FEDERAL COURT OF AUSTRALIA
Redline Contracting Pty Ltd v MCC Mining (Western Australia) Pty Ltd (No 2) [2012] FCA 1
|
Citation:
|
Redline Contracting Pty Ltd v MCC Mining (Western Australia) Pty Ltd
(No 2) [2012] FCA 1
|
|
|
|
|
|
|
Parties:
|
||
|
|
|
|
|
File number:
|
WAD 458 of 2011
|
|
|
|
|
|
|
Judge:
|
SIOPIS J
|
|
|
|
|
|
|
Date of judgment:
|
||
|
|
|
|
|
Catchwords:
|
CONTRACT - construction contract -
unconditional undertaking procured by the contractor in favour of the principal
- each party purported
to terminate the construction contract - the principal
claimed damages from the contractor - the contractor claimed an interlocutory
injunction to preclude the principal from resorting to the unconditional
undertaking - whether contractor demonstrated a prima facie
case that the
principal is precluded from resorting to the security.
|
|
|
|
|
|
|
Legislation:
|
||
|
|
|
|
|
Cases cited:
|
Redline Contracting Pty Ltd v MCC Mining
(Western Australia) Pty Ltd [2011] FCA 1337
Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812 Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420 Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458 FMT Aircraft Gate Support Systems v Sydney Ports Corporation [2010] NSWSC 1108 Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in liq) [2002] QCA 224; [2003] 1 Qd R 259 Merritt Cairns Constructions Pty Ltd v Wulguru Heights Pty Ltd [1995] QCA 273; (1995) 2 Qd R 521 Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283 Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579 Sudholz Pty Ltd v Airlie Summit Pty Ltd [2007] QSC 199 Olex Focas Pty Ltd v Skodaexport Co Ltd [1998] 3 VR 380 |
|
|
|
|
|
|
|
|
|
|
Place:
|
Perth
|
|
|
|
|
|
|
Division:
|
GENERAL DIVISION
|
|
|
|
|
|
|
Category:
|
Catchwords
|
|
|
|
|
|
|
Number of paragraphs:
|
71
|
|
|
|
|
|
|
|
|
|
|
Solicitor for the Applicant:
|
Holding Redlich
|
|
|
|
|
|
|
Counsel for the Respondent:
|
Mr SK Dharmananda SC and Mr MR Collins
|
|
|
|
|
|
|
Solicitor for the Respondent:
|
Corrs Chambers Westgarth
|
|
|
IN THE FEDERAL COURT OF AUSTRALIA
|
|
|
|
|
|
AND:
|
THE COURT ORDERS THAT:
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
|
|
|
|
WESTERN AUSTRALIA DISTRICT REGISTRY
|
|
|
GENERAL DIVISION
|
WAD 458 of 2011
|
|
BETWEEN:
|
REDLINE CONTRACTING PTY LTD (ABN 23 001 685
025)
Applicant |
|
AND:
|
MCC MINING (WESTERN AUSTRALIA) PTY LTD (ABN 69 123 854
740)
Respondent |
|
JUDGE:
|
SIOPIS J
|
|
DATE:
|
6 JANUARY 2012
|
|
PLACE:
|
PERTH
|
REASONS FOR JUDGMENT
Our client requires payment of $1,290,368.05 for its unpaid fuel invoices and outstanding interest immediately. The letter constitutes notice of intention to have recourse under GC5.2 of the contract.
5.2 Recourse
Security shall be subject to recourse by a party who remains unpaid after the time for payment where at least 5 days have elapsed since that party notified the other party of intention to have recourse. (Original emphasis.)
Contract No MCCM-C-0030 (Contract)
Sino Iron Project
Unpaid claims
We refer to our Notice of Dispute dated 12 October 2011 (attached).
(a) has incurred $4,090,515.22 in costs repairing the defective WUC [which it is entitled to recover from Redline]; and
(b) is entitled to recover from Redline:
(i) the cost of re-tendering and awarding a new contract to Murphy Pipe & Civil to complete the Contract’s scope of work in the amount of $303,830.00; and
(ii) the additional amount paid by MCCM to Murphy Pipe & Civil to complete the Contract’s scope of work in the amount of $41,441,987.90.
The provisions in Schedule 1 Division 5 about the time when a payment must be made are implied in a construction contract that does not have a written provision about that matter.
(a) by the principal to the contractor for payment of an amount in relation to the performance or non-performance by the contractor of its obligations under this contract.
7(1) If a party receives a payment claim –
(a) believes the claim should be rejected because the claim has not been made in accordance with this contract; or
(b) disputes the whole or part of the claim,
the party must, within 14 days after receiving the claim, give the claimant a notice of dispute.
7(3) Within 28 days after a party receives a payment claim, the party must do one of the following, unless the claim has been rejected or wholly disputed in accordance with subclause (1) –
(a) pay the part of the amount of the claim that is not disputed;
(b) pay the whole of the amount of the claim.
16.2.1 The contractor’s breach.
16.2.2 What the principal requires the contractor to do to remedy the breach.
16.2.3 A specific reasonable time in which the contractor must remedy the breach.
As a matter of terminology, it is difficult to characterise as “money due” a sum which is asserted by a party in a dispute to be owing by its adversary in a draft interim claim without substantiation and without detail, and of course, without any determination by adjudication, arbitration or otherwise.
In the circumstances, I construe the present building contract to oblige the Principal, which wishes to exercise rights under cl 5.6 as a consequence of an ex-contract liability, to demonstrate that this liability in fact exists. This it may do by agreement or by some authoritative determination whether by judicial order or arbitral award.
Mrs Crennan submitted that cl 3.13(b) expressly permitted Varnsdorf to make a call upon the unconditional letters of credit provided that two conditions were satisfied, first that a notice containing a demand had been sent to Fletcher and secondly that there had been a failure to pay the amounts demanded within 10 business days. She submitted that cl 3.13(b) contained no requirement that a further condition be satisfied to the effect that Varnsdorf’s entitlement to Time Damages must be established, whether by admission, by determination in an arbitration, or by judgment of a court.
Although in some cases, the absence of quantification may suggest that the claim is specious, fanciful or untenable, it does not follow as a matter of language, logic or common sense that quantification is always necessary. In this case, the defendant had a genuine claim for damages which had been assessed internally although no amount had been finalised and communicated to the plaintiff.
UNCONSCIONABILITY
As already pointed out, on their proper construction, the performance bank guarantees were unconditioned on any actual breach and did entitle ONGC to call upon them for the full amount. Given the commercial purpose of such guarantees, recognised in Wood Hall assuming the absence of fraud, there would seem to be very little, if any, scope for the application of equitable doctrines of unconscionable conduct to restrain the exercise by a party of its legal rights under such guarantees. There may be extreme cases which would merge into the area of bad faith exercises of the power. However that may be, the present is not a case which, on the materials before his Honour, justified any finding of a serious question to be tried of a contravention of s 51AA. The wide purpose of the performance bank guarantees and their character as reflecting an allocation of risk and a provision of security to their holder militate against any argument as to disproportion in their exercise.
I reach that conclusion against the background of the historical purpose and use of such bonds, as discussed in the cases that I have referred to earlier and in the textbooks, and against the background of the High Court in Wood Hall, noting with apparent equanimity that it seemed that in making the demands the authority was acting pursuant to what it is described as a “strategy” to put pressure on the contractor in the hope that the dispute between the parties might be settled more advantageously to the authority.
Dated: 6 January 2012