or required
to be fitted, are in
place and fully operational at all times, and
(d) take all reasonable steps to prevent incurring any loss, damage or
liability."
The third defendant
- The
third defendant, on advice, had pleaded guilty in the Chief Industrial
Magistrate's Court to a prosecution for breach of s 10
of the Occupational
Health and Safety Act 2001. The breach of s 10 was particularised as
including, inter alia, breaches of reg39 of the regulations to the
Occupational Health and Safety Act . A statement of agreed facts was
tendered in those proceedings. The prosecution arose out of the injury to the
plaintiff.
- A
breach of s 10 does not give rise to a statutory cause of action for damages
(s32 Occupational Health and Safety Act ) and would not have done under
the general law. Mecon did not ultimately submit that breach of s 10 or the plea
of guilty established
a basis to refuse indemnity.
- Mecon's
primary submission was that the third defendant was not entitled to indemnity as
he had breached one or more of conditions
10.08(b), (c) or (d) of the policy.
- Mecon
also submitted that the third defendant was not entitled to indemnity pursuant
to the policy as he had breached cl 10.08(b)
and/or (d) of the policy in that he
had done "residential building work" or "specialist work" in breach of ss 12 and
13 of the Home Building Act 1989 on the site.
- The
third defendant submitted there was no breach of cl 10.08, or the reasonable
requirements of that clause; ss 12 and 13 of the Home Building Act 1989
did not provide a basis for denial of liability and no loss had been established
by Mecon.
The construction of the policy
- The
policy relevantly provided Mecon would indemnify the third defendant for all
amounts which the third defendant was legally liable
to pay (insuring provision
5) and but that Mecon may avoid paying the claim if the third defendant failed
to observe the nominated
conditions and such failure increased Mecon's exposure
to a claim, exacerbated or caused the loss damage or legal liability for which
indemnity was sought (general condition 10). In the circumstances of this case
the question is whether breach of the condition, if
established, caused loss or
legal liability, there being no evidence Mecon's exposure to a claim was
increased or that the liability
or loss was exacerbated.
- Mecon,
in the manner in which it particularised breach of condition 10.08(d) appears,
correctly, to have accepted that condition 10.08(d)
should be read down in order
to give effect to the commercial purpose of the policy which was to indemnify
the insured against liability
for his negligence, a literal interpretation of
that condition being repugnant to the commercial purpose of the policy. The
reading
down of such a provision accords with a long line of authority since
Fraser v BN Furman (Productions) Limited [1967] 1 WLR 898.
- In
my opinion, the opening words of general condition 10 should be construed as
meaning reasonable as between the insured and insurer
having regard to the
commercial purpose of the policy, thus leading to a similar reading down of
conditions 10.08(b) and (c) as for
10.08(d). The presence of the word
"reasonable" in condition 10.08(d) and not in 10.08(b) and (c) does not preclude
that construction
having regard to the specific words of condition 10 in
referring to "each condition" and that "each condition reflects a reasonable
requirement of you". Insofar as the opening words of condition 10 are ambiguous
they should be construed contra proferentem Mecon.
- The
failure by the third defendant to observe conditions relied on by Mecon would
not entitle Mecon to refuse indemnity to the third
defendant unless the terms of
the condition literally construed (or read down if appropriate) applied and were
breached by the third
defendant and the failure to observe the condition caused
the loss or legal liability for which indemnity is sought.
- I
have had regard to the various authorities to which the parties referred me
including The Committee for the Time Being of the Casino Show Society v
Norris (1984) 3 ANZ Ins Cas 60-580 and Kim v Cole [2002] QCA 176. In
my opinion, the Mecon policy must be construed according to its own terms and,
as those terms differ from the cases referred to,
the latter are not
determinative.
Determination
Breach of condition 10.08(b)
- The
breach of condition 10.08(b) was particularised as a breach of reg 39 of the
Occupational Health and Safety Regulation 2001 which, relevantly,
required that the controller of the premises must ensure that
"(a)
safe access is provided to all parts of a place of work to which a person may
require access and from which the person may fall,
and
...
(c) walkways are provided and maintained over roofs that are wholly or partly
covered by brittle or fragile roofing material, and
...
(e) floors are designed to be safe without risks of slips, trips or falls,
with adequate drainage (if necessary) and appropriate floor
coverings (if
necessary)."
- The
authorities distinguish between access to a place of work and the place of work.
In this case the plaintiff was injured at his
place of work - Australian Iron
and Steel Pty Limited v Luna [1969] HCA 66; (1969) 123 CLR 305 at 310. The alleged breach
did not cause the legal liability for which indemnity was sought. Additionally,
no breach of the condition,
when read down, has been established as the third
defendant had taken steps to avoid such a danger and was not indifferent to
whether
it was averted or not. No basis to refuse indemnity is established.
- Regulation
39(c), in its terms, is limited to a requirement in respect of "roofs covered
with brittle or fragile roofing material". That is not this
case. Regulation
39(c) has no application. No basis to refuse indemnity is established.
- Regulation
39(e), in its terms, is limited to the design of floors. There is no evidence
the design of the floor on which the plaintiff fell was deficient.
The evidence,
such as it was, was to the contrary. The regulation has no application. In any
event, I do not accept the effect of
the morning dew would have been adverted by
drainage or floor coverings envisaged by the regulation. No basis to refuse
indemnity
is established.
Breach of condition 10.08(c)
- The
breach of 10.08(c) was particularised as a failure to ensure that a safety
device such as a barrier, handrail or guardrail around;
or complete or adequate
cover over the stairwell void which was required to be fitted, was in place and
fully operational at all
times.
- Condition
10.08(c) applies to "safety devices". This expression should be given its
ordinary meaning in the sense of a contrivance
or mechanical device. This
construction is confirmed by the words in parenthesis and the concept of being
"fitted or required to
be fitted". Any ambiguity in the expression should be
construed contra proferentem Mecon. Condition 10.08(c) has no application in
the
circumstances. It provides no basis to refuse indemnity.
Breach
of condition 10.08(d)
- The
breach of condition 10.08(d) was particularised as that the third defendant was
aware there was no barrier, handrail or guardrail
around or a complete or
adequate cover over the void at or about the time of the fall, he was aware of
the risk of danger that someone
could fall through the void and despite being
aware of those matters, the third defendant deliberately, recklessly, or with
indifference
to the normal precautions that should have been taken (being the
installation of the safety devices) did nothing to prevent or took
measures
which were inadequate to avert the risk of danger.
- Condition
10.8(d), construed literally, would be repugnant to the commercial purpose of
the policy as it would deprive the insured
of any cover in the circumstances of
this case. In Legal and General Insurance Australia Limited v Eather
(1986) 6 NSWLR 390 it was held the requirement in an insurance policy that
the insured "take all reasonable precautions to avoid or minimise injury,
loss
or damage..." is satisfied by the insured proving either that he did not
recognise that a danger existed or that perceiving
its existence he took some
action to avoid it and was not indifferent to whether the danger was averted or
not.
- It
may be accepted the third defendant was aware of the danger posed by the void.
However, the third defendant had retained qualified
personnel to perform the
work in which the plaintiff was engaged. Action was taken either by those
persons or the third defendant
himself to cover the void to an extent consistent
with its use as a means of access. I accept neither the third defendant nor the
contractor was aware that the cover was not satisfactory in that it could give
way. It is true that with the benefit of hindsight
it is apparent more may have
been done by way of provision of a fence or a stronger cover. However, the
evidence does not establish
indifference on the part of the third defendant as
to whether the danger was averted or not. On the contrary, in my opinion there
was no breach of this condition properly construed.
Breach of the
Home Building Act
- Mecon
submitted that the third defendant was not entitled to indemnity pursuant to the
policy as he had breached cl 10.08(b) and/or
(d) of the policy in that he had
done "residential building work" or "specialist work" in breach of ss 12 and 13
of the Home Building Act 1989 at the site.
- The
Home Building Act contains provisions concerning the residential building
industry. It is concerned to ensure the actual building work is performed
in a
proper and tradesman-like manner and that insurance is available to meet
deficiencies in this regard. It is not concerned with
matters of building site
safety, that is the role of the Occupational Health and Safety Act and
the regulations thereunder. The provisions of the Home Building Act are
not properly categorised as "legal requirements regarding the safety or
maintenance of property" or "relevant workplace authority
regulations regarding
safety and maintenance of property". Accordingly, condition 10.08(b) has no
application.
- The
third defendant did not carry out any actual building work, all of the actual
work was done by subcontractors employed by Mr Marroun.
Mr Marroun held the
relevant licence. He acknowledged his obligation to take reasonable care in
respect of his subcontractors. In
these circumstances, any supervision by the
third defendant was excluded from the definition of residential building work by
the
Home Building Act regulations. There was no breach of condition
10.08(d) by the third defendant literally construed, and, the more so, when read
down
so as to have regard to the commercial purpose of the policy. The absence
of a certificate was not causative of the legal liability
of the third
defendant.
- The
third defendant also relied upon s 54 of the Insurance Contracts Act 1984
as confirming its entitlement to indemnity. In my opinion, for the reasons given
above, the third defendant has proved that no part
of the loss that gave rise to
his claim was caused by any of the acts relied upon by Mecon to refuse to pay
the claim. Accordingly,
Mecon may not refuse to pay the claim - s 54(3)
Insurance Contracts Act . Additionally, there was no evidence Mecon was
prejudiced as a result of any of the acts relied upon by it to refuse indemnity.
However,
in view of my earlier findings, it is unnecessary to determine whether
s 54(1) of the Insurance Contracts Act has any application.
Conclusion
- In
my opinion, Mecon is liable to indemnify the third defendant in respect of his
liability in this matter. None of the conditions
identified by Mecon entitle it
to avoid paying the third defendant's claim for indemnity.
- Counsel
for the third defendant in his final submissions sought damages for wrongful
breach of the insurance contract. He submitted
the third defendant had had to
fund his own defence in these proceedings and in the circumstances of this case
the refusal of indemnity
was entirely without warrant. Accordingly, an amount
reflective of the wrongful breach of contract by Mecon was claimed by the third
defendant to compensate him for the fact that he has been uninsured in these
proceedings and put to enormous expense and worry in
relation thereto.
- Mecon's
counsel objected to such a claim being pressed after the evidence was concluded
and submissions were being made on the grounds
he was not prepared to meet it,
it had not been particularised and had not been the subject of any evidence. He
submitted it would
involve splitting the case and having it dealt with at some
future time.
- I
accept Mecon's submissions. In my opinion, it is too late for the third
defendant to press a claim of the type now suggested.
- Prima
face, Mecon is entitled to a verdict against the first defendant subject to the
first defendant's entitlement, if any, to indemnity
from Mecon against costs
incurred by him. I have refrained from making an order in respect of the second
cross claim pending the
determination of all questions of costs.
Orders
- I
make the following orders:
1. Judgment for the first defendant
against the plaintiff.
2. The plaintiff's claim against the second defendant is dismissed.
3. Judgment for the plaintiff against the third defendant in the sum of
$206,382.11.
4. Declare the first cross defendant on the first cross claim is liable to
indemnify the first cross claimant in respect of his liability
in these
proceedings.
5. Judgment for the third cross defendant on the first cross claim.
6. All questions of costs are reserved pending written submissions by the
parties. Such submissions to be served by 4.00pm on 14 February
2011 with
replies by 4.00 pm on 28 February 2011.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2011/2.html