You are here:
AustLII >>
Databases >>
Federal Magistrates Court of Australia >>
2009 >>
[2009] FMCA 319
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Keldote Pty Ltd & Ors v Riteway Transport Pty Ltd [2009] FMCA 319 (5 May 2009)
Last Updated: 6 May 2009
FEDERAL MAGISTRATES COURT OF AUSTRALIA
KELDOTE PTY LTD & ORS
v RITEWAY TRANSPORT PTY LTD
|
|
INDUSTRIAL LAW – Unfair contracts –
Independent Contractors Act 2006 – contract varied –
variation having element of retrospectivity – variation should not go
beyond what is necessary
to remedy the unfairness identified – discretion
to make no order.
COURTS & JUDGES – Independent Contractors Act 2006 –
Court has jurisdiction to review contracts which are no longer on foot at the
time the application for review is filed.
|
|
Respondent:
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
|
Applicant:
|
L & D LOWE TRANSPORT PTY LTD
|
|
Respondent:
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
|
File Number:
|
SYG 2354 of 2007
|
|
Applicant:
|
TAMBO WATERS PTY LTD
|
|
Respondent:
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
|
File Number:
|
SYG 2431 of 2007
|
|
Hearing date:
|
31 March 2009
|
|
Date of Last Submission:
|
22 April 2009
|
REPRESENTATION
Counsel for the
Applicant:
|
Mr I. Latham
|
|
Solicitors for the Applicant:
|
Turner Freeman
|
Counsel for the Respondents:
|
Mr A. Moses SC
|
Solicitors for the Respondents:
|
Blake Dawson
|
ORDERS
(1) In respect of each applicant’s contract with
Riteway Transport Pty Ltd, the fourth paragraph of clause 5 of the Riteway-TWU
agreement be varied as from the time when the contract was made by inserting
after the sentence ending with the words “8 years”
the following
words:
- Where the
requirement to update a vehicle results in, or is likely to result in, an
increase in the Contract Driver’s operating
expenses, that requirement
will be subject to, and unenforceable in the absence of, agreement between the
Company and the Contract
Driver on a trip rate to be applicable to the use of
the new vehicle.
(2) The matters stand over for consideration of the applicants’ claims for
damages and
injunctions.
FEDERAL MAGISTRATESCOURT OF AUSTRALIA
ATSYDNEY
|
SYG 2353 of 2007
Applicant
And
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
Respondent
SYG 2354 of 2007
|
L & D LOWE TRANSPORT PTY LTD
|
Applicant
And
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
Respondent
SYG 2431 of 2007
Applicant
And
|
RITEWAY TRANSPORT PTY LTD T/AS RITEWAY EXPRESS
|
Respondent
REASONS FOR JUDGMENT
Introduction
- In
these proceedings for relief pursuant to the Independent Contractors Act
2006 (“ICA”) the applicants alleged that the contract which each
of them held with the respondent (“Riteway”)
was unfair. At this
point it should be noted that each of the applicants’ contracts contained
written terms derived from an
agreement between Riteway and the Transport
Workers’ Union dated 1 April 1998 (“Riteway-TWU agreement”).
- In
the reasons for judgment of 22 August 2008 in an earlier stage of these
proceedings (“principal judgment”), relevant
facts were summarised
as follows:
- The
applicants provided linehaul trucking services to the respondent
(“Riteway”) and, prior to the cessation of that
relationship on 23
August 2007, had done so for a number of years. In early 2007 Riteway advised
the applicants that in place of
the vehicles they were then using, it required
each of them to provide a 12 pallet roll-back tautliner lead trailer and a 22
pallet
drop deck mezzanine tautliner rear combination B/double trailer. Riteway
indicated that should the applicants not comply with its
wishes then “the
last journey that [they] would be required to undertake for Riteway would depart
on Thursday, 23 August 2007”.
- Negotiations
to implement Riteway’s requirements were unsuccessful and agreement to
change vehicle configurations was not reached.
(Keldote Pty Ltd &
Ors v Riteway Transport Pty Ltd [2008] FMCA 1167 at [1]- [2])
- Relevantly
for current purposes, in their amended applications each of the applicants
sought the following order:
- 4. That the
term of the contract allowing the respondent to compel the purchase by the
applicant of new equipment be varied to provide
that the respondent shall pay
adequate compensation for the purchase by the applicant of that equipment being
the net cost of that
new equipment.
- In
the principal judgment I found that the contracts between Riteway and the
applicants were unfair because they entitled Riteway
to impose unilaterally, and
without making financial compensation to the applicants, a significant change to
the equipment required
to service the contracts: at [104] and [107].
- When
considering how the contracts might be varied in order to alleviate that
unfairness, I said:
- I have
concluded that the contracts were unfair because they permitted Riteway to
require the applicants to renew their vehicles
with replacements which were
materially different from the vehicles which had previously been acceptable, and
did not require Riteway
to make a commensurate increase in payments to the
applicants such that the necessary additional expenses would be offset by such
increased payments. Having reached that conclusion, and having regard to the
principles set out above at [96], it is appropriate
that I exercise the power
which the ICA confers on the Court to address that unfairness and that I make an
order which places the
parties on a footing such that the unfairness I have
identified no longer obtains. With this in mind, I conclude that clause 5 of
the Riteway-TWU agreement should be varied in each of the applicants’
contracts so that Riteway’s power to require the
applicants to replace
their vehicles is limited to a power to require replacement of like with
like.
- The
applicants suggested or sought various alternative orders which would involve
complex and impractical terms providing for the
calculation of the cost of any
change required under the contracts. In my view, the better approach would be a
variation of the
contract preventing Riteway from unilaterally imposing a
material change in vehicle specifications.
- Consequently,
in respect of each applicant’s contract with Riteway the fourth paragraph
of clause 5 of the Riteway-TWU agreement
will be varied as from the time when
the contract was made by inserting after the word “vehicle” where
second appearing
the following words:
- having
specifications reasonably equivalent to the vehicle to be replaced. (at
[138]-[140])
- Based
upon that reasoning the Court made the following orders:
- (1) In
respect of each applicant’s contract with Riteway, the fourth paragraph of
clause 5 of the Riteway-TWU agreement be
varied as from the time when the
contract was made by inserting after the word “vehicle” where second
appearing the following
words:
- having
specifications reasonably equivalent to the vehicle to be
replaced.
- (2) The
matters stand over for consideration of the applicants’ claims for damages
and injunctions.
- After
the publications of my reasons on 22 August 2008 and the making of the orders
quoted above at [6], Riteway filed an application
in a case for the first order
to be set aside on the basis that it had been neither sought by the applicants
nor foreshadowed by
the Court. Argument on that application took place on 25
November 2008. Having considered the matters put by Riteway and the applicants
I concluded that in making that order the Court had indeed denied Riteway
procedural fairness. By further order made on 16 December
2008 it was set aside:
Keldote Pty Ltd & Ors v Riteway Transport Pty Ltd (No.2) [2008] FMCA
1623.
- The
matter is now before the Court on the question of what orders, if any, the Court
should make consequent upon its finding that
the contracts between the
applicants and Riteway were unfair.
Submissions
- The
applicants submit that the identified unfairness would be corrected if, in each
of their contracts with Riteway, the fourth paragraph
of clause 5 be varied as
from the time when each contract was made by inserting the following
term:
- In the
event that Riteway requires the contractor to upgrade their vehicle from
operating in a single trailer configuration to operating
in a B-Double
configuration effective from about 23 August 2007, then Riteway shall increase
the trip payment made to the contractor
by $265.11 per trip between Sydney and
Melbourne or Melbourne and Sydney.
In the alternative,
the applicants seek an order in terms of order 1 made on 22 August 2008 which
was set aside on 16 December 2008.
Leave to amend the application accordingly
was granted.
Order proposed by applicants
- The
applicants submit that their proposed order ameliorates the identified
unfairness while making the least change to the contract.
This was on the basis
that, as it had been found at [107] of the principal judgment that
each
- ...
contract was unfair because it entitled Riteway to impose unilaterally and
without making financial compensation to the applicants,
a significant change to
the equipment required to service the contracts,
the
simplest way to ameliorate unfairness was to require a commensurate adjustment
of the amount the applicants were paid for each
trip between Sydney and
Melbourne (“trip rate”).
- The
applicants submitted that $265.11 was the appropriate figure by which to
increase the trip rate. This sum was said to be based
on a combination of
figures found in the evidence given by Mr Kent of Riteway as to the increased
cost to the drivers of a one-way
trip, combined with amounts derived from other
evidence concerning repair and maintenance costs and concerning return on
investment,
at the lowest estimates for those items.
- The
applicants conceded that the order they now seek is of the same type as proposed
order 4 of the amended application but amended
with the aid of the evidence
given at the trial to reflect the “net cost of the new vehicle”
amortised over its life.
- Riteway
opposed the applicants’ proposed order, submitting that it:
- called
into question the Court’s evidentiary findings as to the amounts which the
applicants said they would accept to upgrade
to B/double trailers;
- was
inconsistent with the principal judgment;
- was
contrary to the ICA in that no attempt had been made to explain how it was
unfair that a term in the form of the proposed order
had not been included in
the contracts when they were made;
- was
an attempt to seek a notional or fictional variation and had nothing to do with
the alleged unfairness of which the applicants
had complained; and
- fell
foul of estoppel by record principles in that the claim made in proposed order 4
of the amended application had been rejected
by the Court.
- Riteway
further submitted that the variation proposed by the applicants bore no
relevance to the unfairness found and, in any event,
was unsupported by
evidence. In this regard, Riteway observed that none of the applicants had said
that they would upgrade their
vehicles to B/doubles in exchange for an
additional $265.11 per trip. It was submitted that the evidence indicated that
the applicants
would not have accepted less than $1,500 per trip. At that time
they were being paid $1,194 for driving the route with the configuration
they
then had (see principal judgment at [27]).
The order made by the Court on 22 August 2008
- The
applicants submitted in the alternative that the order made on 22 August 2008
addressed the unfairness identified in the principal
judgment. However, it was
conceded that that order might go further than was necessary in that it
potentially prevented Riteway
from being able to compel an upgrade even were it
to provide for payment of fair compensation.
- Riteway
adopted the applicants’ submission that the order made on
22 August
2008 went further than was necessary, saying that it put the respondent at a
disadvantage when it came to termination of
contracts. It was submitted, by
reference to an outline of submissions filed on
23 October 2008 in an
earlier stage of the proceedings, that the Court’s finding on 22 August
2008 did not empower it to stop
Riteway giving reasonable notice of the contract
coming to an end in the event that the applicants did not wish to upgrade their
vehicles, or the parties were unable to agree on rates.
- Moreover,
it was submitted that the words
- ... having
specifications reasonably equivalent to the vehicle to be
replaced,
which were interpolated into cl.5 of the
Riteway-TWU agreement by order 1 made on 22 August 2008, were not sufficiently
certain for
the parties to know what their respective rights were. It was
submitted that such words would lead to disputes and, if agreement
were not
reached as to what was reasonably equivalent or what increased trip rate should
apply to the new vehicles, Riteway would
bear an unfair burden of having to
terminate the contracts of drivers who would not upgrade their vehicles.
No order
- Riteway
also submitted that it was open to the Court to make no order consequent upon
its finding of unfairness. Riteway argued that
it had not sought to impose a
change to B/double trailers unilaterally or without compensation. It pointed out
that it had entered
into negotiations about compensation and gave the applicants
six months’ notice of its intention to change the configuration
of the
vehicles servicing the Sydney-Melbourne route. Riteway submitted that six months
was a reasonable period in which to reach
an agreement on compensation and on
whether the applicants “wished to replace their vehicles in accordance
with their contracts
or not”. It was argued that Riteway’s conduct
was such that the unfairness identified in the contract was, in effect,
illusory, because the parties were already operating on the footing that Riteway
could not require a change in vehicles without providing
compensation or a
reasonable period within which to negotiate it.
Further submissions
- After
judgment was reserved on 31 March 2009, Riteway’s solicitors wrote to the
Court advising that a matter of potential legal
significance had come to their
attention which they felt obliged to raise with the Court. This issue, which had
been raised by neither
party at any earlier stage of the proceedings, was the
construction of s.16(4) of the ICA and whether the Court could make an order
which had retrospective effect. Subsection 16(4) provides:
- (4) An
order takes effect on the date of the order or a later date specified in the
order.
- The
parties were given leave to file further written submissions limited to that
issue.
- The
applicants submitted that the issue had previously been dealt with in Re
Dingjan; Ex parte Wagner [1995] HCA 16; (1995) 183 CLR 323 and in Gerrard v Mayne
Nickless Ltd (1996) 135 ALR 494, the latter being a decision of the Full
Court of the Industrial Relations Court. The applicants submitted that those
authorities
showed that not only could the Court vary contracts which had been
terminated prior to the commencement of proceedings and contracts
which were
terminated after proceedings commenced, but that an order in respect of such
contracts would inevitably but validly have
a retrospective aspect.
- Riteway
submitted that the Court’s power under the ICA to make an order varying a
contract did not extend to making an order
purporting to come into effect before
the date on which the order was made. It submitted that the variation sought by
the applicants
required an order having a retrospective operation but that this
would contravene s.16(4). Riteway further submitted that Re Dingjan; Ex parte
Wagner and Gerrard v Mayne Nickless ultimately only supported the
proposition that the Court has power to vary a contract that is no longer on
foot, which did not address
the question of the date on which an “order
takes effect”. Riteway submitted that the ICA only empowered the Court to
make an order which had effect from the date of the order and that while the
Court might vary a contract that has already been terminated,
such a variation
could only take effect prospectively.
Consideration
- As
already stated, the Riteway-TWU agreement was found to be unfair because it
entitled Riteway to impose unilaterally and without
making financial
compensation to the applicants a significant change to the equipment used to do
the work required by the contracts.
Having made such a finding the Court is
empowered to make an order under s.16(1) of the ICA setting aside or varying the
contracts.
- The
principal relief now sought by the applicants proposes that the unfairness
identified by the principal judgment be addressed by
amending the contracts to
increase the trip rate by a specified amount. This approach confronts a
significant difficulty. This difficulty
is that the evidence before the Court
concerning the additional cost to the applicants of running B/double trailers in
place of the
equipment they were using is not sufficiently clear or detailed to
draw any particular conclusion as to the proper quantification
to be made of
that expense. Nor, given the way the case was presented and argued in the
hearing preceding the principal judgment,
could the Court confidently base any
calculation on a combination of Mr Kent’s evidence and the other evidence
to which the
applicants have referred. Consequently, to the extent that the
order proposed by the applicants provides for a specified increase
in the trip
rate, the Court is unable to conclude that the figure they have identified
accurately quantifies the additional expense
which would have been incurred by
the applicants had they complied with Riteway’s requirement to upgrade
their vehicles.
- In
essence, the applicants’ current proposal fails adequately to address the
shortcomings of the order sought in para.4 of the
amended application. That
original proposal failed to provide for a mechanism by which the parties to the
contract could quantify
the additional costs which Riteway’s requirement
was to impose upon the applicants while this new proposal provides for a figure
purporting to quantify that amount but which is not adequately supported by the
evidence.
- The
applicants’ alternative proposal is that the order originally made by the
Court on 22 August 2008 be made again. However,
I accept Riteway’s
submissions that that order presented difficulties in that its requirement that
a new vehicle was to have
“specifications reasonably equivalent to the
vehicle to be replaced” lacked certainty and specificity. I also accept
Riteway’s submission that such a formulation would be likely to produce
disputes.
- However,
Riteway’s proposal that no order need be made cannot be accepted. The
submissions advanced by Riteway in support of
the proposal that the Court make
no order turned on its conduct in 2007. In effect Riteway submits that, as the
contract worked out
in 2007, any unfairness it demonstrated was negated by the
way Riteway sought to effect the change to B/double trailers. However,
these
proceedings are not concerned, at least at this stage, with Riteway’s
conduct in 2007. They are concerned with whether
the contract was unfair or
harsh at the time when it was made. Riteway’s conduct in 2007 can have no
bearing on this.
- Even
so, Riteway’s conduct in 2007 might suggest that in the exercise of its
discretion the Court should not make an order pursuant
to s.16(1) because no
practical unfairness was suffered by the applicants. In this regard, it should
be kept in mind that Riteway’s insistence
on its right to impose a change
in vehicles without an agreement with the applicants on an increase in the trip
rate which adequately
addressed the increased expenses which were the necessary
concomitant of such a change, led to a lack of agreement regarding the
change
and to Riteway’s insistence that the applicants had repudiated their
contracts. Having concluded that the contracts
were unfair because of the
unilateral power they afforded Riteway, and given that it was the exercise of
that power which led to
the termination of the applicants’ business
relationships with Riteway, I decline to exercise my discretion to refuse to
make
an order addressing the unfairness I have identified.
- Consequently,
I do not accept the submission that the Court should make no orders in these
matters.
- Consideration
must now turn to what order would remedy the unfairness which has been
identified. Section 16(1) of the ICA provides:
- (1) If
the Court records an opinion under section 15 in relation to a services
contract, the Court may make one or more of the following orders in relation to
the opinion:
- (a) an
order setting aside the whole or a part of the contract;
- (b) an
order varying the contract.
Section 16(2)
provides:
(2) An order may only be made for the purpose of placing the parties to the
services contract as nearly as practicable on such a
footing that the ground on
which the opinion is based no longer applies.
- Section
12(3) of the ICA restricts the Court, when reviewing a services contract, to
having regard to the terms of the contract “when it
was made” or to
other matters which existed “at the time when the contract was
made”. That is to say, unfairness
or harshness must be assessed at the
time the contract was made, not at any later point. It was in the context of
these statutory
limitations that the Court found that the applicants’
contracts with Riteway were unfair.
- These
considerations suggest that any setting aside or variation of the contracts
which the Court considers necessary would be best
made effective from the date
the contracts were made. Different circumstances may dictate different outcomes
but in this case there
seems no reason not to make any variations of the
contracts effective from time when each of them was made.
- In
this regard and notwithstanding Riteway’s submission to the contrary, I
conclude that there is no impediment to the Court
making an order in these
proceedings which has a retrospective quality. It was accepted by majority in
Re Dingjan; Ex parte Wagner that the provisions in the former
Industrial Relations Act 1988 relevantly equivalent to parts of ss.12, 15
and 16 of the ICA (ss.127A and 127B) were not limited in their operation to
contracts which were still on foot. Indeed, in Gerrard v Mayne Nickless
the Full Court of the Industrial Relations Court held at 507 that orders under
s.127B could be made notwithstanding that the contract
then under consideration
had terminated before the application for review had been filed. Further,
addressing the issue of retrospectivity,
the Full Court said in that case:
- Technically,
it is incorrect to say that an order made by the Commission in respect of a
terminated contract has retrospective operation;
s.127B(4) provides that an
order takes effect from its date or a later date specified in the order.
However, in a practical sense,
an order will always involve an element of
retrospectivity. The rights and obligations of parties to a contract crystallise
on termination.
If an order varying the contract is subsequently made, it must
affect those rights and obligations.
(at
505-506)
Significantly for the conclusion that the Court
can make an order which has a retrospective quality, s.127B(4) of the
Industrial Relations Act 1988 was in terms practically identical to those
currently found in s.16(4) of the ICA.
- During
submissions on what would be an appropriate order for the Court to make, Senior
Counsel for Riteway submitted for the Court’s
assistance a form of order
in the following terms:
- In respect
of each Applicant’s contract with Riteway Transport Pty Ltd, the fourth
paragraph of clause 5 of the Riteway-TWU
Agreement be varied as from the time
when the contract was made by inserting after the sentence ending with the words
“8 years”
the following words:
- Where the
requirement to update a vehicle results in, or is likely to result in, an
increase in annual running costs, the Company
and the Contract Driver will
negotiate a revised trip rate to take account of any increase in running costs.
In the event that agreement
cannot be reached as to a revised trip rate, or the
Contract Driver otherwise decides not to upgrade their vehicle as required, the
engagement of the Contract Driver will terminate upon expiry of a period of six
(6) months from the date on which the Company first
gave notice of the
requirement that the Contract Driver update their
vehicle.
With his submissions on the s.16(4)
issue, Senior Counsel for Riteway amended this suggestion by replacing the words
“time when the contract was made” with
the words “date of the
order”.
- Regardless
of the moment when such an order might take effect, this suggestion went beyond
the unfairness in the contract which was
identified in the principal judgment
because the second sentence of the variation proposed sought to deal with
contractual termination
in the event that a new trip rate could not be agreed.
When addressing the applicants’ claims Riteway stressed that no variation
of the contracts should not go beyond what would be necessary to remedy the
unfairness identified: Eagle Boys Dial-A-Pizza Australia Pty Ltd v Clifford
[2003] NSWIRComm 101; (2003) 125 IR 35. I accept that submission, reflecting as it does the
limitation placed on the Court by s.16(2) of the ICA.
- In
submissions, Riteway stressed the business importance to it of being able to
stipulate what vehicles would be used in the performance
of its work. It is
clear that Riteway has a concern regarding its ability to design its fleet. It
is also apparent that it wishes
to have the ability to dispense with the
services of contract drivers who are unwilling to satisfy those business
requirements by
saying, in effect, that any failure to satisfy those business
requirements amounts to a repudiatory breach of the contract which
Riteway
should be able to accept. In essence, Riteway opposed any order which would have
the effect of fettering its power to determine
what vehicles did its work or
which would have the consequence that, if an agreement on a change of vehicles
could not be reached,
it would have to terminate a driver’s contract to
prevent him or her from driving an unacceptable vehicle.
- Riteway
is entitled to operate its business in the lawful manner most suitable to it
including by, from time to time in accordance
with cl.5 of the Riteway-TWU
agreement, stipulating the sort of vehicles used to perform its work. It is not
unfair that contract
drivers should meet such requirements. What is unfair is
that drivers already performing that work at agreed rates should be required
to
meet such stipulations without being entitled to compensation for the additional
expenses which they might thereby incur.
- Riteway’s
focus on the need for it to have a mechanism to dispense with noncompliant
contract drivers, by its counsel raising
for consideration the form of order set
out above at [34] or alternatively by submitting that cl.5 of the Riteway-TWU
agreement should
be left unamended, betrays a desire to remain in effective
control of the change of vehicle issue and to have the power to make “take
it or leave it” offers to its contract drivers. As found in the principal
judgment, that is unfair. While it might be arguable
that the contract is unfair
because it does not make provision for termination on notice, that is not an
issue before the Court.
The only matter which the Court is currently required to
address is the unfairness in the contracts which was identified in the principal
judgment.
- Having
rejected the applicants’ proposed order and having concluded that the
order made on 22 August 2008 ought not be made
again, it is necessary that a
different order be formulated. In light of the principles set out at [96] of the
principal judgment
and the matters canvassed during submissions in this latter
stage of the proceedings, I have concluded that the most appropriate
order is
one which recognises Riteway’s legitimate wish to, from time to time,
change the vehicles in its fleet while requiring
that any such change be
consensual. Having regard to the fact that the applicants ran only the
Sydney-Melbourne route and thus a
single rate applied to their work, I am of the
view that an order to the following effect would address the unfairness
identified
by the principal judgment in the way contemplated by s.16(2) of the
ICA:
- In respect
of each applicant’s contract with Riteway Transport Pty Ltd, the fourth
paragraph of clause 5 of the Riteway-TWU
agreement be varied as from the time
when the contract was made by inserting after the sentence ending with the words
“8 years”
the following words:
- Where the
requirement to update a vehicle results in, or is likely to result in, an
increase in the Contract Driver’s operating
expenses, that requirement
will be subject to, and unenforceable in the absence of, agreement between the
Company and the Contract
Driver on a trip rate to be applicable to the use of
the new vehicle.
- There
will be an order to that effect in each of the proceedings, together with
further orders that each matter stand over for consideration
of the
applicants’ claims for damages and injunctions.
I certify
that the preceding forty (40) paragraphs are a true copy of the reasons for
judgment of Cameron FM
Associate:
Date: 5 May 2009
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/cth/FMCA/2009/319.html