You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2011 >>
[2011] NSWSC 1039
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Clyde Bergemann v Varley Power [2011] NSWSC 1039 (9 September 2011)
Last Updated: 12 September 2011
|
Case Title:
|
Clyde Bergemann v Varley Power
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
Equity Division - Technology and
Construction List
|
|
|
|
Before:
|
|
|
|
|
Decision:
|
Summons dismissed with costs.
|
|
|
|
Catchwords:
|
BUILDING AND CONSTRUCTION - Building and
Construction Industry Security of Payment Act 1999 (NSW) - judicial review -
jurisdictional error - whether adjudicator fell into error by finding
entitlement to payment other than
in accordance with the mechanisms of the
contract - natural justice and procedural fairness - whether adjudicator failed
to afford
natural justice or act in good faith by omitting reference to
materials provided to him, but not brought to his attention by parties.
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
|
Parties:
|
Clyde Bergemann Senior Thermal Pty Limited (ACN 064
837 663) (Plaintiff) Varley Power Services Pty Limited (ACN 097 346 435)
(First Defendant) Max Tonkin (Second Defendant)
|
|
|
|
Representation
|
|
|
|
|
Counsel: F C Corsaro SC / I G B Roberts
(Plaintiff) M G Rudge SC / F P Hicks (Defendant)
|
|
|
|
- Solicitors:
|
Solicitors: Judd Commercial Lawyers (Plaintiff)
Moray & Agnew Lawyers (First Defendant) Philip Davenport (Second
Defendant)
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
Judgment
- When
the Building and Construction Industry Security of Payment Bill was
reintroduced into Parliament on 8 September 1999, the Minister made it clear
that the underlying intention was to assist "small
subcontractors, such as
bricklayers, carpenters, electricians and plumbers" to get paid for their work.
The Minister pointed out
(Hansard, Legislative Assembly, 8 September 1999, at
103) that many of those small subcontractors "cannot survive financially"
without
prompt payment, and that this had "severe consequences to themselves and
their families". Against that background, it may be doubted
whether the
legislature contemplated, when it enacted what is now the Building and
Construction Industry Security of Payment Act 1999 (NSW) (the Act), that its
benefits would extend to payment claims of about $3.955 million, relating to
major infrastructure projects,
as is the case in these proceedings.
- The
plaintiff (Bergemann) contracted to design, build, operate and maintain a fly
ash collection and disposal plant at Eraring Power
Station. Bergemann
subcontracted part of the works to the first defendant (Varley), by written
agreement (the subcontract), made
on about 8 July 2008, when Bergemann sent its
purchase order for the subcontract works to Varley.
- On
6 April 2011, following completion of works under the subcontract (but, at least
according to the adjudicator to whom I shall refer
in a moment, within 12 months
of completion of those works), Varley served the payment claim that is the
subject of these proceedings.
As I have said, it claimed an amount of about
$3.955 million. On 20 April 2011, Bergemann provided a payment schedule which
specified
("without prejudice") a scheduled amount of $300,000.00.
- The
dispute thereby constituted was referred to adjudication, by adjudication
application dated 9 May 2011. The second defendant (the
adjudicator) was
nominated as adjudicator, and accepted that nomination. Bergemann served an
adjudication response on 18 May 2011.
The adjudicator, who had been given an
extension of time to produce his determination, gave a determination dated 7
June 2011. He
determined, among other things, that Varley was entitled to a
progress payment of (in round figures) $2.5 million.
The issues
- Bergemann
submitted that the adjudicator fell into jurisdictional error, because (to adapt
the language of s 9(a) of the Act) he did not determine the amount of the
progress payment to which Varley was entitled in accordance with the terms of
the subcontract. This happened, Bergemann submitted, because the adjudicator
misconstrued cls 41.1A and 41.2A of the subcontract,
and failed to conclude (as,
it submits, he should have done) that the latter clause operated to bar Varley's
claim absolutely. In
those circumstances, Bergemann submitted, the adjudicator
had no jurisdiction to award Varley an amount that exceeded its contractual
entitlement.
- Thus,
the first issue for decision is whether an adjudicator acts in excess of
jurisdiction by determining that an applicant is entitled
to a progress payment
that exceeds the amount calculated in accordance with the terms of the contract.
- Alternatively,
Bergemann submitted that the adjudicator denied it natural justice, or failed to
exercise his statutory powers in good
faith, in the way that he dealt with a
number of claims for variations. Since there were many different variations
referred to, and
the reasons why the adjudicator's treatment of them was said to
involve the consequences to which I have referred varied, it is not
profitable
to go into further detail.
The determination
- Before
I turn to the first issue - jurisdictional error - I shall summarise the
adjudicator's approach to his task, as it appears
from his determination. Before
doing so, and referring back to what I said at the beginning of these reasons,
it is worth noting
that the adjudicator was confronted with 20 lever arch
folders of material, involving some thousands of pages in total, and was
required
to digest and analyse that material within the short space of time
allowed by the Act, as supplemented by the parties' generous concession
of an
additional seven days to produce his determination. To the extent that the
adjudicator's reasons are brief or sketchy, that
is hardly surprising; what is
surprising is that he managed to produce the comprehensive, structured and
rational document that he
did in the time available.
- The
parties referred to the adjudicator's determination strictly so called and to
his reasons for it as, together, the determination.
The only matters that are to
be "determined" by an adjudicator are the three set out in s 22(1) of the Act.
However, by s 22(3), the determination must be in writing and must include the
reasons for the determination. The parties' usage is both sanctioned by
the Act
and convenient, and I shall adopt it.
- The
determination comprises some 96 pages and 611 paragraphs. The adjudicator's fee
invoice shows that its preparation occupied him
for 140 hours. At least on its
face, the determination is logically structured. It sets out the general issues
by reference to:
(1) three issues, or groups of issues,
identified by Bergemann, that were said to justify withholding payment of any
amount in full;
(2) some four further reasons, not expressly identified
by the parties but identified by the adjudicator, which were also relied upon
to
justify withholding any payment whatsoever; and
(3) some five further
reasons which were generic although they did not affect all aspects of the
payment claim.
- The
adjudicator dealt with the reasons for non-payment in each category. He then
turned his attention to a further category, of reasons
for non-payment in the
adjudication response that were not, in his view, included in the payment
schedule. He dealt with those as
follows:
Reasons in the adjudication response submissions not included in the
payment schedule
102. There are a number of instances where the respondent has included in
submissions with respect to individual variations, new reasons
that it did not
include in the payment schedule.
103. In some case, but not all, I have identified the new reasons in this
determination.
104. The general principle that I have applied is that s.20(2B) of the Act
prohibits the respondent from including a reason in the adjudication response
that is not first included in the payment
schedule. Submissions based on such
new reasons are not submissions that have been duly made for the purposes of
s.22(2)(d) in my view, and I have not considered them.
- I
turn aside from describing the adjudicator's reasons, to note that Mr Corsaro
criticised this part of the determination on the basis
that it did not tell
Bergemann all the paragraphs had been rejected, and thus did not state
adequately the adjudicator's reasons
for his determination.
- I
note also that, where the adjudicator did identify s 20(2B) as applying, Mr
Corsaro asserted that he was wrong, and thus that Bergemann had been denied
natural justice. That submission cannot
be accepted. In John Holland Pty Ltd
v Roads and Traffic Authority of New South Wales (2007) 23 BCL 205, the
Court of Appeal said, although in obiter dicta, that a decision as to whether or
not a submission was "duly
made" (which is the inquiry that precedes the
application of s 20(2B)) fell within the province of the adjudicator to decide:
see Hodgson JA (with whom Beazley JA agreed) at [63], and Basten JA at [71].
In
Broad Construction Services (NSW) Pty Ltd v Michael Vadasz [2008] NSWSC 1057; (2007) 73
NSWLR 149, I held at [38] that I should follow that aspect of the Court of
Appeal's reasoning in John Holland . I remain of that view.
- Mr
Corsaro accepted that, at least to the extent that the adjudicator had
identified the submissions that he rejected on the basis
of s 20(2B), the
decisions to which I have referred rendered the point (of denial of natural
justice) unsustainable.
- I
return to the determination. Having dealt with matters of generality, the
adjudicator turned his attention to the 74 individual
variation claims that were
the subject of the payment claim and adjudication application. He dealt with
them individually, and summarised
his reasons in a table at [603] of the
determination. At this stage, I note that the total amount claimed for the
variations was
$3,894,910.70. The amount conceded by Bergemann totalled
$41,791.40. The adjudicator allowed amounts totalling $2,451,162.44.
- In
many cases, the adjudicator allowed an individual variation claim in the amount
of the claim. But in many cases, he did not. Having
said that, I do note that,
of the first ten variations listed at [603] (which were those exceeding
$100,000.00 in value) the adjudicator
allowed six in full; he disallowed three
entirely; and he allowed one at about 28% of the claimed amount. The six that
were allowed
in full comprise about 75% by value of the total amount allowed by
the adjudicator.
- In
dealing with the variations, the referee identified, in broad terms, the subject
matter of each; the submissions by Varley in support
and by Bergemann in
response (sometimes dealing separately with submissions directed to entitlement
and submissions directed to quantum);
and then gave reasons. When one reads the
reasons, they appear to be logical and coherent, in the sense that the
adjudicator appears
to deal with the issues posed by the parties as he has
stated them.
- It
is a feature of the adjudicator's reasons that he devotes the most space to the
most substantial (by value) of the variations.
His treatment becomes more
summary as the value decreases. Nonetheless, even in the latter case, it appears
on the face of the determination
that the adjudicator turned his mind to what he
perceived to be the essential issue and dealt with it - although in few words.
- Having
dealt with the variation claims, and having earlier dealt with other matters in
dispute as to credits that Bergemann said should
be offset against the amount of
any entitlement, the adjudicator calculated the amount of the progress payment,
and dealt with the
other matters (due date, interest and costs). His treatment
of those last three items has not attracted any criticism.
First issue: jurisdictional error
- It
was common ground that, since the decision of the Court of Appeal in Chase
Oyster Bar v Hamo Industries [2010] NSWCA 190, the determinations of
adjudicators made under the Act are amenable to judicial review for
jurisdictional error. Thereafter, the
parties parted company, in particular as
to what constitutes jurisdictional error, and whether the error of law alleged
in this case
was jurisdictional.
- In
Kirk v Industrial Relations Commission of New South Wales (2010) 239 CLR
531, the majority of the High Court (French CJ, Gummow, Hayne, Crennan, Kiefel
and Bell JJ) identified three categories of jurisdictional
error at [72]. Their
Honours did so by reference to the earlier decision of the High Court in
Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163 at 177 - 178. The three
categories of error identified by the majority in Kirk were:
(1) the mistaken denial or assertion of jurisdiction, or (in a
case where jurisdiction does exist), misapprehension or disregard of
the nature
of or limits on functions and powers;
(2) entertaining a matter or
making a decision of a kind that lies, wholly or partly, outside the limits on
functions and powers,
as identified from the relevant statutory context; and
(3) proceeding in the absence of a jurisdictional fact; disregarding
something that the relevant statute requires to be considered
as a condition of
jurisdiction, or considering something required to be ignored; and
misconstruction of the statute leading to misconception
of functions. (As to
this last example, the court had said in Craig at 178 that "the line
between jurisdictional error and mere error in the exercise of jurisdiction may
be particularly difficult to
discern".)
- In
Kirk at [73], the majority emphasised "that the reasoning in Craig
... is not to be seen as providing a rigid taxonomy of jurisdictional
error". Nor should it be taken, their Honours said, "as marking
the boundaries
of the relevant field".
- Thus,
in Chase at [33], Spigelman CJ stated that "[t]here is no single test or
theory or logical process by which the distinction between jurisdictional
and
non-jurisdictional error can be determined".
- The
concept of jurisdiction is simple to define. As Gleeson CJ and McHugh J said in
Abebe v The Commonwealth of Australia [1999] HCA 14; (1999) 197 CLR 510 at [24],
"[j]urisdiction is the authority to decide". Alternatively, as Spigelman CJ
pointed out in Chase at [36], the question to be decided in any given
case (involving determinations of adjudicators) "is whether the adjudicator had
jurisdiction
to determine an "application" which had been made without
compliance with" the suggested jurisdictional limitation.
- In
Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR
355, the majority (McHugh, Gummow, Kirby and Hayne JJ) said at [93]:
...a better test for determining the issue of validity is to ask whether it
was a purpose of the legislation that an Act done in breach
of the provision
should be invalid. ... In determining the question of purpose, regard must be
had to "the language of the relevant
provision and the scope and object of the
whole statute".
- The
internal quotation came from the decision of the Court of Appeal of this State
in Tasker v Fullwood [1978] 1 NSWLR 20 at 24.
- In
Chase , Spigelman CJ identified, at [40] to [52], three matters to be
looked at in considering whether a statutory requirement was jurisdictional.
Those matters were:
(1) the language of the statute; his Honour
said that substantial, and often but not always determinative, weight should be
given
to language in mandatory form (at [40]);
(2) the structure of the
legislative scheme (at [42]); and
(3) the adverse effects of finding that a
statutory requirement is jurisdictional (at [52]).
- It
may be noted that in Chase , the language of the statutory requirement
under consideration - s 17(2)(a) of the Act - read within the statutory scheme
as a whole, was of determinative importance. See Spigelman CJ at [31] to [53],
and
my reasons at [207] to [237]; Basten JA agreed with the approach taken by
Spigelman CJ and me (see at [96]).
Section 9
- Section
9 of the Act reads as follows:
9 Amount of progress payment
The amount of a progress payment to which a person is entitled in respect of
a construction contract is to be:
(a) the amount calculated in accordance with the terms of the contract, or
(b) if the contract makes no express provision with respect to the matter,
the amount calculated on the basis of the value of construction
work carried out
or undertaken to be carried out by the person (or of related goods and services
supplied or undertaken to be supplied
by the person) under the contract.
The parties' submissions
- Mr
F C Corsaro of Senior Counsel, who appeared with Mr I G B Roberts of Counsel for
Bergemann, submitted that the starting point was
to be found in the decision of
the majority in Craig at 176 to 180. Mr Corsaro referred, in particular,
to what the court said at 179:
At least in the absence of a contrary intent in the statute or other
instrument which established it, an administrative tribunal lacks
authority
either to authoritatively determine questions of law or to make an order or
decision otherwise than in accordance with
the law.
...
If ... an administrative tribunal falls into an error of law which causes it
to identify a wrong issue, to ask itself a wrong question,
to ignore relevant
material, to rely on irrelevant material or, at least in some circumstances, to
make an erroneous finding or to
reach a mistaken conclusion, and the tribunal's
exercise or purported exercise of power is thereby affected, it exceeds its
authority
or powers. Such an error of law is jurisdictional error which will
invalidate any order or decision of the Tribunal which reflects
it.
- Mr
Corsaro submitted, that the language of s 9(a) of the Act was clear, and
mandatory. The entitlement "is to be... the amount calculated in accordance with
the terms of the contract".
- Mr
Corsaro accepted that not all errors of law were jurisdictional, and thus that
if an adjudicator made an error of law in deciding
a matter that he or she had
been given jurisdiction to decide, the error would not of itself be
jurisdictional error. However, he
submitted, the statutory requirement under
consideration was jurisdictional, simply because it defined, in mandatory terms,
the extent
of a claimant's entitlement to a progress payment.
- Mr
M G Rudge of Senior Counsel, who appeared with Mr F P Hicks of Counsel for
Varley, submitted that any error in the adjudicator's
construction and
application of the relevant provisions of the subcontract was an error within
jurisdiction, because the very task
given to an adjudicator was to determine the
amount of a progress payment to which the claimant was entitled: that is to say,
to
determine the amount of the contractual entitlement. He relied on what I had
said in Musico v Davenport [2003] NSWSC 977 at [47] (where I quoted from
Lord Reid in Anisminic Ltd v Foreign Compensation Commission [1968] UKHL 6; [1969] 2 AC
147, 171) and following, including in particular at [52]:
I therefore conclude that, where the determination of a dispute submitted to
an adjudicator under the Act requires the adjudicator
to consider issues of law,
the adjudicator will not fall into jurisdictional error simply because he or she
makes an error of law
in the consideration and determination of those issues. It
would be otherwise, as the High Court pointed out in Craig (echoing, I
think, what Lord Reid said in Anisminic) , if the error of law causes the
adjudicator to make one or other (or more) of the jurisdictional errors that the
court identified:
in such a case, relief would lie, subject to any relevant
discretionary considerations .
- In
the case of s 9(a), Mr Rudge submitted, the decision of Palmer J in Multiplex
Constructions Pty Ltd v Luikens [2003] NSWSC 1140 showed, at [58], that one
of the functions that the adjudicator had to perform was to decide what were the
relevant or applicable
contractual terms and how they operated in the particular
circumstances. It followed, his Honour said, that the adjudicator should
be
taken to have authority to decide the particular question, for the purposes of
making a determination.
Decision
- I
shall start where Mr Corsaro started, with the observations of the High Court in
Craig at 179. The only matter that adjudicators decide "authoritatively"
is the amount of the progress payment to which a claimant is entitled.
That is
the function entrusted to adjudicators by the Act. In the course of making that
determination, adjudicators may have to consider
(and in many cases will
consider) the proper construction of the contractual provisions governing
entitlement. Where they do so,
they must reach a conclusion as to the meaning
and operation of the relevant provisions. But their determinations do not
provide
any authoritative decision on that point.
- The
parties are bound to accept (subject, of course, to the power of this court to
review) the determination by an adjudicator of
the three matters specified in s
22(1) of the Act: the amount of the progress payment, the date on which it is
payable and the rate of interest on it. They are not bound
to accept any step in
the reasoning of the adjudicator leading to that determination. On the contrary,
as s 32 of the Act makes clear, nothing in Part 3 (which is the Part dealing
with the procedure for recovering progress payments) affects any right that a
party to a construction
contract may have under it or in respect of anything
done or omitted to be done under it (see subs (1)). Nor does anything done under
or for the purposes of Part 3 affect any civil proceedings arising under a
construction contract (see subs (2); the exception in subs (3) can be put to one
side).
- Thus,
whilst I accept the general proposition that, in the absence of clear contrary
intention, administrative tribunals lack authority
to determine authoritatively
questions of law, I do not see that principle as having any particular relevance
in the present case.
(I put to one side the question that I discussed,
relatively briefly, in Musico at [51] as to the limit of the analogy
between an adjudicator appointed under the Act and administrative tribunal
established under
an Act of Parliament.)
- Likewise,
the proposition that administrative tribunals have no authority to make orders
or decisions otherwise than in accordance
with the law may be accepted, at the
level of generality. But, as I said at Musico at [52], it is necessary to
look at the precise nature of the issues that are given to (in this case)
adjudicators for consideration
and determination.
- I
concluded in Musico at [54] that relief would not lie for
non-jurisdictional error of law. I reached that conclusion because I came to the
view that the
legislative scheme was inconsistent with the availability of that
ground of review. That aspect of my reasons was approved by the
Court of Appeal
in Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 at [51] (Hodgson JA,
with whom Mason P and Giles JA agreed). What his Honour said on this point is
not affected by the decision of the Court
of Appeal in Chase .
- I
turn to the language of 9(a). It may be accepted that the language is peremptory
("is to be"). But it does not follow that it must
be treated as "mandatory". As
Spigelman CJ said in Chase at [39], the use of words such as "mandatory"
is no more than a convenient way of expressing a conclusion resulting from a
process
of construction applying all the relevant principles of statutory
interpretation. Thus, to say that the language is "mandatory" does
not answer
the question; rather, it is the answer reached if the process of construction of
the statute so dictates.
- Section
9(a) defines what it is that an adjudicator is to determine: the amount of a
progress payment to which the claimant entitled (s 22(2)(a) of the Act). It
states, in a summary way, the very question that is central to the adjudicator's
exercise of his or her functions.
In this respect, it stands in marked contrast
to the basic and essential statutory conditions of validity identified by
Hodgson JA
in Brodyn at [53], which now may be accepted as jurisdictional
requirements (see Basten JA in Coordinated Construction Co Pty Ltd v J M
Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63 NSWLR 385 at [71]). Section 9(a) stands
in equally marked contrast to s 17(2)(a) of the Act, identified as
jurisdictional in Chase. The jurisdictional requirements so far
identified are, for the most part, anterior to the process of adjudication. The
only one that
is not is the determination of the application in accordance with
s 22(1) (calling up ss 19(2) and 21(5)) and the provision of a determination in
writing.
- In
Chase at [43], Spigelman CJ differentiated elements occurring "at the
application stage of the decision-making process" from "matters which
can arise
during the course of the decision-making process itself". His Honour referred to
a distinction between "a fact to be adjudicated
upon in the course of enquiry
and "an essential preliminary to the decision-making process". In this context,
"preliminary" means
not so much chronologically as legally antecedent to the
decision making process, as his Honour pointed out at [44]. The matters
to which
s 9(a) directs attention are central to the decision-making process, and arise
for consideration, if at all, only during that process.
- For
the reasons that I gave in Musico at [47] and following (which I will not
repeat, because they are summarised at [52] set out at [33] above), I remain of
opinion that,
where matters are entrusted to adjudicators for decision, a
decision involving error of law is not, for that reason alone, a decision
beyond
jurisdiction. Any other conclusion would be, as I said and as Hodgson JA agreed
in Brodyn , inconsistent with the statutory scheme. In this context, I
note that in Chase at [55], Spigelman CJ observed that "the purpose of
the legislative scheme [of the Act] is best served by restricting the scope of
intervention by the courts".
- In
determining the amount of a progress payment, adjudicators are required to
consider, among other things, the provisions of the
construction contract under
which the claimed entitlement arises (s 22(2)(b)). Presumably, they are required
to do so so that they can work out "the amount calculated in accordance with the
terms of" that contract.
In other words, their task requires them to identify
the contractual provisions that are relevant to quantification of the amount
of
a progress payment, to decide (where there is a contest) the proper construction
of those provisions and to apply them to the
facts of the particular dispute. As
Palmer J said in Multiplex at [58]:
...If determination of a disputed progress claim depends upon resolution of a
question as to what are the relevant terms of a contract,
it must necessarily be
implicit in the jurisdiction conferred on the adjudicator by the Act that he or
she have jurisdiction to decide
that question.
- I
agree with his Honour. I should note that Mr Corsaro submitted that his Honour's
reasoning was incorrect, and should not be followed.
I do not accept that
submission. There are indications in at least three subsequent decisions of the
Court of Appeal that support
the view of s 9(a) that Palmer J expressed.
- In
Transgrid v Siemens Ltd [2004] NSWCA 395; (2004) 61 NSWLR 521, Hodgson JA (with whom Mason
P and Giles JA agreed) looked, although briefly and by the way, at s 9(a) at
[35]. His Honour said that an entitlement "calculated in accordance with the
terms of the contract" was the value of the work
less deductions, not the amount
certified.
- Hodgson
JA returned to this topic, again by the way, in John Holland Pty Ltd v Roads
and Traffic Authority of New South Wales (2007) 23 BCLR 205 at [38]. His
Honour, speaking with the concurrence of Beazley JA, said that:
... "calculated in accordance with the terms of the contract" meant
calculated on the criteria established by the contract, and did
not mean reached
according to mechanisms provided by the contract...
- In
the same case, Basten JA spoke at [77] of s 8 of the Act as giving the right to
a progress payment, and of s 9 as proving the method of its calculation.
- The
question arose more recently in the Court of Appeal, in Plaza West Pty Ltd v
Simon's Earthworks (NSW) Pty Ltd [2008] NSWCA 279. Hodgson JA, who agreed
with Allsop P but offered some additional reasons, referred at [53] to
Transgrid and John Holland , saying that he adhered to the views
there expressed. His Honour explained those views as follows, at [54]:
This means that contractors are not deprived of entitlement to payment under
the Act because a condition precedent, such as the obtaining
of a
superintendent's certificate, has not been satisfied; and it means equally that
contractors are not ipso facto entitled to payment because of the
operation of a deeming provision such as cl 37(2) of the contract in this case.
- Allsop
P (with whom Giles JA agreed) also dealt with s 9. In that case cl 37(2) of the
contract provided that if the superintendent did not issue a progress
certificate within 14 days of
receiving a progress claim, the progress claim was
deemed to be the relevant progress certificate. In those circumstances, the
adjudicator
came to the view that, because there was a deemed progress
certificate, he was not required to consider in detail the answers raised
by the
respondent in its payment schedule (as would have been required by s 9(b) of the
Act in the particular circumstances of the case). Allsop P said at [32] that if
the adjudicator thereby erred in law, "that
did not mean that the adjudicator
did not fulfil his statutory task in s 22". His Honour said at [34] that the
adjudicator had not ignored the appellant's submissions, but had dealt with them
"appropriately
on the hypothesis that he worked upon."
- The
significance of his Honour's observations lies in the fact that the peremptory,
or what Mr Corsaro submitted was the mandatory,
language of s 9 (the use of the
words "is to be") governs both para (a) and para (b). If Mr Corsaro's submission
is to be accepted, a failure to
comply with s 9(b) (in a case where it applied,
because para (a) did not) would, equally, amount to jurisdictional error. It is
clear from what Allsop
P said in Plaza West that his Honour did not
regard the adjudicator's failure, in that case, to attend to the requirements of
s 9(b) as vitiating his determination.
- The
reasoning of Hodgson JA in the three cases to which I have referred, of Basten
JA in the second, and of Allsop P in the third,
is in my view consistent with
the approach that Palmer J took to s 9(a) in Multiplex , and supports my
view that s 9(a) is not a condition of jurisdiction but, rather, a description
of the mechanical aspects of the essential task to be performed in
the exercise
of the jurisdiction that is conferred. In my view, it would be most unusual for
a mechanical provision such as s 9 to be characterised as jurisdictional.
- Accordingly,
I conclude that even if the adjudicator did misconstrue or misapply the relevant
contractual provisions, and as a result
did not calculate the amount of the
progress payment to which Varley was entitled in accordance with the terms of
the subcontract,
he did not thereby exceed, or fail to exercise, the
jurisdiction entrusted to him by the Act.
- Having
reached that conclusion, it is not necessary to consider either the contractual
provisions in question, their proper construction,
or whether the adjudicator
misconstrued or misapplied them.
Conclusion on first issue
- The
adjudicator did not fall into jurisdictional error if and to the extent that he
misconstrued or misapplied the relevant provisions
of the subcontract.
Natural justice and good faith: the applicable principles
- In
Brodyn , Hodgson JA at [53] identified five "basic and essential
requirements" for the existence of a (valid) determination. His Honour then
said, at [55], that what the legislature intended to be essential to the
existence of a valid determination:
... was compliance with the basic requirements..., a bona fide attempt by the
adjudicator to exercise the relevant power relating
to the subject matter of the
legislation and reasonably capable of reference to this power... and no
substantial denial of the measure
of natural justice that the Act requires to be
given.
- His
Honour emphasised, at [57], that "natural justice is to be afforded to the
extent contemplated by" the relevant provisions of
the Act. Thus, his Honour
said:
... there is a disclosed legislative intention to make a particular measure
of natural justice a pre-condition of validity, [so that]
failure to afford that
measure of natural justice does make the determination void.
- In
Watpac Constructions v Austin Corp [2010] NSWSC 168, I said at [142] and
[146] that:
(1) consideration of the extent of natural justice
required to be given must take into account the scheme of the Act, and other
matters;
(2) the concern of the law was to avoid practical injustice;
and
(3) it was inappropriate that the court should sift finely through
the reasons of the decision maker in an attempt to find slips warranting
the
court's intervention.
- I
set out those paragraphs:
142 Any entitlement to natural justice must accommodate the scheme of the
Act, including the extremely compressed timetable provided
for the submission of
payment schedules, adjudication applications, and adjudication responses; and
the limited time (subject to
the consent of the parties, which they may give or
withhold at their will) for an adjudicator to determine an application. It must
also accommodate the fact that, in many cases, claimants and respondents will
prepare their documents themselves, and will not avail
themselves of legal
advice in doing so.
...
146 In this context, Gleeson CJ said in Re Minister for Immigration and
Multicultural Affairs ; ex parte Lam [2003] HCA 6; (2003) 214 CLR 1 at 13 - 14 [37]
that fairness is not abstract but practical. His Honour said that "[w]hether one
talks in terms of procedural fairness
or natural justice, the concern of the law
is to avoid practical injustice". To like effect, Kirby J said in Minister
for Immigration and Ethnic Affairs v Wu Shan Liang [1996] HCA 6; (1996) 185 CLR 259 at 291
that the court should not undertake the task of "combing through the words of
the decision-maker with a fine appellate tooth-comb
[sic], against the prospect
that a verbal slip will be found warranting" the intervention of the court.
- I
dealt with the obligation of good faith in Timwin Construction v Facade
Innovations [2005] NSWSC 548 at [38] to [40]. In substance, I said, what was
required was that adjudicators should put their minds to the comprehension and
their wills
to the discharge of their duty (citing Lord Sumner in Roberts v
Hopwood [1925] AC 578 at 604). For convenience, I repeat what I said in
those paragraphs :
[38] There has not been any decision to my knowledge elaborating the
requirement of good faith to which Hodgson JA pointed in Brodyn .
Clearly, I think, his Honour was not referring to dishonesty or its opposite. I
think he was suggesting that, as is well understood
in the administrative law
context, there must be an effort to understand and deal with the issues in the
discharge of the statutory
function: see, for example, the speech of Lord Sumner
in Roberts v Hopwood [1925] AC 578, 603, where his Lordship said that a
requirement to act in good faith must mean that the board "are putting their
minds to the comprehension
and their wills to the discharge of their duty to the
public, whose money and locality which they administer."
[39] That construction of the requirement of good faith is supported by the
provisions of s 22(2), requiring an adjudicator to "consider" certain matters. A
requirement to consider, or take into consideration, is equivalent to
a
requirement to have regard to something: see Zhang v Canterbury City Council
[2001] NSWCA 167; (2001) 51 NSWLR 589 at 602 (Spigelman CJ, with whom Meagher and Beazley JJA
agreed).
[40] As his Honour emphasised, the requirement to "have regard to" something
requires the giving of weight to the specified considerations
as a fundamental
element in the determination, or to take them into account as the focal points
by reference to which the relevant
decision is to be made. His Honour relied on
the tests expounded in R v Hunt; ex parte Sean Investments Pty Ltd [1979] HCA 32; (1979)
180 CLR 322 (Mason J) and in Evans v Marmont [1997] NSWSC 331; (1997) 42 NSWLR 70, 79-80
(Gleeson CJ and McLelland CJ in Eq).
- I
looked at the question of good faith more recently in Laing O'Rourke
Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd
[2010] NSWSC 818 at [30] to [35]. At [30], I repeated the paragraphs from
Timwin that I have just set out. I continued:
[31] Shortly after I decided Timwin , Brereton J considered the
obligation of good faith in Holmwood Holdings Pty Ltd v Halkat Electrical
Contractors Pty Ltd [2005] NSWSC 1129. In a detailed review of the
authorities from [66] to [109], his Honour identified what he described as a
narrow view and a broader
view of good faith. His Honour explained the narrow
view at [80] as "focussing on whether objectively the exercise of power could
be
regarded as honestly referrable to the purpose for which the power was
conferred, and excluding from its ambit the reasoning process
leading to the
decision". His Honour identified the broader view, at [87] and other paragraphs,
as including recklessness or caprice
in the exercise of the power, although
falling short of a wilful and deliberate failure to exercise, or to attempt to
exercise, the
power. For the reasons given at [111] to [116], his Honour
concluded at [110] and [117], that the requirement of good faith required
more
than honesty. In particular, it required faithfulness to the obligation and a
conscientious attempt to perform it (at [117]),
and absence of recklessness or
caprice [at 110], [117]).
[32] The defendant appealed. The appeal was dismissed ( Halkat Electrical
Contractors Pty Ltd v Holwood Holdings Pty Ltd [2007] NSWCA 32).
Nonetheless, Giles JA (with whom Santow and Tobias JJA agreed) referred at [26]
to what Brereton J had said. His Honour did not think
that it was necessary to
embark on "an exegesis of the reference in Brodyn ... to a bona fide
attempt to exercise the statutory power". That was because, as his Honour said
at [27], "the adjudicator simply
did not perform the task required by the Act",
and thus did not exercise his power in good faith.
[33] The Court of Appeal returned to the topic of good faith in Perform
(NSW) Pty Ltd v MEV-AUS Pty Ltd [2009] NSWCA 157. It appeared that the
appellant in that case had submitted that the Court of Appeal did not "fully
endorse" the broader approach to
good faith that Brereton J had identified in
Holmwood . At [114], Giles JA (with whom McColl and Young JJA agreed)
said that the Court "did not endorse it at all".
[34] I do not think that it is necessary to say more than that, in the words
of Lord Sumner in Roberts v Hopwood [1925] AC 578 at 604 (cited by me in
Timwin at [38]), for administrative bodies to act in good faith, they
must put "their minds to the comprehension and their wills to the discharge
of
their duty". As I said at [39] and [40], that view of the content of the
obligation of good faith was supported by the requirement
to "consider" various
matters set out in s 22(2) of the Act. It follows that the obligation of good
faith requires at least that adjudicators should turn their minds to, grapple
with and form a view on all matters that they are required to "consider".
[35] It may be easy to see why an exercise of power that could be
characterised as reckless or capricious is not undertaken in good
faith. But it
does not follow that, for there to be absence of good faith, it must be possible
to characterise what happened as having
been done recklessly or capriciously.
- I
remain of the view that I expressed in those cases as to the content of the
requirement that adjudicators exercise their statutory
function in good faith.
- Because
I saw some connection between the obligation of good faith and the statutory
requirement (s 22(2) of the Act) to "consider" various matters, I will set out
also what I said, as to the obligation to "consider" in Laing O'Rourke at
[36] to [39]:
[36] Section 22(2) of the Act requires adjudicators to "consider" certain
specified matters:
22 Adjudicator's determination
...
(2) In determining an adjudication application, the adjudicator is to
consider the following matters only:
(a) the provisions of this Act,
(b) the provisions of the construction contract from which the application
arose,
(c) the payment claim to which the application relates, together with all
submissions (including relevant documentation) that have
been duly made by the
claimant in support of the claim,
(d) the payment schedule (if any) to which the application relates, together
with all submissions (including relevant documentation)
that have been duly made
by the respondent in support of the schedule,
(e) the results of any inspection carried out by the adjudicator of any
matter to which the claim relates.
...
[37] I looked at the obligation to "consider" in Timwin , in the
paragraphs quoted at [30] above. It is, however, necessary to say a little more
about the content of that obligation in the
context of the Act.
[38] As a matter of plain English, the obligation to "consider" something
requires that it be given attention, or looked at on its
merits (see, for
example, the Australian Oxford Dictionary , Second Edition, 2004). Thus,
in Tickner v Chapman (1995) 57 FCR 451, Black CJ, speaking of a statutory
obligation on a minister of the Crown to consider representations made to him,
said at 464 that
"the consideration of a representation involves an active
intellectual process directed at that representation". In the same case,
Burchett J said at 476 that the obligation required "the Minister... to apply
his own mind to the issues raised by [the representations]",
which involved
obtaining "an understanding of the facts and circumstances set out in them, and
of the contentions they urged based
on those facts and circumstances". Kiefel J
said at 495 that the obligation "requires that the Minister have regard to what
is said
in the representations, to bring his mind to bear upon the facts stated
in them and the arguments or opinions put forward and to
appreciate who is
making them".
[39] In my view, the obligation to consider various matters imposed by s
22(2) of the Act should be read in the same way: namely, as requiring an active
process of intellectual engagement. It may be thought that
this imposes a
substantial burden on adjudicators. That may be so; but there are at least two
reasons why, even if that is correct,
it does not justify reading down the
statutory obligation to "consider". The first is that adjudicators are not
forced to accept
nomination. They may decline nomination; or they may accept
only on condition that they are given some longer period of time than
ten
working days to produce their determination. The second reason is that the
outcome of the adjudicator's consideration may have
very significant
consequences. In this case, the three delay claims total, in round figures, $7.5
million - a little under 75% of
the total of the payment claim. Having regard
both to the limited ability for adjudicators' determinations to be reviewed and
to
the nature of the estoppels that they create, the parties to an adjudication
are entitled to have the adjudicator's consideration,
in the sense that I have
explained, of the case that each of them brings.
- Combining
those two matters, it could be said that the obligation to act in good faith,
insofar as it requires adjudicators to turn
their minds to the statutory task
entrusted to them, requires that they engage intellectually with the disputes
that the parties
have framed, and deal with those disputes in a way that is
reasoned, and not perverse, arbitrary or capricious.
- Mr
Corsaro also brought up for consideration, in the context of good faith, the
obligation of adjudicators to give reasons (s 22 (3)(b) of the Act).
- As
s 22(3)(b) makes clear, the obligation to give reasons is, in substance, an
obligation to state the basis of the determination that the adjudicator
has
made: compare Housing Commission of NSW v Tatmar Pastoral Co Pty Ltd
(1983) 3 NSWLR 378 at 386 (Mahoney JA). The reasons should show that the
adjudicator has turned his or her mind to the dispute entrusted to his or her
determination, and has addressed the issues raised by the parties in support of
or opposition to the payment claim. There is no requirement
that they be
lengthy, elaborate or detailed. On the contrary, it may be thought, the scheme
of the Act tells strongly against any
such requirement: in particular, the
extremely compressed time (ten business days following acceptance of the
nomination, unless
the parties agree to extend time - see s 21(3)) and the
obvious statutory intent that valid payment claims should be paid as quickly as
possible. Indeed, s 21(3) recognises this, because it sets an outer time limit;
the primary obligation on adjudicators "is to determine an adjudication
application
as expeditiously as possible".
- To
put the matter compendiously, the reasons should be sufficient to show that the
adjudicator has engaged actively with the dispute
tendered for his or her
decision, and dealt with it in a way that is reasoned, and not perverse,
arbitrary or capricious.
Second issue: denial of natural justice; good faith
- Bergemann's
submissions attacked, on the grounds of denial of natural justice and want of
good faith, some 37 (or 50%) of the total
number of variations addressed by the
adjudicator. Those attacked ranged from the most substantial (VO-089, for an
amount in excess
of $660,000.00) to the more trivial (VO-201, for $812.00, and
VO-158, for $734.00).
- At
a level of some generality, Bergemann's submissions attacked many aspects of the
adjudicator's reasoning on the 37 variations in
question by alleging that he had
failed to deal with material in the 20 lever arch folders given to him that was
said to cast doubt
on some aspects of Varley's claims for the variations in
question. For example, in relation to VO-089, the adjudicator was criticised,
among other things, for failing to take into account an explanation for delay
given in the statutory declaration of an employee of
Bergemann.
- However,
and again at a level of generality, in many of the cases where such a complaint
is made, reference to the material that is
said to be inconsistent with the
claim or with the adjudicator's preference for Varley's approach shows that the
material is either
non-committal, or cast at a level of unhelpful generality, or
obtuse. Further, in some at least of those cases, it is clear that
the
adjudicator's attention was not specifically drawn to the material that was said
to be inconsistent with Varley's approach.
- In
other instances, the adjudicator is criticised for accepting, in his
quantification of some of Varley's claims, material that not
only was plainly
wrong (as indeed it was), but also was inconsistent with other material on which
he had relied for other claims
(as indeed he had). Again, in many of those
cases, Bergemann had not troubled to draw the adjudicator's attention to these
inconsistencies.
- I
was left with the very strong impression that, in respect of most of the 37
variations in question, Bergemann was seeking to reargue
the merits of the
individual decisions, under cover of nominal reliance on the principles of
natural justice and good faith.
- Mr
Corsaro focussed his attack on a somewhat more limited selection of the 37
variations, doing so, he said, by way of illustration
of problems that were
manifested in respect of other of the impugned decisions. As I indicated, during
the hearing, that I would
do, I propose to limit my consideration of this point
to the particular variations that were the subject of criticism.
VO-089
- Bergemann
makes a number of complaints. The first group of complaints concludes with the
proposition that the adjudicator "ignored
the submission and evidence that" a
certain document "was requested by" Bergemann.
- The
answer to this is simple. The adjudicator did not ignore those submissions. It
is clear from [110] to [120] of the determination
that he had considered
Bergemann's submissions. It is equally clear that he did not agree with them.
Thus, he rejected them. That
is a different matter. The process of reasoning
that underlies the rejection is set out in the determination. It appears to be
logical,
and not perverse, arbitrary or capricious.
- Bergemann
launched a separate attack on [126] of the determination, in which the
adjudicator dealt with the fact that it had taken
twenty weeks, rather than
three weeks as programmed, to fabricate, assemble and install the equipment that
was the subject of this
variation. It is clear that he regarded this factor as
supporting his conclusion. Bergemann submitted that he had failed to take
into
account the explanation for the delay given by its employee Mr Stevenson.
However, reference to the statutory declaration that
the referee is supposed to
have failed to take into account shows that it does not explain the length of
time taken for assembly
and fabrication. At most (or at face value) it says that
Varley proceeded slowly. It does not address the specific problem with which
the
adjudicator was dealing in [126]. It is a particular example of what I
described, at the level of generality, in [70] above.
- There
was evidence that did specifically address the three week / twenty week issue:
from Bergemann's employee or independent expert,
Mr Cook. The adjudicator
considered Mr Cook's views at [126]. He did not agree with them. But again, it
does not mean that he overlooked
them.
- In
addition, Bergemann makes two complaints (or further complaints) about the
adjudicator's assessment of the value of this variation.
It is not entirely
clear that some of the allegedly overlooked reasons to which Bergemann referred
were raised in its payment schedule.
But in any event, the adjudicator set out
the parties' competing positions, analysed them and expressed a preference for
Varley's
position as opposed to Bergemann's. It is clear that he turned his mind
to the dispute and sought to deal with it. His reasons for
doing so are
adequately explained.
- The
final complaint raised is as to the adjudicator's rejection of certain
submissions, based on s 20(2B) of the Act. As I have said above, that was a
matter within the adjudicator's province to decide. He did so.
VO-215
- Bergemann
contended that this claim involved duplication with other, identified,
variations. In its payment schedule, it had identified
one only of those
variations. In its adjudication response, it identified additional variations.
The adjudication said that, to the
extent that additional variations were
identified in the payment schedule, he would not take them into account, because
they were
barred by s 20(2B). Whether or not he was right in that is not a
matter on which I need comment. It is plain that he considered the submission;
he could
not have reached the conclusion that he did had he not done so.
- As
to the one instance of duplication that the adjudicator did think could be
considered, it is clear that he did consider it. The
adjudicator pointed out,
correctly, that the submissions did not assist him to determine the existence or
extent of any duplication.
The errors or inconsistencies in his reasoning that
are now asserted do not relate to any submission properly put to him in the
adjudication
process.
- In
this instance, as in many others (I shall not refer to them individually)
Bergemann's approach appears to be that although it did
not put detailed matters
before the adjudicator to demonstrate that the claim was wholly invalid or that
the amount claimed was excessive,
nonetheless, he should have fossicked through
the 20 volumes of material given to him and found the inconsistencies or
inadequacies
for himself.
- The
extent of compliance with the good faith obligation is not to be assessed in a
vacuum (and nor is the extent of compliance with
the requirement to afford
natural justice, subject to the scheme of the Act). Particularly where the
disputes are substantial and
complex, and where there are thousands of pages of
material put before an adjudicator, it is in my view incumbent on the parties
to
identify with precision all reasons that are open to them (based on the payment
claim and payment schedule) in support of or opposition
to each element of the
claim, and to direct the adjudicator's attention to the relevant parts of the
material given to him or her.
It is not sufficient to put that material before
the adjudicator, accompanied by lengthy but diffuse submissions, and to leave it
to him or her to come to the right result for the right reasons based on every
detail that may be gleaned from whatever is the relevant
material.
- On
the contrary, in my view, both the requirement to consider in good faith and the
requirement to afford natural justice must take
into account the magnitude of
the task and the way that the parties have put the task before the adjudicator.
In particular, it is
inappropriate for a party, who has not done what it can to
clarify the dispute and guide the adjudicator to the relevant material,
to
complain, nonetheless, that there was material, that might have borne on the
adjudicator's conclusions, that could have led to
a different result.
- Thus,
in this and many cases, the complaint now made by Bergemann is that the
adjudicator denied it natural justice, and did not exercise
his functions in
good faith, because he did not pick up a problem that Bergemann had not
identified in its payment schedule, or had
not otherwise drawn clearly to his
attention. That is not, in my view, an appropriate basis for a challenge to an
adjudicator's determination.
VO-225a
- The
adjudicator said at [188] that he had reviewed Varley's assessment of costs and
was "satisfied that the costs indicated are reasonable
in the circumstances". He
acknowledged at [189] that there were no plant and equipment invoices in
support. Nonetheless, he said,
having regard to what was said in the detailed
submissions, the claims for plant and equipment seemed to be reasonable.
- This
was a case where there was a mistake in the transposition of costs from primary
documents to the summary lodged by Varley. What
had been stated as a daily rate
for the hire of certain equipment in the primary material was taken as an hourly
rate in the summary,
with the obvious consequence of inflating greatly the
amount of the claim. The adjudicator did not pick this up. Bergemann criticised
him for this, saying that he had failed to consider the relevant material in
good faith, and that his statement at [188] (to the
effect that he had
considered the relevant material) was evidence of this.
- The
short answer to this complaint is that Bergemann did not raise the issue in its
payment schedule. Apparently, Bergemann - a party
to the subcontract in
question, no doubt having intimate familiarity with all the details of the works
- had not picked up the mistake.
Yet, not having done so (and thus not having
pointed it out to the adjudicator), it criticises the adjudicator for not having
done
so. That criticism must be rejected.
VO-222
- This
variation related to work carried out on four severable portions of the project.
The claim included a claim for a specified number
of hours of work at the
contractually agreed rate of $70.00 per hour. However, primary documents showed
that the claim had been prepared
initially on the basis of a lesser number of
hours at a higher rate, leading to substantially the same dollar result.
- Bergemann
criticised the honesty of this reworking of the claim, suggesting that it was in
some way underhand. However, although the
problem was manifest on the basis of
the documents to which Bergemann referred, Bergemann had not picked it up and
referred to it
in its payment schedule. Two things followed from this. The first
is that, not having drawn the matter to the attention of the adjudicator,
it is
not open to Bergemann to criticise him for having failed to deal with it.
(Indeed, given that it was not raised in the payment
schedule, he should not
have dealt with it even if it had been drawn to his attention.) The second
matter is that, because there
was no point taken in the payment schedule, Varley
was deprived of the opportunity to explain the problem. Mr Rudge submitted that
it could be explained. I said that I did not want to know what the explanation
was; the point is that there was no opportunity to
offer it because the point
was not taken when it should have been taken.
VO-223a
- Bergemann's
complaint was that the adjudicator had decided this variation in favour of
Varley, but that he had decided other variations,
which it submitted were
relevantly indistinguishable, in favour of Bergemann. Thus, it submitted, there
was an unexplained failure
to deal with like variations in the like way.
- The
answer to this complaint is, as Varley submits, that the allegedly similar but
rejected variations were rejected because the adjudicator
concluded that Varley
had not put sufficient material before him to support them. On the contrary, in
respect of this variation,
the adjudicator, having concluded that Varley had
adequately supported the claim, considered that Bergemann's submissions were not
an adequate answer.
- Two
things flow from this. The first is that the complaint goes nowhere, in terms of
demonstrating reviewable error. The second, and
perhaps more important, matter
is that it shows that, contrary to the thrust of Bergemann's complaints, the
adjudicator did grapple
intellectually and rationally with the individual
variations.
- Bergemann
also challenged the adjudicator's reasoning on quantum. However, two points can
be made. The first is that some of the issues
that Bergemann now relies on were
not raised before the adjudicator. The second, and conclusive, matter is that
the adjudicator expressly
referred (at [233]) to the detail of this aspect of
Varley's submissions, and concluded that he was satisfied, on that material,
as
to the amount claimed. Whether he was right or wrong is irrelevant. He carried
out, in a rational way and with sufficient explanation,
the task that was
entrusted to him in relation to this variation.
VO-198
- Bergemann's
challenge is that the adjudicator gave insufficient reasons for his conclusion
as to quantum. However, as the determination
shows (at [300] to [308], there was
material before the adjudicator (including, contrary to Bergemann's submission,
a detailed break-up
of the claim), to which the adjudicator referred, which he
analysed and on which he relied.
- Again,
it matters not whether he was right or wrong. He carried out the task entrusted
to him, and gave logical reasons for his conclusion.
VO-150
- Bergemann's
complaint is that the adjudicator ignored some of its submissions, and gave
insufficient reasons for his conclusion.
- Those
submissions were of the most general kind. The adjudicator referred to them. In
the absence of any meaningful challenge, he
was entitled to conclude, on his
review of the material, that the claim was justified. Again, he addressed the
dispute that was put
before him and dealt with it in an apparently rational way.
The attack on [102] to [104] of the determination
- I
set out the relevant paragraphs of the determination, together with the heading
that preceded them, at [11] above, and noted at
[12] above Mr Corsaro's
criticisms of those paragraphs.
- If
the adjudicator's reliance on s 20(2B) of the Act had been material to his
rejection (or non-consideration) of Bergemann's submissions on variations other
than those where
he expressly made reference to the subsection, there might be
some point to this criticism. At least as a matter of principle, it
would be
undesirable for an adjudicator not to consider a submission, because he or she
regarded it as "out of bounds" by operation
of s 20(2B), without indicating
this.
- However,
Mr Corsaro did not identify, in respect of any variation claim that the
adjudicator had accepted, an undisclosed failure
(presumably based on s 20(2B))
to consider submissions. More pertinently, since any reliance by the adjudicator
on s 20(2B) is immune from review, an undisclosed reliance is no more than a
deficiency in disclosure of reasons. If s 20(2B) were material to the decision
on any matter, that should have been stated. But a hypothetical failure to state
it, in the context
of a massive amount of material, a large number of claims and
a very detailed statement of reasons, is not something that, of itself,
would
invite, let alone require, review in this court.
Conclusion and orders
- Bergemann's
challenges to the determination fail. It follows that the proceedings should be
dismissed with costs (as between Bergemann
and Varley). The adjudicator
submitted save as to costs, and hence there should be no other order as to
costs. Since Varley has succeeded,
it should be released from the undertaking
(not to enforce the determination) given by it to the court on 14 July 2011. It
should
have access to the bank guarantee provided by Bergemann as the price of
obtaining that interlocutory undertaking.
- I
make the following orders:
(1) release the first defendant from
its undertaking given to the court on 14 July 2011.
(2) Order that the
bank guarantee provided by the plaintiff to the court in the amount of
$2,616,530.73 be released to the first defendant.
(3) Direct that the
first defendant be at liberty to call on the said guarantee in accordance with
its terms.
(4) Order that the summons be dismissed.
(5) Order
the plaintiff to pay the first defendant's costs; otherwise no order as to
costs.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2011/1039.html