![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 2 August 2010
NEW SOUTH WALES INDUSTRIAL RELATIONS COMMISSION
CITATION :
Inspector Gary Bruce Mason v Auscott Limited [2010] NSWIRComm
102
FILE NUMBER(S):
250
HEARING DATE(S):
11 and 12
November 2009
DATE OF JUDGMENT:
22 July 2010
PARTIES:
Inspector Gary Bruce Mason (Prosecutor)
Auscott Limited
(Defendant)
CORAM:
Backman J
CATCHWORDS:
LEGAL REPRESENTATIVES
Mr P Ginters of counsel
WorkCover Authority
of New South Wales
(Ms K Lockerby)
Mr B Hodgkinson SC with Mr M Shume of
counsel
Kemp Strang Lawyers
(Ms L Berton)
CASES CITED:
Inspector Colin Wall v Orica Australia Pty Limited [2009] NSWIRComm
146
Riley v Australian Grader Hire Pty Ltd (2001) 103 IR 143
WorkCover
Authority of New South Wales (Inspector Keenan) v Leighton Contractors Pty Ltd
(2005) 147 IR 329
WorkCover v Kevin R Sheather Services Pty Ltd [2001]
NSWIRComm 74
LEGISLATION CITED:
Crimes (Sentencing Procedure) Act
1999
Occupational Health and Safety Act 2000
TEXTS CITED:
JUDGMENT:
- 13 -
INDUSTRIAL COURT OF NEW SOUTH WALES
CORAM: Backman J
Thursday, 22 July 2010
Matter No IRC 250 of 2009
Inspector Gary Bruce Mason
v Auscott Limited
Prosecution pursuant to section 8(1) of the
Occupational Health and Safety Act 2000
JUDGMENT OF THE COURT
[2010] NSWIRComm
102
1 Auscott Limited pleaded guilty to an offence under s 8(1) of the
Occupational Health and Safety Act 2000 (2000 Act). At the time of the
offence, the defendant operated a cotton gin facility at Midkin near Moree
(Midkin Gin). The
Midkin Gin operates as a cotton processing plant between
about April and July.
2 The charge against the defendant alleged that on 8 March 2007, it
failed to ensure the safety of, "all its employees, and in particular,
Ricky
Lawrence Bella". The defendant's failure to ensure safety was further
particularised under four separate heads of allegations.
These were:
(a) The defendant failed to ensure that plant, known as an "IFP Cotton Banding Machine" or "Auto-Strapper", provided for use by its employees at work ("the Strapper"), was adequately guarded so that the Strapper could not move along the Strapper carriage track whilst Mr Bella was, or in the alternative, Mr Bella and Mr Sutherland were, undertaking maintenance work on the Strapper.
(b) The defendant failed to ensure that Mr Bella and Mr Sutherland were provided with such information and instruction in relation to the isolation of power and maintenance of the Strapper as was necessary to ensure the safety of Mr Bella, or in the alternative, Mr Bella and Mr Sutherland, whilst maintenance work was being undertaken on the Strapper.
(c) The defendant failed to ensure that the work procedure known as SWG190 was complied with.
(d) The defendant failed to ensure that Mr Bella and Mr Sutherland were provided with such supervision as was necessary to ensure Mr Bella's safety or, in the alternative, Mr Bella and Mr Sutherland's safety whilst maintenance work was being undertaken on the Strapper.
(e) The defendant failed to adequately maintain such measures, as were identified by a risk assessment, as were necessary to ensure the safety of Mr Bella, or in the alternative, Mr Bella and Mr Sutherland, whilst maintenance work was being undertaken on the Strapper.
3 Particulars (b) and (d) were
disputed by the defendant. The prosecutor therefore was required to prove these
two particulars beyond
reasonable doubt. This matter will be dealt with in
detail later in these sentencing reasons.
Agreed factual background
4 On 8 March 2007, Mr Bella was fatally injured after becoming trapped
between the moving parts of the Strapper carriage and another
item of machinery,
"a Consolidated Up Stroking Cotton Bale Press (the Press).
5 Mr Bella had been employed by the defendant as a "ginner" since 1996.
Craig Gaston, at the time of the accident, was the Gin Manager
and supervisor of
the defendant's employees at the Midkin Gin. Darren George Sutherland was
employed at the Midkin Gin as an electrician.
6 The Press was used to compact cotton into bales. The Strapper fastened
together the cotton bales. Wires were fed through "heads"
of the Strapper under
the compacted cotton bales to a component of the adjacent Press and then fed
back into the Strapper to fasten
the cotton bales. Power and operation of the
Strapper was controlled by a Strapper Console. The main electrical source and
isolator
for the Strapper was housed inside the CP-100 Strapper Electrical
Cabinet (Electrical Cabinet).
7 The Press extended to the ceiling and through the floor to a room below
called the Press Pit. Adjacent to the Press were two operating
consoles, the
Strapper Console (mentioned above) and the Press Console. In the centre of the
Strapper Console was an electronic
touch screen with power control buttons
located immediately below the screen. The left-hand button was an emergency
stop control.
On the floor in front of both Consoles was an electronic pressure
mat (safety mat). Three more safety mats were adjacent to the
Consoles on the
same side. When activated (for example, by a worker standing on them), the
safety mats deactivated electrical power
to the moving parts of the Press and
the Strapper.
8 The Strapper was attached to the Press by a cross beam on the eastern
side of the Press and travelled laterally along the cross
beam toward the Press.
It had five electrical "servomotors" with individual controls that could be
operated manually or remotely.
The five servomotors, identified as A, B, C, D
and E heads respectively (the Strapper heads) controlled individual drive
wheels.
Under the drive wheels, was a knotter box. Under it was an exit track
for the wires that fed under a cotton bale then to the Press
and back into an
entry track on the Strapper, to fasten the cotton bales.
9 On 7 March 2007, the day before the fatal accident, Mr Gaston prepared
to undertake maintenance work on the Press ram. In order
to do this, it was
necessary to move the Strapper away from the Press ram. Mr Sutherland
deactivated the safety mats in front of
the Press and the Strapper by using a
"programmable logic control'. In an interview with WorkCover, Mr Sutherland
said he disconnected
(the power to) the safety mats at Mr Gaston's request so
that Mr Gaston could gain access to the Press with a forklift. Mr Gaston,
in an
interview with WorkCover, said that he did not instruct Mr Sutherland to
deactivate the safety mats. Whichever version is
correct, it was an agreed fact
that prior to the accident on 8 March 2007, the safety mats were not
reactivated.
10 At about 12.00pm on 7 March 2007, Mr Gaston removed the captive key
located at the top right-hand corner of the Press Console.
The removal of the
captive key isolated the electrical control power to the Press and to the
Strapper Carriage. The effect of this
was that all parts of the Strapper
Carriage (with the exception of the Strapper heads) and the Press were
isolated.
11 The captive key was removed by Mr Gaston from the Press Console so
that he could carry out maintenance work in the Press pit.
As at 8 March 2007,
at the time of the accident, it had not been replaced.
12 At and prior to the offence, the defendant had a Standard Work
Instruction (SWG173) for the isolation of machinery. SWG173 required
that prior
to the maintenance work being undertaken on plant, it is first "shut down" and a
"padlock or danger tag [applied] to [the]
local isolator". Mr Gaston complied
with the first part of the instruction, that is, he removed the captive key from
the local isolator
(the Press Console) which "shut down" the Press and the
Strapper carriage (but not the Strapper heads). He did not comply with the
second part of the instruction. His reasons for not doing so were explained by
him in his WorkCover interview:
"SWG 262 was not relevant to the task being performed. SWG 190 was followed to move the ram out of position. Not all steps of SWG173 were followed but this was because I had removed the captive key. I did not consider that it was necessary to apply [sic] additional padlock to the Estop, as the Press and strapping machine could not be operated with the captive key removed. The removal of the captive key isolates both the strapping machine & press from all control power, which disables both machines".
13 SWG173 also required that if a
local isolator was not available then an "authorised person" was to isolate the
main power supply
in the switch room. The procedure to be followed when
isolating the main power supply was set out in SWG173 as follows:
(a) Remove the control fuse first and then remove the three main fuses that supply the motor at the switchboard. Apply a danger tag to the top of the contractor. Ensure all fuses are identified as to where they were removed from.
(b) Turn the circuit breaker to the off position and install a lockout device. Apply a padlock or danger tag.
(c) Turn switch to the off position and apply padlock or danger tag."
14 SWG190, which was referred to by Mr
Gaston in his WorkCover interview, was another safe work instruction in practice
at the time
of the offence. It set out the procedure to be followed when
maintenance work was to be performed on an unguarded machine (that
is, when the
power supply had not been isolated). Two steps to be followed are set out in
the agreed facts:
(a) "The Gin Manager or Supervisor is to be notified that a machine is to be run unguarded."
(b) "The unguarded machine must have an observer and/or a lookout man near its isolation switch at all times while the machine is running."
15 On the morning of 8 March 2007, Mr
Gaston instructed Mr Bella to load spools of wire and bolt down the Strapper
carrier of "Gin
No 5". Mr Gaston then went down to the Press Pit to carry out
the maintenance work, following the preparations he had made the day
before.
16 Mr Bella completed the task assigned to him by Mr Gaston. He then
commenced another task which involved feeding the wire through
the Strapper
heads. He encountered a difficulty feeding the wire through Strapper head A
because the position of the Press Console
was obstructing his access. It will
be recalled that although the captive key had been removed from the Press
Console by Mr Gaston
the day before, electrical power was still being delivered
to the Strapper heads via the electrical cabinet (the main power supply).
The
captive key had, however, isolated the power to the moving parts of the Strapper
and Press which had been rendered immobile.
As a result, Mr Bella could not
reposition the Strapper so that he could gain access to Strapper head A. Mr
Bella asked the electrician,
Mr Sutherland, if he could "make the Strapper so he
could move it". Neither Mr Bella, nor Mr Sutherland, discussed this step with
Mr Gaston or with any other person.
17 Mr Sutherland, in compliance with Mr Bella's request, reconfigured the
wiring (by changing two wires) in a coil control relay housed
inside the main
electrical cabinet. As a result, power was restored to the Strapper. His
actions overrode the local isolation of
the Press Console undertaken the
previous day by Mr Gaston following the removal of the captive key. Mr
Sutherland was able to restore
power to the Strapper because the electrical
cabinet had not been "locked out". Locking out the electrical cabinet (by way
of a
padlock for example), according to the agreed facts, prevents it from being
"powered up".
18 According to the agreed facts:
Manual restoration of power to the Strapper by by-passing the local isolation could have been prevented if power had been isolated at the Electrical Cabinet and a padlock applied to the grey mains isolator level on the Electrical Cabinet.
19 When the Strapper was installed a
Manual (IFP Ultra Twist Operator Manual) was supplied to the defendant which
provided (on page
4):
It is mandatory for the main electrical service panel to be locked out/tagged out before performing any service or maintenance on the machine.
20 In oral examination, during the
sentence proceedings Mr Sutherland's attention was directed to the procedure set
out on page 4
of the Manual. He recognised the document but said that as at 8
March 2007 he could not "specifically" recall having received any
instruction or
training with regard to the procedure and did not recall having been shown page
4 of the Manual. Mr Sutherland, on
8 March 2007, however, was not intending to
perform any service or maintenance work on the Strapper. He reconnected the
power supply
so that Mr Bella could gain access to the Strapper head in order to
feed through the wire. Before Mr Bella could gain access he
needed the power
restored to the Strapper so it would move.
21 As a result of Mr Sutherland's actions, the Strapper was in an
"unguarded" condition. This meant that the procedure set out in
SWG190 should
have been followed and Mr Bella (and/or Mr Sutherland) should have notified Mr
Gaston, the Gin Manager, that the Strapper
was to run "unguarded". Nor did Mr
Bella (nor Mr Sutherland) arrange for an observer or a lookout man to be
stationed near the Strapper's
isolation switch while the machine was running.
As events transpired, however, this last mentioned procedure would, in all
probability,
have been of little utility. The first mentioned procedure on the
other hand would have alerted Mr Gaston to Mr Bella's intentions,
and
appropriate action may have been taken. Unfortunately, this did not occur.
22 Following the wiring by-pass, Mr Sutherland remained in the vicinity
of the Strapper for a short while and observed Mr Bella move
the Strapper and
tie a knot using the Strapper "A" head in order to test the knotter box. Mr
Sutherland also helped Mr Bella tie
a knot by handing him the wire loop.
23 Mr Sutherland returned to his desk. Shortly after he heard a rapid
movement followed by a heavy expulsion of air. He looked in
the direction of
the Strapper and saw that Mr Bella was trapped between the Strapper and a
material column of the press. Mr Sutherland
ran to the Electrical Cabinet and
switched off the main electrical isolator. He then called for assistance. Mr
Bella was taken
to Moree Local Hospital and was pronounced dead as a result of
crush injuries sustained to his head and chest.
24 An incident report generated by the defendant after the accident
revealed a defect in the Strapper's "homing sequence" which meant
that it had
failed to return to its "home position" within the specified timeframe. Testing
by Jamie Condon, an electrical manager
employed by the defendant, identified
that in 97 per cent of homing sequences, the Strapper Carriage would stop for
variable periods
of time at different locations along the Strapper track and
then restart and complete the homing sequence. According to the prosecutor,
who
gave evidence during the sentence proceedings, Mr Condon discovered that one of
the controller units (the Lexium Controller)
for the Strapper had malfunctioned
and that the LED screen on the unit had failed to display the error message once
the fault occurred.
In cross-examination, the prosecutor agreed that as a
result of the malfunction the Strapper Carriage could move erratically along
the
track towards the "home position" and without warning. It appears to have been
accepted by the parties that this is what occurred
at the time of the
accident.
25 Other evidence also established that the Lexium Controller was a
sealed unit containing proprietary software which the defendant
could not access
for the purpose of carrying out internal repairs. After the Strapper was
installed the manufacturer, IFP, had carried
out annual maintenance on the
machine and no issues had been identified by it as a result of this maintenance
in relation to the
Lexium Controller.
Disputed particulars
26 Disputed particular (b) alleges a failure to provide both Mr Bella and
Mr Sutherland with information and instruction, "in relation
to the isolation of
power and maintenance of the Strapper" necessary to ensure Mr Bella's, and/or,
Mr Sutherland's safety while maintenance
was being undertaken on the Strapper.
(The alternative proposition in particular (b) was said to arise because Mr
Sutherland was
in the vicinity of the Strapper when Mr Bella moved it.)
27 In oral submissions, the prosecutor relied on alleged failures of the
defendant to ensure that Mr Bella and Mr Sutherland were
adequately informed and
instructed about the procedures outlined in SWI173, SWG190 and page 4 of the
Manual.
28 According to the prosecutor, Mr Gaston only partly complied with
SWI173, that is, he removed the captive key but did not apply
a padlock or
danger tag to the emergency stop button (ESB) on the press console. The
relevance of Mr Gaston's failure to complete
this second step was said to
demonstrate that the defendant's "paper system" was not followed.
29 It is difficult to see what relevance Mr Gaston's actions with respect
to the procedure outlined in SWI173 could have to particular
(b). The
particular is specifically directed to a failure on the part of the defendant to
provide necessary instruction and information
to Mr Bella and Mr Sutherland. It
does not refer, either expressly or impliedly, to Mr Gaston, or to any other
employee of the defendant.
30 The risk to safety was characterised by the prosecutor as the risk of
being struck by the unguarded, moving Strapper once the captive
key system had
been bypassed (by Mr Sutherland). Mr Sutherland's actions had nothing to do
with SWI173, which concerned the local
isolation of machinery. Had Mr Gaston
fully complied with SWI173 and applied a padlock or danger tag to the ESB on the
Press Console,
this would have had no impact at all on the risk to Mr Bella's
(or Mr Sutherland's) safety. Mr Sutherland's actions in overriding
the local
isolator (the captive key) were accompanied by his reconfiguring of the wiring
in the main electrical cabinet. He would
have been able to accomplish this even
if Mr Gaston had fully complied with SWI173.
31 SWG190 was the relevant procedure that should have been followed by
Messrs Bella and Sutherland. The failure to follow a procedure
formulated by
the defendant does not equate, however, to a failure on the part of the
defendant to provide the necessary, or adequate,
information and
instruction.
32 The effect of Mr Sutherland's actions in bypassing the captive key
system was that the Strapper would run in an unguarded state.
SWG190 therefore
was the applicable procedure. The first step in the procedure required to be
undertaken was that the Gin Manager
or supervisor was to be notified that the
Strapper was to be run unguarded. Mr Gaston was the Gin Manager. He was not
notified
by either of the two workers of their intentions. The work Mr Bella
intended to perform following Mr Sutherland's bypass of the
captive key system
was not authorised work. As earlier mentioned, if Step 1 of SWG190 had been
followed, Mr Gaston may have taken
appropriate action to ensure both workers
were not placed at risk.
33 The issue which arises here for consideration however is the adequacy
of instruction and information, necessary to ensure the safety
of Mr Bella and
Mr Sutherland.
34 Both Mr Bella and Mr Sutherland were experienced, senior and
well-regarded employees. Mr Sutherland trained apprentices in the
SWG190
procedure. He was, therefore, well-aware of the procedure. Mr Bella who, as a
Ginner, performed maintenance and supervision
work, would, in my view, have also
been aware of the procedure. The contrary position in any event was not relied
upon by the prosecutor.
In oral evidence, Mr Sutherland explained that SWG190
was used when the electrician needed to override interlock safety devices
which
were present on a number of machines. The procedure involved re-wiring the
interlock so that the machine remained operational
in order that testing and
observation of the machine could be undertaken while the machine was
operational.
35 These matters, in my view, suggest that Mr Bella and Mr Sutherland
were in fact the recipients of adequate or necessary information
and instruction
with regard to SWG190. Both were experienced, senior employees. The evidence
with regard to Mr Bella in particular
suggests that he was very highly regarded.
Both men were senior supervisors. Mr Sutherland instructed his apprentices in
the SWG190
procedure. In these circumstances, the requisite causal connection
between the failure of instructions, etc, with regard to SWG190,
and the
resultant risk is not made out.
36 This leaves page 4 of the Manual. Mr Sutherland, in his evidence, did
not recall receiving any instruction (or training) about
the matters identified
on page 4 of the Manual. On the other hand, he displayed a detailed knowledge
and understanding of lock out
and tag out procedures, with which page 4
deals.
37 As with SWI173, however, it is difficult to see the relevance of the
procedures on page 4 of the Manual to the risk to safety to
which Mr Bella was
exposed at the time of the incident. The risk to Mr Bella (and Mr Sutherland)
arose after the Strapper was no
longer isolated. The procedures at page 4 are
directed to isolating the power to machinery.
38 In any event, even if Mr Sutherland's attention had not been directed
to the relevant contents on page 4 of the Manual, I have
no doubt that he was
nevertheless aware of the procedures and well-versed in their implementation.
He was, after all, a senior electrician
who trained the defendant's apprentices.
The procedure outlined on page 4 is directed to the isolation of the Strapper,
"before any
servicing can be performed". The defendant relied on the confining
of the procedure to servicing, submitting that the work performed
by Mr Bella at
the time of the incident could not be characterised as "servicing work".
Nevertheless, on the same page there appears
a procedure for locking out or
tagging out the "main electrical service panel" before performing any service
or maintenance (my emphasis) on the Strapper. I have no doubt, given Mr
Sutherland's experience and seniority that he was also aware of, and well
capable of implementing, that procedure. It was not however his intention (or
Mr Bella's) to lock out or tag out the main electrical
service panel (which I
take to be the same thing as the main electrical cabinet).
39 Mr Sutherland's actions therefore in returning power to the Strapper
may be construed as a failure on his part to follow the procedures
on page 4 of
the Manual, but it does not follow from this that the defendant failed to
provide adequate and necessary instruction
to either Mr Bella or Mr Sutherland
"in relation to the isolation of power and maintenance of the Strapper".
40 Again, given Mr Bella's experience in maintenance matters, and his
seniority, there can be little or no doubt that he was also
aware of the
procedure at page 4 of the Manual. The work he was authorised or instructed to
do by Mr Gaston, however, did not involve
returning power to the Strapper. Nor
could it be described as a logical next step in the work he was instructed to
perform. There
is no obvious connection between loading spools of wire and
bolting down the Strapper head and then proceeding to feed the wire through
the
Strapper heads, which was work Mr Bella was not instructed to do and which could
only be accomplished by overriding the captive
key system earlier set up by his
supervisor, Mr Gaston. According to Harvey John Gaynor, the defendant's General
Manager (whose
evidence was not challenged) Mr Bella was instructed by Mr Gaston
to perform work on the battery condenser located elsewhere in the
Gin after he
had completed the two earlier tasks Mr Gaston had assigned to him.
41 The prosecutor has therefore failed to establish beyond reasonable
doubt the requisite causal nexus between this failure as particularised
and the
resultant risk to safety.
42 A similar conclusion follows for the same reasons with regard to
particular (d) which alleges a failure to supervise Mr Bella and
Mr Sutherland
while maintenance work was being undertaken on the Strapper.
43 The work being undertaken (which resulted in the relevant risk to
safety) was unauthorised and against all available and known
procedures (in
particular SWG190). In addition, (although more a pertinent consideration in
relation to the defence provisions under
s 28) it cannot have been contemplated
by the defendant that two such experienced and senior workers would fail to
follow documented
procedures, of which both were aware, to conduct work that
neither was authorised to do and which exposed them both to serious risk
to
their safety. The principle of pro-activity which requires a defendant to
factor into a safety regime circumstances where employees
are careless,
negligent, inattentive, or even disobedient should not be relied upon in
circumstances where the employees in question
were experienced, senior, highly
regarded and whose job descriptions included supervisory responsibilities at a
relatively senior
level, and who had been trained and instructed in the relevant
procedures.
44 The prosecutor also sought to place reliance on a decision of
Peterson J in WorkCover v Kevin R Sheather Services Pty Ltd [2001]
NSWIRComm 74 for the proposition that even if there were no specific
instructions to an experienced employee not to do something there would still
be
a failure to supervise in circumstances where the work was capable of being
performed and the provision of equipment enabled.
The decision, in my view,
does not assist the prosecutor. It is readily distinguishable. In
Sheather, the defendant was found guilty of a failure to supervise. One
factor persuasive of the finding was that the supervisor of workers
who were
performing work on a live switchboard box was aware of the work being performed
and of the fact that the switchboard box
was live while the work was being
performed.
Systems of work prior to offence
45 I return now to consider the charge to which the defendant has pleaded
guilty by reference to particulars (a), (c) and (e).
46 Mr Gaynor, the defendant's General Manager, has set out in an
affidavit the defendant's safety systems in place at the Midkin Gin
prior to the
offence. The affidavit evidences a wide-ranging and comprehensive safety
regime. In summary, that regime included
the following safe work systems in
force prior to the incident:
(a) Occupational Health and Safety Policy;
(b) Adoption of National Safety Council of Australia Five Star rating system;
(c) Adoption of Industry Codes of Practice;
(d) External and internal occupational health and safety training;
(e) Systematic hazard identification, risk assessment and control;
(f) Induction programmes;
(g) Continuous Improvement Action Plan ("CIAP");
(h) Competency Assessments;
(i) JSA and SWI procedures;
(j) Development and implementation of Workplace Policies including but not limited to:
(i) Equipment Isolation and Energy Dissipation Policy;(ii) Hazardous Substances Polices;
(iii) New or Modified Plant, Equipment, materials or Work Methods Policy;
(iv) Physical Hazard Identification Survey Policy;
(v) Standard Work Instructions Policy;
(vi) Sun Safety at Work Policy;
(k) Safety (CIAP) meetings;
(l) Tool box talks;
(m) Permit systems for specific hazard situations;
(n) Checklists for new or modified machinery;
(o) Workplace signage;
(p) Disciplinary procedures for non-compliance;
(q) New machinery training procedures;
(r) Emergency procedures;
(s) Ongoing training;
(t) Physical and electrical safety systems (such as physical guards, interlocks including captive key systems, and presence-sensing safety mats and laser scanner systems);
(u) Workplace inspection checklists scheduled on recurrent activities calendar;
(v) Hazard/Near miss reporting;
(w) Incident investigation and analysis;
(x) Employee health assessments; and
(y) Internal and external auditing.
47 The Strapper was assessed at the time of its installation on 30 March
2005. According to Mr Gaynor:
As a consequence of the assessment, additional Safety Mats were installed in the areas along the front and side of the Strapper and Press. Some existing Safety Mats and a presence-sensing laser scanner were also reconfigured to cater for the Strapper. As recorded in the Auscott Risk Register, Mr Sutherland oversaw this work. Mr Gaston, Ben Pollard and Mr Bella oversaw the introduction of other measures arising from the same assessment.
48 In addition, following the
initial assessment the defendant has kept a Midkin Risk Safety Calculator
Evaluation and Risk Register
with entries showing safety measures that were
implemented for the Strapper.
49 Mr Bella is described by Mr Gaynor as a very experienced ginner, who
had developed a broad knowledge of the ginning process, production
methods and
gin machinery. In particular, he had extensive knowledge of the Strapper and of
the Press having worked on and been
involved with the maintenance of both items
of machinery since installation. Mr Bella had also completed numerous training
courses
and other courses involving the development of supervisory and
management skills.
50 Mr Sutherland, according to Mr Gaynor, is a licensed electrician who
has also completed numerous courses run by TAFE and NSCA involving
matters such
as, "OH&S for Frontline Supervisors and Managers" and "Operational
Management". Mr Sutherland had also completed,
prior to the offence, an
in-house training session which included "team building".
51 Standard work instructions were developed by the defendant prior to
the offence. They include SWI173 and SWG190 which have been
earlier dealt with
in these sentencing reasons and need no repetition.
52 These safety systems attest to a genuine commitment on the part of the
defendant to safety matters in the workplace. As such,
their existence and
implementation prior to the offence operate to reduce the objective seriousness
of the offence.
Reasonably foreseeability of the risk
53 The risk to safety has been earlier described. According to the
prosecutor, prior to the incident, the defendant was on notice
of the importance
of isolating all power services before maintenance work was performed on the
Strapper. Page 4 of the Manual was
relied upon by the prosecutor as
demonstrating the defendant's prior knowledge in this regard.
54 The risk to safety arose, however, when the machine was in an
unguarded state. Page 4 of the Manual, as previously noted, deals
with a
procedure for isolating the machine. Nevertheless, the defendant was on notice
of the importance of safety measures when
machinery was operated in an unguarded
state. SWG190 is an example of a procedure formulated by the defendant in the
event such
tasks were to be undertaken. The incident demonstrates that SWG190
was not followed, and as a result, gave rise to the risk to the
safety of Mr
Bella in particular.
55 The issue of foreseeability of the risk arises in circumstances where
Mr Bella and Mr Sutherland performed work they were not authorised
to do and
failed to follow procedures in relation to which they had received previous
instruction and training. There may be an
element of foreseeability of risk in
circumstances where the Strapper was not adequately guarded and where the
defendant failed to
adequately assess the risks, both of which constitute
particulars of the offence to which the defendant has pleaded guilty. Other
than this, I fail to see that the risk to safety was reasonably foreseeable in
the way characterised by the prosecutor. The defendant
contended that the
foreseeability of the risk was at the "lowest end". Given these matters, I am
prepared to find that the foreseeability
of the risk to safety was at the low
end of the spectrum.
Conduct of the employees
56 The conduct of Mr Bella and Mr Sutherland, in my view, is also
relevant to an assessment of the objective seriousness of the offence.
Both
employees performed work they were not authorised to perform. This factor alone
carries little weight, however, given their
respective experience and expertise.
It would be expected that persons of their skill and experience were more than
capable of showing
initiative in the performance of tasks outside their
immediate set of instructions. It is another matter entirely, however, when
the
work being undertaken without authorisation exposes both men to serious danger,
largely of their own making. The conduct therefore
operates to reduce the
culpability of the defendant, ultimately responsible for their safety: see
Riley v Australian Grader Hire Pty Ltd (2001) 103 IR 143 at 145;
Inspector Colin Wall v Orica Australia Pty Limited [2009] NSWIRComm 146
at [15]- [16].
Availability of remedial measures prior to the offence
57 A factor which adds to the objective seriousness of the offence was
that relatively simple steps could have been implemented in
order to avert the
risk. The agreed facts set out an example of one such step:
Following the incident on 8 February 2007, Auscott modified its electrical isolation procedures for work on machines involving the motor/actuator or electrical componentry so as to require, amongst other things, removal and isolation of the machine's control and main fuses.
Consequences of the breach
58 The consequence of the defendant's breach of the Act carried with it
the risk of significant injury. The tragic death of Mr Bella
manifests the
degree of seriousness of the risk to safety.
Deterrence
59 General deterrence also falls for application. Working on machinery
that has not been isolated carries with it obvious dangers
in relation to which
the importance of implementing and promulgating appropriate safety regimes must
be emphasised.
60 Specific deterrence also arises for application. The defendant
continues in business at the Midkin Gin. Its comprehensive safety
regime which
has been implemented at the Midkin Gin reduces to some extent the overall
component of penalty otherwise attributable
by reason of the application of
specific deterrence.
Maximum penalty
61 The defendant has prior convictions and therefore faces a maximum
penalty of $825,000.
Subjective factors
62 The defendant entered a plea of guilty to the charge at the earliest
or first reasonable opportunity. I propose, in these circumstances,
to assess
an appropriate penalty for the utilitarian value of the plea at 25 per cent.
63 As a separate consideration from the utilitarian value of the plea,
the defendant is also entitled to leniency in recognition of
the remorse shown
by the plea of guilty.
64 The defendant has prior convictions. This disentitles it to leniency
otherwise available to offenders not adversely recorded.
65 The defendant also co-operated with WorkCover during the investigation
and prosecution of the offence.
66 Mr Gaynor said that the defendant's management was "personally
devastated" by the accident which he acknowledged had a wide reaching
impact on
the defendant, its employees and their families. In his affidavit, Mr Gaynor
expressed contrition and remorse for the
tragic death of Mr Bella on behalf of
the defendant, his co-workers and their families. He explained:
As part of a small rural community we knew Mr Balla and his family well outside of the workplace which only adds to the grief we feel.
The manner of Mr Bella's death at work has had a traumatic and continuing effect on his co-workers including senior management and, in particular, on the co-workers who rendered such assistance as they could immediately following the accident. The physical and emotional toll on me and my family has been huge and I know the same is true for other Auscott Managers at Midkin and in Sydney.
I and other managers are sincerely regretful that an accident such as this has occurred on our premises.
Much as we wish that we could, we cannot undo what has occurred, but have worked constantly since the accident to improve our standards above and beyond what we had in place at that time. Our fervent aim is to avoid any repeat of this type of tragedy or indeed any lesser injury. At present we have not suffered any lost time injury at Midkin since May 2007 (over 800 days).
67 These matters provide evidence upon
which the Court may take into account the defendant's remorse in mitigation of
the penalty
to be imposed. As required under s 21A(3)(i) of the Crimes
(Sentencing Procedure) Act 1999 (CSPA), the defendant by its expressions of
remorse and its conduct following the offence has provided evidence upon which
it
may be concluded that it has accepted responsibility for its actions and has
acknowledged the loss caused by those actions.
68 The defendant, following the accident, also provided assistance to Mr
Bella's family and to employees, the latter group receiving
ongoing counselling
assistance. The extent of the assistance rendered is set out in Mr Gaynor's
affidavit:
Auscott's employees at Midkin and senior management knew Mr Bella and his family well so were determined to do whatever could be done to help his family at this tragic time.
On the day of the accident several members of the Midkin management team and gin team (including myself) visited Mr Bella's family to offer our condolences and whatever comfort and assistance we could. I personally maintained regular contact with Mr Bella's partner Melissa Pollard and his brother David between the accident and Mr Bella's funeral and for some time beyond that.
An early issue for Melissa was access to cash for day to day expenses as Mr Bella's accounts were "frozen" and Auscott provided her with $1000 cash to assist.
Auscott also provided a rental car at its own expense for the use of Mr Bella's family members who had travelled from interstate. Auscott also provided a rented minibus and driver to transport mourners to and from the funeral. Auscott printed over 300 colour booklets for the service, which included some photos drawn from our archives. The funeral costs were paid by Auscott.
Auscott's Midkin site was shut down for a day to allow all employees to attend the funeral, and senior employees from the head office and other operational sites also attended.
At the request of Mr Bella's family, Auscott made the arrangements for a "wake" held at the Moree Services Club, and paid all costs.
In August 2007, when payment to Melissa Pollard from the Workers' Compensation insurer (QBE) was delayed, Auscott provided her with $6,000 on an interest-free basis.
The tragic death of Mr Bella has been heartfelt through the whole Auscott organisation. It has had significant and profound impact on management and our employees in general.
All of the employees at Midkin were offered counselling and any other assistance that could be provided. A number of employees made good use of that counselling. This offer of assistance remains open to employees to this day.
All work at the Midkin Gin was halted immediately and gin employees left the site as soon as investigating authorities allowed. The employees were allowed to set their own timetable for returning to work, and chose to do so the following day, but at a measured pace, their first work being re-induction and safety auditing of the machinery. I was careful not to apply any pressure to resume normal operations, preferring to allow the employees to reach emotional preparedness at their own pace.
69 The defendant
has also exhibited good corporate citizenship through its many community
activities and assistance programmes, particularly
in relation to its support
for the indigenous community. These matters are also set out in Mr Gaynor's
affidavit:
Throughout the 46 years that Auscott has been a part of the NSW rural community and Australian Cotton Industry it has placed high priority on supporting both. Numerous community organisations and charities are sponsored each year in all three rural areas where the company operates.
Auscott provides three tertiary education scholarships each year. These scholarships, awarded to students who complete their schooling in the Gwydir, Namoi and Macquarie Valleys provide financial support for the duration of a tertiary degree. The scholars are free to choose their own courses and there are no obligations on them other than to pass. 120 students have been awarded scholarships since the program's inception, and the annual contributions by Auscott are in excess of $100,000 (2008 calendar year $101,178).
Auscott contributed $225,000 to establish a telehealth centre at Warren Multi-Purpose Health Centre. This contribution, along with the Auscott Education Scholarship demonstrate Auscott's genuine understanding of the particular challenges and needs faced by rural communities in which it operates, and its commitment to playing its part in meeting those needs.
Within the cotton industry Auscott is well known as a stable employer, strong supporter of research and development, an innovative and high-quality farmer and ginner and a contributor to many industry bodies. As well as conducting internal research trials Auscott has provided sites and cooperation for many industry researchers in both farming and ginning. The company's average annual expenditure on Research and Development is in excess of $1,250,000.
Moree, Narrabri and Warren, like many western NSW communities, have significant indigenous populations who suffer economic and social disadvantage. In 1997 the Gwydir Valley Cotton Growers' Association commenced the Aboriginal Employment Strategy ("AES"), of which I was a committee member during its early development. AES, which now has offices in three states and the Northern Territory, has helped Moree change from a being a town with a reputation for racism to being recognised nationally as a leader in reconciliation.
Auscott has employed indigenous people through AES and provided equipment, staff and facilities for training programs run by the AES.
70 Following the accident the defendant
took extensive remedial measures. These have been set out in Mr Gaynor's
affidavit as follows:
Management Action
Immediately after the accident, Auscott's Chief Executive Officer, Dave Anthony, ordered safety audits across the whole of Auscott's ginning operations to ensure that all safety systems were working as intended. The audit process delayed the start of ginning by several weeks and created significant commercial issues however Auscott management considered it was imperative that the audit was not compromised. Accordingly, no gin could start operation until the valley General Manager of the site was satisfied with the audit results.
In addition, at the Midkin site an external auditor was engaged to check the rigour of this internal audit process, with the aim of assuring Auscott Management, employees and their families that the audit process was sound.
The internal audit of safety systems of all gin machinery has now become a standard annual pre-ginning process.
Dave Anthony visited each of the Auscott operational sites and held meetings with all employees. The meetings focused on the tragedy at Midkin and the sense of loss, the importance of occupational health and safety in the workplace and restating Auscott's occupational health and safety policy.
On 27 March 2007, 1-2 August 2007, 22 November 2007 Auscott's senior management held three further meetings with employees to further reinforce the company's safety philosophy. The first meeting was with senior management. The second meeting involved all line managers. The third meeting involved all Auscott employees (excepting some administrative employees based in Sydney) and involved a full day' workshop at Narrabri.
Another meeting of all line managers was held on 24 June 2008. This meeting focussed on the importance of "interdependence" in safety throughout the company, and also included a final sign-off on a new "Take 5" system to be implemented company-wide.
Several of these meetings have included an external Human Resources consultant as well as speakers from other businesses (Rio Tinto, Fletchers International).
Re-induction of Gin Employees
All of the employees working in the Midkin Gin underwent a re-induction and training program. As part of the re-induction, the gin employees were required to successfully complete a competency assessment in the use and application of SWG173.
Revised Standard Work Instructions
SWG 173
Auscott undertook a comprehensive review of SWG 173 in conjunction with WorkCover. The changes to SWG173 were in compliance with the WorkCover Improvement Notice (7-128442).
Corporate Standard Work Instructions - CSWI 001 and CSWI 002
In October 2007, SWG173 was upgraded to Corporate Standard Work Instruction ("CSWI 001") which applies to the "Isolation of Fixed Wired Electrically Powered Plant".
CSWI 001 (as was also the case with SWG 173) cannot apply when tying test knots with the Strapper as power is required for the wire feed and knotters.
In May 2007, SWG 190 was revised and upgraded to a permit based system which is now known as CSWI 002 ("CSWI 002") and which applies to "Running a Machine Unguarded or Without Safety Devices". CSWI 002 requires an employee to step through a permit form and obtain approval from the Gin Manager/Shift Supervisor and in some cases Electrician as well, prior to running any machine in an unguarded state.
Training in CSWI 001 and CSWI 002
The new corporate procedures were implemented at training sessions for Permanent Employees firstly by reading the documents, secondly - having the terms of the documents explained to them using a PowerPoint presentation, thirdly - physical demonstration of the SWI procedures and fourthly - by performing the SWI procedures under supervision.
Changes to Strapper
Further changes were made to the electrical and physical components on the Strapper. For example, the wiring of the Safety Mats on the Strapper was incorporated into a circuit which, when interrupted, stops all control power to the Strapper.
In addition to the electrical changes, a fixed Perspex guard has been installed which prevents access from of the front of the Press area across the Press console which prevents access to the Press console from the front area of the Strapper and Press - which is the area where Mr Bella was trapped.
Review of Policies, Procedures and Equipment
Various policies and procedures were reviewed and several site specific policies were standardised as corporate policies applying across all sites. This process is ongoing.
A corporate Equipment Isolation and Energy Policy, and associated procedures (including CSWI 001) was introduced to implement consistent standards across the company.
Auscott has spent $127,108 since the accident on installation of additional lockable local isolators at the Company's gin sites. The program of installing safety systems such as interlocked guards, safety mats and captive key systems has also continued, with expenditure since the accident on this program amounting to $75,061.
Changes to OH&S Coordination
On 30/3/2007 Chris Hogendyk, General Manager of Auscott's Macquarie Valley Operations, was appointed as Chair of a committee of Auscott's occupational health and safety coordinators at each site. The appointment was made so as to strengthen the communication between the various farming and ginning operations.
71 All of these matters will be
taken into account by the Court in mitigation of the penalty to be imposed.
Victim Impact Statements
72 The Court also received statements from Mr Bella's mother, Marcia
Livermore, and his two brothers, Kelvin Bella and David Bella.
I have read
those statements which attest to very close family bonds, and, a sense of deep
loss and grief. The Court expresses
its profound sympathies to Mrs Livermore,
Mr Bella's mother, and to his two brothers, Kelvin and David Bella, for the loss
of a son
and a brother in such tragic circumstances.
Penalty
73 In determining penalty, the Court has taken into account the objective
factors and the subjective factors, including the absence
of prior convictions.
Factors, both in mitigation and aggravation of the offence, have also been
considered by reference to the
CSPA, in particular, s 21A.
Costs
74 The defendant submitted that findings that particulars (b) and (d)
have not been made out, "may sound to some extent in costs".
No authority was
relied upon in support of the submission. It seems to me that where a defendant
has pleaded guilty to a charge,
as here, but has successfully disputed two of
five particulars, it is not thereby entitled to an apportionment of its costs:
see
for example, WorkCover Authority of New South Wales (Inspector Keenan) v
Leighton Contractors Pty Ltd (2005) 147 IR 329 at [12] per Walton J,
Acting President, and Staff J.
Orders
75 In
Matter No. IRC 250 of 2009, I make the following orders:
(1) The defendant, Auscott Limited, is convicted of the offence and fined
$90,000 with a moiety to the prosecutor.
(2) Auscott Limited is to pay the reasonable costs of the prosecutor as agreed, or in the absence of agreement, as assessed.
___________________
LAST UPDATED:
22 July 2010
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2010/102.html