You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2011 >>
[2011] NSWSC 165
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Olympia Group (NSW) Pty Ltd v Hansen Yuncken Pty Ltd & Anor [2011] NSWSC 165 (16 March 2011)
Last Updated: 20 June 2011
|
Case Title:
|
Olympia Group (NSW) Pty Ltd v Hansen Yuncken Pty
Ltd & Anor
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
Before:
|
|
|
|
|
Decision:
|
Amended summons dismissed with costs
|
|
|
|
Catchwords:
|
BUILDING AND CONSTRUCTION CONTRACTS - Building and
Construction Industry Security of Payment Act 1999 (NSW) - whether a decision by
an adjudicator who does not have jurisdiction was a determination under s 22 -
whether entitled to submit new claim under s 17 - whether adjudicator had
jurisdiction to determine claim - whether construction work carried out outside
NSW
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
|
Parties:
|
Olympia Group (NSW) Pty Ltd (Plaintiff) Hansen
Yuncken Pty Ltd (First Defendant) Ian Hillman (Second Defendant)
|
|
|
|
Representation
|
|
|
|
|
Counsel: Mr F C Corsaro SC (Plaintiff) Mr B
C A Bradley (Plaintiff) Mr M Christie SC (First Defendant) Mr B D Kaplan
(First Defendant) No Appearance (Second Defendant)
|
|
|
|
- Solicitors:
|
Solicitors: Knight Lawyers
(Plaintiff) Crawford Legal (First Defendant) No Appearance (Second
Defendant)
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
Judgment
Background
- On
9 October 2009, the plaintiff, Olympia, and the first defendant, Hansen Yuncken,
entered into a subcontract by which Olympia agreed
for a lump sum of $7,034,550
(excluding GST) to refurbish the Geelong building in connection with the
redevelopment of HMAS Creswell.
HMAS Creswell is a shore establishment of the
Royal Australian Navy located on the southwest shores of Jervis Bay. By s 4 of
the Jervis Bay Territory Acceptance Act 1915 (Cth), the area occupied by
HMAS Creswell is a territory of the Commonwealth known as the Jervis Bay
Territory. By s 4A of that Act, the laws of the Territory are the laws of the
Australian Capital Territory.
- The
contract between Olympia and Hansen Yuncken is expressed to be governed by the
laws of the ACT.
- On
28 January 2011, Olympia issued a payment claim in the sum of $946,214.48
(inclusive of GST) under s 13 of the Building & Construction Industry
Security of Payment Act 1999 (the SOP Act ) in respect of work
performed under the contract.
- On
2 February 2011, Hansen Yuncken issued a payment schedule in the sum of
$305,537.17 under s 14 of the SOP Act.
- On
15 February 2011, Olympia made an adjudication application pursuant to s 17 of
the SOP Act to the Australian Solutions Centre (
ASC ), an authorised
nominating authority, for adjudication of its payment claim.
- On
17 February 2011, Hansen Yuncken wrote to ASC drawing its attention to the fact
HMAS Creswell was situated in the Jervis Bay Territory
and to s 7(4) of the SOP
Act. The text of s 7(4) is set out below. In substance, the section says that
the Act does not apply to
a construction contract to the extent that the
contract deals with construction work carried out outside New South Wales or
related
goods and services supplied in respect of construction work of that
type. The letter concluded:
Respectfully, we request the nominated adjudicator to consider,
prior to acceptance of the nomination, whether he or she has the jurisdiction
to
determine the Adjudication Application in consideration of the above matters.
- On
17 February 2011, Knight Lawyers, who acted for Olympia, responded to Hansen
Yuncken's letter. In that response, they asserted:
- The
jurisdictional issue was not raised by Hansen Yuncken's payment schedule;
- Jurisdiction was
determined by the location of the construction work rather than the governing
law of the construction contract;
- "[T]he
construction work and related goods and services which are the subject of the
Payment Claim, has [sic] been carried out in
Jervis Bay (location of site),
Sydney (supply of most materials) and in between those two places
(transportation of materials to
site)" and, in those circumstances, the
adjudicator had jurisdiction.
The letter went on to say:
To the extent which it may be relevant, the Respondent has not yet submitted
its Adjudication Response and the matters contained in
its facsimile will not be
"duly made" for the purposes of section 22(2)(d) of the [SOP Act]. The Claimant
submits that the submission
should not be considered unless and until it is a
submission "duly made" within the meaning of that section.
- The
second defendant was nominated as the adjudicator and, on 21 February 2011, ASC
sent the parties a copy of his notice of acceptance
under s 19 of SOP Act.
Although the adjudicator did not file a submitting appearance in these
proceedings, it is clear from evidence
before the court that he chose not to
participate in them; and the hearing proceeded on the basis that he had
effectively agreed
to submit to any order of the court other than an order as to
costs.
- On
22 February 2011, ASC wrote to the parties stating that the adjudicator had
requested ASC to advise the parties of the following:
Pursuant to
Section 22(2)(a) of the Building and Construction Industry Security of Payment
Act (Act) I have formed the opinion that
I do not have jurisdiction to determine
the adjudication application.
I refer to the Respondent's unsolicited correspondence dated 17 th February
2011, which I note is in relation to jurisdictional issues
so I must consider
the contents.
The Payment Claim in question is for works carried out in an area of Jervis
Bay NSW that comes under the Jervis Bay Territory Acceptance Act 1915 and has
been endorsed under the Building and Construction Industry Security of Payment
Act 1999 being a NSW Act. The Jervis Bay Territory Acceptance Act 1915,
agreement was made [sic] between the Commonwealth of Australia ('Commonwealth')
and the State of New South Wales ('State'), to provide
for the acceptance of
certain territory surrendered by the State to the Commonwealth ...
I am satisfied the ... boundaries [of the Jervis Bay Territory] encompass the
construction site the subject of this adjudication application
and as such is a
territory under Australian Capital Territory jurisdiction.
Based on the above I am satisfied the contract and therefore the payment
claim made under the contract is not under the jurisdiction
of the Building and
Construction Industry Security of Payment Act 1999. As such I have formed the
view the Payment Claim the subject of this adjudication application is invalid.
- Olympia
commenced these proceedings on 7 March 2011, seeking urgent relief. Essentially,
it makes three claims. First, it says that
the adjudicator did have jurisdiction
to deal with its claim because the relevant construction work, or at least a
substantial part
of it, was carried out in New South Wales. Second, Olympia says
that the adjudicator failed to determine its claim within the time
allowed by s
21(3) of the SOP Act with the consequence that it is now entitled under s 26(2)
of the SOP Act to withdraw its original
adjudication application and to make a
new adjudication application under s 17. Thirdly, Olympia claims (in an amended
summons filed
on 8 March 2011) that, if the adjudicator did make a determination
pursuant to s 22 of the SOP Act, that determination was void.
Did the adjudicator determine Olympia's payment claim?
- It
is convenient to deal first with the question whether the adjudicator determined
Olympia's payment claim. However, before dealing
with that issue, I should
mention one preliminary matter. There was a suggestion in Knight Lawyers' letter
dated 17 February 2011
that Hansen Yuncken could not raise with the adjudicator
the jurisdictional issue because that issue was not raised by its payment
schedule. That submission was not seriously pursued at the hearing. In any
event, in my opinion, it has no substance. Section 20(2B)
of the SOP Act
provides:
The respondent cannot include in the adjudication
response any reasons for withholding payment unless those reasons have already
been
included in the payment schedule provided to the claimant.
That section prevented Hansen Yuncken from raising in its adjudication
response a reason for not making a payment that was not raised
in its payment
schedule. It did not prevent it from raising grounds on which it was asserted
that the adjudicator did not have jurisdiction
to make a determination.
- In
relation to the question whether the adjudicator determined Olympia's claim,
Olympia puts its case in two ways. First, it says
that the adjudicator did not
have power to determine his own jurisdiction. Second, Olympia submitted that, on
its face, the decision
of the adjudicator was not a determination of its claim.
Rather, the adjudicator reached a conclusion that he did not "have jurisdiction
to determine the adjudication application" and that the "adjudication
application is invalid". These decisions, whatever they were,
were not a
determination of the claim. That conclusion, according to Olympia, was supported
by the fact that the adjudicator reached
his decision before Hansen Yuncken
served its adjudication response and before the time for it to do so had
expired. That was despite
the fact that s 21(1) of the SOP Act provides:
An adjudicator is not to determine an adjudication application
until after the end of the period within which the respondent may lodge
an
adjudication response.
- Hansen
Yuncken, on the other hand submitted that the letter dated 22 February 2011 from
ASC communicating the adjudicator's decision
satisfied the requirements of s 22
of the SOP Act. That section relevantly provides:
(1) An
adjudicator is to determine:
(a) the amount of the progress payment (if any) to be paid by the respondent
to the claimant (the adjudicated amount ), and
(b) the date on which such amount became or becomes payable, and
(c) the rate of interest payable on any such amount.
(2) In determining an adjudication application, the adjudicator is to
consider the following matters only: (a) the provisions of this
Act;
(b) the provisions of the construction contract from which the application
arose,
(c) the payment claim to which the application relates, together with all
submissions (including relevant documentation) that have
been duly made by the
claimant in support of the claim,
(d) the payment schedule (if any) to which the application relates, together
with all submissions (including relevant documentation)
that have been duly made
by the respondent in support of the schedule,
(e) the results of any inspection carried out by the adjudicator of any
matter to which the claim relates.
(3) The adjudicator's determination must be in writing and must include:
(a) the reasons for the determination, and
(b) the basis on which any amount or date has been decided, if, before the
making of the determination, either the claimant or the
respondent requests the
adjudicator to include those matters in the determination.
In Hansen Yuncken's submission, the determination of the adjudicator in
substance was that the amount of the payment claim was nil
because the payment
claim was not validly made under the SOP Act and that determination was within
the scope of the adjudicator's
function. Hansen Yuncken claimed that that
conclusion was supported by the decision of the Queensland Supreme Court in
John Holland Pty Ltd v Schneider Electric Buildings Australia Pty Ltd
[2010] QSC 159. In that case, an adjudicator had concluded that he did not
have jurisdiction to determine a claim because only one reference date
was
available to the claimant and the claimant had previously served a claim in
respect of that reference date. Section 17(5) of
the Queensland Act, like s
13(5) of the SOP Act, provides that a claimant cannot serve more than one
payment claim in relation to
each reference date. Applegarth J held that the
adjudicator's decision was a decision that fell within s 26 of the Queensland
Act
(which is in substantially the same terms as s 22 of the SOP Act).
Consequently, the claimant was bound by the adjudicator's decision
on that point
and it could not therefore serve a further claim. Hansen Yuncken also claimed
that its submission was supported by
the decision of the Court of Appeal in
Downer Construction (Australia) Pty Ltd v Energy Australia (2007) 69
NSWLR 72.
- I
do not accept Hansen Yuncken's submissions. In my opinion, the adjudicator's
decision was not a determination of the type contemplated
by s 22 of the SOP
Act. Rather, it was a decision whether the SOP Act applied to the claim made by
Olympia having regard to where
the relevant construction work was carried out.
The adjudicator had to make a decision about that question because it was an
essential
precondition to the exercise of the powers granted to him by the Act.
But is does not follow that, in making that decision, he was
exercising a power
to make a determination of the type required by s 22. As Spigelman CJ explained
in Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190;
(2010) 272 ALR 750 at [36]:
The issue to be determined is whether the adjudicator had
jurisdiction to determine an "application" which had been made without
compliance
with the mandatory (in a negative sense) terminology of s 17(2)
[which relevantly states in para (a) that an adjudication application
cannot be
made unless the claimant has notified the respondent within 20 business days
immediately following the due date for payment
of the claimant's intention to
apply for adjudication of its claim]. The issue is not, contrary to some of the
submissions made,
whether the adjudicator had jurisdiction to determine that s
17(2)(a) had been complied with. That section is not addressed to the
adjudicator and is not a matter which he is directed to "determine" within s
22(1) of the Act. It may be that it is a matter which
he must "consider" as one
of the "provisions of the Act" within s 22(2)(a). However, that section confers
no power to determine the
issue.
- The
decision of the Court of Appeal in Downer Construction (Australia) Pty Ltd v
Energy Australia [2007] NSWCA 49 ; (2007) 69 NSWLR 72 is not
inconsistent with the point made by Spigelman CJ. Before dealing with that
decision, it is important to
put it in context. In Brodyn Pty Limited v
Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421, the Court of Appeal held
that relief in the nature of certiorari was not available to quash a
determination of an adjudicator on
the grounds of jurisdictional error. In
reaching that conclusion, the court thought that a legislative intention to
minimise court
involvement in the operation of the SOP Act could be discerned
from the terms of the statute. However, the Court of Appeal thought
that there
were a number of essential preconditions to an adjudication determination which,
if they did not exist in a particular
case, meant that the determination was
void. Those preconditions included:
1 The existence of a
construction contract between the claimant and the respondent, to which the Act
applies (s 7 and s 8).
2 The service by the claimant on the respondent of a payment claim (s 13).
3 The making of an adjudication application by the claimant to an authorised
nominating authority (s 17).
4 The reference of the application to an eligible adjudicator, who accepts
the application (s 18 and s 19).
5 The determination by the adjudicator of this application (s 19(2) and s
21(5)), by determining the amount of the progress payment,
the date on which it
becomes or became due and the rate of interest payable (s 22(1)) and the issue
of a determination in writing
(s 22(3)(a)). ([2004] NSWCA 394; [2004] NSWCA 394; (2004) 61 NSWLR
421 at [53] per Hodgson JA.)
- Brodyn
was overruled by the Court of Appeal in Chase Oyster Bar Pty Ltd v Hamo
Industries Pty Ltd [2010] NSWCA 190; (2010) 272 ALR 750. In that case, the
Court of Appeal held, following the decision of the High Court in Kirk v
Industrial Relations Commission (NSW) [2010] HCA 1; 239 CLR 531, that the
court did have power to grant relief in the nature of certiorari against an
adjudicator for jurisdictional error. Clearly,
Downer Construction
(Australia) Pty Ltd v Energy Australia [2007] NSWCA 49 ; (2007) 69
NSWLR 72 was decided before Chase Oyster Bar and it must be read in that
light.
- In
Downer Construction, the contract was for the construction of a tunnel to
carry electrical cables. A clause in the contract entitled the contractor,
Downer,
to be paid extra costs if it encountered a "Latent Condition" during
tunnelling operations. Downer made a claim under that clause
following water
ingress into the tunnel. The claim was expressed in different terms in the
adjudication application. However, the
adjudicator concluded that the claim and
the application raised substantially the same issues. Energy Australia took
issue with that
conclusion and submitted that, since the adjudication
application was sufficiently different from the payment claim, the application
was not for adjudication of the claim or the adjudicator's determination of the
application was not a determination of the claim.
On that question, Giles JA
(with whom Santow JA and Tobias JA agreed) said (at [87]):
In my opinion, determination of the parameters of the payment claim
is a matter for the adjudicator, and a reasonable but erroneous
decision by the
adjudicator does not invalidate the determination. In the present case, in
determining the amount of the progress
payment (if any) to be made it was for
the adjudicator to decide whether the water ingress fell within latent
conditions for the
purposes of the contract, and the parameters of the payment
claim in that respect. He did so. As to both, it could not be said that
the
adjudicator's decision was without foundation, and if the adjudicator addressed
the matters and came to his decisions, even if
other decisions could have been
come to, he did what the Act required - he determined the adjudicated amount.
What is clear from this passage is that the court took the view that the
question whether the claim and application raised the same
issue was one of the
matters that the adjudicator was required to decide in order to reach a
determination under s 22. It was not
an issue that went to his jurisdiction
either in the narrow sense considered in Brodyn or the broader sense
considered in Chase Oyster Bar . The position in the present case is
quite different since, even on the narrow approach adopted in Brodyn ,
the question whether there was a construction contract to which the Act applies
- that is, a construction contract which did not
involve construction work
carried out outside New South Wales or related goods and services supplied in
respect of construction work
of that type - is a question that goes to whether
the adjudicator can exercise jurisdiction. It is not a question the
determination
of which forms part of the exercise of that jurisdiction.
- I
accept that it is difficult to reconcile the conclusions of the previous
paragraph with statements made by Applegarth J in John Holland . However,
the decision in that case did not turn on whether the original adjudicator's
decision was a decision under s 26 of the
Queensland Act. Rather, it turned on
the extent to which a decision of an adjudicator was binding in a later
adjudication. The resolution
of that issue did not depend simply on
characterising the decision in relation to the earlier adjudication application
as falling
within s 26 of the Queensland Act. It also turned on principles of
issue estoppel and abuse of process. In any event, John Holland was
decided before Chase Oyster Bar . In my opinion, the point made by
Spigelman CJ in the latter case is correct and I should follow it.
- In
my opinion, the conclusion that the adjudicator did not make a determination
under s 22 of the SOP Act is supported by what the
adjudicator actually did. He
was asked to make a decision on the question of jurisdiction before he accepted
his nomination. Faced
with that request, he accepted his nomination but, on the
same day, caused ASC to write to the parties to say that he accepted that
he did
not have jurisdiction. He did not wait for an adjudication response as he was
required to do before making a determination
under s 22. Nor does it appear that
he examined the payment claim or the payment schedule in arriving at his
decision. Rather, what
he relied on was the fact that the construction site was
located outside New South Wales. It seems clear from those facts that the
adjudicator - correctly, in my view - was not purporting to make a determination
under s 22.
What are the consequences of what the adjudicator did?
- Section
26 of the SOP Act relevantly provides:
(1)This section applies if:
(a)a claimant fails to receive an adjudicator's notice of acceptance of an
adjudication application within 4 business days after the
application is made,
or
(b)an adjudicator who accepts an adjudication application fails to determine
the application within the time allowed by section 21(3).
(2)In either of those circumstances, the claimant:
(a) may withdraw the application, by notice in writing served on the
adjudicator or authorise nominating authority to whom the application
was made,
and
(b) may make a new adjudication application under section 17.
There is ample authority for the proposition that "fails" in this context
simply means "does not". So, for example, if the court holds
that the
adjudicator's decision was void for some reason, then the adjudicator has failed
to determine the application: see Multiplex Constructions Pty Limited v
Luikens [2003] NSWSC 1140; Emergency Services Superannuation Board v
Sundercombe [2004] NSWSC 405; John Holland Pty Limited v Made Contracting
Pty Limited [2008] NSWSC 374; Cardinal Project Services Pty Limited v
Hanave Pty Limited [2010] NSWSC 1367 at [22] per McDougall J.
- In
follows, in this case, that Olympia is entitled under s 26(2) of the Act to make
a new adjudication application under s 17. However,
the court would not permit
it to do so unless the court was satisfied that an adjudicator had jurisdiction
to determine the claim.
Does an adjudicator have jurisdiction to determine Olympia's
claim?
- Section
7 of the SOP Act relevantly provides:
(1) Subject to this section,
this Act applies to any construction contract, whether written or oral, or
partly written and partly
oral, and so applies even if the contract is expressed
to be governed by the law of a jurisdiction other than New South Wales.
...
(2) This Act does not apply to a construction contract to the extent to which
it deals with:
(a) construction work carried out outside New South Wales; and
(b) related goods and services supplied in respect of construction work
carried out outside New South Wales.
...
- Section
6(1) of the SOP Act provides:
In this Act, related goods and
services , in relation to construction work, means any of the following
goods and services:
(a) goods of the following kind:
(i) materials and components to form part of any building, structure or work
arising from construction work,
(ii) plant or materials (whether supplied by sale, hire or otherwise) for use
in connection with the carrying out of construction
work,
(b) services of the following kind:
(i) the provision of labour to carry out construction work,
(ii) architectural, design, surveying or quantity surveying services in
relation to construction work,
(iii) building, engineering, interior or exterior decoration or landscape
advisory services in relation to construction work,
(c)goods and services of a kind prescribed by the regulations for the
purposes of this subsection.
- The
question, then, is whether the construction contract in this case "deals with"
construction work carried out outside New South
Wales or with related goods and
services supplied in respect of construction work carried out outside of New
South Wales. That question
is to be answered by considering the terms of the
relevant construction contract in the context in which they operate. In my
opinion,
that requires the court to identify the subject matter of the contract
and to ask whether that subject matter has the required quality
(that is,
dealing with construction work or related goods and services of the type
referred to in s 7(3)). Whether or not it has
the required quality does not
depend simply on the terms of the contract. It also depends on the objective
facts relating to the
relevant work.
- In
this case, the relevant construction contract is the contract between Olympia
and Hansen Yuncken. Clause 2.1 of that contract requires
Olympia to "undertake
and complete building works to Geelong in the manner of a turnkey solution". The
clause then goes on to provide
a non-exclusive list of the areas of work to be
covered by the contract. Clause 3 of the contract then sets out a more precise
description
of the works. Clause 3.4 sets out what is required in relation to
site preparation including matters such as site cleaning and tree
protection.
Clause 3.5 requires Olympia to allow for out of sequencing works and to
coordinate with other contractors working at
HMAS Creswell. Clause 3.6 requires
Olympia to provide adequate levels of supervision. Clause 3.8 requires Olympia
to complete external
infrastructure and civil works adjacent to the Geelong
building including stormwater works, civil work such as excavation and
reinstatement
of grassed areas, electrical and communication services, subsoil
drainage works, gas, sewer and water supply services together with
demolition
work.
- In
order to comply with its obligations under its contract, Olympia engaged a
number of subcontractors. The work performed by the
subcontractors included
piling, structural steelwork, carpentry and joinery. The claim that was the
subject of the adjudication application
included amounts payable to those
subcontractors, among others. The relevant subcontractors are based in New South
Wales and a substantial
amount of the work they did in order to meet their
obligations under the subcontracts was performed in New South Wales.
- In
my opinion, the contract between Olympia and Hansen Yuncken dealt with
construction work outside New South Wales or at least with
related goods and
services supplied in respect of that construction work. Under the contract,
Olympia was to refurbish a building
in the Jervis Bay Territory. Necessarily,
the work had to be performed in that territory. The fact that goods were sourced
in New
South Wales and work was carried out in New South Wales in connection
with the contract does not mean that the contract between Olympia
and Hansen
Yuncken dealt with construction work in New South Wales. At most, all
that could be said was that the contract for the construction work dealt with
related
goods and services which were supplied in New South Wales because the
contract left it open - or, indeed, given the location of the
Jervis Bay
Territory, contemplated - that goods and services of that description would be
supplied. The goods and services actually
supplied in New South Wales were
related goods and services to construction work carried on in the Jervis Bay
Territory because the
goods and services consisted of materials and components
which formed part of the work on the Geelong building or the provision of
labour
in connection with the fabrication of those materials and components. The SOP
Act does not apply to those related goods and
services by reason of s 7(4)(b) of
the Act.
Orders
- In
my opinion, the adjudicator was correct to hold that he did not have
jurisdiction to deal with Olympia's claim. In those circumstances,
its amended
summons should be dismissed with costs.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2011/165.html