![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 2 August 2010
NEW SOUTH WALES INDUSTRIAL RELATIONS COMMISSION
CITATION :
Inspector Anthony Nicholson (WorkCover Authority of New South Wales) v
Bradley Tracey and Others [2010] NSWIRComm 106
FILE NUMBER(S):
2230 of 2007
2231 of 2007
2232 of 2007
2233
HEARING DATE(S):
9, 10 and 11 December 2009
DATE OF JUDGMENT:
29 July 2010
PARTIES:
Inspector Anthony Nicholson (WorkCover Authority of New South
Wales) (Prosecutor)
Bradley Tracey (1st Defendant)
Bradley Tracey
Scaffolding Services Pty Ltd [ACN 112 194 528] (2nd Defendant)
Delta Pty
Limited [ACN 007 069 794] (3rd Defendant)
Waco Kwikform Limited [ACN 002 835
396] (4th Defendant)
CORAM:
Backman J
CATCHWORDS:
Occupational health and safety - Occupational Health and Safety Act 2000 -
demolition site - fall from height through open penetration occasioning fatal
injury - risk to safety - objective factors considered
- subjective factors
considered - respective roles - victim impact statements - penalties -
orders
LEGAL REPRESENTATIVES
Mr R Reitano of counsel
WorkCover
Authority of New South Wales
(Mr G Diggins)
Mr B Tracey (1st and 2nd
Defendants)
(Self-represented)
Mr B Hodgkinson SC (3rd
Defendant)
HWL Ebsworth
(Ms Sonya Kroon)
Ms W Thompson of counsel
(4th Defendant)
Freehills
(Mr M Bastick)
CASES CITED:
Inspector
Dimitri Barlas v C & J Carpentry & Construction Pty Ltd and Others
[2009] NSWIRComm 127
Inspector Dubois v Masters Civil Pty Ltd and Anor [2006]
NSWIRComm 180
Inspector Glass v Foamex Polystyrene Pty Ltd [2004] NSWIRComm
100
Inspector Julie Townsend v Austruc Constructions Limited [2007] NSWIRComm
321
Inspector Stephen Cooper v Franklin Alden Coveney and Another [2008]
NSWIRComm 80
Mark Andrew Bollen (1998) 99 A Crim R 510
Masters Civil Pty
Ltd v WorkCover Authority (NSW) (Inspector Dubois) (2006) 158 IR 10
Rodney
Morrison v Hunter Quarries Pty Limited and Another [2009] NSWIRComm
179
Salvatore Previtera (1997) 94 A Crim R 76
Veen v The Queen (No 2)
[1988] HCA 14; (1988) 164 CLR 465
LEGISLATION CITED:
Crimes (Sentencing Procedure)
Act 1999
Occupational Health and Safety Act 2000
TEXTS CITED:
JUDGMENT:
INDUSTRIAL COURT OF NEW SOUTH WALES
CORAM: Backman J
Thursday, 29 July 2010
Matter No IRC 2230 of 2007
Inspector Anthony
Nicholson (WorkCover Authority of New South Wales) v Bradley
Tracey
Prosecution pursuant to section 8(1) & section 26(1) of
the Occupational Health and Safety Act 2000
Matter No IRC 2231
of 2007
Inspector Anthony Nicholson (WorkCover Authority of New
South Wales) v Bradley Tracey Scaffolding Services Pty Ltd [ACN 112 194
528]
Prosecution pursuant to section 8(1) of the Occupational
Health and Safety Act 2000
Matter No IRC 2232 of
2007
Inspector Anthony Nicholson (WorkCover Authority of New South
Wales) v Delta Pty Limited
Prosecution pursuant to section 8(2) of
the Occupational Health and Safety Act 2000
Matter No IRC 2233
of 2007
Inspector Anthony Nicholson (WorkCover Authority of New
South Wales) v Waco Kwikform Limited [ACN 002 835 396]
Prosecution
pursuant to section 8(2) of the Occupational Health and Safety Act
2000
JUDGMENT OF THE COURT
[2010] NSWIRComm
106
1 Delta Pty Limited (Delta) pleaded guilty to an offence under s 8(2) of
the Occupational Health and Safety Act 2000 (the 2000 Act). Waco
Kwikform Limited (Waco) pleaded guilty to an offence under s 8(2) of the 2000
Act. Bradley Tracey Scaffolding
Services Pty Ltd (BTSS) pleaded guilty to an
offence under s 8(1) of the 2000 Act and Bradley Tracey (Mr Tracey), a director
of BTSS,
pleaded guilty to an offence under s 8(1) and s 26(1) of the 2000 Act.
Each offence to which the defendants pleaded guilty concerns
an incident which
occurred on 5 January 2006 at a site in Sussex Street Sydney at which a building
was to be demolished.
2 At the parties' request, the sentence hearings proceeded "back to back"
with Delta's matter being heard first, followed by Waco
and then BTSS and Mr
Tracey (heard together).
Delta Pty Limited
3 At the time of the offence, Delta was
the principal contractor at the site. It contracted with Energy Australia for
the demolition
of a building known as "Lumley House". The building was of
concrete construction with post-tensioned slabs and pre-tensioned beams.
4 Scaffolding was required to be installed around the building as part of
the demolition process. Delta, as was its practice, sub-contracted
the
scaffolding work. The sub-contractor selected by Delta for this particular site
was Waco. Waco was to provide scaffolding equipment
and scaffold labour
services for the demolition. The contract between the two parties provided that
all materials handling (including
the progressive removal of scaffold as the
demolition progressed) was Waco's responsibility.
5 Waco in turn sub-contracted to BTSS for the provision of labour to
erect and dismantle the scaffolding around the building.
6 BTSS employed Paul Hughes (Mr Hughes) and William Issell (Mr Issell) as
scaffolders to work at the site. Both held advance level
certificates of
competency as scaffolders. Mr Issell also held a Class 1 riggers "ticket".
Delta employed Craig Wallace (Mr Wallace)
as the foreman at the site for the
demolition work. He had over 20 years experience in demolition work and held
Demolition Supervision
Certificates I and II, as well as a riggers
certificate.
7 Mr Issell started work at the site on 21 November 2005. That morning
he was given a site induction by Delta which included a safety
talk. Mr Hughes
started work on the day of the incident, 5 January 2006. He was inducted to the
site by Mr Wallace. The site induction
included occupational health and safety
matters, acknowledged by Mr Hughes in his Site Induction Form which he signed.
Mr Wallace
also conducted a Tool Box talk on 5 January 2006 which was attended
by Mr Hughes and which concerned Delta's Safe Work Method Statement
(SWMS) dated
6 December 2005. Mr Hughes signed a "Record of Tool Box Talk" form. The day of
the incident was the first day Messrs
Hughes and Issell had worked together.
The work
8 The nature of the work undertaken at the site has been conveniently set
out in the agreed facts as follows:
The method adopted for the demolition of the building involved the demolition of each level of the building in turn commencing at level 9 (which was the roof). The concrete slabs comprising the floor/ceiling of each level were to be hammered out by using 2 excavators with hydraulic hammers/munchers. The machines were then to move to the floor below to hammer out the slab and supporting beams and columns. A protective hoarding was erected around the perimeter of the site. Along the Sussex Street frontage of the building a protective gantry was erected. A heavy-duty scaffold was erected between the gantry and the building along the Sussex Street facade and extending around the building with the exception of an area on the southern side. This area was left open to facilitate the removal of demolition material from the bottom of the to-be-decommissioned lift shaft which was to act as a waste chute. As each level of the building was demolished it would be necessary for the scaffolding to be dismantled to the level of the building remaining standing and for the boards which had formed the upper working deck of the scaffolding to be rotated to create a new working deck at a lower level. The dimensions of the scaffolding to be constructed were 81.0 metres long x 1.20 metres wide x 33.0 metres high.
As at 5 January 2006 the task of installing scaffolding around the building at the site had been completed. A hand-over of the scaffolding to the defendant had occurred on 20 December 2005 and a handover certificate was issued by Waco to the defendant on that date. Scaffolding had been installed up to level 9 which represented the roof of the building. Stairs were set up in the south-western corner of the building.
Events
of 5 January 2006
9 On 5 January 2006, Messrs Hughes and Issell were clearing up excess
scaffolding components and stacking and lowering the components
to the ground by
means of an electric winch. They were otherwise on stand-by waiting for the
roof to be demolished after which they
were to dismantle the scaffolding in
accordance with the method adopted for the demolition process. The electric
winch had been
installed for the purpose of lowering the scaffolding components
to the ground as each level of scaffolding was dismantled following
the
demolition of the corresponding floor of the building. Delta was aware of the
intended use of the electric winch, however, it
did not conduct a risk
assessment with regard to its installation and operation.
10 The use of the winch for the stated purpose was the subject of
discussion at the tool box talk conducted by Mr Wallace on the morning
of 5
January 2006.
11 Mr Issell, in a WorkCover interview conducted on 13 January 2006,
explained the extent of his instruction at the tool box meeting
with regard to
the electric winch. He said the winch was to be used to get the material down
with the winch, "through the ... penetration".
In a later interview he
explained that the tool box meeting occurred on the roof of the building with Mr
Hughes present.
12 The winch had been operated by Messrs Hughes and Issell and Mr Tracey
earlier in the morning on 5 January 2006, but had developed
a problem. Mr
Tracey took it away for inspection. Later, he returned the winch to both men
with instructions to re-install and
operate it.
13 Shortly after Messrs Hughes and Issell commenced to install the winch,
Mr Hughes fell through an open penetration 33 metres to
the ground below. He
was fatally injured.
14 Mr Issell, who witnessed the incident, described it in his interview
as follows:
I climbed up the scaffold on to the board. Paul was on the ground, Paul passed the winch up the inside of the scaffold, passed it to me. I had hold of the winch, he climbed up the other side of the scaffold and he assisted me putting the winch on to the standard. As we done that we both climbed down either side of the scaffold. I climbed down this side, Paul climbed down the other side. I've turned around and Paul has just stepped straight in to that penetration.
15 According to the agreed facts,
at the time of the incident, no ladder, stairway or other means of access to the
two-plank working
platform was in place for use by Messrs Hughes and Issell when
installing the winch. According to Mr Tracey, BTSS did not have a
ladder at the
site, but Delta had ladders on-site which were available for use by BTSS.
16 Delta's OHS&R Management Plan for the site prohibited the climbing
of scaffold standards.
17 The recommended means of gaining access to working platforms is set
out in Clause 8.9 of the Australian/New Zealand Standard 4756:1995
Guidelines
for Scaffolding (AS/NZS4576:1995) which states:
Common means of access and egress include existing floor levels, permanently installed platforms, ramps, stairways, ladders personnel hoists, temporary access ways, temporary stair systems and portable ladders.
18 The open penetration through which
Mr Hughes fell had been created by him, and Mr Issell, by removing two of five
scaffolding planks
from one bay of the scaffolding deck on level 9 of the
building. The dimensions of the penetration were approximately 950 mm in
length
and 500 mm wide. As I read the agreed facts, these dimensions were created by
the removal of the two scaffolding planks and
the laying of six wooden planks
across the remaining three scaffolding planks. The six wooden planks were not
secured by any means.
The open penetration was initially barricaded off by
means of a mid-rail which was installed around it. The obvious purpose of
this
latter measure was to prevent access to the open penetration. Directly
underneath the penetration was another open penetration
on level 8 of the
building. This second penetration was much larger, being 2.8 metres long and
1.2 metres wide. It had been created
by the removal of all the scaffolding
planks and covering plywood from a corresponding bay of the working deck on
level 8.
19 Giacomo Pavone, Delta's site supervisor, said in a WorkCover interview
that he saw the scaffolding boarded up and the "handrail"
around it. His
observations were made earlier in the day well before the incident. According
to the prosecutor Mr Pavone's observations
failed to include whether he checked
that the boards were in fact secured, the implication being that they were not
and could be
readily removed, indeed needed to be removed so that the winch
could be lowered through the penetration. Delta, in reply, contended
that the
fact that the "covers" were there, whether secured or not, was not relevant and
in any event could not be determined. The
covers were there when Mr Pavone made
his observations which meant there was no open penetration through which someone
(or something)
could fall.
20 The evidence, in my view, on the issue, putting aside considerations
as to relevance, does not stand for any proposition other
than when Mr Pavone
inspected the boards they did in fact "cover" the penetration on level 9 at that
time but were otherwise not
secured. This is entirely consistent with the
agreed facts.
21 It may be convenient to comment on one further issue which was raised
by Delta during the proceedings. The issue arose from the
agreed facts which
record that the post mortem report for Mr Hughes showed a blood alcohol level of
0.103g/100ml. The prosecutor
contended that the presence of alcohol in Mr
Hughes' bloodstream was irrelevant because the offence, "could have occurred
irrespective
of whether alcohol was found in the toxicology report". I did not
understand Delta, however, to be submitting that it was in any
way a
contributing factor to the nature and quality of the offence. The following
exchange between the Bench and Mr Hodgkinson,
SC, counsel for Delta, illustrates
this:
HER HONOUR: What are you saying the court should make of that evidence?
HODGKINSON: Your Honour can only make of that evidence that there is a factor of alcohol. There is no evidence to which I can point, nor do I, to say that definitely as a consequence of alcohol this incident happened and without alcohol; I don't put anything of that kind. It is but a factor.
22 Given these matters, the Court
intends to accord no weight in the sentencing process to the fact that Mr Hughes
had a blood alcohol
level of 0.103g/100ml, at the time of the incident.
Systems of work in place prior to offence
23 As the agreed facts demonstrate, Delta had a number of systems and
procedures in place at the site devised and formulated with
safety
considerations in mind. Mr Hughes and Mr Issell both received site specific
instructions. A tool box talk was held by Mr
Wallace on the morning of the
incident, attended by Mr Hughes, which focused on Delta's SWMS. Mr Wallace was
a highly qualified
and experienced foreman specialising in demolition work.
24 Raelene Margaret Murphy, the Chief Executive Officer of the Delta
Group of companies, provided more details in her affidavit of
the systems and
procedures specifically developed for, and implemented, at the site.
25 The "site team" which was assembled at some stage in or around
November 2005, included Michelle Davies, Project Manager, Mr Wallace,
site
foreman, and Jim Pavone, Operations Supervisor.
26 Ms Davies was responsible for preparation of documentation pertaining
to the site such as engineering plans, occupational health
and safety management
plans and contract administration. She also acted as a liaison to the
operational staff, Mr Wallace and Mr
Pavone. Mr Wallace's role at the site and
his qualifications and experience have been earlier referred to. Mr Pavone's
role was
that of supervisor of the site and foreman on Delta's sites within New
South Wales. He also held demolition certificates, as well
as certificates for
hoist, excavation, forklifts, asbestos and bobcats. He attended the site each
day to support Mr Wallace as Delta's
site foreman. His practice was to "walk
the site" in order to oversee the project.
27 The site team was responsible for developing the safety documentation
for the project. Ms Davies developed the OH&S Management
Plan for the site
as well as the SWMS, risk assessments and revisions. Ms Davies consulted with
the other members of the site team
when preparing the documentation.
28 The occupational health and safety documentation prepared for the site
comprised the following:
(a) the Delta OHS & R Management Plan dated 15 June 2005;
(b) Safe Work Method Statement for Truck Loading, Ingress and Egress dated 15 June 2005;
(c) Site Specific Risk Assessment dated 17 October 2005;
(d) Traffic Management Plan dated November 2005;
(e) the Demolition Work Plan dated 25 November 2005;
(f) the OH&S Management Plan dated 25 November 2005;
(g) the Safe Work Method Statement for Demolition and Bulk Excavation dated 6 December 2005;
(h) Site Specific Safe Work Method Statement for structural slab and beam demolition dated 21 December 2005;
(i) Site Specific Safe Work Method Statement 03 for slab and beam demolition (undated).
29 Prior to the preparation of the safety documentation outlined in
sub-paragraphs (c) to (i) above, the "demolition methodology"
was settled upon
by the site team in consultation with Delta's consulting engineers, Grasso
Consulting Engineers Pty Limited (Grasso).
Grasso also provided and reviewed
Delta's SWMS dated 6 December 2005, and produced an engineer's certificate in
that respect on
8 December 2005.
30 Delta also prepared Site Safety Rules which addressed various risks
including that of "persons falling" from scaffold. Of particular
relevance in
the Site Safety Rules were the following items:
"Guard rails
· Openings in ground,
holes and open edges at height which present a fall hazard MUST be fitted with
guardrails or handrails.
· ...
· Any handrail or barrier to be removed to carry out work, MUST only
be done with the supervisors approval or be replaced before
leaving the work
area.
"Persons falling
· "Most serious
injuries in this industry result from persons falling from heights. Therefore,
extreme care must be taken when
working aloft.
· Where there is a risk of fall, adequate precautions must be taken
to prevent such fall.
· Report all openings or missing railings so they can be
protected.
· Wherever necessary, safety harnesses or lifelines should be
worn.
Scaffold
· Access is to be provided
to ALL scaffolds and platforms and be used as such.
· Climbing of scaffold standards is not permitted.
Occupational Health and Safety Rules
... 10. All openings in floors are to be adequately guarded or covered.
...
All working platforms, hoists and scaffolds must comply and be securely tied at all times.
...
16. Guard rails must be provided where necessary and employees must not be permitted to remove these barriers without approval.
...
22. do not allow any workmate to work in an unsafe manner."
31 Delta's Site Specific Risk
Assessment dated 17 October 2005 included penetration as an identified hazard,
as well as working at
heights. With regard to those matters the document
provided:
|
Identified Hazard
|
Risk
Category
|
Potential Outcomes
|
Mitigative Measures/Controls
|
Person Responsible
|
|
Working at height (near leading edges, on roofs, scaffold, platform,
ladders etc)
|
1, 2
|
Fall from height
|
Erect fence panels/scaffolding where possible to remove fall hazard
|
Craig Wallace
|
|
|
|
|
Where fence/scaffold is used do not remove or tamper with fencing,
handrails etc.
|
All Workers
|
|
|
|
|
Use harnesses only as a last resort. Where harnesses are used, ensure they
have been inspected by a licensed rigger and that they
are anchored securely by
a licensed rigger.
|
|
|
...
|
...
|
...
|
...
|
...
|
|
|
|
|
Only use correctly install platforms/decks - do not climb on scaffold
|
All Workers
|
|
|
|
|
...
|
|
|
|
|
|
Wear harnesses where manufacturers recommendations indicate they should be
worn
|
All Workers
|
|
Penetrations
|
1, 2
|
Fall through penetration or materials falling through penetration
|
Ensure penetrations are covered and that cover is securely fixed down
|
All Workers
|
|
|
|
|
Where personnel falling is a risk erect fence panels around penetration as
well as covering it
|
All Workers
|
|
Penetrations
|
1, 2
|
Fall through penetration or materials falling through penetration
|
Ensure penetrations are covered and that cover is securely fixed down
|
All Workers
|
|
|
|
|
Where personnel falling is a risk erect fence panels around penetration as
well as covering it
|
All Workers
|
32 Delta's safety systems reveal an impressive
and comprehensive set of polices and procedures which were specifically designed
for
application at the site. Nevertheless, the systems were also deficient in
some respects, particularly with regard to their implementation.
Notwithstanding the prohibition in the Site Safety Rules, for example, against
climbing scaffold standards, this is precisely what
Messrs Hughes and Issell
were doing immediately prior to the incident. Although Delta's site specific
risk assessment identified
penetrations as a hazard and directed that
penetrations be covered and the covers secured, this is not, in fact, what
occurred with
regard to the penetration created by Mr Hughes and Mr Issell on
level 9.
33 None of the safety procedures devised appeared to incorporate measures
to ensure the safety of workers utilising an electric winch
to lower the
scaffolding components. According to the agreed facts, no SWMS existed for the
"winch installation task" performed
by Messrs Hughes and Issell and no site
specific risk assessment was carried out for the installation of the winch.
34 Also, according to the agreed facts, other mechanical devices existed
for lowering scaffolding components. These included scaffold
jib cranes and
tonne cranes which were recommended acceptable means for lowering scaffolding
components when "handballing" or "chaining"
(a gang of workers forming a human
chain to pass equipment to the other) was not practicable. After 5 January
2006, a crane was
in fact used to lower the components placed in pallets.
35 Delta had two supervisors on the site on 5 January 2006. One, Frank
Sinko, was working on the ground. The other supervisor, Mr
Wallace, was working
on the roof area about 30 to 35 metres away from Messrs Hughes and Issell. Mr
Wallace did not see the two men
placing on, or removing from, the working
platform, the planks or boards for the purpose of attaching the winch. He also
did not
observe what fall arrest devices Messrs Hughes and Issell had in place.
Waco had also issued a SWMS which was adopted by the BTSS
employees. Mr
Wallace's responsibilities at the site included ensuring that sub-contractors
followed documentation SWMS. Despite
this, Mr Wallace, in his WorkCover
interview, was unsure about the contents of the Waco SWMS with regard to the
scaling of scaffolding
and scaffolding standards. He also said that he was not
present when Mr Tracey conducted a tool box talk with Messrs Hughes and
Issell
regarding the installation of the winch.
36 Neither Mr Hughes, nor Mr Issell were wearing safety harnesses or
other fall arrest devices at the time of the incident, even though
two harnesses
belonging to Delta were located shortly after the incident on the scaffolding
deck in an adjoining bay approximately
one metre from the open penetration on
level 9.
37 Notwithstanding the deficiencies in Delta's safety systems, Delta
obviously took its occupational health and safety commitments
at the site very
seriously as demonstrated by the impressive and very comprehensive systems it
had devised specifically for implementation
at the site. This will be taken
into account in Delta's favour in mitigation of the objective seriousness of the
offence and will
be reflected in the penalty to be imposed.
Other objective factors
38 The risk to the safety of Messrs Hughes and Issell, which was
characterised by the prosecutor as a risk of falling through an open
penetration
on a building site, was an obvious one in the circumstances and well-known to
Delta as evidenced by its extensive safety
regime which incorporated multiple
references to the hazards associated with working near open penetrations.
Delta, in fact, conceded
during oral hearing that the risk of falling through a
penetration, "is not an unknown or remote risk". There can be little doubt
that
the measures in place to prohibit Mr Hughes and Mr Issell at the time of the
accident were ineffective, consisting as they did
of a handrail around the
penetration and a transom attached to the wire mesh of the handrail.
39 There were certainly available alternative measures in relation to
which the task of lowering scaffolding components could have
been accomplished
safely. These alternative measures have been earlier referred to and need no
repetition. There were harnesses
available only one metre away from the site of
the penetration. Why they were not utilised by Messrs Hughes and Issell has not
been
explained in the evidence. The mere fact they were located in the near
vicinity of the open penetration, in a different bay, would
not enable the Court
to conclude that they had been made available to the two men for their use, or
were otherwise brought to their
attention. With regard to the use of a crane (a
procedure which was utilised for the task after the incident) the agreed facts
refer
to a quotation submitted to Waco prior to the accident by BTSS which
allowed a sum of $12,000 for cranage. This suggests that the
cost of utilising
a crane for the task would not have been prohibitive.
40 The likely consequences of the breach were very serious, a matter
tragically realised in the death of Mr Hughes. Mr Issell also
faced a likely
prospect of suffering fatal injuries by reason of his exposure to the risk to
his safety.
41 These matters in combination compel the conclusion that the offence
against Delta was objectively serious, although this must be
qualified by the
established existence of largely effective, extensive systems and procedures
specifically designed to ensure the
safety of all personnel at the site.
42 Delta has one prior conviction and therefore faces a maximum penalty
of $825,000.
43 General deterrence has real significance in these sentencing reasons.
The factual background involves risks to safety existing
within the demolition
industry, in particular risks arising, as here, from working at heights near
open penetrations. It is imperative,
given the nature of the industry that
employers be made aware of the importance of implementing appropriate measures
to ensure workers
can undertake their work in a safe working environment without
fear of injuries: see on these issues Inspector Dubois v Masters Civil Pty
Ltd and Anor [2006] NSWIRComm 180 at [15] (upheld on appeal in Masters
Civil Pty Ltd v WorkCover Authority (NSW) (Inspector Dubois) (2006) 158 IR
10; Inspector Julie Townsend v Austruc Constructions Limited [2007]
NSWIRComm 321; Inspector Dimitri Barlas v C & J Carpentry &
Construction Pty Ltd and Others [2009] NSWIRComm 127 at [16].
44 Specific deterrence is also relevant. Delta continues to work in the
industry, although the number of effective measures put in
place by Delta
following the offence will be taken into account in its favour when applying the
principle for the purposes of assessing
the appropriate penalty.
Subjective factors
45 Delta entered an early plea of guilty, a matter acknowledged by the
prosecutor. I propose therefore to assess an appropriate penalty
for the
utilitarian value of the offence at 25 per cent.
46 As a separate consideration from the utilitarian value of the plea,
Delta is also entitled to leniency in recognition of the remorse
shown by the
plea of guilty.
47 Delta also co-operated with WorkCover during its investigation into
the details of the accident, for example, by shutting down
the whole of the site
to facilitate the investigation, and by attending to the issue of improvement
notices.
48 Assistance was also provided by Delta to all workers who were on the
site on the day of the accident in the form of a counselling
session. Mr
Wallace, who was deeply affected by the accident, was permitted to take a
six-week leave of absence.
49 Delta has also shown good industrial citizenship by reason of its
position in its field of specialty as a leader in the industry.
It works
closely with the union movement on safety matters. It is only one of three
demolition contractors with Federal Safety
Commission accreditation. It has a
good reputation in the demolition industry as evidenced by the many large and
complex demolition
projects it has been contracted to carry out.
50 Delta also introduced a number of safety measures after the offence in
order to minimise the occurrence of all or any future risks
to safety arising at
its worksites. These measures have been set out in detail in Ms Murphy's
affidavit. They include, in summary,
the following (extracted from Ms Murphy's
affidavit):
Delta has implemented changes to its occupational health and safety systems and procedures with a view to putting measures in place to avoid any incident of a similar nature occurring again. Specifically, Delta has implemented the following areas of improvement:
(a) devoted more personnel resources to occupational health and safety, in particular dedicating personnel resources to particular States under the overall supervision of a National Occupational Health and Safety Manager;
(b) retained the services of an external consultant to advise and improve Delta's occupational health and safety systems and procedures. In 2008 Delta obtained accreditation for its occupational health and safety management system under AS/NZS 4801:2001 in New South Wales, Victoria and the Australian Capital Territory;
(c) implemented a formal system of site auditing to ensure compliance with safe work method statements;
(d) ensured that safe work method statements are prepared when there is any change of work methodology and improved consultation on safe work method statement preparation. Delta has also improved supervision and monitoring of subcontractors particularly regarding the adequacy of and compliance with safe work methods;
(e) improved on the notification and enforcement of Delta's drug and alcohol policy;
(f) since 2006, improved its Occupational Health and Safety Management Plan through a significant number of revisions. This has included implementation of those changes;
(g) since 2006, devoted more resources to the training of all employees nationwide to increase skills and improve the awareness of the importance of occupational health and safety.
51 Following the
accident, Delta also met with Waco to discuss safety concerns arising out of the
incident, in particular, the requirements
for task specific SWMS. Waco
subsequently prepared a supplementary SWMS in relation to which Delta ensured
all scaffolders received
on induction. Delta also re-inducted all its employees
into the supplementary Waco SWMS. Delta also hired a crane for the further
dismantling of the scaffolding.
52 Delta has also expressed contrition for the circumstances of the
offence. Ms Murphy stated that Delta management and its employees
were
"traumatised" by the accident. This, together with the post-offence measures
undertaken by Delta mentioned above, allows the
Court to also take this factor
into account in mitigation of penalty.
53 All of the subjective factors mentioned above will be taken into
account in mitigation of penalty.
54 The presence of a prior conviction disentitles Delta from receiving
leniency, normally granted to an offender not adversely recorded.
Victim Impact Statements
55 During the sentence proceedings, the Court received victim impact
statements from Mr Hughes' parents, Frank and Hetty Hughes, and
his brother,
Christopher Hughes. Christopher Hughes read his statement onto the record.
56 In accordance with the prevailing law, the Court may received the
statements but may not take them into account in determining
an appropriate
sentence: Salvatore Previtera (1997) 94 A Crim R 76; Mark Andrew
Bollen (1998) 99 A Crim R 510; Inspector Glass v Foamex Polystyrene Pty
Ltd [2004] NSWIRComm 100 at [43]; Rodney Morrison v Hunter Quarries Pty
Limited and Another [2009] NSWIRComm 179 at [304] to [322]. It was not
suggested by either party that the Court should receive the statements for any
wider purpose.
57 Mr Christopher Hughes' account on the record and the statements of Mr
and Mrs Hughes illustrate the dreadful impact of this tragedy
on a family. The
Court expresses its deepest sympathy to the Hughes family for the loss of a son
and brother.
Waco Kwikform Limited
58 I turn now to consider the offence with which Waco has been
charged.
59 The agreed facts provided in Waco substantially overlap with the
agreed facts in the matter of Delta. I therefore adopt in these
sentencing
reasons the agreed facts tendered in the proceedings against Delta, in so far as
they are the same facts set out in the
agreed facts document tendered against
Waco.
60 Waco contracted with Delta to supply the scaffolding equipment and
scaffold labour services for the demolition of the building.
It sub-contracted
BTSS to provide the labour to erect and dismantle the scaffolding at the
site.
61 As referred to earlier in Delta's sentencing reasons, it was the
intention of Mr Hughes and Mr Issell to use an electric winch
to lower
scaffolding components to the ground through an open penetration, created by
them, in the scaffolding working deck on level
9. According to the agreed facts
in Waco, Delta knew about and had approved the installation and operation of the
winch for the
stated purpose. Delta had earlier considered and decided against
the use of a crane. Delta did not conduct a risk assessment for
the
installation and operation of the winch, although its anticipated use had been
discussed at a tool box meeting on the morning
of the accident (5 January 2006)
conducted by Mr Wallace, Delta's site foreman. Delta had earlier used the winch
to raise gas welding
bottles and portions of steel.
62 According to the agreed facts, the open penetration was not barricaded
off (at the time of the accident) to prevent access. There
was therefore
nothing in place to prevent persons working in the near vicinity falling through
the penetration 33 metres to the ground.
Systems of work in place prior to the offence
63 Rodney Graham Mill, Executive General Manager of Waco, has set out in
an affidavit, Waco's systems and procedures formulated specifically
for use and
implementation at the site. It is convenient to extract certain parts of Mr
Mill's affidavit which serve to illustrate
the extent of those systems and
procedures in force at the site prior to the offence:
On 21 November 2005, Waco prepared and issued to BTS a safe work method statement in relation to the work being undertaken at the Site pursuant to the Subcontract Agreement (Waco 2005 SWMS).
I was involved in overseeing the preparation of the Waco 2005 SWMS, which had been prepared by Peter Pade (Mr Pade), who was the Sydney Branch OHS Manager at the time (Mr Pade is currently the National OHS Manager). Whilst I was aware of the provisions in the Waco 2005 SWMS, I was not involved in the process of adapting this safe work method statement to specific sites. This process was undertaken by Mr Pade in conjunction with the relevant sales representatives.
The purpose of the Waco 2005 SWMS was to provide subcontractors with an outline of the prescribed methods as to how Waco's scaffolding was to be safely erected and dismantled at specific sites, including in compliance with the relevant industry standards. The Waco 2005 SWMS (like all of Waco's safe work method statements to date) was designed so that subcontractors and Waco had scope (in consultation with each other) to adapt it to the subcontractors' specific requirements from one site/job to another in accordance with the relevant subcontract agreement with Waco. Throughout 2005, Waco had engaged BTS as a subcontractor on a number of occasions to undertake work in compliance with the Waco 2005 SWMS. Further, the Waco 2005 SWMS had been provided to subcontractors (including BTS) at an OHS conference more than six months prior to 5 January 2006. Accordingly, Mr Tracey (as the principal of BTS) would have been familiar with the Waco 2005 SWMS.
The Waco 2005 SWMS and the Subcontract Agreement required BTS and Waco to engage in consultation to prepare a specific safe work method statement. This would ordinarily involve the undertaking of an additional risk assessment and a tool box talk for any unique task/work requirement not covered by the Waco 2005 SWMS. This process of consultation would also apply with respect to the use of any plant (including winches) which was not referred to in the Waco 2005 SWMS.
The Waco 2005 SWMS did not include any references to penetrations (and in particular, the lowering of materials through a penetration) in relation to materials handling because the systems of work prescribed in the Waco 2005 SWMS with respect to the erection and dismantling of scaffolding did not require, contemplate or endorse the use of penetrations. The Waco 2005 SWMS prescribed the use of hoists, cranes and passing scaffolding by hand in relation to materials handling in this regard. For clarification, hoists as compared to winches are distinctly different forms of materials handling.
Similarly, the Waco 2005 SWMS did not include any references to winches (and in particular, the lowering of materials via winch) in relation to materials handling because the systems of work prescribed in the Waco 2005 SWMS with respect to the erection and dismantling of scaffolding id not require, contemplate or endorse the use of winches. If BTS wished to utilise a winch, it would be required to comply with the Subcontract Agreement.
In my experience, the use of winches to erect and dismantle scaffolding is not a work method which is used in the scaffolding industry. During my time at Waco, I have not observed any safe work method statements prepared by Waco and used in relation to a task which has required the use of penetrations or winches in the erection and dismantling of scaffolding.
64 Waco
also had in place at the site, prior to the offence, a regime for the induction
of sub-contractors and the monitoring of compliance
with its SWMS. This regime
is set out in the affidavit as follows:
Waco had systems in place so that it could determine whether the subcontractors engaged were appropriately experienced, inducted in relation to the safe use of its scaffolding and had all the necessary components to undertake the relevant work. The inductions were provided at two levels. OHS conferences were attended by principals/leading hands of subcontractors and Waco site/project supervisors and sales representatives (conducted on an annual basis). Inductions were also held at the sites for each project.
Site specific inductions were undertaken by ensuring that one of Waco's site/project supervisors (for example, Marc Reed) inducted the subcontractor (typically by inducting the subcontractor's principal and those scaffolders whom the subcontractor had selected to immediately start on the job at the site) into Waco's safe work method statement and then handing over that statement so that the subcontractor could then ensure that each of its employees who were to work on the particular site/project were in turn inducted into the statement.
After the induction on site, the site/project supervisor would attend the site on a regular periodic basis (approximately every two days) to facilitate the progression of scaffolding works at the site and to monitor the subcontractor's compliance with the safe work method statement in relation to the erection and dismantling of scaffolding by observing whether the scaffolders were erecting the scaffolding in compliance with the way in which the Waco had designed it. Under the system in place, a Waco site/project supervisor was not responsible for supervising on a day-to-day basis the work undertaken by subcontractors or subcontractor's employees. this responsibility of supervising the subcontractor's employees primarily resided with the principal of the subcontractor.
65 Mr Mill also sought to
emphasise in his affidavit that Waco only engaged experienced and reputable
sub-contractors to undertake
work. Waco's OHS Management Systems also set out
internal control guidelines which Waco representatives were required to follow
when engaging the services of contractors or sub-contractors.
66 As with Delta, Waco had impressive and extensive systems and
procedures specifically formulated and devised to ensure the work
at the site
would proceed safely and that workers at the site would not be exposed to risks
to their safety. There were, nevertheless,
deficiencies in its systems. These
have been set out in the agreed facts.
67 The Waco 2005 SWMS, for example, provided no instruction in relation
to the work method adopted for the task of securing the winch
by Messrs Hughes
and Issell on 5 January 2006. As Mr Mill sought to make clear in his affidavit,
Waco's SWMS did not refer to or
require the use of the winch for materials
handling. Instead, the SWMS prescribed other methods of materials handling such
as "passing
the scaffold by hand" (otherwise referred to as "chaining") or in
the alternative the use of a crane or hoist. Nevertheless, the
omission in the
Waco 2005 SWMS of any reference to a system of procedure for the use of the
winch amounts to a deficiency in its
systems. Waco acknowledged the deficiency
in the context that as a causative factor it was "more distant in time" than
other factors,
relevant to the immediate causes of the accident.
68 It has not been suggested in the evidence, as I apprehend it, however,
that the use of a winch per se as a means of lowering scaffolding
components is, or may be, hazardous. Rather, it was the absence of adequate
procedures with regard
to the work to be performed (using the winch) in the
vicinity of an open penetration that exposed the workers to a risk to safety.
In addition, as the agreed facts highlight, the open penetration was not
barricaded off to prevent access. There was nothing in
place to prevent a
person falling 33 metres to the ground.
69 Waco's 2005 SWMS also failed to identify the hazards posed by
penetration in scaffolding and the associated risk of falling from
the
scaffolding through penetrations. The risk of falls from heights through
penetrations is a well-known risk within the demolition
and construction
industries. The failure of Waco to address this matter in its 2005 SWMS reveals
another deficiency in an otherwise
comprehensive system. The charge to which
Waco entered its plea of guilty alleges in specific terms a failure on its part
to ensure
that the work performed by BTSS did not permit open penetrations
through which persons could fall while working at heights; and,
a failure to
ensure that BTSS provided and maintained a safe system for the securing of the
winch while it was being operated at
height.
70 Another particular of the charge to which Waco entered a plea of
guilty alleged a failure to provide adequate supervision "of the
winch being
undertaken by its subcontractor (BTSS) as was necessary to prevent falls from
heights".
71 According to the agreed facts, Waco did not provide any supervision of
the scaffolders working at the site or of the scaffolding
works. It is
instructive to set out in full the relevant extract of the agreed facts on this
issue. The reference to "BTS" in the
agreed facts is a reference to the
defendant, BTSS:
The defendant did not provide any supervision of the scaffolders working at the site nor of the scaffolding works.
The subcontract agreement between the defendant and BTS did not contain any provisions in relation to the supervision of BTS' scaffolders. The defendant's Site Safety Management Plan provided that "skilled and competent supervision will be provided for all work" without identifying which person(s) would in fact be required to provide such supervision. It was the defendant's understanding that BTS would provide direct supervision in relation to its own employees. The defendant's site/project supervisor, Marc Reed ("Reed"), visited the site on average every second day and remained on site for about an hour during such visits. Such visits were for the purpose of the coordination of material to and from the site rather than for the supervision of workers provided by BTS.
Reed, in his role as one of the defendant's site/project supervisors, was responsible for inducting BTS into the defendant's SWMS and then handing over that statement so that BTS would then ensure that each of its employees who were to work on the particular site/project were in turn inducted into the statement. Reed was not responsible for supervising the work undertaken by subcontractors or the subcontractor's employees. Reed's role did not include an occupational health and safety supervisory element. His role was to coordinate the transport of material to and from the site so as to make sure that equipment was at the site when needed and to observe whether the scaffolders were erecting the scaffolding in compliance with the way in which the defendant had designed it. Reed inducted Tracey and Tatham into the Waco 2005 SWMS at the site on 30 November 2005. BTS was then responsible under the subcontract agreement for ensuring Hughes and Issell were inducted into the Waco 2005 SWMS.
Prior to the incident on 5 January 2006, Reed was not aware of the specific terms of the subcontract agreement between BTS and the defendant but was aware of BTS's obligations in relation to compliance with the Waco 2005 SWMS.
The Waco 2005 SWMS and the subcontract agreement between BTS and the defendant required consultation, additional risk-assessment, the preparation of a specific SWMS and the conduct of a tool box talk for any unique task/work requirement not covered by the Waco 2005 SWMS.
Tracey, over the course of several conversations, mentioned to Reed and to the defendant's sales representative for the project, Andrew Skopin ("Skopin") that BTS was considering various materials handling options which BTS might employ at the site for the purpose of lowering material from the scaffolding, including the use of a crane, lift and winch, without specifically deciding upon one particular option or mentioning the use of penetrations. During these conversations, Tracey did not discuss with Reed or Skopin any alterations to the Waco 2005 SWMS in light of the possible use of a winch or otherwise.
As a result of discussions with Tracey, Reed and Skopin were aware that BTS was contemplating the possibility of using means other than a crane (as quoted) to lower scaffolding componentry. Skopin told BTS that if it implemented method other than the use of a crane, the defendant would still pay the amount allowed as the cost for the use of a crane as quoted by BTS. At no stage did Tracey discuss with Reed any changes to the Waco 2005 SWMS, including changes in relation to the system of work arising from the installation of a winch.
The defendant's national occupational health and safety manager, Peter Pade ("Pade"), did not visit the site prior to the incident on 5 January 2006. Pade was not responsible for visiting and inspecting sites or supervising subcontractors working at sites on which the defendant's scaffolding was being supplied. The defendant's Site Safety Management Plan provided that the defendant would establish an inspection program for the site. No such program was prepared in writing.
The defendant's Occupational Health and Safety Management Plan provided for the identification of an "OHS Supervisor on Site". No person is so identified. This document identified "Bradley Tracey" as the "Labour Company Supervisor".
72 It was submitted on Waco's
behalf that the consumption of alcohol by Mr Hughes and Mr Issell "may have"
affected their decision
to climb the scaffolding standards and if so this was a
mitigating factor in Waco's favour. For my part, I cannot agree. As the
agreed
facts reveal, Waco, through Mr Reed and Mr Skopin, was on notice that BTSS was
considering the use of a winch for the lowering
of scaffolding components.
Under the sub-contracting agreement between Waco and BTSS there was a
requirement that whenever a unique
task was identified requiring a specific work
procedure to be formulated (such as utilising the winch to lower the scaffolding
components),
BTSS would, in consultation with Waco, develop a specific SWMS for
the work. In the present case, this was not done. Moreover,
Messrs Hughes and
Issell had no immediate means of gaining access to the scaffolding standards.
As for the consumption of alcohol
by Messrs Hughes and Issell prior to
installing the winch, I have already made findings in relation to this issue in
Delta's sentencing reasons. I adopt those findings in these reasons. In
any event, Waco's submission was qualified that is, it was put
on the limited
basis that consumption of alcohol by the two workers "may have affected" their
decision (to climb the scaffolding
standards).
73 In addition, as the agreed facts record, the sub-contracting agreement
between Waco and BTSS required BTSS to induct and ensure
that its employees had
signed off on the Waco 2005 SWMS. Mr Hughes is not recorded as signing off on
the SWMS. This was because
the relevant document was not on site at the time Mr
Hughes was inducted. There had been an earlier break-in during the Christmas
period prior to 5 January 2006. Waco was apparently not aware of this situation
until after the accident.
74 Although the foregoing illustrates a number of deficiencies in Waco's
system, its system of safety overall was, as earlier acknowledged,
impressive,
comprehensive and specifically developed to ensure the safety of personnel at
the site. This finding will be taken into
account in Waco's favour in
mitigation of the objective seriousness of the offence and will be reflected in
the penalty to be imposed.
Other objective factors
75 Other objective factors relevant to the offence committed by Waco
substantially mirror those "other objective factors" which I
have earlier
considered in Delta's sentencing reasons. I adopt those considerations and
findings in these sentencing reasons. The
risk to the safety of Messrs Hughes
and Issell was the risk of falling through an open penetration at heights. This
risk was obvious
and in the circumstances well-known by Waco as its extensive
safety systems demonstrate by reason of, for example, the reference
in the 2005
SWMS to the risk of falling from scaffold. Moreover, given the number of cases
coming before this jurisdiction dealing
with falls from height through open
penetrations in the construction industry, and the demolition industry, it
cannot be seriously
contended that the risks associated with that hazard were
not known or were otherwise remote.
76 As identified in the proceedings against Delta, a number of simple,
alternative measures could have been utilised to lower the
scaffolding
components in a safe manner such as the use of appropriate personal protective
equipment. According to the agreed facts
tendered against Waco, neither Mr
Hughes or Mr Issell were wearing a safety harness or other fall arrest equipment
while climbing
the standards or while standing on the work platform or while
installing the winch. Following the accident, Waco issued a new SWMS
(the Waco
2006 SWMS) which specifically addressed the hazards posed by penetrations in
scaffolding, the associated risk of falling
from the scaffolding and the
necessary steps to control that risk. One measure identified in the Waco 2006
SWMS concerned workers
involved in railing off or covering and securing
penetrations. The step identified for those tasks required the workers to be
harnessed
with a lanyard. There is no reason advanced on behalf of Waco as to
why this measure could not have been implemented prior to the
offence.
77 As to the probable consequences of the breach, I adopt and apply my
findings on this issue in Delta's sentencing reasons.
78 Similarly, with regard to the principle of general deterrence which is
applicable to Waco's circumstances in the same way as it
is applicable to
Delta.
79 Specific deterrence is also relevant. Waco continues to work in the
industry. Like Delta, however, the extensive post-offence
measures it has put
in place will be taken into account in its favour when applying the principle
for the purposes of assessing penalty.
80 The objective factors in combination warrant a conclusion that the
offence against Waco was objectively serious, although qualified
by the extent
and effectiveness of its safety systems and procedures in place at the site
prior to the offence.
81 Waco has two prior convictions. It therefore faces a maximum penalty
of $825,000.
Subjective factors
82 Waco entered an early plea of guilty, a matter acknowledged by the
prosecutor. I propose therefore to assess an appropriate penalty
for the
utilitarian value of the offence at 25 per cent.
83 As a separate consideration from the utilitarian value of the plea,
Waco is also entitled to leniency in recognition of the remorse
shown by the
plea of guilty.
84 Waco also co-operated with WorkCover at all times during the course of
the investigation into the accident.
85 Waco has also expressed contrition for the circumstances of the
offence. Mr Mill stated that about eight staff from Waco attended
the funeral
of Mr Hughes. Mr Mill also expressed on behalf of Waco's management, its deep
regret for the accident. Following the
accident, Waco has taken steps to review
and improve its safety management systems in order to prevent a similar incident
from occurring
at its sites in NSW where scaffolding is used. These matters, in
combination allow the Court to take into account this factor in
mitigation of
penalty.
86 The post-accident measures implemented by Waco are set out in Mr
Mill's affidavit. They comprise the following steps taken immediately
following
the accident (extracted from the affidavit):
(a) undertaking an inspection of the scaffolding at the Site by assessing and confirming that the scaffolding was safe for continued use for the job;
(b) amending the Waco 2005 SWMS to expressly prohibit the creation of penetrations (as referred to above in paragraph 40), requiring the use of harnesses in prescribed circumstances and the use of one metre platforms when dismantling scaffolding (outlined further below in paragraph (f));
(c) re-inducting all scaffolders at the Site into the Waco 2006 SWMS;
(d) re-submitting the Waco 2006 SWMS to Delta (on the basis that Delta would also provide the Waco 2006 SWMS to WorkCover for the purposes of satisfying the requirements of the prohibition notice issued to Delta after the incident so that work could continue at the Site);
(e) undertaking (through Waco's site/project supervisors) closer monitoring of BTS's work practices at all relevant sites (and in particular, at the Site). Since 15 May 2006, Waco has not engaged BTS as a subcontractor;
(f) putting in place more stringent procedures for addressing the risks of working from heights where there is a risk of falling two or more metres by:
· implementing a system of work
involving working platforms and ledgers (spaced one metre apart) thereby
providing multiple handrails
for the entire height of the scaffold;
· requiring scaffolders to use safety harnesses when erecting or
dismantling scaffolding near a leading edge. This requirement
is despite the
fact that Australian/New Zealand Standard 4576:1995 does not mandate the use of
harnesses except in limited circumstances;
· ensuring the use of a crane to dismantle equipment at the
Site.
87 The following additional steps have been taken by Waco following the
accident (also extracted from Mr Mill's affidavit):
(a) requiring the principals (or, where the principal is unable to attend, a senior scaffolding employee such as a foreman or leading hand) of all subcontractors to attend monthly meetings organised and run by Waco to discuss safety-related issues. Leading hands of the subcontractors are also encouraged to attend. Subcontractors are warned that failure to attend these meetings places them at risk of not being provided with further or ongoing work from Waco;
(b) disciplining subcontractors who Waco's site/project supervisors observe (during the course of their inspections of sites in accordance with the procedures outlined above in paragraph 44), as having failed to (or failed to ensure that their employees) comply with Waco's safe systems of work. For example, this would include removing subcontractors from sites and refusing to provide work to subcontractors who are observed to not comply with Waco's safe work method statements;
(c) reinforcing the 'sign off' procedures for subcontractors who are currently engaged by Waco. Subcontractors are not paid for their services until all relevant paper work, including the safe work method statement, has been appropriately executed by the subcontractor and its employees;
(d) undertaking audits in relation to all of the sites throughout Australia at which Waco's scaffolding was being used;
(e) reinforcing the requirement that relevant Waco employees undergo risk management document training;
(f) reinforcing safety training of subcontractors and relevant Waco employees through the processes outlined above in paragraph 42;
(g) implementing a system of providing safety bulletins, training programs and alerts to subcontractors and Waco employees as required from time to time (including, for example, training sessions in relation to the safe use of harnesses in New South Wales and SMS alerts to all subcontractors notifying them of high-wind conditions on any particular day); and
(h) undertaking periodic re-induction and re-training of site/project supervisors.
88 The foregoing subjective factors
will be taken into account in mitigation of penalty.
89 The presence of prior convictions disentitles Waco from receiving
leniency normally extended to an offender not adversely recorded.
A submission
was made on Waco's behalf that the present offence constituted an
"uncharacteristic aberration": Veen v The Queen (No 2) [1988] HCA 14; (1988) 164 CLR
465 at 471. I cannot agree. Waco's prior convictions, although based on
different factual backgrounds, nevertheless involved offences
under the
occupational health and safety legislation. Put on that general basis, I am
unable to make the finding that the present
offence constituted an
"uncharacteristic aberration". I should clarify, however, if it be thought
necessary, that this does not
mean that a more severe penalty is warranted. The
presence of prior convictions is relevant in the circumstances only to the
withholding
of leniency.
90 I am prepared to take into account in Waco's favour the size and scope
of Waco's operation in the context of its prior history
and find that Waco has a
good industrial record.
Victim Impact Statements
91 I adopt and apply here the remarks made in Delta's sentencing reasons
with regard to the victim impact statements received by the
Court from Mr
Hughes' parents, Hetty and Frank Hughes, and his brother, Christopher Hughes,
who read his statement onto the record.
Bradley Tracey Scaffolding Services Pty Ltd and Bradley Tracey
92 It was agreed between the parties that the sentence proceedings
against BTSS and its director, Mr Tracey, should be heard together.
93 BTSS, at the time of the offence, provided the labour to the site for
the purposes of erecting, adjusting, and dismantling the
scaffolding components.
It employed Mr Hughes and Mr Issell, both qualified scaffolders (Class
1/advanced level certificates of competency).
Mr Issell also held a Class 1
riggers ticket. BTSS contracted with Waco for the provision of labour. The
methodology adopted for
the demolition of the building at the site has been
earlier set out in the proceedings against Delta. I adopt and apply the
relevant
material set out in Delta's sentencing reasons (at [3] to [8]) on this
issue in Waco's sentencing reasons.
94 With regard to the proposed installation and use of the electric
winch, the agreed facts record that Delta knew and approved of
its installation
and operation for the purpose of lowering the scaffolding components. Delta had
considered, but decided against,
the use of a crane for this purpose. Delta did
not, having approved the use of the winch, conduct a risk assessment with regard
to the installation and operation of the winch.
95 The relevant factual background to the accident is set out in Delta's
sentencing reasons. I adopt and apply that factual background
as set out (at
[12], [13], [15], [17]) in Waco's sentencing reasons.
96 In order to secure the winch (to a ledge in a scaffolding bay), Messrs
Hughes and Issell climbed the scaffolding standards above
the open penetration
on the scaffolding working deck adjacent to the roof of the building. They
secured the winch while standing
on the working platform which was comprised of
two wooden planks positioned directly above the open penetration. After
completing
this task, they proceeded to climb down using the scaffolding
standards. It was at this point that Mr Hughes fell through the open
penetration, 33 metres to the ground and was fatally injured.
97 Climbing of the scaffolding standards was prohibited by Delta in its
OHS&R Management Plan for the site. There was, however,
no alternative
means provided for accessing the two-plank working platform which Messrs Hughes
and Issell had used while installing
the winch. No ladders or stairways were in
place, for example. Moreover, the two-plank working platform on which both men
had been
standing contained neither mid-rails, nor toe-boards, along its outside
edge and at both ends. The open penetration had been created
by the removal of
two of four metal scaffolding planks from one bay of the scaffolding working
deck on level 9 of the building.
Six unsecured wooden planks had been placed
across the remaining three scaffolding planks. The penetration was
approximately 950
mm in length and 500 mm wide. There was, according to the
agreed facts, nothing in place to prevent a person falling through the
open
penetration.
The risk to safety
98 Given this set of circumstances, the risk to the safety of both Mr
Hughes and Mr Issell was obvious, that is, the existence of
an open penetration
33 metres above ground which was not encased by any midrails and which was not
accessible other than by climbing
the scaffolding standard, placed both men at
risk of falling through the penetration.
99 The risk of falling through a penetration is also a well-known risk
being one not infrequently encountered on demolition sites.
100 Mr Tracey, who represented himself and appeared on behalf of BTSS,
also tendered in the proceedings an extract from an Australian/New
Zealand
Standard (AS/NZ 4579:1995) which deals with safe work practices to be adopted in
order to minimise the risk of falling from
scaffolding. The practices set out
in the Standard are relevant to the type of work Messrs Hughes and Issell were
undertaking at
the time of the accident, that is, the installation of the winch.
These procedures, relied upon by BTSS and Mr Tracey tend to confirm
that both
defendants were well aware of the risk to safety arising from working at heights
in the vicinity, or over an open penetration.
Section 9.8 of the extract
entitled "Safety Harness" sets out the following information:
Safety harnesses may be used to provide protection against a fatal or serious fall when a scaffolder is required to work over a void, or lean out from the scaffold or supporting structure without the protection of a guardrail; however, they can increase the risk of injury if used incorrectly or unnecessarily:
Safety harnesses can be used during:
· The
erection and dismantling of hung scaffolds prior to or upon removal of the
platform.
· The fixing and removal of trolley tracks on suspension rigs.
· The attachment and removal of spurs projecting from the supporting
structure.
· The erection and dismantling of cantilever scaffolds prior to or
upon removal of the initial platform.
101 As the agreed facts document records, neither Mr Hughes, nor Mr
Issell, was wearing a safety harness or other fall arrest equipment
while
climbing the standards or standing on the work platform while installing the
winch or otherwise working in the vicinity of
the open penetration.
Available safety measures prior to offence
102 The agreed facts set out a number of available alternative measures
and/or devices which could have been used by Messrs Hughes
and Issell to
minimise the risk to their safety. The following material extracted from the
agreed facts document illustrates this:
Alternative and more suitable mechanical devices exist for lowering scaffolding components. These include material hoists, gin wheels, scaffold jib cranes, tower cranes and scaffold wheels. Such devices are the accepted means for lowering scaffolding components in circumstances where "handballing" or "chaining" (a gang of workers forming a human chain to pass equipment from one to another) is impracticable. Such devices do not require for their operation an open penetration in the working deck of the scaffold.
Issell's usual procedure for the lowering of materials from heights was to "chain" them down with a team of 15 workers.
Handballing, the use of handlines, the use of gin wheels and the use of cantilevered builders' hoists are discussed in section 9 of AS/NZS 4576:1995. Compliance with AS/NZS 4576:1995 was required by a safe work method statement ("SWMS") prepared by Waco and issued on 21 November 2005 ("the Waco 2005 SWMS"). Compliance by the defendant with AS/NZS 4576:1995 was also required by the contract between it and Waco. AS/NZS 4576:1995 is incorporated in the industry code of practice Technical Guidance approved pursuant to section 43 of the Occupational Health and Safety Act 2000.
In its quotation submitted to Waco, the defendant allowed the sum of $12000 for cranage. No crane was present on the site on 5 January 2006.
Subsequent to 5 January 2006 a system of using a crane to lower scaffolding components placed in pallets was used at the site.
Consequences of breach
103 The likely consequences of the breaches of the offence committed by
BTSS and Mr Tracey were very serious. Mr Hughes suffered
fatal injuries as a
result of falling through the open penetration. Mr Issell's exposure to the
risk of falling through the open
penetration carried with it the likely
consequence of a fatal injury.
Systems of work prior to offences
104 The agreed facts document sets out a number of deficiencies in the
system of work adopted by BTSS and Mr Tracey on the day of
the offence. The
relevant part of the document is extracted below. (The reference to "BTS" is a
reference to BTSS.):
BTS did not devise its own SWMS for the work it had contracted to perform at the site. Rather, it adopted the Waco 2005 SWMS. The Waco 2005 SWMS did not identify an electric winch as a device to be used for lowering scaffolding components. Rather, the Waco 2005 SWMS stated in various contexts dealing with the movement of scaffolding:
Pass scaffold by hand with persons not more than 3.0 metres apart (vertically) OR use crane or hoist (emphasis added)
The Waco 2005 SWMS provided no instruction for the work method to be adopted for the task of securing the winch being performed by Hughes and Issell on 5 January 2006.
The Waco 2005 SWMS did not identify the hazard posed by penetrations in scaffolding, the associated risk of falling from the scaffolding and the necessary steps to control that risk.
Site-specific risk assessments prepared by Delta dated 17 October 2005 and 21 December 2005 identified penetrations as a hazard with falls of persons or materials through the penetration as potential outcomes.
The subcontract agreement between BTS and Waco provided that:
17 Work Method Statement/Job Safety Analysis
(a) Waco Kwikform has developed a Work Method Statement in respect of the Works ("the Work Method Statement") a copy of which will be made available to the Subcontractor.
...
(c) The development of the Work Method Statement will not relieve the Subcontractor from its obligation to develop its own work method statement ...
(d) Wherever a unique task is identified requiring a specific work procedure to be formulated the Subcontractor will in consultation with Waco Kwikform develop a specific work method statement for such work ...
The Waco 2005 SWMS in dealing with the tasks of erecting, adjusting and dismantling scaffolding identifies a risk of falling from the scaffold and stated respectively:
Access scaffold by ladder, stairs or hoist
Do not climb the standards (Ref. 5.0)
Access scaffold by ladder, stairs or hoist
Must not climb the standards (Ref. 6.0)
Access scaffold by ladder, stairs or hoist
Do not climb the standards (Ref. 7.0)
On 13 January 2006, Waco prepared a revised SWMS ("the Waco 2006 SWMS") in response to a prohibition notice issued by the prosecutor.
The Waco 2006 SWMS identified the hazard posed by penetrations in scaffolding, the associated risk of falling from the scaffolding and the necessary steps to control that risk. In dealing with controls, the Waco 2006 SWMS stated (in section 6.0A):
Workers will be instructed that should they encounter any penetration (be it in the scaffold deck or elsewhere in the work environment):
(i) They should not have access above any such penetrations.
(ii) If they are required to work above the penetrations, they should ensure the handrails (including mid-rails) are installed to prevent access to the penetration, or that the penetration is covered and secured; and
(iii) Any workers involved in railing off or covering and securing such penetrations must be harnessed with the lanyard while performing such work.
The Waco 2006 SWMS also identified the hazard posed by the task of relocating deck boards, the associated risk of falling from the scaffolding and the necessary steps to control that risk.
No SWMS existed for the winch installation task being performed by Hughes and Issell.
No site-specific risk assessment was carried out for the task of installing and dismantling the electric winch.
105 BTSS had no available supervisor on the day of the accident. Its
regular supervisor, Bradley Tatum, was absent that day on scheduled
leave.
106 Mr Hughes is not recorded as signing off on the Waco 2005 SWMS or on
any other SWMS. No discussions took place between Mr Tracey
and Messrs Hughes
and Issell concerning the issue of access when installing the winch. Mr Issell
had no training in the system of
using the electric winch.
107 These matters demonstrate obvious flaws in the system and procedures
utilised for the installation and intended performance of
the winch. They also
contribute to the objective seriousness of the offences.
108 Other matters were brought to the attention of the Court by Mr Tracey
with a view to mitigating the objective seriousness of the
offences.
109 According to Mr Tracey, BTSS did utilise a crane in the erection
stage of the scaffolding. He said that a SWMS had been specifically
devised in
relation to that task. He also said that "we were asked to stop using the
crane". The agreed facts document provides
some support for Mr Tracey's
assertion with regard to the use of the crane. The document records that Mr
Tracey allowed the sum
of $12,000 for cranage in the BTSS quotation to Waco.
110 Mr Tracey also said he discussed the proposed work method for
lowering the scaffolding components on 5 January 2006 with Mr Hughes
and Mr
Issell. Both men were "advanced scaffolders" and neither, according to Mr
Tracey, saw problems with the method proposed (using
the winch). Mr Tracey said
that if there had been a crane on site it would have been utilised for the
task.
111 Mr Tracey left the site after discussing the proposed work method
with Mr Hughes and Mr Issell because he said he had other things
to do and he
had no reason for concern because both men were experienced and qualified
scaffolders. He also said he respected Mr
Hughes' opinion. Mr Hughes, according
to Mr Tracey, was a safety advisor with other companies. Mr Tracey also
ventured to say that
there was nothing inherently unsafe about using the winch
for lowering the scaffolding components. Chaining was not a commercially
viable
alternative because, "of the size and duration of the job". It would have
required about 15 workers to undertake the task.
112 Mr Tracey also said that BTSS conducted toolbox meetings with the
workers.
113 Accepting these matters advanced in mitigation by Mr Tracey as
accurate (noting that many of the matters raised are supported
by the evidence),
the Court is prepared to take them into account as mitigating, to some extent,
the otherwise objective seriousness
of the offences.
114 BTSS and Mr Tracey have no prior convictions. BTSS therefore faces a
maximum penalty of $550,000 and Mr Tracey, $55,000.
Subjective factors
115 Both defendants also entered pleas of guilty at the first reasonable
opportunity. I propose to award a discount of 25 per cent
of the penalties to
be imposed for the utilitarian benefit derived from the pleas of guilty.
116 As a separate consideration, each defendant is also entitled to
leniency in recognition of the remorse shown by the pleas of guilty.
117 Mr Tracey also made the following statement in oral submissions on
behalf of himself and BTSS:
I am a second generation scaffolder and have been in the scaffolding industry all my working life, about 31 years. During this time both myself and my family have been employers as well as employees in the industry. Over the hundreds and thousands of scaffolding man hours we have never, before this accident, had any serious incidents.
Before this accident I was blessed with a happy home life, a highly respected and successful business and financial security. I had pride in myself, in conducting my business in the correct and proper manner. This included ensuring all my experience, obligations and workers entitlements. We were all direct employees and not subcontractors. They were all fully covered.
I have the utmost empathy for Paul Hughes and his family and share the pain and distress of his untimely death. However, as a result of this terrible accident I now stand before you having lost my family, my marriage, my home and a business and, to some degree, my reputation and dignity.
118 The statement, although
acknowledging the impact of Mr Hughes' tragic death on members of Mr Hughes'
family, does not appear to
fully recognise the culpability of BTSS or Mr
Tracey's culpability in relation to the circumstances of the offences. This
makes
it difficult to assess whether either defendant should benefit on penalty
by reason of having shown contrition. I do not therefore
propose to consider
further whether BTSS or Mr Tracey have shown contrition for the commission of
the offences. (See for discussion
of this issue, which I adopt in these
sentencing reasons: Inspector Stephen Cooper v Franklin Alden Conveney and
Another [2008] NSWIRComm 80 at [34] to [37].) The statement, however,
attests to the good corporate reputation of BTSS and the good reputation of Mr
Tracey within the
industry which will be taken into account in mitigation of the
penalties to be imposed.
119 The absence of prior convictions also entitles both defendants to
leniency.
120 Both defendants also fully co-operated with WorkCover in its
investigation of the offences.
Victim Impact Statements
121 I adopt and apply here the remarks made in Delta's sentencing reasons
with regard to the victim impact statements received by
the Court from Mr
Hughes' parents, Hetty and Frank Hughes, and his brother, Christopher Hughes,
who read his statement onto the record.
Respective roles
122 The prosecutor submitted that the culpability of the four defendants
before the Court was equal. The grounds upon which the submission
was put was
that the risk to safety was the same with regard to the circumstances of each
offence and similar opportunities were
available to each defendant to eliminate
the risk, that is, by ensuring there were no penetrations which exposed workers
at the site
to risk and that the workers had harnesses or other fall arrest
equipment available for use. The prosecutor further submitted on
the issue:
... all three companies, whether they were the direct employer or whether they were merely a contractor on site, all three companies bore the responsibility in respect of safety at the same place.
The simple fact that Waco chose to do the work, for example, by recourse to subcontractors, that is by not directly employing people, did not change its obligation to ensure safety at the site. The fact that Mr Tracey chose to employ people did not change his responsibility or his company's responsibility in respect of safety. The obligation was in respect of all three companies the same obligation, that is, to ensure that the work that was being conducted was risk free or that all three companies had the same obligation to make the work site safe.
Section 8(1) and section 8(2), I submit, should not be seen as less or more serious offences. They are both offences that Parliament has said are punishable by the same fine, and the same fine for a second offence under each section. So simply because Waco and Delta exposed people to the same risk, and I emphasise the same risk, but chose to do so by way of subcontracting people, should not be seen as a matter that either mitigates the offence or makes it one that is less serious. That is the proposition I have tried to put in all three prosecutions. I put something slightly different in respect of Waco because of some of the things in the submissions and affidavit material but not relevant to that.
123 Neither Delta, BTSS or Mr Tracey made
any submissions with regard to their respective culpabilities by reference to
their roles
and occupational health and safety responsibilities at the site.
Waco made submissions on the issue but its ultimate submission
was expressed as
follows:
If your Honour is not inclined to view the culpability of the defendant in all of the circumstances as being lesser, in my submission, it should be no more than equal to the other parties.
124 Waco's
submissions on its culpability, or role, in relation to the circumstances of the
offence first sought to emphasise what
was described as "respective levels of
control over the site". This was a reference to the "level of control" Waco
exercised over
its subcontractor BTSS, and the employees of BTSS, with
particular regard to the creation of the open penetration on level 9, the
lack
of access to that area and the level of supervision provided by BTSS to Mr
Hughes and Mr Issell, "at the time they were left
alone and the climbing of the
scaffolding standards". Waco, however, acknowledged that these matters, "go to
the immediate cause
of the accident" and were not therefore being relied upon on
the issue of which defendant was more, or less, culpable. Rather, it
was
submitted by Waco there were "other" causative factors "which were less
immediate in time but nevertheless contributory". These
other factors were said
to include the toolbox meetings on 3 and 5 January 2006 (before the accident)
during which the proposed installation
and use of the winch was discussed in
circumstances where Mr Pavone (Delta's site supervisor) was aware of the
intended installation
and use of the winch, but had no prior experience of a
system which utilised a winch to lower material through an open penetration.
125 I would add on this aspect that it was an agreed fact in Waco's
agreed facts document that Delta also failed to conduct a risk
assessment
concerning the installation and operation of the winch. Waco also submitted
that BTSS, following the decision to install
and use the winch, was not asked
(by Delta) to provide a SWMS, or any form of risk assessment with regard to the
winch. Waco, as
the agreed facts tendered against it records, did not
"expressly authorise" the use of the winch. It would appear from the agreed
facts, however, that Waco, through its sales representative for the project,
Andrew Skopin, was at least aware that BTSS, on 5 January
2006, was considering
a number of materials handling options for lowering the scaffolding components,
which included the use of a
"lift and winch".
126 Waco submitted, essentially, that its role in the circumstances of
the offences was "more distant in time" than Delta's role or
involvement, and
therefore, by implication, that it was less culpable. In developing the
submission, Waco contended that its role
was limited to an omission in the Waco
2005 SWMS of a reference to the systems to be devised for the installation and
use of the
electric winch, or to an absence of sufficient "identification" that
a winch was not to be used, "unless certain steps were taken".
127 On the site, a building was being demolished. Various corporate
entities were involved in the project. The duties and responsibilities
of each
entity were organised, contractually, through a process of devolution, a not
unusual occurrence on many contemporary construction
and/or demolition sites.
Delta was the principal contractor at the site with all the statutory
obligations attendant upon that particular
role. Waco was contracted by Delta
to provide the scaffolding equipment and labour for the purpose of demolishing
the building.
BTSS was sub-contracted by Waco to provide the labour for the
purpose of erecting and dismantling the scaffolding.
128 All of these corporate entities, and Mr Tracey as the director of
BTSS, had statutory obligations to ensure the safety of all
personnel at the
site. It was not contended otherwise by Waco (or by any of the other
defendants). Each defendant also failed to
ensure that safe work methods were
devised and implemented for the work being undertaken by Mr Hughes and Mr Issell
on 5 January
2006 with regard to the installation and use of the winch. The
supervision by each defendant of the scaffolding workers and of the
scaffolding
works was inadequate and in Waco's case, non-existent, on 5 January 2006. The
agreed facts against Waco record that
its Site Safety Management Plan (the Plan)
provided that "skilled and competent supervision will be provided for all work",
but the
Plan failed to identify which person(s) would be required to provide the
supervision. It was Waco's understanding that BTSS would
supervise its own
employees. Each defendant failed to ensure that there were no open penetrations
through which persons could fall
while working at height. Each defendant also
failed to ensure that BTSS employees had fall arrest equipment (such as safety
harnesses)
necessary to prevent falls from heights.
129 On these matters, which substantially reflect the particulars in the
charges to which each defendant entered a plea of guilty,
the finding is
available that the respective culpabilities of each defendant is equal.
130 No defendant sought to rely (as was suggested by the prosecutor with
regard to Waco's culpability) on a concept of "passing on"
statutory obligations
with regard to safety through contractual delegation.
131 The Court finds therefore that the role of each defendant in the
circumstances of the offences was equal.
Penalties
132 In determining penalties against the defendants, I have taken into
account the objective seriousness of the offences, the maximum
penalties, the
factors in mitigation described above, the absence of prior convictions with
regard to BTSS and Mr Tracey, and the
respective culpabilities of the
defendants. These factors have been considered by reference to the Crimes
(Sentencing Procedure) Act 1999, in particular s
21A.
Orders
133 In Matter No. IRC 2230 of 2007, the Court
makes the following orders:
(1) The defendant, Bradley Tracey, is convicted of the offence and fined
$8,000 with a moiety to the prosecutor.
(2) The defendant is to pay the reasonable costs of the prosecutor as agreed, or in the absence of agreement, as assessed.
134 In Matter No. IRC 2231 of 2007, I make the following orders:
(1) The defendant, Bradley Tracey Scaffolding Services Pty Ltd, is
convicted of the offence and fined $80,000 with a moiety to the
prosecutor.
(2) The defendant is to pay the reasonable costs of the prosecutor as agreed, or in the absence of agreement, as assessed.
135 In Matter No. IRC 2232 of 2007, I make the following orders:
(1) The defendant, Delta Pty Limited, is convicted of the offence and
fined $120,000 with a moiety to the prosecutor.
(2) The defendant is to pay the reasonable costs of the prosecutor as agreed, or in the absence of agreement, as assessed.
136 In Matter No. IRC 2233 of 2007, I make the following orders:
(1) The defendant, Waco Kwikform Limited, is convicted of the offence and
fined $120,000 with a moiety to the prosecutor.
(2) The defendant is to pay the reasonable costs of the prosecutor as agreed,
or in the absence of agreement, as assessed.
___________________
LAST UPDATED:
30 July 2010
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2010/106.html