![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales - Court of Appeal |
Last Updated: 8 February 2010
NEW SOUTH WALES COURT OF APPEAL
CITATION:
Zhao v Goodman &
Anor [2010] NSWCA 2
FILE NUMBER(S):
40012/09
HEARING
DATE(S):
19 November 2009
JUDGMENT DATE:
5 February
2010
PARTIES:
Yan Shuo Zhao
Marla Shoshana Goodman
Brian
Goodman
JUDGMENT OF:
Tobias JA Macfarlan JA McClellan CJ at CL
LOWER COURT JURISDICTION:
District Court
LOWER COURT FILE
NUMBER(S):
DC 976/06
LOWER COURT JUDICIAL OFFICER:
Johnstone
DCJ
LOWER COURT DATE OF DECISION:
1 October 2008
COUNSEL:
A: In person
R: M Dolenec (Ms)
SOLICITORS:
A: In Person
R:
Mills Oakley Lawyers, Sydney South
CATCHWORDS:
CONTRACTS –
Building contract – Identification of contract between parties –
Claim for rectification of defects
and completion of works – Cross-claim
for unpaid works – Where findings of primary judge based upon credit of
parties
– Requirement of appellant to overcome principle in Fox v Percy
LEGISLATION CITED:
Evidence Act 1995
Home Building Act
1989
CATEGORY:
Principal judgment
CASES CITED:
Cullen v
Trappell [1980] HCA 10; (1980) 46 CLR 1
Dowling v Rae [1927] HCA 5; (1927) 39
CLR 363
Fox v Percy [2003] HCA 22; (2003) 214 CLR 118
Sindel v Georgiou
[1984] HCA 58; (1984) 154 CLR 661
TEXTS CITED:
DECISION:
Appeal dismissed with costs
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF
APPEAL
CA 40012/09
DC 976/06
TOBIAS JA
MACFARLAN JA
McCLELLAN CJ at CL
Friday5 February 2010
YAN SHUO ZHAO v MARLA SHOSHANA GOODMAN and BRIAN GOODMAN
Judgment
1 TOBIAS JA: In 2000 and 2001, the appellant, a licensed builder, constructed a dwelling house upon land owned by the first respondent at 2 Cadigal Place, Dover Heights (the property). That respondent instituted proceedings by Statement of Claim filed in the District Court on 9 March 2006 alleging that the building work performed by the appellant was defective and claiming damages for incomplete work and the cost of rectification work.
2 On 7 April 2006 the appellant filed a defence denying liability on the basis that any damage or defects related to work that was not performed by him but by others or arose because the work was performed in accordance with express instructions from the first respondent or her agent, the second respondent. The appellant also filed a cross-claim seeking outstanding payments which he alleged were due to him under the building contract. This claim was opposed by the respondents. In a judgment delivered on 1 October 2008, following 14 days of hearing, Johnstone DCJ awarded damages to the first respondent in the sum of $157,847.30 plus interest, found in favour of the first and second respondents on the cross-claim and ordered the appellant to pay the respondents’ costs of both the claim and the cross-claim. It is from those orders that the appellant appeals to this Court. It may be noted that the appellant was represented by counsel at trial but represented himself on the appeal.
The issues at trial and the findings of the primary judge
(a) The identification of the contract between the parties
3 The second respondent is the husband of the first respondent. The second respondent met the appellant when the latter was undertaking construction works on a property opposite the premises of the first respondent’s parents. They entered into discussions with a view to the appellant being engaged to construct a dwelling house on the property. His Honour noted at [3] that it was common ground that the second respondent acted as agent of the first respondent at all relevant times.
4 During the course of negotiations, a number of documents were created. These relevantly included:
¦ an itemised quotation totalling $533,800 (the alleged contractual quotation) dated 25 January 2000 and initialled by the appellant and the first respondent (Blue 3, 1175); and
¦ a Department of Fair Trading Standard Form Home Building Contract, dated 1 February 2000, in booklet form signed by the appellant and first respondent (the Home Building Contract) (Blue 3, 881).
5 His Honour found (at [14]) that it was common ground that a final contract was concluded between the parties on a date in either late January or early February 2000 when the appellant met with the respondents at the first respondent’s parents’ house (the meeting). However, the parties disagreed as to the sequence in which the above documents came into existence and which of them governed their contractual relationship.
6 The respondents contended that the contract between the first respondent and the appellant was constituted by the Home Building Contract and incorporated documents including the specifications and drawings and that this contract was signed by the parties during the course of the meeting.
7 The contract price in the Home Building Contract was stipulated to be $533,800 (Blue 3, 886). Its signature page (Blue 3, 910) contains the signatures of the appellant as builder and first respondent as owner each of which was witnessed by the second respondent. The date of the contract is stated to be 1 February 2000. The second respondent purportedly inserted this date some time after the meeting to reflect the date that a deposit of $25,000 was paid to the appellant.
8 Stapled to the inside cover of the Home Building Contract (at Blue 3, 883) was a typed quotation (the booklet quotation). Except for some handwritten notes made by the second respondent next to some of the items, that document is identical to the alleged contractual quotation (for the details of which, see [8] below). The booklet quotation appears to have been initialled by the appellant. That quotation reveals a total price of $533,800 comprising a fixed sum of $375,000 and prime cost (PC) items totalling $158,800.
9 The appellant agreed that he signed the Home Building Contract and that he discussed the booklet quotation with the respondents. (Although he initially denied having signed the booklet quotation, this was conceded in cross-examination.) However, he contended that within minutes of his signing of the Home Building Contract, that agreement was discarded and replaced with another contract constituted by the alleged contractual quotation and certain oral terms. Essentially, the appellant asserted that the respondents had told him at the meeting that they wanted to save money and that he should not follow the architect’s specifications incorporated into the Home Building Contract but that the second respondent would instruct him as to the nature of the works that he was to undertake.
10 The parties therefore agreed, so the appellant contended, to take responsibility for the jobs that they respectively completed and that the contract price would be reduced to account for any works that the second respondent himself arranged for third parties to complete. In light of this agreement, the second respondent typed up the alleged contractual quotation. It reflected the same price as that contained in the Home Building Contract, that is, $533,800, which was formulated from an itemised list of works and prices. It was also identical to the booklet quotation except for the second respondent’s handwritten notes thereon. The alleged contractual quotation was signed by the appellant and the first respondent and dated 25 January 2000 in handwriting. The appellant contended that this document, combined with oral instructions given to him by the second respondent from time to time, formed the basis of the contractual relationship between the parties.
11 The primary judge held (at [16]) that on both the appellant’s and the respondents’ case with respect to which document constituted the contract between them, there was no doubt that the contract price was $533,800. (It was agreed that an additional $10,000 was to be paid to the appellant if the respondents decided to proceed with the construction of a fourth bedroom, which they ultimately did, bringing the total contract price to $543,800.)
12 However, his Honour was required to determine the circumstances in which each of the documents referred to at [4] above came into existence. He found (at [16]) that the appellant’s assertion that the alleged contractual quotation was prepared in order to become the basis of the contract after the preparation of the booklet quotation and the signing and discarding of the Home Building Contract, was “entirely unreliable”.
13 His Honour preferred the second respondent’s evidence that the alleged contractual quotation was prepared before the iteration of that document constituting the booklet quotation. He found (at [17]) that the alleged contractual quotation was simply the final quote in which the agreed upon negotiated price of $533,800 was recorded and that the booklet quotation came into existence subsequently, when the second respondent made handwritten notes on a copy of the pre-existing document. His Honour also noted (at [17]) that the booklet quotation, stapled to the inside cover of the Home Building Contract, was only relevant insofar as it reflected the manner in which the contract price was arrived at and thus the objective intention of the parties as to price. He stated that he was satisfied that none of the discussions alleged by the appellant to the effect that the Home Building Contract was discarded, varied, replaced or renegotiated took place at the meeting.
14 His Honour therefore found (at [18]) that the contract that governed the building works, the subject of the dispute, was comprised of the Home Building Contract dated 1 February 2000. He continued:
“19. But it is not just by reference to the inconsistencies and discrepancies in [the appellant’s] evidence as to the [alleged contractual quotation] that I came to this conclusion and have preferred the evidence of [the respondents] to that of [the appellant]. In the first instance, I agree with the submission that it is implausible the [respondents] would have gone to the effort and expense of obtaining detailed architectural specifications and preparing a formal written contract, only to abandon them moments later after some cursory discussions with [the appellant]. My assessment of [the second respondent] was that of a careful and meticulous businessman who would not wish to leave important matters of contractual agreement at large or outside the protection of a formal written agreement. His care and attention to the detail of the various quotes reinforced this impression of him. It is also inconsistent that both [the second respondent] and [the appellant] kept their respective counterparts of the Home Building Contract if it was no longer relevant.
20. There were other matters that were improbable. For example, I did not believe that [the first respondent] said the things attributed to her. In my assessment of her, she left all the discussions as to contractual detail and price to her husband. Given that she was only ‘vaguely familiar’ with the specifications it is unlikely she said they should not be followed. Nor is it likely that [the second respondent] described [the specifications] as ‘rubbish’. The meeting at which the final contract was agreed occurred at the house of [the first respondent’s] parents and it is also unlikely that [the second respondent] could have gone inside and typed up [the alleged contractual quotation] on his computer.”
15 His Honour then relevantly observed:
“21. In my view, much of [the appellant’s] evidence in this case was a reconstruction of events, designed to advance a defence that fitted the available documents but avoided their consequences. The unfavourable view that I formed as to his evidence in respect of the formation of the contract in turn infects my view as to his credit on other aspects of the dispute ...”
16 The primary judge concluded his consideration of the contract issue by noting the submission made by the appellant to the effect that the respondents had made numerous variations in respect of the works during the course of construction which was said to be evidence of an objective intention consistent with the appellant’s version of the agreement between the parties. His Honour rejected this submission at [22] and adopted the respondents’ submission that the fact that changes were requested and agreed to in no way proved that it was a term of the contract that the appellant would only perform such work as he was directed from time to time to do by the second respondent. The primary judge noted at [22] that
“[i]t is part of the usual course for residential construction work for variations to occur at the request of the owner.”
(b) The claim for rectification of defects and completion of works
17 The first respondent’s claim for the cost of rectifying defective work was based upon the alleged negligence of the appellant as well as his alleged breaches of the express warranties contained in clause 8 of the Home Building Contract and the warranties in the same terms which were implied pursuant to s 18B of the Home Building Act 1989 (the Act). That section provides:
“The following warranties by the holder of a contractor licence, or a person required to hold a contractor licence before entering into a contract, are implied in every contract to do residential building work:
(a) a warranty that the work will be performed in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract,
(b) a warranty that all materials supplied by the holder or person will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new,
(c) a warranty that the work will be done in accordance with, and will comply with, this or any other law,
(d) a warranty that the work will be done with due diligence and within the time stipulated in the contract, or if no time is stipulated, within a reasonable time,
(e) a warranty that, if the work consists of the construction of a dwelling, the making of alterations or additions to a dwelling or the repairing, renovation, decoration or protective treatment of a dwelling, the work will result, to the extent of the work conducted, in a dwelling that is reasonably fit for occupation as a dwelling,
(f) a warranty that the work and any materials used in doing the work will be
reasonably fit for the specified purpose or result,
if the person for whom the
work is done expressly makes known to the holder of the contractor licence or
person required to hold
a contractor licence, or another person with express or
apparent authority to enter into or vary contractual arrangements on behalf
of
the holder or person, the particular purpose for which the work is required or
the result that the owner desires the work to achieve,
so as to show that the
owner relies on the holder’s or person’s skill and
judgment.”
18 Section 18F of the Act provides the following defence to a breach of a statutory warranty:
“In proceedings for a breach of a statutory warranty, it is a defence for the defendant to prove that the deficiencies of which the plaintiff complains arise from instructions given by the person for whom the work was done contrary to the advice in writing of the defendant or person who did the work.”
19 The first respondent relevantly made claims for defective work in relation to the following items:
i. Failure to construct drip grooves on the terrace bulkheads;
ii. Failure to waterproof the level 3 terraces, the kitchen fountain and the front entry tiles;
iii. Defective cement render;
iv. Termite damage and failure to provide for sub-floor ventilation;v. Failure to complete the garage ceiling and install a power point for the garage door.
20 The first respondent relied below on the expert evidence of a Dr Bayliss as well as that of Messrs Robinson, Howard and Valencia. The appellant did not call any expert evidence in support of his defence. In addition, the primary judge noted at [29] that he had had the benefit of a view of the property on 26 March 2008 which enabled him to obtain a better understanding of the nature and extent of the defects in the construction work. He was entitled to draw any reasonable inference from that inspection in accordance with s 54 of the Evidence Act 1995.
21 His Honour’s consideration of the nature, cause and costs of
rectification of each of the alleged defective items is set
out below.
i. Failure to construct drip grooves on the terrace bulkheads
22 The respondents alleged that the appellant had constructed the eave soffits and external bulkheads of the level 2 and 3 terraces without drip grooves, the absence of which allowed rainwater to penetrate at the external edge and cause damage. They contended that the appellant did not construct the soffits in accordance with the plans and drawings, which required a drip groove to be installed.
23 The appellant responded to this claim to the effect that he had been instructed by the second respondent to produce a square finish to all roof edges, irrespective of the plans, and in particular, that he was instructed not to install drip grooves despite him giving advice to the second respondent that this was necessary to prevent rainwater from blowing inside. The appellant also gave evidence that the relevant drawing did not show that any drip grooves were to be installed.
24 As a result of his findings as to the appellant’s credibility, the primary judge did not accept his account that he did not install drip grooves because the second respondent told him not to. He found (at [34]) that the appellant “simply did not understand the detail in the drawings” and (at [36]) that he was negligent and in breach of warranty in respect of his construction of the eave soffits and external bulkheads for the level 2 and 3 terraces.
25 His Honour also found (at [35]) that even if the appellant’s evidence in relation to the drip grooves were to be accepted, it could not amount to a defence to the claim for breach of warranty under s 18F in that he did not establish that the deficiencies of which the respondents complained arose from any written instructions contrary to his advice.
ii. Failure to waterproof the level 3 terraces, the kitchen fountain and the front entry tiles
26 The respondents alleged at trial that there was a failure to properly, or at all, waterproof and/or flash the balconies, terraces and deck, a fountain constructed in the kitchen as well as the front entry tiles. The respondents’ expert, Mr Robinson, found minimal to no evidence of waterproofing of these areas upon his inspection of the relevant work.
27 The appellant contended that he did waterproof these areas. However, with respect to the terraces and balconies, his case was that the water damage arose because the respondents had changed their minds and instructed him to install concrete pavers that were thicker and heavier than the intended tiles without reconstructing the terrace and balcony surface levels to accommodate the variation. Although, so he submitted, he warned the second respondent that the pavers were too high and heavy and could damage the membrane, the second respondent instructed him to proceed with the concrete pavers and not the tiles provided for in the specifications with the result that the variation in materials caused the water penetration.
28 At [41] his Honour stated that he preferred the evidence of the second respondent that it was always his intention to use concrete pavers. He found (at [44]) that it was unlikely, having regard to the fact that successful rectification work involving the same type of concrete pavers and no change to the superstructure had been effected, that the height of the pavers was the cause of the water damage, and it was more probable that, in accordance with the evidence of Mr Robinson, a waterproof membrane simply was not installed.
29 Again, his Honour found (at [45]) that even if he were to accept the appellant’s account of events, this could not amount to a defence under s 18F of the Act as the appellant did not establish that the deficiencies of which the respondents complained arose from any written instructions that they had given him contrary to his advice.
30 With respect to the front entry tiles, Mr Robinson gave evidence, which his Honour accepted at [78], that the water penetration occurred as a result of inadequate sealing. The primary judge therefore rejected the appellant’s contention that water entry was also caused by the increased height of the concrete pavers.
31 Finally, with respect to the kitchen fountain, the appellant suggested that any damage to the waterproofing was caused by the installation of the plumbing for the fountain, for which he had not been responsible. At [72] his Honour found that there was no evidence of any damage caused by the plumbing. He again accepted the evidence of Mr Robinson who, on inspection, had found minimal to no waterproofing of the water holding receptacle of the fountain.
32 The primary judge thus found (at [44], [46], [72]-[73] and [78]-[79]) that the water damage claimed by the respondents in respect of the balconies, terraces, kitchen fountain and front entry was caused by the appellant’s failure to properly waterproof the surfaces concerned by the installation of membranes and flashing and that he was negligent and in breach of warranty in respect of these failures.
33 His Honour also found (at [49], [77]) that attempted rectification by the application of a silicon shield or coating over the pavers as suggested by the appellant would be short term and inadequate and that rectification would require the removal of the pavers and the waterproofing of the sub-strata. He thus awarded damages for the cost of rectification and repair of the affected areas on this basis: the sum of $23,878.21 was awarded for the terraces and balconies and the sum of $2,016.63 was awarded for the front entry. The sum of $443.05 was awarded for the kitchen fountain claim.
iii. Defective cement render
34 The primary judge noted (at [50]) both on the basis of the report of Dr Bayliss and his own inspection, that much of the render work was defective in that it was uneven and cracked, was salting and shrinking, had lost adhesion and had fallen off or was peeling away.
35 At [52] his Honour recorded the following factors as contributing to the defective render according to Dr Bayliss:
¦ the absence of a bond coat;
¦ the use of render with little or no lime addition and of excessive strength for application to a clay brick background;
¦ the application of render at a thickness in excess of 15mm; and
¦ the lack of adequate curing considering the location of the residence and the exposure of the rendered walls to the prevailing winds and sunlight.
36 At [54] his Honour found on the basis of the reports of Dr Bayliss and Mr Robinson that
“[t]he uncontroverted expert evidence was, therefore, that the defective render was a result of faulty workmanship”.
37 The primary judge then considered (at [56]) the appellant’s defence which was to the effect that the expert opinions did not adequately explain the basis for their assertions of improper workmanship, that cement rendering skills are, of their very nature, imprecise, and that a possible cause of the defective render was rainwater which had penetrated the external walls underlying the render as well as natural cracking. The appellant also asserted that he had used experienced tradesmen to perform the work which he had supervised. Having set out (at [55]) the appellant’s assertion as to the methodology he had adopted, his Honour noted that none of the tradesmen or employees who had performed the work had been called to corroborate the appellant’s testimony as to that methodology.
38 His Honour continued:
“57. It is to be observed that no explanation is offered on behalf of [the appellant] as to why the render was defective. The essence of his defence is that he did the best he could in the circumstances, and that the render was drummy and crazed [technical terms relating, respectively, to phenomena consistent with non-observable bond failure and observable cracking in the render] through circumstances for which he was not responsible ... Nor, as I have already observed, was an expert called in his case to say that what he did was in accordance with sound building practice. There is no evidence to support the assertion of rainwater penetrating the external walls, and this was but further eristic conjecture on the part of [the appellant].
58. I am satisfied that the experts called by the [respondents], Dr Bayliss and Mr Robinson, were sound and reliable. Their experience relevant to this issue is extensive. Their opinions were formulated carefully and logically, and soundly based on appropriate investigation and consideration. I have no hesitation in accepting their opinions. I prefer their evidence to that of [the appellant] on these matters.”
39 After considering the experts’ opinions as to the reasons for the defective render, the primary judge concluded:
“63. I am satisfied, therefore, that more probably than not the defective render resulted from its having been incorrectly mixed and applied, through a combination of the failure to use a bonding agent, the application of a high strength render on a clay brick background, with inadequate lime, inadequate curing, the use of excessive water and/or the wetting-up of batches, an excessively wet surface at the time of application, and excessive thickness in a number of areas.
64. ... The evidence establishes that [the appellant] did not competently mix or apply the render, with the result that it was defective in a number of ways; in particular there was extensive drummy and crazing, with salting and shrinking, peeling and delamination.
65. For these reasons I find that [the appellant] was negligent and in breach of warranty in respect of his failure to properly mix and apply the cement render, as a result of which the defective work [was] required to be rectified.”
40 His Honour then turned to consider the question
of quantum. He found (at [67] and [68]) that rectification required removal and
reapplication of 433 square metres of the render. On this basis he awarded
damages for this item in the sum of $68,962.29.
iv. Termite damage and failure to provide for sub-floor ventilation
41 The first respondent alleged that the appellant had failed to provide any, or any proper, termite protection system, continuous ant capping and proper sub-floor ventilation.
42 In 2003 a termite infestation was discovered in the respondents’ house. Experts in pest control retained by the respondents, Mr Howard and Mr Valencia, found:
¦ mould and fungi in the sub-floor timbers caused by the absence of ventilation as a result of soil being left against the wall of the building and weep holes having been rendered over;¦ the moisture in the timbers created a haven for termites;
¦ that ant capping to one of the bedrooms was not continuous and there were holes in the ant capping as a result of rusting, rendering it ineffective.
43 In the opinion of Mr Howard, the termites had obtained access to the house through a build up of soil that was abutting the external wall above the level of the internal floor of one of the bedrooms (Black 1, 390). No expert evidence on this issue was called by the appellant so that that of the respondents’ experts, his Honour found (at [96]), was uncontradicted.
44 The specifications for the works required the installation of a product known as Termimesh (see Blue 1, 312). During the negotiations that led to a reduction in the contract price, the appellant had reduced the allowance made in respect of termite protection from $6,000 to $2,000. It was the appellant’s case that the reduction occurred as a result of the abandonment by the second respondent of the requirement for the Termimesh. Instead, the appellant was only required to use a protective spray, and this was indicated by the words ‘spray only’ written by the second respondent next to the termite protection item on the booklet quotation.
45 Once the contract had been concluded, so the appellant submitted, the requirement for the spray was dispensed with as the second respondent told him that he would arrange for the spraying himself, and another contractor carried it out.
46 In addition, the appellant claimed that he had told the second respondent that a retaining wall needed to be built to prevent soil from abutting the house and allowing termite entry but that the second respondent had said that building such a wall would be too expensive.
47 The second respondent denied the version of events given by the appellant. In particular, he denied that the reduction of price involved dispensing with the requirement for Termimesh or that he had told the appellant not to conduct the spraying. Despite discussions occurring with respect to a retaining wall, according to the second respondent, this was never in the context of termite protection.
48 Having regard to his findings as to the appellant’s credibility, the
primary judge did not accept the appellant’s account
of the termite issue,
observing at [99] that
“[i]t had the flavour of reconstructed evidence tailored to meet the exigencies created by the evidence served on behalf of the [respondents], rather than evidence based on genuine recollection, and I was totally unconvinced by it”.
49 His Honour also found at [100] that no preventative termite spraying was ever carried out at the respondents’ house, the sub-floor ventilation was inadequate, the ant capping installed was substandard, and that the appellant was negligent and in breach of warranty in respect of these failures.
50 His Honour then considered the cause of the termite damage, finding at [101] that
“[t]here is no doubt that entry occurred through the soil and debris left abutting the external wall at a height in excess of the floor level. ... But the magnitude and extent of the infestation and the scale of the damage was exacerbated and facilitated by the other factors described by the experts, including the defective ventilation and ant capping”.
51 He stated (at [102]) that it was the appellant’s responsibility to ensure that soil did not slip onto the site of the building works and to remove building debris that had accumulated. The appellant had created the site conditions for which he could not avoid responsibility. Accordingly, his Honour found (at [103]) that the appellant’s negligence and breach of warranty was the cause of the termite infestation. He awarded $53,940.00 for the termite claim and $4,336.40 for the sub-floor ventilation claim.
52 His Honour also remarked (at [104]) that even if the appellant’s conversations with the second respondent were to be accepted, they could not amount to a defence to his breach of warranty under s 18F of the Act in that the appellant did not establish that the deficiencies of which the respondents complained arose from any written instructions given to him contrary to his advice.
53 In light of his findings, the primary judge found it unnecessary to decide
whether the respondents agreed to excise the requirement
for the installation of
Termimesh in accordance with the specifications. However, he noted (at [107])
that if this were to become
a relevant consideration, he was not satisfied that
the parties dispensed with the requirement to install the mesh as no amendment
to the specifications was formally recorded and the words “spray
only” in the booklet quotation were equivocal.
v. Failure to complete the garage ceiling
54 The first respondent claimed that there was a failure by the appellant to fill voids within and complete the painting of the garage ceiling. The appellant conceded that he did not complete the garage ceiling work, but contended that he did not do so because the second respondent had given him a direction to do other work instead. Having regard to his findings in relation to the appellant’s credibility, the primary judge did not accept the appellant’s explanation as to why he did not complete the work on the garage (at [84]). He awarded $4,420.72 in damages in respect of this item.
(c) The cross-claim
55 The appellant’s cross-claim was brought against both the first respondent and the second respondent, seeking payment for amounts the appellant claimed remained outstanding in respect of various items of work that he had performed and for which he alleged he had not been paid.
56 The primary judge found (at [112]) that there was no basis for the joinder of the second respondent as a cross-defendant, as there was no suggestion that he acted at any time other than as agent for the first respondent and he was not party to the relevant building contract with the appellant.
57 Insofar as the cross-claim against the first respondent depended upon the appellant’s case as to the applicable building contract, his Honour rejected it at [113]. In any event, he noted that the appellant would have been unable to enforce the contract he alleged applied (consisting of the alleged contractual quotation and oral terms) on the basis of s 10(b) of the Act which was in the following terms:
“A person who contracts to do any residential building work ... and who so contracts ... under a contract ... that is not in writing or that does not have sufficient description of the work to which it relates ... is not entitled to damages or to enforce any other remedy in respect of a breach of the contract.”
58 In addition, to the extent that the cross-claim against the first respondent relied upon alleged variations to the works contracted for, his Honour rejected (at [116]) this claim on the basis that there was no evidence of any written variations in accordance with the requirements of clause 12 of the Home Building Contract which, as noted above, was the contract found by his Honour to govern the parties’ relationship.
59 Furthermore, the primary judge found (at [119])
that the items for which payment was claimed were either part of the works
covered
by the agreed fixed price, or had already been the subject of payments
made by the first respondent above that fixed price.
60 His Honour also rejected an alternative claim based upon a quantum meruit. In this regard the appellant had relied upon paragraphs 12, 13 and 14(b) of his Statement of Cross-Claim which relevantly provided:
“12. Alternatively, the [appellant] claims the moneys particularised above as work done at the request of the first [respondent].
13. Alternatively, the [appellant] claims the moneys particularised above as work done at the request of the second [respondent].
14. The [appellant] claims:
...
(b) alternatively, work done at the request of the first and second [respondents].”
61 The appellant submitted that these allegations were wide enough to encompass a quantum meruit claim. However, the primary judge held at [117] that these paragraphs were insufficient to put the respondents on notice of such a claim such that the appellant was unable to agitate the quantum meruit claim which he therefore rejected.
The appeal
62 On 11 May 2009 the appellant filed an Amended Notice of Appeal containing
10 grounds of appeal. This was supplemented by a set
of submissions dated 12
April 2009 (Submission 1) and another set of submissions dated 16 November 2009
(Submission 2). The appellant
also filed a reply to the respondents’
submissions on 12 July 2009 (Reply 1) and filed another document on 18 November
2009
which purported to respond to the respondents’ amended submissions
(Reply 2). I have carefully considered these submissions
which, with respect to
the appellant, are often discursive and repetitive. However, I have attempted
to distil from them the essential
contentions relevant to the issues in the
appeal.
63 It is, as the respondents submitted, difficult to identify the
relationship between Submission 1 and Submission 2 on the one hand
and the
grounds of appeal on the other such that the submissions include matters which
are not raised in the Amended Notice of Appeal
and there is considerable overlap
between Submission 1 and Submission 2. With all due respect to the appellant,
being a litigant
in person, both Reply 1 and Reply 2 are quite difficult to
understand and they do not appear to have been strictly confined to responding
to the respondents’ amended submissions. However, as the appellant
appeared in person on the appeal he presumably prepared
his submissions and
Amended Notice of Appeal with little or no legal advice. Accordingly,
notwithstanding the attendant difficulties,
I have attempted, as I have said, to
identify by reference to each of the appellant’s documents the key
challenges made to
his Honour’s findings.
64 It is convenient to set out seriatim each of the appellant’s challenges to the findings of the primary judge, the respondents’ response thereto and my determination of the relevant challenge.
65 However, before doing so it is necessary and relevant to make two observations. The first is that, as noted at [15] above, the primary judge formed an adverse view as to the appellant’s credit which infected his findings on those aspects of the dispute between the parties where the issue was whether to accept the evidence of the respondents and/or the experts they called on the one hand, or the uncorroborated evidence of the appellant on the other. The second is that it can be fairly said that most, if not all, of the submissions of the appellant seek to assert that his Honour in effect erred by failing to accept the appellant’s evidence. But to succeed in the appeal on this ground requires the appellant to overcome the constraints, where evidence has been rejected by a trial judge on the basis of adverse credit findings, authoritatively stated by the High Court in Fox v Percy [2003] HCA 22; (2003) 214 CLR 118 at 129 [29]. I shall refer further to this constraint when dealing with the individual issues to which I now turn.
(A) The documents constituting the construction contract
66 The appellant submitted that his Honour erred in accepting the respondents’ account that the Home Building Contract and the documents incorporated by clause 3 thereof governed the agreement between the parties and rejecting the appellant’s contention that this agreement was constituted by the alleged contractual quotation as well as oral terms.
67 Before considering this submission, I should clarify that the determination of which documents constituted the building contract between the parties was, in effect, only relevant to the cross-claim. This is because each of the documents asserted by the parties to constitute the agreement between them stipulated an identical contract price. The only difference of any significance between the two asserted agreements was the additional clauses contained in the Home Building Contract, and in particular, clause 12 which related to variations. The import of this clause was that it required a contractor (in this case, the appellant) to provide the owner (in this case, the first respondent) with notice in writing before commencing work on any variations. As the variations alleged by the appellant in the cross-claim were not in writing in compliance with clause 12, a finding that that clause did not apply to the contract between the parties would have assisted the appellant.
68 At the hearing of the appeal, counsel for the
respondents agreed that the appellant’s assertion that the alleged
contractual
quotation applied but the Home Building Contract did not was, in
essence, only relevant to the appellant’s cross-claim. However
she also
noted that the appellant’s assertion that the contract between him and the
first respondent included oral terms was
relevant to the issue of whether the
contract was for a fixed price, as asserted by the respondents, or on the basis
that the appellant
would perform and be paid for works as and when directed, as
asserted by the appellant.
69 Having explained the import of this ground of appeal, I now turn to my
consideration of it.
70 Consistent with my remarks at [65] above, I indicated to the appellant at
the hearing of the appeal that this Court was limited
in its power to set aside
the primary judge’s finding of fact as to which documents constituted the
construction contract between
the parties. To the extent that that finding was
based upon his Honour’s impressions of the appellant’s credibility,
this Court could only set it aside if the appellant established inconvertible
facts or uncontested testimony demonstrating that the
primary judge’s
conclusions were erroneous or glaringly improbable or contrary to compelling
inferences drawn from the evidence.
71 It appears to me that his Honour’s finding that the Home Building Contract comprised the relevant agreement between the parties was indeed reached on the basis of his findings as to the appellant’s credit and his observation (at [16]) that the appellant was “entirely unreliable”. Although he noted at [19] that
“it is not just by reference to the inconsistencies and discrepancies in [the appellant’s] evidence ... that I came to this conclusion”,
it appears that the further justification he provides (at [19] and [20]) for
accepting the account of the respondents and rejecting
that of the appellant is
independently additional to, rather than merely cumulative upon, his credibility
findings. In other words,
his finding that the Home Building Contract, on the
balance of probabilities, formed the relevant agreement between the parties,
was
based not only upon his impression of the demeanour of the relevant witnesses,
but also was independently confirmed or reinforced
by the improbability of the
account provided by the appellant, rather than deriving from a combination of
his impressions as to credit
and the relative persuasiveness of the respective
parties’ accounts. Accordingly, in my opinion, the appellant is
constrained
by the rule in Fox v Percy in successfully reversing his
Honour’s finding on this issue.
72 The appellant referred in his submissions to a number of facts which he
asserted were contrary to the primary judge’s ultimate
finding. However,
for the reasons I articulate below, none of these facts are incontrovertible;
nor do they demonstrate that his
Honour reached an erroneous conclusion.
73 First, the appellant contended (at Orange 8N) that the primary judge erred
in accepting the second respondent’s evidence
that the alleged contractual
quotation was typed by him as a quote because the appellant “could not
type”, and that this evidence was false as he was in fact able to
type. In his affidavit sworn 23 March 2007, the second respondent
had stated
that he typed the booklet quotation on the appellant’s letterhead because
the appellant had said “I can’t because I do not have a
computer”. However, whether or not the appellant could type or access
a computer was not relevantly in issue and his Honour’s
acceptance of the
second respondent’s evidence in this regard could not have influenced his
ultimate finding on the contract
which applied to the building works. The
appellant agreed (at Orange 8P) that the second respondent had typed the alleged
contractual
quotation. The only issue was whether this document was intended as
a quote of the agreed upon price or as a final record of the
contract between
the parties. The question of who typed the document or who was capable of
typing this document cannot have affected
the determination of this issue.
74 Second, the appellant contended (at Orange 9D) that his Honour erred in finding (at [14]) that the Home Building Contract was signed by the first respondent in either late January or early February 2000. In support of this contention, he asserted that the respondents’ counterpart of the Home Building Contract, which they had provided to their insurer and the appellant had seen in 2005, only contained the appellant’s signature and had not yet been signed or dated by the first respondent (see Blue 2, 744, 856). The appellant claimed that this evidence was inconsistent with the evidence given at trial by the second respondent to the effect that the first respondent signed and dated her counterpart of the Home Building Contract “shortly [after] or a few months [after]” the meeting (Black 1, 135R). At Black 1, 136, an explanation is proffered by counsel for the respondents to the effect that the copy of the Home Building Contract which was provided to the insurer was one which was made before the additional signature of the first respondent was added. It would therefore appear that the testimony of the second respondent was not necessarily inconsistent with his Honour’s findings.
75 In any event, in his affidavit evidence (at Blue 2, 716) the appellant
deposed that after he signed one copy of the Home Building
Contract on 25
January 2000 which he then handed to the second respondent, the respondents went
out of the appellant’s sight
but then returned and handed one of the
copies of the document to the appellant which had the first respondent’s
signature
on it at page 23. The appellant then said that he signed the same
copy but did not date it. The evidence of the second respondent
was that he
dated the document 1 February 2000 being the date upon which he paid the
appellant a deposit of $25,000 (Blue 1, 135
para 11) in accordance with the
contractual terms.
76 However, the appellant also asserted that both the evidence of the Home
Building Contract which had been unsigned by the first
respondent and the oral
evidence of the second respondent was nevertheless inconsistent with the
evidence of the first respondent
to the effect that she signed both copies of
the Home Building Contract at the meeting in the presence of the appellant and
did not
subsequently add anything to the signature page (See Blue 1, 135; Black
1, 74-75). It does appear therefore that there was inconsistent evidence as to
when the first respondent signed her counterpart of
the Home Building Contract.
Indeed, the respondents conceded this inconsistency in their submissions at
trial (at Black 2, 763).
Yet the submission itself was consistent, except with
respect to the dating of the document, with the appellant’s affidavit
evidence to which I have referred at [75] above.
77 Nevertheless, I do not think that this inconsistency (if such it be) in
the evidence as to when the first respondent signed her
counterpart of the Home
Building Contract is an incontrovertible fact demonstrating that the primary
judge’s finding was glaringly
improbable. At its highest, this
inconsistency may cast doubt on the credibility or reliability of the evidence
of either the first
or second respondent (depending on which account as to the
signing of the contract is indeed accurate). However, given that, where
a
contract is concluded by way of an exchange of identical counterparts signed by
each of the parties, it is unnecessary for both
parties to sign both
counterparts immediately, the inconsistency in the evidence as to when the first
respondent’s signature
was added to her counterpart does not make his
Honour’s finding that the Home Building Contract was executed by the
parties
and that this document constituted the whole of the construction
agreement between the parties “glaringly improbable”:
Sindel v
Georgiou [1984] HCA 58; (1984) 154 CLR 661 at 665-666.
78 Third, the appellant contended (at Orange 12U-13F) that his claim that the
Home Building Contract did not constitute the construction
agreement between the
parties was supported by the fact that the schedule of progress payments under
clause 11 of the Home Building
Contract (Blue 2, 758, 782) was different to the
payment record (Blue 2, 811) which indicated the amounts that were actually paid
to the appellant during the course of the works. The appellant also referred
(at Orange 13C-F) to evidence demonstrating that the
first respondent contracted
a not insignificant proportion of the construction work to third parties, which
was purportedly in contravention
of clause 25 of the Home Building Contract, as
well as evidence showing that the respondents purchased construction materials,
purportedly
in contravention of clause 15 of the Home Building Contract. This
evidence proved, so it was submitted, that the parties had not
intended to be
bound by the Home Building Contract. In my view, this submission should fail
for the same reason that it was rejected
by the primary judge: see [16] above.
79 Finally, the appellant submitted (at Orange 13W-14T) that the following
findings of his Honour were flawed:
¦ That the second respondent was a careful and meticulous businessman;¦ That it is implausible that the respondents would have gone to the effort and expense of obtaining architectural specifications and prepared a formal contract only to abandon them;
¦ That it would have been inconsistent for both the second respondent and the appellant to retain their respective counterparts of the Home Building Contract if this document did not constitute the relevant contract;
¦ That it was unlikely that the second respondent could have typed the alleged contractual quotation given that he was at his wife’s parents’ house at the relevant time.
80 It is arguable that at least the third and fourth of these contentions
have some force. However, notwithstanding the merit or
otherwise of these
complaints with respect to his Honour’s reasons, these allegations neither
suggest nor establish the existence
of any incontrovertible fact or uncontested
testimony which demonstrates that the primary judge’s finding that the
Home Building
Contract constituted the relevant agreement between the parties
was erroneous and should be set aside.
81 I should also observe that although the primary judge formed his
conclusion as to the identity of the contract between the parties
on the basis
of his credibility findings, there was nevertheless contemporaneous documentary
evidence inconsistent with the appellant’s
case. In particular, on an
application form submitted on 2 February 2000 by the appellant to obtain home
warranty insurance in respect
of the building works (Blue 3, 1131) the
“contract date” appears to have been filled in as
“01/02/2000”.
This document suggests that the building contract
between the parties was indeed the Home Building Contract dated 1 February 2000
and not the alleged contractual quotation dated 25 January 2000. In
cross-examination (Black 2, 742-743) the appellant did not provide
any
convincing explanation as to why this document stipulated the contract date to
be 1 February 2000 even though the true contract
date, on his case, was 25
January 2000.
82 Accordingly, the challenge to his Honour’s findings as to which
documents comprised the building contract between the parties
should be
rejected.
(B) The claim for rectification of defects and completion of works
83 Before turning to consider the submissions on the appeal in relation to
the primary judge’s findings in respect of each of
the alleged defects, I
should note that many of the challenges to his Honour’s findings on each
of the defects were repetitive
of the appellant’s submissions at trial.
His case with respect to a number of the defects (namely, the absence of
appropriate
drip grooves, waterproofing and termite protection) was that even
though the works were not perfect, they were carried out pursuant
to the
explicit instructions of the second respondent.
84 In relation to these defects, his Honour unequivocally rejected the appellant’s evidence that he received instructions from the second respondent to perform the allegedly defective works at a reduced standard or not at all.
85 His Honour then found at [35], [45] and [104] that even if he had accepted
the appellant’s evidence that he had received
instructions from the second
respondent to deviate from the specifications (relating to, respectively, the
drip grooves, waterproofing
and termite protection), the defence contained in s
18F of the Home Building Act 1989 could not be invoked by the appellant.
This was because the defective work complained of by the respondents was not
performed pursuant
to any written instructions that they had provided to the
appellant contrary to his advice: see paragraphs [25], [29] and [52] above.
86 In my view the primary judge erred with respect to his treatment of s 18F
in this manner. That section, which I have recorded at [18] above, provides a
defence to a builder whose work is subject to a complaint
where the builder can
prove that the work was completed in accordance with instructions provided by
the building owner that were
contrary to the builder’s written advice. In
other words, although the primary judge indicated that the s 18F defence should
fail because there was no evidence of written instructions from the
respondents in respect of the relevant items, the section only requires the
advice from the builder, in this
case, the appellant, to have been in writing.
87 Nevertheless, despite his Honour’s misinterpretation of s 18F, his consideration of this defence was only recorded as an alternative piece of reasoning and, therefore, any error contained therein does not of itself affect the validity of his Honour’s findings with respect to the relevant defects. It is convenient to now turn to the appellant’s challenges to those primary findings.
i. Failure to install drip grooves
88 It should be recollected that the appellant contended at trial that he was instructed by the second respondent not to install a drip groove. It is not unimportant to observe that such a contention implicitly acknowledges that but for that instruction, the appellant recognised that a drip groove was in fact required. Nevertheless, his Honour (at [34]) rejected the appellant’s evidence which was denied by the second respondent on the ground of the appellant’s lack of credibility and upon the basis that the second respondent was not cross-examined upon his denial of the alleged instruction.
89 The appellant also submitted that his Honour erred in holding that his
failure to install drip grooves on the terrace bulkheads
was work that did not
accord with the relevant drawing. He referred to the architect’s drawing
numbered AKDGM-108 (at Blue
2, 637) and asserted that a sketch by Mr Robinson
(at Blue 2, 631) to explain this drawing misconstrued it. The appellant relied
upon the observation of a Mr Martin to the effect that there was no drip groove
detailed in the drawing and also asserted that his
contention that there were no
drip grooves required by the drawing should be accepted on the basis of his own
expertise as a builder
(Orange 15H). He also submitted that the experts called
on behalf of the respondents, presumably Dr Bayliss and Mr Robinson, did
not
tell the truth and did not have sufficient knowledge of the respondents’
house. There is no substance in these last-mentioned
submissions given his
Honour’s finding that the evidence was uncontradicted by any contrary
expert evidence as none was called.
90 The respondents contended that the primary judge had the benefit of Mr Robinson’s oral evidence and explanation of the drawing AKDGM-108 and that the report by Mr Martin was not in evidence such that there was no incontrovertible evidentiary basis upon which his Honour’s findings could be disturbed. This submission is clearly correct.
91 At Blue 3, 1016 Mr Robinson circled the relevant part of the section
depicted on drawing AKDGM-108 which detailed the location
of the drip groove
which is shown as a gap depicted as a small horizontal line from the outside of
the vertical sheet to the edge
of the horizontal sheet. The purpose of the drip
groove or gap between the outside vertical surface of the eave and the
horizontal
lining is to prevent rainwater being drawn from the edge of the eave
back into the lining (Black 1, 341). The necessity for such
a groove would seem
to be self-evident and Mr Robinson’s evidence, accepted by the primary
judge, was that it was shown on
the relevant architectural drawing. No Fox v
Percy basis exists for rejecting that evidence.
92 The appellant further submitted (at Orange 16E) that the water damage
caused to the eave soffits was not due to his failure to
install drip grooves,
but rather due to the overflow of the gutters which, he alleged, had not been
maintained free from debris.
He referred in support of this submission to
photographs of the soffits prepared by Mr Robinson (Blue 2, 575) as well as
photographs
that he himself arranged to be taken of the roof and which were
Exhibit 8 at the trial. It is clear that these photographs do not
provide, of
themselves, proof of the cause of the water damage.
93 The appellant further asserted that his Honour erred in failing to give
any weight to the evidence that the level 3 terrace ceiling
was replaced by the
respondents without the installation of a drip groove and no longer experiences
water penetration problems.
The respondents submitted, and I accept, that this
was contrary to the evidence as the water penetration damage can be observed in
the photographs included in both reports of Mr Robinson.
94 Accordingly, the challenge to his Honour’s findings as to the
appellant’s failure to install drip grooves and damages
arising therefrom
should be rejected.
ii. Failure to waterproof
95 The appellant submitted that his Honour erred in finding that the appellant did not install a waterproof membrane beneath external tiling on the balconies and terraces.
96 The appellant contended that he did install a
waterproof membrane, but that this was damaged as the respondents had instructed
him to use concrete pavers rather than the tiles specified in the plans and for
which the relevant sub-strata was designed. He relied
upon a drawing by the
respondents’ architect (at Blue 3, 1222) which identified that
“tiles” were to be used in the door sills to the balconies as
well as a drawing (at Blue 3, 1224) which specifically referred to concrete
paving which, he submitted, revealed some kind of design flaw.
97 The appellant also claimed (at Orange 9Q) that his Honour erred in finding
at [44] that the rectification works were successful,
as upon his own inspection
of the property on 26 May 2008, it was evident that the ceiling beneath the
concrete paving was leaking
to a greater degree than before the paving had been
rectified. He finally submitted that his Honour should not have found that the
application of a coating or sealant to the affected areas (as suggested by the
appellant) would be a temporary solution only.
98 Despite these claims, the appellant does not refer to any incontrovertible
evidence that contradicts the primary judge’s
findings in relation to the
waterproofing which were based upon his Honour’s acceptance of Mr
Robinson’s evidence that
was, his Honour found, uncontradicted by any
expert evidence called on behalf of the appellant. The challenge to these
findings
cannot, therefore, be sustained.
99 The appellant made no substantive submission with respect to the kitchen
fountain issue, such that his Honour’s findings
with respect to this
defect should remain undisturbed. He simply did not believe the
appellant’s explanation for the problem
given the evidence of Mr Robinson
that on inspection he found no or minimal waterproofing.
iii. Defective cement render
100 In relation to the render issue, the appellant first submitted (Orange 10 and 23) that the evidence of Dr Bayliss and Mr Robinson should not have been admitted or accepted as neither of them were experts in the field of rendering and neither had told the truth in their evidence. Although it is true that Dr Bayliss was academically trained as a chemist, he was an expert in coatings and construction materials. In particular, according to his CV, as a self-employed consultant for over eight years, he had inspected and reported on the condition of coatings and associated substrates including cement render. His expertise with respect to cement render was not called into question in his cross-examination: cf Black 1, 438Y. Mr Robinson had been a licensed builder since 1992, had been a council health and building surveyor for many years and a recognised building consultant by the Department of Fair Trading since 1994 and in private practice since 1991. The opinions expressed by each of these experts indicated on their face that each had a clear understanding of the issues relating to the proper application of cement render to external walls of a residence. The primary judge clearly thought so and no good reason has been advanced by the appellant to reject his Honour’s assessment of the expertise and evidence of those witnesses.
101 With respect to Dr Bayliss’ evidence, the
appellant further submitted (at Orange 23) that not only did he not have
experience
in brick wall rendering but was only a painting coat expert but also
his opinions as to render mixing were inconsistent with Australian
Standard
3700-1988 and (at Orange 24O) that he should not have taken render samples from
the ground. In relation to the contention
that Dr Bayliss’ opinions
contravened the relevant provisions of Australian Standard 3700-1988, not only
was he not cross-examined
on that Standard but also it was not in evidence. In
any event, it is clear from the exchanges in the transcript (at Black 1,
434-437)
that Dr Bayliss took render samples from many locations in the house
and that there was no evidence to support the contention that
his method of
sampling was flawed.
102 At the hearing of the appeal, the respondents confirmed (at Tpt 31) that
although there was an objection taken at trial in relation
to whether or not
there was a specialist field of knowledge in relation to rendering (his Honour
found that there was at Black 1,
331S), as I have already noted no objection was
taken to Dr Bayliss’ expertise, even though he was a chemist and a
construction
materials consultant rather than a building expert. In these
circumstances, there is nothing in the appellant’s submissions
which
persuades me that his Honour erred in accepting Dr Bayliss’ expert
opinions.
103 With respect to Mr Robinson, the primary judge specifically rejected (at
Black 1, 331T) an objection to Mr Robinson’s evidence
on the basis that he
did not possess a level of expertise sufficient to express an opinion in
relation to the specialist ‘rendering’
body of knowledge. The
appellant challenged the rejection of this objection.
104 The appellant submitted (at Orange 24R) that Mr Robinson’s lack of
expertise was evidenced by his absence of knowledge
of the product range of
PlasterMaster and that he was untruthful because despite saying in
cross-examination that it was not part
of his brief to consider whether water
had been driven back through the window sill (Black 2, 558Y-559B), in his report
dated 19
January 2001, he referred to this phenomenon in paragraph 3.6.8 (Blue
2, 547), thus indicating that it clearly was part of his brief.
In addition,
even though he had said in cross-examination that he had not read the report of
a Mr Martin (Black 2, 507), this was
untruthful as a letter dated 7 May 2007 to
him from the respondents’ solicitors enclosed this report (Blue 2, 621).
His statement
in his report dated 19 January 2007 (at Blue, 529) that
“in arriving at my opinion, I have considered all the documents
provided to me by the solicitor” was, so it was submitted, also
untruthful.
105 In my opinion, Mr Robinson’s concession in cross-examination that he did not know the detail of the product range offered by PlasterMaster does not cast any doubt on his expertise, especially given his previous statement which disclosed his awareness of PlasterMaster as a company manufacturing plasterboard and his evidence as to the effects of a product with PlasterMaster’s chemical properties. I do not think that the first and second mistruth alleged against Mr Robinson necessarily discredits his evidence. Rather, these inconsistencies appeared to be slips or mistakes in the context of a lengthy cross-examination which extended over some 70 pages of transcript (excluding his cross-examination on the voir dire). Moreover, the third alleged mistruth is clearly unfounded as even if Mr Robinson did lie in cross-examination about having seen the report of Mr Martin, this report was only purportedly sent to him in May 2007, three months after Mr Robinson prepared his own report on the evidence then available to him.
106 At [62] the primary judge observed that Mr Robinson did not change his
opinion when cross-examined (at some length) as to the
appellant’s use of
the PlasterMaster product. A reading of that cross-examination reveals that Mr
Robinson stood his ground
on all the defect issues upon which he was challenged.
It was thus open to his Honour to accept his evidence.
107 Thus, as with Dr Bayliss, in my opinion the appellant has failed to
disclose any evidence which would persuade me that the primary
judge erred in
his acceptance (at [58]) of the expertise of and evidence given by Mr Robinson.
The appellant’s assertion that
he himself was a qualified expert and that
his evidence should have been accepted on this basis does not assist him in this
regard.
As his Honour noted (at [57]), the appellant called no independent
expert evidence on this or any other issue.
108 Second, in relation to the render issue the appellant submitted (at
Orange 10) that his Honour erred in stating (at [57]) that
he did not offer any
explanation as to why the render was defective, as he had in fact provided a
comprehensive list of reasons.
It is clear when this statement is read in
context that his Honour was referring to the appellant’s failure to offer
a plausible
or compelling explanation as to the reasons for the defective
render, rather than his failure to provide any justification at all.
109 Third, the appellant submitted (at Orange 18) that although the render
was defective, this was a result of rainwater penetrating
the cavity between the
render and the external wall. He relied upon clause 19 of the British Standard
on rendering which provided
that water is liable to cause loss of adhesion,
further cracking or complete disintegration of the rendering through either
frost
action or the action upon the cement of soluble sulphates that may be
present in bricks. However, the respondents submitted that
Dr Bayliss had
specifically given evidence that this clause did not apply to Australian
conditions because Sydney did not experience
sufficient frost action and bricks
manufactured in Australia do not contain soluble sulphates.
110 There was an apparent inconsistency in the evidence of Dr Bayliss and Mr
Robinson with respect to the effects of water penetration
on the render which
the appellant referred to in support of his submission that these witnesses were
not qualified experts. Whilst
Dr Bayliss said (at Black 1, 456Y) that continuous
leaking of salt through the cracks in the render could not cause it to lift, Mr
Robinson gave evidence (at Black 2, 495) that if water continuously entered
through hairline cracks, it could cause a deterioration
of the bond between the
render and the surface of the brick wall, leading to drummy render and to it
lifting. However, Dr Bayliss’
statement was made in the context of his
evidence that where the bond between the render and the external wall is
adequate, the continuous
penetration of water into the cavity between the render
and the brickwork would not cause the render to lift (Black 1, 495). Mr
Robinson does not appear to have been asked specifically about the effects of
water continuously entering the wall cavity.
111 Nevertheless, I agree with the respondents’ submission (at Orange
34D) that regardless of whether continual exposure to
rainwater could
cause the relevant render damage, the appellant did not point to any
incontrovertible evidence tending to show that anything other
than his own
negligence or breach of statutory duty did in fact cause the defects in
the render work.
112 It is true that the appellant asserted that water penetration occurred due to a number of factors over which he had no control, namely:
¦ overflow from the roof gutters caused by the respondents’ failure to clear debris therefrom;¦ water leaking from the window sill;
¦ the second respondent’s faulty construction of the pipe to the kitchen fountain through a brick wall; and
¦ the second respondent’s use of defective grout to fix a glass panel to the balustrade wall.
113 However, an examination of the following documents referred to by the
appellant in support of these assertions does not self-evidently
reveal that any
of this evidence clearly supports the appellant’s case that any of these
factors actually caused the acknowledged
defects in the render: See photograph
13 of roof from Exhibit 8 at the trial; transcript at Black 1, 207-208 relating
to slope of
windows; report at Blue 2, 547 relating to increased possibility of
leaking around the window; photograph of rendering around window
at Blue 1, 160;
photograph of glass joinery at Blue 1, 411; report at Blue 2, 556 relating to
the kitchen fountain. In particular,
it is not suggested that any of these
documents were put to Dr Bayliss or Mr Robinson in cross-examination or that
either of them
accepted that any of the four factors relied on by the appellant
could have contributed to the defective render.
114 Fourth, the appellant claimed that his Honour erred in finding that he
did not competently mix or apply the render. He submitted
(at Orange 46J) that
Dr Bayliss should not have found that the manufacturer’s instruction as to
how to apply the PlasterMaster
was incorrect. However, it appears to me that
this was not asserted by Dr Bayliss. Rather, Dr Bayliss gave evidence (Black 1,
424-429)
that the ratios allegedly contained in the PlasterMaster instructions
corresponded to a high-strength render which was unsuitable
for the relevant
clay brick background wall, and that the relevant mix required the addition of
lime to prevent cracking. His Honour’s
finding (at [64]) was not that
the appellant failed to follow the PlasterMaster instructions, but rather that
the application of
cement render is an acquired skill and that the methodology
employed by the appellant with respect to the selection of render additives
was
defective. The appellant has not adverted to any evidence that is contrary to
this finding.
115 Finally, the appellant submitted (at Orange 8) that because of the fact
that in the eight years since their house was constructed,
the
respondents’ had elected not to strip the defective render and redo the
rendering, the work that he performed could not
be as defective as was claimed.
In my opinion, even if the respondents had chosen not the redo the rendering,
this fact would not
provide incontrovertible evidence that his Honour’s
finding on the render claim was incorrect. In any case, the Court has
no
concern as to the use to which a successful party may put the amount paid to him
in satisfaction of an award of damages: Cullen v Trappell [1980] HCA 10;
(1980) 46 CLR 1 at 15.
116 For the foregoing reasons, I see no reason to disturb his Honour’s
finding at [65] that the appellant did not competently
or properly mix and apply
the cement render as a result of which it was defective and, therefore, in
breach of the statutory warranties.
iv. Termite damage and failure to provide for sub-floor ventilation
117 The appellant made a number of submissions that his Honour erred in
finding that the termite damage was caused by works he performed.
First he
relied upon the affidavit dated 8 May 2007 of Mr Howard (at Blue 2, 702), the
respondents’ pest control expert, to
the effect that “the
Sentricon baiting system is the only way to deal with termites at this Property,
due to the way the Property was initially constructed”. The appellant
contended (at Orange 20M) that this evidence proved that the termite infestation
was caused by the fact that
the ground level of the house was higher than the
floor levels because the property was located on a hill, rather than due to the
manner in which he built the house. It is clear that this statement of Mr
Howard does not assist the appellant. In its context,
the reference to the
“way the Property was initially constructed” should be read
as relating to Mr Howard’s observation in his earlier affidavit (at Blue
2, 649) that “no joints in the ant capping had been sealed”
and that “termites were entering ... via soil build up to the external
wall”, both construction faults caused by the appellant, rather than
any inherent design flaw in the building.
118 Second, the appellant asserted that he gave the second respondent a quote
for the construction of a retaining wall to prevent
the soil from sliding
downhill and that the second respondent accepted this (at Black 2, 570B). This
submission is of no consequence
as his Honour did not find that the termite
infestation occurred due to the presence or absence of this retaining wall.
Indeed,
a retaining wall was ultimately constructed.
119 Third, the appellant submitted (at Orange 20V) that an inspector retained
by the second respondent advised him to cover the ant
capping once it had been
installed, indicating that this work was acceptable to the respondents. There
is no compelling evidence
referred to which would support this submission. In
my opinion, even if this submission was substantiated, it would not relieve
the
appellant from the breach of warranty or negligence found by the primary judge
due to the gaps in the ant capping which rendered
it ineffective.
120 Fourth, the appellant submitted (at Orange 21C) that clause 58(1)(k)(vii)
of the Home Building Regulation 2004 precluded the respondents from
claiming damages for termite infestation on the basis that any loss suffered was
a result of the respondents’
failure to maintain appropriate protection
against pest infestation of the natural timber. Although I think that the
appellant’s
reliance upon this clause is misplaced, even if it were
relevant, the appellant has not referred to any evidence to suggest that
his
Honour erred in failing to find that the termite damage was due to the fault of
the respondents rather than the manner in which
the appellant had constructed
the sub-floor area of the house.
121 Fifth, the appellant appears to submit (at Orange 21K) that he could not
be held responsible for failing to spray the site because
the second respondent
had independently arranged for this to be done by another contractor, a Mr Kevin
Joyce/Jolie (see Blue 3,
1290; Red 71 [97]), and a witness had seen the spraying
being performed. This alleged cause of the termite infestation (if that is what
is being
alleged and that is far from clear) was specifically rejected by his
Honour at [98] and the appellant has not referred to any substantive
evidence
which would support a finding to the contrary.
122 Sixth, the appellant submitted that he could not be held liable for
failing to install an exhaust fan which Mr Howard said (at
Black 1, 382) was
necessary to provide ventilation to the sub-floor timbers, as there was no
indication in the drawings or specification
of the need for such a fan. Again,
this submission is baseless – the primary judge did not find that the
appellant should
have installed an exhaust fan, but rather that the sub-floor
ventilation was inadequate, presumably for the reasons articulated by
Mr Howard:
see [43] above.
123 Finally, the appellant submitted that the words “spray
only” written next to the termite protection item in the booklet
quotation combined with the fact that this item cost $2,000 as
opposed to the
$6,000 which had been contained in a previous quote dated 8 December 1999 (Blue
2, 780) meant that the appellant was
only required to apply a termite spray, and
was not required to install the Termimesh.
124 However, the respondents submitted that this was not the case, as the
Home Building Contract was a fixed price agreement which
incorporated a
specification which required the installation of Termimesh (Blue 1, 312). They
contended that the booklet quotation
was not a contract document under clause 3
of the Home Building Contract. However, even though his Honour found that the
contract
between the parties had not been varied so to dispense with the
requirement to install the Termimesh, a contrary finding would not
have affected
his ultimate award with respect to the termite damage. This is because even if
the reduction in price and the words
“spray only” were
construed to evidence an agreement that Termimesh would not be installed –
which, in my view, is a logical inference
– his Honour’s findings as
to the termite damage were not dependent upon the absence of Termimesh. Rather,
so the respondents
submitted, the soil abutting the external wall enabled the
original infestation and the defective ant capping created the main termite
problem as this allowed the termites continual concealed entry into the
sub-floor area of the house.
125 Having regard to the expert reports and the findings of his Honour, I
accept the respondents’ submission that the question
of whether or not the
appellant was required to install Termimesh or to only apply a spray treatment
was essentially a false issue.
His Honour expressly stated (at [107]) that in
the light of the findings that he had made it was unnecessary for him to make a
finding
as to whether the respondents agreed to excise the installation of
Termimesh from the contract.
126 Mr Howard, both in his affidavit sworn 22 November 2006 and the oral evidence he gave at trial, emphasised the defective ant capping as the source of the ongoing termite problem as well as the absence of sub-floor ventilation (see Black 1, 382-385). Although his Honour found (at [101]) that the cause of the termite damage was “multi-factorial”, and termite entry occurred “through the soil and debris left abutting the external wall”, he held that the damage was
“exacerbated and facilitated by the other factors described by the experts, including the defective ventilation and ant capping”.
127 Indeed, his Honour found (at [105]) that because of the fact that the ant
capping was defective and unable to be rectified without
lifting the house from
its foundations that a baiting and monitoring system for the termites was
required to be implemented (see
also, Black 1, 385).
128 Accordingly, even if the found failure of the appellant to apply a spray treatment or install the Termimesh were to be disregarded, his Honour’s findings that the construction work was defective in that “the sub-floor ventilation was inadequate” and that “the ant capping installed was substandard and unfit”, do not reveal error. Thus the appellant’s challenge to his Honour’s award of damages with respect to the termite issue should be rejected.
v. Failure to complete the garage ceiling
129 Despite the appellant’s contention (at Orange 20H) that his Honour erred in disbelieving his account as to why he did not complete works on the garage ceiling, there is no substance to this challenge. No relevant evidence is referred to that contradicts his Honour’s finding which was based on his assessment of the parties’ credibility.
(C) Additional submissions on the appeal
130 The appellant submitted (at Orange 8) that his Honour was prejudiced against him and did not take him seriously/ridiculed him, referring to Black 2, 698-699. In the passages referred to, the appellant was asked by his Honour to be more precise when he was referring to the first or second respondent due to the lack of gender distinction in the Chinese language. By no means were these comments prejudicial and the appellant’s submission that the judge was ridiculing him is baseless.
131 The appellant also appears to argue at (Orange
8) that the respondents instituted proceedings against him to obtain money from
their insurance company under false pretences. This submission also lacks any
foundation.
(D) The cross-claim
132 The appellant claimed $61,185 on his cross-claim both at trial and on the appeal. In order to determine whether the appellant is entitled to this amount, it is necessary to first consider what amount the appellant was owed under the contract and then what amount the appellant was paid by the respondents.
133 The appellant in his submissions at Orange 22-23 arrived at the sum of $61,185 in the following manner:
|
Contract price
|
$533,800
|
|
Less work performed by the respondents
|
$172,830
|
|
|
$360,970
|
|
Plus variations including GST
|
$47,715
|
|
|
$406,685
|
|
Less paid
|
$345,500
|
|
Amount owing
|
$61,185
|
134 According to the appellant’s evidence at trial, in January 2001 the second respondent provided the appellant with a breakdown of costs and payments which can be summarised as follows:
|
Contract price
|
$543,800.00
|
|
Less PC’s
|
$92,500.00
|
|
|
$451,300.00
|
|
Less paid
|
$437,215.26
|
|
Balance owing
|
$14,084.24
|
|
Plus extras (incl GST of $6,000)
|
$17,450.00
|
|
Balance owing
|
$31,534.74
|
135 The reconciliation of the contract payments
contended for by the respondents was provided in their submissions at trial in
the
following table (Black 2, 819):
|
Total contract price for fixed costs works
|
$375,000
|
|
|
Plus Variations
Bedroom 4 Agreed extras |
$10,000 $2,298.00 |
|
|
Plus PCs supplied and installed
|
0.00
(nil - no evidence of actual cost)
|
|
|
Adjusted Contract Price
|
|
$387,295
|
|
Less amount paid directly to [the appellant]
|
-$302,500
|
|
|
Less amount paid directly to sub-contractors and suppliers
|
-$117,662.12
|
|
|
Total paid to [the appellant] or directly to his sub-contractors or
suppliers
|
|
-$420,162.12
|
|
Credit to [respondents] in respect of fixed works
|
|
($32,867.12)
- reduced to $30,722.12 to take account of a further admitted extra in the
sum of $2,145.
|
136 The foregoing table only refers to the contract
price for fixed items, being $375,000, and payments made in respect of these
items
as it seems to have been agreed by the parties that the respondents were
to pay for the PC items directly. A payment claim prepared
by the appellant and
issued to the second respondent on 25 May 2001 after the completion of the works
seems to accept that the PC
items listed in the booklet quotation were indeed
items that were paid for by the respondents, as these are described as
“less owner buy or taked (sic) job”. Thus, the
parties’ original identification and reconciliation of the PC items was
identical but with three exceptions.
137 First, the “cornice & skirting item” was not
included in the appellant’s list of PC items paid for by the respondents
and the respondents conceded that this
PC item was provided by the appellant.
However, as there was no evidence from the appellant as to the cost of this
work, the respondents
did not include this as a sum owing to the appellant above
the fixed price component of the contract. Second, while the respondents
claimed that the costs of the PC items for indoor tiling and terrace tiling were
$11,200 and $10,000 respectively in accordance with
the booklet quotation, the
appellant’s reconciliation stated that these items cost $3,300 and $3,150
respectively. Third,
in reconciling the contractual payments, the appellant
calculated the amount owing to him to be the total contract price (including
the
fourth bedroom) of $543,800, minus the sum of the PC items as identified by him
to have been paid by the respondents, resulting
in a total price of $406,850.
In contrast, the respondents took $375,000 to be the base price of the fixed
cost items as specified
in the booklet quotation. An extra $10,000 was added to
this amount for the fourth bedroom along with agreed extras of $2,295 such
that
the total amount to which the appellant was entitled to be paid under the
contract was $387,295.
138 The primary judge (at [115]) accepted the calculations of the respondent
with the consequence that no moneys were owing to the
appellant - if anything,
he had been overpaid. The question is whether it was open to his Honour to
accept the respondent’s
calculations in preference to those of the
appellant.
139 The respondents claimed both at trial and on the appeal that they had
paid $420,162.12 to the appellant or his contractors and
suppliers. As they
were only required to pay the appellant $387,205, they submitted, and his Honour
found at [119], they had overpaid
the appellant for the fixed price contract
works by some $32,867.12.
140 The appellant contended that in addition to the fixed price for the
contract works (whichever amount was accepted), he was entitled
to further
amounts referrable to variations to the contract as well as GST. The items
included in the cross-claim were set out at
Orange 22 (and summarised at [133]
above. However, they overlap considerably with the items and amounts claimed by
the appellant
as “extra works” in his payment claim of 25 May
2001 (Blue 3, 1134-1135) and a list headed “Cost breakdown of extra
works completed for: [property]” at Blue 2, 800. It is
difficult to ascertain from each of these documents how the total claim of
$61,185 is arrived at although this
figure does appear in the “Payment
record for Lot 6 Military Road Dover Heights” at Blue 2, 811 as the
amount owing to the appellant as at 30 April 2001 except for the fourth bedroom
($10,000) which was
conceded and included in the table set out at [135] above.
If one excludes that item and the GST ($12,870), the balance of the alleged
variations is $22,845.
141 The respondents submitted, and his Honour found at [115], that under clause 10 of the Home Building Contract which applied as between the parties, the installation of PC items was included in the fixed contract price of $533,800. In any case, his Honour also found (at [116]) that to the extent that the extra items for which payment was claimed were alleged variations, the appellant could not enforce these variations as they were not effected in writing in compliance with clause 12 of the Home Building Contract. (In addition, the respondents submitted that ss 6(1)(b), 7 and 10 of the Act precluded a builder from enforcing a variation to a written contract that is not itself in writing: see also Dowling v Rae [1927] HCA 5; (1927) 39 CLR 363.)
142 The primary judge found, and I have confirmed, that the contract between the parties was that constituted by the Home Building Contract. That contract complied with the relevant provisions of the Act. I would be inclined to reject any submission by the respondents that a variation of that contract was unenforceable by the appellant by virtue of s 10(1) of the Act because it was not in writing. I would also doubt that any such variation was irrecoverable for non-compliance with clause 12 of the Home Building contract where otherwise it was agreed by the parties that the work was to be, and was in fact, performed. However, it is unnecessary to form a concluded view with respect to those issues.
143 The difficulty in the present case is that the primary judge made no finding to the effect that the items claimed by the appellant as variations (and which amount in my view to $22,845) were in fact variations to the works the subject of the Home Building Contract and that they were performed by the appellant at the respondents’ request. At least one reason for this is that the appellant’s case was always that the building contract was constituted by the alleged contractual quotation and that the Home Building Contract was abandoned immediately after it was signed, a submission his Honour rejected. Certainly, there was reason for the primary judge to find (at [114]) that the alleged contractual quotation did not comply with the Act and was thus unenforceable by virtue of s 10.
144 But for present purposes, the critical finding of his Honour is at [119] where he found that even if the appellant had a valid claim for variations, he had in fact been paid for them as he accepted the calculations in the table that I have recorded at [135] above.
145 His Honour therefore accepted that the first respondent had paid the
appellant and his suppliers a total of $420,162.12. On the
appellant’s
own case, the total amount which he was entitled to be paid (including
variations) was $406,685 (see [133] above).
Although the appellant contended
that he and his suppliers had only been paid $345,500, this assertion was
rejected.
146 It is not suggested by the appellant that the respondents’ payment records did not support their claim to have paid the appellant and his suppliers a total of $420,162.12. The second respondent tendered a form of spreadsheet detailing all the payments he had made with supporting documentation: see at Blue 1, 12-16 and to which he deposed at Blue 1, 3-4 (para 14 of his affidavit sworn 11 January 2007); Blue 1, 193-217, paras 10-83 of his affidavit sworn 29 June 2007. The spreadsheet and some of its supporting documentation (cheque butts) was also tendered as Exhibit E: Blue 3, 926-1010. This evidence was referred to at paras 302-312 of the respondents’ written submissions at trial (at Black 2, 818-819) which his Honour accepted at [119]. The appellants’ written submissions at trial did not challenge those of the respondents to which I have referred although reliance was placed upon the appellants’ own calculations at Black 2, 919 (paras 22-30). Whether the appellants dealt with the issue in oral submissions is unknown as the appeal papers do not include the transcript, if any, of those submissions.
147 I have read the relevant cross-examination of the second respondent relating to payments made by him to or on behalf of the appellant. It is confined to the transcript at Black 1, 244-252 and at Black 2, 583-584. This cross-examination comprised only 11 pages of transcript out of a total of approximately 150 pages of cross-examination of the second respondent. Moreover the main cross-examination on this issue at Black 1, 244-252 was generally confined to ascertaining whether the second respondent had invoices to match the payments itemised in his cheque butts. It is thus apparent that the main issues between the parties related to the respondents’ claim for defective work and that the appellants’ cross-claim received but scant attention.
148 It is telling that it was never suggested to the second respondent (except once at Black 1, 252D) that either the payments evidenced by the cheque butts were not in fact made or that they were unrelated to the building works undertaken by the appellant. Furthermore, at Black 1, 249N, counsel for the appellant conceded that there had been discovery of those quotations or invoices in the respondents’ possession. It also needs to be acknowledged that the second respondent was being cross-examined in 2008 about payments he had made in 2000-2001, some seven to eight years earlier.
149 In the foregoing circumstances it cannot be said that it was not open to the primary judge to accept the first respondent’s evidence as to the total payments he had made to or on behalf of the appellant.
150 Accordingly, in my view it has not been demonstrated that his Honour
erred in finding at [119] that the total amount paid by the
respondents exceeded
that to which the appellant was entitled with the consequence that as no further
monies were due to the appellant
and unpaid, his cross-claim fails.
Conclusion
151 For the foregoing reasons, the appellant has not established any proper basis which would warrant appellate intervention with respect to his Honour’s findings and orders. Accordingly, I would propose that the appeal should be dismissed with costs.
152 MACFARLAN JA: I agree with Tobias JA.
153 McCLELLAN CJ at CL: I agree with Tobias JA.
**********
LAST UPDATED:
5 February 2010
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCA/2010/2.html