![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 10 December 2010
NEW SOUTH WALES INDUSTRIAL RELATIONS COMMISSION
CITATION :
Australian Workers Union v. BlueScope Steel Limited [2010] NSWIRComm
1059
FILE NUMBER(S):
IRC 122
HEARING DATE(S):
09/11/2010, 17/11/2010
DATE OF JUDGMENT:
3 December 2010
PARTIES:
APPLICANT
Australian Workers
Union
RESPONDENT
BlueScope Steel Limited
CORAM:
Connor C
CATCHWORDS: industrial dispute - steelworks - paintline operations
- agreement to operate the paintline in a modified fashion with
reduced manning
- toolbox meeting aborted - alleged refusal of two employees to attend a toolbox
meeting to implement a modified
plan for work with reduced manning - warnings
given - no justification for intervention - suggestions made for modifying
existing
agreement under which work with reduced manning is
performed.
LEGAL REPRESENTATIVES
APPLICANT
Branko
Gorgievski
Australian Workers Union
RESPONDENT
Aaron
Dearden
Duncan Cotterill Lawyers
CASES CITED:
Australian
Workers Union v. BlueScope Steel Limited [2005] NSWIRComm 1194
Australian
Workers Union v. BlueScope Steel Limited [2010] NSWIRComm 1001
BlueScope
Steel Limited Paintline Manning Dispute Case [2008] NSWIRComm
1070
LEGISLATION CITED:
Industrial Relations Act 1996
TEXTS CITED:
JUDGMENT:
INDUSTRIAL RELATIONS COMMISSION OF NEW SOUTH WALES
CORAM: CONNOR C
Friday, 3 December, 2010
Matter No IRC 122 of 2010
Australian Workers Union
and BlueScope Steel Limited
Notification under S.130 of the
Industrial Relations Act, 1996 re warnings given to operators on the
paintline
DECISION
[2010] NSWIRComm 1059
Introduction
1 Pursuant to the provisions of S.130 of
the 1996 Industrial Relations Act, the Australian Workers Union lodged a
notification of an industrial dispute with BlueScope Steel Limited concerning
warning notices
placed on the files of two employees on the No.3 paintline [CPL
3] of the Painting and Finishing Department [PFD] of its Springhill
operations -
Mr Josef Pleli and Mr Bradley O'Hare. The warning given to Mr Pleli (which is in
similar terms to the warning given
to Mr O'Hare) is in the following
terms:
"...This disciplinary note has been given...for refusal to comply with a reasonable request from a supervisor. On Tuesday, 9 February, 2010...a line delay occurred due to an issue relating to manning at CPL 3. At the start up toolbox (meeting) the employee refused to take part in the development of the shift plan unless the crew were all in one place (ie a line stop). Josef was provided with several opportunities to comply with the request, including:
(a) an overview of the proposed plan at the toolbox;
(b) a discussion of the proposed plan to highlight potential points of conflict with the plan;
(c) any discussion of the shift plan that did not involve a line stop for toolboxing purposes.
Josef refused to comply with the request or pro-offer any alternative proposals not involving a line stop and this behaviour is deemed as unacceptable and outside of the expectations under Manufacturing Excellence.
Josef is notified that the above behaviour has resulted in a warning and that any re-occurrence will result in escalation of the level of discipline up to dismissal. I also note a number of warnings and final warnings on your history file and, although this incident is not serious enough to warrant dismissal, I encourage you to consider this in your ongoing interactions with PFD company officers..."
2 The matter came before Grayson DP for conference
on Friday, 26 February, 2010, Thursday, 8 April, 2010, Friday, 23 April, 2010
and
Friday, 18 June, 2010. Conciliation had not succeeded in resolving the issue
in dispute. The file was allocated to me. All proceedings
before Grayson DP and
subsequently before me were convened in the Commission's premises at 90 Crown
Street, Wollongong.
3 I set the matter down for a mention and a
conference for further conciliation on Tuesday, 29 June, 2010. That further
attempt at
conciliation before me also failed. I issued the certificate of
attempted conciliation required by S.135, lodging it in the prescribed manner,
and programmed the matter for arbitration in a hearing on Wednesday, 4 August,
2010. But that
hearing was vacated at the request of the AWU, and with the
concurrence of BlueScope Steel, and rescheduled for Wednesday, 22 September,
2010. The hearing of Wednesday, 22 September, 2010 was also vacated. Ultimately,
I set the matter down for a further conference on
Wednesday, 20 October, 2010
and ultimately a hearing on Tuesday, 9 November, 2010 and Wednesday, 17
November, 2010.
4 Mr Gorgievski represented the AWU in the
hearing, calling Mr Pleli and Mr O'Hare to give evidence. Mr Gorgievski
argued that the warnings given to Mr Pleli and Mr O'Hare were not warranted and
that, in fact, they were only acting within the terms
of an agreement reached
between the AWU and BlueScope Steel, as they understood it. That agreement had
been brokered in earlier proceedings
before me. I will discuss it in more detail
later in this decision as I believe it to be fundamental to the resolution of
the matter
before me in this hearing. Mr Dearden represented BlueScope
Steel in the hearing, calling Mr Steven Day, a shift team leader for the
paintline operations of BlueScope
Steel (whose directions to Mr Pleli and Mr
O'Hare led to the warnings given to them). Mr Dearden argued that the
directions given to the two employees by Mr Day were reasonable and were
consistent with the agreement reached over
manning between BlueScope Steel and
the AWU.
5 I have always understood that the agreement which had been
reached between the parties was of a temporary nature - and as the evidence
before me in this hearing has revealed, it is often honoured more in its breach.
It appears to me to have been appropriate for the
parties to confer further over
it with a view to modify it to meet current needs and I had directed that the
AWU and BlueScope Steel
do so with a view to reassessing and, if necessary,
altering the agreement. Some discussions have, in fact, taken place between the
parties in that respect but they have been unable to finalise their negotiations
to date.
Background
6 The paintline is ideally a
continuous operation. Initially, following an unreported decision of O'Neill C
on Wednesday, 14 December,
2005 in Australian Workers Union v.
BlueScope Steel Limited [Matter No.IRC 1206 of 2004], manning levels for
the continuous operations on the paintline were reduced from 13 operators on
each
crew to 9 operators . The line now operates continuously with 8 operators
in a crew on each shift but it can still operate continuously
with 7 operators
if 8 operators are not available for a particular shift for any reason. But the
line cannot run continuously if
less than 7 operators are available for any
shift.
7 Nevertheless, the line may also run with less operators - 5 or
6 - on certain agreed conditions, ie that the line will stop for
crib and other
necessarily operational issues. There are, in fact, 5 work stations which must
always be manned - the entry point,
the coater room (with 2 operators), the
laboratory/pre-treatment area and the delivery area. And when heavy gauge
galvanised product
is being processed, an acknowledged more complex operation, a
minimum of 6 operators is required. The line may not run at all with
less than 5
operators.
8 During 2008 and 2009 financial constraints applying
generally throughout the community, and the steel industry in particular, led
to
a substantially reduction in throughput in the paintline. There are apparently a
number of factors influencing the amount of product
being processed - capacity
of the paintline, the amount of product arriving to be processed but,
principally, what orders have been
received. In any event, for much of 2008 and
2009 paintline throughput has been curtailed to some extent.
9 It was in
that light that BlueScope Steel and the AWU entered into lengthy discussions
with a view to putting in place some interim
arrangements to accommodate the
reduced level of product being processed. Temporary arrangements have been
required in those circumstances
and the paintline operators had for the most
part accepted them. Nevertheless, there were still issues in dispute over
manning of
the paintline. In particular, the position of rover on the paintline
has been the subject of some disputation.
10 On Tuesday, 29 January,
2008 BlueScope Steel had lodged a S.130 notification of an industrial dispute
with the AWU over its proposal to abolish a position of rover on each of the
crews on the paintline.
The matter came before Grayson DP for a conference on
Friday, 1 February, 2008. It had been suggested that a 6 month trial of the
new
manning arrangements would be put in place. That suggestion was ultimately
adopted and the file was then allocated to me to oversight.
11 The AWU
subsequently indicated that it was the intention of the employees to opt out of
the trial, essentially because they had
formed the view that the manning levels
in the trial were unsafe and unfair to the paintline operators. I reconvened the
proceedings
for a further conference on Friday, 4 July, 2008 and I was informed
at that time that the paintline employees had formed the view
that the
arrangements in the trial were no longer workable. The AWU argued that the trial
should be abandoned and the employees revert
to the previous shift arrangements
- 9 employees per shift. Since the AWU believed that the change proposed was a
significant one,
it argued that the status quo should be preserved in
that respect until the arbitration of the matter in accordance with the
provisions of the BlueScope Steel
Limited Springhill and CRM Employees Award
[Clause 36.4.3(j)] and the terms of the trial itself.
12 Nevertheless,
the trial remained in place until the matter could be further discussed in
proceedings before me on Monday, 7 July,
2008. Those proceedings were adjourned
until Tuesday, 15 July, 2010 to give BlueScope Steel the opportunity to consider
a proposal
advanced from the AWU. The parties were unable to reach an agreement
over the matter and on Tuesday, 15 July, 2008 I programmed the
matter for
arbitration. However, for my part, I regarded it as unfortunate that the trial
was being abandoned, making my opinion
clear in the proceedings on Monday, 7
July, 2008 and Tuesday, 15 July, 2008. Ultimately, the hearing of the matter was
scheduled
for Monday, 15 September, 2008 and Tuesday, 16 September, 2008 but
that did not eventuate.
13 On Friday, 18 July, 2008 the AWU again
requested a further urgent conference concerning this matter and I reconvened
those proceedings
at midday on Friday, 18 July, 2008. I was informed that in the
afternoon the paintline operators were intending to cease work. I
saw no benefit
from such industrial action and it did not eventually occur. Ultimately, in the
proceedings before me on Tuesday,
19 August, 2008 a compromise position was
reached between the parties and they finalised their position in documents which
were provided
to me to form part of the file. I finalised the matter with an
ex tempe decision dated Tuesday, 19 August, 2008.
14 The
agreement described in my decision involved certain guidelines [Attachment 2],
viz:
"....When faced with reduced manning, it is possible to run the paintline in a modified system of work to facilitate some production for the company and full payment for those at work. The specific schedule on a night will always determine exact details of how the line will operate. The crew would need to meet to develop a plan to run in the modified fashion. Some guidelines to manage the workload for the crew to deliver successful operation can be summarised below:
For 6 or 5 man operation:
* combined stop for crib;
* 2 colours to be run with threaders on either side;
* line does not start until the paint is already on the landing;
* no forklifts movements during production (not possible with 5 men anyway);
* bin to be squashed/changed at threader time;
* rover to be based at exit for unforeseen circumstances when line is running;
* the dual paint changes to be carried out on the threader and all paint drums would then be brought to the landing and ready for the next colour before the line is started again.
The company will not request the crew to run the line with 4 men, alternative work would be found for these 4 men.
These are reasonable guidelines, which will allow the company to gain some production in low manning situations and ensure that no operators are taken off pay for refusing to run the line in a reasonable manner..."
On that basis, the trial was brought to an end. As I indicate later in this
decision the words I have emphasised above in the agreement
struck between
BlueScope Steel and the AWU - and it is their agreement - appears to now be the
point of contention.
15 The current manning arrangements for the
operation of the paintline, in accordance with the agreement of the parties, is
for it
to run continuously when 7 or 8 employees present themselves for work on
any shift. If 5 or 6 operators are present on any shift,
the paintline will not
operate continuously but will do so with combined stops for crib and the other
conditions contained in the
agreed guidelines. If only 4 operators present
themselves for work, the paintline will not run at all but the employees will be
found
alternate duties.
16 However, a further industrial dispute arose
over the paintline operations and the interpretation of the terms of the
agreement
reached. The AWU notified the dispute to the Commission under S.130.
The matter was allocated to me and I set it down for a series of conferences and
ultimately arbitration in a hearing on Wednesday,
16 December, 2009 and Monday,
11 January, 2010. I concluded the matter with my unreported decision of Friday,
5 February, 2010 in
Australian Workers Union v. BlueScope Steel
Limited [Matter No.IRC 114 of 2009].
17 The AWU contended that it
was a term of the agreement reached between the parties that there was an
obligation in cases where less
than 7 operators present themselves for work to
call in other employees (on overtime) to make up the number of employees to run
the
line continuously. It argued the agreement between the parties was
predicated on the basis that the line would only run with the
reduced manning
if, after making an effort to call in additional staff, the management was
unable to do so. BlueScope Steel maintained
that the management had the right at
all times to decide to run on such reduced numbers and that there was nothing in
the agreement
reached which obliged it to do so.
18 In my decision I
commented (at pp.12 and 13) that:
"...the agreement does no more than outline what the arrangements are if and when there is insufficient operators on a shift to man the paintline to operate continuously. It does not really set out whether or not BlueScope Steel management is under an obligation to man up on any particular shift where for one reason or another there is insufficient employees available to run the paintline continuously. I do not believe that there is such an obligation... It is, of course, customary industrial practice for an employer to determine how a business will ultimately be run - in this case, whether to run the paintline continuously or not. That will primarily be determined by how many orders there are and the relationship between the paintline operations and the rest of the steelworks and whether there is actually product available to be processed.
In my opinion, BlueScope Steel may continue to run the paintline as it choses, provided it imposes no unfair or unsafe burden on the employees and provided at the present time it follows the guidelines in Attachment 2. The operators do not have the right - either under the agreement reached or according to ordinary industrial practice - to dictate whether the paintline must always run continuously. That is a matter for BlueScope Steel management, dependent upon its particular requirements at the time..."
However, I had also indicated in my decision (at p.11):
"....Clearly, the paintline operators are experienced operators and the guidelines in Attachment 2 seems to me to suggest they should be instrumental in working together with BlueScope Steel management to determine how best to run the paintline when it runs with reduced manning. The guidelines provide as follows: '...The crew would need to meet to develop a plan to run in the modified fashion...'. That suggests to me that the paintline operators do have a role in how the paintline may run when there is reduced manning..."
19 The interpretation of those comments seem to
have led to the current industrial dispute.
The Current
Incident
20 At the commencement of each shift the team leader
conducts a toolbox meeting of the paintline operators. On the night shift of
Tuesday, 9 February, 2010 [A Crew] the line was short 2 employees on annual
leave and sick leave. Only 5 employees presented themselves
for work on their
shift. Mr Pleli had been called in on overtime but a further operator was not
obtained and, with a crew of 6 operators,
the line could not run continuously.
Mr Day prepared a shift plan. It involved Mr Pleli being assigned to work in the
coater room.
21 Mr Pleli claimed that he had no objection in going to
that work station. However, some confusion appears to have arisen over the
plan
when Mr Day approached Mr Pleli and Mr O'Hare and one other operator - Mr Lou
Ivanovski - for a tool box meeting. Mr Brett Dutton,
a technical advisor for the
paintline on the crew - a staff officer - was also present at the work station
and was available for
discussions with Mr Day concerning the running of the
line. According to Mr Day, Mr Pleli and O'Hare stopped him. According to Mr
Pleli and Mr O'Hare, they did not. Mr Day claimed that Mr Pleli said words to
the following effect:
"Before you go on with any of that, are you going to stick to the agreement?"
22 Mr Day had not seen the agreement at that time.
Mr O'Hare handed him a copy of it. Mr Day again attempted to commence the
toolbox
meeting and he claimed that Mr Pleli stopped him again, asking
him:
"Are you going to honour the agreement? The whole crew has to be here."
Mr Day replied:
"I think it's reasonable for the shift plan to be communicated via toolbox meetings on most occasions, especially with 6 men (as opposed to 5) at work. The rover should be located wherever the workload is."
23 Mr Day indicated that it was his
intention to honour the agreement reached but he claimed that Mr O'Hare and Mr
Pleli insisted
that the whole crew had to be present to consider the plan. Mr
O'Hare asserted that Mr Day was abusive to Mr Pleli. Mr Day denies
that claim.
24 Mr Day pointed out:
"Having a crew meeting will mean stopping the line."
Mr Pleli allegedly shrugged his shoulders and stated:
"Whatever!"
And Mr O'Hare responded:
"According to the official ruling from the Commission, the whole crew needs to meet."
25 Mr Day floated the idea of taking a crew
representative to each of the toolbox meetings with him but that proposal was
rejected
by Mr Pleli and Mr O'Hare who indicated that such an arrangement was
not in the agreement. Ultimately, Mr Day was required to put
a threader in the
line and he did so - against the wishes of the rest of the crew, according to Mr
Day. That was particularly the
case with the employees on the crew who had to
clean up (unnecessarily) each time the line was stopped and
restarted.
26 It is Mr Pleli's claim, contained in a written statement
which provided the basis of his evidence in this hearing, that at no time
had he
refused to work at the coater room, provided the crew had no objection to him
doing so. He further added in his written statement
that:
"....at no time did I say that all the crew had to be in one place for a shift plan to be developed. I told Mr Day that he could talk to each operator individually so that everyone was in agreement on how the line would be run for that shift. It was Mr Day's decision to put a threader in place in order to hold a crew meeting and a plan was developed for that shift..."
27 And Mr O'Hare recorded in his
written statement that:
"...at no time did I refuse to take part in the development of the shift plan and at no time did I say that the line should be stopped for a crew meeting. Mr Day did not believe the line had to stop. He asked me, as the crew's representative, to walk the line with him and ask individuals for their input on running the line. I felt uncomfortable with his request and declined to do that, stating that he was capable of asking the crew himself. At no time did I say that the crew had to be in one place for a meeting on how the line was going to run. Mr Day finally contacted the entry operator, instructing him to place a threader on the line so that we could have a meeting. We never once asked for the line to stop. That was his decision..."
28 In the subsequent combined meeting of the
crew Mr Day modified the plan following agreement with the crew - something he
claimed
could have been worked out at the aborted toolbox
meeting.
Conclusion
29 Bearing in mind the fact that the
tool box meeting which Mr Day attended with his shift plan at the commencement
of the night shift
on Tuesday, 9 February, 2010 already involved three of the
six operators on that shift - Mr Pleli, Mr O'Hare and Mr Ivanovski -
(and Mr
Dutton) - it would not have been a difficult or time consuming task for Mr Day
to address the remaining operators who were
not present individually.
Notwithstanding the claims made by both Mr Pleli and Mr O'Hare to the contrary,
they seem to have been
suggesting by their conduct that the crew had to meet
together to approve of the shift plan and that would necessarily have
meant that the line had to stop. When Mr Pleli shrugged his shoulders
and said:
"Whatever!" - and I accept that he did say that - he was clearly inviting Mr Day
to stop the line. Mr Day had no other
option, in the circumstances.
30 Mr
Pleli and Mr O'Hare seem to be relying in that respect on an excessively strict
wording of the agreement which the parties reached
between BlueScope Steel and
the AWU in Attachment 2 - "...the crew would need to develop a plan to run (the
line) in a modified fashion...".
However, it was certainly not the intention of
BlueScope Steel management for those words in the agreement to mean that the
paintline
had to stop for the entire crew to be the sole arbiter of how the line
should run when there is less than standard manning. Commonsense
suggests to me
that when the agreement reached between the parties indicated that "...the crew
would need to meet to develop a plan
to run in the (line) in a modified
fashion..." and when in my decision of Friday, 5 February, 2010 in Australian
Workers Union v. BlueScope Steel I indicated (at p.18) that the
paintline operators "...should be instrumental in working together with
BlueScope Steel management
to determine how best to run the paintline when it
runs with reduced manning...", it was not being suggested that the crew would
need to meet together to determine how to do so, only that they should be
consulted - as Mr Day was attempting to do.
31 To put the conduct of Mr
Pleli and Mr O'Hare in its best light, they were simply acting on a
misunderstanding of the agreement.
Notwithstanding Mr Gorgievski's
strenuous defence of them, it seems to me more likely that they were scanning
the agreement and my decision to find any excuse to
legitimatize their somewhat
unhelpful position. They seem to have had an eccentric industrial agenda of
their own, as Mr Day suspects,
which, in my opinion, ran counter to the best
interests of the crew. They were apparently acting on their perception that the
employees
had a right to direct how the line was to run and BlueScope Steel
management had no right to develop a plan in the first place until
the crew, as
a whole, rubber stamped it. Not only is that inconsistent with the agreement
reached, as I understand it, it would fly
in the face of acceptable industrial
practice. Their role was to act together with their supervisor to develop
a plan in consultation with him. Their conduct was unacceptable and I therefore
see no grounds to
intervene in support of them in this
hearing.
32 However, as I indicated earlier in this decision, I emphasise
that the agreement reached between the parties was their agreement
in the first
place - not something that flowed out of an arbitrated decision of this
Commission. It was also designed to be of a
temporary nature only. The issue
before me in this hearing is confined to consider the warning notices given to
Mr Pleli and Mr O'Hare
but I have to say that it would appear to me that the
guidelines in Attachment 2 for modified operations of the paintline with reduced
manning are honoured more in the breach and, as Mr Day indicated in his
evidence, he has often found it necessary to depart from
them. He has done so,
always in consultation with the crew on the paintline for particular shifts -
which is quite proper. Clearly
the guidelines need modification.
33 I therefore direct the parties into further discussions to consider
variation to those guidelines to reflect what the evidence
before me suggests is
actually taking place on the paintline and the observations I have made
concerning them in this decision.
P J
CONNOR
Commissioner
LAST
UPDATED:
3 December 2010
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2010/1059.html