![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Industrial Relations Commission of New South Wales |
Last Updated: 23 July 2008
NEW SOUTH WALES INDUSTRIAL RELATIONS COMMISSION
CITATION :
Transport Workers Union of New South Wales v Sydney Civil Excavation Pty Ltd
[2008] NSWIRComm 1049
FILE NUMBER(S):
2073
HEARING
DATE(S):
28/04/08 and 29/04/08
DATE OF JUDGMENT:
27 June
2008
PARTIES:
APPLICANT
Transport Workers Union of New South
Wales
RESPONDENT
Sydney Civil Excavation Pty Ltd
CORAM:
Macdonald C
CATCHWORDS: Dispute Notification - s332 of the
Industrial Relations Act 1996 - allegation by Union that Respondent underpaid
certain contract carriers who performed work for the Respondent - conciliation
failed to resolve underpayment claim - Hearing - Held that carriers' work for
Respondent regulated by a Contract Determination -
Respondent had engaged the
carriers for excavation work and underpaid the carriers for cartage work -
appropriate underpayment orders
made by Commission.
LEGAL
REPRESENTATIVES
Transport Workers Union of New South Wales
Mr R
Olsen
Sydney Civil Excavation Pty Ltd
Mr S Sarkis
CASES CITED:
LEGISLATION CITED:
Industrial Relations Act 1996
TEXTS CITED:
JUDGMENT:
INDUSTRIAL RELATIONS COMMISSION OF NEW SOUTH WALES
CORAM: MACDONALD C
27 June 2008
Matter No IRC 2073 of 2007
Transport Industry -
Excavated Materials Contract Determination
Notification under
section 332 of the Industrial Relations Act 1996, by the Transport Workers Union
of New South Wales, of a dispute with Sydney Civil Excavation Pty Ltd re
underpayments to contract
carriers
DECISION
[2008] NSWIRComm 1049
1 The Transport Workers Union of New South Wales ("the Union") lodged
a dispute notification, pursuant to section 332 of the Industrial Relations
Act 1996 ("the Act"), against Sydney Civil Excavation Pty Ltd ("the
Respondent").
2 The dispute notification set out the dispute in Schedule A to that
notification and stated that the Respondent engages a number
of contract
carriers under the Transport Industry - Excavated Materials Contract
Determination ("the Determination") and the Respondent was paying rates
(below that set by the Determination) to a number of the carriers who are
also
members of the Union.
The dispute notification sought the assistance of the Commission.
3 The matter was set down for a compulsory conference on 22 November 2007
and a Report Back on 14 December 2007. Failing resolution
of the dispute, the
matter was programmed for a Hearing - including the filing of evidentiary
material by certain dates.
4 The Union filed its evidentiary material on 19 February 2008, being
four days overdue.
The Respondent did not file any evidentiary material.
5 The Hearing took place on 28 and 29 April 2008.
The Union was represented by Mr R Olsen, union official. The Union filed the following witness statements:
Mr Robert Tabet
Mr Jerry Kemplen
Mr Phillip Mizzi
Mr Joe Dimech
Mr Paul Xiberras
Mr Richard Webb
6 All of the foregoing witness
statements were made out by contract carriers who deposed they had carried out
work for the Respondent
and had been short paid per the Determination.
7 Only four of the deponents were available to give evidence: Messrs
Xiberras and Webb were not available but Mr Sarkis did not object
to the witness
statements of those two drivers being entered into evidence.
8 Although the Respondent did not file any material, Mr Sarkis sought to
have a Mr Joe Constantine, project manager, give evidence.
This notification
was at short notice made on the first day of the Hearing.
The Union consented to that application by Mr Sarkis.
BACKGROUND
9 The Union filed a dispute notification on behalf of members of the
Union, who are owner-drivers.
10 Those members/owner-drivers were engaged by the Respondent said the
Union, to cart excavated material from one site to another
site.
11 The Union alleged that these members/owner-drivers were not paid their
full entitlement under the Determination for the cartage
work performed.
12 Conciliation failed to resolve the dispute.
FINAL SUBMISSIONS
For the Union
13 Mr Olsen, for the Union, put the following in final submissions.
(a) The six owner-drivers had performed cartage work for the Respondent.
(b) There is an industrial instrument (the Determination) that sets out the methods of remuneration for such cartage work (excavated material work).
(c) The Determination sets out two methods of remuneration: kilometre rates or hourly rates (or a combination of both).
(d) The Respondent's claim that it can set its own cartage rates for the owner-drivers is wrong given that the Determination applies.
For the Respondent
14 Mr Sarkis, for the Respondent, put the following in final
submissions:
(a) The Respondent and owner-drivers negotiated a rate for the job to be performed. If an owner-driver is subsequently unhappy about the rate then the owner-driver should discuss it with the Respondent.
(b) If there is a rate to be followed (as in a rate in the Determination), then every construction company in Sydney is guilty in not following the Determination rate(s).
(c) The evidence of the owner-drivers is that their documentation authorising cartage by the Respondent was not signed off by the appropriate Respondent officer - Mr Constantine.
(d) Many of the owner-drivers were organised by one owner-driver (Mr Tabet) to perform the cartage work and therefore he should be held accountable for the shortfall in rates paid for the work performed.
(e) The evidence of the owner-drivers is that they worked all day, excavating material for the Respondent, and did not take a meal break. This is against the law.
Union in Reply
15 Mr Olsen, in reply, put the following:
(a) There was no evidence that the owner-drivers did not have a meal break. The owner-drivers fit in their meal breaks with the work to be performed on the day.
(b) The Respondent is liable for the underpayments for the work performed and not Mr Tabet.
(c) The Determination sets out the rates to be paid and no lesser rate can be paid.
CONSIDERATION
16 The Union has filed a dispute notification under Part 4 - Dispute
Resolution, of Chapter 6 - Public Vehicles And Carriers, of the Act. The
dispute notification (s332) alleges that the Respondent has underpaid certain
contract carriers who performed cartage work for the Respondent.
17 The dispute notification was accompanied by a section 380 Particulars
Of Small Claim.
18 The Union alleged that the relevant industrial instrument regulating
the work of the contract carriers is the Transport Industry
- Excavated
Materials Contract Determination ("the Determination").
19 The Respondent denies that there has been any underpayment. The
Respondent asserted that the contract carriers performed cartage
work for an
agreed rate and therefore there can be no underpayments claim. The Respondent
also asserted that most of the contract
carriers were not engaged by the
Respondent but were engaged by one contract carrier (Mr Robert Tabet of Tabet
& Sons Earthmoving
Pty Ltd). The Respondent also contested the underpayment
claims on the basis that the cartage work, performed by these contract
carriers
in question, had not been signed off by the appropriate Respondent officer.
20 In considering the Respondent's case against the Union's claim for its
members, it is to be noted that the Respondent did not file
any material in
response to the six witness statements filed by the Union on behalf of the six
contract carriers. The only evidence
(apart from what fell during
cross-examination) put on by the Respondent, is that from Mr Constantine who
gave oral evidence. He
was only able to give evidence because the Union did not
object to Mr Sarkis' request to be able to call Mr Constantine. This call
was
made during the Hearing.
21 By not filing material, in response to the Union's filed material,
then the Respondent was not challenging the content of that
filed material. To
the extent that Mr Sarkis challenge the content during cross-examination, then
the Commission had regard as to
what weight to give to the challenged evidence
of the six contract carriers.
Similarly, the evidence of Mr Constantine had to be assessed as to what weight to give his evidence where it conflicted with that of the six contract carriers. Of course, if Mr Constantine gave evidence conflicting with that of any of the carriers, but such conflict was not put to the carriers by Mr Sarkis (when those carriers were in the witness box), then little weight (if any) could be given to the evidence of Mr Constantine where it conflicted with that of any of the carriers.
The Union's Claim
22 The Union is entitled to make an application for an order for a small
claim: s380(1) of the Act.
23 The maximum amount that an industrial court may order an employer to
pay an employee under a small claims application, is currently
$20,000 for any
one employee: s379(3) of the Act. Although this particular statutory
provision refers to "any one employee" (contra "contract carrier"), another
provision of the Act extends this small claims jurisdiction for employees to
also apply to contract carriers: s343(1)(j).
24 The amount of the small claim being pursued by the Union, on behalf of
the six contract carriers, is an amount less than $20,000
for each contract
carrier.
25 Given the foregoing jurisdictional criteria, the Commission finds it
has the jurisdiction to proceed in its deliberation of the
Union's claim.
The Determination
26 The Union asserts that the relevant industrial instrument governing
the work performed by the six contract carriers is the Transport
Industry -
Excavated Materials Contract Determination ("the Determination").
The Respondent's case (per Mr S Sarkis) was that if this Determination applied, then every construction company is guilty in not following this Determination. The rate to be paid to any contract carrier, said Mr Sarkis, was one struck between the Respondent and the contract carrier.
27 Having considered the evidence surrounding this issue, the Commission
finds that the work performed by the contract carriers is
work that is regulated
by an industrial instrument and that is the Determination (Ex 7).
28 The Determination (Vol 301 IG 1082), "applies to all contracts of
carriage of excavated and demolition material and to all contractors and
contract carriers engaged in
or in connection with such work...." (Clause
21. Area, Incidence and Duration).
29 The Respondent (Sydney Civil Excavation Pty Ltd), (emphasis
added) is engaged in work that falls within this definition of the Area,
Incidence and Duration Clause. Accordingly,
the Determination applies to these
contract carriers, in question.
The "Engagement" of the Carriers
30 Another aspect as to whether the Determination applied to these
contract carriers, was the claim of the Respondent that it did
not engage the
contract carriers. Instead, the Respondent asserted, five of the six contract
carriers were engaged by Mr Robert
Tabet of Tabet & Sons Earthmoving Pty
Ltd, and therefore Mr Tabet should make good any shortfall in remuneration.
31 The Commission rejects this submission for the reasoning set out
below.
32 Mr Sarkis did cross-examine Mr Tabet on this issue, but he denied he
had engaged the other carriers.
The Commission has highlighted the term, "engaged", because the oral evidence of some witnesses is that, for this term to have significance for the Respondent's case, it would have to be shown that Mr Tabet was a fleet owner. That is, it would need to be shown that he owned two or more trucks and was therefore in a position to "engage" these other trucks/truck drivers because these trucks/truck drivers would be employees of Mr Tabet.
33 Mr Kemplen gave evidence that Mr Tabet was not a fleet owner. (Tr
28/04/08 - p46, line 48 and 49). Mr Dimech denied he was "working
through Mr
Tabet" and said he was "working for Sydney Civil". (Tr 29/04/08 - p11, line 46
and 47).
34 It was not put, per se, to Mr Tabet, by Mr Sarkis (during
cross-examination), that Mr Tabet was a fleet owner. Mr Sarkis put to
Mr Tabet
that he had employed the other carriers. Mr Tabet denied that he had employed
them. (Tr 28/04/08 - p38, line 36 and 37).
Mr Sarkis, the Commission records,
did not bring any evidence to show that Mr Tabet was a fleet owner.
35 There was evidence, however, from Mr Tabet about how the other truck
drivers came to have knowledge that the Respondent required
other trucks
(carriers) to perform cartage work - as opposed to they were engaged by
Mr Tabet.
36 The evidence of the contract carriers is that they sometimes obtain
work by word of mouth. Thus, a company tells a contract carrier
that it needs a
number of truck drivers (carriers) to perform certain work. That contract
carrier then contacts his mates (fellow
carriers) and advises that there is
carrier work at such and such a work site - if they are interested.
37 Mr Tabet described this practice (as to work availability) as being
"like a network and we (the contract carriers) help one another
out." (Tr. 28/04/08 - p29, line 33 and 34).
Three other carriers who gave evidence, confirmed the foregoing "network" practice: Mr Kemplen (Tr 28/04/08 - p47, line 48 to p49, line 25); and Mr Dimech (Tr 29/04/08 - p12, line 24 to 37).
38 A related issue, as to the engagement, was put by Mr Sarkis during
cross-examination. This issue was that the proper authorised
officer had not
signed off on the paperwork of the various carriers as to the work performed by
them for the Respondent and therefore,
the carriers were not entitled to their
underpayment claim.
39 The Commission rejects this submission.
If the Commission was to accept this argument, then contract carriers could be working for no remuneration.
This submission leaves it open for a principal contractor to not only deny an underpayment claim but demand repayment of any monies given to a contract carrier for work performed for the principal contractor because the principal contractor "discovered" that the proper authorised officer had not authorised the carrier work performed.
40 The evidence of the carriers as to this issue was that they drove up
to the work site and were given a direction to carry out the
cartage work.
The evidence of Mr Kemplen was that a Charlie Ceccine was the Respondent's employee who organised the work for the contract carriers on a given day. (Tr 28/04/08 - p43, line 8 to 19) Mr Mizzi gave evidence that it was "the foreman" for the Respondent who signed the invoice on the job for work carried out. (Tr 29/04/08 - p3, line 28 to 33). Mr Dimech gave evidence that it was "the foreman" who signed the invoice for the work performed. (Tr 29/04/08 - p9, line 9 to 32).
41 In summary, the Commission finds that a representative of the
Respondent did allocate work to the contract carriers and the contract
carriers
were paid for the cartage work performed. The filed witness statements of the
carriers included documentary material about
the particular cartages
performed.
The Respondent paid the carriers for the cartage work performed.
The Respondent can not now advance an argument that the underpayment claims are invalid because Mr Constantine did not sign off on the work performed.
CONCLUSION
42 The Commission has considered all of the evidence surrounding the
Union's claim that six contract carriers were underpaid for the
cartage work
performed for the Respondent.
43 The Commission finds that the work performed by these carriers is work
governed by the Determination. And so, the Commission rejects
the Respondent's
submission that it was free to negotiate a rate for the excavation work with
each carrier and if the carrier did
not like the rate, then the carrier was free
to decide not to do the cartage work.
44 The Commission finds that it was the Respondent who engaged the six
carriers. They were engaged by the Respondent's representative
on the work
site.
45 The Commission finds that Mr Tabet did not engage the five other
contract carriers. To have done so would at least require that
Mr Tabet was a
fleet owner. Mr Tabet denied that he was a fleet owner. The Respondent brought
no evidence to show that he was a
fleet owner.
46 The Commission finds that the other five carriers learnt of the
cartage work availability through word of mouth - being the "network"
practice
that operates amongst carriers to pass the word around that there is a client
who requires carriers for its business.
47 The Union filed six witness statements on behalf of the six carriers
claiming under payment of monies, per the rates contained
in the Determination,
for the work performed for the Respondent.
Four of the six carriers gave oral evidence (Messrs Tabet, Kemplen, Mizzi and Dimech). Two of the carriers (Xiberras and Webb) were not available to give oral evidence in support of their filed statements. Despite they're not being able to do so, the Commission finds that the issues raised by the Respondent in cross-examination against the four carriers, are the same issues for Messrs Xiberras and Webb.
Accordingly, the findings of the Commission about those issues for the four carriers also apply to Xiberras and Webb.
48 The filed witness statements contained annexures being documentary
evidence about the billings (by the carriers) against the Respondent
for work
performed. The amount of the underpayments claimed were also set out by the
carriers. The underpayments were based on
certain rates found in the
Determination.
49 The Commission, in conclusion, finds that the Union has made out its
case that the Respondent has underpaid the six carriers, per
the Determination,
and makes the appropriate order against the Respondent in satisfaction of the
underpayment claims.
ORDERS
1. Sydney Civil Excavation Pty Ltd shall pay to:
(a) Tabet & Sons Earthmoving Pty Ltd, the sum of $1975.45; and
(b) J K Tipper Hire Pty Ltd, the sum of $788.70; and
(c) P & D Mizzi Pty Limited, the sum of $2209.93; and
(d) J & J Dimech Pty Ltd, the sum of $1302.76; and
(e) P & R Xiberras Tipper Hire Pty Ltd, the sum of $104.62; and
(f) Webbs Tipper Hire, the sum of $112.20,
within 21 days of the date of this order.
2. This order shall take effect on and from Friday, 27 June, 2008.
A Macdonald
Commissioner
LAST UPDATED:
30 June 2008
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWIRComm/2008/1049.html