![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 5 September 2011
|
Case Title:
|
|
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
|
Decision Date:
|
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
|
Before:
|
|
|
|
|
|
Decision:
|
1. In Matter No IRC 1772 of 2009, I find the
defendant guilty of the offence as charged.
2. The defendant is fined in the sum of $15,000 with a moiety to WorkCover Authority of New South Wales. 3. The defendant is to pay costs of the prosecutor. There has been no agreement between the parties as to the quantification of the costs. I will hear the parties on this issue in the event no agreement can be reached. Leave to re-list at short notice. |
|
|
|
|
Catchwords:
|
OCCUPATIONAL HEALTH AND SAFETY - breach of s 10(1)
of the Occupational Health and Safety Act 2000 - individual defendant a director
of corporation who was owner of the premises and principal contractor on site -
failure to ensure
high voltage electrical wires were not removed from above
construction site - safe systems of work not put in place given knowledge
of
risk - plasterer not warned suffers electrocution - plea of guilty - foreseeable
element - general deterrence - remorse and contrition
demonstrated - director
defendant bankrupt - early plea challenge - penalty
|
|
|
|
|
Legislation Cited:
|
|
|
|
|
|
Cases Cited:
|
Capral Aluminium Ltd v WorkCover Authority of New South
Wales [2000] NSWIRComm 71; (2000) 49 NSWLR 610
Fisher v Samaras Industries Pty Limited (1996) 82 IR 384 Inspector Morgenthal v Houghton [2010] NSWIRComm 192 Inspector Patton v Hall and Quinn [2010] NSWIRComm 6 Inspector Wilkie v Anstee (No. 2) [2007] NSWIRComm 20 Lawrenson Diecasting Pty Ltd v WorkCover Authority of New South Wales (Inspector Ch'ng) [1999] NSWIRComm 343; (1999) 90 IR 464 Markarian v R [2005] HCA 25; (2005) 215 ALR 213; (2005) 228 CLR 357 Morrison v Powercoal Pty Limited [2003] NSWIRComm 416; (2003) 130 IR 364 R v Dib [2003] NSWCCA 117 R v Gallagher (1991) 23 NSWLR 220 R v Stambolis [2006] NSWCCA 56 R v Thomson; R v Houlton [2000] NSWCCA 309; (2000) 49 NSWLR 383; (2000) 115 ACrimR 104 R v Way [2004] NSWCCA 131; (2004) 60 NSWLR 168 Tyler v Sydney Electricity (1993) 47 IR 1 WorkCover Authority of NSW (Insp Mansell) v Chen and Obing Pty Ltd t/as Old But New [2004] NSWIRComm 247 |
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
Parties:
|
|
|
|
|
|
Representation
|
|
|
|
|
|
|
|
|
- Solicitors:
|
|
|
|
|
|
File number(s):
|
|
|
|
|
|
Publication Restriction:
|
|
By its acts or omissions particularised below, ensure that the premises were
safe and without risks to health contrary to section 10(1) of the
Occupational Health and Safety Act 2000.
The particulars of the
charge are:
(a) The corporation at all material times had control or alternatively limited control over the premises;
(b) At all material times person not employed by the corporation, in particular Darren Bunney, Hussein Al-Jaboore, Gary Cook and Said Al-Khaled performed work at the premises;
(c) At all material times the corporation had control by virtue that it was the owner of the premises and principal contractor for the construction of thirteen townhouses and units at the premises.
(d) At all material times the defendant was a director of the corporation.
The particulars of the risk are:
(e) There was a risk of injury to non-employees working on scaffolding at the
premises of suffering electric shock and/or electrocution
from accidental
contact by plant or equipment utilised by non-employees, with live overhead
power lines running across the premises.
The particulars of the acts or
omissions in failing to eliminate the risk are that:
(f) The corporation failed to ensure that the premises were safe and without
risks to health in that it failed to ensure that people
working on or otherwise
accessing the scaffold at the premises were provided with a safe system of work
for working near live overhead
power lines in that it failed to undertake
measures as follows:
(i) ensuring that the live overhead power lines running across the premises were de-energised or re-directed away from the work area , in particular from areas where scaffolding was erected for the construction of blocks;
(ii) ensuring that scaffold was not erected within four metres from live overhead power lines as required by Australian Standard 4576;
(iii) isolating the power lines through the erection of physical control barriers around the scaffold;
(vi) place warning signs on the scaffold to alert persons to the presence and
proximity of live overhead power lines;
(g) The corporation failed to ensure that the premises was safe and without risks to health in that it failed to undertake a risk assessment which:
i considered and identified the hazards associated with working near live overhead power lines; and
ii considered and identified the risk of equipment coming into contact with
live overhead power lines.
(h) The corporation failed to ensure that the premises was safe and without
risks to health in that it failed to ensure that some
or all of the non
employees working at the premises were provided with information, instruction
and/or training in relation to working
near live overhead power lines in that it
failed to undertake measures as follows:
i conduct site specific inductions to inform persons of the presence and proximity of live overhead power lines;
ii conduct tool box talks to inform persons of the presence and proximity of live overhead power lines;
iii inform person that live overhead power lines were approximately 2.9
metres from the highest point on the scaffold.
(i) The corporation failed to ensure that the premises were safe and without
risks to health in that it failed to ensure that a safe
work method statement
was in place for working near live overhead power lines as required by clause of
the 227 Occupational Health and Safety Regulation 2001;
(j) The corporation failed to ensure that the premises was safe and without
risks to health in that it failed to supervise to persons
undertaking work at
the premises in relation to working near live overhead power lines in that it
failed to undertake measures as
follows:
i ensuring that non employees did not work from the top level of the scaffold
that was in excess of 2 metres high with equipment that
was capable of coming
into contact with overhead power lines.
(k) As a result of the corporations failures non-employees present at the
premises, and in particular, Said Al-Khaled, sustained severe
injuries from
electric shock which was a manifestation of that risk.
2. At all material times STUART JOHN HILL of 28 Forest Road Yowie Bay ("Stuart Hill") was a director of Jacarada Property Developments Pty Ltd [ACN 091 272 132] ("Jacaranda"), a company which was wound up pursuant to an order of the NSW Supreme Court on 20 April 2009.
3. At all material times Stuart Hill was responsible for obtaining, managing and overseeing the contracts for building work for Jacaranda, including engaging subcontractors.
4. At all material times Neatrule Cement Rendering Pty Ltd [ACN 125 742 761], ("Neatrule") was a corporation with its registered office located at KPR Partners Pty Ltd, Suite 10, 2/4 Northumberland Drive Caringbah in the State of New South Wales.
5. At all material times Neatrule carried out cement rendering and plastering work in the construction industry.
Background
6. At all material times Jacaranda was involved in the business of building and construction of premises, including town houses.
7. At all material times Jacaranda was the owner and principal contractor for the construction of 13 townhouses and units at 9 Fenton Avenue, Caringbah ("the site").
8. At all material times Jacaranda had control in the course of its trade, business or undertaking of the site by virtue that it was the owner of the premises and principal contractor for the construction of 13 townhouses and units at the site.
9. At all material times persons not employed by Jacaranda, in particular Darren Bunney, Hussein Al-Jaboore, Gary Cook and Said Al-Khaled performed work at the premises.
10. At all material times the site was not occupied as a private dwelling.
11. At all material times Jacaranda contracted Tony Palmer as a site manager. Along with overseeing the work of subcontractors, Tony Palmer's duties included liaising with the local authorities and utilities as well as general labour.
12. Construction commenced at the site in or around February 2007.
13. In or around July 2007, Jacaranda engaged Waco Kwikform Limited ("Waco") to provide and erect scaffolding at the site. In turn, Waco subcontracted Solidscaff Pty Ltd ("Solidscaff'") to undertake the erection and dismantling of the scaffold.
14. At all material times, Darren Bunney was a director and employee of Neatrule. Darren Bunney is an experienced wet and dry plasterer and has been issued a Contractor License to undertake this work by the Office of Fair Trading.
15. In or around July 2007, Jacaranda entered into a verbal contract with Darren Bunney on behalf of Neatrule to provide cement rendering to the external walls of the newly constructed townhouses.
16. In turn, Neatrule entered into a number of subcontract agreements with the injured worker, Said Al-Khaled ("Mr Al-Khaled"), Hussein Al-Jaboore and Gary Cook to perform the cement rendering work ("the rendering subcontractors").
17. Mr Al-Khaled is the holder of a Contractor Licence for wet plastering by the Office of Fair Trading.
18. Neatrule's rendering subcontractors commenced work on the site in mid-late July 2007.
The Site
19. The site consisted of six double story blocks, which were a mix of freestanding townhouses and unit blocks. There were six blocks at the site named A to F.
20. Fenton Avenue bordered to the site on the west and Captain Cook Drive on the east, wrapping to the north of the site.
21. Six 33,000 volt power lines ran adjacent to the site along Captain Cook Drive from Pole CR02549 (north) to Pole CR02550 (south). Pole CR02549 was approximately 2m north of Block A and situated 4m to the East (1m outside the side fence). Pole CR02550 was situated outside the site fence at approximately Block C.
22. The power lines varied in height from estimated 10.7m from the grade upward. The power lines were identified as 33kV via the six insulators at each line at the connection with the poles.
23. Due to the fact that Captain Cook Drive ran on the east of the site and wrapped around to the north, this placed at the power lines between poles CR02549 and CR02550 at an angle running through the north east side of the site.
24. The scaffolding at the north eastern corner of Block B extended approximately 1 metre past the property line. The 33kV overhead line passed over the top of the scaffold at the north eastern corner of Block B. At this point the overhead line was approximately 10.7 metres from the ground. The scaffold work deck was approximately 5.5 metres from the grade and approximately 5.2 metres below the overhead power lines at the point at which they intersected. The scaffold handrail was approximately 6.5 metres from the grade and approximately 4.2 metres below the overhead power lines at the point at which they intersected. Several standards rose an additional 1.2 metres above the handrail, reaching approximately 7.7 metres from the grade. At the first standard to the south of the north east corner standard the power lines were approximately 2.9 metres above the highest point of the scaffold (being the top of the second scaffold standard on the eastern face). From directly above or below, the 33kv power lines were horizontally 0.3 metres inside the outer corner of the scaffold hand rail and 0.5 metres from the outer corner of Block B.
Safe scaffold clearances
25. Clause 5.4 of AS/NZS4576 "Guidelines for Scaffolding" requires a safe working distance of 4 metres or more between metal scaffolding and overhead power lines of 33,000 volts.
26. Clause 6.5(d) of the WorkCover Code of Practice - Work Near Overhead Power lines (2006) ('the Code") provides that high visibility wrapping or "tiger tails" is not appropriate for use on overhead power lines exceeding 1000 volts. The Code further provides that although tiger tails provide a useful visual indication to people working in the area of overhead power lines, they should not be regarded as providing electrical protection from electrical hazards.
27. Clause 9.2 of the WorkCover "Safe Working at Heights" Guide 2006 provides that the power lines should be de-energised and access authority should be obtained from the network operator if the scaffold and the overhead power line have the potential to come within the 4 metre approach distance.
28. Clause 6.5(f) of the Code provides that safe working control measures include ensuring that a person or anything held by a person, or attached to the person, coming closer than 4 metres may require the erection of a hoarding on the external face of the scaffolding.
Erection of Scaffold to Block A
29. On 23 July 2007 Solidscaff attended the site to erect the scaffold to Block A.
30. On 25 July 2007 Solidscaff stopped erecting the scaffold on the North East corner of Block A because its employees were concerned that by continuing to do so would result in the scaffold being too close to the overhead power lines.
31. Solidscaff/Waco told Tony Palmer to contact the local network operator, Energy Australia, to determine how to proceed.
32. Accordingly, work on Block A was put on hold whilst Stuart Hill sought advice from Energy Australia.
33. On 30 July 2007, Jonathan Mallin, Engineering Officer (Overhead Transmission) from Energy Australia, attended the site to undertake a preliminary assessment, including taking measurements.
34. At approximately 2:00pm on 2 August 2007, Jonathan Mallin attended the site again, together with several other Energy Australia employees, for a pre-arranged follow up meeting.
35. Jonathan Mallin told Tony Palmer that the power lines were 33,000 volts, and that tiger tails would not be appropriate.
36. Mr Palmer states that Jonathan Mallin suggested that the scaffold on Block 'A' would be too close to the overhead power lines if it was taken any higher. Mr Palmer states that Mr Mallin suggested an option would be to move the power lines to the other side of the power pole. Mr Palmer states that Mr Mallin provided a rough quote of $30,000.00 for the cost of Energy Australia moving the power lines to the other side of the power poles.
37. Jonathan Mallin told Tony Palmer work would need to cease immediately in the vicinity of the power lines and that arrangements would need to be made to move the power lines to the other side of the pole.
38. Jonathan Mallin provided Tony Palmer with a costs estimate for the work of $30,000.00 and said that these costs were to be borne by the owner/builder. Jonathan Mallin gave Tony Palmer his contact details so that Tony Palmer could formally accept the costs estimate. Tony Palmer told Jonathan Mallin that he would discuss the issue with Stuart Hill and they would decide on a course of action.
39. On 6 August 2007, having heard nothing from either Stuart Hill or Tony Palmer regarding the required changes, Jonathan Mallin alerted WorkCover to the situation.
40. On 10 August 2007, Inspector Jeffrey Bell visited the site in response to Jonathan Mallin's telephone call. Inspector Bell observed no work being conducted on Block A and assessed the scaffold in the presence of Tony Palmer. Inspector Bell observed that the scaffolding that was located on the east side of the building on level one had been erected without handrails. Inspector Bell observed that if the handrails had been installed they would have encroached the four meter exclusion zone. Inspector Bell advised Mr Palmer that if there was any work to be conducted on that level that harnesses should be used.
41. Mr Palmer informed Inspector Bell that there would be no work conducted on level one of that building until Energy Australia and the developer resolved their dispute regarding the power lines. Inspector Bell advised Mr Palmer that he should tape off the area to ensure that no workers would enter the area.
42. Inspector Bell agreed with Tony Palmer that rather than installing handrails the work would be undertaken using static lines and harnesses so as to maintain a safe working distance.
43. Having still heard nothing regarding the required changes, Jonathan Mallin telephoned Tony Palmer on two separate occasions after 6 August 2007. Tony Palmer told Jonathan Mallin that the owners were seeking money from the Council in relation to moving the power lines.
Erection of Scaffold on Block B
44. Block B was a two-storey premise of approximately 105 m floor space. It was approximately 7m high at the north gutter line and around 8m high at the south ridgeline. It was situated between Block A (north) and Block C (south), approximately 4m from each. Block B is approximately 6m from Captain Cook Drive to the east and approximately 6m to the corner of Fenton Ave.
45. On 17 October 2007, Solidscaff erected the scaffold around Block B.
46. Block B was enclosed by perimeter scaffolder on the north, south, east and west sides. The first lift bays were at approximately 3m in height. The top bays were approximately 5.5m from the grade. The north and east faces had hand rails which were situated 1m above the top bays at approximately 6.5m. Several standards rose an additional 1.2m above the handrail (reaching approximately 7.7m from the grade). On the north side, top level, the scaffold was 6 bays long.
47. The power lines ran over the scaffolding at Block B, intersecting with it at the 1 st bay end point on the east (2 nd standard at 1.787m from the north-east corner standard) and the 4 th standard to the south (4.8m south from the north east corner standard) and were visible from the ground and the scaffolding.
48. The distance between the overheard power lines and the second standard on the eastern face of the scaffold on Block B (being the highest point on the scaffold) was 2.9m.
49. Upon completion of the scaffold Solidscaff/Waco gave Jacaranda a Scaffold Inspection Report. The report stated that the scaffold had passed an inspection, which included consideration of AS/NZS4576, and that it was safe to use. Annexed to this document and marked "Annexure A" is a true copy of Waco Kwikform Limited Scaffold Inspection Report (Inspection No. 21804) dated 17 October 2007.
50. However, the employees of Solidscaff had not ensured that the scaffold was compliant with AS/NZS4576 in that it did not allow a safe working distance of 4m from the overhead power lines. Rather than accurately measuring the distance from the power lines, the scaffolders relied on an estimate based on sight alone.
51. No warning signs were placed on the scaffold alerting workers to the presence or location of the overhead power lines.
Incident
52. As at 12 November 2007, Block B was nearing structural completion. The roof and guttering (without downpipes) had been installed. Brickwork was finished or nearing completion. Windows, frames and glass panes were installed.
53. As at 12 November 2007, the power lines which ran over the scaffolding at Block B had not been moved or de-energised.
54. At approximately 7:00am on 12 November 2007, the rendering subcontractors - Mr Al-Khaled, Hussein Al-Jaboore, and Gary Cook - started work. Tony Palmer instructed them to start work on Block B.
55. They commenced working on the western wall of Block B. By approximately 3:00pm, the rendering subcontractors had completed rendering the wall on the western side of the Block B.
56. Shortly after 3:00pm on 12 November 2007, Darren Bunney arrived on site. Darren Bunney instructed Mr Al-Khaled, Hussein Al-Jaboore, and Gary Cook to complete the rendering on different walls of Block B. Hussein Al-Jaboore was instructed to clean tools on the western side of Block B, whilst Mr Al-Khaled was instructed to continue the rendering work on the scaffold adjacent to northeast of Block B.
57. Mr Al-Khaled proceeded up a set of stairs to the top level of the scaffold situated at the northeastern corner of Block B. The scaffold at this level was at approximately at roof height.
58. Immediately prior to the incident, Mr Al-Khaled was preparing to apply an aluminium straight edge onto a corner of Block B.
59. The aluminium straight edge was approximately six metres long. The purpose of using the straight edge was to make sure that the edge of the building that was being rendered was straight.
60. Mr Al-Khaled stated that before the Incident he was not aware that there were high voltage overhead power lines in close proximity to the scaffold at Block B. Hussein Al - Jaboore, a labourer working for Neatrule Cement Rendering stated that he was aware that there were high voltage overhead power lines in close proximity to the building at Block B, as they were very visible. Mr Darrren Bunnney, Director of Neatrule Cement Rendering stated that he was not aware that there were high voltage overhead power lines in close proximity to the building Block B, as it was the first day on working on that Block. The incident occurred towards the end of the first day that the renders had worked on Block B.
61. Some of the Neatrule Cement Rendering renders had worked on Block A which was also located in close proximity to the same high voltage overhead power lines as were located in close proximity to the building at Block B.
62. At approximately 3.45pm, Mr Al-Khaled lifted the straight edge in order to place it between the wall and the scaffold. In doing so, the straight edge struck the overhead power lines and Mr Al-Khaled received a severe electric shock.
63. At the time of the incident, Darren Bunney was working underneath the scaffold on the western side of Block B cleaning cement render off the windows. Darren Bunney said that he "got a flash" which threw a tool out of his hand. In response, Darren Bunney called out to Gary Cook as he thought that he was working above him on the scaffold.
64. Darren Bunney proceeded to call out to Hussein Al-Jaboore and Mr Al-Khaled. Immediately, he heard a voice which he recognised as Mr Al-Khaled saying "Allah Allah."
65. Darren Bunney proceeded to run up the stairs and saw Mr Al-Khaled keeled over with his feet dangling over the scaffold at the far end of the eave.
66. Darren Bunney yelled for someone to call an ambulance. Gary Cook called the ambulance, climbed up the stairs and handed the telephone back to Darren Bunney who spoke to the operator.
67. Darren Bunney continued to attend to Mr Al-Khaled with the assistance of Hussein Al-Jaboore. He then called Anthony Palmer and requested that he attend the premises immediately.
68. An ambulance arrived at the premises and Mr Al-Khaled was transported to St George Hospital. Mr Al-Khaled was then airlifted to Concord Hospital. Mr Al-Khaled remained in Concord Hospital Burns Unit for two and a half weeks and was discharged on 26 November 2007.
69. As a result of the electric shock Mr Al-Khaled suffered burn injuries to
35% of his body.
Systems of Work Prior to the incident
Jacaranda
70. Mr Palmer, Site Manager for Jacaranda stated that he gave Mr Al-Khaled a verbal site-specific induction or briefing prior to commencing work at the site, however he was not able to indicate on what date this occurred, nor was the fact of the induction or what was contained in the induction documented. Mr Palmer stated that the induction would have been limited to a general overview of the site, where the amenities were located, where the first aid box was located and the assembly area in case of emergency. Mr Al-Khaled stated that he did not receive a site-specific induction or briefing prior to commencing work at the site. Jacaranda subsequently provided Hussein Al Jaboore and Gary Cook, renders engaged by Neatrule Cement Rendering with a site-specific induction on 19 November 2007.
71. Neatrule Cement Rendering did not provide to Jacaranda with a copy of their Safe Work Method Statements ("SWMS") for the work to be undertaken at the Site.
72. Jacaranda did not provide any instruction or documented risk assessment to Neatrule or the rendering subcontractors , in particular dealing with risks associated with working on scaffold near overhead power lines.
73. Jacaranda did not provide the rendering subcontractors with specific information or instruction in relation to the cement rendering works to be performed at the premises.
74. Jacaranda did not hold any toolbox talks with Neatrule or its rendering subcontractors. Neatrule and its rendering subcontractors, including Mr Al-Khaled, were not informed of the presence and location of power lines at Block B prior to commencing work.
75. Notwithstanding that it had been made aware of the rules regarding safe
working distances from power lines as a result of its
experience with Block A
(detailed in paragraphs 29 to 43 above), Jacaranda relied on a Scaffold
Inspection Report (Report No. 21804
dated 17/10/07) produced by the scaffolders.
The Scaffold Inspection Report did not specifically address the issue of the
proximity
of the scaffolding to the power lines in the vicinity of Block B.
However, Scaffold Inspection Report No. 21804, including a statement
as follows:
" NOTES This report should reflect the structure at the time of
inspection. In assessing the structure you should refer to...Guidelines
for
scaffolding AS/NZS4576..."
76. Jacaranda did not undertake its own risk assessment and did not inspect or check the distance themselves in a situation where they were aware of the risk of the proximity of power lines to scaffolding. Jacaranda did not believe that it had a duty to make further enquiries of the scaffolders once the Scaffold Inspection Report was received from the scaffolders.
77. Jacaranda did not put in place any warning signs on the scaffold to alert workers to the presence and location of power lines.
78. Tony Palmer was off site temporarily at the time of the incident and Jacaranda did not have another supervisor at the site supervising the works being undertaken by the rendering subcontractors at the premises.
Neatrule
79. At the time of the incident, Neatrule had in place an informal system of work, which was communicated verbally amongst the rendering subcontractors regarding the performance of tasks. It was the usual practice of Neatrule for its rendering subcontractors to work from the middle level of the scaffold and use the hop up to get to the top level. From there Neatrule's rendering subcontractors would put the straight edge in place.
80. Neatrule undertook a basic risk assessment in relation to cement rendering works at the site; however the assessment did not consider the risk of working on scaffold in close proximity to overhead power lines.
81. Neatrule did not have a written SWMS in place for the cement rendering works being undertaken at the premises.
82. Further, Neatrule did not request that its rendering subcontractors provided it with SWMS's.
83. Neatrule did not provide an induction or any daily toolbox talks to its rendering subcontractors.
84. Neatrule did not have a system in place to ensure that Jacaranda had adequately assessed the safety of the scaffold, in particular in that the scaffold maintained a safe working distance of 4 metres from the overhead power lines.
85. Neatrule did not have a system in place to ensure that Jacaranda advised it of identified risks identified on the site, in particular the risk of working on scaffold in close proximity to overhead power lines.
86. Neatrule did not provide its subcontractors any instruction on how work safely at the site safely, and in particular how to work safety on the scaffold in close proximity to power lines. Rather, Neatrule relied on the experience of its rendering subcontractors to work safety.
87. Neatrule did not provide adequate supervision to its rendering subcontractors.
Investigation
88. On 12 November 2007, Inspector Derek Pryor attended the site in response to an incident notification. Inspector Pryor undertook an inspection and made observations contained in the Factual Inspection Report dated 3 December 2007, which is annexed and marked "Annexure B."
89. Inspector Prior took a number of photographs and bunted off the incident area for further investigation. Annexed to this document and marked "Annexure C" are seven coloured photographs numbered 969-5, 969-6, 969-7, 969-8, 969-10, 969-11, and 969-12.
90. On 15 November 2007, Inspector Prior returned to the site and took a number of measurements. Using a Leica Disto A3 (serial A299) laser measurement device Inspector Pryor measured the distance between the overheard power lines and the second standard on the eastern face of the scaffold on Block B (being the highest point on the scaffold) as being 2.9m.
91. Inspector Pryor issued Jacaranda two Prohibition Notices (No 170562 and
No170564), which directed Jacaranda to:
(a) immediately cease work on scaffold Block B;
(b) in consultation with WorkCover appoint a scaffolder to rectify the scaffold to meet AS1576; and
(c) liaise with Energy Australia and develop an agreement regarding the management of the 33,000volt power lines around the site.
(Annexed to this document and marked "Annexure D" are true copies of the Prohibition Notices.)
System of work after the incident
92. After the incident Jacaranda instructed the scaffolders to drop the height of the scaffold outside Block B so that it would fall within the safe working distance. This was completed on 21 November 2007.
93. Jacaranda prepared a site-specific work method statement for the work to be conducted on Block B.
94. Tony Palmer stopped working for Jacaranda in June 2008.
Criminal History
95. Stuart John Hill has no prior convictions. Annexed to this document and
marked "Annexure E" is a record of prior convictions.
Relevant Principles
The instinctive synthesis approach is the correct general approach to
sentencing. This does not, however, necessarily mean that there
is no element
which can be taken out and treated separately, although such elements ought be
few in number and narrowly confined.
As long as they are such, their separate
treatment will not compromise the intuitive or instinctive character of the
sentencing process
considered as a whole.
Proper regard is to be had to
express legislative provisions and to the relevant statutory regime (
Markarian at [27]). The object of the Act is to protect employees from
risk to safety, health and welfare whilst compelling attention to occupational
health and safety issues
so that persons are not exposed to risk to their health
and safety at the workplace.
In R v Way [2004] NSWCCA 131; (2004) 60 NSWLR 168 it was emphasised that the provisions
of the Crimes (Sentencing Procedure) Act ...are not to be construed as
representing "a departure from settled principles of sentencing practice, or an
abandonment of the discretion
that is essential to any system calling for
individualised justice". As was said at [59]:
'[i]t is clear that the legislative policy ... so far as that can be
discerned from the legislation itself, was not to create a straight
jacket for
judges ... but rather [was] intended to provide "further guidance and structure
to judicial discretion."
. . .
(2) Aggravating factors
. . .
(d) the offender has a record of previous convictions,
...
(g) the injury, emotional harm, loss or damage caused by the offence was substantial,
. . .
(3) Mitigating factors
. . .
(e) the offender does not have any record (or an significant record) of previous convictions,
...
(g) the offender is unlikely to re-offend,
...
(k) a plea of guilty by the offender (as provided by section 22)
(l) the degree of pre-trial disclosure by the defence (as provided by section 22A),
(m) assistance by the offender to law enforcement authorities (as provided by section 23)
. . .
Consideration
In case of prosecutions under the OH&S Act, this proposition has often
been expressed by saying that the "true measure of penalty
lies in the nature
and quality of the offence" ...
And in Morrison v Powercoal Pty
Limited [2003] NSWIRComm 416; (2003) 130 IR 364 at [32]:
In assessing the gravity of the offence the focus, therefore, must be on the
risk and, viewing it objectively, the seriousness of
the act or omission that
gave rise to the risk. In other words, the consequence of an accident will not,
of itself dictate the seriousness
of the offence or the amount of penalty.
However, the occurrence of death or serious injury may well manifest the degree
of seriousness
of the risk to health and safety to which persons may have been
subjected ...
Notwithstanding the scaffold was erected in full (in Block B) the wires were
not as close to Block B as they were to Block A.
This was Mr Hill's
opinion, not a fact. Mr Hill says he instructed workers on the top level of
Block B to use the approved procedure,
that is: the use of harnessing and static
lines when on the top level. However, that procedure was not followed by Mr
Al-Khaled when
he went up to the top level of the scaffolding and held up the
aluminium length. As a result, when the aluminium length struck the
overhead
powerlines, he suffered injury.
NOTES This report should reflect the structure at the time of
inspection. In assessing the structure, you should refer to :
Australian Standard-Scaffolding AZS/NZS1576
Guidelines for Scaffolding AZS/NZS1576
Waco Kwikform design and quotation
Waco Kwikform Guidelines for Safe use of Scaffold
Waco Kwikform Work Instructions for Ties and Needles
I do not accept
this submission. Jacaranda, as head contractor, had an obligation itself to
ensure that its premises were safe and
without risk to health. Further, it
possessed knowledge of the danger and the presence of the high voltage, overhead
power lines.
Jacaranda failed to ensure that the subcontractor provided a safe
work method statement. It also failed to ensure non-employees did
not use
equipment from the top level of the scaffolding on Block B which was capable of
coming into contact with the overhead power
lines. It particularly failed to
ensure a worksite, on which it invited contractors to perform work, was safe.
The existence of a reasonably foreseeable risk of injury will necessarily
result in the offence being more serious in nature. However,
the absence of
foreseeability does not necessarily render the offence as being nominal or not
serious. In this regard the relevant
approach is that set out in the judgment of
Wright J, President, in Ferguson v Nelmac Pty Ltd (at 209-210) in these
terms:
... reliance on 'hindsight' must be seen in an appropriate perspective in
terms of culpability. It is a relevant consideration but
the very terms of s 15
impose an obligation on an employer which is not confined to the taking of
precautions only when there are warnings or signals of
danger or when experience
indicates that a risk to safety has arisen and requires remedy.
Accordingly Jacaranda, and the individual defendant director in this
case, were under an obligation to exercise abundant caution,
maintain constant
vigilance and take all practical precautions to ensure safety.
The gravity of the damage or injury actually resulting from the breach does
not, of itself, dictate the amount of penalty. However,
the gravity or otherwise
of the potential risk flowing from the breach and its foreseeability are clearly
relevant ...
Where the risk of death or serious injury becomes a
reality, in a case such as this, it will be indicative of the seriousness of the
risk. Section 21 A(B)(i)(b) of the Crimes (Sentencing Procedure) Act 1999
provides that the fact that an offence involved the risk of death or a serious
injury is an aggravating factor to be taken into account
in determining the
appropriate sentence. Mr Al-Khaled suffered burns to 35 percent of his body
through electrocution. It was a serious
injury.
... both aspects of deterrence are matters which should normally be given
weight of some substance in the sentencing process; and
although there may be
exceptional cases (see, for example , Page v Walco Hoist Rentals Pty Ltd
(No 2) [2000] NSWIRComm 39 at [40]- [43] ) we would expect such cases to be
very rare, and where the relevant circumstances were held by the sentencing
judge to be established,
the judge must indicate with some precision the
circumstances which had led to the exceptional course being adopted.
In
Capral , the Full Bench also affirmed what was said by Hungerford J in
Fisher v Samaras Industries Pty Limited (1996) 82 IR 384 (at 388):
the fundamental duty of the Court in this important area of public concern
... [is] to ensure a level of penalty for a breach as will
compel attention to
occupational health and safety issues so that persons are not exposed to risks
to their health and safety at
the workplace.
[56] ... it is not to be overlooked that there is a well established body of
principles that have been developed by the courts over
a long period of time. By
providing guidance in the form of a list of aggravating and mitigating factors
in s 21A, the Parliament did not intend to overrule or disturb those principles
or restrict their application. In so far as those principles
refer to factors,
whether objective or subjective, that affect the "relative seriousness" of the
offence, they are expressly preserved
by s 21A(1)(c)
Ultimately, all of
the above factors must be considered as part of "a complex of inter-related
considerations" ( R v Gallagher (1991) 23 NSWLR 220 (at 228)).
[11] Frankly I do not understand how on the established principles it could
be determined that the pleas of guilty for the offences
for which the respondent
was sentenced were early pleas and that they justified a discount of 25 per
cent. There is no utility in
a plea of guilty that has not been forthcoming. If
the accused is not prepared to plead guilty until the Crown takes some course,
then so be it. But if by withholding the plea the offender achieved the result
he wanted, I do not understand why he should receive
further favourable
treatment on the basis that the plea of guilty had utilitarian value when it did
not. Rarely, if ever, will the
reason why the accused has withheld the plea of
guilty be a relevant matter in determining the utilitarian discount. Where it
has
been used as a bargaining tool in order to achieve a favourable outcome from
the Crown in respect of some other charge, I do not
understand that this
circumstance can excuse the delay or provides a basis for asserting that the
plea was made at the first reasonable
opportunity.
[12] I accept that there may be exceptional cases, where as a matter of
fairness to the offender, a discount will be given even though
there was no
utilitarian value in it. One such situation that has been recognised is where
the Crown rejects the accused's plea of
guilty to manslaughter and the accused
is later acquitted of murder but convicted of manslaughter after trial: R v
Oinonen [1999] NSWCCA 310; R v Cardoso [2003] NSWCCA 15. But in R
v Harmouche [2005] NSWCCA 398 Hulme J, with whom Sully J and Latham J
agreed, wrote:
[38] Undoubtedly, the Respondent on the evidence before, and findings of,
Judge Delaney made out an impressive subjective case. He
had the factors of a
plea, delay and youth arguing for a lesser penalty than would have been
appropriate in their absence and was
also entitled to have taken into account
134 days, i.e. something over 4 months, pre-sentence custody.
[39] That said, the 25% discount for the Respondent's plea was unduly
generous. In giving it his Honour seems to have made a mistake
commonly seen in
this Court that because a plea was entered at the earliest opportunity (commonly
shortly after the Crown reduces
a charge) an offender is entitled to that
discount. Such an approach is to misread R v Thompson and Houlton (2000) 49
NSWLR 383 and
to ignore the rationale for a discount of that degree. The Chief
Justice made it clear, at [154-5], that the rationale for a 25%
discount was the
extent of the utilitarian benefit and the complexity of evidence gathering and
of any trial which was avoided. Certainly
his Honour made reference to a plea
being entered at the earliest opportunity but that was in the context to which I
have referred
and where his Honour was obviously contemplating the committal
stage of criminal proceedings where the community would be saved the
costs
associated with prosecution of the case from (the beginning of) that stage.
40 That what I have said correctly reflects what the Chief Justice said
derives support from observations of Hodgson JA, with whose
remarks Barr J
agreed, in R v Dib [2003] NSWCCA 117 where, dealing with a complaint that only
16.7% had been allowed in the case of a plea entered in response to a lesser
charge than
originally preferred, his Honour said, at [5 - 6]:
"If a plea is entered a long time after a person is first charged, but at a
time when a lesser charge is substituted for a greater
charge, the advantages to
the administration of justice are less, even though the plea may have been made
at the earliest opportunity.
There is in any event no entitlement to a 25%
discount; and the fact that in this situation there are less advantages to the
administration
of justice can justify a smaller discount.
This approach
may mean that in some cases an offender may obtain a lower discount just because
the prosecuting authorities initially
brought a greater charge than that
ultimately pursued, so that the delay in the plea of guilty was not the
offender's fault. But
this is consistent with the nature of the discount as
being at least in part a recognition of practical advantages, and not merely
a
recognition of mitigation of culpability."
[41] I myself would go further.
Albeit the extent of any discount is a matter in which a sentencing judge has
some discretion - although
as R v Thompson and Houlton at [159] makes clear, one
subject to appellate review - where the rationale for a discount as high as
25%
does not exist, a discount of that degree should not be given.
The
prosecutor relies also upon the reasoning of Hodgkinson JA in R v Dib
[2003] NSWCCA 117 at [5] and [6]:
[5] If a plea is entered a long time after a person is first charged, but at
a time when a lesser charge is substituted for a greater
charge, the advantages
to the administration of justice are less, even though the plea may have been
made at the earliest opportunity.
There is in any event no entitlement to a 25%
discount; and the fact that in this situation there are less advantages to the
administration
of justice can justify a smaller discount.
[6] This approach may mean that in some cases an offender may obtain a lower
discount just because the prosecuting authorities initially
brought a greater
charge than that ultimately pursued, so that the delay in the plea of guilty was
not the offender's fault. But
this is consistent with the nature of the discount
as being at least in part a recognition of practical advantages, and not merely
a recognition of mitigation of culpability.
... restricted to pleas entered at the earliest opportunity and should rarely
be given after a matter has been set down for trial.
In Cameron (2002)
187 ALR 65 (24.2.02) the High Court however held when a defendant accepts
responsibility for a crime and shows a willingness
to facilitate the course of
justice, the Court in the assessment of the value of such a circumstance must
consider ". . . whether
the plea was entered at the first reasonable
opportunity". The effect of Cameron on the guideline judgment in
Thomson was considered by the Court of Criminal Appeal in R v Sharma
[2002] NSWCCA 142; (2002) 54 NSWLR 300. The court held that the reasoning in Cameron was
not applicable in New South Wales because the common law principles enunciated
there have been modified by statute. It held s22 of the Crimes (Sentencing
Procedure) Act 1999, renders it mandatory that a sentencing judge in New
South Wales take into account both "the fact" of the plea of guilty and "when"
it was made. Further, if a lesser penalty is not to be imposed then the Court
must give reasons. The Chief Justice held in Sharma the statutory
reference to "the fact" of the plea as the matter required to be considered,
does not direct attention to the subjective
intention of the person pleading
guilty. Nor is the element of timing, reflected in the reference to "when" a
plea was made, a reference
only to subjective elements. Thus the Court must take
the plea into account even if there is no subjective intention to "facilitate
the administration of justice", as referred to in Cameron . The Chief
Justice concluded that the guideline judgment of Thomson is still of full
force and effect and must be followed.
[36] The provisions of the Fines Act 1996 requiring the Court to give
consideration to the means of a defendant to pay a fine also extends to the
question of costs (see the
Full Bench in WorkCover Authority (Inspector
Yeung) v Wilson (t/as Wilson's Tree Service) (2005) 143 IR I87 at para [122]
et seq ). In that case the Full Bench accepted the proposition that
normally, a successful litigant, including a prosecutor in occupational
health
and safety prosecutions, is entitled to his or her costs but that, nevertheless,
the Court possessed a wide discretion in
relation to the issue of costs. In
applying the provisions of the Fines Act and considering the means of the
defendant to pay the fine and the costs, adjustments to the reasonable costs
sought may be required.
At the request of the Court, the prosecutor, following
the completion of argument, indicated that the approximate total professional
costs and disbursements in each matter were as follows: in the matter of Mr
Hall, approximately $10,000 and in the matter of Mr Quinn,
approximately
$11,000. It should be noted, however, that there was considerable overlap in the
evidence in both cases with the specific
role of each defendant being the main
difference. As pointed out by the Full Bench in Wilson, the costs should
not be disproportionate to the fine. Bearing those principles in mind and the
evidence as to the means of each defendant,
the Court determines that a just and
reasonable order for costs in the case of Mr Quinn would be $2,000 and in Mr
Hall's case, $1,000.
[37] One final matter requires brief mention. The prosecutor submitted that,
in the present proceedings, the Court should not follow
the course I adopted in
Inspector Batty v Brian John Goldsmith [2009] NSWIRComm 72 . In that
case, the defendant had only recently been declared bankrupt and the evidence
supported a conclusion that he had an ongoing
incapacity to pay any fine. In
applying the provisions of the Fines Act the Court reduced the penalty to
be imposed but also took the step of deferring the payment of that penalty until
the expiration of
the nominal term of the defendant's bankruptcy. In the present
proceedings the prosecutor urged that course should not be adopted
in these
cases and further submitted that there was no legislative support permitting the
Court to suspend or defer the payment of
the fine. In the present proceedings it
appears the nominal term of bankruptcy for Mr Hall will expire within the next
few months
and Mr Quinn's nominal expiry date is in 2011: they have prospects of
being discharged from their bankruptcy at that time. Those
facts and the
different circumstances found in Goldsmith would lead the Court to
conclude that the approach adopted in Goldsmith is not necessarily
appropriate in the present matter and indeed, neither defendant sought such an
order. Because of the general difficulty
of dealing with bankrupt defendants in
sentencing under the Occupational Health and Safety Act , it is of some
importance to clarify the basis upon which the Court acted in Goldsmith.
It may be accepted that there is no precise statutory provision permitting
the suspension of payment of a fine although it might be
said that a Court
could, as an integral part of the sentencing process, defer the issue of orders
until such time as the defendant
was discharged from bankruptcy and was able to
return to some normality in relation to their financial affairs. It may be
possible
for the Court to lay down a regime for the payment of a fine beginning
at a future date. Quite apart from these possibilities, it
should be understood
that, in the absence of a statutory limitation, a superior court of record (such
as this Court) even though
of limited jurisdiction, has power to do all things
necessary to give effect to that jurisdiction which is conferred upon it. That
approach is consistent with the judgments in Philip Morris Inc and anor v
Adam P Brown Male Fashions Pty Ltd and ors (1981) 148 CLR 457 and
National Parks and Wildlife Service and anor v Stables Perisher Pty Ltd
(1990) 20 NSWLR 573 although these cases were decided in a different
context. Ultimately, the Court must impose a sentence that is just and
appropriate
having regard to all the factors, including the defendants' capacity
to pay a fine. The imposition of a fine that is crushing in
its effect on a
defendant does not advance the cause of justice or assist in obtaining its
numerous objectives. In view of the course
proposed to be taken by the Court in
the current matters, this issue need not be fully considered for present
purposes although it
should be noted that in WorkCover Authority of NSW v
Anywhere Tower Cranes Pty Ltd and ors (20070 NSWIRComm 44, in the context of
applying the Fines Act to a bankrupt defendant, Marks J
contemplated that the payment of the monetary penalty would occur after
discharge from bankruptcy. For present purposes, these matters
need not be
considered further but are mentioned in view of the issues raised by counsel for
the prosecutor and the general importance
of the subject matter.
Orders
1. In Matter No IRC 1772 of 2009, I find the defendant guilty of the offence
as charged.
2. The defendant is fined in the sum of $15,000 with a moiety to WorkCover
Authority of New South Wales.
3. The defendant to pay the costs of the prosecutor. There has been no
agreement between the parties as to the quantification of the
costs. I will hear
the parties on this issue in the event no agreement can be reached. Leave to
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2011/119.html