You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2011 >>
[2011] NSWSC 116
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Filadelfia Projects Pty Limited v Entirity Business Services Pty Limited& Anor (No 2) [2011] NSWSC 116 (4 March 2011)
Last Updated: 14 April 2011
|
Case Title:
|
Filadelfia Projects Pty Limited v Entirity Business
Services Pty Limited & Anor (No 2)
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
|
|
|
|
|
Decision:
|
The court orders that: 1. The first defendant be
restrained from seeking or enforcing an Adjudication Certificate under the
Building and Construction Industries Security of Payment Act 1999 (NSW)
in respect of an adjudication determination of Adjudicator Sullivan dated 23
March 2010. 2. The plaintiff be at liberty to withdraw the sum of $500,000
from the controlled moneys account held by its solicitors and referred
to in
paragraph 2 of the short minutes of order made by consent by the court on 30
August 2010. 3. The first defendant pay the plaintiff's costs of the
proceedings.
|
|
|
|
Catchwords:
|
CONTRACT - informal agreements - construction
contracts - relevance of post contractual conduct in determining who the parties
to
the contract are - objective determination - contract found between builder
and contractor, not developer and contractor. PROCEDURE
- adjudication
application under Building & Construction Industry Security of Payment Act
1999 - natural justice - failure to
supply same documents to adjudicator and
opposing party - denial of natural justice - whether relief should be refused in
circumstances
where conduct not deliberate and issue determined on the merits by
the court - abuse of process - deliberately withheld relevant
documents from
adjudicator - no duty of full disclosure in adjudication process
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
|
Parties:
|
Filadelfia Projects Pty Limited
(Plaintiff) Entirity Business Services Pty Limited (First
Defendant) Master Plumbers and Mechanical Contractors Association of New
South Wales (Second Defendant)
|
|
|
|
Representation
|
|
|
|
|
Counsel: Mr M Rudge SC (Plaintiff) Mr I
George (Plaintiff) In Person (First Defendant) No Appearance (Second
Defendant)
|
|
|
|
- Solicitors:
|
Solicitors: Veritas Legal (Plaintiff) In
Person (First Defendant) No Appearance (Second Defendant)
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
Judgment
Introduction
- In
these proceedings the plaintiff, Filadelfia, seeks an injunction against the
first defendant, Entirity, restraining Entirity from
applying for an
adjudication certificate in respect of a claim served by Entirity on Filadelfia
on 18 February 2010 under the Building & Construction Industry Security
of Payment Act 1999 ( the Act ).
- The
claim relates to electrical work performed by Entirity at a residential unit
development in Wahroonga which was being developed
by Filadelfia. A critical
issue between the parties is whether there was a construction contract within
the meaning of the Act between
Filadelfia and Entirity. Filadelfia contends it
engaged a company known as Zebicon Pty Limited as the builder of the project and
that Zebicon had subcontracted the electrical work to Entirity. Consequently,
Filadelfia maintains that the construction contract
for the electrical work was
between Entirity as subcontractor and Zebicon as head contractor, not between
Entirity and Filadelfia.
- The
claim was the subject of an adjudication application under s 17 of the Act. The
adjudicator resolved the question of who were
the parties to the contract in
favour of Entirity and determined that Filadelfia was liable to pay Entirity the
sum of $414,361.58
excluding GST as at 25 February 2010 and interest on that
amount at 9 per cent per annum from that date.
- Filadelfia
then made an application for an interlocutory injunction restraining Entirity
from applying for an adjudication certificate
in respect of that amount. On 13
May 2010, McDougall J granted an interlocutory injunction. Subsequently on 30
August 2010, Hammerschlag
J made orders by consent requiring Filadelfia to pay
the sum of $500,000 into a controlled moneys account pending final determination
of the proceedings. His Honour granted the interlocutory injunction for three
reasons. First, his Honour held that there was a serious
question to be tried
concerning whether there was in existence a construction contract between
Filadelfia and Entirity. As his Honour
pointed out (applying the decision of the
Court of Appeal in Brodyn Pty Ltd t/as Time Cost and Quality v Davenport
[2004] NSWCA 394; [2004] NSWCA 394; (2004) 61 NSWLR 421 at [53]), the existence of a
construction contract is one of the basic and essential requirements for the
existence of a valid adjudication
determination and the court is not constrained
by the adjudicator's finding on that issue: see Filadelfia Projects Pty
Limited v Entirity Business Services Pty Ltd [2010] NSWSC 473 at [7].
- Second,
it was agreed between the parties that the adjudicator had not been provided
with some material which was relevant to the
question whether Filadelfia or
Zebicon was the contracting party, although there was evidence that Filadelfia
was not aware of that
fact at the time. His Honour thought that that raised the
question whether there had been a substantial denial of procedural fairness:
see
[2010] NSWSC 473 at [8].
- Thirdly,
his Honour thought that it may be arguable that the failure of Entirity to
provide the adjudicator with relevant material
was an abuse of process having
regard to the pressures of time and other constraints which apply in relation to
an adjudication determination
in much the same way as it is incumbent on a party
applying to the court for ex parte relief to place all material matters
before the court: see [2010] NSWSC 473 at [9].
- It
is those issues which now require final determination.
Was Entirity's contract with Filadelfia?
- On
5 February 2008, Filadelfia, as owner, and Zebicon, as builder, signed a
building contract substantially in the form of the Housing
Industry Association
Limited's Plain Language Building Contract for New Home Construction. Filadelfia
was 50 percent owned by Mr
Tony Merhi through a company known as Stabla Pty Ltd
and 50 percent owned by Zebigroup Pty Ltd, whose shareholders were Mrs Silvana
Zerilli and Mr Frank Bilotta. It had two directors, Mr Merhi and Mr Bilotta. Its
principal place of business at the time was at premises
in Toongabbie. Zebicon
was owned by Mrs Zerilli and Mr Bilotta. Mr Emanuel Zerilli, Mrs Zerilli's
husband, was its sole director.
Its principal place of business was at premises
in Leichhardt. At the time, Mr Bilotta was employed as a construction manager
with
it. An administrator was appointed to Zebicon on 22 March 2010, although
the administration is likely to finish shortly as a result
of a deed of company
arrangement.
- Clause
22.2 of the building contract provides:
The Builder may subcontract any part of the Building
Works but remains responsible for all of the Building Works .
"Building Works" is defined in cl 1.1 to mean "the Building Works to
be carried out, completed and handed over to the Owner in accordance with
this Contract as shown in the Contract Documents and including
Variations ". The work is described in the contract as:
The construction of the three (3) residential flat buildings comprising fifty
(66) [sic] Apartments in accordance with Development
Consent No. 10732 of 2006,
and the approved DA & CC plans and specifications.
- It
is clear from these provisions that Zebicon was responsible for building the
development. It could either do so itself or it could
engage subcontractors to
do so on its behalf. However, if it did the latter, it was still responsible for
the work done by those
subcontractors. This is not a case where Zebicon was
engaged by Filadelfia to supervise contractors who were engaged directly by
Filadelfia.
- The
building contract was for a lump sum of $15,620,000. The total cost of the
project was to be funded by ING Bank, which took a
mortgage over the property.
- Mr
Paul Barlow is the sole director and shareholder of Entirity. He, with leave,
appeared on Entirity's behalf at the hearing. There
is no suggestion that he or
anyone else from Entirity knew of the terms of the building contract between
Filadelfia and Zebicon.
- The
possibility of Entirity performing the electrical works at the Wahroonga
development was first raised by Ms Natalie Werch. Ms
Werch was Zebicon's
bookkeeper, although she also did bookkeeping work and other administrative
tasks for Filadelfia and, in fact,
the address given by Filadelfia as its
principal place of business at the time was also Ms Werch's residence. Ms Werch
also owned
a company known as ACA Communications Pty Ltd. It appears that Ms
Werch was a friend of, or acquainted with, Ms Hyde, who is Mr Barlow's
sister
and who is employed as Entirity's office and administration manager.
- In
March 2008, Entirity was doing some work for ACA Communications on the NSW
central coast. While Mr Barlow was working on that project,
Ms Werch suggested
to him that Entirity may be interested in doing the electrical work for the
Wahroonga project and subsequently
she spoke both to Mr Bilotta and Mr Zerilli
about that possibility.
- On
4 April 2008, Ms Werch telephoned Mr Barlow and asked if he could arrange for a
technician from Entirity to do some preliminary
work at the Wahroonga site,
which he did.
- On
or about 9 April 2008, Ms Hyde prepared an invoice for the preliminary work
performed by Entirity. Originally, the draft invoice
was addressed to ACA
Communications. However, at about the time the invoice was prepared, Ms Werch
telephoned Ms Hyde and asked her
to address the invoice to Zebicon. Ms Hyde
amended the draft invoice by hand. A final invoice was prepared from that
amended draft.
It is dated 9 April 2008 and is addressed to Zebicon.
- On
18 April 2008, Ms Werch emailed Mr Barlow a set of tender drawings for the
project. It is unclear whether Mr Barlow met with either
Mr Bilotta or Mr
Zerilli before that time. In addition, there is a dispute about whether Mr
Zerilli at some point also handed Mr
Barlow a copy of the tender drawings.
Nothing, however, turns on the resolution of these matters.
- At
the time that Mr Barlow was provided with a copy of the drawings, Filadelfia had
lodged an amended development application to combine
two of the buildings that
comprised the project into one. The amended DA did not involve any significant
changes to the carpark for
the development or alter the number of units to be
built. Ultimately, the amended DA was the subject of an application by
Filadelfia
to the Land and Environment Court which failed and the amended
development did not proceed. However, at the time the electrical works
were put
out for tender, it was expected that the amended DA would be approved.
Consequently, the plans provided to Mr Barlow were
the amended plans. Those
plans indicated that they had been prepared for Filadelfia.
- Entirity
submitted four proposals for the electrical work in all. Each proposal was
described as being "for Filadelfia Pty Ltd". Mr
Barlow gave evidence, which I
accept, that he handed a copy of the first version of the plans to Mr Bilotta at
the offices at Leichhardt
at a meeting which occurred on 16 May 2008. The
likelihood is that Mr Zerilli was also present at that meeting. That was Mr
Bilotta's
evidence, and Mr Zerilli gave evidence that he attended a number of
meetings with Mr Barlow. The meeting was held in Zebicon's offices.
Mr Zerilli
had overall responsibility for the contractual administration of the project
whereas Mr Bilotta was the project manager
on site. It is natural in those
circumstances that Mr Zerilli would attend a meeting in which an important
contractor presented its
proposal.
- Following
discussion of the proposal, Mr Barlow agreed to submit an amended proposal.
There is a dispute about what happened next
and, in particular, the extent of Mr
Barlow's dealings with Mr Bilotta and Mr Zerilli. Mr Barlow says that he dealt
principally with
Mr Bilotta and that it was Mr Bilotta who was responsible for
awarding the contract for the electrical work. On the other hand, both
Mr
Bilotta and Mr Zerilli say that Mr Zerilli was principally responsible for
awarding the contract for the electrical works and
that it was Mr Zerilli who
had most of the meetings with Mr Barlow. In my opinion, little turns on the
resolution of this dispute.
Mr Barlow attached significance to the issue because
it was his submission that he dealt with Mr Bilotta as a representative of
Filadelfia.
But even if Mr Barlow dealt principally with Mr Bilotta, it does not
follow that Mr Barlow was dealing with Filadelfia. Mr Bilotta
was employed as
the project manager for the Wahroonga site by Zebicon. It is to be expected that
he would have dealings with subcontractors
in that capacity. On the other hand,
if the true position is that Zebicon was a project manager acting on
Filadelfia's behalf, then
there is nothing surprising if Mr Zerilli had
extensive dealings with Mr Barlow as the director of Zebicon acting in that
capacity.
In any event, the likelihood is that Mr Barlow had significant
dealings with both Mr Bilotta and Mr Zerilli. Each played an important
role in
relation to the project and each had an interest in the selection of the
contractors who were going to perform the work.
It is also relevant that Mr
Barlow had some contact with Mr Sanchez who described himself in emails he sent
to Mr Barlow as "Construction
Manager Zebicon Pty Ltd", although there is also
evidence that, on occasions, Mr Sanchez sent correspondence to others on behalf
of Filadelfia.
- There
are two other events that occurred before or at the time the contract was
awarded to which particular significance was attached
during the course of the
hearing.
- The
first of those is that Mr Barlow says that, when he presented the first version
of Entirity's proposal to Mr Bilotta, Mr Bilotta
gave him a copy of a quote for
the electrical work at Wahroonga dated 18 September 2007 from Citigroup
Electrical Pty Ltd. That quote
described the "customer" as "Filadelphia P/L"
[sic]. It was for an amount of $675,000 plus GST. Mr Barlow says that Mr Bilotta
told
him that he needed to do better than that quote. Mr Barlow places some
significance on this evidence because according to him it
points to Filadelfia
being the contracting party. Mr Bilotta disputes that evidence. As I have said,
Mr Zerilli does not refer to
this meeting specifically in his affidavit. I
prefer the evidence of Mr Bilotta on this issue. The quote from Citigroup
Electrical
was an old one which was given before Filadelfia entered into its
contract with Zebicon. Mr Bilotta had sought or had been given
quotes by a
number of other entities at about the time Mr Barlow presented his first quote.
In particular, on 13 May 2008 (3 days
before Mr Barlow presented his first
quote), Multi Purpose Electrical Services Pty Ltd faxed Mr Bilotta its quote.
That quote, which
was addressed to Zebicon, was for an amount of $625,000 plus
GST. It strikes me as implausible that Mr Bilotta would provide Mr Barlow
with
an out of date quote for an amount that was more than a recent quote that had
been provided to Mr Bilotta and would ask Entirity
to better that out of date
quote.
- The
second matter is of much greater significance. On 6 June 2008, Mr Barlow
attended the Leichhardt offices to present the final
version of his quote. Some
time between then and 25 June 2008, when Entirity commenced work at the site, Mr
Zerilli says there was
a meeting with Mr Barlow at which Ms Werch may also have
been present and at which Mr Zerilli told Mr Barlow that Entirity had been
successful in tendering for the work. Mr Zerilli says that, during that meeting,
there was a conversation to the following effect:
Mr Zerilli You keep putting Filadelfia on the proposal, you need to
change that. You are aware that if you are to be engaged, you
are to be engaged
as a subcontractor by Zebicon, the builder. Filadelfia is the developer.
Mr Barlow I have Filadelfia on the proposal as the drawings are in the name
of Filadelfia and not Zebicon.
Mr Zerilli It's common for the plans to be in the name of the developer,
Entirity is being engaged by Zebicon, the builder. You need
to change it.
Mr Barlow Okay.
- Mr
Barlow denies this conversation. He does not explain in his evidence the
circumstance's in which he says Entirity's quote was accepted
except that he
says it was accepted by Mr Bilotta.
- I
prefer Mr Zerilli's evidence in relation to this issue. There are a number of
reasons for that.
- First,
Mr Zerilli's evidence is consistent with the objective facts. There is no doubt
that Zebicon had entered into a building contact
with Filadelfia. Mr Barlow
submitted that that contract was a sham. The basis for that submission was that
the contract called for
a development of three buildings whereas the work for
which Entirity was asked to tender called for two. But that does not make the
contract a sham. Zebicon was required under the contract to build three
buildings. It was hoped by Filadelfia that there would be
a variation to that
contract following the approval of an amended DA. That approval was never
granted and, as a consequence, Zebicon
proceeded to build the project in
accordance with its contractual obligations. That, of course, entailed a
revision to the work that
Entirity was required to do and, on 3 October 2008, Ms
Werch sent Mr Barlow revised plans describing that work. Mr Barlow also
submitted
that these facts meant that Entirity's contract could not be with
Zebicon because the work that Zebicon was required to perform was
different from
the work that Entirity was required to perform. But again, when looked in
context, I do not think that that demonstrates
that Zebicon did not engage
Entirity. Entirity was engaged on the basis of an anticipated change in the
building work; and it is
clear that, as between Filadelfia and Zebicon, that
changed work would be performed by Zebicon. It is entirely consistent with that
that Zebicon would give Entirity a copy of the plans that reflected the work
that Zebicon would be required to undertake either directly
or through its
subcontractors.
- Second,
and connected to the first point, I think that the likelihood is that Mr Zerilli
would have been conscious of the contractual
relationships between the parties
and that he would have regarded them as being of some significance. It is clear
that Mr Zerilli
had substantial experience in the construction industry. He, no
doubt, would have wanted Zebicon to get paid and he would no doubt
have been
conscious that Zebicon would need to establish not only to Filadelfia but, more
importantly, ING Bank that Zebicon had
performed its work in accordance with the
construction contract and its legal obligations. Consequently, I think that it
would be
of some significance to Mr Zerilli that Zebicon received invoices
addressed to it so that it could submit those invoices in support
of any payment
claims it made; and it would be natural for him to raise that issue with Mr
Barlow at the time that he told Mr Barlow
that Entirity had been awarded the
contract. On the other hand, at the time, it would have been of no significance
to Entirity whether
it was engaged by Zebicon or Filadelfia, and consequently it
would not be surprising if Mr Barlow paid little attention to the issue.
- Third,
the contractual relationships between the parties would also have been of some
significance to Mr Bilotta. He, like Mr Zerilli,
had substantial experience in
the construction industry. He was no doubt aware that Filadelfia was obliged to
pay Zebicon under the
construction contract and relied on ING Bank to fund those
payments. It seems unlikely that he would have said anything to Mr Barlow
that
committed Filadelfia to paying Entirity. Again, it seems natural in those
circumstances that he would have left the final contractual
negotiations to Mr
Zerilli.
- Fourth,
it is clear that Mr Barlow was aware of Zebicon. He had received emails from Mr
Sanchez who described himself as a construction
manager with Zebicon. He
attended meetings at Zebicon's offices. He accepts that he was told by Ms Werch
that Entirity should make
its invoices out to Zebicon, which is what it did. Ms
Hyde gave evidence that Ms Werch made a similar request of her. However, neither
Mr Barlow nor Ms Hyde suggest that they queried this instruction. On the
contrary, it seems clear that Entirity had no difficulty
in complying with it.
The most plausible explanation of this fact is that Mr Barlow had been told that
Zebicon was the builder.
- Fifth,
it is clear that the other electrical contractors who tendered for the work were
told that Zebicon was the builder, since they
addressed their quotes to it. In
those circumstances, it seems likely that Entirity was given the same
information.
- After
the contract was awarded, Entirity commenced work in late June 2008. The first
part of the work was performed on the carpark
while Filadelfia was waiting for
approval to its amended DA. Work was then suspended for approximately three
months pending that
approval. When that approval was refused work recommenced
some time in October 2008 in accordance with the original plans. As I have
said,
all Entirity's invoices were addressed to Zebicon. All payment schedules and
remittance advices were sent by Zebicon and all
payment certificates were issued
by Entirity to Zebicon except one. The exception was that on 1 September 2009
Entirity issued a
payment certificate certifying a payment "from Leading
Ceramics Pty Ltd for Zebicon Pty Ltd". Leading Ceramics was Mr Zerilli's company
and it made the payment in circumstances where, by that time, Zebicon was in
financial difficulties for reasons unassociated with
the Wahroonga project. In
addition, Mr Barlow signed a number of statutory declarations which formed part
of the subcontractor's
statements provided under the Workers Compensation Act
1987, the Payroll Tax Act 2007 and the Industrial Relations Act
1996. In those statutory declarations, Mr Barlow certifies that Entirity had
a contract with Zebicon.
- On
15 September 2009, Zebicon served notice of termination of the contract on
Entirity. Entirity replied to that letter on 17 September
2009 in a letter
drafted by its solicitors. That reply disputed Zebicon's right to terminate the
contract. Entirity sent a further
letter to Zebicon on 22 September 2009, again
drafted by its solicitors, asserting that Zebicon had repudiated the contract
and giving
notice that Entirity accepted the repudiation and terminated the
contract itself. Nowhere do the letters sent by Entirity say that
Entirity's
contract was with Filadelfia and not Zebicon.
- Mr
Barlow tried to deal with this material principally in two ways.
- First,
he submitted that Entirity was forced to provide the documents it did in order
to get paid; and Ms Hyde gave evidence to that
effect.
- Second,
Mr Barlow said that it only became apparent to him after Entirity sent its
letters dated 17 and 22 September 2009, and after
examining all the facts, that
the contract was with Filadelfia and not Zebicon. Underlying this submission was
the view that Entirity
had made its proposals to Filadelfia, the last of those
proposals had been accepted and that, as a result, the contract must have
been
with Filadelfia.
- I
do not accept either of these submissions.
- I
do not think that Entirity was forced to provide documents that it knew to be
false in order to get paid. There is no contemporaneous
evidence that suggests
that that was the case. In addition, the submission is inconsistent with Mr
Barlow's evidence that he did
not appreciate that the contract was with
Filadelfia until after it was terminated.
- There
are two principal difficulties with Mr Barlow's second submission. First, it is
inconsistent with the finding that I have made
that Mr Zerilli explained to Mr
Barlow that Zebicon was the builder. Second, it is clear that post-contractual
conduct can be taken
into account in determining whether a contract was formed:
see, for example, Geebung Investments Pty Ltd v Varga Group Investments (No
8) Pty Ltd (1995) 7 BPR 14,551 at 14,569-70 per Kirby P; Brambles
Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153 at
[25]. Necessarily, that extends to the question whether it was formed between
particular parties, since contracts do not exist in the
abstract. It is equally
clear that the question whether there is a contract is to be determined
objectively and not by reference
to the subjective intention of the parties:
see, for example, Ryledar Pty Ltd v Euphoric Pty Ltd [2007] NSWCA 65;
(2007) 69 NSWLR 603 at [262]- [265] per Campbell JA. Looking at the position
objectively, and even leaving aside the conversation between Mr Zerilli and Mr
Barlow at
the time that Mr Barlow was told that Entirity had been successful,
the position was that Entirity performed work on the site at
Wahroonga. It was
paid by Zebicon for that work and it acknowledged that Zebicon was paying it for
that work. It complied with the
obligations imposed on a subcontractor. In my
opinion, that evidence points clearly to the existence of a contract between
Entirity
and Zebicon.
- Having
regard to the conclusions I have reached, it is strictly unnecessary for me to
express a view on the other issues in the case.
However, since I heard evidence
and submissions in relation to them, I think that I should say something about
them.
Factual background to other issues
- Entirity
made two claims under the Act. The first claim was served on Filadelfia on 10
December 2009. That claim was supported by
a large number of folders including
two marked "EBS5" and "EBS6". Those folders contained the correspondence between
the parties.
During the course of preparing those folders, two things happened
which are of relevance to this aspect of the case. First, Entirity
decided to
remove a number of documents from them and to insert in their place pages marked
"This page has" - or where consecutive
pages were removed, "these pages have" -
"been intentionally left blank". The page numbers of the pages removed were then
identified
on the top right hand corner of the inserted pages. The documents
that were removed were the subcontractor's statements and the payment
certificates provided by Entirity. Second, Entirity created duplicate sets of
EBS5 and EBS6 from which the documents were not removed.
How that came about is
not important. What is important is that, at the time that Entirity lodged its
first adjudication application,
the version of EBS5 and EBS6 that was provided
to the adjudicator did not include the excluded pages but the version that was
provided
to Filadelfia's solicitors did. Ms Hyde gave evidence, which I accept,
that that resulted from an error on her part. That adjudication
application was
out of time and did not proceed. The adjudicator returned the documents in
support of the application to Entirity.
Entirity then served a second claim on
Filadelfia and subsequently lodged an adjudication application based on that
claim. That adjudication
application is the application that is the subject of
these proceedings.
- The
parties accept that the version of EBS5 and EBS6 provided to the adjudicator in
support of the second adjudication application
did not include the excluded
pages. There is a dispute between the parties about whether the copies of EBS5
and EBS6 which were served
on Filadelfia in support of the second claim and in
support of the second adjudication application included the excluded documents.
Entirity submits that they did not. Filadelfia, on the other hand, submits that
they did.
- Entirity's
case on this aspect has two limbs. First, it relies on evidence from Ms Hyde and
Mr Russell Barlow (who is Mr Barlow's
father and who was assisting in the
collation of material for the second adjudication application) about how the
documents in support
of the second adjudication application were prepared to
demonstrate that the wrong versions of EBS5 and EBS6 could not have been
provided to Filadelfia. Second, Mr Barlow submitted that what must have happened
was that Filadelfia's solicitors confused the versions
of EBS5 and EBS6 which
were served in support of the first adjudication application (which contained
the excluded documents) with
the version served in support of the second
adjudication application (which he says did not).
- Mr
Bazouni, who was the employed solicitor with Veritas Legal and who was
responsible for preparing Filadelfia's response to the second
adjudication
application, denies that he confused documents served in support of the first
adjudication with documents served in
support of the second. He says that the
documents in support of the second adjudication application were delivered to
Veritas Legal's
offices in sealed boxes by Mr Zerilli and that, at the time that
happened, Mr Zerilli took away the documents in support of the first
adjudication application. Mr Zerilli agrees that that happened, although he says
(and Mr Bazouni denies) that he returned those documents
a few days later. Mr
Bazouni's evidence was supported by an affidavit sworn by Mr Qutami, the
responsible partner, although Mr Qutami
was unavailable for cross-examination
due to ill health.
- I
prefer the evidence of Mr Bazouni in relation to this issue. He was adamant that
he worked from the documents served in support
of the second adjudication
application. He was obviously very familiar with the documents. It is difficult
to see how an earlier
version of EBS5 and EBS6 could get mixed up with the
material served in support of the second adjudication application without that
fact coming to Mr Bazouni's attention at some stage. On the other hand, Ms Hyde
admitted in cross-examination that she had very little
to do with compiling the
documents for the second adjudication application and Mr Russell Barlow's role
was limited to an administrative
one. It seems more plausible that he
substituted the wrong folders than that Mr Bazouni did. It also seems that there
would be greater
opportunity for that to happen. Mr Barlow was working with
several sets of the documents. On the other hand, the uncontested evidence
is
that Mr Bazouni handed over the documents relating to the first adjudication
application at the time that he took possession of
the documents relating to the
second adjudication application. It seems plausible, having regard to the strict
deadline on preparing
a response, that he would have started working on those
documents almost immediately. There is no reason to suppose that he started
using a second set, even assuming the documents relating to the first
adjudication application were returned to the offices of Veritas
Legal a few
days later as Mr Zerilli suggests.
- I
should add that it was not put to any witness that it was a deliberate decision
of Entirity to provide a different version of the
documents to the adjudicator
and to Filadelfia and Filadelfia did not submit that that was the case. In those
circumstances, the
only conclusion that can be drawn was that a different
version was supplied to Filadelfia by mistake.
Was Filadelfia denied natural justice?
- The
first question is whether Filadelfia was denied natural justice because it was
not supplied with the same documents as those supplied
to the adjudicator.
- There
can be no doubt that the requirements of natural justice apply to an
adjudication determination, that a denial of natural justice
will render an
adjudication determination a nullity and that, in the context of an adjudication
determination, natural justice requires
that a party who provides the
adjudicator with material must provide the opposing party with the same
material: Fifty Property Investments v O'Mara [2006] NSWSC 428 at
[44]- [45] per Brereton J; Shorten v David Hurst Constructions Pty Limited
[2008] NSWSC 546 at [21]-[22] per Einstein J. The denial of natural justice
does not have to affect the result in order for the determination to be
a
nullity. As Brereton J explained in Fifty Property Investments v O'Mara
at [53]:
The result of a denial of natural justice is that the decision is
void, even if the decision would not have been affected by any submissions
which
might have been made had an opportunity to make them been afforded. While, as a
matter of discretion, relief may be declined
if it can be shown that the denial
of natural justice could not possibly have made a difference to the outcome, all
that a plaintiff
need establish is that the denial of natural justice deprived
it of the possibility of a better outcome, and in order to negate that
possibility it is necessary to conclude that a properly conducted adjudication
could not possibly have produced a different result
...
- In
my opinion, however, this is one of those cases where the court ought to refuse
relief even though there has been a denial of natural
justice. There are two
interrelated reasons. First, although it is true to say that there has been a
denial of natural justice in
relation to the adjudication determination, there
has not been a denial of natural justice in relation to the question whether
there
is a contract between Filadelfia and Entirity. There has been a full
hearing on the merits in relation to that question. Secondly,
it was always open
to Filadelfia to have a full hearing on the merits before the court. If it
succeeded in convincing the court that
there was no contract, the question
whether it was afforded natural justice in relation to that issue in the hearing
before the adjudicator
does not arise. On the other hand, if Filadelfia had
failed before the court, the effect of its application based on a denial of
natural justice would be to seek a remedy from the court on the basis that it
had lost an opportunity to convince the adjudicator
of a proposition which the
court has held, after a hearing on the merits, was wrong. In my opinion, it is
not appropriate for the
court to give relief in those circumstances, even
accepting that there was a denial of natural justice in the hearing before the
adjudicator. The position may well be different if the denial of natural justice
arose from deliberate conduct on the part of Entirity.
However, as I have said,
in this case, it was not submitted on behalf of Filadelfia that Entirity had
deliberately provided different
versions of the supporting documents to the
adjudicator and to Filadelfia.
Was there an abuse of process?
- There
can be no doubt that Entirity deliberately withheld relevant information from
the adjudicator. Indeed, it appears to have gone
to some trouble to ensure that
that material was not put before the adjudicator. This is not simply a case
where it decided not to
go to the additional trouble of collecting together
relevant material to place before the adjudicator. The question remains whether
that can be characterised as an abuse of process.
- It
is well established that a party which makes an ex parte application owes
a duty of candour - that is, a duty to disclose all material facts relevant to
the application which are known to
the party. The duty is imposed on the party
itself. It is not simply a professional obligation owed by the parties' legal
representatives.
The duty applies in relation to any application for an order
which involves the exercise or quasi judicial power: see Garrard t/as Arthur
Andersen & Co v Email Furniture Pty Limited (1993) 32 NSWLR 662. The
reason for the rule was explained by Isaacs J in Thomas A Edison Ltd v
Bullock [1912] HCA 72; (1912) 15 CLR 679 at 681-2:
The law in such a case is well established. There is a primary
precept governing the administration of justice, that no man is to
be condemned
unheard; and therefore, as a general rule, no order should be made to the
prejudice of a party unless he has the opportunity
of being heard in defence.
But instances occur where justice could not be done unless the subject matter of
the suit were preserved,
and, if that is in danger of destruction by one party,
or if irremediable or serious damage be imminent, the other may come to the
Court, and ask for its interposition even in the absence of his opponent, on the
ground that delay would involve greater injustice
than instant action. But, when
he does so, and the Court is asked to disregard the usual requirement of hearing
the other side, the
party moving incurs a most serious responsibility.
Dalglish v Jarvie ..., a case of high authority establishes that it is
the duty of a party asking for an injunction ex parte to bring under the
notice of the Court all facts material to the determination of his right to that
injunction, and it is no excuse
for him to say he was not aware of their
importance. Uberrima fides is required, and the party inducing the Court
to act in the absence of the other party, fails in his obligation unless he
supplies
the place of the absent party to the extent of bringing forward all the
material facts which that party would presumably have brought
forward in his
defence to that application. Unless that is done, the implied condition upon
which the Court acts in forming its judgment
is unfulfilled and the order so
obtained must almost invariably fall.
- In
my opinion, an adjudication determination is a type of quasi judicial process
which attracts the operation of the principle stated
by Isaacs J. A
determination involves an order requiring a party to pay a sum of money
depending on the establishment of various
facts and, in some cases, principles
of law.
- However,
I do not think that the application in this case can be equated to an ex
parte application. It is true that the Act imposes a very tight timetable.
Nonetheless, it provides a mechanism by which the respondent
has an opportunity
to be heard. That opportunity was exercised in this case. Had Filadelfia been
served with the same set of material
as the adjudicator, it would have had the
opportunity - an opportunity I have no doubt it would have exercised - to draw
the adjudicator's
attention to the material that had been excluded from EBS5 and
EBS6. In those circumstances, it seems to me that the rationale for
the
principle of full disclosure does not apply.
- It
is true, of course, that Filadelfia was deprived of that opportunity because it
was not provided with the same set of material
as was provided to the
adjudicator. That, however, seems to me to go to the question whether Filadelfia
was afforded natural justice,
not whether Entirity owed a duty of full
disclosure. As I have said, in the special circumstances of this case, it seems
to me that
Filadelfia was not denied natural justice.
Orders
- The
court orders that:
- (1) The first
defendant be restrained from seeking or enforcing an Adjudication Certificate
under the Building and Construction Industries Security of Payment Act
1999 (NSW) in respect of an adjudication determination of Adjudicator
Sullivan dated 23 March 2010.
- (2) The
plaintiff be at liberty to withdraw the sum of $500,000 from the controlled
moneys account held by its solicitors and referred
to in paragraph 2 of the
short minutes of order made by consent by the court on 30 August 2010.
- (3) The first
defendant pay the plaintiff's costs of the proceedings.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2011/116.html