![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
High Court of Australia |
FORESTRY COMMISSION OF N.S.W. v. STEFANETTO [1976] HCA 3; (1976) 133 CLR 507
Contract
High Court of Australia
Barwick C.J.(1), Mason(2) and Jacobs(3) JJ.
CATCHWORDS
Contract - Penalty - Forfeiture - Construction contract - Default by contractor - Works proprietor entitled to take possession of plant owned by contractor and use to complete works - Plant held under hire-purchase and leasing agreements - Contractor not entitled to compensation for use of plant - Whether penalty.
HEARING
Sydney, 1975, November 17; 1976, February 19. 19:2:1976DECISION
1976, February 19."35.5. LIQUIDATED DAMAGES FOR DELAY IN COMPLETION.
If the Contractor fails to complete the Works or a separable
part of the Works, as the case may be, within the relevant
time referred to in sub-cl. 35.2, or within any extended
time granted or allowed pursuant to sub-cl. 35.4, the Contractor
shall pay to the Principal by way of pre-estimated
and liquidated damages and not as a penalty the amount or
amounts stated or referred to in the Annexure hereto for
every week and part of a week that shall lapse after that time
or the extended time until the whole of the Works or the
separable part of the Works, as the case may be, has been
completed and that amount or those amounts may be
deducted from any moneys which may then be or thereafter
become payable to the Contractor by the Principal,
including any retention moneys then held by the Principal,
and, if such moneys are insufficient for this purpose, then
from the Contractor's security under the Contract, and any
deficiency then remaining may be recovered by the Principal
as a debt due to the Principal by the Contractor.
Where the Principal has used or occupied any part of the
Works pursuant to sub-cl. 35.3, the amount of pre-estimated
and liquidated damages payable by the Contractor to the
Principal by virtue of this subclause may be reduced to an
amount determined by the Superintendent and notified by
him to the Contractor.
43.1. PROCEDURE ON DEFAULT OF CONTRACTOR.
If the Contractor defaults in the performance or observance
of any covenant, condition or stipulation in the Contract
or refuses or neglects to comply with any direction as
defined in cl. 23 but being one which either the Principal or
the Superintendent is empowered to give, make, issue or
serve under the Contract and which is issued or given to or
served or made upon the Contractor by the Principal in writing
or by the Superintendent in accordance with cl. 23, the
Principal may suspend payment under the Contract and may
call upon the Contractor, by notice in writing, to show cause
why the powers hereinafter contained in this clause should
not be exercised.
The notice in writing shall state that it is a notice under
the provisions of this clause and shall specify the default,
refusal or neglect on the part of the Contractor upon which
it is based.
If the Contractor fails, within the period to be specified in
the notice in writing, to show cause which in the opinion of the
Principal offers reasonable assurance that the default will be
remedied or such direction of the Principal or the Superintendent,
as the case may be, will be complied with and the
Contract satisfactorily completed, the Principal, without
prejudice to any other rights that he may have under the
Contract against the Contractor, may -
(a) take over the whole or any part of the work remaining
to be completed and for that purpose and insofar
as it may be necessary exclude from the site the
Contractor and any other person concerned in the
performance of the Works; or
(b) cancel the Contract, and in that case exercise any of
the powers of exclusion conferred by sub-par. (a) of
this paragraph.
If the Contractor notifies the Superintendent in writing
that he is unable or unwilling to complete the Works, or to
remedy the default, refusal or neglect stated in the notice in
writing referred to in the first paragraph of this subclause,
the Principal may act in accordance with the provisions of
sub-par. (a) or sub-par. (b) of the last preceding paragraph,
as he thinks fit.
43.3 ENGAGEMENT OF OTHERS.
If the Principal elects to exercise the power conferred on
him by sub-par. (a) of the third paragraph of sub-cl. 43.1
he may complete the whole or any part of the work remaining
to be completed and for that purpose may let a contract
or contracts for the work remaining to be completed or, as
the case may be, for any part of that work or may employ
any person or persons other than the Contractor to carry
out that work or, as the case may be, the part of that work.
The Principal may take possession of and permit other
persons to use any materials, Constructional Plant and other
things on or about the site which are owned by the Contractor
and as are requisite and necessary for the purposes
of any such contract or any such employment.
The Contractor shall have no right to any compensation
or allowance for any action taken by the Principal pursuant
to this subclause, other than a right to require the Principal
to maintain in good working order the Constructional Plant
referred to in the preceding paragraph.
On completion of the work all Constructional Plant and
the surplus of the materials and other things so taken possession
of will be handed over to the Contractor, but without
payment or allowances for the fair wear and tear they may
have sustained in the meantime PROVIDED HOWEVER, that if
there is a deficiency as referred to in sub-cl. 43.4 and if the
Contractor fails to make good that deficiency, the Principal
may retain in his possession the said Constructional Plant,
materials and other things until the deficiency is made good
pursuant to the provisions of sub-cl. 43.4.
43.4 ADJUSTMENT OF COSTS ON COMPLETION OF THE WORKS.
On completion of the Works in accordance with the Contract
the Superintendent will ascertain the cost of the Works
to the Principal, comprising payments to the Contractor and
all losses, costs, charges and expenses incurred by the Principal
in carrying out the whole or any part of the Works completed
by him pursuant to sub-cl. 43.3 and any sum or sums
payable or due to the Principal as liquidated damages under
the Contract and he will certify such amount to the Principal.
A certificate signed by the Superintendent stating the
cost of the Works to the Principal shall be prima facie evidence
of the matters stated in the certificate.
Should the amount so certified be greater than the amount
which would have been paid to the Contractor if the whole
of the Works had been carried out by him, the difference
between the two amounts may be deducted from any moneys
which may then be or thereafter become payable to the Contractor
by the Principal, including any retention moneys then
held by the Principal, and, if such moneys are insufficient
for this purpose, from the Contractor's security under the
Contract.
If the amount of such moneys together with the amount of
the security be less than the amount to be deducted, the
deficiency may be recovered by the Principal as a debt due
to the Principal by the Contractor.
43.6. CANCELLATION OF CONTRACT.
If the Contract is cancelled under sub-cl. 43.1 or under
any other provision of the Contract it shall be deemed cancelled
as from the date when notice of cancellation in writing
under the hand of the Principal is served upon the Contractor,
or upon any Official Receiver, Trustee in Bankruptcy,
Liquidator, Official or Provisional Liquidator, Official
Manager, or Receiver or Receiver and Manager of the
Contractor or of the business of the Contrator.
On such cancellation of the Contract all or any sums of
money which may be in the hands of the Principal in respect
of the Contract and are not then payable to the Contractor
under or pursuant to any provision of the Contract, and all
or any sums lodged or retained as security for the due and
proper performance of the Contract and all or any sums
named in the Contract as liquidated damages which have
accrued due to the Principal may be declared by the Principal
to be forfeited and all such sums that are so declared
to be forfeited shall be forfeited and shall be retained by or
become payable to or vested in the Principal.
On such cancellation of the Contract all moneys which
have been previously paid to the Contractor shall be deemed
to be in full satisfaction of all claims of the Contractor of
any kind or description whatsoever under or in respect of the
Contractor.
The amount of the security is $30,000 (sub-cl. 5.2)."
(at p513)
2. The respondent made default in his performance of the contracted work.
The appellant became entitled to exercise its rights under
the third paragraph
of cl. 43.1. It elected to take over the part of the work then remaining to
be done. It did not cancel the
contract. (at p513)
3. At the time the appellant took over the work, there was on the site
road-making machinery and plant brought there by the respondent
in order to
perform the contract. Part of this machinery and plant was the property of
the respondent and part was being acquired
by him under hire-purchase
arrangements with the proprietor of that machinery and plant. (at p513)
4. The appellant claimed to be entitled, by virtue of the second paragraph of
cl. 43.3, to take possession and make use of all the
machinery and plant which
was on the site. The respondent disputed the appellant's right to take
possession of or use any of such
plant and machinery. (at p513)
5. The respondent commenced proceedings in the Equity Division of the Supreme
Court of New South Wales to recover possession of
all the machinery and plant
with certain ancillary relief to which I need not refer. (at p513)
6. The Supreme Court (Needham J.) held that, upon the true construction of
the second paragraph of cl. 43.3, the appellant was entitled
to take
possession only of that machinery and plant which was the property of the
respondent: in other words, the Supreme Court
held that the machinery and
plant under hire-purchase to the respondent did not come within the expression
in the clause "which are
owned by the contractor". It did so, both because of
the natural meaning of the word "owner" in relation to chattels, and upon a
comparison of the language of this paragraph of cl. 43.3 and the language of
other clauses of the contract, such as the definition
of constructional plant
and the terms of cl. 16.1. I have no need to set out these clauses: they are
fully set out in the reasons
for judgment of the Supreme Court (1975) 1 NSWLR
332 . (at p513)
7. I am of opinion that the Supreme Court was right in its construction of
the expression "which are owned by the contractor". Further,
I agree with the
reasoning by which his Honour reached his construction of the contract. I
would add nothing to his reasons. (at
p514)
8. The respondent submitted that the second, third and fourth paragraphs of
cl. 43.3, in giving the appellant the right to take
possession of and use the
machinery and plant owned by the respondent without payment or any
responsibility to make allowances for
fair wear and tear, and to retain such
possession till any moneys ultimately due by the respondent to the appellant
had been paid,
constitute a penalty against which a court of equity would
grant relief. Accordingly, the respondent claimed to recover possession
of
his own machinery and plant, though the work may not have been completed and
final accounts taken between the parties. (at p514)
9. In a carefully expressed judgment, the Supreme Court, after consideration
of a number of authorities, accepted this submission,
holding that the
doctrines of equity extended beyond relief against pecuniary sums, considered
to be penalties as distinct from genuine
pre-estimates of damage. His Honour
then concluded that the contractual right to take and retain possession of and
to use the respondent's
machinery and plant did constitute relevantly a
penalty and made orders conformable to that conclusion. (at p514)
10. His Honour thought that the great value of machinery and plant used
currently in constructional work called for a different
approach to such a
clause as cl. 43.3 to that which might be made if only manual tools and
unmechanised machinery were used. His
Honour considered that it was material
in deciding the relevant nature of cl. 43.3 that the contract provided a sum
of $1,000 per
week or part thereof as liquidated damages for delay on the part
of the respondent in the completion of the work (see cl.35.5) and
a
substantial sum by way of security for the performance of the contract (see
cl. 5.2). His Honour said (1975) 1 NSWLR, at p 344
: "I cannot accept that a
contractual right to appropriate highly expensive equipment and materials
belonging to another contracting
party for an indefinite period, without
payment and without liability to compensate, not only for damage but also for
fair wear and
tear, could be anything but a penal provision aimed at ensuring
that the contractor does not breach his contract." (at p514)
11. I am unable to accept this conclusion. Being of a contrary opinion, I
find no need to discuss the interesting question as to
the reach of the
doctrines of equity in relief against forfeitures and penalties. Whether, if
cl. 43.3 were properly held to be
relevantly penal in its nature, there would
be jurisdiction to grant relief against its operation will remain for me an
open question.
(at p515)
12. I do not think the provisions of the contract as to liquidated damages
for delay in completion or as to the provision of security
for the performance
of the contract are relevant considerations when determining the nature of the
grant of the contractual right
to take possession and use the respondent
contractor's machinery and plant in the completion of the work. It must be
observed that
the appellant is not primarily interested in obtaining damages
for breach of the contract. It is primarily concerned with the completion
of
the work within a stipulated time. Both the provisions as to liquidated
damages and as to the provision of security are means
to that end, coupled
with an ease of recovery of damages in the event of breach. But the
possession and use of the machinery and
plant are, to my mind, a direct means
of achieving the purpose of the contract, namely, the completion of the work.
They are not
a means of providing the appellant with any form of compensation
in respect of the breach of the agreement. (at p515)
13. The clause does not give the appellant any rights of property in the
machinery and plant of which it authorizes possession and
use. I see a
critical difference between a clause which gives absolute property rights to
the person in the situation of the appellant
and cl. 43.3 which limits the
appellant's right to possession and use. Consequently, I would not regard
Bysouth v. Shire of Blackburn
and Mitcham (No. 2) [1928] VicLawRp 81; (1928) VLR 562 , if
generally acceptable, as an authority for the course taken by the Supreme
Court. (at p515)
14. The respondent laid emphasis upon the fact that there is to be no
compensation payable to him for the use of his machinery and
plant, including
its wear and tear: but the appellant by the contract is to maintain the plant
in good working order. No doubt
the appellant, having taken possession of the
respondent's machinery and plant, will be bound by the general law to use it
efficiently
to complete the work as expeditiously as possible and to maintain
it in good working order not doing any harm or damage to the machinery
and
plant other than that which is entailed in fair wear and tear in its proper
use. (at p515)
15. It seems that the provision allowing the appellant to complete the work
with the aid of the respondent's plant is both reasonable
and in the interest
of both the parties, i.e. the interest of both parties to effect early
completion. True it is that the respondent
is denied the immediate use of the
machinery and plant: but he is in default. It is not unreasonable that the
appellant should
not be confined to rely only on the liquidated damages for
delay or the security provided by the respondent. These are not really
a
substitute for completion. Clause 43.3 is not, in my opinion, in any sense a
punitive clause. Therefore, whatever the stretch
of the appropriate equitable
doctrine, cl. 43.3 would not be within it. (at p516)
16. In my opinion, the appeal in relation to the penalty issue should be
allowed, and the Supreme Court's order varied in this respect.
I would
otherwise dismiss the appeal. (at p516)
MASON J. On 30th June 1974 the appellant Commission and the respondent
entered into a written agreement by which the respondent
agreed to construct
for the appellant a gravel road twenty-three miles in length through the Imlay
Forest, near Eden, for $803,459.
The respondent made default in performance
of his obligations under the agreement thereby bringing into operation the
provisions
of cl. 43.1 of the general conditions of contract which were
specifically incorporated in the agreement. This clause entitled the
appellant by notice in writing to call on the respondent to show cause why
certain powers conferred by the clause should not be exercised.
(at p516)
2. Apparently the appellant served such a notice upon the respondent, for it
is now common ground that there occurred the preliminary
conditions essential
to the exercise by the appellant of its right, conferred by cl. 43.1(a) of the
general conditions of contract,
to "take over the whole or any part of the
work remaining to be completed". The appellant in fact exercised this right
on 3rd January
1975. (at p516)
3. The relevant part of cl. 43.1 is in these terms:
"... the Principal, without prejudice to any other rights
that he may have under the Contract against the Contractor,
may -
(a) take over the whole or any part of the work remaining
to be completed and for that purpose and insofar
as it may be necessary exclude from the site the Contractor
and any other person concerned in the performance
of the Works; or
(b) cancel the Contract, and in that case exercise any of
the powers of exclusion conferred by sub-par. (a) of
this paragraph.
If the Contractor notifies the Superintendent in writing that
he is unable or unwilling to complete the Works, or to
remedy the default, refusal or neglect stated in the notice in
writing referred to in the first paragraph of this subclause,
the Principal may act in accordance with the provisions of
sub-par. (a) or sub-par. (b) of the last preceding paragraph,
as he thinks fit." (at p517)
4. The consequences which flow from an exercise of the right given by cl.
43.1 are set out in cl. 43.3 which is in the following
terms:
"If the Principal elects to exercise the power conferred on
him by sub-par. (a) of the third paragraph of sub-cl. 43.1
he may complete the whole or any part of the work remaining
to be completed and for that purpose may let a contract
or contracts for the work remaining to be completed or, as
the case may be, for any part of that work or may employ
any person or persons other than the Contractor to carry
out that work or, as the case may be, the part of that work.
The Principal may take possession of and permit other
persons to use any materials, Constructional Plant and other
things on or about the site which are owned by the Contractor
and as are requisite and necessary for the purposes
of any such contract or any such employment.
The Contractor shall have no right to any compensation
or allowance for any action taken by the Principal pursuant
to this subclause, other than a right to require the Principal
to maintain in good working order the Constructional Plant
referred to in the preceding paragraph.
On completion of the work all Constructional Plant and
the surplus of the materials and other things so taken possession
of will be handed over to the Contractor, but without
payment or allowances for the fair wear and tear they may
have sustained in the meantime PROVIDED HOWEVER, that
if there is a deficiency as referred to in sub-cl. 43.4 and if
the Contractor fails to make good that deficiency, the Principal
may retain in his possession the said Constructional
Plant, materials and other things until the deficiency is made
good pursuant to the provisions of sub-cl. 43.4." (at p517)
5. At the time of the taking over of the work by the appellant the respondent
had on the site plant and machinery belonging to him
and also plant and
machinery which was the subject of hire-purchase or leasing agreements in his
favour. The plant and equipment
was extensive and was of considerable value.
(at p517)
6. The appellant having claimed to be entitled to possession of the whole of
this plant and equipment, the respondent commenced
an action in the Supreme
Court of New South Wales. In this action Needham J. made a declaration that
the provisions of cl. 43.3
are in the nature of a penalty and that the
respondent was entitled to relief therefrom. His Honour also declared that
the appellant
was not entitled to retain plant and equipment not owned by the
respondent (1975) 1 NSWLR 332 . The arguments advanced by Mr. Handley
for the
appellant have not persuaded me that his Honour was incorrect in reaching this
result. (at p518)
7. It would, I think, be a bold step to construe cl. 43.3 as conferring upon
the appellant the right to take and keep possession
of plant and equipment not
owned by the respondent in the legal sense of that word, being plant and
equipment owned by third parties
which was on lease or on hire-purchase to the
respondent. Under a hire-purchase agreement it is the vendor, not the hirer,
who is
the owner of the goods and who is correctly so described as a matter of
legal terminology, notwithstanding that the hirer has an
"equity" in the goods
which by statute may amount to a proprietary interest for certain purposes.
Likewise, under a bailment or lease
agreement, it is the bailor or lessor, not
the bailee or lessee, who is the owner of the goods and who is properly so
described.
(at p518)
8. It may be that on some occasions a person who has a limited or possessory
interest in chattels is popularly referred to as the
"owner" of them or is
said to "own" them, but I can see no justification in the present context for
attributing to cl. 43.1 such
a meaning. Indeed, the context tells strongly
against such a usage. As Needham J. observed (1975) 1 NSWLR, at p 337 , there
is a
contra-distinction between cl. 43.3 when it refers to "constructional
plant" which is "owned by the contractor" and other provisions
such as cl.
16.1 which deal with constructional plant brought on to the site without
limiting that plant to plant which is owned
by the contractor. (at p518)
9. Quite apart from indications of this kind to be gathered from the
provisions of the general conditions of contract, there are
considerations
arising from the very subject matter of the agreement which suggest strongly
that the respondent's construction of
the clause is incorrect. If it were
correct it would bring about the result that the taking by the appellant of
possession of the
respondent's plant and equipment would result in a
termination of his limited or possessory interest in the goods by reason of
the
presence in hire-purchase and lease agreements of conditions which entitle
the vendor or lessor to terminate the agreement in the
event that there is a
parting with possession of the goods. (at p518)
10. Accordingly, I am of the opinion that his Honour was correct in thinking
that cl. 43.1 did not entitle the appellant to take
and retain possession of
plant and equipment in which the respondent had a limited or possessory
interest only under hire-purchase
agreements and lease agreements. (at p519)
11. Although the appellant argued at first instance that the jurisdiction to
relieve against penalties did not extend to provisions
relating to property,
as distinct from provisions which sounded in the payment of money, this
argument was not pressed before us.
Here the appellant conceded that the
courts have jurisdiction to relieve against contractual provisions resulting
in the forfeiture
of property on the footing that they constitute a penalty,
but went on to submit that the clause in question was not such a provision.
(at p519)
12. The appellant's concession was well founded because the equitable
doctrine of relief against forfeiture is consistently applied
so as to protect
property and proprietary interests, the granting of relief against penalties
being no more than a special application
of the general doctrine (Kreglinger
v. New Patagonia Meat and Cold Storage Co. Ltd. [1913] UKHL 1; (1914) AC 25, at p 35 ). The
distinction between
a penalty (when it takes the form of an obligation to pay
a sum of money in the
event of a breach of contract) and liquidated damages
is
that the latter is a genuine pre-estimate of loss or damage (Dunlop Pneumatic
Tyre Co. Ltd. v. New Garage and Motor Co. Ltd. [1914] UKHL 1; (1915)
AC 79, at p 86 ),
whereas the former is not. Except in so far as it throws some light on the
character of the penalty this
distinction
has little relevance to the
provision now in question. The purpose of the provision is not so much to
provide compensation
for loss
which the principal may sustain as a result of
the contractor's breach of contract, but to enable the principal to complete
the contract
works which the contractor has engaged to execute. If the
provision were limited in its operation to the attainment
of this objective,
it might be impossible to characterize it as a penalty, so long at any rate as
the advantage which the principal
might derive from
the use of the
contractor's materials, plant and equipment was to be taken into account in
arriving at the contractor's
entitlement
or liability under, or by virtue of,
the contract. (at p519)
13. However, there are two reasons why this character cannot be assigned to
the power conferred upon the appellant by cl. 43.3.
First, the power to take
possession is not confined to possession for the purpose of executing the
contract works. As I read the
clause, the appellant could take and retain
possession of the materials, plant and equipment until completion of the
contract works
without using them at all. Secondly, the clause specifically
denies to the respondent any compensation or allowance for the use
or
deprivation of the materials, plant and equipment. It may be that there are
additional reasons for arriving at a similar conclusion
but it is unnecessary
to explore them for enough has already been said to demonstrate that the power
may be exercised arbitrarily
and capriciously so as to prejudice and penalize
the respondent and that the power is not one which is so confined as to enable
the
appellant to complete the contract works on a footing whereby the
respondent receives some credit or allowance for the use or deprivation
of his
property. (at p520)
14. I have not discovered in the authorities referred to in argument any
support for a contrary view. True it is that in Emden
and Gill's Building
Contracts and Practice, 7th ed. (1969), p. 302, the distinction is drawn
between clauses which forfeit the builder's
property absolutely and clauses
which allow the employer to use the builder's property for the purpose of
completing the contract.
This passage should be understood as differentiating
between the forfeiture of the builder's property which, although expressed to
be by way of liquidated damages, in truth constitutes a penalty, and a
provision which does no more than entitle the employer to
use the builder's
property for the exclusive purpose of completing the contract of work on the
footing that the builder receives
some credit or allowance, when no question
of penalty arises. (at p520)
15. The observations of Lord Cranworth L.C. in Ranger v. Great Western
Railway Co. [1854] EngR 73; (1854) 5 HLC 72, at pp 108-110 [1854] EngR 73; (10 ER 824, at
pp 839-840) were
directed to a different situation. There the contract conferred upon the
railway company a power
to seize and appropriate
plant belonging to the
contractor. Lord Cranworth said (1854) 5 HLC, at p 108 (10 ER, at p 839) :
"The question is, whether, having taken possession, theyHis Lordship went on to say (1854) 5 HLC, at p 110 (10 ER, at p 840) :
became absolutely entitled to all which they seized, or
whether the whole provision is not to be regarded as mere
machinery for enabling them to complete the works, at the
risk and cost of the appellant. I think the latter is the true
construction of the clauses."
"I have come to the conclusion that the true meaning ofThe absence here of any obligation on the part of the appellant to account for the value of plant and equipment seized distinguishes this case from Ranger's Case. (at p521)
this part of the contract is, that the Respondents, though at
liberty to seize and appropriate the plant belonging to the
appellant, were yet bound to account for its value in settling
their accounts with him."
16. The other authority to which I should refer is Bysouth v. Shire of
Blackburn and Mitcham (No. 2) [1928] VicLawRp 81; (1928) VLR 562 . The contract
there provided
that upon determination by the council the materials and plant in or upon the
works should become the property of
the council. By a majority, the Full
Court of the Supreme Court held that the forfeiture of the contractor's
property was a penalty,
there being no provision that the value of the
materials and plant should be taken into account in determining the financial
position
of the parties. (at p521)
17. That situation differed from the present circumstances, so it was argued,
in that here there is no provision for the forfeiture
of property - no more is
involved than the possession and, perhaps, the use of materials, plant and
equipment by the principal. However,
as Needham J. pointed out, if the
principle on which Bysouth's Case was decided be correct, as in my opinion it
is, it can make no
difference that the contractor is deprived not of property
but of possession. The deprivation is none the less a penalty, though
not as
severe. There is in my view no convincing basis for distinguishing the present
case. (at p521)
18. For these reasons I would dismiss the appeal. (at p521)
JACOBS J. I agree with the conclusion of Needham J. that the reference in
cl. 43.3 to "any materials, constructional plant and
other things on or about
the site which are owned by the contractor" is a reference to such things when
owned by the contractor "in
a legal sense", by which I understand him to mean
owned at law. Chattels held under lease or hire, including hire purchase, are
not so owned. (at p521)
2. The second question, as Needham J. observed, is of greater difficulty.
Clause 43.3 provides:
"43.3. ENGAGEMENT OF OTHERS.What is claimed is that the provision that the appellant "may take possession of and permit other persons to use any materials, constructional plant and other things on or about the site which are owned by the contractor and as are requisite and necessary..." constitutes a penalty and as such is void. It appears to me that this provision is not in itself a provision for any penalty. There could be no objection to such a contractual provision for use of the plant and materials provided compensation or allowance were made: cf. Ranger v. Great Western Railway Co. [1854] EngR 73; (1854) 5 HLC 72 (10 ER 824) . It is the immediately following provision that the respondent should have no right to any compensation or allowance for any action taken by the appellant pursuant to the earlier provision which may create a situation where equity would relieve against such a forfeiture of the right to ownership of materials and to possession of the plant without compensation or allowance. (at p522)
If the Principal elects to exercise the power conferred on
him by sub-paragraph (a) of the third paragraph of sub-cl.
43.1 he may complete the whole or any part of the work
remaining to be completed and for that purpose may let a
contract or contracts for the work remaining to be completed
or, as the case may be, for any part of that work or
may employ any person or persons other than the Contractor
to carry out that work or, as the case may be, the part of
that work.
The Principal may take possession of and permit other
persons to use any materials, Constructional Plant and other
things on or about the site which are owned by the Contractor
and as are requisite and necessary for the purposes
of any such contract or any such employment.
The Contractor shall have no right to any compensation
or allowance for any action taken by the Principal pursuant
to this subclause, other than a right to require the Principal
to maintain in good working order the Constructional Plant
referred to in the preceding paragraph.
On completion of the work all Constructional Plant and
the surplus of the materials and other things so taken possession
of will be handed over to the Contractor, but without
payment or allowances for the fair wear and tear they
may have sustained in the meantime PROVIDED HOWEVER,
that if there is a deficiency as referred to in sub-cl. 43.4
and if the Contractor fails to make good that deficiency, the
Principal may retain in his possession the said Constructional
Plant, materials and other things until the deficiency
is made good pursuant to the provisions of sub-cl. 43.4."
3. The primary argument on behalf of the appellant is that no question either
of penalty or relief against forfeiture arises because
on the true
construction of the contract the respondent is entitled, as the appellant has
exercised the power to take over the work
pursuant to cl. 43.1(a) rather than
to cancel pursuant to cl. 43.1(b), to receive the whole of the contract price
when the works
have been completed by or on behalf of the appellant. Included
in that contract price, it is claimed, will be compensation for the
use of the
respondent's plant because if he had completed the work he would have used the
plant and his compensation for that use
would have been part of the contract
price. I cannot accept this argument. The contract no doubt remains on foot
so far as rights
are thereby conferred upon the appellant, but it does not
follow that the respondent, who is admittedly in breach of contract, is
entitled to payment or credit thereunder for work not executed by him. The
completion of the works by the appellant was not a contractual
substitution of
a different mode of performance thereof by the respondent. The argument is
not consistent with cl. 41 whereby payment
to the respondent was to be made
against certificates and the latter were to be certificates of work "carried
out in performance
of the contract" (cl. 41.1) and "executed by the
contractor" (cl. 41.6). The final certificate under cl. 41.8 is only to be
issued
"when all work under the contract has been finally and satisfactorily
executed and the contractor has fulfilled all his other obligations
under the
contract". (at p523)
4. On a not dissimilar contract the same argument was presented in Simpson v.
Trim Town Commissioners (1898) 32 Ir LT 129 . FitzGibbon
L.J. in delivering
the judgment of the Court of Appeal in Ireland said that the argument had been
presented "with such marked ability
that we almost regret to be obliged to
pronounce it fallacious". With much the same regret I reach the same
conclusion on the present
contract. The words of FitzGibbon L.J. are
applicable to this contract: "The contractor having broken his contract, was
out of
it altogether, except as regards what was or might be due under interim
certificates and his liability for delay, and what might
be due if the work
was completed" (1898) 32 Ir LT, at p 130 . (at p523)
5. So there is no comfort for the appellant in this, its primary, argument.
But a second argument was presented. It is submitted
that cl. 43.3 is a
clause which confers on the appellant a contractual right in aid of the early
completion of the contract whereby
delays that would otherwise take place may
be reduced, delays which would arise if the appellant or a new contractor
could not use
the plant and materials already on the site. The existence of
the right, it is argued, is something which is likely in the ordinary
course
to reduce the damages otherwise payable by the respondent. (at p523)
6. In my view these submissions are correct so far as I have stated them.
The appellant would go further and submit that therefore
no question of relief
against forfeiture or penalty can ever arise. I am not satisfied that this is
correct. The provision for
use of the plant is a contractual provision in aid
of the appellant getting the work completed. As such, it cannot be impugned.
Equity may relieve against the forfeiture without compensation or allowance of
the respondent's right to possession of the plant
during the period of
completion of the works but it does not follow that the only relief which
equity may grant is the avoiding of
the appellant's right to the use of the
plant during the period of completion of the works. It cannot be determined
whether equity
will relieve against such a forfeiture until it is known
whether the forfeiture in fact results in an impermissible burden or penalty
having been imposed on the respondent. There could only be such a burden or
penalty if the works are completed for a smaller outlay
than would have been
payable by the appellant to the respondent if he had completed the work. If
they are not, then there could
be no occasion for equity to interfere. The
additional cost of the works to the appellant payable by the respondent under
cl. 43.3
would have been reduced by the fact that the appellant had used the
plant and materials instead of incurring the cost of obtaining
other plant and
materials. In the possible but hardly probable event that the works should be
completed for a sum less than the
original contract price, the question would
arise, and only then would arise, whether equity would treat the provision in
cl. 43.3,
that no compensation or allowance should be made, as impermissibly
penal and would interfere by declaring that provision void and
would require
upon a final account that compensation or allowance for the use of the plant
and materials be made by the appellant
to the respondent. It may be that
equity would not allow the appellant to make a profit from the respondent's
breach of contract.
A court of equity can mould its relief so that the
substantial purpose of its doctrine of relief against forfeiture and penalties
is achieved. It can leave the contractual right to use the plant and
materials unaffected and can avoid that part and that part
only of the
agreement between the parties which is, or may be, open to challenge under the
equitable doctrine. Whether or not there
is substance in the challenge is at
this stage hypothetical. (at p524)
7. I would therefore allow the appeal in respect of this issue. Otherwise I
would dismiss the appeal. (at p524)
ORDER
Appeal allowed.
Order of the Supreme Court of New South Wales set aside and in lieu thereof
declare that the appellant is not entitled to detain
from the respondent and
or put to its use constructional plant of which the respondent is not the
owner and order that the appellant
forthwith take all such steps, or cause to
be done all such things, as are necessary to effect delivery to the respondent
of all
items of constructional plant and equipment, set forth in the schedule
to the order of the Supreme Court, of which the respondent
is not the owner.
Defendant to pay plaintiff's costs of the suit.
AustLII:
|
|
|
URL: http://www.austlii.edu.au/au/cases/cth/HCA/1976/3.html