![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales - Court of Appeal |
Last Updated: 21 April 2009
NEW SOUTH WALES COURT OF APPEAL
CITATION:
Dualcorp Pty Ltd v Remo
Constructions Pty Ltd [2009] NSWCA 69
FILE NUMBER(S):
40264/08
HEARING DATE(S):
10 March 2009
JUDGMENT DATE:
15 April 2009
PARTIES:
Dualcorp Pty Ltd (Appellant)
Remo
Constructions Pty Ltd (Respondent)
JUDGMENT OF:
Allsop P Macfarlan JA
Handley AJA
LOWER COURT JURISDICTION:
District Court
LOWER
COURT FILE NUMBER(S):
DC 1685/08
LOWER COURT JUDICIAL OFFICER:
Quirk DCJ
LOWER COURT DATE OF DECISION:
10 March
2009
COUNSEL:
F Corsaro SC/S Tzouganatos (Appellant)
G Inatey
SC/F Hicks/P Coady (Respondent)
SOLICITORS:
Turner Freeman
(Appellant)
Blackstone Waterhouse (Respondent)
CATCHWORDS:
CONTRACTS - Building and Construction Industry Security of Payment Act 1999
- progress claim for amounts the subject of a previous claim - adjudicator's
determination that most of previous claim not maintainable
- whether further
claim precluded by provisions of the Act or principles of estoppel
ESTOPPEL -
issue estoppel - adjudication under Building and Construction Industry Security
of Payment Act 1999
LEGISLATION CITED:
Building and Construction
Industry Security of Payment Act 1999
Workers' Compensation and
Rehabilitation Act 1981 (WA)
CATEGORY:
Principal
judgment
CASES CITED:
Bitannia Pty Ltd v Parkline Constructions Pty
Ltd [2006] NSWCA 238; (2006) 67 NSWLR 9
Batistatos v Roads and Traffic Authority of New South
Wales [2006] HCA 27; (2006) 226 CLR 256
D'Orta-Ekenaike v Victoria Legal Aid
[2005] HCA 12; (2005) 223 CLR 1
John Goss Projects v Leighton Contractors
& Anor [2006] NSWSC 798
Kuligowski v Metrobus [2004] HCA 34; (2004-2005)
220 CLR 363
Rothnere v Quasar & Ors [2004] NSWSC 1151
Walton v
Gardiner [1993] HCA 77; (1992-3) 177 CLR 393
TEXTS CITED:
Spencer
Bower, Turner and Handley, Res Judicata, 3rd ed (1996)
Butterworths
DECISION:
(a) Leave to appeal granted.
(b) Appeal
dismissed.
(c) The applicant/appellant to pay the respondent's costs of the
leave application and of the appeal.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF
APPEAL
CA 50264/08
DC 1685/08
ALLSOP P
MACFARLAN JA
HANDLEY AJA
WEDNESDAY 15 APRIL 2009
DUALCORP PTY LTD v REMO CONSTRUCTIONS PTY LTD
Judgment
1 ALLSOP P: I have had the advantage of reading in draft the
reasons of Macfarlan JA. I agree with the orders proposed by his Honour. His
Honour’s
reasons relieve me of the need to set out much of the background
to and context of the appeal, as well as many of the provisions
of the
Building and Construction Industry Security of Payment Act 1999 (the
“Act”).
2 I agree with Macfarlan JA that the Act was not intended to permit the
repetitious use of the adjudication process to require an
adjudicator or
successive adjudicators to execute the same statutory task in respect of the
same claim on successive occasions.
A party in the position of the applicant
(Dualcorp), here, should not be able to re-ignite the adjudication process at
will in order
to have a second or third or fourth go at the process provided by
the Act merely because it is dissatisfied with the result of the
first
adjudication.
3 The principal provisions of the Act that are directed to this question
of repetition are ss 13(5) and (6) and 22(4). Macfarlan
JA has dealt with s
22(4). I will return to that provision.
4 Subsections 13(5) and (6) should be read with s 8 and the definition of
the phrase “progress payment” in s 4. Section
8 is in the following
terms:
“(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) who has undertaken to supply related goods and services under the contract,
is entitled to a progress payment.
(2) In this section, reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or
(b) if the contract makes no express provision with respect to the matter—the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month.”
The definition of “progress payment” in s 4 is as follows:
“In this Act:
progress payment means a payment to which a person is entitled under section 8, and includes (without affecting any such entitlement):
(a) the final payment for construction work carried out (or for related goods and services supplied) under a construction contract, or
(b) a single or one-off payment for carrying out construction work (or for supplying related goods and services) under a construction contract, or
(c) a payment that is based on an event or date (known in the building and construction industry as a ‘milestone payment’).
5 In the relevant
design and construction contract between Dualcorp Pty Ltd (as subcontractor) and
Remo Construction Pty Ltd (as contractor),
clause 8 dealt with contracting sum,
payment and security. Clause 8.3 dealt with payment claims and certificates
and, relevantly,
stated:
“(a) At the times stated in Annexure A, item 11, and upon the times set out in Clauses 8.9 and 8.13, the Subcontractor may submit a Payment Claim to the Contractor. Save for the formalities of Clauses 8.9 and 8.13, a Payment Claim must include the value and description of work carried out by the Subcontractor in the performance of the Agreement to the permissible reference date (‘Payment Claim’).
(b) Within 10 days after receipt of a Payment Claim, the Contractor must issue to the Subcontractor a Payment Certificate (‘Payment Certificate’) stating the amount of payment, which in the opinion of the Contractor, is to be made by the Contractor to the Subcontractor or by the Subcontractor to the Contractor (‘Certified Amount’). The Contractor shall set out in the Payment Certificate the calculations employed to arrive at the Certified Amount and, if the Certified Amount is more than or less than the amount claimed in the Payment Claim, the reasons for the difference.
(c) A Payment Claim must be submitted and received by the Contractor on each permissible reference date as provided within Annexure A, item 11, and upon the times set out in Clauses 8.9 and 8.13.
(d) In the event that the reference date falls on a day other than a defined business day, then the Subcontractor must submit a Payment Claim on the subsequent business day.”
6 Annexure A, Item 11
was in the following form:
“Date for submission ofpayment claims: 15th of each month
(reference date)”
7 Clause 8.9 dealt with
retention moneys. Clause 8.13 dealt with final payment claim in the following
terms:
“Within 10 days after ground floor slab is formed up, the Subcontractor must submit to the Contractor a final Payment Claim endorsed as (‘Final Payment Claim’) being a Payment Claim subject to the terms of this Agreement under Clause 8, together with all claims showing all claimed adjustments to the Contract Sum and all amounts received by the Subcontractor up to the date of the expiration of the Defects Liability Period.”
8 As can be seen from the Act, s
13(5) a claimant is limited to one payment claim in respect of each reference
date. Section 13(6)
permits, however, inclusion in another payment claim
(necessarily by reference to another reference date) of an amount that has been
the subject of a previous claim. Amongst other usual and uncontroversial
examples, this permits the submission of cumulative payment
claims by reference
to later reference dates, which include an amount the subject of a previous
claim. In such circumstances, if
there has been an adjudication, s 22(4) will
apply to require the same value to be given to such work, subject to the
qualification
in that subsection.
9 Here, Dualcorp, after undertaking the works, left the site in November
2007. It claimed to have substantially completed the works
under the contract
in November 2007.
10 A payment claim was made on 29 January 2008 attaching six invoices,
four of which were dated 24 January 2008 and two of which were
dated 29 January
2008. The relevant reference date was not identified on the claim or
invoices.
11 On 3 March 2008, Dualcorp purported to serve a second payment claim
annexing the same invoices and claiming the same amount. Again,
no reference
date was identified on the documentation.
12 Whether or not this was a final claim or a progress claim does not
matter. The claim represented by the six invoices must have
been in respect of
only one reference date – either 15 December 2007 or 15 January 2008, if
pursuant to Annexure A, Item 11
or the reference date pursuant to the operation
of cl 8.13, if a final payment claim. In either case, there must have been one
reference
date under the contract or the last day of the month as provided for
by the Act, s 8(2)(b).
13 I see no warrant under either the contract or the Act, s 8 for
permitting a party in Dualcorp’s position to create fresh
reference dates
by lodging the same claim for the same completed works in successive payment
claims. That is not the intended operation
of the last phrase of s 8(2)(b)
(“and the last day of each subsequent named month”).
14 Here, the work had been done; Dualcorp, the subcontractor, had left
the site; it claimed payment by six invoices; six weeks later
it repeated that
claim by reference to the same invoices and, in my view, in respect of the same
reference date. Dualcorp was prevented
from serving the second payment claim.
The terms of s 13(5) are a prohibition. The words “cannot serve more than
one payment
claim” are a sufficiently clear statutory indication that a
document purporting to be a payment claim that is in respect of
the same
reference date as a previous claim is not a payment claim under the Act and does
not attract the statutory regime of the
Act.
15 For these reasons, Dualcorp was not entitled to proceed to judgment on
a claim founded on the operation of the Act premised on
the second payment claim
of 3 March 2008 being a payment claim under the Act.
16 As to s 22(4) I agree with Macfarlan JA’s approval of the
approach of McDougall J to this section. I also agree that the
Act as a whole
generally manifests an intention to prevent repetitious reagitation of the same
issues. The primary mechanism for
the effectuation of that intention would
appear to be ss 13(5) and 22(4). The former is sufficient to deal with the
present controversy.
I would leave to another occasion, should it be necessary,
the consideration of principles of estoppel to prevent any apparently
abusive
operation of the Act not specifically covered by ss 13(5) and 22(4).
17 MACFARLAN JA: This is an application for leave to appeal from
a decision of Quirk DCJ declining to enter summary judgment in favour of the
applicant
in the full amount claimed by it. The arguments of the parties have
extended to those which would be put if leave were granted.
Accordingly, it is
open to the Court to determine now the appeal which would follow if the Court
decided to grant leave.
Nature of Case and Conclusion
18 The application for leave to appeal raised the question of whether a
person making a progress claim under the Building and Construction Industry
Security of Payment Act 1999 (“the Act”) who is dissatisfied
with the determination of an adjudicator appointed to resolve disputes in
relation
to the claim may serve another claim and seek a redetermination of the
same issues before the same, or another, adjudicator. My
conclusion is that
this would be contrary to the intent of the Act and that it is precluded by the
principles of issue estoppel.
Factual Circumstances
19 The proceedings relate to a subcontract between the respondent
(“Remo”) as contractor and the applicant (“Dualcorp”)
as
sub-contractor for excavation and piling work at a building site at 97 Queens
Road, Five Dock, Sydney. The parties agree that
the subcontract was a
“construction contract” within the meaning of that term as defined
in s 4 of the Act.
20 Evidence called by Remo indicated that Dualcorp undertook the works
and left the site in or about November 2007, with no further
work having been
completed by Dualcorp on site after that time. The proceedings were conducted
at first instance on the basis that
Dualcorp had substantially completed the
work required under the subcontract.
21 On or about 29 January 2008, Dualcorp served a payment claim under the
Act (the “January Claim”). The claim attached
six invoices
(numbered 2129, 2130, 2131, 2132, 2136 and 2137) totalling $743,612.50.
22 On 11 February 2008, Remo served a Payment Schedule pursuant to s 14
of the Act (a “Payment Schedule”) which disputed
the bulk of the
claim in respect of the first four invoices but, save for an immaterial amount,
conceded the claims in respect of
invoices 2136 and 2137.
23 Pursuant to the provisions of the Act, Dualcorp applied for
adjudication of its claim in respect of the first four invoices. Mr
Anthony
Makin was appointed as adjudicator.
24 On 11 March 2008, Mr Makin determined that Dualcorp was entitled to an
amount of $75,509.43 (which included an amount of $36,834.88
which had been
accepted by Remo in its Payment Schedule). This was considerably less than the
total of $659,619.65 of the four invoices
the subject of the adjudication.
25 Pursuant to the provisions of the Act, Dualcorp sought and obtained
judgment in the District Court for $75,509.43 based upon a
certificate of the
adjudicator. It was agreed between the parties that judgment was entered on 3
April 2008.
26 Being dissatisfied with the amount to which Mr Makin determined it was
entitled, Dualcorp, on or about 3 March 2008, made a further
claim under the Act
(“the March Claim”). The claim was based upon, and attached, the
same six invoices the subject of
the January Claim. The total of the March
Claim was accordingly the same as that of the January Claim although for an
unexplained
reason there was a one cent difference. Neither party sought to
attribute significance to that difference.
27 As a result of Remo not serving a Payment Schedule in relation to this
claim, Dualcorp commenced proceedings in the District Court
for the amount of
the March Claim pursuant to the provisions of s 15 of the Act. The present
application for leave to appeal is
brought from the decision of Quirk DCJ
declining to enter summary judgment in favour of Dualcorp in the full amount
claimed by it.
The Statutory Provisions
28 The Act provides a mechanism by which a person who undertakes
construction work is able to obtain progress payments, even if the
construction
contract does not provide for them to be made. The procedure for obtaining a
progress payment involves the making of
a payment claim, the provision of a
Payment Schedule by the person on whom the claim is made, the referral of any
disputed claim
to an adjudicator for determination and the payment of the
progress payment determined to be payable.
29 The procedure is plainly one designed to facilitate the speedy making
and payment of progress claims and, where necessary, the
speedy resolution of
any disputes.
30 The provisions of the Act of particular relevance to these proceedings
are as follows:
“3 Object of Act
(1) The object of this Act is to ensure that any person who undertakes to carry out construction work (or who undertakes to supply related goods and services) under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work and the supplying of those goods and services.
(2) The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement to such a payment regardless of whether the relevant construction contract makes provision for progress payments.
(3) The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves:
(a) the making of a payment claim by the person claiming payment, and
(b) the provision of a payment schedule by the person by whom the payment is payable, and
(c) the referral of any disputed claim to an adjudicator for determination, and
(d) the payment of the progress payment so determined.
(4) It is intended that this Act does not limit:
(a) any other entitlement that a claimant may have under a construction contract, or
(b) any other remedy that a claimant may have for recovering any such other entitlement.
13 Payment claims
(1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount), and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount:
(a) that the respondent is liable to pay the claimant under section 27 (2A), or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
(4) A payment claim may be served only within:
(a) the period determined by or in accordance with the terms of the construction contract, or
(b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),
whichever is the later.
(5) A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract.
(6) However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim.
14 Payment schedules
(1) A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.
(2) A payment schedule:
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent’s reasons for withholding payment.
(4) If:
(a) a claimant serves a payment claim on a respondent, and
(b) the respondent does not provide a payment schedule to the claimant:
(i) within the time required by the relevant construction contract, or
(ii) within 10 business days after the payment claim is served,
whichever time expires earlier,
the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.
15 Consequences of not paying claimant where no payment schedule
(1) This section applies if the respondent:
(a) becomes liable to pay the claimed amount to the claimant under section 14 (4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section, and
(b) fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.
(2) In those circumstances, the claimant:
(a) may:
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (b) in relation to the payment claim, and
(b) may serve notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
(3) A notice referred to in subsection (2) (b) must state that it is made under this Act.
(4) If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract.
22 Adjudicator’s determination
...
(4) If, in determining an adjudication application, an adjudicator has, in accordance with section 10, determined:
(a) the value of any construction work carried out under a construction contract, or
(b) the value of any related goods and services supplied under a construction contract,
the adjudicator (or any other adjudicator) is, in any subsequent adjudication application that involves the determination of the value of that work or of those goods and services, to give the work (or the goods and services) the same value as that previously determined unless the claimant or respondent satisfies the adjudicator concerned that the value of the work (or the goods and services) has changed since the previous determination.”
The Judgment at First Instance
31 Having referred to the submissions of the parties, the primary judge
expressed the following views:
“The situation here is that, quite clearly, a large proportion of the monies which comprises this claim for summary judgment was dealt with in accordance with the Building and Construction Industry Security of Payment Act, by the referral to adjudication of those amounts claimed in the four invoices and the subsequent entry of judgment in respect of the amount determined by the adjudicator.
Although it is clear that the judgment and the adjudication by the adjudicator itself are not final, and that the rights of the parties under the contract are still open to be litigated, the issues as between the parties in respect of those four invoices were dealt with by the adjudicator under the Act and I accept that to seek to have those same invoices in respect of the same work re-agitated is barred because of principles akin to res judicata at least or constitutes an abuse of process as submitted by Mr Hicks. In respect to that part of the amount claimed in these proceedings which was the subject of the earlier payment claim and consequent determination by the arbitrator, I am of the view that it would be an abuse of process for the Court to grant the application for summary judgment and therefore in respect of the larger proportion of the claim, the Court will not so grant.
However, in respect of the two invoices which were not referred to adjudication and which were clearly rejected by Remo, in its letter to which I earlier referred, as valid payment claims, despite the issuing of a payment schedule in respect of those two invoices as well as the four other invoices which were the subject of adjudication, in my view the service of payment claims, that is the service of the two invoices numbered 2136 and 2137 on 3 or 4 March, were valid payment claims and in response to which there is no payment schedule served.
Although the defence filed by Remo would suggest that all six invoices were dealt with initially in the same manner, I do not accept that this was the case. Nor do I accept the submission made in respect to the claim being a “substantial completion payment claim”, as that was rejected by Remo at the time of service. Therefore although the submissions and the pleadings by Remo are apposite to the four invoices numbered 2129 to 2132, they do not apply in my view to the other two invoices, 2136 and 2137.
Although it is submitted by Remo that Dualcorp could have availed itself of the remedy available under s 16 of the Act, I do not necessarily agree. Because of the position taken by Remo upon the service of the six invoices in January 2008 it could have been argued by Remo that Dualcorp was not entitled to the benefit of section 16 because it had not served a valid or proper payment claim in respect of those two invoices.
I therefore propose to enter summary judgment for the plaintiff in the amount claimed in those two invoices, which is in respect of invoice 2136, $1,642.55 and invoice 2137, $82,350.40 which amount total $83,992.95 plus interest to be agreed between the parties.”
Dualcorp’s Submissions on Appeal
32 Dualcorp contended first that the Court was precluded by s 15 of the
Act from giving effect to the defence based on principles
“akin to res
judicata” or “abuse of process” found by the primary judge to
be applicable. It was said that
s 15(4)(b) disentitling a respondent from
raising any defence “in relation to matters arising under the construction
contract”
was applicable as each of the matters referred to by her Honour
was such a defence.
33 Alternatively, it was submitted that the elements of res judicata were
not present. In particular, that the decision of the adjudicators
was not
“judicial” in the required sense, was not “final”
(reliance being placed on ss 25(4) and 32), was
not “on the merits”
(reliance being placed on s 32) and did not determine the same question as arose
in the subsequent
Court proceedings (reliance being placed on ss 25(4) and 32).
34 Dualcorp also submitted that the primary judge’s decision to
direct the entry of summary judgment in relation to the fifth
and sixth of the
invoices involved a denial of procedural fairness to Dualcorp. It was said that
the possibility of her Honour taking
that course was not raised with the parties
and Dualcorp did not therefore have any opportunity to make submissions on the
point.
I do not consider that this submission should be accepted. It was open
to her Honour to enter judgment for a lesser sum than that
for which it was
sought: the greater included the lesser. No prejudice has been suffered by
Dualcorp by reason of the alleged procedural
unfairness as the point was one of
law and it was open to Dualcorp to put to this Court any reasons why her
Honour’s approach
was inappropriate. In any event, the consequence of the
point succeeding would be to Dualcorp’s disadvantage as it would result
in
the judgment which it obtained (albeit limited) being set aside in the event
that it was otherwise unsuccessful before this Court.
In argument, it
disclaimed any desire for this to occur.
35 Another submission made by Dualcorp was that the judgment entered
below in its favour should be increased by the amounts of the
items which it
said the adjudicator did not determine on the merits but in effect decided on a
“non-suit” basis, that
is, upon the basis that he had insufficient
evidence to accept the claim. It was accepted that this argument was not put at
first
instance. In my view, particularly bearing in mind the nature of the
proceedings before this Court, that is, an application for
leave to appeal in
relation to a decision on a summary judgment application, the argument should
not be entertained. In any event,
as will be apparent from the reasons which
appear below, the argument would not in my view have succeeded (see
[71-72]).
Remo’s Submissions
36 Remo contended that the primary judge’s approach was correct.
It joined issue with the submissions of Dualcorp, particularly
Dualcorp’s
contentions that the adjudicator did not constitute a relevant tribunal for the
purposes of res judicata principles
and that his decision was not sufficiently
final to attract those principles.
37 Additionally, Remo contended that the March Claim conflicted with s
13(5) and (6) of the Act. Those subsections prohibit the making
of more than
one payment claim in respect of a single reference date, subject to the
qualification that a claimant may include “in
a payment claim an amount
that has been the subject of a previous claim”. Remo contended that the
relevant reference date
in respect of each claim was the same and that because
the claims were identical, subsection (6) did not render the prohibition in
subsection (5) inapplicable. It was submitted that subsection (6) did not apply
because it only dealt with a situation where the
subsequent claim embraced more
than the previous one: otherwise it would not be a case of the claimant
“including” an
amount from a previous claim in a subsequent
claim.
Defences able to be raised in Court proceedings seeking Judgment
38 The Act provides two avenues for a claimant to obtain a judgment in
its favour.
39 The first is to be found in s 15 which applies where, as here, the
recipient of a claim has not served a Payment Schedule. The
section provides
that in those circumstances the claimant may sue for the unpaid portion of the
claimed amount as a debt in any court
of competent jurisdiction. Subsection (4)
provides that judgment is not to be given in favour of the claimant unless the
court is
satisfied that a Payment Schedule has not been served by the recipient
of the claim and that the claimed amount is still outstanding.
It also
disentitles the respondent to the claim from bringing any cross claim and, as
mentioned earlier, from raising any defence
“in relation to matters
arising under the construction contract”.
40 The provision as to cross-claims and defences is mirrored in s 25
which provides the other avenue for the obtaining of judgment.
This section
applies where there has been an adjudication. In that circumstance, the
claimant may file an adjudication certificate
“as a judgment for a debt in
any court of competent jurisdiction” and enforce it accordingly.
41 The restrictions in these sections as to the defences that may be
raised do not in my view prevent the raising of one based upon
or, to use the
primary judge’s expression, “akin to” res judicata, or indeed
issue estoppel if that defence is
otherwise available. Such a defence could not
in my view be described as a matter “arising under the construction
contract”.
Rather, it is a matter arising out of the proper construction
of the Act in conjunction with relevant common law principles. The
defence may
thus be raised, as may one that service of a payment claim was not effective
because it involved misleading or deceptive
conduct (Bitannia Pty Ltd v
Parkline Constructions Pty Ltd [2006] NSWCA 238; (2006) 67 NSWLR 9 especially at [96] per
Basten JA).
Finality: General Law Principles
42 In my view, the question of whether proceedings for judgment under s
15 can be defeated by proving that the payment claim (or part
thereof) upon
which the proceedings are based is inconsistent with an earlier
adjudicator’s determination under s 22 of the
Act is to be determined by
construing the Act against the background of relevant common law principles. In
particular, it is necessary
to determine whether the legislative intention was
to confer upon adjudicators’ determinations a sufficient degree of
finality
to attract the principles of res judicata, issue estoppel or of the
more general concept of abuse of process. Although not expressly
mentioned by
the primary judge, I include reference to issue estoppel as I consider it to
fall within the umbrella of her description
of “principles akin to res
judicata” and “abuse of process”. Indeed, her reference to
the issues having
earlier been dealt with by the adjudicator suggests she had
this principle in mind.
43 Before turning to the provisions of the Act, it is convenient to refer
to some relevant general law principles and their possible
application in the
present circumstances.
44 It is a principle of the law “that controversies, once resolved,
are not to be reopened except in a few, narrowly defined,
circumstances”
(D’Orta-Ekenaike v Victoria Legal Aid [2005] HCA 12; (2005) 223 CLR
1 at [34]. The plurality judgment in D’Orta went on to state
that:
“The principal qualification to the general principle that controversies, once quelled, may not be reopened is provided by the appellate system. But even there, the importance of finality pervades the law. Restraints on the nature and availability of appeals, rules about what points may be taken on appeal and rules about when further evidence may be called in an appeal (in particular, the so-called "fresh evidence rule") are all rules based on the need for finality. As was said in the joint reasons in Coulton v Holcombe: "[i]t is fundamental to the due administration of justice that the substantial issues between the parties are ordinarily settled at the trial". (Citations omitted) (at [35]).
45 As pointed out, in
D’Orta, the principle of finality finds reflection in the doctrines
of res judicata and issue estoppel (at [34]).
46 In Spencer Bower, Turner and Handley, Res Judicata, 3rd ed
(1996) Butterworths it is said that the principle of res judicata is a
substantive rule of law and is to the following effect:
“Where a final judicial decision has been pronounced on the merits by ... [a] judicial tribunal with jurisdiction over the parties and the subject matter, any party to such litigation, as against any other party ... is estopped in any subsequent litigation from disputing such decision on the merits ... “ (at [9]).
47 The requirements for issue estoppel
incorporate a like requirement of finality of the earlier decision. These
requirements were
described by the High Court in Kuligowski v Metrobus
[2004] HCA 34; (2004-2005) 220 CLR 363 at [21] in the following terms:
“21. In his speech in Carl Zeiss Stiftung v Rayner & Keeler Ltd (No 2) Lord Guest, after noting that the doctrine of issue estoppel had been accepted by Australian courts for a number of years, indicated that, for the doctrine to apply in the second set of proceedings, the requirements were:
‘(1) that the same question has been decided; (2) that the judicial decision which is said to create the estoppel was final; and, (3) that the parties to the judicial decision or their privies were the same persons as the parties to the proceedings in which the estoppel is raised or their privies.’” (citations omitted)
48 It is well accepted
that domestic tribunals are within the ambit of the res judicata principles. As
Spencer Bower, Turner and
Handley say:
“Every domestic tribunal, including any arbitrator, or other person or body or persons invested with authority to hear and determine a dispute by consent of the parties, court order, or statute, is a ‘judicial tribunal’ for present purposes and its awards and decisions [are] conclusive unless set aside” (citations omitted) (at [25]).
The position is no different with issue estoppel, as Kuligowski illustrates.
49 The fact that adjudication proceedings under the Act are abbreviated
in character does not mean that they are not of a sufficiently
“judicial” character: the process is put in train because there is
a dispute between the parties as to a monetary entitlement;
an independent
person is appointed to adjudicate the dispute; the issues are defined by a claim
and a response to the claim; submissions
including relevant documentation are
put before the adjudicator (s 22(2)(c) and (d)); the adjudicator is obliged to
make a determination
in writing and to give reasons for the determination (s
22(3)).
50 In these circumstances I consider the critical question to be answered
in deciding whether the principles of res judicata and issue
estoppel are
capable of applying to adjudicators’ determinations under the Act to be
whether the Act, on its true construction,
manifests an intention to confer a
sufficient degree of finality on those determinations to attract those
principles.
Finality: Construction of the Act
51 Important features of the Act relevant to the degree of finality
intended to be attached by the Act to adjudicators’ determinations
are as
follows:
52 First, the objects of the Act are relevant (see s 3). Clearly the
overall intent of these is to provide a simple and quick means
of contractors
obtaining progress payments, with a mechanism being provided for the speedy
resolution of disputes. It would be inconsistent
with this objective to allow a
claimant who was dissatisfied with an adjudication of its claim to obtain a
reconsideration of the
claim simply by serving another which was identical to,
or included, the previous claim, especially if there was no limit to the
number
of times that a claimant could seek to have this reconsideration occur.
53 Secondly, as earlier mentioned, under s 13(5) only one payment claim
may be served in respect of each reference date under the
construction contract.
There is a qualification that the claimant may include in a payment claim an
amount that has been the subject
of a previous claim. However, taking into
account the Act’s objectives and its provisions, I do not consider that
that qualification
can, or should, be read as authorising the inclusion in a
payment claim of an amount which has been the subject of an earlier
adjudication.
It would in my view be inconsistent with the carefully structured
procedures as to adjudication and the provisions, which I am in
the course of
mentioning, pointing towards finality of adjudication determinations to give it
that construction.
54 Thirdly, in determining an adjudication application, an adjudicator is
bound, unless he or she is satisfied that the value of the
work has changed
since the previous determination, to value construction work consistently with a
valuation made in the course of
a previous adjudication application (s 22(4)).
I will refer to this provision again later.
55 Fourthly, under s 23(2) a respondent is required to pay any amount
determined by the adjudicator.
56 Fifthly, under s 24, failure to pay an adjudicated amount may have the
consequence that construction work is suspended.
57 Sixthly, s 25 provides that an adjudication certificate signed by the
adjudicator may be filed as “a judgment for a debt
in any court of
competent jurisdiction and is enforceable accordingly”. If application is
made by the respondent to have the
judgment set aside, the defences that may be
raised are restricted in the way referred to earlier (see [38] to [41] above).
As well,
it is expressly stated that the respondent is not entitled to
“challenge the adjudicator’s determination”. This
is a strong
indication of an intent to clothe the determination with a significant degree of
finality.
58 Seventhly, whilst s 26 permits a new application for adjudication to
be made, it narrowly defines the circumstances in which it
may be made: that
is, to circumstances where an adjudicator’s notice of acceptance of
appointment is not received within a
defined time or the appointed adjudicator
fails to determine the application within a defined time. It is implicit that
new applications
for determination may not be made in other circumstances. It
would be curious if these constraints could be circumvented by the
claimant
simply lodging a new claim and basing a new application for adjudication on that
claim, rather than on the earlier claim.
59 Eighthly, the argument in favour of inferring that adjudication
determinations were intended to be conclusive is in my view strengthened
when
one has regard to the fact that they determine rights in relation to progress
claims only and, by reason of s 32 of the Act,
do not affect contractual rights.
Thus, any inability of the claimant to reagitate the issues is confined to its
rights as to progress
payments. Its rights to put its case as fully and
completely as it wishes in pursuit of a contractual claim are preserved.
60 These various provisions in my view indicate a legislative intent to
render adjudication determinations relevantly conclusive.
Such determinations
do not conclude contractual rights. Section 32 expressly so provides. The Act
however creates special statutory
rights to progress payments. When a claim is
made, a dispute arises and an adjudication determination resolves that dispute.
I
consider that determination to be final and binding between the parties as to
the issues determined, except to the extent that the
Act allows the
determination to be revisited. It would in my view be quite contrary to the
scheme of the Act to permit claimants
simply to resubmit the already adjudicated
claims if they were dissatisfied with the adjudication.
61 In Kuligowski the High Court considered the concept of finality
in the context of a case concerned with issue estoppel. It said:
“A single ‘final’ decision, then, is one which is not of an interlocutory character, but is completely effective unless and until rescinded, altered or amended. The fact that an appeal lies from a decision does not make it any less final. It must be ‘final and conclusive on the merits’: ‘the cause of action must be extinguished by the decision which is said to create the estoppel’” (at [25], citations omitted).
62 Thus, in that case, decisions of a
review officer appointed under the Workers’ Compensation and
Rehabilitation Act 1981 (WA) were held to be sufficiently
“final” for the purposes of the doctrine of issue estoppel. In the
course of reaching
that conclusion, their Honours said that “the
legislative goal of having workers’ compensation disputes heard and
determined
in an informal, quick and cheap manner would not be assisted by a
construction of the legislation which prevented the doctrine of
issue estoppel
ever applying. That would increase the chance of double litigation of issues
and vexation of parties” (at [32]).
These comments are equally applicable
to the informal procedure laid down by the Act for the quick and cheap disposal
of claims
for progress payments.
Section 22(4): previous valuations
63 I return now to s 22(4), as I said I would in [39] above.
64 Section 22(4) has been the subject of consideration by McDougall J in
a number of judgments. In Rothnere v Quasar & Ors [2004] NSWSC 1151
his Honour said:
“41. There is one other point that needs to be mentioned. Mr Christie submitted that, where s 22(4) referred to the valuation of construction work, it meant, in substance, the value that the respondent to a payment claim was liable to pay. That was a step in his argument which was that s 22(4) was introduced by the Building and Construction Industry Security of Payment (Amendment) Act 2002, to discourage what the Minister, in the Second [Reading] Speech, had referred to as "adjudicator shopping", and that it should be construed (if ambiguous) so as to facilitate the achievement of that end.
42. I do not think that it is possible to read s 22(4) in this way. Section 8 gives an entitlement to a progress payment for construction work. Section 10 sets out how construction work is to be valued. The phrase "construction work" itself is a defined phrase: see section 5.
43. A determination under the Act may involve both questions of quantification - the section 10 issue - and questions of entitlement; or it may involve one or the other.
44. In my judgment, s 22(4) itself makes it clear that an adjudication determination need not necessarily include the valuation of construction work: the use of the introductory word "If" makes this clear. Subsection (4) therefore only applies where a component of a determination - that is to say, in terms of s 22(1)(a), of the determination of the amount of the progress payment (if any) to be paid - includes a determination of the value of construction work. Where it does, then subs (4) applies. Where it does not (either because the work has not at all been valued before or because the value of the work has changed) then s 10(1) applies. But there is nothing in these considerations that indicates that the phase "construction work" when used in s 22(4) should be construed in any way other than the way that it is used throughout the Act.”
65 In John Goss Projects v
Leighton Contractors & Anor [2006] NSWSC 798; (2006) 66 NSWLR 707, his
Honour said:
“37. The provisions of the relevant construction contract (s 22(2)(b)) will be relevant for a number of reasons. They may specify the reference dates on and from which a claimant has an entitlement to a progress payment (s 8). They may specify how the amount of the progress payment is to be calculated (s 9). They may specify how the construction work is to be valued (s 10). They may specify the due date for payment (s 11).
38. Although all those matters (and many others that may be taken into consideration under s 22(2)) go to the determination of the amount of the progress payment that is payable, they do not all deal with the valuation of the construction work that is the subject of the payment claim for that progress payment. The adjudicator’s task may (and usually will) comprehend more than merely the valuation of the relevant construction work. Attention to the requirements of the contract may indicate that there are to be deducted from, or offset against, that value some particular amounts (for example, retention payments or conceded back charges for defective or incomplete work). Thus, construction work may be valued at a particular sum, but the adjudicated amount of the progress payment may be less than that sum because of some such deduction or offset.
39. Further, there may be a question as to whether the claimant is entitled to be paid at all for construction work: for example, for an unauthorised variation where the contract specifies that the written authority of the respondent is required as a precondition of entitlement. (I leave aside, for present purposes, the possible impact of s 34 on such a provision.)
40. he precise issue that s 22(4) posed for Mr Davenport was not the amount determined by Mr Dutton as the progress payment payable in respect of the March payment claim. It was whether, in determining the amount of that progress payment, Mr Dutton had valued construction work that was required to be valued in the second adjudication pursuant to the May payment claim. Sections 9 and 10 make it clear that there is a distinction between the calculation of the amount of a progress payment (which is, ultimately, what the adjudicator is required to do) and the valuation of construction work. That is the distinction that I sought to point out (on reflection, in a way that was perhaps unduly brief and somewhat delphic) in para [43] of my decision in Rothnere.”
66 I agree with the
approach taken by McDougall J to the construction of s 22(4). As his Honour
points out, there are many issues
of potential relevance to a progress claim
which could not aptly be described as involving the determination of the value
of the
construction work. For example, s 11 of the Act provides that if the
contract makes a relevant express provision, a progress payment
becomes due and
payable “on the date on which the payment becomes due and payable in
accordance with the terms of the contract”.
If a claim for a progress
payment were made prior to a date stipulated by the contract and an adjudicator
rejected the claim because
it was premature, that determination could not in my
view be said to be, or involve, one as to the value of the construction work.
67 I do not consider however that s 22(4) should be regarded as an
exhaustive statement of the matters determined by an earlier adjudication
which
are binding on a subsequent adjudicator. For reasons I have given, I consider
that the Act when read as a whole manifests
an intention to preclude reagitation
of the same issues. Thus, if questions of entitlement have been resolved by an
adjudication
determination, those findings may not in my view be reopened upon a
subsequent adjudication. Likewise, if no subsequent adjudication
occurs but a
claimant proceeds (as here) to seek judgment following upon the failure of the
other party to serve a Payment Schedule
the claimant should be denied judgment
to the extent that what it seeks is inconsistent with findings of the
adjudicator.
Issue Estoppel and Abuse of Process
68 Thus the primary judge here was correct in considering that
“principles akin to res judicata” or “abuse of process”
were applicable. Consistent with that broad description, I conclude that the
principles of issue estoppel were applicable. Primarily
because temporal
considerations are of particular significance in relation to progress claims,
the analogy between an adjudicator’s
determination and a completed cause
of action which the principles of res judicata would require is an incomplete
one. It is best
that the applicable principles be recognised to be those of
issue estoppel. The more general principle of abuse of process is probably
also
applicable but it is unnecessary to reach a final view about this. This
principle involves a broad concept “insusceptible
of a formulation
comprising closed categories” (Batistatos v Roads and Traffic Authority
of New South Wales [2006] HCA 27; (2006) 226 CLR 256 at [9]) but certainly
including within its ambit an attempt to “litigate anew a case which has
formerly been disposed of by earlier
proceedings” (Walton v
Gardiner [1993] HCA 77; (1992-3) 177 CLR 378 at 393).
69 As pointed out in Kuligowski, for the principle of issue
estoppel to apply, the same issue must have been earlier determined as is later
sought to be reagitated
(at [40]). Thus, if a progress claim were rejected by
an adjudicator because it was premature by reason of the date stipulated for
payment by the contract, a later claim made on a timely basis would not be
precluded. However (to take as an example the issue which
was before McDougall
J in John Goss Projects) if a progress claim were rejected because
it was not made in accordance with express requirements of the contract, that
determination
would be binding on a subsequent adjudicator before whom the same
issue arose. Similarly, it would be an abuse of process for the
claimant to
rely upon a later progress claim in response to which no Payment Schedule was
served to obtain judgment on a basis conflicting
with issues resolved in the
earlier determination.
70 I thus disagree with the view ultimately arrived at by McDougall J in
John Goss Projects that s 22(4) defines the extent to which an
adjudicator is bound by an earlier adjudication. The view that the claimant once
disappointed
by an adjudicator can seek a different determination from another,
or indeed from a succession of others, until a favourable decision
is reached
would in my view conflict with the policy of the Act to render
adjudicators’ determinations final on issues which
they resolved, subject
only to provisions of the Act conferring limited rights of correction of
determinations.
71 Dualcorp asserts that this approach could produce unfair outcomes
where a claim has not been the subject of adjudication on the
merits but has
been rejected for want of evidence. It was submitted that because of the
unfairness that would flow from precluding
a claimant bolstering its evidence on
another adjudication, it cannot have been intended that adjudications would be
conclusive.
72 I do not agree. It is not at all unusual that persons seeking
remedies in courts or other forums have a once only opportunity
to bring forward
evidence and submissions in support of their claim. This is in fact the usual
situation and is consistent with
what the High Court in D’Orta
referred to as the “central and pervading tenet of the judicial system ...
that controversies, once resolved, are not to be
reopened except in a few,
narrowly defined, circumstances” (at [34]).
Conclusion
73 My conclusion is that the primary judge was correct to refuse summary
judgment in respect of the amounts which were the subject
of the four invoices
referred to in the adjudicator’s determination. The issues relevant to
Dualcorp’s rights to progress
payments in respect of the amounts in those
invoices had been determined by the adjudicator. The application for summary
judgment
(and judgment) was therefore inconsistent with that determination.
74 As the application for leave to appeal raised an issue of general
importance in relation to the construction of the Act, I would
grant leave to
appeal. As I have concluded that the primary judge was correct in the course
she took, the appeal should be dismissed.
75 The orders I propose are as follows:
(a) Leave to appeal granted.
(b) Appeal dismissed.
(c) The applicant/appellant to pay the respondent’s costs of the leave application and of the appeal.
76 HANDLEY
AJA: I agree with Macfarlan JA.
**********
LAST UPDATED:
21 April 2009
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCA/2009/69.html