You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2011 >>
[2011] NSWSC 1128
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Gales Holdings Pty Limited v Tweed Shire Council [2011] NSWSC 1128 (21 September 2011)
Last Updated: 22 September 2011
|
Case Title:
|
Gales Holdings Pty Limited v Tweed Shire
Council
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
15,17,and 21 February 2011; 2, 3, 4, 7, 8, 9, 10,
11, 14, 15, 18 March 2011; 4, 5, 6, 7, 8 April 2011 (written subs 10 May
2011)
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
Before:
|
|
|
|
|
Decision:
|
Nuisance established - plaintiff entitled to damages
|
|
|
|
Catchwords:
|
[NUISANCE] - stormwater runoff onto plaintiff's
land - whether unreasonable interference with enjoyment of the land - land in
undeveloped
state - whether drainage inadequate and caused wetting up of the
land causing harm with consequence of invasion of protected species
of
frogs [STATUTORY DEFENCES] - whether Civil Liability Act 2002 applies -
whether defendant acted in good faith - whether defendant's conduct justified or
excused [DAMAGES] - whether mandatory injunction or whether damages an
adequate remedy
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
Clerk & Lindsell on Torts, 19th Ed. (Sweet &
Maxwell, London) Dominic Villa Annotated Civil Liability Act 2002 (NSW)
(2004, Law Book Co)
|
|
|
|
Category:
|
|
|
|
|
Parties:
|
Gales Holdings Pty Limited (Plaintiff) Tweed Shire
Council (Defendant)
|
|
|
|
Representation
|
|
|
|
|
TF Robertson SC/M Green (Plaintiff) SR
Donaldson SC/S Glascott/N Broadbent (Defendant)
|
|
|
|
- Solicitors:
|
Allens Arthur Robinson (Plaintiff) DLA Phillips
Fox (now DLA Piper) (Defendant)
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
Judgment
- The
town of Kingscliff is on the Pacific Ocean coast in northern New South Wales.
The Tweed River is to the west of the town and flows
approximately parallel to
the coast to meet the Ocean just north of the town. In the last thirty years
Kingscliff has grown from
a small beachside community to a well-developed
seaside resort. Its inhabitants include both permanent residents and
holidaymakers.
Another inhabitant of the area is the Wallum Froglet, the
endangered species Crinia tinnula , the presence of which has added
complexity to the dispute between the parties to this litigation. Since 1974 the
plaintiff, Gales
Holdings Pty Limited, has been the registered proprietor of
approximately 27 hectares of undeveloped land in Kingscliff (the Land)
that is
in the local government area of the Tweed Shire Council, the defendant.
Background
- The
plaintiff's claim against the defendant, described in detail later, is for
damages in nuisance. Although the circumstances relied
upon span more than 30
years, the nuisance alleged by the plaintiff is that since 1994 the defendant
has conducted itself so as to
cause or allow untreated and polluted stormwater
runoff to discharge directly and indirectly via the defendant's closed pipe
system,
roads, kerbs and gutters and the stormwater outlets from the local
catchments onto the Land and to prevent and obstruct stormwater
passing and
flowing away from the Land. It is not seriously in issue that since 1994 there
has been an increase in the amount of
stormwater runoff flowing onto the Land.
However the parties are at issue in relation to a number of the specific claims
the plaintiff
makes against the defendant (referred to later) and in particular
whether the presence of the stormwater runoff on the Land constitutes
a
nuisance.
- The
plaintiff claims that one of the foreseeable consequences of the increase in the
levels of stormwater runoff on the Land as a
result of the defendant's conduct
was the occurrence of ephemeral ponding of water for periods that would result
in the establishment
of a habitat suitable for Wallum Froglets with the
foreseeable further consequences that the Wallum Froglets would be attracted to
and breed in that habitat and that the plaintiff would lose that portion of the
Land for development and have to bear the burden
of maintaining a habitat for
the Wallum froglets. The expression "Wallum Froglet habitat" has been used in
differing ways in the
proceedings. It has been used to describe the physical
home or habitat of the Wallum Froglet. It has also been used to describe the
mix
of vegetation and other environmental factors, including ephemeral ponding, to
which Wallum Froglets are attracted to live and
breed.
The
Land
- The
Land is within the green boundary line in the photograph in Schedule A (Ex A) to
this judgment. Turnock Street dissects the Land
and the issues in the
proceedings have been addressed by reference to parts of the Land being either
to the north or the south of
Turnock Street. Pearl Street and Kingscliff Street
are to the east of the Land and Quigan Street is to the south of the Land.
Turnock
Street meets Elrond Drive to the west of the Land at a roundabout.
Elrond Drive runs in a north-westerly direction along the south
western corner
of the Land north of Turnock Street. The western boundary of the Land north of
Turnock Street abuts the eastern boundary
of a housing estate known as "Noble
Park Estate" (NPE). The northern boundary of NPE is relevant to what has been
referred to as
the "Northern Drain". To the north of the Land are properties
referred to in the proceedings as the "Nursing Home" or "Nursing Association"
and the "Bowls Club".
- Prior
to the 1990s the drainage of the Land and of the Kingscliff area generally was
as depicted in Schedule B (Ex B) to this judgment.
Stormwater drained from the
Land to the Tweed River via the Northern Drain, the Eastern Drain, the South
Westerly Drain, the Natural
Watercourse and the Chinderah Drain.
- The
Land is zoned 2(c) under the Tweed Local Environmental Plan 2000 (LEP 2000), the
primary objectives of which are to identify land
for urban expansion and to
ensure its optimum utilisation consistent with environmental constraints and the
need to minimise residential
landtake. The secondary objectives of LEP 2000 are
to allow associated non-residential development to ensure that sensitive
environment
areas within the Zone are protected from adverse impacts of
developments and to enable planning flexibility to achieve the other
objectives
of the Zone by means of detailed guidelines in a development control plan. One
of the objectives of LEP 2000 is to "promote
development that is consistent with
the four principles of ecologically sustainable development" identified as: the
precautionary
principle; inter-generational equity; conservation of biological
diversity and ecological integrity; and improved valuation, pricing
and
incentive mechanisms.
- The
defendant is able to grant consent to development only if it is satisfied that
it is consistent with the primary objective of
the Zone within which the
proposed development is located; if it has considered those other aims and
objectives of LEP 2000 that
are relevant to the development; and if it is
satisfied that the development would not have "an unacceptable cumulative impact
on
the community, locality or catchment that will be affected by its being
carried out or on the area of Tweed as a whole".
- The
Land was first acquired by Dr Harry Segal (a director and controlling
shareholder of the plaintiff) and his wife in 1969. It was
transferred to the
plaintiff in 1974. Dr Segal's son, Stephen Segal, has been a director of the
plaintiff since 1977 and assumed
the management of the Land from the late 1990s.
- The
Land was cleared of large vegetation in the 1970s and subsequently used for
grazing cattle until the 1990s and thereafter for
agistment of horses. During
the period from the 1970s through to the late 1990s Dr Segal walked over the
Land from time to time to
check on the cattle and/or the fences. At other times
he would observe the Land from the top of the hill south of Quigan Street from
which he could see the whole of the Land. Dr Segal was never restricted from
walking over the Land by any flooding nor did he observe
it to be overly moist,
except for one area below the Kingscliff hill on the south eastern edge of the
Land near Quigan Street.
- The
plaintiff read a number of affidavits of witnesses who had made observations of
the Land during the period from 1970 to the late
1990s. That evidence was
unchallenged. Between the 1970s and the early 1990s Peter Gray managed cattle on
the Land and accessed it
generally on horseback but also by foot, tractor and
utility. His evidence was that he never experienced vehicles being bogged nor
did he observe any inundation of water except after certain flooding events.
After a flooding event the water level always returned
to normal, meaning that
the drains on the Land were between approximately half and three quarters full,
depending on the tide. Mr
Gray observed that the vegetation was the same as the
vegetation on surrounding land. It was mostly low-lying scrubby vegetation
such
as bottlebrush and small trees.
- Between
1971 and the 1990s Verlie Moodie walked on the Land regularly to collect cow
manure for her garden and/or for leisure and
exercise. Mrs Moodie's evidence was
that the Land was a large open space with a few scattered trees. After rainfall
some of the Land
was damp and moist but it was never sludgy or drenched with
water. Mrs Moodie could not recall any occasion on which the Land was
ponded or
submerged with water.
- In
1978 Gil May travelled on an "east/west road to the main Chinderah north/south
drain". He then "went into a small boat, a duck
punt", up a drain "which went
east/west". He went up that drain "about third of a kilometre". Mr May referred
to this drain in his
evidence as the "northern east/west drain". He described it
as a natural watercourse that had been dug to make it deeper. It was
about 2 to
3 metres wide when full of water and about 1.5 to 2 metres deep in a king tide.
The banks of the drain were covered in
grass, sedge and native plants. It was
lined with mangroves near the intersection with the Chinderah Drain. The last
time Mr May
went fishing in the northern east/west drain was in 1991 when it was
in much the same condition as in 1978. The water in the drain
was at least waist
deep. There was no cross-examination of Mr May and it is probable that the
northern east/west drain that he described
in his evidence is the Northern
Drain.
- Mr
May observed acacias on the north eastern side of Lots 11, 12 and 13 of the
Land. There was a wet patch in Lot 12 north of where
Turnock Street was later
constructed in which Mr May observed that there was a two to three metre section
with a sandy bottom where
the water would go up to "just below your knees". Mr
May observed that it was a natural depression and was grazed by cattle with
clusters of small trees and patches of sedge.
- Catherine
Boyd who has lived in Pearl Street, Kingscliff since the 1950s gave evidence of
observing cattle grazing on the Land from
the 1970s to the 1990s. Mrs Boyd
walked over the Land during that period on a weekly basis for "leisure". Mrs
Boyd did not observe
any parts of the Land being "wet, flooded or submerged".
She observed wallabies and kangaroos and "lots of" small trees. Mrs Boyd
also
gave evidence that about once a year, the local fire brigade would practice
their fire management skills on the Land.
- Reginald
Goodwin worked on the Land in 1990 and 1991 spraying herbicide on groundshell
bush in Lot 10. Mr Goodwin brought a tractor
and spraying equipment (that
together weighed approximately 6 tonne) in the back of an 11 tonne tip truck
which he drove through
the Land. He then unloaded the tractor, completed the
spraying and loaded the tractor back onto the truck and drove back through
the
Land. Mr Goodwin said that the ground was "rock solid" and he never had any
trouble with the truck or the tractor becoming bogged.
At this time he observed
approximately 30 horses on the Land.
- After
the construction of Turnock Street in 1997 Mr Goodwin returned to the Land and
began "slashing" the Land both north and south
of Turnock Street. He slashed the
Land at least once a year. Since the construction of Turnock Street the tractor
"got bogged continuously".
Mr Goodwin had to use two tractors, "one tractor to
pull the other tractor out", because the Land is "so soggy now". Mr Goodwin
noticed
that after the construction of Turnock Street the vegetation in Lots 11,
12 and 13 of the Land had become thicker with "more reedy
types of grass".
Early drainage problems
- On
31 July 1974 Dr Segal wrote to the defendant advising that he felt that the
defendant must accept responsibility for the large
drains which "open directly"
onto the Land that were "causing severe localised drainage problems".
- On
4 August 1974 Les Noble of Les Noble Pty Limited, Auctioneers, Real Estate
Agents and Valuers, owner of the adjoining property
to the west of the Land,
wrote to Dr Segal in the following terms:
The so-called swamp on your property, which is at the back of our property,
is only brought about by the fact that the now existing
drains in the property
have never been cleaned out for the past twenty years and if you feel like doing
that, also in the new part,
it would improve it immensely.
- On
27 August 1974 the defendant wrote to Dr Segal in response to his letter of 31
July 1974 and advised that the defendant did not
"at present" have sufficient
funds to consider drainage through the Land. That letter included the following:
Whilst it is accepted that drainage from Kingscliff streets discharges onto
the property, the area, of course, is a natural water
course or collection area.
The matter may be further considered when development proposals in the areas are
considered.
- On
5 November 1974 Mr Noble wrote to Dr Segal advising him of his recent
discussions with some drainage contractors and suggested
that Dr Segal spend up
to $600 on drainage. On 3 December 1974 Mr Noble advised Dr Segal that he had
engaged the drainage contractor
and that when the work was completed "you will
be looking at a different property". Dr Segal gave affidavit evidence that he
did
not understand why it was that Mr Noble used the expression "swamp" in his
correspondence to describe the Land.
Proposal to develop the
Land - 1978
- In
1978 the plaintiff submitted a proposal to develop the Land. The defendant
advised the plaintiff that detailed flood and environmental
studies would have
to be completed. The plaintiff offered to contribute to the cost of the flood
studies, however in December 1978
the defendant advised the plaintiff that funds
had been allocated for such studies and it would not be necessary for the
plaintiff
to contribute to the cost of them.
Growth Plan
- In
1980 the plaintiff instructed Burchill & Partners Pty Limited, Consulting
Engineers and Planners, to provide a report in respect
of a proposed "Growth
Plan" for Kingscliff. That proposal was to develop not only the Land but also Mr
Noble's property. The report
noted that the Land was subject to "inundation in
the 1:100 flood in the Tweed River System, to a depth of average 2.0 metres" and
that up to that time it had been omitted from planning for new development for
that reason. The report included the following:
If a practical and economically viable method can be found of overcoming the
flood factor, by filling and draining, then the land
would be available to serve
the desired use as the preferred future development zone for Kingscliff.
- The
report also noted that the combined area of the properties was approximately 75
hectares, about one half the area of the then
existing township. It also noted
the demographic phenomenon of increasing migration from major cities to
provincial coastal towns
with the most desirable climates and environments and
it was suggested that Kingscliff would attract an overspill of the growth
element
in the Gold Coast. The report also noted that there was too little
existing stock and it was essential to stimulate new development
rather
urgently. The report made reference to the Draft Tweed Coast Plan and included
the following:
The Draft Tweed Coast Plan showed that there were no flora and fauna species
on our clients' lands which require or warrant protection.
- The
Burchill & Partners report was submitted to the defendant. The defendant
advised the plaintiff that it had considered the
proposal for the Growth Plan at
its meeting on 17 December 1980 and had resolved to prepare a draft Local
Environmental Plan. It
also advised that a detailed report was required on the
effect of excavating and filling the flood plain and that an environmental
assessment needed to be made of the impact of the proposed artificial lakes that
formed part of the Growth Plan.
- On
12 March 1981 the defendant advised the plaintiff that it was necessary for the
Growth Plan to demonstrate how flooding would be
overcome "including the
determination of pumping or other facilities necessary to remove local
stormwater from within the protected
area" and to identify the drainage paths of
existing Kingscliff urban development and the effect of the proposed works on
such existing
usage. It is not clear to what the expression "protected area"
referred but it was not suggested that it has any significance to
the issues in
this litigation. The plaintiff met with the defendant during 1981 and was
advised more than once that "not a grain
of sand can be moved until drainage
studies are done and these drainage studies permit filling to occur".
- Between
the early 1980s and the early 1990s the Land was not developed nor was the
Growth Plan adopted. However it is apparent that
the defendant worked on
developing a draft Development Control Plan.
Cessation of
cattle grazing
- Some
time in the 1990s the plaintiff discontinued grazing cattle on the Land because
of reports of the presence of a pack of dogs
that were killing newborn calves.
There were also reports of vandalism on the Land. Subsequently the plaintiff
made a decision to
permit the agistment of horses on the Land.
Development Consent to NPE - December 1992
- On
9 December 1992 a Development Consent was issued to Baclon Pty Ltd (Baclon) for
the development of Mr Noble's land to the west
of the Land into the NPE. The
proposed development included the construction of a lake to the west of NPE and
west of Elrond Drive.
The Eastern Drain (on the boundary between the NPE and the
Land) was to be filled in and a batter wall was to be created onto the
western
boundary of the Land.
- The
conditions to the Development Consent included the following:
36. The proposed subdivision is to be filled to RL 3.5m AHD in accordance
with the approved plans.
...
40. The Engineer Drainage Design plans shall address the 5 year discharge
from the ultimate fully developed upstream contributing
catchment and any
foreshadowed development in upstream catchment which will contribute to the
runoff through this development.
...
43. A drainage overflow path to accommodate Q 100 flows shall be retained
along the northern boundary of the land until such time
as the drainage strategy
is resolved. Details to be shown on the engineering plans.
- The
drainage overflow path along the northern boundary referred to in condition 43
to the Development Consent was necessary because
one of the streets in the NPE,
Lorien Way, was to be extended across the Northern Drain.
Murray vegetation mapping -1992
- In
June 1992 Andrew Murray, a botanist and vegetation ecologist, surveyed the Land
as part of a comprehensive fine scale vegetation
mapping project for coastal
lands in the Tweed Shire. Mr Murray observed "shallow standing water" over a
large part of the Land at
this time.
DCP 9 - 1993
- The
Tweed Development Control Plan No 9 (DCP 9) (which applies to the Land) came
into force on 7 October 1993. Its purpose is, inter alia , to provide
detailed guidance to developers within the area and to indicate the defendant's
policies with respect to development
in the area. Matters pertinent to this
litigation in DCP 9 include: (1) A water quality report and water quality
monitoring program
is required for all applications for filling and subdivision;
(2) Filling of land for residential development is to be 3.4m AHD;
and (3)
Applications for filling are to include information demonstrating that fill will
have no adverse effects on flooding or drainage
characteristics of nearby land.
DCP 9 also includes a section entitled "E. Drainage & Water Quality
Management", the objectives
of which include the prevention of "flooding and
stormwater damage to the built and natural environment". It is noted in the DCP
that subdivision applications will be refused unless it is "proved that the land
is capable of development without adverse effects
on flooding or drainage
elsewhere".
1994 complaints
- Baclon's
consulting engineers for the NPE development were Martin Findlater &
Associates Pty Ltd. On 15 March 1994 Mr Henley of
the defendant met Mr Findlater
to inspect the work at NPE. In a note made of that meeting on 17 March 1994 Mr
Henley wrote:
I am not very happy with the connection from the end of new works to the old
drain. I have agreed with Martin Findlater outflow improvements
may be able to
await the moving of machinery on site for next stage. Either the outlet drain is
to be widened or the overland flow
path is to be cleared and levelled. This
could be considered as part of maintenance but I advised Martin that if we have
any problems
I will require that he immediately complete improvements to the
outflow channel.
- On
21 April 1994 the consulting engineer for the Bowls Club, Ian Hill of Ian Hill
& Associates Pty Limited, wrote to the defendant
advising that he acted for
both the Bowls Club and the Nursing Association and that he had recently
inspected the rear of properties
north of NPE. The letter included the
following:
The temporary diversion drain, that was constructed around the subdivision at
the time of the lake construction contract, has been
filled in as has also the
union drain that followed the east-west boundary within the Noble Park property.
A recent inspection revealed that water is ponding along this latter boundary
line, and little cognisance appears to have been taken
of the upstream catchment
of Pearl Street, Kingscliff Street, the land between these streets and the
subdivision.
- Mr
Hill advised that he had spoken with Mr Findlater and requested the engineering
drawings so that he could make an assessment of
the position. On 27 April 1994
the defendant wrote to Mr Hill and requested that he liaise with Mr Findlater in
relation to the resolution
of any future problems.
- On
17 June 1994 Mr Hill wrote again to the defendant advising that he had completed
the investigation of the drainage at the rear
of the properties and reported as
follows:
We do not believe that it is this firm's responsibility to resolve the
problem as the works associated with the subdivision, which
clearly prejudice
our Client, were approved and supervised by Council.
You are aware that Council's drainage, from Kingscliff and Pearl Streets,
discharge onto the Club property and this was extended at
the Club's cost, with
no assistance from Council, across the property to the open drain that ran along
the northern boundary of Baclon
Pty Ltd property to the Kingscliff union drain.
This drain is shown as lateral Drain B in the draft report on Kingscliff
Drainage
Strategy prepared by WBM Oceanics Pty Ltd and, with Council's
permission, has been filled in by Baclon Pty Ltd.
We would appreciate advice as to what remedial action will be implemented
before the start of the next wet season.
Warren Report - 1994
- In
mid 1994 the plaintiff had applied to the defendant for approval for clearing
operations to be carried out on the Land in areas
that were covered by a Tree
Preservation Order. In June 1994 James Warren, a biological and environmental
consultant, provided a
report to the plaintiff entitled " Flora and Fauna
(Section 4A) Assessment ". An assessment under s 4A of the Environmental
Planning and Assessment Act 1979 (NSW) (the EPA Act) determines whether a
development will have a significant impact on endangered fauna or their habitat.
Mr Warren
noted that the Land was still being utilised for horse and/or cattle
grazing purposes and he identified a Paperbark forest and a
"clump of Wallum
bottlebrush" in the southern portion of the Land. Mr Warren referred to a
computer check on the local records that
had been carried out by the National
Parks & Wildlife Service (NPWS) that had identified significant threatened
species recorded
in the locality. He observed that a number of endangered
species "might also be expected to occur in the locality". Although there
was
mention of the Wallum tree frog ( Litoria olongburensis ), there was no
mention of the Wallum Froglet. That survey included the following:
The sites, due to their highly disturbed nature are likely to contain high
numbers of Cane toads. These amphibians displace native
frogs and are even
thought to feed on small native frogs. It is possible, though unlikely, that the
site contains Wallum frogs. If
the frogs occur it is most likely that they would
occur in the perennially wet areas associated with the Paperbark forests.
- The
Wallum Froglet is a "vulnerable species" under the Threatened Species
Conservation Act 1995. It first attained a protected status in 1992 when it
was listed as a "Vulnerable and Rare Species" in Schedule 12 of the National
Parks and Wildlife Act 1974. If a proposed development would significantly
affect a threatened species, the EPA Act requires a species impact statement to
be
prepared before the application may be considered. The impact of the
development on the threatened species must be assessed when
determining the
development application. It is an offence under section 118A of the National
Parks and Wildlife Act for a person to harm any "threatened species" (which
includes a "vulnerable species").
WBM Oceanic - 1994
- On
10 August 1994 WBM Oceanic Australia (WBM), commissioned by the defendant,
produced the "Kingscliff Drainage Strategy Plan" (Ex
O) (the WBM Report). The
WBM Report documented the development of the drainage strategy for major
flooding of the Kingscliff area.
It recorded that the need for the Plan had
arisen "due to the degree of urbanisation and filling planned for the
catchment". Figure
1.1 of the Plan entitled "Kingscliff Drainage Catchment"
showed a "Catchment Boundary" that is also depicted in Schedule A to this
judgment by the yellow boundary line. WBM reported that the development of a
"stormwater drainage strategy plan for the Kingscliff
drain" in Figure 1.1 was
in accordance with the Development Control Plan No. 9 (DCP 9) for the West
Kingscliff area.
Ian Hill & Associates Report
- On
14 September 1994 Mr Hill provided the defendant with a copy of a report
prepared by his firm entitled "Drainage of Kingscliff
Street Site". That report
included the following:
3.0 DRAINAGE PATTERNS - 1993
During 1993, the subdivision known as Noble Park Estate was constructed; part
of construction involved filling of the site by some
2 m, during which the open
drain was filled in and the filling extended across into the Club's land without
any further discussions
with the Club and without the Club's approval.
At a brief inspection of the Bowls Club site, in February 1994, Mr Hill of
this office noted that the drainage path was blocked by
filling, including the
filling for a roadway from the adjacent Middle Harbour development.
Mr Hill rang the Tweed Council and spoke to Mr John Samuels, voicing concern
that no provision had been made for drainage of the land
to the north and east
of the Baclon development, and was advised that the blockage was only temporary.
An inspection in March 1994, showed that the subdivision filling had been
completed; no allowance was made under the roadway for escape
of stormwater, and
a 1200mm dia concrete pipe had been provided at the corner of the Bowls Club
property, which was supposed to carry
the stormwater to the west and north of
the subdivision.
- The
report concluded that the 1200mm height was "under capacity" for the Q5 event
(being a storm event of a magnitude that occurs
on average once every five
years) and no provision had been made for the Q100 event; that the design
ignored the defendant's drainage
strategy for Kingscliff; that the installed
drainage system had not been constructed as designed, further reducing the
capacity of
the system to cater for stormwater runoff; and that as a result, the
properties of the Bowls Club and Nursing Association would be
subject to a
greater degree of flooding than would have occurred prior to the construction of
NPE.
- After
the defendant received the report from Mr Hill and a further letter from the
lawyers for the Bowls Club it wrote to Martin Findlater
on 31 October 1994
expressing its concerns regarding the Q5 hydraulic capacity of the 1200 diameter
pipe and the resulting potential
for flooding of adjoining property owned by the
Kingscliff Bowls Club. The defendant referred to the WBM Report that indicated a
catchment larger than that adopted by Mr Findlater in his design and suggested
that this "discrepancy should be clarified".
- On
2 February 1995 the defendant wrote to Mr Hill advising him that it had recently
held discussions with Mr Findlater "in an attempt
to formulate a solution to the
problem". The defendant advised that as a result of the meeting it was agreed
that Mr Findlater would
"submit a number of options" for the defendant's
consideration, which it was still awaiting.
Retention Basin Proposal - March 1995
- At
this stage Baclon was seeking approval for the fourth stage of the NPE
development from the defendant. On 1 March 1995 the defendant
advised Mr
Findlater that no further approvals or consents would be given "until the
drainage solution and its funding is agreed
upon". That letter included the
following:
Given that your original stormwater design did not adequately cater for the
Q100 storm event and that Council has no funds for such
analysis at this stage,
it is intended that Council initiate the analysis at the consultants cost.
- On
2 March 1995 the defendant wrote to Mr Findlater in terms that included the
following:
The Panel also resolved that any fresh development application will not be
determined until the upstream drainage issues are resolved
because the approved
Part 12 application causes inundation of properties in excess of permissible
levels.
- On
9 March 1995 Mr Findlater wrote to the defendant referring to verbal advice from
the defendant on 8 March 1995 that permission
to complete the drainage work
through NPE Stage Four would be approved upon the condition that Baclon Pty Ltd
requested the defendant
to amend DCP 9 and the Section 94 Plan for West
Kingscliff. That letter included the following:
In accordance with your instructions we suggest the DCP 9 be amended as
follows:
A nominal area of 1 Ha for future multi-purpose open space/flood
retention/wet land filter should be reserved east of Noble Park estate.
The
value of the land shall be incorporated into the drainage and S94 Plan and
reimbursed from that plan. Any open space component shall be credited against
the passive or active open space requirements
for development in the area as
appropriate to the use of the land.
Our client is offering this suggestion as an alternative to the proposed 20m
wide open channel adjacent to the northern boundary of
Noble Park estate. That
proposal formed part of WBM Oceanics Kingscliff Drainage Strategy Plan report
dated August 1994. Calculations
demonstrating the feasibility of the alternative
have been supplied to Mr Henley.
- Although
Mr Findlater did not expressly refer to it, the proposal to put aside an area of
one hectare east of NPE was really a suggestion
that the Land be used as a
retention basin.
- On
10 March 1995 Mr Findlater wrote to the defendant in answer to its letter of 1
March 1995 refuting the assertion that the original
stormwater drainage design
did not adequately cater for the Q100 storm event. That letter included the
following:
The drainage for the estate was designed and constructed in accordance with
Council's Development Consent for the estate. This is
confirmed by the approval
of the layout plan, the engineering drawings and the release of the linen plan
of subdivision.
Council has now developed a drainage strategy for Kingscliff which is
reported by Council's consultant WBM Oceanics. That drainage
strategy (dated
August 1994) incorporates specific water level controls which were not required
under the consent and are a consequence
of the study.
To achieve those controls the strategy provides for an open drain at least
20m wide adjacent to our clients northern boundary. Our
client is concerned
about the practicality of such a drainage ditch. He is also concerned that piped
alternatives are expensive and
would unnecessarily increase Section 94
Contributions.
We have provided objective alternatives to the drainage strategy and
identified corrections that should be made to the model. This
work has been
carried out at no cost to Council. We are disappointed that Council should
consider our comments as an implication
that Noble Park drainage is deficient.
Our client has been required to supply work in kind to the value of $586,000.
This is for a S94 liability for approved development of less than $200,000. Our
client does not intend to provide additional funding other than what
is required
as a result of reasonable variations to the S94 Plan. Such variations can be
adjusted in credits due.
We also confirm that we shall not be contributing to any additional analysis
by Council to determine alternatives to their drainage
study. We understand from
discussions with Mr J. Henley that this will not be required.
- On
13 March 1995 the Manager Subdivisions of the defendant wrote to the Director
Development Services of the defendant in terms that
included the following:
As you will recall, following completion of the early stages of Noble Park
Estate it became apparent that a drainage problem existed
in relation to the
existing developed land upstream of the estate.
Following rainfall, complaints were received from residents; Ian Hill on
behalf of the Blue Nursing Service and the Bowls Club in
relation to inundation
of their properties.
Investigations and discussions between Council officers and Martin Findlater,
(consultant for Noble Park) have been continuing for
some months, however as the
matter had not been resolved, no further consents/releases have been issued for
West Kingscliff for about
3 months.
Following further discussions on 7 March 1993 between John Henley, Col Dutton
and Martin Findlater, a possible solution was agreed
to in principle.
That concept involves:
1. A detention basin in Dr Segals land adjacent to Noble Park Estate;
2. Possible "joint use" of the basin as a water quality control pond;
3. Possible "joint use" of the basin/pond for recreation purposes (ie.
passive open space).
To allow for this concept to be formally considered the following approach
has been agreed:
1. Martin Findlater will make a formal request to amend Development Control
Plan No. 9 and the Section 94 plan (if necessary) to facilitate the proposal;
2. The written approval of Dr Segal, will accompany this request;
There is a high degree of urgency in finalising the Development Control Plan
amendments having regard to the interests of Council
and the community and
therefore it is recommended that processing of the matter be given a high
priority.
- On
15 March 1995 the Strategic Town Planner of the defendant wrote to the Director
Development Services of the defendant in terms
that included the following:
The land on which the detention basin is proposed is nominated for medium
density housing in the DCP and I think it is highly unlikely
that Gales Holdings
would agree to its use for any other purpose.
...
I am concerned that a 'quick fix' of the current drainage problem may have
implications for drainage and development in the rest of
West Kingscliff which
has not been evaluated.
- On
23 March 1995 the defendant wrote to the plaintiff in the following terms:
DCP No. 9 - West Kingscliff
Following preparation of the Kingscliff Drainage Strategy Plan and
investigation of drainage issues it is proposed to recommend to
Council that the
above DCP be amended as follows:
1. To allow for the provision of a stormwater detention basin of about 1 ha
within land owned by Gales Holdings Pty Limited adjacent
to Noble Park Estate,
generally as indicated on the attached map;
2. To enable the possible "joint use" of the basin as a water quality control
pond and passive recreation area.
- The
plaintiff had retained town planners, Outline Planning Consultants Pty Limited
of which Mr Gary Peacock was a director, to assist
it with reviewing DCP 9. On 5
May 1995 the defendant wrote to Mr Peacock advising that it wished to work
closely with him in reviewing
DCP 9. The defendant conceded that DCP 9 required
significant review and accepted that Mr Peacock's proposal that a steering
committee
or working group be established was a positive and sound approach and
that he would be invited to participate in such committee or
group. Mr Peacock
met with the defendant's officers on 30 May 1995 in relation to the roads and
drainage infrastructure needs of
the West Kingscliff area and their likely
impact on the Land. On 22 June 1995 the Council wrote to Mr Peacock advising
that it may
be possible to reduce the area of the Land affected particularly in
relation to drainage and water quality needs. The defendant advised
that it
could only make an assessment if it had "full knowledge of the future plans"
that the plaintiff had for the Land.
- The
plaintiff, through Outline Planning Consultants, also retained Ray Sargent, a
Civil and Structural Engineer, to assist it with
assessing the defendant's
proposal for the retention basin to be situated on the Land. Mr Sargent met with
an officer of the defendant,
John Henley, an engineer, in September 1995 and
undertook a detailed inspection of the Land for the purposes of assessing the
drainage
aspects of the Land.
DCP 9 to be amended
- On
27 September 1995 the defendant resolved to prepare an amendment to DCP 9 and
Contribution Plan No 7 relating to West Kingscliff.
In a Council report in
support of the resolution it was noted that it had become apparent after the
completion of the early stages
of NPE that a drainage problem existed in
relation to developed land upstream of NPE. It was noted that "a possible
solution" involved
the construction of a detention basin on the Land and that
Baclon had no objection to the proposal. That is hardly surprising having
regard
to the fact that the proposal imposed all the burden on the plaintiff for the
drainage problems created by Baclon's development.
The report concluded that the
way in which to resolve the drainage problem promptly was to prepare and exhibit
amendments to DCP
9 and to make further efforts to obtain the plaintiff's views
during the exhibition period.
- An
internal memorandum of the defendant dated 1 November 1995 records that any
further action on the detention basin was to be held
in abeyance. It was noted
that the plaintiff was "now aware" of the need for a detention basin and the DCP
9 amendment process could
be delayed provided that everyone remained aware of
the location of the proposed detention basin. It was also noted that if the
plaintiff
sold the Land there was no mechanism for ensuring that any future
owner was aware that one hectare of land should not be filled and
should remain
available for drainage retardation.
- On
2 November 1995 Mr Hill, who by that stage had moved to another firm, Cardno
& Davies, wrote to the defendant noting that he
had heard nothing in the
nine months since he had been advised that the defendant was seeking a number of
options from Mr Findlater
towards solving the drainage problems. The defendant
responded by letter dated 18 December 1995 advising that "agreement has been
reached" with Mr Findlater "for the creation of a stormwater/flood retention
basin adjacent to the culvert in question". There was
no mention of the fact
that the proposed retention basin was on the Land rather than on NPE. Nor was
there any mention of the fact
that the plaintiff had not agreed to the retention
basin.
- Mr
Peacock had been communicating with the defendant in October 1995 in relation to
the proposed amendment to DCP 9. On 23 November
1995 the defendant wrote to Mr
Peacock advising that there would be no immediate action to proceed with the
draft amendment to DCP
9 and observing that as the plaintiff was now "formally
aware" of the need for a retention basin it would be necessary to obtain
a
formal assurance that a prospective purchaser of the Land would be notified that
one hectare of the Land should not be filled and
had to remain available for
drainage retardation. There is no evidence that the request for such a "formal
assurance" was ever pursued
further or given.
Plans for Turnock Street
- It
was in late 1995 that the defendant proposed constructing a distributor road
that was later to become Turnock Street. It was agreed
between the parties that
the defendant would make a direct purchase of a portion of the Land at an agreed
valuation or provide a
credit against future contributions levied against
development on the Land under the EPA Act. The defendant had to comply with
section
111 of the EPA Act and consider whether the construction of Turnock
Street would require an environmental impact statement (EIS)
under section 112
of the EPA Act and what other impacts it would have on the environment. The
defendant advised the plaintiff that
it wished to proceed with an environmental
assessment of the proposed activity and requested from Mr Peacock the results of
any studies
previously undertaken on the site. In late December 1995 the
plaintiff provided its consent to the defendant to enter the Land for
the
purpose of carrying out site survey work associated with the proposed road.
- Mr
Peacock provided a copy of Mr Warren's June 1994 report to the defendant to
assist it with its assessment of the Turnock Street
extension. In March 1996
Woodward-Clyde, consulting engineers, put a proposal to the defendant to carry
out flora and fauna assessments
of the Land including the carrying out of an
amphibian survey utilising "call recording and analysis". Woodward-Clyde advised
that
the call analysis was to be undertaken by an officer of the Queensland
Museum and that the frog survey could be most effectively
carried out between
August and March during rainfall to ensure maximum species identification.
Woodward-Clyde Report - May 1996
- In
May 1996 Woodward-Clyde produced their report entitled "Flora and Fauna
Assessment of a Proposed Road Deviation". The report referred
to NPWS records
that indicated that certain threatened faunal species could occur either on the
site or nearby at various times including
both the Wallum Froglet and the Wallum
tree frog. The report recorded that sampling efforts had attempted to detect the
widest possible
range of species utilising a range of methods including call
identification, direct observation, Pitfall traps (buckets and drift
fences) and
Elliott traps. The report included the following:
Neither the Wallum froglet nor Wallum treefrog were recorded during site
surveys. Gilmore et al (1986) indicates that both species are
particularly sensitive to the alteration of water chemistry and are found only
in oligotrophic
waters. However, WWC (1995) have recorded the Wallum froglet in
a piggery effluent drain suggesting that it is perhaps more adaptable
than
previously thought. The Wallum froglet was considered most likely to occur along
the drain to the south of the roundabout where
a number of other frogs were
recorded.
- Appendix
3 to the Woodward-Clyde report noted that the Wallum Froglet was not recorded
during site surveys but that it "may be present"
in a drain south of the study
area. Appendix 3 also recorded that the effect of the development on the life
cycle of the Wallum Froglet
was minor in respect of breeding and foraging and
there was a nil effect on the migration/movements of the Wallum Froglet.
- On
29 July 1996 Ray Sargent & Associates (at this time retained by the
defendant) wrote to the defendant enclosing a number of
plans showing the "major
drainage outlet points for the Turnock Street/Elrond Drive area". Those
documents illustrated the situation
after the construction of the roadworks "and
future site filling works". That letter included the following:
(1) After construction of the deviation road, the low lying areas to the
north of the road will drain through outlet 2. This outlet
is to be sized to
drain the selected design storm over the catchment without causing flooding to
existing developed areas. The catchment
area is the total of the areas marked A,
B, C, D & E (41.64ha).
(2) Area E will ultimately drain to the future open drain and outlet labelled
7 as per DCP No. 9. As the embankment of Lorien Way
currently blocks this path,
Catchment E needs to be temporarily drained through outlet 2 until the outlet at
7 is opened.
...
(6) Outlet 2 would become redundant if the ultimate scheme is implemented as
shown. The design of outlet 2 is indicated on the attached
Sketch SK1 and has
been based on limiting headwater to a level of 2.1m AHD to avoid flooding of the
existing surface level of the
proposed Bowling Club for the design event. To
compare the culvert sizes detailed below are culvert sizes for 1:100, 1:20 and
1:5
year events:
1:100 3 x 1500 dia
1:20 3 x 1200 dia
1:5 2 x 1050 dia
...
Please advise if the above scheme is acceptable to Council so that the
drainage design for the proposed roadworks can be finalised.
- The
plan attached to the letter, "SK 1", referred to the total catchment area north
of Turnock Street as 41.64ha and recorded that
three 1500 millimetre pipes would
be at point 2 on SK 1. Point 2 on SK 1 is in the area that the Elrond Drive
culvert (referred to
later) was constructed. The three pipes as suggested in SK
1 were not constructed in that location. The plaintiff submitted that
despite
the fact that the defendant knew that the Elrond Drive culvert had a catchment
area of 41.64ha and required three 1500 millimetre
pipes to pass water under
that culvert to drain that area, it did not provide three pipes to do so (tr
142).
- On
9 August 1996 Ray Sargent & Associates (at this stage retained by the
plaintiff) produced a report entitled " Proposed Stormwater Quality
Improvement Scheme for West Kingscliff, Tweed Shire" . That report proposed
that a "first flush runoff system" be instituted to catch the first flush of
runoff from the catchment and
retain it in ponds for a sufficient time for the
water quality to be improved prior to discharge. The report concluded that the
treatment
of stormwater runoff in this way would improve the quality of the
final downstream water outflow by up to 50%. It also included the
following:
This will be a significant improvement on the existing drainage system which
contains no formal structures for removing contaminates
from runoff apart from
sedimentation action within the main drains.
- On
23 August 1996 the plaintiff provided its consent to the defendant's development
application for the proposed Turnock Street extension.
Follow up of 1994 complaints
- On
3 September 1996 Mr Hill resumed communications with the defendant in relation
to the problems that he had identified with the
1200mm pipe where the Northern
Drain was previously located. He wrote to the defendant on that date advising
that he had not had
any further information as to the location, sizing or time
of construction of the proposed retention basin referred to in the defendant's
letter to him of 18 December 1995. Mr Hill advised that a recent inspection
showed the inlet to the 1200mm pipe to be restricted
by weed growth. He also
suggested that with the approach of the wet season his clients (the Bowls Club
and the Nursing Home) were
concerned that nothing appeared to be happening
notwithstanding that concern was initially expressed in April 1994. Mr Hill
asked
for advice as to the present status of any remedial work.
- An
internal report from the defendant's Director of Engineering Services presented
to the Council meeting of the defendant on 18 September
1996 included the
following:
Gales Holdings Pty Ltd
Gales Holdings Pty Ltd are represented by Mr Gary Peacock of Outline Planning
Consultants. Mr Peacock has advised that the owners
have no urgency to develop
this site. This lack of urgency is certainly reflected in the difficulties and
time involved in negotiating
a purchase.
Agreement was reached with Mr Peacock in February 1996 to have independent
valuations undertaken, to be exchanged on completion. However,
on completion of
Council's valuation Mr Peacock advised that his client had instructed him that
Council's valuation would be required
before any further action would be
considered.
- In
September 1996 the Bowls Club's solicitor wrote to the defendant requesting
information as to whether there was any likelihood
of a reasonable engineering
resolution of the matters raised by the Bowls Club in relation to the 1200mm
pipe.
- On
11 November 1996 the defendant wrote to Mr Hill in the following terms:
With reference to your letter of 3 September 1996, I wish to confirm that
until filling of the Gales Holdings land proceeds there
should be adequate
retention area available to satisfy flood drainage in accordance with
investigations and calculations by Martin
Findlater & Associates.
Prior to any development of the Gales Holdings land the trunk drainage system
will have to be resolved and the need for a retention
basin at this locality is
being addressed in this plan.
- On
12 November 1996 the defendant wrote to the Bowls Club's solicitors in terms
that included the following:
While the Gales Holding land remains at its present level there should be
adequate retention area available to satisfy flood damage
in accordance with the
investigations and calculations by Martin Findlater and Associates.
Prior to any development of the Gales Holding land the trunk drainage system
will have to be resolved and the retention needs in this
locality are being
addressed in that scheme. Council is fully aware of the drainage needs in this
locality. Final resolution of details
cannot be predicted at this time as they
are largely related to actions by Gales Holdings.
- The
irresistible inference from this correspondence is that the defendant had
concluded that until it was filled, the Land would be
used as a "retention area"
for flood drainage.
- On
24 March 1997 the plaintiff wrote to the defendant enclosing a signed consent
form in respect of the permission for the defendant
to enter upon the Land for
the purpose of constructing Turnock Street. That letter included the following:
"Please note that we will
need fencing to be erected to ensure that the cattle
we run on the property do not escape".
Turnock Street completed
- On
Tuesday, 9 December 1997 Turnock Street was officially opened.
Proposed application to fill the Land
- In
March 1998 the plaintiff was considering obtaining development consent for the
filling of the Land. A memorandum from Mr Peacock
to the plaintiff dated 30
March 1998 included the following:
As Mayor Boyd indicated, you will need to obtain in the first instance
Development Consent for the filling of your land.
With this consent in hand, it will then be possible to make separate
applications for various forms of development over your land
eg. retail,
commercial, townhouses, residential flat buildings etc.
Obtaining this consent will then remove any uncertainties over what land can
and cannot be developed.
- That
advice included reference to steps that needed to be taken prior to the
plaintiff being in a position to lodge a development
application for filling the
Land including the development of a Master Plan for West Kingscliff and a Master
Drainage Plan. Mr Peacock
sought the plaintiff's approval for the engagement of
the services of Bill Knobel, a consulting engineer and principal of Knobel
Consulting Pty Ltd (Knobel), to assist with monitoring the work of the
development of a Master Drainage Study for West Kingscliff
and any follow up
engineering work, for example landfill, road design, services provision and
drainage.
Funding of $21,156 for further studies
- On
12 June 1998 the plaintiff agreed to provide funding of $21,156 to the defendant
out of a total budget of $25,100 for the preparation
of a drainage/water quality
study by WBM Oceanic. The plaintiff drew the defendant's attention to its
previous undertakings to notify
the plaintiff how the proposed drainage system
(including the retention basin) would work and that it had not done so. The
plaintiff
also drew the defendant's attention to the fact that a final decision
on the stormwater scheme for the area was still outstanding.
- On
21 July 1998 Knobel wrote to WBM Oceanics referring to a site meeting in
relation to the West Kingscliff master drainage strategy.
Knobel confirmed their
concerns regarding drainage at the northern end of the Land adjacent to the
Nursing Home and the Bowls Club.
That letter included the following:
It would appear from closer inspection that the local drainage ponds behind
the new residential development and has no outlet or Q100
overland flow through
the adjacent subdivision.
We will be addressing this matter further with Council.
We also request that you examine the requirements for drainage under Elrond
Drive and Turnock Street. Major construction has recently
been undertaken and
the Tweed Shire Council would have the construction records and how any drainage
structures relate to your previous
study.
- The
records of WBM Oceanics record a communication with Mr Knobel in which he
expressed his concern about the drain behind the Nursing
Home and the Bowls
Club. Those records also include a record of a phone call to Mr Henley of the
defendant which noted that the drain
was "a purely hydraulic problem" and that
WBM did not need to consider it in their study. WBM records also include a note
of a telephone
call with Patrick Knight of the defendant on 30 July 1998 that
includes the following:
He asked about including the problem drain at the back of the Bowls Club land
into the study. I paid an extra $4 to $5000 but told
him John Henley had advised
to leave this drain alone as it has been the subject of previous investigations
& further investigations
were not required.
- The
WBM Oceanics records for 31 July 1998 include notes in relation to a phone call
from Mr Knobel as follows:
Problem drain actually has a low flow pipe taking water under filled site
& directly to main channel.
Box culverts in place to provide for flow under road (we didn't see them on
initial visit with Bill as they were under weeds).
- On
3 August 1998 a meeting took place attended by Mr Henley of the defendant,
Messrs Peacock and Knobel on the plaintiff's behalf,
and representatives of WBM
Oceanics. Mr Peacock and Mr Knobel suggested that the defendant reduce the size
of the proposed drainage
through the Land from 50 metres to 20 metres. It was
noted that WBM Oceanics would look in more detail at the land near the Bowls
Club and that the plaintiff wished to submit a Development Application for
landfill immediately after WBM Oceanics study was completed.
- On
10 February 1999 the defendant advised Mr Peacock that the Water Quality
Management Study for West Kingscliff was "essentially
completed" and provided
the basis for more detailed discussions on planning for the Land.
Turf farm litigation
- In
the late 1990s, probably in 1998/1999, the plaintiff commenced legal proceedings
against the defendant to prevent it from proceeding
with a turf farm proposal to
spread bio solids from a sewerage treatment plant on an area of land adjacent to
other land in the area
owned by the plaintiff. The plaintiff was successful
against the defendant in those proceedings (tr 357).
Wallum Froglet identified
- On
7 May 1999 Mr Warren (retained in 1998 by Outline Planning Consultants Pty Ltd
on behalf of the plaintiff to undertake a preliminary
flora and fauna assessment
of the Land including searches for significant fauna habitats) produced a report
in relation to his observations
and findings from a survey carried out in July
1998. That report included the following:
A single Wallum froglet was heard calling from flooded grassland in the south
east of the southern property. Warren (1993) considered
the Wallum froglet a
possible occurrence in the locality. WWC (1996) failed to record this species
but considered it a possible occurrence
along the table drain over which the
Turnock Street bypass crosses. WWC (1996) considered it unlikely that the
construction of Turnock
Street bypass would have a significant impact on a local
population of this species.
Based on the availability of habitat and the results of other surveys in the
immediate locality, it is considered that this population
will be restricted to
the small areas of lowlying Paperbark vegetation in Lot 13 and in the intact
Paperbark swamps to the south
of the southern properties. The drain running
through the northern property is subject to saline intrusion and is highly
unlikely
to provide habitat for the Wallum froglet. The remainder of the area is
also generally elevated and does not provide suitable habitat
for this species.
Woodward-Clyde - May 1999
- On
28 May 1999 Woodward-Clyde produced a report entitled " Statement of
Environmental Effect - Flora, Fauna and Fire Hazard Assessment " in relation
to the proposed construction of a library near the Land. That report recorded
that the Wallum Froglet had been detected
in a "brief field survey" and included
the following:
Habitat Assessment:
The wallum froglet was recorded from the site in this region although the
majority of its habitat is found off the site in adjoining
areas and adjacent
land on either side of Turnock Street deviation. Given the disturbed nature of
the site, the proposed development
is considered unlikely to impact on any
native species such that it is placed at the risk of extinction.
...
The wallum froglet, north of the site will need to be protected from indirect
changes in water quality resulting from development.
...
Another species, the wallum froglet ( Crinia tinnula ) was recorded
from areas adjacent to the site and occurring just inside the borders of the
site near the Turnock Street/Cudgen Road
roundabout. This species is listed in
Schedule 2 of the Threatened Species Conservation Act 1995 as vulnerable. This
species was not previously recorded in surveys of the area but is known to occur
in the region and has been recorded
from nearby Cudgen wetlands. The NSW
National Parks and Wildlife Service Wildlife Atlas records this species from the
locality. The
habitat for this species is mostly found off site with the
exception of the northern most boundary near the roundabout. It appears
restricted to the closed fernland communities with occasional paperbark. Habitat
for this species as it occurs on and near the site
is illustrated in Figure 5.
It is not entirely surprising that this species was missed in the previous
surveys given that it is known to "appear and disappear"
depending on
conditions, particularly rainfall and subsequent changes in pH (Greg Czechura,
pers comm.). In the supplementary survey
this species was detected during the
diurnal survey of the site, but was not detected at night.
...
The wallum froglet was recorded from the site in this region although the
majority of its habitat is found off site in adjoining areas
and adjacent land
on either side of the Turnock Street deviation. The species appears restricted
to the closed fernland habitats
within these regions. The habitat on site is
considered to be marginal and of low significance to this species given the
proportion
of more suitable habitat in adjacent areas. It is possible that this
species increases and decreases its range according to environmental
conditions
such as rainfall and disturbance.
...
A summary of the potential impacts are provided below:
...
Alteration in water quality on low lying flats. This may impact on the wallum
froglet habitat north of the site;
Changes in hydrology for the remaining habitat areas. This may alter the
biodiversity of these areas thus comprising their habitat
value.
...
The largest detected grouping of the species was found to be between Turnock
Street (east) and the new residential area to the north.
Additional groupings
were detected northwest of the Turnock Street roundabout at the rear of the
residential subdivision and south
of Turnock Street (east) in the area
surrounding the roundabout.
- On
23 August 1999 Mr Knobel notified the plaintiff that commencing on 1 September
1999 a contractor would undertake drainage works
through the Land. Mr Knobel
noted that unfortunately the water table had been extremely high with much of
the Land flooded around
the main drain. He also advised that this had been
brought about by an unusually high winter rainfall but that water levels were
now returning to normality.
WBM Oceanics - March 2000
- The
minutes of the Council meeting of the defendant held on 19 April 2000 noted that
WBM Oceanics had completed the report on drainage
management for Kingscliff
catchment and that it would guide the drainage strategy in the Kingscliff West
area. It was noted that
DCP 9 and Contributions Plan 7 would need amendment to
reflect the new strategy. Those minutes noted that the WBM Oceanics' report
was
issued on 24 March 2000 at a total cost of approximately $29,000 with $21,156
being paid by the plaintiff that would be a credit
towards future section 94
contributions for drainage works in the Kingscliff catchment. Those minutes also
referred to the recommendations for new development
in the area as follows:
Development and fill is not to cause ponding on adjacent land and overland
flow paths must remain open. The drainage of existing properties
must not be
adversely affected as a consequence of fill operations.
A second buffer strip should be incorporated between the existing development
along Lorien Way and Blue Jay Circuit, and new development
proposed for the
adjacent undeveloped land. Again, this buffer strip should incorporate an
overland flow corridor and be designed
to preserve existing vegetation.
DCP 9 Revisited - April 2000
- It
was unanimously resolved at that meeting that an amendment occur to DCP 9
incorporating the drainage strategy produced by WBM Oceanics
and that an
amendment to Section 94 Contributions Plan No. 7 be pursued reflecting the
revised drainage strategy.
- During
2000 the plaintiff objected to the proposed expansion of the Kingscliff Shopping
Centre and made a written submission to the
defendant. On 14 November 2000 the
plaintiff wrote to the defendant in terms that included the following:
2 Drainage :
There is no discussion of our submission regarding legal drainage discharge
rights onto our land, nor the implications and management
of Q100 flood flows.
Indeed, the report dismisses this issue, noting simply that the Council's
Engineering Services Division advises "there are no issues
with regard to
drainage".
With respect, the authority to discharge stormwater onto and across our land
is fundamental to the development. At this time, no such
authority exists.
- The
Minutes of the Council meeting of the defendant of 15 November 2000, at which
the proposed extension of the shopping centre was
considered, notes that the
design did not incorporate any of the recommendations of the Kingscliff
Catchment and Drainage Management
Plan concerning commercial developments and
also that no details were provided to quantify Q100 overland flows and impacts
on adjoining
land. It included the following:
One of the objectors raised concerns regarding site drainage and impacts on
land to the south west. Councils Infrastructure Engineer
has reviewed the
drainage proposed and has advised that the point of discharge proposed by the
proponent is into Council's existing
pipe in Turnock Street which discharges
further south west (along Turnock Street) adjacent to Gales Holding land. In its
present
form the development proposal is likely to increase peak flows and
pollutant concentrations across Gales Holdings land to the south
west.
The proposal will increase the impervious cover to almost 100% of the site,
decrease the stormwater runoff time of concentration and
result in substantially
increased peak stormwater flow rates. There is no overland flow path available
in Turnock Street as there
is a sag in the longitudinal gradient of the street
adjacent to the subject property. The uncommitted capacity of the existing 750mm
pipe is also very limited. To accommodate Q100 flows and minimise nuisance
increase to downstream owners it will therefore be necessary
to limit discharge
from the site (into Council's 750mm pipe) to the pre-development Q 5 level
(0.17cu.m/sec). This flow rate can
be achieved by on site detention or retention
or a combination of both.
- The
application was refused at that time. However at a Council meeting of the
defendant on 20 December 2000 the application was approved
subject to conditions
including that the discharge of stormwater onto the Land would be limited to
pre-development rates and evenly
distributed across the southern boundary by
means of a low spillway. The Minutes of that meeting include the following:
It should be noted that DCP 9 shows a drainage reserve adjacent to the
subject land within the residential zone to the west. This
reserve has a width
of 50m.
This drainage reserve has not been created and whether or not it is developed
in the location shown will be a factor in determining
the extent the development
will impact on development on this land. In respect of the location of this
drainage reserve, Council's
Infrastructure Engineer has advised that the
drainage reserve indicated on the DCP9 plan is still proposed, however its
location
on the plan is schematic and will not necessarily be in the exact
location shown. The plan is indicative only that there will be
a drainage
reserve and trunk drain in this general location for the purpose of conveying
stormwater from the existing urban area
south east of Turnock Street in a south
westerly direction to the ultimate junction with the major south to north drain
through West
Kingscliff.
Notwithstanding the above, it is considered that the current proposal
satisfactorily addresses the potential impact on future development
of the land
to the west.
...
Councils Manager of Planning and Design has advised to overcome the issue
regarding legal discharge points raised by one of the objectors
that a condition
requiring discharge of stormwater into the adjoining property shall be limited
to the pre-development as indicated
on the drainage plans submitted by the
applicant and evenly distributed across the southern boundary by means of a low
spillway.
- On
22 February 2001 the defendant noted that there had been a failure of a sewer
gravity main adjacent to Quigan Street which had
resulted from the main being
"undermined by flow from a Council stormwater outlet".
Meetings - 2001
- On
6 March 2001 a meeting was held at which both the defendant and representatives
of the plaintiff were present. The Minutes of that
meeting include the
following:
(a) Kingscliff drainage plan basis of examining storm drainage issues for
Gales Holding properties.
(b) There is significant external drainage entering Gales Holdings'
properties. This is being examined at the present time by Knobel
Consulting and
further discussions are to be held with Council once drainage outlets and paths
established through the various parcels.
(c) It is recognised that there is a need to treat existing stormwater from
Kingscliff township before it enters the main drainage
system. Land may have to
be made available for this to take place.
(d) The drainage channel from Turnock Street towards Kingscliff is not fixed
in location and opportunity exists to vary the alignment
to suit future
developments.
- A
workshop took place on 5 April 2001 in relation to "West Kingscliff Planning" at
which representatives of the plaintiff and the
defendant were present. The
defendant's record of that meeting dated 12 April 2001 includes the following:
The western side of Pearl Street is at a lower level than that which West
Kingscliff will be filled and Council has some significant
potential stormwater
liabilities relating to the planning, design and construction of the Gales
Holdings land, with Gales Holdings
development being anticipated as a self
contained development for drainage and water quality management. Bill Knobel
commented upon
how ( sic ) and Council had worked very productively
together at this point. The fill will be permeable material to assist water
quality management.
Some significant drainage occurs from the existing
Kingscliff township onto the Gales Holdings land and he reinforced how this
drainage
management and treatment was a significant issue for Council in terms
of potential liabilities and expenditure. The Company and Council
should work
together to work out solutions for the total sub-catchment to agree drainage and
water quality outcomes. Re-design of
pipes for drainage in Elrond to Turnock
will have to be considered and there is an opportunity for water quality
treatment area in
the vicinity of the junction of Elrond and Turnock.
Considerable flexibility is still available in the design of the drainage and
water quality systems. There is currently contaminated stormwater disposing onto
the Gales Holding property and treatment devices
will be required in relation to
runoff from the existing Kingscliff township. Darren Gibson commented on how the
drainage system
can be used as open space and recreation and recreated as
landscaped corridors and become as natural as possible. The main drains
in the
system are likely to be about 1m in depth in "dry times". John Henley
acknowledged the residual liability.
Northern Drain
- On
24 August 2001 Mr May wrote to the plaintiff in relation to the Land generally.
That communication included the following:
14. To the north west near or just below the Bowls Club sporting field, there
used to be a large drain running east west to the Chinderah
flood drain. It
would appear that it was about where Channel Street is. This has been filled.
- This
would appear to be the first time that the plaintiff was alerted to the fact
that the Northern Drain had been filled.
- In
November 2001 Knobel provided a report to the plaintiff which included the
following:
In addition to managing stormwater generated by the development of its land
holdings, Gales Holdings Pty Ltd has also inherited the
management of stormwater
generated by surrounding urban development, which is discharged directly onto
its land. Tweed Shire Council
has acknowledged its liabilities in this regard.
Detailed drainage analysis of land north of Turnock Street, Kingscliff (Lots
11, 12 and 13 DP 871753) reveals significant problems
arising from recent land
use planning decisions which have overlooked the formalized conveyance of Q100
stormwater flows to the trunk
drainage system serving West Kingscliff. That
oversight has significant implications for the management of stormwater on land
owned
by Gales Holdings Pty Ltd, and consequently, the development potential of
that land.
- The
reference in this part of the report to the defendant acknowledging its
liabilities appears to have arisen from what was discussed
at the 5 April 2001
meeting, the summary of which included the reference to Mr Henley acknowledging
"residual liability".
- That
report referred to Mr Findlater's 1995 report that included the proposal for the
construction of a retention basis on the Land,
the placement of additional pipes
and the inclusion of a lateral drainage system as identified in the WBM Report.
Mr Knobel concluded
that the extension of Turnock Street to the Elrond Drive
roundabout had "effectively dammed all stormwater that is generated within
the
catchment". Mr Knobel also concluded that there was a compounding of the problem
because the invert levels of the culverts under
Turnock Street did not allow for
the Land to drain freely. Mr Knobel also referred to the WBM Report and reported
as follows:
Unfortunately with development having been established across the alignment
of this proposed lateral drainage channel; the cost of
acquiring land,
excavating a drainage path and structurally revetting the channel and providing
additional infrastructure (ie. bridge
or culvert crossings) would be
substantial.
However, the failure to allow for this drainage path, in accordance with s6
of WBM Oceanic's Conclusions and Recommendations, has severely disadvantaged
Gales Holding's development potential and the development
potential for other
adjoining properties.
Planit reports 2001/2002
- Jim
Glazebrook & Associates, Town Planners and Development Consultants, on
behalf of the plaintiff, retained Planit Consulting
Pty Limited (Planit) in 2000
to provide an assessment of the vegetation on the Land in support of its
development proposals. In its
October 2001 report, Planit reported on that
vegetation with passing reference to the fauna in the "Wider Locality". The
Wallum Froglet
was not the subject of the report other than a description of its
physical features and habits and a tabular reference to its scientific
name.
- In
December 2002 Plaint produced a detailed flora and fauna investigation of the
Land. The methods of the survey included diurnal
frog call identification
conducted across a variety of 50 and 100m grids depending on the complexity and
similarity of the available
habitat, and nocturnal survey methods such as
Elliott traps, Pitfall traps and open wire traps. Trapping efforts were
conducted for
a total of 650 trap nights with traps set at varying intervals of
10-20m depending on the habitat complexity. Traps remained in place
for between
36 and 48 hours and were checked and emptied (when necessary) every eight hours.
All trap lines were replicated a minimum
of twice over the survey period.
- In
the section of the report on amphibians (3.2.1.2) Planit reported that the
Paperbark Forest within the southern portions of Lots
26C and 26D were
considered the primary habitat for amphibian species on the Land. The largest
populations of frog species noted
on the Land were recorded in these areas with
"suitable breeding habitat for two protected species". Planit reported that
following
extensive rainfall events in March 2002, Wallum Froglets were recorded
calling in a small area adjacent to the Turnock Street roundabout
in Lot 11 of
the Land. The report included the following:
Given the extensive cleared areas located adjacent to this area it is
considered that the Wallum Froglet did not relocate into this
area but, rather,
lay dormant within the soil profile and resurfaced following recharging of the
groundwater table.
- Planit
concluded that the Wallum Froglets were mainly in the areas of Lots 26C and 26D.
It was noted that the defendant had failed
to record the Wallum Froglet within
this area during its ecological assessments conducted prior to the construction
of Turnock Street.
The report continued:
The failure to record this species and consequent construction of Turnock
Street has severed an existing (at the time) movement corridor
for the species
linking Lots 11-13 ... north of the road to drainage corridors which ultimately
link to suitable breeding grounds
on the southern portions of Lots 26C & 26D
...
It is hypothesised that this action has resulted in the isolation of a small
number of individuals which now lay dormant in the soil
close to the water table
during dry periods as they are unable to retreat to areas of permanent tannic
Melaleuca wetland. This retreation
has been noted in other areas of the site
during dry periods ...
Given the above, it is considered that a population of Wallum Froglets does
exist on the subject land, predominantly confined to the
most suitable habitat
area contained within the southern portions of Lots 26C & 26D.
...
A small number of isolated individuals which exist adjacent to the Turnock
Street roundabout will be impacted upon by the proposed
development which
proposes the filling of these areas. It is considered that these individuals,
which are separated from permanent
water, undergo a period of dormancy during
drier months and resurface during the winter months or periods of extensive
rainfall which
raise the groundwater table.
Further discussions - 2002
- On
22 January 2002 the plaintiff wrote to the defendant in respect of a draft Tweed
Local Environment Plan 2000 Amendment in terms
that included the following:
Drainage . Council's previous planning decisions resulted in
the main open drain servicing Gales land north of Turnock St being filled in,
with the Retirement Village now standing on part of it. Gales' recent studies
show that filling in this drain, along with other stormwater
being directed onto
Gales land presents great problems and that the cost to Council of rectifying
these past planning decisions could
be several million dollars.
- The
plaintiff requested discussions with the defendant to seek "solutions". On 7
February 2002 the defendant wrote to the plaintiff
advising that the appropriate
manner in which to progress matters would be that consultants acting for the
plaintiff and the defendant's
staff, including any consultants it engaged,
should "work together". The defendant advised that it was sure that this would
"provide
the appropriate outcomes within a reasonable time frame".
- On
18 July 2002 a meeting of representatives of the defendant took place. A
memorandum in relation to that meeting included the following:
1. Drainage Issues
Around 1995 Council agreed to subdivision works and filling that deleted the
eastern branch open channel proposed in the original
drainage study report
prepared by WBM.
A report prepared by Martin Findlater proposed a 1ha detention basin in lieu
of the eastern branch. Council resolved 27 September
1995 to amend DCP9 and
s94CP7 to incorporate the detention pond. There has been much correspondence on
this issue with Gales Holdings,
but, there is no agreement with them for these
works to be on their land and no agreement on who bears the costs.
To solve the drainage issue may cost in excess of $1 Million. Options being
Purchase houses to reinstate original eastern branch.
Provide a small detention basin (on either their land or Bowling Club Land)
and a southern outlet through Gales Holdings land to south
of Turnock Street.
Provide a large detention basin and utilise the existing underground drainage
system as an outlet.
Provide no detention basin and use a larger outlet through Gales Holdings
land to south of Turnock street.
...
3. Possible Strategies
Advise Gales Holdings that it is their problem to deal with upstream drainage
as the problem will only occur as a consequence of filling
their land north of
Turnock Street. They can provide detention storage on their land or purchase
land from the Bowling Club.
TSC will assist with acquisition of road (but no $) through Bowling Club
land.
If detention basin needed on Bowling Club land Council would also assist (but
no $).
Development Application
- On
19 December 2002 the plaintiff lodged a Development Application for a proposed
shopping centre on Lots 11 and 12 of the Land.
Drainage system inadequate
- In
a letter dated 21 January 2003 from the defendant to a resident who had
complained about stormwater drainage in Kingscliff Street
the following was
written:
Internal inspections of the piped system indicated that no significant silts
or obstructions exist in the system. The problem appears
to be that the system
has been rendered inadequate to convey runoff generated by development in the
area over the years.
Works to increase the inlet pit capacity and some additional piping are
scheduled for early February 2003.
Further discussions - 2003
- In
an internal memorandum dated 27 February 2003 Mr Knight of the defendant
recommended that the plaintiff's application to develop
part of the Land into a
shopping centre be refused. In a memorandum of that date Mr Knight wrote as
follows:
At present an area of approximately 12ha (developed areas of Kingscliff in
sections of Marine Pde and Kingscliff St) upstream of Kingscliff
Bowling Club
land, drain through a stormwater pipe system which runs through the Bowling Club
land and thence in a westerly direction
via pipes under Blue Jay Way and other
streets and reserves to the main Kingscliff Drain. This pipe system is only
designed for Q5
capacity, and at present flows in excess of Q5 overflow to
unfilled land owned by the Bowling Club and adjacent Gales Holdings land.
These
lands operate as a detention basin for the in excess of Q5 flows.
...
This application (for the shopping centre) would incrementally eliminate
detention storage in Gales Holdings land, and the filling
proposed by the
appended "master plan" would eliminate all detention storage from that land. The
combined effect of filling both
these parcels of land (without any other
compensatory measures) would be to eliminate in excess of Q5 drainage capacity
for the upstream
catchment and cause flooding of land and property.
It can be argued that the land owned by Gales Holdings, being low lying land
at the rear of the frontal dunal system is the natural
area for runoff to be
discharged from the foreshore dune area and acts as a natural detention basin
for the foreshore dune area.
- The
memorandum then referred to the plaintiff's preferred method of dealing with the
external drainage by creating a north/south open
drain through Lots 11 and 12 of
the Land extending from the Kingscliff Bowling Club land in the north to the
Kingscliff drain south
of Turnock Street, including a new drainage structure
under Turnock Street. The memorandum also referred to the defendant's
Engineering
Services Division' preferred option being a detention basin of
around 0.8ha in the northern section of the Land and also on the Bowling
Club
land. The memorandum suggested that the reasons that the plaintiff's application
should be refused were:
1. In the absence of a master plan for landforming and infrastructure of the
whole Gales Holding West Kingscliff site
(a) The application has failed to demonstrate that the proposed drainage
systems will be compatible with ultimate development of the
West Kingscliff
area.
(b) The application has failed to demonstrate that the proposed landform is
compatible with ultimate development of the West Kingscliff
area.
(c) The application has failed to demonstrate that proposed stormwater
quality treatment measures are compatible with ultimate stormwater
treatment
strategies for the West Kingscliff area.
2. The application has not provided a lawful point of discharge for major and
minor stormwater runoff from the proposed development.
3. The application has failed to assess the environmental impacts of filling
the site and the impacts on amenity of persons along
any potential haul routes.
"Permit" withdrawn "
- On
5 March 2003 Mr Glazebrook wrote to the defendant on the plaintiff's behalf in
terms that included the following:
We are instructed that in the course of at least the last ten (10) years,
polluted stormwater from urban catchments upstream of our
client's property has
been discharged from Council's stormwater drainage system onto our client's
holdings at West Kingscliff.
In minutes of a workshop meeting held with Council Officers and some
Councillors, produced by the Director, Development Services (April,
2001), the
then Manager, Water acknowledged Council's " residual liability " in this
regard (see extract attached).
...
1. Despite the best efforts of Gales Holdings Pty Ltd, there has been little
evidence in Council's process that the long term implications
of the unlawful
discharge of stormwater onto our client's land, has been objectively and
properly considered.
2. Further, there has not been meaningful and proper consideration by Council
officers of environmental and strategic planning issues,
and
3. In reality there has been a lack of Council initiated discussion and
negotiation with our client.
This has culminated in the preparation by Council officers of a new version
of draft DCP9 - West Kingscliff (version 2) without prior
reference or
discussion or consultation with Gales Holdings. This is despite the Council's
undertaking to work co-operatively with
Gales Holdings. In addition, the new
draft DCP9 (version 2) has been prepared without awaiting the comprehensive
studies being prepared
for our client. Council has known about those studies for
the whole of their gestation and has encouraged our client to prepare the
studies and has indicated to our client that Council would consider the studies
in co-operation with our client and in the planning
process.
However, the draft DCP9 is presented without awaiting these studies and
without the benefit of any similarly comprehensive studies.
Council has failed to address the stormwater management issues referred to
above.
We are instructed by our client that it is no longer prepared to permit the
unlawful discharge of concentrated stormwater flows from
Council's existing
drainage structures onto our client's land holdings at West Kingscliff.
Council is aware of the importance of drainage and water quality management,
which is described in detail in draft DCP9 (version 2).
It is inequitable that
Council should demand standards that it does not adhere to itself, and has not
applied to itself over a period
of many years.
Our client therefore requires Council to immediately identify all points of
illegal discharge of stormwater onto our client's holdings,
and take measures to
prevent that discharge within ninety (90) days of the date of this notice.
- On
18 March 2003 the defendant wrote to Mr Glazebrook advising that the DCP would
address all of the "necessary planning and engineering
issues" associated with
the area, including strategic drainage issues. The defendant also advised that
it was unaware of any unlawful
discharge points as referred to in Mr
Glazebrook's letter and that all stakeholders including the plaintiff would be
fully consulted
in completing DCP 9.
- On
4 March 2003 the NPWS wrote to the defendant in relation to the "conservation
value" of the Land. That letter specifically eschewed
any suggestion that the
comments within it were in relation to the plaintiff's DA for the shopping
centre. The NPWS advised that
there were a number of "regionally vulnerable"
vegetation communities on the Land and that it also contained suitable habitat
for
a number of additional threatened species that had not been recorded to date
because of limitations in the survey design and methods.
In addition the NPWS
advised that the Land was of "critical importance" for the Mitchell's Rainforest
Snail, an endangered species
under the Threatened Species Conservation Act
1995. It was noted that extensive areas of suitable habitat for the
Mitchell's Rainforest Snail occurred within the Land and that an approved
Recovery Plan had been prepared for the species which required a detailed
consideration of the impact of development proposals on
the species. It was also
noted that one of the other important populations within the Land was the Wallum
Froglet.
- Although
the NPWS claimed its comments were not in relation to the plaintiff's DA for the
shopping centre the letter included the
following:
The proposal to develop land on the north and south sides of Turnock Street
and the construction of the road linking Turnock Street
to Quigan Street is not
supported. This proposal would further fragment habitat for Mitchell's
Rainforest Snail, increasing the degree
of isolation. Isolated habitats will
also be subject to altered hydrological regimes and increased edge effects,
which over-time,
will reduce the quality and viability of habitat.
An altered hydrological regime is expected to occur when a large amount of
fill is placed in close proximity to snail habitat. The
specific habitat
requirements of Mitchell's Rainforest Snail make it particularly susceptible to
changes in hydrology. The fragmentation
and isolation of habitat coupled with
potential changes in hydrology and increased extent of edge effect may have a
substantial and
irreversible impact on snail habitat.
- On
11 April 2003 the proposed action by the plaintiff to develop the Land was
designated as a "controlled action" under the Environment Protection and
Biodiversity Conservation Act 1999 (Cth). The Commonwealth Department of the
Environment and Heritage advised the plaintiff that the Land contained an
important population
of the "critically endangered" Mitchell's Rainforest Snail
and that it considered that site works were likely to directly and indirectly
affect important habitat for the snail if adequate controls were not in place.
It was also noted that any works associated with the
DA for the shopping centre
potentially affecting the habitat of the snail could not commence until approval
had been given under
that Act.
Wallum Froglets take hold
- On
12 May 2003 Peter Parker of Environmental Consultants Pty Limited advised the
defendant that his review of the reports of Planit,
who had been retained by the
plaintiff through Mr Glazebrook, led him to the conclusion that Planit had
failed to undertake a proper
eight part test with respect to the Wallum Froglet.
Mr Parker advised the defendant that Planit had incorrectly assumed that the
Wallum Froglet on the Land would not be significantly affected despite the
construction of a road through its "core habitat", the
pumping of 98,000 cubic
metres of fill onto the Land and the construction of drainage works to
accommodate drainage from a proposed
shopping centre onto the remaining Wallum
Froglet habitat. Mr Parker advised that there would be significant hydrological
changes
or changes to nutrient status. He attached a chart to his report
comparing the calls of the Wallum Froglets recorded by Planit and
the calls he
recorded in his survey. That chart recorded that Planit had heard less than five
calls of the Wallum Froglet compared
with more than 1000 calls heard on 29 April
2003 (during the day) and on 5 May 2003 (during the evening) in his own survey.
Blockage of the Elrond Drive culvert
- There
is no issue that in mid-2003 there was a blockage of the Elrond Drive culvert.
Mr May's unchallenged evidence was that when
the culvert was constructed a small
area was damaged and a "wooden prop" was placed in the pipe whilst new concrete
was put in to
replace the broken area. Mr May observed on 9 May 2003:
The wooden prop is still in place and had collected masses of accumulated
grass around it causing the blockage. This is the only pipe
set low enough to
act as a drain.
Significant ponding
- On
11 August 2003 Planit advised the plaintiff that there had been significant
ponding north of Turnock Street and the area was unable
to drain because of
"previous culvert design". Planit also advised that this ponding was generally
greater than 30cm and there were
areas with standing water still present after
several months. Planit observed that the population of all frog species,
including
the Wallum Froglet, had increased within the area as a result of
"ongoing suitable conditions, likely breeding and potential immigration
from
other populations on site (as a result of flooding)".
Access to the defendant's file
- It
was during the latter part of 2003 and early 2004 that the plaintiff's
consultants sought access to the defendant's files. The
plaintiff was also
seeking expert advice in relation to the proposed development of the Land. In
May 2004 Ingham Planning Pty Limited
advised the plaintiff as follows:
Land to the south east around Turnock St experiences ponding and low level
flooding generally caused by stormwater flowing in from
the developed areas to
the east and natural drainage flows being blocked by developments. The altered
stormwater flow and ponding
has changed the ecological characteristics of the
area. This area can be filled if the stormwater is redirected to the west by
reintroducing
a westward channel, or by providing an open drain south across the
property and across Turnock St/Elrond Drive.
Nuisance alleged - May 2004
- The
plaintiff had received advice from Dr Stephen Webb and on 4 May 2004 the
plaintiff's then solicitors wrote to the defendant in
the following terms:
In the opinion of Dr Webb, the Turnock Street extension effectively acts as a
dam for even small storm events.
Clearly adequate under-road and lateral drainage is required to ensure that
unnatural ponding does not continue to occur to the north
of Turnock Street.
The above set of circumstances constitutes an unreasonable interference with
the reasonable use and enjoyment of our client's land
and as such amounts to a
legal nuisance.
Our client now asks that Council urgently review the problems created by
Council's construction of Turnock Street through our client's
above land with a
view to Council advising that it will, as a matter of urgency, make alterations
to the drainage to stop the unnatural
ponding occurring. This should be carried
out in consultation with our client's hydrologist, Dr Steve Webb.
- On
12 May 2004 Mr Knobel gave permission to the defendant to enter the plaintiff's
land to re-establish the outlet to the stormwater
drainage discharging from
Cudgen Heights. Mr Knobel advised that the works would entail excavating the
outlet through the existing
grass and feathering the outlet works into the
existing drainage paths across the Land. Mr Knobel requested the defendant to
provide
an inventory of all existing stormwater pipes discharging onto the Land.
- On
14 May 2004 the plaintiff's solicitors wrote to the defendant reporting on a
number of matters. The first was a council drain at
the eastern end of Turnock
Street discharging water onto the Land causing "increasing wetness". The letter
continued:
The discharge of the water substantially interferes with the reasonable use
and enjoyment of our client's land and our client holds
Council responsible for
all loss and damage suffered as a result of the discharge of the water.
- The
plaintiff's solicitors invited the defendant to inspect the Land to make an
assessment of this matter. That letter also included
the following:
3. Our client has in recent times become aware of the filling of lateral
drain B at the northern end of the Noble Park Estate and
being the drain shown
as lateral drain B in the Kingscliff Drainage Strategy Plan, WBM 1994. The
filling in of the drain which was
allowed by Council means that there are no
remaining direct drainage paths from our client's land to the Tweed River.
Our client has recently obtained from Council's files a copy of a letter
written by Ian Hill & Associates on behalf of Kingscliff
Bowls Club and the
Blue Nurse Association being a letter dated 17 June 1994.
...
Council's method of resolving the drainage problem was to deliberately
provide for the stormwater from the Kingscliff urban area to
flow onto our
client's land in the short term and then propose a detention basin to solve the
problem in the long term: letter of
23 March 1995 from Council to our client
proposing amendment to DCP 9 to include a 1 hectare area for a stormwater
detention basin.
Council failed to advise our client that the reason for
requiring the detention basin was the filling in, with the approval of the
Council, of lateral Drain B.
In other words Council did not require the developer of the Noble Park Estate
to rectify the drainage problem which their actions,
taken with the Council's
approval had caused, but rather arranged with those developers to have the
drainage problem dealt with by
(intentionally) ensuring the water flowed onto
our client's land and be retained there and flow through our client's land. This
deliberate
concentration of water on our client's land, however, was plainly
unlawful.
Our client has not until recently been aware of the above matters or of the
consequences to our client's land.
Please immediately advise Council's proposal to rectify the position
described above.
- The
plaintiff's solicitors also repeated Mr Knobel's request for an inventory of all
stormwater drainage paths onto the Land and for
such inventory to be provided
within 10 days.
- On
18 May 2004 a meeting took place between representatives of the plaintiff (Mr
Gibson from Jim Glazebrook & Associates and Mr
Knobel) and the defendant (Mr
Hodges, Director Planning & Environment and Mr Knight, Infrastructure
Engineer). Discussion in
relation to "drainage issues" included that the
defendant would investigate the establishment of a table drain north of Turnock
Street
to convey water westward to the existing "low flow" pipes under Elrond
Drive to ease the ponding problem on the Land north of Turnock
Street. The
plaintiff's representatives advised that the plaintiff's preference was for the
re-establishment of an open drain similar
to the Northern Drain. In the
defendant's note of the meeting it is recorded that the defendant did not
consider this to be "a realistic
option for cost and political reasons".
- On
6 July 2004 the defendant wrote to the plaintiff's solicitors referring to their
correspondence of 4 and 14 May 2004. That letter
included the following:
The development of your client's land, and other adjacent land in Kingscliff,
will require significant amounts of filling to raise
these lands above flood
level. This filling and previous filling/drainage work irreversibly change the
natural landform and as a
consequence change the natural drainage patterns of
the area.
Council acknowledges that the West Kingscliff area requires a comprehensive
drainage strategy to satisfy landowner's and Council's
needs.
In this regard, Council in partnership with your client commissioned a report
by WBM in 1998 to investigate drainage issues in West
Kingscliff. Your client's
consultant Garry Peacock was a key contributor in this investigation and the
final report.
Council officers are now meeting with your client's representatives (Darren
Gibson of Jim Glazebrook & Associates and Bill Knobel
of Knobel Consulting)
on a regular basis to further develop and progress structure planning of your
client's land. Drainage strategies
for lots 11 and 12 referred to in your
letters have been analysed in detail at these meetings and there is significant
agreement
on key drainage issues.
It is expected that the final outcome of these meetings will be a drainage
strategy that is equitable and acceptable to both parties.
- The
Minutes of a Council meeting on 4 August 2004 note that a comprehensive plan for
the Land was considered to be essential and the
sooner this was achieved the
better. It was proposed that a small technical group under the chairmanship of
the Manager Strategic
Planning of the defendant be established to complete a
comprehensive draft Structure Plan for the Land for reporting to the defendant
by the end of November 2004. It was also noted that DCP 9 required a major
review particularly in respect of the Land.
Freedom of information litigation
- After
the plaintiff obtained the defendant's files referred to in the correspondence
extracted above, it sought access to a report
in the defendant's possession
produced by Core Economics. The defendant refused the plaintiff access to that
report and the plaintiff
commenced proceedings in the Administrative Decisions
Tribunal. The plaintiff was successful in this litigation and access was allowed
to that document in mid 2005 (tr 367).
Proposed DA to fill the Land
- On
3 November 2004 the plaintiff wrote to the defendant in terms that included the
following:
Gales has been trying to develop its land and build a supermarket centre at
West Kingscliff for many years. This required fill and
the most critical
component of this was drainage in the area that Turnock St now crosses. A letter
from Mr Rayner Director Engineering
Services dated 22/6/1995 refers to this.
Information recently available to Gales indicates that the cause of the drainage
problems
was alterations in the natural drainage flow.
These issues were raised at a Development Assessment Panel (DAP) on 5
February 1998 (Council's minutes attached). These minutes were
not entirely
accurate and there was subsequent correspondence regarding this.
The reason that Gales has not built a shopping centre as mentioned in points
6 and 7 of the DAP minutes is that the land could not
be filled till the
drainage problems were resolved.
...
Gales has paid for drainage studies done under Council control to enable
filling of the area - specifically Ray Sargent and WBM, but
neither of these
mentioned the cause of the drainage problems (filling in of the natural drainage
path and the drainage canal) or
enabled filling to proceed, despite these being
the specific reasons for Gales paying for the studies. Council was fully aware
of
the cause of the drainage problems and Gales was totally unaware, and was
kept uninformed despite paying for those studies.
Over the years Gales has tried to work with Council to resolve the issues and
has had extensive studies done at great cost which have
defined to a certain
degree the cause of the problems and suggested some alternative solutions.
Gales intends to submit a DA for filling the area north of Turnock St around
the first week of December 2004 - in 4 to 5 weeks.
A critical component of this is how the water flow external and upstream from
Gales property, that previously flowed to the north
and west away from Gales
property, might be handled, possibly by flowing southwards across Gales
property.
Gales seeks most urgently a meeting with Council to determine a final outcome
of the drainage strategy.
- On
9 November 2004 the Department of Environment and Conservation (NSW) wrote to
the defendant advising that the plaintiff's application
to develop its Land by
the construction of a shopping centre and associated car parking facilities was
not supported "due to its
potential impacts on threatened species and their
habitats". The Department noted that it was the Commonwealth Department of
Environment
and Heritage that determined whether a development is a "controlled
action" under the Environment Protection and Biodiversity Conservation Act
1999 (Cth) and noted that the development proposal was in the immediate
vicinity of a significant population of the Mitchell's Rainforest
Snail. The
Department recommended that the defendant forward the application to the
Commonwealth Department for consideration.
- On
11 November 2004 Jim Glazebrook & Associates wrote to the defendant on the
plaintiff's behalf referring to the plaintiff's
request in its letter of 3
November 2004 for an urgent meeting with the defendant. That communication
included the following:
As you would be aware, there is a need for Council to convey stormwater away
from affected properties upstream of Gales Holdings land
in major storm events.
Council has indicated a preferred option involving some form of conveyance
through Gales Holdings land. In
this regard, Gales believes that its interests
have been adversely affected by prior events which were not of its doing and
were
outside its control.
Gales Holdings has incurred significant losses and costs caused by the
drainage problems, including funding Council studies (WBM,
Ray Sargeant ( sic
)) and its own independent investigations in an effort to identify the
problems and possible solutions. Through its own investigations,
Gales believes
that it has identified the causes of the drainage problems. To this end, it has
also investigated possible technical
solutions to the conveyance of upstream
flows. Further discussions on technical matters are to take place with Council's
Patrick
Knight on 16 November 2004. In an effort to resolve this matter in a
mutually acceptable way, Gales would be prepared to consider
certain options
involving its land, subject to an appropriate consideration (financial or
otherwise).
Table drain constructed
- In
2004 the plaintiff, with advice from Dr Webb, constructed a table drain north of
and parallel with Turnock Street. The initial
table drain was built according to
usual drainage practice however there were problems with the invert. Dr Webb
observed puddles
in the drain and concluded that the drain was not operating
properly. The problem was subsequently remedied with a laser leveller
and the
table drain was graded appropriately all the way to Elrond Drive culvert.
- By
letter dated 24 November 2004 the defendant advised the plaintiff that it had to
address a number of issues in relation to the
DA being non-compliant with the
defendant's "adopted drainage strategy". The "adopted drainage strategy" was
defined in the letter
as "see DCP9, CP7, WBM Report 'Kingscliff Catchment &
Drainage Management Plan'". This "strategy" included the "dedication of
a 50m
wide drainage easement for drainage and associated linear parkway use". The
plaintiff's DA included the proposed reconstruction
of some drains which the
defendant advised included non-compliant "cross sections". The defendant advised
the plaintiff that any
departures from the drainage strategy must be justified
and, in particular, it must be demonstrated that the "proposed departures
will
be consistent with provision of adequate drainage for the entire catchment in
its ultimate development form". The defendant
also advised the plaintiff that
there would need to be treatment ponds of an area equal to 5% of the
contributing catchment located
adjacent to or along and immediately north of the
proposed drain. The defendant requested the plaintiff to address the "issues"
preferably
within 28 days, after which a further assessment of its DA would be
considered.
- On
21 December 2004 the defendant served on the plaintiff an "Order under section
124 Local Government Act 1993" requiring it to remove excess vegetation
(specifically long grass) from the Land along the boundary of Cudgen Road and
the fence
line of Boomerang Street to ensure that the Land is "placed or kept in
a safe or healthy condition".
LEP litigation
- The
plaintiff and the defendant were also in negotiations in relation to a land swap
of areas other than the Land. By amendment to
the Tweed Local Environmental Plan
that came into force on 6 August 2004 the defendant rezoned some aspects of that
land. The plaintiff
commenced legal proceedings in which the defendant was named
as the second defendant and at first instance failed in establishing
that the
amendment was invalid: Gales Holdings Pty Ltd v Minister for Infrastructure
and Planning and Anor [2005] NSWLEC 617.
DA to fill the Land - 2005
- In
late 2004 or early January 2005 the plaintiff lodged a DA to fill the land north
of Turnock Street and to construct a shopping
centre south of Turnock Street. On
31 January 2005 the defendant wrote to Mr Glazebrook in response to that DA in
terms that included
the following:
After discussing the matter with staff, and in view of the open manner that
Council has and is discussing the future structure of
Kingscliff with your
representatives, it is considered that the lodgement of the Development
Application for filling on the north
side of Turnock Street is pre-emptive given
all the studies and planning required for this location. This Development
Application
substantially commences the process of subdivision and development
of the area north of Turnock Street including the effects on fauna
and flora in
the immediate area and in Kingscliff as a whole.
The subdivision of this area would be a SEPP 71 matter, and in view of this
and the need for providing a strategic structure for the
development of
Kingscliff, it has been decided to report to Council on the process needed to
review and replace the existing Development
Control Plans (DCP) for Kingscliff
with options (including Gales Holdings option) for the development of the area,
especially greenfields
sites adjacent to the existing town centre.
- On
7 February 2005 the Commonwealth Department of the Environment and Heritage
wrote to the plaintiff advising that its DA had been
referred to it on 5 January
2005 for decision as to whether or not approval was needed under Chapter 4 of
the Environment Protection and Biodiversity Conservation Act 1999 (Cth).
The letter advised that the Department had decided the proposed development was
a "controlled action" and therefore the development
could not continue without
approval under Part 9 of the Act. The Department also advised the plaintiff that
it was responsible for
carrying out certain steps as part of a requisite
environmental impact assessment, the first of which was to provide preliminary
information as the basis for determining the level of assessment.
- On
15 March 2005 Jim Glazebrook & Associates wrote to the defendant referring
to recent discussions regarding the status of the
plaintiff's DA and a proposal
for a meeting between the ecologists acting for both the plaintiff and the
defendant. The issue for
discussion was whether or not a Species Impact
Statement was required, a matter in respect of which the parties were in
disagreement.
- On
17 March 2005 the plaintiff wrote to the defendant referring to Mr Glazebrook's
letter of 15 March 2005 and advising that the plaintiff
had to determine whether
to commence an action for the defendant's deemed refusal of the DA to fill the
Land and to construct the
shopping centre. That letter included the following:
In reviewing the Agenda of the Meeting of 7/10/2004 it seems most issues have
not been much advanced, despite being critical to the
DAs. Indeed, Council's
minutes of 2/3/2005 record that Gales actions are pre-emptive. This despite
Gales having first discussed a
supermarket on the same site with Mr Jardine on
28/7/1997 and Mr Broyd on 13/10/1997, and with Council's Development Assessment
Panel
on 5/2/1998, where Mayor Boyd said the area should be filled as the first
step in development. Gales has been continuously trying
to fill the area ever
since, at all times with full and open communication to Council. Council
concealed from Gales that the reason
that drainage was a problem was that
Council had allowed the natural drainage flow path to be blocked in 1992.
Proceedings in relation to deemed refusal of DA
- The
plaintiff appealed to the Land and Environment Court against the deemed refusal
of the DA to fill the Land and the deemed refusal
for the development of the
Land south of Turnock Street into a shopping centre. The defendant contended
that a Species Impact Statement
was necessary before the DAs could be determined
and was successful in that contention: Gales Holdings Pty Limited v Tweed
Shire Council [2006] NSWLEC 85; Gales Holdings Pty Limited v Tweed Shire
Council [2006] NSWLEC 212.
- They
were four experts, two retained by the plaintiff and two retained by the
defendant, who disagreed as to whether the Turnock Street
and Elrond Drive
embankment/road was a barrier to movement of the Wallum Froglets. In those
circumstances a Court Appointed Expert
was instructed to ascertain whether the
"Wallum Froglet or its tadpoles are able to use or are likely to use in the
context of genetic
interchange any of the drains under any of the roads on the
land or cross any of the roads surrounding land for the purposes of movement
between those portions of land on the northern side of Turnock Street, the
southern side of Turnock Street and the western side of
Elrond Drive": Gales
Holdings Pty Limited v Tweed Shire Council [2006] NSWLEC 212 at [18]. The
Court Appointed Expert concluded that the Wallum Froglets could traverse pipes
under Turnock Street and Elrond Drive but that
there was little likelihood of
them doing so. The expert also concluded that the Wallum Froglets could cross
over both Turnock Street
and Elrond Drive with a reasonable chance of success
between the hours of midnight and 6 am.
Present proceedings commenced
- On
26 May 2005 the plaintiff's solicitors, Allens Arthur Robinson (AAR) (the
plaintiff had also retained a firm, Woolf Associates,
to which reference is made
in some of the correspondence) wrote to the defendant advising that they had
been instructed to commence
proceedings against the defendant in respect of
nuisance and negligence in respect of "the drainage problems" on the Land and
"consequent
changes in the ecology and difficulties in developing the land as
result of acts (and lack of action)" by the defendant. AAR referred
to the
filling of the Northern Drain, the manner in which Turnock Street was
constructed and the defendant's conduct in relation
to the surrounding
developments. After further communication these proceedings were commenced.
Public allegations
- In
April 2006 the plaintiff published pamphlets alleging that the defendant was
deceiving the public. Those pamphlets included allegations
that the defendant's
officers had manipulated reports, provided false information or withheld vital
critical information that would
completely change the results and
recommendations of certain reports on major projects in the area. There were
also allegations that
Mr Jardine had suppressed or hidden a report obtained in
the Freedom of Information proceedings.
- On
24 May 2006 the plaintiff wrote to Mr Mike Rayner, who had recently been
appointed as the General Manager of the defendant, referring
to the "relevant
history going back many years" and in terms that included the following:
Gales, as always, would welcome the opportunity to meet in any forum with a
view to genuine discussions with a view to resolving the
many complex issues to
allow proper development for the ultimate benefit of the community.
Gales believes that such meetings, if you or the Administrators should agree,
should take place without delay as the numerous Court
cases that Gales has been
forced to undertake will continue to consume resources in time, money and effort
that would be better spent
on productive endeavours.
- On
22 June 2006 Mr Rayner responded to the plaintiff's letter of 24 May 2006 in the
following terms:
Could I say in the first instance, that Council is very keen to find a
solution in partnership with you to the many complex issues
that have evolved
between your company and Council.
Council Administrators had appointed Mr John Mant, at no small cost to the
Council, to attempt in the past what you are proposing
to be done now. Council
would need to be assured, before it embarks on any further mediation, that the
company and particularly its
members are genuinely seeking a fair outcome and
resolution of all outstanding matters.
Prior to entering into further discussions with you in regard to the
mediation process to be adopted your company needs to demonstrate
good faith by,
in the very least:
1. Publicly apologising to Mr Douglas Jardine for the false, outrageous and
hurtful comments made by Gales Holdings Pty Ltd in recent
times.
2. Making arrangements to pay the Council the substantial outstanding legal
costs that your company already owes the Council.
Litigation continues
- The
litigious relationship between the plaintiff and the defendant continued. The
plaintiff appealed from the judgment in which it
failed to establish that the
amendment to the Tweed Local Environmental Plan was invalid. The plaintiff was
successful in the Court
of Appeal: Gales Holdings Pty Limited v Minister for
Infrastructure and Planning and Anor [2006] NSWCA 388. Tobias JA, Beazley JA
agreeing and Basten JA dissenting, held that the amendment was invalid as the
defendant had, inter alia , failed to take into account a report prepared
by Core Economics who had been engaged to advise the defendant on a retail
development
strategy.
More complications
- The
relationship became more complicated in late 2007 when the defendant notified
the plaintiff that it had received complaints concerning
unauthorised drainage
works on the Land. The defendant directed the plaintiff to cease any further
drainage works failing which immediate
legal action would be commenced.
- On
30 June 2008 AAR wrote to the defendant's solicitors referring to the previous
correspondence in terms that included the following:
We are instructed that since Woolf Associates' letter of 22 October 2007, the
condition of the Quigan Street Outlets have deteriorated
further. In particular
we understand that the concrete apron has become significantly undermined and
that a large block of concrete
previously forming part of the apron has broken
off and is now lying several metres below the road in the channel on our
client's
land created by water flowing out of the Quigan Street Outlets. We are
instructed that the undermining of the concrete apron and
of the land on the
road reserve around the Quigan Street Outlets is now so significant that when a
member of the public was walking
on the road reserve next to the gutter
diversion, the ground gave way under one of his feet and he found that his leg
was in a hole.
We are also instructed that cracks can be observed in and near
the road surface beside the Quigan Street Outlets.
Our client is concerned that this presents a serious potential danger to
members of the public including children travelling to and
from a nearby school.
Our client is also concerned about the scouring and gouging of its land near the
Quigan Street Outlets, and
the resulting deposition of this material further
downstream blocking the open channel. The scouring and subsequent deposition is
a result of stormwater flowing from Quigan Street Outlets without any energy
dissipation system in place to slow down the flow of
stormwater on to our
client's land.
...
Our client is concerned that the volume and quality of untreated stormwater
flowing out of the Quigan Street Outlets can cause damage
to the Mitchell's
Rainforest Snail habitat. We are also instructed that the undermining of the
concrete apron and the road reserve
above the Quigan Street Outlets has exposed
a length of the sewer line and that a blue repair section can be seen on the
sewer line
where our client understands it was repaired by Council several years
ago. Our client is concerned that the exposed sewer line could
be vulnerable to
rupturing as it did previously, which could cause raw sewerage to flow on to the
Mitchell's Rainforest Snail habitat.
- AAR
requested that the defendant take a number of steps including the installation
of energy dissipation works below the Quigan Street
Outlets.
Development Consent
- On
14 July 2008 the Land and Environment Court granted development consent for the
plaintiff's development on certain conditions:
Gales Holdings Pty Limited v
Tweed Shire Council [2008] NSWLEC 209. On 28 August 2008 the Land and
Environment Court Orders were entered upholding the plaintiff's appeal and
granting development consent
to fill the Land subject to conditions including
that the consent would not operate until the plaintiff satisfies the defendant
by
producing satisfactory evidence of various matters set out in Schedule A of
the conditions. Those matters included the production
of a Wallum Froglet
management plan and monitoring and reporting in relation to matters including
climatic conditions, water quality
and hydrology. They also included a
requirement that the results of the monitoring be given to the defendant at the
end of each season
together with a final report after 12 months with conclusions
regarding Wallum Froglet numbers, population fluctuations, number of
breeding
events and observations of water quality and the length of the time there is
standing water. The conditions also required
a stormwater network with two
separate water quality treatment criteria, one being for the Wallum Froglet
habitat and the other for
all other stormwater. There are also conditions in
relation to the quality of the fill to be used and a condition that if the fill
had a shell grit content in excess of 1%, an impermeable barrier is to be placed
within the fill batter to the Wallum Froglet precinct.
Blue Jay Circuit Scheme
- The
defendant has proposed stormwater augmentation works in relation to what has
been described as the "Blue Jay Circuit Drainage
Scheme" (Blue Jay Circuit
Scheme). Blue Jay Circuit is part of the road system adjacent to the Land and
within the NPE, intersecting
with Lorien Way. The Review of Environment Factors
in respect of the Blue Jay Circuit works (Ex GG) recognises that "surplus flows
greater than a Q5 storm event" flow down stream "via default" onto the Land "as
the inlet capacity is exceeded". It includes an "upgrade"
of the 1200mm pipe and
there is no issue that the implementation of this augmentation will adequately
address the problems the plaintiff
is experiencing with the increase in
stormwater runoff onto the Land. There is no issue that the defendant has
commenced these works,
however they are not to be completed until a contribution
is received from the developer of the Nursing Home. It is not clear when
such a
contribution will be made.
The proceedings
- When
the plaintiff commenced these proceedings in 2005 claims were made against the
defendant in negligence and nuisance. The plaintiff
sought an injunction to
restrain the defendant from causing or permitting stormwater runoff to discharge
onto the Land so as to cause
a nuisance, an order that the defendant carry out
works to abate the nuisance and equitable damages. The pleadings have been
amended
over the years and on the seventh day of a nineteen-day trial the
plaintiff abandoned its claim in negligence. Its claim against
the defendant for
an injunction and damages is now based only in nuisance.
- The
proceedings were heard on 15, 17 and 21 February, 2, 3, 4, 7 to 11, 14, 15 and
18 March and 4 to 8 April 2011. Mr TF Robertson
SC, leading Mr M Green, of
counsel, appeared for the plaintiff. Mr SR Donaldson SC leading Mr S Glascott,
of counsel, and Mr N Broadbent,
of counsel, appeared for the defendant.
- At
the commencement of the trial the plaintiff relied upon a document of 18 pages
entitled "Outline of Opening Submissions" dated
14 February 2011 and the
defendant relied on a document 10 pages entitled "Outline of Submissions" dated
11 February 2011. In an
attempt to identify the real issues the parties were
ordered to prepare an Agreed Statement of Facts. A document of 42 pages entitled
Agreed Facts (Ex PD 12) was handed up in Court on 3 March 2011 but it was not
agreed (tr 225). During final submissions on 6 April
2011 the plaintiff filed a
document of 18 pages entitled "Outline of Hydrology Evidence and Contentions".
It also filed a document
of 6 pages entitled "Plaintiff's Outline of Claim"
together with a document of 2 pages entitled "Proposed Orders" with an attached
plan and drawings.
- During
final submissions on 7 April 2011 the defendant filed and relied upon a document
of 52 pages entitled "Written Submissions".
When the matter concluded on 8 April
2011 the parties sought and were granted leave to file further written
submissions. On 12 April
2011 the plaintiff filed a document of 51 pages
entitled "Plaintiff's Schedule of Documentary Evidence based on Agreed Facts and
Documents referred to in Court" said to be "substantially based on the Agreed
Facts Document" (Ex PD 12). On 18 April 2011 the defendant
filed a document of
85 pages entitled "Defendant's Response to Plaintiff's Schedule of Documentary
Evidence", a document of 3 pages
entitled "Defendant's Supplementary Submission"
and a document of 23 pages entitled "Defendant's Supplementary Chronology". On
10
May 2011 the plaintiff filed a document of 74 pages entitled "Submissions in
Reply" and a document of 9 pages entitled "Appendix:
Reply to Defendant's
response to Plaintiff's schedule of documentary evidence and to Defendant's
supplementary chronology". Judgment
was reserved on 10 May 2011.
Issues on plaintiff's claims
- The
plaintiff makes a number of claims in relation to the defendant's conduct since
1994 as the cause of the alleged nuisance.
- The
first claim is that the defendant permitted the filling of the Northern
Drain by 1995 and failed to create an adequate alternative drainage
route. There
is really no issue that the Northern Drain was filled by 1995. The defendant
conceded that the developer of NPE failed
to comply with condition 43 of the
Development Consent (the construction of a drainage overflow path along the
northern boundary
of NPE). Condition 43 was imposed in circumstances where the
defendant knew that the Northern Drain would be filled during the development
of
NPE and no doubt saw it as a necessary step to facilitate proper drainage of NPE
and the surrounding properties. NPE constructed
the 1200mm pipe, however the
legal title to the drainage network vested in the defendant. The real
issue in relation to this claim is whether in all the circumstances this
was an adequate, alternative drainage route to the Northern Drain.
- The
second claim is that the defendant constructed Elrond Drive with
inadequate culverts and without table drains. There is no issue that there
was
only one culvert under Elrond Drive and there were no table drains constructed
by the defendant. The real issue in respect of this claim is whether in
all the circumstances that single culvert was adequate for the proper drainage
of the Land.
- The
third claim is that the defendant constructed Turnock Street in 1997 with
inadequate culverts and table drains. There is no issue that there
were no
culverts at ground level and there were no table drains constructed by the
defendant. There were three culverts about halfway
up the embankment of Turnock
Street that would only be of any use in a major flood and/or when the Land was
filled. It appears that
the defendant constructed the culverts at that level in
anticipation of the Land being filled. The issue in respect of this claim
is whether in all the circumstances this construction was inadequate for the
proper drainage of the Land
and/or was an impediment to the proper drainage of
the Land.
- The
fourth claim made by the plaintiff is that the defendant failed to
provide adequate fauna access under Turnock Street and Elrond Drive. The
only
way that any fauna can travel under Turnock Street and Elrond Drive is through
the culvert under Elrond Drive and the Turnock
Street culverts. Mr Robertson
indicated that after the appeal to the Land and Environment Court in relation to
the deemed refusal
of the DA to fill the Land (referred to earlier) the
plaintiff "subsequently found through further expert analysis that the frogs
did
cross the road and were seen crossing the road" (tr 74). In those circumstances
this does not appear to be an issue in the case.
- The
fifth claim the plaintiff makes is that the defendant permitted blocking
of drainage of stormwater runoff from the Land and from surrounding
land to the
Natural Watercourse (by reason of approval of development of the Nursing Home)
and has failed to construct an adequate
alternative drainage route. There is no
doubt that the defendant approved the development of the Nursing Home and that
in allowing
development of the Nursing Home and other developments to the north
of the Land the Natural Watercourse to the north of the Land
has been blocked.
This fact needs to be taken into account when considering the other issues in
relation to the adequacy of the drainage
of the Land.
- The
sixth claim the plaintiff makes against the defendant is that it
permitted the extension of Lorien Way without provision for the Northern
Drain
to flow under it and has failed to construct an adequate alternative drainage
route. There is no issue that the defendant permitted
the extension of Lorien
Way without provision for the Northern Drain to flow under it. The defendant
conceded that the extension
of Lorien Way in 1994 blocked the Northern Drain.
This fact needs to be taken into account when considering the other issues in
relation
to the adequacy of the drainage of the Land. That consideration also
needs to take into account the circumstance that the defendant
has resolved to
construct the Blue Jay Circuit Scheme.
- The
seventh claim the plaintiff makes against the defendant is that it
permitted filling of the Eastern Drain between 1992 and 1995. There is
no real
dispute that the Eastern Drain was filled between 1992 and 1995 when the
plaintiff consented to the establishment of batters
on the eastern perimeter of
the NPE and the western boundary of the Land. The fact that the Eastern Drain is
no longer available
for the drainage of stormwater off the Land is a
circumstance to be taken into account in considering the other issues in
relation
to the adequacy of the drainage of the Land.
- The
eighth, ninth and tenth claims the plaintiff makes against the
defendant relate to the Quigan Street outlets. They are respectively that: the
defendant constructed,
or permitted construction, of the stormwater outlets and
gutter diversion at the corner of Quigan Street and Boomerang Street discharging
stormwater runoff onto Lot 13; constructed or permitted construction of a
stormwater outlet near the corner of Quigan Street, Herford
Street and Cudgen
Road and to the west of that intersection discharging stormwater runoff onto
Quigan Street road reserve and then
onto Lot 13; and constructed a stormwater
outlet on the southern edge of Turnock Street near the north eastern corner of
Lot 13 discharging
stormwater onto Lot 13. There is no dispute that stormwater
is being discharged onto the Land from the Quigan Street outlets and
onto Lot
13.
- The
fact that there is stormwater discharge onto the north eastern corner of Lot 13
north of Turnock Street is to be taken into account
when considering the
issue of the adequacy of the drainage of the Land north of Turnock Street
in all the circumstances, including the adequacy of the 1200mm
pipe, the closure
of the Northern and Eastern Drains, the construction of the single culvert under
Elrond Drive, the lack of culverts
at ground level under Turnock Street and the
closure of the Natural Watercourse to the north of the Land (the other drainage
issues).
- The
eleventh and twelfth claims against the defendant relate to other
outlets constructed by the defendant from which stormwater flows onto the Land.
Those
claims are respectively that the defendant: constructed or permitted
construction of a stormwater outlet near the north eastern corner
of Lot 6
carrying stormwater from Pearl Street which directly or indirectly discharged
onto Lots 11-13; and constructed or permitted
construction of two stormwater
outlets on the northern corner of the Land in Lot 11 discharging stormwater onto
that Lot. These facts
are not in serious dispute. They are to be considered in
relation to the other drainage issues.
- The
thirteenth claim the plaintiff makes against the defendant is that it
allowed development within the catchment whereby the volume, frequency,
velocity
and peak flows of stormwater redirected and concentrated through the stormwater
outlets is unreasonably increased. It is
clear that the volume of the stormwater
has increased. There is an issue as to whether the frequency, velocity
and peak flows have increased. There is also an issue as to whether, if
the frequency, velocity and peak flows have increased, such increase has been
unreasonable.
- The
fourteenth claim the plaintiff makes against the defendant is that it
permitted and continued to permit urban stormwater runoff to flow onto
the Land
via the stormwater outlets without appropriate treatment for water quality (eg.
gross pollutant traps and sediment traps
as referred to in DCP 9). There is no
dispute that there are no gross pollutant traps or sediment traps. The
issue is whether the absence of those traps is causative of a nuisance.
- The
fifteenth claim the plaintiff makes against the defendant is that it
failed to maintain on a regular and timely basis, or at all, the drains
which it
owns or is responsible for and which would, if properly maintained, convey
stormwater away from the Land. There is no dispute
that the defendant did not
have a system of regular checks on its drains.
- The
plaintiff claims that the consequences of the defendant's conduct are that: (1)
stormwater runoff pools and remains in and on
the Land more frequently, for
longer periods and in greater quantities than in its natural state and/or its
undeveloped state; (2)
stormwater runoff coming upon the Land is diverted and
altered from its usual and regular course; (3) the quality of the stormwater
runoff coming onto the Land is decreased; (4) stormwater runoff is prevented and
obstructed from passing through and flowing from
the Land into the drains and
the Natural Watercourse; (5) the stormwater runoff coming onto the Land is
redirected and concentrated
and is in greater volumes and with greater velocity
and frequency and higher peak flows; (6) the Land is flooded more frequently,
for longer periods and in greater quantities than in its natural or undeveloped
state; and (7) there have been ecological changes
on the Land (first observed by
the plaintiff in about 2001) including the creation of habitats suitable for
Wallum Froglets.
- Although
not expressly admitted there is really no serious dispute in relation to claims
(1), (2), (4), part of (5), and (6). There
is no issue that the Land has "wetted
up" by reason of some of the defendant's conduct. The real issue for
determination, along with
a number of other sub-issues, is whether that wetting
up amounts to an actionable nuisance against the defendant.
Expert Opinion
- Many
of the issues for determination have required the assistance of expert opinion.
The questions of the adequacy of the 1200mm pipe,
the culverts in Turnock Street
and the Elrond Drive culvert to drain the Land need to be addressed in the
context of the physical
circumstances of the Land, including the soil content
and vegetation. It has also been necessary to review the likelihood of ponding
of the water/stormwater in particular periods creating ephemeral ponding as a
breeding ground for Wallum Froglets.
- The
Court was assisted by the expert opinion of witnesses with expertise in various
fields including hydrology [Dr Stephen Webb (hydrologist/engineer)
and Mr Drew
Bewsher (hydrologist)], vegetation [Dr Andrew Benwell (botanist/plant
ecologist), Dr Anne Clements (plant ecologist),
Mr Andrew Murray
(botanist/vegetation ecologist) and Dr Andrew Smith (applied
ecologist/eco-system management)], soil [Dr Pam Hazelton
(soil scientist)] and
ecology/fauna [Dr Andrew Smith, Dr Michael Mahoney (ecologist/conservation
biologist) and Mr Peter Parker (ecologist/environmental
consultant)]. The
experts gave evidence in concurrent session in their relevant specialties with
Dr Smith giving evidence in two
concurrent sessions. An agenda for discussion
with each group of experts was prepared to assist in the determination of the
issues
in dispute. The parties have addressed their cases and submissions in
part by reference to these categories of expertise.
Hydrology Issues
- The
first area of expert evidence that requires assessment is that of the hydrology
experts, Dr Stephen Webb and Mr Drew Bewsher.
Their evidence is relevant to the
adequacy of the drainage of the Land, in particular the issues in relation to
the adequacy of the
1200mm pipe, the culverts under Turnock Street and the
Elrond Drive culvert. They also commented on other issues such as the level
of
groundwater and the likelihood of ponding on the Land in particular periods.
Opinions of the experts in other specialities will
also impact upon the
hydrology issues. For instance, the nature of the vegetation on the Land at
particular times and the likelihood
or otherwise that the increase in the
stormwater in the circumstances of alleged inadequate drainage changed the
nature of the vegetation
such as to create a Wallum Froglet habitat.
- Dr
Webb's reports are dated 25 August 2010 and 1 March 2011. Mr Bewsher's reports
are dated 2 December 2010 and 21 February 2011.
There are Joint Hydrology
Reports of 22 January 2011 and 3 March 2011. The hydrology experts engaged in a
joint conference and gave
oral evidence in concurrent sessions on 8, 9 and 10
March 2011.
- Dr
Webb is the principal of Stephen N Webb & Associates Pty Limited, Consulting
Engineers, specialising in the provision of floodplain
management and drainage
advice. Dr Webb holds a Bachelor Degree with Honours in Engineering (Civil) from
the University of Canterbury,
New Zealand and is a Doctor of Philosophy
(Hydrology) from the University of New South Wales. He has worked in the area of
hydrology
for approximately 40 years. Mr Bewsher holds a Bachelor Degree with
Honours in Engineering from the University of Tasmania and a
Master of Science
in Civil Engineering from the California Institute of Technology. Mr Bewsher is
the principal of Bewsher Consulting
Pty Limited which specialises in the area of
hydrology including floodplain risk management and design and management of
flooding
and drainage infrastructure projects. Mr Bewsher has been working in
the area of hydrology/hydraulics for the past 34 years.
- Dr
Webb has been visiting the Land since 2003 and has taken many photographs of the
Land over that period. He has reviewed Parish
Maps and aerial photography
together with topographic information to analyse the change in the Land over
time. He has also collected
daily rainfall data from the Bureau of Meteorology
and has analysed surface water levels and groundwater levels from information
along a transect that ran from the southern point of the open drain (gauge SW9)
to the north across Turnock Street and past gauge
SW4 to gauge GW1 ("SW"
denoting surface water and "GW" denoting groundwater). The water level
measurements from the gauges along
the transect are collated in Figure E2 of Dr
Webb's August 2010 Report. Dr Webb has also analysed groundwater in a number of
piezometers
in the Land and collected water quality data from 2003.
- Dr
Webb referred to "flood studies" for the Tweed River that have been carried out
by the defendant in response to flood and development
pressures along the Tweed
River. He formed the opinion that the drainage system in respect of the area and
in particular in relation
to the Land functioned well until the main drainage
paths became obstructed by development in the area. Dr Webb expressed the
opinion
that the filling of the land in the vicinity of the Bowl's Club and the
Nursing Home caused the initial drainage problems by blocking
a major natural
drainage path, the Natural Watercourse, northwards from West Kingscliff to the
Tweed River.
- Dr
Webb was critical of Mr Findlater's drainage study. He claimed that it failed to
correctly and clearly show the existing drains
at the time the study was done
and that the catchment area he used for calculating inflows to the 1200mm pipe
was about half of the
actual catchment (as pointed out by Mr Hill and agreed
with by the defendant in its correspondence). Dr Webb was also critical of
the
defendant's acceptance of Mr Findlater's proposal or recommendation for a
detention basin on the Land to solve the problem caused
by the development of
the NPE blocking the Northern Drain. Dr Webb claimed that solving a drainage
problem in this fashion was "not
good drainage practice". His opinion also
included the following:
In fact it would not been [ sic ] found in any practice manual for
drainage unless the affected landowner was properly compensated after
acknowledgment of the problem.
...
The permanent blocking of the Northern Drain (or equivalent) by this decision
meant that the Subject Land and adjoining properties
wetted up. The 1200 pipe
could not meet the drainage needs for the area even for low flow. After adopting
the detention basin "solution",
Council persisted with seeking approval for the
detention basin from Gales (which was not forthcoming). Council letters
throughout
this period said that there was no need to take any further action on
drainage until the Subject Land was developed, as the unfilled
land provided
adequate retention for now.
They then compounded the drainage problem, at least as far as the Subject
Land is concerned, by constructing Turnock Street/Elrond
Drive with inadequate
drainage structures. This was despite sensible advice to Council by the
consultant designing Turnock Street
(Ray Sargent & Associates (RSA)) that
adequate drainage needed to be provided, and such drainage was dependent upon
the "Ultimate"
drainage scheme (involving a "Future open drain (as per WBN
study)"), which even at that time (1996) RSA showed on their sketch.
- Dr
Webb analysed the collected data in relation to surface water and groundwater
levels north and south of Turnock Street. From that
data he claimed that he was
able to establish a relationship between ponding duration north of Turnock
Street and rainfall assisted
by land-based photographs taken at regular
intervals. He used that relationship to assess the pattern of dry periods and
wet (ponded)
periods north of Turnock Street on the assumption that the culvert
under Elrond Drive was properly maintained and that there was
a reasonable
opportunity for surface runoff to drain to that culvert via a shallow table
drain. Dr Webb established that there would
have only been 7 periods of summer
ponding lasting six weeks or more in the period from 1989 to mid 2010. Dr Webb
concluded that
three of the ponding periods had been in the 4.5 years prior to
mid 2010 that were unusually wet (except for 2007).
- Mr
Bewsher referred to the topography of the Land and concluded that following
local rain and ponding, water would be present for
long periods, weeks and
sometimes months, and would gradually diminish as a result of evaporation and
infiltration. Mr Bewsher said
that he would agree that some slow drainage would
occur in north-westerly, westerly and southerly directions to other areas if the
ground level was lower. Mr Bewsher accepted that during local catchment flooding
when the capacity of the 1200mm pipe was exceeded,
a portion of the flood flows
that may have otherwise travelled in a generally east-to-west direction would
likely have been directed
to the south across the Land. Mr Bewsher concluded
that those flows would have then joined with other flows travelling across the
Land. He expressed the opinion that additional low-level culverts under Turnock
Street would have increased the potential for the
Land to drain.
Increase in stormwater runoff
- There
does not seem to be any issue in these proceedings that the amount of stormwater
coming onto the Land has increased. In this
regard Talbot J in Gales Holdings
Pty Limited v Tweed Shire Council [2006] NSWLEC 85 said at [6] that urban
runoff onto the Land had increased "significantly over recent years as a
consequence of the closing off of
the main flow path to the north and west".
- Mr
Bewsher accepted that the increase has "certainly" been "significant" and had
largely come from a change in the catchment area
to the north flowing onto the
Land (tr 456). Dr Webb calculated it at 200% or three fold from the northern
sub-catchments between
1974 and 2009. Dr Webb expressed the opinion that the
increase had occurred because the northern sub-catchments did not previously
drain onto the Land north of Turnock Street because there was a capacity for the
water to flow into the Natural Watercourse prior
to the development in that
area. Once the development of the Bowl's Club, NPE and Kingscliff Beach Estate
occurred the stormwater
runoff onto the Land increased. This was to be expected
because the area of sub-catchments draining onto the Land had increased by
a
factor of three.
- I
am satisfied that between 1974 and 2009 there has been a 200% increase in the
quantity of stormwater draining onto the Land from
the northern sub-catchments.
The adequacy of the 1200mm pipe
- Prior
to the blockage of the Northern Drain the stormwater from the north in
Catchments 1B, 1C, 1D and 1E (as identified in Schedule
A to this judgment)
flowed down from the north and the Bowls Club but had "a good drain off" to the
west, through the Northern Drain
(tr 450). In the early 1990s NPE and Kingscliff
Beach Estate (further to the north) were under construction and there were
earthworks
at the Bowls Club. The Eastern Drain was also filled in as part of
the NPE development (tr 451). By the time the Northern Drain was
filled the only
flow path for the stormwater runoff out of the northern region was the 1200mm
pipe. There was a small branch drain
coming into the 1200mm pipe from the
Nursing Home area at the western end of the pipe.
- The
plaintiff's case is that the 1200mm pipe was not an adequate alternative to the
Northern Drain and that this inadequacy was a
cause of the increased flow of
stormwater runoff onto the Land. The defendant submitted that it has not been
demonstrated that the
1200mm pipe is, or could sensibly be anticipated to be,
any less effective than the Northern Drain in draining the Land on a day-to-day
basis.
- The
Joint Report of Dr Webb and Mr Bewsher of 22 January 2011 included the following
agreement pertinent to this issue:
33. The experts agree that the filling and development of land to the west
and north-west of the Site and the provision of only a
1200mm pipe has meant
that at the current time, a significant portion of the local catchment flood
flows are diverted south through
the Site, once flood levels in the general
vicinity of the 1200mm pipe reach a level of about 0.9mAHD.
- However
Mr Bewsher expressed the opinion that the 1200mm pipe provided the same measure
of drainage as previously provided by the
Northern Drain (tr 481). Mr Bewsher's
opinion was based on the premise that there was no available description or
detail of the level
or size of the Northern Drain, except for what he could find
in a document referred to as "Figure 5" included in his report dated
2 December
2010. Mr Bewsher described "Figure 5" as "an old undated plan" which he labelled
"Plan of Levels and Ground Features at
North-Western Corner of Subject Site
(Circa 1990)". That label is in issue.
- When
Mr May's description of the Northern Drain at the time he went fishing in it in
1978 and 1991 was drawn to Mr Bewsher's attention
(tr 479), he said that he had
some difficulty with that description when he compared it with what is in Figure
5. The dimensions
of the Northern Drain described by Mr May were not the subject
of any challenge and I accept his evidence that he went fishing on
that
particular drain both in 1978 and in 1991. Mr Bewsher made the point that Mr
May's evidence did not make clear whether the dimensions
that he described were
at that part of the Northern Drain immediately adjacent to the Land. In those
circumstances he suggested that
the "key issue" was the level of the Northern
Drain at the boundary between the north eastern corner of the NPE and the north
western
corner of the Land. Those are reasonable observations in the
circumstances because Mr May's evidence was that he travelled up the
Northern
Drain about a third of a kilometre and there is no evidence of the precise
distance between the Chinderah Drain and the
point at which the Northern Drain
meets the Land.
- Dr
Webb expressed the view that Figure 5 shows the Land and the position of the
Northern Drain at the time that the flows of water
were diverted around the NPE
during the filling of the NPE. He expressed the opinion that Figure 5 depicts a
relatively recent man-made
network of drains in that location. Dr Webb based
this conclusion on the "regular size" of the drains as depicted in Figure 5 both
on the northern and eastern boundaries of the NPE. He emphasised that prior to
the development of NPE the Eastern Drain joined up
with the Northern Drain and
he expressed the expectation that the Northern Drain would be of the dimensions
described by Mr May "right
to the corner of" the Land, at the entrance point of
the 1200mm pipe.
- Irrespective
of this disagreement there is no issue between Dr Webb and Mr Bewsher that
before the stormwater would flow south onto
the Land, the level of the water at
the invert or mouth of the 1200mm pipe would have to reach 0.9m AHD.
- I
am not satisfied that Figure 5 depicts the true position or dimensions of the
Northern Drain prior to it being filled by Baclon
in developing the NPE. Dr Webb
expressed the opinion that absent the Northern Drain the smaller drains "could
not contain the existing
flows" and could not accommodate the rapidly increasing
flows. He described the 1200mm pipe as "grossly inadequate". His oral evidence
was (tr 503):
So a pipe that doesn't carry the flow can't even get into on a lot of
occasions, and even when it tries to get in not very much can
get in, is not the
adequate replacement for anything, in my view.
- Both
Dr Webb and Mr Bewsher were assisting the Court in difficult circumstances where
there was a lack of photographic evidence or
contemporaneous documents relating
to the filling in of the Northern Drain and the establishment and construction
of the 1200mm pipe.
However Mr Henley's note of his conversation with Mr
Findlater on 15 March 1994 and the correspondence between Mr Hill and the
defendant
soon after the 1200mm pipe was installed is of some assistance on this
issue. Mr Hill referred to the ponding along the boundary
line and claimed that
the 1200mm pipe was "under capacity" to cater for stormwater runoff. Mr Hill
claimed that his client's land
was thereby subjected to a greater degree of
flooding than would have occurred prior to the construction of NPE. There is
also the
defendant's letter to the local resident in response to a complaint
about drainage problems on 21 January 2003 in which it made the
admission that
the drainage system had been "rendered inadequate" by development in the area
over the years. This admission is more
general in its terms and not specifically
related to the 1200mm pipe. However it is a matter that is to be taken into
account generally
when considering this issue.
- With
the assistance of the contemporaneous documents and to a lesser extent taking
into account this general admission I am satisfied
that Dr Webb's opinion is to
be preferred. I do not accept that the 1200mm pipe provided the same measure of
drainage as previously
provided by the Northern Drain. I am satisfied that there
was additional stormwater runoff flowing onto the Land that would not have
otherwise flowed onto the Land had the Northern Drain not been filled and had
the 1200mm pipe been adequate. It is not possible to
identify the precise extent
of that additional stormwater runoff. However I am satisfied that the 1200mm
pipe did not replicate the
same drainage capacity that was in place prior to the
filling in of the Northern Drain and Baclon's failure (conceded by the
defendant)
to comply with condition 43 of the Development Consent.
Turnock Street
- The
plaintiff claims that the defendant's conduct in constructing Turnock Street
without any culverts at ground level created an impediment
to stormwater runoff
flowing away from the Land. It claims that this contributed to the wetting up of
the Land such as to constitute
a nuisance.
- The
construction of the culverts half way up the embankment of Turnock Street
appears to have been in anticipation of the plaintiff
filling the Land. However
the question of the adequacy of the drainage of the stormwater runoff from the
Land after the construction
of Turnock Street is to be considered in the
circumstances as they exist rather than in the circumstances as they might exist
should
the plaintiff fill the Land.
- There
is no real issue between Dr Webb and Mr Bewsher that Turnock Street blocked the
south-westerly flow of water from the Land so
that it then flowed in a more
westerly direction to the Elrond Drive culvert. They agreed that the groundwater
levels to the north
of Turnock Street are on average higher than the groundwater
levels to the south of Turnock Street. However they disagree on the
cause of the
higher levels north of Turnock Street.
- The
relevance of the level of groundwater is that when the level is elevated it is
more difficult for water/stormwater runoff to infiltrate
the ground and ponding
is likely to occur. It is also relevant as to the length of such ponding. If
there is a sustained elevation
in the level of groundwater it will be more
difficult for the surface water to infiltrate the ground over longer periods and
thus
there will be longer periods of ponding. Dr Webb and Mr Bewsher agreed that
if the groundwater table has risen close to the surface
very little rainfall is
required to maintain ponding on the surface of the Land.
- Both
experts agreed that the gradient of the Land is north to south. Dr Webb
expressed the view that since the construction of Turnock
Street the flow of the
water south on the Land is a much longer torturous path at a lower flow rate
with the consequence that the
water has longer to infiltrate the ground and
raise the groundwater level. Dr Webb's analysis of groundwater levels during the
period
25 October 2007 to 8 September 2009 is depicted in Figures E3 to E7 of
his Report of August 2010. The average of the groundwater
levels during that
period is depicted in Figure E3. Dr Webb reported as follows [8.3.7]:
It can been seen that the groundwater surface is essentially horizontal
through Turnock Street to the north and then drops off steadily
to the south in
the direction of the South Westerly Drain. I attribute this behaviour to one of
two alternatives - it is because
either construction of Turnock Street created a
groundwater barrier preventing groundwater flows to the south, or the surface
flow
barrier created by Turnock Street forced groundwater recharge north of
Turnock Street artificially raising the groundwater level
in this location. From
either viewpoint, Turnock Street artificially elevates groundwater levels north
of Turnock Street even with
the tabledrain in place.
- Dr
Webb also analysed the results of the readings from piezometers installed in the
Land from June 2003 to February 2010. Those results
are depicted in Annexure F
"Other Groundwater Observations" to Dr Webb's Report of August 2010. The
"elevation data" collected from
the two piezometers located north of Turnock
Street (SP2N and SP3N) are depicted in graphs attached to the Report. Mr Bewsher
did
not comment on these particular readings although he said he "had a look
over them" (tr 570).
- Mr
Bewsher did not perform any comparable analysis of groundwater levels but
disagreed with Dr Webb's analysis. His evidence was that
the reason the
groundwater levels in Dr Webb's Figures E3 to E7 are lower on the southern side
of Turnock Street is because of the
drains that have been constructed in that
area enabling the surface water to flow away to the South-Westerly Drain (tr
551). He gave
the following further evidence (tr 551-553 and 595-596):
Q. But doesn't that tend to suggest then that the groundwater level on the
high side has been increased by reason of the construction
of Turnock Street
because there aren't any drains except for the table drain?
A. I think the issue is that at the time Turnock Street was constructed were
these table, extra drains we see on the southern side
present or not. My
understanding is they were not present at that time.
Q. That is what I am saying. It suggests to me that when you look at the
analysis that Dr Webb has carried out, the groundwater levels
on the northern
side of Turnock Street are obviously higher in the main than on the
right-hand-side, the southern side.
A. Yes.
Q. On the southern side there is the capacity to drain away by reason of the
construction of the drains.
A. Yes.
Q. There is now the capacity on the northern side to better drain away with
the table drain.
A. Yes.
Q. But as you have said that is still not the ideal. Doesn't it suggest that
by reason of the absence of the drains on the northern
side the level of the
groundwater as observed on the northern side that the factor that caused it to
increase to be higher than the
southern side is the presence of the construction
of Turnock Street?
A. Your Honour I maybe put it slightly the other way, the reason why it is
lower on the other side is because the table drains were
constructed,
subsequently constructed there. If those table drains, a great network of drains
had been constructed within the subject
site it wouldn't have been.
Q. I don't have a chart that tells me what the level of the groundwater was
prior to the time of the construction of Turnock Street.
A. No your Honour.
Q. But on this analysis do you suggest that Turnock Street has no impact on
the level of the groundwater?
A. It has an impact to the extent that, and maybe it's not an impact but when
the table drains were constructed on the south-western
side when they came up to
Turnock Street they stopped, as opposed to continuing through. But I am not sure
that that's necessarily
as a result of construction of Turnock Street, it is
just--
Q. A consequence, has to be a consequence, doesn't it, if the water can't get
away and if it flows ever so gently to the right, if
it can get away in a drain
we see the evidence that the groundwater will be less, we see that on the
southern side.
A. Correct.
Q. The increase in water on the northern side, it follows doesn't it, with
the incapacity to get away is likely to increase the groundwater
level?
A. Increase the groundwater?
Q. Level of the groundwater.
A. Are you postulating your Honour a situation where the table drains on the
southern side of Turnock Street had been constructed
and Turnock Street hadn't?
Q. No, I am just asking you what your opinion is hydrologically in respect of
water flowing on to the land not being able to get away
as it used at Turnock
Street having an effect on the level of the groundwater by reason of that
factor, that it can't get away the
way it used to get away and it ponds.
A. Yes, I understand. I believe that the construction of Turnock Street
itself and the compaction that would have taken place underneath,
which gets
back to the first of the two reasons, may have had an impact, though I believe
it would be very minor because it is underlying
sand. I don't believe that these
diagrams demonstrate what you have put to me.
Q. I am not referring to the diagrams, I am just asking you your opinion as
to whether the water, increased water--
A. Understood.
Q. --and the lack of capacity for it to get away would have had
hydrologically a probable impact on the level of the groundwater.
A. Yes, my answer is I believe there is more water, the site is wetter, the
extent of ponding on the northern side of Turnock Street
would have been
marginally higher. It is my opinion that it wouldn't have had any material
impact on the groundwater, was unlikely
to have had any material impact on the
groundwater and I see no evidence from Dr Webb's transect information that that
is actually
what has happened.
Q. Why do you say that?
A. Because the diagrams that he has produced, the blue diagrams I believe
illustrate how an effective drainage system, if probably
(sic) constructed,
could lower groundwater levels in the area. They don't demonstrate the impact
caused by the construction of Turnock
Street at all.
Q. Have you seen evidence of the changes in the groundwater Mr Bewsher?
A. The only groundwater information we have in relation to the subject site,
the majority of it, is in these diagrams and in the table
of information. There
is some piezometer records that Dr Webb presented in his report but principally
it is this information in annexure
E I believe.
...
Q. If you have an increase above what is usually or had usually been on the
land do you say that it can affect the groundwater or
not?
A. I do your Honour.
Q. So that if there is an increase in the volume of water coming on to a site
it can affect the level of groundwater.
A. Yes and I have in my statement said that I believe the site has got
wetter.
Q. Yes and you said that yesterday afternoon, in your evidence you said it is
wetter and the extent of ponding would thereby have
been marginally higher but
you also said that it was your opinion that there had been no material impact on
the groundwater and I
am trying to just analyse what your position is.
A. Understood.
Q. You say, do you, it can have effect on the groundwater?
A. Yes.
Q. But in this instance it did not?
A. Yes, that's correct.
- Mr
Bewsher was asked about the relationship between the level of groundwater and
ponding and said (tr 567):
If the groundwater level was actually above the bottom of the pond that we're
talking about, then the water from the groundwater will
be seeping into the pond
and so, in that case, the groundwater level will be delivering water to the
ponds. If the groundwater stays
up at that level for six weeks, for that period
of six weeks the water in that pond will be coming from the groundwater
entirely.
- The
propositions for which the plaintiff contends include that: (1) there was an
inability for the increased stormwater on the Land
to flow away as it did prior
to the construction of Turnock Street; (2) the groundwater levels north of
Turnock Street increased
by reason of the Land becoming wetter because of the
inability for the increased stormwater to flow away; and (3) this caused ponding
in the area north of Turnock Street from time to time.
- The
defendant submitted that there is no evidence that the groundwater levels north
of Turnock Street in 2003 were any higher than
in 1992. The defendant submitted
that Mr May's evidence establishes that the groundwater levels in the area north
of where Turnock
Street was constructed were very near the surface when Mr May
observed the Land in 1991/1992. Mr May encountered a large pond north
of Turnock
Street when the Land appeared otherwise to be dry. Mr May's evidence was that
there was a wet area north of Turnock Street,
probably in Lot 12, and that the
water came up to just below his knees. He also described this as a "natural
depression". The defendant
also relied upon Mr Murray's survey for the defendant
in 1992 in which he recorded "shallow standing water" being present over a
large
part of the Land in particular in an area north of where Turnock Street now is.
- Dr
Webb accepted that groundwater levels were high between 1989 and 1993 prior to
the construction of Turnock Street and attributed
the elevated water levels to
poor performance of the drains that serve to facilitate the flow of water away
from the Land. The defendant
submitted that whilst this may be the case it
raises two insuperable difficulties for the plaintiff. It was submitted that it
renders
neutral all of the anecdotal evidence of a dry site in the period prior
to the construction of Turnock Street because the observations
that the site
appeared to be well drained encompassed periods of years during which it is
known that the groundwater level was high
enough to create ponding. The second
is that Dr Webb's evidence establishes very clearly that there was a range of
significant drainage
problems on the site not associated with the construction
of Turnock Street or the inadequacy of the 1200mm pipe that were remedied
in
2004 by the creation of the table drains.
- The
defendant submitted that a further difficulty for the plaintiff's claim that
Turnock Street has influenced the groundwater levels
to the north of Turnock
Street is that the elevation recorded by Dr Webb is uniform along the northern
half of the transect. Groundwater
levels are not elevated adjacent to Turnock
Street where the additional ponding is alleged to be occurring. It was submitted
that
no explanation has been proffered to link the alleged elevated groundwater
level 200 metres north of Turnock Street with the diversion
of flows at Turnock
Street.
- Mr
Bewsher agreed that the changes in drainage caused by the filling of the
Northern Drain and the construction of Turnock Street
would result in additional
ponding immediately on the northern side of Turnock Street. He did not dispute
that the surface water
was being diverted but he did not believe that it would
"make much difference at all".
- I
do not regard these as insuperable difficulties for the plaintiff. On the basis
that the anecdotal evidence is given little weight,
the fact that there were
significant drainage problems prior to the construction of Turnock Street means
that the construction of
Turnock Street with no drainage would compound the
problem. There is no direct evidence of the level of groundwater during specific
periods prior to 2003. Assuming the groundwater levels were high prior to the
construction of Turnock Street, I am satisfied that
the construction of Turnock
Street had the impact of increasing those levels because there was less
opportunity for the surface water
to flow away as it did prior to its
construction.
- There
is no issue between the two experts that the construction of Turnock Street has
made the Land wetter. The reason for that is
a lack of capacity for the water to
flow under Turnock Street with the necessity for the water to flow to the south
west to escape
through the Elrond Drive culvert. I accept Dr Webb's evidence
that the flow of the water was slowed by reason of the construction
of Turnock
Street without ground level culverts. I also accept Dr Webb's evidence that the
path of the water flow and the rate of
the water flow caused the Land to become
wetter with a consequence that ponding occurred. I prefer the evidence of Dr
Webb in relation
to the impact of the construction of Turnock Street on the
wetting up of the Land and the higher levels of groundwater to the north
of
Turnock Street.
- The
natural flow of the stormwater through the Land was diverted to the south west
by the construction of Turnock Street. It was not
possible for the stormwater to
drain at Turnock Street other than through the Elrond Drive culvert. I have no
doubt that had the
defendant constructed culverts at ground level the stormwater
runoff could have drained through those culverts. I am satisfied that
the
culverts as constructed were inadequate for the draining of the stormwater
runoff from the Land. I am also satisfied that the
construction of Turnock
Street impeded the efficient drainage of the stormwater runoff from the Land.
Elrond Drive culvert
- The
original drawings produced by Ray Sargent on 29 July 1996 in relation to the
construction of Turnock Street proposed three 1500mm
pipes in the vicinity of
the Elrond Drive culvert. Notwithstanding the covering letter advising on
construction of three 1500mm pipes,
the defendant constructed only one 900mm
pipe through which the stormwater runoff could drain from the Land.
- Dr
Webb expressed the opinion that the blockage of the culvert in 2003 was the
principal cause of the ponding at that time. Mr Bewsher
acknowledged that whilst
the blockage of the culvert "would have caused ponding, inadequate maintenance
of the downstream drain leading
from the pipe, could also have caused ponding".
- It
may be that the Elrond drive culvert would have been adequate had there been
culverts under Turnock Street at ground level. However
I am satisfied that the
single 900mm culvert under Elrond Drive in the absence of culverts at ground
level under Turnock Street,
with the increase of the stormwater runoff onto the
Land, was inadequate to allow that stormwater runoff to flow off the Land
without
ponding.
Ponding
- The
experts sought to identify wet and dry periods to assess the likelihood of
ponding at particular times and particular periods.
As I have already outlined
the plaintiff's case is that the wetting up of the Land was caused by the
defendant's conduct and one
of the consequences of the wetting up of the Land
was the creation of the ponding suitable for breeding of Wallum Froglets. The
type
of ponding suitable for the breeding of Wallum Froglets is "ephemeral
ponding" defined by Dr Webb as a "closed depression that temporarily
stores
surface water for a defined period. It may be at a low topographic level and
sustained at least partly by groundwater, or
it may be more elevated and
sustained by regular surface water inflows, have a semi-impervious base, and
could be sustained partly
by a perched (or locally elevated) water table".
Ephemeral ponding is to be understood to be for a period of six weeks or more in
summer.
- Dr
Webb used the measured wet and dry periods from available records for the period
2007 to 2010 to derive relationships between rainfall
and observed wet and dry
periods and then applied those relationships to predict the wet and dry periods
from 1989 to 2010 based
on certain assumptions. Dr Webb used the surface water
level observations across the transect, and in particular the readings in
the
shallow pond at SW4 to assess the frequency of ponding north of Turnock Street.
He collected daily rainfall data from the Bureau
of Meteorology website and
plotted it in six-month blocks. He then plotted the observations at SW4
commencing on 25 October 2007
up to 1 July 2010. The period over which
observations are available at this site was used as the "calibration period".
Relationships
between rainfall and water level were obtained for that period by
considering the wet and dry periods and the rainfall distribution.
On completion
of the calibration period analysis and plotting of the wet and dry periods, the
photographs of the area were used to
check the calibration. Dr Webb assumed that
the Wallum Froglet required a period of about five to six weeks to metamorphose
in summer
and a longer period of up to six months at other times.
- Dr
Webb concluded that between 1989 and 2010 there were only seven periods of six
weeks or more of ponding north of Turnock Street:
one period in each of the
years 1990, 1994, 1999, 2003, 2006, 2007 and 2009. He concluded that there was
one period of six weeks
ponding in winter in 1998 and one period of nine weeks
ponding in the winter of 1999 with further periods in the winter of 2008 of
11
weeks and 3.5 months in 2009.
- Mr
Bewsher made a number of criticisms of Dr Webb's analysis. The first was the
suggestion that SW4 (a surface water gauge in the
transect north of Turnock
Street) "may not be" representative of site ponding except when levels rise
above the local undulations
around it, and identified a measure of 0.8m AHD. Dr
Webb answered this criticism by observing that SW4 is one of the lowest points
in the landscape immediately north of Turnock Street and relatively distant from
the Elrond Drive culvert and the table drain. He
observed that it is one of the
last local depressions to dry up and that when it is dry there is no extensive
ponding left immediately
north of Turnock Street.
- Mr
Bewsher's next criticism was a suggestion that there are number of anomalies or
inconsistencies in the water level records presented
by Dr Webb. He identified
five dates around which he claimed the inconsistencies in the SW4 water levels
occurred. However he later
removed four of those dates, identifying them as
"outliers" for the purpose of his proposed model, leaving only one on 20 October
2008. He claimed that such an anomaly may be a measurement error at SW4. Dr Webb
answered this complaint by stating that the SW4
data for that date was
consistent with the behaviour of the other data points along the transect.
- Mr
Bewsher's next criticism was a suggestion that rainfall records used by Dr Webb
were not representative of conditions on the Land.
Dr Webb used the rainfall
recorded at Tweed Heads, about 7 km from the Land, and compared that data with
the rainfall data at the
Bowls Club (up to 2008) and found "very good
consistency". Dr Webb conceded that there would be some variability with smaller
storms
and accepted that the observed rainfall on those days may not be the same
as that which occurred on the Land.
- Mr
Bewsher's next criticism was a suggestion that inconsistencies might be due to
changes in groundwater levels. Dr Webb observed
that changes in groundwater
levels tend to be related to rainfall but on a longer term basis than surface
ponding. He observed that
Mr Bewsher's new model (referred to below) ignores
groundwater and he therefore could not see this as a constraint. Mr Bewsher also
referred to changes in ground levels near SW4. Dr Webb observed that the water
level was measured relative to a fixed stake and he
could not see how this would
have introduced any errors. He did not observe any other factors that could have
affected the ground
level at SW4. Mr Bewsher also referred to changes in
vegetation (affecting evapo-transpiration) as a possible cause of inconsistency.
Dr Webb's response to this was that there was little vegetation in or near SW4
and "certainly insufficient to cause any significant
variation in
evapo-transpiration".
- Mr
Bewsher also complained that Dr Webb failed to include any specific duration
associated with the rainfall. Dr Webb responded to
this complaint by observing
that in this regard judgment is required. He said that rain tends to occur in
bursts and when looking
for bursts he did not generally extend the duration
beyond one week because by that time the first day of the rain would have
receded.
Mr Bewsher also claimed that Dr Webb ignored any rainfall less than
60mm. Dr Webb suggested that this claim is incorrect because
60mm was the
trigger in his study for the change from dry periods to wet periods but that any
ongoing rain after that was in fact
considered. Mr Bewsher also claimed that Dr
Webb had taken no direct account of infiltration or evaporation. Dr Webb
observed that
his assessment was based on observations of water levels and
rainfall and that infiltration is dependent on the properties of the
soil and
the level of the groundwater table. He said that water levels vary due to the
input of rainfall and the losses due to infiltration
and evaporation.
Accordingly he implicitly took them into account but did not let them vary
throughout the year.
- Mr
Bewsher also complained that Dr Webb failed to take any direct account of
smaller follow-up rainfall. Dr Webb claimed that this
was also incorrect because
follow-up rainfall was allowed to extend the wet period if it was significant.
- Mr
Bewsher also complained that Dr Webb did not simulate SW4 directly. Dr Webb said
that this is partially true but that it was not
the purpose of his assessment.
His purpose was to establish the frequency of 6 week ponding periods in summer
under the current drainage
and topographic conditions. It was the duration of
the ponding that was critical, not the precise level of SW4.
- Mr
Bewsher's next criticism was that Dr Webb failed to consider antecedent rainfall
and the water level at SW4 prior to the onset
of rainfall. Dr Webb said that
this was incorrect. He observed:
After a dry period I found that a certain minimum amount of rainfall was
required to commence ponding. This is analogous to the "initial
loss" commonly
used in hydrologic models. Ongoing significant rainfall was allowed to extend
the duration of ponding thus allowing
for antecedent conditions. A further
factor is that once the ponding level dropped below the cessation of flow line
thus inducing
a dry period, very little time was required for SW4 to in fact
become completely dry.
- Mr
Bewsher also observed that "two operators of [Dr Webb's] procedure will likely
get different predictions". In response Dr Webb
observed:
Once the assessment criteria were established it was remarkably easy to carry
out the empirical assessment. The initial assessment
was carried out by one of
my staff. I then checked it and found that I needed to make very few changes.
The issue that caused the
most changes was in determining when follow-up rain
was sufficient to extend the period of ponding.
- Mr
Bewsher concluded as follows:
19. Hydrology is not a precise science. All hydrological models are to some
extent only approximations of reality. It is normal to
include assumptions and
other approximations in such modelling. The key issue is whether the
uncertainties that these create, make
the predictions of any value. Expressed
another way, is the model 'fit for purpose'?
20. In my opinion, the Court can't be confident that Webb's procedure is
'robust', i.e. one can't be confident that it will produce
reliable results
outside the 2 year calibration period.
21. Further given the nature of the procedure, it's difficult to test the
sensitivity of the procedure to different assumptions about
the 'cessation of
ponding' level.
22. It is not possible to prepare normal statistical measures of the
'goodness of fit' for this procedure (as would usually be undertaken
for a
hydrological model).
23. I have analysed the statistical correlation between the observed SW4
water levels records over the 2 year period ... What this
shows is that SW4
levels are more highly correlated to the number of raindays rather than the
rainfall itself. The implications of
this are that it's not just the quantum of
rainfall that's important to ponding at SW4, but it's the way that the rain is
temporally
distributed that is crucial in predicting behaviour at SW4. In my
opinion this significantly limits the accuracy of Dr Webb's procedure
and
confirms the reservations I expressed in my original Statement that there may be
a large uncertainty in the predictions he has
provided.
- In
response Dr Webb observed:
I disagree that my Empirical Assessment is not robust. I carried out informal
sensitivity tests in setting up the criteria. The "model"
is fit for the
purpose. Somewhat surprisingly ... Mr Bewsher gets exactly the same number of 6
week summer ponding events in the
period of assessment as I did.
- Mr
Bewsher had originally proffered what was referred to as the "Pocket Model" for
the purpose of predicting the periods of ponding
on the Land. He later adopted a
model referred to as the "SW4 model". Mr Bewsher explained that the Pocket Model
was a "quick and
easy simulation of what might happen" in relation to ponding if
there are impermeable layers in the soil. He gave evidence that he
did not know
whether they existed or not although he accepted Dr Hazelton's opinion in the
Joint Report dated 3 March 2011 (Ex PD4)
that there was high degree of
permeability in the soil (tr 610). I am not really assisted by the Pocket Model
because the evidence
does not support the assumption upon which it was based.
Indeed Mr Bewsher described the SW4 Model as a "much better model" (tr 612).
- The
SW4 model was described by Mr Bewsher as approximating the physical processes on
the Land including rainfall, evaporation, infiltration
and spill from the SW4
area. It uses daily rainfall and evaporation records and produces daily
estimates of the water level at SW4.
Mr Bewsher then used the model to hindcast
1989-2007 water level behaviour.
- From
the SW4 model Mr Bewsher predicted ponding periods of 6 weeks or more over the
period as follows at 0.68m AHD: 1 in the years
1988/89, 1990/91, 1991/92,
1993/94, 1994/95, 1995/96, 1998/99, 1999/00, 2008/09, 2009/10, and 2 in 1989/90.
He predicted fewer periods
at 0.70m AHD: 1 period in 1988/89, 1989/90, 1990/91,
1991/92, 1993/94, 1994/95, 1999/00, 2009/10; and fewer again at 0.72m AHD: 1
period in 1988/89, 1989/90 1990/91 and 1993/94.
- Dr
Webb was critical of Mr Bewsher's SW4 model. He said it is a "mathematical
model" often referred to as a "black box" in which the
inputs (rainfall, etc)
are converted to outputs (the level at SW4) with very little known of what
happens in the "box". Dr Webb expressed
the opinion that even if such a model
provides a good prediction of the outputs from the inputs, it is "dangerous" to
use such a
model to predict outputs beyond the calibration period. He emphasised
that his own approach did not involve a mathematical model
and claimed that Mr
Bewsher's SW4 model had a number of flaws including: (1) it fails to consider
the impact of the groundwater table;
(2) it fails to relate infiltration to the
position of the groundwater table; (3) the coefficient for infiltration bears no
relationship
to the actual properties of the soil; (4) it fails to consider the
relationship of the soil moisture store to the initial level of
the groundwater
table; and (5) the mathematical weighting of 10 given to the "dry" readings at
SW4 is entirely arbitrary. Dr Webb
claimed that the SW4 model could not reliably
be used outside the period against which it was calibrated.
- As
can be seen by the comparison between the experts' predictions of ponding, Mr
Bewsher predicted far more periods of ponding prior
to the construction of
Turnock Street in 1997. Dr Webb predicted two periods, in 1990 and 1994, whereas
Mr Bewsher predicted eight
periods over the period 1988 to 1996 (at 0.68m AHD).
The only years in which both experts predicted ponding prior to 1997 was when
Dr
Webb predicted one period in 1990 and 1994 and Mr Bewsher predicted two periods
in 1989/90 and one in 1993/1994. After 1997, Dr
Webb's analysis showed five
periods of ponding between 1999 and 2010 and Mr Bewsher's analysis showed only
four periods of ponding.
After 1997 they both predicted one period of ponding in
the year 1999/2000 and one in 2008/2009. In the whole period Dr Webb concluded
that there would have been seven periods of ponding and Mr Bewsher concluded
that there would have been twelve periods of ponding
(at 0.68m AHD) or eight
periods (at 0.70m AHD) or four periods (at 0.72m AHD). Mr Bewsher's Pocket Model
concluded that there would
have been thirty nine periods of ponding, twenty five
before the construction of the Turnock Street and the balance after its
construction.
- The
Joint Report (Ex PD4) dated 3 March 2011 included the following ("SW" in this
context refers to Dr Webb and "DB" refers to Mr
Bewsher):
SW provided further information to DB by email on 3 rd March 2011 as set out
below for the 21 year period from 1989/90 to 2009/10.
This information provide
estimates of ponding frequencies under different scenarios which SW did not
consider in his original assessment:
Cessation of Ponding Level 0 .7 mAHD
Original = 7 summer ponding events of 6 weeks or more (DB = 7) 5 week
ponding = 8 summer ponding events of 5 weeks or more (DB = 9)
4 week ponding = 17 summer ponding events of 4 weeks or more (DB = 14)
Cessation of Ponding Level 0.68 mAHD (6 weeks ponding or more)
10 summer ponding events of 6 weeks or more (DB = 11)
Cessation of Ponding Level 0.72 mAHD (6 weeks ponding or more)
4 summer ponding events of 6 weeks or more (DB = 3)
SW & DB agree that the ponding frequencies set out above for both
approaches are essentially the same, even though SW & DB
disagree with the
methodologies used by the other.
- In
the concurrent session of evidence on this topic on 10 March 2011 Dr Webb said
(tr 617):
Anyway, I took the current relatively well-drained conditions and I took the
rainfall period. My purpose was to find, for a six week
period of summer
ponding, how many occurrences were there. That was my objective. That's what I
did. And I got 7.
Mr Bewsher, with his what I call a black box model - I am not being impolite
in using those words. It sounds like I am but that is
the terminology if you
have something in between an input and an output and you have things happening
in it.
I also suggest he does not have enough things happening in it, because he
does not have enough information. That is why it is a black
box. But you have an
input and an output.
He also got 7, as you see from our joint report.
Certainly, what I was trying to do was find the number of occurrences. We
essentially get the same number. So, I do not agree with
his model at all. He
quite clearly does not agree with my model, but we do get the same answer.
During the course of conferencing, I did a quick assessment, because he has
looked at four week and five week periods as well. I did
a quick assessment of
those. They have not been fully checked.
Once again, I found that I got similar answers to his approach. So, in the
end, I suppose, I do not "care". That is probably not the
right word, but we are
both getting the same - to assist the Court we are getting the same answers and
that is what we have written
in our joint report.
- The
plaintiff urged caution in accepting that where each of the experts predicted a
ponding period in the same year, the ponding period
was more likely to have
occurred. The plaintiff submitted that such reasoning overlooks the manifest
problems with the SW4 model
and Dr Webb's detailed concerns with it. It was
submitted that where the opinions of Dr Webb and Mr Bewsher differ, Dr Webb
should
be preferred. The plaintiff propounded a number of reasons for this
preference including: (1) that Dr Webb had visited the Land over
several years
and had the opportunity to observe first-hand the operation of the hydrological
processes affecting the Land and the
existence of ponding over extended periods,
whereas Mr Bewsher's only encounter with the Land was three visits over a
three-month
period; (2) that Dr Webb meticulously used a range of materials,
including voluminous aerial photography, topographic data, rainfall
data and
direct measurements of water levels and water quality to assemble a history of
changes to land use and catchments since
the Land was in its natural state to
ascertain flow paths, groundwater and the effect of pollution from run-off,
whereas Mr Bewsher
did no such thing; (3) that Mr Bewsher had apparently
discarded his Pocket Model and had failed in cross-examination to properly
explain the operation of his new model for "retrofitting" rainfall data; (4)
that Dr Webb's criticism of Mr Bewsher's SW4 model was
eloquent; (5) that Mr
Bewsher failed to take into account groundwater levels and manipulated three
coefficients solely for the purpose
of retrofitting the curve to levels observed
at SW4; and (6) Dr Webb's diagrams of the groundwater levels along the transect
which
uses a level survey conducted over an extended period provides an
indication of the effect of the presence of Turnock Street on groundwater.
- Dr
Webb's attention to detail and the care with which he applied his expert
knowledge to the voluminous material upon which he relied
was extremely
impressive. Mr Bewsher was in a much more difficult position because as he put
it there was a "great shortage of time"
within which to prepare his expert
opinion. His first attempt to provide assistance to the Court with his Pocket
Model was recognized
by him as dependent upon an assumption that may not be
justified, and ultimately as I have found above was not justified. Both experts
defended their respective methodologies and analysis and I am sure that both
were attempting to assist the Court in reaching a conclusion
in these difficult
circumstances. There is no doubt that each had to apply a level of judgment in
making the predictions of ponding
over the years. I am satisfied from each of
their approaches that on the balance of probabilities ephemeral ponding has
occurred
on the Land prior to the construction of Turnock Street and after its
construction.
Quigan Street problems
- The
plaintiff's claims in relation to the stormwater outlets in the Quigan Street
area have changed over time. However Dr Webb gave
the following evidence in
relation to the outlets (tr 653-654):
I have had the advantage over Mr Bewsher of being able to observe the
situation at Quiggan (sic) Street since 2003.
There have been several things happening there. One is that the actual head
work structure, where the pipes come in, has always been
a bit unsatisfactory. I
have discussed it with council on a number of occasions. Then it has failed in
different ways and it has
been repaired, but only repaired in what I would call
a stop gap way, or patching.
When I visited it in December last year, it had, in my words, completely
collapsed.
The importance of this is that, in its present state, it is unsafe, I
believe, to public risk. And the water sort of flows over the
structure and down
into the channel, and tries to go further downstream.
The other important thing about it is that, historically, there has been a
channel below it for a very long time, which may or may
not have been developed
by the water flowing down, or by efforts to stop the water ponding within the
site.
Gales, during the period that I have been engaged, did clean out that
channel, right down through to the south-westerly drain and,
immediately,
scouring occurred in the channel, and the sand shifted from the top to the
bottom and started to block the channel up
again.
It became apparent to me - well, it was apparent before but - what we really
needed was a structure that collected the water, reduced
the velocity, and then
the velocity of water coming out of the energy dissipation structure was such
that you could maintain a channel
before that without scour.
To achieve that, the normal process is to have an energy dissipation
structure. That's why I suggested at that time that that's what
should be
installed when the whole structure is re-engineered. I have discussed that with
council.
...
It is quite a steep drop from where these pipes come in from the road down to
the land. Unless you do something, there is going to
be a high velocity at the
foot of the bank. It is really as simple as that, as I see it.
- There
is no issue that this problem exists. The Quigan Street outlets are clearly in
disrepair. During the course of the trial it
was suggested that the defendant
would repair it. I am not aware whether that has occurred at this stage.
- The
inadequacy of the 1200mm pipe combined with the construction of Turnock Street
without any drainage culverts at ground level,
the 900mm capacity of the Elrond
Drive culvert and the 200% increase, or the significant increase, of stormwater
runoff onto the
Land, resulted in what has been described and adopted by the
experts as a "bottleneck" of the flow of the stormwater runoff to the
south
western corner of the Land. The disrepair of the Quigan Street outlets caused an
increase in the velocity of the stormwater
from the outlets, causing an adverse
impact on the Land.
- I
am satisfied that the defendant failed to install adequate drainage to enable
the stormwater runoff to flow off the Land resulting
in the wetting up of the
Land and at times ephemeral ponding suitable for the breeding of Wallum
Froglets.
- I
am also satisfied that if the culverts under Turnock Street had been at ground
level rather than approximately half way up the embankment,
and if the culverts
under Elrond Drive had been constructed in accordance with the advice (i.e.
three 1500 mm pipes), the "bottleneck"
would not have been created.
Vegetation/Soil Issues
- Five
experts assisted the Court on vegetation/soil issues: Dr Andrew Benwell, Dr Anne
Clements, Mr Andrew Murray, Dr Andrew Smith
and Dr Pamela Hazelton.
- Dr
Andrew Benwell is a botanist and plant ecologist. He provides consultancy
services for Ecos Environmental Pty Ltd and has performed
work for state
government departments and local councils. He holds a Diploma of Horticulture
from the Victorian College of Agriculture
and Horticulture, a Bachelor of Arts
(Honours) (Biogeography) from the University of New England and is a Doctor of
Philosophy in
plant ecology from the University of New England. Dr Benwell has
been working in his field of expertise for approximately 30 years.
- Dr
Clements is a plant ecologist and principal of Anne Clements & Associates
Pty Ltd, a company specialising in botanical conservation
assessment and the
development of conservation strategies. Dr Clements holds a Master of Science
degree from Macquarie University
and is a Doctor of Philosophy the thesis for
which examined the vegetation of sand masses of the mid-north coast of New South
Wales.
Dr Clements has been working in her field of expertise for approximately
25 years.
- Mr
Murray is a botanist and vegetation ecologist with 25 years experience in field
surveying and vegetation mapping on the far north
coast of New South Wales. He
is the principal of AS Murray & Associates and holds a Bachelor of Science
(Botany and Oceanography)
from the University of New South Wales.
- Dr
Smith specialises in eco-system management and biodiversity conservation. He is
the principal of Austeco Environmental Consultants.
He was an academic for
sixteen years in the Faculty of Natural Resources, University of New England. He
holds a Bachelor of Science
(Honours) degree from the University of Sydney and
is a Doctor of Philosophy. Dr Smith has been working in his field of expertise
for approximately 20 years.
- Dr
Pamela Hazelton, a soil scientist, is the program head, coordinator and lecturer
of the Master of Environmental Engineering Management
at the University of
Technology, Sydney. Dr Hazelton provides consultancy services through PA
Hazelton Soil Survey and Investigations
Pty Ltd. She holds a Bachelor of Science
from the University of Sydney and is a Doctor of Philosophy. Dr Hazelton has
been working
in her field of expertise for approximately 30 years.
- The
experts provided a number of reports being: Dr Benwell of December 2010 and 2
February 2011; Dr Clements of 24 January 2011; Mr
Murray of 2 December 2010; and
Dr Smith of 27 August 2010. Each of these experts was also a signatory to the
Joint Report of 12 February
2011. Dr Hazelton provided a report of 21 January
2011 (and her Joint Report with the Hydrologists of 3 March 2011). Evidence was
given in concurrent session on 11 March 2011.
- Although
the evidence of the vegetation and soil experts during the concurrent session
was addressed in accordance with an agreed
agenda for discussion, the real issue
for determination is whether the wetting up of the Land north of Turnock Street
after the construction
of Turnock Street in 1997 caused the vegetation to change
so that a Wallum Froglet habitat was established when it had not otherwise
existed prior to the construction of Turnock Street and the wetting up of the
Land.
- The
vegetation evidence is also relevant to the hydrology issue of whether the Land
became wetter after the construction of Turnock
Street in 1997. However it is
unnecessary to analyse the vegetation evidence in relation to that issue because
the hydrology experts
agreed and I have already found, that the Land to the
north of Turnock Street became wetter after the construction of Turnock Street.
If there were species north of Turnock Street after 1997 that thrive in wet
conditions that were not present prior to the construction
of Turnock Street in
1997 there would be further justification for the conclusion that I have already
reached that the Land became
wetter after 1997. However, as I say, it is not
necessary to analyse the evidence for that purpose.
- The
plaintiff submitted that the wetting up of the Land north of Turnock Street
caused the vegetation north of Turnock Street to become
more suitable as frog
habitat because of the increase in sedges and wet vegetation and the reduction
in grasses and exotic species
that had previously been prevalent. The plaintiff
also submitted that there was a change in the abundance of the sedge type
species
to the north of Turnock Street that contributed to the establishment of
suitable habitat for the Wallum Froglet because it supplied
one of three
essential characteristics identified for that habitat: (1) slightly acid soils;
(2) Wallum vegetation, in this case
sedge wetland vegetation; and (3) the
presence close to that vegetation of ephemeral ponds. It was submitted that the
hydrological
cause, the wetting up of the Land, is the only probable explanation
for the change in the vegetation because some species disappeared
from the south
of Turnock Street and other species became much more prevalent to the north of
Turnock Street after 1997.
- The
defendant submitted that prior to the construction of Turnock Street plant
species typical of the Wallum Froglet habitat were
dominant both north and south
of Turnock Street and the construction of Turnock Street has not affected
vegetation composition. The
defendant also submitted that any emergence of
vegetation north of Turnock Street suitable for Wallum Froglets is due to land
management
techniques such as slashing and not hydrological changes.
- The
determination of this issue requires an assessment of the vegetation on the Land
prior to and after the construction of Turnock
Street. For convenience I will
simply refer to the date 1997 in dealing with these comparisons. In expressing
their opinions in relation
to the nature of the vegetation on the Land prior to
1997, the experts relied in part on Mr Murray's 1992 vegetation survey referred
to earlier in this judgment. In expressing their opinions on the vegetation on
the Land after 1997 the experts relied in part on
the survey conducted by Dr
Smith and Mr GN Elks in 2007 (Elks G and Smith A (2007) Vegetation of Gales
Holdings, West Kingscliff. Austeco Environmental Consultants).
- The
vegetation experts agreed in their Joint Statement (Ex PD 2) that "vegetation
communities on the low-lying generally tree less
parts of the site were similar
north and south of Turnock Street" prior to the 1997. All of the experts agreed
in concurrent session
that the surveys show that the species composition and
vegetation communities on the Land prior to 1997 was different to the species
composition and vegetation communities on the Land after 1997 (tr 699-701).
- Mr
Murray expressed the opinion that elevated water tables and increased frequency
and duration of high water events would cause the
emergence of species such as
sedges, for instance schoenoplectus mucronatus and lepironia
articulata . He said that there is a suite of species that he would expect
to see more prevalent on the Land if there were permanent levels of
change to
the water table. He accepted that those species are present in the "wetter
parts" of the Land but said that they have not
really taken over to the extent
that he would expect (tr 713).
- Mr
Murray analysed a 1995 aerial photo and observed tracks all over the Land and
concluded that "every available piece" of the Land
had been driven over. He also
expressed the view that there is a whole range of species that are assisted in
their growth by slashing.
One of them is the exotic grasses that are on the Land
and others such as rhizomatous grasses like the common reed, with
underground roots so that when slashed they regrow easily and quickly.
- Dr
Benwell expressed the view that slashing rather than the wetting up of the Land
had changed the whole plant community. He said
that if the vegetation had
changed because of the wetting up of the Land he would expect to see different
species that are characteristic
of wetter soils and a higher water table. He
said there was no sign of such species coming in but rather the vegetation had
been
cut back all the time by slashing and it was going into an early regrowth
phase. He said it is basically the same plant community
but just a different
stage of growth (tr 714). Dr Benwell conceded that one species that would emerge
because of the wetting up of
the Land, sphagnum moss , was growing in the
ruts on the Land north of Turnock Street (tr 715). However he expressed the view
that any change in the species
composition and vegetation communities is not due
to the increase in the wetness of the Land north of Turnock Street (tr 715).
- Dr
Clements said that the growth of sphagnum moss is a real indicator of how
wet the soil is at the time of observation (tr 718). Her view was that the
species composition and vegetation
communities have changed because of the
increase in the wetness of the Land. Dr Clements said that slashing has an
effect on the
"structure" of the species but the vegetation community remains
the same and the species composition remains very similar (tr 721-722).
- It
is accepted by the experts that blechnum fern was a dominant species at
the time Mr Warren conducted his surveys in 1992 and 1996. It is also accepted
that blechnum fern has always been on the Land. However Dr Clements
observed that when there is an increase in moisture there is an increase in the
occurrence
of blechnum fern and it is more abundant where the soils are
wetter.
- Dr
Smith has walked over the Land since 2003 and said that he had observed that the
vegetation north of Turnock Street had become
characteristically wetter over
time. He gave the following evidence (tr 724):
Sphagnum moss is a very important indicator of a swamp wetland and it simply
doesn't occur to the south, and it didn't previously
occur to the north. So it's
something that has accumulated slowly over time. And it also persists in areas
that are slashed.
So while I accept that there is a difference in the structure and appearance
of vegetation of Turnock Street as you cross from the
unslashed froglet area to
the slashed grassland to the north, I took - intentionally took note of what was
happening to the Sphagnum
moss, and the Sphagnum moss was continuing to the
north in the slashed areas. Because it's low growing, you wouldn't expect it to
be affected by slashing.
So I think that species, that single species alone, is sufficient evidence
that the area to the north has become wetter, because you
simply don't get that
plant growing in conditions other than frequent high moisture level near the
ground surface.
- The
abundance of sphagnum moss is greater close to the northern side of
Turnock Street than elsewhere. There is no abundance of sphagnum moss to
the south of Turnock Street. The presence of the drains south of Turnock Street
was identified as a factor for the absence of the
sphagnum moss on that
side of the street.
- It
is understandable that the vegetation experts focused on whether the Land was
wetter because that was an issue in the proceedings
until the hydrology experts
agreed that the Land was wetter. I have found that the Land became wetter
because of the inadequacy in
the drainage as outlined earlier. The issue for the
vegetation experts is whether that wetness caused a change in the vegetation
north of Turnock Street such that a Wallum Froglet habitat was established when,
if the Land had not been wetter, it would not have
been established.
- The
following exchange in the concurrent session is of some significance (tr
731-732, 734, 743):
HER HONOUR: No. I am asking you what species established or changed north as
a result of the increased wetness, in your opinion.
DR CLEMENTS: They increased in abundance north. They have always been hanging
around, but they increase in abundance once you increase
the water.
HER HONOUR: There is nothing new?
DR CLEMENTS: There is nothing totally new. They are in lower numbers south,
but when you put more water on it, it becomes more favourable
for these native
wetland plants to grow. When you take the water away, the exotic pasture species
are more successful.
DR SMITH: Could I ask Dr Clements, does that include sphagnum moss, because,
as far as I am aware, that is actually a new record north?
DR CLEMENTS: It is a native wetland plant. That is a new record but it
historically would have occurred, because we have - the soils
are telling us
historically.
DR SMITH: Pre drain.
DR CLEMENTS: Pre draining and pre clearing for agriculture. They probably
occurred then. Then (sic) may have occurred in some flood
event post the drains,
when drains weren't working, or something similar, and you are just lucky when
you pick it up.
HER HONOUR: So, the species are the same. There is just more of them.
DR CLEMENTS: Yes.
MR MURRAY: ... I certainly agree with the fact that we have the same
essential vegetation type ..
...
HER HONOUR: Yes. I think everybody agrees there is no difference in the
species or the vegetation on the north side of the land prior
to 1997 and post
1997, except for the moss. Is that right?
DR CLEMENTS: No, because pasture species do not grow under water. So, what I
am seeing north of Turnock Street is a loss of the exotic
pasture species; a
massive decrease in the occurrence of those pasture species.
The other thing I noticed--
HER HONOUR: Sorry, there is nothing new.
DR CLEMENTS: In terms of species, no, there is nothing new. You just get a
decrease in occurrence of pasture species north of Turnock
Street because
pasture species do not grow under water.
HER HONOUR: ... The fact is, as I could find after this very helpful
discussion, there was no change in species. Is that correct?
DR SMITH: Apart from the moss.
DR CLEMENTS: And the decrease.
DR BENWELL : Changing the structure of the vegetation.
...
HER HONOUR: So, I think the common factor is that the species haven't
changed.
DR BENWELL: Yeah, no, the species list for the site is the same, more or
less.
HER HONOUR: Whether they be slashed or not?
DR BENWELL: Yes, yeah, I think if you did a survey right across the whole
slashed area you will pick up all the species in some abundance
or other.
- Notwithstanding
that there is "nothing new", Dr Clements recorded distinct differences between
the vegetation north and south of Turnock
Street in January 2011. Dr Clements
recorded the dominant species along a 300m transect which was parallel to Dr
Webb's hydrology
transect. Dr Clements explained that the presence of
phragmites in relatively equal abundance north and south of Turnock
Street is consistent with the water table being close to the surface even
south
of Turnock Street although it is higher north of Turnock Street. Similarly the
predominance of paspalum urvillei south of Turnock Street is consistent
with the water table being high but not "over the top" (tr 752).
- Dr
Smith concluded that immediately prior to 1997 potential Wallum Froglet habitat
to the north of where Turnock Street was located
was limited to a small patch
near the Pearl Street stormwater outlet and a small patch of wet heath near the
current roundabout.
However Dr Smith concluded that following construction of
Turnock Street and Elrond Drive the whole of the area north of Turnock
Street
below about 1m AHD became potential Wallum Froglet breeding habitat.
- Dr
Clements observed that the vegetation south of Turnock Street is dominated by
exotic pasture species. She referred to the increased
abundance of the pasture
species south of Turnock Street, in particular setaria sphacelata and
paspalum urvillei. Dr Clements said that these pasture species are
consistent with the land being dry. The native species baumea rubiginosa
and blechnum indicum were much more abundant north of Turnock Street
than south of Turnock Street. Native species baloskion tetraphyllum, gahnia
sieberiana, sphagnum moss and villarsia exaltata were also abundant
north of Turnock Street but absent south of Turnock Street.
- The
plaintiff argued that it is not correct to submit, as the defendant did, that
the composition of vegetation in the area which
is now the Wallum Froglet
habitat is substantially the same as it was prior to the construction of Turnock
Street. The plaintiff
referred to Mr Murray's survey in 1992 in which he
recorded wetland species blechnum indicum and gahnia sieberiana as
among the dominant species in a polygon that covered the area in which the
Wallum Froglet habitat now is. Mr Murray's 1992 survey
used polygons created to
describe the extent of the vegetation communities. These are approximately the
same as the mapping done
by Mr Warren in 1994. Mr Warren mapped most of the Land
that is now froglet habitat as fernland/grassland in 1994 and identified
a
number of species as the main species in that community including blechnum
indicum , gahnia sieberiana and baumea rubiginosa . Mr Warren
did not attempt to measure the relevant abundance of the species listed in his
report. Mr Elks and Dr Smith (2007) recorded
baumea rubiginosa and
hemarthia uncinate as amongst the dominant species in the area.
- None
of the surveys done by Mr Murray (1992) or Mr Warren (1994) recorded the
presence of the wetland species hemarthia uncinate or sphagnum moss
that Dr Clements recorded in the habitat. Other wetland species identified
by Dr Clements in the area included baloskion tetraphyllum, philydrum,
phragmites and villarsia exaltata. Most of these were not identified
by Mr Murray or Mr Warren.
- The
plaintiff submitted that the only plausible explanation for the changes observed
in species composition and vegetation community
is the rise in the water table
north of Turnock Street. It was submitted that this explanation is consistent
with the appearance
of sphagnum moss north of Turnock Street but not
south of Turnock Street.
- The
plaintiff submitted that the sphagnum moss is a very good indicator of
the nature of the Land at particular times. It is accepted by the experts that
sphagnum moss cannot survive when the Land is inundated with water. It
was submitted that its presence is consistent with the decline of persistent
wetness caused by better drainage conditions north of Turnock Street and that
its presence and absence is almost perfectly consistent
with the hydrological
conditions described by Dr Webb.
- The
defendant submitted that prior to 1997 species typical of the environment in
which Wallum Froglets breed and feed were dominant
north and south of Turnock
Street. The plaintiff submitted that this contention overlooked the evidence of
Dr Smith that there are
three critical habitat requirements, referred to above,
which must be present for Wallum Froglet habitat. The plaintiff submitted
that
the presence of Wallum vegetation (coastal heath and wetland vegetation), by
itself, is not an indicium of suitable habitat
for the Wallum Froglet. It was
submitted that if that were the case the froglet would be widespread and secure,
as is Wallum vegetation,
rather than vulnerable to extinction.
- It
is clear that the combination of species and the structure of the vegetation
communities were such after 1997 that the Wallum Froglet
habitat was created.
There are probably four propositions in relation to this creation. The first is
that there is nothing new in
this habitat. The vegetation has always been the
same and its creation could have occurred at any time irrespective of the
construction
of Turnock Street. The second is that even if the vegetation is the
same, it was the wetting up of the Land that caused the abundance
of the wetter
species appropriate for the creation of the Wallum Froglet habitat. The third is
that it was land management, slashing,
that caused the creation of the habitat
and not the wetting up of the Land. The fourth is that it was a combination of
both the wetting
up of the Land and the slashing that caused the creation of the
habitat.
- The
first proposition is not really sustainable. It is true that there is "nothing
new" in the type of vegetation on the Land. The
vegetation has always been there
but in different composition and communities. There had to be particular
circumstances for the creation
of the habitat in the area that it now exists and
it is probable that those circumstances did not exist before 1997. The Land is
wetter and it is probable that such wetness was a contributing factor in the
creation of the Wallum Froglet habitat. However it probably
was not the only
factor that contributed to the creation of the habitat. Certainly the
flourishing of the sphagnum moss on the Land north of Turnock Street
evidences the wetness of the Land. However that does not mean that the slashing
of the Land was
not a contributing factor to the creation of the habitat.
- Dr
Benwell gave evidence that slashing on the Land had a big impact on the
"floristic composition of the plant communities and their
structure" (tr 707).
His evidence included the following (tr 714-715):
A. I see the slashing as it is changing the whole plant community. It is not
just grasses it is sedge being favoured, herbs. So it
is a whole range of native
and exotic herbs, grasses, sedges, they are being favoured by this slashing and
some of them are just
being changed in abundance they are present in both the
slashed and unslashed, but in different abundance.
...
Q. I thought we established that they are pre 1997 and post there were
different species composition.
A. It is, yes, it is due to the serial, to the effect of slashing changing
vegetation.
Q. Coming back to what you said, I don't want any confusion about this, you
earlier agreed that the pre 1997 surveys and post 1997
surveys establish that
there are different species composition and vegetation communities, that's
established on your opinion.
A. Yes.
Q. We have moved to the next step. You are telling me on the assumption that
the northern land, that is north of Turnock Street, is
wetter and I am trying to
understand whether you say that the increase in moisture and wetness on the
northern land has had an effect,
that is it has caused a difference in species
composition and vegetation, was it that that caused it?
A. Yes, I was looking for evidence of changes and species composition which
could be due to increased wetness and I just can't find
any really obvious ones.
Q. Any at all?
A. One, perhaps one difference was the sphagnum moss growing in the ruts on
the northern side of the site. But that could also be
due to a soil nutrient
gradient across the site.
...
Q. So I understand your opinion to be that the change in the species
composition and vegetation communities that have been observed
is not due to the
increase in wetness of the land north of Turnock Street?
A. Yes.
- The
plaintiff submitted that even Dr Benwell admitted that sphagnum moss
could not be affected by slashing because it was a ground dweller and
slashing only affects the species that sprout. Thus, it was
submitted, the
presence of sphagnum moss north of Turnock Street is contrary to Dr
Benwell's hypothesis that slashing is controlling the abundances and presence
and absence
of species. It was conceded that there was no doubt that slashing
affects the structural nature of plant communities by reducing
the height of all
but groundcovers and that it enables new growth. However the plaintiff submitted
that it cannot be the "principal"
cause of the changes in vegetation observed on
the Land. This submission that it was not the principal cause accommodates the
fourth
proposition of a combination of causes including both wetness and
slashing. It was not suggested that slashing, without wetness,
could have caused
the creation of the habitat.
- Dr
Clements expressed the view that slashing alters vegetation height but not
vegetation species. The roots remain in the soil so
the same species will
re-grow after slashing. This is consistent with the observations of Dr Clements
along the vegetation transect
that there were predominantly the same species in
the slashed and unslashed areas north of Turnock Street. However it was noted
that
further north of Turnock Street the Land became drier and the wetland
species became less abundant consistent with wetness being
the main cause of
vegetation change. Dr Clements noted in her evidence that gahnia sieberiana
persists after slashing. Baumea rubiginosa is also unlikely to be
affected by slashing and it is low lying and grows quickly. It is observed in
both the slashed and unslashed
areas.
- Dr
Smith compared the vegetation in the two areas north and south of Turnock Street
where the plaintiff was not permitted to slash
under the conditions of the
development consent. Those areas had not been slashed for three years. It was
submitted that if Dr Benwell
is correct that it is slashing and not wetness that
drives species composition and abundance, then the area to the south of Turnock
Street, which is left unslashed, should have the same characteristics of the
area to the north of Turnock Street. Before Turnock
Street was constructed they
were part of the same vegetation community. However the unslashed area south of
Turnock Street does not
have the same vegetation characteristics as the area
north of Turnock Street. There is no sphagnum moss in it and there is a
far greater abundance of sedge in the north than the south. Thus, it was
submitted it is the wetness and not
the slashing that drives the changes in
vegetation observed north of Turnock Street.
- I
am satisfied that it is probable that the wetting up of the Land was the
dominant factor in the creation of the Wallum Froglet habitat.
However I am also
satisfied that the slashing of the Land was a factor in the creation of the
habitat.
Ecology (Frogs) Issues
- Three
experts assisted the Court in these issues: Dr Smith (who also gave evidence in
the vegetation concurrent session and whose
background is referred to earlier),
Dr Michael Mahony and Mr Peter Parker.
- Dr
Michael Mahony is an ecologist and conservation biologist with over thirty years
experience, with particular expertise in the ecology
and biology of Australian
frogs. He is the head of Environmental Science and Management at the University
of Newcastle. Dr Mahony
holds a Bachelor of Arts and a Doctor of Philosophy from
Macquarie University.
- Mr
Peter Parker is an ecologist and environmental consultant. He has over
thirty-five years experience in conducting flora and fauna
surveys and thirty
years experience in surveying the distribution and habitats of threatened
species in northern New South Wales.
He is the principal of Peter Parker
Environmental Consultants Pty Ltd and holds a Master of Philosophy Research
Degree from Griffith
University.
- Dr
Smith provided the reports already referred to above and he was a party to the
Joint Report of the Ecologists dated 14 February
2011 (Ex PD1). Dr Mahoney
provided a report dated 1 September 2010 and was a party to the Joint Report of
14 February 2011. Mr Parker
provided a report dated 6 December 2010 and was a
party to the Joint Report dated 14 February 2011. These experts gave evidence in
concurrent session on 14 March 2011.
- The
experts agreed that Wallum Froglets require ephemeral ponds that last long
enough for completion of embryonic and larval (tadpole)
life stage for
successful breeding. This may range from about 32 or 34 days to 6 months. Mr
Parker considered a minimum of 32 days
is sufficient. Dr Mahoney preferred a
minimum of 34 days. Wallum Froglets can tolerate acidic water conditions more so
than other
non-acidic adapted frog species. The Joint Report included the
following:
3. Wallum Froglet terrestrial habitat consists of a broad range of native and
occasionally partially exotic vegetation types that
occur within a limited
distance of breeding sites. Studies by Pyke and White (unpublished) have
indicated a mean movement distance
from breeding sites of 18 metres and a
maximum of 84 m on dry nights, and a mean of 4 m and maximum of 15 m on wet
nights.
4. Dispersing froglets may move far greater distances than the maximum of 84
m reported above.
5. Wallum Froglets can colonise and breed in created habitat.
6. ...There were no significant barriers to frog movement prior to the
construction of Turnock street and Elrond Drive in 1997 and
the wallum froglet
could readily migrate over quite a large and suitable habitat. Thus the subject
land north of Turnock Street would
have comprised only a part of the Wallum
Froglet habitat at west Kingscliff in which the 'local population' occurred.
...
9. ...An increase in ground water level (surface water ponding) of 10 to 20
centimetres can result in the creation of new Wallum Froglet
habitat in areas
where it previously did not occur.
- There
is no issue that the number of Wallum Froglets on the Land increased between
1999 and 2003. In July 1998 Mr Warren identified
a single Wallum Froglet call.
This was the first time that the Wallum Froglet was identified on the Land,
notwithstanding a number
of earlier surveys. Mr Parker claimed that he heard
"1000 calls" of Wallum Froglets on the Land in 2003. However the defendant
contended
that the Wallum Froglet was present on the Land prior to the
construction of Turnock Street. It was submitted that the more likely
explanation of the presence of a population of Wallum Froglets of the extent
encountered by Mr Parker, described by the defendant
as an "explosion", is that
the earlier surveys did not accurately reflect the situation.
- Mr
Parker's evidence in relation to the document in which he recorded the 1000
calls included the following (tr 887-888):
The diagram I produced in 2003 was produced for council plans and I did
pretty little pictures and tried to make it as simple as I
could and it's turned
out to be way too complicated and ambiguous, I agree.
Dr Mahoney correctly interpreted that one frog picture doesn't equal a
thousand. We estimated, myself and Dr White about a thousand
frogs over the
whole of the site. We walked throughout the site. ... I tried to in this
diagram, poorly explained I accept, cluster
the frogs. The closer the frog
together is the better quality frog habitats so as you move off to the north
west of the site north
of the site the froglet habitat is of poorer quality.
- Dr
Mahoney expressed the opinion that the land north of Turnock Street did not
contain habitat for the Wallum Froglet prior to 1997.
In support of this opinion
Dr Mahoney referred to Mr Warren's two surveys in the early 1990s and the
Woodward-Clyde report of 1996.
He noted that none of those surveys observed the
Froglet which is easy to detect with its strong and strident call. He emphasised
that the Woodward-Clyde survey included several methods appropriate for
detecting the Froglet in its terrestrial and aquatic habitats
(pit-line traps,
call recordings) and was conducted in the appropriate location and time to
record the Froglet. The Froglet was first
observed in July 1998 south of Turnock
Street and subsequently north of Turnock Street as reported by Mr Warren in
1999.
- Dr
Mahoney observed that Wallum Froglets are capable of moving over roads and
embankments and expressed the opinion that with the
wetting up of the Land north
of Turnock Street ephemeral ponding occurred suitable for breeding, foraging and
sheltering of the Froglet
and its population expanded under those conditions. He
concluded that it was unlikely that a population of Wallum Froglets occurred
on
the Land prior to 1999. It was most likely that the population occurred in the
Paperbark swamp forest with a fern/grass sedge
understorey in the lower
topographic areas in the south west of the Land in Lots 26C and 26D. His opinion
was as follows:
Following the construction of Turnock Street in 1997 and with other
developments in the local area, considerable changes occurred
in the hydrology
of the area to the north of Turnock Street. After that time froglets colonised
the wetlands habitats that formed
to the north of Turnock Street. Initially the
population was small and limited in distribution to the low topographic area
which
now surrounds the roundabout on Turnock Street. With an increase in the
extent of the surface water which provided habitat for the
froglet, the
population grew and was more widely distributed to the north of Turnock Street.
This was manifest by the occurrence
of ponding of water across a larger portion
of the land and a consequent increase in the habitat available to the wallum
froglet,
which in turn increased its population size and distribution to the
north of Turnock Street.
- Dr
Mahoney was of the view that the origin of the Wallum Froglet that colonised to
the north of Turnock Street was most likely to
be from the lower lying Paperbark
swamp forest areas to the southwest of the Land on Lots 26C and 26D. He noted
that after the construction
of the table drain in 2004 the extent of surface
ponding and the length of ponding decreased and the Wallum Froglet numbers
decreased.
He emphasised this point in support of his conclusion that without
the wetting up of the Land to the north of Turnock Street there
would not have
been a local viable population of the Wallum Froglet to the north of Turnock
Street.
- The
recording of the call of the Wallum Froglet (Ex OO) supports Dr Mahoney's claim
that it is a distinctive call. Notwithstanding
this, the defendant persisted in
its submission that the surveys conducted prior to 1999 failed to identify the
presence of the Wallum
Froglet even though it was likely to have been present on
the Land at the time. That submission is based on the so-called "explosion"
in
numbers of froglets identified by Mr Parker in 2003. The defendant submitted
that the increase in numbers was somewhat of a "mystery"
(tr 1282). It was
submitted that there was no scientific explanation for the increase in numbers
between 2002 when a few froglets
were identified to a thousand froglets in 2003.
Mr Parker's estimate of a thousand calls was reached when he stood on the side
of
the Land and estimated numbers from a distance of up to 150 metres. Dr
Mahoney criticised Mr Parker's 2003 observations noting the
absence of any
quantitative methodology as to how he distinguished 1000 individual calls.
However Dr Mahoney's report included the
following (par 314):
The most pertinent observation is the large increase in the distribution and
abundance of the Wallum froglet on the Subject Land in
the period between
surveys in 2001 and 2002 when Planit (2002) recorded a small number of froglets
calling adjacent to the roundabout
on Lot 11 to the situation reported Parker
(2003) and White (2003). Planit (2003) ... also reported the abundance of Wallum
froglets
to the north of Turnock Street during autumn of 2003 and estimated a
maximum of 275 calls/ha, which is not all that less than the
estimate of
>1000 individuals for the whole area reported by Parker (2003).
- On
this analysis there was not the so-called "explosion" referred to by the
defendant. In any event the increased number of froglets
in 2003 is consistent
with the biology and ecology of the froglets, which move widely and can rapidly
colonise a suitable area.
- The
defendant criticised the earlier surveys as containing opportunistic sightings
and calls and highlighted the fact that: Mr Warren's
survey in 1994 was not a
fauna survey; Woodward-Clyde's 1996 survey was of flora and fauna at five spot
locations in a narrow road
corridor for Turnock Street's construction and in an
unusually dry month; and Mr Warren's survey in July 1998 when a single call
was
detected in Lot 26C or 26D was carried out in a relatively dry month. The
defendant submitted that Dr Mahoney and Dr Smith based
their opinions on the
unlikelihood of Mr Warren not hearing the froglet if it had been present. Dr
Mahoney gave the following evidence
in the concurrent session in relation to the
increase in the number of froglets in 2003 (tr 885):
A No, I think it is explicable if you have a period of long rainfall, of
rainfall and ignoring whether it's because of blockage and
drains, the photos I
have seen certainly indicate that the surface water, the extent of surface water
was considerable and in those
conditions the Wallum Froglet would disperse and
rapidly take up that habitat. The alternative to think about is that when the
whole
thing is flooded like a swimming pool and there are photographs that show
that for 2003, none of the - a terrestrial frog is essentially
wiped out in that
situation, there is no more terrestrial habitat for the bottom half of the north
of Turnock Street. So they have
to reinvade at the end of that major flood. So
if, in the beginning of 2003 we have this massive rain event at the end of
summer,
they have flooded the site, the Wallum Froglet had to have actually been
wiped out on the site because it was essentially a swimming
pool. So the fact
that they then move back as it became ephemeral at the end of that wetting, is
an indication of their capacity
to disperse.
Q. So your explanation then is that the froglets that Mr Parker observed are
likely to be froglets that hadn't bred north of Turnock
Street, but returned to
the north of Turnock Street after the Turnock Street population had been wiped
out?
A. Or they may have moved to the higher ground to the east on the dune, but
they have to reinvade from somewhere or colonise it from
somewhere, because they
are not aquatic in the sense they don't live underneath the water. So I mean,
yeah, I think that you add
those two things together and in a short period of
time, the animal can quickly colonise the suitable smaller wetland habitats once
the flood is over.
- The
defendant submitted that this thesis propounded by Dr Mahoney is important
because it demonstrates that the Froglets may have
bred south of Turnock Street
and taken the opportunity to establish themselves north of Turnock Street at a
time when attractive
conditions presented themselves after the flooding. It was
submitted that this adds weight to Mr Parker's views that Wallum Froglets
are
likely to have inhabited the Land on earlier occasions and suggests the absence
of any clear link between the construction of
Turnock Street and the emergence
of a Froglet population.
- The
plaintiff submitted that prior to the construction of Turnock Street, Wallum
Froglets were not detected in the area which is now
north of Turnock Street.
There is no doubt that the Froglet call is distinctive and by 1994 Mr Warren was
familiar with its call.
It was submitted that the survey methods used by Mr
Warren in 1996 required field workers to be on site for some time and Dr
Mahoney's
evidence was that if Wallum Froglets were present on the Land at that
time they would have been detected (tr 845). It was submitted
that the most
likely reason why Mr Warren did not detect Wallum Froglets or report
semi-permanent ephemeral ponding was because at
that time the Land drained
freely and surface and groundwater were not impeded. The plaintiff submitted
that the essential element
to the Wallum Froglet habitat (even if the
appropriate vegetation was present), ephemeral ponding for the requisite period,
was not
present. It was submitted that the surveys conducted prior to 1997
should be accepted as accurate and leading to the conclusion that
the Wallum
Froglet was not present on the Land north of Turnock Street until after the
construction of Turnock Street.
- I
am not satisfied that I should reject the surveys prior to 1997 as inaccurate. I
accept that some of the surveys were conducted
for reasons other than
identifying the Wallum Froglet. However I am satisfied that the Wallum Froglet
was probably not present on
the Land north of Turnock Street until after the
construction of Turnock Street. I am also satisfied that the hydrology
conditions,
prior to the construction of the table drains in 2004, were such
that ephemeral ponding occurred enabling the Wallum Froglet to take
hold some
time after 1999. The plaintiff's Opening Submissions included a contention that
there was a "great abundance" of the Wallum
Froglets "certainly from 2003 and
possibly earlier" (par 9). This great abundance" was recorded in April 2003. I
am satisfied that
a viable population of Wallum Froglets was established on the
Land north of Turnock Street probably in late 2002/early 2003.
Conclusions from Expert Assistance
- It
is appropriate to set out my findings in relation to each of the issues in the
plaintiff's claims that I have made with the assistance
of the expert evidence.
They are as follows: (1) There was no adequate alternative drainage route to
replace the Northern Drain after
it was filled by the developer of NPE; (2) the
1200 mm pipe was inadequate for the proper drainage of the Land in all the
circumstances;
(3) the single culvert under Elrond Drive was not adequate for
the proper drainage of the Land; (4) the construction of Turnock Street
with no
culverts at ground level was not adequate for the proper drainage of the Land
and/or was an impediment to the proper drainage
of the Land; (5) the inadequate
drainage combined with the increase in stormwater run-off caused the wetting up
of the Land after
the construction of Turnock Street; (6) the wetting up of the
Land and to a lesser extent the slashing of the Land caused the vegetation
north
of Turnock Street to change so that the species composition and vegetation
community was suitable for Wallum Froglets; (7)
the wetting up of the Land after
the construction of Turnock Street caused ephemeral ponding, enabling the Wallum
Froglets to take
hold in the Wallum Froglet habitat north of Turnock Street in
late 2002/early 2003; and (8) the velocity of the stormwater coming
onto the
Land in the Quigan Street vicinity has increased because of a failure in the
Quigan Street stormwater outlets.
Applicable Principles
- Nuisance
is the unreasonable interference with the use and enjoyment of a person's land:
Hargrave v Goldman [1963] HCA 56; (1963) 110 CLR 40 at 62 per Windeyer J;
Sedleigh-Denfield v O'Callaghan & Ors [1940] UKHL 2; [1940] AC 880 at 904 per Lord
Wright. The determination of whether there has been "unreasonable interference"
is by the application of an objective
test - whether a person of ordinary habits
and sensibilities in the plaintiff's position and circumstance would regard the
interference
with the enjoyment of the land as unreasonable. It is necessary to
decide whether there has been "an inconvenience materially interfering
with the
ordinary comfort physically of human existence, not merely according to elegant
or dainty modes and habits of living, but
according to plain and sober and
simple notions" of the community: Walter v Selfe [1851] EngR 335; (1851) 4 De G. & Sm.
315 at 322, cited with approval by Jordan CJ in Don Brass Foundry Pty Ltd v
Stead (1948) 48 SR (NSW) 482 at 486. These include the notion of "reasonable
give and take": Bamford v Turnley (1862) 3 B.& S. 66 at 83-4 cited
with approval by Jordan CJ in Don Brass Foundry Pty Ltd v Stead at 487.
- Liability
in nuisance is not strict or absolute and fault in the alleged wrongdoer must be
shown: Sutherland Shire Council v Becker (2006) 150 LGERA 184; [2006]
NSWCA 344 at 225-226 [118]- [119] per Bryson JA. Damages may be awarded for
reasonably foreseeable harm caused by the defendant's activity that amounted to
the nuisance:
Overseas Tankship (UK) Limited v Miller Steamship Company Pty
Ltd ("Wagon Mound (No 2)") [1966] UKPC 1; [1967] 1 AC 617 at 639-640 per Lord Reid. The
Court may also grant an injunction, including a permanent injunction, to
restrain an ongoing nuisance:
Pride of Derby and Derbyshire Angling
Association Ltd v British Celanese Ltd [1953] 1 Ch 149 at 181 per Evershed
MR; 194 per Romer LJ.
- In
Willoughby Municipal Council v Halstead [1916] HCA 80; (1916) 22 CLR 352 the local
Council in the exercise of its statutory powers, laid an 18 inch pipe through
Mrs Halstead's (the plaintiff's) land to
carry off water flowing from the north.
This was in execution of a statutory power conferred on the Council. The
plaintiff alleged
that by reason of the insufficient size and faulty
construction of the pipe it did not carry off heavy rainfall with the
consequence
that large quantities of water accumulated on her land and became
stagnant and offensive. Griffith CJ (at 356) observed that when
the defendants
brought water through the pipe onto the plaintiff's land "they were bound to
make provision by an adequate drain for
carrying it further, and the adequacy of
such a drain would not depend upon the original but upon the then existing
condition of
the surface". Isaacs and Rich JJ said at 360:
The quantity and concentration of filth-impregnated storm water on the
plaintiff's land was manifestly greater than would have been
the case had the
Council been altogether inactive in relation to the drain.
- A
number of judgments in nuisance cases have referred to the expression used in
Clerk & Lindsell on Torts 19 th ed. (Sweet & Maxwell, London
2006), [20-39] p 1185, that in a particular type of nuisance (where the
defendant creates (rather
than adopts or continues) a nuisance and knew, or
ought to have known, that as a consequence of its actions harm to its neighbour
was reasonably foreseeable) "nuisance and negligence coincide": Robson v
Leischke [2008] NSWLEC 152; (2008) 72 NSWLR 98 at 109-110 [47]- [48]; Quick v Alpine
Nurseries Sales Pty Ltd [2010] NSWSC 1248 at [142], [147]. This coincidence
has created some complexity, however the "duty" that is imposed in that
circumstance is an obligation to
take the positive action a reasonable person in
that position and circumstance would take, to eliminate the foreseeable risk of
damage
from the nuisance: Sedleigh-Denfield at 894, 905; Wagon Mound
(No 2) at 639; see also Owners Strata Plan 4085 v Mallone (2006) 12
BPR 23,691 at 23,693 [22]
- Certain
public bodies, including local councils, have a limited immunity from liability
for a nuisance arising from an exercise of
their statutory powers. As Gleeson
CJ, Gummow, Hayne and Callinan JJ said in Bankstown City Council v Alamdo
Holdings Pty Ltd (2005) 223 CLR 660; [2005] HCA 46 at [16], "a body such as
the Council is not, without negligence on its part, liable for a nuisance
attributable to the exercise of, or failure
to exercise, its statutory powers".
The expression "negligence" is here used in a "special sense", requiring "the
undertaker, as
a condition of obtaining immunity from action, to carry out the
work and conduct the operation with all reasonable regard, and care
for the
interests of other persons": Melaleuca Estate Pty Ltd v Port Stephens Council
(2006) 143 LGERA 319; [2006] NSWCA 31 at 332-333 [47]-[48] per Giles JA,
referring to Allen v Gulf Oil Refining Ltd [1980] UKHL 9; [1981] AC 1001 per Lord
Wilberforce. As Giles JA said in Melaleuca Estate at 333 [49], "if
exercise of [the defendant's] statutory power means that the interests of other
persons are harmed despite all reasonable
regard and care for those interests,
there is no right of action" against the defendant. Negligence in this "special
sense" is to
be applied in only limited circumstances. It is to be applied in
the special circumstance where the inevitable consequence of the
actions of the
statutory authority will be harm to others. If the statutory authority does not
act with such regard it cannot claim
the immunity. Negligence otherwise than in
this special circumstance of nuisance means that there is a failure to take
reasonable
steps to eliminate the foreseeable risk of damage from the nuisance.
- Consistently
with the notion of give and take, a neighbour may tolerate an interference with
the enjoyment of the land for various
reasons including perhaps a need to
engender a friendly neighbourly relationship. That tolerance, an indicium of
which is a lack
of complaint, may be taken into account as evidence of there
being no "unreasonable" interference with the enjoyment of the land.
However
when the interference has reached the stage that the neighbour no longer feels
obliged or willing to tolerate it, either
because of the continuance of it or
the more serious nature of it, depending upon the particular circumstances of
the case, the neighbour
will be entitled to claim that there is an unreasonable
interference with the enjoyment of the land, notwithstanding that earlier
tolerance. However the neighbour will not be entitled to claim damages for the
interference that was tolerated prior to the complaint
being made, or put
another way, in respect of which there was acquiescence: Duke of Leeds v Earl
of Amhurst (1846) 2 Ph 117 at 124; Orr v Ford (1989) 167 CLR 316 at
341 per Deane J. Where there is a change in approach in the neighbour who has
hitherto acquiesced in the violation of the right
of enjoyment of the land, it
is necessary to inform the offender that tolerance has ceased.
Characterisation of the plaintiff's claim
- There
is a fundamental difference between the plaintiff and the defendant in relation
to the nature of the nuisance claimed by the
plaintiff. The plaintiff claims
that it is the inundation of untreated stormwater runoff on the Land that has
caused the unreasonable
interference with the enjoyment of its Land. The
defendant contends that properly understood, the plaintiff's claim is that it is
the presence of the Wallum Froglets that is the nuisance, rather than the
presence of the stormwater runoff on the Land.
- The
defendant submitted that, contrary to the position propounded by the plaintiff,
its claim is confined to loss of value of the
development arising from the
presence of the Wallum Froglet on the Land and not a complaint of damage to
property. There is no doubt
that in the early stages of the trial there was some
blurring of the boundaries of the plaintiff's case. The plaintiff's Outline
of
Opening Submissions included the claim that the case "is about the loss of
development rights and prospects" (par 4). Once the
plaintiff abandoned its
claim in negligence it focused on the elements of the nuisance case.
- The
defendant submitted that in order to establish an entitlement to relief based in
nuisance, the plaintiff must show that some other
right has been infringed that
the law of nuisance protects. The defendant relied upon two examples. The first
related to the clear
limitations in the categories of "rights" protected by the
law of nuisance. In this regard it was conceded there could be no argument
with
the proposition that collapsing buildings are a substantial interference with a
use and enjoyment of land, but relief in connection
with such losses of that
kind has not been available as a matter of course: Sutherland Shire Council v
Becker at 189 [5] per Giles JA. The other example was in relation to what
was described as the "rights of privacy". It was submitted that
while the
capacity of the plaintiff to exploit its property through the operation of
commercial enterprise was clearly interfered
with in Victoria Park Racing and
Recreation Grounds Co Ltd v Taylor [1937] HCA 45; (1937) 58 CLR 479, the activities on
neighbouring land which caused that interference were not recognised as a
nuisance. Relief was denied because
there was no damage to the plaintiff's
property and there was no right incidental to its ownership of the property that
was violated.
- The
defendant submitted that it is necessary to determine whether there exists a
right to which legal protection will extend which
has been infringed. It was
contended that the right the plaintiff alleges is, in substance, the right of a
landowner to be free of
wildlife the survival of which the law has seen fit to
endeavour to promote and protect, and the presence of which is otherwise
entirely
innocuous. The defendant submitted that there is no such right, or
alternatively no such entitlement, within the recognised scope
of protection
afforded by the law of nuisance. It was submitted that if the law does not
recognise as a right, or as a benefit attaching
to the ownership of property,
the entitlement to be free of protected species, then that is the end of the
matter. It was submitted
it is not open to the Court to extend the scope of
nuisance principles to protect rights that the law does not recognise.
Alternatively
it was submitted that if such an entitlement exists the plaintiff
must overcome the obstacle of establishing that the right should
be recognised
as attracting protection under the law of nuisance. It was submitted that this
would involve persuading the Court to
expand the recognised categories of rights
attracting protection.
- The
defendant also submitted that in determining this aspect of the case an
important consideration is to ensure that coherence with
other legal principles
and statutory schemes is preserved: Sutherland Shire Council v Becker at
189-190 [8]; Sullivan v Moody (2001) 207 CLR 562 at 580 [50]; Hill v
Van Erp (1997) 188 CLR 159 at 231. It submitted that there is plainly
incoherence between the existence of a legislative framework for the
preservation of threatened
species and the existence of a right, protected by
the law of nuisance, to be free of the presence of protected species on one's
land. The Threatened Species Conservation Act 1995 provides that upon
listing of a species as vulnerable or endangered, persons may be liable for
offences under that Act in relation
to that species. Orders can be made
restraining breaches or apprehended breaches of the Act and of acts harming a
protected species.
It was submitted that as nuisance protects private interests
in the use and enjoyment of land, it would be anomalous for the law
to recognise
legislative limits upon such interests on the one hand and, on the other hand,
to recognise remedies protecting such
private interests enforceable by
injunction or damages.
- It
was suggested that a further example of incoherence is found in the
circumstances that have given rise to the complaint in these
proceedings, in
that an invasion of Wallum Froglets from the area south of Turnock Street
(apparently Lots 26C and 26D of the Land)
was a realistic possibility (tr
848-851). It was submitted that if those Lots were under different ownership,
that owner could not
be restrained from preserving a Froglet habitat or be sued
in damages if it preserves such a habitat and its Froglets invaded the
Land.
Accordingly it was submitted that if a neighbour cannot be made liable for
protecting the Wallum Froglet and thereby exposing
the plaintiff to the risk of
invasion by protected fauna, then coherence requires that the defendant should
not be exposed to such
a liability.
- By
way of further example the defendant submitted that if the Statement of
Environmental Effects accompanying the NPE development
had identified a
community of Wallum Froglets on that site, adjacent to the Land, the question
would arise as to how the defendant
could perform its obligations to protect
that population without exposing the plaintiff to the risk of froglet invasion
and potential
development restrictions. It was submitted that to extend the law
of nuisance to provide protection of a right to be preserved from
endangered
species would impose an intolerable burden on the defendant in this case because
of the possible twenty-seven different
species potentially affected by
development in the area. It was submitted that the defendant could not sensibly
be burdened with
the responsibility of ensuring that the habitat for each such
endangered species will not be enhanced by development (for example,
by
providing cleaner water or more open space or trees in the vicinity of
neighbouring lands) not least because the defendant is
obliged to provide the
creation of suitable habitat, not prevent it.
- The
plaintiff submitted that the defendant's arguments about incoherence are based
on an incorrect analysis of its claim that the
existence of the Wallum Froglets
is the harm rather than a consequence of the harm for which it seeks damages.
The plaintiff submitted
that its case is analogous to Cattanach v Melchior
[2003] HCA 38; (2003) 215 CLR 1 in which the plaintiff was awarded damages for the birth of
an unintended child resulting from a doctor's negligent advice and failure
to
warn. In Cattanach the High Court considered the existence of obligations
imposed by the law to maintain and raise a child, including sanctions of the
criminal law for a failure to maintain and support children. However the
imposition of those legal obligations did not absolve the
respondents from
liability for damages: per McHugh and Gummow JJ at [59]; Callinan J at [295],
[301]. It was submitted that in the
present case, as in Cattanach , an
award of damages of the kind sought by the plaintiff is consistent with the
underlying notion that the availability of damages
serves as a measure of
deterrence of the defendant's tortious conduct.
- I
am not sure that reliance on Cattanach supports the plaintiff's position.
In any event, as I said above, the plaintiff submitted that the existence of the
Wallum Froglet
is not the "harm" alleged and any award of damages of the kind
sought does not involve an extension of the law of nuisance. The plaintiff
submitted that it relies on a long established category of the tort of nuisance
arising from the discharge and retention of stormwater
on land. It was submitted
that it is this category of traditional nuisance referred to in Willoughby
Municipal Council v Halstead that is relied upon rather than any notion of
extending the law to include a right to be protected from threatened species.
The right
for which the plaintiff claims it is entitled to protection is its
right to the enjoyment of the Land. It claims that the Land was
inundated with
untreated stormwater so that it could not enjoy it, a consequence of which was
the establishment of the Wallum Froglet
habitat that would otherwise not have
been established because the Land would have been free of the water and the
consequence of
ephemeral ponding.
- The
plaintiff submitted that the nuisance alleged by it arose not from an isolated
act by the defendant but from a series of steps
taken by it including:
constructing or permitting the construction of stormwater outlets directing and
concentrating stormwater runoff
on the Land; permitting the filling of the
Northern Drain without replacing it with an overland flow path for the Q100
storm; only
requiring a drain to be sized for Q5 flows, but approving a drain
which was undersized for the Q5 flows and also ineffectual; designing
and
constructing Turnock Street and Elrond Drive so that all but one of the culverts
draining stormwater from the Land were placed
above ground level; failing to
provide a table drain to drain stormwater dammed by Turnock Street to a lawful
point of discharge;
and designing and constructing a culvert under Elrond Drive
which was undersized for both the Q100 and the Q5 storm events.
- The
plaintiff submitted that the harm caused by the discharges was worsened by the
impaired drainage system, progressively established
by or with the approval of
the defendant. It was submitted that the defendant did so with knowledge of the
incapacity and the deficiencies
of that drainage system and therefore with
"fault": Torette House Pty Ltd v Berkman [1940] HCA 1; (1940) 62 CLR 637 at 659.
- The
plaintiff's claim is that the defendant's conduct has caused an increase in
stormwater runoff on its Land that has caused an unreasonable
interference with
the enjoyment of its Land, irrespective of the presence of the Wallum Froglets.
I accept that this is an accurate
characterisation of the plaintiff's claim and
I intend to consider whether there is an actionable nuisance on that basis.
- The
plaintiff does contend that its measure of damages should include at least the
cost of maintaining the Wallum Froglet habitat
and the diminution in the value
of its Land as developed, because the natural and foreseeable consequence of the
inundation of the
Land, the wetting up of the Land, was the establishment of the
Wallum Froglet habitat. In these circumstances I will deal with the
plaintiff's
claim in two parts: first, the claim of unreasonable interference with the
enjoyment of the Land irrespective of the
presence of the Wallum Froglets; and
secondly, its entitlement to recover damages for, inter alia : (a) the
cost of establishing and maintaining the Wallum Froglet habitat; and (b) the
loss of the use of that part of the Land for
development.
An unreasonable interference
- The
relationship between these parties over the last 30 years is not free from
complexity. It was in many respects very co-operative
with the plaintiff being
willing to provide and in fact providing funds to assist the defendant to
complete various studies not only
in respect of the drainage of the Land but
also in respect of the drainage of the Kingscliff area generally. However they
had a number
of court cases when disagreement occurred in respect of particular
aspects of their respective approaches to the development of the
Land and/or the
area generally. Their relationship appears to have deteriorated after the
plaintiff published the political pamphlets
criticising an officer of the
defendant and the defendant generally. Notwithstanding this lengthy relationship
in which the parties
were communicating with each other on a regular basis there
is no written communication in evidence between them prior to 2004 in
which the
plaintiff made a complaint that the enjoyment of its Land had been unreasonably
interfered with by the presence of the
stormwater run-off on the Land. The
letter of 31 July 1974 suggested that the defendant should take responsibility
for the "severe
localised drainage problems" but made no claim of unreasonable
interference with the enjoyment of the Land.
- However
on 5 March 2003 the plaintiff's consultant Mr Glazebrook advised the defendant
that the plaintiff was "no longer prepared
to permit the unlawful discharge of
concentrated stormwater flows" onto its Land. There was no reference in that
letter to any unreasonable
interference with the plaintiff's enjoyment of its
Land. That letter was written in circumstances where the plaintiff was having
difficulty obtaining development consent to fill the Land and to construct the
proposed shopping centre. The terms of this letter
suggest that prior to 5 March
2003, there was alleged unlawful discharge of concentrated stormwater flows onto
the Land but that,
for whatever reason, the plaintiff was prepared to permit it.
However that permit was withdrawn as and from 5 March 2003.
- It
is apparent that the plaintiff's priorities in respect of the Land over the
years up to 5 March 2003 accommodated the stormwater
on its Land without
complaint. Dr Segal's evidence was that from as early as 1977 the plaintiff's
plan has been to develop the Land
into a combination of residential and retail
uses. There is no issue between the parties that prior to any development of the
Land
it will be necessary to fill the Land. Accordingly the day-to-day use of
the Land, initially with the grazing of cattle and later
with the agistment of
horses, were temporary uses until the Land was developed. However the plaintiff
either directly or through
its expert representatives took part in many, many
meetings and at its own cost, retained numerous and various consultants to
assist
it, and at times to assist the defendant, in achieving some sensible and
consensual regime and plan for the drainage of the Land
and the area generally.
I am satisfied that the plaintiff's attitude was that it would tolerate the
presence of the stormwater run-off
on its Land whilst these discussions and
meetings were pursued for the joint endeavour (as it saw it at the time) of
achieving a
sensible and workable plan for the drainage of the Land and the area
generally. However it was not prepared to tolerate it after
5 March 2003.
- On
4 May 2004, for the first time in this long relationship between these parties,
the plaintiff claimed that the defendant's conduct
in constructing Turnock
Street with the consequential increased wetness of the Land, constituted an
unreasonable interference with
the enjoyment of its Land.
- The
volume of water on the Land since 5 March 2003 has not only been described in
evidence by the experts but photographs of the Land
have been taken (Volume 6 of
the Court Book) and have also been the subject of detailed observations by Dr
Webb. The photographs
are in various "series" - the "EDC series" being the
Elrond Drive series of which there are 13 photographs taken during the period
July 2003 and June 2008; the "TD series", being the Table Drain series, of which
there are 16 photographs taken during the period
July 2003 and March 2008; the
"SW 1200 series", being the 1200mm Pipe series, of which there are 14
photographs taken during the
period July 2003 and June 2008; the "NTS-E series",
being the Land North of Turnock Street at Eastern Limit series, of which there
are 69 photographs taken during the period March 2003 and March 2008; the "NTS-W
series" being the Land North of Turnock Street at
the Western Limit series, of
which there are 29 photographs taken during the period March 2003 and June 2008;
and a series of 28
photographs taken on 17 November 2004, 30 June 2005 and 16
April 2009 depicting drainage problems on Lots 26C and 26D, which was
divided
into three sets: the southern section of the Chinderah Drain adjoining Lot 26C
("DR-CHIND"); the south westerly drain within
Lots 26C and 26D ("DR-SW"); and
the cleared areas of Lots 26C and 26D north of the south westerly drain ("Lots
26C&D").
- These
photographs depict what may reasonably be described as inundation of parts of
the Land between 2003 and 2008 through which it
would be impossible to walk
comfortably (or at all) because of the presence of the water as depicted - see
especially photographs
in the EDC series, in particular photographs 11 to 13;
the SW 1200 series, in particular photographs 8 to 10, 13 and 14; the NTS-E
series, in particular photographs 1 to 36, 49 to 52 and 62 to 66; and the NTS-W
series, in particular photographs 3 to 8, 11 to 14,
18 to 22, 28 and 29.
- The
plaintiff alleged that the stormwater coming onto the Land contained pollutants.
The untreated stormwater from the defendant's
drains is of different quality to
the rainwater that falls directly onto the Land during storm events. It was not
in serious issue
that the stormwater from the drains would come from various
sources including the roofs and downpipes of the buildings in the surrounding
catchment. That stormwater consequently carried with it "such impurities as are
ordinarily found in surface water so collected":
Willoughby Municipal Council
v Halstead at 357 per Griffith CJ. It would also come from areas in the
catchment that are under development. In this regard the plaintiff relied
upon
the defendant's policy documents to claim that it is accepted that urban
development increases "pollutant loads" in the stormwater
runoff that is not
treated (Ex UU: 5.5, page 29). The defendant's Development Design Specification
for new developments requires
the removal of pollutants from stormwater (Ex FF:
D7 4-5).
- Baseline
water quality data was collected by Dr Webb over the period December 2007 to
November 2009 at four locations within the designated
Wallum Froglet habitat and
at three stormwater outlets that drain from the surrounding urban areas. Water
samples were collected
on 29 occasions during the two year monitoring period
however not all locations were sampled on every occasion.
- The
results showed that the observed conditions differ significantly from the water
quality requirements imposed in the conditions
to the 2008 Development Consent.
In particular, the mean observed value of the water within the Wallum Froglet
habitat is significantly
above the requirements imposed by the development
consent conditions for all parameters except turbidity and pH. Dr Perrens'
report
of 2 September 2010 (that was in evidence and was unchallenged) concluded
that the two year monitoring program provided a good characterisation
of the
local water quality and provided sufficient data from which to derive a range of
desirable and practicable water quality goals.
It is true, as the defendant
submitted, that the monitoring of the water quality was for the purpose of the
accommodation of the
Wallum Froglet habitat. Its submission that it did not
provide proper evidence of pollutants in the stormwater is however rejected.
- The
plaintiff claimed that the principal pollutants are suspended solids. It also
submitted that there is no doubt that the urban
stormwater is itself a pollutant
and all of the defendant's policy documents treat it as such: (Ex EE; Ex FF; and
Ex UU). The defendant
submitted that the evidence relating to pollutants is
confined to two areas: a single observation in general terms from Dr Webb
regarding
presence on the site of gross pollutants, in the form of plastic
bottles and the like, immediately downstream of the Pearl Street
outlet; and
observations made in the HMC Environmental Consulting Pty Ltd report annexed to
Dr Webb's August 2010 report. It was
submitted that the evidence of gross
pollutants does not establish an unreasonable interference amounting to
nuisance. It is common
ground that the Pearl Street catchment drains naturally
to the Land. Stormwater flowing naturally onto the Land would be expected
to
carry gross pollutants of the type complained of whether or not it was
concentrated.
- In
Willoughby Municipal Council v Halstead it was accepted that the
"ordinary impurities" would be present in the water. However the plaintiff in
that case "proved" that the
water that "actually passed through" the Council's
pipe was "further contaminated by slop water and house refuse which in fact ran
into the water-tables": per Griffith CJ at 357.
- The
200% increase in the stormwater runoff onto the Land over the years has come
from the increased urbanisation of the catchment.
I am satisfied that the
plaintiff has proved that there are pollutants in the stormwater as identified
by Dr Perrens. I am satisfied
that the irresistible conclusion is that the
untreated stormwater flowing onto the Land had the ordinary impurities within it
and
also some pollutants.
- The
defendant submitted that because the plaintiff did not want to use the Land
except for development purposes there was no unreasonable
interference with the
enjoyment of the Land by the presence of the stormwater runoff because it was
just a "dormant" development
site. The evidence in relation to the use to which
the plaintiff put the Land whilst it awaited development approval establishes
that over the years it was used for cattle grazing and horse agistment. It is
clear that the plaintiff's contractors had to change
the way they managed the
Land because the Land became so soggy. I am of the view that the defendant's
characterisation of the Land
as "dormant" is misconceived. The defendant's
argument that there was no interference with the enjoyment of the Land because
it was
"dormant", if accepted, would mean that any land within its jurisdiction
that is presently awaiting development approval and not
being used for any
particular purpose could be categorised as "dormant" and utilised by the
defendant with impunity to discharge
its stormwater and/or create retention
basins and/or perhaps to store some other by-product of its operations. I do not
accept that
simply because the plaintiff was not using the Land for a specific
and continuous operation at any particular time from 2003 onwards
means that
there was no unreasonable interference with the enjoyment of the Land.
- The
Land was in part converted into a retention basin for the water from the
defendant's drains and from the NPE. This combined with
the 200% increase in the
stormwater runoff onto the Land changed part of the Land physically from a
rather flat grazing property
to a soggy watery expanse causing very serious
interference with the plaintiff's enjoyment of the Land. Apart from losing the
use
of that part of the Land because it was covered in water, the plaintiff has
had to instruct many consultants to obtain assistance
with the preparation of a
plan as to how the water should be drained from the Land. It has also had to
construct table drains with
the assistance of expert advice and at further cost
to itself.
- I
am satisfied that the plaintiff has established that there has been an
unreasonable interference with its right to enjoy the Land.
Defendant's knowledge/steps taken
- It
is clear that the defendant decided to utilise the plaintiff's Land as a
retention basin for the stormwater run-off in the area
generally and it
continued to do so after the letter of 5 March 2003. Mr Knight's memorandum of
27 February 2003 noted that the plaintiff's
application for the shopping centre
would "incrementally eliminate detention storage" in the Land and the filling
would eliminate
all detention storage from the Land. Mr Knight noted that the
combined effect would be to "eliminate in excess of Q5 drainage capacity
for the
upstream catchment and cause flooding of land and property". He argued that the
Land was the "natural area for runoff to
be discharged from the foreshore dune
area and acts as a natural detention basin for the foreshore dune area". The
defendant was
conscious that if it allowed development it would have to find
some alternative for its retention basin for stormwater runoff.
- From
5 March 2003 the defendant became aware that the plaintiff was alleging that
there was "unlawful" discharge of stormwater onto
the Land. From 4 May 2004 the
defendant must have been aware that the plaintiff was alleging that there was an
unreasonable interference
with the enjoyment of the Land. It was on 4 May 2004
that the plaintiff advised the defendant that Dr Webb had expressed the opinion
that Turnock Street was acting as a dam for even small storm events and that
adequate under-road and lateral drainage was required
to ensure that unnatural
ponding did not continue to the north of Turnock Street.
- The
question then arises as to whether the defendant conducted itself to remedy the
problem from that time without undue delay: Sutherland Shire Council v Becker
at 226 [121]. If the defendant knew or ought to have known of the nuisance
and the real risk of reasonably foreseeable consequential
damage to the
plaintiff, it had an obligation to take such positive action as a reasonable
person in its position and circumstances
would consider necessary to eliminate
the nuisance: Robson v Leischke at 109-110 [48]-[52].
- Although
I have rejected as inapt the defendant's argument that there was no interference
with the enjoyment of the Land because it
was "dormant" and awaiting
development, it is necessary to analyse the steps the defendant took or the
position it adopted once it
was put on notice that there was damming of the
water north of Turnock Street and unnatural ponding. The defendant knew that it
had
imposed a number of conditions on the plaintiff as pre-requisites to
development consent, including the production of an acceptable
drainage plan. It
knew that the culverts under Turnock Street were of no use to the drainage of
the Land because they had been constructed
to the level of the anticipated
filled Land. The defendant did not take any steps to alleviate the damming of
the water north of
Turnock Street when it was notified in March 2003 and/or May
2004. I regard this as most unreasonable. It was left to the plaintiff
to
alleviate the problem by the construction of the table drain with the assistance
of expert advice including that of Dr Webb.
- It
was reasonably foreseeable that harm would be caused to the plaintiff by reason
of: (1) the wetting up of the Land with untreated
polluted stormwater; and (2)
the need to find a method of accommodating the additional water. The defendant
could not seriously resist
the proposition that it was foreseeable that the
wetting up of the Land may cause physical damage to the Land (tr 1291-1292). By
May 2004 when the complaint was made the defendant knew that there were Wallum
Froglets on the Land in "great abundance".
- The
plaintiff claims that the defendant failed to take any steps to eliminate the
nuisance once it was made aware of it. In fact the
plaintiff claims that the
defendant was well aware that it had caused the nuisance when it decided to
establish the retention basin
on the Land in 1995. There is no doubt that the
additional water on the Land was caused by the defendant's inadequate drainage
system
as described earlier, however as I have already said it was not until
March 2003 that the plaintiff decided not to tolerate the interference
with its
enjoyment of the Land.
- The
plaintiff claims that the defendant has failed to react appropriately to this
continuing nuisance. It claims that the defendant
recognises that the nuisance
continues; that it has approved the Blue Jay Circuit works that will rectify the
problem; and it has
failed to implement the approved solution. I agree that the
defendant has recognised that there is a need to eliminate the increased
flow of
stormwater onto the Land. The defendant had recognised the "drainage problem"
from as early as 1995 when it sought to find
a "solution". It also knew from
that time that there was a need for water quality control of the additional
stormwater runoff onto
the Land as reflected in its internal documents, for
example, in the communication of 13 March 1995 referred to earlier (par 49).
- I
am satisfied that from 5 March 2003 when the plaintiff notified the defendant
that it would no longer tolerate the flow of stormwater
onto the Land and
certainly no later than 4 May 2004 when the plaintiff's solicitors complained of
nuisance, the defendant was aware
that the increased flow of water onto the Land
may cause physical damage to the Land.
Nuisance
- I
am satisfied that the presence of untreated polluted stormwater runoff from the
defendants' drains onto the Land constituted an
actionable nuisance from 4 May
2004.
- The
plaintiff contended that if the defendant had established table drains north of
Turnock Street, as the plaintiff itself did in
2004, the stormwater could have
drained away more effectively. The plaintiff accepted that since it established
the table drain north
of Turnock Street and cleared the Elrond Drive culvert,
the water has drained away more effectively (Dr Webb's August 2010 report
paragraph 8.3.24). However there are still problems after major storm events
when the Land once again becomes inundated as shown
in the photographs referred
to above (and also Dr Webb's August 2010 report paragraph 7.5.7). The nuisance
continues to this day
in this regard but to a lesser extent, that is, confined
to periods after major storm events.
- I
am satisfied that the presence of the untreated polluted stormwater runoff on
the plaintiff's Land constituted a nuisance from 4
May 2004 until some short
time after the table drains were installed in 2004 and the water began to drain
more effectively. I am
satisfied that the nuisance continues and/or there is a
separate nuisance after major storm events.
Defences
- The
plaintiff submitted that unlike in most negligence cases where the burden
remains with the plaintiff throughout, once it is established
that the defendant
caused a nuisance, the defendant bears the onus of justifying its conduct or
having its conduct excused: Brodie v Singleton Shire Council (2001) 206
CLR 512; [2001] HCA 29 at 567 [122] per Gaudron, McHugh and Gummow JJ citing
Denning LJ in Southport Corporation v Esso Petroleum Co Ltd [1954] EWCA Civ 5; [1954] 2 QB
182 at 197 (reversed on other grounds in Esso Petroleum Co Ltd v Southport
Corporation [1956] AC 218). The defendant accepted this position and relied
on various provisions of the Civil Liability Act 2002 (the CLA), the
Roads Act 1993 and s 733 of the Local Government Act 1993 (the
LGA) to claim that it is not liable in respect of these nuisances. The defendant
does not claim its actions should be excused
on the basis of the "statutory
authority" defence referred to by Giles JA in Melaleuca at [49].
Civil Liability Act 2002 (CLA)
- The
plaintiff submitted that the policy found in sections 120 and 142A of the
Protection of the Environment Operations Act 1997 (NSW) precludes the
defendant from relying upon the operation of the CLA to justify or excuse its
actions of depositing polluted
stormwater on the Land. Section 120 of that Act
makes it an offence to pollute any waters. "Water pollution" or "pollution of
waters"
is defined to mean the placing in or on, or otherwise introducing into
or onto, waters "any matter, whether solid, liquid or gaseous,
so that the
physical, chemical or biological condition of the waters is changed". It also
includes the placement or introduction
onto the waters of "any refuse, litter,
debris or other matter" likely to make the waters "unclean, noxious or harmful"
or "undrinkable
for farm animals" or "is likely to obstruct or interfere with
persons in the exercise or enjoyment of any right in relation to the
waters"
includes making the water unsuitable for use in irrigation. Section 142A makes
it an offence for any person to pollute land.
"Land pollution" is defined as the
placing in or on or otherwise introducing into or onto the land any matter "that
causes or is
likely to cause degradation of the land, resulting in actual or
potential harm to the health or safety of human beings, animals or
other
terrestrial life or eco systems, or actual or potential loss or property damage,
that is not trivial".
- The
fact that the provisions of Protection of the Environment Operations Act
define land pollution and water pollution and make it an offence to pollute
land and water does not in my view prevent the defendant
seeking to rely on the
provisions of the CLA, if they are otherwise applicable.
Part 1A of the CLA
- The
defendant relied upon ss 5 and 5A of Part 1A of the CLA that provide as follows:
PART 1A NEGLIGENCE
...
5 Definitions
In this Part:
"harm" means harm of any kind, including the following:
...
(b) damage to property,
(c) economic loss.
"negligence" means failure to exercis e reasonable care and skill.
...
5A Application of Part
(1) This Part applies to any claim for damages for harm resulting from
negligenc e , regardless of whether the claim is brought in
tort, in contract,
under statute or otherwise.
(2) This Part does not apply to civil liability that is excluded from the
operation of this Part by section 3B.
5B General principles
(1) A person is not negligent in failing to take precautions against a risk
of harm unless:
(a) the risk was foreseeable (that is, it is a risk of which the person knew
or ought to have known), and
(b) the risk was not insignificant, and
(c) in the circumstances, a reasonable person in the person's position would
have taken those precautions.
(2) In determining whether a reasonable person would have taken precautions
against a risk of harm, the court is to consider the following
(amongst other
relevant things):
(a) the probability that the harm would occur if care were not taken,
(b) the likely seriousness of the harm,
(c) the burden of taking precautions to avoid the risk of harm,
(d) the social utility of the activity that creates the risk of harm .
- Section
3B of the CLA makes no reference to nuisance. The section excludes cases that
involve an intentional act done with intent
to cause injury or death; sexual
assaults or other sexual misconduct; claims for damages for dust diseases;
claims in respect of
injury or death resulting from smoking or other use of
tobacco products; damages in respect of injuries suffered in motor accidents;
claims for workers, and other, compensation.
- The
plaintiff submitted that these provisions of the CLA are not applicable because
negligence as defined is not an element of the
tort of nuisance. The defendant
submitted that even if this Part of the CLA is not applicable, the principles to
be considered in
deciding whether its actions were justified or should be
excused are the same as those outlined in s 5B of the CLA. It has been suggested
that to "the extent of the plaintiff bringing a claim for damages in nuisance
must establish that the defendant has failed to exercise
reasonable care and
skill" Part 1A of the CLA will apply. However doubt was expressed as to whether
the Australian common law continues
to recognize any such instances other than
perhaps in the case of support of land : Dominic Villa Annotated Civil
Liability Act 2002 (NSW) Law Book Co 2004 [1A.5A.070].
- I
am of the view that the use of the expression "negligence" in s 5A, as defined
in s 5 of the CLA, as the "failure to exercise reasonable care and skill" is
limited to causes of action alleging negligence whether in
tort, contract or
under statute. This is a cause of action in nuisance that has imported into it
some features of the duties that
might otherwise be found in the tort of
negligence. Damages are available for harm that is suffered by reason of the
nuisance, the
unreasonable interference with the enjoyment of land. The breach
of duty in the tort of nuisance in this case, the failure to take
reasonable
steps to eliminate the foreseeable risk of damage from the nuisance, is
different from the breach of duty or "negligence"
defined in s 5 as the "failure
to exercise reasonable care and skill". I am satisfied that Part 1A of the CLA
does not apply.
- However
I accept that the principles referred to in s 5B of the CLA are similar to those
to be considered in determining whether the steps taken or the position adopted
by the defendant
were reasonable in all the circumstances: Leakey v National
Trust for Places of Historic Interest or Natural Beauty [1979] EWCA Civ 5; [1980] 1 QB 485 at
524 per Megaw LJ.
Part 5 of the CLA
- The
defendant also relied upon ss 42, 43A and 45 of the CLA and submitted that these
are in a different category to Part 1A of the CLA. These sections are all in
Part 5 of the CLA entitled "Liability of Public and Other Authorities". Section
40 provides:
40 Application of Part
(1) This Part applies to civil liability in tort.
(2) This Part extends to any such liability even if the damages are sought in
an action for breach of contract or any other action.
(3) This Part does not apply to civil liability that is excluded from the
operation of this Part by section 3B.
- This
Part of the CLA extends to any civil liability (not excluded by s 3B) of a
public or other authority even if the damages are sought in an action for breach
of contract or any other action: Sydney Water Corporation v Turano [2009] HCA 42; (2009)
239 CLR 51 at 62 [14]. I agree with the defendant's submission that this Part of
the CLA appears to be dealing with broader liability than the action in
negligence referred to in Part 1A. However it will be necessary to separately
consider the applicability of each section relied upon by the defendant.
Section 42 of the CLA
- The
first sections relied upon by the defendant are ss 41 and 42 in Part 5 of the
CLA that relevantly provide:
41 Definitions
In this Part:
"exercise" a function includes perform a duty.
"function" includes a power, authority or duty.
...
42 Principles concerning resources, responsibilities etc of public or
other authorities
The following principles apply in determining whether a public or other
authority has a duty of care or has breached a duty of care
in proceedings for
civil liability to which this Part applies:
(a) the functions required to be exercised by the authority are limited by
the financial and other resources that are reasonably available
to the authority
for the purpose of exercising those function s ,
(b) the general allocation of those resources by the authority is not open to
challenge,
(c) the functions required to be exercised by the authority are to be
determined by reference to the broad range of its activities
(and not merely by
reference to the matter to which the proceedings relate),
(d) the authority may rely on evidence of its compliance with the general
procedures and applicable standards for the exercise of
its functions as
evidence of the proper exerci s e of its funct i on s in the matter to which the
proceedings relate.
- The
defendant submitted that by operation of ss 41 and 42 of the CLA, its obligation
to perform any duty is limited by resources reasonably available to it for
performing those functions
and the allocation of those resources is not open to
challenge. It was submitted that the plaintiff's assertion that it was incumbent
upon the defendant to expend millions of dollars of public funds eliminating the
risk that the lack of a flow path for flood waters
across NPE would result in
damage to the Land and/or the creation of additional froglet habitat involves
"challenging" the defendant's
allocation of its resources which is prohibited by
s 42 of the CLA.
- The
defendant submitted that irrespective of whether or not s 42 operates in this
way, an assessment of the reasonableness of the defendant's conduct in failing
to undertake the Blue Jay Circuit
project or its equivalent cannot be undertaken
without also factoring into consideration the risk to the plaintiff that ought
to
have been in the defendant's contemplation and that ought to have been
balanced against the expenditure to complete the work. It
was submitted that it
is relevant in that context to note that there was no complaint of ponding or
saturation of the area in the
vicinity of Turnock Street, associated with the
inadequacy of the 1200mm pipe or otherwise, at any time prior to the discovery
of
the froglet population in 2003. I agree that there was no such "complaint"
made by the plaintiff. However it is clear that the parties
had been working
towards a drainage strategy for the area.
- The
defendant submitted that even if it is accepted that the creation of the ponds
and the Wallum Froglet habitat were foreseeable,
circumstances surrounding the
breach of development conditions at NPE were not such as to suggest extensive
works were required in
order to avoid the creation of such ponding and habitat.
Precisely the same issues arise in connection with the claim that additional
culverts and table drains should have been constructed under and adjacent to
Turnock Street. The defendant submitted that any such
drainage was temporary and
would be redundant when the land was filled. If the question of whether public
resources should be expended
in order to ameliorate the risk of the propagation
of an endangered froglet species is to be considered, and even assuming that the
risk was foreseeable, the defendant submitted that it cannot be regarded as
having been in breach of a duty owed to the plaintiff
in failing to expend funds
on temporary drainage to address that risk.
- Finally,
the defendant submitted that liability can only be established for a failure to
address the blocked drains if it can be established
that the defendant owed a
duty to carry out routine inspections of such a nature and at such intervals as
would have revealed the
existence of the problem in time to avoid the creation
of the froglet habitat. It was submitted that in light of the provisions of
s
42(d) of the CLA that expressly permit the defendant to rely upon its general
procedures (reactive maintenance of drains), the plaintiff's
difficulties are
insuperable.
- Mr
Stephen Paff is an engineer and has been employed by the defendant as a
"Maintenance Engineer" since 1994. His duties include responsibility
for
maintenance activities to public roads, bridges, stormwater, footpaths and
associated infrastructure within the Tweed Shire;
development and management of
Asset Management Systems for road infrastructure; and management of road
maintenance staff and budgetary
control. Mr Paff gave evidence that in January
2003 the defendant adopted a "Strategic Asset and Service Management Program"
which
was devised by an independent risk management firm. That program included
the following:
14.26.2 Preventative or Routine Maintenance Inspection
No preventative or routine maintenance inspection of any stormwater or
drainage system shall be carried out.
14.26.3 Technical Inspections
A technical inspection of stormwater or drainage systems shall be carried
out:
as and when determined necessary; and
at a level and standard;
determined by a responsible person.
- In
cross-examination Mr Paff agreed that a "Drainage Assets Management Plan" (Ex 3)
had been drafted in 2009 but that the defendant
had not yet adopted it (tr
1007). In the "Stormwater Drainage Maintenance Service Level Manual" (Ex 4)
there is reference to "Proactive
Inspections" which are said to be "As per
Council 'Proactive Inspection Schedule' in Maintenance Manual". However this
Manual also
provides that "Pipes will be inspected on a needs basis". The
Drainage Assets Management Plan includes the following:
5.5 Maintenance Inspections of Drainage Assets
The frequency of proactive and reactive maintenance inspections is undertaken
as per the frequency, documented in Council's maintenance
levels of service.
...
5.11 Routine Maintenance
Over time, minor faults can occur within the Drainage network. Tweed Council
addresses the repairs and maintenance of these faults
on the basis of defined
intervention levels and response times.
The intervention level defines the condition, state or risk level associated
with an asset component, i.e. the point in time at which
the asset is considered
to be below an acceptable level of service. Maintenance is scheduled as soon as
the asset reaches this point
Response time defines a reasonable timeframe within which the residents can
expect the Tweed Shire to remedy the defect. The intervention
levels and
response times are contained in the Shire's maintenance levels of service
documents, (available for inspection at Council's
offices).
- The
Drainage Assets Management Plan also includes a section on costing in particular
an historical overview of the capital expenditure
between 2005 and 2009 on
certain "Capital Activity" being drainage asset management, drainage
construction and stormwater drainage
rehabilitation. That history records total
capital expenditure in 2005/06 of $199,050, in 2006/07 of $1,377,854, in 2007/08
of $1,929,478,
and in 2008/09 of $1,749,094. The total "Operation and
Maintenance Activity" expenditure is recorded as $854,497 in 2004/05, $1,192,825
in 2005/06, $1,273,912 in 2006/07 and $1,615,204 in 2007/08.
- Mr
Paff gave evidence that there is no proactive maintenance of stormwater
infrastructure. It is only inspected on a complaints basis
(tr 1005). Mr Paff
has only been aware of complaints by the plaintiff about the wetting up of its
Land since 2007. He was not aware
of complaints by the plaintiff prior to that
date (tr 1040). That may be so but it is clear that from 5 March 2003 the
plaintiff
had complained that there was unlawful discharge of concentrated
stormwater onto the Land from the Council's drainage structure.
It is not clear
why Mr Paff was not made aware of the plaintiff's complaints in this regard.
- Mr
Paff was cross-examined in relation to the Roads and Traffic Authority (RTA). He
said that responsibility for roads are allocated
to the defendant under the
Roads Act and that the defendant is the roads authority for most regional
roads other than expressways and motorways. The defendant has the
legal
responsibility under that Act for maintaining both regional and local roads (tr
1053). Mr Paff agreed that for the maintenance
of regional roads the RTA
provides a block grant. The defendant also receives funding from the Federal
government by way of untied
financial assistance grants that it can spend on
local roads (tr 1054). Every year the defendant receives $400,000 for stormwater
repairs as part of a seven-year plan (tr 1055). Elrond Drive is a "road drain"
(tr 1056). Kerb and gutter and table drain clearing
have always been costed to
road maintenance and not to stormwater (tr 1057).
- A
print out from the defendant's webpage, downloaded on 18 March 2011, (Ex SS)
includes the following:
West Kingscliff Drainage $2,000,000
The stormwater drainage outlet for part of Kingscliff (behind the southern
section of Kingscliff Street and northern section of Pearl
Street) has been
partially blocked by filling associated with past subdivision development in
West Kingscliff. The pipes that drain
this area are only big enough for a 1 in
five year storm. A larger outlet is needed for bigger storms. If this is not
provided there
is likely to be periodic stormwater flooding of some property,
and residences in this part of Kingscliff. Council may be exposed
to liability
claims if this outlet is not provided.
- Mr
Paff did not know the origin of part of this entry on the defendant's webpage
(tr 1059). He is provided with a budget for the year's
works and if there is a
need to go outside that budget to deal with an urgent drainage issue he reports
that to his next level of
management. There is then a budget review. He agreed
that he had exceeded his budget from time to time (tr 1061). What usually
happens
is that money is reallocated from other programs within the total budget
so that the total budget stays the same but activities change
(tr 1061).
- The
plaintiff submitted that s 42 of the CLA is premised upon a judicial
consideration of a "duty of care" and can have no application
in relation to the
present claim, which is based in nuisance and not in negligence. It was
submitted that this is sufficient to dispose
of the so-called "defence" under s
42 of the CLA. Although Part 5 may be applicable to wider claims than
negligence, including nuisance,
the provisions of s 42 deal specifically with a
duty of care. The "duty" imposed on the defendant in the tort of nuisance is not
in the circumstances of this case (where the defendant caused and was notified
of the nuisance) a "duty of care" but a duty to take
reasonable steps to
eliminate the nuisance. It is conceivable that in taking steps to eliminate a
nuisance a duty of care may be
separately imposed on a defendant the breach of
which would expose it to a suit in negligence. I am satisfied that the
plaintiff's
submission that s 42 is inapplicable to this case should be
accepted. That is not to say that in considering whether the defendant
took
reasonable steps to eliminate the nuisance I should not have regard to matters
that are reflected in s 42 of the CLA.
- The
plaintiff also submitted that the two distinct aspects relied upon by the
defendant are the resource limitations in relation to
carrying out drainage
works and compliance with procedures for maintenance of drainage works. In
respect of the resource limitations
the plaintiff relied upon what was said in
Sydney Water Corporation v Turano at 65 [27] that the defendant must lead
evidence of its financial or other resources so as to raise the operation of the
section.
The plaintiff submitted that the evidence led from Mr Paff did not
establish any financial limitations on the defendant. I agree
with that
submission.
- The
plaintiff relied upon two reports from Gary Frederick Mottau an accountant with
experience of working in local government. Mr
Mottau worked as the principal
accounting officer at Warringah Shire Council for nine years and is now the
principal of the accounting
firm Hill Rogers Spencer Steer. In his reports (Ex
TT) Mr Mottau analysed the financial statements of the defendant for the year
ending 30 June 2010. He concluded that the operating result for the year was a
surplus of $9.005 million and that it had excess available
funds of $10.414
million. Its available working capital was $6.816 million. Mr Mottau noted that
the defendant had unanimously adopted
the Quarterly Budget Review statement as
at 31 December 2010 at its ordinary meeting held on 15 February 2011. That
report discloses
the projected Available Working Capital as at 30 June 2011 to
be $6.069 million. Mr Mottau analysed the variations in the General
Fund and
concluded that the changes demonstrated a considerable discretion in allocating
funds to and from the capital works program
during the year. Mr Mottau's
conclusion was that the defendant has access to a number of sources of funding
in the short term to
carry out additional stormwater drainage works without
adversely impacting its key financial performance indicators.
- In
cross-examination Mr Mottau was taken to the financial statements of the
defendant for the year 2009/10. The non-cash contributions
for water at $2.395
million, sewage at $5.834 million together with dedications for roads at $2.936
million, drainage at $1.532 million
and open space at $1.814 million were drawn
to his attention. He gave the following evidence (tr 1160):
Q. But the simple proposition is that a non-cash contribution is in the
nature of a dedication of an asset; it doesn't provide funds
from which the
council can fund its activities, correct?
A. Well, it doesn't stop a council from disposing of that asset and using the
funds to carry out its activities, as long as it goes
through the process on
which the asset has been provided to the council, and councils have done that.
Q. You wouldn't expect that road and drainage dedications would be capable of
being realised in the course of the management of the
council's activities and
used to fund its expenditure would you?
A. Your Honour, what has happened - it has happened in the past, I know of
examples where councils have closed roads, sold with approval
under the Roads
Act, and used those funds for the purposes of which the council saw fit.
- Mr
Mottau was cross-examined in relation to the suggestion that the defendant was
not able to fund depreciation from its revenue.
He gave the following evidence
(tr 1162):
Q. What this demonstrates is that it is unable to fund its depreciation from
its revenues in 2010, isn't it?
A. From its operating revenue, yes.
Q. And the surplus shown, five lines further down is after capital grants and
contributions of $24.4 million, correct?
A. That's correct.
Q. And those that council is not at liberty to expend those capital grants
and contributions in any way it wishes, is it?
A. No, there are often conditions attached to those grants and contributions.
Q. We have seen that a substantial proportion of the $24.4 million capital
contribution is in the form of noncash capital grants and
contributions,
correct?
A. Correct.
Q. Any capital contributions from a section 94 plan would be tied to whatever
project was related to the section 94 plan, correct?
A. Correct.
Q. And capital grants and contributions from government agencies are
frequently tied to particular types of projects, for example
road projects from
road authorities, correct?
A. Yes.
- Mr
Mottau was cross-examined in relation to the criteria published by the
Department of Local Governments (DLG) including an indicator
for the ratio of
current unrestricted assets to current unrestricted liabilities. He was also
cross-examined in relation to the way
that he used that information as follows
(tr 1163-1166):
Q. The proposition that I put to you is that that isn't an exercise by which
you can meaningfully make an assessment of the amount
of funding available to
the council or excess funding available to council to fund additional projects
such as drainage projects,
is it?
A. I think it is a very good indicator, in fact the DLG has it as the number
one indicator.
Q. The DLG has it as an indicator of the current state of financial health of
a council, correct?
A. It does, yes.
Q. It doesn't use it to calculate what amount of, as you describe it, excess
available funds a council has for funding such things
as drainage projects, does
it?
A. It can be used for that purpose.
Q. You have used it for that purpose, the DLG doesn't use it for that
purpose?
A. I am not aware what the DLG uses it for other than to provide comparative
data.
Q. It is not an appropriate means of identifying excess available funds for
things such as drainage projects because the ratio rates
only to current assets
that are not the subject of external restrictions, doesn't take into account
internal restrictions, does it?
A. No it doesn't but internal restrictions are the discretion of the council.
Q. Yes and the discretion of council in imposing internal restrictions as you
understand it and in your experience is exercised as
part of a proper and
prudent management of the council's affairs, isn't it?
A. That's correct.
...
Q. You did describe the amount of reduction in the current assets that this
council could endure without falling into the unsatisfactory
category as excess
available funds, correct, in paragraph (b)(ix) of your report?
A. I described it as being, that's correct, excess available funds given that
calculation, yes.
Q. They are not excess available funds in the sense of being available to use
on things such as drainage projects if those funds are
subject to internal
restrictions, are they?
A. Your Honour they are. Internal restricted assets as you see at the
discretion of council and can be changed at the next council
meeting.
Q. And if we make the assumption that the internal restrictions were placed
on those funds in the exercise of the careful and prudent
management of the
council's affairs then you wouldn't expect council to do that, would you?
A. That's given the assumption that is what those, I haven't made an
assessment, I think the Court should know I haven't conducted
an audit of
council's financials and haven't referred to their internally restricted cash. I
am merely using the DLG as a headline
indicator for indicating that an excess of
current assets existed as at that 30 June 2010 given the published financial
data.
...
Q. And of that amount only $1.91 million is unrestricted cash, that's the
position, isn't it.
A. In relation to cash it is.
Q. You would expect things such as drainage works and drainage maintenance
carried out by council to be funded from its general fund
resources?
A. Yes.
Q. And you would expect it to be funded from cash resources wouldn't you?
A. Cash is one source. There are debtors of nine and a half million dollars
which are readily realisable to cash, there are inventories,
there are other
sources that make up current assets other than just cash.
Q. We will come to your calculations in relation to current assets in a
moment. The proposition that your calculation at paragraph
14(b) of the report
identifies excess available funds of $10.4 million is, I suggest to you, a
little rash in light of the fact that
council had available to it as at the
balance date only $1.91 million in unrestricted cash, do you agree with that?
A. I don't agree with that.
...
Q. And you have identified there that available working capital of the
council as at the balance date stood at 6.816 million?
A. Correct.
Q. That is primarily a function, isn't it, of an exercise of comparison
between the balance of payables and the balance of receivables,
correct?
A. No, it isn't. The net current assets of the council which is looking at
current assets less current liabilities on the face of
the balance sheet would
indicate that council's net current assets is $132 million. My calculation over
the page is where I go through
adjusting for the restrictions that are placed on
those assets to come up with the net result of $6.8 million dollars (sic).
...
Q. Receivables in the form of resources in the form of cash when council
receives the payment expected?
A. Yes.
Q. And the amount of the cash available at any particular time will depend
upon timing of the performance by the council of its obligations
and in
connection with its payables?
A. Yes.
Q. The available working capital as at 30 June 2010 insofar as it comprised
cash resources still only comprised the $1.9 million in
unrestricted cash that
we identified a few minutes ago, didn't it?
A. Yes, that is $1.9 million would be a component of that 6.8.
Q. And there was no other component of that $6.8 million as at the balance
date that represented a resource available to the council
to pay for drainage
maintenance or infrastructure works?
A. Well, on the contrary your Honour, I think that any organisation, councils
included, any business uses its working capital to build
its budget for the next
year and as at that time its my assessed view that council had $6.8 million to
build its budget for the next
year.
Now, that would include, that's access to things like receivables less the
amount it owes in creators and you would expect in the
normal course of time,
within a year, otherwise it wouldn't be classed as current asset or liability,
that there was an excess to
the extent of $6.8 million to build its, to add to
its budget for the following year.
- Mr
Mottau agreed that there are difficulties associated with increasing the revenue
needed to service borrowings on the general fund
(tr 1169). He also accepted
that he had not conducted an analysis that would enable him to make any comment
on whether in the prudent
operation of the defendant's activities it would be
sensible to increase the debt service ratio. He made clear that he was not
suggesting
that one of the variations that the defendant might consider was
additional funds. Rather he suggested that the defendant has a discretion
to
allocate funds within its budget to different priorities (tr 1170).
- Mr
Mottau's evidence and reports are not a challenge to the way in which the
defendant has structured its financial activities. Rather
it demonstrates that
there is a capacity to meet the cost for the completion of the Blue Jay Circuit
project that would eliminate
the nuisance on the Land.
- As
to the procedures of reactive maintenance referred to in the evidence of Mr
Paff, the plaintiff submitted that the defendant has
not complied with the
procedures. The plaintiff complained that the defendant failed to call its
General Manager, Mr Rainer, or its
Director of Engineering Services, Mr Knight.
It was submitted that in the result the evidence does not support an assertion
that
there are any relevant general procedures with which the defendant has
complied for the purpose of s 42(d) of the CLA or otherwise.
- The
evidence of Mr Paff and Mr Mottau does not support the conclusion that there are
real financial constraints on the defendant.
Even taking into account the broad
obligations that the defendant has to the general community in the area, I am
satisfied that once
it became aware of the withdrawal of the permit by the
plaintiff it was able to create a plan to eliminate the nuisance, being the
Blue
Jay Circuit scheme, but failed to implement it. There is no real challenge to
the way that the defendant has allocated its resources.
The fact of the matter
is that the defendant had an obligation to take steps to eliminate the nuisance
that it had created over the
years, tolerated by the plaintiff for many years,
but in respect of which it had an obligation to rectify from 4 May 2004.
- In
conclusion I am satisfied that s 42 does not apply to the circumstances of this
case and even if it did I am not satisfied that the evidence supports the
conclusion
that the defendant's failure to take steps to eliminate the nuisance
and/or nuisances is justified or should be excused by reason
of any financial
constraints on the defendant.
S 43A CLA
- Section
43A relevantly provides:
43A Proceedings against public or other authorities for the exercise of
special statutory powers
(1) This section applies to proceedings for civil liability to which this
Part applies to the extent that the liability is based on
a public or other
authority's exercise of, or failure to exercise, a special statutory power
conferred on the authority.
(2) A "special statutory power" is a power:
(a) that is conferred by or under a statute, and
(b) that is of a kind that persons generally are not authorised to exercise
without specific statutory authority.
(3) For the purposes of any such proceedings, any act or omission involving
an exercise of, or failure to exercise, a special statutory
power does not give
rise to civil liability unless the act or omission was in the circumstances so
unreasonable that no authority
having the special statutory power in question
could properly consider the act or omission to be a reasonable exercise of, or
failure
to exercise, its power.
- The
defendant submitted that all of the alleged acts of nuisance concern exercises
or failures to exercise "special statutory powers"
within the meaning of s 43A
of the CLA. The conduct in relation to the conditions imposed in respect of the
filling the Northern
Drain and the extension of Lorien Way concerned the
defendant's approval powers under the EPA Act. The failure to inspect and
maintain
the 1200mm pipe concerned the defendant's failure to exercise either
its Roads Act powers or its drainage powers under s 59A of the LGA. It
was submitted that the failure to eliminate the nuisance was a failure to
exercise a special statutory power within the meaning of s 43A of the CLA.
- Additionally
it was submitted that the construction of Turnock Street with inadequate
culverts and without table drains concerned
the defendant's exercise of its
approval powers under Part V of the EPA Act and its Roads Act powers in
constructing and failing to maintain the culvert. It was submitted that all of
this conduct involved the exercise or failure
to exercise "special statutory
powers".
- The
defendant contended that it learned of an inadequacy in the design and
construction of the 1200mm pipe after it had released the
linen plan in respect
of the NPE. It approved the Martin Findlater design before its receipt of the
WMB draft drainage strategy providing
for the lateral drain. It contends that
between 1994 and 1997 it took reasonable steps to amend DCP 9 to provide for a
detention
basin solution as recommended by Mr Findlater in 1995. In 1997 it
constructed Turnock Street providing a low level culvert for overflows
from the
1200mm inlet in accordance with the design produced by an independent consultant
engineer.
- The
defendant submitted that at the time Turnock Street was constructed, flows of
stormwater to the southern end of the Land might
reasonably have been expected
every five years or so, perhaps every few years, but it had not been identified
by anyone as a likely
frequent occurrence. It was submitted that it is also
important to bear in mind that the drainage problems that were said to have
occurred in the vicinity of Turnock Street substantially disappeared when basic
maintenance was carried out to the plaintiff's drains.
The defendant also
submitted that it had no reason to anticipate that the plaintiff would not
assume responsibility for the maintenance
of its own drains and consequently the
defendant had no reason to anticipate that the construction of Turnock Street
would injure
the plaintiff. The complaints regarding the design of Turnock
Street relate to the absence of table drains and the provision of only
one low
lying culvert. It was submitted that given the circumstances that further low
level culverts and table drains would be rendered
obsolete when the Land was
filled, and given that any substantial impediment to the use of what was then an
unoccupied development
site was not readily obvious, acceptance of a proposal
from a consultant engineer which served to reduce the cost to the public of
building a road in that fashion was manifestly reasonable conduct.
- The
plaintiff submitted that s 43A(2) has two components, first that a "power" be
conferred under a statute, and secondly that a power
is of the kind that
"persons generally are not unauthorised to exercise without specific statutory
authority". It was submitted that
the so-called "powers" identified by the
defendant do not satisfy these requirements. For example an approval of a
development, such
as NPE, might involve several powers. It could be the grant of
development consent, building approval, sub-division approval, a construction
certificate, a sub-division certificate and so on. It was submitted that at
least three different statutes are potentially involved:
the Local Government
Act 1919 (applicable until 1994, except for sub-division approvals, which
continued in force until 1 July 1998); the LGA and the EPA Act.
- It
was submitted that s 43A calls for a complex evaluative exercise requiring the
Court to consider the particular exercise of the
identified special statutory
power and to consider its contextual reasonableness. It was also submitted that
the Court must consider
the extent to which the special statutory power is
"involved", if at all. It was contended the defendant's attempt to activate the
defence at a high level of generality is inadequate and should be rejected.
- Precision
Products (NSW) Pty Ltd v Hawkesbury City Council (2008) 74 NSWLR 102; [2008]
NSWCA 278 was a case in which the Council sought the protection of s 43A of the
CLA in respect of the alleged negligent exercise of power under
the
Protection of the Environment Operations Act 1997 said to have caused
damage to the appellant's business. Allsop P, with whom Beazley and McColl JJA
agreed, said it was not appropriate
to express a concluded view about the
meaning and effect of s 43A. The learned President observed that the wording of
s 43A(3) has
"its source in what is often referred to as "Wednesbury
unreasonableness" from Associated Provincial Picture Houses Ltd v Wednesbury
Corporation [1947] EWCA Civ 1; [1948] 1 KB 223 at 229-230". His Honour also said at 141 [177]:
Whether it is appropriate to describe s 43A as encapsulating the blunt
expression of "gross negligence" is a matter for debate. However,
it is plain
that the drafter of s 43A was attempting to ameliorate the rigours of the law of
negligence.
- The
High Court has noted the "uncertain reach of s 43A": Sydney Water Corporation
v Turano at 65 [26]. Notwithstanding this uncertainty and perhaps the
limitation of the section to ameliorating the law of negligence rather
than
nuisance, I am going to assume that it applies to the consideration of whether
the defendant took reasonable steps to eliminate
the nuisance.
- The
plaintiff submitted that there is a more fundamental difficulty with the
defendant's attempt to rely upon this section. The plaintiff's
claim against the
defendant is one brought in nuisance by reason of the continuing operation of
the stormwater drainage network.
The defendant performs many functions and has
many duties. Relevantly it is the drainage authority for drainage, including
stormwater
drainage. Section 43A speaks of a "special statutory power", not the
exercise of a function or a duty. It was submitted that it is
the narrower
exercise of, or failure to exercise, that power. The LGA and the defendant's
policies required developers to vest in
the defendant the legal title to the
drainage network. It was submitted that the defendant needed no special power to
inspect or
maintain its own land. The proposed works for Blue Jay Circuit
entailed upgrading the existing corridor and no "special" statutory
powers are
required to do that. It was submitted that therefore the circumstances of this
case do not involve the exercise of or
a failure to exercise identifiable
special statutory powers.
- The
defendant's obligations to its constituents are complex and overlapping. In
exercising its powers to require an applicant for
development approval to
conduct various impact studies, it has regard to numerous and varied attributes
of the particular community.
It exercises powers under the various statutes
referred to above to enable the implementation of drainage strategies that may
complement
one property but be adverse to another. It has to balance numerous
interests and community priorities in a fair and transparent manner.
- The
plaintiff must establish that "the act or omission was in the circumstances so
unreasonable that no authority having the special
statutory power in question
could properly consider the act or omission to be a reasonable exercise of, or
failure to exercise, its
power". The defendant contended that the plaintiff
cannot satisfy this test on the evidence. The plaintiff submitted that the
factual
matters upon which it relies justifies a finding that the defendant's
conduct was unreasonable in the Wednesbury sense. Those matters included:
the failure of the defendant to inform the plaintiff that it had permitted the
extension of Lorien
Way without provision for the Northern Drain to flow under
it; that it filled or permitted the Northern Drain to be filled without
the
construction of an adequate alternative drainage route for the stormwater
runoff; and that it had instructed WBM not to address
problems raised by it and
by Knobel Consulting in relation to the 1200mm pipe. It was submitted that the
defendant knew of the problem
with the 1200mm pipe well before the release of
the NPE linen plans.
- These
matters, although factually correct, relate to conduct that caused the
unreasonable interference with the plaintiff's enjoyment
of the Land. They are
matters concerning the creation of the nuisance rather than steps taken towards
its elimination. The question
to be decided is whether, after the plaintiff
advised the defendant of the nuisance in May 2004, did the defendant take
reasonable
steps to eliminate the nuisance. The plaintiff submitted that the
defendant has taken no steps to eliminate the nuisance. The plaintiff
mitigated
the harm itself by the creation of the table drains. It designed around the
problems, at its own cost, and complained to
no avail. In all the circumstances
it was submitted that no reasonable Council would act in the manner that the
defendant has acted.
Rather it was submitted that a reasonable Council would
have taken steps to eliminate the flow of stormwater onto the Land.
- I
accept that the defendant took the view that the plaintiff planned to develop
the Land and that it would be necessary to fill the
Land to the level at which
the culverts under Turnock Street were constructed. I accept that is why the
culverts were designed and
constructed at the level to accommodate the fill. The
defendant's conduct suggests that it had anticipated the plaintiff would move
more promptly than it has been able to in developing the Land. However the
defendant burdened the plaintiff with the additional stormwater
runoff when NPE
breached its obligations. It then imposed a condition on the plaintiff that
before any development consent would
be granted the plaintiff was required to
submit an acceptable drainage plan to remove the additional stormwater.
Accordingly the
timing of the development consent was in part in the defendant's
control.
- When
the plaintiff withdrew the permit in March 2003 and from 4 May 2004 when it
advised the defendant that there was an unreasonable
interference with its
enjoyment of the Land, the defendant was obliged to take reasonable steps to
eliminate the nuisance. Mr Knight's
memorandum of 27 February 2003 is
instructive. It is clear that the defendant regarded any development of the Land
as a removal of
its stormwater drainage storage capacity, that is, it would
inhibit the defendant's capacity to use the Land as a retention basin
for the
stormwater run-off. This use had been without any compensation to the plaintiff.
- Once
the plaintiff complained and withdrew the permit the position between these
parties changed. The defendant had created the nuisance
and it did not take any
steps to eliminate the nuisance. It has a plan, the Blue Jay Circuit Scheme,
that will eliminate the nuisance
but it will not implement it until it receives
a contribution from the Nursing Association. In the mean time the plaintiff has
had
the burden of the cost and inconvenience of retaining experts to assist it
to mitigate the harm to the Land by the creation of the
table drain in 2004 and
commencing and pursing these proceedings to prompt the defendant into taking
steps to eliminate the nuisance.
- The
vagaries of the development of land are such that any reasonable Council would
know that there is always uncertainty about the
time within which a development
may be approved and/or constructed. The longer there was no development of the
Land, the longer the
defendant was able to utilise the Land as a retention
basin. That seemed to be Mr Knight's attitude in February 2003. That position
remains the same today, eight years after the plaintiff made it very clear that
it was no longer willing to tolerate the additional
stormwater runoff onto the
Land.
- I
am satisfied that no reasonable Council would act in the manner that the
defendant has acted after it was notified by the plaintiff
that it would no
longer tolerate the inundation of the Land with the additional stormwater
runoff. I am also satisfied that to decide
on a scheme that will eliminate the
nuisance but not implement it and not take any other steps to eliminate the
nuisance is so unreasonable
that the defendant does not have the benefit of s
43A(3) of the CLA to justify or excuse its conduct.
- As
I have said above, in considering the application of s 43A of the CLA, I
regarded the relevant conduct of the defendant to be the
steps it took after
being notified of the nuisance. However if that is wrong and the relevant
consideration includes the original
conduct that caused the wetting up of the
Land, I am satisfied that no reasonable Council would act in the way the
defendant acted.
To burden the innocent neighbour, the plaintiff, with the
retention basin on its Land for the consequence of the breach of NPE, without
advising it of the true reason for its need and without any proposal for
compensation and then requesting it to fund expert surveys
on drainage of the
area in the amount of approximately $21,000 (albeit that there was some
suggestion of later s 94 credits in respect
of this amount), is in my view
extremely high-handed and unreasonable. The defendant does not have the benefit
of s 43A to excuse
or justify its conduct.
S 45 CLA
- The
defendant also relied on s 45 of the CLA which provides:
45 Special non-feasance protection for roads authorities
(1) A roads authorit y is not liable in proceedings for civil liability to
which this Part applies for harm arising from a failure
of the authority to
carry out road work, or to consider carrying out road work, unless at the time
of the alleged failure the authority
had actual knowledge of the particular risk
the materialisation of which resulted in the harm.
(2) This section does not operate:
(a) to create a duty of care in respect of a risk merely because a roads
authority has actual knowledge of the risk, or
(b) to affect any standard of care that would otherwise be applicable in
respect of a risk.
(3) In this section:
"carry out road work" means carry out any activity in connection with the
construction, erection, installation, maintenance, inspection,
repair, removal
or replacement of a road work within the meaning of the Roads Act 1993 .
"roads authority" has the same meaning as in the Roads Act 1993 .
- The
defendant submitted that it was the relevant "road authority" for all public
roads within the Tweed Shire and was responsible
for the roads including Pearl
Street, Quigan Street, Elrond Drive, Turnock Street and Lorien Way. The
defendant also submitted that
all of those roads and the drainage constructed
within the roads were public roads for which it was the relevant road authority.
- Section
45 of the CLA applies to "civil liability in tort" and for the same reasons as
submitted in respect of s 43A, the defendant contended
that it applies to an
action in nuisance.
- A
road authority is not liable for failure to carry out "road work" unless at the
time of the alleged failure the authority had "actual
knowledge of the
particular risk the materialisation of which resulted in the harm": The relevant
risk is the physical condition
which creates the risk: North Sydney Council v
Roman (2007) 69 NSWLR 240; [2007] NSWCA 27 at 272 [157] and 277 [186] per
Basten JA, Bryson JA agreeing.
- The
defendant submitted that in this case the relevant physical condition alleged
against it is the blockage and/or incapacity of
the Elrond Drive culvert. The
first complaint of incapacity of the Elrond Drive culvert was on 4 May 2004 in
the plaintiff's solicitor's
letter to the defendant. It was submitted that s 45
operates to protect the defendant, as by the time the Froglet was established in
2003, the defendant did not have actual knowledge
of the alleged incapacity.
However the presence of the ponding of the water per se (the non-frog case) was
well known to the defendant
at the time of the complaint and the knowledge of
the presence of the additional stormwater runoff on the Land would carry with it
an understanding that such presence could cause physical damage to the Land,
irrespective of the presence of the Wallum Froglets.
- It
was submitted that the plaintiff has not proved that the defendant actually knew
that the Elrond Drive culvert was blocked or drainage
through it was impeded at
any time before 4 May 2004; that there was any risk of ephemeral ponding of
sufficient duration to create
a habitat suitable for the Wallum Froglet to
establish a viable local population north of Turnock Street; and that there was
any
blockage or impediment downstream of the Elrond Drive culvert affecting the
drainage through the culvert. Accordingly it was submitted
that the defendant is
protected by the immunity from any civil liability in tort arising from any
blockage of that culvert or in
any part of the road and road reserve.
- The
plaintiff submitted s 45 of the CLA creates "special" non-feasance protection
for "roads authorities". The plaintiff submitted that the defence has no
application
to the present case for three reasons. First, the provision only
protects a "roads authority": Buckle v Bayswater Road Board [1936] HCA 65; (1936) 57 CLR
259 at 273. In the present case the defendant is sued by reason of its function
as a landowner and a drainage authority. However assuming
non-feasance, the
plaintiff submitted that the work which was not done was not the carrying out of
"road work" in the capacity of
the defendant being the roads authority. The
special protection given by s 45 of the CLA cannot be called in aid generally by
an authority carrying out functions in a different capacity. Secondly, the
installation
of the 1200mm pipe and the Elrond Drive culvert was not "road work"
within the meaning of the Roads Act 1993. Thirdly, the complaint is in
relation to the design of the drainage, the incapacity of the 1200mm pipe and
the inadequacy of the
Elrond Drive culvert and is not a complaint arising from a
failure "to carry out road work" within the meaning of s 45 of the CLA.
- Section
146 of the Roads Act 1993 provides:
146 Nature of ownership of public roads
(1) Except as otherwise provided by this Act, the dedication of land as a
public road:
(a) does not impose any liability on the owner of the road that the owner
would not have if the owner were merely a person having
the care, control and
management of the road, and
(b) does not affect the rights or liabilities of any person under any
easement or under any Act or law, and
...
(d) does not constitute the owner of the road as an occupier of the land, and
...
(2) This section does not restrict the power of a roads authority to regulate
the digging up of public roads pursuant to the provisions
of any other Act.
- It
was submitted that the Roads Act does not exclude the liability of the
defendant by virtue of its ownership of the land and the drains which run
through the Road.
It was further submitted that the correct interpretation is
that the culvert was not "road work" because its construction was undertaken
by
reason of the defendant's duties as a drainage authority under the LGA and not
"for the purpose of facilitating the use of the
road as a road": Roads Act
Dictionary, "road work".
- It
was submitted that in this context the defence can only apply to a roads
authority. The activity about which the plaintiff complains
was not the conduct
of the roads authority but of the defendant in managing its stormwater system.
The plaintiff submitted that there
is no doubt, according to Mr Paff's evidence,
that the defendant manages the stormwater system separately from its road
programs.
Of critical significance was Mr Paff's evidence that drainage
culverts, as distinct from table drains, were not funded from the roads
budget
or managed as part of the road (tr 1056-1057). The roads authority itself does
not manage culverts as part of the road. It
was submitted that the defendant
cannot make good the predicate for the defence because it does not manage the
culverts in its capacity
as a roads authority.
- The
plaintiff submitted that the inlet to the 1200mm pipe is not in a road way. It
does not form any part of a road and is under a
pathway dedicated as such. The
language of the instrument (Ex XX) compels the conclusion that the path was not
dedicated as a public
road and the defendant does not need any special powers to
maintain it. The plaintiff submitted that the pathway and the pipe vested
with
the pathway upon the registration of the plans for that stage of the NPE.
- The
plaintiff submitted that s 45 of the CLA only requires actual knowledge of the
particular risk and not the harm or its materialisation. It was submitted that
the
defendant knew its drains were poorly designed and were inadequate. It was
aware from the drainage investigations by WBM in 1998
and by Knobel in 2001 that
its drains were causing drainage problems. It was submitted it therefore had
actual knowledge of the risk
that the drains would fail. It was submitted that
in any event because the legal onus is on the defendant to excuse its conduct,
it is required to establish, at the minimum, absence of actual knowledge. The
plaintiff emphasised the absence of Mr Knight and Mr
Rainer as witnesses and
submitted that the defendant had failed to discharge the onus.
- I
agree with the plaintiff's submission that the drainage system maintained by the
defendant is not "road work". However even if the
failure to install the
culverts under Turnock Street and the additional pipes provided for in the plans
for Elrond Drive could be
categorised as "road work", the defendant was well
aware that it had decided to use the Land as a retention basin and as such had
actual knowledge of the risk at the time, of the increased volumes of untreated
stormwater on the Land, that resulted in the harm.
- Assuming
the defendant is a roads authority and the Blue Jay Circuit Scheme is "road
work", it is quite clear that the defendant knew,
certainly from 4 May 2004,
that there was a risk that harm to the Land by the increased stormwater on it
would result from its failure
to carry out the road work. The defendant's
conduct is not justified or excused by the provisions of s 45 of the CLA.
Section 733 LGA
- The
defendant claims that it has at all times acted in good faith in its drainage
works. In this regard it relies upon s 733 of the
LGA which provides as follows:
733 Exemption from liability-flood liable land, land subject to risk of
bush fire and land in coastal zone
(1) A council does not incur any liability in respect of:
...
(b) anything done or omitted to be done in good faith by the council in so
far as it relates to the likelihood of land being flooded
or the nature or
extent of any such flooding.
...
(3) Without limiting subsections (1), (2) and (2A), those subsections apply
to:
(a) the preparation or making of an environmental planning instrument,
including a planning proposal for the proposed environmental
planning
instrument, or a development control plan, or the granting or refusal of consent
to a development application, or the determination
of an application for a
complying development certificate, under the Environmental Planning and
Assessment Act 1979 , and
...
(c) the imposition of any condition in relation to an application referred to
in paragraph (a), and
...
(g) any other thing done or omitted to be done in the exercise of a council's
functions under this or any other Act.
(4) Without limiting any other circumstances in which a council may have
acted in good faith, a council is, unless the contrary is
proved, taken to have
acted in good faith for the purposes of this section if the advice was
furnished, or the thing was done or
omitted to be done, substantially in
accordance with the principles contained in the relevant manual most recently
notified under
subsection (5) at that time.
(5) For the purposes of this section, the Minister for Planning may, from
time to time, give notification in the Gazette of the publication
of:
(a) a manual relating to the management of flood liable land, or
(b) a manual relating to the management of the coastline, or
(c) a manual relating to the management of land subject to the risk of bush
fire.
The notification must specify where and when copies of the manual may be
inspected.
- The
defendant submitted that ponding of water of the kind alleged by the plaintiff
falls within the meaning of "flooded" or "flooding"
in s 733: Melaleuca
Estate at 341-342 [78] to [80] per Giles JA. The existence of good faith
must be proved by the defendant as an attribute of the negligence
which excuses
liability. Good faith must be more than honest ineptitude: Mid Density
Developments Pty Limited v Rockdale Municipal Council [1993] FCA 408; (1993) 44 FCR 290.
- It
is conceded that in 1994 the defendant recognized the need for a drainage
strategy that accommodated the whole of the Kingscliff
area in accordance with
DCP 9. The defendant commissioned consultants to produce such a strategy. When
Mr Hill produced the drainage
report for the Bowls Club, the defendant provided
it to Mr Findlater who refuted its conclusions relating to the catchment size
and
the allowance for the Q100 flow. In early 1995 Mr Findlater produced an
Alternative Drainage Strategy that presented the three alternatives
referred to
earlier with a recommendation that the retention basin was the most economical
alternative. The defendant claims that
it encouraged the plaintiff to propose
further designs in relation to a final drainage solution but that this
encouragement was met
by the plaintiff's requests to delay the changes to DCP 9
until it prepared a "master plan" for all of the plaintiff's landholdings
in the
Kingscliff area.
- The
plaintiff submitted that the provisions of s 733 of the LGA do not apply because
the ponding complained of by the plaintiff is
not "flooding" but a failure of
the defendant's stormwater drainage system to cater for relatively small regular
stormwater runoff
events. It was submitted that s 733(4) and (5) refer to a
manual relating to the management of flood liable land. The NSW Floodplain
Development Manual was first released in 1986 and gazetted in 1987. The next
version was issued and gazetted in April 2005. The plaintiff
submitted that it
is significant that the defendant does not allege that the drainage problems
that are the subject of these proceedings
fall within the scope of either
version of that manual. The plaintiff contended that this is because the
drainage problems are local
drainage problems that fall outside its scope. The
plaintiff also submitted that to the extent that the acts and omissions of the
defendant relate to water quality as opposed to flooding, the section has no
application.
- The
plaintiff submitted that the defendant has not established that it acted in good
faith in relation to the nuisances. It contended
that the defendant acted
contrary to its stormwater and flooding protection policies and also permitted
NPE to breach them. It imposed
Q5 and Q100 conditions of consent on NPE and
approved the sub-divisions without the drainage works required by those
conditions,
knowing of those breaches. It permitted the blocking and subsequent
filling of the Northern Drain despite its experience with local
drainage
problems during the development of NPE and despite the fact that it had
previously permitted the blocking and filling in
of the Natural Watercourse.
- The
plaintiff submitted that when the defendant became aware of the drainage
problems resulting from the filling in of the Northern
Drain and NPE's refusal
to replace it with a Q100 flow path, it adopted the strategy put forward by Mr
Findlater despite the fact
that he had a clear conflict of interest and in
circumstances where the plaintiff was to bear the costs and damages burden of
either
accepting stormwater or apparently gifting its land to the defendant for
a retention basin without the informed consent or knowledge
of the reason for
the increased flow being the breach by NPE and its agent Mr Findlater.
- The
plaintiff submitted that the defendant met and corresponded with the plaintiff
and its agents on numerous occasions about drainage
issues on the Land, agreed
to the plaintiff undertaking the drainage study, and later requested the
plaintiff fund the bulk of the
WBM drainage study. It was submitted that at no
stage did the defendant inform the plaintiff that the drainage problems on the
Land
were the result of the filling of the Northern Drain and its replacement by
the inadequate 1200mm pipe. The defendant did not invite
the plaintiff to
participate in working groups directed at resolving the Kingscliff drainage
issues. Rather the plaintiff proposed
that a working group be established when
it was informed by the defendant that a large retention basin would be required
on the Land.
The plaintiff was not advised as to why such retention basin was
required. Although there is the ubiquitous mention from 1995 onwards
of the need
for amendment to DCP 9, this has not occurred.
- The
plaintiff also submitted that the defendant caused Turnock Street and Elrond
Drive to be designed and constructed with all but
one of the culverts above
ground level and with no table drain, in breach of its policies for drainage
under public roads and despite
the fact that it was aware of the increased
stormwater flows coming onto the Land. The plaintiff submitted that in those
circumstances
the defendant had not established that it acted in "good faith"
within the meaning of that expression in s 733 of the LGA.
- The
defendant's conduct in retaining Mr Findlater in the first place when he was the
representative of NPE, the party in breach of
the conditions of development
consent, is quite extraordinary. But to accept his recommendation that the
plaintiff should be the
party to bear the burden of the consequences of NPE's
breach is even worse. To accept it and impose it on the plaintiff without
advising
the plaintiff of the reason for its imposition and without offering any
form of relief or compensation to the plaintiff is extremely
high handed and
could not be described as acting in good faith. The defendant failed to disclose
the reason for its decision to utilise
the Land as a retention basin when it
entered into the agreement to purchase part of the Land and construct Turnock
Street. It was
not until the plaintiff's representatives had access to the
defendant's files that the plaintiff became aware that the Northern Drain
had
been filled by NPE in breach of the conditions of its development consent.
- Assuming
that the section applies I am not satisfied that the defendant's conduct in
imposing the retention basin on the plaintiff
was done in "good faith".
- The
defendant's conduct after the nuisance was bought to its attention in 2004 was
in my view also lacking in good faith. The plaintiff
approached the defendant in
a conciliatory fashion to see if they might find a "solution" together. Rather
than accept this approach
the defendant called for a public apology and payment
of large amounts of costs at a time when the defendant was still using the
plaintiff's Land as a retention basis at no cost to the defendant. It is hardly
conduct that could be described as in good faith.
- The
defendant does not have the protection of the provisions of s 733 of the LGA in
all the circumstances.
Damages
- The
plaintiff makes a number of claims in respect of the relief sought to abate the
nuisance including a mandatory injunction requiring
the defendant to complete
the Blue Jay Circuit Scheme. However in the alternative the plaintiff seeks an
award of damages in the
amount of $600,000 to compensate it for the need to
install a drainage system across the Land to accommodate the additional
stormwater
on the Land. The plaintiff also claims damages in respect of the loss
of the value of the Land that has to be quarantined to protect
the Wallum
Froglet habitat. A further claim is made for the additional cost and expense of
maintaining the Wallum Froglet habitat
by reason of the requirement to treat the
untreated stormwater to make it suitable for the Wallum Froglet habitat. The
plaintiff
also makes a claim for the additional cost that will be incurred in
relation to the fill that it will have to provide by reason of
the presence of
the untreated stormwater on its Land. There is also a claim for the cost
incurred in obtaining expert assistance
in 2004 in relation to the establishment
of the table drain and for the costs of and associated with the construction of
the table
drain. The plaintiff also seeks injunctive relief to rectify the
problems in relation to the Quigan Street outlets.
Blue Jay Circuit Scheme
- The
defendant has resisted this relief on the basis that it is premature to complete
the works until the plaintiff has indicated the
nature of the proposed
development of the Land and that it will proceed with its development. There is
no doubt that the plaintiff's
establishment of the table drain in 2004 has
reduced the problems that arose with the ponding of water north of Turnock
Street. I
have found that the table drain has abated the nuisance except after
major storm events. The drainage system in respect of the Land
is still
inadequate after major storm events and it is necessary to find a way in which
the plaintiff can be relieved of the burden
that has been imposed upon it by
reason of the inadequate drainage system and the use of its Land as a retention
basin.
- The
nuisance after major storm events will continue unabated unless steps are taken
to rectify the problem. It is accepted that the
drainage problems that have
caused the nuisance on the Land will be solved by the construction of the Blue
Jay Circuit Scheme. However
that process involves obligations to and of third
parties who are not parties to this litigation. Although it may be convenient to
describe the project in a short hand way as the "Blue Jay Circuit Scheme", it is
a complex process of road and drainage construction
that will affect a number of
third parties. There are also the vagaries of development and construction with
the consequent uncertainties,
both temporal and more substantive. If it were the
subject of a mandatory injunction of this Court it would require supervision.
This would be a most unsatisfactory outcome.
- The
question arises as to whether damages are an adequate remedy in the
circumstances: Bankstown City Council v Alamdo Holdings Pty Limited at
665 [11]. I am satisfied that damages are an adequate remedy. The plaintiff's
alternative claim for $600,000 is based on an agreed
figure adopted by Philip
Barlow and Kent Wood, valuers (Ex PD 10) that will enable the plaintiff to
install a drainage system on
the Land that will abate the nuisance. This figure
is made up of $571,000 plus an allowance for interest. I am satisfied that this
is the appropriate relief rather than the mandatory injunction.
Loss of value of the Land for Wallum Froglet habitat
- The
increase in the number of the Wallum Froglets on the Land was recorded in Mr
Parker's Report in April and May 2003. I have found
that there was a viable
population of Wallum Froglets on the Land in late 2002/early 2003. This occurred
before 5 March 2003 when
the plaintiff advised the defendant that it was no
longer willing to tolerate the discharge of the stormwater runoff onto the Land
and before 4 May 2004 when the plaintiff advised the defendant that there was an
unreasonable interference with the enjoyment of
its Land. Although all of the
physical features that were present at 4 May 2004 were present prior to that
time, the plaintiff tolerated
those physical features without demur as to its
enjoyment of the Land and thus there was no actionable nuisance prior to that
time.
- The
plaintiff cannot complain that the presence of the viable population of Wallum
Froglets was a consequence of the actionable nuisance.
It may well have been a
consequence of the conduct of the defendant prior to 2004 but the nuisance
action did not arise until there
was the unreasonable interference with the
plaintiff's enjoyment of the Land. As I have already said, the action in
negligence that
concerned the events prior to this time was abandoned on the
seventh day of the trial.
- I
am satisfied that because there was a viable population of Wallum Froglets on
the Land prior to the time of the first nuisance,
the plaintiff is unable to
recover damages for the exclusion of that part of the Land from its development
that is to be preserved
for the Wallum Froglet habitat.
- Although
in the circumstances of this finding it is unnecessary, I will shortly address
the foreseeability arguments that were raised
by the parties. The defendant
submitted that the plaintiff's claim that it should have had the risk of the
invasion of any endangered
species in mind in the course of its activities
raises the spectre of an obligation to have in mind the "risk" of preserving a
bewildering
array of potential invaders and presumably of promoting a wide range
of habitat requirements. The defendant posed the question of
whether in the
circumstances it is required to balance in its mind whether to preserve a wet
environment conducive to frog survival
or create a dry environment for the
survival of the threatened Mitchell's Rainforest Snail. The complexity of the
problem is illustrated
by the consideration of the species identified in the
fauna and flora studies prepared in connection with the Land. In the 1994 Warren
survey the threatened species included a broad range of "Avifauna", "Mammals"
and "Amphibians" recorded in the localities. Endangered
fauna possibly occurring
on the Land included the osprey, white-eared monarch, black-necked stork, black
flying fox, and the Queensland
blossom bat. The 1996 Woodward-Clyde survey
identified many different threatened faunal species on or near the Land.
- The
complexity is exacerbated by the differing opinions that were provided to the
parties during the 1990s. Mr Warren expressed the
view in 1994 that it was
possible though unlikely that the Land contained Wallum Froglets. He expressed
the view that if they were
to be on the Land it would be most likely that they
would be found in the "wet areas associated with the Paperbark forests". In 1996
Mr Warren said that they were most likely to occur "along the drain to the south
of the roundabout where a number of other frogs
were recorded". In 1999 he
expressed the view that they would be restricted to the "small areas" of
low-lying Paperbark vegetation
in Lot 13 and in the Paperbark swamp to the south
of the Land.
- I
do not accept that the prospect of the invasion of a colony of Wallum Froglets
should have been in the mind of the defendant when
it authorised the NPE
development or when it decided to utilise the plaintiff's Land as a retention
basin for the stormwater run-off
of the area. The amount of research that has
been carried out on the Land over the years would not have alerted either party
to the
prospect of the invasion of the colony of Wallum Froglets. The research
identified a single call of the Wallum Froglet in 1998, two
years after the
construction of Turnock Street, at a time when there was an anticipation that
the plaintiff would fill its Land in
the not too distant future.
- The
defendant did give consideration to whether there were Wallum Froglets present
on the Land that might be harmed by the proposed
development and the
construction of Turnock Street. There is no doubt that those investigations
suggested that there was no Froglet
population of any significance in that area.
The defendants submitted that in those circumstances it would be manifestly
unreasonable
to suggest that a reasonable Council would have been alert to the
risk that the development might serve to alter that position.
- I
accept that the defendant anticipated that the plaintiff would seek to develop
the Land sooner rather than later. I accept that
this anticipation was the
reason it constructed Turnock Street with the culverts approximately halfway up
the embankment to accommodate
the Land as filled. If the plaintiff is correct in
its submissions that the risk was foreseeable, the defendant would have had to
anticipate that the plaintiff would delay by a measure of years its filling of
the Land, that the increase in stormwater run-off
onto the Land would not only
be impeded by the absence of the culverts at ground level but would also be
impeded to the extent that
ephemeral ponding would not only occur but would
remain for necessary periods of five to six weeks in summer and/or some months
in
winter. I do not accept that the risk was reasonably foreseeable in all the
circumstances of this case. It was remote.
Cost of treating water for the Wallum Froglet habitat
- The
plaintiff submitted that the defendant must take the plaintiff as it finds it,
with the Wallum Froglet habitat and with its legal
obligation to protect it:
Roberts v Rodier (2006) 12 BPR 23,453; [2006] NSWSC 282 at 23,477. At the
time the defendant was put on notice that the plaintiff's enjoyment of the Land
was being unreasonably interfered
with it knew that there was a viable
population of Wallum Froglets on the Land. The risk that the plaintiff would be
put to additional
cost and expense in treating or improving the quality of the
untreated stormwater so as to accommodate the Wallum Froglet was foreseeable
but
the defendant has done nothing to alleviate or eliminate the flow of the
untreated stormwater onto the Land.
- It
is clear that the Wallum Froglet population has declined and indeed it could
disappear from the Land. There is the prospect that
the Blue Jay Circuit Scheme
will be completed when the contribution is received from the Nursing
Association. The timing of that
contribution is uncertain. It is also possible
(although it would be hoped not probable) that the defendant may revisit its
decision
and not proceed with the Blue Jay Circuit Scheme. There is the
complicating factor of the timing of the completion of any drainage
works the
plaintiff undertakes to remove the stormwater from its Land. As this process
will have to be undertaken in consultation
with and approved by the defendant
delay may well occur (having regard to the previous history between these
parties).
- The
plaintiff is entitled to recover any additional costs of treating the stormwater
that are incurred prior to the completion of
its drainage works or the
completion of Blue Jay Circuit Scheme. It is necessary to take into account the
fact that the plaintiff
would have to treat the water irrespective of the
stormwater on the Land caused by the nuisance. I am satisfied that the
appropriate
way to deal with this is to allocate a percentage of those costs.
This cannot be done with any mathematical or scientific precision
and in the
circumstances of the evidence, particularly since the installation of the table
drains in 2004, I am satisfied that the
appropriate allocation is 30% of those
costs up to the completion of the plaintiff's drainage works or the Blue Jay
Circuit whichever
is the earlier. These costs will need to be assessed in due
course.
Costs of the fill
- The
plaintiff also made a claim for the additional costs that will be incurred by
reason of the type of fill that will be required
for the development of the Land
that is caused by the presence of the additional stormwater on the Land. In the
light of the order
to be made for the award of damages for the plaintiff's
drainage works with the consequence that the nuisance will be abated I do
not
intend to make an award of damages for this claim.
Costs in relation to table drain
- The
plaintiff retained experts, including Dr Webb, to assist it to find an
appropriate mechanism to abate the nuisance. This resulted
in the construction
of the table drain. As I have already said this resulted in more efficient and
effective drainage of the Land,
so that the nuisance only occurs after major
storm events. I am satisfied that the plaintiff is entitled to recover the costs
of
retaining the experts and the costs of and associated with the construction
of the table drain.
Quigan Street Outlets
- There
was a question raised during the proceedings as to whether the plaintiff had
properly pleaded its claim in respect of the Quigan
Street outlets. Although
that submission may have had some force I was of the view that the evidence in
relation to those outlets
was relevant and that the plaintiff should be allowed
to proceed with its claim for injunctive relief in relation to the Quigan Street
outlets.
- After
the plaintiff opened its case I indicated to the defendant that the problem with
one of the Quigan Street outlets required attention.
The defendant indicated
that its officers wished to attend to repair the concrete apron on the side of
that outlet (tr 424). It is
not clear whether any rectification or repair work
has been done. The plaintiff seeks orders that the defendant install pollutant
traps and energy dissipation structures. I am satisfied that such work should be
completed. Unfortunately there has been disagreement
as to what steps should be
taken in this regard mainly, I apprehend, because the defendant has not regarded
itself as liable for
the cost of completing the works.
- I
am satisfied that the gross pollutant traps and energy dissipation structures
should be installed. I will either award the plaintiff
damages to compensate it
for the costs of the installation or alternatively the defendant can agree to a
regime of installation of
the gross pollutant traps and energy dissipation
structures. I will hear the parties on the orders to be made to effect this
result.
Conclusion
- The
plaintiff's claim for the mandatory injunction in respect of the completion of
the Blue Jay Circuit Scheme will be dismissed.
The plaintiff is entitled to an
award of damages in the amount of $600,000 on the basis that it will install a
drainage system on
the Land to divert the additional stormwater from the Land.
- The
plaintiff is not entitled to recover damages for the loss of the value of the
Land to be used for the Wallum Froglet habitat.
The plaintiff is not entitled to
recover the costs as claimed for the fill for the Land.
- Should
the plaintiff be required to continue to maintain the Wallum Froglet habitat, it
is entitled to recover 30% of any costs of
treating the stormwater to make it
suitable for the Wallum Froglet habitat up to the date of completion of its
drainage works on
the Land or the date of the completion of the Blue Jay Circuit
Scheme, whichever is the earlier. Those damages will be assessed in
due course.
- The
plaintiff is also entitled to damages for the costs of the expert advice and
assistance in respect of the table drain installed
on the Land in 2004 and of
the costs of and associated with the construction of that table drain. Those
damages are to be agreed
and if not agreed they will need to be assessed.
- Gross
pollutant traps and energy dissipation structures are to be installed in the
Quigan Street outlets. I will hear the parties
on the orders to be made to
effect this result.
- The
matter will be listed for the filing of Short Minutes of Order to reflect these
findings together with any agreed costs orders.
If the parties are unable to
agree on those orders I will list the matter for argument on a date to be
arranged with my Associate.
The parties should make contact with my Associate
with the agreed date for that listing by no later than 20 October 2011.
***************
SCHEDULE A
Image 1
SCHEDULE B
Image 2
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2011/1128.html