![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales - Court of Appeal |
Last Updated: 2 October 2008
NEW SOUTH WALES COURT OF APPEAL
CITATION:
Skoric v Meriton
Apartments Pty Ltd [2008] NSWCA 239
FILE NUMBER(S):
40410/07
HEARING DATE(S):
22 September 2008
EX TEMPORE
DATE:
22 September 2008
PARTIES:
Djordje Skoric (A)
Meriton
Apartments Pty Ltd (R1)
Karimbla Construction Services Pty Ltd
(R2)
JUDGMENT OF:
Young CJ in Eq Campbell JA Handley AJA
LOWER COURT JURISDICTION:
District Court
LOWER COURT FILE
NUMBER(S):
DC 86/2005
LOWER COURT JUDICIAL OFFICER:
Delaney
DCJ
LOWER COURT DATE OF DECISION:
6 March 2007
COUNSEL:
B Toomey QC and S Maybury (A)
L King SC and W Reynolds
(R)
SOLICITORS:
Albert A Macri Partners (A)
McCabe Terrill Lawyers
(R)
CATCHWORDS:
TORTS- Occupiers liability- Respondents as occupiers
of building site- Appellant worker suffered serious injuries walking down a
stairwell
carrying a heavy trolley- At first instance focus on safety of stairs-
Primary judge finds no fault with stairs- Pleadings faintly
suggest that
respondents are negligent in not providing lift services and co-ordinating
movements of materials- Primary judge disposing
of such allegation in few words-
Held no error but even had that case been fully considered, there was
insufficient material to demonstrate
the liability of the
respondents.
LEGISLATION CITED:
CASES CITED:
TEXTS CITED:
DECISION:
The appeal is dismissed with
costs.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF
APPEAL
CA 40410/07
DC 86/05
CAMPBELL JA
YOUNG CJ in EQ
HANDLEY AJA
Monday 22 September 2008
SKORIC v MERITON APARTMENTS PTY LTD
Judgment
1 YOUNG CJ in EQ: This is an appeal from the District Court in
which his Honour Judge Delaney found a verdict for the defendants/respondents in
a
claim by the plaintiff/appellant for damages for personal injury.
2 Whilst there were two defendants below and two respondents in this
Court, the primary judge found they were each occupiers. Both
in the court
below and on appeal, they can be considered as one.
3 The basic facts which are not in dispute are that on 22 May 2002, the
appellant who was then 58 years of age was working on the
World Square building
in Goulburn Street, Sydney. He had come to work at about 7.30am and somewhere
between 7.30am and 9am, possibly
about 8.30am, the foreman, a man who was
identified as Zoki, instructed the appellant and another man, Mr Maodus, that
they were
each to take a small trolley known as a “dolly” down to
the 18th floor as a matter of urgency. They were working at
that stage on the
19th floor of the building which was under construction.
4 The dollies each weighed about 35 kilograms and would need to be
carried in both hands. The reason for the movement from the 19th
floor to the
18th floor was that the dollies needed to be filled with gypsum which at the
time of the request appears to be coming
up from ground level by crane and the
crane needed to be discharged of its load.
5 The appellant and Mr Maodus took their dollies to the bank of two
workers’ lifts. They communicated with the driver who was
an employee of
the respondents that they wished to board. However, they say that twice as the
lift passed empty on their floor going
down, the driver waved in a manner to
indicate that he would not pick them up. There was evidence before the learned
primary judge
that there was a rule that before 9am, the workers’ lifts
were to be used for conveying workers from the ground level to their
working
area and were not to be delayed by carrying workers from floor to floor.
6 However, there was evidence from management that there was no such
rule; his Honour never made any factual finding on this.
7 The workers who gave evidence seemed to think that there was such a
general rule, but that, from time to time, the employee who
was driving the lift
would not observe it and would pick them up.
8 Doubtless, in this hope the two men approached the lifts and waited.
They say that after two refusals they realised that their
foreman wanted the
load removed promptly, indeed they could see that the crane with the load of
gypsum was waiting on level 18 to
be speedily unloaded and they realised that
the only way they could get to level 18 was to carry their dollies down the
stairs.
9 The stairs were internal stairs, fully finished, and although the
appellant had alleged otherwise, the learned primary judge found
no defect in
them nor any obstruction on them. Indeed the appellant and others had used the
steps carrying loads on previous occasions
without problems. There was a
landing halfway down the stairs between the 19th and 18th floors, the appellant
had just reached a
point below that landing when he slipped and fell and quite
seriously injured himself.
10 The appellant sued the occupiers of the building and there was some
dispute before the learned primary judge as to who was the
occupier; his Honour
held that both the first and second respondents were the occupiers. There has
been no cross-appeal on this
finding and I have just referred to them as the
respondents.
11 Before us the appellant says that there were two prime issues before
the District Court:
(a) (i) that the respondents as occupiers were negligent in not providing sufficient lift service to allow workers to transport goods; or
(ii) that the respondents as coordinators of the site so carelessly arranged the programme that there was not coordination between those who needed to have loads moved from floor to floor and the lift service; and
(b) that the occupiers were negligent in not providing safe stairs for the workers to carry goods.
12 The
respondents denied liability and also pleaded contributory negligence. They
also sought the court to apply s 151Z of the Workers Compensation Act
1987 to reduce any damages that they might be ordered to pay.
13 On the appeal, Mr B Toomey QC and Mr S Maybury appeared for the
appellant, Mr L King SC and Mr W Reynolds appeared for the respondents.
14 The learned judge had found for the respondents on what I have called
(b) above and that finding is not the subject of the appeal.
Mr Toomey said
that the main ground of the appeal was that his Honour did not accord the
appellant procedural fairness in that he
did not properly consider the case
involving the lifts, particularly the case as to failure to coordinate.
15 There were two principal problems in the way of that argument. As Mr
King said with respect to (a)(ii), it was not pleaded, it
was not part of the
case and even if it was, it was not proved. Mr Toomey says that was far from
correct and that if one looks at
the pleadings and the way the case was run
(particularly the way the appellant below put it at p 208 of the Black Book),
those matters
were put before the judge. Thus we have here a situation where
the appellant lost the case and really does not know why, and that
is not the
way in which litigation should be conducted.
16 If one looks at the amended statement of claim which is on pp 56 and
following of the Red Book, one would find it very difficult
to realise that
either case (a)(i) or case (a)(ii) was before the court. The only matters
appear to be in para 10 (c) where there
is a pleading that the respondents are
responsible for the safe use (of stairs) by workers moving between floors
carrying heavy objects
where there might be slippery substances accumulating on
the floor by reducing the risk of slipping. The words “reducing the
risk
of slipping” are to my mind directed to the staircase rather than to the
case involving coordination or the use of the
lifts.
17 Then particulars of negligence are given in connection with para 16.
Again all of them, except possibly (d) and (e), are particulars
that go to the
case involving the stairs; (d) and (e) are in general terms, namely:
“(d) failing to provide a safe place of work for persons working on the site; and
(e) failing to provide safe access to all places at which workers were obliged to work.”
18 Again, there is
nothing that would make an objective reader think that what was being put was
the case that Mr Toomey outlined
to us, that is, although the appellant was an
employee of a sub sub-contractor, the respondents were the occupiers of the
building
and were in overall control of everything, including the coordination
of cranes and lifts. Thus it was up to the respondents to
see that things were
safe for the workers so that there was not the problem that came about in this
particular case. He says the
respondents must have known that equipment like
dollies would be being moved from floor to floor yet they allowed the unsafe
situation
to continue.
19 On appeal, the emphasis was not so much on (a)(i), that is that the
lift service was unavailable to the workers before 9am. The
notice of appeal
states that the learned primary judge misunderstood the appellant’s case
that the unavailability of the lifts
forced the appellant into the perilous
course of taking the stairs carrying a 35 kilogram trolley and that his Honour
wrongly thought
that that part of the appellant’s case was “faintly
argued” and peripheral and his reasons for rejecting that part
of the case
produced procedural unfairness. It also complained that the learned primary
judge wrongly held that the appellant had
not established any causal connection
between the unavailability of the lifts and the appellant’s fall in the
stairwell.
20 I have doubt as to whether that matter was sufficiently drawn to the
attention of the judge making the decision for that to be
fair comment. It is
the obligation of parties who wish to make a case to put their best foot forward
and to make it completely plain
to the learned judge what are the matters that
he or she have been asked to determine. Even though I have read again what is
on
pp 208 to 209 of the Black Book, one can see that possibly case (a)(i) was
before the judge but it is very difficult indeed to say
that case (a)(ii) was
before the judge.
21 It is certainly correct that if one trawls through the evidence one
can see some material which would base an argument to establish
(a)(ii) but the
appellant has got to do more than that. It has to direct the mind of the judge
by the pleadings, the evidence and
the addresses to the points that need to be
determined. Even if the matters were properly before the judge, it does not
seem to
me that on the material that either case was made out in connection with
what I have called point (a).
22 Mr Toomey pointed out it had been put to the primary judge that even
if he found that the stairs were the best stairs in the world,
to walk down
them, carrying a heavy and awkward weight without a handrail (because the load
needed two hands to hold) was dangerous
in itself and it was thus unreasonable
to refuse the appellant the use of the lifts.
23 Mr King put there was no evidence to support an inference that there
was no justification for the lift driver to decline to accommodate
the appellant
and even if the situation were otherwise, there was no causal connection between
the lift driver’s refusal and
the appellant’s injury. The lift
driver’s refusal is merely a “but for” feature of the sequence
of events.
24 It seems to me that the respondents’ submissions ought to be
upheld. Maybe carrying the load down the stairs was awkward
but it had been
done before, the stairs were in good condition on the fact that the judge found
them and there was nothing perilous
about carrying out that particular task.
Doubtless using the lifts would have been easier and had the lifts been
available, the
accident would not have occurred, but this in my view is not
enough to demonstrate liability on the part of the occupiers.
25 It is true that the learned judge did not direct his mind to the
question of coordination but there was really no sufficient material
to enable
the judge to find for the appellant on this part of the case, if it was part of
the case before him, we just do not know
what arrangements were made for the
delivery of gypsum at 8.30am on this particular day. We do not know if that was
by prior arrangement,
nor do we know if there was some communication problem and
whether that was the communication problem of the appellant’s employer
or
of the respondents’. There was no material before the judge to enable him
to decide whether there was a “not before
9am rule”. It was a rule
that was adopted without consideration as to its implications and indeed it
seems from the evidence
that was before the judge that no-one ever said that if
there was such a rule it was an unreasonable rule.
26 In my view even if case (a)(ii) were properly before the judge, the
material before him was not sufficient to enable the appellant
to succeed, but
in the circumstances it does not appear to me to be any need for the learned
primary judge to have dealt with the
claim about the lifts in any more detail
than he gave. Accordingly I would dismiss the appeal with costs.
27 There was a cross-appeal on an aspect of the case. It is unnecessary
to deal with that in light of my view on the appeal. The
learned primary judge
also found 30% contributory negligence if he were wrong on the primary question.
Mr Toomey properly says that
that was a finding of contributory negligence as to
the case involving inadequate lighting of the stairs and it is not to be taken
as a finding that on the lift count the same would be found. I think that is
right but again it is unnecessary for me to deal with
it. Accordingly I am of
the view that the appeal should be dismissed with costs.
28 CAMPBELL JA: I agree with the orders proposed and with the
reasons given for them.
29 HANDLEY AJA: I also agree. I would only add that the
plaintiff called the foreman, Zoki Kakozakov, without asking him how it came
about that
at 8.30 on the morning of the accident these dollies had to be moved
urgently from level 19 to level 18 and did not ask any questions
to establish
that his situation had arisen urgently as a result of the direction from the
head contractor. The defendant called
Mr Russell, the construction manager,
employed on this site by the head contractor who said that he was the person
with the overall
day to day control of the development. He was asked no
questions in cross examination to establish that the situation that lead
to the
urgent instruction from the foreman Zoki to move these dollies to the lower
level had arisen as a result of any action or
failure of action on his part. In
these circumstances it is clear in my view that the case was never run as a case
where the head
contractor failed to adequately coordinate the trades and the
movement of goods onto this site.
30 CAMPBELL JA: I also agree with the supplementary reasons of
Justice Handley. The orders of the court will therefore be those proposed by
Justice
Young.
[Mr King made submissions on costs]
31 YOUNG CJ in EQ: Since giving reasons it was drawn to our
attention that there has been what is called an offer of compromise, that is if
the appeal
was withdrawn the parties could pay their own costs. There must be
great doubt as to whether that is an offer of compromise, whether
it is or not
would to a great degree depend on the time in which it was made and how far the
costs had been expended at that time.
However, we are not able to be informed
of that fact today. Mr King has asked for time to put in further written
submissions.
However, the court is under an obligation to deal with cases
justly, cheaply and expeditiously. There is no reason why that material
was not
here today and I do not think it is appropriate that we should extend the
hearing of this case any further to enable that
time to be given and on the
material that is before us, there is no sufficient reason to make any special
order for costs.
32 CAMPBELL JA: I agree.
33 HANDLEY AJA: I agree.
34 CAMPBELL JA: The orders of the court remain those earlier put
out.
***********************
LAST UPDATED:
1 October 2008
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCA/2008/239.html