![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
High Court of Australia |
T.C. INDUSTRIAL PLANT PTY. LIMITED AND ANOTHER v ROBERT'S QUEENSLAND PTY.
LIMITED [1963] HCA 57; (1963) 180 CLR 130
Contract
HIGH COURT OF AUSTRALIA
KITTO, WINDEYER AND OWEN JJ
Contract - Sale of goods - Breach of implied condition as to fitness for purpose - Damages - Whether entitlement to recover both expenditure uselessly incurred and loss of profits.
DECISION
KITTO, WINDEYER AND OWEN JJ These appeals are brought by the defendants, T.C. Industrial Plant Pty. Ltd. (hereinafter called the T.C. Company) and Esanda Ltd. (hereinafter called Esanda), in an action heard by Stable J. in which he gave judgment for the plaintiff, Robert's Queensland Pty. Ltd., against the defendants for pounds 27,889 15s. 6d. and for the plaintiff on a counterclaim pleaded by Esanda.
2. At all relevant times the business of the T.C. Company included that of
selling and supplying "Hazemag" Impeller Breakers which
are machines designed
to crush stone and gravel for use in concreting work and Esanda, which was a
wholly owned subsidiary of the
E.S. and A. Bank, carried on a hire-purchase
business. Early in 1958 the Commonwealth required a large quantity of screened
crushed
aggregates in three sizes for use at an aerodrome near Brisbane and
called to tenders kg the supply and delivery to the aerodrome
of about 24,000
cubic yards of this material. A man named Robert, who later became the
managing director of the plaintiff company,
lodged a tender and on 8 July
1958, it was accepted. The specifications and conditions upon which the
tenders were called and which
later became part of the contract with the
Commonwealth required the material to be delivered at the rate of not less
than 250 cubic
yards per week for each size of aggregate. In the events that
happened this would have meant that, as to one size of aggregate, delivery
would be required to be completed not later than 2 December 1958; as to
another size not later than 17 March 1959, and, as to the
third, not later
than 24 March 1959. The specifications and conditions further provided that in
default of delivery within the times
allowed or any extension thereof granted
by the Commonwealth the contractor would pay liquidated damages at the rate of
pounds 30
for each week beyond the time allowed by the contract and for each
type of aggregate and, in addition, would forfeit all moneys deposited
with
the Commonwealth by way of security for the due performance of the contract.
Provision was also made by which the Commonwealth
could cancel the contract in
the event of the contractor's failure to perform any of its terms and it
contained a clause forbidding
the assignment of the contract.
3. It was Robert's intention to form a proprietary company to carry out the
contract if his tender was accepted and this was made
known by him to the
Commonwealth officials who were concerned with its execution and performance.
The plaintiff company was accordingly
incorporated towards the end of May
1958. The contract, which was dated 11 August 1958, was made with and signed
by Robert but in
fact, to the knowledge and with the assent of the
Commonwealth officers concerned, the plaintiff carried out all the work that
was
done and the deliveries that were made and the plaintiff paid to the
Commonwealth the sum of pounds 467 which was required to be
paid by way of
security for the due performance of the work.
4. Before the contract was signed and in anticipation of its execution
Robert and those associated with him took steps to find
a crushing machine
suitable for the work and their search led them to the T.C. Company. They,
themselves, had had no experience in
gravel and stone crushing work but they
explained in detail to the responsible officers of the T.C. Company the nature
of the work
to be done and the terms of the contract which was about to be
made with the Commonwealth. In the course of these discussions the
representatives of the T.C. Company assured them that a crushing machine known
as the Hazemag A.P. 4 Impeller Breaker which the T.C.
Company could supply was
suitable for the purpose of carrying out the work for which the contract
called. An order for the crusher
was there upon given by the plaintiff and an
initial payment of pounds 1,500 was made by it, the T.C. Company being told
that Esanda
would complete the purchase from the T.C. Company and let the
machine on hire to the plaintiff under a hire-purchase agreement. In
consideration of the plaintiff making the initial payment and arranging for
Esanda to provide the balance of the price the T.C. Company
gave a number of
warranties relating to the crusher which need not be detailed. The learned
trial judge found also that the plaintiff
had made known to the T.C. Company
the particular purpose for which the crusher was required so as to show that
it had relied on
the skill and judgment of the T.C. Company and that it was an
implied condition of the agreement between that company and the plaintiff
that
the crusher was fit for the purpose of crushing the stone and gravel required
for the fulfilment of the contract with the Commonwealth.
Arrangements were
then made by the plaintiff with Esanda by which the latter agreed to buy the
crusher from the T.C. Company and
pay the balance of the price and let it to
the plaintiff on hire purchase. Before Esanda agreed to do this discussions
took place
between Robert and other representatives of the plaintiff and one
Carlisle, who was the manager of the branch of the E.S. and A.
Bank at which
Robert and the plaintiff banked and was also an officer of Esanda. All that
Carlisle knew about the crusher and its
fitness for the purpose of carrying
out the contract with the Commonwealth came to him from the plaintiffs
representatives and they,
as his Honour found, were to Carlisle's knowledge
merely repeating the assurances given to them by the T.C. Company. Following
these
discussions and early in September 1958 the crusher was purchased by
Esanda from the T.C. Company for E9,668 less the deposit of
pounds 1,500 which
the plaintiff had already paid and Esanda, in turn, hired it to the plaintiff
under a hire-purchase agreement
under which an initial payment of pounds 3,223
was made by the plaintiff and it agreed to pay monthly instalments of pounds
306 38s.
About 12 September 1958, the crusher was delivered to the plaintiff
at the site where the crushing operations were to be carried
out. It was
correctly assembled there and work began. The machine, however, proved to be
unfitted fot the purpose for which it had
been supplied with the result that,
despite the plaintiff's best endeavours, deliveries of aggregates to the
Commonwealth were far
below those for which the contract provided. In a letter
dated 28 October 1958, from the Commonwealth Director of Works to the
plaintiff
attention was drawn to this fact and the plaintiff was required to
take action to improve the rates of delivery so that the contract
might be
performed within the times specified. The plaintiff made every endeavour to
rectify the faults in the crusher but the troubles
persisted and on 17
December 1958, the Director of Public Works wrote a further letter to the
plaintiff stating that default in making
deliveries could not be tolerated any
further and required the plaintiff to state within seven days its "intentions
for fulfilling
all the terms of the contract". The plaintiff replied on 29
December that an officer of the T.C. Company had promised to inspect
the
crusher and had guaranteed to make it operate efficiently. On 31 December the
solicitors for the plaintiff wrote to the T.C.
Company making further
complaints of the deficiencies of the crusher and pointing out that, as a
result, the plaintiff was in danger
of having its contract with the
Commonwealth cancelled. The letter called upon the T.C. Company to "replace"
the equipment in full
working order but no reply was received. On 8 January
1959, the plaintiff wrote to the Director of Public Works conceding that it
was in default in making deliveries and giving a lengthy account of its
unsatisfactory dealings with the T.C Company. It went on
to say that inquiry
had shown that other equipment for stone and gravel crushing was "available
for purchase only" but that the plaintiff
had not the finance to purchase such
equipment and that in these circumstances it had no alternative but to advise
that it was unable
to perform the terms of the contract. The letter
accordingly asked that it be released from the contract in order to avoid as
far
as possible incurring further losses.
There followed a request that the Commonwealth would not seek "penalties" from
the company in addition to the losses which it had
already suffered and asked
that the moneys deposited by way of security be repaid. On 30 January 1959,
the plaintiffs solicitors
wrote to the T.C. Company that it had been forced to
"retire" from the performance of its contract with the Commonwealth because
of
the defects in the crusher and asked that the T.C. Company "repurchase this
plant from our client at the full cost which was paid
for it" and accept full
responsibility for the damages which the plaintiff had sustained. No reply to
this letter was received. On
27 February the Director-General of Works gave
written notice of the cancellation of the contract addressed to Robert c/o the
plaintiff.
The notice recited that "Whereas by written communication dated 8th
January, 1959, you have requested to be relieved from having
to carry out the
remainder of the work" and went on to give notice of cancellation and to
declare forfeited "all sums of money remaining
in the hands of the
Commonwealth in respect of the said contract together with all sums deposited
by Robert's (Qld.) Pty. Ltd. and
retained as security for the due and proper
performance and completion of the said contract". Further correspondence
passed between
the Director of Works and the plaintiff and ultimately the
amount of the deposit was retained by the Commonwealth but no claim was
made
by it for the payment of liquidated damages and all material in fact delivered
by the plaintiff at the aerodrome was paid for
at the contract rates. On 4
March 1959, the plaintiff gave written notice to Esanda that it elected to
treat the hire-purchase agreement
of 5 September 1958, as repudiated by the
latter on the ground that Esanda had committed breaches of "conditions
required to be fulfilled
by you pursuant to the said agreement and the said
Acts". The Acts in question were The Hire-purchase Agreement Acts 1933-1946
(Q.).
The crusher was not in fact used by the plaintiff after its contract
with the Commonwealth was cancelled and the machine was, as
his Honour found,
put by it in a place of safe keeping where it was available to Esanda.
5. What has been said is no more than a brief outline of the events which
led to the institution of the action in April 1959. In
it the plaintiff
claimed damages for breaches of contract against both defendants. The claim
against the T.C. Company was based (inter
alia) upon a breach of the implied
condition that the crusher was reasonably tit for the purpose of carrying out
the work of crushing
required for the performance of the plaintiffs contract
with the Commonwealth. The learned trial judge found that there had been
a
breach of this condition and this finding has not been attacked on appeal. Ile
proceeded then to assess the plaintiffs damages
at pounds 27,889 15s. 6d. of
which pounds 15,889 15s. 6d. represented, in the main, expenditure and
liabilities incurred by the plaintiff
in the course of and for the purposes of
carrying out its contract with the Commonwealth less the amounts paid to it by
the Commonwealth
under that contract. The balance of pounds 12,000 represented
his Honour's estimate of the profits which the plaintiff would have
made had
it been able to carry out its contract with the Commonwealth and a further
contract Kr the delivery of additional quantities
of aggregate which would,
his Honour considered, have probably been made with it by the Commonwealth if
it had been able to fulfil
the contract in fact made.
6. It is convenient at this point to state the ground on which the
plaintiff's claim against Esanda was upheld by the learned trial
judge. By its
statement of claim the plaintiff alleged (inter alia) that, by reason of the
provisions of s. 7A of The Hire-purchase
Agreement Acts 1933-1946 (Q.), it was
an implied condition of the contract between the plaintiff and Esanda that the
crusher was
reasonably fit for the particular purpose for which it was
required and that there had been a breach of that condition. His Honour
was of
opinion that in the circumstances of the case no warranties or conditions as
to the fitness of the crusher for the purpose
for which it was let to the
plaintiff on hire purchase were to be implied by the common law because "all
that Esanda did was to sign
a hire-purchase agreement for a machine of which
all its knowledge was what it had gleaned from the plaintiff'. He was of
opinion,
however, that s. 7A(1) of The Hire-purchase Agreement Acts 1933-1946,
which was in force at the relevant time, applied. By that subsection
it was
provided that
"If any chattel has been let or sold under a hire-purchase agreement to a
hirer who, at any time within a period of six months
prior to the making of
such hire-purchase agreement, made known - (a) To ... the owner; or (b) To ...
any other person who within
the said period shall ... have offered or agreed
to let or sell to the hirer or obtained or received from the hirer an
application
or order for the letting or sale to the hirer of such chattel ...
the particular purpose for which the chattel is required, so as
to show that
the hirer relied on the skill or judgment of the owner or of such other
person, as the case may be, and the chattel
is of a description which it is in
the course of the business of the owner or of such other person, as the case
may be, to supply
... there is an implied condition that the chattel shall be
reasonably fit for such purpose and such implied condition shall be binding
in
law as well upon such other person as upon the owner".
7. His Honour was of opinion that the T.C. Company was "any other person"
within the meaning of par. (b) of the sub-section and
that all the other
requirements of the sub-section had been fulfilled. The plaintiff had, within
a period of six months before the
making of the hire-purchase agreement with
Esanda, made known to the T.C. Company the particular purpose for which the
crusher was
required so as to show that it relied upon the skill and judgment
of the T.C. Company. That company had obtained or received from
the plaintiff
an application or order for the letting or sale to the plaintiff of the
crusher and the machine was of a description
which it was the business of the
T.C. Company to supply. The result was therefore that there was to be implied
in the hire-purchase
agreement between Esanda and the plaintiff a condition
that the crusher was fit for the purpose for which it was hired. There had
been a breach of that implied condition and accordingly the learned trial
judge found in favour of the plaintiff as against Esanda
for the same amount
of damages as he awarded against the T.C. Company.
8. It was contended before his Honour and on the appeal that, as against
Esanda, the plaintiff was estopped from asserting that
the crusher was unfit
for the purpose for which it was supplied because, so it was said, the
plaintiff had represented to Esanda
that it was fit for that purpose and,
acting on that representation, Esanda had agreed to let it on hire purchase to
the plaintiff.
The submission was rejected by the learned trial judge for the
reason, amongst others, that in the discussions between the plaintiff's
representatives and Carlisle which led up to the making of the hire-purchase
agreement the former had, to the latter's knowledge,
merely repeated the
assurances which the T.C. Company had given as to the capabilities of the
crusher. In other words, the representation
made to Esanda by the plaintiff
was not that the machine was fit for the purpose for which it was required but
that the T.C. Company
had stated that it was fit for that purpose. On the
evidence this was a finding which was clearly open and no good reason has been
shown why it should not stand. This submission therefore fails and it is
necessary then to consider the matters which were argued
on the issue of
damages.
9. The same submissions were made on behalf of each of the defendants. Some
of them related to matters of detail but three of them
were on broader lines.
It was said that the contract for the supply of aggregates was made between
the Commonwealth and Robert and
not between the Commonwealth and the plaintiff
and that accordingly the latter could not maintain a claim for loss of profits
resulting
from a failure to perform that contract. The learned trial judge was
of opinion that, although Robert had signed the original contract,
the
evidence showed that it had either been assigned by him to the plaintiff with
the knowledge and assent of the Commonwealth or
that a novation of it had
occurred thus creating a contractual relationship on the same terms between
the plaintiff and the Commonwealth.
An examination of the evidence, both oral
and documentary, seems to us to establish that the contract had been novated
and this point
therefore fails. Next it was said that the plaintiff had failed
to mitigate its damage in that it should, so it was said, have sought
from the
Commonwealth an extension of time for performance of the contract and made
arrangements to obtain another crushing machine
capable of carrying out the
necessary work. But it was for the defence to show that the plaintiff had
failed to mitigate damages
and it is a sufficient answer to this submission to
say that when regard is had to the evidence and in particular to the letters
of 28 October and 17 December 1958, from the Director of Works to the
plaintiff, to which reference has earlier been made, it is
most improbable
that, had the plaintiff applied for an extension of time, it would have been
granted and that the plaintiff's action
in asking, in its letter of 8 January
1959, to the Director of Works, to be released from the further performance of
the contract
was reasonable. Had it not taken this course, it is probable that
it would have incurred further loss and become liable to pay substantial
sums
by way of liquidated damages and, in such circumstances, might well have been
charged with an unreasonable failure to mitigate
its damages.
10. It was also submitted that the plaintiff could not recover under both
the heads of damage upon which the learned trial judge
based his award but was
bound to elect whether it would pursue its claim for expenditure uselessly
incurred as a result of the defendants'
breaches of contract or, in the
alternative, its claim to recover for the loss of the profits it would have
earned had the crusher
been fit for the purpose for which both defendants knew
it was required, namely to carry out the plaintiff's contract with the
Commonwealth,
the terms of which were at all material times known to each of
them. This submission was based upon the decision in Cullinane v.
British
"Rema" Manufacturing Co. Ltd. (1). That was a case in which the plaintiff had
purchased a clay pulverizing machine from the
defendant, to be made according
to certain specifications, the defendant warranting that it would pulverize
clay at the rate of six
tons per hour. The machine was built according to the
specifications but would only pulverize clay at less than the warranted rate.
The plaintiff had incurred expense in erecting a building to house the
(1) (1954) 1 QB 292.
reason of the fact that its capacity was less than had been warranted his
operations were less profitable than they would have been
had it complied with
the warranty. He claimed to recover by way of damages the cost of erecting the
building, purchasing the ancillary
plant and purchasing the machine itself
less the estimated residual value of those assets as at the time of the
institution of the
action. In addition he claimed for loss of the profits he
would have made up to the date of trial had the machine been as warranted
and,
in arriving at the amount of profits lost, he allowed for depreciation and
maintenance on the building, the machine and the
ancillary plant.
11. Judgment in the action was delivered three years after the date of
delivery of the machine. The claim for loss of profits was
limited to that
period, notwithstanding that the machine had a life of ten years. This
introduced into the case a complication which
led to an ultimate disagreement
amongst the members of the Court of Appeal. Evershed NCR. and Jenkins L.J
thougt that as a result
of the limitation the case had to be decided on the
footing that if the machine had been as warranted it would have earned profits
during the three years but none thereafter. Morris LJ on the other hand
thought that the limitation meant only that although loss
of profits after the
three years would have been incurred it was not claimed for. This difference
of opinion as to the effect of
the limitation led to disagreement as to the
fate of the appeal. It is important to see how that came about. The
plaintiff's claim
had been submitted to an official referee under five heads.
Heads A., B. and C. were capital expenditure, A. being the cost (less
break-up
value) of buildings etc. erected specially to house the machine, B. the cost
of the machine less its residual value, and
C. other capital expenditure
preliminary to the working of the machine, less residual values. Then a claim
D. was made for interest
on A., B. and C. for the three years. Finally a claim
E. was made for loss of profit for the three years, arrived at by taking the
estimated receipts for the warranted output and subtracting not only running
costs, office expenses and interest but also depreciation
at ten per cent per
annum. The official referee allowed A, B. and C. as representing capital
thrown away; he allowed D.; and in addition
he allowed E., but without the
subtraction of depreciation. On the assumption by which the majority of the
Court of Appeal considered
the plaintiff was bound, namely that if the machine
had been as warranted profits would have been earned for three years but no
longer,
what the official referee had done amounted to saying that the
plaintiff was entitled to recover not only the whole of the profit
(without
deduction for depreciation) which he would have got by laying out A., B. and
C., but also A., B. and C. themselves. Plainly
that could not be right. It
would mean that in the end the plaintiff would have the equivalent of his full
profit without having
borne the expense of earning it. The plaintiff s claim
as pleaded had not suggested that. What it had suggested was that the
plaintiff
should recover, in addition to A., B., C. and D. only so much of the
three years' profits as should remain after writing off out
of them the three
years' proportion (i.e. three-tenths) of A, B, C. and D. If Morris LJ's
opinion had prevailed as to what the limitation
to the three years' period
really implied, this would, we think, have been considered by the majority of
the Court to be unexceptionable
in principle, provided that it meant accepting
as the proper measure of damages the aggregate of A., B, C. and D. plus, not
the profits
earned by the laying out of A., B. and C., but only We excess of
those profits that would have remained after recouping A., B. and
C. This
would only have been another way of giving the plaintiff the full amount of
the lost profits without any deduction for depreciation,
and it would have
accorded with the basic principle of Hadley v. Baxendale (2), and Victoria
Laundry (Windsor) Ltd. v. Newman Industries
Ltd. (3), which the Court was
keeping steadily before it. But the majority of the Court, if we understand
their judgments aright,
would not have agreed with Morris LJ that a deduction
of only three years' depreciation would produce the correct result.
12. There is a sentence in the judgment of Evershed M.R. upon which a
comment may be permissible. After having said that a person
who has obtained a
machine unable to perform what it was warranted to perform may adopt the
course of claiming to recover the capital
cost he has incurred, deducting
anything he can obtain by disposing of the material that he got, his Lordship
proceeded (4) "But,
alternatively, where the warranty in question relates to
performance, he may, in my judgment, make his claim on the basis of the
profit
which he has lost ... If he chooses to base his claim on that footing, it
seems to me that depreciation has nothing whatever
to do with it." Jenkins LJ
spoke similarly (5). We understand their Lordships to mean that in such a case
the plaintiff, having paid
for the machine at the beginning, should not have
to pay for it a second time (in effect) by having its value, spread over the
period
of its life, subtracted from what otherwise would be his damages. The
reason
(2) [1854] EWHC J70 (Exch); (1854) 9 Exch. 341 (156 ER 145).
(3) (1949) 2 KB 528, at p. 539.
(4) (1954) 1 QB, at p. 303.
(5) ibid., at p. 306.obviously is that where the plaintiff adopts, as the amount the machine would have been worth to him if it had been as warranted, the amount of the profits he would have made by using it to the point of exhausting its useful life, he is entitled to recover the whole amount of those profits, without making provision for replacement of the cost of the machine; for those profits are what he was really buying when he bought the machine in reliance upon the warranty. But the same result may be produced by claiming for recoupment of hi capital outlay and in addition for the excess of the estimated profits over the amount of the capital outlay; and that is all that is done by a plaintiff who claims his capital outlay and in addition profits estimated after deduction of depreciation (6). The justification for the refusal of the majority of the Court in Cullinane's Case to follow such a course lies, we venture to think, in the fact that since nothing was proved about the probable amount of We profits that would have been made in the final seven years of the machine's life, and therefore nothing about any probable excess of profits during the whole ten years of the machine's life over amounts of depreciation equalling the total capital cost, the plaintiff failed to show that damages assessed on the loss-of-profits basis would be greater than damages assessed by reference to capital expenditure plus interest. What was perfectly clear was that the plaintiff could not have damages assessed on the one basis plus damages assessed on the other basis. To sum the matter up, the seller (in effect) promised the buyer that the machine was such that upon the buyer laying out pounds X in acquiring and installing the machine he would be able to get pounds X + Y by working it. For breach of the promise the buyer, having laid out his pounds X, may recover, if he chooses, what the machine would have been worth to him if it had been as promised (presumptively pounds X) minus the actual value of the machine. Alternatively he may recover pounds X + Y; he is not to be restricted to (pounds X + Y) - (pounds X in the form of depreciation), for he has already parted with LX once, namely at the beginning. And it is only stating the second alternative in another way to say that he can recover (pounds X + Y) - (pounds X in the form of depreciation) and in addition his capital outlay pounds X.
13. We have been invited to say that what was held in Cullinane's Case is
opposed to the decision of an earlier Court of Appeal
in the case of Hydraulic
Engineering Co. Ltd. v. McHaffie Goslett and Co. (7). That was not a case of a
warranty relating to performance;
it was a
(6) See (1954) 1 QB, at p. 308, per Jenkins LJ
(7) (1878) 4 QBD 670.case of a contract to supply an article within an agreed time, the article being required by the plaintiff (as the defendant knew) for incorporation in a machine, the rest of which the plaintiff was manufacturing himself, to be sold for a price exceeding the total cost to the plaintiff. The Court held that the plaintiff was entitled to recover the cost he incurred in manufacturing the rest of the machine plus the profit he would have made by selling the completed machine. But the word "profit" was there being used in a sense different from that in which it was to be used in Cullinane's Case. In the latter case the word meant a profit from operating the article purchased; in other words the excels of the receipts that would have been obtained by the contemplated use of the article to perform profitable work (if it had been as warranted) over the expenditure which that use would have involved. But in the former case "profit" meant the excess of the price that would have been obtained on a contemplated sale of a machine (which included the article in question and other integers) over the cost to the plaintiff of that machine, sale of the machine having been made impossible by the nonfulfilment of the stipulation sued upon. As an authority that the damages recoverable included both cost and profit the case means only that the plaintiff, having expended pounds X which he would love got back together with pounds Y profit if We defendant had performed his obligation, can recover for breach of that obligation the whole sale price he should have been enabled to obtain, viz. pounds X + Y; and it makes no difference if you prefer to say that he can recover pounds X under the name of cost plus pounds Y under the name of profit. It is hardly surprising that Hydraulic Engineering Co.'s Case was not cited in Cullinane's Case. The difference between them may be expressed by saying that in the former case the plaintiff by incurring the items of cost (less residual values) would have obtained, but for the defendant's breach, the whole of the price for which he could have sold the machine, and therefore must have the amount of that price (cost plus profit) as damages; whereas in the latter case the plaintiff, but for the defendant's breach, by incurring the items of cost (less residual values) would have obtained the operating profit and is entitled to damages for the loss thereof, but would not have got back the amount of the cost and is therefore not entitled to damages as if he had lost that through the defendant's breach.
14. The case before us is one of a breach of condition followed by the
election by the plaintiff to terminate its contract with
Esanda. The only
difference that that makes as regards damages is that the defective machine
reverted to the defendant Esanda and
consequently there is no item of residual
value to be allowed for. The learned vial judge awarded damages in two parts.
First his
Honour awarded pounds 15,889 15s. 6d. to cover all items of cost
incurred by the plaintiff (including interest) less the amount of
the payments
received by the plaintiff from the Commonwealth. This would restore the
plaintiff to the position it was in at the start.
Secondly his Honour awarded
pounds 12,000 for loss of the profits which he thought the plaintiff would
probably have gained if the
machine had been as warranted. The judgment does
not reveal how his Honour arrived at that figure, but from a reference which
he
made to figures submitted to him by counsel for the plaintiff, and a
statement that he was allowing for contingencies normally to
be expected
whereby the optimum is not always attained, it seems probable that his Honour
accepted the items in a Sch. "C" which
counsel had placed before him, showing
a loss of profit of pounds 15,440 1s. 5d., and then reduced that figure to a
round pounds
12,000. If his Honour had made an estimate of the plaintiff's
probable working profit after deducting from the future receipts that
would
have been obtained from the Commonwealth the expense (not including any items
already covered by the pounds 15,889 15s. 6d.)
of earning those receipts, it
would have been right to allow in the damages the excess of that profit over
the pounds 15,889 15s.
6d. But it is not clear that such an estimate could be
made on the material in Sch. "C". The only satisfactory way of dealing with
the case, it seems to us, is to remit the question of damages to the Supreme
Court for further consideration. It may of course be
that the learned judge
will find it preferable to work out a single calculation, taking the whole of
the actual and probable expenditure
which the plaintiff would have incurred in
performing its contract with the Commonwealth and the probable extension
thereof had the
crusher been of the warranted fitness, and subtracting the
resulting figure from the total receipts the plaintiff would have obtained
under the contract and the extension.
15. It remains to deal with one further matter. In its counterclaim Esanda
denied that the plaintiff had any right to treat the
hirepurchase agreement as
repudiated and sought to recover from it pounds 7,613 19s. representing
twenty-one instalments of hire
under the hire-purchase agreement, together
with interest thereon. At the trial the counterclaim was supported upon the
ground that
the plaintiff had not returned the machine to Esanda's place of
business when We notice of 4 march 1959, was given and that for this
reason
the plaintiff remained liable for instalments of hire thereafter falling due,
together with interest. On the appeal this contention
was abandoned. Instead
it was submitted that the plaintiff, when it discovered that the condition as
to the fitness of the machine
to perform the work had not been complied with,
kept and worked it to a considerable time. It had, so it was said, thereby
elected
to treat the breach of the condition as a breach of warranty and,
while it was entitled to recover damages for that breach, the hire-purchase
agreement remained on foot and the plaintiff was liable to pay instalments of
hire and interest thereon. If this be correct, it would
seem to follow that
the damages recoverable by the plaintiff from the T.C. Company would be
correspondingly increased but it is unnecessary
to consider this further
because the point now raised should not, in our opinion, be entertained. Had
the matter been put forward
at the trial, issues of fact would have arisen as
to which relevant evidence might have been led to show that, in all the
circumstances,
the plaintiff had not made any such election as was suggested.
The evidence suggests that during the period when the plaintiff was
endeavouring to have the machine put into proper working order, by the renewal
of parts and the like, Esanda was informed of the
difficulties being
encountered but no attempt was made to elicit evidence as to what passed
between it and the plaintiff on these
occasions. In these circumstances we
think we should apply what was said by Lord Watson in Connecticut Fire
Insurance Co. v. Kavanagh
(8), and adopted by this Court in Suttor v. Gundowda
Pty. Ltd. (9):
"When a question of law is raised for the first time in a court of last
report, upon the construction of a document, or upon facts
either admitted or
proved beyond controversy, it is not only competent but expedient, in the
interests of justice, to entertain the
plea. The expediency of adopting that
course may be doubted, when the plea cannot be disposed of without deciding
nice questions
of fact, in considering which the court of ultimate review is
placed in a much less advantageous position than the courts below.
But their
Lordships have no hesitation in holding that the course ought not, in any
case, to be followed unless the court is satisfied
that the evidence upon
which they are asked to decide establishes beyond doubt that the facts, if
fully investigated, would have
supported the new plea."
16. In the result we find ourselves, except on one point, in agreement with
Stable J., by whose exhaustive and careful judgment
we have been greatly
asssited. We are of opinion that the judgment below should be set aide and
that the action should be remitted
to the Supreme Court for further hearing as
to the quantum of damages. The respondent should pay one-half of the
appellants' costs
of the appeals.
(8) (1892) AC 473, at, 480(9) [1950] HCA 35; (1950) 81 CLR 418, at p. 438.
17. Appeals allowed. Judgment of the Supreme Court set aside except in so
far as the counterclaim of the defendant Esanda Ltd.
is thereby dismissed with
costs. Action remitted to the Supreme Court to re-assess the damages and to
enter judgment for the plaintiff
against the defendants accordingly-Respondent
to pay one-half of the appellants' costs of the appeals.
Solicitors for the first appellant, Hawthorn Cuppaidge and Badgery.
Solicitors for the second appellant, Tulley and Wilson.
Solicitors for the respondent, Thynne and Macartney.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/cth/HCA/1963/57.html