You are here:
AustLII >>
Databases >>
Federal Court of Australia >>
2011 >>
[2011] FCA 639
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
ActewAGL Distribution v The Australian Energy Regulator [2011] FCA 639 (8 June 2011)
Last Updated: 10 June 2011
FEDERAL COURT OF AUSTRALIA
ActewAGL
Distribution v The Australian Energy Regulator [2011] FCA 639
|
Citation:
|
ActewAGL Distribution v The Australian Energy Regulator [2011] FCA
639
|
|
|
|
Parties:
|
ACTEWAGL DISTRIBUTION, A PARTNERSHIP BETWEEN
ACTEW DISTRIBUTION LIMITED AND JEMENA NETWORKS (ACT) PTY LIMITED v THE
AUSTRALIAN ENERGY
REGULATOR
|
|
|
|
File number(s):
|
NSD 1252 of 2010
|
|
|
|
Judge:
|
KATZMANN J
|
|
|
|
Date of judgment:
|
|
|
|
|
Catchwords:
|
ADMINISTRATIVE LAW – Application for
review under s 5 of the Administrative Decisions (Judicial Review) Act
1977 (Cth) – National Electricity Law – National Electricity
Rules – decisions relating to the regulation of the wholesale
price of
electricity in the ACT – whether the Australian Energy Regulator had the
power to vary a decision about the averaging
period to be used to determine the
nominal risk-free rate of capital after the period had been specified –
application filed
well outside statutory period – whether extension of
time should be granted – whether discretion should be exercised
under
s 10(2)(b)(ii) of the Administrative Decisions (Judicial Review) Act
to refuse to grant the application
|
|
|
|
Legislation:
|
Acts Interpretation Act 1901 (Cth)
s 33(1)Administrative Decisions (Judicial Review) Act 1977 (Cth)
ss 5, 5(2)(j), 10(1)(a), 10(2)(b), 10(2)(b)(ii), 11Competition and
Consumer Act 2010 (Cth) ss 37, 42, 44AEElectricity
( National Scheme) Act 1997 (ACT) s 5 Federal Court of
Australia Act 1976 (Cth) ss 37MFederal Court Rules
O 54 r 7(2) Judiciary Act 1901 (Cth) ss 37, 39B,
42 National Electricity (South Australia) Act 1996 (SA) Sch,
National Electricity Law ss 9, 34, 71B(1), 71C, 71D, 71P(2) 71P(5),
71Q(1), Sch 1 cll 7, 7A(2) National Electricity Rules
cll 6.13(a), 6.5.2
|
|
|
|
|
|
|
16, 17, 29 and 30 March 2011
|
|
|
|
Date of last submissions:
|
6 April 2011
|
|
|
|
Place:
|
Sydney
|
|
|
|
Division:
|
GENERAL DIVISION
|
|
|
|
Category:
|
Catchwords
|
|
|
|
Number of paragraphs:
|
198
|
|
|
Counsel for the Applicant:
|
Mr A Robertson SC with Ms RCA Higgins
|
|
|
|
Solicitor for the Applicant:
|
Mallesons Stephen Jaques
|
|
|
|
Counsel for the Respondent:
|
Mr S Lloyd SC with Mr S Balafoutis
|
|
|
|
Solicitor for the Respondent:
|
Australian Government Solicitor
|
|
IN THE FEDERAL COURT OF AUSTRALIA
|
|
NEW SOUTH WALES DISTRICT REGISTRY
|
|
|
|
|
|
|
ACTEWAGL DISTRIBUTION, A PARTNERSHIP BETWEEN
ACTEW DISTRIBUTION LIMITED AND JEMENA NETWORKS (ACT) PTY
LIMITEDApplicant
|
|
AND:
|
THE AUSTRALIAN ENERGY
REGULATORRespondent
|
|
|
|
|
DATE OF ORDER:
|
|
|
WHERE MADE:
|
|
THE COURT ORDERS THAT:
- The
application be dismissed.
- The
applicant pay the respondent’s costs.
Note: Settlement and entry of orders is dealt with in Order 36 of
the Federal Court Rules.
The text of entered orders can be located using
Federal Law Search on the Court’s website.
IN THE FEDERAL COURT OF AUSTRALIA
|
|
|
NEW SOUTH WALES DISTRICT REGISTRY
|
|
|
GENERAL DIVISION
|
NSD 1252 of 2010
|
|
BETWEEN:
|
ACTEWAGL DISTRIBUTION, A PARTNERSHIP BETWEEN ACTEW DISTRIBUTION LIMITED
AND JEMENA NETWORKS (ACT) PTY LIMITED Applicant
|
|
AND:
|
THE AUSTRALIAN ENERGY REGULATOR Respondent
|
|
JUDGE:
|
KATZMANN J
|
|
DATE:
|
8 JUNE 2011
|
|
PLACE:
|
SYDNEY
|
REASONS FOR JUDGMENT
INTRODUCTION
- This
case is concerned with decisions made in 2008 and 2009 relating to the
regulation of the wholesale price for the distribution
of electricity in the
Australian Capital Territory (“ACT”) in the five-year period from
2009 to 2014.
- The
decision-maker is the respondent (“AER”), the body responsible for
the economic regulation of electricity distribution
and transmission services in
the National Electricity Market, a wholesale electricity exchange for those
Australian States and Territories
that are electrically connected, that is to
say, all except Western Australia and the Northern Territory.
- The
AER is established as a body corporate under s 44AE of the Competition
and Consumer Act 2010 (Cth) (formerly s 44AE of the Trade Practices
Act 1974 (Cth)). Its functions and powers are defined by the National
Electricity Law (“NEL”) and the National Electricity Rules
(“NER”). The NEL is a schedule to the National
Electricity (South Australia) Act 1996 (SA) and is applied as a law of
the Australian Capital Territory by s 5 of the Electricity
(National Scheme) Act 1997 (ACT). The NER consist of rules
made initially by the Minister, and thereafter by the Australian Energy Market
Commission (“AEMC”),
pursuant to s 34 of the NEL, and which (by
s 9 of the NEL) have the force of law.
- The
regulatory scheme determines the allowed revenue of a regulated business. For
this purpose, the costs of the business must be
calculated by reference to the
rate of return on capital.
- The
AER’s chief regulatory function is the setting of annual revenue
requirements that a transmission network service provider
and a distribution
network service provider can recover from the provision of direct control
services in a regulatory control period.
The regulatory control period, in
substance, is a period of no less than five years during which the controls are
in place.
- The
applicant (“ActewAGL”) is a distribution network service provider
registered under cl 2.5.1 of the NER, and the owner
and operator of the ACT
electricity distribution network.
- In
the period between July 2008 and April 2009 the AER made a series of decisions
relating to ActewAGL culminating in the publication
on 28 April 2009 of its
distribution determination for the five-year regulatory control period from 1
July 2009 to 30 June 2014:
Final Decision, Australian Capital
Territory distribution determination, 2009-10 to 2013-14 (“Final
Decision”). The Final Decision is 274 pages long and documents the
processes that the parties undertook in the
lead-up to the distribution
determination, the submissions made by ActewAGL (and, where relevant, other
network service providers),
and the reasons for the various decisions made by
the AER. At the same time the AER published distribution determinations
affecting
other network service providers.
- ActewAGL
is aggrieved by the AER’s decisions concerning one variable in an equation
used to calculate the rate of return on
capital specified in August 2008 and
applied in the Final Decision. At the heart of ActewAGL’s grievance is
its perception
(shared by other service providers) that it has been unfairly
disadvantaged by the imposition of a rate that did not account for
the impact of
the global financial crisis.
- It
was open to ActewAGL to challenge the Final Decision on its merits in the
Australian Competition Tribunal (“the Tribunal”),
as other network
service providers did, but it chose not to. The other providers succeeded in
their challenges, which included challenges
to the rate of return. The Tribunal
made a decision upholding the approach they had tried to persuade the AER to
adopt: Application by EnergyAustralia [2009] ACompT 8
(“EnergyAustralia”). After ActewAGL became aware of their
success, it tried to persuade the AER to alter its decision in conformity with
the
approach taken by the Tribunal. Those attempts failed and on 24 September
2010 ActewAGL filed an application in this Court for an
order of review pursuant
to s 5 of the Administrative Decisions (Judicial Review) Act 1977
(Cth) (“the ADJR Act”) setting aside the relevant parts of the Final
Decision and referring the matter back to the AER
for reconsideration. Clause
2(da) of Schedule 3 of the ADJR Act relevantly provides that the National
Electricity (South Australia) Act 1996 (SA) is an enactment for the purposes
of the ADJR Act. As the application was filed well outside the prescribed time,
ActewAGL seeks
an extension of time.
- The
AER opposes both the application and the extension of time. It also argues that
the Court should exercise its discretion under
s 10(2)(b) of the ADJR Act
to refuse to grant the application because of ActewAGL’s entitlement to
seek a review of the decision
in the Tribunal.
- Although
the application as filed challenged only the Final Decision, it referred to an
earlier decision and, over the objection
of the AER, I granted leave to ActewAGL
to amend the application to make it clear which decisions it wished the Court to
review.
In the result, ActewAGL challenges three decisions of the AER made in
July and August 2008 and April 2009.
- The
decisions were made under the transitional rules contained in transitional
chapter 6 of the NER. The transitional rules specify
a formula for calculating
the rate of return for the five-year regulatory control period. One component
of that formula is what
is known as “the nominal risk-free rate”.
That is determined by reference to the yield on 10 year Commonwealth Government
bonds and an agreed or appointed period (“averaging period”) over
which the rate will be calculated. The averaging period
that is chosen affects
the weighted average cost of capital, which, in turn, affects the annual revenue
requirement, and, ultimately,
the prices a distribution network service provider
can charge its customers.
- Under
the terms of the NER, the distribution network service provider must first
propose an averaging period. The AER may either
agree with that proposal or
not, but its agreement may not be unreasonably withheld.
- ActewAGL
proposed one period, with which the AER did not agree. After the AER had
specified a different period, ActewAGL then submitted
a revised proposal which
the AER declined to accept. ActewAGL contends that the AER unreasonably
withheld its agreement to the two
proposals and its decisions to do so were
reached or affected by reviewable error.
THE LEGISLATIVE SCHEME
- The
NER commenced on 1 July 2005, replacing the National Electricity Code which
previously regulated electricity and gas distribution.
Division 2 contains
special transitional provisions applying to NSW and the ACT for the 2009-2014
regulatory control period. Those
special provisions appear in Chapter 11. In
substance they adopt a varied form of chapter 6 of the NER for the NSW and ACT
distribution
network service providers. The prices ActewAGL was entitled to
charge its customers and the revenue it was able to generate for
the five-year
period from 1 July 2009 were determined by those transitional rules and the
decisions under review were made under
them.
- Under
the transitional rules, the annual revenue requirement for the distribution
network service providers for each regulatory year
of a regulatory control
period had to be determined using a “building block” approach that
employed defined building
blocks. They included the indexation of the
regulatory asset base of the provider (that is, the value of the assets used to
provide
the distribution service but only to the extent that they are so used:
cl 6.5.1(a)) and a return on capital for that year: cl 6.4.3(a).
ActewAGL, as a distribution network service provider, was obliged to submit a
regulatory proposal (that included a building block
proposal) for the 2009-2014
regulatory period on or before 2 June 2008: cl 6.8.2.
- Subject
to the provisions in the NEL and the NER about confidentiality, the AER was
required to publish the regulatory proposal and
invite written submissions on
the proposal and other matters within a prescribed period: cl 6.9.3. The
AER was obliged to consider
those submissions and then make and publish a draft
distribution determination, which included its reasons for making the
determination
and its various constituent decisions (defined in cl 6.12.1):
cll 6.10.1, 6.10.2. One of those constituent decisions was a decision
in
relation to the rate of return on capital: cl 6.12.1(5). In addition to
making a written submission, a provider was entitled
to submit a revised
regulatory proposal to the AER within 30 business days after the publication of
the draft determination, but
only “so as to incorporate the substance of
any changes required to address matters raised by the draft distribution
determination
or the AER’s reasons for it”: cl 6.10.3(a) and
(b). The AER was entitled, but not bound, to invite written submissions
on the
revised proposal: cl 6.10.3(e). It was required to consider any
submissions made on the draft determination or any revised
proposal and then
make a distribution determination in relation to the provider:
cl 6.11.1.
- The
regulatory framework was described by the Tribunal in the EnergyAustralia
case at [10]-[14]:
[10] The NEL and the National Electricity Rules (‘the Rules’)
provide the economic and legal framework for the regulation
of the revenues of
the Applicants operating in the national electricity market.
[11] The NEL requires that in performing or exercising its economic regulatory
functions or powers the AER must:
- do so in a
manner that will, or is likely to, contribute to the achievement of the national
electricity objective (s 16(1)); and
- take into
account the revenue and pricing principles (s 16(2)).
[12] The national electricity objective, found in s 7 of the NEL,
is:
... to promote efficient investment in, and efficient operation and use of,
electricity services for the long term interest of consumers
of electricity with
respect to:
(a) price, quality, safety, reliability and security of supply of
electricity; and
(b) the reliability, safety and security of the national electricity
system.
[13] The revenue and pricing principles set out in s 7A of the NEL
are:
(2) A regulated network service provider should be provided with a reasonable
opportunity to recover at least the efficient costs
the operator incurs in
–
(a) providing direct control network services;
and
(b) complying with a regulatory obligation or requirement or making a
regulatory payment.
(3) A regulated network service provider should be provided with effective
incentives in order to promote economic efficiency with
respect to direct
control network services the operator provides. The economic efficiency that
should be promoted includes –
(a) efficient investment in a distribution system or transmission system with
which the operator provides direct control network services;
and
(b) the efficient provision of electricity network services;
and
(c) the efficient use of the distribution system or transmission system with
which the operator provides direct control network
services.
(4) Regard should be had to the regulatory asset base with respect to a
distribution system or transmission system adopted
–
(a) in any previous
–
(i) as the case requires, distribution determination or transmission
determination; or
(ii) determination or decision under the National Electricity Code or
jurisdictional electricity legislation regulating the revenue
earned, or prices
charged, by a person providing services by means of that distribution system or
transmission system;
or
(b) in the Rules.
(5) A price or charge for the provision of a direct control network service
should allow for a return commensurate with the regulatory
and commercial risks
involved in providing the direct control network service to which that price or
charge relates.
(6) Regard should be had to the economic costs and risks of the potential for
under and over investment by a regulated network service
provider in, as the
case requires, a distribution system or transmission system with which a
regulated network service provider provides
direct control network services.
(7) Regard should be had to the economic costs and risks of the potential for
under and over utilisation of a distribution system
or transmission system with
which a regulated network service provider provides direct control network
services.
[14] The national electricity objective provides the overarching economic
objective for regulation under the NEL: the promotion of
efficient investment
and efficient operation and use of, electricity services for the long term
interests of consumers. Consumers
will benefit in the long run if resources are
used efficiently, that is if resources are allocated to the delivery of goods
and services
in accordance with consumer preferences at least cost. As reflected
in the revenue and pricing principles, this in turn requires
prices to reflect
the long run cost of supply and to support efficient investment, providing
investors with a return which covers
the opportunity cost of capital required to
deliver the services.
Calculating the rate of return on capital: clause 6.5.2
- Clause
6.5.2 of the transitional rules prescribes the method for calculating the rate
of return on capital for the regulatory control
period.
- Clause
6.5.2(a) provides that the return on capital for each regulatory year must be
calculated by applying a rate of return for
the relevant distribution network
service provider for the five-year regulatory control period to the value of the
regulatory asset
base as at the beginning of the regulatory year. The rate of
return is calculated in accordance with cl 6.5.2(b).
- Clause
6.5.2(b) contains both a conceptual definition of the rate of return and a
mandatory requirement to use a particular formula
to ascertain it. The rate of
return is defined as “the cost of capital as measured by the return
required by investors in
a commercial enterprise with a similar nature and
degree of non-diversifiable risk as that faced by the distribution
business of the provider” (original emphasis). A non-diversifiable risk
is one that relates to market-wide risk factors as
distinct from a diversifiable
risk, which is a unique risk specific to an asset and which can be eliminated by
investors who hold
a well-diversified portfolio of assets. The clause
stipulates that the rate of return must be calculated as a nominal post-tax
weighted
average cost of capital (“WACC”), by a statutory formula.
- The
formula is complex. It involves multiple equations. The relevant equation is
that which determines the return on equity (ke), which paragraph (b)
provides must be determined using the Capital Asset Pricing Model
(“CAPM”) and certain defined
parameters. The CAPM yields the
expected return on equity having regard to the return on the market portfolio,
the volatility of
the market and the systematic risk of holding equity in the
particular business. It specifies a relationship between the expected
return of
an individual risky asset or business and the level of systematic (or
non-diversifiable) risk.
- The
equation for determining the return on equity involves adding the multiple of
the equity beta (âe) and the market risk
premium (MRP) to the nominal
risk-free rate for the regulatory control period, which is determined in
accordance with the process
described in paragraph (c) of the clause. That
calculation appears as:
rf + âe × MRP
where:
rf is the nominal risk free rate for the regulatory control period
determined in accordance with paragraph (c);
âe (the equity beta) is deemed to be 1.0; and
MRP (the market risk premium) is deemed to be 6.0%
- The
risk-free rate is the rate of return an investor receives from holding an asset
with guaranteed payments, that is, where there
is no risk of default. The AER
described the nominal risk-free rate (rf) in this way in its August
2008 issues paper on the review of the WACC parameters (at
26):
Where a risk free rate is calculated in nominal terms (actual cash flows) the
risk free rate will compensate investors for the opportunity
cost of not being
able to invest in the next best equivalent ‘riskless’ investment.
This includes compensation for:
- the time value
of money
- the expected
cost of inflation which is expected to decrease the purchasing power of the
certain cash flows to be received and
- other possible
premiums for certain risks, which might include liquidity and inflation
risk.
- The
equity beta (âe) is a measure of the sensitivity of the return of a
particular asset or business to the return on the market
portfolio. An equity
beta higher than 1.0 indicates that the asset has a higher systematic
(non-diversifiable) risk relative to
the rest of the market and,
correspondingly, an equity beta of less than 1.0 signifies the asset has a lower
systematic risk than
the market.
- The
market risk premium (MRP) refers to the additional return (or premium) over the
risk-free rate that investors require in order
to be induced to invest in a
well-diversified portfolio of risky assets. Unlike the equity beta, it is
common to all assets in the
economy. Both the equity beta and the MRP are fixed
under paragraph (b). The equity beta is deemed to be 1.0 (that is, level with
the rest of the market) and the MRP is fixed at 6.0%.
- Clause
6.5.2(c) defines the method for determining the nominal risk-free rate that is
to be factored into the calculation of the
return on equity prescribed by
paragraph (b). Paragraph (c) provides for a proxy for the risk-free rate, as
well as a means of determining
the period over which the rate is to be
calculated (namely, the averaging period).
- First,
it mandates the method for determining the nominal risk-free rate: by using
“a moving average” (that is, an average
of share prices over a
period that moves forward regularly) from the annualised yield on Commonwealth
Government bonds with a maturity
of 10 years. Commonwealth Government bonds or
securities are generally considered to be the best proxy for the nominal
risk-free
rate in this country as they are essentially free of the risk of
default, are highly liquid assets and their yields are transparent.
The Capital
Asset Pricing Model requires the use of the most current information for
deriving the rate of return. This in theory
involves the use of the risk-free
rate on the day that required returns are to be estimated (in this case, the
beginning of the regulatory
period) (“on-the-day rate”).
Nevertheless, there are recognised problems with the use of an on-the-day rate
which an
averaging period is intended to address. In particular, deploying an
averaging period will minimise day-to-day volatility in the
market.
- Secondly,
paragraph (c) prescribes the way in which the nominal risk-free rate is to be
calculated, namely, by using the indicative
mid rates published by the Reserve
Bank of Australia (“RBA”).
- Thirdly,
paragraph (c) provides that the period of time over which the rate is determined
is either a period proposed by the distribution
network service provider (and
agreed to by the AER) or a period specified by the AER (and notified to the
provider within a reasonable
time before the commencement of the period). In
the former case, where the provider proposes a period, it stipulates that the
agreement
of the AER is “not to be unreasonably withheld”. It is
the operation of this discretion with which this case is concerned.
- Clause
6.5.2(c) provides:
Meaning of nominal risk free rate
(c) The nominal risk free rate for a regulatory control period is the rate
determined for that regulatory control period by the AER on a
moving average basis from the annualised yield on Commonwealth Government bonds
with a maturity of 10 years using:
(1)
the indicative mid rates published by the Reserve Bank of Australia; and
(2) a period of time which is either:
(i) a period (‘the agreed period’) proposed by the relevant
Distribution Network Service Provider, and agreed by the AER (such
agreement is not to be unreasonably withheld); or
(ii) a period specified by the AER, and notified to the provider within a
reasonable time prior to the commencement of that period, if the period proposed
by the provider
is not agreed by the AER under subparagraph (i),
and, for the purposes of subparagraph (i):
(iii) the start date and end date for the agreed period may be kept
confidential, but only until the expiration of the agreed period;
and
(iv) the AER must notify the Distribution Network Service Provider
where or not it agrees with the proposed period within 30 business days
of the date of submission of the building block proposal.
[original emphasis]
- All
the italicised terms are defined in a lengthy glossary in chapter 10 of the NER.
- A
“regulatory control period” in respect of a distribution
network service provider is defined as:
A period of not less than 5 regulatory years for which the provider is
subject to a control mechanism imposed by a distribution
determination.
- A
“regulatory year” is defined as “each consecutive
period of 12 calendar months in a regulatory control period”, the
first 12 month period starting at the beginning of the regulatory control period
and the last ending at the end of the
period.
- “Building
block proposal” is defined for a distribution network service provider
as “the part of the provider’s regulatory proposal relevant
to the regulation of standard control services”. Clause 6.2.3C(a)
deems a distribution service provided by ActewAGL to be classified as both a
direct control service and
a standard control service. Clause 6.8.2 of the
transitional rules provides that a “regulatory proposal for
direct control services classified as standard control services”
must include a building block proposal. As I mentioned earlier, the contents of
the
building blocks are set out in cl 6.4.3(a).
BACKGROUND TO THE DECISIONS UNDER REVIEW
- On
2 June 2008 ActewAGL lodged with the AER its regulatory proposal for the
five-year regulatory control period commencing 1 July
2009. In that regulatory
proposal, ActewAGL proposed that the period of time to be used to determine the
nominal risk-free rate
be the period of 20 business days ending on 30 June 2008
(“the original proposed averaging period”).
- On
8 July 2008 the AER wrote to ActewAGL rejecting its original proposed averaging
period.
- The
letter stated, amongst other things:
The AER does not agree with the averaging period proposed by ActewAGL as the
starting date of ActewAGL’s proposed averaging
period is almost 12 months
prior to the commencement of the regulatory control period. In this regard, the
AER considers that the
starting date of the proposed period is too far removed
from the date by which the AER is likely to publish ActewAGL’s final
determination, which is expected to be in April 2009, and the commencement of
the 2009—14 regulatory control period. The averaging
period proposed by
ActewAGL is contrary to accepted regulatory practice as reflected in previous
AER and ACCC determinations; the
ACCC’s Statement of Regulatory Principles
and previous jurisdictional AER’s determinations, all of which apply a
nominal
risk free rate averaging period considerably closer to the final
determination date.
The AER’s regulatory practice is supported by accepted expert views in the
economics and finance literature. Capital Asset
Pricing Model (CAPM) theory
suggests that, ideally, the nominal risk free rate input will be calculated on
the day of the final determination.
The CAPM is an ex ante model and therefore
the most up to date information should be used if
available.
Further, applying an averaging period which is closely aligned to the date of
the final determination provides an unbiased rate of
return that is consistent
with the market conditions at the time of the final
determination.
- I
interpolate that the reference to “an unbiased rate of return”
involves making a prediction about interest rates which
although too high or too
low at any particular point in time, is on average correct.
- In
its letter, the AER proposed a different period (20 days starting on 23 February
2009 and ending on 20 March 2009) and went on
to invite ActewAGL to nominate an
alternative averaging period between 1 February 2009 and 20 March 2009 if it
disagreed with the
AER’s proposal.
- On
14 August 2008 ActewAGL responded by proposing a period of 20 business days
commencing 2 February 2009 and the AER agreed to the
proposal on 20 August 2008.
This is the period the AER referred to in the Final Decision as “the
agreed averaging period”.
More accurately (and this appears to be common
ground), it involved the AER specifying the period in accordance with
cl 6.5.2(c)(2)(ii)
(so from now on I will refer to this period as the
“specified” averaging period).
- On
7 November 2008 the AER released its draft distribution determination in
accordance with its obligation under cl 6.10.2. That
determination
included its draft constituent decision on the rate of return in accordance with
cl 6.5.2 (see cl 6.12.1(5)). In the
draft determination, the AER
noted that the risk-free rate would be updated, based on the specified averaging
period, at the time
of the final decision.
- The
averaging period was not disclosed in the draft determination because of a
request from ActewAGL to keep the period confidential.
- On
16 January 2009 ActewAGL submitted a revised regulatory proposal in which,
amongst other things, it proposed a different averaging
period, namely the
period of 20 business days starting on 11 August 2008 and ending on 5 September
2008 (“the revised averaging
period proposal”). The reason it gave
was that, since its correspondence with the AER in July/August 2008, the global
financial
crisis (“GFC”) had begun, its impact in Australia was
“extreme”, and it depressed yields for Commonwealth
Government
securities used by the AER in determining the risk-free rate. It was concerned
to avoid the inclusion of “abnormal
market observations” which, it
contended, would result from an averaging period that started after 5 September
2008 when the
GFC began to worsen. It attached to its revised proposal a report
by Competition Economists Group (“CEG”) concerning
the selection of
an averaging period for the risk-free rate. The report recommended that the AER
set an averaging period before
September 2008 because of the effect of the GFC.
At the time the AER did not question ActewAGL’s entitlement to submit a
revised
averaging period proposal (and therefore the AER’s obligation to
consider it), although now it does.
- On
28 April 2009 the AER published the Final Decision. It rejected
ActewAGL’s revised proposed averaging period, standing
by the period of 20
business days commencing 2 February 2009 that it specified in August 2008. It
applied the same approach to the
proposals of all the network service providers,
each of whom had made similar requests. Consequently, it also rejected the
revised
proposals of those other network service providers.
THE DECISIONS UNDER REVIEW
- The
first decision ActewAGL challenges is the decision made (or communicated) on 8
July 2008 to reject ActewAGL’s original
proposed averaging period, namely,
the period of 20 business days ending on 30 June 2008. The second was the
decision made (or communicated)
on 20 August 2008 that the period of 20 business
days commencing on 2 February 2009 would be used for the purpose of the final
determination.
- The
third and final decision under challenge was the decision made on 28 April 2009
to reject the revised averaging period proposal.
THE REASONS FOR THE DECISIONS
- The
AER set out its reasons for disagreeing with ActewAGL’s original proposal
in its letter of 8 July 2008, part of which is
extracted above at [38]. In
short, its reasons were:
(a) The starting date for the proposed
averaging period (20 business days ending 30 June 2008) was too far removed from
the start
of the regulatory control period (1 July 2009) and too far removed
from the date the AER is likely to publish its final determination
(April 2009),
and such an approach was contrary to accepted regulatory practice, which, it
noted, was supported by recognised experts.
It footnoted the letter with
references to examples of articles and reports.
(b) Applying an averaging period closely aligned to the date of the final
determination provides an unbiased rate of return consistent
with market
conditions at the time of the final determination.
- The
AER noted ActewAGL’s concern about the volatility in debt markets and the
need for certainty in order to manage its commercial
risks. But it voiced its
disagreement that certainty is relevant to applying an averaging period, the
purpose of which, it stated,
is to address the possible daily volatility in
financial markets. It asserted that the publication of the regulatory
determination
provides a distribution network service provider with certainty
about the rate of return which would apply during the ensuing regulatory
control
period and, in any event, that information is provided before the start of the
regulatory control period.
- In
the letter to ActewAGL of 20 August 2008 the AER merely accepted the period
nominated by ActewAGL in its letter of 14 August 2008
and, accordingly,
specified the period to be used in the final determination as the 20 business
days commencing 2 February 2009.
- The
reasons for the decision not to accept the revised averaging period proposal are
summarised in Chapter 12 and detailed in Appendix
I of the Final Decision. The
AER referred to the arguments of both ActewAGL and all other network service
providers who had made
similar revised proposals. All were providers caught,
like ActewAGL, by the transitional provisions of the NER. They were the
applicants
in the proceedings in the Tribunal. The AER said that it had
considered the key arguments put forward in the revised regulatory
proposals and
the additional material, that is to say, the submissions and the
consultants’ reports furnished with them. In
rejecting them, it also
defended the decision it had made in August 2008.
- In
summary the AER made the following points:
(a) As the CEG report was
applicable to the NSW distribution network service providers, Transgrid and
Transend, it should be taken
into account in connection with their
proposals.
(b) The decision to withhold agreement was reasonable and the averaging
period specified in August 2008 is consistent with finance
theory, regulatory
practice, the NER and the NEL. The use of an averaging period “as close
to the start of the next regulatory
control period as practically possible is
consistent with the forward looking nature of the capital asset pricing model
(CAPM) and
is correct in finance theory”.
(c) “[G]iven the evidence at the time, the additional material
contained in the revised regulatory proposal does [scil.] not justify a
conclusion that the AER’s decision to withhold agreement ... was
inconsistent with regulatory practice”.
(No doubt this was a response to
a point CEG had made and to which the AER had referred on the previous page of
its report that
previous regulatory decisions in Australia, the UK and the US
had adjusted the averaging period for the risk-free rate to account
for specific
events.)
(d) ActewAGL’s argument that there was an insufficient return on equity
was based on the view that the market risk premium (MRP)
of 6 per cent, which is
prescribed in the rules, is out of line with current variations in the MRP and
for that reason there should
be adjustments to the risk-free rate. The AER
maintained that this would “circumvent WACC parameters prescribed ... in
the
NER [and] would undermine the intended certainty under the regulatory regime
which results from these values being prescribed”.
(e) The fact that the Commonwealth Government Securities (“CGS”)
are at or close to historical lows does not of itself
mean that they cannot be
used. Interest rates move all the time and reflect the market’s
assessment of the price of money
at a particular time. If ActewAGL can lock in
an averaging period that it considers provides the most advantageous rate of
return
early in the regulatory process based on its view about future interest
rates “then it may create opportunities for ‘gaming’
the
regulator if its view transpires to be disadvantageous”.
(f) The material provided by ActewAGL in support of its revised regulatory
proposal does not reasonably justify the conclusion that
an averaging period
before September 2008 is better than a period as close as practically possible
to the start of the next regulatory
control period. The averaging period
specified in August 2008 did not exclude the downward movement of the CGS yield
and was not
abnormal. Setting the risk-free rate using this period (that is,
the period commencing 2 February 2009) is consistent with the NEL
objective of
efficient investment, with the forward looking nature of the CAPM and with
economic theory.
THE GROUNDS OF REVIEW
- The
amended application for review challenges the decisions on several grounds,
although there is a degree of overlap. They are
that:
(1) The
decisions involved an error of law in that the AER misconceived its task under
cl 6.5.2(c)(2)(i) of the transitional rules.
The particulars of this ground were as follows:
With respect to the July-August decision:
- The
reasons for decision stated in the 8 July 2008 letter do not evidence any
consideration by it of:
(a) the merits of ActewAGL’s original proposed averaging period; or
(b) whether the AER’s agreement to the original proposed averaging period
would be, or was being, withheld on grounds that
were capable of being
characterised as reasonable.
ii. Instead, the AER considered only:
(a) whether there existed a period which it preferred to the original proposed
averaging period for use in determining the risk free
rate within clause
6.5.2(c);
(b) which period it would specify under clause 6.5.2(c)(2)(ii), without
recognising that the power under that clause could only arise
for exercise where
the legislative priority afforded to the period ActewAGL proposed had been
displaced by a not unreasonable withholding
of agreement by the
AER.
With respect to the April 2009 decision:
- The
AER never conducted any analysis which would have allowed it to assess whether
it would be reasonable or not to withhold agreement
to the original or the
revised proposed averaging period.
(2) The April 2009 decision involved an error of law in that the
AER failed to act on “reliable, up to date and material
information”,
adopting the decision it had made nine months earlier, and
used the fact of having made that decision as the basis for refusing
to use
reliable, up to date and material information at the later date.
In the particulars to this ground ActewAGL relied on the AER’s
statement in the Final Decision that its decision to withhold
agreement to the
averaging period contained in the original proposal of 2 June 2008 was
reasonable and consistent with finance theory,
regulatory practice, the NEL and
the NER.
(2A) It was an error of law for the AER in its April 2009 decision to rely on
the July/August 2008 decision which was, itself, invalid.
This ground rested on the same particulars as ground 1.
(3) The AER did not have jurisdiction to make the Final Decision nor the
July/August decision with respect to the averaging period.
This ground also rested on the same particulars as ground 1.
(4) The decisions were not authorised by the enactment in pursuance of which
they were purported to be made.
ActewAGL repeated here too the particulars to ground 1, and also repeated
grounds 2 and 3.
(5) The making of the decisions were an improper exercise of the power
conferred by the enactment in that the AER exercised a discretionary
power in
accordance with a rule or policy without regard to the merits of the case. The
rule or policy cited was “that the
averaging period to be used in
calculating the nominal risk-free rate should always be the period as close as
possible to the commencement
of the regulatory control period” (regardless
of whether that was reasonable having regard to the particular characteristics
of the period).
(6) The making of the decisions was an improper exercise of the power
conferred by the enactment in that the AER failed to take into
account certain
relevant considerations. They were:
- whether
ActewAGL’s proposals were likely to result in an unbiased risk-free rate,
given that the equity beta and market risk
premium were deemed (under
cl 6.5.2(b)) to be 1.0 and 6.0% respectively;
- whether
the original or revised proposal promoted the national electricity objective
prescribed by s 7 and the revenue and pricing
principles prescribed by
s 7A of the NEL;
- “the
exceptional and anomalous conditions” arising from the global financial
crisis, and
- any
“forward-looking analysis” of whether the periods proposed by
ActewAGL would provide a reasonable proxy for the risk-free
rate that would be
expected to apply either on 1 July 2009 or on 1 July in each of the five years
of the regulatory period.
(7) Not pressed.
(8) The making of the decisions was an improper exercise of the power
conferred by the enactment in that its exercise of the power
was so unreasonable
that no reasonable person could have so exercised it.
ActewAGL repeated the particulars to grounds 1, 2 and 3 and added:
- Further,
the [AER] could withhold agreement to the period proposed by [ActewAGL] only if
it were satisfied that it was not unreasonable
to do so. For that purpose the
[AER] would have required but did not have, access to a forward looking analysis
of whether the period
of 20 business days ending 30 June 2008 or 5 September
2008 would provide a reasonable proxy for the risk free rate that would be
expected to apply either on 1 July 2009 or on 1 July in each of the years
between 2009 and 2013 inclusive.
- In
making the [April 2009 decision], the [AER] had regard to yields for bonds of
different maturities during the period June 2008
to which the [AER] referred in
the [April 2009 decision], in circumstances in which [ActewAGL’s] revised
proposed averaging
period at that time was the period of 20 business days
ending 5 September 2008 and not any period in June 2008, and the [AER’s]
averaging period was the period of 20 business days commencing on 2 February
2009 and not any period in June 2008.
- ActewAGL
seeks an order setting aside the decisions under review pursuant to
s 16(1)(b) of the ADJR Act and referring the matter
to the AER for further
consideration according to law.
- In
support of its application, ActewAGL relied on an affidavit affirmed by David
Graham, its Director of Regulatory Affairs and Pricing,
who was cross-examined,
and documents exhibited to that affidavit. ActewAGL also tendered two expert
reports. The AER called no
lay evidence, relying on the documents that were
before it at the time it made its decisions, but proffered expert evidence to
meet
the reports presented by ActewAGL. The experts collaborated on the
preparation of a joint report and gave evidence concurrently.
On the question
of their expertise there was little to choose between them.
- The
two experts were economists: Gregory Houston for ActewAGL, and Associate
Professor Martin Lally for the AER, upon whose writings
the AER had relied in
reaching its decisions. Mr Houston is a director of the firm NERA Economic
Consulting. He has 20 years experience
in the economic analysis of markets and
in providing expert economic advice in litigation, business strategy and policy
contexts.
He has worked in the private sector and government in the United
Kingdom and New Zealand respectively, and has advised on regulatory
and
competition matters in various countries including Australia. He was a member
of the expert panel convened to advise the Ministerial
Council on Energy on
achieving harmonisation of the approach to regulation of electricity and gas
transmission and distribution infrastructure
in Australia. Dr Lally is
Associate Professor of Economics and Finance at the Victoria University of
Wellington, New Zealand. Over
the last 20 years he too has advised a wide range
of public and private sector entities on financial issues, and over the last 10
years he has provided advice to regulatory bodies in Australia and New Zealand.
- Ultimately,
the dispute between the experts was of a narrow compass. To the extent to which
it is relevant I will deal with it when
I come to discuss the merits of the
application.
THE POWER TO VARY THE AVERAGING PERIOD DECISION
- Logically,
the first question to be considered is whether the Court should permit ActewAGL
to apply for a review of any or all of
the various decisions although they were
brought outside the time prescribed under the ADJR Act. There is, however, a
threshold
question that affects ActewAGL’s application to set aside the
decision to reject the revised averaging period proposal in April
2009. It is
convenient to deal with it first.
- The
AER argued that, despite what it appears to have assumed in the Final Decision,
once it had specified the averaging period in
August 2008, it had no power to
alter it.
- Thus,
in order for ActewAGL to challenge the Final Decision, it must prove that under
the NER it could present a revised proposal
on the averaging period, and
establish that the AER had the power to accept it.
Was ActewAGL entitled to submit a revised averaging period proposal?
- ActewAGL
argued that it was entitled to submit a revised averaging period proposal
because of the terms of cl 6.10.3(b) of the NER.
This provision, it will
be recalled, authorises a distribution network service provider to make
revisions to its regulatory proposal
within 30 days of the publication of the
draft determination but only “so as to incorporate the substance of any
changes required
to address matters raised by the draft determination or the
AER’s reasons for it”.
- ActewAGL
submitted that the subject of the averaging period was raised in the draft
determination, referring to a definition of “raise”
from the
Oxford Pocket Dictionary of Current English, namely, “to cause to
be heard, considered or discussed; to cause to occur, appear or be felt”.
It submitted that the averaging period was considered and discussed in
the draft determination and so the AER could revise the period.
I reject the
submission.
- Firstly,
it is doubtful whether it can be said that the averaging period was discussed in
the draft determination. It was certainly
not considered. The draft
determination did include a section entitled “AER considerations”
under the topic of “the
risk-free rate”. But all that was included
there was an account of the history and a brief reference to the reasons the AER
had previously given ActewAGL for withholding its agreement to the original
proposal.
- Secondly,
even if it can be said that the AER considered or discussed the averaging period
in the draft determination, in my opinion
that is not the relevant meaning of
“raised” in cl 6.10.3(b). Rather, the relevant meaning in this
context is “brought
up (a question, a point, etc.)” or “put
forward (an objection, a difficulty, etc.)”: See Oxford English
Dictionary. The clear intention of the paragraph is to afford a
distribution network service provider procedural fairness; to enable it to
address concerns the AER has before it makes its decision, not to give
the service provider the opportunity to reverse a decision already made. No
question or point
concerning the averaging period was brought up by the AER in
the draft determination and no objection or difficulty was put forward.
The AER
was not foreshadowing a decision it would make or expressing a provisional view.
It was merely reporting on its previous
decision and the reasons for it,
consistently with its statutory obligation under cl 6.12.2 to set out the
basis and rationale of
the determination, including the values it adopted for
each of the input variables in any calculations and formulae. One of those
input variables was the risk-free rate.
- The
next question is whether the AER had the power to vary the averaging period
specified in August 2008 in any event.
Did the AER have the power to agree to or specify a revised averaging
period?
- ActewAGL
contended that the power to vary the decision derives from cl 19(1) of
Schedule 2 of the NEL which provides:
19—Performance of statutory functions
(1) If this Law confers a function or power on a person or body, the function
may be performed, or the power may be exercised, from
time to time as occasion
requires.
-
It
also referred to clause 20:
20—Power to make instrument or decision includes power to amend or
repeal
If this Law authorises or requires the making of an instrument, decision or
determination—
(a) the power includes power to amend or repeal the instrument, decision or
determination; and
(b) the power to amend or repeal the instrument, decision or determination is
exercisable in the same way, and subject to the same
conditions, as the power to
make the instrument, decision or determination.
- Clause
41 applies Schedule 2 to a statutory instrument (including the NER),
“except so far as the context or subject matter
otherwise indicates or
requires”. This qualification is critical.
- Here,
the NEL conferred on the AER a power or function in cl 6.5.2(c)(2): to
agree with, or to withhold its agreement to, the averaging
period ActewAGL
originally proposed and specify another. The decision to agree or disagree with
ActewAGL’s proposal is also
a “decision” authorised by the NEL
in the sense of cl 20. Thus, ActewAGL contends that the AER could amend or
repeal
that decision and make a new one in the same way and subject to the same
conditions as before. In this case, however, I am of the
opinion that the
context or subject matter of that provision indicates or requires otherwise.
- In
Minister for Immigration and Ethnic Affairs v Kurtovic [1990] FCA 22; (1990) 21 FCR 193
at 211 Gummow J said of s 33(1) of the Acts Interpretation Act 1901
(Cth), which is similar in form to cl 19(1) as read with
cl 41:
[I]n any given case, a discretionary power reposed by statute in the decision
maker may, upon a proper construction, be of such a
character that it is not
exercisable from time to time and it will be spent by the taking of the steps or
the making of the statements
or representations in question, treating them as a
substantive exercise of the power. The result is that when the decision maker
attempts to resile from his earlier position, he is prevented from doing so not
from any doctrine of estoppel, but because his power
to do so is spent and the
proposed second decision would be ultra vires. The matter is one of
interpretation of the statute conferring
the particular power in
issue.
- The
question of whether the AER had the power to vary its decision turns, then, on
the proper interpretation of cl 6.5.2(c)(2) in
its context and having
regard to its general purpose and policy, accepting, however, the paramount
significance of the words themselves:
Nominal Defendant v GLG Australia Pty
Limited [2006] HCA 11; (2006) 228 CLR 529 at [22].
- Clause
6.8.2 of the transitional rules required a distribution network service provider
to submit its original regulatory proposal
(including the building block
proposal) by 2 June 2008. Clause 6.5.2(c)(2) stipulates the use of an averaging
period, which is either
agreed between the parties or specified by the AER and
notified to the service provider within a reasonable time before the specified
period begins. Clause 6.5.2(c)(2)(iv) requires the AER to notify the provider
whether or not it agrees with the period proposed
within 30 business days of the
date of submission of the building block proposal. One of the building blocks
is the return on capital
for each regulatory year of the regulatory control
period calculated in accordance with cl 6.5.2. Thus, one of the ingredients
of
a building block proposal is a proposal about the averaging period for
determining the nominal risk free rate used to determine the
rate of return. If
the provider put forward a proposal about the averaging period after the
building block proposal had been submitted,
the AER could not provide the
requisite 30 days’ notice. If the AER did not agree with the
provider’s proposal and specified
a period, the AER had to notify the
provider within a reasonable time before the period commenced. The clear
legislative intention is to set an averaging period a reasonable time before the
commencement of the period. In this
particular case ActewAGL’s revised
proposal was for a period that had already concluded. Not only could the
requisite 30
days’ notice not be given but, if the AER disagreed with the
proposal, it could not specify a period within the prescribed
time.
- ActewAGL’s
case rests on a construction of the rules that would entitle a distribution
network service provider to renege on
an agreement or to submit a new proposal
after the times set in the clause.
- ActewAGL
submitted that the requirement of 30 days’ notice in paragraph (iv) is for
the benefit of the provider and can therefore
be waived. The Tribunal was of
the same opinion: EnergyAustralia at [312(a)]. The AER argued
otherwise, contending that paragraph (iv) does not confer a right on ActewAGL;
it imposes a constraint
on the AER’s powers. That is true, but it does
not answer ActewAGL’s point. If the constraint is imposed for the benefit
of the network service provider, then, provided observance of the condition is
not a condition precedent to the exercise of statutory
power, it is accepted
that it can be waived: SS Constructions Pty Ltd v Ventura Motors Pty Ltd
[1964] VicRp 32; [1964] VR 229 at 245.
- Nevertheless,
ActewAGL’s construction overlooks the notification period set by paragraph
(ii). That is the requirement that
the AER notify the provider within a
reasonable time prior to the commencement of the period if it does not
agree with its proposal.
- In
my view, the transitional rules do not contemplate that a different proposal for
an averaging period might be put after a period
has been specified and certainly
not after the proposed period has passed.
- An
examination of the purpose of the provision and the historical context in which
it was introduced confirm the interpretation conveyed
by the ordinary meaning of
the text.
- The
following extrinsic materials bear upon this question:
(a) The
AEMC’s Rule Determination, National Electricity Amendment (Economic
Regulation of Transmission Services) Rule 2006 No. 18 (“Rule
Determination”) made on 16 November 2006. The Rule Determination inserted
clause 6A.6.2 (“Transmission Revenue
Rules”) into the NER. The
Transmission Revenue Rules were used as a basis for drafting the transitional
rules. Clause 6.5.2 in the transitional rules is in substantially
the same form as cl 6A.6.2 (a)-(e) of the Transmission Revenue Rules.
(b) The ACCC’s Statement of principles for the regulation of
electricity transmission revenues (“SRP”), including the
Background Paper to the SRP, published on 8 December 2004. In the Rule
Determination, the AEMC
stated that the methodology for estimating the WACC
“was incorporated into the ACCC’s Statement of Regulatory Principles
(SRP) and has been codified in the Revenue Rule through this Review
process”.
- These
materials meet the description of “Rule extrinsic material” in
clause 8(1) where that expression is defined
as:
(a) a draft Rule determination; or
(b) a final Rule determination; or
(c) any document (however described)—
(i) relied on by the AEMC in making a draft Rule determination or final Rule
determination; or
(ii) adopted by the AEMC in making a draft Rule determination or final Rule
determination.
- The
Background Paper to the SRP included the following statement (emphasis
added):
In determining the risk free rate to apply to the WACC calculation it is
theoretically correct to use the on-the-day rate as it fully
reveals the latest
information available.
However, using the on-the-day rate exposes the TNSP [transmission network
service provider] to day-to-day volatility. For this reason,
an averaging
period methodology is used to smooth out the
volatility...
[T]he ACCC considers that ... the ability of TNSPs to game with the length of
period used in calculating the moving average is minimal
because a TNSP has
to specify the averaging period at the time of submitting its application for a
revenue reset and can not [sic] change it
afterwards.
Professor Davis has similarly stated on this
issue:
Provided that the averaging period is it well specified in advance, there
is little risk of ‘gaming’
behaviour...
Therefore, the ACCC considers the period (between 5 to 40 days) used to
calculate the moving average of the bond rate should be left
to the discretion
of the TNSP when making its application. However, the TNSP will not be
allowed to change the averaging period after the application is
lodged.
- This
makes it clear that the intention was that the averaging period would be fixed
at an early stage and, once fixed, not altered.
- ActewAGL
submitted that none of the extrinsic material deals with a situation in which
the AER rejects a proposed averaging period,
specifies a period in lieu and then
decides to amend the period. That is true. But it does not detract from the
conclusion that
the extrinsic materials support a construction of
cl 6.5.2(c) which envisages that the distribution network service
provider’s
proposal for the averaging period be incorporated in the
regulatory proposal and, once agreement is reached with the AER or the AER
has
specified a period, there is no scope for varying the period.
- ActewAGL
argued that other material supported its position. Specifically, it referred to
passages in paragraph 5.5.1 of the Rule
Determination (at 82-83) which emphasise
the importance of taking into account current evidence concerning the accuracy
of parameters
within the WACC calculation. That is also true, but without
qualification it is misleading. The AEMC was referring to the need
for the
regulator to review the methodology and the parameters of the WACC
“periodically”. The reason given was to provide
flexibility and to
give the regulator the discretion to take account of changes in financial market
conditions and developments in
financial theory and practice. But the context
provides no support for ActewAGL’s argument. The context is obvious from
the
next passage (emphasis added):
For this reason the Revenue Rule [cl 6A.6.2(f)-(j) in the case of
determinations concerning the cost of capital for transmission
network service
providers and cl 6.5.4 in the case of distribution network service
providers] gives the AER the discretion to vary
the WACC methodology or
parameters at subsequent five-yearly reviews following the consultation
process in the Rules.
- The
AEMC was not concerned to give the AER the discretion to change its decision
about the appropriate averaging period for a particular
regulatory control
period.
- Accordingly,
the AER’s submission should be upheld. The purpose of the rule was to
lock in an averaging period early in the
consultation process. The rule does
not contemplate a revision of the averaging period where agreement had earlier
been reached
or the AER had specified a period. Once the AER specified a
period, which it did in August 2008, its discretionary power to agree
(or not)
to a provider’s proposal or to specify an alternative period was spent.
As the AER submitted in this proceeding,
the decision it made on the revised
proposal was beyond power and therefore in law no decision at all: Minister
for Immigration and Multicultural Affairs v Bhardwaj [2002] HCA 11; (2002) 209 CLR 597. It
follows that the only decisions open to be challenged are the July/August 2008
decisions.
- I
now turn to consider the application for an extension of
time.
THE APPLICATION FOR AN EXTENSION OF TIME
- The
ADJR Act imposes a 28-day time limit from the date of a decision in which an
aggrieved party may apply for a review: s 11(3)(a).
The Court may,
however, extend the period: s 11(1)(c). Notwithstanding the view I have
taken about the extent of the AER’s
powers, in case I am wrong I intend to
consider whether an extension of time should be granted to challenge all the
decisions, including
the April 2009 decision to reject the revised averaging
period proposal.
The relevant principles
- The
Court’s discretion under s 11 of the ADJR Act is a broad one. There
are no preconditions to be satisfied before it can
be enlivened. Nevertheless,
the discretion is to be exercised judicially and in accordance with the objects
of the statute. Wilcox
J summarised the applicable general principles, which
his Honour drew from the case law, in the frequently cited judgment in Hunter
Valley Developments Pty Limited v Cohen [1984] FCA 176; (1984) 3 FCR 344 at 348-349
(“Hunter Valley Developments”). I do not suggest, however,
that these considerations are exhaustive. Indeed, his Honour was at pains to
point out that they were
not. Those principles are:
(a) There is no
need to show special circumstances but the Court cannot ignore the statutory
period. The starting point is that the
legislature has prescribed a period. An
extension of time will not be granted unless the Court is “positively
satisfied that
it is proper to do so”. Any applicant for an extension
must provide an acceptable explanation for the delay and establish
that it is
“fair and equitable in the circumstances” to extend time.
(b) Any action the applicant has taken apart from the proceedings is relevant
to the question of whether an acceptable explanation
for the delay has been
furnished. A distinction is to be made between the case of a person who, by
non-curial means, has continued
to make the decision-maker aware that she or he
contests the finality of the decision (that she or he has not “rested on
his
[sic] rights”) and a case where the decision-maker was allowed to
believe that the matter was finally concluded. The reasons
for this distinction
are not only the “need for finality in disputes” but also the
“fading from memory” problem
referred to in Wedesweiller v
Cole [1983] FCA 94; (1983) 47 ALR 528.
(c) Any prejudice to the respondent, including any prejudice in defending the
proceedings occasioned by the delay, is a material factor
militating against the
grant of an extension.
(d) Still, the mere absence of prejudice is not enough to justify the grant
of an extension. In this context, public considerations
often intrude. A delay
which may result, if the application is successful, in the unsettling of other
people or of established practices
is likely to prove fatal to the application.
(e) It is proper to take into account the merits of the substantive
application.
(f) Considerations of fairness as between the applicants and other persons
otherwise in a similar position are relevant to the way
in which the discretion
should be exercised. Here, his Honour referred to Wedesweiller again. I
note that in Wedesweiller, at 534, Sheppard J expressed the view that,
but for the fact that there were pending before the Court about 190 similar
applications,
all arising out of similar incidents as those in the case before
him, he would have thought that an application brought almost 12
months after
the expiry of the prescribed time, was too late to be entertained.
(g) Decisions affecting only the immediate parties are to be distinguished
from those involving public administration, where the public
interest may well
dictate refusal of an extension, even after only a short delay.
- I
accept ActewAGL’s submission that “the basal principle guiding the
Court’s discretion is the justice of the case”
or, as Kenny J put it
in Dickson v Whiddett [2001] FCA 585 at [34] the period may be extended
“where the justice of the case requires it”. But each of the
matters to which Wilcox J referred
in Hunter Valley Developments bears on
the question of where the justice of the case lies.
The explanation for the delay
- The
explanation for the delay was provided by Mr Graham. In summary, his evidence
was that ActewAGL had decided against making an
application to the Tribunal but
that, after the success in the Tribunal of the claims by the other network
service providers, it
had opted for non-litigious methods to achieve the same
result and, after those attempts failed, it brought this proceeding.
- Mr
Graham testified that after the AER’s Final Decision he and his team, in
consultation with the General Manager Networks
and the Commercial Manager
Networks, considered applying to the Tribunal. The application had to be made
no later than 15 business
days after the AER’s decision was published:
NEL, s 71D. ActewAGL knew that. The time limit is inflexible. There is
no
provision for an extension. ActewAGL knew that too.
- In
his affidavit Mr Graham gave four reasons for ActewAGL’s decision not to
seek a review of the decision in the Tribunal.
He listed them
as:
(a) the expected high costs of an appeal;
(b) the expectation that the AER would allocate substantial resources to defend
their position in respect of the WACC as it had also
recently conducted an
extensive but separate review on the WACC to apply to all upcoming network
distribution decisions for the next
five years. The approach recommended in that
review to determine the averaging period was the same approach taken by the AER
in determining
ActewAGL’s averaging period and I expected that the AER
would vigorously defend that approach;
(c) the resources of my team were already being fully utilised in relation to a
range of key regulatory matters, including:
(i) preparing the regulatory proposal in respect of ActewAGL’s gas
network, which was due to be submitted to the AER on 30
June 2009;
(ii) preparing the final submission to the AER on the 2009/10 pricing proposal
for the electricity network, which was due to be
submitted to the AER on 21 May
2009;
(iii) responding to a major regulatory review by the ICRC into the ACT retail
electricity transitional franchise tariff to apply
for 2009/10, which was at a
critical phase in May 2009; and
(iv) preparing 2009/10 prices for gas distribution, electricity and gas retail,
water and wastewater prices and Queanbeyan bulk water,
and the accompanying
reports demonstrating compliance with the relevant regulatory requirements;
(d) awareness that the NSW Electricity Distribution Businesses were considering
appeals against the AER’s determination in
relation to the AER’s
decision to withhold agreement to their proposed averaging period, as well as
other parts of the AER’s
determinations affecting them. I entertained a
hope that, in the event that these applications were successful in relation to
the
averaging period, there could be some scope for the AER to amend its
decision in relation to ActewAGL’s averaging period to
ensure consistent
treatment between ActewAGL, the NSW Electricity Distribution Businesses and
Transgrid and Transend, which the AER
had indicated they considered appropriate
in the Final Decision.
- He
then elaborated on the final point. On 18 May 2009, he said, he had a
conversation with the then General Manager Network Regulation
North Branch of
the AER, Mike Buckley. He said that Mr Buckley mentioned a case in which
Transgrid had applied to the AER to correct
a material error and that correction
was then applied to another utility (EnergyAustralia) which had not appealed the
error. He
went on to say (and this evidence was not contradicted) Mr Buckley
had told him that this might be a decision for ActewAGL to investigate
“but noted that a similar outcome would not be automatic”.
- On
19 May 2009 time to apply to the Tribunal for review expired: NEL,
s 71D.
- On
26 May 2009 time to apply for judicial review under the ADJR Act expired: ADJR
Act, s 11.
- In
cross-examination Mr Graham acknowledged that ActewAGL had made a commercial
decision neither to appeal nor to seek any other
form of review of the decision.
The gist of his evidence was that the cost to ActewAGL was too high to justify a
legal challenge,
having regard to the “small probability” of
success, although he professed to be unaware of the mechanism for judicial
review at the time. He said he did not remember whether he sought legal advice
before November 2009.
- On
19 June 2009 the Tribunal granted leave pursuant to s 71B(1) of the NEL to
the other five network service providers to apply for
review of the final
decision. The review provided for in the statute is limited by the terms of
s 71C, but it is certainly wider
than the review provided for under the
ADJR Act and permits a reconsideration of the merits.
- On
1 July 2009 ActewAGL wrote to the AER, first expressing its appreciation for its
“constructive approach” during the
price review process for the
2009-2014 regulatory period and acknowledging that the AER gave
“appropriate consideration to
most aspects” of its proposal. It
then went on, however, to record “one significant concern” with the
decision.
It claimed that it did not believe that the final decision on the
weighted average cost of capital adequately addressed the arguments
in its
submissions and, in particular, adequately took into account the implications of
the GFC and the provisions in the transitional
Rules. The letter, written by
Michael Costello, ActewAGL’s Chief Executive Officer, included this
admonition:
While we did not formally seek leave to appeal the final decision, we noted we
had a very strong case in our deliberations on this
matter. Our decision not to
appeal should not be taken as any form of acceptance or satisfaction with this
outcome.
- Still,
at this stage ActewAGL did nothing to challenge it or to seek by informal means
to have it reversed.
- On
12 November 2009 the Tribunal handed down its decision, varying the AER’s
decision on the averaging period in favour of
all the applicants:
EnergyAustralia. By s 71P(5) of the NEL, the decision of the
Tribunal became the decision of the AER. ActewAGL hoped to secure the benefit
of the
decision, despite not having been a party to it.
- Soon
afterwards ActewAGL sought legal advice from Stephen Skehill, Special Counsel,
Mallesons Stephen Jaques.
- On
25 November 2009 Mr Graham spoke to Mr Buckley about an intended application to
revoke the determination and substitute a new
determination under the existing
rules. Mr Buckley said that, if the AER did not accept a request to amend the
determination under
the existing rules, a further option ActewAGL could consider
to achieve consistency would be to apply to the AEMC for a change to
the NER.
- Mr
Skehill’s legal advice was furnished on 21 December 2009. A copy of it
was in evidence. It related solely to the question
of whether the AER had the
power to amend a determination previously made under the NEL. Mr
Skehill’s advice was that it had
the power to revoke and replace its
previous decision. Somewhat surprisingly, the advice was based on the opinion
that the AER’s
determination was affected by a material error or
deficiency of each of the following kinds and therefore susceptible to
revocation
and substitution under cl 6.13(a) of the transitional rules (an
argument not made on this application):
(1) a clerical
mistake;
(2) an accidental slip or omission;
(3) a miscalculation or
misdescription; and
(4) a defect in form.
- On
23 December 2009 Mr Costello wrote to the AER on behalf of ActewAGL asking that
the AER revoke its determination in relation to
the averaging period and
substitute the revised proposed averaging period and provided it with a copy of
Mr Skehill’s advice.
- On
16 February 2009 Mr Costello sent another letter to the AER making further
submissions in support of its case for a revocation
of the averaging period
decision and the substitution of a new decision accepting its revised averaging
period proposal. It attached
an additional advice from Mr Skehill providing
further reasons in support of the points made in the previous advice and
emphasising
those points.
- On
19 February 2010 the AER wrote to inform ActewAGL that while “there are
sound reasons for applying a consistent WACC”,
its position was that it
did not have the power under cl 6.13(a) of the NER to amend the ACT
distribution determination as ActewAGL
had sought, on the ground that the clause
does not allow the AER to revisit the substance of a decision unaffected by
inadvertent
errors.
- ActewAGL
then sought further legal advice. On 3 March 2010 Mr Graham instructed Mr
Skehill to seek advice from Alan Robertson SC,
a pre-eminent administrative
lawyer. On 15 April 2010 Mr Graham and Mr Skehill conferred with Mr
Robertson. Mr Robertson’s
advice was not in evidence but Mr Graham said
that at this stage ActewAGL decided to “concurrently” explore two
“options”:
to try to persuade the AEMC to change the rules to give
the AER the power to make the changes ActewAGL sought, and also to apply
for
judicial review of the AER’s decision. But the intention to apply for
judicial review (or to explore that option) was
not then flagged to the
AER.
- Mr
Graham further said that he received legal advice from Mr Skehill on 27 April
2010 and in May and June (the details of which were
not disclosed), and
“there was further consideration and refinement of the application for
judicial review by [his] team and
[him], Mallesons Stephen Jaques, counsel and
NERA [presumably Mr Houston]”. Mr Graham also said he attended another
conference
with Mr Robertson on 13 July 2010 and received “further
legal advice” from Mr Robertson through Mr Skehill on 26 July
2010.
Once again, neither Mr Skehill’s nor Mr Robertson’s further
advice found its way into evidence.
- On
11 August 2010 Mr Graham, Mr Costello and Mr Skehill (with Ms Holmes) met with
the new Chairman of the AER and other AER personnel.
At this meeting, and for
the first time, ActewAGL informed the AER that it intended to seek judicial
review of its decision. It
also provided the AER with a draft of the
application. ActewAGL was still pressing for a rule change and, when Mr
Costello told
the AER representatives of its intention, the AER Chairman said
they would prefer to have the matter dealt with by a rule change.
By
14 September 2010 it became clear that there were “very limited
prospects” that the AEMC would accept the proposal
for a rule change. It
was then that Mr Costello instructed Mr Skehill to finalise the application
for judicial review. On 21 September
2010 ActewAGL made a courtesy call to the
AER to advise it of the decision.
The arguments
- ActewAGL
argued that the following considerations favour an extension of
time:
(a) The merits of the case, pointing to the outcome in
EnergyAustralia, which, it argued, showed that the claim has
“substantive strength”;
(b) The fact that ActewAGL protested the making of the decision at the time
it was made;
(c) After the decision in EnergyAustralia it continued, by various
non-curial means, to make clear to the AER that it was contesting the finality
of the averaging period decision
(being the decision on that question made in
the Final Decision) and the AER “cooperatively participated in these
discussions”;
(d) The exercise is of an annual nature and ActewAGL does not seek to adjust
its charges for any past period;
(e) The fact that the effect of a successful challenge will be to put
ActewAGL in the same or an equivalent position to those of the
network providers
who successfully obtained merits review in the Tribunal and will therefore
secure the consistency of treatment
that the AER said was the aim of its
approach and accords with sound principle; and
(f) There is no prejudice.
The merits
- Taking
these matters in order, the first point to make is that when Wilcox J in
Hunter Valley Developments referred to the merits he cited Lucic v
Nolan (1982) 45 ALR 411 (“Lucic”) at 417 and Chapman v
Reilly, unreported, Federal Court of Australia, 9 December 1983 at 6,
where Neaves J also referred to Lucic. What those cases make clear is
that it is inappropriate for this purpose to fully investigate the merits,
although an obvious strength
or weakness in the applicant’s case is a
factor for or against the exercise of the discretion. It seems to me that the
proper
approach is that which French J (as his Honour then was) described in
Seiler v Minister for Immigration, Local Government and Ethnic Affairs
[1994] FCA 878; (1994) 48 FCR 83 at 98:
The question of the merits of a substantive application has to be approached
with some caution in any consideration of a claimed
extension of time. If an
application has no reasonable prospect of success, then the discretion to refuse
an extension on that basis
reduces to a decision to strike it out. To say a
substantive application has a reasonable prospect of success is to say no more
than that there is a finite non-trivial probability that it will succeed. The
statement of its merits is then stochastic. It is
based upon necessarily
incomplete evidence or consideration of the case. It is difficult to imagine
any case which appeared weak
but not hopeless in which it would be proper to
refuse an extension on that account. On the other hand, the stronger the case
appears
to be, the higher may be the probability that an injustice will be done
if an extension is refused. So a strong case may be a positive
factor in
favour of the grant of extension, but an apparently weak case cannot be treated
as a factor weighing against it.
- As
I have already mentioned, ActewAGL argued that this was a strong case
“made manifest” by the outcome of the appeals
in EnergyAustralia.
That brings me to the second point.
- The
decision in EnergyAustralia was based on the application of a different
test and does not speak to the strength of ActewAGL’s application for
judicial review.
The Tribunal proceeded on the basis that, if it was of the
view that the AER unreasonably withheld its agreement, this could amount
to
either an incorrect exercise of the discretion in all the circumstances or the
decision being unreasonable in all the circumstances,
each of which is an
available ground of review in the Tribunal: EnergyAustralia at [69(k)].
It went on to find (at [100]) that in July 2008 the AER had unreasonably
withheld its agreement. The task confronting
this Court on judicial review,
however, is quite different from the task the Tribunal faced. This Court is not
concerned to determine
whether the AER unreasonably withheld agreement to
ActewAGL’s proposals. The Tribunal’s views about the merits of that
decision, or mine for that matter, are irrelevant. While the exercise of the
AER’s discretion is reviewable under the ADJR
Act, the mere fact that it
was exercised incorrectly or unreasonably will not be enough to set a decision
aside. While unreasonableness
is also a ground of judicial review, the ADJR Act
does not authorise the correction of unreasonable decisions, only those where
the
exercise of the discretion was so unreasonable that no reasonable person
could have so exercised it (Wedenesbury unreasonableness, so-called,
after Associated Provincial Picture Houses Ltd v Wednesbury Corporation
[1947] EWCA Civ 1; [1948] 1 KB 223 at 223-234). Cf. Australian Competition and Consumer
Commission (ACCC) v Australian Competition Tribunal ([2006] FCAFC 83; 2006) 152 FCR 33
(“ACCC v Australian Competition Tribunal”) at [176]. The
Tribunal recognised this distinction at [60]-[63] of its decision in
EnergyAustralia.
- Nevertheless,
the decision in EnergyAustralia does show that another tribunal
considered that the AER’s discretion to withhold agreement to the original
proposals of the
network service providers miscarried. On this basis it may
reasonably be supposed that the application with respect to the 2008
decisions
would be unlikely to be futile.
- For
the following reasons I am not, however, persuaded that ActewAGL’s case is
a strong one, such that it should count in favour
of a grant of an extension.
If I am right in the view I have taken about the power of the AER to change its
mind, then this is
an obvious weakness in ActewAGL’s application to set
aside the 2009 decision. Indeed, that circumstance alone would be sufficient
to
deny ActewAGL an extension of time to apply to review it.
- The
grounds of review appear at [53] above. In its submissions, ActewAGL grouped
the grounds into categories of error and I will
deal with them in the same
way.
Grounds 1, 3 and 4: Did the AER misconceive its task?
- ActewAGL
submitted that the AER’s statutory task under cl 6.5.2(c)(2) involved
“focusing reflectively on whether there
was a reasonable basis upon which
it could reject ActewAGL’s original proposed averaging period”. It
submitted that
the AER ignored the correct purpose of its statutory task which,
by its own account, was to generate an unbiased risk-free rate to
derive an
unbiased estimate of the regulated rate of return.
- Dealing
first with the 8 July decision, ActewAGL argued that the AER assumed that
a period as close as possible to the commencement of the regulatory control
period was the optimal period and therefore rejected
the original proposed
averaging period. It argued that the decision did not reveal any consideration
of the merits of ActewAGL’s
proposal or whether the AER’s agreement
would be, or was being withheld on grounds that were capable of being
characterised
as reasonable. It submitted that the letter should have
“identified reasons which were objectively reasonable; which were relevant
to the parties to the regulatory interaction; and which were not based upon
erroneous premises. This in turn directs attention to
the purpose of setting a
rate of return and within that, of establishing the risk-free rate, and of the
broader statutory objectives”.
- I
disagree. The letter informed ActewAGL that it did not agree with its proposal
and provided reasons before nominating an alternative
averaging period. The
reasons are set out at [38] above. They were relevant, not based upon erroneous
premises, and were objectively
reasonable. There was no dispute between the
experts that the CAPM theory “suggests that, ideally, the nominal
risk-free rate
input will be calculated on the day of the final
determination”. The AER believed that applying an averaging period that
is
closely aligned to the date of the final determination provides an unbiased
rate of return that is consistent with the market conditions
at the time of the
final determination. It had support for that view from experts in the field.
Contrary to ActewAGL’s submission,
the letter does show that the AER
considered the merits of ActewAGL’s proposal. That is clear from the
passage cited in [38].
The reasons given in the draft decision confirm that
there was no misunderstanding of the statutory task. At 135 of its draft
report,
the AER stated:
The AER did not agree with the period proposed by [ActewAGL] on the basis that
it considered the proposed dates of the period were
too far removed from the
final determination date and the commencement of the next regulatory control
period. A period that is too
far removed from the final determination date may
not provide the most relevant information. This is consistent with past practice
by the AER and other state regulators, and supported by CAPM
theory.
- Contrary
to ActewAGL’s submissions, the AER did not withhold consent merely because
it preferred another averaging period.
It first found that ActewAGL’s
proposal was inappropriate and then specified an alternative period for
apparently sound reasons.
- I
now turn to the April 2009 decision on the premise that the AER had the power to
vary its decision.
- I
see no justification for the contention that the AER never conducted an analysis
which would have allowed it to assess whether
or not it was reasonable to
withhold agreement to ActewAGL’s proposal. The AER said it considered the
key arguments in the
revised regulatory proposals and the additional material.
It referred to them at some length, analysed them and rejected them.
- ActewAGL
submitted that the AER asked itself the wrong question when it said at 262-263
of the Final Decision:
The NSPs’ key argument in their revised regulatory proposals is one that
suggests an obligation on the AER to move away from
the agreed averaging period
if that period is set in abnormal times. The alleged abnormality affecting the
agreed averaging period
was not manifest at the time of the AER’s July
2008 decision to withhold agreement. The issue therefore is whether the
averaging
periods in the revised regulatory proposals are reasonable compared
with the agreed averaging periods.
- ActewAGL
submitted that if the averaging period ActewAGL proposed was otherwise
appropriate, the AER was not permitted to withhold
consent only on the basis
that it preferred another period. It argued that, in effect, the AER assumed
that the risk-free rate at
a date closer to the start of the regulatory control
period would give a better estimate but that “it should not have made
that
assumption”. Rather, it submitted, “a principled adoption of this
position required examination of the evidence
regarding expected future
rates”. According to ActewAGL the question the AER had to ask itself was
(quoting the Tribunal decision)
whether it had “sufficient reason to
believe that the proposed averaging periods [that is, those proposed by the
distribution
network service providers] were unlikely to produce an unbiased
estimate of CGS rates in the regulatory control period”. But
in its Final
Decision the AER made it plain that its purpose was to set an unbiased risk-free
rate in order to derive an unbiased
estimate of the regulated rate of return
over the next regulatory control period. In my view ActewAGL has approached
the AER’s
reasons in an “over-zealous” way, looking for
inadequacies in the expression of the reasons, and contrary to the High
Court’s directive in Minister for Immigration and Ethnic Affairs v Wu
Shan Liang [1996] HCA 6; (1996) 185 CLR 259.
- The
Tribunal said that the only clear basis on which the AER might reasonably
withhold consent to an averaging period proposed by
a network service provider
was if the period proposed would be likely to generate a rate of return that was
inappropriate, either
too high or too low, having regard to the period in which
it was to be applied. Of course, the Tribunal’s remarks need to
be read
in the context of the review it was conducting; it was not answering the same
questions that are raised here.
- The
extent of the discretionary power to withhold consent is determined by reference
to the scope and purpose of the enactment:
FAI Insurances Ltd v Winneke
[1982] HCA 26; (1982) 151 CLR 342 at 368 per Mason J. The statutory scheme does place some
limits on the AER’s discretion, most notably in the requirements
in
s 16 of the NEL.
- The
AER did not accept that the rules preclude it from choosing a period which it
prefers, so long as it does not do so unreasonably.
-
The
Full Court explained in ACCC v Australian Competition Tribunal at
[178]:
The concept of “unreasonableness” imports want of reason. That is
to say the particular discretion exercised ... is
not justified by reference to
its stated reasons. There may be an error in logic or some discontinuity or non
sequitur in the reasoning.
It may be that the decision has an element of
arbitrariness about it because there is an absence of reason to explain the
discretionary
choices made ... in arriving at its
conclusion.
- I
agree with the Tribunal that consent could not be withheld only on the basis
that the AER had a preference for a different period.
But, in my view, provided
that the decision to withhold consent is not arbitrary, is based on reasonable
grounds and is justified
by reference to the AER’s stated reasons, the AER
discharges its statutory task. Here, the decision to withhold consent was
not
arbitrary, was based on reasonable grounds and is justified by reference to the
AER’s stated reasons. It may be that the
result is that its preferred
position prevails. But that is not necessarily the same
thing.
Grounds 2, 2A and 6: Failing to take into account relevant considerations
- ActewAGL
submitted that the AER failed to act on reliable, up to date and material
information when it made its final decision because
it adopted the decision it
had made some nine months earlier and used that fact as the basis for refusing
to use reliable, up to
date and material information as at the later date.
- ActewAGL
also submitted that the AER failed to take into account the following
considerations:
(a) whether ActewAGL’s original or revised
proposed averaging periods were likely to result in an unbiased risk-free rate,
given
that the equity beta and market risk premium were deemed to be 1.0 and
6.0% respectively;
(b) whether ActewAGL’s original or revised proposed averaging periods
promoted the national electricity objective prescribed
by s 7 of the NEL and the
revenue and pricing principles prescribed by s 7A of the NEL;
(c) the exceptional and anomalous conditions which arose from mid-September
2008 as a result of the global financial crisis; and
(d) any forward looking analysis of whether the period of 20 business days
ending 5 September 2008 would provide a reasonable proxy
for the risk-free rate
that would be expected to apply either on 1 July 2009 or on 1 July in each of
the years 2009-2013.
- This
ground of review is only made out if the AER was bound to take into account one
of these matters. Whether that will be so is
determined by construing the terms
of the NER, as the legislative instrument conferring the discretion. Where the
relevant considerations
are not expressly stated they must be determined by
implication from the subject matter, scope and purpose of the Act. Here,
therefore,
unless that implication can be found in the subject matter, scope and
purpose of the NEL or the NER, the AER cannot be said to have
been bound to
consider it. Moreover, if the factor is one which could not have materially
affected the decision, the Court is not
justified in setting it aside on this
account. The limited role of a court reviewing the exercise of an
administrative discretion
must constantly be borne in mind. See Minister for
Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24
(“Peko-Wallsend”) at 39-40.
Failing to act on reliable, up-to-date information
- It
may be accepted that the AER was obliged to consider the most recent material
available: Peko-Wallsend at 45.
- But
I am not persuaded that the AER failed to discharge its obligation. In the
first place, it discussed at length the reports from
the four consultants
submitted to it on behalf of the service providers. See the Final Decision at
93-97 and 262-274. It also considered
the statement made by the RBA on monetary
policy released in February 2009 and the RBA’s cash rate announcement on 7
April
2009, only a short time before publication.
Failing to consider whether ActewAGL’s original or revised proposed
averaging periods were likely to result in an unbiased
risk-free rate
- Neither
do I accept that the AER did not consider whether ActewAGL’s proposals
would set an unbiased risk-free rate (assuming,
in ActewAGL’s favour that
it was bound to do so). It asserted at 263 of the Final Decision that setting
the averaging period
close to the start of the next regulatory control period
was designed to achieve that end. Implicit in that assertion is the proposition
that ActewAGL’s proposal to set the averaging period so early would
not.
Failing to consider whether ActewAGL’s original or revised proposed
averaging periods promoted the national electricity objective
and the revenue
and pricing principles
- The
AER was certainly bound to have regard to the national electricity objective and
the revenue and pricing principles but I do
not accept that it did not. At I.8
of Appendix I its Final Decision, it expressly adverted to the NEL objective of
promoting efficient
investment. It said that the specified period was
consistent with that objective. It also expressly adverted to the revenue and
pricing principles. It observed (at 272) that:
[R]evenue and pricing principles in the NEL state that an NSP [network service
provider] should be provided with a reasonable opportunity
to recover at least
the efficient costs incurred in providing direct control services and complying
with a regulatory obligation
or making a regulatory
payment.
- This
principle was the only revenue and pricing principle upon which ActewAGL relied.
- The
AER then referred to the submission made by the network service providers that
it should have regard to whether the selection
of the averaging period in
determining the rate of return provides a reasonable opportunity to recover at
least their efficient costs.
It stated (emphasis
added):
[T]he determined WACC is consistent with the NER and as intended moves
commensurate with interest rate changes in the Australian
economy which is also
consistent with the NEL objective of promoting efficient investment. The fact
that the risk-free rate is at (or close to) historical lows does not by itself
mean that the resulting WACC does not provide
a reasonable opportunity to
recover the efficient costs of capital.
The AER notes that the WACC parameters are based on benchmarks and are part of
the incentive framework. Therefore, the NSPs have
an opportunity to achieve a
higher rate of return by better managing their operating
costs.
- As
the fact that the risk-free rate was at (or close to) historical lows was the
reason behind ActewAGL’s revised proposal
and as the only revenue and
pricing principle that was apparently relevant was the one to which the AER
referred, it would be wrong
to conclude that the AER did not consider whether
the proposal promoted the NEL objective and the revenue and pricing principles.
Failing to take into account the exceptional and anomalous conditions which
arose from mid-September 2008 as a result of the global
financial crisis
- Contrary
to ActewAGL’s submission, there is no doubt that the AER considered the
“exceptional and anomalous conditions”
resulting from the GFC.
Chapter I.3 of Appendix I of the Final Decision is entitled “Historically
low nominal risk-free rate”.
The AER’s consideration commenced with
these observations:
CEG stated that the weight of the regulatory precedent from overseas and
Australia supports a view that if the most recent averaging
period overlaps with
abnormal levels of the risk-free rate or periods of economic crisis then such a
period should not be adopted.
The AER notes that this is a continuation of the argument for a variable MRP
given the alleged abnormally low CGS yields. However,
given the dramatic
changes in circumstances within the economic environment the AER has considered
whether in fact the agreed averaging
periods will result in an unreliable
estimate of the risk-free rate such that it no longer reflects a reasonable
forward looking
estimate.
- The
AER concluded, however, that the legislative intent was that the rate should
vary with general economic conditions. It based
that view on the degree of
prescription in the terms of cl 6.5.2, which fixes a proxy for the risk-free
rate (the yield from Commonwealth
Government Securities) and the maturity
period, which requires the observed rates to be averaged and defines the debt
risk premium
in terms of a margin between the CGS yield and a benchmark
corporate bond with a credit rating of BBB+. It also noted, however,
that the
specified averaging periods “do not exclude the downward movement of the
CGS yields commensurate with an easing in
monetary policy and a softening in
economic growth”. This is another way of saying that the AER did take
into account the
impact of the GFC. In other words, although it did not agree
to vary the averaging periods to mitigate the effects of the GFC, it
did have
regard to them.
Failing to undertake a forward looking analysis
- The
final matter upon which ActewAGL relied for this ground of review was an alleged
failure to undertake a “forward looking
analysis” of whether the
period ActewAGL proposed in its revised proposal would provide a reasonable
proxy for the risk-free
rate that would be expected to apply either on 1 July
2009 or on 1 July in each of the years of the regulatory period.
- ActewAGL
submitted that it was required to have regard to forward interest rates because
of what the Tribunal said in EnergyAustralia at
[90]:
Rather than assume that the rate at a closer date would give a better estimate,
the AER should have examined the evidence regarding
expected future rates. Such
evidence of forward interest rates, ie, rates that will apply at some future
time for a prospective period,
is available from market data. Comparisons could
be made between rates expected to prevail during the averaging period proposed
by
the NSP and rates expected at later periods. But it follows from the
Tribunal’s reasoning that it would be insufficient and
inappropriate to
only compare with rates expected to prevail close to the time of the final
determination.
- I
am not concerned with whether this conclusion is right or wrong. The threshold
question is whether or not the AER was bound by
some implication in the subject
matter, scope and purpose of the relevant legislation to use forward interest
rates.
- Expert
evidence was given on the utility and benefits of using forward (or forward
looking) rates. The experts agreed that economic
theory states that the
required rate of return to be used in valuing an investment decision is the
forward looking rate estimated
as at the date of the decision. In this context,
they said, the relevant required rate of return is the forward looking rate
estimated
“as at the commencement of the regulatory period”. The
experts also agreed that forward looking risk-free rates can
be measured with a
high degree of precision. Nevertheless, the evidence from Dr Lally was that
forward interest rates have not been
used by any Australian regulator to guide
the selection of an averaging period for the risk-free rate.
Mr Houston did not dispute this. There was also evidence from both
experts that forward interest rates are not satisfactory predictors
of future
on-the-day rates. Mr Houston made it plain that he was not advocating that a
regulator should look at forward rates when
making the averaging period
decision. His point was that if the AER was looking to set an unbiased
risk-free rate, as it said it
was, then it could only do so by examining forward
rates. In his oral evidence Dr Lally signified his agreement. Whether
or not the criticism of the AER’s decision is valid, I very
much doubt
that the AER is bound by the statutory scheme to deploy forward rates to make
the averaging period decision.
- Moreover,
it is also doubtful whether expert evidence on this question is admissible. The
authorities have limited the receipt of
expert evidence on an application for
judicial review to the explanation of technical meanings or trade usage and
where the ground
of review is Wednesbury unreasonableness. The AER
sought an order pursuant to s 136 of the Evidence Act 1995 (Cth)
limiting the use to which the expert evidence could be put to these two matters.
In my view, it would be appropriate to make
that order. In the result, the
evidence concerning the need to consider forward interest rates could only bear
on the Wednesbury unreasonableness ground of
review.
Ground 5: The AER’s treatment of regulatory precedent
- By
ground 5 ActewAGL contends that the AER exercised its discretion by following a
rule or policy without regard to the merits of
the case. That rule or policy
was that the averaging period to be used in calculating the nominal risk-free
rate should always be
the period as close as practicable to the commencement of
the regulatory control period. ActewAGL submitted that the AER did not
consider
whether it was reasonable to adopt that policy having regard to the
characteristics of that period compared with the characteristics
of the period
ActewAGL proposed.
- Yet,
the AER stated (in a passage ActewAGL criticised) that “the issue ... is
whether the averaging periods in the revised
regulatory proposals are reasonable
compared with the agreed [i.e. specified] averaging periods”. It noted
(at 264) that the
arguments the network service providers put forward regarding
an insufficient return on equity were based on the view that the MRP
of 6% in
the NER (based on an historical average) was out of line with the current
variations in the MRP. It also noted that the
argument the network providers
put (and which was supported by Mr Houston’s evidence in this proceeding)
was that the risk-free
rate should be adjusted to take into account the
variations in the MRP, since the MRP was fixed by the NER. The AER rejected the
argument, not because it was blindly adhering to a rule or policy but for
multiple reasons explained in the Final Decision at 264-265.
It suffices to
refer to one: adjusting the risk-free rate to make up for a higher MRP was an
attempt to circumvent the legislation
and would undermine the intended certainty
provided under the regulatory regime.
- It
is true that the AER was concerned from the outset to use an averaging period
“as close to the start of the next regulatory
control period as
practically possible”. This gives every appearance of following a policy
decision. Nevertheless, as the
authorities indicate, there are good reasons for
adopting a policy. It can, for example, focus attention on the purpose of the
discretion
and promote consistency in decision-making. Adopting a policy is
therefore permissible, provided that it is not used to improperly
fetter the
exercise of the discretion, for example, by precluding consideration of relevant
arguments that might reasonably be put
in a particular case where they conflict
with the policy and provided that the policy is consistent with the statute
which confers
the power. See Re Drake and Minister for Immigration and
Ethnic Affairs (No. 2) (1979) 2 ALD 634 (“Drake”) at 640;
Neat Domestic Trading Ply Ltd v AWB Ltd [2003] HCA 35; (2003) 216 CLR 277 at 289.
- The
AER’s approach is consistent with the statute under which the relevant
power is conferred. Clause 6.5.2 of the transitional
rules requires the use of
the Capital Asset Pricing Model to determine the return on equity. The experts
in this case agreed that
it accorded with the theory of the Capital Asset
Pricing Model to select a risk-free rate (and therefore an averaging period)
“as
close to the start of the next regulatory control period as
practically possible”. Assuming that the AER’s approach
was to
apply a policy, ActewAGL put forward reasons why the policy should not apply to
it and the AER considered what it had to say
but dismissed its arguments. In
the circumstances I do not believe it can be said that the AER was so wedded to
a policy that it
“shut its ears” to ActewAGL’s proposal
(British Oxygen Co v Board of Trade [1970] UKHL 4; [1971] AC 610 at 625).
Ground 8: Wednesbury unreasonableness
- This
brings me to the final ground of review.
- Not
every unreasonable decision will justify review under the Act. The Full Court
in Zizza v Federal Commissioner of Taxation (1999) 99 ATC 4711 noted at
[15] that “the Wednesbury principle”, which is incorporated
into the ADJR Act, “will usually be concerned with decisions lacking any
logical foundation”.
This decision is not of that kind.
- ActewAGL’s
argument was threefold. The first was that the AER could withhold agreement to
the period proposed by ActewAGL
only if it were satisfied that it was not
unreasonable to do so. For that purpose, it submitted, the AER would have
required, but
did not have, access to a forward looking analysis of whether the
originally proposed period would provide a reasonable proxy for
the risk-free
rate that would be expected to apply either on 1 July 2009 or on 1 July in each
of the years between 2009 and 2013
inclusive.
- The
AER decided that it should set the averaging period close to the start of the
forthcoming regulatory control period and that
it was not unreasonable not to
depart from that position in abnormal times. I do not think that, in so doing,
the AER could be said
to have exercised its discretion in a way that was so
unreasonable no reasonable decision-maker would have done the same. In
circumstances
where forward interest rates have never been used in this country
for this purpose it seems to me to be difficult to come to such
a conclusion.
Indeed, the AER’s position was endorsed by Dr Lally and Mr Houston agreed
it was consistent with economic theory.
Mr Houston departed from Dr
Lally’s position only because it was his view that the theory was
inapplicable where the legislation
set some, but not all, of the parameters in
the equation.
- The
second aspect of ActewAGL’s argument is that the AER had regard to yields
for bonds of different maturities during the
June 2008 period in the original
proposal, even though ActewAGL’s revised proposed averaging period was the
period August-September
2008 and the period the AER favoured was in February
2009. It seems to me, however, that the argument proceeds on a false
assumption.
The AER did not rely on yields during the June 2008 period. It
certainly referred to them but in a different context and for a
different
reason. Its purpose was made clear in the detailed analysis in the appendix.
It was to illustrate a point to answer
one of the arguments put by CEG on behalf
of the network service providers. The point it was making was that setting the
risk-free
rate based on an averaging period at an early time in the regulatory
process would lead to “systematic ex ante overcompensation
of firms
relative to the efficient cost of capital and would be inconsistent with the
forward looking nature of CAPM” and so
would not result in an unbiased
risk-free rate. Even if my construction of the reasons is wrong and the proper
interpretation is
that the AER did have regard to the June 2008 yields in
deciding to reject the revised averaging proposal, I do not think that it
could
be said that this consideration materially affected the AER’s
decision.
- The
third aspect of ActewAGL’s argument is that it was central to the
AER’s conclusion that the regulatory control period
was a single period of
five years, rather than five consecutive one year periods. ActewAGL repeated
its contention that this was
a misunderstanding of the statutory scheme and an
error of law. ActewAGL did not identify any particular part of the reasoning in
either of the AER’s decisions to support its contention, nor why the
alleged misconstruction would make the decision so unreasonable
as to fall
within the terms of s 5(2)(g) of the ADJR Act.
ActewAGL’s protests
- ActewAGL’s
second and third submissions in support of its application for an extension of
time were that it protested the decision
when it was made and continued to do so
thereafter. ActewAGL relied on the last sentence of the following passage in
Seiler at 96:
The exercise of the discretion to extend time, for which s11(1)(c) provides,
must be informed by the purposes served by the statutory
limitation and
associated dispensing power. The limitation is directed to achieving certainty
and finality in administrative decision-making.
In the ordinary course, where a
reviewable decision is taken, and the review procedure is not instituted within
the prescribed period,
the decision-maker is entitled to proceed on the basis
that the decision stands and will not be called into question by way of judicial
review. Finality and certainty are not ends in themselves, but means to the end
of efficient administration. If the relevant decision-maker
or others act upon a
decision after the prescribed period expires then the objective of efficient
administration may be compromised
if the decision can be challenged and set
aside after that expiry. Time and resources may have been expended to no effect.
Where
it is clear that an applicant for review of an administrative decision
has, at all times, pursued the reversal of that decision administratively
then
the statutory purpose is less likely to be jeopardised by a liberal approach to
the grant of an extension of time.
- Here,
however, ActewAGL did not at all times pursue the reversal of the decisions
administratively. Nor did it do so when they were
made. In the case of the
2008 decisions, no protest was offered until, at the earliest, the time the
application was filed in this
Court, and more accurately, ActewAGL’s
written submissions were served in February 2011.
- Furthermore,
there is no suggestion in the correspondence between the parties that before
that date it was ever ActewAGL’s
position that it was unreasonable for the
AER to reject the June 2008 dates ActewAGL had originally proposed and to
specify dates
in February 2009. The letter the AER sent ActewAGL on 8 July
2008, which contained the first decision ActewAGL now wishes to challenge,
was
met by Mr Costello’s letter of 14 August 2008, which proposed a new
averaging period within the parameters proposed by
the AER. It is true that in
that letter ActewAGL reiterated all the matters raised in its original proposal
and asserted its belief
that the AER had not “effectively addressed”
them. Nevertheless, it also acknowledged that “regulatory precedent
and
financial theory are important factors in the choice of averaging period which
might on balance influence the AER’s position”.
In my view it is
fair to describe ActewAGL’s position at this time as grudging acceptance
of the AER’s decision, rather
than opposition to it. Up until (at the
earliest) this proceeding was brought, ActewAGL’s grievance was with the
AER’s
decision in April 2009 to withhold agreement to the revised
averaging period proposal.
- The
first time ActewAGL raised a concern about the Final Decision was on 1 July
2009, more than two months after it was made and
more than five weeks after the
time for any review (both merits and judicial) had expired. It is true that on
18 May 2009 Mr Graham
spoke to Mr Buckley. I have referred to the
substance of the conversation at [93] above. The evidence was sparse. Whatever
was
said before or after they spoke is unknown. No evidence was given that, at
that point in time, ActewAGL told the AER that it did
not agree with the
decision or that it wanted the AER to reverse it. There is nothing in this
evidence to suggest that ActewAGL
informed Mr Buckley that it did not accept the
averaging period decision or even that the concern he had was with that
particular
decision.
- In
the letter to the AER of 1 July 2009 ActewAGL informed the AER that it had
decided not to seek leave to appeal. I acknowledge
that in the same letter
ActewAGL emphasised that the decision not to appeal “should not be taken
as any form of acceptance
of satisfaction with this outcome”. But it did
not indicate that it had any intention of challenging it or even that it would
like the AER to review it. In those circumstances, the AER was entitled to
conclude that the matter was finalised.
- It
was not until 25 November 2009 – seven months after the Final Decision was
published – that ActewAGL next contacted
the AER. The first notice the
AER received that ActewAGL had any intention of seeking judicial review was on
11 August 2010, almost
16 months after the Final Decision. Although it
commenced its investigation into the possibility of judicial review in March
2010,
ActewAGL did not disclose its thinking to the AER. No explanation was
provided for why it took five months from the time of the
conference with senior
counsel to file the application. It took nearly three months after the initial
conference, and two and a
half months after the first legal advice was received,
to make an internal request for funding “for a possible application
to the
Federal Court”. After so much time had passed since the decisions under
review were made, this rather leisurely approach
to the filing of an application
counts against ActewAGL.
ActewAGL does not seek to adjust its charges for any past period
- The
fact that ActewAGL does not seek to adjust its charges for any past period is
relevant to the exercise of the Court’s discretion
because it reduces the
possible impact on consumers and I take that into account in ActewAGL’s
favour.
The question of consistency
- The
fifth point ActewAGL makes is that if it succeeds in this challenge it would put
it in the same position as the other network
providers who won in the Tribunal.
ActewAGL noted that the effect of s 71P(5) of the NEL is that a decision of
the Tribunal is a
decision of the AER. ActewAGL was critical of the AER for
making submissions contrary to those findings and for departing from the
aim of
consistency of treatment, contrary to its stated aim and legal principle. I
regard these criticisms as rhetorical flourishes.
No ground of review is
brought to support them, although ActewAGL referred to Sunshine Coast
Broadcasters Ltd v Duncan (1988) 83 ALR 121, where the decision under review
was successfully challenged as an abuse of power under s 5(2)(j) of the
ADJR Act. In that case
the decision-maker had competing applications before him
in respect of the same area, applied a guideline against one and not another
without any stated or rational justification for doing so. This is not such a
case. It is clear from the Final Decision that the
AER was concerned to treat
the various network service providers consistently. Indeed, ActewAGL
acknowledges as much.
- I
was for some time attracted to this argument but, as the AER pointed out, there
are two difficulties with it. First, s 71P(5)
fixes the AER with the
Tribunal’s decision, not its reasoning. Secondly, the inconsistency was
not of the AER’s making.
It was the inevitable outcome of
ActewAGL’s considered decision not to take the same course as the other
network service providers
and apply for merits review in the Tribunal.
The question of prejudice
- The
final point ActewAGL makes is that there is no prejudice. To the contrary, the
AER submitted that there were two species of
prejudice: prejudice to it and
prejudice to third parties. The prejudice to the AER was put in the following
way. The AER devoted
significant resources to defending the proceedings in the
Tribunal, which took two weeks to be heard, involved eight parties and
the AER
retained four counsel. If ActewAGL had joined those proceedings in the
Tribunal, which provided an adequate vehicle to agitate
the issues the subject
of this proceeding, the present application would have been unnecessary. This
application also involves the
AER incurring significant expenses and devoting
its own internal resources. Accordingly, ActewAGL’s failure to join the
proceedings
in the Tribunal has meant that it is now necessary to revisit some
of those issues in this Court. The time and expense incurred
by the AER in
defending these proceedings is a prejudice that would not have been suffered if
ActewAGL had joined the Tribunal proceedings.
- In
response to a query from the Court, ActewAGL offered to pay the AER’s
costs of this application on a party and party basis.
That would not eliminate
the prejudice to the AER but it certainly reduces its significance.
- I
turn now to consider the impact of a successful application on third parties.
- The
parties agreed that the 2011/12 period would be unaffected by any decision of
the Court made after ActewAGL submitted its pricing
proposal for that period,
due on 30 April 2011. In that case, ActewAGL would be limited to the last two
years of the 2009-2014 regulatory
period. It was also agreed that in 2013/14
the average residential customer in the ACT would pay an additional sum of
$55.55 in
the penultimate year and $62.21 in the last year, assuming the
September 2008 averaging period were applied (ActewAGL’s revised
proposal), or $71.39 and $117.30 respectively, assuming the June 2008 averaging
period were used (ActewAGL’s original proposal).
Thus, the figures range
from just over $1 per week to $2.25 per week.
- ActewAGL
played down the prejudice to the consumer, arguing that these sums were minimal.
Whilst that is true for many consumers,
the impact of any price increase for
social security beneficiaries (for whom every dollar counts) should not be
underestimated.
There are some additional points to be made. First, this is
the figure for the average residential consumer. It follows that some
residential consumers would have to bear a larger burden. How many is unknown.
Then there is the absence of any evidence of the
impact on business of a change
in the averaging period. It is reasonable to infer that the additional costs at
least for some businesses
would be significantly greater. Furthermore, there is
no evidence to indicate that ActewAGL warned its customers or consumers of
the
possibility of a price rise. As the AER submitted, the fact that any price rise
will be unexpected is itself a form of prejudice.
The NER obliges a
distribution network service provider to maintain on its website the classes of
customer subject to a particular
tariff or tariffs and the constituent elements
of each tariff, together with a statement of expected price trends to be updated
for
each regulatory year, indicating how it expects prices to change over the
regulatory control period and the reasons for the expected
changes:
cl 6.18.9(a). The provider is required to post the information for a
particular regulatory year on its website within 20
business days before its
commencement where practicable or as soon as practicable thereafter: cl
6.18.9(b). The plain intention
is that customers be given sufficient notice of
price increases. There is at least the possibility, as the AER submitted, that
some
customers will have budgeted, and perhaps even made business and investment
decisions, upon the basis of pricing expected under the
Final Decision. An
unexpected rise in the price of electricity may also have an impact on other
budgetary decisions.
- ActewAGL
also argued that if ActewAGL succeeded that would “tend to equalise the
position vis-à-vis New South Wales
consumers and ACT consumers”.
Frankly, I doubt that this is a relevant consideration. Whether that was a just
outcome might
depend at least in part on whether electricity costs in the ACT
and New South Wales were ever equal and whether the cost of living
in the ACT
and New South Wales is comparable, about which there is no
evidence.
An acceptable explanation for the delay?
- The
AER submitted that ActewAGL had provided no acceptable explanation for the
delay, pointing in its written submissions to the
absence of any explanation in
the affidavit evidence of the failure to seek judicial review for so long.
- It
might be said that an explanation emerged during Mr Graham’s oral evidence
when, under cross-examination, he said he was
unaware of that option. But Mr
Graham is not ActewAGL. Mr Graham did not say that ActewAGL had not received
legal advice before
the Tribunal’s decision was published. He said he did
not remember whether it had. Even if Mr Graham’s ignorance can
be sheeted
home to ActewAGL, by February 2010 ActewAGL knew about the availability of
judicial review and offered no explanation
for failing to alert the AER for six
months that it was considering it. I accept that at the same time that it was
exploring that
option it was also pressing the
AEMC for a change to the rules
but there is no reason why it could not have informed ActewAGL of its fallback
position. Certainly
none was proffered in evidence. In sum, there were
significant gaps in ActewAGL’s explanation. I appreciate that it is not
a
precondition for success that an applicant provides an acceptable explanation,
let alone a full one: Comcare v A’Hearn [1993] FCA 498; (1993) 45 FCR 441 at 444.
But it is a factor to be taken into account in the exercise of the Court’s
discretion.
Interpreting s 11 in accordance with the overarching purpose
- Section
s 37M of the Federal Court of Australia Act 1976 (Cth) (“the
FCA Act”) declares that the overarching purpose of the Federal Court Rules
and any other provision made by or under the FCA Act “or any other Act
with respect to the practice and procedure of the Court”
is to facilitate
the just resolution of disputes “according to law” and “as
quickly, inexpensively and efficiently
as possible”.
- The
AER argued that s 11 of the ADJR Act must be interpreted and applied in a
way that best promotes the “overarching purpose”,
which includes the
objective of the disposal of all proceedings in a timely manner. The AER
submitted that it is inconsistent with
this objective to grant an extension of
time to bring proceedings two years after the prescribed period expired and this
is a further
reason to refuse the application for an extension of time.
- It
is quite clear that the effect of s 37M(3) and (4) of the FCA Act is that
the power to extend time pursuant to s 11(1) of the
ADJR Act (and also I
might add the discretion conferred by s 10 of that Act) must be interpreted
and applied in the way that best
promotes the overarching purpose. Section
11(1) of the ADJR Act is a provision with respect to the practice and procedure
of the
Court. It prescribes the manner in which an application to the Court
under that Act must be made, what should be contained in that
application, where
the application is to be lodged, and the time within which to lodge it.
Undoubtedly, the overarching purpose
includes the disposal of all proceedings in
a timely manner. That is a relevant consideration but it is not the only
relevant consideration.
Subsection (2) provides (emphasis
added):
Without limiting the generality of subsection (1), the overarching purpose
includes the following objectives:
(a) the just determination of all proceedings before the Court;
(b) the efficient use of the judicial and administrative resources available for
the purposes of the Court;
(c) the efficient disposal of the Court’s overall caseload;
(d) the disposal of all proceedings in a timely manner;
(e) the resolution of disputes at a cost that is proportionate to the importance
and complexity of the matters in dispute.
- Nevertheless,
I do not think that extending the time within which to file the application
would offend against this particular objective.
“Proceeding” is
defined in s 3 of the FCA Act to mean “a proceeding in a
court...” The relevant delay occurred
before the application was filed.
Before the application was filed there was no proceeding. It might be thought
that to extend
the time in this case would not best promote the efficient use of
the judicial and administrative resources available for the purposes
of the
Court or the efficient disposal of the Court’s overall caseload. But no
submissions were directed to these questions
and I therefore refrain from
reaching any conclusions about them.
- Quite
apart from s 37M, however, the time limits imposed under s 71D for
applications to be made to the Tribunal (15 business days)
and under
s 71Q(1) for the Tribunal to endeavour to deliver its decision (within
three months after leave is granted) evince a clear
legislative intention that
electricity price determinations should be finalised as quickly as possible.
This legislative intention
weighs heavily against ActewAGL where, as here, the
delay is considerable.
- What
is more, the delay was not brought about by ignorance on ActewAGL’s part.
ActewAGL made a calculated decision not to
mount a legal challenge when it had
the opportunity to do so. The evidence is opaque about whether it sought legal
advice before
deciding not to appeal to the Tribunal, but it sought and obtained
legal advice shortly after the Tribunal decision was published
and yet it did
not file the application until ten months later.
- ActewAGL
noted that comparable or longer delays have been excused in other cases. It
relied, in particular, on the decision in Aerolineas Argentinas v Federal
Airports Corporation (1995) 63 FCR 100 (“Aerolineas
Argentinas”) (which was not disturbed on appeal: Federal Airports
Corporation v Aerolineas Argentinas [1997] FCA 723; (1997) 76 FCR 582. There, Beazley J was
prepared to hear an application for review of a decision which was not
challenged until two years and two months
after it was made. In that case the
Federal Airports Corporation made a determination in June 1991 to place an
impost on the operators
of commercial passenger airlines using various
Australian airports in order to fund the provision of counter-terrorist services
at
those airports. The airlines had paid the charges the Corporation had
imposed (over $24 million) but, they argued, had made their
disagreement with
the decisions known to the Corporation. Thirty-eight commercial airlines
instituted proceedings in the NSW Supreme
Court for declaratory relief and for
an order that the Corporation repay the monies they had paid. Those proceedings
were cross-vested
to this Court because the Corporation’s determination
was an administrative decision made under an enactment and s 9 of the
ADJR Act
deprived the Supreme Court of jurisdiction to hear it.
- Although
the airlines opposed the changes, the respondent submitted that the obligation
to pay was not disputed in any way until
August 1993, when the legal challenge
was brought. The airlines claimed that they did not appreciate they had a legal
means of challenging
the decision until December 1992, which was not confirmed
by counsel until the following year. The misconception in the Supreme
Court
proceedings was that the determination was legislative, not administrative, in
character.
- I
should point out that Aerolineas Argentinas was not concerned with the
exercise of the discretion under s 11(1) to extend the period prescribed in
s 11(3), but with the power
of the Court under s 11(4)(c) of the ADJR
Act to refuse to entertain the application where no period is prescribed if it
is of the
opinion that the application was not made within a reasonable time
after the decision was made. Here, however, ActewAGL’s
application was
clearly outside the 28-day limitation period in s 11(3). Nevertheless,
there is obviously some overlap in the relevant
principles.
- Even
so, Aerolineas Argentinas is distinguishable on the facts. Whilst the
extent of the delay is comparable, there are other circumstances that are not.
Her
Honour emphasised that the airlines commenced recovery proceedings two years
into a six-year limitation period, which time, she observed,
“could not be
considered unreasonable in respect of those proceedings”. Here, ActewAGL
did not commence any proceedings
within a statutory limitation period. The
first time it communicated an intention to launch any legal challenge was more
than one
year and two months outside the limitation period in the ADJR Act. In
Aerolineas Argentinas, her Honour observed that the question of whether
the airlines were entitled to take those proceedings without having challenged
the
decisions of the Corporation in administrative law proceedings, was not free
of legal difficulty. Here, the legislation is abundantly
clear, ActewAGL knew
it was entitled to take proceedings in the Tribunal, was aware of the time limit
and, for commercial reasons,
chose not to mount a legal challenge. Her Honour
noted that it was a serious matter for a government authority to retain a tax or
charge that had been wrongly or invalidly extracted. We are not in this kind of
territory in the present case.
- The
Full Court on the appeal referred to the unique features of the case. At 602
Lehane J, with whom Beaumont and Whitlam JJ agreed,
remarked:
But a decision as to what is reasonable in a particular case must, of course, be
made having regard to its peculiar circumstances.
Periods found reasonable in
other cases offer useful and authoritative guidance, but do not determine the
way in which the discretion
is to be exercised in relation to different facts.
This was not, after all, a relatively simple case (as are a number of the
reported
cases in this area) involving a decision made by a governmental
authority in relation to particular affairs of a particular individual.
It was a
decision of general application, the subject of substantial controversy,
affecting the interests of a large (and no doubt
theoretically unlimited) number
of substantial corporations. There are, after all, 38 respondents to this
application. The questions
involved are by no means easy. It may be expected
that what is reasonable in a case such as the present will involve
considerations
rather different from those with which most of the reported cases
have been concerned.
- At
most, then, one could say that the decision in Aerolineas Argentinas
demonstrates that a lengthy delay will not necessarily disqualify an otherwise
worthy applicant from applying for judicial review.
Conclusion
- I
have carefully considered the various competing factors. On balance, I am not
satisfied that it is proper to grant ActewAGL an
extension of time. I am not
persuaded that the justice of the case warrants accepting the application
outside the prescribed period.
As I have already indicated, the delay in this
case is substantial. It was not caused by factors outside ActewAGL’s
control.
At the time the decisions were made ActewAGL was in possession of all
the relevant information to enable a challenge to be brought.
For the reasons
given above, its explanation for the delay is incomplete and to that extent
unsatisfactory. There is some evidence
of prejudice. This is not a case where
only the immediate interests of the parties are affected. That is an important
consideration.
As Wilcox J said in Hunter Valley Developments at
351-352:
The adequacy of an explanation for delay is intimately related to the nature of
the case. The distinction drawn in Wedesweiller between a case which is
merely inter-parties and a case involving elements of public interest in
relation to other people, practices
or the need for finality is here relevant.
The point goes beyond absence of prejudice. An applicant concerned to challenge
a decision
which has implications for other people or for day to day public
administration may properly be regarded as being under a heavier
duty to act
expeditiously than is an applicant who is aware that his case has no such
implications.
- The
system of regulating electricity prices relies on timely decision-making in the
public interest. The time limit for applications
to the Tribunal is short and
there is a statutory exhortation to the Tribunal to deliver its decisions
promptly. It flies in the
face of the legislative scheme to permit a collateral
attack on the regulator’s decisions after so much time has passed. This
is not a case of an aggrieved party who, from the outset, contested the
decisions (Hunter Valley Developments) or who, at all times, pursued
their reversal administratively (Seiler). Rather, it is a case where
– months after the dispute was over – the disaffected party tried to
resuscitate it. In
the case of the 2008 decisions, ActewAGL made no attempt to
have them reversed at any time before the commencement of this proceeding.
ActewAGL first sought the reversal of the 2009 decision seven months after the
decision was made. Until that time it led the AER
to believe that –
unlike the other network service providers – it was prepared to accept,
acquiesce in, or submit to
the AER’s decisions. In the circumstances the
AER was entitled to proceed on the basis that the dispute was finally concluded.
Whilst consistency of decision-making is important, the inconsistency in this
case was not brought about by the conduct of the AER,
but by the calculated
decision of ActewAGL not to join the other network service providers in
challenging the decisions in the Tribunal.
That forensic choice always carried
with it a risk that the other providers would prevail and ActewAGL, alone of the
affected parties,
would have to wear the AER’s determination. It is a
risk of which ActewAGL was well aware.
DISCRETION TO REFUSE TO GRANT THE APPLICATION
- There
is an additional consideration. Section 10(1)(a) of the ADJR Act provides that
the right of an aggrieved person to seek a
review of a decision is in addition
to any other rights that person may enjoy. However, s 10(2)(b) of the ADJR
Act gives the Court
a discretion to refuse to grant an application where other
remedies are available. Section 10(2)(b)(ii) provides
that:
the Federal Court ... may, in its discretion, refuse to grant an application ...
for the reason that adequate provision is made by
any law other than this Act
under which the applicant is entitled to seek a review by the court, by another
court, or by another
tribunal, authority or person, of that decision, conduct or
failure.
- “Review”
is defined in subsection (3) to include “a review by way of
reconsideration, re-hearing, appeal, the grant
of an injunction or of a
prerogative or statutory writ or the making of a declaratory or other
order”.
- As
Northrop J observed in Edelsten v Minister for Health (1994)
58 FCR 419 (“Edelsten”) at 421-422, on one view,
the discretion conferred by s 10(2)(b)(ii) should be exercised only after
the applicant has otherwise
made out its case. But there is ample authority for
the proposition that it can be exercised at a far earlier stage. Indeed,
O
54 r 7(2) of the Federal Court Rules provides that an
application for an order of review to be dismissed or stayed under s 10 of
the ADJR Act must be made within 14 days
after the party is served with the
application for an order of review. ActewAGL did not resist the application on
this basis and
did not oppose the grant of an extension of time in which to make
it. In all the circumstances and consistently with Northrop J’s
approach
in Edelsten, for present purposes, I assume in favour of ActewAGL that it
would succeed on its application.
- The
AER referred to a number of cases in which the court declined to exercise its
jurisdiction where merits review was available
before an independent statutory
tribunal with a right of appeal to, or review by, a court. Often this situation
arises where an
application for merits review has already been made. See, e.g.
Saitta Pty Ltd v Commonwealth of Australia [2000] FCA 1546; (2000) 106 FCR 554 at 575
[104]. Section 10(2)(b)(i) partly deals with this situation. It permits the
court to refuse to grant an application where the applicant
has sought a review
of the decision by the court or another court. Section 10(2)(b)(ii) also
catches cases in which a review has
been sought in a tribunal or by a person or
authority. But the discretion to refuse relief under subsection (2)(b)(ii) is
not founded
on the premise that another proceeding is pending. A mere
entitlement to seek a review is enough. Moreover, the power in subsection
(2)(b)(ii) is not limited either (as ActewAGL submitted) to a situation in which
the entitlement subsists at the time the ADJR Act
application is made:
Kimberly-Clark Ltd v Commissioner of Patents (1988) 83 ALR 714
(“Kimberley-Clark”) at 718-719. If ActewAGL were right, as
Jenkinson J pointed out in Kimberley-Clark, that would mean that the
entitlement might often be lost by the effluxion of time. An aggrieved party
could sit on its hands, do
nothing, wait for the time for an appeal to pass, and
then seek judicial review. The reference to “is entitled” in
subsection
(2) must be read as a reference to an entitlement the applicant
enjoyed when the decision under review was made.
- Plainly,
the definition of review in subsection (3) is wide enough to catch the kind of
review provided for in the Tribunal, which
includes review of material errors of
fact, errors of fact which in combination can be said to have been material, the
incorrect
exercise of a discretion and where the decision is unreasonable in all
the circumstances: NEL, s 71C. It is true that leave is
required before
an application for review can be made: NEL, s 71B(1). But ActewAGL did
not contend that the leave requirement meant
that ActewAGL was not entitled to
seek a review. In the present case, at least, there could be no doubt that
ActewAGL could have
sought a review in the Tribunal. Its position concerning
the averaging period was relevantly indistinguishable from those of the
other
network service providers who were given leave to make their applications.
- I
have no doubt that the merits review mechanism under the NEL is an adequate
alternative remedy. For the purpose of hearing a review,
the Tribunal is
constituted by a judge of this Court, who presides and is required to determine
any question of law, together with
two lay members, who are appointed for their
knowledge or experience in industry, commerce, economics, and/or public
administration:
Competition and Consumer Act 2010 (Cth), ss 37, 42. The
grounds of review are very broad, certainly far broader than those provided for
in the ADJR Act. The Tribunal’s powers
are also greater than the powers
given to the Court on an ADJR Act application; they include the power to vary
the decision under
review: NEL s 71P(2). Although there is no statutory
right of appeal from a decision of the Tribunal, its decisions are subject
to
judicial review under the ADJR Act and under s 39B of the Judiciary Act
1901 (Cth): see Telstra Corporation Limited v Australian Competition
Tribunal [2009] FCAFC 23 at [2].
- In
Bragg v Secretary, Department of Employment, Education and Training
(1995) 59 FCR 31 the applicant applied for judicial review of two decisions
of a delegate of the respondent made under the Public Service Act 1922
(Cth). He could have appealed the decisions under another provision
of the Public Service Act to a Disciplinary Appeal Committee. Davies
J held
that the appeal was an adequate review within the meaning of s 10(2)(b)(ii)
and refused to grant the application in the exercise
of the Court’s
discretion before the applicant had exercised his right to appeal, but left the
door open if he were to fail
on the appeal. His Honour said that the
general practice of the court is not to consider a dispute for the resolution of
which a satisfactory administrative
remedy has been provided. Also see Swan
Portland Cement Ltd v Comptroller-General of Customs (1989) 25 FCR 523 at
530.
- ActewAGL
emphasised that the ADJR Act provides that the rights conferred by it are
additional to rights available elsewhere and I
accept that the starting point is
that an applicant may rely on any or all of the available remedies –
review in this Court
or review or appeal elsewhere: Kelly v Coats [1981] FCA 58; (1981)
35 ALR 93 at 94. It cannot be the purpose of s 10(2)(b)(ii) to invariably
require an applicant to exhaust whatever rights of review (s)he
or it has before
making an application under the ADJR Act because that would require everyone
with alternative remedies who seeks
judicial review to apply for an extension of
time as a matter of course.
- Nevertheless,
in this case, having regard, in particular, to the nature of the issues to be
considered, the expertise of the Tribunal
(not to mention the inability of the
Court to provide a review of the merits) (cf. Yarmirr v Australian
Telecommunications Corporation (1990) 96 ALR 739 at 750), I consider that
this is an appropriate case for the exercise of the discretion vested in the
Court by s 10(2)(b)(ii). The
Tribunal is a more appropriate forum for the
resolution of the particular dispute between the parties (cf. McGowan v
Migration Agents Registration Authority [2003] FCA 482; (2003) 129 FCR 118 at 133).
- As
Burchett J said in Swan Portland Cement Ltd v Comptroller-General of
Customs (1989) 17 ALD 551 (and with which the Full Court agreed:
(1989) 25 FCR 523 at 530), notwithstanding the terms of s 10(1)(a),
“it should not be thought that it is always appropriate to bring a matter
of this kind before the court. The legislation provides its own method of
review”. It is clear from the terms of the NEL
that parliament envisaged
that in the normal course, if there were to be a challenge to the correctness of
a decision of the AER,
including the exercise of its discretion, then that would
be heard by the Tribunal. Here, ActewAGL chose not to exercise its statutory
right to apply to the Tribunal. In all the circumstances, and particularly when
so much time has passed, it is fair that it be held
to the consequences of that
decision. I have take into account in ActewAGL’s favour that merits
review is no longer available
(see Kimberley-Clark at 719). It lost that
opportunity, however, not through ignorance or mistake, but by its own election
for commercial reasons not
to contest the decision.
CONCLUSION
- The
application should be dismissed with costs.
I certify that the preceding one hundred and
ninety-eight (198) numbered paragraphs are a true copy of the Reasons for
Judgment herein
of the Honourable Justice Katzmann.
|
Associate:
Dated: 8
June 2011
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/cth/FCA/2011/639.html