You are here:
AustLII >>
Databases >>
Administrative Decisions Tribunal of New South Wales >>
2011 >>
[2011] NSWADT 129
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
O'Brien v Building Professionals Board (No 2) [2011] NSWADT 129 (3 June 2011)
Last Updated: 6 June 2011
|
|
Administrative Decisions Tribunal
|
|
Case Title:
|
O'Brien v Building Professionals Board (No 2)
|
|
|
|
Medium Neutral Citation:
|
|
|
|
|
Hearing Date(s):
|
|
|
|
|
Decision Date:
|
|
|
|
|
Jurisdiction:
|
|
|
|
|
Before:
|
Magistrate N Hennessy, Deputy President, P
Hayward, Non-Judicial Member
|
|
|
|
Decision:
|
The Building Professionals Board is to pay Mr
O'Brien's costs of the adjournment of the hearing listed for 5 and 6 March 2009
as agreed
or assessed.
|
|
|
|
Catchwords:
|
COSTS - general rule is each party pays own costs
- whether fair for State agency to pay costs of applicant requesting review of
disciplinary
finding - significance of State agency acting as model
litigant
|
|
|
|
Legislation Cited:
|
|
|
|
|
Cases Cited:
|
|
|
|
|
Texts Cited:
|
|
|
|
|
|
|
|
|
|
Parties:
|
|
|
|
|
Representation
|
|
|
|
|
|
|
|
|
- Solicitors:
|
|
|
|
|
File number(s):
|
|
|
|
Publication Restriction:
|
|
REASONS FOR
DECISION
Introduction
- Mr
O'Brien has applied for a costs order against the Building Professionals Board
(the Board). The application has been determined
'on the papers' following
written submissions from each party: Administrative Decisions Tribunal Act
1997 ( ADT Act ), s 76.
- The
Board found Mr O'Brien, who is an accredited certifier, guilty of unsatisfactory
professional conduct, reprimanded him and fined
him $11,000. Mr O'Brien applied
to the Tribunal for a review of the disciplinary finding and the action taken by
the Board: Building Professionals Act 2005 ( BP Act ), s 33. The
Tribunal set aside the Board's decision: O'Brien v Building Professionals
Board (No 2) [2010] NSWADT 250.
- The
factual background to these proceedings, which is relevant to Mr O'Brien's
application for costs, is summarised in the Tribunal's
decision at [2] to [5]:
2 In 2000 Mr O'Brien, Mr Bernie Cohen and Mr Richard Moy, were all accredited
certifiers and directors of Essential Certifiers Pty
Ltd (Essential Certifiers).
The proceedings before the Tribunal relate to a construction certificate for a
26 unit residential apartment
building in Campbell Street, Northmead (the
Northmead project). . .
3 On 2 November 1999 the Land and Environment Court granted development
consent for the Northmead project. On 29 June 2000, Austcorp
No 459 Pty Ltd
became the registered proprietor of the land. Diab Finianos was the developer
and his son Ray Finianos (through Silky
Constructions Pty Ltd) was the builder.
In early 2000 Mr Diab Finianos engaged Richard Drummond of Drummond & Rosen
Pty Ltd,
architects, to prepare construction plans for the Northmead project. On
21 August 2000 Silky Construction Pty Ltd applied to Essential
Certifiers for a
construction certificate to enable building work to begin. Mr Cohen assessed
some plans in relation to the Northmead
project on or about 21 August 2000 and
sent a facsimile to the builders on 1 September 2000 saying that he had assessed
the plans
for compliance with the BCA and the development consent. In the same
facsimile Mr Cohen listed six further items that needed to be
provided before
the construction certificate could be issued. On 11 September 2000 Mr Cohen went
on leave to attend the Olympic Games
in Sydney. The following day an
administrative employee of Essential Certifiers printed the construction
certificate. The certificate
named "Essential Certifiers Pty Ltd" as the
Certifying Authority and "Bernie Cohen" as the accredited certifier.
4 Some time between 12 September 2000 and 26 September 2000 Mr O'Brien
endorsed the construction certificate with following words:
'B Cohen per ROB'
(his initials). The certificate was released to the builders on 26 September
2000 after the six outstanding items
referred to in Mr Cohen's facsimile of 1
September 2000 had been provided.
5 The Northmead project was completed on 26 October 2001. The owners,
Austcorp No 459 Pty Ltd, applied to the Baulkham Hills Shire
Council for strata
subdivision approval. Council refused that application because the development
did not comply with the development
consent. Among other things, the project had
been built with only one level of car parking instead of two, as shown on the
construction
plans. Litigation in the Land and Environment Court and the Supreme
Court followed. The building was unoccupied for over four years
before
rectification works were completed.
- The
substantive application for review was listed for two days on 5 and 6 March
2009. Two days before the hearing the solicitors for
the Board sought to amend
the reasons for decision so as to plead an alternative ground for the
disciplinary finding. The necessity
to amend the reasons was said to have arisen
on the advice of Mr Robertson SC. Mr O'Brien opposed that application. The
hearing dates
were vacated so that the Board's amendment application could be
determined. The Tribunal decided not to allow the Board to amend
its reasons for
decision: O'Brien v Building Professionals Board [2009] NSWADT 189.
Costs applications and relevant provisions
- Mr
O'Brien has applied for the following costs orders:
(1) that the Board pay Mr O'Brien's costs thrown away by reason of the
adjournment of the hearing listed for 5 and 6 March 2009 (
costs for causing
an adjournment );
(2) that the Board pay Mr O'Brien's costs of the Board's unsuccessful
application to amend ( costs of unsuccessful amendment application );
(3) that the Board pay Mr O'Brien's costs of the proceedings from 1 August 2009
to date ( costs of the principal proceedings ).
- The
Tribunal has power to award costs under s 88 of the ADT Act in relation
to these proceedings: Building Professionals Act 2005, s 35. Section 88
relevantly provides that:
88 Costs
(1) Each party to proceedings before the Tribunal is to bear the party's own
costs in the proceedings, except as provided by this
section.
(1A) Subject to the rules of the Tribunal and any other Act or law, the
Tribunal may award costs in relation to proceedings before
it, but only if it is
satisfied that it is fair to do so having regard to the following:
(a) whether a party has conducted the proceedings in a way that unnecessarily
disadvantaged another party to the proceedings by conduct
such as:
(i) failing to comply with an order or direction of the Tribunal without
reasonable excuse, or
(ii) failing to comply with this Act, the regulations, the rules of the
Tribunal or any relevant provision of the enactment under
which the Tribunal has
jurisdiction in relation to the proceedings, or
(iii) asking for an adjournment as a result of a failure referred to in
subparagraph (i) or (ii), or
(iv) causing an adjournment, or
(v) attempting to deceive another party or the Tribunal, or
(vi) vexatiously conducting the proceedings,
(b) whether a party has been responsible for prolonging unreasonably the time
taken to complete the proceedings,
(c) the relative strengths of the claims made by each of the parties,
including whether a party has made a claim that has no tenable
basis in fact or
law,
(d) the nature and complexity of the proceedings,
(e) any other matter that the Tribunal considers relevant.
- The
general rule is that each party to proceedings pays his or her own costs. The
Tribunal has a discretion to award costs 'but only
if it is satisfied that it is
fair to do so' having regard to the matters listed at (a) to (e). Those matters
include 'any other
matter that the Tribunal considers relevant'. A relevant
factor in this case is that the Board, being a state agency, is required
to act
as a model litigant: AT v Commissioner for Police [2010] NSWCA 131 at
[32]; Mahenthirarasa v State Rail Authority of NSW (NSW) (No 2) [2008]
NSWCA 201 at [15] to [22]; Galea v Commonwealth (No 2) [2008] NSWSC 260
at [18] to [21]. The Court of Appeal has held that s 88 sets "a relatively low
hurdle for an applicant seeking an order": AT v Commissioner of Police, NSW
[2010] NSWCA 131 , per Basten JA at [33].
Costs for causing an adjournment
- The
first part of Mr O'Brien's application relates to the costs incurred by the
Board's application for an adjournment, two days before
the hearing. The
adjournment was necessary in order for the Tribunal to hear its application to
amend its reasons for decision. The
Tribunal granted the adjournment but refused
the application to amend. In its reasons for decision ( O'Brien v Building
Professionals Board [2009] NSWADT 189), the Tribunal made the following
comment at [28], in relation to the adjournment application;
In my view, the delay in notifying Mr O'Brien of the alternative basis for
its decision arose because, until it received Mr O'Brien's
detailed submissions,
the Board was firmly of the view that he had signed the construction certificate
on 12 September as the certifying
authority. The Board apparently did not regard
Mr O'Brien's submissions as tenable until close to the hearing date. It was at
that
stage that it sought to amend the Reasons for Decision.
- Mr
O'Brien submitted that the Board should pay his costs because it caused an
adjournment and thereby unnecessarily disadvantaged
him: ADT Act , s
88(1A)(a)(iv).
- The
Board submitted that while it had caused an adjournment, the adjournment did not
"unnecessarily disadvantage" the other party:
s 88(1A)(a). The Board submitted
that Mr O'Brien has not shown actual disadvantage beyond referring to
unspecified costs thrown away.
Secondly, the Board submitted that Mr O'Brien's
conduct was relevant to the question of whether he had been unnecessarily
disadvantaged.
The Board said that he was responsible for the first hearing date
being vacated one week prior to the hearing. Thirdly, Mr O'Brien
failed to
comply with the Tribunal's directions in relation to the filing of evidence, so
it was not until 28 November 2008 that
the Board was in a position to assess his
evidence and respond.
- The
adjournment meant that Mr O'Brien was unnecessarily disadvantaged because the
resolution of his application was delayed. He does
not need to adduce evidence
for me to be satisfied that he was unnecessarily disadvantaged by the
adjournment. The extent of any
legal costs he may have incurred is for him to
establish if those costs are not agreed.
- Secondly,
even if Mr O'Brien's previous conduct caused unnecessary delays, it is
nevertheless fair for the Board to pay the costs
of the adjournment. The Board
had all Mr O'Brien's evidence three months before the hearing. The adjournment
was requested two days
before the hearing following advice from senior counsel.
There is no doubt that the Board caused the adjournment and that Mr O'Brien
was
unnecessarily disadvantaged as a result. We are satisfied that in all the
circumstances it is fair to order the Board to pay
Mr O'Brien's costs for
causing the adjournment.
Costs of unsuccessful amendment application
- The
application to amend the reasons for decision was heard on 6 May 2009. Reasons
for dismissing the application were given on 21
July 2009.
- Mr
O'Brien submitted that the Board should be ordered to pay his costs relating to
the Board's unsuccessful amendment application.
He said that had the Board
conducted its proceedings properly, it would have raised the alternative
argument at the outset, thus
avoiding the need for the interlocutory
application. Mr O'Brien relied on s 88(1A)(b) or (e) (prolonging unreasonably
the time taken
to complete the proceedings and any other relevant matter).
- The
Board submitted that if costs are awarded against it for causing an adjournment,
it would be unfair for further costs to be awarded
merely because the Board's
interlocutory application proceeded, but was unsuccessful. We are persuaded by
that argument. A costs
order would not have been justified if the Board had made
its application in a timely manner. As we have decided to award costs for
causing an adjournment, we are not satisfied that it would be fair to award
further costs in relation to the interlocutory proceedings
themselves.
Costs of principal proceedings (from 9 August 2009 to present)
Introduction
- The
basis for this aspect of the costs application is that the Board, as a State
agency, is required to act as a model litigant. In
AT v Commissioner for
Police [2010] NSWCA 131 Basten JA (Giles and Bell JJA agreeing) stated at
[32] that 'a further factor to be taken into account [under s 88(1A)(e)] is that
the respondent, being a State agency, was also required to act as a model
litigant.' However, his Honour noted at [33] that 'that
approach does not
diminish the force of the general principle that each party should bear its own
costs in the Tribunal.'
- Section
88(1A)(b) and (c) provide that relevant factors in determining whether it is
fair to make a costs order include whether a
party has been responsible for
prolonging unreasonably the time taken to complete the proceedings and the
relative strengths of each
party's claim.
- In
Sheppard v Commissioner for Fair Trading, NSW Office of Fair Trading
[2010] NSWADT 192 the Tribunal ordered a State agency to pay the applicant's
costs because it did not reconsider its position even after it was apparent
that
the assumption on which the decision was based was "without any substance". In
awarding costs, the Tribunal relied on the principles
relating to model
litigants and the power in s 88(1A)(b) (prolonging unreasonably the time taken
to complete the proceedings).
- In
Mr O'Brien's view, certain statements made by the Board's senior counsel support
the view that the Board was determined to make
somebody liable for the Northmead
project.
- Mr
O'Brien also submitted that the Board should have known shortly after its
application for amendment was refused that Mr Cohen was
not a credible witness
and that the Tribunal would reject his evidence. If his evidence was rejected
then it was highly likely that
the Tribunal would find that Mr O'Brien was not
exercising functions as a certifying authority at the time and that a
disciplinary
finding could not be made against him.
Board's motivation
- During
the adjournment application on 3 March 2009, Mr Robertson SC on behalf of the
Board said (taken from transcript prepared on
behalf of Mr O'Brien's
solicitors):
So we don't want to be in a situation as the Board having responsibilities to
the public obviously of having the seminal example of
poor certification
practise (sic) not being capable of having some sort of disciplinary outcome and
we said as to Mr O'Brien for
participation (sic) but we considered that he may
not have been primarily responsible for the decisions that were made within the
certification of the firm to give this degree of leniency to the developer, but
nonetheless he is the person - he is the only person
who actually signed,
physically signed and issued or was responsible for issuing the CC, but we don't
want to be in a situation where
we fall between two stools as a consequence of
the clever and carefully instructed legal submissions that defends (sic) Counsel
has
prepared.
- According
to Mr O'Brien, the submissions which senior counsel for the Board referred to
were that:
(1) when the construction certificate was issued, there were, contrary to the
Board's finding, no requirements/items identified in
Mr Cohen's facsimile of 1
September 2000 which still remained outstanding; and
(2) Mr Cohen's evidence on the issue could not be accepted; and
(3) the Board's case must fail because Mr O'Brien was not performing functions
as a certifying authority of the project.
- The
Board denied Mr O'Brien's assertion that it was determined to make someone
liable for the project. The oral submissions of Mr
Robertson SC were made in the
context of a proposed amendment of the Board's reasons for decision to ensure
all relevant issues were
before the Tribunal.
- The
Board further submitted that Mr O'Brien did not complete Mr Robertson's sentence
which, according to his transcript, continued
as follows:
...hence we say if they're right and we're wrong, nevertheless,
even if he [O'Brien] acted administratively, you could say under the
general
concept of unsatisfactory professional conduct that it fell below the standards
the public would expect someone in his position
to perform because he signed a
certificate that was just not dated correctly.
- According
to the Board, this made it clear that their submissions were restricted to the
policy position behind the amendment and
the public interest in ensuring
unsatisfactory professional conduct is dealt with.
Mr Cohen's credibility
- Mr
O'Brien said that the Board should have reconsidered its position once doubt had
been cast on the accuracy of the information that
was given to it by Mr Cohen.
He said that the matter was unnecessarily prolonged from late July 2009, when
the Board's application
for amendment had been rejected, until the end of the
proceedings. In all the circumstances, he submitted that it is fair that he
should receive his costs from 1 August 2009, being ten days after the Board
learnt that its application to amend had been refused.
- The
Tribunal ultimately rejected the Board's finding that Mr O'Brien was exercising
functions as a certifying authority at the time:
O'Brien v Building
Professionals Board (No 2) [2010] NSWADT 250 at [55]. At [23] the Tribunal
found that Mr Cohen, not Mr O'Brien, was the certifying authority on the
Northmead project. That conclusion
was based on several findings including the
following:
a) Mr Cohen's name and accreditation number appeared on
the certificate;
b) despite the fact that the construction certificate named Essential
Certifiers Pty Ltd as the certifying authority, the certifying
authority must be
an individual who is an accredited certifier;
c) the functions of a certifying authority cannot be delegated nor can
another accredited certifier act as agent for a certifying
authority;
d) Mr Cohen met with the developer and the architect and told them he could
certify the plans;
e) after the builders applied for the construction certificate, Mr Cohen
assessed some plans for compliance with the BCA and the development
consent and
requested six further items to be attended to before the construction
certificate could be issued;
f) Mr Cohen did not transfer the file for the Northmead project to Mr
O'Brien; and
g) the construction certificate was printed by administration staff on Mr
Cohen's instructions.
- Mr
O'Brien submitted that these matters were known to the Board at a very early
stage in the proceedings. Only items (d), (f) and
possibly (g) were matters that
were in dispute.
- Mr
O'Brien submitted that the Board appreciated that by failing to reconsider its
position after the amendment application had been
refused, their case was
"...largely a question of testing the evidence given by only one witness, a Mr
Cohen" (Transcript, 26 August
2009, page 1.15-20). Yet at the same time, the
Board knew the following:
(1) that Mr Cohen had not co-operated with the Board in providing a witness
statement, contrary to a direction in relation to the
serving of witness
statements (Transcript 26 August 2009, page 1.20);
(2) that the evidence of an independent witness, Mr Whitely (the quantity
surveyor appointed by the mortgagee) was directly contrary
to Mr Cohen's claim
that he did not say that the construction certificate could issue (Transcript 27
August 2009, page 16-17);
(3) Mr Cohen's evidence would also be contradicted by Messrs Finianos, Hefren
and Drummond. The Board never intended to suggest that
the evidence of these
witnesses was wrong (Transcript 26 August 2009, page 27.25);
(4) that Mr Cohen had received the most cautions, fines and reprimands in the
Board's register of disciplinary action (Transcript
27 August 2009, page 2.35);
(5) that in the 10 years since the incident, Mr O'Brien's conduct as an
accredited certifier had been exemplary and he posed no risk
to the public.
- According
to Mr O'Brien, this information was sufficient for the Board to appreciate that
he was not the certifying authority. At
that stage the Board (acting as a model
litigant) should have reconsidered its position and accepted that the finding of
unsatisfactory
professional conduct should be set aside.
Conclusion
- Where
it is clear that a respondent has refused to reconsider its decision in the face
of clear evidence or legal argument that the
decision is wrong, an award of
costs may be fair. A decision to that effect may be supported on the basis of s
88(1A)(b) or (c) or
because a State agency is expected to act as a model
litigant: s 88(1A)(e). However, it would not be fair to award costs in these
proceedings. After the Tribunal had refused the application for amendment, the
Board would have known that the chances of its decision
being affirmed were less
than if the amendment had been granted. That was the case because the Board knew
that there was a risk that
Mr Cohen would give evidence that was inconsistent
with the evidence he gave during the Board's earlier investigation.
- However,
because Mr Cohen refused to provide a witness statement prior to the hearing,
the Board did not know exactly what his evidence
would be. The Board decided not
to cross-examine Mr Diab Finianos, Mr Drummond or Mr Hefren. Ultimately, the
Tribunal found that
Mr Cohen's evidence had been comprehensively discredited in
cross examination and that it was inconsistent with the evidence of Mr
Diab
Finianos, Mr Drummond and Mr Hefren: O'Brien v Building Professionals Board
(No 2) [2010] NSWADT 250 at [28]). That is not an outcome which the Board
could have predicted with any certainty.
- Nor
are we persuaded that Mr Robertson's observations during the application for
adjournment, mean that the Board was determined to
make someone liable
regardless of culpability. His comments, which I accept were made, do not
constitute a basis for concluding that
it is fair to award costs against the
Board. One of the Board's aims is to uphold the public interest in ensuring that
unsatisfactory
professional conduct of accredited certifiers is addressed.
Although the Board must act as a model litigant, that does not prevent
it from
acting firmly and properly to protect the public interest.
Order
The Building Professionals Board is to pay Mr O'Brien's costs of the
adjournment of the hearing listed for 5 and 6 March 2009 as agreed
or assessed.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWADT/2011/129.html