![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 1 February 2012
|
Case Title:
|
|
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
|
Decision Date:
|
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
|
Before:
|
|
|
|
|
|
Decision:
|
1. Each of the defendants is found guilty of the
offence charged and convicted accordingly.
2. A monetary penalty of $80,000 is imposed on Tekman Group Pty Ltd and of $8,000 on Hassan Tekman with a moiety in each case to the prosecutor. 3. The defendants are to pay the costs of the prosecutor in an amount assessed in default of agreement in such proportion as the penalty imposed on each of them bears to the aggregate of the penalties. |
|
|
|
|
Catchwords:
|
OCCUPATIONAL HEALTH AND SAFETY - breach of s 8(1)
of the Occupational Health and Safety Act 2000 - personal defendant deemed
guilty of same offence by virtue of s 26 - early guilty pleas - appropriate
penalty - objective seriousness - inadequate site induction - inadequate risk
assessment - general
and specific deterrence - remorse and contrition -
cooperation with the WorkCover Authority - inappropriate in circumstances to
apply
s10 Crimes (Sentencing Procedure) Act 1999 - penalties imposed
|
|
|
|
|
Legislation Cited:
|
|
|
|
|
|
Cases Cited:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Parties:
|
|
|
|
|
|
Representation
|
|
|
|
|
|
|
|
|
- Solicitors:
|
|
|
|
|
|
File number(s):
|
|
|
|
|
|
Publication Restriction:
|
|
(a) The 'work' referred to in these particulars refers to the work of laying bricks and blocks at the site, in particular, bricking up the opening/access way in the wall between units 8 and 9 at the site including but not limited to incidental tasks such as cleaning the wall or knocking out any temporary wooden lintel(s).
(b) The 'risk' referred to in these particulars and in the charge is the risk of Sabahattin Secim and Nevzat Tekman falling from height to the ground.
(c) Tekman Group did not ensure that:
i. a fall arrest device, such as a harness or similar device, that was capable of preventing the risk was provided and used by Sabahattin Secim and Nevzat Tekman whilst they were undertaking the work;
ii. a scaffold or elevated work platform, or similar equipment, with hand rails or other forms of physical barriers that were capable of preventing the risk was provided, positioned and used in units 8 and 9 at the site so that Sabahattin Secim and Nevzat Tekman could work from them whilst they were undertaking the work;
iii. handrails or other forms of physical barriers that were capable of preventing the risk were provided, positioned and used on the walkway/accessway between units 8 and 9 of the site; and/or
iv. there was guarding or physical barriers for a penetration on the upper level between units 8 and 9,
so as to ensure Sabahattin Secim and Nevzat Tekman's health, safety and welfare at work.
(d) Tekman Group did not provide any or any adequate supervision to Sabahattin Secim and Nevzat Tekman such as by having a supervisor monitor the work to ensure they:
i. were using a harness or similar fall arrest device that was capable of preventing the risk;
ii. worked from a scaffold, elevated work platform, or similar equipment, with hand rails or other forms of physical barriers that were capable of preventing the risk, positioned in units 8 and 9 at the site, whilst they were undertaking the work;
iii. did not use a walkway/accessway between units 8 and 9 of the site that did not have handrails or other forms of physical barriers that were capable of preventing the risk; and/or
iv. did not work next to an unguarded penetration on the upper level between units 8 and 9,
so as to ensure Sabahattin Secim and Nevzat Tekman's health, safety and welfare at work.
(e) Tekman Group did not ensure that Sabahattin Secim and Nevzat Tekman were provided with any or any adequate instruction and training to ensure that they:
i. did not work at height unless they used a harness or similar fall arrest device that was capable of preventing the risk;
ii. worked from a scaffold, elevated work platform or similar equipment, with hand rails or other forms of physical barriers that were capable of preventing the risk, positioned in units 8 and 9 at the site, whilst they were undertaking the work;
iii. did not use a walkway/accessway between units 8 and 9 of the site that did not have handrails or other forms of physical barriers that were capable of preventing the risk; and/or
iv. did not work next to an unguarded penetration on the upper level between units 8 and 9,
so as to ensure Sabahattin Secim and Nevzat Tekman's health, safety and welfare at work.
(f) Tekman Group did not have and did not provide to Sabahattin Secim, Nevzat Tekman and Mono Constructions Pty Ltd [ACN 107 404 679] a Safe Work Method Statement for the work at the site so as to ensure the health, safety and welfare at work of Sabahattin Secim and Nevzat Tekman.
(g) Tekman Group did not ensure that a risk assessment or an adequate risk assessment was conducted for the work that identified the risk at the site and the means by which it could be controlled, such as:
i. using a fall arrest device, such as a harness or similar device, whilst working at height;
ii. working from a scaffold, elevated work platform or similar equipment, with hand rails or other forms of physical barriers that were capable of preventing the risk, positioned in units 8 and 9 at the site;
iii. ensuring that handrails or other forms of physical barriers that were capable of preventing the risk were provided, positioned and used on the walkway/accessway between units 8 and 9 of the site; and/or
iv. providing guarding or physical barriers for a penetration on the upper level between units 8 and 9,
so as to ensure the health, safety and welfare at work of Sabahattin Secim and Nevzat Tekman.
As a result of Tekman Group's acts and omissions, Sabahattin Secim and Nevzat Tekman were exposed to the risk at the site. Sabahattin Secim's injury was a manifestation of that risk.
1. The Prosecutor is an Inspector duly appointed under Division 1 of Part 5 of the Occupational Health and Safety Act 2000 ("the Act") and empowered under Section 106(1)(c) of the said Act to institute proceedings in the within matter.
2. The prosecution relates to an incident at 324 William Street, Kingsgrove, New South Wales ("the site") on 1 December 2008.
3. At all material times, Hasan Tekman (DOB 1 May 1956) was a person concerned in the management of Tekman Group Pty Ltd (ACN 132 759 794) ("Tekman Group").
Background
4. On 1 December 2008, Mr Sabahattin Secim, a 64-year-old labourer/bricklayer employed by Tekman Group Pty Ltd [ACN 132 759 794] ("Tekman Group"), and Mr Nevzat Tekman, a labourer/bricklayer employed by Tekman Group, were exposed to risks of falls from heights while performing work at the site.
5. Mr Secim and Mr Nevzat Tekman were bricking up void in the wall between units 8 and 9 which involved working at a height of approximately 2.77 - 3.02 metres without adequate fall protection. They arrived at the site at approximately 7:00am.
6. At approximately 2:00pm, Mr Secim fell approximately 3m through the void whilst trying to either clean some excess mortar off a brick wall or knock out a temporary wooden lintel. Mr Secim was working above unit 9 where the staircase was to go (the scaffold was in unit 8), and fell into unit 9.
7. As a result of the incident, Mr Secim suffered serious injuries including a shattered knee cap, open knee wound (which became infected as a result), broken left wrist and fractured C1 and C2 vertebrae (requiring the wearing of a halo brace). Mr Secim ceased wearing a halo brace on 28 March 2009 and has not returned to work.
8. Albatross Property Group Pty Ltd and Chevron Holdings (NSW) Pty Ltd owned the site and contracted Mono Constructions as the principal contractor to build residential and commercial units at the site ("the project").
9. Mono Constructions is a construction company and undertakes the business of residential and commercial construction.
10. The construction work for the project was valued at in excess of $250,000.
11. During the course of the construction work for the project access ways (voids) were left in the units being constructed to allow easier access for persons and materials from one part of the site to another.
12. Mono Constructions subcontracted Tekman Industries Pty Ltd [ACN 114 020 905] ("Tekman Industries") to do brick and block work for the project at the site. This contract is in writing.
13. Tekman Industries was a brick laying company and was established on 28 April 2005. On 24 October 2008, notification of the appointment of a Liquidator of Tekman Industries was made. On 24 January 2010, Tekman Industries was deregistered. Mr Hasan Tekman was the sole Director of Tekman Industries ("Mr H Tekman").
14. Tekman Group [ACN 132 759 794] ("Tekman Group") is also a brick laying company and was established on 15 August 2008. Mrs Yuming Li, the wife of Mr Hasan Tekman, is the sole Director of Tekman Group. Mrs Li has very little involvement in the running of Tekman Group and handed complete control of Tekman Group to Mr Hasan Tekman. Mrs Li completes some administration work as instructed by Mr Hasan Tekman, such as paying telephone bills. Other than that, Mrs Li stays at home to care for their children.
15. Tekman Industries completed most of the bricking work on the project except bricking up the access ways between the units.
16. After Tekman Industries was placed under external administration, Tekman Group Pty Ltd took over the contract of Tekman Industries to complete the bricking work, that is, to brick up the access ways at the site.
17. Tekman Group told Mono Constructions that Tekman Industries was under external administration about 2 to 3 months prior to the incident. Officers of Mono Constructions have stated that they had no contract with Tekman Group and that the first time they heard about Tekman Group was in or about October 2008, when Mr Hasan Tekman asked them to write a cheque out to Tekman Group. Mono Constructions refused to write the cheque out to Tekman Group.
18. Mono Constructions believed that it had overpaid Tekman Industries by approximately $5000 for work it had done at the site. Tekman Group agreed to do the patch up brick work at the site to settle the overpayment and to maintain a good working relationship with Mono Constructions.
19. There is no written contract between Tekman Group and Tekman Industries or Mono Constructions to complete the brick and block work or the patch up work for the project at the site.
20. Mr Secim was employed by Tekman Group to do "labouring, carrying bricks, preparing the cement" on the day of the incident.
21. Mr Secim was previously employed by Tekman Industries "on and off for about a year" and had "worked on the same site about 5-6 times before". Mr Secim had previously worked for Tekman Industries in the same building for 3 days in May 2008 and 2 days in July 2008 and was paid by Tekman Industries in cash.
22. Mr Secim has been in the bricklaying industry as a labourer for twenty years.
23. Mr Nevzat Tekman was employed by Tekman Group on the day of the incident and stated that he had been employed with "Tekman Company" as a labourer/bricklayer for 6 years.
The incident
24. When Mr Secim and Nevzat Tekman were at the site on 1 December 2008, Mr Peter Khamis, Site Supervisor employed by Mono Constructions, instructed Mr Nevzat Tekman to brick up the opening/access way in the wall between units 8 and 9. This task involved working at a height of approximately 2.77 - 3.02 metres. There were unsecured planks (without handrails) which formed a walkway running perpendicular across the void between the floor above units 8 and 9. There was scaffolding in unit 8, which had been placed perpendicular to the planks. There was no scaffolding in unit 9.
25. According to Mr Khamis he told Mr Nevzat Tekman that before they were to start, they were to remove the planks and slide the scaffold located in unit 8 across to the right so that they would have a safe working platform to work from. Mr Khamis then left Mr Nevzat Tekman and Mr Secim to do the job. Mr Secim's fall occurred about 20 minutes to half an hour later.
26. Mr Secim and Mr Nevzat Tekman could speak English but had limited English language skills and required interpreters when interviewed. It is not clear whether Mr Secim received or understood Mr Khamis' instructions to remove the planks, however, he did not remove the planks.
27. The scaffolding could not be easily moved. There was no scaffolding in unit 9.
28. Mr Khamis thought the walkway had handrails but did not check this prior to instructing Mr Secim and Mr Nevzat Tekman to perform the task.
29. The system of work, even if the planks had been removed, was unsafe because the scaffold did not have adequate handrails and there was a risk of the workers falling from the scaffold into unit 9. The workers were also able to access the floor of the next level above units 8 and 9, and when working from this level the void constituted an unguarded penetration.
30. Neither Mono Constructions nor Tekman Group undertook a documented risk assessment for the work to be completed by Mr Secim and Mr Nevzat Tekman on 1 December 2008.
31. Neither Mr Secim nor Mr Nevzat Tekman received an adequate induction at the site which explained to them that they were not to work at height without adequate fall protection or next to unguarded penetrations.
32. Mr Nevzat Tekman and Mr Secim were not provided with safety harnesses or other fall protection devices when they were undertaking the bricking up work.
33. Mr Khamis did not monitor the work performed by Mr Secim and Mr Nevzat Tekman to ensure that any instructions he had issued were carried out.
34. Mr Secim and Mr Nevzat Tekman did not slide the scaffold across and stood on the part of the planks that were in unit 9 to brick in the opening/access way in the wall. Immediately prior to the incident, Mr Nevzat Tekman was standing on the floor of the level above unit 8 and Mr Secim was standing near to Nevzat Tekman either adjacent to the unguarded penetration or on the walkway planks.
35. It is unclear as to whether Mr Secim wanted to clean some excess mortar off the bricks or knock out the temporary timber lintels. Prior to Mr Secim's fall he and Mr Nevzat Tekman were cleaning bricks or knocking out a temporary timber lintel with a hammer and that he took over this task from Mr Nevzat Tekman when he got tired.
36. Mr Nevzat Tekman told Mr Secim not to worry about cleaning the bricks as he would do it later.
37. Prior to his fall, Mr Secim swung at either a piece of excess mortar or a timber lintel and lost his balance and fell into the ground in unit 9.
38. Mr Khamis heard someone screaming and ran into unit 9 to find Mr Secim on the ground. Mr Khamis immediately called for an ambulance and asked what had happened.
39. The ambulance subsequently arrived and took Mr Secim to hospital. The NSW Police also attended the site.
40. After Mr Secim fell, "Hasan", a contractor from NSW Formwork, advised him that before the incident, Mr Secim had dropped a tool down to the level below where Hasan was working. Mr Secim allegedly apologised and said that he was feeling a bit dizzy as he was on medication. Mr Secim denied that this was the case.
Systems of work prior to incident
41. In relation to Mono Constructions:
(a) Mono Constructions did not obtain a Safe Work Method Statement from either Tekman Industries or Tekman Group prior to them commencing work on the site. There was no Safe Work Method Statement prepared for the task of bricking up the void that Mr Secim and Mr Nevzat Tekman were performing on the day of the incident.
(b) Mono Constructions did not have or follow an adequate, safe system in place for working at heights or guarding penetrations at the site.
(c) Mono Constructions' safe work method statement for working at heights was not discussed with subcontractors either when they were inducted onto, or after they started work at the site.
(d) Prior to the incident on 1 December 2008 Mono Constructions had identified that it had a lack of occupational health and safety systems ("OH&S systems") in place. On 27 November 2008, Mono Constructions engaged Acumen Management Services Pty Ltd, OHS consultants, to develop its OH&S systems. However, the OH&S systems were not developed until after the incident.
(e) Mono Constructions did not document or record all toolbox talks at the site.
(f) Employees of Mono Constructions (other than Christopher and Peter Moujalli and Peter Khamis) and employees of entities subcontracted to do work by Mono Constructions were not present during Mono Constructions' toolbox talks.
(g) Mono Constructions does not have a record of inducting Mr Tekman or Mr Nevzat Tekman into the site, although it had a record of inducting Mr Secim in May 2008.
(h) Mono Constructions did not undertake a documented, site specific, risk assessment for the site.
(i) Mr Khamis did not supervise Mr Nevzat Tekman and Mr Secim to ensure that they moved the scaffold in Unit 8 and did not work on the concrete floor of the next level next to the unguarded penetration on the floor above units 8 and 9.
(j) Mono Constructions failed to provide two sets of scaffolding, one for each side of the void.
(k) The scaffolding in Unit 8 could not be easily moved.
42. In relation to Tekman Group:
(a) Tekman Group did not have a Safe Work Method Statement for the brick and block work at the site. Mr Secim had never seen a Safe Work Method Statement for the work at the site and was never involved in any toolbox talks. Mr Nevzat Tekman confirmed that no Safe Work Method Statements were completed and that he didn't know what a Safe Work Method Statement was.
(b) Mr Tekman did not attend the site to inspect it prior to Mr Secim and Mr N Tekman starting work on the day of the incident.
(c) Tekman Group did not conduct a risk assessment or a toolbox meeting for the brick and block work at the site.
(d) Tekman Group does not have any training records for its employees. Mr Secim never received any training from Tekman Group or Tekman Industries.
(e) Mr Nevzat Tekman does not have a trade certificate for bricklaying or a licence to erect scaffolding. Mr Nevzat Tekman was trained in bricklaying and erecting scaffolds by Mr Hasan Tekman. Mr Secim did not have a trade qualification for bricklaying but had a TAFE College Statement dated 5 September 1991 certifying that he had completed the requirements of the LMP - Handypersons Course at Randwick college of TAFE.
(f) Mr Secim was never provided with a harness nor had received training on how to use a harness from Tekman Group or Tekman Industries.
(g) Tekman Group did not provide supervision at the site and relied on the supervision of Mono Construction. Mr Nevzat Tekman was not a supervisor although he was more experienced than Mr Secim.
Systems of work after the incident
43. After the incident Mr Nevzat Tekman returned to the site two days later to complete the work but with no instructions from Mr Hasan Tekman about how the work could be done more safely. Tekman Group did not attend the site to inspect it or conduct a risk assessment to ensure the site was safe.
Orders
1. Each of the defendants is found guilty of the offence charged and convicted accordingly.
2. I impose a monetary penalty of $80,000 on Tekman Group Pty Ltd and of $8,000 on Hassan Tekman, with a moiety in each case to the prosecutor.
3. The defendants are to pay the costs of the prosecutor in an amount assessed in default of agreement in such proportion as the penalty imposed on each of them bears to the aggregate of the penalties.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2011/149.html