|
Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of New South Wales |
Last Updated: 3 March 2009
NEW SOUTH WALES SUPREME COURT
CITATION:
The Craftsmen Restoration
& Renovations v Thomas Boland; Thomas Boland v The Craftsmen Restoration
& Renovations [2009] NSWSC 82
JURISDICTION:
FILE
NUMBER(S):
030128/06
030130/06
HEARING DATE(S):
10/07/2008
JUDGMENT DATE:
2 March 2009
PARTIES:
The
Craftsmen Restoration & Renovations Pty Ltd v Thomas Boland &
Ors
Thomas Boland & Anor v The Craftsmen Restoration & Renovations
Pty Ltd & Anor
JUDGMENT OF:
Howie J
LOWER COURT
JURISDICTION:
Consumer Trader and Tenancy Tribunal of NSW
LOWER COURT
FILE NUMBER(S):
HB 03/32695; HB 03/41455
LOWER COURT JUDICIAL
OFFICER:
Senior Member C. Paull
LOWER COURT DATE OF DECISION:
28/08/2006
COUNSEL:
E Olsson SC -
Plaintiff/Defendant
K Kelly - Defendant/Plaintiff
SOLICITORS:
Massey Bailey, Solicitors and consultants - Plaintiff/Defendant
G
Aronstan, Solicitor and Attorney - Defendant/Plaintiff
CATCHWORDS:
Contracts - breach results in payment of damages - interest recoverable
under common law - calculation of interest - Costs - "calderbank
offer" -
whether rejection before hearing unreasonable - appeal but no further offer of
compromise
LEGISLATION CITED:
CATEGORY:
Consequential
orders
CASES CITED:
Jones v Bradley (No. 2) [2003] NSWCA 258
SMEC
Testing Services Pty Ltd v Campbelltown City Council [200] NSWCA 323
Evans
Shire Council v Richardson [2006] NSWCA 61
Road and Traffic Authority of NSW
v Turner (No 2) [2008] NSWCA 241
TEXTS CITED:
DECISION:
Please refer to paragraph 33.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COMMON LAW DIVISION
ADMINISTRATIVE LAW LIST
JUSTICE HOWIE
MONDAY 2 MARCH 2009
030128/06 THE CRAFTSMEN RESTORATION &
RENOVATIONS v THOMAS BOLAND & ORS
030130/06 THOMAS BOLAND & ANOR v THE CRAFTSMEN
RESTORATION & RENOVATIONS & ANOR
JUDGMENT
1 HIS HONOUR: In this matter the principal judgment was delivered
on 1 July 2008; see [2008] NSWSC 630. The proceedings were appeals arising from
a building dispute before the Consumer, Trader and Tenancy Tribunal. The parties
were
referred to in the substantive judgment as “the owners”,
“the builder” and “the Tribunal”. I
shall continue to
refer to them in that way as it should be obvious, even without reference to the
earlier judgment, to whom reference
is being made. Proceeding 30128 of 2006 was
an appeal by the builder and proceeding 30130 of 2006 an appeal by the owners.
The nature
of the proceedings in this Court is fully considered in the principal
judgment. The resolution of the appeals resulted in determinations
not
substantially different from that made by the Tribunal even though some of the
reasons and the facts found differed from those
of the Tribunal.
2 In brief, the determinations made on the hearing of the appeal were
largely in favour of the owners. This was notwithstanding that
they were in
breach of the building contract by purporting to terminate the contract when
they themselves had failed to meet one
of its terms as to progress payments.
However, because of poor workmanship by the builders, the owners were required
to carry out
substantial rectification work for which they were entitled to
damages by way of compensation. The owners were also entitled to interest
on the
amount paid for that work. On the other hand the builder was entitled to
progress payment no. 8 that the owners had refused
to pay and monies retained by
the owners under the contract with interest on both those sums.
3 The parties were requested to settle orders in accordance with the
findings set out in the principal judgment. However, they were
unable to agree
on what those orders should be. It should be noted that there were obvious
errors in the proposed orders submitted
to the Court by both parties. There was
a short hearing on 10 July 2008 when the matter was discussed and leave was
granted to the
parties to file submissions on outstanding matters including the
question of costs and the calculation of interest.
4 An outstanding issue arising after the principal judgment was delivered
was the date upon which interest on the damages was to be
calculated. There was
also a dispute as to the amount of interest due in respect of a retention sum of
$11,705.90 to be paid to the
builder in accordance with the contract. A further
issue arising after the matter was reserved was the issue of set off. The
question
on costs related to whether the builders should be entitled to costs on
an indemnity basis in light of offers of compromise made
pending the hearing of
the dispute before the Tribunal. None of these matters were addressed during the
hearing of the appeals.
5 Submissions were filed from both sides and as late as 28 November 2008
final submissions were received from the owners. Even at
this stage, as was the
case throughout the course of the litigation, virtually every point was
contested both as to the applicable
principles and the findings that should be
made by the Court.
6 I have been informed that the builder has appealed from the principal
judgment but I am requested nevertheless to make final orders.
Interest
A. Damages
7 In effect the owners submit that the date for the
calculation of interest should be the commencement of the proceedings being 6
August 2003, the date of the filing of a statement of claim in the District
Court. The builder initially submitted that the Court
should choose 15 January
2004 as an approximation of the date when the owners paid money to have the work
rectified.
8 I expressed the view at the hearing in July that the interest for
rectification work should be paid from the date the money for
that work was
expended but that I had little or no evidence about that matter and neither of
the parties had addressed that issue
in the submissions made following the
delivery of the principal judgment. I expressed the opinion that the amount of
damages to be
paid to the owners by the builder should be $113,947.25 and there
was no apparent opposition to that figure.
9 In light of what occurred on 10 July, the solicitor for the builder
filed an affidavit dated 1 October 2008 to address matters that
had been raised
as to the calculation of interest. Annexed to that affidavit was a schedule
drawn from the evidence as to the date
of particular payments made by the owners
and calculating interest on those payments. Where that date was unknown, a
“median
date” of 30 September 2002 was chosen.
10 However, in answer to that affidavit submissions were filed on behalf
of the owners contesting that this was an appropriate means
of determining the
date for the calculation of interest and noted that some of the work occurred
before the proceedings commenced,
and as early as 2001.
11 In light of the continuing dispute between the parties as to what is
the evidence as to payments and the proper basis for determining
interest, and
having regard to the submissions originally made in the proposed orders before
the hearing of 10 July, I intend to
untie the Gordian Knot in much the way that
Theseus did by taking the bold course of slicing through the competing
submissions and
picking a date of 30 October 2003 (mid-way between 6 August 2003
and 15 January 2004). That seems to me to be an appropriate measure
of justice
between the parties, particularly having regard to the initial submissions made
by both.
B. Retention sum
12 The retention sum is governed by the terms of the contract. However, because of the way the matter proceeded, the builder having suspended works and the owners later purporting to terminate the contract, practical completion never occurred and a Final Certificate was never issued so that the preconditions for release of the money in accordance with cl 10.15.1 of the contract were never met.
13 The issue here is what interest rate applies to the retention sum
under the contract. The builder claims that the contract was
never completed
because of the breach by the owners in refusing to pay progress payment 8. So,
the builder argues, it is entitled
to interest on the retention sum in
accordance with the penalty provisions of the contract and item L of the
appendix to the contract:
see cl 10.5 of the contract. The owners claim that
these provisions do not apply to the retention sum and that interest is due only
in accordance with the interest earned on the joint account in which the
retention money was held.
14 It was made clear at the hearing of 10 July that the Court intended to
make the same order as the Tribunal made in respect of the
retention sum, that
is interest from 26 June 2002 “pursuant to the contract”. However,
there is now a dispute as to what
that order would mean in terms of the interest
payment because the parties have different views about what interest the
contract
allows on that sum.
15 This is not really a matter that comes within the terms of the appeals
from the Tribunal but in order to try to bring some finality
to this litigation
I should indicate my view that the owners’ argument should apply and that
interest on the retention sum
should be payable in accordance with the interest
accrued on the sum in the joint account. I do not believe that cl 10.5 applies
because there is no date upon which the payment of the retention sum was or
should have been due. True it is that the pre-conditions
for the payment of the
retention sum never eventuated because of the breach of contract by the owners,
but there is no provision
of the contract dealing with that situation.
Costs
16 The issue on the question of costs is whether,
notwithstanding the success of the owners both before the Tribunal and on
appeal,
the builder should have the benefit of an order for costs on an
indemnity basis having regard to the principles that have arisen
in respect of,
what are referred to as, Calderbank offers. It is accepted that the
Court’s adjudication is less favourable to the owners in the final result
than an offer made
by the builder during the proceedings before the Tribunal and
rejected by the owners.
17 There is little doubt about the jurisdiction of the court to grant the
order sought by the builder. It is a discretionary decision
and there is no
general principle that the rejection of the offer will entitle the offeree to
costs on an indemnity basis: Jones v Bradley (No 2) [2003] NSWCA 258 at
[8]. The test is whether the failure to accept the offer in all the
circumstances of the case warrants a departure from the ordinary
rule that costs
follow the event: SMEC Testing Services Pty Ltd v Campbelltown City
Council [2000] NSWCA 323 at [37]. The party seeking an order for indemnity
costs has the burden of showing the court why such an order should be made in
its favour
and generally this means that it should persuade the court that the
refusal to accept the offer was unreasonable: Evans Shire Council v
Richardson [2006] NSWCA 61 at [26]. The simple fact that the offeree ends up
worse off than had the offer been accepted does not mean that the refusal was
unreasonable:
SMEC Testing Services Pty Ltd above. There are usually two
matters that indicate whether the rejection of the offer was unreasonable:
whether the amount and/or
the terms of the offer is seen as genuine; and whether
the time during which the offer is open is reasonable.
18 The owners commenced proceedings in the District Court on 6 August
2003. On 12 August 2003 the builder commenced proceedings before
the Tribunal
and, as a consequence, the owners’ proceeding in the District Court was
transferred to the Tribunal.
19 On 15 December 2003 the builder made an “offer of
compromise” which was in effect the sum of $28,348.03 inclusive of
interest and costs, being the difference between the outstanding amount under
the contract of $22,211.97 and “allowances”
of $50,560 for various
rectification work or losses suffered by the owners. The offer was open until 18
December 2003. The offer
indicated that, if it were not accepted, it would be
tendered on the question of costs. No reply was received from the owners.
20 On 22 March 2004 the builder made a further offer to the owners, this
time in the sum of $57,788.03. This offer was based upon
an increase in the
allowance for the owners’ claims, from $50,560 to $80,000 from which was
deducted the balance of the monies
payable under the contract being $22,211.97.
The payment was subject to release by the owners of the sum of $11,705.90 from
the retention
fund with interest on that sum. There was the threat that, if the
offer were not accepted, it would be used on the issue of costs.
21 On 26 March 2004 the owners’ solicitor replied indicating that
the offer was “incapable of acceptance” and noted
that the builder
had not filed an amended defence to the owners’ amended points of claim
and that this has “had a significant
impact on our client’s ability
to assess the litigation risk in the context of your client’s
offer”. There were,
however, some points of clarification sought by the
owners as to the manner in which the offer had been determined.
22 The builder’s solicitor answered this letter on 30 March 2004
and the effect of the increase in the offer was explained as
being a net payment
to the owners of $57,788.03 after payment of the retention sum and the progress
payment. There was a “fresh
offer” attached in the same terms as
that of 22 March with an extended period for its acceptance until 2 April 2004.
This was
no response to this further offer.
23 On 8 December 2004 the builder made a further offer with an increase
in the sum payable to the owners from $57,788.03 to $127,788.03.
That was an
“allowance” of $150,000 less $22,211.97 being the retention monies
and the outstanding progress payment.
The offer was open for 7 days to expire on
Wednesday 15 December 2004.
24 On 14 December 2004 the solicitor for the owners asked for an
extension to consider the offer until 17 December 2004. The extension
was
granted.
25 On 17 December 2004 the owners requested information as to whether a
refund for the windows was included in the offer and the amount
allowed for that
item. On the same day the builder’s solicitor indicated that the offer was
“in full and final settlement
of all claims”. There was no further
reply to the offer.
26 The owners point out that there are no applicable rules relating to
compromise in the proceedings before the Tribunal. They also
note that the offer
was made in respect of the proceedings before the Tribunal and not in respect of
the appeal. They do accept that
the offers of the builder should be considered
against the principles that have been established for Calderbank offers.
However, they point out that the offers did not refer to Calderbank or
indicate that indemnity costs would be sought: see SMEC Testing Services,
above. However the offers made it clear that they would be used on the question
of costs, and it seems to me that they were obviously
intended to be
Calderbank offers especially as there were no relevant rules as to
compromise.
27 The owners concede that they were no better off after the judgment of
the Tribunal and the builder in his submissions points to
the significant
difference between the final offer and the Tribunal’s award. However, the
owners note the following: the time
frame for accepting the offer was only 7
days; the offer did not indicate how the amount on offer of $150,000 was
derived; there
was a double counting of the retention sum; and the offer
required that Trend recover the doors yet the owners had paid for the doors
and
the builder had received a refund. Finally the owner notes that the offer
required the owner not to make any claims on the home
warranty insurer.
28 In my opinion having regard to the substantial difference between the
amount awarded before the Tribunal and the offer of $150,000
and all the
surrounding circumstances the refusal of the offer was unreasonable. I believe
that it was a genuine offer of compromise.
Even taking into account the matters
of which complaint is now made, the owners would have been very significantly
better off taking
the offer. No question was raised about any of the matters now
suggested as difficulties with the offer at the time of the offer.
The 7 days
was adequate in view of the fact that the offer of $150,000 was the third offer
and the time was extended to allow the
owners to have legal advice. The offer
was made before the conclave of experts was due to meet and well in advance of
the hearing
date.
29 The owners should pay the costs of the builder before the Tribunal
from 17 December 2004 on an indemnity basis.
30 However no further offer was made after the Tribunal made its decision
and during the hearing of the appeal. Although the owners
are still worse off,
they have improved their position and succeeded in part on their appeal. The
builder’s appeal was dismissed.
The owners were entitled to seek to
correct errors by the Tribunal by way of appeal. In Road and Traffic
Authority of NSW v Turner (No 2) [2008] NSWCA 241 at [7], the Court stated
the following:
“An appeal is a fresh proceeding which creates a fresh opportunity for compromise. Any offer made before the trial will have lapsed and fresh offers can be made in the appeal which reflect the narrower and more focused issues.”
31 The builder should pay the
owners’ costs on the appeals.
Orders
32 The Court orders:
A. In proceeding no.30130 of 2006:
1. The appeal by the plaintiffs (the owners) is allowed in part.
2. The defendant (the builder) is to pay the plaintiffs (the owners) damages in the sum of $113,947.25 together with interest in accordance with the Uniform Civil Procedure Act from 6 October 2003 until payment.
3. The plaintiffs are to make the “trend Windows” available for collection by Trend Windows and Doors Pty limited.
4. The defendant is to pay the plaintiffs’ costs of the appeal.
5. The plaintiffs are to pay the defendant’s costs of the proceedings before the Tribunal and on an indemnity basis from 17 December 2004.
6. The plaintiffs are to pay the defendant the sum of $21,662.39 plus interest in accordance with the contract and release the sum of $11,705.90 plus accrued interest.
B. In proceeding no. 30128 of 2006:1. The appeal by the plaintiff (the builder) is dismissed.
2. The plaintiff is to pay the defendants’ (the owners’) costs of the appeal.
3. The defendants are to pay the plaintiff’s cost of the proceedings before the Tribunal and on an indemnity basis from 17 December 2004.
**********
LAST UPDATED:
2 March 2009
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2009/82.html