![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
High Court of Australia |
PETELIN v. DEGER INVESTMENTS PTY. LTD. [1976] HCA 4; (1976) 133 CLR 538
Vendor and Purchaser
High Court of Australia
Barwick C.J.(1), McTiernan(2) and Mason(3) JJ.
CATCHWORDS
Vendor and Purchaser - Contract - Real property - Option to purchase - Standard form of contract of sale to be executed upon exercise of option - Right to rescind if land affected by planning otherwise than as disclosed in schedule to contract of sale - Schedule not completed - Land affected by planning restriction - Whether vendor entitled to rescind.
HEARING
Sydney, 1975, November 12,13; 1976, February 19. 19:2:1976DECISION
1976, February 19.
2. The manner of exercise of the option was specified. The third clause of
the agreement was in the following terms:
"3. Immediately upon the exercise of this option the GrantorThe second schedule to the option agreement contained the following statement: "The grantees are aware of the proposed roadway intended for this land by Liverpool City Council." (at p541)
and the Grantee or its nominee will execute a contract on
the terms referred to above and containing the conditions of
sale as approved by the Real Estate Institute of New South
Wales and the Law Society of New South Wales together
with such conditions (if any) as appear in the Third Schedule
hereto."
3. Liverpool Properties Pty. Ltd. duly nominated the respondent as its
nominee and the respondent duly exercised the option. (at
p541)
4. The form of contract approved by the Real Estate Institute and the Law
Society of New South Wales in current use at the time
of the grant of the
option to purchase contained the following condition:
"16. Should it be established prior to completion that at
the date of this Agreement the property was affected by any
town and country planning Scheme or interim development
prepared or prescribed under the provisions of the State
Planning Authority Act or Pt XIIA of the Local Government
Act 1919 as amended otherwise than as stated in the fourth
schedule hereto or was affected by any Residential District
Proclamation under s. 309 of the Local Government Act
1919, or by any existing proposals for re-alignment widening
or siting of a road by any competent authority otherwise than
as disclosed in the said fourth schedule, either party shall be
entitled to rescind this Agreement by notice in writing to the
other". (at p541)
5. The fourth schedule to this form of contract was as follows:
"The property is affected as shown in the copy certificateIndorsed in the margin to the fourth schedule was the statement "Delete if not applicable". (at p541)
under s. 342AS of the Local Government Act 1919 annexed
hereto".
6. The third schedule to the option agreement merely provided that if the
option were exercised, settlement should take place within
ninety days. (at
p541)
7. No copy of the Real Estate Institute form of contract was annexed to the
option agreement: nor did the parties at any time expressly
agree to delete
the provision of the fourth schedule to that form: nor was any certificate
under s. 342AS of the Local Government
Act, 1919 (as amended) annexed to the
option agreement. Further, it did not appear that any such certificate had
been issued at
the time of the signature of the option agreement.
Consequently, neither party had any such certificate in hand at that time. (at
p541)
8. In fact, at that time, the land was subject to zoning. It was shown as
Part Zone 3 (a) Business General and Part Reservation
Roads 2 (c) Local Road
Proposed under the City of Liverpool Planning Scheme. (at p541)
9. On 2nd March 1972, the appellant gave notice of rescission of the contract
pursuant to cl. 16 of the Real Estate Institute form
of contract. The notice
was based apparently upon the existence of these zoning provisions. (at p542)
10. On 24th May, the respondent commenced proceedings for specific
performance of the agreement constituted by the exercised option
to purchase.
The appellant defended the suit upon the ground, amongst others, that the
contract had been duly rescinded. (at p542)
11. The Supreme Court in its Equity Division (Holland J.) decreed specific
performance following the decision of the Court of Appeal
Division in Cullen
v. Petelin (1973) 2 NSWLR 485 . In that case, it was decided that the
decisions in Wolczyk v. Barr (1970) 92
WN (NSW) 518 and Jonray (Properties)
Pty. Ltd. v. Taranto (1970) 92 WN (NSW) 929; 21 LGRA 399. were
distinguishable from the circumstances
of that case and that, in order to give
business efficacy to the contract between the parties, there must be implied
therein an intention
on the part of the parties that when the formal contract
was entered into "the matter proposed to be inserted in the fourth schedule"
would be inserted. Accordingly, the contract between the parties was taken to
include "the material objectively in existence at
the date of the exercise of
the option and of the entering into the necessary written agreement of sale as
contemplated by the option
document". It was said: "This is material that can
be obtained from the appropriate authorities." (at p542)
12. From the decree for specific performance the appellant appeals to this
Court. It is now necessary to decide a point which this
Court found it
unnecessary to decide in Petelin v. Cullen [1975] HCA 24; (1975) 132 CLR 355 . (at p542)
13. In my opinion, the first matter to be decided is the relationship of the
terms of the Real Estate Institute form of contract
to the terms of the
option. The respondent in argument initially took the stand that cl. 3 of the
option agreement called upon the
appellant, when the option had been
exercised, to enter into a new contract containing terms which had not formed
part of the option.
But later, counsel for the respondent seemed to accept the
position that cl. 3 did no more than require the execution of a document
to
record in a formal fashion the agreement which resulted from the exercised
option. That, in my opinion, is the correct analysis
of the operation of cl.
3. It introduces into the option agreement as part of the terms of the option
the terms of the Real Estate
Institute form of contract. There was no
question of the formation of a new and different contract. With the execution
of a document
in the Real Estate Institute form, the agreement resulting from
the exercise of the option would contain, amongst other terms derived
from the
form, clause 16 and the fourth schedule to the form. The suit was initiated
on such a basis for no form of contract was
executed. (at p543)
14. The contract between the parties was therefore one for the sale of an
unencumbered freehold in possession, planning restrictions
being regarded, in
my opinion, as within the description "free of all mortgages charges and other
encumbrances easements restrictions
and convenants". The exception from this
generality of the proposed roadway intended for the land by the Liverpool City
Council
as mentioned in the second schedule to the option agreement is
indicative to my mind of the extensive sense in which the word "restriction"
was used in the description of the estate to be conveyed. But a right of
rescission was given to each party if it should be established
prior to
completion that the land was affected by, amongst other things, planning
restrictions otherwise than as stated in the fourth
schedule to the Real
Estate Institute form. (at p543)
15. The difficulty in the case is due to the fact that nothing was stated in
that schedule. The schedule provides for the annexation
of a certificate
under s. 342AS of the Local Government Act. But the disclosure of existing
planning restrictions was not confined
to the method of attaching such a
certificate. The parties were at liberty, so far as the form was concerned, to
notify their current
knowledge of any planning restrictions by any agreed
statement they chose to insert in the fourth schedule. The evident purpose
of
cl. 16 and the fourth schedule is to provide against the possibility of their
common knowledge of planning restrictions at the
date of the grant of the
option being mistaken or inexact. Clearly, the relevant knowledge was that
which both had on the matter
and the relevant time was, in my opinion, the
time of the giving of the option, whose terms would govern their contractual
relations
when it was exercised. (at p543)
16. The very purpose of cl. 16 and its use of the fourth schedule
contemplates that even if a current certificate under s. 342AS
were in hand at
the time of the formation of the contract, or the parties otherwise had then a
mutual understanding of what I may
call the planning situation, the
certificate or that understanding as contained in the agreement might be
inaccurate or insufficient
fully to disclose the then planning restrictions.
When the terms of the form are introduced into those of an option to purchase,
so that the expression "the date of this agreement" refers, as I think it
does, to the date of the exercise of the option, a question
arises as to
whether the clause would cover any changes in planning restrictions which
supervened on the granting of the option and
become effective before its
exercise. It is unnecessary to resolve that question now; but at least the
clause refers to the agreed
understanding of the parties as to the planning
situation at the date of the exercise of the option. It is the annexing of the
certificate
under s. 342AS which expresses the parties' agreement, not the
existence or contents of such a certificate not so consensually annexed
to
form part of the contract. (at p544)
17. It follows from these considerations, in my opinion, that the difficulty
which arises in this case from the absence of any statement
in or relating to
the fourth schedule cannot be solved by the insertion by the Court of the
terms of a certificate obtained now from
the appropriate office as at the date
of the grant of the option or as at the date of its exercise. The contents of
the fourth schedule
must, in my opinion, be the result of the agreement of the
parties. It must be their agreed statement of their common knowledge or
understanding of the planning restrictions operative at the relevant time,
which in my opinion was at least the date of the grant
of the option. (at
p544)
18. It seems to me that a failure to make an agreed statement of that common
knowledge or understanding does not vitiate their agreement
for a mutual right
of rescission should planning restrictions stand in the way of the performance
of the promise to convey a fee
simple unencumbered in the sense in which I
have read the contractual description of the estate to be conveyed. The
effect of the
absence of a relevant statement in the fourth schedule is, in my
opinion, to leave the right of rescission unqualified. If in fact
planning
restrictions at the date of the exercise of the option are shown to exist, the
right of rescission will have arisen. No
common knowledge or understanding of
such existence would be shown as qualifying that right. Consequently, in my
opinion, the appellant
validly exercised a right of rescission, it being
established that there were relevant planning restrictions: the decree for
specific
performance ought not to have been made. (at p544)
19. Two observations should be made. First, I do not see that such a
conclusion creates any real difficulty in the use of the Real
Estate Institute
form referentially to incorporate its terms in an option to purchase. The
parties are able to obtain the relevant
certificate as at the date of the
grant of the option or to state for themselves their common understanding of
the planning situation
as at that date. If operative at the date of the
option, they will, unless meantime repealed, be operative at the date of the
exercise
of the option. The question whether further restrictions supervening
on the grant of the option and before its exercise would give
rise to a right
of rescission need not presently be decided. Of course, repeal of
restrictions operative at the date of the option
will not warrant rescission.
(at p545)
20. Secondly, I am unable to find any relevance in the resolution of this
case of the concept of business efficacy. Here, the parties
have made an
agreement which, as I have analysed it, is quite capable in its terms of being
carried out. They did not qualify their
agreed mutual right of rescission by
reference to their agreed common understanding at the time of the grant of the
option of the
planning position in which the subject land then stood, or such
understanding of what that position would be at the date of the exercise
of
the option. They did so evidently because they had no such common knowledge
or understanding. There is no room for any implication,
in my opinion, in
order to render what they had agreed efficacious. On the contrary, to insert
into their agreement a term upon
which they had not agreed, so far from
lending efficacy, is to depart in a radical respect from what they had agreed.
(at p545)
21. In my opinion, the decision in Wolczyk v. Barr (1970) 92 WN (NSW) 518
was well decided and this case, in relation to the lack
of any statement in
the fourth schedule to the Real Estate Institute form, is indistinguishable.
(at p545)
22. It will be observed that I have treated the expression in cl.16, "the
property was affected by any town or country planning
scheme", as referring to
any effect of such a scheme as restricts the availability or use of the land.
Accordingly, I have spoken
of planning restrictions. I do not accept a
submission made on behalf of the respondent that an exception of land from the
operation
of a planning scheme would fall within the purview of the
contractual expression. (at p545)
23. In my opinion, the appeal should be allowed and the suit for specific
performance dismissed. (at p545)
McTIERNAN J. I agree in the reasons for judgment of the Chief Justice. (at
p545)
MASON J. This matter comes before us by way of an appeal from the decision
of Holland J. sitting in the Equity Division of the
New South Wales Supreme
Court. (at p546)
2. By an agreement made on 6th April 1971 the appellant in consideration of
the sum of $100 paid by a third party, Liverpool Properties
Pty. Ltd., granted
an option in favour of that third party to purchase certain real property at
Liverpool, New South Wales. The
time limit for the exercise of this option
was 6th June 1971. The period of the option was subsequently extended for a
further six
months from 6th June 1971. On 3rd December 1971 the third party
nominated the respondent as its nominee in respect of the option
and on the
same day the respondent notified the appellant that it exercised the option by
serving upon him a document entitled "Exercise
of Option". (at p546)
3. The appellant, it seems, refused to recognize the exercise of the option
and took no steps to transfer the land to the respondent.
Accordingly, the
respondent commenced a suit, claiming, inter alia, specific performance of the
agreement. (at p546)
4. We are told that in the Supreme Court, Holland J. felt that he was bound
by the decision of the New South Wales Court of Appeal
in Cullen v. Petelin
(1973) 2 NSWLR 485 , and accordingly granted the relief sought by the
respondent. Cullen v. Petelin was the
subject of appeal to this Court recently
where the decision of the Court of Appeal on the non est factum issue was
reversed (see
Petelin v. Cullen [1975] HCA 24; (1975) 132 CLR 355 ). However, as will appear
shortly, the issue which now arises differs from
that previously
decided. (at
p546)
5. The present dispute resolves principally around cl. 3 of the option
agreement which provides as follows:
"3. Immediately upon the exercise of this option the
Grantor and the Grantee or its nominee will execute a contract
on the terms referred to above and containing the conditions
of sale as approved by the Real Estate Institute of
New South Wales and the Law Society of New South Wales
together with such conditions (if any) as appear in the Third
Schedule hereto." (at p546)
6. The crucial provision, in this case, of the "conditions of sale as
approved by the Real Estate Institute of New South Wales and
the Law Society
of New South Wales" is that contained in cl. 16 of the Law Society and Real
Estate Institute's standard form contract
of sale which provides as follows:
"16. Should it be established prior to completion that at
the date of this Agreement the property was affected by any
town and country planning scheme or interim development
prepared or prescribed under the provisions of the State
Planning Authority Act or Pt XIIA of the Local Government
Act 1919 as amended otherwise than as stated in the fourth
schedule hereto or was affected by any Residential District
Proclamation under s. 309 of the Local Government Act
1919, or by any existing proposals for re-alignment widening
or siting of a road by any competent authority otherwise
than as disclosed in the said Fourth Schedule, either party
shall be entitled to rescind this Agreement by notice in
writing to the other." (at p547)
7. The fourth schedule referred to in cl. 16 contains the printed words:
"The property is affected as shown in the copy certificate
under s. 342AS of
the Local Government Act 1919 annexed hereto." However, in the margin beside
these words is the advisory phrase,
"Delete if not applicable". (at p547)
8. No copy of the standard form contract was annexed to the option agreement;
nor was there a s. 342AS certificate attached. The
crux of the appellant's
submission is that whatever interpretation of cl. 3 of the option agreement be
adopted none the less the
only contract for sale of the land that he could be
required to execute is one with a blank fourth schedule because no s. 342AS
certificate
was annexed to the agreement and so cl. 16 must be regarded as
expressing a condition of sale (in the words of cl. 3 of the option)
that
there were no planning or zoning restrictions governing the subject property
(see Wolczyk v. Barr (1970) 92 WN (NSW) 518 ; Sargent
v. A.S.L. Developments
Ltd. [1974] HCA 40; (1974) 131 CLR 634 ). It follows, according to this submission, that
since indisputably
the land was
subject to a planning scheme
then there was an
automatic breach of the condition and thus cl. 16 of the conditions of
sale
gave the
appellant, notwithstanding
that he is the vendor, a right to rescind
the agreement. (at p547)
9. The decision of this Court in Sargent v. A.S.L. Developments Ltd.
establishes that the omission of a s. 342AS certificate or
of particulars in
lieu of a certificate from the fourth schedule in the standard form of
contract does not make the contract void
for uncertainty. The absence of
information of the kind contemplated by the standard form of contract is
tantamount to a statement
that the land is not relevantly affected by town
planning restrictions or proposals. The issue here is whether a similar
approach
is to be taken when the standard form of contract is incorporated in
an option agreement so as to set out the terms of the contract
which will
arise on the exercise of the option and when the fourth schedule contains
neither a s. 342AS certificate nor particulars
in lieu of a certificate. (at
p547)
10. In Sargent v. A.S.L. Developments Ltd. (1974) 131 CLR, at pp 639-640 ,
Stephen J. said that the function of cl. 16 is "to set
out in the contract the
planning status of the land so that the contracting parties may agree upon its
sale and purchase on the footing
of the status thus revealed; there is to be
an agreed, disclosed statement of any affecting of the land by planning
provisions, anything
not so stated giving rise to a right of rescission.
Fundamental to this concept is that the parties should have before them, when
executing the contract, an agreed statement of planning status, which of
course may indicate the total absence of all planning".
(at p548)
11. Although an option agreement antedates the making of a binding contract
created by an exercise of the option, the observations
of Stephen J. in
Sargent's Case in my view apply with equal force to cl. 16 when it has been
incorporated as part of the standard
form in the terms of an option agreement
for the purpose of setting out the provisions of the contract which will come
into existence
in the event that the option is exercised. (at p548)
12. The only distinction between the two cases lies in the circumstance that
here the statement of planning status is made on the
making of the option
agreement, whereas it is made on the making of the contract when a binding
contract is entered into not preceded
by an option agreement. This
distinction is in my view of little moment. It is natural that the parties
should wish to protect
themselves against the unforeseen consequences of
disconformity between actual and understood planning status - this is achieved
by recording, or by making provision for representing, in the option
agreement, the planning status of the land as the parties then
agree it to be.
(at p548)
13. The respondent's argument imputes to the parties an intention that the
certificate or particulars for which the fourth schedule
makes provision
should be inserted on or after the exercise of the option. This argument
proceeds upon the footing that the option
agreement requires the execution of
a formal contract after the option has been exercised and that this formal
contract will contain
material not necessarily known to or agreed upon by the
parties, as for example a s. 342AS certificate as may be issued by the
responsible
authority on application made to it. A contrary view, and one
which to my mind accords more closely with the usual character of
an option
agreement, is that such an agreement sets out all the terms and material on
which there will come into existence, upon
exercise of the option, the
contract thereby constituted without the necessity for the parties executing a
subsequent formal or substituted
contract. (at p548)
14. The respondent's argument also attributes to cl. 16 in the context of an
option agreement a function which is, to say the least
of it, curious. It
would enable the party to rescind the contract constituted by the exercise of
the option, not for disconformity
between the actual planning status at the
date of the agreement and the planning status of the land as agreed and
recorded by the
parties, but for disconformity between the actual planning
status of the land at that date and the planning status of the land as
the
council declares it to be, a status which may have been unknown to the parties
at the time they entered into the option agreement.
(at p549)
15. The respondent sought to draw some comfort from that part of cl. 16 which
makes it clear that it is disconformity at the date
of a contract which
grounds the right of rescission. I do not perceive any lack of harmony
between this provision and the notion
that what is critical is a disconformity
existing at the date of the contract between the actual planning status of the
land and
the planning status as it has been expressed at an earlier time, that
is at the date of the grant of the option. (at p549)
16. Finally it was said that the form of the fourth schedule provided some
support for the respondent because it contemplated that
a certificate would be
annexed. Assuming, as appears to be the case, that it is contemplated that
the usual means of providing the
information to be inserted in the fourth
schedule will be by means of annexing a certificate, it does not follow that
the certificate
must coincide in date with the making of the contract. It may
antedate the contract; all that is required is that it fulfils the
function of
disclosing the planning status of the land as the parties agree it to be. (at
p549)
17. For these reasons I would allow the appeal and dismiss the suit for
specific performance on the ground that it would be futile
to grant relief to
the appellant when the respondent has a right to rescind the contract which he
intends to exercise. (at p549)
ORDER
Appeal allowed with costs.
Order of the Supreme Court of New South Wales set aside and in lieu thereof order that the suit be dismissed with costs.
AustLII:
|
|
|
URL: http://www.austlii.edu.au/au/cases/cth/HCA/1976/4.html