![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
High Court of Australia |
OGLE v. COMBOYURO INVESTMENTS PTY. LTD. [1976] HCA 21; (1976) 136 CLR 444
Vendor and Purchaser
High Court of Australia
Barwick C.J.(1), Gibbs(2), Mason(2), Jacobs(2) and Murphy(3) JJ.
CATCHWORDS
Vendor and Purchaser - Sale of land - Contract of sale - Refusal by purchaser to complete - Anticipatory breach - Suit for specific performance by vendor - Continued refusal by purchaser to complete - Whether vendor entitled to rescind and claim damages.
HEARING
Sydney, 1976, April 5, 30. 30:4:1976DECISION
April 30.
2. I might observe in passing that there had been difficulties between the
respondent and the proprietor of the land in connexion
with the completion of
the contract between them which had delayed and, from time to time, rendered
uncertain settlement of that
contract. These circumstances are not relevant to
any principal matter in the case, though I shall need to refer to them later
in
connexion with an alternative submission made on behalf of the appellant.
(at p447)
3. In its notification of 8th October, the respondent, whilst retaining time
as of the essence, gave the appellant the option of
settling on any one of the
days 21st, 22nd or 23rd October. The appellant did not choose any of these
days and did not complete on
any one of them. By 23rd October, he therefore
would have been in radical breach of his contract with the respondent. (at
p447)
4. However, on 17th October and 18th October, the respondent's solicitors
called the attention of the appellant's solicitors to
statements by the
appellant that indicated that he did not intend to complete the contract at
any of the times indicated by the respondent
in its letter of 8th October. The
respondent's solicitors in their letter said that if no replies were received
to its correspondence
- which in truth called for reply - counsel would be
briefed on the question whether there was a clear anticipatory repudiation of
the contract by the appellant: and that, in the event that counsel's view was
in the affirmative, a writ for specific performance
would be issued on the
following Monday, which was 21st October. A letter from the appellant's
solicitors received in the interim,
so far from indicating an intention to
settle, raised the possibility of setting up misrepresentation inducing the
contract. The
appellant's solicitors replied in substance that they took this
letter as indicating a refusal to settle and that, failing a statement
by the
respondent to the contrary, the writ would be issued first thing on the Monday
morning. To this letter there was no reply.
The respondent's anxiety for
certainty is understandable. A suit for specific performance was commenced on
21st October 1974. That
suit was based on the appellant's anticipatory breach
of the contract. But the respondent did not accept it on the basis of a
termination
of the contract. It treated the contract as still on foot. The
writ was sent to the appellant's solicitors under cover of a letter
in which
it was said that the respondent remained ready, willing and able to settle on
any one of the days 21st, 22nd or 23rd October.
(at p447)
5. On receipt of the writ and this letter, the appellant's solicitors wrote
the same day, reiterating the possibility of raising
inducing
misrepresentation but giving no indication of any willingness to complete on
any of the suggested days. (at p448)
6. On 7th November, the appellant unsuccessfully applied for summary judgment
in the suit for specific performance. However, leave
to add to the writ an
alternative claim for damages, i.e. for loss of bargain, was given to the
respondent. That amendment was made
on 20th November. In opposing summary
judgment, the appellant asserted that he was not obliged to complete the
contract at all. (at
p448)
7. On 14th November, the respondent, whilst indicating its own willingness to
complete the contract and maintaining that time remained
of the essence,
informed the appellant that it had decided to accept the appellant's
repudiation of the contract and to proceed for
damages, unless it received
within a time specified the appellant's undertaking to complete on a date
which the appellant might reasonably
nominate, time being acknowledged by the
appellant as of the essence. On the following day, the respondent's solicitors
amplified
their letter by pointing out that the respondent was not departing
from its position that settlement was overdue or that time was
of the essence:
and that it was not offering to substitute another day for settlement for the
day prescribed by the contract. (at
p448)
8. It is clear from this correspondence that, without departing from its
situation as a party entitled to sue for damages for breach
of the contract,
the respondent was prepared to afford the appellant an opportunity to remedy
its breach. (at p448)
9. On 18th November, the respondent terminated the contract on the basis of
the appellant's repudiation of it. The respondent notified
the termination on
19th November. (at p448)
10. When the respondent's suit for specific performance with its alternative
claim for damages was about to be heard, the appellant
notified the respondent
that it would be contended that, because the writ had not been amended to
include the alternative claim for
damages until a date after the alleged
acceptance of the appellant's repudiation of the contract, the cause of action
on which the
suit was founded was not complete at the date of the issue of the
writ. For this reason, it was said, the respondent must fail. (at
p448)
11. Thereupon, the respondent was given leave to discontinue its suit for
specific performance with its alternative claim for damages.
A suit commenced
by a writ issued on 12th February 1975, claiming only damages for breach of
contract was brought on for hearing.
In this suit, the respondent alleged the
repudiation by the appellant on or about 18th November 1974, the respondent's
election thereupon
to terminate the contract and the communication of that
election to the appellant on 19th November 1974. Alternatively, it was alleged
in the suit that the appellant had repudiated the contract on or about 21st
November 1974, and that the respondent had elected to
terminate the contract
and had notified that election to the appellant on the same day, 21st November
1974. The appellant's defence
to this suit was a denial of the paragraphs of
the statement of claim which alleged that repudiation on the alternative dates
and
the acceptance of the repudiation. It was alleged in par. 3 of the defence
that "On or about 18th November 1974, the plaintiff sold
the land the subject
of the contract to one John Blackburn, which sale was the subject of a letter
and notice referred to in par.
3 (b) of the statement of claim". This was a
reference to a sale by the respondent to the registered proprietor of the land
which
it had bought from that registered proprietor under the contract which
is referred to in cl. 25 of the contract. I shall refer later
to the
circumstances of this sale. It was then alleged by pars 4 and 5 of the
statement of defence that, at the respective times
of the alleged repudiation
and acceptance, the suit for specific performance was pending, there being no
other claim in it at those
dates than the claim for specific performance. For
this reason, the appellant said that in point of law it was not competent for
the respondent to rescind the contract as alleged in the statement of claim.
(at p449)
12. In giving his reasons for judgment, the learned trial judge said, "I
would myself have no doubt that the defendant's conduct
up to 21st November
led irresistibly to the inference that he did not intend to perform the
contract at all." With that conclusion
I am fully in accord. His Honour also
found that the appellant, being in breach of the contract by 23rd October
1974, continued at
all material times to be in breach but that he did not
commit any fresh or different breach after 23rd October. His Honour thought
that thereafter there was merely a failure to remedy the breach already
committed. With that conclusion I agree. However, his Honour
concluded that,
although the appellant committed no fresh breach, it was legitimate for the
respondent to regard him as having finally
repudiated the contract at that
time, that is to say, by 18th November 1974, as alleged in par. 3 of the
statement of claim. This
finding also has my agreement. (at p449)
13. But I would add that the appellant was in breach of the contract on 22nd
October or, at latest, 23rd October, in failing to
complete. That breach could
have been waived or the respondent been estopped from relying on it. But, in
my opinion, it ought not
to be held that the respondent did waive that breach
or do anything to estop itself from relying upon it. It was submitted in
argument
by counsel for the appellant that the respondent could not sue upon
that failure to complete without first rescinding the contract.
However, in my
opinion, that submission was erroneous and misconceived. Where a promisor has
failed to perform his promise, he may
without more, be sued for such damages
as flow from the breach. Where the promise which is not performed is the
promise to complete
a purchase, the damages will include the loss of the
benefit of the performance of that promise, properly referred to as damages
for loss of bargain. There is no need first to rescind the contract in order
to recover damages in that case, which is a case of
actual, as distinct from
anticipatory, breach or repudiation. In the latter case, there must of course
be an acceptance of the anticipatory
breach or repudiation and thus a
termination of the contract, as from that time. But it is otherwise in the
case of an actual breach.
(at p450)
14. Here the appellant failed to perform his promise to complete. That
failure not being waived and the respondent not being estopped
from relying
upon, was sufficient to support the verdict in this case, without resort to
any question of rescission. However, the
respondent relied on the subsequent
repudiation of the contract by the appellant, presumably not realising that
the failure to complete
provided the necessary basis for a claim to damages
for loss of bargain. The trial judge has found the appellant's repudiation and
the respondent's acceptance of it. Having called attention to the effect of
the failure to complete, which really left no room for
repudiation, I shall
consider the case on the footing of the judge's findings. (at p450)
15. It seems to me that the case on these findings can be resolved by the
application of well-known and well authenticated propositions
of the law of
contracts. Where a promisor has so conducted himself prior to the date for
performance of his promise that the promisee
may reasonably form the opinion
that the promisor does not intend to perform the promise, the promisee may
terminate the contract
in the sense of putting an end to his own and the
promisor's further obligation to perform thereunder. He may, of course, not
choose
to regard the promisor's attitude or conduct as warranting the
termination of the contractual obligations of further performance,
but instead
he may insist on the performance of the promisor's promise according to its
terms. If he takes the latter course, the
promisor, if he performs his promise
at a subsequent time, will not be liable in any respect for conduct which
might have been treated
as an anticipatory breach or a repudiation of the
contract. Further, he may rely to his advantage on conduct of the promisee
subsequent
to the time at which the promisee chooses not to terminate the
contract. (at p451)
16. But if the promisee chooses to treat the contract as at an end, in so far
as it requires further performance on the part of
either party to it, the
promisor will be quit of any obligation further to perform the contract,
assuming of course that he does
not successfully contest the right of the
promisee so to treat the contract as at an end. However, the promisee's right
to damages
for any breach which has occurred up to the date of the termination
of the contract, including the anticipatory breach or repudiation
of it,
remains. It is also a consequence of the acceptance of the repudiation that
the contract, being duly terminated, may not be
revived except by consent of
the parties. It will not be revived, if duly terminated by the unilateral
action of the promisee. (at
p451)
17. Now, in this case, as the learned trial judge found, the respondent was
entitled in all reason to regard the appellant as having
repudiated the
contract on 18th November: that is to say, the appellant had by that time
indicated that he did not propose in any
event to perform his promise. In
truth, in my opinion, this was really no more than an indication that the
appellant did not intend
to remedy the actual breach which was complete on
22nd or 23rd October. That breach, as I have pointed out, remained available
to
the respondent without any need to rescind the contract. However, treating
the appellant, as the trial judge did, as having repudiated
the contract, the
respondent was entitled to treat it as no longer calling for performance on
the part of either the appellant or
the respondent. It notified to the
appellant on 19th November its acceptance of the repudiation. It is clear that
the respondent
did not then lose its right to damages for the breach of the
contract which had occurred by the appellant's failure to settle on
or before
23rd October, or for the breach of the contract by the repudiation of the
appellant. The action in which judgment has been
given for the respondent was
an action in which it sought damages for the breach by repudiation of the
contract by the appellant.
As well, as I have pointed out, it had the benefit
of the breach on or before 23rd October, which breach remained available to it
throughout. I should have thought that, on either basis, this appeal should
fail. (at p451)
18. However, some submissions have been raised by the appellant with which I
should deal. It is said that, because a suit for specific
performance was on
foot, there could be no claim for damages for repudiation and for this we were
referred to some cases which depended
upon procedures formerly obtaining in
Chancery and to a case in the Court of Appeal, Public Trustee v. Pearlberg
(1940) 2 KB 1 .
The cases in Chancery and the case in King's Bench, in which
they were cited, were all cases which dealt with a contractual right
to
rescind in the sense of treating the contract as inoperative from its
beginning. They were none of them cases which involved the
termination of a
contract resulting from an accepted repudiation. Further, the first three
cases which are referred to in Public
Trustee v. Pearlberg depend on the
understandable rule of the Court of Chancery that no case at law antithetic to
the basis of a
suit in Chancery could be permitted. But, once the suit in
Chancery was disposed of, the reason for denying the cause of action at
law
disappeared. These procedural rules of Chancery really had no place in the
Judicature system. Thus, within that system, as in
the Supreme Court of
Queensland, a plaintiff could sue concurrently for specific performance and,
in the alternative, for common
law damages, ultimately choosing between the
remedies. It cannot be said as of these times that a suit for specific
performance and
an alternative claim for damages for loss of bargain cannot
co-exist in point of procedure. (at p452)
19. Consequently, I question the validity of the conclusions in Public
Trustee v. Pearlberg. But however that might be, I am unable
to accept so much
of the views of Luxmoore and Goddard L.JJ. as would carry over these rules and
considerations of the Court of Chancery
into the common law as to rescission
of contracts upon accepted anticipatory breach. (at p452)
20. It being found that the appellant had repudiated by 18th November, that
there had been an election to terminate and that notification
of such
termination had been given, it seems to me no point arises out of the fact
that there was a suit for specific performance
subsequently commenced and
later abandoned. Even if the Chancery rule were applied, on abandonment of the
suit the right to damages
was exercisable. But, in any case, as I have
indicated, the commencement of the suit for specific performance did not
terminate the
right to damages for failure to complete by a time made
essential to the contract or to revive the contract if it had been duly
terminated.
The point intended to be made by the appellant in relation to the
suit for specific performance was misconceived and of no validity.
If the
contract was duly terminated, no unilateral act of the respondent could
displace that termination. Only a consensual act could
do so. Thus, it seems
to me that the respondent's suit for specific performance did not alter the
rights of the parties. To that
suit as originally founded, the appellant would
have had a complete defence in the fact of the due termination by the
respondent
upon the appellant's repudiation. Of course, if that termination
had been wrongful, and the appellant had treated and accepted it
as a
repudiation by the respondent, the consequential termination of the contract
by the appellant would equally have afforded the
appellant a defence to the
claim for specific performance. But the termination by the respondent being
lawful, the right to damages
for the appellant's repudiation and breach
remained quite unimpaired. The claim for damages was made as early as November
20th, if
not before. It was quite open to the respondent to have the benefit
of that claim notwithstanding the existence as of that date of
the claim for
specific performance. (at p453)
21. In one other submission with which I should deal some weight was placed
by the appellant's counsel on the decision of this Court
in Carr v. J. A.
Berriman Pty. Ltd. [1953] HCA 31; (1953) 89 CLR 327 . I find great difficulty in finding
anything of benefit to
the appellant in
the decision of that case. It is
quite
true that in that case this Court thought that, by reason of a breach
additional
to the breach
which had been relied upon in
the Court below, the
conclusion was warranted that there was a repudiation by the building
owner of
his promise under the contract;
that, by the second breach, he had
demonstrated intention not to be bound by the contract.
The Court
in so
concluding allowed the
first breach to be regarded as giving colour and
significance, on the issue of repudiation,
to the second
breach on which, in
the
long run, the Court seemed to found itself. (at p453)
22. It is true, as pointed out by counsel for the appellant, that in Carr v.
J. A. Berriman Pty. Ltd., the Court indicated that
the attempt to terminate
the contract on the part of the builder was a repudiation on his part, if in
truth there was no repudiation
by the building owner which warranted the
termination of the contract by the builder. No doubt, in general, an
unwarranted termination
of a contract in consequence of a purported acceptance
of what is wrongly claimed to be repudiation will be regarded as a repudiation
by the person giving the notice of termination. But it seems to me not
necessarily to be so in all cases and in all circumstances.
What is said in
Carr v. J. A. Berriman Pty. Ltd. should be read in relation to the facts of
that case. (at p453)
23. However, assuming that the giving of a notice of termination as upon a
repudiation to the appellant was unwarranted in this
case, and that the
respondent's attempted termination of the contract could be regarded as itself
a repudiation by the respondent,
that repudiation would need to have been
accepted by the appellant if any rights were to accrue to him from the
unwarranted giving
of a notice of termination. No case of a repudiation by the
respondent accepted by the appellant was made on the pleadings or in
the
evidence, nor do I find any trace of it in the judgments of the Court below.
Paragraph 3 of the statement of defence cannot be
read, in my opinion, as
counsel for the appellant proposed, as an allegation of an accepted
repudiation of the contract by the respondent.
But, in any case, as I have
indicated, I agree with the findings of the primary judge, quite apart from
the failure to complete on
22nd or 23rd October, that there was a repudiation
by the appellant and that the giving of the notice to terminate the contract
consequent
upon that repudiation was justified. Consequently, no question of a
repudiation of the contract by the respondent arises. (at p454)
24. I must now deal with an alternative submission made on behalf of the
appellant. Strictly having regard to the conclusion I have
so far expressed,
the point it seeks to raise is not available to him. The point is that in fact
the time for settlement had not
arrived by 21st November or, for that matter,
at all, because there had been no settlement of the contract between the
respondent
and the registered proprietor of the land, Blackburn, on 8th
October or at all. If, in truth, the appellant had repudiated the contract
on
18th November (putting on one side the breach on 22nd or 23rd October), and
the respondent had accepted it and notified to the
appellant the consequential
termination of the contract on 19th November, it matters not when the contract
would thereafter in truth
fall for completion. It had been repudiated and for
that reason terminated so far as further performance was concerned. (at p454)
25. However, I shall briefly express my further reasons for rejecting the
submission. The contract between the respondent and Blackburn,
the registered
proprietor, became the subject of litigation in the Supreme Court of
Queensland. Upon a suit for specific performance,
brought by the respondent
against Blackburn, being called on for hearing, it was settled on terms. In
consequence, there were two
settlement documents agreed upon by the parties:
but the substance of the settlement was that the respondent would settle for
the
land on 8th October, paying the balance of the purchase price, namely,
$149,000. The respondent promised Blackburn that forthwith
after completion of
the contract between it and Ogle, it would pay Blackburn, in addition to the
price, $40,000. In the event that
the respondent was unable to obtain
completion of the contract between itself and Ogle, the respondent promised
that it would resell
the land to Blackburn for the price paid for it by the
respondent. The respondent did complete the contract to purchase the land
from
Blackburn, paying the agreed price. But, when the appellant repudiated the
subject contract, the respondent by a notice of 18th
November called upon
Blackburn to purchase the land in accordance with the terms of settlement.
Thereafter, there was further litigation
between the respondent and Blackburn,
resulting in the completion of the repurchase of the land on 8th January 1975.
(at p455)
26. It is quite clear from these facts that the contract between the
respondent and Blackburn was completed on 8th January. It is
nothing to the
point that, in order to gain the concurrence of Blackburn to that completion,
the respondent had to agree that in
default of completion of the subject
contract with the appellant, it would sell to Blackburn. (at p455)
27. I would dismiss the appeal. (at p455)
GIBBS, MASON AND JACOBS JJ. The appellant ("purchaser") on 6th February 1974
agreed to purchase certain land from the respondent
("vendor"). The agreement
was subject to the following condition:
"25. This Contract of Sale is subject to the completionPayment of the balance of purchase money - $337,000 - was to be made within fourteen days of the completion of the sale referred to in the above clause. By cl. 23 time was expressed to be of the essence of the contract. (at p455)
within twelve (12) calendar months from the date hereof (or
within such extended time as the Vendor may allow in
writing) of the Contract of Sale between the Vendor herein
and the present registered proprietor of the land (hereinafter
referred to as "the proprietor") for the acquisition of the lands
hereby agreed to be sold such Contract being dated the
Twelfth day of November 1972.
It is hereby agreed by the parties hereto that should the
Contract of Sale between the Vendor and the proprietor
referred to in this Clause be not completed within twelve (12)
calendar months from the date hereof (or within such
extended time as the Vendor may allow in writing) then this
Contract shall be at an end and all monies paid by the
Purchaser hereunder shall be refunded by the Vendor to the
Purchaser."
2. On 8th October 1974 the prior sale was completed and on the same day the
purchaser was notified accordingly. Settlement was requested
within fourteen
days. During the period of fourteen days the vendor, for reasons which it is
not necessary to state in detail but
which related at least partly to a claim
that prior to contract certain representations had been made to the purchaser
by a representative
of the vendor, came to the conclusion that the purchaser
did not intend to complete at the agreed time and informed the purchaser
that
action would be taken for specific performance. The writ was issued on 21st
October, the vendor at the same time informing the
purchaser by letter that it
was ready to complete on that day or on 22nd or on 23rd October. On 21st
October 1974 the purchaser stated
in a letter from its solicitors that it
intended to comply with its contractual obligations but it took no steps to do
so. (at p456)
3. On 7th November the vendor applied for summary judgment for specific
performance. In opposition to the summary judgment affidavit
evidence was
presented by the purchaser that prior to contract various representations had
been made to him by a Mr. Stephens acting
on behalf of the vendor. It is not
clear whether this was intended to foreshadow a defence of misrepresentation
or hardship or both.
Nothing more has ever been heard of these claims but
summary judgment was refused on 11th November. At the same time the vendor was
granted leave to amend the writ by adding a claim for damages for breach of
contract. This amendment was made on 20th November 1974.
Meanwhile by letter
on 14th November the vendor requested performance and indicated its readiness
and willingness to complete. That
letter was as follows:
"Your client's refusal to perform at any time the Contract
sued on is obvious. This was so at the time the action was
commenced and the position has been emphasised by his
conduct since, including his opposition to a Declaration that
the Contract ought to be performed and the submissions
made before Dunn J. by counsel on behalf of your client in
opposition to our client's application for such declaration.
Our client remains ready willing and able to complete the
contract and continues to assert that time is of the essence;
however, it has determined to accept your client's repudiation
and proceed for damages unless:-
1. It receives by noon tomorrow an unequivocable and
unconditional undertaking that your client will settle
that contract;
2. The date nominated by your client for settlement is
reasonable;
3. It is acknowledged that time is of the essence in respect
of that date." (at p456)
4. By letter of the following day the vendor made it clear that it regarded
settlement as overdue, that time was of the essence
and that the vendor was
willing to settle immediately and it requested nomination of a time for
settlement. Nothing other than a
formal reply was ever received to these
letters. (at p457)
5. On 18th November pursuant to an arrangement between them the vendor
required Blackburn, the vendor under the prior contract of
sale to it,
settlement of which had taken place on 8th October, to re-purchase the land
and the re-purchase was completed on 8th
January 1975. (at p457)
6. Meanwhile on 17th December 1974 the statement of claim in the proceedings
pending between the vendor and the purchaser was delivered.
By it damages only
were claimed for breach of the contract. The vendor claimed that the purchaser
had repudiated the contract and
that the vendor accepted the repudiation
alternatively on 14th, 15th, 19th or 21st November. (at p457)
7. The purchaser notified the vendor that it would claim at the hearing that
the cause of action had not, on these allegations,
accrued at the date of the
writ. So, another action for damages was commenced on 12th February 1975 and
on 14th February 1975 the
earlier proceedings were by leave discontinued. The
proceedings commenced on 12th February are the subject of this appeal. By the
statement of claim in this action the vendor alleged repudiation by the
purchaser on 18th November 1974 with rescission on 19th November
or
alternatively repudiation on or about 21st November 1974 with rescission by
the vendor on the same day. The purchaser raised two
issues in his defence.
First he denied that he had repudiated the contract; secondly, he denied that
the vendor could rescind the
contract at the dates alleged because on those
dates there was pending in the court an action for specific performance, and
indeed
at the earlier date for specific performance alone. (It is to be
remembered that the alternative claim for damages was not indorsed
until 20th
November and that the statement of claim claiming damages alone was not
delivered until 17th December.) (at p457)
8. That the purchaser on 18th November and 21st November was in breach of
contract is clear. Completion ought to have taken place
at the latest by 23rd
October and it had not done so as a result of the purchaser's failure to
complete. The commencement of the
action for specific performance did not
waive the breach of contract. It waived reliance by the vendor on the breach
of contract
as the breach of a fundamental term thereof entitling the vendor
to rescind. It has been submitted that events thereafter up to 18th
November
were no more than a continuation of a preceding breach, reliance upon which as
a ground for rescission had been waived.
We do not agree. By the time of the
repudiation and rescission alleged in the current statement of claim, it had
become clear that
the purchaser had no intention of completing within a
reasonable time, or probably at all. Much reliance was placed by the purchaser
on the decision of this Court in Carr v. J.A. Berriman Pty. Ltd. [1953] HCA 31; (1953) 89 CLR
327 in support of the proposition
that continuance
of a breach which the
other party had not elected to treat as
a ground for rescission could not
thereafter be a
ground for such rescission
unless a further breach amounting
to repudiation of
the contract was proved. See also Larking v. Great
Western
(Nepean) Gravel Ltd.
(In liq.), per Dixon J. [1940] HCA 37; (1940) 64 CLR 221, at p 237 . But
in Carr v. J.A. Berriman Pty.
Ltd. Fullagar J. enunciated the further
principle
that "a failure
to remedy the breach might continue so long and in
such circumstances
as to evince an intention ... no longer to
be bound by the
contract". Fullagar J. continued (1953) 89 CLR, at p 349 :
"In other words, the only legitimate inference might be thatWhen this principle is particularly applied to contracts for the sale or purchase of land and where the breach is a failure to complete on the due date, a party who has waived a right to treat that failure to complete on the due date as the breach of an essential term may nevertheless thereafter call on the other party to complete and a failure on the part of the latter to complete on or by a further named day fixed reasonably ahead or even a continued long failure to complete will amount to a refusal to be bound by the contract (Holland v. Wiltshire, per Kitto J. [1954] HCA 42; (1954) 90 CLR 409, at p 420 ) and a repudiation thereof entitling the other party to rescind and to claim damages for loss of the bargain. In this particular context there is no different in consequence between regarding the conduct subsequent to the actual breach as a further breach of the contract and regarding it as a refusal to be bound by the contract and consequently a repudiation thereof. Or it may perhaps better be said that the first breach is a failure to complete on the due date and the later breach is a failure to complete at all. (at p459)
he is saying: 'Not only have I broken my contract by not
doing the thing on the due day, but I am not going to do the
thing at all', or 'I am not going to do the thing at all unless
and until I find it convenient to do it'. In this way a right to
rescind might arise which is not based on breach of the
particular promise as such. That promise, even if essential to
begin with, has become non-essential by reason of the
election of the promisee, but the promisee may nevertheless
be able to establish that the conduct of the promisor with
respect to his promise amounts to a refusal to be bound by the
contract."
9. If after a purchaser fails to complete at the time fixed for completion,
when that time is an essential term of the contract,
a vendor elects to treat
the contract as repudiated by a usually be a basis for regarding the contract
as repudiated by a purchaser
until a further time has been fixed in a way that
shows an intention on the part of the vendor to make that further time of the
essence
of the contract. See Balog v. Crestani, per Gibbs J. [1975] HCA 16; (1975) 132 CLR
289, at pp 296-298 , for the analogous principle
applicable where
time was not
originally of the essence of the contract.
These circumstances must be
distinguished from the circumstances
where the
breach of the agreement is not
unconditionally waived
but further time is allowed on condition that
completion takes place
at the
further nominated time. See Holland v.
Wiltshire, per
Dixon C.J. (1954) 90 CLR, at p 415 . (at p459)
10. Thus although mere delay will be no more than an omission to remedy the
past breach which has been waived as a ground for rescission,
there are cases
where the purchaser by further unreasonable delay or by a further act
expressly evinces an intention no longer to
be bound by the contract. Either
the further delay or the further act may constitute a repudiation of the
contract. In our opinion
the trial judge was entitled to find that by 21st
November the purchaser had evinced an intention no longer to be bound by the
contract
and had thereby repudiated the contract. We have no doubt that on the
evidence he was correct in so finding. (at p459)
11. We have not so far particularly considered the effect in this connexion
of there having been current during this period from
21st October to 20th
November the action for specific performance. There are two aspects to be
considered - the effect of the action
on legal rights under the contract and
the application of any principle of equity which would curtail or suspend the
legal rights
of the vendor. (at p459)
12. By commencing an action for specific performance the vendor elected not
to rescind for failure to complete on the agreed day,
completion on that day
being an essential term of the contract. In Mayson v. Clouet (1924) AC 980, at
p 985 , Lord Dunedin stated
the law as follows:
"The law is quite plain. If one party to a contract commitsThis legal effect was discussed by Goddard L.J. in Public Trustee v. Pearlberg (1940) 2 KB 1, at pp 22-23 :
a breach then if that breach is something that goes to the
root of the contract, the other party has his option. He may
still treat the contract as existing and sue for specific
performance; or he may elect to hold the contract as at an
end - i.e., no longer binding on him - while retaining the right
to sue for damages in respect of the breach committed."
"If one contracting party, either expressly or by conduct,Goddard L.J. then stated the alternative course open to the vendor in a way with which we with respect would not agree if it was intended as a comprehensive statement of the law.
repudiates a contract, the other can either accept the
repudiation and treat the contract as rescinded, or can refuse
to do so, and regard the contract as still alive, so that his
rights will fall to be determined when the time for
performance arrives. He cannot, however, insist on performance
and at the same time adopt the remedies open to him on
rescission. Applying that rule to a case where equity would
entertain a claim for specific performance, it follows that if a
vendor, by applying for that remedy, asserts that he regards
the contract as subsisting, he loses his right to forfeit a
deposit, on the footing that the contract has been rescinded
by the purchaser's default."
"But he may resile from the position he has thus taken up,In our opinion this last statement, if it is thereby meant that the action for specific performance must be abandoned before the repudiation is accepted, is too wide. It may be correct in those cases where the fault of the purchaser is the original continuing breach but not in those cases where the purchaser commits a further breach of contract or evinces an intention never to complete and thus impliedly repudiates the whole contract. (at p460)
and if he abandons his action by discontinuing it in the
manner provided by the Rules of Court he can, if the
purchaser is still at fault, accept the repudiation and forfeit
the deposit."
13. It does not follow that so long as the action for specific performance is
on foot the vendor cannot ever rescind at law for
further breach or, on the
distinction drawn in Carr v. J.A. Berriman Pty. Ltd. [1953] HCA 31; (1953) 89 CLR 327 for
further refusal
or neglect
which amounts to a repudiation. Legal rights are
not affected at law by the mere
existence of an action for specific
performance
though they are affected by the election involved in its
institution. However, in
equity a party would not in certain circumstances
have been allowed to rescind a contract if his action for specific performance
was still pending. That is the effect of the decision
in Warde v. Dixon (1858)
28 LJ Ch 315 . It is a very understandable rule of
equity and is unaffected in
principle by the introduction
of the Judicature system. (at p461)
14. A party to a contract who commences proceedings for specific performance
thereby submits the dispute to the court in exercise
of an equitable
jurisdiction. In specific performance there must be mutuality and it is in
equity inconsistent with him continuing
to seek specific performance that he
sould rescind the contract. In many circumstances it would be inequitable of
him to do so. If
the dispute between the parties to the contract is one which
relates to title or to the mode of completion of the contract or if
there is a
genuine dispute between the parties on the meaning and effect of the contract,
then in those cases and in others, as for
instance Public Trustee v. Pearlberg
(1940) 2 KB 1 a party who has commenced proceedings for specific performance
cannot be allowed
to rescind without first discontinuing his action for
specific performance. It may be that he would need to give the defendant a
further chance to perform the contract by fixing a fresh date for completion
if not to do so would mean that the defendant who had
impliedly concurred in
having the parties' rights determined in equity was thereby prejudiced and an
inequitable advantage was thereby
obtained at law by the plaintiff. It would
be an inequitable advantage if the plaintiff could rely on the delay while the
action
for specific performance was pending as a refusal to perform and as a
repudiation justifying rescission. (at p461)
15. But is this a rule applicable to all cases where an action for specific
performance is or has been pending? That is the basic
question in the present
case. It seems to us that it is not. If a party has by his conduct shown and
continues to show an intention
never to complete the contract, especially
where his conduct by express act or by implication is not consistent with an
intention
to perform the contract pursuant to any judgment for specific
performance, then it must be open to a vendor to rescind even if there
is
current an action for specific performance. If there is a further breach of an
essential term or some further conduct amounting
to a repudiation while the
action for specific performance is pending, the existence of the action will
not then prevent the vendor
electing to rescind but he will on such an
election lose the right which he previously had to specific performance and
will be limited
to damages for the breach. The damages will be those which
result from the breach which entitled the vendor to rescind and those
which
flow from any earlier breach which had been waived as a ground for rescission.
Damages for the latter breach would not be for
loss of the contract but for
breach of a term which must be treated as nonessential, e.g. for delay. (at
p462)
16. If the law were otherwise it would place a party in circumstances such as
the present in an impossible position. A vendor commences
proceedings for
specific performance. He thereby offers to perform and keeps the contract on
foot. However, delay on the part of
the purchaser makes it practically
impossible for the vendor to retain the land. He has to sell it. Thus it is
put out of the power
of the vendor to perform the contract on his part. In
those circumstances he has no alternative but to discontinue his claim for
specific performance and to claim damages for breach of contract instead.
However, if he has to rely on some further act or default
of the purchaser
after the discontinuance before he can rescind or if he cannot rescind after
he has elected to discontinue his claim
for specific performance but before it
is actually discontinued, he may no longer be in a position himself to perform
the contract
and thus at the time of a later rescission he may be unable
himself to perform a condition precedent. Thus he would be deprived of
his
right to sue for damages because he could no longer himself complete as a
result of the delay which had compelled him to re-sell
the land. We do not
believe that the rule of equity was ever intended to apply in such
circumstances. (at p462)
17. In the circumstances of the present case we do not consider that it was
necessary for the vendor to discontinue its claim for
specific performance
before rescinding. The purchaser by his conduct after 23rd October in the
light of his conduct prior to that
date had by 18th November evinced a clear
intention that he would never perform the contract by the last mentioned date.
This was
accepted as a repudiation and there was rescission. (at p462)
18. The rule of equity applied in Warde v. Dixon (1858) 28 LJ Ch 315 through
to Public Trustee v. Pearlberg (1940) 2 KB 1 was
correctly applied in those
cases but it has no application to the facts disclosed in the present case
where the purchaser had made
it clear that he would never complete the
contract. It may be that before the Judicature system was introduced a
plaintiff would
have had to discontinue his proceedings in equity before he
could pursue his action for damages at law. That can no longer be necessary
but the point does not arise in the present case. The proceedings the subject
of the present appeal were commenced after the vendor
had abandoned its claim
for specific performance. (at p463)
19. Lastly it was submitted that the prior contract between Blackburn and the
present vendor was never completed within the meaning
of cl. 25 of the
contract between the present vendor and the purchaser. The basis for this
submission is that the present vendor
paid to Blackburn a different price or
consideration for the land from the price in the contract of 12th November
1972. It is clear,
however, that the real substance of cl. 25 was a condition
not that the contract should be completed without variation of the
consideration
payable by the present vendor to Blackburn, if the present
vendor should agree, but that the lands should be conveyed by Blackburn
pursuant to their contract, with or without variation of the consideration, so
that the vendor might complete the sale to the purchaser.
(at p463)
20. We would dismiss the appeal. (at p463)
MURPHY J. This appeal from the Court of Appeal of Queensland arises from an
action in the Supreme Court for damages for breach of
contract of sale of land
following recission by the respondent (vendor) for repudiation by the
appellant (purchaser). (at p463)
2. Whether there was repudiation entitling the respondent to rescind is a
question of fact. There was ample and convincing evidence
of repudiation and
rescission prior to commencement of the action on 12th February 1975. The
purchaser had persistently neglected
and refused to complete. The words of
Kitto J. in Holland v. Wiltshire are applicable [1954] HCA 42; (1954) 90 CLR 409. at p 421
:
"The purchasers were refusing, deliberately and finally, to
complete the purchase ... The contract unquestionably stood
repudiated by the purchasers, and the vendor, ... at any time
while the repudiation continued, was entitled to treat the
contract as no longer binding upon him." (at p463)
3. The correspondence, the proceedings for specific performance (including
those for summary judgment) and the conduct of the defendant
in relation to
them were part of the factual material. On this question of fact, the trial
judge was correct in concluding that there
was repudiation by the purchaser
and that the plaintiff was entitled to rescind and to obtain damages. (at
p463)
4. During the hearing of the appeal, many judicial observations were referred
to as though they were propositions of law. Judicial
conclusions of fact or
observations on facts are too often treated as propositions of law. This
applies to many cases of repudiation
and rescission. The warnings in Qualcast
(Wolverhampton) Ltd. v. Haynes (1959) AC 743 , an English negligence case, are
relevant
to other cases in which a judge decides fact as well as law. Lord
Denning said (1959) AC, at p 761 : "'... we ought to beware of
allowing tests
or guides which have been suggested by the court in one set of circumstances,
or in one class of cases, to be applied
to other surroundings', and thus by
degrees to turn that which is at bottom a question of fact into a proposition
of law ... see
Harris v. Associated Portland Cement Manufacturers (1939) AC
71, at p 78 by Lord Atkin." (at p464)
5. There is no rule that a contract cannot be rescinded for repudiation while
a suit (or action) for specific performance is in
existence. The conduct of
the defendant in his defence (for example, pleading that he is unable to or
refuses to complete) or otherwise
may entitle a plaintiff to rescind for
repudiation. (at p464)
6. The remaining point was not well founded. On the facts, the respondent's
contract with Blackburn was completed. (at p464)
7. The appeal should be dismissed. (at p464)
ORDER
Appeal dismissed with costs.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/cth/HCA/1976/21.html