![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Federal Court of Australia |
Last Updated: 12 February 2003
IN THE FEDERAL COURT OF AUSTRALIA |
|
NEW SOUTH WALES DISTRICT REGISTRY |
THE COURT ORDERS THAT:
1. The parties bring in short minutes of orders to give effect to these
reasons.
2. Further hearing to consider the question of costs is adjourned to a date to
be fixed.
Note: Settlement and entry of orders is dealt with in Order 36 of the Federal
Court Rules.
IN THE FEDERAL COURT OF AUSTRALIA |
|
NEW SOUTH WALES DISTRICT REGISTRY |
JUDGE: |
FINN J |
DATE: |
12 FEBRUARY 2003 |
PLACE: |
CANBERRA |
"One commonly practiced form of emulation is interface emulation, used where one hardware/software sub-system (A), which interacts, inter alia, with another (B), needs, for whatever reason, to be fully tested before B is available. A can still be tested, before B is available, if one develops an interface emulator for B, which mimics some or all of the interactions between A and B, as defined in an interface specification, but has none of the functionality required of B itself. From A's point of view, an interface is all it ever sees of B and if this behaves correctly then A can be fully tested. For example, if A has to send a signal to B, initiating a particular B-mediated event and then pause until it receives an acknowledging signal back from B - indicating that the B-mediated event, however complex, has taken place and is satisfactorily completed - before it (A) can proceed further, all the interface emulator has to do is mimic the acknowledgment. From the point of view of testing A's functionality it is irrelevant as to whether or not the B-mediated event actually took place."
22 The term "test harness" is used in the contractual documentation in a way
which is synonymous with emulation.
PART I:
A THE ADCNET CONTRACTS
23 Save as to parties the Commonwealth/BHP-IT contract ("the Head Contract")
and the BHP-IT/GEC Marconi contract ("the Sub-Contract")
were at the time of
their execution relevantly identical save where I indicate to the contrary. As
the principal claims made in
the proceeding relate to the latter agreement,
reference here will be made to its provisions alone. As some provisions of the
contract
are relevant only to a particular claim I will defer detailed
reference to those provisions until that claim is considered.
24 In the Sub-Contract BHP-IT was referred to as "the Customer" and GEC Marconi
as "the Contractor". The contract recitals stated
that:
"1. The Customer wishes to procure the supply of software development services and the integration of the System in accordance with this Contract; and
2. The Contractor has agreed to supply the software development services and integrate the System in accordance with the provisions of this Contract."
25 The "System" so referred to was defined in cl 1.1 to mean "the working
system which complies with this Contract and comprises the
CSE and CSI". The
same clause defined "CSE" to mean Contractor supplied equipment. "CSI", a
subject matter important to GEC Marconi's
claim, was defined to mean "the
Customer supplied items to be supplied by the Customer under this Contract and
referred to in clause
7".
26 Clause 7, insofar as presently relevant, imposed the obligation on the
Customer to supply the CSI: cl 7.1; and then provided
in cl 7.2 that:
"CSI specified in Schedule 6 shall at the time of its supply by the Customer to the Contractor comply with the specifications, if any, set out in Schedule 6."
Schedule 6, which was one of sixteen schedules to the contract, listed and provided for the provision of the CSI. The "Stubs devices and related equipment and software" were identified in cl 1.4(b) of the Schedule to be part of the "Test and Integration/Acceptance Test System". I would note in passing that cl 1.2 of the same Schedule provided in part that:
"CSI shall include the equipment and non-Developed Software as defined in subclause 1.4 below ... [s]uch equipment and non-Developed Software may be subject to change as a result of revising the Preliminary Architecture Design Document for the purposes of preparing the Final Architecture Design Document": emphasis added.
Further reference will be made to the Architecture Design Document ("the
ADD") below.
27 Clause 1.1 of the Contract defined "Integration" in respect of the System to
include the integration services set out in Schedule
4. That Schedule listed
"Contractor Supplied Services and Charges". Clause 1.1 of the Schedule
provided:
"The Contractor shall provide the following services.
...
(c) Integration of the Developed Software with the following CSI operating on Hewlett-Packard's UX BLS operating system (version 9.08) or Hewlett-Packard's UX operating system (version 9.04):
...
(iv) Security Equipment
The Security Equipment shall consist of Stubs devices, designed and manufactured in accordance with the Stubs Requirements Specification (reference 1403.01.004)."
28 The "Developed Software" referred to in cl 1.1(c) was defined in
cl 1.1 of the Contract to mean "the software that is
to be developed and
supplied in accordance with this Contract and includes any associated
integration services". Further reference
will be made to this software
below.
29 Clauses 4 and 5 of the Contract stipulated particular obligations of the
Contractor and Customer respectively. Clause 5 provided
(inter alia):
"5.1 The Customer shall take all reasonable measures to maintain the processing environment as constituted by the elements of the CSI.
...
5.3 The Customer shall supply the CSI in accordance with clause 7 and shall perform its obligations specified in the Project Plan and the Implementation Plan pursuant to subclause 10.1.
...
5.6 Except where otherwise provided for in the Contract, the Customer, Delegate, Project Officer and Supervisor agree that in the exercise of any obligation, function or power imposed or conferred on them under this Contract they will:
(a) act in a fair and reasonable manner; and
(b) act within the time prescribed under this Contract or, where no time is prescribed, within a reasonable time."
30 I would note in passing of cl 5.6, first, that all of the persons
referred to there other than the Customer are defined to
be officers of the
Customer in cl 1.1 of the Contract; and, secondly, that the Contract did
not expressly impose a like obligation
on the Contractor in exercising its
obligations etc under the Contract.
31 The "Project Plan" and "Implementation Plan" referred to in cl 5.3 of
the Contract were each defined in cl 1.1. "Project
Plan" meant the
project plan set out in Schedule 7. That Schedule summarised the
responsibilities of the Commonwealth, the Customer
and the Contractor in Table
7.1 which itself designated the "Supply and maintenance of all hardware
(including STUBS) and COTS software"
to be the responsibility of the
Commonwealth. I would note in passing that "COTS software" was Commercial Off
The Shelf software.
Clause 1.1 of the Schedule - incorrectly described as cl
2.1 in the Schedule - concluded with the observation in the BHP-IT/GEC
Marconi
contract (though not in the Commonwealth-BHP-IT contract) that:
"Any responsibility identified in Table 7.1 as Commonwealth shall be assumed by the Customer [ie by BHP-IT]."
Table 7.2 of the same Schedule provided a timetable for the delivery of CSI items. Insofar as it related to STUBS, it provided:
Reference |
CSI Description |
Date required to be provided to Contractor |
... |
||
3 |
Detailed
Software Interface Specification for Stubs Untrusted Workstation/Server
Software |
1/12/94 |
4 |
Stubs Untrusted Workstation and Server Software |
01/04/95 |
... |
||
10 |
Stubs equipment and associated software |
01/08/95 |
It is unnecessary at this point to explain what was comprehended by the various
items described in the Table.
32 Two other responsibilities of the contractor set out in the Project Plan
which are of relevance were:
"WP2100 Requirements and Design Maintenance
Updating of the Customer's Functional Specifications, CSCI Software Requirements Specification and the Architecture Design Document to incorporate approved Contract Amendments. This work involves the preparation of the changes to the Document, internal review and approval of the changes with the Customer and the incorporation of the changes.
WP4500 Development of any Test Harnesses required for CSCI and acceptance testing."
33 The "Implementation Plan" referred to in cl 5.3 of the Contract was
defined to mean "the time schedule for the performance
of this Contract set out
in Schedule 8". Reference will be made to that Schedule in detail when
considering the specific GEC Marconi
claim that BHP-IT failed to pay Milestone
4000.
34 Clause 7.1 of the Contract provided that after delivery of the CSI at the
times and places stated in the Project Plan:
"the Contractor shall incorporate the CSI into the System or utilise the CSI in the integration of the System in accordance with the Customer's Functional Specifications."
The "Customer's Functional Specifications" were defined in cl 1.1 of the Contract to mean the specifications "set out or identified in Schedule 1". That Schedule indicated that the relevant specifications were:
"(a) Functional Requirements Specification (Version 3.0);
(b) Preliminary Architecture Design Document (Version 1.0)."
35 The Functional Requirements Specification ("the FRS") to which it will be
necessary to refer on a number of occasions in these
reasons is of central
importance in GEC Marconi's claim based on the non-provision of STUBS. I have
referred already to the purpose
of the FRS: see "The Language and Processes of
Software Development". The Architecture Design Document ("the ADD") described
the
architecture of Release 3 of the ADCNET system. It identified the hardware
and software components of the system and described how
they were to be
configured to meet the requirements set out in the FRS.
36 Clause 9 of the Contract dealt with "Supply and Integration of the System".
Five sub-clauses require mention. They are:
"9.1 The Contractor shall, if necessary with the assistance of the Customer, prepare a specification known as the Final Architecture Design Document for all parts of, and the whole of, the System before the Developed Software is supplied.
9.2 The specification referred to in subclause 9.1 shall be submitted to the Customer for review and subsequent acceptance or otherwise in accordance with the dates specified in the Implementation Plan.
9.3 The Customer's assistance in preparation of any specifications under this Contract, or giving approval of any specifications prepared by the Contractor, shall not vary or limit in any way whatsoever the Contractor's obligations under this clause or the Contract to supply the Developed Software or integrate the System in accordance with the Contract.
9.4 The System shall be integrated in stages in accordance with the Contract, including the Project Plan and the Implementation Plan.
...
9.6 The Contractor shall integrate the System in accordance with the Contract Specifications."
37 Clauses 9A to 9D provided for the development, delivery and installation of the Developed Software. Reference need only be made to cl 9B and this for the purpose of indicating the documentary hierarchy it ordains. I will refer further below to the hierarchy in contractual documentation. Clause 9B provided:
"The Developed Software supplied by the Contractor shall conform to:
(a) the Customer's Functional Specifications [ie the FRS and the ADD]; and
(b) the specifications and representations in respect thereof, including the Developed Software Detailed Design Specification, communicated specifically by the Contractor to the Customer in writing;
and to the extent that there is any inconsistency between the specifications referred to in paragraph (a) and those referred to in paragraph (b), those referred to in paragraph (a) shall, to the extent of any inconsistency, be deemed to be the specifications to which the Developed Software supplied by the Contractor must conform."
38 It should be noted in passing that cl 27 of the Sub-Contract vested
in the Commonwealth title to, and intellectual property
rights in, the
Developed Software "upon its creation". The Sub-Contract, further, obliged the
Contractor to supply Services and
the Developed Software which complied with
the standards set out in the SDP and any subsidiary documents to it:
cl 55, Schedule
3.
39 After the Developed Software had been delivered and installed on the
prescribed equipment (which included the "Security Equipment":
see above
Schedule 4 cl 1.1), it was to undergo acceptance testing. Provision for
this was made in cl 9E of the Contract.
I would again note in passing
that issues relating to the possible acceptance testing of the Developed
Software in the absence of
the STUBS devices have loomed large in this
proceeding.
40 Clause 9E.0.1 provided in part:
"The Acceptance Tests shall be carried out in accordance with the test cases as agreed between the Customer and the Contractor and based on the Testing and Acceptance Criteria as defined in Schedule 9. The Contractor is responsible for testing the Developed Software and those aspects of the CSI with which the Developed Software interfaces, and to reasonably demonstrate that the remaining software components of the CSI are unaffected as a result of the integration of the Developed Software with the CSI."
The Acceptance Test was to be "conducted on the System" although all that
the Customer would then accept from the Contractor was the
Developed Software
only: cl 9E.0.2.
41 The Contract, it should be noted, made express provision for what courses
could be taken if during a specific Acceptance Test
"a failure occurs which is
due to a defect in the CSI": cl 9E.3.5A. One possible course was the
Acceptance Test to be deemed
to have been passed.
42 Clause 9E.5 dealt with the Acceptance Tests. It provided, in part, that:
"9E.5.1 The Contractor shall prepare a Test Plan and Test Descriptions in accordance with the Testing and Acceptance Criteria as set out in Schedule 9 for approval by the Customer prior to commencement of the Acceptance Tests.
...
9E.5.3 The System shall be tested in accordance with the relevant Test Plan and Test Descriptions. ...
9E.5.4 The Acceptance Tests for the Developed Software shall, unless otherwise specified in the Test Plan, be carried out by the Contractor in accordance with the Project Plan, Implementation Plan and Test Plan and shall demonstrate to the Customer and the Commonwealth that the Developed Software integrated with the CSI meets the Customer's Functional Specifications."
Express provision was made for what was to occur "[w]here the System [did]
not meet the performance Acceptance Tests as referred to
in ... Schedule 9".
43 Schedule 9 was entitled "Testing and Acceptance Criteria" and it specified
the criteria to be used to develop an Acceptance Test
Plan ("ATP") and Test
Descriptions for "acceptance of the System": cl 1.1. Clause 2.2.1,
relating to Qualification Testing
provided:
"The qualification of the Developed Software shall be based on the adherence of the software development to the testing and quality provisions as defined in the Software Development Plan together with a series of Acceptance Tests which will demonstrate that the software complies with the Functional Requirements Specifications. These Acceptance Tests will be for specific test cases only and will be designed to show that the Developed Software complies with testable "shall" statements in the Functional Requirement Specification."
44 Acceptance Testing was thus linked directly to what were described as the
"testable `shall' statements" in the FRS. The language
of the FRS in
describing the individual functions specified for the System used declaratory
and mandatory language: "the system
shall ..."; "an authorised user
shall be able ..."; "the interface shall ..."; "validation
shall"; etc. Such were the "testable shalls" that the test cases were
to demonstrate could be met. It is part of GEC Marconi's case
that, with the
non-provision of STUBS, the testable shalls of the FRS could not all be tested
fully in accordance with the Contract.
45 A provision of some importance in this proceeding is cl 11 of the
Contract. It dealt with "Variations of Contract" and provided:
"11.1 If either Party wishes to vary the Contract, that proposing Party shall submit a copy of the proposed variations to the other Party. The receiving Party shall advise the proposing Party within 10 normal working days, or such other period as is mutually agreed between the Parties, of receipt of the variations either:
(a) that the receiving Party accepts the variations; or
(b) that the receiving Party rejects the variations, and the reasons for such rejection.
11.1A Where the Customer requests the Contractor to assess the feasibility and cost of undertaking a proposed variation, the costs incurred by the Contractor in undertaking the assessment shall be paid for by the Customer in accordance with the time and materials rates as set out in Table 4.3 of Schedule 4. Where the Contactor proposes a variation the costs incurred by the Contractor in assessing the proposal shall be borne by the Contractor.
11.2 If the receiving Party accepts the variations, the Contract Specifications shall be deemed to incorporate the accepted variations from the date upon which the receiving Party notifies the proposing Party in writing that it accepts the variations.
11.3 If the receiving Party rejects the proposed variations, the Contractor and Customer shall jointly use reasonable endeavours to reach agreement on the proposed variation. Where agreement cannot be reached the Contractor shall continue to integrate the System in accordance with the unvaried Contract."
I would draw particular attention in this to the structured process the
clause envisaged and to the reasonable endeavours provision
of cl 11.3.
46 Relatedly, cl 45 of the Contract provides:
"45.1 The provisions of this Contract shall not be varied either in law or in equity except by agreement in writing signed by the Customer and the Contractor.
45.2 A waiver by either Party in respect of a breach of a provision of this Contract by the other Party shall not be deemed to be a waiver in respect of any other breach and the failure of either Party to enforce at any time any of the provisions of this Contract shall in no way be interpreted as a waiver of such provision."
47 The principal defence raised by BHP-IT to GEC Marconi's claim based on
the non-provision of the STUBS devices is that the Sub-Contract
was varied even
if this was not done in accordance with the above provisions of the
Sub-Contract.
48 The Contract made express provision for termination for default by either
party. The provisions relating to termination by the
Contractor were as
follows:
"40.8 Where the Customer is in breach of an obligation under this Contract so that there is a failure by the Customer to perform this Contract, the Contractor may, by notice in writing to the Customer, specify that breach and where that breach is capable of being remedied require the Customer within 32 days of receiving such notice to remedy that breach or commence appropriate action to remedy that breach.
40.9 Where the Customer has not:
(a) remedied the breach referred to in subclause 40.8 within 32 days of receiving a notice (including because the breach was incapable of being remedied); or
(b) commenced appropriate action to remedy that breach within 32 days of receiving a notice and remedied the breach within a reasonable time after that period has elapsed;
the Contractor may, by notice in writing to the Customer, terminate this Contract without prejudice to any right of action or remedy which has accrued or which may accrue in favour of either Party."
49 Again I would emphasise the structured process ordained by the provision.
GEC Marconi invoked this provision in terminating its
contract with BHP-IT.
50 There are five clauses that individually are of significance to particular
claims brought by or against GEC Marconi and of which
mention should be made
here. Clause 16 provided for the making of milestone payments in accordance
with the payment plan provided
in Schedule 8. Clause 17 required the
Contractor to provide an unconditional financial undertaking from an approved
guarantor.
In clauses 36.1 and 36.1A each party respectively agreed to
indemnify the other from designated losses. Clause 38 imposed a damages
cap in
respect of actions between the parties arising out of the operation of the
Sub-Contract. Clause 39 was a liquidated damages
clause.
51 Finally, as is apparent from the above, the contract is premised upon the
existence of, or the creation of, a body of subordinate
documents most being of
a technical character. To obviate problems arising from inconsistency between
the contract and those documents
and between those documents themselves,
cl 2 of the contract specified an order of documentary precedence. It was
as follows:
"2.1 In the event of any inconsistency between the clauses of this Contract, the Schedules to this Contract and the content of any other Document, the order of precedence shall be:
(a) the Clauses of this Contract;
(b) the Schedules to this Contract; and
(c) the content of any other Document.
2.2 In the event of any inconsistency between:
(a) the Customer's Functional Specifications [ie the FRS and the ADD]; and
(b) other Contract Specifications;
the Customer's Functional Specifications shall prevail to the extent of the inconsistency."
B AN INTRODUCTORY OVERVIEW
(1) The Principal Actors
52 There is a very large cast of persons and bodies who participated in the
events to be narrated in this Part. It is useful to
identify the principal
participants at the outset. The evidence to be considered is overwhelmingly
documentary. The persons to
whom I wish to refer were often enough the authors
of documents or of communications that are of central importance to the
resolution
of the issues with which I am concerned.
53 First, DFAT. The Information Technology Branch ("the ITB") of the
Department had direct responsibility for the delivery and development
of the
Department's information technology requirements including the ADCNET project.
The Commonwealth's contract with BHP-IT was
managed from this branch. The
project manager for the Department was Leslie George Cook ("Les Cook"). He
joined DFAT in 1971 with
a background in computing systems and information
technology. He left the Department in 1989 but was engaged by it as a
consultant,
first, to assist in the definition of, and then to manage, the
ADCNET project. He retained the position of project manager until
25 March
2000.
54 The head of the ITB from 1990 to 1996 was Anthony Skinner, who was an
Assistant Secretary (a public service rank in the Senior
Executive Service
("the SES")) in DFAT. A subordinate of his in the ITB was Robert Nichols. Mr
Nichols had worked on the ADCNET
project from 1989. He described himself as an
assistant to Les Cook. He was not a member of the SES.
55 The ITB was one of five branches within the Corporate Services Division
("the CSD") of DFAT. The senior officer of that Division
from 1993 to 1997 was
Robert Cotton, a First Assistant Secretary of the Department. One of his
responsibilities was the oversight
of the ITB. Mr Skinner reported to him. Mr
Cotton in turn reported to Clive (Kim) Jones, a Deputy Secretary of DFAT who
had the
general oversight of three Divisions including the CSD.
56 Secondly, BHP-IT. The company's project manager for the ADCNET contracts
was Kyrill Brent. Mr Brent commenced employment with
BHP-IT in July 1989
having worked in the Australian Public Service since 1966. He participated on
BHP-IT's behalf in the earlier
phases of the ADCNET project that commenced in
1989 and led to the 1994 contract. He ceased to work on the ADCNET contracts
in May
1997.
57 During 1994 and 1995 Ian Dart was BHP-IT's National Manager for Systems
Integration Services and, as such, was responsible for
all systems integration
including the ADCNET project. It was Mr Dart who signed the ADCNET contracts
on BHP-IT's behalf. In 1996
he was appointed Group General Manager of BHP-IT.
Mr Brent reported to him indirectly in this position through his own
superior.
58 Thirdly, GEC Marconi. It was GEC Marconi's predecessor, EASAMS, that first
participated in the ADCNET project being BHP-IT's
subcontractor for the ADCNET
Release 1 contract. That contract was entered into in December 1990. Its
Project Director for EASAMS
from 1991 to 1994 was Roger Cooke. From 1994 to
1997 Mr Cooke was Canberra Branch Manager for GEC Marconi, a position that gave
him responsibility for projects being carried out in Canberra. He was EASAMS'
signatory to the Sub-Contract in 1994 and to GEC Marconi's
contract when the
Sub-Contract contract was novated shortly thereafter.
59 The project manager for that contract from its inception was Peter Wishart.
Mr Wishart had been previously employed by EASAMS
and had worked on the ADCNET
project from 1991 to 1993. He ceased being project manager in January/February
1996 and ceased his
employment with GEC Marconi shortly thereafter. His
successor was Edward Goldsmith who in turn left the project and the company
in
August 1996.
60 The General Manager of the division of GEC Marconi responsible for software
development and systems integration in the period
from September 1994 to
November 1995 was Lindsay Pears. He was replaced then by Ian Sharp. As
General Manager Mr Pears, then Mr
Sharp, were responsible for the conduct of
the ADCNET project. In October 1996 Mr Sharp became managing director of GEC
Marconi.
It was Mr Sharp who terminated the Sub-Contract.
61 Fourthly, the various persons - BHP-IT and GEC Marconi - who made up the
actual ADCNET project team, were physically located at
DFAT's Canberra office
in the Administrative Building until their relocation to the Edmund Barton
Building in September 1996. BHP-IT's
ADCNET staff was of the order of 10
people (including Mr Brent), though some additional BHP-IT staff worked on the
project under
GEC Marconi's direction and control. GEC Marconi's staff was
about 50 persons (including Mr Wishart and then Mr Goldsmith), though
there was
significant fluctuation in the numbers involved.
62 Finally, a note on nomenclature. After its takeover of EASAMS, GEC Marconi
continued to trade as "EASAMS Australia". In consequence
both names have been
used in correspondence and in this proceeding to describe the applicant. In
these reasons I will refer to the
applicant as GEC Marconi save where it would
be an anachronistic to do so. Quotations drawn from documents that refer to
the company
as EASAMS will be left in their original form.
63 To avoid possible confusion I have resorted to the expedient of referring to
DFAT's Mr Cook and GEC Marconi's Mr Cooke as Les
Cook and Roger Cooke
respectively. This follows the course taken during the trial.
64 Distinctly, BHP-IT is commonly referred to in documents as the PSI. This is
an acronym for the description "Prime Systems Integrator".
This usage is
retained in these reasons.
(2) A General Chronology
65 The following is a brief chronological overview of matters relevant to the
GEC Marconi/BHP-IT claims and defences. It should
not be taken as making, or
suggesting, findings on matters that are in issue between the parties.
66 From the early 1970's DFAT embarked on the course of developing computing
systems to automate many of the processes of its secure
Diplomatic
Communications Network. That Network at that time utilised message switching
centres in Canberra, London and Washington
to receive and send electronic
communications to and from overseas posts and governmental agencies. In 1979
the Department commissioned
its first computerised message switch system ("the
IBM message switch") that had been built by IBM.
67 In 1988 DFAT commenced the ADCNET project. As conceived, its first stage
involved the replacement of the existing communications
network (which was used
to carry formal messages, informal messages, telephone, facsimile and data
transmissions) with a single network;
the IBM switch was to be replaced with a
new security system; and secure, modern office automation was to be provided
for communications
staff in overseas posts, regional offices in Australia and
in Canberra.
68 DFAT invited expressions of interest for the design and development of the
ADCNET project in late 1989. In March 1990 BHP-IT
entered into a teaming
arrangement with EASAMS and they began work together on the preparation of a
joint tender in response to a
Request for Tender that had been issued by DFAT.
That tender, submitted around July 1990, was successful. On 13 and 14 December
1990 the Commonwealth and BHP-IT and BHP-IT and EASAMS entered into
back-to-back time and materials contracts. The objects of these
contracts, as
recited in the latter of the two contracts, was to specify, design, develop and
implement Stage 1 of ADCNET.
69 It was envisaged at the time of the contracts that BHP-IT (hence EASAMS) was
to design software to meet the security baseline
defined for the ADCNET system.
Boundary security was, apparently, a part of that baseline. The object of
boundary security was to
prevent classified data being sent from ADCNET
computers to less secure networks as a result of errors in the software or
equipment
of the ADCNET computers or of successful attacks on the ADCNET
computers being made via electronic connections to less secure networks.
This
security was required in addition to `need to know' security mechanisms which
would control access to data stored in the ADCNET
computers by persons with
direct access to terminals connected to those computers.
70 The approach that was to be taken to boundary security resulted, apparently,
from an agreement reached between DFAT and the Defence
Signals Directorate
("DSD"), a unit within the Department of Defence ("Defence"). It required the
development of a security "gateway"
to allow the interconnection of networks.
That gateway involved, first, the use of an encrypted seal which would be added
to the
document to be exported by the person who created or modified that
document, and then the checking of that seal by a gateway computer
before
allowing the export of the document.
71 In mid-1992, DSD advised DFAT that the Defence Science and Technology
Organisation ("DSTO"), another unit within Defence, had
built a prototype
version of what became known as the STUBS devices and that these devices were
likely to offer the most secure means
of providing boundary security for
ADCNET. DFAT was subsequently informed that the STUBS devices were to be
developed as a commercial
product by AWA Defence Industries Pty Ltd ("AWADI").
It then commenced discussions with AWADI concerning the possible use of STUBS
for ADCNET. BHP-IT and GEC Marconi became aware of this development in early
1993.
72 In the course of the time and materials contract, EASAMS designed and
developed what became known as Release 1 of the ADCNET software.
Originally
intended to fall within Stage 2 of the ADCNET project, this Release was of
computer software for ADCNET systems to be
installed at overseas posts. This
appears to have been an accelerated security measure. The process of
installation abroad commenced
in 1992.
73 As part of its work EASAMS also prepared design documents that were to be
used in the next phase of the ADCNET project. Importantly,
in conjunction with
the Commonwealth, it developed the FRS, this being the document that would
govern the requirements for the work
to be done in that phase.
74 In 1993 discussions commenced between the Commonwealth, BHP-IT and EASAMS
concerning the contractual arrangements that were to
obtain for the next phase
of the project. This phase involved the development of what was known as the
Release 3 software and its
integration with the ADCNET system. DFAT advised
BHP-IT and EASAMS that the STUBS devices were the preferred choice for boundary
security. The 1994 contracts were prepared on the basis the Commonwealth would
supply and be responsible for the functionality of
STUBS related hardware and
software and that BHP-IT's (hence GEC-Marconi's) responsibility would be to
integrate the STUBS devices
with the Release 3 software. A schedule to the
resultant contracts (Schedule 7) provided a timetable for the Commonwealth's
delivery
of (inter alia) STUBS related items, the first element of which was to
be provided by 1 December 1994.
75 On 14 September 1994 the Commonwealth, BHP-IT and EASAMS executed the
back-to-back contracts that are the subjects of this proceeding.
The contract
price fixed for the Head Contract was $9,609,569 and for the Sub-Contract,
$6,218,260. Contemporary internal BHP-IT
documentation projected a gross
profit on its contract of $835,912.
76 At the time of execution of the ADCNET contracts the Commonwealth had not
concluded an agreement with AWADI for the supply to
it of STUBS hardware and
software, though negotiations to this end were in train. On 1 December 1994
the Commonwealth failed to
deliver to BHP-IT (which in turn failed to deliver
to GEC Marconi) the first contractually scheduled STUBS related deliverable.
This
was the STUBS Software Interface Specification ("the STUBS SIS"). That
document was later purchased by the Commonwealth from AWADI
and supplied
directly to GEC Marconi on 6 January 1995 though its adequacy was questioned
thereafter.
77 On 22 December Les Cook sent a minute to Tim Harris, GEC Marconi's Systems
Engineering Manager, whose principal responsibility
was the integration and
acceptance testing of the ADCNET software. That minute was aimed at initiating
discussion on whether additional
software might be provided to emulate the
STUBS devices and software, the same question having previously been raised
with BHP-IT.
The emulation of STUBS is a matter that looms large in this
proceeding. It is appropriate to indicate here that the concept of
"surface
emulation" has earlier been described: "Introduction: the Language and
Processes of Software Development".
78 From early in the performance of the contracts GEC Marconi found itself
unable to meet the contracted milestone dates for delivery
of project
"deliverables". It was over a month late in completing the second milestone
(Milestone 2000) scheduled for 8 November
1994. By late March it was apparent
to GEC Marconi that it would be four weeks late in meeting Milestone 3000 and
that a project
schedule slippage of 13 weeks was forecast. By late April that
slippage had grown to 17 weeks.
79 DFAT had contracted to supply STUBS Untrusted Workstation and Server
Software by 1 April 1995. It failed to do so. This software
was in fact never
supplied. By 12 April Mr Brent in correspondence was seeking Les Cook's
"formal advise (sic) on the status of
STUBS so that DFAT and the PSI can adopt
appropriate contingency measures".
80 On 18 May Mr Brent again wrote to Les Cook that letter suggesting amongst
other things that "it would be prudent to examine alternatives
to STUBS".
81 As will become apparent when the circumstances giving rise to BHP-IT's
cross-claims against the Commonwealth are narrated, Les
Cook and the ITB had
been considering from at least January 1995 what options there were should
STUBS not be available. In March
1995 he prepared two option papers in which he
recommended that STUBS be abandoned and that another option ("Option C") be
adopted,
that option having a design based on sealing and gateways as was the
option suggested to Mr Cook by Mr Brent in his 18 May letter.
82 From July onwards the parties' correspondence focussed increasingly on
surface emulation of the STUBS devices. This correspondence
is set out in
detail later in these reasons. Here it will be referred to in very general
terms.
83 On 20 July 1995 Mr Brent inquired of Mr Wishart of GEC Marconi's capacity to
design and develop an emulator for STUBS. Mr Wishart
confirmed it possessed
that capacity by letter of 3 August 1995.
84 On 25 July Les Cook wrote a letter to Mr Brent (which was forwarded to GEC
Marconi on 4 August 1995) that indicated that:
"it is not possible to provide sufficient STUBS devices to meet the requirements of the Acceptance Test Plan. In order to allow the testing to complete, it will be necessary to emulate the STUBS devices. A change request will be raised for this work as soon as agreement has been reached on the use of emulation and the means of achieving it."
85 It should be noted in passing that 1 August 1995 was the day on which the
Commonwealth, hence BHP-IT, had contracted to provide
the STUBS equipment and
associated software. On 10 August and again on 24 August Les Cook wrote to Mr
Brent concerning the emulation
of the STUBS devices, the latter letter
disputing the contention that the need to emulate STUBS would result in
significant delays
to the ADCNET development schedule. Both letters were
forwarded to GEC Marconi the day after they were written.
86 On 6 September 1995 DFAT raised a change request (CR 3049) under its
contract with BHP-IT seeking the development of STUBS emulation
software. CR
3049 was forwarded to GEC Marconi on 8 September with a request for a quotation
for undertaking the scoping of the
change request. The emulation envisaged by
CR 3049 was a full surface emulation of the STUBS devices. Less than a week
later, on
13 or 14 September Mr Brent and Roger Cooke were advised by Les Cook
that STUBS had been cancelled and would not be provided as CSI
under the ADCNET
contracts. Les Cook also made known around this time that DFAT had an
alternative strategy.
87 On 26 September Les Cook wrote to Mr Brent and e-mailed Mr Wishart
confirming that STUBS would not be supplied for acceptance
testing. This
letter is central to BHP-IT's defence of GEC Marconi's claim and is considered
in detail later in these reasons.
88 On the same day DFAT raised CR 3052 to have investigated "the feasibility of
the STUBS replacement strategy outlined in the attached
minute". The minute
referred to was a document sent by Les Cook to Mr Harris of GEC Marconi that
outlined design principles for
the STUBS replacement. It noted that
"[b]oundary security will continue to be based on the concept of sealing and
gateways".
89 Sometime in September 1995 Mr Wishart contacted a self-employed software
consultant, Peter Newton, and invited him to scope an
emulator for STUBS. On 3
October Mr Newton provided Mr Wishart with a preliminary paper titled "STUBS
Emulation" the purpose of
which was to enable Mr Wishart to consider whether
the emulator Newton was proposing would meet Wishart's requirements. Two
further
versions of the paper were produced, one on 9 October, the other on 30
October.
90 On 5 October Mr Wishart signed GEC Marconi's quote for scoping CR 3049. It
was forwarded by BHP-IT to DFAT for approval the following
day. And on 11
October that approval was given and a request was made by DFAT for a quote for
implementing CR 3049. On 23 October
and 25 October Mr Wishart wrote separate
letters each of which attached GEC Marconi's costing to implement CR 3049. It
was in the
order of $31,507. As will be seen, the relationship of these two
letters and the status of the first is a matter in issue in this
proceeding.
91 By mid-October it was apparent within GEC Marconi that the company faced a
potential loss of $1 million or greater on the ADCNET
contract. On 18 October
Mr Pears instructed Roger Cooke to hire or contract a new project manager but
to retain Mr Wishart as a
Technical Manager. Pears indicated to Cooke that
"[t]he bottom line is that the company is not prepared to carry a potential
loss
of $1M or greater".
92 On 26 October Les Cook signed the Contract Amendment to give effect to CR
3049. It was CA 23 in the Head Contract. Mr Brent
signed the amendment for
BHP-IT on 1 November. No like amendment was formally signed for the
Sub-Contract though on 1 November Mr
Brent notified Mr Wishart that formal
approval had been given by DFAT for GEC Marconi to develop the STUBS emulation
software.
93 In early November 1995 Mr Sharp replaced Mr Pears as GEC Marconi's General
Manager.
94 On 8 November DFAT raised a further change request (CR 3057). The
accompanying letter described its burden:
" STUBS REPLACEMENT - CHANGE REQUEST
Attached is a change request which proposes a set of changes to the FRS which will allow the replacement of the STUBS sealer and gateway devices with an approach based on the KIV-7 encryption device.
Accompanying the change request form are the following documents which define the scope of the change request:
a. `STUBS Replacement - FRS Changes'; and
b. `KIV-7 Sealer/Gateway Interface Specification'."
GEC Marconi was requested to provide a quotation for scoping the work
required. A scoping price of $79,482.85 was later provided
by GEC Marconi.
95 Throughout November both a number of further change requests were raised and
proposals were made to modify contract amendment
proposals, to amend
documentation referenced in the contract so as to remove references to STUBS
devices and software and to add
references to STUBS emulation software. On 25
November Mr Harris of GEC Marconi sent an Acceptance Test Plan ("ATP") so
modified
to BHP-IT for approval under CR 3015. On 28 November he sent a
similarly modified Architecture Design Document ("ADD") to BHP-IT
for approval
under CR 3060. The latter change request is of some importance in the defence
raised to GEC Marconi's claim based on
the non-provision of STUBS.
96 On 13 November 1995 Les Cook wrote to Mr Brent a letter addressing Mr
Newton's paper on STUBS emulation. He pointed out that
a number of required
functions could not be tested by the emulator. Mr Wishart wrote to Mr Brent on
22 November responding specifically
to the concerns so raised by Mr Cook.
97 Following a transitional period in late January and early February 1996 Ed
Goldsmith replaced Mr Wishart as GEC Marconi's project
manager.
98 On 6 February 1996 an invoice for developing the STUBS emulator under CR
3049 was rendered by GEC Marconi. Sometime prior to
9 February the emulation
software was demonstrated by Mr Newton. On the 9th Mr Cook wrote to
Mr Brent confirming that:
"to the degree of detail presented, the emulation will be adequate to enable formal qualification testing of the release 3 software to be performed."
BHP-IT paid the GEC Marconi invoice for CR 3049 on 19 February 1996.
99 On 6 February 1996 Roger Cooke wrote to Mr Brent concerning the next
contracted milestone, Milestone 4000, which related to Test
Readiness Review
("TRR"). The letter stated in part:
"There is a conflict in the contract baseline documentation regarding the conduct of the Test Readiness Review. The contractual deliverable's in the document which takes precedence, namely the contract, does not provide deliverable's to enable the TRR as the SDP requires until the final milestone. We are proposing to replace the TRR milestone (Milestone 4000) with three milestones namely Milestone 4100, 4200 and 4300."
The letter proposed that the contracted milestone payment be split between
the three milestones proposed.
100 Mr Brent wrote to Les Cook on 9 February 1996 proposing that Milestone 4000
be split as suggested by Roger Cooke. Les Cook replied
on 12 February
rejecting this proposal though he agreed to participate in the documentary
review required by the TRR in accordance
with a revised and three-staged
schedule commencing on 26 February and finishing on 2 May 1996.
101 A GEC Marconi Project Status Report of 23 February 1996 forecast a loss of
$4.317 million on the ADCNET contract and a schedule
slippage of up to 18
months.
102 On 23 February a meeting took place between Mr Brent and Messrs Sharp,
Goldsmith and Becker of GEC Marconi. Mr Becker at that
time was Commercial
Manager of the Company. In a letter written to Mr Dart on 26 February, Mr
Brent gave a resumé of that
meeting in which GEC Marconi is said to have
made the point that it perceived "that the inability of DFAT to supply STUBS as
per
the contract may constitute a default on the part of DFAT and BHP-IT".
This was the first occasion on which this view had been communicated
to BHP-IT.
A further meeting between GEC Marconi, BHP-IT and DFAT was held on 29 February
1996 at which GEC Marconi put the same
view to DFAT, again for the first
time.
103 On 1 March Mr Goldsmith sent a facsimile to Mr Sharp in which he indicated
that he had located a letter and a memorandum authored
by Peter Wishart
concerning testing the ADCNET software. In light of them Mr Goldsmith
indicated that:
"I don't think you have a viable case to say that the system won't work if it is tested against the emulator. I also don't think that you can make much of a case that DFAT can't use the system without STUBS. It is their risk."
104 On 4 March 1996 Mr Brent sent Mr Goldsmith a copy of CR 3057 together
with a detailed definition of the scope of work (dated 22
November 1995) asking
that he be provided with evidence of work to substantiate the funding for the
CR. Mr Goldsmith replied on
8 March providing the information sought, but also
indicating that GEC Marconi was "not prepared to offer a price for this CR in
isolation". It wished "to offer a price recognising Customer induced delays
and frustrations of the Contract".
105 A letter to Mr Brent from Mr Goldsmith of 12 March invoiced BHP-IT for
Milestone 4000 in the sum of $1,250,000. The letter claimed
GEC Marconi had
met its obligation in relation to the TRR. On 21 March Mr Brent wrote to Mr
Goldsmith refusing to authorise payment
for the Milestone. He did not consider
that the TRR requirements of the contract and the Software Development Plan had
been met.
106 The Sub-Contract (Schedule 6) made provision for BHP-IT to supply its own
personnel to GEC Marconi on a time and materials charge
out rate. By early
March 1996 disagreement was emerging between the parties as to the hours
claimed by BHP-IT and of the time still
due to GEC Marconi. By late March a
dispute had arisen and on 26 March 1996 GEC Marconi rejected a BHP-IT invoice
for $157,036.81
rendered on 22 March 1996.
107 On 28 March Mr Sharp wrote to BHP-IT providing GEC Marconi's response to CR
3057. It was proposed that the contract be concluded
on completion and payment
of Milestone 4000; that there be a 4 month time and materials contract period
at the end of which a Critical
Design Review would be held; and that the
company would then be in a position to confirm "an appropriate arrangement for
progression
of the Contract to its conclusion". The letter indicated that GEC
Marconi believed that "a rough order of magnitude price for completion
of the
Contract, as proposed, is $8,000K with completion in the latter part of 1997".
This proposal was not accepted by BHP-IT.
108 On 2 April Mr Sharp wrote a letter to Mr Brent that stated, in part, that
BHP-IT had overlooked that:
"
1. BHP-IT is contractually obligated to supply STUBS to EASAMS. That has not occurred and, as we understand it, will never occur. BHP-IT is thus in breach of contract.
Moreover, the failure to supply STUBS makes it impossible for EASAMS to complete its contract. EASAMS has done what it can do to minimise the breach. This includes emulating the AWADI STUBS interface and the submitted response to the suggestion that the STUBS be deleted from the contract and replaced by an alternative solution incorporating KIV-7.
The fact remains that BHP-IT is in breach. It is now further in breach by reason of your refusal to pay the Milestone payment of $1,250,000 against Milestone 4000.
If that attitude continues then EASAMS will prepare and serve a Notice of Breach."
109 On the following day (3 April 1996) a Notice of Breach was served on BHP-IT. It alleged the following breaches:
"1. You have failed to provide STUBS hardware and associated documentation and software as Customer Supplied Items ("CSI") under the contract.
You have failed to supply CSI in accordance with Clause 7 and have failed to perform your obligations specified in the project plan and the implementation plan pursuant to Sub-clause 10.1.
2. You have failed to pay the Milestone payment of One million two hundred and fifty thousand dollars ($1,250,000.00) pursuant to Invoice 14248 of 12 March 1996.
3. You have failed to comply with your obligations under the contract. You have failed to act in a fair and reasonable manner. Refer paragraphs 1 and 2 above.
4. You have failed to act within the time prescribed in the contract for provision of STUBS as CSI and/or failed to act within a reasonable time.
5. You have misled EASAMS in relation to the delay in supply of STUBS and inability to supply STUBS.
6. You have failed to act reasonably pursuant to Clause 9E.2.1.
7. You are in breach of Clause 16.1 in failing to make payment. Refer paragraph 2 above."
The notice concluded with the following demand:
"You are required in respect of that breach, where that breach is capable of remedy, to remedy that breach within thirty-two (32) days of receiving this Notice or commence appropriate action to remedy that breach."
110 The notice was forwarded by BHP-IT to DFAT on 11 April 1996 and served
as BHP-IT's Notice to the Department under the Head Contract.
On 17 April DFAT
responded to the notice denying any alleged breach arising from the
non-provision of STUBS and contending that
the Contract Amendment consequent
upon CR 3049 varied the contract to remove the obligation to provide STUBS CSI
and, instead, to
require the development of STUBS emulation software.
111 BHP-IT also responded to GEC Marconi's notice on 17 April. It later
repeated its denial of any of the alleged breaches in a
letter from its
in-house lawyer, Margaret Beattie, to Mr Sharp on 3 May 1996. The penultimate
paragraph of that letter stated:
"Alternatively, if a breach has occurred (which we deny) then it does not constitute "a failure by the Customer to perform this Contract" for the purposes of clause 40.8. Alternatively, if at any stage you had a right to terminate the contract (which is denied) then you are estopped from now exercising that right or otherwise have lost those rights by virtue of without limitation your acceptance of the instructions concerning the development of STUBS emulation software and your delay."
112 On 20 May Les Cook made a presentation to BHP-IT and GEC Marconi as to
how the contract could be concluded and ADCNET deployed
without STUBS. The
proposals envisaged the initial retention of the IBM message switch as a
security device. It would be replaced
progressively by a new message switch
system using Release 3 software.
113 On 30 May DFAT wrote to BHP-IT indicating what it saw as BHP-IT's
obligations in relation to the completion of the ADCNET contract.
It went on
to propose changes to specified documentation "to remove any ambiguity arising
from the use of STUBS emulation". This
letter was forwarded to GEC Marconi
which replied to BHP-IT on 18 June. The reply stated in part:
"We note it is proposed that various documentation changes be made to the contract and other documentation. This clearly is a proposal to vary the contract. We advise that we reject the proposal/variations. We are prepared to use reasonable endeavours to reach agreement. If however agreement cannot be achieved we note that pursuant to clause 11.3 of the contract, the contract will remain unvaried. Any endeavours to reach agreement are without prejudice to our rights concerning termination of the sub-contract and/or any other rights or remedies we may have."
On the same day a second Notice of Breach was served on BHP-IT. It added a
new breach to those specified in the first notice. This
alleged a failure to
pay $78,482.85 pursuant to an invoice of 8 March 1996 in respect of CR 3057.
BHP-IT again denied the allegations
and indicated in relation to the CR 3057
invoice that payment had in fact been made.
114 Ed Goldsmith ceased to be GEC Marconi's project manager on 30 August 1996.
115 On 24 September 1996 a third Notice of Breach was served on BHP-IT. It was
similar in substance to the first although it added
the additional alleged
breach:
"You have stated that BHP-IT
(i) will not supply either STUBS or a STUBS replacement; and
(ii) that BHP-IT does not have any obligation to supply same.
Such statement or conduct evinces an intention on the part of BHP-IT not to be bound by the terms of the contract and as such is a repudiation of such contract."
116 On 10 December 1996, GEC Marconi served a notice of termination of the
ADCNET sub-contract on BHP-IT. The Notice relied upon
BHP-IT's not having
remedied the alleged breaches in the three Notices of Breach (save that in
relation to the CR 3057 invoice payment).
117 As part of the process of vacating the DFAT supplied premises at which it
conducted its ADCNET work, GEC Marconi wrote to BHP-IT
on 12 December directing
that:
"3. STUBS Interface Emulator files should be deleted from the system and the backups."
118 For its part, consequent upon the receipt of the Notice of Termination,
BHP-IT (a) wrote a letter on 24 December 1996 to the second
cross-respondent,
GEC Marconi Australia Pty Ltd, calling upon a Performance Guarantee it had
given on 31 October 1994 in respect
of GEC Marconi's performance of the ADCNET
contract; (b) treated GEC Marconi's Notice of Termination as a repudiation of
the contract
and it communicated to GEC Marconi its acceptance of that
repudiation on 21 January 1997; (c) terminated a separate standing offer
agreement it had entered into with GEC Marconi on 6 February 1995 in relation
to GEC Marconi's possible provision of services to
BHP-IT as a member of the
Defence Preferred Systems Integrator panel; and (d) wrote three letters to
Banque Nationale de Paris calling
upon Unconditional Financial Undertakings
given covering the payments made to GEC Marconi in respect of Milestones 1000
($1,250,000),
Milestone 2000 ($1,250,000) and Milestone 3000 ($1,375,000).
119 BHP-IT assumed the performance of the ADCNET contract in the absence of GEC
Marconi. Its contract with the Commonwealth was
varied on 24 December 1997.
Its performance of the original and then the varied contract will be outlined
later in these reasons:
see below Part III: Damages:
120 The present proceeding was commenced by GEC Marconi against BHP-IT on 11
September 1997.
PART II: GEC MARCONI'S CLAIM
A GEC MARCONI'S CLAIMS AND BHP-IT DEFENCES: AN OVERVIEW
(1) The Primary Complaints and Defences
121 The Amended Statement of Claim particularises 14 respects in which BHP-IT
is alleged to have failed or refused to comply with
its contractual
obligations. These 14 matters are referable to one or other of two primary
complaints. The first was BHP-IT's failure
to provide STUBS hardware and
software as required by the Sub-Contract. The second was BHP-IT's failure to
pay GEC Marconi for its
achievement of Milestone 4000, again as required by the
Sub-Contract.
122 Each of these failures, it is said, severally justified GEC Marconi in
terminating the Sub-Contract in accordance with the provisions
of cll 40.8 and
40.9 of the contract. The proper construction of those provisions is very much
in issue as are the claims that BHP-IT
was in breach of its contractual
obligations by failing either to supply STUBS or to pay for Milestone 4000.
123 In relation to the non-provision of STUBS, BHP-IT has contended that the
Sub-Contract was amended by agreement in about November
1995 to remove the
obligation to provide STUBS and to substitute the use of the STUBS emulator for
Acceptance Testing. Alternatively,
it is said, GEC Marconi elected to affirm
the Sub-Contract notwithstanding the non-provision of STUBS, or else it waived
the obligation
that STUBS be provided, or was estopped from asserting that
STUBS was required to be provided.
124 As to the non-payment of Milestone 4000, BHP-IT asserts that GEC Marconi
was not entitled to be paid as it had not complied with
the requirements for
payment under the Sub-Contract or else that BHP-IT had reasonable grounds for
considering it had not and was
in consequence contractually justified in
refusing payment. Alternatively it is alleged GEC Marconi affirmed the
Sub-Contract after
the first Notice of Breach had been served.
125 Distinctly, BHP-IT claims that GEC Marconi was subject to an implied
contractual duty to act honestly, fairly and reasonably
in giving any notice of
termination and it breached that duty in giving the notices.
126 In addition to its reliance upon the termination under cl 40 of the
Sub-Contract, GEC Marconi alleges that BHP-IT's breaches
of contract amounted
to a repudiation of the contract which GEC Marconi accepted. BHP-IT's response
is that if it did breach the
contract as claimed, those breaches did not go the
root of the Sub-Contract and did not amount to a failure to perform it. GEC
Marconi
was in consequence not entitled to terminate the Sub-Contract under the
general law.
127 The damages GEC Marconi claims it suffered in consequence of the breaches
and termination are sought to be recovered primarily
on a quantum meruit claim.
BHP-IT contests the availability of such a claim in the factual setting in
which it has been made.
(2) The Subsidiary Complaints
128 There are four additional and discrete claims made by GEC Marconi. These
are claims for loss suffered because:
(i) BHP-IT wrongfully called upon the bank guarantees for $3.875M provided by
GEC Marconi as security under the Sub-Contract;
(ii) BHP-IT wrongfully converted the STUBS emulator after the Sub-Contract was
terminated;
(iii) BHP-IT repudiated the Standing Offer Agreement in respect of DPSI panel
services;
(iv) BHP-IT has failed or refused to pay GEC Marconi delay and prolongation
costs required by the Sub-Contract.
Clause 38 of the Sub-Contract imposes a cap on damages in respect of actions
between the parties arising out of the operation of
the Sub-Contract. BHP-IT
has relied upon this provision to limit any damages recoverable by GEC Marconi
to the cap of $8,600,000.
For its part GEC Marconi contends that cl 38 does
not apply to its quantum meruit claim.
129 The two primary complaints, the four subsidiary complaints and the damages
cap defence will be considered separately and sequentially
in this Part.
(3) The Non-Provision of STUBS
130 GEC Marconi's claim has a beguiling simplicity: BHP-IT was obliged to
provide STUBS; it failed to do so; and that failure
justified termination of
the Sub-Contract both at common law and under cl 40 of the contract. The
complexity in dealing with the
claim arises primarily from the diverse array of
defences that BHP-IT has marshalled against it. These defences have their own
and
different legal foundations and factual underpinnings. For ease in
exposition, the course I intend to take initially is to assume
that unless a
defence can be made out, GEC Marconi can establish its claim. I will in
consequence consider the defences first.
As will become apparent, the volume
of factual material virtually compels the taking of this course.
131 The principal defences raised were as follows:
1. The Sub-Contract was varied so as to remove the obligation to provide STUBS
and permit the use of emulation software in its place
to complete the
Sub-Contract ("the Emulation Variation Agreement"). This agreement, I would
note, is a composite of what in the
pleadings are referred to as the STUBS
Emulation Agreement and the Sub-Contract Variation Agreement.
2. GEC Marconi affirmed the Sub-Contract both after it had been notified that
STUBS would not be provided and after it had served
its first notice of breach
("Affirmation by Election").
3. As a result both of representations made by GEC Marconi and relied on by
BHP-IT and of the common understanding acted on by the
parties, GEC Marconi was
estopped from denying that BHP-IT was no longer required to provide STUBS and
that GEC Marconi would no
longer assert any right to require its provision
("Estoppel").
4. In the circumstances, GEC Marconi waived or dispensed with BHP-IT's
obligation to deliver STUBS and substituted for it STUBS
emulation software as
an alternative means of performing the contract ("Waiver").
5. The non-provision of STUBS was not a repudiatory breach at common law or
one that permitted termination under cl 40 of the
Sub-Contract ("Improper
Termination").
6. When GEC Marconi terminated the Sub-Contract it was not itself ready,
willing and able to perform the Sub-Contract ("Ready, Willing
and Able").
1. THE EMULATION VARIATION AGREEMENT
(a) Additional Factual Material
132 I preface the following narrative with the observation that it has been
necessary to set out in some detail the contents of a
significant number of the
documents that are said to bear on the issue of the alleged variation
agreement. Extensive written submissions
have been made analysing the burden
of many of the documents to which I will refer.
(i) The ADCNET project to November 1995
133 As indicated in the "General Chronology", in 1993 the Commonwealth selected
the STUBS devices as its preferred choice for boundary
security and BHP-IT and
EASAMS became aware of this. At the time of execution of the Head Contract and
Sub-Contract the Commonwealth
had not concluded an agreement with AWADI for the
supply to it of STUBS hardware and software, though negotiations to this end
were
in train. BHP-IT concedes it was aware of this when it signed both
contracts.
134 From early in the life of the ADCNET contracts all parties were aware of
the possibility that it might be necessary to resort
to emulation of the STUBS
devices for some purposes at least. In a "Pre-Review Check Sheet" prepared by
GEC Marconi on 18 November
1994 for the projected Preliminary Design Review
("PDR") of 23 November 1994 a major defect identified in the Acceptance Test
Plan
(a document to be approved at the PDR) was described in the following
fashion:
"The ATP specifies some 25 STUBS devices to be provided (19 for Phase A and 6 for Phase B). The contract provides for the delivery of a small number of Stubs devices (2 sealers, 1 KDC and 1 gateway) to be installed by 1/8/95 - i.e. some time after the commencement of Phase A testing.
Present indications from AWADI are that, at best, a prototype system could be installed by 1/8/95. Production units would not start to be delivered until January 1996. The ATP should be amended accordingly.
This means that it may be necessary to emulate the sealing of documents during performance testing in Phase A."
135 On 22 December 1994 Les Cook wrote directly to Mr Harris of GEC Marconi
on the subject of "Emulation of STUBS Devices". The letter
contained a
handwritten notation from Les Cook that stated: "This is to initiate
discussion of practicality at this stage". The
letter itself indicated that
the supply of STUBS equipment and software was "likely to be too late to allow
testing and integration
of PSI software without some form of emulation". The
emulation envisaged was such as to ensure that "all PSI software (other than
emulation) operates unchanged whether STUBS is emulated or not". I would note
in passing that a modified version of this letter
was revived by Mr Cook in
July 1995 by which time the emulation of STUBS was a live issue.
136 The Acceptance Test Plan, that was approved on the completion of PDR (which
seems to have occurred in mid-January 1995), provided
that
(cl 3.3.3.4.1.1.1):
"The availability of Stub devices during the Acceptance testing is likely to be limited and will not be sufficient for the Minimal Message Switch to support the Acceptance Tests. The use of simulators and/or interface stubs and any test waivers related to the Stub device will be resolved by agreement between the Customer and the Contractor."
137 On 20 February a Project Management Committee meeting was held that was attended by, amongst others Les Cook, Mr Brent and Mr Wishart. Mr Wishart produced a report of that meeting on the same day. It noted:
"10. DFAT getting even more concerned with STUBS. Very high possibility that STUBS will not be available in any quantities for testing. Some possibility that STUBS may never be available. LGC [Les Cook] considering other options, will keep us informally advised and raise CR's for any work to build emulators or (worst case) rework of security policy."
138 By this time a default had already occurred under the contracts in
relation to the delivery of STUBS related items. The STUBS
Software Interface
Specification ("the STUBS SIS") was required to be delivered on 1 December
1994. Delivery occurred on 6 January
1995 but was alleged by GEC Marconi to be
deficient in some respects. The STUBS untrusted workstation and server
software in turn
was scheduled for delivery on 1 April 1995. It was never
delivered. Delay in its delivery was foreshadowed by Les Cook as early
as 19
December 1994.
139 The issue of the possible emulation of STUBS was again raised at a Project
Management committee meeting of 29 March 1995. Mr
Wishart's notes of that
meeting recorded:
"DFAT may raise a CR to conduct acceptance tests without STUBS devices.
DFAT to make a judgment on whether STUBS is in the project or not within next 4 weeks."
140 On 26 April an internal memorandum of GEC Marconi prepared by Mr Pears recorded a meeting with Mr Dart of BHP-IT concerning ADCNET. It recorded in part:
"1. ... Broke the news that we could be up to 17 weeks late as a result of under estimation of Code & Unit Test (CUT) phase.
...
4. It is highly likely that the customer will be unable to deliver a key piece of CFI/CFE, the AWADI STUBBS device. We will then be in a position to remove LD's [liquidated damages] by negotiation of the scope of ensuing delay. We should know by June/July, and resolve by October."
141 Earlier, on 12 April, Mr Brent wrote a letter to Les Cook that concluded with a request for his "formal advise (sic) on the status of STUBS so that DFAT and the PSI can adopt appropriate contingency measures". Mr Brent's concern with STUBS was reiterated in a letter of 18 May 1995. It warrants quotation in full (omitting formal parts). I should preface this by noting that the reference in it to HPUXBLS is a reference to the "Hewlett Packard Unix `B' Level Secure Operating System". The letter stated:
" RE: STUBS
During the course of recent project management meetings there has been a lot of discussion concerning the status of STUBS. The situation in brief is as detailed below:
* STUBS Software Interface Specification is delayed 4 months;
* STUBS delivery is likely to be delayed;
* STUBS may not be delivered at all;
* the Department does not have a contract for the delivery of STUBS;
* high level discussions between AWA, DFAT, Defence are imminent and will decide the outcome. This may well be that the STUBS program is cancelled within AWA.
The impact of these developments on the PSI has been that:
* all work on STUBS-related design has been halted due to a four month delay in the supply of the software interface specification;
* the uncertainty associated with STUBS has thrown into doubt the viability of the entire system;
* if STUBS is not available then the current ADCNET architecture and the associated design are invalid.
In the light of the position described above it would be prudent to examine alternatives to the use of STUBS. Suggested options are:
* implement the necessary boundary security functions in software on HPUXBLS and seek appropriate waivers from DSD concerning accreditation for the system;
* conduct an international technology search/review in order to identify device(s) which could conceivably meet ADCNET objectives/needs;
* explore the options for the design and implementation of an alternative security architecture.
Whatever the outcome of STUBS availability we need to move quickly on all fronts in order to contain significant and costly delays to the ADCNET program.
In the context of the current position I request an urgent and extensive conference between the Department and the PSI concerning this issue."
142 Les Cook was overseas at the time of this letter, returning on 28 May. He did not reply to it until 6 June, his reply indicating:
" STUBS
As you have noted, there is great uncertainty surrounding the supply of STUBS to the Department in time for the deployment of ADCNET Release 3 in Canberra. The Department's Executive are schedule to meet within the next 10 days to determine whether to proceed with STUBS or to accept an alternative method of providing ADCNET boundary security.
I agree with your analysis of the broad options available. Of these, I have advised the Department's management that only the first is a practical option. The reasons for this are noted below."
After outlining the proposal that had been put to the DFAT executive, the letter concluded:
"DSD is in the process of commenting on the proposal and the Department intends to make a decision on the use of STUBS or this approach within the next two weeks. I will, of course, inform the PSI as soon as such a decision is reached. In the meantime, I have recently sent a copy of the outline design proposal to you and I would welcome comments on it."
143 As was noted in the "General Chronology", it will become apparent when
the circumstances giving rise to BHP-IT's cross-claims
against the Commonwealth
are narrated that Les Cook and the ITB had been considering from at least
January 1995 what options there
were should STUBS not be available. In March
1995 Mr Cook prepared two option papers in which he recommended that STUBS be
abandoned
and that another option ("Option C") be recommended, that option
having a design based on sealing and gateways as was the HPUXBLS
option
suggested to Mr Cook by Mr Brent in his 18 May letter.
144 By July 1995 neither BHP-IT nor GEC Marconi had been informed by DFAT
whether or not it was proceeding with STUBS. A meeting
of the Acceptance Test
Team (involving DFAT and BHP-IT representatives) occurred on 7 July 1995, the
minutes of that meeting noting,
inter alia, that:
"3.1.5 Action: There are a number of issues with the connection of External Partitions to the test system given the lack of STUBS.
Status: PSI is still unaware of DFAT official position on STUBS. RN to provide PSI with advice in relation to the go ahead with the emulation of STUBS for testing. R Nichols to speak to L Cook regarding contract variations and will then advise."
These minutes were copied to Mr Wishart and Mr Harris of GEC Marconi.
145 GEC Marconi's risk analysis report of 19 July - such a document was
prepared almost monthly under the direction of Mr Wishart
- dealt with STUBS in
the following manner:
"Ref: 14
Title: STUBS Availability date and numbers
Description: The earliest available date for the STUBS device and the number of devices available on that date may present some problems for the development and testing efforts.
RAP Details: DFAT/BHP to advice [sic]
Status: MEDIUM risk"
146 Mr Brent wrote to Mr Wishart on 20 July 1995 seeking information on a
variety of STUBS related matters. Two of these were (i)
the impact on the
formal test program if STUBS was not available and (ii) GEC Marconi's capacity
to design and develop test harnesses
simulating STUBS. In cross-examination
and again in re-examination Mr Wishart confirmed that he understood the second
query to relate
to the development of an emulator that would enable the
acceptance testing of the ADCNET system. His letter in response of 3 August
indicated in relation to these two matters, first, that GEC Marconi would not
accept responsibility for any issues identified with
STUBS during formal
acceptance testing if STUBS was not available for integration and system
testing; and, secondly, that GEC Marconi
had the capabilities to design and
develop test harnesses for STUBS.
147 On 25 July Les Cook wrote to Mr Brent raising the issue of a change request
to allow emulation of the STUBS devices. That letter
was an adaptation of the
letter sent to Mr Harris on 22 December 1994 to which reference has been made
above. Insofar as presently
relevant it stated:
" SUPPLY OF STUBS DEVICES FOR ACCEPTANCE TESTS
1. As previously stated in meetings, it is not possible to provide sufficient STUBS devices to meet the requirements of the Acceptance Test Plan. In order to allow the testing to complete, it will be necessary to emulate the STUBS devices. A change request will be raised for this work as soon as agreement has been reached on the use of emulation and the means of achieving it.
...
4. It is proposed that all STUBS sealers and gateways required by the Acceptance Test Plan be emulated. Some of the untrusted software will also be emulated.
5. The emulation should ensure that, to the degree possible, all PSI software (other than that which provides the emulation) operates unchanged whether STUBS is emulated or not. ...
6. The emulation should allow all cases of success or failure of STUBS functions to be tested, in so far as they are relevant to PSI software, without requiring changes to PSI software. It should include the creation of audit log information as defined in the STUBS SIS."
148 Mr Brent forwarded this letter to Mr Wishart on 4 August 1995, his own letter indicating that:
"I would appreciate your advice on the issues raised with specific reference to:
- schedule impact
- viability of the proposed approach
- any other issues."
149 It appears to be common ground between the parties that the 25 July
letter contemplated that the proposed emulator would be used
for acceptance
testing.
150 The contracted date for the delivery of the STUBS devices was 1 August
1995. On 4 August Mr Wishart wrote to Mr Brent indicating
that GEC Marconi had
"not yet received anything or any indication of when it will arrive".
151 On 10 August Les Cook revisited the question of emulation of STUBS in a
letter to Mr Brent. The letter was forwarded to GEC
Marconi the following day.
The context of the letter related to DFAT's requirements for agreement to an
extension of the contract
schedule. The subject of delays occasioned (inter
alia) by the non-provision of STUBS related materials had by now become
contentious.
The letter stated in part:
"As discussed with Mr Cooke and at no additional charge to DFAT, software will be developed by the PSI to emulate AWADI's untrusted workstation software and the STUBS devices. The emulation will include and allow to be tested all components of the interface as described in the STUBS Software Interface Specification dated 1 December 1994 and previously provided to the PSI.
As this will allow acceptance testing to proceed in the absence of AWADI's untrusted workstation software and STUBS devices, any defect in the PSI's Developed Software which may be encountered when STUBS is implemented will be remedied under the warranty for the Developed Software, provided that AWADI's untrusted workstation software complies with the Software Interface Specification."
In cross-examination Roger Cooke accepted of this letter that DFAT was
proposing an emulator suitable for acceptance of the R3 software,
though he
also insisted that he thought there would be at least one sealer and gateway
available.
152 A letter from GEC Marconi to BHP-IT of 21 August signed by Mr Pears but
prepared by Mr Wishart and Roger Cooke, responded to
DFAT's proposals in the 10
August letter. Its focus was on delay claims and the proposed extension to the
contract schedule. Mr
Pears put forward GEC Marconi's proposals which would
"wipe the slate clean for any existing delay claims including pending claims
for non delivery of STUBS". It proposed amongst other things that it would
"Implement a STUBS test harness suitable for development
and acceptance of R3".
A benefit it saw stemming from its proposal was that DFAT would no longer be
dependent on the delivery of
STUBS to allow GEC Marconi "to continue
development and to conduct acceptance". Mr Wishart, but not Roger Cooke,
accepted that he
knew by this time that it was most unlikely that STUBS would
be available at all.
153 Les Cook wrote a further letter on emulation to Mr Brent on 24 August which
again was forwarded to GEC Marconi on the following
day. This letter, though
of a technical character and directed primarily at suggestions that emulation
of STUBS would occasion delays,
is of some importance. It was incorporated by
reference into Change Request 3049 ("CR 3049"), this CR relating to the
development
of STUBS emulation software. The emulation it contemplated was a
full surface emulation of STUBS that was compliant with the STUBS
SIS, the
emulation being developed in two phases. The object of the two phase proposal
was to minimise delay to the project arising
from the need to emulate the STUBS
devices.
154 In a report to GEC Marconi's project management team of 28 August, Mr
Wishart referred to the contract negotiations to extend
the schedule and noted
that GEC Marconi did not agree with DFAT's negotiation position that lack of
STUBS devices should not hold
up the project. The report also noted that STUBS
devices were due on 1 August and that they would be required on 28 August 1995.
He recorded he intended to raise a diary entry which would say that STUBS had
not been received yet. The minute on this matter continued:
"Actual
resolution of issue will almost certainly bee (sic) via the contract
negotiations, but we need the diary entry to document
our formal position."
The diary entry was raised the following day. It referred back to GEC
Marconi's letter to Mr Brent of 4 August
(noted above). Les Cook wrote two
responses on the diary note. The first was that:
"DFAT advised the PSI formally on 25 July 1995 that STUBS would not be provided for acceptance testing and requested action to emulate the devices to minimise schedule delay. This advice was apparently ignored in the referred correspondence."
Secondly, in response to a further comment of Mr Wishart in the diary note
requiring DFAT to "advise delivery date of STUBS equipment
and software ASAP",
Les Cook wrote: "This has been done, see above", this being a reference to his
first notation. Mr Wishart in
oral evidence indicated that he saw Les Cook's
comments at the time though he was uncertain as to precisely when. Extrinsic
evidence
suggests it may well have been only at the end of September.
155 The change request foreshadowed in Les Cook's letter of 25 July was sent by
Mr Brent to Mr Wishart on 6 September. The letter
accompanying the change
request (CR3049) - sought a quotation for undertaking the scoping of the change
request. The purpose of
CR3049 was to "[d]evelop STUBS emulation software".
It described the "scope of work" as:
"Develop STUBS emulation software in a way that will minimise the impact on the project schedule (refer to Mr Cook's letter dated 24/8/95)."
156 In GEC Marconi's risk analysis report of 8 September the following was recorded:
"Ref: 14
Title: STUBS Availability date and numbers
Description: The earliest available date for the STUBS device and the number of devices available on that date may present some problems for the development and testing efforts.
RAP Details: STUBS devices will not be available in time. DFAT proposing use of a STUBS emulator to be constructed by the PSI and used for acceptance. Being considered in contract negotiations.
Status: MEDIUM risk."
157 The "contract negotiations" referred to were the ongoing ones concerning delay claims, cost of additional work and contract schedule extension. As part of those negotiations Roger Cooke wrote to Mr Brent on 11 September detailing GEC Marconi's proposal to amend the ADCNET contract. These involved a schedule amendment of eleven weeks and an increase to the contract price by $195,000. In its reference to STUBS the proposal stated insofar as relevant:
"However, in fulfilment of our obligation under the Contract to take reasonable action to mitigate the effect of Customer delay, EASAMS proposes that a STUBS interface emulator be developed in order that ADCNET software development and testing as planned can continue without further impact to the schedule. This is not a requirement and is an increase in scope."
158 A meeting or meetings occurred between representatives of DFAT, BHP-IT
and GEC Marconi on 13 and/or 14 September. Les Cook, Mr
Brent, Roger Cooke and
Mr Wishart were among those present. Roger Cooke's evidence, which I accept,
was that the meeting had been
scheduled to discuss various delay claims. At
that meeting Les Cook announced that STUBS had been cancelled.
159 Though the evidence is unclear as to timing - there appears to have been a
meeting as well on 15 September - Les Cook in this
composite of meetings (i)
briefly outlined DFAT's alternative strategy for boundary security based on the
use of an encryption device
(known as KIV-7) as the sealer and gateway; and
(ii) indicated in relation to GEC Marconi's contract amendment proposal, that
DFAT
wished to include the STUBS replacement issue in the negotiations. The
evidence in this paragraph is drawn from a memorandum of
Roger Cooke of 15
September 1995, and from the witness statements of Roger Cooke and Les Cook. I
merely note I do not accept as
accurate Mr Brent's recollection of the
meeting(s).
160 Mr Brent wrote to Les Cook on 15 September outlining BHP-IT's and GEC
Marconi's proposals for a contract schedule extension and
the price increase of
$195,000. Mr Brent reiterated his views on contract schedule extension in a
further letter of 25 September
in which he indicated as well that BHP-IT had
not received "any formal notification of the demise of the STUBS program" and
that,
though there had been considerable discussion regarding the proposed
STUBS emulation software there had been "no formal agreement
or agreed
specification for the STUBS emulator".
161 At a meeting on 22 September 1995 between Les Cook and the GEC Marconi
"team leaders" it was confirmed that, with only a "cut
down" emulator now being
envisaged, new Application Program Interface specifications ("the API") would
need to be defined.
162 On 25 September Les Cook prepared a minute to be sent directly to Mr Harris
of GEC Marconi outlining the design principles for
the STUBS replacement. That
document indicated that boundary security was to continue to be based on the
concept of sealing and
gateways. Mr Harris' evidence is that he received the
minute on or about the date it bore.
163 Around this time Mr Wishart had engaged a software consultant, Peter
Newton, to scope an emulator for STUBS. Mr Wishart recognised
that with the
abandonment of STUBS conformance with the STUBS SIS was no longer important.
His Project Management Report of 26 September
1995 noted that it had been
agreed that Mr Newton would prepare a specification for submission to DFAT
outlining GEC Marconi's approach
to emulation.
164 A document of great significance in this proceeding was sent by Les Cook to
Mr Brent on 26 September 1995. An e-mail copy was
received by Mr Wishart on
the same day. The first four paragraphs were in the following terms.
"I confirm my informal advice to you of 15 September 1995 that AWADI will not continue with the development and supply of the STUBS security devices.
The Department informed the PSI on 25 July 1995 (ref PSIR3-207) that it would be unable to supply STUBS devices for Acceptance Testing. The letter recommended that the STUBS devices be emulated to enable development and testing to continue and proposed that a change request be raised to investigate the use of AWADI-developed software to perform the emulation. The PSI did not accept this approach and proposed instead that it develop the emulation software. DFAT agreed to this course of action and raised a change request on 6 September. To date, this change request has not been returned to the Department with a quotation.
There has been considerable discussion on the functional and contractual requirement for a comprehensive STUBS emulator. DFAT stated that the functional requirement was that the emulation meet all the requirements of the STUBS Software Interface Specification as previously supplied to the PSI. A cost of $40,000 has been stated for the emulator in several draft letters from the PSI. DFAT has indicated that it regards this figure as high but probably acceptable and understands that development work has commenced. The vehicle for formal agreement on the scope of work and cost must be the change request already raised by the Department.
Because the Department had previously informed the PSI that STUBS devices would not be provided for development and acceptance testing and had asked that emulation be considered, there was no urgent reason for it to provide formal advice that the STUBS program will not be continued until official advice has been received that this is correct. It is now important that a strategy to replace these devices be agreed by all parties, including the Department's security authorities and DSD. In order to avoid further schedule delays, the Department has agreed that an emulation of the STUBS devices should proceed in the interim to the extent necessary to complete the development and testing of ADCNET software which depends on the functioning of the interfaces to STUBS devices. To the extent practical, this emulation should be reduced from a full emulation of the STUBS interface to the minimum functions which will allow ADCNET software to be tested. DFAT is awaiting advice from the PSI as to the extent of such an emulation and whether this will be scoped in response to the original change request or whether that CR should be cancelled and replaced with another. The most recent development was that Mr Wishart and Mr Newton will examine the specification and advise.
Despite the lack of a formal response to the CR, the Department accepts that continued work on the emulator is a valid delay mitigation strategy. ..."
165 In relation to delay claims, the letter sought an agreement that was fair
to both sides and stated that DFAT considered that
"any such agreement must
include a strategy for STUBS replacement". The cost of work necessary to
examine strategies to replace
STUBS were to be covered by one or more change
requests.
166 On the same day Les Cook signed and sent CR 3052. It related to the
feasibility of the STUBS replacement strategy. A quotation
for undertaking the
scope of work was requested. Attached to CR 3052 was a copy of the 25
September minute sent to Mr Harris. The
change request was forwarded to GEC
Marconi on 5 October and was responded to (in the form of a commentary on the
paragraphs of the
minute attached to CR3052) on 12 October 1995. I would note
in passing that that response led to the raising in early November of
a change
request for the STUBS replacement (CR3057), a matter referred to later in this
narrative.
167 To anticipate matters slightly, Mr Brent responded to Les Cook's 26
September letter on 4 October. His letter stated in part:
"Notwithstanding advice from the Department regarding unavailability of STUBS, work on STUBS emulation and related matters is in my view, outside the contracted scope of work. Consequently unequivocal agreement is necessary regarding the scope and impact of the variation to the contracted scope of work."
In relation to the delay and contract schedule extension proposals previously put to DFAT by BHP-IT and GEC Marconi in September of 1995 (referred to above), and which Les Cook's letter linked to "a strategy for STUBS replacement", the letter indicated that:
"My concern is that deliberation on STUBS replacement may be protracted and inconclusive since the issue involves matters of DFAT security policy and an external agency (DSD).
Accordingly, I believe that consideration of our proposal by the Department should not be predicated on work associated with the development of the STUBS replacement strategy. In this context the Department should be aware that our proposal for contract extension is also our claim for delay costs and schedule impact."
168 Les Cook's response of 12 October 1995 accepted that the work on emulation was outside the contracted scope of work. In reference to the subject of delay claims (another topic referred to by Brent), the letter commented:
"The Department remains willing to avoid a protracted examination of the details of each claim, provided that an overall position can be reached which both sides consider to be fair and which allows the project to move forward to a successful completion. Just as it was important to the PSI to include in this the effects of non-provision of STUBS, it is important to the Department that an agreement include the strategy for completion of the project in the absence of STUBS. Without a satisfactory resolution of this matter, the software will be of little value to DFAT. The Department has proposed such a strategy in some detail. It has also raised change requests to allow the PSI to examine the strategy and to estimate its cost and schedule effect. I trust that the PSI will move as quickly as possible to complete this work so that the overall negotiation on contract variations to allow the project to move to completion may be concluded."
169 Les Cook's evidence was that at the time he wrote this letter he
believed the best outcome was to see the ADCNET project completed
with a
substitute for STUBS rather than with no STUBS and no substitute provided it
was practicable and that this remained his view.
In cross-examination he
suggested that the observation that " the software will be of little value" was
not accurate.
170 Mr Newton prepared a paper entitled "STUBS Emulation" on 3 October, the
purpose of which was to enable Mr Wishart to consider
whether the emulator
Newton was proposing would meet Wishart's requirements. That paper was sent to
Mr Brent on 9 October, the accompanying
letter stating in part:
" STUBS Emulation
The attached paper describes the basic approach for developing a minimal STUBS emulator for ADCNET (as per CR3049). If you have any comments on this approach then please return them as soon as possible. Specifications for the APIs are being developed and will be made available as soon as possible."
In light of submissions made by GEC Marconi I would emphasise the references
(i) to a "minimal STUBS emulator ... (as per CR3049)"
and (ii) to "the APIs
being made available as soon as possible". The foreshadowed APIs were
forwarded to Les Cook on 16 October
by Mr Brent along with a revised version of
Mr Newton's draft paper.
171 On 11 October Mr Brent was provided with a DFAT letter containing Les
Cook's comments on Mr Newton's original 3 October draft
paper. By 30 October
Newton had produced a further paper entitled "STUBS-E STUBS Emulation" which
sought to address Mr Cook's comments
and which further detailed the proposed
emulator. To anticipate matters which will be narrated more fully below (i)
Les Cook did
not respond with comments on the Newton draft sent to him on 16
October until 13 November; (ii) Mr Newton's evidence is that he
did not see
Les Cook's 13 November comments and that he had finished developing the
emulation software prior to that date.
172 To backtrack somewhat, on 5 October Mr Wishart signed the "ADCNET Release 3
Scoping and Costing Request Sheet" for CR 3049.
The cost given for undertaking
scoping of CR 3049 was $4617.82. Mr Brent in turn signed a like document for
transmission to DFAT.
The cost given in that document of $6,014 included
BHP-IT's margin on GEC Marconi's quotation. Les Cook approved BHP-IT's
quotation
on 10 October. On 11 October by letter to Mr Wishart, Mr Brent in
turn confirmed DFAT's approval of the initial quotation. He went
on to request
Mr Wishart to provide a detailed quotation for implementation of the work
necessary to build the emulation software.
In his oral evidence Mr Wishart
accepted that the emulation was to be the cut down emulation the specifications
for which were being
prepared by Mr Newton.
173 On 16 October Mr Wishart sent a memo to Mr Breden (Commercial Manager, GEC
Marconi) seeking his approval of the draft quotation
of $18,389.86 he had
prepared. The memorandum indicated insofar as is relevant that:
"DFAT has raised a change request (CR 3049) to cover implementation of the cut down emulator for STUBS. The focus of the emulator is now to allow development of the rest of the system to proceed with minimal delay. It is no longer required that the emulator be compliant with the STUBS Specification.
...
The costs shown below are to implement the emulator and cover our costs in rescheduling to minimize the impact of the late delivery of the STUBS devices (or replacement). ...
The software will not be developed with the process defined in the ADCNET Software Development Plan. It will [be] developed using rapid prototyping type methods with minimal external reviews, targetted at producing non-production software. The software is only to be used for development, integration and acceptance of the system under the contract. Warranty after acceptance will not apply since the software will not be used after the system has been accepted (this last point has not yet been proposed to the customer, it will be stated in the CR cost to complete)." Emphasis added
174 This quotation was revised on 18 October by Mr Wishart. The new price
was $31,507.86 which included over $13,000 for re-work
of the schedule. It was
sent to Mr Breden for approval and was copied to Roger Cooke under cover of a
facsimile which also included
the earlier 16 October memorandum. That approval
was given shortly thereafter.
175 On 23 October 1995, in a letter of contested importance in this proceeding,
Mr Wishart sent Mr Brent GEC Marconi's quotation
for CR 3049. Omitting formal
parts, the letter stated:
" CR3049 (Cut-down Stubs Emulator)
The price shown for the attached Change Request (CR3049) are to implement the emulator and cover our costs in rescheduling to remove any impact of the late delivery of the STUBS devices (or replacement).
The software for CR3049 will not be developed with the process defined in the ADCNET Software Development Plan. It will be developed using rapid prototyping type methods with minimal external reviews, targeted at producing non-production software. The software is only to be used for development integration and acceptance of the system under the contract. Warranty after acceptance will not apply since the software will not be used after the system has been accepted.
In order to avoid an impact on the project of the delay to STUBS we will reschedule the work to put the STUBS related work later in the project. This involves examination of the CSC dependencies and a rescheduling of most of the CSC's. This allows the STUBS work to be done later and still maintain the project schedule. The cost for this work is shown under the Rework of Schedule item. This rescheduling removes the need for a delay claim associated with late delivery of the STUBS devices (or replacement)."
176 The minutes of a GEC Marconi Project Management Team meeting of 24
October recorded that Mr Wishart received a phone call from
Kyrill Brent "today
(ie 24 October) concerned that a delay claim for STUBS would not be lodged,
since the STUBS emulator CR covered
it. [Peter Wishart] to discuss with [Roger
Cooke]."
177 On 25 October 1995 a further letter was written to Mr Brent by Mr Wishart
enclosing GEC Marconi's quotation for CR 3049. Omitting
formal parts, it
stated:
" CR3049 (STUBS Emulation)
Attached is the cost to complete for CR3049. Please note that the late delivery of STUBS devices (or replacement) may be the subject of delay claims."
The reason for this letter and its relationship to that of 23 October are
matters of real contention which are considered in detail
below: "The 23 and
25 October letters".
178 CR 3049 was submitted by Mr Brent to DFAT for approval. The CR was
attached as part of Contract Amendment No 23 ("CA23"). CA23
was signed by Les
Cook on 26 October 1995 and later by Mr Brent on 1 November 1995. The form of
the CA was as follows:
ADCNET Release 3 Contract NOT A CONTRACT VARIATION
DETAILS OF CONTRACT AMENDMENT PROPOSAL |
SCOPE
OF WORK TO BE UNDERTAKEN (use additional sheets if required): |
PRICING:
This amendment has no impact on the firm price. |
AUTHORISATION: |
The internal contradictions in this document as to whether it varied the
contract were a matter of submission.
179 On 1 November Mr Brent wrote to Mr Wishart indicating that DFAT had given
approval for GEC Marconi to develop the STUBS emulation
software and BHP-IT
agreed the quotation for $31,507.06 to undertake the work. Mr Brent did not,
though, prepare a formal Contract
Amendment document for the Sub-Contract
corresponding to CA23. He was not able to explain in evidence why he did not.
I would note
in passing that it is BHP-IT's submission, denied by GEC Marconi,
that it is clear from the documentary evidence that by November
1995 all of the
parties, including GEC Marconi, objectively intended and agreed:
(1) to remove the obligation upon BHP-IT and the Commonwealth to deliver STUBS
and correspondingly to remove the obligation upon
GEC Marconi and BHP-IT to
integrate STUBS into ADCNET; and
(2) to use an emulator to be constructed by GEC Marconi in performing the
contracts, and in carrying out acceptance testing, so
as to allow completion of
the contracts.
180 BHP-IT goes on to submit that the alleged contract variation to the
Sub-Contract for which it contends was manifest in later
actions of the parties
after 1 November. Before turning to those actions it is convenient to refer to
the evidence on the relationship
of the 23 and 25 October letters.
(ii) The 23 and 25 October letters
181 My concern for the moment is not with the ultimate effect to be given the
two letters as such. It is with the evidence concerning
their relationship.
182 I have referred above to the contents of the two letters and to the minutes
of the GEC Marconi Project Management team meeting
which recorded a call from
Mr Brent concerning delay claims for STUBS.
183 In their Witness Statements both Roger Cooke and Mr Wishart recount a
conversation between them, said to have been initiated
by Mr Cooke in which he
indicated that the 23 October letter could be misinterpreted as it could be
read to suggest that emulation
would cure future delays. Mr Wishart in turn
stated he would go to Kyrill Brent and recover the letter.
184 In his oral evidence Roger Cooke indicated that while his witness statement
referred only to his objection to the issue of delay
claims, he objected to the
entire letter. He acknowledged that he was aware that one of the central
issues in this proceeding was
whether the emulation software was to be used for
development, integration and acceptance of the ADCNET system but that nowhere
in
his statements did he record his objection to that part of Mr Wishart's 16
October memorandum to Mr Breden or to the 23 October letter
which said the
emulation software would be so used. He equally accepted that there was no
contemporary GEC Marconi document that
recorded such an objection.
185 Mr Wishart's oral evidence confirmed that of his Witness Statement that he
saw Mr Brent and indicated he wanted it back. He
said Mr Brent expressed
surprise at the language of the letter. Mr Wishart did accept that it was
possible the letter was not given
back. From discovery in this proceeding it
is clear that the original of the letter of 23 October as also that of 25
October remained
with BHP-IT on its Change Request file. However a copy of
only the latter letter was on BHP-IT's Correspondence file.
186 Mr Brent, while denying the occurrence of any meeting and conversation
concerning the return of the letter, conceded he had no
recollection whether or
not the claimed meeting occurred.
187 Finally Mr Wishart accepted in oral evidence that the second paragraph of
the 23 October letter concerning the use to be made
of the software reflected
what he thought was his understanding at the time and that this was that the
emulator would allow completion
of acceptance testing of the ADCNET Release 3
software. He had no recollection of what he was trying to convey in the third
paragraph
of that letter.
188 As I will indicate below, GEC Marconi's contention is that the 25 October
letter superseded the 23 October letter so withdrawing
any offer, or nullifying
any representation made, in the earlier letter. BHP-IT and the Commonwealth
contend that the purpose of
the 25 October letter, having regard to the events
giving rise to it, was to withdraw that part of the 23 October letter contained
in its third paragraph that related to delay costs.
(iii) From November 1995
189 By 4 November 1995 DFAT had prepared in draft form a document entitled
"KIV-7 Sealer/Gateway Interface Specification". On 8
November Les Cook sent
CR3057 to Mr Brent. The accompanying letter stated in part:
" STUBS REPLACEMENT - CHANGE REQUEST
Attached is a change request which proposes a set of changes to the FRS which will allow the replacement of the STUBS sealer and gateway devices with an approach based on the KIV-7 encryption device.
Accompanying the change request form are the following documents which define the scope of the change request:
a. `STUBS Replacement - FRS Changes'; and
b. `KIV-7 Sealer/Gateway Interface Specification'
Please note that the latter document is a draft at this stage as development is continuing to prove that the interfaces to the KIV-7 behave as described ...
Also accompanying the change request are the following documents which are not a party of the change request but contain explanatory material which may assist the PSI in determining the extent of the proposed changes and the reasoning behind them:
a. `STUBS Replacement - Design Principles';
b. `STUBS Replacement - Encryption Device Performance';
c. `STUBS Replacement - Routing Principles and Examples'.
The first of these is is (sic) a reply to your letter KB-752 which was a critique of the original draft proposal."
The change request was forwarded to Mr Wishart seeking a quotation for undertaking the scope of work. That quotation ($79,482.85) was provided on 27 November together with an outline of the scope of work. That outline disclosed it was based on the following assumptions:
"i That the CR will be approved by end Feb 1996. ...
...
iii KIV-7 devices will be treated as CSI.
iv Hardware changes to the Test and Integration Facility (TIF) to install KIV-7 devices and make them operational in the agreed reconfigurations will not be the responsibility of EASAMS. Software configuration of the TIF (except KIV-7 devices) will be the responsibility of EASAMS." Emphasis added.
Approval for the scoping was given by Les Cook on 7 December 1995.
190 Returning to November, the issue of delay claims and contract schedule
extension again became a subject of correspondence in
early November. On 10
November Mr Brent wrote to Mr Sharp of GEC Marconi seeking his support and
cooperation in progressing certain
matters "to a successful conclusion". These
were described as follows:
. our client the Department of Foreign Affairs and Trade has
issued a detailed specification for changes to the ADCNET Functional
Requirements
Specification and subsequent development and implementation of an
alternative to the STUBS device. This specification was referred
to EASAMS for
scoping under cover of change request 3057 dated 8 November, 1995;
. our formal proposal to the Department for contract amendment
and schedule extension included the development of a STUBS emulator
but did not
include the development of a STUBS alternative: Thus CR3057 constitutes an
additional scope of work;
. the Department has indicated that in order to give our proposal for
contract amendment favourable consideration a priced quotation
for the
implementation of CR3057 is required. This task needs to be completed quickly
to facilitate the passage of our proposal
and the establishment of a new
contract baseline;
. in order to substantiate our proposal for contract amendment
and schedule extension BHP IT and the Department require a revised schedule
to
be submitted for detailed analysis and ratification. ...
I am concerned that some of these matters have been outstanding for some
time without resolution. In my view we have an excellent
opportunity to
"reset" the project baseline. I would not wish to see this opportunity
forgone."
191 To again anticipate matters, discussions took place between Mr Brent and
Les Cook concerning delays occasioned by STUBS and otherwise.
On 1 December Mr
Brent wrote to Les Cook proposing extensions to the Contract Acceptance Date
for (inter alia) the Canberra System.
Les Cook replied on 5 December. The
letter stated:
" PROJECT DELAYS
The Department is not prepared to agree to an extension of the project schedule outside the contract mechanisms of change requests and claims for excusable delay, except in the case of a comprehensive agreement including the settling of all outstanding diarised incidents and the change requests relating to STUBS replacement, Xerox batch printers and the use of Applixware version 3.2 for HP/UX BLS.
As you have noted, there is a possibility that the contracted date for delivery of the Canberra software, after adjustment for currently approved change requests, will be reached before agreement is achieved. This would mean that the PSI had technically defaulted in the terms of the contract and that liquidated damages would commence. I note that the PSI is probably already in default of the contract, having failed to meet the contracted date for milestone 4000 even if the most generous view of possible claims for excusable delay is taken.
We believe that, provided that scoping of the referenced change requests is performed promptly, it should be possible to reach agreement before liquidated damages become payable. If it becomes likely that this will not be achieved, the Department will consider individual claims for excusable delay where these have been diarised and are reasonable within the requirements of the contract.
It is not the Department's intention to require liquidated damages to be paid if a comprehensive agreement on changes to the contract schedule is close to achievement. The Department is prepared to accept that a comprehensive agreement will nullify any liability for liquidated damages which would, under the terms of the existing contract, become due before the date of the agreement, provided that this occurs before 1 March 1996. If no agreement has been reached by 1 March 1996, the contract will be unchanged and liquidated damages will be payable from the contracted dates of milestones 5000 and 6000, modified by approved change requests and agreed delay claims."
192 Again to return to November, on 13 November Les Cook responded to a BHP-IT letter of 16 October which enclosed a copy for comment of Mr Newton's revised interface specifications for the STUBS emulator. This response post-dated the agreement on CR3049. Nonetheless Les Cook commented that the proposed interface design was sound in concept but had been simplified to the point at which some required functions could not be tested. These included five matters to which he referred specifically. The response went on to indicate:
"Although it has been agreed that it is no longer necessary to emulate STUBS-specific actions such as particular audit messages, it is important that all functionality included in the ADCNET software can be tested. It was for this reason that DFAT agreed to the cost of the emulation change request, which was greater than had been proposed by the PSI for a full scale emulation of the STUBS software interface specification."
193 The letter was forwarded to Peter Wishart for comment. In his oral evidence he accepted that it was apparent from Mr Cook's letter that what was wanted was an emulator that would enable completion of the ADCNET contract. In his reply of 22 November 1995 Mr Wishart commented that:
"The cutdown STUBS emulator was intended to provide a mechanism to exercise all paths through the IPD code which could be affected by the STUBS device. While this is being done mostly in the STUBS emulator, some components are more effectively implemented by changes directly to the IPD code."
He then replied specifically to the individual matters raised by Les Cook,
and concluded: "I believe that this addresses all the issues raised in
the correspondence": emphasis added. In cross-examination directed at the
first of the above-quoted sentences Mr Wishart accepted
that the "exercising"
process for which the emulator was to be used would permit the Release 3
software to be "ultimately acceptance
tested".
194 I earlier indicated that Mr Newton's evidence is that he did not see the 13
November comments of Les Cook. He likewise did not
see, or speak to Mr Wishart
about, the contents of 22 November reply. He nonetheless indicated in evidence
that Mr Wishart's replies
could have been based on the Newton paper of 30
October and that those replies did not seem to require any additional knowledge
or
discussion.
195 I would also note in passing that BHP-IT and the Commonwealth contend, but
GEC Marconi denies, that the above Cook-Wishart correspondence
provides written
confirmation of the Emulation Variation Agreement.
196 In December 1995 and January 1996 first the Commonwealth and then GEC
Marconi agreed a contract amendment to the Head Contract
(CA45) and to the
Sub-Contract (CA30). The amendment incorporated changes to Schedule 8 of the
two Contracts to reflect an extension
of time to complete the work approved in
twenty-eight change requests one of which was CR3049.
197 In GEC Marconi's risk analysis report of 14 December 1995 the following was
recorded:
"Ref: 13
Title: STUBS Availability date and numbers
Description: The earliest available date for the STUBS device and the number of devices available on that date may present some problems for the development and testing efforts.
RAP Details: STUBS devices will not be available in time. DFAT proposing use of a STUBS emulator to be constructed by the PSI and used for acceptance. STUBS devices is (sic) not being used on ADCNET.
Status: CLOSED."
198 As indicated in PART I, "The ADCNET Contracts", the Architecture Design
Document ("the ADD") described the architecture of Release 3 of the ADCNET
system.
It identified the hardware and software components of the system and
described how they were to be configured to meet the requirements
of the FRS.
The ADD was prepared by GEC Marconi and was deliverable under the Sub-Contract.
Along with the FRS, the ADD was one of
the designated "Customer's Functional
Specifications" in Schedule 1 of the Sub-Contract. One of GEC Marconi's
contractual obligations
was to update the ADD to incorporate approved contract
amendments to the Sub-Contract: Schedule 7, cl 2.2, WP2100.
199 Mr Harris, as GEC Marconi's Systems Engineering Manager, was responsible
for updating the ADD. Consequent upon the abandonment
of the STUBS devices, Mr
Harris made a number of amendments to the ADD in November 1995 which were
forwarded to Mr Brent in CR3060
on 28 November. The accompanying letter he
wrote stated, in part, that:
"The Attached CR is for changes to the Architecture Design Document. It has been updated to include the current definition of logical servers and mapping of these to CSC's. It has reference to STUBS KDC devices, Sealer Workstations etc. removed or replaced by STUBS emulation software."
Paragraph 1.2 ("System Overview") in its unamended form provided, insofar as relevant, that:
"Additional security specific software will provided (sic) as per COTS Software. This functionality will include:
. STUBS sealer and Gateway (Hardware and Software)."
Mr Harris' proposed amendment read:
"Additional emulation of security specific software will provided (sic) to emulate COTS Software. This functionality will include:
. STUBS sealer emulation and STUBS Gateway emulation (Hardware and Software)."
Some number of other STUBS related amendments was also made to the ADD
though some references to STUBS devices remained, as also did
a reference to
"trusted import/export gateway".
200 CR3060 was approved in turn by BHP-IT and by Les Cook and resulted in
Contract Amendment 31 (CA31) to the Sub-Contract (signed
19 December 1995) and
CA42 to the Head Contract. The relevant contract amendment instructions in
each case were:
"Architecture Design Document
Replace the amended pages of the Architecture Design Document (ADD), Version 2.0 with the new pages. When completed, the Architecture Design Document becomes Version 2.1.
Release 3 Contract
The Contract should be amended to refer to the Architecture Design Document as Version 2.1 (Schedule 1 in the Contract)."
201 Schedule 9 of the Sub-Contract specified the criteria to be used to
develop an Acceptance Test Plan ("the ATP"). The ATP was
to be used to show
that the Developed Software complied with the "testable shalls" of the FRS. It
was again Mr Harris who was responsible
for developing and maintaining the
ATP.
202 On 9 November 1995 Les Cook wrote to Mr Brent indicating that a current
contract amendment proposal was by then out of date given
"recent decisions to
[inter alia] replace STUBS". That contract amendment related to the ATP. Mr
Cook now proposed changes which
included:
"b) delete references to Stubs devices, Stubs workstations and Stubs software from the CSI List in Appendix C.
c) add references to Stubs emulation software where appropriate."
The letter concluded with the observation that "[o]nce agreement on the
STUBS replacement has been reached, further changes to the
ATP will be
necessary".
203 Mr Cook's letter was forwarded by Mr Brent to Mr Wishart on 13 November
under the heading CR3015. Mr Harris responded to Mr
Brent that the changes to
the ATP had been made as requested. The documentation was then sent to Les
Cook for approval. By this
time, though, Les Cook was proposing that the
contract amendment be delayed to reflect change to the ATP which would be
necessary
following the approval of contract amendments for (amongst others)
"the replacement of Stubs": letter to Mr Brent of 30 November
1995. He
nonetheless proposed the making of further amendments to the ATP.
204 On 18 December Mr Cook's letter was forwarded to Mr Wishart by Mr Brent,
who asked that Mr Cook's requested amendments to the
ATP be made. Mr Wishart
made a notation on that letter which he copied to Mr Harris which included:
"I do not want to wait for the other issues to be resolved before accepting this CR. I propose to flag delays to TRR until this is resolved."
205 The amended ATP was sent to Mr Brent on 7 February 1996 under cover of a letter from Mr Goldsmith who had replaced Mr Wishart as GEC Marconi's project manager. The letter, insofar as presently relevant, stated that the changes incorporated into the new version of the ATP included:
"Removed STUBS Sealers, STUBS Devices, KDC workstations, STUBS Audit workstations and STUBS conversion. STUBS Gateway workstations remain. STUBS conversion software changed to STUBS emulation software."
It went on to reject as "not practical" Les Cook's proposal to delay the
contract amendment until the details of (inter alia) the
STUBS replacement CR
was finalised.
206 It was Mr Harris' evidence in his Witness Statement that though he made the
amendments to the ATP it was not his understanding
then that the emulation
software proposed would enable Formal Qualification Testing ("FQT") without the
FRS being amended.
207 The amended ATP was approved by the Commonwealth on 6 March 1996 subject to
two minor amendments for which its further approval
was not needed. Mr Brent
forwarded CR3015 to Mr Goldsmith for signature on 8 March 1996. This was never
signed by GEC Marconi.
208 On 23 February GEC Marconi intimated to BHP-IT for the first time that the
inability of DFAT to supply STUBS might constitute
a default on the part of
DFAT and BHP-IT. This view was reiterated at a tri-partite meeting of the
parties on 29 February 1996.
209 The first notice of default was served on 3 April.
210 There is an additional piece of evidence to which reference should be made.
It relates to KIV-7 and I wish briefly to refer to
certain of the oral evidence
that touched upon it. Mr Wishart in cross-examination did not agree with the
proposition that the agreement
entered into in relation to CR3049 was to enable
the ADCNET contracts to be completed within a reasonable time. He described
his
own state of mind on the matter to be:
"I believe that the STUBS cutdown emulator agreement was dependent upon reaching agreement on the alternative STUBS strategy. So in my view in agreeing to the STUBS emulator I was aware that we had to have a replacement for STUBS strategy and that there was a CR forthcoming in that area."
Les Cook's evidence in cross-examination was that, when STUBS was known to
be unavailable, the best option DFAT had was KIV-7 though
it required further
investigation.
(b) Relevant Sub-Contract Provisions
211 In the description of "The ADCNET Contracts" in Part I of these reasons I
referred to those provisions of the Sub-Contract and the related contractual
documentation that have some bearing
on the question whether the alleged
Emulation Variation Agreement was entered into by BHP-IT and GEC Marconi.
Those provisions are
(i) cl 45 of the Sub-Contract which required any
variation to be in writing; (ii) cl 11 that stipulated the procedure
to
be followed in effecting a variation; (iii) cl 1.2 of Schedule 6 to the
Sub-Contract which envisaged the possibility of
change to CSI to be provided by
BHP-IT (including the STUBS devices) as a result of revision of the ADD; and
(iv) cl 2.2 of
Schedule 7 which included within GEC Marconi's project
management function the development of test harnesses for CSCI and acceptance
testing. Additionally cl 2.2.4.1 of Schedule 9 required that a test
harness be used for Interface Acceptance Testing where
operational equipment
was not available. For present purposes I need only indicate that a "test
harness" is a type of emulation
usually taking the form of emulation
software.
212 Both the relevance and the proper interpretation or effect of the above
provisions are contested by the parties. These are matters
considered below in
"Applicable Principles" and in "Submissions and Conclusions".
(c) Applicable Principles
(i) Was writing a prerequisite?
213 Clause 45 of the Sub-Contract required any contractual variation to be in
writing. BHP-IT's primary case is that the Emulation
Variation Agreement was
in writing. It claims in the alternative, though, that cl 45 does not preclude
the making of an oral or
implied contract, or else, if the requirements of cl
45 were required to be but were not satisfied, the parties by their conduct
clearly intended to waive formal requirements. GEC Marconi's contention is
that, as the variation was not in writing, the alleged
variation was
ineffective. Compliance with cl 45 was mandatory. As to the alleged waiver,
it is contended, that it was not open
to BHP-IT to make this submission as it
did not plead waiver of cl 45.
214 The pleading point apart, the submissions raise the question whether the
legal effect of cl 45 was to render ineffective any
subsequent implied or oral
contract the purport or effect of which was to vary the Sub-Contract?
215 That question must, in my view, be answered in the negative for reasons of
principle and of authority.
216 (1) While there is a voluminous case law concerned with the consequences
that can flow from non-compliance with formal requirements
imposed by statute,
as for example the Statute of Frauds and its offsprings: see Phillips v
Ellison Brothers Pty Ltd [1941] HCA 35; (1941) 65 CLR 221 at 243-244; Tallerman &
Co Pty Ltd v Nathan's Merchandise (Victoria) Pty Ltd [1957] HCA 10; (1957) 98 CLR 93 at
112-113, 122-124; Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1986) 162 CLR
221; Trimis v Mina [1999] NSWCA 140; it has no bearing on the present
question which involves the legal effect to be given to self-imposed, not
externally imposed (ie
imposed by law), formal requirements. Further, the
consequences of non-compliance with statutory requirements fall to be
determined
under the shadow of the legislative purpose of the particular
statutes in which they may be found: cf Chitty on Contracts, vol 1,
para 4-003 (28th ed).
217 (2) The principal cases in this country dealing with non-compliance with
contractually imposed written modification clauses are
those dealing with
claims to be paid for extra work or services rendered under contracts which
require written orders or written
agreements for such works or services:
Liebe v Molloy [1906] HCA 67; (1906) 4 CLR 347; see generally, Halsbury's Laws of
Australia, vol 3(2), 65-1145. The conclusions to be drawn from the cases
in this category are that (i) notwithstanding the writing requirement,
it is
open to the parties by express oral agreement or by contract implied from
conduct to impose further or different rights and
obligations on each other
from those contained in the original contract: Liebe v Molloy, above at
353-355; Commonwealth of Australia v Crothall Hospital Services (Aust) Ltd
(1981) 36 ALR 567 at 576ff; or (ii) that one party may so induce or
encourage the other's assumption on which it relies that the
relevant formal
requirements need not be complied with, as to be estopped from later setting up
those requirements: Update Constructions Pty Ltd v Rozelle Child Care
Centre Ltd (1990) 20 NSWLR 251. The relevant principle, for present
purposes, was stated concisely by Ellicott J in the Crothall Hospital
case in the following terms (at 576):
"It is open to the parties to a written contract to vary it. This may be done in writing or, except where the contract is required by law to be evidenced in writing, by oral agreement. The agreement to vary may be express or implied from conduct." Emphasis added.
The common, often fatal, difficulty experienced by a party in seeking to make
out a contract to vary has been the evidentiary one
of proof of the contract
itself: see Liebe v Malloy, above; Trimis v Mina, above at
[64].
218 (3) For an alleged subsequent variation to be contractually effective
notwithstanding non-compliance with the written modification
requirement, it
must itself otherwise satisfy the requirements of a valid contract, ie "the
terms of the arrangement must be certain,
and ... there must generally be real
consideration for the agreement": Ermogenous v Greek Orthodox Community of
SA Inc [2002] HCA 8; (2002) 187 ALR 92 at 99; and see below, "Formation of a contract of
variation".
219 (4) Internationally, the law varies widely as to the efficacy of what are
commonly described as "no oral modification" clauses
(a description I will use
hereafter). The common law rule in the United States has traditionally denied
effect to such clauses:
eg Bartlett v Stanchfield 19 NE 549 (1889);
Farnsworth, Contracts, §7.6 (3rd ed). As Cardozo J
observed in Beatty v Guggenheim Exploration Co 122 NE 378 (1919):
"Whenever two men contract, no limitation self-imposed can destroy their power
to contract again". Article 2-209(2)
of the Uniform Commercial Code, in
contrast, gives mandatory effect to a writing requirement for modification:
see White and Summers, Uniform Commercial Code, vol 1, §1-6
(4th ed, 2000 reprint); see also Unidroit, Principles of
International Commercial Contracts, Art 2.18. In the European Union, there
are countries that give only evidential value to a no oral modification clause,
while in
others such clauses are enforced: see Lando and Beale, Principles
of European Contract Law, Art 2:106, where the respective positions in the
countries of the European Union are described.
220 (5) The usual objection raised to depriving a no oral modification clause
of legal effect is that it involves a failure to give
effect to what the
parties have agreed. In the present case GEC Marconi has raised just this
objection. The vice in it, though,
is that a later oral or implied contract is
itself an agreement. As a US commentator recently observed (Snyder, "The Law
of Contract
and the Concept of Change: Public and Private Attempts to Regulate
Modification, Waiver and Estoppel" (1999) Wis L Rev 607 at 640):
"The question for the court is not whether to honour the parties' original agreement, but rather which of their agreements should be effective. To say that contract law should enforce the parties' agreement, therefore, does not resolve the issue. The question is whether to enforce the first agreement or the second.
The common-law courts addressing [no oral modification] issues chose the second. This choice makes a fair amount of sense; the later agreement probably reflects what the parties want better than their earlier agreement does."
I would add that the opinion expressed in the second quoted paragraph is
particularly appropriate to relational contracts which,
as in the present
instance, may be evolutionary in character.
221 (6) Though lacking legal effect in the face of a subsequent oral or implied
agreement, it seems to be accepted that a no oral
modification clause can have
significant evidentiary effect. As Holmes J commented in Bartlett v
Stanchfield, above: "The [clause] is a fact to be taken into account in
interpreting the subsequent conduct of the plaintiff and defendant";
see also
Principles of European Contract Law, above, Art 2:106.
222 (7) As a practical matter, the lack of legal efficacy of a no oral
modification clause may be attributable as much to the law
of estoppel as it is
to the apparent policy of the law to favour a later agreement over an earlier
one: cf Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd,
above, 275ff; see also W J Alan & Co Ltd v El Nasr Export and Import
Co [1972] 2 QB 189 at 213. As Farnsworth observes: "In most cases [in the
US] holding such clauses ineffective ... the party that
seeks to escape the
effect of the no oral modification clause has relied upon the oral
modification": Contracts, 450 (3rd ed).
223 I have not here made reference to the various submissions advanced by the
parties concerning the legal effect which ought be
given cl 45.1 of the
Sub-Contract. I mean no disrespect in so doing. While there may be
interesting questions yet to be resolved
in applying the relevant principles to
claims for extra works/variations under building contracts containing writing
requirements
for such works: see eg the judgment of Mason P in Trimis v
Mina, above, at [55]ff; the principles themselves are not, in my view,
open to serious question - the more so in a court of first instance:
see
Liebe v Malloy, above; the Crothall Hospital case, above.
(ii) Formation of a contract of variation
224 By way of prefatory comment I use the term "relational contract" in what
follows and in these reasons generally as signifying
no more than that it is "a
contract that involves not merely an exchange, but also a relationship, between
the contracting parties":
Eisenberg, "Relational Contracts", in Beatson and
Friedman, Good Faith and Fault in Contract Law, 296 (1995). Likewise, I
should not be taken as suggesting that special rules apply to such contracts
though I will indicate, as
is well accepted, that particular rules of contract
law have greater or less ease of application in relational contract settings.
However, I would suggest that account should be taken of such contracts as we
shape and develop contract law: see eg Goldwasser
and Ciro, "Standards of
Behaviour in Commercial Contracting" (2002) 30 Aust Bus Law Rev 369.
225 There has been a number of recent instances in which courts in this country
have given extended attention to the principles governing
contract formation:
see eg Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR
153; John R Keith Pty Ltd v Multiplex Constructions (NSW) Pty Ltd
[2002] NSWSC 43. The parties, reasonably, have not suggested that a like
exposition is again necessary in this instance. For present purposes I
would
merely note the following propositions which are relevant to issues raised in
this proceeding.
226 (1) Parties to an existing agreement may vary or extinguish some of its
terms by a subsequent agreement: Tallerman & Co Pty Ltd v Nathan's
Merchandise (Victoria) Pty Ltd, above. In so doing the parties will have
made "two contracts": Federal Commissioner of Taxation v Sara Lee Household
& Body Care (Australia) Pty Ltd [2000] HCA 35; (2000) 172 ALR 346 at 350; with the
latter, no less than the former being subject to the ordinary rules governing
contract formation:
eg BP Refinery (Westernport) Pty Ltd v Hastings Shire
Council [1977] HCA 40; (1977) 180 CLR 266 at 286; Tekmat Pty Ltd v Dosto Pty Ltd
(1990) 102 FLR 240 at 248.
227 (2) Conduct engaged in for the purposes of ongoing commercial arrangements
is not always readily susceptible to the traditional
forms of analysis employed
by common lawyers for the purposes of determining whether a contract has been
formed: Integrated Computer Services Pty Ltd v Digital Equipment Corp
(Aust) Pty Ltd (1988) 5 BPR 11,110 at 11,117. This can be particularly the
case when dealings are analysed on an offer and acceptance basis. So
in
Vroon BV v Foster's Brewing Group Ltd [1994] 2 VR 32 at 81, Ormiston J
was prepared to accept:
"that agreement and thus a contract can be extracted from circumstances where no acceptance of an offer can be established or inferred and where the most that can be said is that a manifestation of mutual assent must be implied from the circumstances."
Likewise in Integrated Computer Services Pty Ltd, above, at 11,118 McHugh JA observed that:
"in an ongoing relationship, it is not always easy to point to the precise moment when the legal criteria of a contract have been fulfilled. Agreements concerning terms and conditions which might be too uncertain or too illusory to enforce at a particular time in the relationship may by reason of the parties' subsequent conduct become sufficiently specific to give rise to legal rights and duties. In a dynamic commercial relationship new terms will be added or will supersede older terms. It is necessary therefore to look at the whole relationship and not only at what was said and done when the relationship was first formed."
228 (3) "In determining whether the communications between the parties
constitute a contract the court is not confined to a consideration
of the terms
or manner in which the communications were made: they must be interpreted by
reference to the subject matter and the
surrounding circumstances including,
inter alia, the nature of, and the relationship between, the parties, and
previous communications
between them, as well as to standards of reasonable
conduct in the known circumstances": Film Bars Pty Ltd v Pacific Film
Laboratories Pty Ltd (1979) 1 BPR 9251 at 9255.
See also Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd
(1988) 18 NSWLR 540 at 550.
229 (4) Post-contractual conduct is admissible on the question whether a
contract was formed though it is not admissible on the question
of what that
contract, if formed, means: Brambles Holdings Ltd v Bathurst City
Council, above, at 163-164; Lord Steyn, "The Intractable Problem of The
Interpretation of Legal Texts", 9ff, The John Lehane Memorial Lecture
(2002).
230 (5) The need frequently arises in relational contracts of significant
duration to adjust terms to accommodate changed or unforeseen
circumstances.
For that reason it is common for such contracts to make express provision for
variation. Nonetheless, and notwithstanding
their contract, parties in an
ongoing business relationship equally commonly "regulate their relationships in
accordance with what
they consider is fair and reasonable or commercially
necessary at particular points in time rather than by reference to a
priori rights and duties arising under a contract": Integrated Computer
Services Pty Ltd, above, at 11,117.
231 (6) There are two discrete classes of case where, notwithstanding that the
agreement of the parties does not finally settle what
is intended to be the
totality of their anticipated rights and obligations inter se, that agreement
nonetheless can constitute a
valid, effectual and binding contract. The first
class of case, now well accepted: see John R Keith Pty Ltd v Multiplex
Constructions (NSW) Pty Ltd, above; is where the parties are content to be
bound immediately and exclusively by the terms they have so far agreed upon
while
expecting to negotiate additional terms that will be embodied in a
further contract that will be in substitution for the first contract:
Sinclair, Scott & Co Ltd v Naughton [1929] HCA 34; (1929) 43 CLR 310; Graham
Evans Pty Ltd v Stencraft Pty Ltd [1999] FCA 1670, Full Court of the
Federal Court of Australia. The second class of case is where, for the
purposes of bringing about what is anticipated
will or may be their ultimate
legal relationship, the parties separately contract for discrete steps or
stages leading to that anticipated
relationship. Common examples are a process
contract followed by a substantive contract: eg Hughes Aircraft Systems
International v Airservices Australia (1997) 76 FCR 151; or contracts
dealing with discrete periods or discrete subject matters of the anticipated
relationship: cf South Sydney District Rugby League Football Club Ltd v
News Ltd (2000) 177 ALR 611 at 700-701. What differentiates this class of
case from that earlier mentioned is that a later contract is not
intended to be
in substitution for the first contract. Rather it is an additional and
different contract.
232 As will be seen, both of the above classes of case are relevant in this
matter.
233 I will in my "Findings and Conclusions" refer to one distinct matter of
legal principle that has not been the subject of detailed
submissions, though
it arises out of an assertion made by GEC Marconi. This relates to how
inconsistencies between the content of
an original agreement and that of a
later variation agreement are to be resolved, the inconsistencies being created
by the variation
agreement.
Submissions
234 The following is intended only as a broad outline of the respective
conclusions each of the parties invites me to reach as to
the existence and
scope of the alleged Emulation Variation Agreement. In the following section
("Findings and Conclusion"), I refer
to more detailed aspects of the quite
voluminous written and oral submissions made by the parties on the Emulation
Variation Agreement.
235 The parties' submissions reflect the temporal division (pre- and post- 1
November 1995) made in the factual narrative above.
I imply no criticism in
saying that while this allows for a more ordered consideration of a volume of
material, it somewhat artificially
contrives the framework for judging the
consequences to be attributed to communications and conduct engaged in by the
parties in
what was clearly a continually evolving relationship that was
confronting changing circumstances for which complex responses were
necessary.
I will comment further on this matter in my "Findings and Conclusions" which,
for the same reasons of convenience, adopts
the temporal division in the
parties' submissions to which I have referred.
236 BHP-IT's case can be put shortly. In its primary form it is that BHP-IT's
acceptance on 1 November of GEC Marconi's offer to
undertake CR3049 gave rise
to the Emulation Variation Agreement. The scope of that agreement was to be
discerned from anterior correspondence
(or anterior correspondence and
conduct). The agreement removed both BHP-IT's obligation to provide STUBS as
CSI and GEC-Marconi's
obligation to integrate it with the ADCNET software. It
substituted for those obligations an agreement that the Sub-Contract was
to be
completed using emulation software for acceptance testing. The agreement to
emulate necessarily carried with it an agreement
to amend all subsidiary
documents such as the FRS so as to enable emulation to be used effectively up
to and including acceptance
testing. Subsequent contract variations such as
that flowing from CR3060 evidence the carrying into effect of the Emulation
Variation
Agreement.
237 BHP-IT contends that, while no formal contract amendment document was
executed by the parties, it nonetheless is contained in
the correspondence and
associated documents that passed between the parties from the 25 July 1995
letter onwards. That documentation
was sufficient to satisfy the writing
requirement of cl 45.1 of the Sub-Contract. In any event, it is said,
cl 45.1 was
ineffective to defeat the Emulation Variation Agreement if it
did not satisfy cl 45.1 as it was a later valid and binding contract.
It
was also contended that GEC Marconi waived its right to insist on cl 45.1
(a matter considered under the heading "Waiver"
below).
238 The secondary submission advanced by BHP-IT was that the Emulation
Variation Agreement (having similar terms to that advanced
in the primary
submission) was agreed or confirmed in January 1996 as a result of change
requests and/or contract amendments made
in December 1995 and January 1996 (ie
CA30, CR3060 and CR3015 and its associated documentation).
239 Before noting GEC Marconi's response to BHP-IT it is convenient to note as
well the Commonwealth's submissions on this matter.
The Commonwealth's
interest in BHP-IT's defence of the GEC Marconi claim is twofold. First,
BHP-IT in its Further Amended Cross-claim
against the Commonwealth seeks an
indemnity and/or damages in respect of any liability BHP-IT may bear to GEC
Marconi. Secondly,
given the notices of breach served by BHP-IT on the
Commonwealth are substantially identical to those served by GEC Marconi on
BHP-IT,
to the extent that BHP-IT is able successfully to resist the claims
made against it by GEC Marconi for breach of the Sub-Contract,
so also should
the Commonwealth be able to resist the claims made by BHP-IT under the Head
Contract.
240 Because their respective interests in defending the claim by GEC Marconi
are common, the Commonwealth has in the main been content
to adopt BHP-IT's
submissions albeit with some elaboration on occasion. Save for Mr Wishart's
letter to Mr Brent of 23 October 1995,
all of the relevant documentation relied
upon by BHP-IT to establish the variation agreement either originated with, or
was passed
to, the Commonwealth.
241 There are several additional Commonwealth submissions that require notice.
First, it is claimed that under Schedule 6 of the
Head Contract and of the
Sub-Contract, the CSI (including STUBS) could be changed in the manner
envisaged in that Schedule (ie by
revising the Preliminary ADD). Such a change
was made as a result of CR3060 which removed references in the ADD to STUBS
devices
etc and replaced these with references to STUBS emulation software.
242 Secondly, the Commonwealth emphasises that the possible need to emulate for
acceptance testing had been raised at the very inception
of the two contracts.
Likewise, the issue of whether STUBS would be available at all was known by
BHP-IT and GEC Marconi from at
least February 1995.
243 Thirdly, it was contended that the basis upon which the parties contracted
in entering into the respective Emulation Variation
Agreements was that the
Head and Sub-Contracts would be completed using the emulator but that at the
same time they would explore
the feasibility of a replacement for STUBS.
244 Fourthly, to the extent that it is said by GEC Marconi that it was
technically impossible to complete the contract using the
emulator (unless the
FRS was amended to remove those "testable shalls" that presupposed STUBS had
been supplied), neither the Commonwealth
nor BHP-IT could insist on
requirements that could not be demonstrated using the emulator once they had
required the contract to
be completed with the emulator.
245 GEC Marconi's response to BHP-IT's defence is two tiered. The first
focuses upon the writing formalities and variation procedures
ordained by
cl 45.1 and cl 11 of the Sub-Contract. The second's concern is with
whether there was an Emulation Variation
Agreement.
246 As to the ordained contractual formalities, it is contended that (i) the
writing requirements of cl 45.1 were mandatory
but were not complied with;
(ii) before the Sub-Contract could be varied otherwise than in accordance with
cl 45.1 that clause
itself had to be varied to permit such variation, but
such did not occur in the instant case; (iii) even if the writing requirement
was not mandatory, the Court, nonetheless, should be slow to infer that the
parties intended a contractual amendment in circumstances
where the
requirements of cl 45 and cl 11 were not adhered to but had
previously been adhered to regularly when amendments
were intended.
247 As to the alleged Emulation Variation Agreement, GEC Marconi accepts that a
contractual relationship was created as a result
of BHP-IT's acceptance of GEC
Marconi's offer to undertake CR3049 but that the resultant contract was not at
all as BHP-IT suggests.
It is acknowledged that the terms of that contract
were not to be found simply in what was stipulated in the 24 August letter
which
was annexed to CR3049 as that was varied by conduct (and in particular in
correspondence) up to 1 November. But it is contended
that what was agreed was
neither that emulation was to replace the obligation to supply STUBS so as to
allow completion of the Sub-Contract,
nor that the emulator was to be used for
acceptance testing. The purpose of CR3049 as agreed after it was announced
that STUBS was
cancelled was to enable the development of the ADCNET software
to continue. An emulator was necessary for that purpose as the ADCNET
software
was designed with an interface to STUBS and it was not then known with what it
would eventually interface. From the time
of STUBS' cancellation alongside
emulation discussions there were discussions for the replacement of STUBS with
KIV-7 being contemplated
for this purpose. Those discussions made it
improbable that the parties had agreed to delete the obligation to provide
STUBS and
to complete the Sub-Contract using the emulator. It is GEC Marconi's
contention that no change to the parties' contractual rights
was intended
unless and until agreement was reached on a replacement.
248 Distinctly, GEC Marconi submits that the agreement propounded by BHP-IT was
so inherently uncertain as to be incomplete and unenforceable.
It did not
identify what were the consequential changes that needed to be made to the FRS,
the ADD and other contract-mandated documentation.
Nor did it provide an
agreed mechanism for working out those changes.
249 The events which occurred after 1 November, it is said, are of no
assistance in the matter either because they are post-contractual
and cannot be
used to determine what were the terms of the antecedent contract, or because
they do not confirm or carry forward contractually
the alleged Emulation
Variation Agreement.
(d) Findings and Conclusions
250 It is common ground between the parties that a contract was formed on
BHP-IT's acceptance of GEC Marconi's offer to undertake
CR3049. What is in
issue is the content of the contractual commitments then made. To anticipate
what follows, my own view is that
what was agreed was no less than the
Emulation Variation Agreement propounded by BHP-IT. The terms of that contract
were not to
be found in a simple documentary exchange of an offer and an
acceptance. Rather they were to be discerned from communications made
and
actions taken, leading to BHP-IT's acceptance of the CR3049 offer. I do not
consider that, in their setting, those communications
and actions admit of any
other conclusion than what was agreed was the Emulation Variation Agreement.
251 In reaching my conclusion I have relied little on the evidence of witnesses
called (save for Mr Wishart), unless that evidence
is supported by
contemporaneous documentary evidence. I regard the uncorroborated evidence of
Mr Brent and Roger Cooke in particular
as being generally unreliable though for
different reasons. I have made little reference to it in these reasons. I
later indicate
my reasons for treating Mr Brent's evidence as I do. Here I
would merely note that so imperfect is his recollection and so obvious
is his
reconstruction that it would be unsafe in most instances to accept his evidence
unless supported by contemporary documentation.
I do not rely upon Mr Cooke's
evidence for a different reason. I am unable to resist the conclusion that,
while there was much
in the detail of his evidence that was helpful, he was
clearly strategically partisan in the evidence he gave. This was most apparent
in his embellishment of, or qualification of, contemporary documentation
whether composed by himself or others.
252 Before turning to the documentary evidence, it is necessary to reiterate
that this is one of those cases in which the ongoing
working relationship of
the parties is a factor of no little importance for the light it sheds upon the
communications made and actions
taken in the period of immediate concern: cf
Film Bars Pty Ltd v Pacific Film Laboratories Pty Ltd, above, at 9255;
Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty
Ltd, above, at 11,118. That relationship provides the context in which
documentary exchanges are to be interpreted. They cannot properly
be divorced
from it.
253 By way of general background to what, somewhat inaccurately, I will call
the "CR3049 contract", I would note three matters.
First, not only did the
Head Contract and Sub-Contract contemplate the possible need for test harnesses
for CSCI and acceptance testing:
see eg Schedule 7, WP4500; but also it was
actually envisaged from early in the life of the ADCNET contracts that
emulation of
the STUBS devices could be necessary (inter alia) to minimise the
effects of possible delays in the provision of STUBS related items.
Secondly,
notwithstanding the formal obligation under the contracts to supply STUBS, it
was appreciated both by BHP-IT and by GEC
Marconi from at least 20 February
1995 that there was some possibility that STUBS might never be available.
Thirdly, by the time
active consideration was being given to the emulation of
STUBS for acceptance testing purposes, the Commonwealth (hence BHP-IT) had
twice been in contractual default in relation to the delivery of STUBS items
and, in relation to the provision of the STUBS untrusted
software, remained in
default.
254 The communications between BHP-IT and GEC Marconi that had direct bearing
on the content of the CR3049 contract began, for practical
purposes with Peter
Wishart's response of 3 August to Mr Brent's letter of 20 July 1995, in which
he confirmed GEC Marconi's capability
to design and develop test harnesses to
emulate STUBS. The premise of that communication was - and I so find - that
the emulation
envisaged was for the purposes of acceptance testing.
255 The Commonwealth's letter of 25 July foreshadowing what later became CR3049
was forwarded by BHP-IT to GEC Marconi on 4 August.
It is common ground in
this proceeding (a) that the letter contemplated acceptance testing with an
emulator, but (b) the formal
obligation to provide the STUBS devices remained.
As to the latter, DFAT's letter of 10 August that was forwarded to GEC Marconi
on 11 August, while reiterating that the emulation proposed would be for
acceptance testing, referred directly to circumstances in
which GEC Marconi
could incur liability under the contractual warranty when "STUBS [was]
implemented".
256 Pausing at this point, and disregarding Roger Cooke's evidence to the
contrary which I reject, the only reasonable understanding
the parties could
then have entertained of what was being proposed was that emulation was to be
used for acceptance testing under
the Head Contract and Sub-Contract,
notwithstanding the continuing obligation to provide STUBS. It is in
consequence unsurprising
that, in the context of the negotiations over contract
extensions and delay claims, GEC Marconi incorporated in its own proposals
to
BHP-IT that it "implement a STUBS harness suitable for development and
acceptance of R3".
257 The proper interpretation to be given Les Cook's letter of 24 August (which
was incorporated by reference into CR3049) has been
a significant issue in this
proceeding. The stimulus to this letter is revealed in its heading and opening
two sentences. These
state:
" EFFECTS OF HAVING TO EMULATE STUBS DEVICES
There have been suggestions that the need to emulate the STUBS devices will result in significant delays to the development schedule. The Department does not accept that such delays are beyond the control of the PSI."
The letter went on to identify what in Mr Cook's view were the software
modules the testing of which could have effects on the schedule
(ie those
modules which interfaced to the STUBS devices or other software which depended
on those modules). The letter indicated
that integration testing of such
software was not scheduled to be performed before STUBS emulation could be made
available and that
effects on testing at CSC level of such software could be
minimised by developing the emulation in two parts (which it then went
on to
outline).
258 GEC Marconi has submitted that this letter departed from what was envisaged
by the 25 July letter in that it only contemplated
the use of the emulator for
CSU testing, CSC testing and integration testing. In its submissions the
Commonwealth quite properly
asked rhetorically: "What had changed in the
intervening fortnight [from the 10 August letter]?"
259 I cannot accept GEC Marconi's submission. The purpose of the letter was
not to canvass directly the emulation to be expected
of the emulator as such
(though it did contemplate, variously, "full emulation" and "emulation of all
functions defined in the STUBS
SIS"). Its concerns were with quite particular
subject matter. These were (a) with delay to be occasioned by the need to
produce
the emulator; (b) with identifying where in the testing processes (ie
CSC testing etc) actual delays might occur; and (c) with
proposing how those
delays might be minimised (ie by the two part development). I do not consider
that the letter qualified, or
could reasonably be taken to have qualified, the
previously stated intent of the 25 July letter that the emulator was to be used
for acceptance testing.
260 When CR3049 was raised by DFAT on 6 September it described the scope of
work (inter alia) as "Develop STUBS emulation software
in a way that will
minimise the impact on the project schedule (refer to Mr Cook's letter dated
24/8/95)". I would make two comments
of this. The first is that, given the
explicit concern with minimising delay to the schedule, the reference to Mr
Cook's letter
is unsurprising. Secondly, the form used for the change request
did not itself go on to describe further the purposes to be served
by the STUBS
emulation software. The only proper inference to draw from CR3049 as raised is
that it carried forward the purposes
stated in the 25 July and 10 August
letters that emulation was to be used for acceptance testing. Mr Wishart's
risk analysis report
of 8 September 1995 clearly indicated that this was what
he understood was being proposed. I would also note in passing that Roger
Cooke's "contract negotiations" letter of 11 September to Mr Brent embodied a
like proposal.
261 In light of subsequent events, I should indicate what, in my view, was at
this time being proposed by the Commonwealth, hence
BHP-IT, to GEC Marconi and
was well understood by all three parties as being proposed. It was that (i)
there be a full surface emulation
of the STUBS devices; (ii) emulation be used
for acceptance testing; and (iii) formally, the obligation to supply STUBS
devices
(albeit at a later date) remained. For its part, GEC Marconi was
representing to BHP-IT that it had the capacity to design and develop
an
emulator that could be so used. I would also add that by the end of August,
Peter Wishart was of the view that it was most unlikely
that STUBS would be
available at all.
262 The cancellation of STUBS had a number of effects on what so far had been
proposed, the principal of which were encapsulated
in Les Cook's 26 September
letter. This letter is of some moment in this proceeding. First, it was
obvious that with the cancellation
there was no further need for a full surface
emulation of STUBS. This was made plain by Les Cook at the time and was
reiterated
as I will note below in the 26 September letter. Secondly, with the
demise of STUBS, a new strategy for ensuring boundary security
needed to be
adopted. Again Les Cook outlined at the cancellation meeting(s) the proposal
that KIV -7 be considered for this
purpose.
263 An apparent link was made between these two matters in the following part
of the 26 September letter:
"It is now important that a strategy to replace [the STUBS] devices be agreed by all parties, including the Department's security authorities and DSD. In order to avoid further schedule delays, the Department has agreed that an emulation of the STUBS devices should proceed in the interim to the extent necessary to complete the development and testing of ADCNET software which depends on the functioning of the interfaces to STUBS devices. To the extent practical, this emulation should be reduced from a full emulation of the STUBS interface to the minimum functions which will allow ADCNET software to be tested."
I would note in passing that GEC Marconi has submitted that the reference in
this passage to "an emulation ... [proceeding] in the
interim" was no more than
a delay avoidance device to permit development to proceed during the period
that might be occupied by the
parties in their negotiations for a replacement
device. It was no longer emulation for acceptance testing.
264 Immediately following the above passage, the 26 September letter
continued:
"DFAT is awaiting advice from the PSI as to the extent of such an emulation and whether this will be scoped in response to the original change request or whether that CR should be cancelled and replaced with another. The most recent development was that Mr Wishart and Mr Newton will examine the specification and advise.
Despite the lack of a formal response to the CR, the Department accepts that continued work on the emulator is a valid delay mitigation strategy."
265 The reference made here to CR3049 (which Mr Wishart was then costing for
scoping the work) is of some significance. As I have
indicated, CR3049
envisaged both a full surface emulation and the use of emulation for
acceptance testing. The letter clearly enough recognised that there was now an
asymmetry between the former
of these and what was now being proposed (ie a
cut-down emulation). This, of itself, would explain why Les Cook would ask
whether
CR3049 "should be cancelled and replaced with another". The critical
question, to which I will return below, is whether the letter
purported as well
to address and modify the second requirement of CR3049 (ie emulation for
acceptance testing).
266 GEC Marconi has submitted that the reference in the quoted paragraph to Mr
Newton and Mr Wishart `examining and advising' left
the question of the extent
of the emulation to the future and in consequence robbed the letter of
contractual significance. I should
indicate immediately that I reject this
submission. The letter indicated unequivocally the emulation that was proposed
and sought.
How that was to be achieved and the specifications for it were
clearly seen to be matters for further discussion if not agreement.
This was
understandable given the "to the extent practical judgment" that the letter
indicated need to be made. But that of itself
would provide no impediment to
the parties being able to agree to the proposal for emulation made even if
there was the need for
further agreement on the means to be employed to that
end: cf the discussion of cases of this type in John R Keith Pty Ltd v
Multiplex Constructions (NSW) Pty Ltd, above, para 217ff.
267 In relation to the cost of work necessary to examine strategies to replace
STUBS, DFAT indicated in the letter that this would
be covered by one or more
change requests. Les Cook in fact raised such a Change Request (CR3052) on the
same day.
268 I have referred above to GEC Marconi's submission that the emulation
contemplated by the letter was simply an interim measure
to avoid delay and to
allow development to proceed while replacement negotiations took place. It is
further submitted that the references
simply to "testing" with the emulator was
significant. When coupled with the notions of emulating "in the interim" and
of testing
the ADCNET software "which depends on the functioning of interfaces
to STUBS devices", it is said that there are clear indications
that what the
letter contemplated was not the use of the emulator for completion of the
ADCNET software but merely for completion
of those parts of it which interfaced
to STUBS. What ultimately seems to have informed these submissions was an
appeal to "commercial
sense". It was proposed that acceptance testing with a
STUBS emulator in anticipation of the eventual arrival of STUBS would make
obvious commercial sense. Acceptance testing with a STUBS emulator in
anticipation of the eventual arrival of a boundary security
device other than
STUBS would not make obvious commercial sense. Whether or not there was any
commercial sense would depend upon
knowing the outcome of negotiations for the
agreed strategy to replace STUBS.
269 I am unable to accept these submissions. Despite the assertion to the
contrary, they divorce the letter from the context and
the relationship in
which it was passed. The letter formally addressed what all parties recognised
was a new state of affairs.
After months of uncertainty as to whether STUBS
would be available late or at all, that matter was now clarified. It was not
coming.
In consequence a new strategy needed to be agreed. The need for such
a strategy inhered in the very nature of the ADCNET project
itself. Boundary
security was an integral element of it. The clear burden of the letter was a
request now to move on, to treat
STUBS as expunged from the project and the
ADCNET contracts, and to agree a strategy for replacement devices. The CR3049
proposal,
if accepted, had already envisaged acceptance testing of the ADCNET
software without STUBS. That testing should go ahead, albeit
with a "cut down"
emulator, in order to avoid further schedule delays which would result from
waiting until a replacement had been
decided.
270 In relation to acceptance testing, the letter changed nothing - and I do
not consider that the reference to testing software
that interfaced with STUBS
imposed a change or limitation on the emulation to be undertaken. That
reference was linked to the explanation
of the cut-down emulation now being
sought. What change the letter did invite the parties (ie BHP-IT and then GEC
Marconi) to accept
was that (i) STUBS was being removed from the ADCNET
project, hence the ADCNET contracts, and a replacement strategy in consequence
needed to be agreed; and (ii) a full surface emulation was no longer
necessary. It also envisaged further communications concerning
the
specifications for the emulator (involving Mr Wishart and Mr Newton). That
matter is further considered below.
271 GEC Marconi's appeal to "commercial sense" is, in my view, misplaced. A
rational commercial entity having regard to its own
self-interest could have
rejected what was being proposed for the "commercial sense" reasons proposed in
GEC Marconi's submissions
- though its so doing could well have imperilled the
levels of trust and cooperation to be expected in a contractual relationship
having the history and characteristics of the ADCNET contracts. I will return
to this theme later in these conclusions. What those
commercial sense reasons
cannot permissibly do is contrive the meaning of the terms of the letter
itself. Given the history of the
matter, what Les Cook was proposing as the
way forward was both reasonable and, I would venture, understood at the time -
as witness
Peter Wishart's oral evidence on the 23 October letter referred to
below.
272 The use of the phrase "in the interim", if understandable, was perhaps
unfortunate. What was being proposed could be said to
be an interim measure
pending a hoped for further agreement for a replacement. But it was
nonetheless, a distinct and self-contained
contractual arrangement for
completing acceptance testing of the ADCNET Release 3 software. What was being
proposed, in other words,
was what was expected to be the first of successive
contracts: cf South Sydney District Rugby League Football Club Ltd v News
Ltd, above, at 700-701. And it does seem clear (as witness Les Cook's 12
October letter quoted in the "Additional Factual Material")
that, for its part,
DFAT did not consider that the ADCNET project could be completed until
the second - the "replacement" - contract had been agreed. I would add that
the sequential character of
what was being proposed provided, perhaps, the
basis of Peter Wishart's erroneous belief that the STUBS cut-down emulator
agreement
was in fact dependent upon reaching agreement on the alternative
strategy.
273 GEC Marconi made no direct response to the 26 September letter though it
commenced acting in ways consistent with what was proposed.
Mr Newton was
commissioned to design the cut-down emulator. Mr Harris made the requested
comments on CR3052.
274 The next significant sequence of correspondence for present purposes was
the 23 and 25 October letters to BHP-IT which accompanied
GEC Marconi's
quotation for CR3049. Because of their significance it is necessary to again
set out their terms although I will not
repeat here the evidence earlier
narrated that bears on why the second letter was written.
275 The 23 October letter, which was approved in substance by Mr Breden
stated:
"The price shown for the attached Change Request (CR3049) are to implement the emulator and cover our costs in rescheduling to remove any impact of the late delivery of the STUBS devices (or replacement).
The software for CR3049 will not be developed with the process defined in the ADCNET Software Development Plan. It will be developed using rapid prototyping type methods with minimal external reviews, targeted at producing non-production software. The software is only to be used for development, integration and acceptance of the system under the contract. Warranty after acceptance will not apply since the software will not be used after the system has been accepted.
In order to avoid an impact on the project of the delay to STUBS we will reschedule the work to put the STUBS related work later in the project. This involves examination of the CSC dependencies and a rescheduling of most of the CSC's. This allows the STUBS work to be done later and still maintain the project schedule. The cost for this work is shown under the Rework of Schedule item. This rescheduling removes the need for a delay claim associated with late delivery of the STUBS devices (or replacement)."
The 25 October letter simply stated:
"Attached is the cost to complete for CR3049. Please note that the late delivery of STUBS devices (or replacement) may be the subject of delay claims."
276 All three parties have put in extensive written submissions on the
significance and interrelationship of these letters. Even
though they
communicated GEC Marconi's offer to undertake CR3049, I do not consider that
they warrant quite the attention they have
been given.
277 As to the 23 October letter, neither it nor the attached Change Request
actually describe the emulator to be implemented, though
the heading to the
letter refers to "CR3049 (Cut-down Stubs Emulator)". However, it is clear that
what was contemplated by all parties
was the emulator proposed, not in the
original CR3049, but in the 26 September letter which was now finding
reflection in Mr Newton's
paper and the API's that had been sent via Mr Brent
to Les Cook by 16 October.
278 The second paragraph in its reference to use of the software for
"acceptance of the system under the contract", did no more than
describe the
purpose of the emulator in terms that both BHP-IT and the Commonwealth would
reasonably have expected in light of the
26 September letter and its
predecessors back to the letter of 25 July. As I have indicated, the policy of
using the emulator for
acceptance testing had remained unchanged from 25 July
(though the need for it had changed with the cancellation of STUBS) and CR3049
was the vehicle that was to give effect to that policy. Mr Wishart in oral
evidence accepted that he thought his understanding at
the time was that the
emulator would be used for acceptance testing. And such clearly were the
contemporary understandings of the
Commonwealth and BHP-IT.
279 Even if this letter did not contain this description of the purpose of the
emulator, that statement of purpose would necessarily
still be taken to have
been part of the CR3049 offer in any event. It was, and was known to be, what
was expected of the emulator
since July 1995.
280 The evidence on the relationship of the two letters is unsatisfactory. I
am satisfied that Mr Brent, Roger Cooke and Mr Wishart
were, or became,
concerned about the observation in the third paragraph of the 23 October letter
that what was there being proposed
removed "the need for a delay claim
associated with the late delivery of the STUBS devices (or replacement)". Mr
Brent clearly raised
the matter with Mr Wishart on 24 October, and the matter
clearly was discussed by Roger Cooke and Peter Wishart. I am equally
satisfied,
despite Roger Cooke's evidence to the contrary, that this reference
to delay claims alone was all that was of concern in the letter
to either Roger
Cooke or Mr Wishart.
281 It is unnecessary to express any concluded view on whether a copy of the 23
October letter was retrieved by Mr Wishart from Mr
Brent. The evidence on this
matter is unsatisfactory. I am satisfied, though, that Mr Wishart met with Mr
Brent and discussed the
23 October letter. I am also satisfied on the balance
of probabilities that they did not wish this letter to be operative between
the
two companies because of what was contained in the offending third paragraph
concerning the absence of any need for a delay claim
and that that provided the
explanation for the sending of the 25 October letter (which expressly flagged a
possible delay claim).
I accept that Mr Wishart may well have intended to
replace the 23 October letter with that of 25 October, even if such may not
physically
have occurred. But I do not accept that he intended to resile from,
or to bring home to Mr Brent that he had resiled from, what
was conveyed in the
second paragraph concerning acceptance testing. Given the prior communications
back to 25 July about the purpose
of the emulation it would have required a
very clear statement indeed on Mr Wishart's and GEC Marconi's part that the
emulator was
not to be used for acceptance testing if this was what was
intended to be conveyed to BHP-IT by the 25 October letter.
282 The 25 October letter and the attached CR3049 did not describe at all
either the emulator to be implemented (ie cut down or otherwise)
or the purpose
of the emulator. In consequence, as BHP-IT rightly submits, the CR3049 offer
that was being made necessarily had
to be understood in the light of the
previous communications. Again, as BHP-IT submits, those communications going
back to July
1995 proceeded on the basis that the emulator would allow
acceptance testing. That never changed. And it was on this basis that
the
CR3049 offer was made. Equally, in light of the 26 September letter and its
reflection in the Newton paper and APIs sent to
Mr Brent prior to 25 October,
the emulation that was being offered BHP-IT was a cut-down one. GEC Marconi
has made particular submissions
on which of Mr Newton's papers it says have
possible contractual significance. I deal with those submissions below in the
context
of communications between Les Cook and Mr Wishart on 13 and 22
November. I merely note here that I have not accepted those submissions.
283 Finally, and I will return to this below, it ought be inferred that at or
around the time of making the 25 October offer GEC
Marconi was offering, and
would properly and reasonably be taken as offering, to proceed on the basis
proposed in the 26 September
letter as to the way forward - there would no
longer be an obligation to provide STUBS and the parties would seek to agree to
a strategy
to replace STUBS through Change Requests (one of which had already
been raised by the Commonwealth and commented upon by GEC Marconi).
CR3049 as
now amended was an integral part of what had been proposed. If it was to be
divorced from those proposals, GEC Marconi
had to bring that home clearly to
BHP-IT. It did not.
284 BHP-IT communicated its acceptance of the CR3049 offer to GEC Marconi on 1
November 1995. Unlike in the Head Contract, no consequential
formal Contract
Amendment was executed for the Sub-Contract. I do not consider this to be of
any particular moment. The Contract
Amendment (CA23) for the Head Contract in
any event merely described the amendment as "Development of STUBS emulation
software for
the Department of Foreign Affairs". As a statement of the burden
of the Emulation Variation Agreement and of its significance for
the then terms
of the Head Contract, that description was utterly uninformative. I likewise
do not consider that the internal contradictions
on the face of the Head
Contract's CA23 illuminated in any way, or otherwise had bearing upon, the
nature and terms of such contract
as was entered into by BHP-IT and GEC Marconi
at this time.
285 I am satisfied that the Emulation Variation Agreement was formed at least
by 1 November. I will explain below the reasons for
the uncertainty as to when
all parts of that agreement were settled.
286 If I am incorrect in concluding that GEC Marconi's offer on 25 October
encompassed, or could reasonably be interpreted as encompassing,
eliminating
the obligation to supply STUBS, I remain satisfied that its CR3049 offer was to
develop STUBS emulation software to enable
the ADCNET Release 3 software to be
acceptance tested using emulation and that that offer was accepted. I will
refer to this as
the "emulation agreement". If that agreement alone was all
that was entered into on 1 November 1995, it would nonetheless have
considerable
significance in this proceeding, particularly in relation to the
defences of affirmation and estoppel raised by BHP-IT. I will refer
to those
defences later in these reasons.
287 It is necessary to indicate what I consider to be the terms of the
Emulation Variation Agreement and whether or not these are
capable in the
circumstances of giving rise to an effective and enforceable contract. As I
have already indicated, GEC Marconi's
principal submission has been that the
parties never intended to enter into such an agreement. I have rejected that
submission.
GEC Marconi's further submissions are that if there was such a
purported agreement (a) it was ineffective because of the writing
requirement
of cl 45.1 of the Sub-Contract; (b) it contained inconsistent provisions
concerning the obligation to provide STUBS;
(c) it was inherently uncertain
and unenforceable because no amendments had been made to a range of
contract-mandated documents
and particularly the FRS; and (d) any agreement
that STUBS no longer had to be supplied by BHP-IT was conditional on the
parties
subsequently agreeing a replacement.
288 These submissions provide a convenient vehicle to deal with some number of
the issues concerning the terms and the effectiveness
of the Emulation
Variation Agreement. Before turning to them it is appropriate that I indicate
without further elaboration what
I find to be the terms of the agreement.
These are that:
(i) GEC Marconi would develop STUBS emulation software: (CR3049);
(ii) that software should emulate the STUBS devices to the extent necessary to
complete the development and testing of ADCNET software
that depended on the
functioning of the interfaces to STUBS devices: (the 26 September letter - the
cut-down emulation);
(iii) the emulator would be used in acceptance testing of the ADCNET Release 3
software: (the common understanding of the intended
purpose of the emulation
since 25 July 1995);
(iv) BHP-IT was no longer contractually obliged to provide STUBS devices under
the Sub-Contract as CSI: (the 26 September letter
proposal); and
(v) the parties would amend all subsidiary contractual documentation (including
the FRS) so as to enable emulation to be used for
acceptance testing: (an
implied term).
I would add that this agreement was made in a setting in which the parties had
available to them the machinery of the Sub-Contract
for amending the terms of
the contract and the contractual documentation so as to give formal expression
and/or effect to what they
had agreed.
(e) GEC Marconi's Attack on the Agreement
(i) Non-compliance with the cl 45.1 writing requirement
289 I have already indicated that such a provision in a written contract does
not preclude parties from later entering into even
an oral contract to vary
that written contract. It is the case, though, that no single document exists
that was signed by the parties
which embodied all that, objectively, was agreed
by them. Given the view I take of the ineffectiveness of cl 45.1, it is
unnecessary
to decide whether, having regard to the totality of the written
communications between them, all of the terms actually agreed were
agreed in
writing signed by the parties. My own view is that such, probably, was not the
case and that it is necessary to resort
as well to what was manifest in conduct
to ascertain the terms of the contract. I would, for example, note that for
reasons given
below it may well be said that GEC Marconi's agreement to the
deletion of the obligation to provide STUBS was manifest initially in
conduct.
290 I should also indicate that I accept that (a) the existence of cl 45.1
and the related procedural cl 11 in the Sub-Contract,
and (b) the pattern
of their prior use, are facts to be taken into account in determining whether
the subsequent conduct of the parties
was intended to be contractual in nature
though not conforming to those clauses or to that prior usage: Bartlett v
Stanchfield, above, at 395. Nonetheless I am satisfied that the course of
communication and conduct in this instance was intended to, and did,
have a
contractual outcome in the agreement I have found.
291 There is one additional matter to which I need refer though I will not
enlarge upon it. It proceeds on the assumption that I
am incorrect in the view
I take as to the legal effect of a provision such as cl 45. If cl 45
was binding and not complied
with, I would nonetheless find that GEC Marconi
was in the circumstances estopped from setting up the lack of writing to defeat
the
Emulation Variation Agreement: cf Principles of International
Commercial Contracts, Art 2.18. That estoppel, I am satisfied, has been
sufficiently pleaded and in issue to allow this matter to be raised. I refer
to it briefly below in "Estoppel".
(ii) The contract contains inconsistent provisions
(iii) The contract was inherently uncertain
292 These two matters can be dealt with together. As I understand them, GEC
Marconi's submissions are premised on my having found
an agreement both to
emulation for acceptance testing and to remove the obligation to provide STUBS.
It is contended that by agreeing
this much without also agreeing to make
corresponding amendments to requirements in those subsidiary contractual
documents (the FRS,
the ADD, etc) that are premised upon STUBS being available
for acceptance testing and which would preclude the use of the emulator
for
that purpose, the parties have created a state of affairs in which the
Emulation Variation Agreement and the Sub-Contract contain
inconsistent
provisions.
293 Alternatively, it is said, even if a consequence of the Emulation Variation
Agreement was that the subsidiary contractual documents
were to be amended,
there was no agreed mechanism for identifying the provisions that required
change or for determining what were
the changes that were needed. In
consequence the contract was inherently uncertain and unenforceable.
294 These submissions, in substance, challenge the implied term I have said was
part of the Emulation Variation Agreement. Before
discussing that term - which
I consider to be a complete answer to GEC Marconi's submissions - I should
comment first on the general
issue raised by GEC Marconi and on the responses
made to it by BHP-IT and the Commonwealth.
295 I have already indicated that GEC Marconi concedes that the STUBS emulator
was capable of being used for acceptance testing but
that the impediments to
its being so used were provisions in the subsidiary contractual documentation
and in particular the FRS which
contained "testable shalls" which could not be
demonstrated using the emulator. As BHP-IT indicated in its written
submissions,
the experts called - Dr Lewis and Professor Offen - both expressed
like views to the above concession. Later in these reasons I
will refer to
events in 1996 where it is claimed the Commonwealth and BHP-IT offered to waive
those FRS and other requirements that
stood in the way of completing acceptance
testing using the emulator. My concern here, in contrast, is with whether the
emulation
variation contract itself actually eliminated the alleged impediments
to completing acceptance testing on which GEC Marconi has focussed.
296 BHP-IT's response on this matter seems to be twofold. First, it contends
that the parties' agreement to remove the obligation
to provide STUBS and to
use emulation for acceptance testing, constituted agreed variations to the
Sub-Contract. As such these variations
attracted the operation of cl 11.2
of the Sub-Contract. It provided that where one party proposes contract
variations to the
other in writing, then -
"If the receiving Party accepts the variations, the Contract Specifications shall be deemed to incorporate the accepted variations from the date upon which the receiving Party notifies the proposing Party in writing that it accepts the variations."
The "Contract Specifications" referred to were defined in the Sub-Contract
to include (inter alia) the FRS and the ADD. Accordingly,
by force of this
provision the subsidiary contractual documentation was deemed varied so as to
permit the use of the emulator for
acceptance testing. The actual
documentation itself would later need amendment to accord with this new state
of affairs. It was
GEC Marconi's obligation under the contract to update the
subsidiary documentation to incorporate approved contract amendments:
Schedule
7, cl 2.2, WP 2100.
297 Distinctly, BHP-IT submitted that the agreement that STUBS was no longer
CSI and that emulation would be used for acceptance
testing carried with it
necessarily an agreement to amend all subsidiary documents (including the FRS)
so as to enable emulation
to be effectively used for development, integration
and acceptance testing. This, it is claimed, was part of the agreed scope of
the variation agreement.
298 The Commonwealth, while adopting BHP-IT's submissions, added a further
variant based on irrevocable waiver which led to the result
that BHP-IT was
precluded from taking advantage of GEC Marconi's inability to complete
acceptance testing with the emulator to the
extent that it could not
demonstrate requirements that were premised on the provision of STUBS. This
waiver involved a true abandonment
of rights and was irrevocable in consequence
of GEC Marconi's proceeding to build the emulator.
299 For its part GEC Marconi has submitted that cl 11.2 of the
Sub-Contract only applied to variations that were sufficiently
precise to admit
of incorporation; it did not apply to consequential variations occasioned by
an agreed variation; and the acceptance
of the variation had to be in writing.
These requirements were not satisfied in this instance.
300 Alternatively, it was contended that, given the actual inconsistency
between the Emulation Variation Agreement and the subsidiary
documentation, no
term could be implied into the agreement obliging the parties to act jointly so
as to remove any inconsistency.
The reason for this was that the contract as
it stood provided for inconsistent benefits and it was impossible for the
parties to
cooperate to give effect to those inconsistent provisions: cf
Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1998) 43
NSWLR 104.
301 Before turning to my own conclusion on this matter, there are some
evidentiary considerations to which I should refer. First
it is not open to
doubt that, with appropriate changes to the Sub-Contractual documentation, the
emulator could be used for acceptance
testing. The experts stated as much.
GEC Marconi's contract negotiation proposal for emulation presupposed as much.
Secondly, the
identification of the needed changes was a technical matter on
which opinions might differ. But there is no reason to believe that,
if
agreement as to the necessary changes was required for acceptance testing to be
completed, that could not have been achieved.
Thirdly, as Mr Varatharajan
accepted in oral evidence, the requirements that prevented completion with the
emulator would have become
apparent in any event at the time of system
integration.
302 In my view, it simply confronts common sense to suggest that, having agreed
to use an emulator for acceptance testing, the parties
would nonetheless have
continued to agree that BHP-IT would remain able to insist upon provisions in
subsidiary documents that would
have the effect of preventing that testing
being completed. It is for this reason both that BHP-IT and the Commonwealth
had striven
to find justifications for the contrary result, and that GEC
Marconi's submissions in opposition are quite so unappetising.
303 For my own part I do not consider that the BHP-IT submission based on
cl 11.2 of the Sub-Contract is available to it. The
effect that
sub-clause procures is, I consider, properly to be considered as dependent upon
the parties following the procedure mandated
by cl 11. That procedure
required direct specification of proposed variations to the Sub-Contract and
explicit agreement in
writing by the other party to those proposed variations.
Where agreement was procured in this formal way, it is understandable that
the
parties would agree in consequence to a provision such as cl 11.2
notwithstanding that later formal changes to the Contract
Specifications were
required to be made - the more so given that GEC Marconi was contractually
obliged to update those Specifications
to accord with agreed contract
amendments. There is a document to which the parties could later turn that
described what actually
was proposed and for which agreement was given.
However, where the parties' agreement is to be divined, as here, from a course
of
communications and of conduct, it seems to me that neither the letter nor
the spirit of cl 11 applies to such an agreement.
BHP-IT did not
explicitly submit a copy of its proposed contract variations to GEC Marconi.
It did not receive GEC Marconi's acceptance
in writing of those variations. I
have found that the parties did agree to contractual variation but this they
did in what I consider
to be an informal contract part of which, it is
reasonably arguable, was to be inferred from GEC Marconi's agreement to
undertake
CR3049.
304 Rejecting the cl 11.2 submission is not the end of the matter. I,
nonetheless, consider that there was an implied term
of the Emulation Variation
Agreement that related to the consequential amendment of the subsidiary
contractual documentation. Before
turning to that implied term, it is
appropriate to question the very premise of GEC Marconi's submission that the
inconsistencies
between the Emulation Variation Agreement and the
Sub-Contract's documentation render the emulation agreement ineffective.
Accepting
that there are such inconsistencies, two consequential questions need
to be answered. The first relates to the legal effect of the
Emulation
Variation Agreement on the Sub-Contract. The second relates to how the
Sub-Contract is to be interpreted (if it still
remains on foot) after it has
been varied.
305 As to the first of these questions, it is clear that when the parties
contracted in the Emulation Variation Agreement to vary
the Sub-Contract they
did not intend to end the Sub-Contract and replace it with that variation
agreement. Rather their intent was
to leave the Sub-Contract on foot subject
to the alteration: cf Federal Commissioner of Taxation v Sara Lee Household
and Body Care (Australia) Pty Ltd, above, at 350-351; Tallerman and Co
Pty Ltd v Nathan's Merchandise (Victoria) Pty Ltd, above, at 144. In
consequence it was the Sub-Contract as altered that the parties were required
to perform. But that contract
now contained inconsistent provisions relating
in particular to acceptance testing. And the resolution of that
inconsistency?
306 There is a large body of case law dealing with how a contract should be
construed when it contains inconsistent provisions, having
regard to the nature
and cause of the inconsistency: see generally Cheshire and Fifoot, Law of
Contract, 213 (8th Aust ed); Chitty on Contracts, vol 1,
para 12-076 (28th ed); Lewison, The Interpretation of
Contracts, para 8 - 08ff (2nd ed); Farnsworth,
Contracts, §7.11 (3rd ed). It is unnecessary here to
outline in detail the various "rules" of construction that have evolved to
resolve inconsistencies.
These rules reflect the types and causes of
inconsistencies: if specially tailored terms contradict standard terms, the
specially
tailored terms will prevail over the standard terms: cf Re
Theodorou [1993] 1 Qd R 588; "[i]f a later clause cannot be reconciled
with an earlier one creating an obligation, then if it altogether destroys
the
obligation it must be treated as void": Australian Guarantee Corporation
Ltd v Balding [1930] HCA 10; (1930) 43 CLR 140 at 151; if the terms of a document
incorporated into an agreement conflict with expressly agreed terms in that
agreement, the expressly agreed terms prevail: Modern Building Wales Ltd v
Lemmer and Trinidad Co Ltd [1975] 1 WLR 1281 at 1289; etc. The
common thread in the cases is that effect is given to that part of an agreement
"which
is calculated to carry into effect the real intention of the parties as
gathered from the instrument as a whole, and that part which
would defeat it
must be rejected": Chitty on Contracts, para 12-076.
307 In the present case the real intention of the parties in relation to
acceptance testing must be regarded as having been reformed
by the Emulation
Variation Agreement. Accordingly, the agreement to complete using emulation
must prevail over those provisions
in the subsidiary documentation that would
prevent this outcome occurring. The alleged inconsistency in other words would
be resolved
as a matter of construction though, it might be said, a hiatus in
the subsidiary documentation necessary for acceptance testing would
ensue.
308 It is unnecessary to consider whether the obligations imposed by the
Sub-Contract would themselves require the parties to amend
the subsidiary
documentation to permit acceptance testing with the emulator. No submissions
have been made either on this point
or, for that matter, on how the rules of
construction to which I have referred provide an answer to GEC Marconi's
submission.
309 BHP-IT, quite properly, was content to deal with resolution of the alleged
inconsistencies by resort to the terms of the Emulation
Variation Agreement
itself. It was an implied term of that agreement that, having agreed emulation
would be used for acceptance
testing, the parties would amend all subsidiary
documentation (including the FRS) to permit this to occur.
310 For my own part, necessary corollaries of BHP-IT and GEC Marconi agreeing
that BHP-IT was no longer obliged to provide STUBS
and that the STUBS emulator
would be used for acceptance testing were that:
(1) BHP-IT could no longer insist upon, and GEC Marconi could no longer be
required to demonstrate, those requirements of the subsidiary
documentation
that would defeat the very thing agreed - ie acceptance testing using the
emulator; and
(2) given the known contractual role of the FRS and other subsidiary
documentation in acceptance testing, that documentation would
be amended to
permit acceptance testing using the emulator.
It may well be that these corollaries were so much part and parcel of what
actually was agreed by the parties as to be able properly
to be treated as
representing their inferred intent. However, I consider that it is both open
and sufficient to imply a term ad
hoc to the same effect.
311 The present case is clearly one in which "the parties themselves did not
reduce their agreement to a complete written form ...
[they] have left some [of
the terms] ... to be inferred or implied": Byrne v Australian Airlines Ltd [1995] HCA 24;
(1995) 185 CLR 410 at 442. In determining what, if any, terms should be
implied in such circumstances, it is now well accepted that
caution is required
against a rigid or automatic application of the criteria specified in BP
Refinery (Westernport) Pty Ltd v Shire of Hastings [1977] HCA 40; (1977) 180 CLR 266 at
283, which govern the implication of terms into formal written contracts: see
the discussion in Yau's Entertainment Pty Ltd v Asia Television Ltd
[2002] FCA 338 (Full Court) at [27]ff.
312 For present purposes, and in light of Yau's case, it is sufficient
to say that a term based on the parties' imputed intention should be implied
into the Emulation Variation Agreement
if, but only if, it can be seen that the
implication of the particular term is necessary for the reasonable or effective
operation
of the contract in the circumstances of the case, and that that term
so would have been accepted by the parties as a matter so obvious
that it would
go without saying: see Yau's case at [33]-[36].
313 The term that I have indicated should be implied satisfies the Yau
requirements. It is, indeed, integral to what actually was agreed. While
it may be said that it would be sufficient simply to imply
a term precluding
BHP-IT from relying on those provisions that would prevent the emulation being
used to complete acceptance testing,
the role the Sub-Contract contemplates for
the subsidiary documentation in acceptance testing makes necessary the
implication that
the parties will amend that documentation to permit acceptance
testing with the emulator.
314 There are two additional comments I would make for the sake of
completeness. The first is that it remained open to the parties
to later reach
a different agreement both about emulation and about documentary changes. And
such might, though need not necessarily,
have happened if a replacement for
STUBS was earlier agreed and was available. Secondly, the implied term I have
found does require
further matters later to be agreed by the parties, albeit to
achieve a known end. The Emulation Variation Agreement was, nonetheless,
a
complete contract. What was left over were "matters of detail" which it was
open to the parties to leave "for future decision"
and inclusion in the formal
contractual documentation: Pagnan SpA v Feed Products Ltd [1987] 2
Lloyds Rep 601 at 619; and see Graham Evans Pty Ltd v Stencraft Pty Ltd
[1999] FCA 1670; John R Keith Pty Ltd v Multiplex Constructions (NSW)
Pty Ltd, above.
315 One matter I have not considered in dealing with GEC Marconi's submissions
is whether the inconsistency issue raised may be able
to be resolved by resort
to the order of precedence of documents prescribed by cl 2.1 of the
Sub-Contract. I express no view
on that matter.
(iv) A contingent agreement
316 The submission made here by GEC Marconi is that, if there was an agreement
that BHP-IT was no longer obliged to provide STUBS,
that agreement was
contingent upon a replacement for STUBS being agreed.
317 There is no doubt that from the time of the 26 September letter, the
parties became engaged in the processes that it was hoped
would lead to the
agreement of a replacement strategy for STUBS. CA3052 was raised on the very
day of the letter. Nonetheless,
as I indicated when considering that letter,
what was proposed were two discrete activities each of which, if agreed to,
would give
rise to separate contracts. The first was to remove STUBS from the
ADCNET contracts and to proceed to acceptance testing with an
emulator. The
second was to use change requests to examine replacement strategies.
318 It was, perhaps, the expectation of all parties at the time that a
replacement would be agreed - this was Les Cook's preferred
outcome. Yet there
was nothing in the 26 September letter or in any subsequent correspondence
before 1 November to justify the conclusion
that the Commonwealth, hence
BHP-IT, was making the deletion of STUBS contingent upon such later agreement.
On the contrary. The
Commonwealth was concerned to complete the ADCNET
project and agreement on a replacement strategy was essential to that.
The Commonwealth indicated in its 12 October letter, for example,
that it
wished to tie agreement on that strategy to the ongoing contract negotiations
for extension to the contract schedule and
that it trusted that work on CR3052
would be completed quickly "so that the overall negotiation on contract
variations to allow the
project to move to completion may be concluded":
emphasis added.
319 What the Commonwealth did not do as well was to tie the deletion of the
STUBS obligation to the contract extension negotiations
or to the agreement on
a replacement strategy. It is unsurprising it did not. STUBS no longer had
any place in the ADCNET project.
This was irrespective of whether the parties
were later able to agree a replacement strategy. The 26 September letter was
proposing
a moving on from the old STUBS status quo.
320 I am unable to agree that the emulation agreement was contingent in the
manner suggested by GEC Marconi.
321 The additional comment that should be made on the agreement to delete the
STUBS obligation is that, while it was not assented
to in express terms, that
assent can properly be inferred from GEC Marconi's binding itself to undertake
CR3049, if not from actions
taken some time before then. Objectively
considered, its assumption of that task in the context both of what was
proposed in the
26 September letter and of the steps already taken by way of
participation in what was proposed (ie the comment on CR3052 and the
exchanges
over the Newton paper), manifested to BHP-IT not merely an assent to develop
the cut-down STUBS emulator for acceptance
testing, but also agreement as to
how to proceed for the future - there would be no STUBS and no obligation to
provide it and resort
would be had to the change request procedure to explore
replacement strategies.
322 It is unnecessary for me to express a concluded view on whether GEC Marconi
so conducted itself prior to 1 November as to be
taken as having earlier bound
itself to at least the abandonment of STUBS. It had prior to that date begun
to act in ways consistent
with what was proposed on 26 September. Given the
view I have taken of the 1 November contract, I need not determine whether,
there
had already been a sufficient "manifestation of mutual assent" to delete
the STUBS obligation and to seek to agree a new strategy
through Change
Requests: Vroon BV v Foster's Brewing Group Ltd, above, at 81; see
also Integrated Computer Services Pty Ltd, above, at 11,118.
323 In the end, I am satisfied that by 1 November 1995 the parties entered into
the Emulation Variation Agreement. That agreement
provided a complete defence
to the claim brought by GEC Marconi insofar as it is founded on a continuing
failure to supply STUBS.
324 I will comment below more generally on my conclusion that the parties
entered into this agreement, but before so doing I should
refer (more briefly)
to the post-1 November matters on which BHP-IT relies in confirmation, or in
furtherance of, that agreement.
The evidence here is, in a sense,
multi-dimensional in its significance in that it is of relevance, variously, to
BHP-IT's defences
of election to affirm, estoppel and contractual variation.
(f) Post-November 1995
(i) The November correspondence concerning the emulator
325 The evidence dealing with this matter has been outlined above in
"Additional Factual Material". It will not be repeated here.
GEC Marconi has
submitted that this correspondence concerning the emulator, being
post-contractual, cannot be relied upon to demonstrate
the terms of the 1
November contract. In any event, it is said that correspondence merely
confirms that CR3049 related only to development
testing of the ADCNET software
and not to acceptance testing of the ADCNET system.
326 As to the latter point I am satisfied that, objectively considered, Mr
Wishart's 22 November response to Les Cook's comments
in his 13 November
letter, conveyed in clear terms that CR3049 would be adequate for its agreed
purpose and that, as I have indicated,
was to enable the parties to complete
acceptance testing of the ADCNET software without STUBS devices.
Unsurprisingly, Mr Wishart
in oral evidence indicated that he understood Les
Cook's letter as being premised on that purpose and that his own technical
description
in his 22 November response of what the "cutdown STUBS emulator was
intended to provide" conveyed that the emulator was to allow
the ADCNET Release
3 software to be acceptance tested.
327 I do not accept, though, that these communications are inadmissible on the
basis of the principle that "post-contractual conduct
is not admissible on the
question of what a contract means": Brambles Holdings Ltd v Bathurst City
Council, above, at 164. The purpose of the emulator was agreed on 1
November 1995 at the time CR3049 was agreed. Agreement on that purpose
did
not, in my view, carry with it the consequence that further comment on, and
revision (if necessary) of, the specifications for
the emulator were foreclosed
as from that date. Given that the function to be performed by the emulator was
specified by the ultimate
Customer, the Commonwealth, its continuing comments
on the sufficiency of the specifications for their purpose was properly to be
expected.
328 What is to be inferred, then, from this exchange of correspondence is that
it confirmed for the time being that the specifications
proposed were
sufficient to effectuate the agreed purpose of the emulator. It constituted,
in other words, a review of the sufficiency
of the documentation supporting
CR3049. As such I regard it as part of the matrix of facts of later actions of
the parties which
were, or were intended to be, contractual in character and
which in differing ways gave, or were intended to give, effect to the
Emulation
Variation Agreement as I have described it.
(ii) Sub-Contract Amendment 30
329 This Contract Amendment incorporated changes to Schedule 8 of the
Sub-Contract to reflect an extension of time to complete the
work approved in
twenty-eight change requests one of which was CR3049. I do not regard CA30 as
illuminating in any relevant way
the Emulation Variation Agreement. For
present purposes, it merely acknowledges the fact of CR3049, but not its burden.
(iii) GEC Marconi's 14 December risk report
330 Item 13 of this risk report stated that "STUBS devices is (sic) not being
used on ADCNET". It regarded the risk associated with
STUBS availability as
"Closed". This report was sent to Mr Brent on the same day, Mr Wishart
indicating in the accompanying letter
that he would like the report used "as
the basis of the project risk management meeting with BHP and DFAT".
331 While assisting in establishing the common understanding of the parties at
the time as to the status of STUBS in the ADCNET project,
this evidence
probably is not admissible to prove either the earlier 1 November Emulation
Variation Agreement: cf Brambles Holdings Ltd v Bathurst City Council,
above; or the terms of the later Contract Amendment (CA31), there being no
relevant ambiguity etc that, as objective background
circumstances, this
evidence could assist in resolving: Codelfa Construction Pty Ltd v State
Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337 at 348ff.
(iv) Change Request 3060/Contract Amendment 31
332 The evidence relating to this Change Request and Contract Amendment (signed
by Mr Brent and Mr Wishart on 18 and 19 December)
has been narrated above.
Briefly described, on 1 November 1995 Mr Harris of GEC Marconi made a number of
updating amendments to the
ADD, removing references to STUBS devices etc
(though not all such references) and replacing these with references to STUBS
emulation.
These amendments to the ADD were part of the subject matter of
CR3060. The letter sending CR3060 to Mr Brent on 28 November 1995
described
the updating as removing or replacing references to STUBS. The changes made
were approved by the Commonwealth and BHP-IT.
The resultant Contract Amendment
authorised the replacement of the pages of the ADD on which amendments had been
made. Further
it required that the "Contract should be amended to refer to the
Architecture Design Document as Version 2.1. (Schedule 1 in the
Contract)".
333 The Commonwealth and BHP-IT have attributed large significance to this
Contract Amendment. The ADD for the time being was one
of the two documents
that constituted the Customer's Functional Specifications under Schedule 1 of
the Sub-Contract. Their submission
is that the Sub-Contract, Schedule 6 paras
1.2, 1.3 and 1.4 envisaged that CSI equipment and Non-Developed Software could
be subject
to change as a result of revising the Preliminary ADD for the
purpose of preparing the Final ADD. This change to the specified CSI
by the
Customer's substitution of a different item of CSI for the originally specified
CSI as part of the System requiring integration
with the Developed Software,
need not have been a breach of the Customer's obligations under the Contract,
nor even a variation of
its terms. Instead it was a variation of the
content of existing obligations under the Contract taking effect no
later than upon the agreement to, and the making by the Contractor of,
appropriate changes to the Final ADD.
334 To understand this submission it is necessary to set out at some length
provisions of the Sub-Contract and of its Schedules.
The CSI to be supplied by
GEC Marconi pursuant to cl 7 of the Sub-Contract was that specified in
Schedule 6. Paragraph 1.2
of that Schedule stated:
"CSI shall include the equipment and non-Developed Software as defined in subclause 1.4 below. While such equipment and non-Developed Software may be subject to change as a result of revising the Preliminary Architecture Design Document for the purposes of preparing the Final Architecture Design Document, any increase ...": emphasis added.
Paragraph 1.3 provided, insofar as presently relevant:
"The following principles will apply to the evolution of the equipment configuration required for the development, integration, testing and commissioning of the Canberra and post and regional office systems:
...
(ii) the configuration defined under Item 1.4(b) shall be known as the Test and Integration/Acceptance Test System;
...
The Software Development System and the Test and Acceptance System shall be defined in the Software Development System Design Document and the Test and Acceptance System Design Document respectively."
Paragraph 1.4(b) provided in part:
"Test and Integration/Acceptance Test System
The physical configurations for the following systems shall be described in the Final Architecture Design Document.
The Test and Integration/Acceptance Test System shall consist of the following systems:
Secret Canberra System:
...
(xi) STUBS devices and related equipment and software."
335 Finally, cl 9 of the Sub-Contract required GEC Marconi to prepare
the Final ADD, and to submit it for review and subsequent
acceptance in
accordance with the Implementation Plan. That plan indicated that review of
the Final ADD was to occur at Milestone
2000. By cl 9.6 the Final ADD was
one of the documents in accordance with which GEC Marconi was to "integrate the
System".
336 Put shortly the submission is that, by replacing STUBS with STUBS emulation
in the ADD, the contracted for CSI was changed.
That some STUBS references in
fact remained was to be explained as oversight, no one intending by their
continuing presence in the
ADD that STUBS was ever going to be used in
ADCNET.
337 For its part GEC Marconi has submitted that the actual updating of the ADD
engaged in by GEC Marconi suggested no more than that,
as a transitional
matter, the system would include STUBS emulation but that it did not vary in
any way GEC Marconi's contractual
obligation in relation to testing.
Importantly no changes were made to the "testable shalls" in the FRS.
338 Additionally it was submitted that the ADD which was amended was not the
Final ADD envisaged by the Sub-Contract. The ADD would
only become the Final
ADD when it was accepted at Milestone 5000. It would be that document which
would depict at the end of the
process what the actual architecture of the
system was.
339 I should indicate immediately that I do not accept this last submission.
The document reviewed at Milestone 2000, which was an
earlier version of the
ADD amended by CA31, was itself described in the Schedule 8 "Implementation
Plan" as the "Final Architecture
Design Document". When para 1.2 of Schedule 6
referred to changes to CSI "as a result of revising the Preliminary [ADD] for
the
purposes of preparing the Final [ADD]", I consider that the obvious
contemplation of the provision in the setting of a contract that
envisaged
change, was that agreed changes to the ADD reviewed at Milestone 2000 were
"changes for the purposes of preparing" the
Final ADD and that they had
contractual effect once so agreed unless and until they were later changed by a
further amendment to
the ADD. In this sense the Final ADD could be said to be
and remain an evolving document until it had served all of its purposes
and was
contractually spent. But throughout that process it was at all times the Final
ADD.
340 Of GEC Marconi's general submission that CA31 was transitional, unrelated
to testing, and inconsistent with the FRS, I again
cannot agree. The actual
terms are not, in my view, uncertain or ambiguous such as would permit resort
to the factual matrix of
this contract to assist in their interpretation: cf
Codelfa Construction Pty Ltd v State Rail Authority of NSW, above, at
348ff. What is important, for present purposes, is to ascertain the purpose
and legal effect of the Contract Amendment.
To discover these does, in the
end, require resort to the Sub-Contract as altered by the Emulation Variation
Agreement, given the
relationship of CA31 to the Sub-Contract it amended. The
ADD identified the hardware and software components of the system to be
delivered. Under the Sub-Contract (Schedule 7, cl 2.2, WP2100) GEC
Marconi was required to update the ADD to incorporate approved
Contract
Amendments. As Mr Harris said in evidence, it was important that the ADD
reflected the architecture of the hardware that
would be part of the final
delivered system. That system was required by cl 9 of the Sub-Contract to
be integrated in accordance
with (inter alia) the ADD.
341 Considered in this setting, there is nothing in my view in the terms of the
amendments (so far as they went) or in the background
matters to which I have
adverted, to suggest that the amendments were, and were intended to be,
transitional. Those amendments,
having been accepted by the parties, had
contractual significance. By virtue of the terms of the Sub-Contract, their
premise was
that performance of the Sub-Contract involved integrating the
software with the components of the System described in the ADD including
the
emulation and that acceptance testing would be of the Developed Software so
integrated. The purpose of CA31, as far as it went,
was to give effect to that
premise.
342 The alleged inconsistency with the FRS - a document of coordinate
precedence in the matrix of contractual documents - was of
itself, in my view,
of no significance at the time; irrespective of the matter of construction of
inconsistent provisions to which
I earlier referred. The agreement to
acceptance test using STUBS emulation required significant updating of
contractual documentation
if that testing was to be conducted in accordance
with the documentation and not by resort to so-called waivers and ad hoc
variations.
The parties having agreed to this updating in the Emulation
Variation Agreement, it clearly was open to them to update that documentation
piecemeal, and to the extent that the updating was inconsistent with as yet
unvaried documentation, the former not the latter gave
effect to the real
intention of the parties as now expressed in the Emulation Variation
Agreement.
343 There is one additional matter to which I should refer in relation to
CR3060/CA31. Mr Harris gave evidence of what at the time
was his understanding
about the emulator and its use for acceptance testing. That evidence has no
relevance to any contractual issue
with which I am concerned. If it had, I
would have rejected it. It is, moreover, inconsistent in significant respects
with contemporary
documentation.
(v) Change Request 3015: Acceptance Test Plan
344 Schedule 9 of the Sub-Contract prescribed the criteria to be used to
develop the ATP. The ATP was to be used to show that the
Developed Software
complied with the "testable shalls" of the FRS. Again, it was Mr Harris who
was responsible for the ATP.
345 In the "Additional Factual Material" above I have referred to the raising
of CR3015 to amend the ATP in consequence of the cancellation
of STUBS, to the
amendments proposed by GEC Marconi, to their acceptance by the Commonwealth and
BHP-IT and, importantly, to GEC
Marconi's subsequent refusal ultimately to sign
CR3015 in March of 1996. By that time, GEC Marconi had indicated its view that
the
non-provision of STUBS might constitute a default by BHP-IT.
346 Though the significance of CR3015 has been the subject of lengthy
submissions by all three parties, I do not consider it necessary
to rehearse
their various contentions in any detail. GEC Marconi's submissions, in
addition to claiming that CR3015 had in the end
no contractual consequence,
simply reiterate by now familiar objections: the amendments were intended to
be transitional; and the
contractual obligation of GEC Marconi remained that
of demonstrating the "testable shalls" of the FRS.
347 In these circumstances I will state my own conclusions shortly. The Change
Request originally signed by Mr Harris stated its
"Issue/Concern" to be:
"Changes to ATP to show agree HW config[uration], software and External Devices
required for FQT [ie acceptance
testing]". The relevant amendments proposed in
the ATP sent to Mr Brent on 7 February 1996 by Mr Goldsmith (now GEC Marconi's
project
manager) were described as:
"Removed STUBS Sealers, Stubs Devices, KDC workstations, STUBS Audit workstations and STUBS conversion. STUBS Gateway workstations remain. STUBS conversion software changed to STUBS emulation software."
The STUBS workstations referred to are of no significance for present purposes. Illustrative of the changes made are those to para 3.3.2.3.1 which were as follows:
"3.3.2.3.1 Stubs {DELETE Devices DELETE} Emulation
3.3.2.3.1.1{DELETE The availability of Stub devices during the Acceptance testing is likely to be limited and will not be sufficient to support the Acceptance Tests. The use of simulators and/or interface stubs and any test waivers related to the Stub device will be resolved by agreement between the Customer and the Contractor.DELETE}Stubs Sealer and Stubs Gateway emulation software shall be used for FQT testing."
At the time GEC Marconi received CR3015 and the related proposed CA39 on 8
March from BHP-IT for signing, it was aware that the Commonwealth
had approved
the Change Request (subject to presently inconsequential amendments). I
equally infer that at that time GEC Marconi
was aware that BHP-IT likewise
approved of the amendments. It is the case, though, that no contract amendment
actually was signed
by GEC Marconi. I will comment later on the wellsprings of
GEC Marconi's decision to so act.
348 In the circumstances I am unable to find that the ATP amendments (a) had
contractual effect and (b) were another piecemeal step
in giving effect to the
Emulation Variation Agreement (which provided the rationale for the proposed
ATP amendments). At best the
events leading up to GEC Marconi's refusal to
sign evidence the clear common understanding of the parties that the Emulation
Variation
Agreement both had been entered into and was being put into effect.
It do not consider that the proposed amendments were intended
to be other than
operative when agreed. The only sense in which they may have been transitional
was if, before completion of acceptance
testing, a later contract was entered
into for a STUBS replacement which was required to be integrated with the
ADCNET software.
I equally consider that the failure to propose parallel
amendments to the FRS at the same time would not have robbed the ATP amendments
of any efficacy, if agreed in a Contract Amendment. I have indicated
sufficiently earlier in these reasons why I object to this
"inconsistency"
submission.
349 The events relating to CR3015 cannot, in the end, be relied upon make out,
or to establish a contractual confirmation of, an
Emulation Variation
Agreement. This said, the significance of those events to BHP-IT's alternative
claims based on affirmation by
election and on estoppel is self-evident.
350 The final observation I would make on the pre- and post- 1 November
communications and conduct of the parties is that, objectively
considered, they
clearly demonstrate that the parties agreed to the composite of proposals
making up the Emulation Variation Agreement
and that they then proceeded to put
into effect what had been agreed. If there is any element of doubt in this at
all, it relates
to the precise identification of the point or points in time at
which each of the component parts of those proposals were agreed.
I have
found, in any event, that this was no later than 1 November.
(g) Additional Observations
351 Having found that BHP-IT and GEC Marconi entered into an Emulation
Variation Agreement, I should make the following comment about
that finding.
While I am satisfied as to the making of that agreement and, for that matter,
that its making reflected the level of
cooperation and fair dealing that the
parties exhibited at that time, the agreement itself was an evolutionary one.
There is no little
artificiality, in my view, in having to subject the
communications and conduct of the parties over time to a traditional offer and
acceptance analysis. Equally, in my view, the dynamic character of the
parties' relationship rather suggests that the temporal differentiation
between
when an agreement was reached and when it was being performed for the purpose
of determining the terms of the contract can
be likewise artificial. As the
law now stands, I am not permitted to use post-contractual conduct for the
purposes of determining
the scope of the contract: cf Brambles Holdings Ltd
v Bathurst City Council. In relational contract settings at least, I would
suggest there is much to be said for the view that such conduct (insofar as it
reflects the parties' common interpretation of their contract: cf Spunwill
Pty Ltd v BAB Pty Ltd (1994) 36 NSWLR 290 at 309ff) should be admissible in
the interpretation of their agreement: cf Restatement of Contracts,
Second, §202(4); see also Lord Steyn, "The Intractable Problem of
Interpretation of Legal Texts", 10. In saying this I acknowledge
that "[i]t is
not easy to explain why subsequent conduct should be relevant to what the
parties intended when the contract was made":
Farnsworth, Contracts,
490 (3rd ed).
2. AFFIRMATION BY ELECTION
352 A distinct defence of BHP-IT is that, if it was in breach of the
Sub-Contract by its failure to supply STUBS and if that breach
entitled GEC
Marconi to terminate the contract either under cl 40 of the Sub-Contract
or at common law, GEC Marconi clearly
and unequivocally elected to affirm the
contract and in consequence lost its right to terminate.
353 This defence, I should note, would come into play if my conclusion as to
the entry into the Emulation Variation Agreement was
incorrect and if, in the
circumstances, a right to terminate existed either under cl 40 of the
Sub-Contract or at common law.
(a) Additional Factual Material
354 I have outlined already much of the dealings between the parties covering
the period from the cancellation of STUBS in mid-September
1995 until the
service of the first Notice of Breach on 3 April 1996. When later in these
reasons I deal with the alleged breach
arising from the non-payment of
Milestone 4000 I will refer to the evidence relating to the Test Readiness
Review ("the TRR") which
is relevant to the question of affirmation
notwithstanding the non-provision of STUBS. There is nothing additional that
needs be
narrated here.
(b) Relevant Sub-Contract Provisions
355 Though I will defer consideration of the proper construction of cl 40
of the Sub-Contract until later in these reasons,
it is necessary because of
GEC Marconi's election submissions to refer to the provisions of cl 40.8
and cl 40.9. These
provide:
"40.8 Where the Customer is in breach of an obligation under this Contract so that there is a failure by the Customer to perform this Contract, the Contractor may, by notice in writing to the Customer, specify that breach and where that breach is capable of being remedied require the Customer within 32 days of receiving such notice to remedy that breach or commence appropriate action to remedy that breach.
40.9 Where the Customer has not:
(a) remedied the breach referred to in subclause 40.8 within 32 days of receiving a notice (including because the breach was incapable of being remedied); or
(b) commenced appropriate action to remedy that breach within 32 days of receiving a notice and remedied the breach within a reasonable time after that period has elapsed;
the Contractor may, by notice in writing to the Customer, terminate this Contract without prejudice to any right of action or remedy which has accrued or which may accrue in favour of either Party."
(c) Applicable Principles
356 (1) A right of election arises when a state of affairs comes into existence
which enables a person to exercise alternative and
inconsistent rights against
another, for example, the right to terminate a contract for breach or
repudiation and the right to insist
on performance of the contract: Sargent
v ASL Developments Ltd [1974] HCA 40; (1974) 131 CLR 634 at 655. When "confronted" with
such a choice that person is required to elect which of the mutually exclusive
courses of action he or she wishes to take: Immer (No 145) Pty Ltd v
Uniting Church in Australia Property Trust (NSW) [1993] HCA 27; (1993) 182 CLR 26 at 41;
Motor Oil Hellas (Corinth) Refineries SA v Shipping Corporation of India
[1990] 1 Lloyds L Rep 391 at 398.
357 (2) Before a person can be said to be confronted with such a choice, that
person must at least be aware of the circumstances
giving rise to the choice:
Sargent's case, at 656-658; Khoury v Government Insurance Office
(NSW) [1984] HCA 55; (1984) 165 CLR 622 at 635. While there is still some degree of
controversy as to whether that person must as well have knowledge
of his or her
rights in cases involving common law rights: see Carter and Harland,
Contract Law in Australia, [1971] (4th ed): cf Chitty on
Contracts, vol 1, para 25-002 (28th ed); no issue has been
taken in this proceeding as to GEC Marconi's relevant state of knowledge.
358 (3) An election is not required to be made as soon as the choice arises.
"[The elector] is entitled to a reasonable time to consider
his position and
the merits of each course": Champtaloup v Thomas [1976] 2 NSWLR 264 at
273; Majik Markets Pty Ltd v S & M Motor Repairs Pty Ltd (No 1)
(1987) 10 NSWLR 49 at 54. As Mason J indicated in Sargent's case,
at 656: "He may keep the question open, so long as he does not affirm the
contract ... and so long as delay does not cause
prejudice to the other side".
I would note in passing that there is considerable United States authority in
favour of the view that
a right to terminate "must be exercised with reasonable
promptness after discovery of the breach": Cities Service Helix Inc v The
United States 543 F 2d 1306 at 1315; and see Farnsworth, Changing Your
Mind, 184. I will refer below to the significance of delay and prejudice
in this matter.
359 (4) Whether an election has been made is to be judged, not by the
subjective intention of the person having the choice, but by
that person's
words or conduct: Tropical Traders Ltd v Goonan [1964] HCA 20; (1964) 111 CLR 41 at
55. What is required is an "unequivocal act": United Australia Ltd v
Barclays Bank Ltd [1941] AC 1 at 30; an election taking place "when the
conduct of the party is such that it would be justifiable only if an election
had been made one way or the other": Sargent's case, at 656; that is,
"it is consistent only with the exercise of one of the two sets of rights and
inconsistent with the exercise
of the other": ibid, at 646. Additionally, as
the party making an election is "communicating his choice whether or not to
exercise
a right": Motor Oil Hellas (Corinth) Refineries SA v Shipping
Corporation of India, at 399; that choice will, as a rule: cf
Halsbury's Laws of Australia, vol 6 "Contract", 110-9465; be required
to be communicated to the party affected by the choice: Sargent's case,
at 655-656.
360 (5) While subsequent conduct in exercise of a right under the contract will
ordinarily manifest an election to affirm - unless
the right exercised is one
which allows the making of a choice to be deferred eg as in invoking an
arbitration clause: Larratt v Bankers and Traders' Insurance Co Ltd
(1941) 41 SR(NSW) 215 at 229 - words or conduct that merely recognise the
contract may not amount to an election to affirm. As Glass
JA commented in
Champtaloup's case, at 269:
"It is always necessary to examine the conduct relied upon as an affirmation in its particular evidentiary setting. The question must then be answered whether the party able to rescind has communicated to the other party an unequivocal election to affirm, ie to renounce its right to rescind. The materials upon which the decision is to be made will include any reservations which have also been communicated. The answer to be given is a decision of fact based upon all the evidentiary data. There is no overriding principle of law that an act done under the contract will always communicate the decision to affirm, regardless of the surrounding circumstances."
So, for example, conduct subsequent to a breach may result in the right to
terminate being made conditional on a further breach, as
for example in a case
where, time being of the essence, an extension of time is given consequent on a
failure to complete on time:
Tropical Traders Ltd v Goonan, above.
Distinctly, the parties' entry into negotiations after a breach or repudiation
might, depending on the context and the subject
matter of the negotiations,
"warrant the inference that there had been ... an election", or, in contrast,
that the parties were negotiating
on the assumption that the innocent party was
no longer bound by the contract: Petrie v Dwyer [1954] HCA 75; (1954) 91 CLR 99 at
105.
361 (6) There is a considerable body of authority for the proposition that a
party cannot avoid the legal consequences of conduct
amounting to an election
by stating that it is acting "without prejudice": see eg Davenport v R
(1877) 3 App Cas 115 at 132; Haynes v Hirst (1927) 27 SR(NSW) 480;
Central Estates (Belgravia) Ltd v Woolgar (No 2) [1972] 1 WLR 1048 at
1054. Nonetheless where the conduct said to give rise to an election is
"consistent with the reservation of
a right to terminate": cf Immer (No
145) Pty Ltd, above, at 30; an election may not be found notwithstanding
that acts may have been done that are consistent with the continuance
of the
contract. Equally, consideration of whether a decision to affirm has been made
must take account of "any reservations which
have ... been communicated":
Champtaloup's case, at 269. I would note in passing that in the US the
Uniform Commercial Code §1-207 takes a more generous view of the
effectiveness of an explicit reservation of rights.
362 (7) The effect of an election to affirm is that, once communicated to the
other party, the choice made becomes irrevocable and
the right to terminate is
lost in respect of the breaches of contract or repudiation that required the
election to be made: Sargent's case, at 656; Tropical Traders Ltd v
Goonan, above, at 55; and see generally Cheshire and Fifoot, Law of
Contract, para 21.31 (8th Aust ed); Chitty on Contracts,
vol 1, para 25-003 (28th ed); Farnsworth, Changing Your
Mind, 183. The irrevocability of the choice made does not depend on proof
of reliance by, or of detriment to, the party in breach. "An
election, unlike
estoppel, is concerned with what a party does and not what he causes the other
party to do": Khoury v Government Insurance Office (NSW), above, at
633.
363 (8) An election to affirm in respect of a breach of contract or of a
repudiation does not prevent the elector from relying upon
an available later
breach: cf Foran v Wight [1989] HCA 51; (1989) 168 CLR 385 at 441-442; or
repudiation: Ogle v Comboyuro Investments Pty Ltd [1976] HCA 21; (1976) 136 CLR 444 at
458-459; Carr v J A Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327; to terminate
the contract provided that there is a later breach or repudiation that is
distinguishable from
the earlier breach: cf Larking v Great Western
(Nepean) Gravel Ltd [1940] HCA 37; (1940) 64 CLR 221, at 236ff on the distinction between
a "once and for all" and "continuing" breach.
364 (9) Distinct rationales have been advanced to support various of the
principles that make up the law of election. Because
of their relevance to
the present matter, I would note the following two matters. First, the
requirements that the election be made
within a reasonable time (or, in the US,
promptly), and that it be irreversible have been said to prevent the elector
speculating
on the future progress of the contract at the other party's risk:
see Farnsworth, Changing Your Mind, at 184ff; that other party, having
no control over the choice finally made, being vulnerable necessarily to the
party having the
power of election: ibid 182. In consequence, these
requirements have been seen as having the capacity to help keep together
ongoing
transactions, for example, construction contracts, in which a breach
has occurred sufficient to give rise to the right to terminate:
Farnsworth,
Contracts, §8.19 (3rd ed). Secondly, and
correspondingly, the requirement that the election be communicated to the party
affected by the choice made has
been said to have no doubt been adopted:
"in the interests of certainty and because it has been thought to be fair as between the parties that the person affected is entitled to know where he stands and that the person electing should not have the opportunity of changing his election and subjecting his adversary to different obligations": Sargent's case, at 656.
(d) Submissions and Conclusions
365 BHP-IT has contended that GEC Marconi's election to affirm is clearly
evidenced in its continuing to perform the Sub-Contract
on the basis that it
would be completed without STUBS using emulation software; by GEC Marconi's
participation in the various change
requests and contract amendments between
mid-September 1995 and 3 April 1996; by undertaking the review work for the
Test Readiness
Review and then issuing an invoice to BHP-IT for Milestone 4000
on 12 March 1996; and by not notifying BHP-IT at any relevant time
that it
would or might rely on the non-provision of STUBS to trigger cl 40 of the
Sub-Contract.
366 Though contesting the construction BHP-IT sought to place on some of the
correspondence passing between it and BHP-IT, the Commonwealth
substantially
supported BHP-IT's submissions and contended, further, that GEC Marconi's
election to affirm the Sub-Contract was mirrored
in BHP-IT's like election to
affirm the Head Contract.
367 For its part, GEC Marconi denies it elected to affirm the Sub-Contract. It
contends, first, that cl 40 of the Sub-Contract
did not, on the
cancellation of STUBS, give rise to an inconsistent right. Rather it clearly
contemplated the continued performance
of the Sub-Contract, the giving of
Notices and of termination thereafter. By continuing to perform - and it was
bound to do so pending
the issue of Notices - GEC Marconi could not be said to
have elected to waive its right to terminate. Secondly, the various contract
amendments and change requests are said by GEC Marconi not to evidence an
election. In particular, CR3049 was a separate contract
and the pending of
CR3057 made GEC Marconi's conduct equivocal. Thirdly, it is said that BHP-IT's
refusal to supply STUBS was repudiatory
and continuing. Even if there was an
earlier election this did not preclude a later termination. Fourthly, if the
failure to supply
STUBS was a "once and for all" breach, GEC Marconi did not
elect to affirm and for this it relies upon (a) its inability to complete
the
ADCNET contract without STUBS in the absence of an agreed variation to the
contractual documentation; and (b) its entitlement
to await the outcome of
negotiations for a variation before it needed to elect whether to affirm or to
terminate.
368 My own conclusion is that, despite GEC Marconi's ingenious argument as to
the operation of cl 40 of the Sub-Contract, this
is a clear case of
affirmation and that GEC Marconi's purported termination was an attempt,
opportunistically and too late, to avoid
a "regretted decision" it had long
since made. The non-provision of STUBS was not a "sleeper" that GEC Marconi
could awaken for
its own advantage five months after the cancellation of STUBS
was announced: cf Cities Service Helix Inc v The United States, above,
at 1315. Given the nature of the contractual relationship and what transpired
in the intervening five months, GEC Marconi
had lost its right to resort to
cl 40 of the Sub-Contract to precipitate a termination.
369 I should deal first with GEC Marconi's submission that, in the case of a
breach that could attract cl 40 of the Sub-Contract,
that clause did not
occasion the need to make a choice between inconsistent rights as it clearly
contemplated a continued performance
of the Sub-Contract pending non-compliance
with the Notice of Default and the consequent decision to terminate.
370 For my own part I do not consider that the effect of cl 40 can be
dispensed with so easily. Assuming the cancellation of
STUBS was a failure to
perform the Sub-Contract such as to attract the provisions of cl 40, GEC
Marconi was then confronted
with a clear and obvious choice. It could then and
there affirm the contract and claim damages (if it was so minded) flowing from
the non-provision of STUBS, but by so doing it could no longer seek to
terminate the contract because of that failure to perform.
Alternatively it
could invoke cl 40 thereby creating the conditions that would permit it to
terminate the contract. Such a
state of affairs clearly required a choice to
be made. It is not sufficient to say that both affirmation and invoking
cl 40
required GEC Marconi to continue to act in performance of the
contract. That action in performance would be to quite different ends
in each
case: in one, it was premised upon the contract being kept on foot shorn of
the right to terminate; in the other, it was
for the purpose of creating the
conditions for its demise.
371 GEC Marconi's submission in effect invites me to conclude that, having
cl 40 available to it, GEC Marconi could keep BHP-IT
at its mercy
indefinitely, BHP-IT never knowing whether the continuing performance of the
Sub-Contract resulted from GEC Marconi's
affirmation or from its intent to keep
open the possibility of activating cl 40. This, clearly enough, offends
the policies
informing the law of election to which I have referred as well as
"simple considerations of common sense and equity": Johnson v Agnew
[1980] AC 367 at 398. More importantly though, it highlights why a state
of affairs existed in which GEC Marconi was able to exercise
alternative and
inconsistent rights against BHP-IT and why, being confronted with such a
choice, it had to elect either to affirm
the contract or to activate
cl 40.
372 I do not consider that the facts (i) that cl 40 required the giving of
a notice to remedy before termination could be effected;
and (ii) that
termination under cl 40 was not automatic but gave a discretion to the
contractor, affected the conclusion at
which I have arrived. These provisions
provided a graduated procedure involving in the first instance the taking of "a
less drastic
course of action": cf Motor Oil Hellas (Corinth) Refineries SA
v Shipping Corporation of India, above, at 398; before termination could
be effected. Affirmation and cl 40 gave rise to two quite different and
inconsistent
regimes of contractual rights and obligations. GEC Marconi was
obliged within a reasonable time to elect of which of the two it
wished to
avail.
373 I should add the following for the sake of completeness. First, I do not
consider that cl 40 was intended to be a provision
that would enable
deferral for an indefinite period of a decision to terminate. It simply
allowed for a period of grace before such
a decision could be taken. Secondly,
GEC Marconi has submitted that the cl 40 procedure is additional to the
common law rights
to terminate. If such was the case, and I express no view on
the matter, it would be anomalous if the common law right was able
to be lost
by affirmation while that self-same affirmation did not as well preclude resort
to cl 40. Finally, though it does
not bear on the question of
characterisation of cl 40.8 and cl 40.9, it went without saying when
GEC Marconi served the
first notice, that it was beyond BHP-IT's power to
remedy the breach or to commence appropriate action to remedy it (as envisaged
by cl 40.9(a) or (b)). These were matters within the control of the
Commonwealth.
374 To the extent that GEC Marconi relies upon the fact of negotiations for a
possible replacement to STUBS as relieving it of the
need to make an election
until the outcome of CR3057 was known, I simply reiterate what I earlier stated
(see "Applicable Principles"):
negotiations after breach, depending on their
context and subject matter, may warrant or preclude the inference that the
contract
has been affirmed. The fact of CR3052 and CR3057 and the associated
dealings between the parties are simply part of the material
to be considered
in determining whether a choice was made. Even if, contrary to my view, it was
the case that GEC Marconi could
have delayed making its choice until the
outcome of CR3057 was known, it did not do so as I will indicate below.
375 Distinctly, GEC Marconi contends that the refusal to provide STUBS was a
repudiatory and continuing breach such that the issue
of affirmation did not
arise as the repudiation continued to operate until it had been either
withdrawn or remedied by performance.
Thus, an election to affirm did not
preclude a subsequent termination.
376 This, in my view, mischaracterizes the cancellation of STUBS in the setting
in which it occurred. It is the case that (i) the
loss by affirmation of the
right to terminate for breach will not preclude termination for a later
repudiation of the contract: Ogle v Comboyuro Investments Pty
Ltd, above, at 458-459; (ii) the loss by affirmation of the right to
terminate for repudiation will not preclude termination for a
subsequent breach of contract that gives rise to the right to terminate:
cf Foran v Wight, above at 441-442; and (iii) the loss by
affirmation of the right to terminate for breach will not prevent
termination for a further breach that gives rise to the right to
terminate: Larking v Great Western (Nepean) Gravel Ltd, above, at
236.
377 The present matter, though, does not fall within any of the above three
classes of case. I will indicate later in these reasons
(the "Construction of
Clause 40") that I do not consider that the non-provision of STUBS was, for the
purposes of cl 40.8, a
"failure ... to perform [the] Contract". Accepting
for present purposes that it was, it amounted to no more than a failure to
perform
by reason of a breach of a "once and for all" provision of the
Sub-Contract. The obligation to provide STUBS was an obligation to
do a
definite act and not to create and maintain a state of affairs: cf Larking
v Great Western (Nepean) Gravel Ltd. BHP-IT, in fact, persisted in failing
to provide STUBS, though there is nothing in the evidence to suggest that that
failure during
the period relevant for present purposes was other than expected
and acquiesced in by the parties. From mid-September 1995 until
the first
intimations in late February 1996 that GEC Marconi might treat the
non-provision of STUBS as a default, the parties were
directing themselves, not
to the future provision of STUBS, but to agreeing a replacement strategy, with
KIV-7 being the initial
subject of examination.
378 In the same way that BHP-IT's continuing failure to provide STUBS did not
constitute any further breach of contract but was merely
a failure to remedy a
past breach, the "failure to perform" for cl 40.8 purposes was of a like
character. BHP-IT's conduct
was not repudiatory in the sense of amounting
additionally to a refusal to be bound by the Sub-Contract: cf Carr v J A
Berriman Pty Ltd, above at 349. Its failure amounted to "the breach of a
specific provision", not "the renunciation of the contract as a whole":
cf
Sibbles v Highfern Pty Ltd [1987] HCA 66; (1987) 164 CLR 214 at 227. I would merely
add that, considered in its factual setting, it is far from the reality of the
matter to
suggest other than that the Commonwealth (hence BHP-IT) were
committed to the completion of the ADCNET project so that, once STUBS
was
cancelled, ways forward were being proposed.
379 I do not consider that BHP-IT was guilty of a further breach of contract
or of a subsequent repudiation beyond its breach of
contract (and for
cl 40 purposes, its "failure to perform") because of the continuing
non-provision of STUBS. Likewise I do
not consider either (i) that that breach
was other than a once and for all breach, or (ii) that the parties at the time
considered
the breach in any different light.
380 I do not intend again to analyse either the communications and agreements
reached or negotiated (if not reached: eg CR3015)
between the cancellation of
STUBS announcement on 13 or 14 September and the serving of the first Notice in
April 1996, or the known
conduct of the parties in that period. I would simply
make the following observations about it.
381 First, those communications, etc manifested in a variety of ways that GEC
Marconi was electing to affirm the contract. The change
request and contract
amendment mechanisms were used on a number of occasions during that period.
That usage was consistent only with
a choice on GEC Marconi's part to keep the
contract on foot despite the breach. Contrary to GEC Marconi's submission, it
is not
to the point that some of those requests and amendments involved
separate contractual agreements (as for example CR3049). Those
agreements were
predicated upon, and had no justification without, the continuation of the
Sub-Contract.
382 Secondly, the emulation agreement resulting from CR3049, represents the
clearest early act of affirmation. Its later culmination
in the building of
the emulator, its demonstration, and the receipt of payment for it, merely
confirmed what had previously been
affirmed.
383 Thirdly, GEC Marconi not only did acts which recognised the Sub-Contract,
it proceeded to perform its own obligations, not merely
in the continued
development of the ADCNET software, but also in relation to the TRR contractual
Milestone. In relation to the latter
it went so far as to call on BHP-IT to
perform its Milestone 4000 obligation and to pay GEC Marconi. What makes this
latter action
the more significant is that it occurred after GEC Marconi had
raised the prospect of the non-provision of STUBS being a default
under the
Sub-Contract. The claim to be paid for Milestone 4000, made over four months
after the notice of STUBS cancellation, presupposed
that GEC Marconi was
relying on the continued operation of the Sub-Contract to make good that claim
and that it was insisting upon
BHP-IT's continuing performance of its
obligations.
384 BHP-IT has not relied upon the passage of time as such to preclude GEC
Marconi from asserting its right to terminate, because
of prejudice to BHP-IT.
Rather it properly points to the communications made and conduct engaged in
during that period as confirmatory
of the inference that the choice to affirm
was made. It likewise points to the absence of any communicated reservation of
rights
across the period until the default issue was raised in late February
1996. Given both the way forward proposals put by Les Cook
in the 26 September
letter and the immediate moves made then to investigate a replacement for
STUBS, if there was to be any prospect
of the inference of affirmation not
being drawn from what transpired from and after the CR3049 agreement an
explicit reservation
of rights needed to be made within a reasonable time and
to be communicated to BHP-IT clearly and unmistakably.
385 This was a relational contract and the second in a sequence that dated back
to 1990. The parties' actions necessarily need to
be considered in the context
of a long standing business relationship - a relationship, moreover, through
which GEC Marconi sought
to derive other advantages from its association with
BHP-IT beyond the completion of the ADCNET contract. I merely note in passing
that on 6 February 1995 GEC Marconi entered into a standing offer agreement
with BHP-IT in the expectation of being asked to provide
IT systems integration
services to BHP-IT which would in turn be supplied to the Department of
Defence: see below "BHP-IT's Termination
of the Standing Offer Agreement".
386 The evidence suggests that, notwithstanding uncertainty about the
availability of STUBS (in time or at all), from at least July
1995 (if not
considerably earlier) the parties were prepared to consider cooperating and to
propose compromises (often admittedly
self-interested) to have the ADCNET
contracts completed. So, for example, GEC Marconi had itself proposed in the
context of schedule
renegotiation prior to the cancellation of STUBS, that
emulation be used to conduct acceptance testing. I consider that through
1995
the parties, though not acting disinterestedly, were regulating their
relationship more by reference both to what was fair and
reasonable having
regard to the objectives of the ADCNET project and to what could be mutually
accommodated in changing circumstances,
"than by reference to a priori
rights and duties arising under [the] contract": cf Integrated Computer
Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd, above, at 11,
117.
387 That GEC Marconi might activate cl 40 of the Sub-Contract to terminate
the contract within a reasonable time after the formal
26 September notice that
STUBS would not be provided, was not an expectation that any of the parties
including GEC Marconi would
reasonably have entertained at that time. Not
surprisingly, from 26 September until at least the first default Notice, GEC
Marconi
continued to perform and to participate in the exercise of rights under
the Sub-Contract - as did BHP-IT. In relation to the Head
Contract, BHP-IT and
the Commonwealth acted similarly. The prospect of termination for breach was
simply not on the horizon and
the parties acted accordingly. Their
negotiations for a replacement strategy were not to be conducted under the
shadow of a retained
right to terminate. On the contrary.
388 So it was that Mr Sharp could not disagree with the proposition put to him
in cross-examination that all of the communications
that he had been making
with BHP-IT until 19 February 1996 had been aimed at reassuring BHP-IT that GEC
Marconi intended to continue
with the fixed price contract and that it intended
to cooperate with changes to the contractual arrangements that might be
necessary
to enable that to occur.
389 Mr Sharp went on to admit that he had read the Sub-Contract carefully and
that in or shortly prior to March 1996 he had fastened
upon the failure to
provide STUBS as an opportunity for GEC Marconi to escape from its obligations
under the contract.
390 As Mr Hilton SC happily put the matter, GEC Marconi was "content to proceed
[with the contract notwithstanding the non-provision
of STUBS]. Mr Wishart
gave evidence to that effect. That's what the documents say. It's only when
the businessmen took over the
management of the contract that a commercial
decision was made to escape from the obligations ... [B]y then it is just too
late".
3. ESTOPPEL
391 There are two quite distinct defences founded on estoppel. The first is
premised upon the Emulation Variation Agreement having
been entered into but
being ineffective to vary the Sub-Contract (contrary to my conclusion) because
it failed to satisfy the requirements
of cl 45.1 of the Sub-Contract. The
defence raised is that the circumstances both leading up to, and consequent
upon, the entry
into that agreement on 1 November were such as to estop GEC
Marconi from later insisting upon the cl 45 writing requirement.
392 The second estoppel defence related to the non-provision of STUBS. Put
shortly and somewhat inaccurately, it is that in consequence
of BHP-IT's
detrimental reliance both on representations by GEC Marconi and on the common
understanding of the parties that BHP-IT
was no longer required to provide
STUBS and that GEC Marconi would no longer assert any right to require it, GEC
Marconi was estopped
from departing from the position so represented and so
conventionally understood.
(1) Estoppel and Clause 45
393 I have already found that the Emulation Variation Agreement was entered
into on 1 November 1995 and that the parties proceeded
to carry it into effect.
Emblematic of the latter were (i) the producing of the specifications for the
emulator and the communications
between all three parties concerning them;
(ii) GEC Marconi's building and demonstration of the emulator; and (iii) GEC
Marconi's
invoicing BHP-IT and BHP-IT's payment for the performance of
CR3049.
394 I likewise have indicated that I consider that it was open to BHP-IT to
raise this defence. There was no express pleading of
estoppel directed at
cl 45.1 as such, but there was such a pleading directed at the obligation
to provide STUBS. In the circumstances
of this trail and of the issues raised
in it, I am satisfied that it was open to BHP-IT to raise the cl 45
estoppel notwithstanding
GEC Marconi's protests to the contrary. It arises so
directly out of the matters that have been in contention in both the Emulation
Variation Agreement and the second estoppel defences that I am unable to accept
that it cannot now be relied upon or that GEC Marconi
would be prejudiced in
any way by BHP-IT so doing.
395 As to the estoppel itself, I consider it unnecessary either to reiterate
here the evidence I have already analysed when considering
the Emulation
Variation Agreement or to anticipate the additional matters to which I will
refer when dealing with the second estoppel
claim. Having found that the
parties entered into the Emulation Variation Agreement, that evidence clearly
demonstrates the reliance
of both parties on their common understanding that
there was such an agreement and that it would be, and then was being, carried
into effect. I have illustrated this above. Such reliance in the
circumstances makes it unjust to allow GEC Marconi to raise the
cl 45
writing requirement and to depart from the understanding it both shared with,
and reinforced in, BHP-IT: Thompson v Palmer [1933] HCA 61; (1933) 49 CLR 507 at 547;
Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20
NSWLR 251 at 276-277; see also Unidroit, Principles of International
Commercial Contracts, Art 2.18.
(2) Estoppel and the Obligation to Provide STUBS
396 The two species of estoppel pleaded are estoppel by representation and
estoppel by convention. The former is advanced in both
its common law and
equitable guises. The evidence relied upon to make out both the representation
alleged and the conventional understanding
of the parties, is essentially the
same as is the subject matter of the representation and understanding
respectively.
397 Insofar as presently relevant, the representation and understanding as
pleaded were said to be:
"(b) the Sub-Contract Variation Agreement had been entered; or
(c) the Respondent was no longer obliged to deliver STUBS equipment or associated software to the Applicant; or
(d) the Applicant would no longer assert or rely upon any right to require delivery of STUBS equipment or associated software under the Sub-Contract."
The "Sub-Contract Variation Agreement", as pleaded, made up only part of the
Emulation Variation Agreement I have found. It removed
BHP-IT's obligation to
provide STUBS and GEC's obligations in respect of STUBS, and it varied the
Sub-Contract's contract specifications
to that effect. A separate CR3049 STUBS
Emulation Agreement has, though, been pleaded. For practical purposes, that
Agreement replicated
the first three clauses (relating to emulation) of the
Emulation Variation Agreement I have found. The Emulation Agreement, I would
add, is one of the evidentiary matters relied upon in making out the estoppel
advanced.
398 The detriment that has been pleaded as having resulted from BHP-IT's
reliance upon the representation or conventional understanding
is also common
to both claims. It is said to be:
"(a) The Respondent did not require the Commonwealth to provide the STUBS hardware and software as CSI under the Head Contract.
(b) The Respondent did not serve notices of breach on the Commonwealth under the Head Contract until 11 April 1996 ... and did not negotiate a full time and materials variation to the Head Contract."
399 As was perfectly plain from the evidence of a hearing that occupied over
seventy days, if the representation and understanding
were made or entertained
as alleged and were relied upon by BHP-IT, the above two specified matters of
detriment (both in the nature
of omissions to act) would clearly not exhaust
the matters to which BHP-IT might be able to point as possibly constituting
detriment
if GEC Marconi were to be permitted to depart from what was
represented or commonly understood. I will later refer in particular
to
evidence given by Mr Brent on this.
400 Predictably, BHP-IT in submissions has sought to cast its net more widely
than those two specified matters. This, also predictably,
has generated a
pleading dispute, GEC Marconi alleging it would be prejudiced if this was to be
allowed. The prejudice apprehended
is the possible effect of not knowing at
the time various BHP-IT witnesses were cross-examined of what is now sought to
be relied
upon. For reasons I enlarge upon in "Findings and Conclusions", I
have allowed BHP-IT to raise these "new" instances of detriment.
I would have
to say that I regard the objection in any event as being more technical than
substantial in the circumstances. Given
the nature of the representation and
understanding pleaded, and the character and extent of the conduct engaged in
by the parties
subsequent to the alleged representation and understanding, I
consider that the apprehended prejudice can in the circumstances be
safeguarded
against in the findings I am prepared to make. I would note that GEC Marconi
has experienced no apparent difficulty
in making lengthy submissions on the
newly relied upon matters.
(a) Additional Factual Material
401 All of the material referred to earlier in relation to the Emulation
Variation Agreement has been recycled for this defence.
There are several
additional pieces of evidence to which I should refer. It is also necessary to
refer in a little detail to Mr
Brent's evidence of his state of mind and
reasons for action in late 1995 and early 1996.
402 (i) After being appointed General Manager of GEC Marconi, Mr Sharp met with
Mr Brent on 27 November 1995. On 5 December Mr Brent
wrote a letter to Mr
Sharp which contained a resumé of the matters discussed. It included
the following:
". EASAMS schedule - you indicated that EASAMS was moving it's ADCNET project control mechanisms to a more rigorous project control regime. We agreed that EASAMS will provide a month-end schedule of the ADCNET project each month to BHP IT beginning with the month of November, 1995;
. EASAMS estimate to complete - you indicated that EASAMS propose to have an independent estimator conduct a full re-estimate of the work remaining. These estimates will be calibrated against work completed to determine the accuracy of the estimate;
...
. STUBS - you indicated that EASAMS would produce a formal priced proposal for the replacement of STUBS by 22 January, 1996. In this context we discussed options for ensuring smooth passage to the proposal."
403 (ii) On or about 9 February 1996 representatives of the Commonwealth, BHP-IT and GEC Marconi including Les Cook, Mr Brent and Mr Wishart attended a demonstration of the emulator at DFAT's premises. I accept that the view was there expressed that the emulation software was considered satisfactory. After the demonstration Les Cook wrote to Mr Brent in the following terms:
"The STUBS emulation software was demonstrated by Mr Peter Newton and additional information was provided by Mr Scott Preston.
I confirm that, to the degree of detail presented, the emulation will be adequate to enable formal qualification testing of the release 3 software to be performed."
There is no documentary evidence indicating that this letter was sent to Mr
Wishart. Mr Wishart could not recall if he had read the
letter.
404 (iii) GEC Marconi raised an invoice for the emulation software on 6
February 1996. Payment of $31,507.06 was authorised by Mr
Brent and was made
on 19 February 1996.
405 (iv) On 1 March 1996, Mr Goldsmith sent a facsimile to Mr Sharp which was
copied to Roger Cooke. It opened with the following:
"Regarding the letter about the Partial Emulation of STUBS:
1. After much searching through the documents, we discovered a letter from Peter to Kyrill dated 21 November (File Ref 081/PJW-95-11-21-1 copy attached) which at the second para states "The cutdown STUBS emulator was intended to provide a mechanism to exercise all paths through the IPD code which could be affected by the STUBS device".
2. In a memo to Howard Breden dated Oct 16 1995, Peter states that the STUBS Emulator `software will only be used for development, integration and acceptance of the system under contract'. He states that we wont warranty the emulator s/w ... I attach this memo.
3. Basically I don't think you have a viable case to say that the system wont work if it is tested against the emulator. I also don't think that you can make much of a case that DFAT can't use the system without STUBS. It is their risk."
The 21 November letter referred to in the first paragraph is (from its File
Ref number) Mr Wishart's 22 November letter.
406 (v) On 28 March GEC Marconi wrote both to Mr Brent and to Mike Haddad (the
Senior Commercial Manager of BHP-IT) outlining its
response to CR3057. This
was "$8 million letter". It precipitated internal written communications in
BHP-IT to which I will refer
below.
407 (vi) On 28 May 1996, Mr Brent wrote to Les Cook seeking his advice on
(inter alia) the following matters:
"3. given that the purpose of STUBS emulation is to allow the development and testing only of ADCNET Release 3 how does the Department intend to commission ADCNET Release 3?;
...
6. implementation of CR3049 STUBS emulation notwithstanding, what does the Department intend to do about obligations defined in the contract and subsidiary documentation which still depend on the delivery of STUBS?"
408 (vii) It was Roger Cooke's evidence in cross-examination (a) that from
July 1995 until March 1996 he never wrote to BHP-IT objecting
that GEC Marconi
could not proceed to complete the contract in the absence of STUBS; and (b)
that he did not record any objection
he had to the statement that the emulation
software was to be used for acceptance of the system under the Sub-Contract.
409 (viii) It was Mr Sharp's evidence (a) that from 1 November until 26
February, there was not a GEC Marconi document that conveyed
that its view was
that the non-supply of STUBS might constitute a default under the contract;
(b) that until 19 February the communications
he had been making with BHP-IT
had been aimed at reassuring BHP-IT that GEC Marconi intended to continue with
the fixed price contract
and would cooperate to make changes to the contractual
arrangements that might be necessary to make that occur.
410 The evidence of Mr Brent to which I need refer derives from his witness
statements, communications he made within BHP-IT in early
1996 and his oral
evidence. Mr Brent's state of mind - hence the reason he acted as he did - in
that period is in issue in the estoppel
claim.
411 The position taken by GEC Marconi is that so much of Mr Brent's evidence
was shown, by cross-examination, to be the product of
reconstruction that it
would be entirely unsafe to act merely upon Mr Brent's assertions about the
beliefs that he held. It is said,
in particular, that Mr Brent's evidence
about his state of mind prior to February 1996 concerning the use of the STUBS
emulator for
acceptance testing was nothing more than reconstruction.
412 The cross-examination of Mr Brent took place over seven days. I have
earlier foreshadowed my view of the unreliability of Mr
Brent's evidence. I
should indicate my reasons for that view given the nature of the attack GEC
Marconi has mounted upon his evidence.
Mr Brent had a marked tendency to
reconstruct from documents, his own recollection of events being quite
imperfect; he was susceptible
to suggestion to the point where what could have
occurred, or would have been in accordance with best practice, did occur; and
he
had quite understandable difficulties in giving precise temporal locations
to matters of which he had recollection. In consequence
I have not, in the
main, accepted his evidence unless it has documentary support.
413 In his fourth witness statement Mr Brent stated that he believed that the
following matters were agreed or understood by each
of BHP-IT, GEC Marconi and
the Commonwealth:
"(a) Agreement upon emulation removed the obligation upon the Commonwealth and BHP-IT to supply STUBS as CSI.
(b) The purpose of the STUBS emulator was to allow acceptance testing and completion of the ADCNET software under the Release 3 contract in the absence of actual STUBS hardware and software.
(c) References to STUBS in the acceptance test plan and the architecture design document would be removed and replaced with references to STUBS emulation."
He further stated that he acted on that belief in (1) signing CA23 and
accepting GEC Marconi's CR3049 offer and in participating in
correspondence
passing between the Commonwealth and GEC Marconi concerning the purpose of the
emulator and in particular Les Cook's
13 November 1995 letter and Mr Wishart's
22 November response; (2) participating in the correspondence leading to, and
then the
approval of, CA45 and CA30 (its Sub-Contract equivalent); (3)
participating in the CR3015 ATP amendment proposals; and (4) amending
the ADD
under CR3060.
414 In evidence that has bearing on the issue of possible detriment, Mr Brent
went on in his witness statement that, if GEC Marconi
were permitted to resile
from what he understood to be the common understanding of the parties
(including the Commonwealth) then
BHP-IT might be prejudiced in two respects.
The first was that it continued to perform its obligations under each of the
Head Contract
and the Sub-Contract and took no action in relation to the
non-supply of STUBS where, but for its belief as to the common understanding,
it would not have done so. Secondly, BHP-IT may be exposed to liability if any
change or variation of its obligations under the
Head Contract was not mirrored
by a corresponding change or variation in the Sub-Contract.
415 Mr Brent further indicated that he first heard of the suggestion that the
non-supply of STUBS might constitute a default at the
23 February 1996 meeting
with GEC Marconi. Of that meeting, he commented in his witness statement:
"I said that I rejected any suggestion of default. I said that there is correspondence from EASAMS on the file that directly contradicts it as it states that the emulator would allow acceptance testing to be completed. I asked the EASAMS representatives to reconsider their position."
416 Mr Brent provided his National Manager, Mr Dart, on 26 February 1996 with a resumé of the 23 February meeting with GEC Marconi. The resumé included the following:
". EASAMS will not put forward a firm price proposal for STUBS replacement because they perceive the risk to be too high;
. EASAMS perceive that the inability of DFAT to supply STUBS as per the contract may constitute a default on the part of DFAT and BHP-IT;
. EASAMS would like to explore the possibility of doing some or all of the work on a T&M basis and resetting/re negotiating the basis of the existing contract;
. EASAMS would like all outstanding commercial issues resolved, these were held in abeyance by DFAT pending the submission of the STUBS proposal;
...
. EASAMS have requested a conference between BHP IT, DFAT and EASAMS."
He went on to state:
"In my view we should arrange a conference between BHP IT and DFAT and BHP IT, DFAT and EASAMS in order to table outstanding issues and determine the way ahead for the project which is acceptable to all parties."
417 After receiving GEC Marconi's CR3057 proposal Mr Brent provided Mr Haddad with his review of it by letter on 1 April. In putting his view as to the position BHP-IT should take, he wrote:
"we must not allow the contract to be terminated. The STUBS breach has been remedied by the STUBS emulation change request and processed as a formal variation to the contract. Therefore there is no contractual problem."
418 The following day he had meetings, first, with representatives from GEC Marconi and, then, with GEC Marconi and the Commonwealth. Mr Brent, by letter of 3 April, provided Mr Haddad with a resumé of those meetings. He gave the following as part of his analysis of "the present position":
"STUBS unavailability - EASAMS were formally advised that STUBS would not be available and were requested to quote on the development of a STUBS emulator as a mitigation against delay in development, integration and formal acceptance of the system. EASAMS proposed the quotation, accepted the change request and the associated formal contract amendments citing schedule impact of 0.5 days and confirming by letter (Attachment D [Wishart's letter of 23 October 1995]) that the emulation would be sufficient for purposes of development, integration and formal acceptance of the system. Thus I believe EASAMS do not have a case on this issue."
419 I do not propose to summarise at all the several hundred pages of
cross-examination of Mr Brent that bears upon his state of mind
in the relevant
period. It would be unsafe to accept (a) his accounts of meetings in the
relevant period (save to the extent that
contemporary documentation supports
such accounts) and (b) his assertions that he had particular documents in mind
when making both
oral and written communications. In consequence I agree with
a deal of the criticism levelled by GEC Marconi at both his oral and
written
evidence. I equally do not consider that any significance should be attributed
to the manner in which he suggested, both
in contemporary correspondence and in
oral evidence, that legal effect was given to his belief that STUBS emulation
was to be used
for acceptance testing.
420 There are, though, two parts of his evidence to which I must refer as in
each instance I accept the substance of what he said.
The first of these
relates to his formation of the understanding he claims he had that there had
been a change to the contract which
meant it was to be completed with the
emulator rather than with STUBS.
421 The particular evidence on this matter I wish to note was given in response
to questions whether that was his understanding in
February 1996. Over ten
pages of the transcript Mr Brent narrated in a somewhat disconnected way the
various matters that informed
his understanding. His narrative, for
understandable reasons, worked backwards from February 1996, and focussed upon
what he described
on several occasions as "streams of activity" relating both
to "STUBS not being there" and to STUBS emulation, that were going on
during
the period from late 1994 to early 1996. These were, variously (i) the recent
demonstration of the emulator, and the payment
for it; (ii) the contract
variations that had been made, particular reference being made to the variation
to effect changes to the
ADD; (iii) Mr Wishart's 23 October 1995 letter making
the CR3049 offer and his 22 November 1995 letter responding to Les Cook's
comments on the emulator; (iv) DFAT's advice on 15 September 1995 that STUBS
was cancelled and the raising of CR3052 and later CR3057;
(v) correspondence
in December 1994 and June or July 1995 that was concerned with STUBS emulation
and, in the case of the latter,
with acceptance testing; and (vi) the change
request to develop the emulator.
422 Having indicated the above, Mr Brent concluded:
"So that's my understanding and my recollection of those sorts of issues surrounding STUBS and emulation. My view was always, as I recall, that emulation was for the purposes of acceptance testing. It wasn't for some interim progression. My recollection is that that concept arose at some later stage, I think, once the dispute was extant."
He was then asked by Mr Simpkins SC:
"Q. When was it, do you say, after 15 September 1995 that you first reached an understanding that the obligation to provide STUBS had gone and been replaced by an obligation to finish with an emulator?
A. I think my recollection of that was the letter that said - the letter from EASAMS that said emulation was for integration and acceptance of the system, the quotation and my acceptance of that quotation and subsequently confirmed in those contract variations that I talked about."
423 To anticipate my findings below I accept that Mr Brent's understanding
was as he described it. However, for the general reasons,
I gave above I do
not accept that any of the particular matters upon which he based his
understanding were actually present to his
mind at the 23 February 1996
meeting.
424 The second body of evidence relates to the state of the contractual
documentation in light of the variation that Mr Brent considered
had occurred.
The following two passages are set out in full - as they are in GEC Marconi's
written submissions - because of submissions
made on them. The cross-examiner
in each instance was Mr Simpkins SC and a day of hearing separated the two.
"THE WITNESS: ... My recollection of events surrounding the STUBS emulation were that the emulation would allow the acceptance of the system and, therefore, we were not dependent on the availability of STUBS any more. Subsequent to advice by the Department that STUBS would not be available, the fact that the emulator was there and would allow the system to be taken to acceptance was further confirmation to me that we could complete the job and that we were no longer dependent on the availability of STUBS to complete the job. That is my understanding and that is why I believe that the obligation to provide STUBS was removed.
Now, the changes that were necessary on that - there are still schedules in the Contract that still talk about STUBS and there are still references to STUBS in the Functional Requirement Specification, but the intent was to remove those. But the dispute came and from the moment of that dispute everything effectively stopped and the Acceptance Test plan was one example of that.
MR SIMPKINS: Q. Can I ask the question again. The question:
When you say it is your understanding are you reconstructing or are you telling His Honour that this is what you can actually remember thinking throughout the last few months in 1995 and the early part of 1996?
A. Certainly I think my thinking was consistent with that, your Honour.
Q. So no element of reconstruction at all?
A. Well, I'm just wondering. I don't know. I don't know whether there is an element of reconstruction but -
Q. You see - I don't mean to cut you off. Please finish.
A. Because this is the end of '95 beginning of '96?
Q. I'm asking you about the last few months in 1995 and early 1996.
A. Certainly the last few months of 1995 - my - sorry, your Honour, it's been a long week. The last few months of 1995 my - and February 1996, my state of mind was that an emulation was in fact being constructed and by February has been constructed to allow the system to be accepted. Also, by the end of 1995 I knew that STUBS was not available and I knew that the emulation was designed to take the place of STUBS for the purposes of acceptance only.
I knew that we processed contract variations in which the emulator was included. The contract variation I interpreted as a contract variation and amendment of the contract for replacement of STUBS with STUBS emulation. I was also conscious at the time that there were schedules in the contract that still were not amended and still reflected that STUBS in fact was the item of CSI to be delivered. My recollection is that those changes - that the intention, in my mind, was that those changes to the contract would occur once a replacement for STUBS was known. And, therefore, one could substitute the references in the contract schedules from STUBS to whatever the replacement was and action was in train to do that.
Similarly, as part of that changes to the FRS, we would have expected the replacement exercise, which was significant, to identify the necessary changes to the FRS. That is my state of mind, yes.
...
(2) Q. ... Mr Brent, you knew, didn't you, in the last quarter of 1995 and, indeed, in early 1996, that there were obligations relating to STUBS in the contract that remained unchanged?
A. Yes, there were CSI schedules in the contract that still included STUBS.
Q. You knew at the same time, didn't you, that there were requirements in relation to STUBS in the FRS that remained unchanged?
A. Because of my lack of detailed knowledge of the FRS and the understandings of the information, the amending information that was passing through me, I guess what I am saying is that I couldn't say one way or the other with all probability there would be requirements left within the FRS that related to STUBS, yes.
Q. Can I suggest to you that your belief at that time - that is, in the last quarter of 1995 and early 1996 - was that those obligations would be the subject of change?
A. Yes. Sorry, what was the time period of that?
Q. The last quarter of 1995 and early 1996.
A. After the announcement, yes, my belief was that they would be subject of change.
Q. You thought it most likely that that change would take place once the outcome of change request 3057 was known?
A. That - as I recall, that was my understanding at the time, yes. There would be no point in doing otherwise.
Q. It is a more accurate statement, is it not, of your state of mind in the last quarter of 1995 and early 1996 that you thought the obligations relating to STUBS would be removed rather than they had been removed?
A. I think I in fact - I think I in fact made that clarifying point in my statement."
(b) Applicable Principles
There has been no disagreement between the parties as to the principles to be
applied in resolving this matter, nor has any attempt
been made by GEC Marconi
to exploit such uncertainties as may still exist either in relation to the
permissible subject matter of
estoppel by convention: see the authorities
discussed in Government Employees Superannuation Board v Martin (1997)
19 WAR 224 at 242ff; or in the principles governing the award of remedy in
cases of equitable estoppel: see Giumelli v Giumelli [1999] HCA 10; (1999) 196 CLR
101. The disagreement between the parties is limited to whether the evidence
is sufficient to support a finding of
estoppel that would preclude GEC Marconi
from asserting that at no time was BHP-IT relieved of its obligation under the
Sub-Contract
to supply STUBS.
425 For present purposes it is sufficient for me to refer to separate
formulations of the principles governing equitable estoppel
and estoppel by
convention. They conveniently encapsulate the elements of each in brief
propositional form. I do recognise, though,
that there are differences to be
found in judicial statements relating to both species of estoppel, these being
occasioned in some
measure by whether it should now be accepted that there is
"a single overarching doctrine" of estoppel: cf Commonwealth of Australia v
Verwayen [1990] HCA 39; (1990) 170 CLR 394 at 411.
426 In relation to equitable estoppel, Brennan J described its requirements in
the following way in Waltons Stores (Interstate) Ltd v Maher [1988] HCA 7; (1988) 164
CLR 387 at 428-429:
"In my opinion, to establish an equitable estoppel, it is necessary for a plaintiff to prove that (1) the plaintiff assumed that a particular legal relationship then existed between the plaintiff and the defendant or expected that a particular legal relationship would exist between them and, in the latter case, that the defendant would not be free to withdraw from the expected legal relationship; (2) the defendant has induced the plaintiff to adopt that assumption or expectation; (3) the plaintiff acts or abstains from acting in reliance on the assumption or expectation; (4) the defendant knew or intended him to do so; (5) the plaintiff's action or inaction will occasion detriment if the assumption or expectation is not fulfilled; and (6) the defendant has failed to act to avoid that detriment whether by fulfilling the assumption or expectation or otherwise."
Of estoppel by convention, the New Zealand Court of Appeal said the following in National Westminster Finance NZ Ltd v National Bank of NZ Ltd [1996] 1 NZLR 548n at 550:
"The authorities show that for an estoppel by convention to arise the following points must be established by the party claiming the benefit of the estoppel (the proponent):
(1) The parties have proceeded on the basis of an underlying assumption of fact, law, or both, of sufficient certainty to be enforceable (the assumption).
(2) Each party has, to the knowledge of the other, expressly or by implication accepted the assumption as being true for the purposes of the transaction.
(3) Such acceptance was intended to affect their legal relations in the sense that it was intended to govern the legal position between them.
(4) The proponent was entitled to act and has, as the other party knew or intended, acted in reliance upon the assumption being regarded as true and binding.
(5) The proponent would suffer detriment if the other party were allowed to resile or depart from the assumption.
(6) In all the circumstances it would be unconscionable to allow the other party to resile or depart from the assumption."
I should add that I consider that this statement of the law sufficiently
identifies the law of this country as well, save that in
Australia the
assumption of law may well be limited to one relating to "private legal
rights": Elsea Holdings Ltd v Butts (1986) 6 NSWLR 175 at 188ff;
Riseda Nominees Pty Ltd v St Vincent's Hospital (Melbourne) Ltd [1998] 2
VR 70 at 77; Government Employees Superannuation Board v Martin, above.
This qualification is not of present moment in that, insofar as the
conventional understanding in question was one of law,
it related to private
legal rights.
427 In light of GEC Marconi's factual submissions it is appropriate to comment,
additionally, on the concept of "detriment" itself.
428 Whether one is speaking of estoppel at common law: see Thompson v
Palmer, above, at 547; in equity: see Legione v Hateley [1983] HCA 11; 152 CLR
406 at 437; or under a unified doctrine: see Walton Stores (Interstate)
Ltd v Maher, above, at 451ff; "detriment" or "material disadvantage" is an
indispensable requirement. The place and purpose of the requirement
in the law
of estoppel were identified by Dixon J in Thompson v Palmer, above, in
relation to estoppel in pais and were further elaborated by the same judge in
Grundt v Great Boulder Pty Gold Mines Ltd [1937] HCA 58; (1937) 59 CLR 641 at 674-675.
What His Honour there said, subject to one qualification I will notice, remains
"instructive as an indication
that the detriment against which the law protects
is that which flows from reliance upon the deserted assumption":
Commonwealth of Australia v Verwayen, above, at 415.
429 In Thompson v Palmer, his Honour said (at 547):
"The object of estoppel in pais is to prevent an unjust departure by one person from an assumption adopted by another as the basis of some act or omission which, unless the assumption be adhered to, would operate to that other's detriment. Whether a departure by a party from the assumption should be considered unjust and inadmissible depends on the part taken by him in occasioning its adoption by the other party."
Having illustrated the various ways in which a party might `take a part' in occasioning the adoption of an assumption, Dixon J continued:
"in each case, he is not bound to adhere to the assumption unless, as a result of adopting it as the basis of action or inaction, the other party will have placed himself in a position of material disadvantage if departure from the assumption be permitted."
430 In Grundt's case Dixon J enlarged on this. Speaking of the rules governing estoppel he said (at 674-675):
"One condition appears always to be indispensable. That other must have so acted or abstained from acting upon the footing of the state of affairs assumed that he would suffer a detriment if the opposite party were afterwards allowed to set up rights against him inconsistent with the assumption. In stating this essential condition, particularly where the estoppel flows from representation, it is often said simply that the party asserting the estoppel must have been induced to act to his detriment. Although substantially such a statement is correct and leads to no misunderstanding, it does not bring out clearly the basal purpose of the doctrine. That purpose is to avoid or prevent a detriment to the party asserting the estoppel by compelling the opposite party to adhere to the assumption upon which the former acted or abstained from acting. This means that the real detriment or harm from which the law seeks to give protection is that which would flow from the change of position if the assumption were deserted that led to it. So long as the assumption is adhered to, the party who altered his situation upon the faith of it cannot complain. His complaint is that when afterwards the other party makes a different state of affairs the basis of an assertion of right against him then, if it is allowed, his own original change of position will operate as a detriment. His action or inaction must be such that, if the assumption upon which he proceeded were shown to be wrong and an inconsistent state of affairs were accepted as the foundation of the rights and duties of himself and the opposite party, the consequence would be to make his original act or failure to act a source of prejudice."
431 The qualification I foreshadowed is this. While detriment of the
character to which Dixon J referred is necessary to establish
an estoppel - "it
would be strange to grant relief if such detriment were absent":
Verwayen's case, at 415-416 - it is not the case, at least in relation
to equitable estoppel, that if such detriment is there, the only way
in which
it will be averted by way of relief is by holding the party estopped to the
assumption he or she induced: ibid, 415-416;
Giumelli v Giumelli, above.
(c) Submissions and Conclusions: Representation/Understanding and
Reliance
432 To reflect GEC Marconi's submissions I have separated the submissions and
findings on representation/understanding and reliance,
and those on
detriment.
433 Put shortly BHP-IT's submissions are that if the conduct of the parties
leading up to the 1 November agreement did not result
in a binding Emulation
Variation Agreement, it was sufficient to found an estoppel. Insofar as the
estoppel is based on representations
made by GEC Marconi, reliance is placed on
the conduct and communications commencing with the early emulation discussions
in December
1994, through the 25 July 1995 and 10 August letters, the original
CR3049 and GEC Marconi's own schedule extension proposals, to
the 26 September
letter and then the 23 and 25 October letters. This evolving state of affairs
led GEC Marconi to make in October
what are described in BHP-IT's written
submissions as the October 1995 representations. These were:
"In October 1995, in the course of exchanges leading to the execution of CR3049, EASAMS represented to BHP-IT that, as BHP-IT was unable to supply STUBS (due to circumstances beyond its control), EASAMS would:
(1) build emulation software and use it in lieu of STUBS so as to complete development, integration and acceptance testing of the ADCNET software without STUBS;
(2) build the emulation software as part of an agreed change request, CR3049;
(3) no longer assert or rely upon a contractual right to the supply of STUBS as CSI under the Sub-Contract."
The common understanding, it is claimed, emerged from the same material but with the additional element of an already agreed CR3049. The common understanding was described in submissions in following fashion:
"In BHP-IT's submission, the Court ought to find that by early November 1995, each of EASAMS, BHP-IT and DFAT believed that through their correspondence and by CR3049 they had reached an understanding that the cut-down emulator would be used to achieve acceptance testing in the absence of STUBS. So too, they believed that by this understanding they had resolved the difficulties associated with the non-supply of STUBS as CSI and had thereby agreed a means of completing the contracts. This understanding also carried with it a broader appreciation by all the parties that, in these circumstances, BHP-IT and EASAMS would forgo existing rights to demand the supply of STUBS as CSI under the Head and Sub-Contracts. Indeed, from 13/14 September onwards, all communications between the parties proceeded on the basis that STUBS would not be supplied.
This common understanding was not in any way dependent on the parties identifying and agreeing upon, an alternative security gateway to replace STUBS. ... All parties signed CR3049 without conditions."
434 The subsequent conduct of the parties from Mr Wishart's 22 November
letter, through the change requests and contract amendments,
to the
demonstration and payment for the emulator, evidenced repetition of the
representations, confirmation of the common understanding
and the carrying into
effect (reliance upon) the assumption induced by the representation/common
assumption.
435 On the issue of reliance, BHP-IT contends I should find (i) that Mr Brent's
understanding of the use of the STUBS emulator was
as he stated it in evidence
and (ii) that the actions he subsequently took, were taken in reliance on that
understanding.
436 The Commonwealth's submission is that a like estoppel arose between BHP-IT
and itself, that estoppel properly being characterised
as an estoppel by
convention. Parallel material is relied upon by the Commonwealth to establish
both the understanding and its reliance
upon it.
437 For its part GEC Marconi contends, optimistically, that the representation
and conventional understanding were not sufficiently
clear and unambiguous: cf
Legione v Hately, above, at 436; Low v Bouverie [1891] 3 Ch 82,
at 106. Focussing particularly on the 23 October 1995 letter, the submission
goes on to indicate that the mere fact
that Mr Brent received this or other
communications does not prove that it had any relevant operative effect in his
mind. From this
GEC Marconi seeks to dismiss his oral and written evidence as
reconstruction, again focussing in particular on the effects the 23
October
letter were said to have on his mind in February 1996 and April 1996. I am
invited to hold that prior to 23 February 1996
Mr Brent had no occasion to
reflect upon whether the parties' obligations had been changed (informally or
otherwise) so as to require
acceptance testing with the emulator.
438 It is said, further, that insofar as the contractual documentation was
concerned, Mr Brent's state of mind was not that the obligations
in relation to
STUBS had been removed. His evidence was only of an expectation that the
obligations would be removed and that such
removal would take place once
agreement had been reached on a replacement for STUBS. Such a belief, if
accepted, does not support
the pleaded estoppel and is incapable of supporting
any estoppel. It does not remotely approach an understanding on Mr Brent's
part
that the Contract with GEC Marconi was `as good as amended'. He was
responsible for drafting or approving Contract Amendments which
specifically
discounted any intention to vary any contractual obligations: eg CA23. He was
aware at all times of the formal regime
for contract variation established not
only by the Contract, but by project documentation - in particular, the ADCNET
Project Configuration
Management Procedures. In short, if Mr Brent's evidence
is treated as acceptable evidence of his state of mind rather than
reconstruction,
the state of mind is insufficient.
439 Little point would be served by my re-analysing the communications and
conduct of the parties up to the time when the non-provision
of STUBS was
seriously raised as a default, for the purposes of indicating both the
representations they would reasonably convey
in the circumstances in which they
were made or occurred, and the common understandings they engendered or
reflected. I am entirely
satisfied that the representations and common
understanding alleged by BHP-IT have been made out on the evidence. I do not
consider
it necessary to add significantly to what I have already said in the
preceding sections on the "Emulation Variation Agreement" and
"Affirmation by
Election". The one general comment I would wish to make is that there was an
evolutionary process concerning STUBS
and emulation from early in the ADCNET
project. In consequence, more often than not the parties' communications and
conduct require
to be interpreted in light of what preceded them. This is
particularly so of the 23 October CR3049 offer letter.
440 GEC Marconi state the obvious in proposing that a person's receipt of a
letter does not necessarily prove it had operative effect
on that person's
mind. Nonetheless, as I have already indicated, I accept Mr Brent's evidence
of his state of mind concerning the
use of emulation for acceptance testing and
that his understanding was formed at the time GEC Marconi's CR3049 offer was
made and
accepted and that it was confirmed by later events and correspondence.
I do not consider his rambling account of the "streams of
activity" that
informed his understanding either as being contrived and artful or as being
mere reconstruction. The process he described
of the evolution, and then the
consolidation, of his understanding reflected a process that made what was
understood memorable even
if the particular component elements of that process
did not remain well remembered. Mr Brent did not have an invincible memory.
Few people do.
441 As I have indicated, I consider it would be unsafe to accept his assertions
that, when making both oral and written communications,
he had particular
documents in mind which confirmed his understanding at those times. I except
from this, necessarily, his letter
to Mr Haddad of 3 April which annexed Mr
Wishart's 23 October 1995 letter. It may well be, as GEC Marconi submitted,
that Mr Brent
only reacquainted himself with this letter specifically and in
detail prior to writing the 3 April letter. But that submission detracts
in no
way from the significance of the understanding he earlier arrived at and
continued to entertain. It merely reflects a fallible
memory as to its
composite of sources. His understanding up until the 23 February meeting did
not misrepresent either what previously
had been represented to him by GEC
Marconi, or what previously had been the parties common understanding.
442 I should add that the matter-of-fact character of the 26 February letter Mr
Brent wrote to Mr Dart - it purported to be nothing
other than a resumé
of a meeting with a consequential proposal for an all party conference - is not
of itself of any particular
assistance in revealing what at the time was Mr
Brent's understanding about STUBS emulation. I similarly do not consider that
such
contrast as there may be between Mr Brent's 1 April and 3 April letters to
Mr Haddad throws useful light on the matter other than
that both indicate that
Mr Brent considered there was no substance to GEC Marconi's complaint.
443 However, I do accept that Mr Goldsmith's memorandum to Mr Sharp of 1 March
cannot safely be treated as reflecting in some way
a response to a view
expressed by Mr Brent at the 23 February 1996 meeting on acceptance testing or
at some further meeting after
that date. It is more likely to relate to the
then emerging dispute about what the emulator was to be used for.
444 I am unable to accept at all GEC Marconi's submissions that related to Mr
Brent's view of the state of the contractual documentation
and to the removal
from it of STUBS-related obligations. My understanding when that evidence was
given was, and remains, that in
responding to Mr Simpkins SC's questions about
"obligations relating to STUBS in the contract that remained unchanged", Mr
Brent
was referring to obligations other than the obligation to supply
STUBS. It was those other obligations in the Schedules, the FRS, etc that were
later to be varied - as some
in fact were. I likewise do not consider that his
evidence in either of the extracts quoted earlier were reconstructions. Mr
Brent
did reconstruct on a significant number of occasions. These were not
instances of them, even though the first of the passages reveals
an
understandable glimmer of self-doubt about the matter.
445 I should add that I do not regard Mr Brent's awareness both of the formal
regime for contract variation established by the Sub-Contract
and by the
project documentation as having any real bearing on what his state of mind was
in relation to the obligation to supply
STUBS and the use of emulation for
acceptance testing. After the original CR3049 had been altered in its scope by
the 26 September
1995 letter and Les Cook had indicated the basis for the
proposed way forward, there ensued a disorder in the contractual documentation
for which all parties bear responsibility. I merely instance the metamorphosis
of one of the purposes of the original CR3049 from
a full surface emulation to
a "cut down" emulation without the issue of a new change request. I should
add, that whatever the precise
reason for Mr Brent's letter to Les Cook of 28
May 1996, his query concerning the subsistence of STUBS related obligations in
the
contract and subsidiary documentation reflects the disorder to which I have
referred.
446 I have already indicated that I am satisfied that GEC Marconi made the
representation to BHP-IT that was in substantially the
terms referred to by
BHP-IT in its written submissions (see above). Likewise I am satisfied that
the conventional understanding
of the parties from 1 November onwards into
early 1996 was in substance such as was described in BHP-IT's written
submissions.
447 I should make two further observations about these findings. First, I
earlier concluded that I would find the emulation agreement
to have been
entered into in any event even if I were incorrect in my finding as to the
Emulation Variation Agreement. A consequential
matter arises from this
concerning the representation and common understanding I have found. It is
this. Insofar as the representation/common
understanding related to STUBS
emulation and its purpose, it would be contractual in any event. BHP-IT would
then need only to rely
upon its estoppel defence insofar as it related to the
representation/common understanding concerning the abandonment of the
requirement
that STUBS be provided. The only reason I mention this is that the
nature of the common understanding as to that matter was probably
sufficient to
found an estoppel by convention at common law (assuming the satisfaction of all
other necessary requirements), in that
it related to the parties then
understanding of what were, and were to be, their private rights inter se in
relation to the provision,
etc, of STUBS: the authorities are conveniently
collected in the judgment of Ipp J in Government Employees Superannuation
Board v Martin, above at 242ff; see also National Westminster
Finance NZ Ltd v National Bank of NZ Ltd, above. However, I will in
what follows, treat the estoppel defence as if no part of the representation or
common understanding had
independent contractual effect.
448 The second observation relates to the nature of the representation and
common understanding respectively: ie was the representation
etc one of fact,
of law, of intention, etc. This has not been a matter of contention, the
parties seemingly sharing the view that
if a sufficiently clear and unambiguous
representation or conventional assumption is established that representation or
assumption
will be sufficient to found an estoppel, if not at common law, then
in equity provided the other elements sufficient to found an
estoppel in equity
can be made out. There is nothing in GEC Marconi's submissions to suggest to
the contrary, its principal attack
on BHP-IT's defence being that it suffered
no detriment in relying upon the representation or common understanding.
449 In this state of affairs I do not consider it necessary to analyse the
precise nature of either the representation or the conventional
understanding.
I will treat the matter as if it was founded entirely upon estoppel in equity.
Howsoever one characterises the component
elements of the representation or
common understanding as embodying assumptions of fact, of law, of intention,
etc, the actual and/or
assumed "state of affairs": cf Waltons Stores
(Interstate) Ltd v Maher, above, at 415-416; the representation made and
the common understanding held was a sufficient platform to found an estoppel
in
equity: Legione v Hateley (1983), above, at 435-437; Waltons Stores
(Interstate) Ltd v Maher, above at 406; 428-429; 458-459;
Commonwealth of Australia v Verwayen, above, at 413; Silovi
Pty Ltd v Barbaro (1988) 13 NSWLR 466 at 472; Austotel Pty Ltd v
Franklins Selfserve Pty Ltd (1989) 16 NSWLR 582 at 610; and see generally
Dal Pont and Chalmers, Equity and Trusts in Australia and New Zealand,
298-300 (2nd ed).
450 Turning briefly to reliance, it is in my view too clear for contest that
the understanding entertained by Mr Brent did in fact
provide the basis for
actions subsequently taken by BHP-IT in relation to its continuing performance
both of the Sub-Contract and
of the Head Contract. That understanding was a
consequence both of what was represented by GEC Marconi and of what was
commonly
understood at the time by the Commonwealth, BHP-IT and GEC Marconi as
providing the explanation for what was being, and was to be
done. It is
unnecessary to recount again the steps taken by BHP-IT from its making of its
own parallel CR3049 offer to the Commonwealth
in consequence of GEC Marconi's
CR3049 offer to it, down to the ultimately abortive CR3015.
451 The remaining question is whether, by so acting, BHP-IT placed itself in a
position of material disadvantage should GEC Marconi
be permitted to depart
from the understanding relied upon.
(d) Findings and Conclusions: Detriment
452 I have already referred to the two matters of detriment pleaded by BHP-IT
ie that (i) it did not require the Commonwealth to
provide STUBS under the Head
Contract; and (ii) it did not serve notices of breach on the Commonwealth
under the Head Contract until
11 April 1996 and did not negotiate a full-time
and materials variation to the Head Contract. I have also referred to the two
matters
of "prejudice" raised by Mr Brent in his witness statement ie that (a)
BHP-IT continued to perform both contracts and did not take
action in relation
to the non-supply of STUBS; and (b) it may be exposed to liability to the
Commonwealth if the contract changes
made in the Head Contract were not
mirrored in the Sub-Contract.
453 GEC Marconi's original written submissions dealt with all four of these
matters, contending in each instance that, when regard
is had to the facts,
they reveal no relevant detriment. The essence of GEC Marconi's contention is
that (i) there is not the slightest
basis for inferring that DFAT would have
provided STUBS if BHP-IT had sought it; (ii) Mr Brent did not identify
specific actions
BHP-IT would have taken instead of continuing to perform the
two contracts so that, at best, the alleged "lost opportunities" were
no more
than a matter of speculation; and (iii) notwithstanding the contract
variations, there were no material differences between
the two contracts so
that BHP-IT's position vis-à-vis the Commonwealth continued to mirror
that of GEC Marconi vis-à-vis
BHP-IT.
454 The additional matters of detriment raised by BHP-IT in its written
submissions (to which I earlier referred) were:
"(1) BHP-IT remains unpaid for the work it performed under the Release 3 contract in 1994, 1995 and 1996;
(2) BHP-IT incurred costs in labour and resources in resuming the project following EASAMS' departure on 10 December 1996;
(3) BHP-IT had to recommence the ADCNET project in December 1997 for the same price it had agreed in 1994 under the Head Contract, thereby being denied the opportunity to price this project at commercial prices appropriate for that time;
(4) EASAMS refused to pay BHP-IT's invoices for the labour BHP-IT provided to EASAMS under the Sub Contract;
(5) BHP-IT is exposed to damages claims from the Commonwealth."
As to the last of these, it is claimed that, even if the Commonwealth is
unsuccessful for the same reason that BHP-IT is unsuccessful
in its defences to
GEC Marconi's claim, BHP-IT will nonetheless incur costs in defending the claim
(as is now the case) so that detriment
has already been suffered.
455 In its reply submissions, GEC Marconi has contended that, properly
analysed, none of these matters constitutes relevant detriment
for estoppel
purposes. The objection that is common to the first four matters is that the
alleged detriment has not been shown to
be the consequence of any reliance by
BHP-IT on the representation or common understanding. As to the fifth matter,
it is said that
in deciding to defend the Commonwealth's claim, BHP-IT has not
altered its position to its detriment.
456 Before indicating my own view on the issue of detriment, I should indicate
that it has not been suggested by either party that,
if the grounds for an
estoppel have been established, the proper remedy should be other than that GEC
Marconi be prevented from acting
inconsistently with what it represented or
with the common understanding.
457 It is unquestionable that, had BHP-IT been informed of what GEC Marconi now
contends was the true state of affairs - ie the obligation
to supply STUBS
remained and that the emulator would not be used for acceptance testing -
BHP-IT would not have acted as it did.
As I will suggest below, such a
disclosure by GEC Marconi would have produced a state of affairs requiring a
quite different response
from that in fact made by BHP-IT and then the
Commonwealth on, and from, November 1995. The matter I would emphasise,
though, is
that BHP-IT's detriment case is not founded simply on inaction
(hence the loss of an opportunity) resulting from its relying on GEC
Marconi's
representation and the common understanding: on "lost opportunity" see
Mortgage Acceptance Nominees Ltd v Australian Thoroughbred Finance Pty Ltd
(1996) 69 SASR 302 at 308-309; Austral Standard Cables Pty Ltd v Walker
Nominees Pty Ltd (1992) 26 NSWLR 524 at 540; Dal Pont and Chambers, above,
309-310. Rather the matter is one in which, though action in reliance
was
taken by BHP-IT, different action would of necessity have been taken had the
true state of affairs been known.
458 It equally is not open to question on my findings that BHP-IT took
significant steps in the performance both of the Head Contract
and of the
Sub-Contract in reliance upon GEC Marconi's representation and on the common
understanding it shared with GEC Marconi
and the Commonwealth. That reliance
continued for around four months before BHP-IT became aware there was a serious
issue of default
being raised by GEC Marconi on account of the non-provision of
STUBS. The question is whether, because of such action, BHP-IT would
suffer
real detriment if the assumption it relied upon could later be falsified by GEC
Marconi? To anticipate matters, the answer
to this must be yes.
459 To appreciate the significance of BHP-IT's action in reliance, it is
important to understand what would have been the state of
affairs in late
October/early November 1995 had GEC Marconi then revealed that the obligation
to provide STUBS remained, that BHP-IT
remained in breach, and that the
emulation would not be used for acceptance testing. Its so doing would have
signalled a rejection
both of Les Cook's 26 September 1995 "way forward"
proposals and of the known purpose of CR3049. In this state of affairs
negotiations
to vary or to renegotiate the ADCNET contracts would have been
inevitable. One can only speculate as to what the probable or possible
outcomes of those negotiations might have been, although it is likely that they
would have been influenced somewhat by the cooperative
and long-standing
character of the relationship of the three parties and by GEC Marconi's
deteriorating financial position in relation
to the contract. What properly
can be inferred is that that state of affairs would have required action by
BHP-IT given its exposure
to GEC Marconi, and that BHP-IT would at that time
have made commercial judgments as to how best to conserve its interests given
the Commonwealth's failure to supply STUBS. This may have involved the
negotiation of a time and materials variation to the Head
Contract (as pleaded
in BHP-IT's defence). It may not.
460 What it would not have involved was BHP-IT committing itself to a course of
action founded upon the premise that STUBS was not
required to be provided and
that the emulation would be used for acceptance testing. I accept, in
consequence, the burden of Mr
Brent's statement in his fourth witness statement
that BHP-IT continued to perform its obligations under each of the Head
Contract
and the Sub-Contract and took no action in relation to the non-supply
of STUBS in circumstances where, but for the assumption on
which it relied, it
would not have done so.
461 Turning to actions that were taken in reliance upon the representation and
the common understanding, BHP-IT in fact did commit
itself to courses of action
that were predicated upon the continuing correctness of that representation and
common understanding.
It made representations and shared an understanding with
the Commonwealth that replicated the representations made by, and the
understanding
shared with, GEC Marconi. GEC Marconi was aware of this. The
Commonwealth now founds its estoppel defence against BHP-IT on the
representation so made etc. Equally it agreed with either the Commonwealth or
GEC Marconi a number of similarly premised change
requests the most significant
of which being CR3049 (but also CR3060 and, until aborted, CR3015). More
generally, it continued to
perform its functions and obligations under both the
Head Contract and the Sub-Contract.
462 If GEC Marconi was able to falsify the assumption on which BHP-IT relied,
several consequences would follow. First, it would
place BHP-IT in the
position of having made a representation to, and having shared an understanding
with, the Commonwealth for the
purposes of the Head Contract which on its own
evidence it believed represented the true state of affairs (it relied on their
accuracy
for the purposes of the Sub-Contract) and from which it could only
resile if the Commonwealth, for some reason, was unable to establish
or rely
upon its estoppel defence. Secondly, the agreed change requests and actions
taken in relation to them would be stripped
of their rationale and purpose if
they were to be severed from the assumption that informed them. Thirdly, these
actions as also
the continuing performance of the two contracts, occurred
across a four month period and were taken in relation to a contract with
GEC
Marconi under which BHP-IT could not reasonably have expected there to be any
continuing risk to it in consequence of the non-provision
of STUBS.
463 These various consequences are sufficient to make out the detriment
required to found BHP-IT's estoppel claim. It is, in my
view, unsurprising
that BHP-IT has not made lengthy submissions on the issue of detriment. The
essence of its case was put by Mr
Young QC as being that, from October/November
1995, BHP-IT suffered positive detriment in taking courses in that period in
reliance
on the assumption it entertained and negative detriment in failing to
take actions it might otherwise then have taken. The detriment
suffered,
moreover, was ongoing because BHP-IT adhered to its contract with the
Commonwealth and sustained losses in so doing. It
is unnecessary to consider
whether the actual losses relied upon in the submissions and with which GEC
Marconi takes objection can
individually be said to constitute detriment for
present purposes. What I would emphasise, though, is that GEC Marconi's
resiling
from its representations and the common understanding did not - and
could not - result in BHP-IT having in turn to resile from the
representation
it made to, and the common understanding it shared with, the Commonwealth, or
otherwise to take action adverse to
the Commonwealth. It had its own
commercial interests to consider. It changed its position by committing itself
to a course of
action under the Head Contract in November 1995. It was
entitled to adhere to that course notwithstanding GEC Marconi's resiling.
In
this sense, as Mr Young QC submitted, it properly can be said to have suffered
ongoing detriment.
464 I should acknowledge that not all of the matters to which I earlier
referred as constituting the detriment suffered by BHP-IT
were the subject of
explicit submission by it. GEC Marconi alone has addressed on the alleged
insufficiency of the "lost opportunity"
to take action referred by Mr Brent.
The Commonwealth alone has referred to its own estoppel defence and its effect
on BHP-IT. Nonetheless
I do not consider there is anything unfair or
impermissible in dealing with BHP-IT's detriment in the manner in which I have.
I have
done no more than enlarge upon what BHP-IT has submitted in general
terms.
465 The final question is whether it would be unfair and unconscionable for GEC
Marconi either to resile from what it represented
and from the common
understanding or to rely on the non-supply of STUBS as a breach of the
Sub-Contract. Having regard (a) to the
unambiguous and continuing
representations GEC Marconi made; (b) to its knowledge of BHP-IT's actions in
reliance both in relation
to it and to the Commonwealth; (c) to the length of
time in which it permitted those actions to occur before signalling the
"default
issue", and (d) to the character of the detriment suffered by BHP-IT,
the question admits of only one answer. It would be unconscionable
for GEC
Marconi so to resile. In consequence it is unable to rely on the non-provision
of STUBS as a breach of the Sub-Contract.
466 Assuming my conclusions both on variation and affirmation were incorrect,
BHP-IT would nonetheless be able to make out an estoppel
defence insofar as it
related to an alleged breach of contract occasioned by the non-provision of
STUBS.
4. WAIVER
467 The terminology of waiver has been used for a number of purposes and to a
number of different ends in this proceeding. Given
the conclusions I have
reached on "The Emulation Variation Agreement", "Election to Affirm" and
"Estoppel" I do not intend to deal
with the "waiver defences" in any detail or,
in some instances, at all.
468 I preface what I have to say with the following observation. There is no
need in this proceeding to analyse the independent
province occupied by the
doctrine of waiver that is distinct from the respective provinces of estoppel
and election: but see Commonwealth of Australia v Verwayen [1990] HCA 39; (1990) 170
CLR 394; H K Lücke, "Non Contractual Arrangements for the Modification of
Performance: Forbearance, Waiver and Equitable
Estoppel" (1991) 21 WALR 149;
Chitty on Contracts, vol 1, para 23-045 (28th ed); The
Law of Contract, §2.99 (1999); Farnsworth, Changing Your Mind,
Ch 16; Farnsworth, Contracts, §8.5 (3rd ed); Wilken
and Villiers, Waiver, Variation and Estoppel, Ch 4; cf Uniform
Commercial Code, §2-209(5). Sufficient has been said in these reasons
on estoppel and election so as to indicate that waiver has a very minor
possible role in the defence raised by BHP-IT.
469 BHP-IT has raised waiver in two ways. First, it is said that in the
circumstances, GEC Marconi waived its right to insist upon
the cl 45.1
writing requirement for the Emulation Variation Agreement. Given what I have
said on the efficacy of that agreement,
and on GEC Marconi being estopped in
any event from setting up the lack of writing, I do not consider it necessary
to deal with this
waiver claim.
470 Secondly, relying upon the same matters particularised to make out the
defences so far considered, BHP-IT has pleaded that GEC
Marconi waived or
dispensed with BHP-IT's obligation to deliver STUBS equipment and associated
software as CSI and substituted STUBS
emulation software therefore as an
alternative mode or manner of performance. This submission attempts to build
upon the observation
of Williams J in Phillips v Ellinson Brothers Pty Ltd [1941] HCA 35;
(1941) 65 CLR 221 at 244 that confirm the efficacy of an arrangement
relating to the mode of performance of an existing obligation
which is not
intended to substitute a new obligation for that obligation. Given my earlier
conclusions, I refrain from expressing
a view on this submission other than to
observe that it appears to be a particularly optimistic one.
471 In oral submissions DFAT propounded a quite distinct "waiver" defence that
presupposed there was no Emulation Variation Agreement.
It relates in an
important way to GEC Marconi's alleged inability to complete the contract
because it could not demonstrate all
of the "testable shalls" in the FRS in the
absence either of an agreed variation to the FRS or of waivers of the
particular requirements
that could not be demonstrated. And it has an
attractive simplicity.
472 Put shortly, the primary submission is that by refusing to supply STUBS,
the Commonwealth (hence BHP-IT) renounced its right
to insist upon GEC
Marconi's demonstration of the STUBS-dependent testable shalls of the FRS,
those requirements embodying specifications
made by the Commonwealth to suit
its own needs. Cast in relatively conventional waiver language, the submission
is that by its own
unilateral act (ie in refusing to supply STUBS) the
Commonwealth (and BHP-IT) renounced irrevocably the right to have the
STUBS-dependent
FRS requirements demonstrated.
473 As a variant on this, the Commonwealth has gone on to submit that, by
agreeing to build the emulator, GEC Marconi acted upon
the waiver because the
emulator could not demonstrate the STUBS dependent requirements.
474 As I earlier indicated, there is an obvious attraction in the primary
submission. In the usual case, it would prevent a contract
breaker from
exploiting to its own advantage and to the other party's prejudice the state of
affairs created by its breach. I say
in the usual case, because the curiosity
in this matter is that it is the party not in breach that is seeking to insist
on that state
of affairs.
475 While I cannot accept in its entirety the submission put, I agree with its
general thrust. I accept as a matter of principle
that, unless and until the
Commonwealth (and BHP-IT) have acted so as to cure the breach of contract
arising from the non-provision
of STUBS, then, questions of estoppel and
election apart, neither could insist upon GEC Marconi having to demonstrate the
STUBS dependent
requirements of the FRS.
476 I do not think it necessary to fit this conclusion within the doctrine of
unilateral waiver. For my own part I regard the preclusion
from so insisting
upon the FRS requirements as consequential contractual effects of the breach of
contract occasioned by the non-provision
of STUBS. Neither the Commonwealth
nor BHP-IT could reprobate, then approbate, the STUBS requirement.
477 A different route to the same result may well be found in the Mackay v
Dick (1881) 6 App Cas 251 duty to cooperate. It was well understood by the
parties to the ADCNET contracts that, in the absence of STUBS,
emulation could
be used for acceptance testing. In the state of affairs created by the breach
of contract, emulation could have
been so used. I merely indicate without
deciding that it well may have been the Commonwealth's and BHP-IT's obligation
in the circumstances
to perform the co-operative acts necessary to enable
acceptance testing (eg by modifying the FRS to remove STUBS dependent
requirements):
cf Electronic Industries Ltd v David Jones Ltd [1954] HCA 69; (1954) 91
CLR 288 at 298.
5. THE PROPER CONSTRUCTION AND THE APPLICABILITY OF SUB-CLAUSES 40.8 AND
40.9
478 If the failure to provide STUBS was a breach of contract, it was not, so
BHP-IT submits, such a breach as would have entitled
GEC Marconi to resort to
its right to terminate under cl 40.8 and 40.9. This submission raises two
issues. The first relates
to the proper construction of cl 40.8 and cl
40.9. The second is whether, in light of that construction, the non-provision
of STUBS was a breach of such character as enlivened GEC Marconi's right to
resort to those sub-clauses.
(a) The Issue of Interpretation
479 Both the Sub-Contract and the Head Contract made separate provision for
termination by the "Customer" and the "Contractor" respectively.
Because
submissions have been advanced in light of the alleged differences between the
separate regimes, it is necessary to set
out each in full.
480 In the Sub-Contract, termination by the Contractor (ie GEC Marconi) could
be effected under the following provisions:
"40.8 Where the Customer is in breach of an obligation under this Contract so that there is a failure by the Customer to perform this Contract, the Contractor may, by notice in writing to the Customer, specify that breach and where that breach is capable of being remedied require the Customer within 32 days of receiving such notice to remedy that breach or commence appropriate action to remedy that breach. Emphasis added
40.9 Where the Customer has not:
(a) remedied the breach referred to in subclause 40.8 within 32 days of receiving a notice (including because the breach was incapable of being remedied); or
(b) commenced appropriate action to remedy that breach within 32 days of receiving a notice and remedied the breach within a reasonable time after that period has elapsed;
the Contractor may, by notice in writing to the Customer, terminate this Contract without prejudice to any right of action or remedy which has accrued or which may accrue in favour of either Party."
481 The regime that applied to termination by the Customer (BHP-IT) was as follows:
"40.1 If the Contractor is in default under this Contract, the Customer may, without prejudice to any right of action or remedy which has accrued or may accrue in favour of either Party, by notice in writing to the Contractor, specify the relevant default and, where such default is capable of being remedied, require the Contractor within 28 days of such notice to remedy or commence appropriate action to remedy the default promptly.
40.2 For the purposes of this clause, the Contractor will be in default under this Contract where the Contractor fails to perform or observe any obligation or undertaking to be performed or observed on its part under this Contract. Emphasis added.
40.3 Where:
(a) the Contractor has received a notice under subclause 40.1 and fails to take appropriate action in response to that notice, or, having commenced appropriate action within 28 days, fails to continue and complete such action in a satisfactory manner and with all reasonable speed; or
(b) in circumstances where the default is not capable of being remedied, the Contractor has either not claimed an extension of time or other waiver or, if it has, the Customer has determined that an extension of time or waiver cannot be justified;
the Customer may by notice in writing require the Contractor to show cause, to the satisfaction of the Customer, why the whole of this Contract, or any part of it that is specified in the notice, should not be terminated by the Customer pursuant to this clause.
40.4 A notice to show cause under subclause 40.3 shall:
(a) set out the circumstances which entitle the Customer to issue the notice; and
(b) specify the time and date by which the Contractor must show cause, which time shall not be less than 6 clear days after the notice is given to the Contractor.
40.5 The Customer shall be entitled, by notice in writing to the Contractor, to immediately terminate this Contract in whole or in part, without prejudice to any right of action or remedy which has accrued or which may accrue in favour of either Party, where the Contractor:
(a) fails, within the time allowed, to show cause to the satisfaction of the Customer in accordance with a notice under subclause 40.3;
..."
482 Put in short form the controversy between the parties is whether, as
BHP-IT contends, the type of breach envisaged by cl 40.8
was one of a
repudiatory character, or, as GEC Marconi submits, it was simply any breach of
an obligation under the Sub-Contract.
The language of cl 40.8 that fuels
this controversy is to be found in the words "so that there is a failure by the
Customer
to perform this Contract". BHP-IT submits these words qualified the
earlier terms "[w]here the Customer is in breach of an obligation
under this
Contract" - and qualified them by requiring the breach to be of a particular
character, ie repudiatory. GEC Marconi submits
that the words were tautologous
in that they said no more than that a breach of any obligation under the
Sub-Contract would constitute
a "failure to perform this Contract".
483 Such support as each party seeks to derive from the separate regime
applying to termination by the Customer turns upon whether
the apparent
differences between the two were differences of substance (BHP-IT) or merely of
form and expression without self-evident
purpose (GEC Marconi). In particular
GEC Marconi submits that "the failure to perform" the contract in cl 40.8
expressed the
same concept as the failure "to perform any obligation or
undertaking" in cl 40.2.
484 The construction for which GEC Marconi contends is not one, it says, which
is unreasonable notwithstanding that any breach could
trigger cl 40.8 no
matter how insignificant or technical. The terms of the Sub-Contract were
such, in all cases of breach,
as to give BHP-IT the opportunity and time either
to remedy the breach or to propose a contract variation to vary or eliminate
the
obligation in question.
485 It is unnecessary here to refer in any detail to the canons of construction
to be applied in construing commercial contracts
other than to note the
following statements of principle which, for convenience, I respectfully
reproduce verbatim.
(1) "The language of a term is generally assigned its natural and ordinary meaning, read in the light of the contract as a whole but where it is ambiguous surrounding circumstances may be taken into account in assigning the presumed meaning. The surrounding circumstances include the matrix of mutually known facts, and the background, object, context and commercial purpose of the transaction, in the objective sense of what reasonable persons in the position of the parties would have had in mind: Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (at 347-352); Schenker & Co (Aust) Pty Ltd v Maplas Equipment and Services Pty Ltd ([1990] VR 834 at 844-850); Manufacturers' Mutual Insurance Ltd v Withers (1988) 5 ANZ Insurance Cases ¶60-853 at 75,343."
Spunwill Pty Ltd v BAB Pty Ltd, above, at 299, Santow J.
(2) "It is well established that the task of construction of a written instrument requires the whole of the instrument to be considered (Re Media Entertainment and Arts Alliance; Ex parte Hoyts Corporation Pty Ltd [1993] HCA 40; (1993) 178 CLR 379 at 386-7). A corollary is that there is a presumption against surplusage, although it is not a strong presumption in the light of modern drafting techniques involving standard form commercial documents (cf Lewison, The Interpretation of Contracts 2nd ed, 1997 §6.03)."
Big River Timbers Pty Ltd v Stewart (1999) 9 BPR 16,605 at 16,607, Mason P; see also Chitty on Contracts, vol 1, para 12-075 (28th ed).
(3) "[I]f detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business commonsense, it must be made to yield to business commonsense."
Antaios Compania Naviera SA v Salen Rederierna AB [1985] AC 191 at
201; see also Hide and Skin Trading Pty Ltd v Oceanic Meat Traders Ltd
(1990) 20 NSWLR 310 at 313-314; Minchillo v Ford Motor Company of
Australia Ltd [1995] 2 VR 594 at 609.
486 It is obvious that cl 40 of the Sub-Contract is not in some respects a
happily drafted clause. While contending that the
language of cl 40.8 is
clear and unambiguous, Mr Simpkins SC for GEC Marconi, nonetheless, has had to
concede that there are
differences in expression between the various
sub-clauses of cl 40 which I am invited to accept are without any
self-evident
purpose.
487 If one were to disregard the fact that one was dealing with a clause in a
termination provision, and if one read cl 40.8
in isolation both from the
rest of cl 40 and of the Sub-Contract more generally, the meaning proposed
by GEC Marconi might be
arguable - though I rather doubt that the "so that"
descriptive clause could be so easily disposed of even then. However, when
read
in its contractual setting, the language of cl 40.8 reveals an
intention which does not require disregard of the descriptive
clause and which
reflects what would be expected of reasonable persons in the position of the
parties.
488 In both cl 40.2 and cl 40.8 the contract purports to describe the
type or quality of "default" or "breach" to which
each respectively applies.
The differences in descriptive formulae used, and in particular the use of the
formula "fails to perform
... any obligation" in cl 40.2, necessitates the
conclusion that the cl 40.8 formula , in having abjured this language,
envisaged
a distinct and different state of affairs. I am satisfied for
textual reasons that the parties did not intend in the descriptive
clause
simply to reiterate in different words that a breach of an obligation was a
"failure to perform an obligation". It is not
surprising that they did not.
489 Clause 5 of the Sub-Contract (which is entitled "Customer's Obligations")
contains provisions such as the following:
"5.1 The Customer shall take all reasonable measures to maintain the processing environment as constituted by the elements of the CSI.
...
5.3 The Customer shall supply the CSI in accordance with clause 7 and shall perform its obligations specified in the Project Plan and the Implementation Plan pursuant to subclause 10.1.
5.4 The Customer shall manage the project risks which are identified as the Customer's responsibility under this Contract."
490 Even if one were to accept, as GEC Marconi submits, the practical
unlikelihood that the contract would be terminated for breach
of such generally
stated obligations as those in cl 5.1 and cl 5.4, cl 5.3 is of a
different order entirely. The
obligations imposed on the "Customer" that were
encompassed by cl 7 and cl 10 were enumerated in quite specific and
detailed
terms in Schedules 6, 7 and 8 of the Sub-Contract. It is, in my view,
inconceivable that the parties would have intended that any
breach of any one
of this multitude of obligations would permit resort to cl 40.8.
491 The language used in cl 40.8 does not require me "to attribute to the
parties an improbable and unbusinesslike intention":
Mitsui Construction Co
Ltd v Attorney-General of Hong Kong (1986) 33 BLR 1 at 14. It is
reasonably capable of an interpretation which attributes to the parties an
intention to provide for
termination for breach by the Customer, on a sensible
and businesslike basis: ibid.
492 I am satisfied, having regard to the type and terms of contract in
question, that a reasonable interpretation which is open on
the words of the
Sub-Contract: J Kitchen & Sons Pty Ltd v Stewart's Cash and Carry
Stores [1942] HCA 18; (1942) 66 CLR 116 at 124; and see Carter, "Termination Clauses"
(1990) 3 JCL 90 at 99-100; and which accords with "business commonsense":
Antaios Compania Naviera SA, above, at 201; is one that broadly equates
a breach that amounts to a failure to perform the contract with a breach
(other than an anticipatory breach) that would justify termination at common
law. I except anticipatory breaches as the language
of cl 40.8 and
cl 40.9 seems to envisage breach of an obligation the time for performance
of which has arrived: cf Moschi v Lep Air Services Ltd [1973] AC 331 at
356. Qualifiedly then, I agree with BHP-IT's submissions.
493 I would add in support of the view I take that one historically important,
and judicially sanctioned, category of circumstances
which would permit
discharge of a contract for breach was that formulated by Sir William Anson.
It was for "failure of performance":
see eg Anson, Law of Contract, 289
(8th ed); Heyman v Darwins, Ltd [1942] AC 356, at 397;
Anson's Law of Contract, 539ff (27th ed); and see generally
Chitty on Contracts, vol 1, paras 25,016 and 25,033ff (28th
ed). Modern understanding of this category encompasses principally breaches of
essential terms and of terms going to the root of
the contract: see generally,
Chitty, above, at para 25,033ff. For present purposes, I am prepared to
accept that the parties would as well have intended that cl 40.8
extends
to an actual breach of an obligation in circumstances evincing an intention not
to be bound by the terms of the contract:
for the difference at common law
between repudiation and failure of performance, see Byrnes v Jokona Pty Ltd
[2002] FCA 41 at para [70]- [80].
(b) The Applicability of Cl 40.8 and Cl 40.9
494 On the assumption that there was a subsisting breach arising from the
failure to provide STUBS, the short question is whether
there was, in
consequence, a failure to perform the contract for cl 40.8 purposes.
Though this, formally, is the central issue
in GEC Marconi's case, it has not
been the subject of particularly detailed submissions by the parties (the
Commonwealth apart).
GEC Marconi's submissions on this matter - as distinct
from the interpretation of cl 40.8 - are notably sparse and are baldly
assertive.
495 Much of the evidence that has some possible bearing on the question has
been, or will be narrated, in other parts of these reasons.
I do not intend to
collect and repeat here that material. I have already described the purpose
and evolution of the ADCNET project;
the objective of replacing the IBM
message switch; the role of boundary security in the project based on the use
of sealers and
gateways; DFAT's adoption of STUBS in 1993 as the preferred
choice for boundary security; the execution of the ADCNET contracts
in 1994,
these having been prepared on the known basis that the Commonwealth would
supply and be responsible for the functionality
of STUBS; and that BHP-IT's
(hence GEC Marconi's) responsibility would be to integrate the STUBS devices
with the Release 3 software.
496 I will later deal with the knowledge BHP-IT and GEC Marconi had of the
Commonwealth having no contract with AWADI for the supply
of STUBS and their
respective appreciations of the likelihood or otherwise of STUBS being
provided: see "BHP-IT's Second Cross-claim".
497 Reference has been made to other breaches relating to the provision of
STUBS (ie specifications and software) and to the stances
taken in relation
thereto; to the various proposals made for emulation including for acceptance
testing; to GEC Marconi's proposals
made prior to the cancellation of STUBS
being announced to complete the contract without STUBS; and to the passage of
time from
that announcement until the first Notice of Breach was served.
498 There are only two additional factual matters to which I should refer. The
first is that the integration of STUBS into the ADCNET
software constituted
only a very small part of the work to be performed by GEC Marconi under the
Sub-Contract. Most of the Developed
Software could be built and tested quite
independently of the development of the STUBS interfaces. It is GEC Marconi's
own evidence
that of the over 2000 CSU's that made up the source code, only 4
CSU's could not be developed because of the absence of STUBS.
499 Secondly, there is documentary evidence which I accept that GEC Marconi was
aware that the ADCNET system could be used by DFAT
without STUBS. As Mr
Goldsmith commented to Mr Sharp in a memo of 1 March 1996: "It is their
risk".
500 In Part I of these reasons I have set out relevant provisions of the
Sub-Contract, the Schedules, and contractual documentation
which related to the
provision of STUBS, GEC Marconi's obligations and to acceptance testing. I
will not repeat these here.
501 Having referred to the state of GEC Marconi's submissions on this matter, I
intend merely to express my own conclusions without
detailed reference to the
evidence or to the helpful submissions of BHP-IT and the Commonwealth.
502 First, I am not satisfied that the obligation to provide STUBS as CSI under
the contract was an essential term (or condition)
of the Sub-Contract. I
accept (a) that a continuing objective of the ADCNET project was to replace the
IBM message switch; (b)
that, from early in the project, the boundary security
adopted for the system was to be based on trusted sealers and gateways; and
(c) that in 1993 STUBS was selected for that boundary security purpose and it
was to be supplied by the Commonwealth. Nonetheless
it was well-understood by
all parties at the time the ADCNET contracts were entered into that GEC
Marconi's contractual responsibility
in relation to boundary security was to
deliver software that would interface with STUBS and would be compliant with
the STUBS SIS.
The risk relating to the functionality of boundary security lay
with the Commonwealth: it selected and supplied the device to be
used. GEC
Marconi's risk stopped at the interface.
503 The Head Contract and the Sub-Contract both reflected this understanding.
GEC Marconi's central obligation was to build and deliver
the Developed
Software. That software had to be integrated with STUBS and with other CSI.
The integration with STUBS was known to
be, and was, only a minor part of the
software development work (EASAMS had developed the FRS). The Sub-Contract
itself contemplated
the possibility that there could be changes to the CSI (a
matter earlier discussed in relation to CR3060). It also contemplated
that, if
operational equipment was not available, a test harness would be used in
acceptance testing. Although the method for interface
acceptance testing had
to be agreed, the contract thus contemplated that the "testable shalls" of the
FRS could be demonstrated using
a test harness even though that harness did not
provide the substantive functionality of operating equipment.
504 I accept both that changes to the CSI and the methods of use of an emulator
in acceptance testing needed to be the subject of
agreement. My reason for
emphasising these matters is that they assist in confirming what is otherwise
apparent both from the contractual
risk allocation concerning boundary security
and from the minor dimensions of the work to be undertaken by GEC Marconi in
relation
to STUBS. This is that the STUBS related obligations were not
essential to the Sub-Contract. As both BHP-IT and the Commonwealth
submit, the
Sub-Contract envisaged acceptance testing and delivery of the Developed
Software with or without STUBS. I will refer
below to GEC Marconi's submission
that the Sub-Contract was unable to be completed without STUBS because of
requirements in the FRS.
505 In Ankar Pty Ltd v National Westminster Finance (Australia) Ltd [1987] HCA 15;
(1987) 162 CLR 549 at 556-557, it was stated that:
"In deciding whether a promise has the status and effect of a condition, courts are not too ready to construe a term as a condition and, at least where other considerations are finely balanced, will hold that a term is of such a kind that breach of it does not give rise to an automatic right to rescind. This approach is explained by a preference for a construction that will encourage performance rather than avoidance of contractual obligations."
This is not a case where, in my view, the considerations are "finely
balanced". But if it were, it would warrant the application
of the
constructional preference referred to. With an obligation having the relative
size and significance to the ADCNET contract
that the STUBS obligation had,
this is a clear case in which preference should be given for "a construction
that will encourage performance".
506 The STUBS obligation was not an essential term of the Sub-Contract.
Neither did the failure to supply STUBS go to the root of
the contract. It did
not impose burdens on GEC Marconi, or deprive it of benefits of such
seriousness or significance as to so change
the character of the Sub-Contract
that it can be said to be a commercially different bargain: see Byrnes v
Jokona Pty Ltd, above, [75]-[80]. As I will indicate later in these
reasons, GEC Marconi attempted to use the non-provision of STUBS so as to
procure
for its own benefit a commercially different bargain.
507 I need not enlarge upon this conclusion, other than to say that, apart from
the delays to be endured prior to the announcement
of STUBS cancellation (and
these were to be the subject of delay claims) the non-provision of STUBS did
not have a particularly significant
adverse effect upon GEC Marconi. As GEC
Marconi's Systems Architect wrote in a report of 15 July 1996:
"Non-delivery of the STUBS device and use of the STUBS emulator does have an impact on the project. It will cause us to rework a number of documents and make a number of code changes. Compared to the other problems on the project however, it is fairly minor."
508 The failure to provide STUBS was, as I indicated earlier in these
reasons, a "once-and-for-all" breach. BHP-IT's conduct in the
matter could not
warrant a finding of repudiation. It did not evince an intention that it was
no longer to be bound by the contract
or that it would only fulfil the contract
in a manner substantially inconsistent with its obligations and not in any
other way:
Progressive Mailing House Pty Ltd v Tabali Pty Ltd [1985] HCA 14; (1985)
157 CLR 17 at 33, 40; Honner v Ashton (1979) 1 BPR 9478. The
Commonwealth, hence BHP-IT, made plain that it would not supply STUBS. But
otherwise it sought and promoted
the completion of the contract. There was
nothing repudiatory in its, or BHP-IT's, actions. If repudiation of a contract
is "a
serious matter, not to be lightly found or inferred": Ross T Smyth
& Co Ltd v TD Bailey & Son [1940] 3 All ER 60 at 71; no basis at
all exists here for even contemplating such a finding.
509 As I earlier indicated, GEC Marconi has submitted that the ADCNET contract
could not be completed because there were "testable
shalls" in the FRS that
could not be demonstrated in the absence of STUBS and no amendments to, or
waivers of, these requirements
were made. I have dealt with this matter in a
number of contexts already. I do not intend to repeat what I have said other
than
to note yet again that I reject the submission.
510 BHP-IT has separately submitted by way of defence that it had in any event
remedied its breach before February 1996. It is unnecessary
to consider this
submission.
6. NON-PAYMENT FOR MILESTONE 4000
511 The second ground upon which GEC Marconi relied to terminate the
Sub-Contract was BHP-IT's failure to pay the invoice for Milestone
4000. That
milestone related to the Test Readiness Review. By way of defence, BHP-IT
claims that its refusal to pay was justified
in the circumstances and that in
any event it did not evince any intention to no longer be bound by the
provisions of the Sub-Contract.
512 The issues raised here are of two types. The first are ones of
construction. To set the scene for them it will be necessary
to make
reasonably extensive reference both to the Sub-Contract and to a deal of
subordinate documentation. The second type of issue
is essentially factual in
character. Again it will be necessary to make lengthy reference to the
evidence and particularly to technical
evidence. I will deal with the two
separately.
513 I should say that, for reasons I later give: see Part III: The
Repudiation Claim; there is a distinct air of unreality that
envelops the
claims made in this section. I would merely note here what is clear
beyond contention. When GEC Marconi rendered its invoice for Milestone 4000 it
was, as its
senior representatives recognised, engaged in a ploy to increase
commercial pressure on BHP-IT and DFAT. Mr Sharp, who participated
in the
decision to render the invoice, had no belief that all of the money for
Milestone 4000 was due.
(1) The Construction Issues
(a) Relevant Sub-Contract Provisions
514 Clause 10 of the Sub-Contract obliged the parties to perform their
obligations in accordance (inter alia) with the Implementation
Plan of Schedule
8. Clause 1 of that Plan, insofar as presently relevant, was in the following
form:
Deliverable |
Deliverable |
Customer's |
Date |
Contract |
Payment |
1000 |
Project Mobilisation |
Nil |
Not |
Contract |
1 250 000 |
2000 |
Preliminary
Design |
|
08/11/94 |
subject
to |
1 250 000 |
3000 |
Critical
Design Review |
|
31/03/95 |
subject
to |
1 375 000 |
4000 |
Test
Readiness Review |
|
06/09/95 |
subject
to |
1 250 000 |
5000 |
Canberra
system |
Acceptance |
15/01/96 |
15/01/96 |
500 000 |
"9F.1 ADMINISTRATION
9F.1.1 Where the Customer is required to review Documentation prepared by the Contractor for the purposes of commenting (reviewing), approving or accepting that Documentation, the Contractor shall deliver the Documentation in hard copy to the Customer's nominated Lodgement Officer. The Customer's Lodgement Officer shall be responsible to formally receive the Documentation and, for its distribution to the appropriate officers of the Customer.
9F.1.2 The Customer shall return the Documentation including any associated comments to the Contractor's Lodgement Officer who shall be responsible for formally receiving the Documentation and providing the Customer's comments to the Contractor's appropriate officer(s).
9F.2 PROCEDURE
9F.2.1 During the period of preparation of deliverable Documentation, the Contractor shall keep the Customer and the Commonwealth informed at all stages while the Documentation is being prepared so that the Customer's and Commonwealth's personnel who will be assessing the Documentation for the purposes of subclause 9F.2.2 will have a reasonable knowledge of the content of the Documentation by the time the Documentation is delivered to the Customer for approval, acceptance or otherwise.
9F.2.2 If the Customer has any objection to the Documentation provided by the Contractor it shall notify the Contractor promptly of any alterations it reasonably requires to be made to the same. The Contractor shall not unreasonably refuse to amend the Documentation to take account of the Customer's reasonable requirements. Where the Documentation complies with the Customer's Functional Specifications, amendments requested by the Customer may constitute a variation to the Contract."
517 There is a dispute between the parties as to when TRR was to occur, this dispute bearing as well on the proper meaning to be ascribed to the term "review" in the Table above. The provision of the Sub-Contract that is said to bear directly on this matter was cl 55. It provided:
"The Contractor shall supply to the Customer Services and the Developed Software which comply with the standards specified in Schedule 3."
Schedule 3 in turn stated that:
"The Contractor will comply with the standards as set out in the Software Development Plan (reference number 1401.01 Version 1) and any subsidiary documents to that plan."
A subsidiary document of the SDP is said by BHP-IT to have been the IPD
Standard for Inspections, Reviews and Audits. It is necessary
to refer both to
that document and to the SDP, each of which was prepared by GEC Marconi.
518 First, the SDP. The "Document Overview" clause (cl 1.3) described the
purpose of the SDP as being to define the development
process to be applied to
Phase II of the ADCNET project by the IPD team. That process was to be known
as "Best Commercial Practice",
a description which was elaborated upon in
Appendix C to the SDP. In relation to "Formal Reviews in the Development
Process", the
Appendix described TRR as being mandatory and to be conducted at
the end of the "Integration Testing Phase". A table in the SDP,
which is
reproduced as Schedule 3 to these reasons, identified when that phase would
end. Clause 3.8 of the SDP provided:
"Formal external reviews will be conducted during the development process in accordance with IPD Standard for Reviews and Audits ... . The planned formal external reviews are:
...
iii. Test Readiness Review (TRR) - The TRR shall be held at the end of the Integration Testing phase, and shall be used to ensure that the system is ready for Acceptance Test."
519 The IPD Standard document described the purposes and processes of reviews (External and Internal) in some detail. It stated that the objective of the external review process was "to allow the customer to formally evaluate products created during a development phase that have been deemed as deliverable". In commenting generally on the review process itself, the document indicated that reviews should not be considered as a single point in time "as preparation starts weeks before and the review is not finished until all action items are satisfactorily completed": cl 3.5. The External Review process accommodated two stages, the first relating to the review meeting, the second, the follow-up. The former stage involved a "page-by-page walk-through" of the documents to be reviewed with "agreed actions" arising there from being noted on the "Review Action Sheet". At the end of this process (cl 7.6.2):
". The Reviewers then determine the review result and the Review Chairperson records this result on the Review Result Record. The review result can be either a `Passed and Complete' (no follow-up action required), a `Passed with follow-up action required' (as specified in the Review Action Sheet), or a `Re-submit' (the product requires sufficient further work to merit another review process). For the last two a date should be recorded indicating when it is estimated follow-up action should be complete by, or the date for a rescheduled review respectively.
...
. On completion of the review meeting the Review Chairperson is to brief the Customer on the review outcome through a formal letter. The Review Chairperson is then to organise the review follow-up, if the review was not assessed as `Passed and Complete'."
520 The purpose of the follow-up process was to complete satisfactorily all agreed review action items that had been marked in the Review Action Sheet. A series of steps was ordained, the last of which being described as follows (cl 7.6.3):
". When all action items are complete the Review Chairperson signs the Review Action Sheet and Product Issue Report as complete and files this on the products Development File. He then informs the Customer that the review process has been successfully completed."
Clause 7.7 went on to provide "Exit Criteria" for the completion of an
External Review which culminated in a Review Report being issued
to the
customer. Annexed to the IPD Standard document were the standard forms of the
various documents (Review Action Sheet, etc)
used in the review process.
521 The Sub-Contract made express provision for the making of payment for
milestones. Clause 16, insofar as presently relevant,
provided:
"16.1 The Customer shall make progress payments in accordance with the milestone payment schedule in Schedule 8 upon the Delegate being satisfied on reasonable grounds that the supply of the Documentation, Developed Software or integration of that part of the System referable to that milestone payment meets the requirements of this Contract.
...
16.3 When a payment is due under Schedule 8 the Contractor shall provide a correctly rendered invoice to the Delegate.
16.4 The Customer shall make payment within 21 Normal Working Days after receipt of a correctly rendered invoice.
16.5 An invoice is correctly rendered if:
(a) the amount claimed in the invoice is due for payment."
522 Two issues arose out of this provision. The first was whether the
amount claimed by GEC Marconi for Milestone 4000 was due;
the second, assuming
it was, was whether Mr Brent was justified in not making the payment for
discretionary reasons envisaged in
cl 16.1.
523 The final contractual matter to be referred to relates to the character of
GEC Marconi's obligations relating to the SDP. In
addition to cl 55
referred to above, cl 10.1 of the Sub-Contract required the parties to
perform their obligations "in
accordance with the Project Plan ... [Schedule 7]
and the Implementation Plan [Schedule 8]". Clause 2.2 of Schedule 7 obliged
GEC
Marconi, in performing its Project Management function, to "[ensure] that
the provisions described in the Software Development Plan
are implemented".
(b) Additional Factual Material
524 I refer to the following matters as they have been relied upon in BHP-IT's
and the Commonwealth's submissions.
525 (1) Some number of versions of the SDP were prepared by GEC Marconi during
the period 1994-1996. The operative version for present
purposes was Version
3.3 and the SDP references in the preceding section were to that version. An
earlier version of the SDP (Version
3.1) provided for TRR to be held just prior
to integration testing (ie at the end of CSC Integration testing) and not after
it as
was the case with Version 3.3.
526 (2) In cross-examination Roger Cooke accepted that the purpose of TRR was
to check that everything was in place for the system
to be acceptance tested,
and that the practice in his 30 year experience was that TRR occurred
immediately prior to (Version 3.1)
or immediately after (Version 3.3)
integration testing. It is Mr Harris' evidence (he was responsible for
updating the SDP) that
he derived the Version 3.3 requirements for the TRR from
a "Government Standards" document for software development (DOD-STD-2167A)
that
was a referenced document in both Version 3.1 and 3.3.
527 (3) On 5 December 1995 Les Cook wrote a letter to Mr Brent concerning TRR.
It stated in part:
"The relevant description from the SDP is that the `Test Readiness Review shall be held at the end of the integration testing phase and shall be used to ensure that the system is ready for Acceptance Testing'. The Department considers that this means that completion of integration testing is a prerequisite for TRR. With the current development plan, this means that TRR should follow successful integration of build 5."
528 (4) The positions taken by GEC Marconi and BHP-IT in relation to TRR was evidenced in the following two letters. The first, from GEC Marconi, reflected the fact that not even Build 2 had by then completed the integration test phase. It proposed replacing Milestone 4000 with three separate milestones and apportioning the contracted for payment between these. It prefaced this proposal with the following:
"There is a conflict in the contract baseline documentation regarding the conduct of the Test Readiness Review. The contractual deliverable's (sic) in the document which takes precedence, namely the contract, does not provide deliverable's (sic) to enable the TRR as the SDP requires until the final milestone."
This proposal was rejected by Les Cook. BHP-IT's position on TRR was reflected in the response made by letter of 21 March 1996 to the invoice sent to it by GEC Marconi of 12 March 1996. Though of some length, this letter will be quoted in full to avoid the need for later repetition.
"I have reviewed the contractual position on the issue of the Test Readiness Review (TRR) with the following results:
* the contract (Agreement No ADC/001) between BHP-IT and EASAMS is comprised of the document itself, the schedules and documents which include the Functional Requirements Specification (FRS), the Architecture Description document (ADD) and the Software Development Plan (SDP);
* Clause 2.1 of the contract defines the order of precedence;
* Clause 55 of the contract states "The contractor shall supply to the customer services and the Developed Software which comply with the standards specified in Schedule 3 of the contract;
* Schedule 3 of the contract states that the Contractor will comply with the standards set out in the Software Development Plan;
* Schedule 7 of the contract is the project plan. Under the "Contractors scope of work" it states "WP1000 Project Management (ii) ensuring that the provisions describes in the Software Development Plan are implemented";
* Section 4.2.3 of the Software Development Plan states that DOD-STD-2167A Defence System Software Development shall be the basic design standard used;
* Section 4.2 Software process of the Software Development Plan refers to Figure 4.1;
* Figure 4.1 of the Software Development Plan Best Commercial Software Development Process defines the position of the TRR in the Software Development process after completion of coding and integration testing of all CSU's and all CSC's and is predicated on the availability of a favourable integration test report. This is the purpose of TRR, to ensure that the system is ready for final acceptance;
* This is confirmed by Section 3.8 Formal External Reviews item (iv) which states inter alia that "the TRR ... shall be held at the end of the appropriate Integration Testing phase, and shall be used to ensure that the system is ready for Acceptance Test;
* Schedule 8 of the contract defines the payment milestones of which TRR is one;
* Schedule 9 of the contract paragraph 2.2.1 states inter alia that "The qualification of the Developed Software shall be based on the adherence of the software development to the testing and quality provisions as defined in the Software Development Plan". The TRR is a testing and quality provision of the SDP.
Thus there is no conflict between the contract and the Software Development Plan. The TRR as defined by the contract and the Software Development Plan requires that:
* all test documentation be complete and approved;
* all software development complete;
* all integration testing be satisfactorily complete;
* appropriate integration test reports be provided to support the contention that the system is ready for acceptance testing.
As at the date of this letter none of the criteria defined above have been satisfied. The TRR is now more than six months late.
Accordingly, I cannot authorise the milestone payment of $1,250,000, billed under your invoice 14248, dated 12 March 1996, until the requirements of the contract and the Software Development Plan are met."
(c) Submissions and Conclusions
529 By way of prelude to what follows, I would reiterate that the Table in
Schedule 8 required that two documents - the Test Descriptions
(Procedures) and
the Acceptance Test Data - be "approved" and that another two - the Software
Developed System Design Documents ("the
SDSDD") and the Test and Acceptance
System Design Document ("the TASDD") - be the subject of review. I would also
note that the
first two documents were in fact combined into one document
entitled the Acceptance Test Descriptions ("the ATD").
530 There are three issues of construction seemingly raised in the parties'
submissions. I say "seemingly" as the first to which
I refer seems only to
have been put directly in GEC Marconi's reply to the Commonwealth's
submissions. These issues are:
(i) Subject to the Delegate being satisfied on reasonable grounds that the
document submitted for a milestone met the requirements
of the Sub-Contract,
was the cl 16.1 payment obligation triggered by the mere delivery of those
documents for "approval" or
"review"? Or was "approval" or "review" a
precondition of payment?
(ii) What was required for there to be "approval" or "review"?
(iii) Was the TRR referred to in Schedule 8 for Payment Plan purposes, the same
TRR as referred to in the SDP for software development
purposes?
(i) The cl 16.1 payment obligation
531 GEC Marconi's submission is, essentially, that the "Customer
Responsibility" column of Schedule 8 does not stipulate a precondition
for
payment. Clause 16.1 speaks for itself. These submissions imply (a) that cl
1.2 and cl 1.3 of Schedule 8, in their references
to deliverables "subject to
review" and deliverables "subject to approval", have no significance in
relation to the Payment Plan
ordained by Schedule 8; and (b) that the
reference in cl 16.1 to the "supply of the Documentation ... [meeting] the
requirements
of this Contract" does not necessitate that the documents in
question be "approved" or "reviewed" as the case may be.
532 Both BHP-IT and the Commonwealth submit that before payment is due under
Schedule 8 all of the requirements for TRR must be met.
And it is only then
that an invoice for that milestone can be rendered under cl 16.3.
533 For my own part, I do not consider that the language of cl 16.1, read
in light of cl 16 as a whole and of the Sub-Contract
more generally,
requires me to attribute to the parties an intention so improbable as GEC
Marconi proposes. The documents that are
to be supplied for TRR under the
Schedule 8 "Delivery Schedule and Payment" plan are (i) contract deliverables
and (ii) are required
to be approved or reviewed by the Customer. Nonetheless
the submission advanced is that the Customer is obliged to pay for what
is to
be a deliverable without being able to exercise its right of approval or review
before it does so.
534 The clear contemplation of cl 16, when read in light of Schedule 8, was
that a contracted milestone payment became due when the
requirements of that
milestone had been met. Clause 16.1 and cl 16.3 were not concerned with
when a progress payment was due.
They presupposed that. Rather their concern
was with the manner in which (cl 16.3), and the conditions subject to
which (cl 16.1),
payment was to be made. There is nothing surprising in
requiring the Delegate to be satisfied that the supply of the documentation
referable to a milestone met the requirements of the contract. The Delegate
may well not have been a participant in the review process
- Mr Brent was not a
participant on all of the TRR reviews - and in consequence may have needed to
be satisfied that the documents
supplied met the contract's requirements, (ie
they were approved or reviewed by the Customer) before payment was made by
BHP-IT.
(ii) The Meaning of "Approval" and "Review"
535 The need to attribute meanings to these terms in Schedule 8 arises because,
at the very least, the TRR documents were required
to be either approved or
reviewed before it could be claimed that the requirements of TRR had been
satisfied and the Milestone 4000
payment was due. I say "at the very least" as
BHP-IT has submitted that there were other conditions to be satisfied before
payment
was due.
536 GEC Marconi's submission is that (i) all that the contractual process of
"approval" required was the provision of an opportunity
to BHP-IT to stipulate
amendments to any of the documents identified in Schedule 8 as requiring
approval; and (ii) the process of
"review" required no more than that the
documents to be reviewed be submitted to BHP-IT for comment. This submission
is based in
large measure on the construction GEC Marconi placed upon
cl 9F1.1 and cl 9F2.2 of the Sub-Contract and the description
given
of "Documentation Acceptance" for the purposes of cl 3 of Schedule 9 of
the Sub-Contract.
537 I do not intend to rehearse here the contentions of the parties in any
detail. The key to the meaning of the two terms lies
in Schedule 8 itself.
Clause 1.2 of the Schedule specified that documents that were "subject to
review" were to be "reviewed by the
Customer in conjunction with the Contractor
during the formal review process conducted by the Contractor": emphasis
added. The formal review so envisaged was clearly the one the SDP required to
be undertaken
for TRR: cl 3.8. It was to be a formal external review and
at least one representative from BHP-IT was required to be part
of the review
group for TRR. As I have indicated the IPD Standard document prescribed the
manner of conduct of this type of review.
Though cl 1.2 might seem to
suggest that the "[review] by the Customer in conjunction with the Contractor"
was to be a review
within a review in that it was to take place "during the
formal review process", the intention properly to be attributed to the parties
was that there was to be only one review in which the Customer participated as
a reviewing party. I would note as part of the objective
framework of facts:
Schenker & Co (Aust) Pty Ltd v Maplas Equipment and Services Pty Ltd
[1990] VR 834 at 837; that early versions of the SDP which pre-dated the
Sub-Contract envisaged a similar formal external review
for TRR. Further,
because the TRR external review was to be conducted in accordance with the IPD
Standard, the review contemplated
by cl 1.2 would only be completed in
respect of a particular document when the TRR review of that document was
completed in
accordance with the requirements of the IPD Standard document. I
will return to that Standard document below.
538 I should add I do not consider that cl 9F1.1 assists in the
construction of Schedule 8. It opens with the words "[w]here
the Customer is
required to review Documentation ... for the purposes of commenting
(reviewing), approving or accepting that Documentation"
etc. It is from this
that GEC Marconi derives its submission that "review" means "comment upon".
Clause 9F.1 has no greater purpose
than to describe the machinery to be
employed governing distribution of documents to the Customer, their retrieval
and the proper
communication of any comments made by the Customer. The use in
that general setting of "reviewing" as a synonym for "commenting"
is readily
understandable. The word "review" as used in the specific context of Schedule
8, and its elaboration in cl 1.2 of
that Schedule, leaves no room for the
suggestion that it simply means "comment upon" in that context.
539 Clause 1.3 of Schedule 8 required that a document subject to "approval" was
to be subject to conditions set out in cl 9F.2.
All I need say of this is
that I agree with the Commonwealth's submission that that clause was purely
procedural in character.
For the purposes of cl 1.3 of Schedule 8,
cl 9F.2 provided the means to enable the Customer to exercise its
contractual
responsibility to approve the documents concerned. It did not
stipulate what was to constitute approval.
540 I again agree with the Commonwealth that the word "approval" was intended
to have its ordinary natural meaning. It required
a positive act on the
customer's part that "assented to", "confirmed" or "approbated" the document in
question - that "pronounced
[it] to be good": see Shorter Oxford English
Dictionary, "approval", "approve". I should add without elaborating on the
matter that I do not consider that the provisions of Schedule 9
relating to
document acceptance affect the conclusion at which I have arrived. I agree
with the Commonwealth's submissions.
541 The sources of the requirements that both the Acceptance Test Data and the
Test Descriptions (Procedures) be approved individually
by the Customer were to
be found in cl 9E.4.1 and cl 9E.5.1 of the Sub-Contract. As I have
noted, these two documents
were combined into the ATD. That document (because
it involved Test Descriptions) had to be approved by the Customer "prior to the
commencement of the Acceptance Tests": cl 9E.5.1. Given that the TRR
specified in the SDP was to be conducted after integration
testing in
anticipation of acceptance testing: SDP cl 3.8iv; it is proper to infer
that, for the purposes of the Schedule 8 Milestone, it was envisaged
that that approval would be signified on and by successful completion of the
TRR. In saying this, I am not necessarily
implying the Customer may not have
been able to require alterations to the ATD after TRR as a matter of
contractual right.
(iii) The Schedule 8 TRR and the SDP TRR
542 I have already indicated my view above that documents required to be
reviewed or approved for Schedule 8 purposes had to be reviewed
as part of the
formal external review for the TRR mandated by the SDP. The corollary of this
is that the Schedule 8 Payment Plan
was linked to the SDP TRR.
543 It has been GEC Marconi's contention that it was open to the parties to
define TRR differently for different purposes. The SDP's
TRR was for the
purpose of software development. Schedule 8's TRR was designed to impose a
payment obligation. Assuming GEC Marconi
was obliged to implement the SDP
(which is denied), both TRR's could operate quite independently of each
other.
544 I have in effect rejected this conclusion already by making the link I have
between the Schedule 8 "review" and the SDP formal
external review for TRR. I
should nonetheless indicate why I consider GEC Marconi was in any event obliged
to implement the provisions
of the SDP in relation to TRR.
545 The combined effect of cl 55 and Schedule 3 of the Sub-Contract was to
oblige GEC Marconi to comply with the standards set
out in the SDP (and any
subsidiary documents to the SDP) in supplying services to the Customer. The
SDP defined the software development
process, that process being self-described
as "Best Commercial Practice". An integral element of that process and
"Practice" was
the conduct of formal external reviews of which TRR was one. In
my view, the requirement of formal external review was a "standard"
mandated by
the SDP to be applied in the development process. The manner of conduct of
those reviews (ie "in accordance with IPD
Standard for Reviews and Audits":
SDP cl 3.8) in turn required compliance with detailed procedures the
object of which was to
enable the customer formally to "evaluate products
created during a development phase". Those procedures, when considered in
light
of the purpose they served, properly can be described as standards for
the conduct of a review, and were no less so for being concerned
with process
and procedure. The IPD Standard document was for the purposes of Schedule 3 of
the Sub-Contract a subsidiary document
of the SDP. In consequence GEC Marconi
was obliged to comply with its standards.
546 Finally, and additionally, cl 10 of the Sub-Contract required the
parties to perform their obligations in accordance with
the Project Plan in
Schedule 7. One of GEC Marconi's contract obligations was to "assume project
management and control ..." in
accordance with the Sub-Contract: cl 4(j).
A project management function prescribed for GEC Marconi by Schedule 7 was to
ensure
that "the provisions described in the Software Development Plan are
implemented". While cl 4 of the Sub-Contract did not directly
oblige GEC
Marconi to implement the SDP, the indirect route adopted of obliging GEC
Marconi to perform its obligations in accordance
with the Schedules, provided a
prescription against which the adequacy and propriety of its performance was to
be judged. The Sub-Contract,
in other words, clearly contemplated that GEC
Marconi would implement the SDP. I would add that the reference made to the
"formal
review" in cl 1.2 of Schedule 8 reflects that contemplation.
547 My conclusions then on the construction issues can be put as follows.
Payment became due for Milestone 4000 when GEC Marconi
satisfied the
requirement for TRR that was prescribed in cl 3.8 of the SDP. The
"review" of documents envisaged by Schedule
8 was the TRR itself. The
"approval" of documents envisaged by the Schedule required assent to those
documents by the Customer,
though those documents had as well to pass TRR.
(2) The Factual Issues
548 There are two discrete issues here. The first is whether in fact the
review of the test documentation was completed. The second
is whether, if that
review was completed, were the requirements that needed to be satisfied for TRR
in fact satisfied. This second
issue is premised upon the SDP stipulation that
the TRR was to be held at the end of integration testing so that requirements
for
that testing and reports from it were part of the TRR requirements. Both
of these matters can be dealt with together.
549 Preconditions required to be satisfied for the Milestone 4000 payment to be
due were at least that the ATD be approved and that
the SDSDD and the TASDD be
reviewed. BHP-IT and the Commonwealth both submit that (i) the ATD was not
approved; (ii) the SDSDD
review was "Passed with follow-up action to occur";
and (iii) the review of the TASDD was never completed. As I understand the
position
taken by BHP-IT, it accepts that for Milestone 4000 purposes the
review of the SDSDD was passed, the follow-up action being taken
on the day
after the review was passed "with follow-up action" and the Review Action
Sheets were signed off by the Review Chairman
as required by the IPD Standard
document.
550 There is a considerable controversy between the parties as to whether or
not the ATD was approved. It is common ground that
the ATD review was split
into three reviews and that these were held on 26 February 1996, on 11 March
1996 and on 9 and 12 April
1996. Each such review generated Review Action
Sheets with action items running into many hundreds. No overall Review Result
Record
was signed for the ATD. The controversy between the parties relates to
the reason why that did not happen.
551 As to the TASDD, it was the subject of a number of review meetings from 21
September 1995 to 6 June 1996 which generated significant
comments and action
items. The minutes of the Formal External Review of 6 June, while recording
five action items, does not record
that a review result was determined. While
there was a Review Action Sheet created, there was no Review Result Record.
BHP-IT and
the Commonwealth submit that no result having been arrived at, the
review was incomplete while GEC Marconi has submitted that no
result was
necessary in the circumstances and that the TASDD had been reviewed.
(a) Additional Factual Material
(i) The ATD
552 The Sub-Contract provided for TRR to take place on 6 September 1995. Such
did not occur. In mid-November 1995 Mr Harris prepared
a schedule for the
delivery of the ATD. This led Mr Wishart to write to Mr Brent on 22 November
1995 proposing that the TRR for
ATD occur on 15 January. That letter, as did
some others in correspondence concerning the ATD, indicated that the TRR would
be conducted
in accordance with the sections on formal external reviews in the
IPD Standard document.
553 A working draft of the ATD was forwarded to BHP-IT on 4 January. The
version to be reviewed was forwarded to BHP-IT on 5 February,
the TRR then
being scheduled for 19, 20 and 21 February.
554 On 8 February 1996 Les Cook wrote to BHP-IT proposing that the ATD review
be split into three reviews. That proposal was reiterated
in a further letter
of 12 February 1996 which, because of submissions made on it, is set out at
length below. Between these two
letters, Mr Brent put GEC Marconi's separate
proposals to Mr Cook that Milestone 4000 be split into three reviews with
separate payments
being made for each. That separate proposal was rejected in
the 12 February letter which was forwarded by Mr Brent to GEC Marconi
on 13
February.
555 Omitting formal parts the 12 February letter stated:
"In response to your letter of 9 February, the department is unable to agree to any split of Milestone 4000 until the impact of CRs 3057 (Stubs replacement) and 3048 (Xerox interface) is known.
In the meantime, we are prepared to participate in the review of the ATD, SDSDD and TASDD documents as per the schedule shown below. We believe a progressive review of the ATD is necessary over a period of time given the size of the document.
26 February
DFAT will jointly review and approve (subject to any agreed follow up changes being made no later than 1 month prior to the commencement of FQT) the ATD chapters on Functional Test Packets 1 to 10 for the Secret Canberra operational scenario only.
DFAT will also jointly review the TASDD and SDSDD.
1 April
DFAT will jointly review and approve (subject to any agreed follow up changes being made no later than 1 month prior to the commencement of FQT) the ATD chapters on Interface, Performance, Recoverability, COTS Software Regression, Developed Software Regression, Security and Support Subsystems for the Secret Canberra operational scenario only.
2 May
DFAT will jointly review and approve (subject to agreed changes being made no later than 1 month prior to the commencement of FQT) the remaining operational scenarios in the ATD."
556 Three separate review meetings were agreed and these took place 26
February, 11 March and 9 and 12 April 1996. The Review Action
Sheets of the
first review contained two hundred and twenty-six action items; those of the
second, one hundred and twenty-four items;
and the Review Action Sheets of the
third review, one hundred and forty-four items.
557 On 22 April 1996 Mr Goldsmith wrote to Mr Brent concerning the third
review. His letter stated:
"Attached are the Review Action Sheets recorded at the Formal External Review for the ATD Part 3. Please have this document circulated and allow the following to review and confirm the accuracy of the comments by initialling at the bottom of each page. The reviewers are invited to record any inaccuracy beside, underneath or over the applicable comment.
Les Cook
Bob Nichols
David McGregor
Please have this document returned to IPD Systems Engineering by COB Friday 26 April 1996 to enable rework to begin."
558 On 24 April 1996 Les Cook wrote to Mr Brent concerning the Review Action Sheets of the third review. That letter stated in part:
"The IPD Review Action Sheets from the ATD review meeting held on 9 April 1996 are accepted subject to the following changes:
ATD Review Part 3 of 3
...
Items No 43, 45, 50 etc
The wording of the action sheet represents what was said in the review. The action is to consider a large scale rework of the recoverability tests rather than to define a specific set of changes which can be agreed to at this stage. Because of the possible magnitude of the changes necessary to meet the intent of the comments provided, DFAT reserves agreement until the redrafting is completed and has been examined: emphasis added
...
ATD Review Part 3 of 3 - Security
Item #6
The action item states that the issue will be `checked'. DFAT reserves comment until the outcome of this checking is known.
Item #18
Action is to supply the test when design is finalised. DFAT reserves comment until the outcome of this is known.
Item #26
The action item states that the issue will be `checked'. DFAT reserves comment until the outcome of this checking is known.
...
Item #48
The action item states that the issue will be `investigated'. DFAT reserves comment until the outcome of this checking is known.
Item #56
The action item states that the issue will be `investigated'. DFAT reserves comment until the outcome of this checking is known.
Item #68
The action item states a question. DFAT reserves comment until the answer to this question is known.
Not Present
See DFAT comments #62, #63, #65, #84 and #86 which seem to be absent from the action sheets."
For reasons given below I infer that Mr Brent forwarded these comments to
GEC Marconi on 29 April 1996.
559 On 12 August 1996 Mr Goldsmith wrote to Mr Brent, his letter opening with
the following:
"Issues Raised at the ATD Review (Phase 3) on 9 April 1996
Reference: A. BHP IT Letter KB-1184 dated 29 April 1996
At Reference A, Mr Les Cook (DFAT Project Director) raised a number of issues regarding the review comments made during the third review of the Acceptance Test Description (ATD) Document. Below are the issues which Les raised (in italics) followed by EASAMS responses. Would you please pass them on to Les and the Department."
The letter then proceeded to respond to three matters.
560 By separate letter of 12 August 1996 to Mr Brent, Mr Goldsmith indicated
that the review action sheets had been updated as requested
by the Department,
and he asked Mr Brent to "ensure that the Department reviews and approves the
amendments so that EASAMS can then
update the ATD document as requested".
561 The Department's response was conveyed to Mr Brent in a letter of 26
August. It stated:
"The consolidated IPD Review Action Sheets from the ATD reviews have incorporated most of the amendments requested by DFAT. Security items 6, 18, 26, 48, 56 and 68 are, however, still to be addressed and the outcomes reviewed (see attached copy of DFAT review comments). Further, DFAT comments on Security items 62, 63, 65, 84 and 86 have not been included in the action sheets.
The ATD review has not yet been signed off as complete. The Department is not prepared to approve the document as complete, nor as complete subject to agreed reworking. The significance of the degree of reworking required by several of the comments made at the review require the document to be reviewed again when the reworking has been performed."
562 Mr Brent in turn wrote to GEC Marconi on 28 August forwarding DFAT's
letter and requesting that its comments be incorporated in
the document and
that the necessary arrangements be made "for the final review of the
document".
563 Unlike with the SDSDD and the TASDD reviews, no minutes of any of the three
ATD reviews are in evidence. There is, though, what
purports to be an unsigned
Review Result Record which records no result for the ATD review, but to which
was attached the following
typed note:
"Notes: The review was held in 3 parts. At the completion of the part 3 (12 April 1996) the Customer "unofficially" informed IPD that the ATD would be passed with rework. Due to contractual issues at the time the Customer declined to sign-off on the review until the contractual issues had been resolved. N. Brazil."
Mr Brazil, though working with, and representing, GEC Marconi at the time,
was a BHP-IT employee. Next to his typed name are initials.
The typed Result
Record lists one of Mr Brazil's roles in the review as "Review Recorder". He
was not called by BHP-IT to give
evidence.
564 Les Cook was cross-examined at length both about this note and about his 26
August letter. Because of the reliance placed upon
parts of that
cross-examination by GEC Marconi, it is necessary to set out some number of
extracts of that cross-examination by Mr
Simpkins SC.
565 Reference having been made to Mr Brazil's note, the following exchange
occurred:
"Q. At the review meeting held on 12 April 1996, do you remember who it was that represented DFAT, or do you need to go back to the review sheet?
A. No. It was primarily myself.
Q. Did you tell Mr Brazil at the completion of the review meeting held on 12 April 1996 that the acceptance test description document would be passed with rework?
A. I certainly did not.
Q. Did you tell Mr Brazil that due to contractual issues at the time, you, however, were not prepared to sign-off on the review?
A. No, I don't believe that's true at all.
Q. Well, at the conclusion of the review held on 12 April 1996, did you speak to Mr Brazil?
A. I don't recall that.
Q. Did Mr Brazil ask you what the outcome of the review was?
A. I'm afraid I don't recall.
Q. Did he produce a review result record and ask you to sign it for the acceptance test descriptions document?
A. I don't recall doing so."
566 A later sequence of questions again addressed the Brazil note:
"Q. Can I suggest this you, Mr Cook: If the ATD had been passed with rework it would have been entirely consistent, wouldn't it, with the practice which was followed between the parties in relation to the milestone 2000 and milestone 3000 documents?
A. Depending on the state of completion of document, yes.
Q. As I understand what you wish to say, Mr Cook, you say, do you, that there were particular things about the acceptance test descriptions document which meant that it was much more incomplete than any earlier document you'd reviewed and that, therefore, the review couldn't be concluded on the basis of a pass with rework conclusion?
A. Yes."
567 He was then taken to his 26 August 1996 letter to BHP-IT:
"Q. Do you see in the first paragraph of this letter you say in relation to the IPD review action sheets from the ATD reviews that there are some identified security items which are still to be addressed and the outcomes reviewed, and that there are some comments that DFAT's made on some other identified security options that have not been included in the action sheets?
A. Yes.
Q. I just want to understand the sense of this letter. Does the letter mean the ATD has not been approved because of those identified security matters, or do you suggest that they are irrelevant to the question of completeness of the document presented for review at the ATD review? Perhaps I can withdraw that and put it more directly. I'm trying to understand, Mr Cook, what it is that you are referring to when, in the second paragraph in this letter, you are describing something as `the significance of the degree of the reworking required'. What is that a reference to?
A. At this distance and time, I'm not sure that I can remember what the significant items were.
Q. These items were the items in 1996 that you say meant that contrary to an assumption that you had adopted perhaps in earlier correspondence the ATD could not be approved by DFAT, correct?
A. Yes.
Q. And, indeed, I think in your evidence to this Court you have suggested that there were, in fact, significant aspects of the ATD which prevented documents from being approved; correct?
A. Yes.
Q. And is His Honour to understand that you now can't tell him what significant aspects required reworking?
A. I can't recall them in detail. If I went through the document and all the action sheets I could perhaps derive that information.
Q. That's not an exercise that you've carried out for the purposes of giving any evidence in this case?
A. No, I haven't.
Q. Well, if these were matters of serious difficulty with the ATD in 1996, may I take it your ordinary practice would have been to maintain some reasonable record of what those matters were and what was being done by way of drawing attention to them so far as BHP-IT and/or GEC Marconi were concerned?
A. I believe that record is in the review of the - in the documentation of the review.
Q. Mr Cook, no doubt there are matters in the record of review which are identified as matters requiring attention. What I'm asking you about are those matters which you believed in 1996 to be of such significance that it meant that the ATD just could not be approved. Do you follow?
A. I do."
...
Q. Mr Cook, I do want to be fair about it so I just need to understand whether the document that I've just taken you to, which is a letter you wrote to Mr Brent on 24 April 1996, sets out, as you presently recall it, what those matters of great significance were that you believed in 1996 precluded the acceptance test descriptions document from being approved by DFAT?
A. I think it sets out the concerns I had relating to what was reviewed in the third review. I suspect there are similar documents relating to the other two reviews. And even in this one, for example, the bottom of page 14583, the second last items, number 43, 44 and 50, et cetera, define the need to consider a large scale reworking of some tests. That is not a minor matter.
Some of these points are minor wording changes. Others relate to complete changes of large areas of testing. I believe if we look at the documents relating to the other two reviews there will be similar points made.
Q. Well, can I go back to the question that I was wishing to ask a moment ago, again, and get an answer to it. I'm asking you whether it would be in accordance with your ordinary practices in 1996 in respect of such significant matters to maintain some appropriate record of what those matters were and what was being done to remedy them?
A. No, I believe that the result - the review action sheets were sufficient to document what the problems were, or issues were. And at that time I believe I, and probably Mr Nichols and others, had in our minds what the problems were - the understanding of the problems."
568 Shortly afterwards and in response to question of my own Mr Cook
conceded that he was now speculating as to what might then have
been in his
mind. Mr Cook was then invited to review the Action Sheets overnight to see if
he could identify what matters were so
significant as to require non-approval
of the ATD. Though he returned next morning with a list of matters in the
Action Sheets that
were inadequately defined, he again conceded to me, that the
list did not represent anything he recollected, but was a contemporary
rationalisation.
569 There are only two aspects of Mr Harris' evidence relating to the ATD
reviews to which I need refer. First, he accepted that
on receipt of the
review sheets, his team would change the acceptance test descriptions and that
that process occurred from the end
of April 1996 onwards. He equally agreed
that by mid-August GEC Marconi was still trying to finalise the review comments
about the
ATD. Secondly, he agreed that he was aware that the position of both
DFAT and BHP-IT in August 1996 was that the ATD documents had
not been approved.
(ii) The TASDD
570 As an early precursor to TRR, on 18 September 1995 GEC Marconi forwarded a
"working draft" of the TASDD to BHP-IT for information
and comment. BHP-IT
provided comments in letters of 21 and 25 September 1995. The TASDD went
through a number of versions subsequently
and on 19 February Mr McGregor sent
comments to GEC Marconi on what was then TASDD Version 1.0 Draft C1, in
anticipation of the formal
external reviews of (inter alia) this document.
Those comments identified nine major defects. In the accompanying letter Mr
McGregor
said of this document and the SDSDD:
"The major problem with [them] as they currently stand is that they do not contain sufficient detail for either the contractor ... or the Commonwealth ... to install, configure and build the systems."
571 On 28 February 1996, Mr Brent forwarded to GEC Marconi DFAT's comments on the above draft. These identified five major and two minor defects. Item 7, which was described as a major defect, was in the following terms:
"The system should be configured to use sealers and a gateway. This will be by either:
(a) using Stubs emulation software if agreement is not reached on CR3057 (Stubs replacement); or
(b) using the Stubs replacement (KIV-7) as per CR3057.
Something should be shown in the TASDD to reflect the above."
572 A formal external review meeting for the TASDD was held on 1 March 1996.
The Review Action Sheets are in evidence and disclose
thirty action items
resulting from the meeting.
573 According to Mr Harris further meetings were held between 1 March and 6
June. The minutes of the 6 June meeting to deal with
now what was Version 1.0
Draft C2 of the TASDD indicated that:
"This review incorporated comments made at an informal discussion held on the 4th of June 1996, the letter titled TASDD Review (File: 90/015051, 24 May 1996) from L G Cook and the comments concerning the content of the document raised by David McGregor (KB-1259)."
The letter and comments referred to are not in evidence.
574 Under the heading "Broad Issues", the minutes recorded:
"BHP-IT raised the following broad issues:
* Sections 4.1, 4.3, and 4.6 require modifications. Figure 4-1 also requires modifications.
DFAT raised the following broad issues:
* TAS should be using the same software as the operational system. Therefore, the STUBS system (CR3049) should be included in the TAS.
* It was agreed that in principle the TAS should use as much of the existing equipment in the TIF as is possible, rather than requiring the purchase of new equipment.
* The diagram 4-1 is an extract from the ADD, and is out of date. The ADD should be re-reviewed to reflect reality, rather than have the TASDD using the ADD as its source. In DFAT's view, the PSI is responsible for maintaining documentation. There was some discussion on the process required to update the documentation."
The Review Action Sheet recorded nineteen action items.
575 In the "Relevant Sub-Contract Provisions" section of the "Construction
Issues" above, I quoted from cl 7.6.2 of IPD Standard
for Inspections
Reviews and Audits. It envisaged that at the end of the review meeting the
reviewers determine the review result
and that this is to be recorded in the
Review Result Record. The minutes of the formal review for the SDSDD record
such a determination
being made for that document. The meeting for the SDSDD
occurred on 6 June 1996 and ran from 9.42am to 9.53am. It was immediately
followed by the TASDD meeting which finished at 11.27am on the same day. The
same persons were attendees at both meetings. The
minutes of the TASDD meeting
do not record any determination being made as to the result of the review.
576 Mr Harris accepted in cross-examination that he did not remember ever
seeing a final version of the document that had been reviewed
on 6 June. Les
Cook in cross-examination, having been shown the minutes of the TASDD 6 June
meeting recalled the TASDD was reviewed
and in light of the minute that it must
have been reviewed again on 6 June. To the question: "Will you agree that
certainly by
no later than 6 June 1996 the TASDD had been reviewed?" he
responded: "There had been a review, yes".
(b) Submissions and Conclusions
(i) The ATD
577 As I earlier indicated the positions taken by the parties in relation to
the ATD external review were, on the part of BHP-IT
and the Commonwealth, that
the ATD was never approved (conditionally or otherwise) as work was still being
done, and, on GEC Marconi's
part, either that the review was completed and the
ATD approved for practical purposes or that the improper action of the
Commonwealth
prevented such from occurring.
578 The Brazil note on the Result Record Sheet is at the core of GEC Marconi's
submission: the ATD would have been "passed with
rework" but for the
"contractual issues". Given the evidence before me, though, there is a very
real question whether the point
had in fact been reached where approval would
have been given in any event. I make that observation for this reason.
579 On 12 February 1996 Les Cook wrote to Mr Brent describing what the
Commonwealth's participation in the three ATD review meetings
would be. In
relation to that he said it would jointly "review and approve (subject to any
agreed follow up changes being made no
later than 1 month prior to the
commencement of FQT)" that part being reviewed in each review. What this
conveyed is of some importance.
While anticipating that approval would be
given on each occasion, it contained an important implicit qualification. That
was that
the "agreed follow-up action" would be identified and agreed prior to
the approval being given. Unless and until it was agreed,
the ATD would not be
approved. And when it was agreed the approval would be an approval subject to
agreed follow up action etc,
or, to put it briefly, approval "subject to
rework".
580 It should be said that this letter obviously was prospective and
anticipatory in character and proceeded on the assumption that
the ATD document
would be able to be approved subject to agreed follow-up action. Save for any
question of an estoppel subsequently
arising in consequence of it: see below;
it did not preclude a change of mind. It remained open to the Commonwealth to
act otherwise
than as foreshadowed in relation to approving the ATD
document.
581 After the third ATD review, on 9 and 12 April, Mr Goldsmith by letter of 22
April sought both BHP-IT's and the Commonwealth's
review and confirmation of
the accuracy of the comments on the Review Action Sheets. Les Cook provided
his to Mr Brent on 24 April
1996. That letter indicated in relation to some
number of items that "DFAT reserves comment"; in relation to one group of
items,
"DFAT reserves agreement until the redrafting is completed and has been
examined"; and it commented on a number of security items
being absent from
the action sheet.
582 It is clear from both of Mr Goldsmith's letters of 12 August 1996 that Mr
Brent wrote to him on 29 April 1996 to provide comments
from Les Cook on the
third ATD review. One of those two letters addressed directly three comments
so received, describing those
comments in the actual language used in Les
Cook's 24 April letter. Mr Brent's 29 April letter is not in evidence and no
oral evidence
was given on this sequence of correspondence. It is equally
clear from the other of Mr Goldsmith's 12 August 1996 letters that
Mr Goldsmith
was aware from April 1996 that Les Cook was requiring
amendments to the Action Sheets and that those sheets had not been agreed in
their entirety. The burden of this letter was to get DFAT's approval to the
amendments made so that GEC Marconi could update the
ATD (ie take "agreed
follow up action").
583 While it may not strictly be necessary in light of the above to make the
following findings I do so because of criticisms made
of DFAT's actions and, in
particular, that it delayed until 26 August before communicating its reasons
for refusing to pass the ATD.
I infer as the most probable deduction that may
reasonably be drawn from the correspondence (i) that BHP-IT received the Cook
24
April letter prior to 29 April 1996; and (ii) that BHP-IT forwarded that
letter to GEC Marconi on 29 April 1996, rather than sending
merely extracts
from it relating to the three specific comments mentioned in Mr Goldsmith's 12
August 1996 letter.
584 Les Cook's comments on 24 April may be said to depart from what was
expressly foreshadowed in the 12 February letter in that
it indicated that
agreement was reserved on some items until redrafting was complete and had been
examined. It nonetheless made
plain, as it did in relation to the security
items, that DFAT was not agreeing, or agreeing conditionally, to the action
items.
585 As at 12 August it was known that the action sheets still had not been
approved by Les Cook. That approval was then being sought.
It was denied in
Les Cook's letter of 26 August 1996. A review was required after reworking had
been performed.
586 Les Cook's evidence was subjected to the criticism that he was unable over
five years later to indicate what were the matters
that required such reworking
as precluded the ATP being passed with follow-up action. I accept he had no
memory of them when he
gave evidence, but I am prepared to infer that such
matters did exist at the time. The comment made on "Items No 43, 45, 50 etc"
in his letter of 24 April 1996 clearly enough conveyed that DFAT was then
reserving agreement until a redraft had been completed
and examined "[b]ecause
of the possible magnitude of the changes necessary to meet the intent of the
comments provided".
587 As the Commonwealth had indicated in its submissions, GEC Marconi did not
lead evidence to establish that the substance of the
rework that was required
was of such a trivial nature that, from a qualitative viewpoint, the ATD
document should have been passed.
588 I do not consider that the objections raised by Les Cook to the Review
Action Sheets were contrived or manufactured for a collateral
purpose; I have
no basis in the evidence for holding that from a technical point of view the
reservations he made and the agreement
he withheld were unreasonable. Mr
Goldsmith did not give evidence in this proceeding so I am unable to consider
what his understanding
was of the outcome of the ATD reviews from at least the
time he wrote his 22 April letter. What his correspondence then and thereafter
indicated is that he was working to secure agreement to the Review Action
Sheets so that the ATD document could be updated. Those
actions were
consistent with an appreciation that the review was still not completed for the
reasons conveyed in Les Cook's correspondence.
589 Mr Brazil's note apart, the contemporary documentation would satisfy me (i)
that the ATD review was not completed by agreement
either at the end of the
third review on 12 April 1996 or thereafter for reasons related to the ATD
document itself and to action
that needed to be taken in relation to it, and
(ii) that the actions both of GEC Marconi and of the Commonwealth from 22 April
until
the "re-review letter" of 26 August 1996 were consistent with these
reasons having that operative effect. The question is whether
that note gives
a quite different complexion to what occurred on and after the 12 April
review.
590 Quite understandably, GEC Marconi has invited me to accept that the note
was not a fictitious record. If it did not record a
conclusion reasonably open
having regard to the communications in which Mr Brazil had engaged there was a
ready solution - BHP-T
could have (and should have) called Mr Brazil to explain
the note. For DFAT to have acted in the way suggested in the note was wrongful
and cannot be relied upon by it or by BHP-IT.
591 I would have to say that I have been troubled by this unexplained document
and by the course taken by BHP-IT in relation to it.
While he both worked with
the GEC Marconi at the time and represented it at the ATD reviews, Mr Brazil
was a BHP-IT employee. Not
only did BHP-IT not call him to give evidence, it
was content simply to rely upon the Commonwealth's submissions on the status
of,
and weight to be given to, the Brazil note.
592 Having said this, I am satisfied that, the Brazil note notwithstanding, I
should not depart from the conclusion I foreshadowed
in light of the
correspondence. My reasons for not attributing significant weight to the note
in the circumstances are as follows.
First, the note itself raises questions.
It recorded that the Commonwealth unofficially informed GEC Marconi that the
ATD would
be passed with rework but the Commonwealth nonetheless declined to
sign off until the contractual issues were resolved: (I will
for convenience
use the term "communication" to encompass both matters.) How GEC Marconi was
informed (separately from, or as part
of the meeting) was not indicated. Who,
as representing GEC Marconi, was so informed was likewise not indicated.
Though the Result
Record Sheet names four GEC Marconi representatives as
participating in the review of the ATD (Ms Schmidt, Mr Brazil, Mr Harris and
Mr
Carter), the evidence would suggest that only Ms Schmidt and Mr Brazil were
present at the third review. Mr Harris' evidence
is that he was present at the
first two of the three reviews. Ms Schmidt, who appears to have been the
"Chairperson" of the third
review, was a GEC Marconi employee and in early 1996
took over as IPD integration acceptance test manager. There is nothing in the
note to suggest that the communication was to Mr Brazil alone. Distinctly, the
Result Sheet suggests that the intended signatories
were to be the persons who
took part in any one or more of the three ATD reviews even if they were not at
the third review. As I
will note below, Mr Harris was such a person. There is
no evidence that he (or for that matter any other of the listed signatories)
was ever aware of, or asked to sign, the Result Sheet. There is no evidence to
suggest the note reflected the agreed view or understanding
of the listed
reviewers. On the contrary, in relation to Mr Cook and Mr Harris.
593 Secondly, what makes the communication to GEC Marconi unusual is that, if
it was made at the meeting, there is no evidence to
suggest that it was
communicated beyond the meeting (particularly by the Chairperson) to persons in
GEC Marconi who, one would expect,
would have had a real interest in knowing of
the communication either for reasons related to the document, or to the
contractual
dispute. I refer to Mr Harris, Mr Goldsmith and Roger Cooke. I
would note in passing that GEC Marconi served its first notice of
breach on
BHP-IT nine days before the 12 April meeting, and BHP-IT forwarded its notice
to DFAT the day prior to the meeting. Of
the people to whom I have referred
perhaps the most significant was Mr Harris as he participated in two of the
three reviews; he
was a person listed to sign off on the review of the ATD;
and he was the person responsible for the ATD document. There is no evidence
of the Commonwealth's communication being passed on to him. Rather, the
evidence was that in August 1996 he understood the Commonwealth's
position to
be that it had not approved the ATD.
594 Thirdly, I will not traverse again the correspondence between the parties
subsequent to 12 April other than to note the following.
Not only was the
correspondence bereft of any indication that would reflect the Commonwealth's
unofficial communication, it also
revealed the reason why the ATD review was
not considered to be complete by the Commonwealth. The parties' actions in
that period
were consistent with their working towards completion of the ATD
review.
595 Fourthly, Les Cook in cross-examination categorically denied making the
unofficial communication. The other Commonwealth person
listed as a
participant in the ATD review on the Result Record Sheet was Mr Nichols (though
the evidence does not suggest he was
at the third review). Mr Cook's
recollection of the detail of what transpired and of his own thoughts at the
third review meeting
is generally quite unreliable. Nonetheless, having regard
both to the particular subject matter and to the context in question,
I accept
his disavowal of having made such an unofficial communication at the 12 April
meeting notwithstanding he did not recall
speaking with Mr Brazil at the
conclusion of the review meeting. It is quite possible that something was said
at the meeting about
contractual issues given that the meeting was held the day
after BHP-IT forwarded GEC Marconi's notice of breach to the Commonwealth
and
that one item in the notice related to non-payment of an invoice for Milestone
4000 (of which the TRR of the ATD was part).
My preparedness to accept Mr
Cook's disavowal is reinforced by what I consider to be the unlikelihood of
such a communication being
made in the circumstances. I later indicate (Part
IV: BHP-IT's Second Cross-claim: Matters of weight and credit) that Les Cook
on occasion could properly be said to be both partisan and manipulative. I do
not consider that these qualities infected his denial
of the unofficial
communication and of the reason given for the failure to sign. Having regard
to the significance of the communication
and of the conduct attributed to the
Commonwealth in the Brazil note and in light of the general evidence concerning
Les Cook's project
management and relationship with the Department, I consider
it unlikely that he would have taken such an open and unequivocal step
that
would have had immediate contractual significance both for BHP-IT and GEC
Marconi without the authority of at least Mr Skinner.
There is no evidence of
any such authorisation.
596 Finally, if the communication had been made in the terms indicated in the
note it is surprising that GEC Marconi did not take
steps, if only by way of
seeking reassurance, to ensure that the two other reviews then underway, the
SDSDD review (which was "Passed
with follow-up action") and the TASDD review,
would result in judgments being made on the merits.
597 There is no basis for my inferring that the Brazil note is a fabrication.
Nonetheless, when considered in light of all of the
evidence and in particular
in light of (a) the general conduct of each of GEC Marconi, the Commonwealth
and BHP-IT subsequent to
the 12 April meeting; and (b) the absence of any
reflection of the note in that conduct, I consider that it would be unsafe to
attribute
any significance or weight to it. The note itself is contradicted by
what otherwise are established facts. When considered with
the Result Sheet,
the composite document raises ambiguities, doubts and speculations.
598 I am satisfied then that the third ATD review was not completed,
conditionally or otherwise, at the conclusion of the 12 April
meeting or
thereafter.
(ii)
The TASDD
599 The positions taken by the parties in relation to the review of the TASDD
were as I earlier indicated: BHP-IT and the Commonwealth
contend the review
was never completed; GEC Marconi submits to the contrary, it being said in
light of the minutes that no further
work was to be done beyond implementation
of what had been agreed and there was no suggestion that any further process of
review
was required.
600 Given (a) the long history of this document, (b) the exchanges and meetings
that took place in relation to it, (c) that broad
issues were raised by both
BHP-IT and DFAT, (d) the absence of any recorded determination of a result (in
contrast with the SDSDD
meeting that preceded the TASDD meeting) and (e) the
lack of evidence of a final version of the TASDD, I do not consider that the
most probable deduction that may reasonably be drawn is that the review was
completed for practical purposes. The absence of a recorded
result in the
minutes or in a Review Result Record is telling and made the more so as both
the SDSDD and TASDD minutes suggest that
the procedures followed for the
reviews reflected those of the IPD Standard for Inspections, Reviews and
Audits.
601 Les Cook's evidence that there had been a review by 6 June does not assist
GEC Marconi. In the context in which his answers
were given he can only
reasonably be taken as affirming the facts that reviews of the TASDD took place
on 1 March and 6 June. His
answers did not address the result of the 6 June
meeting let alone suggest that the formal external review process was
completed.
602 I am not satisfied that a result had been reached in relation to the TASDD
or that the review process had been completed for
practical purposes. I agree
with the submission of BHP-IT and the Commonwealth.
(c) GEC Marconi's Reply: Estoppel
603 I can deal with this matter shortly. GEC Marconi by reply, asserts that
BHP-IT is not permitted to advance as a fact that the
TRR documents were not
"approved" or "reviewed" as the Sub-Contract on its face required. There was,
it is alleged, an assumed state
of affairs between the parties relating to
external reviews upon which it relied detrimentally and from which BHP-IT and
the Commonwealth
are not permitted to resile. That state of affairs was that
for the purposes of reviews in general, but of TRR in particular, the
Commonwealth's role was to be limited to making comments which GEC Marconi was
free to ignore, but which, if agreed with, should
result in changes being made
to the ATD no later than one month prior to the commencement of Acceptance
Testing and that by such
process, the Commonwealth would be taken to have
approved the ATD.
604 This assumed state of affairs was claimed to be the product of
correspondence passing between the parties both in 1995 and in
1996. I need to
refer to several of the letters in some detail.
605 The first letter was written on 14 February 1995 after Milestone 2000 (the
Preliminary Design Review or "PDR") in response to
a letter forwarded by Mr
Brent. It related to the manner in which DFAT had been commenting on agreed
changes and making further
comments on the documents. The letter stated in
part:
"Following discussions with Mr Harris concerning the effort involved, DFAT will not insist on receiving versions of the documents with all of the agreed changes, provided that the agreed changes are incorporated by CDR.
Your letter raises questions concerning the purpose of the reviews. There is an implication that the review is to be regarded as a major contractual event in its own right. In fact, other than as proof that a certain amount of work has been done in order to justify a progress payment (which is refundable should final acceptance of the Canberra system not be achieved), the PDR and CDR have no contractual significance. The sole exception to this is the Acceptance Test Plan which is to be agreed as a final document.
DFAT regards its role in the design process as advisory, intended to provide advance warning to the PSI should there be an indication that the system may not meet the functional requirements when tested or that the standard of documentation will not meet the requirements identified in the DIDs. This advice should be offered whenever potential problems are perceived.
In particular, I am concerned by the statements that `If their (DFAT's) comments are not returned in time then we must reserve the right to disregard them. Also major issues identified after the formal review meeting (particularly at CDR) must be regarded as CRs, not as part of the review process'. Firstly, the PSI is under no obligation to act on any of the comments. If comments are ignored, the PSI risks failing to achieve requirements in acceptance testing or other project completion criteria."
This letter was passed on by BHP-IT to GEC Marconi on 21 February 1995.
606 Almost a year later, the Commonwealth wrote two letters concerning TRR to
BHP-IT which resulted in the definitive version of
the triple ATD reviews.
That version was contained in the 12 February 1996 letter the terms of which
are set out in full in "Additional
Factual Material: (i) ATD" above. Here I
merely repeat the first relevant part of that letter which reads:
"26 February
DFAT will jointly review and approve (subject to any agreed follow up changes being made no later than 1 month prior to the commencement of FQT) the ATD chapters on Functional Test Packets 1 to 10 for the Secret Canberra operational scenario only.
DFAT will also jointly review the TASDD and SDSDD." Emphasis added.
607 I would note of this that the qualification ("subject to agreed changes"
etc) may well relate only to the concept of "approval",
given that no such
qualification is attached to the term "review" in the last sentence quoted
above.
608 Both of Les Cook's February 1996 letters were forwarded to GEC Marconi. I
infer that GEC Marconi acquiesced in the proposals
put by Les Cook in the 12
February letter.
609 I have already indicated what I consider to be the burden of the 12
February letter as it related to the ATD review. Contrary
to GEC Marconi's
submission on the agreed state of affairs, that letter (i) required the agreed
follow up action to be part of what
was approved; (ii) it did not preclude a
change of mind on the Commonwealth's part (subject to any question of
estoppel); and (iii)
being prospective in character, the letter presupposed
that the ATD document was one capable of being approved with agreed follow-up
action if necessary.
610 The 1995 letter could, in my view, only properly be taken as being
concerned with the PDR and the Critical Design Review ("the
CDR") and with the
design process. These two reviews were quite different in function and purpose
from the TRR. I do no consider
that this letter had any bearing at all on the
understanding any of the parties brought to the nature of the Commonwealth's
participation
in the TRR process - the more so given (i) that some number of
GEC Marconi letters to BHP-IT (eg 22 November 1995 from Mr Wishart
and 5
February 1996 from Mr Harris and, importantly given its date, 20 February 1996
from Mr Goldsmith) indicated that the various
TRR reviews would be conducted in
accordance with the IPD Standard for Inspections, Reviews and Audits; and (ii)
that the evidence
is quite consistent with their having been so conducted.
611 I am not satisfied at all there was the conventional understanding
propounded by GEC Marconi. I likewise am not satisfied on
the evidence that it
was in fact relied upon in the actual review process itself. It is quite clear
that the conduct of the Commonwealth
and, to a degree, BHP-IT in both the long
sequence of correspondence and meetings for the TASDD, and in the ongoing
exchanges over
and comments on, the ATD from the first review on 26 February
1996 until Les Cook's letter of 26 August 1996 would have made any
such action
in reliance quite unreasonable. Neither the Commonwealth nor BHP-IT were
assuming the role of bare commentators. Moreover,
even on GEC Marconi's own
assumption the time for making "comments" was not spent. I have found the
TASDD review was not completed.
It was likewise with the ATD. Les Cook's 24
April letter is strongly indicative of this.
612 Distinctly, there is no evidence at the time in relation to either of the
above reviews that GEC Marconi objected to the supposed
change of stance by the
Commonwealth. This tends to confirm my view that the Commonwealth was not
actually perceived by GEC Marconi
as having unexpectedly or otherwise moved
from a position to which it had previously committed itself.
613 I agree with the submissions both of the Commonwealth and BHP-IT that the
GEC Marconi's submission is based on a contrived use
of the 1995 and 1996
correspondence. I reject the estoppel claim.
(3) Outcome
614 In light of my findings in relation both to the ATD and to the TASDD, the
documents in question had not been "approved" or "reviewed"
respectively at the
TRR. Consequently in both instances the conditions required to be satisfied
for the Milestone 4000 payment to
become due, were not established. There was
no breach of contract occasioned by BHP-IT's refusal to make payment on the
Milestone
4000 invoice rendered by GEC Marconi. Accordingly the Notices of
Breach lacked foundation.
7. MILESTONE 4000: ADDITIONAL DEFENCES
615 There are four additional matters raised by BHP-IT by way of defence to its
alleged Milestone 4000 breach of contract.
616 The first is a consequence of what is said to be the proper construction of
the Sub-Contract. This defence is that for TRR to
be achieved not only must
the relevant documents have been reviewed or approved, GEC Marconi also had to
demonstrate to BHP-IT that
the Developed Software was ready for acceptance
testing. That need, reflecting the purpose of TRR, was a consequence of the
provision
in the SDP which provided:
"The TRR shall be held at the end of the Integration Testing phase, and shall be used to ensure that the system is ready for Acceptance Test."
I will refer to this as "the SDP Defence".
617 The second defence is that the invoice for Milestone 4000 was not correctly
rendered. The essence of this defence is that when
the invoice was submitted
to BHP-IT on 12 March 1996 the review approval processes were not complete and
GEC Marconi was still working
on the relevant documents. In consequence
payment for the Milestone was not due; the invoice was not "correctly
rendered" as required
by cl 16.5 of the Sub-Contract; and no fresh
invoice was ever submitted to BHP-IT: ("the Invoice Defence").
618 The third defence is that even if the non-payment of the invoice
constituted a breach, the breach was not one entitling GEC Marconi
to terminate
for "failure ... to perform [the] Contract" under cl 40.8: ("the
cl 40.8 Defence"). There is a related defence
that the non-payment was
not a breach at all as Mr Brent was not satisfied on reasonable grounds under
cl 16.1 of the Contract
that the documentation met the requirements of the
contract: ("the cl 16 Reasonable Grounds Defence").
619 The fourth defence is that, if there was a breach, GEC Marconi continued to
proceed with the Sub-Contract and thus elected to
affirm it: ("the Affirmation
Defence").
620 I do not intend to consider all of these defences in detail. It is
necessary for me to express concluded views on aspects of
two of them.
Otherwise I will confine myself to brief comments. My reason for taking this
course is that I consider there to be
an overwhelming case of bad faith on GEC
Marconi's part in relation both to its claim that payment for Milestone 4000
was due and
to its attempt to use non-payment of that Milestone as a basis for
termination for breach.
(1) The SDP Defence
621 I would make simply this comment. The SDP indicated when and why TRR was
to occur. In the event, the parties began the formal
external reviews of the
relevant documents long before integration testing was ever likely to occur.
By so doing they acted inconsistently
- and it must be presumed knowingly: cf
Sargent v ASL Developments Ltd, above, at 645 - with the SDP. If they
were content to proceed to approve or review the relevant documents, why should
it not be said
that the TRR was then completed, albeit at a time different from
that prescribed in the contractual documentation?
(2) The Invoice Defence
622 In light of my findings, it is the case that when GEC Marconi submitted its
invoice to BHP-IT on 12 March 1996, payment for Milestone
4000 was not due.
The invoice at that time was not "a correctly rendered" invoice: Sub-Contract,
cl 16.5(a), and cl 16.3.
There was in consequence no trigger to the
Delegate's obligation to make a progress payment pursuant to cl 16.1. No
fresh
invoice was ever rendered, although GEC Marconi now submits in this
proceeding that all matters required to occur for Milestone 4000
to be achieved
occurred no later than 6 June 1996. In all three of its Notices of Breach, GEC
Marconi claimed that BHP-IT failed
to pay the Milestone payment "pursuant to
Invoice 14248 of 12 March 1996".
623 It is GEC Marconi's submission that if the TRR conditions were in fact
later satisfied (ie payment for Milestone 4000 was due)
that of itself would
render effective the previously ineffective invoice. It is said that it would
be commercial nonsense to construe
cl 16 so as to require GEC Marconi to
go through the "hollow formality" of submitting a fresh invoice.
624 I cannot accept this submission. The Sub-Contract went to some lengths in
cl 16 to establish a regime for the making of
payments based on correctly
rendered invoices. For present purposes a correctly rendered invoice was one
in which the amount claimed
for payment was due for payment: cl 16.5(a).
Unless and until such an invoice was submitted the Delegate's obligation under
cl 16.1 was not enlivened. Neither did the 21 "Normal Working Day" period
begin to run within which payment was to be made.
On GEC Marconi's submission,
on the day that fortuitously TRR was completed, the ineffective invoice was
rendered effective; the
21 day period began to run; and the Delegate's
obligation was triggered - notwithstanding (i) that no one might actually have
been
aware, or at least realised at the time, that TRR was completed; and/or
(ii) that the Delegate might have been and might have remained,
unaware that
his obligation under cl 16.1 had been triggered and that the 21 day period
had began to run.
625 If, as GEC Marconi further submits, a failure to make the TRR payment would
entitle it to resort to cl 40.8 for termination
purposes, it is readily
understandable why the cl 16 payment procedure was agreed to be the
parties. On GEC Marconi's submission,
it would be possible for a contractor in
the position of BHP-IT to be in breach of contract without ever being aware
that its obligation
to make payment had arisen or without ever being asked to
pay after payment became due.
626 The submission is manifestly inconsistent with the actual requirements of
cl 16. It also is contradicted by cl 40.8.
A Notice of Breach had
to specify the particular breach required to be remedied: cl 40.8. All
these notices did this by reference
to the non-payment of the 12 March invoice.
It was that breach and no other that BHP-IT was required to remedy: cf
Italmare Shipping Co v Ocean Tanker Co Inc [1982] 1 WLR 158 at 164. And
it required BHP-IT to do something it was never, and could never be, obliged to
do.
627 I agree entirely with the submissions of BHP-IT and the Commonwealth. The
requirement that a fresh invoice be submitted once
payment became due was no
hollow formality. There were clear prudential reasons for it. Accordingly,
having found that the 12 March
invoice was incorrectly rendered at the time, I
conclude that it was and remained ineffective to trigger BHP-IT's obligation to
make
payment under cl 16 of the Sub-Contract (assuming TRR was later
completed), and that there was no breach of contract in relation
to TRR that
could activate the termination provisions of the Sub-Contract.
628 I need not explore the question whether GEC Marconi ever directed its mind
at the time to the question of the date when TRR was
completed. If it did and
was satisfied that it was by a particular date, it was on its own head that it
did not then render an invoice
for payment.
(3) The cl 40.8 Defence/The cl 16.1 Reasonable Grounds
Defence
629 I refrain from comment on either of these defences.
(4) The Affirmation Defence
630 I have earlier found that, prior to the service of the first Notice of
Breach, GEC Marconi had in any event elected to affirm
the Sub-Contract
notwithstanding the breach occasioned by the non-provision of STUBS. BHP-IT
has raised a like election to affirm
defence on the dual assumptions that the
non-payment of the 12 March invoice was a breach of contract and that it was
one that attracted
the cl 40.8 and cl 40.9 termination provisions.
631 The first Notice of Breach was served on BHP-IT on 3 April 1996. That
Notice gave BHP-IT thirty-two days to remedy the breach.
No payment on the
invoice thereafter being made, the cl 40.9 conditions were satisfied by
early May for GEC Marconi to terminate
the contract. It did not do so then, or
shortly thereafter. Two further Notices of Breach were served - the one on 18
June 1996,
the other on 24 September 1996. Both relied upon the non-payment of
the 12 March invoice. Termination was not effected until 10
December 1996.
632 Before referring to the evidence and arguments relating to affirmation, it
is necessary to consider the legal significance of
the second and third notices
of breach. They were in my view incapable of altering the legal character of
the breach resulting from
the non-payment of the 12 March invoice. That
breach, I consider, was a once-and-for-all breach when it occurred: cf
Larking v Great Western (Nepean) Gravel Ltd, above; albeit (on the
assumption that is being made) it was of such a character as permitted resort
to the cl 40 termination
provisions. I should add that I do not consider
that the breach in its setting was repudiatory in the sense of evincing an
intention
no longer to be bound by the terms of the contract: see Byrnes v
Jokona Pty Ltd, above, at [70]-[80]. As Mr Brent's 21 March 1996 letter
setting out his reasons for not authorising payment of the invoice illustrates:
see above "Construction Issues, Additional Factual Material"; he was
endeavouring to adhere to the contract and to have it performed.
The actual
significance of the second and third notices was, at best, evidentiary. If an
election to affirm had not been made prior
to the service of each of them, the
respective notices may have constituted evidence of continuing "reservations"
communicated to
BHP-IT: cf Champtaloup v Thomas, above, at 269.
633 The conduct subsequent to the first Notice of Breach that is relied upon by
BHP-IT as being justifiable only if an election had
been made to affirm is the
following.
(i) In the period 3 April 1996 to 10 December 1996, GEC Marconi continued to
perform software development and testing work and it
continued to seek guidance
and clarification from DFAT concerning requirements of the FRS through User
Guidance Requests it raised.
(ii) Between April and August 1996 it continued to participate in the review of
documents required for the TRR milestone. The evidence
of this has been
outlined previously.
634 It is GEC Marconi's submission that, at no time after 6 June 1996 (the date
it submitted TRR was completed) and prior to 10 December
1996, did GEC Marconi
ever resile from its contention that BHP-IT was in breach in failing to make
payment. Nor did GEC Marconi
ever expressly elect to affirm. The issuing of
the two subsequent Notices of Breach is quite inconsistent with such an
election
having been made.
635 For my own part, I do not consider that acts of performance done by GEC
Marconi during the thirty-two day period specified in
the notice for remedying
the breach could, as of course, be regarded as evidencing an election to affirm
in that period. A clear
and expressly communicated election would ordinarily
need to be shown for an affirmation to be made out during that time. But if
the circumstances were such that there was no reasonable likelihood of the
breach being remedied, account properly could be taken
(a) of that thirty-two
day period in determining when after it a reasonable time to make an election
had passed; and (b) of the
significance of acts of performance done in that
period in considering whether they led to a later election.
636 In the present case, the evidence does not suggest that BHP-IT gave any
indication that it was likely at all to resile from the
position it stated in
Mr Brent's 21 March 1996 letter. BHP-IT confirmed as much in a letter to GEC
Marconi of 3 May 1996. And on
5 May it wrote to GEC Marconi requiring it to
comply with and complete its obligations under the Sub-Contract. I am prepared
to
infer that GEC Marconi had no reasonable expectation of BHP-IT to the
contrary. In these circumstances, account properly can be
taken of the passage
of time from 3 April 1996 and of the acts done since then in determining
whether the point had been reached
by early June 1996 where GEC Marconi's
conduct became unequivocal and was justifiable only on the basis of an election
to affirm.
637 The period from 3 April onwards was one in which claims of breach or,
alternatively requests to perform, passed between the parties.
That state of
affairs did not abate prior to termination of the Sub-Contract. In that
climate of dispute in the period to early
June 1996 BHP-IT could not have
reasonably expected that GEC Marconi was no longer continuing to hold it in
breach on account of
the non-payment of Milestone 4000. Nonetheless GEC
Marconi's continuing conduct in relation, in particular, to the TRR reviews
from
April 1996 until the 6 June TASDD review meeting was such as to evince an
intention to keep the contract on foot at some time between
late April and the
beginning of June. Absent a notice of termination shortly after the expiry of
the thirty-two day remedying period,
that conduct was only justifiable if such
an election had been made. In saying this I appreciate that there were other
matters besides
the non-payment of Milestone 4000 which GEC Marconi was
continuing (mistakenly) to assert constituted breaches. But it was not open
to
GEC Marconi to act inconsistently by joining in the continuing performance of
the contract while purporting to "keep warm" its
power to terminate. The
continuation of the TRR review after 3 April brought about the need to make an
election. And that election
was made by conduct that was not "consistent with
the reservation of a right to terminate": Immer (No 145) Pty Ltd,
above, at 30.
638 I would make this additional comment. Having activated the cl 40.8
termination provisions, GEC Marconi was required after
the expiry of the
thirty-two day period of grace to indicate with reasonable promptness what was
the election it intended to make.
Though it is unnecessary for me to express a
concluded view on the matter, I consider that such a requirement is implicit in
a clause
structured in the fashion of cl 40.8 and cl 40.9. What GEC
Marconi could not do was leave BHP-IT caught in a state of
uncertainty. It
could not speculate at BHP-IT's risk. Clauses such as cl 40.8 simply are
not designed to hold the party in
breach in continuing suspense, not knowing
whether their further performance will, or will not, be rendered fruitless in
the event.
GEC Marconi purported to do this for a period of eight months from
3 April 1996.
639 On the dual assumptions I have been making for the purposes of this
submission, an election to affirm was made prior to the service
of the second
Notice of Breach. The non-payment of Milestone 4000 no longer furnished a
breach that could attract the termination
provisions of the Sub-Contract.
8. GENERAL DEFENCE
640 BHP-IT has pleaded that in serving the three Notices of Breach, GEC Marconi
breached its implied duty of good faith and fair
dealing. It has not, though,
relied on that breach to attack the efficacy of the termination itself. Rather
that breach is advanced
in BHP-IT's cross-claim against GEC Marconi as evidence
of repudiatory conduct, a matter considered later in these reasons: see
Part
III: The Repudiation Claim.
641 A distinct general defence, nonetheless, has been raised to challenge the
termination. It is based on the proposition that,
in order to exercise an
election to terminate for breach, the electing party must be able to establish
that it was capable of performing,
and willing to perform, the contract at the
time. GEC Marconi, it is said, was not so capable and willing. For its part,
GEC Marconi
disputes the applicability to its express power to terminate of the
proposition relied upon.
642 Given the conclusions I have already arrived at as to why GEC Marconi's
claim must fail, I consider it unnecessary to do more
than note that this was
yet another defence raised to that claim.
9. PECUNIARY RELIEF/DAMAGES
643 In light of the number and range of grounds upon which GEC Marconi's
principal claim must fail, I do not intend to engage in
the process of
assessing the pecuniary relief/damages to which it would have been entitled had
it been successful. That would add
appreciably to what already are lengthy
reasons for judgment.
644 However, there are two particular matters to which I consider it is
appropriate to refer. One relates to the nature of the claim
for relief
prosecuted by GEC Marconi. The other involves the proper construction of a
provision of the Sub-Contract (cl 38)
that imposed a "damages cap" on the
designated liabilities of the parties.
(1) The Nature of the Claim Made
645 The Sub-Contract, as will be seen later in these reasons, was manifestly a
losing contract: see Part III: The Repudiation Claim.
For this reason
GEC Marconi sought to frame its case, as best it could, in restitution and not
for contractual relief by way of damages.
It put its claims in the
alternative.
646 The first basis was that, the contract having been terminated, it could
recover in a quantum meruit claim the reasonable cost
to it of performing the
work it had performed under the Sub-Contract, the contract price not providing
a ceiling to the amount recoverable.
This way of putting the claim was based
upon the decisions in Renard Constructions (ME) Pty Ltd v Minister for
Public Works (1992) 26 NSWLR 234 and Iezzi Constructions Pty Ltd v
Watkins Pacific (Qld) Pty Ltd [1995] 2 Qd R 350.
647 The alternate basis of the claim is that, as GEC Marconi had achieved
Milestones 1000, 2000, 3000 and 4000, it was entitled to
be paid for them.
Additionally, it could recover in quantum meruit for work performed after it
achieved Milestone 4000 until the
Sub-Contract was terminated.
648 Distinct from the above alternatives, a contractual claim for damages was
made to recover lost commercial benefits, the relevant
benefits being those
that would otherwise have accrued from performance of the Sub-Contract itself.
This claim is said to have been
based on Commonwealth of Australia v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64.
649 BHP-IT has disputed all of the claims made. It denies that a quantum
meruit claim is available because, in the circumstances,
BHP-IT did not accept
or receive any benefit from the work performed so that there was no unjust
enrichment. And unjust enrichment
underpins this claim in Australian law:
Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221. As to the
milestone payments, it contends that payment has already been made for
Milestones 1000, 2000 and 3000.
That BHP-IT drew upon the unconditional
guarantees given to cover those payments - a matter considered later in these
reasons:
see "The Call on the Financial Securities", below; does not alter
this. It simply means that if the calls were wrongly made that
money had to be
returned. Finally the damages claim for lost commercial benefits is attacked
on both legal and factual grounds.
650 The aspect of these various claims and defences upon which I consider it
appropriate to comment, relates to the quantum meruit
alone and to the
milestones plus quantum meruit claims. The comments that I make are subject to
this reservation. I have not been
addressed on the first of the two matters to
which I will refer, although GEC Marconi has properly adverted to it in
response to
issues I raised in oral submissions. For this reason my
conclusions must be considered tentative ones. The two matters are (i)
to what
extent, if at all, was quantum meruit an available remedy on termination of
this Sub-Contract at the time it was terminated; and (ii) assuming it
was an available remedy, what were the limits of the relief it could provide in
the circumstances?
(i) Was quantum meruit an available remedy?
651 It is trite law that when a contract is terminated under a termination
clause or at common law, both parties are discharged from
the further
performance of the contract but that rights are not divested or discharged
which have already been unconditionally acquired
unless the contract provides
to the contrary: McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 CLR 457
at 476-477; Westralian Farmers Ltd v Commonwealth Agricultural Service
Engineers Ltd [1936] HCA 6; (1936) 54 CLR 361 at 379-380; Hyundai Heavy Industries Co
Ltd v Papadopoulos [1980] 1 WLR 1129; Carter and Harland, Contract Law
in Australia, [2225] (4th ed). So, for example, a right to be
paid a liquidated sum under a contract which has accrued unconditionally before
termination
is recoverable after termination: eg Westralian Farmers
Ltd, above.
652 In the present case the contract price was defined to be:
"the total amount payable by the Customer to the Contractor under this Contract for CSE supplied by the Contractor up to the [Actual Acceptance Date] of the Developed Software and specified in Schedule 4 and includes any price variations as a result of amendments to this Contract."
653 Schedule 4 described the seven milestones, their respective
"deliverables" and the differing sums payable in respect of each.
Clause 3 of
the Sub-Contract made those prices firm for the delivery period set out in
Schedule 8. That Schedule prescribed the
different dates upon which the
relevant deliverable was to be "Submitted to Customer", though the actual
acceptance date for the
deliverables for Milestones 2000, 3000 and 4000 was
stated to be the date of achievement of Milestone 5000. Clause 16 of the
Sub-Contract,
as has been seen, provided the machinery for payments that were
due on achievement of a milestone.
654 For the purposes of highlighting the issue to which I wish to draw
attention, I will assume that (i) the rights to receive the
payments for
Milestones 1000 to 3000 were unconditional in the circumstances; and (ii) the
right to payment for Milestone 4000 had
been acquired unconditionally in that
on completion of TRR it had become due: see Hyundai Heavy Industries Co Ltd
v Papadopoulos, above: cf Carter, Breach of Contract, [1239]ff
(2nd ed). In making this assumption I emphasise that, for present
purposes, the party that has failed to perform is not GEC Marconi,
but is
BHP-IT and that the obligation to perform Milestone 5000 has been discharged on
termination. I equally have not overlooked
that, in an alternative submission,
GEC Marconi has contended that the Sub-Contract was an "entire contract": on
which see Phillips v Ellinson Brothers Pty Ltd, above, 233ff per Starke
J; Baltic Shipping Co v Dillon [1993] HCA 4; (1993) 176 CLR 344 at 350; Carter and
Harland, Contract Law in Australia, [1822]ff (4th ed);
Chitty on Contracts, vol 1, para 22-027ff (28th ed);
Butterworths, The Law of Contract, §7.45 (1999); and note the
"advances clause" (cl 10) in Hyundai Heavy Industries Co Ltd,
above, at 1131. The question whether the contract was an "entire" one is dealt
with later in these reasons: see Part II: The
Call on Financial Securities.
I would also note that BHP-IT has submitted, without enlarging on it, that the
Sub-Contract provided
for GEC Marconi's entitlement to payment for work done
and that this remained on foot after termination which only discharged future
performance.
655 Turning now to restitutionary claims, it is equally well accepted law, to
use the language of Mason P in Trimis v Mina [1999] NSWCA 140 at [54]
which I respectfully adopt, that:
"The starting point is a fundamental one in relation to restitutionary claims, especially claims for work done or goods supplied. No action can be brought for restitution while an inconsistent contractual promise subsists between the parties in relation to the subject matter of the claim. This is not a remnant of the now discarded implied contract theory of restitution. The proposition is not based on the inability to imply a contract, but on the fact that the benefit provided by the plaintiff to the defendant was rendered in the performance of a valid legal duty. Restitution respects the sanctity of the transaction, and the subsisting contractual regime chosen by the parties as the framework for settling disputes. This ensures that the law does not countenance two conflicting sets of legal obligations subsisting concurrently. As Deane J explained in the context of the quantum meruit claim in Pavey & Matthews (at 256), if there is a valid and enforceable agreement governing the claimant's right to payment, there is "neither occasion or legal justification for the law to superimpose or impute an obligation or promise to pay a reasonable remuneration". See also Update Construction at 275n; Ansett Transport Industries (Operations) Pty Ltd v Alenia Aeritalia & Selenia Spa (1991) 105 FLR 169; Brenner v First Artists Management Pty Ltd [1993] 2 VR 221. This principle is applicable to other restitutionary claims (see, eg Foran v Wight [1989] HCA 51; (1989) 168 CLR 385 at 413, 432; Baltic Shipping Co v Dillon (The Mikhail Lermontov) [1993] HCA 4; (1993) 176 CLR 344 at 355-6, 385)."
656 The issue this raises is whether, if the rights to be paid for the four
milestones had accrued, was there either "occasion [or]
legal justification":
Pavey & Matthews Pty Ltd v Paul, at 256; for a quantum meruit claim
for the services to which those accrued rights to be paid related? On the
various assumptions
I have been making, the answer would appear to be "no".
Payment for Milestones 1000 to 3000 had already been made pursuant to the
Sub-Contract and the right to be paid for Milestone 4000 had accrued
unconditionally before termination. Payment for that Milestone
would be a
contractual matter: cf Bank of Boston Connecticut v European Grain and
Shipping Ltd [1989] 1 AC 1056 at 1098-1099; and not a matter of quantum
meruit: Chitty on Contracts, vol 2, para 37-160 (28th ed);
Farnsworth, Contracts, 858 and 571ff. This conclusion, which seems to
me to be a principled and appropriate one and one which GEC Marconi seems to
have
had in mind in its alternate quantum meruit claim, has the following
consequences.
657 First, it gives greater significance to the different consequences of
termination and rescission respectively for the purposes
of quantum meruit
claims than has been assumed to be the case in light of Renard Constructions
(ME) Pty Ltd v Minister for Public Works, above and Iezzi Constructions
Pty Ltd v Watkins Pacific (Qld) Pty Ltd, above. Secondly, insofar as it is
premised upon the proposition that the right had accrued in consequence of the
necessary performance
having been rendered to acquire that right, it is
consistent with the majority view in the United States to the extent that
restitutionary
claims are not permitted to a party who "has fully ... performed
and all that remains due for him is a liquidated sum of money":
Dobbs, Law
of Remedies, vol 1, 650 (2nd ed); Farnsworth, Contracts,
858 (3rd ed); Palmer, Law of Restitution, §4.3;
Restatement of Contracts, Second, §373(2). It may well be
inconsistent with the majority view in the United States if that view would
limit the above restriction
on restitutionary claims to cases of full
performance of a contract: see eg Boomer v Muir 24 P 2d 570 (1933);
but cf to the contrary Restatement of Contracts, Second, §373
Comment (d) and §240; Farnsworth, Contracts, 858 and 571ff. The
United States view in any event has owed much to the proposition that
termination for repudiation or material
breach effected a rescission ab initio:
see Renard Constructions (ME) Pty Ltd, at 277; but see more generally
Palmer, above, §4.6.
658 A quite distinct question may arise in the present case in relation to
Milestone 4000. If it was the case that TRR was achieved
by GEC Marconi but,
by agreement or waiver, at a time earlier than that envisaged by the contract:
see the SDP Defence, above; there
would remain the question whether the
performance for which the payment was made included that work which the SDP
presupposed would
be done prior to TRR but which had not been done by GEC
Marconi. (The SDP did not envisage TRR being held until the end of Integration
Testing.) In such a case, would GEC Marconi's right to receive Milestone 4000
preclude a quantum meruit claim for work done after
the right in fact accrued
but which was work which was to be done prior to the time contractually
scheduled for TRR? Would such
a claim allow GEC Marconi "to recover more than
once for the same loss"?: see Baltic Shipping Co v Dillon (1993),
above, at 355.
659 I have considered it necessary to raise the above questions as it may
be the case that, in the circumstances, GEC Marconi had no entitlement to
bring a restitutionary claim at all.
(ii) The Limits of Quantum Meruit
660 "The conventional view is that it is unjust enrichment which gives rise to
the obligations of restitution": Roxborough v Rothmans of Pall Mall
Australia Ltd [2001] HCA 68; (2001) 185 ALR 335 at 354; see also Commissioner of State
Revenue (Victoria) v Royal Insurance Australia Ltd [1994] HCA 61; (1994) 182 CLR 51 at 75.
On the assumption that quantum meruit was a remedy available to GEC Marconi,
BHP-IT has taken its stand on
this view. It asserts that, as a factual matter,
it derived no actual benefit from the work performed; it was not in
consequence
unjustly enriched; hence there should be no restitutionary
relief.
661 The weight of authority would not permit me to accede to this submission in
such a bald form: see the cases collected in Mason
and Carter, Restitution
Law in Australia, [1166]ff. A party in breach may be deemed to have
received a benefit where it has received part of the agreed or requested
return:
see Brenner v First Artists' Management Pty Ltd [1993] 2VR 221
at 256ff. In any event, the performance received in respect of the first three
milestones enabled BHP-IT in turn to
receive its milestone payments under the
Head Contract.
662 Perhaps the more significant point to the attack relates to how the value
of the services performed are to be assessed. The
Sub-Contract was a losing
one and this is of present significance. It has long been recognised that in
such cases a quantum meruit
claim can result in a recovery that far exceeds
what the innocent party would have derived had the contract been performed.
Importantly,
the stipulated contract price provides no ceiling to what can be
recovered: Slowey v Lodder (1901) 20 NZLR 321; affd Lodder v Slowey
[1904] AC 442; Palmer, Law of Restitution, §4.4. It equally
has long been recognised that "it is difficult to see why breach, which saves
the plaintiff further loss,
should be grounds for recovery of a greater sum
[than the contract price]": Dobbs, Law of Remedies, vol 3,
§12.7(5) (2nd ed). Criticism of this outcome, particularly in
this country, has not abated: see Carter and Harland, Contract Law in
Australia, [2339] (4th ed); Carter, "Discharged Contracts:
Claims for Restitution" (1997) 11 JCL 130. As is said in Mason and Carter,
Restitution Law in Australia, at [1430]: "There is ... little to be
said in principle or policy for a rule which provides a clear incentive to
manufacture or
snatch at repudiation as a means of escaping a bad bargain".
663 All that I wish to note here is that BHP-IT has in its submissions
challenged directly the decisions in Renard and, inferentially,
Slowey v Lodder (1901) 20 NZLR 321; affd Lodder v Slowey [1904]
AC 442, for their disregard of the contract price.
664 Distinctly, BHP-IT has challenged the basis upon which GEC Marconi invites
me to assess the fair value of the work it performed.
That basis, derived from
Renard at 276-277, was "the reasonable cost [to the contractor] of the
work he had done and the money he has expended". That proposition,
I would
note, is but one of the ways in which the courts have formulated how "fair
value" or "fair remuneration" is to be assessed:
for a helpful summary see
Brenner's case, above, at 262-264; see also Mason and Carter, above,
[1415]ff.
665 On the facts of the present case, BHP-IT submit in effect that the
Renard principle would compensate GEC Marconi for its loss (of which, it
is said, it was in large degree the author) but without regard to
the value of
its work in terms of its quality and utility to BHP - IT and the
Commonwealth. In this manner the submission
obliquely challenges the modern
rationale of the quantum meruit claim. If it is founded on unjust enrichment
which must be disgorged,
then that enrichment cannot be assessed simply by
reference to the reasonable cost to GEC Marconi of the work it performed when
much
of that work done was, it is said, inefficient and ineffective.
666 I have referred to the challenges made by BHP-IT to the current orthodoxy
in quantum meruit claims for this reason. On one possible
view of the facts of
this case (I express no comment on this), those challenges would expose sharply
the obvious lack of coherence
between the modern rationale of quantum meruit
(ie unjust enrichment) and the principles presently employed in giving effect
to it.
(2) The cl 38 "Damages" Cap
667 The value GEC Marconi placed upon its work performed for quantum meruit
purposes was $9,124,012.00. As will be seen, it has
other claims as well
against BHP-IT one of which (for $3,875,000.00) relates to BHP-IT's wrongful
call upon bank guarantees supplied
by GEC Marconi as security under the
Sub-Contract.
668 Clause 38 of the Sub-Contract, insofar as presently relevant provided:
"38.1 The liability of a Party for breach of this Contract, or in tort, or for any other common law or statutory cause of action arising out of the operation of this Contract, shall be determined under the relevant law in Australia that is recognised, and would be applied, by the High Court of Australia.
...
38.3 The aggregate liability of a Party under this Contract, in respect of actions described in subclause 38.1 shall except in relation to liability:
(a) for personal injury (including sickness or death) which shall be limited to $40,000,000;
(b) for loss of, or damage to, tangible property which shall be limited to $40,000,000;
(c) under an indemnity provided by a Party under clause 28 of this Contract which shall be limited to $10,000,000; or
(d) under an indemnity provided by a Party under clause 36 of this Contract which shall be limited to $40,000,000;
be limited to an amount equal to $8,600,000."
669 GEC Marconi contends that this provision does not apply either to its
quantum meruit claim or to its claim in respect of the bank
guarantees. As
different reasons are given for these results they need to be treated separately.
(i) The quantum meruit claim
670 GEC Marconi submits that the critical words in cl 38 are the words
"under this Contract" in cl 38.3. And it is contended
that they qualify
the words "aggregate liability" so that the opening words of cl 38.3 could
be recast as "The aggregate liability
under this Contract of a party, in
respect of actions described in Sub-Clause 38.1 shall ...". So read, for a
liability to be caught
by the "cap", it must be a liability "under" the
contract, ie it must be a liability "created by, in accordance with, pursuant
to
or under the authority of" the Sub-Contract: cf Chan v Cresdon Pty Ltd [1989] HCA 63;
(1989) 168 CLR 242 at 249. If the words "under this Contract" were treated
as qualifying the immediately preceding word "Party",
those words, it is said,
would be superfluous and the word "under" inapt in that one does not naturally
speak of a party under a contract as opposed to a party to
a contract. A quantum meruit claim is not a liability under contract:
Pavey & Matthews Pty Ltd v Paul, above. It is an autonomous
liability.
671 BHP-IT submissions, with which I agree, are that cl 38.1 identifies
the liabilities to which cl 38.3 is intended to
apply: ie "breach of this
Contract, ... or for any ... cause of action arising out of the operation of
this Contract". Taken as
a whole the expression in cl 38.3 - "The
aggregate liability of a Party under this Contract in respect of actions
described
in subclause 38.1" - refers to the limitation of liability imposed by
the sub-clause. That expression does not impose a requirement
that the "cause
of action must be under this Contract". If it did it would rob the words "in
respect of actions described in subclause
38.1" of their intended meaning.
672 Agreeing as I do with the BHP-IT submission, I need add little. The
reference in cl 38.3 to actions described in sub-clause
38.1 encompasses
actions for breach of contract and causes of action in tort, at common law or
under a statute, that arise out of the operation of the Contract. It is
that nexus with the Contract that makes such actions the subject of contractual
regulation. But it would be anomalous in my
view for all such actions to be
regulated by cl 38.1 for its purposes, while only a small sub-class of
them were to be regulated
by cl 38.3. If "under" has the meaning in this
setting that is ascribed to it by GEC Marconi, it is difficult to see how a
common law action, let alone a statutory one, could be said to give rise to a
liability "under this Contract". The use of the word
"under" in cl 38.3
may have been infelicitous. But the intent of the sub-clause in its setting is
clear enough. It was to
apply the limitation of liability to all of the
actions referred to in cl 38.1. The relevant liability had to "arise out
of
the operation of this Contract". It did not have to arise "under" it. If
one was to ascribe a separate meaning to the words "under
this Contract"
(rather than treating them as part of a composite expression which conveys its
own meaning), that meaning would probably
best be equated with "for the
purposes of this Contract".
(ii) The calls on the bank guarantees
673 Clause 17(2) of the Sub-Contract required GEC Marconi to provide security
from an approved guarantor in the form of an unconditional
financial
undertaking ("the Financial Security"). It was to be substantially in the form
prescribed in Schedule 13 and to be provided
in accordance with Table 8.3 of
Schedule 8. Three such guarantees were given in respect of Milestones 1000,
2000 and 3000.
674 Clause 41 of the Sub-Contract indicated the circumstances in which BHP-IT
could have resort to the Financial Security consequent
upon a breach of
contract by GEC Marconi.
675 GEC Marconi accepts that no issue arises in relation to the cap if BHP-IT's
conduct in calling on the Financial Securities was
lawful. If it was not it
would, for cl 38(3) purposes, have constituted at least a breach of
contract (ie of cl 41).
Any other possible cause of action arising from
the call down would likewise be one "arising out of the operation of [the]
Contract":
cl 38.1. And so any positive claim against BHP-IT for such a wrong
to recover the $3,875,000 would on its face be caught by the
cl 38.3
cap.
676 GEC Marconi seeks to avoid this consequence by submitting that, in the
circumstances, BHP-IT was precluded from raising the cl 38.3 cap in
respect of any claims made by GEC Marconi concerning the Financial Securities.
The practical
effect of BHP-IT's action in calling on the guarantees would be
to reduce the limit for GEC Marconi's claims from $8,600,000 to $4,725,000.
It
is of this effect that GEC Marconi complains.
677 The bases of this preclusion seem to be, first, that to allow BHP-IT to
rely upon the cap would be to allow it to profit from
its own wrong; and,
secondly, it would be unconscionable to raise the cap, BHP-IT having no
reasonable basis for resorting to the
guarantees. I would note that there is
no pleaded or positively asserted claim of estoppel as such.
678 The first of these - profiting from one's own wrong - is clearly
unsustainable. It amounts to no more than an assertion that
a wrongdoer is
better off who can attract the benefit of a cap, than is a wrongdoer who
cannot.
679 The second basis depends first and foremost on a factual finding of
unconscionable conduct, whatever the juridical basis for
such a finding may
happen to be in this setting. I deal with the substantive claim made by BHP-IT
later in these reasons: see "The
Call on the Financial Securities", below. I
merely note here that I do not find BHP-IT to have engaged in unconscionable
conduct.
Hence the asserted preclusion, whatever its basis, lacks
foundation.
680 I would note finally, that GEC Marconi has not pleaded or asserted that, in
calling on the Financial Securities, BHP-IT breached
its implied duty of good
faith and fair dealing; that the call was ineffective; and that the money
received by BHP-IT was recoverable
as money had and received to GEC Marconi's
use.
10. THE SUBSIDIARY CLAIMS
681 Four additional and discrete claims have been made by GEC Marconi. These
are claims for loss suffered because:
(i) BHP-IT wrongfully called upon the bank guarantees for $3.875M provided by
GEC Marconi as security under the Sub-Contract;
(ii) BHP-IT wrongfully converted the STUBS emulator after the Sub-Contract was
terminated;
(iii) BHP-IT repudiated the Standing Offer Agreement in respect of DPSI panel
services;
(iv) BHP-IT has failed or refused to pay GEC Marconi delay and prolongation
costs required by the Sub-Contract.
11. THE CALL ON FINANCIAL SECURITIES
682 Clause 41 of the Sub-Contract provided, insofar as presently relevant,
that:
"Any damages, liquidated damages, losses, costs and expenses recoverable by the Customer from the Contractor in consequence of the Contractor's breach of this Contract may be deducted from the Financial Security."
683 GEC Marconi contends that if it was entitled to terminate the
Sub-Contract on 10 December 1996 (contrary to my finding), it was
not lawful
for BHP-IT to make calls on the guarantees on 29 January 1996 and GEC Marconi
could take proceedings for the recovery
of those calls subject to the possible
application in the circumstances of the cl 38(3) cap. Alternatively, if,
as I have held,
GEC Marconi's termination was ineffective, BHP-IT could call on
the guarantees if the requirements of cl 41 were satisfied.
GEC Marconi
submits that they were not on either of two grounds. The first is that for
damages, etc, to be recoverable under the
clause, recoverability had first to
be demonstrated either by a declaration to that effect or by an arbitral award:
Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd
(1998) 15 BCL 158. The second is that if it was sufficient merely to make
a demand for a disputed amount, no bona fide claim could
have been made for the
full amount of the guarantees and BHP-IT has not attempted to demonstrate its
demand was bona fide.
684 The first of the alternative submissions above is, in substance, a claim of
breach of contract against BHP-IT. BHP-IT's response
to it is that the sums
recovered under the three guarantees were in the amounts paid to GEC Marconi
for Milestones 1000-3000. The
contract having lawfully been terminated by
BHP-IT those sums were recoverable from GEC Marconi as they were paid to it
subject to
acceptance of the contract deliverables on achievement of Milestone
5000: Schedule 8, Table 8.1.
685 BHP-IT's response opens up what is a recurrent issue in this proceeding. I
briefly referred to it in the context of GEC Marconi's
quantum meruit claim.
It reappears later in these reasons in one of the Commonwealth's defences to
GEC Marconi's claims for delay
and prolongation costs: see below "The Delay
and Prolongation Claim (c) The Defences". That issue is in substance whether
the achievement
of Milestone 5000 was a condition of the payments made to GEC
Marconi for Milestones 1000 to 3000. BHP-IT's submission here, as
also the
Commonwealth's in relation to the delay and prolongation claim, is that the
Sub-Contract was one containing an "entire obligation":
cf Baltic Shipping
Co v Dillon (1993), above, at 350; which required the delivery of the
Canberra System Developed Software at Milestone 5000 as a condition precedent
to the payment of the earlier milestones becoming irrevocable, ie those
milestones were only earned upon achievement of Milestone
5000. This somewhat
arresting result is said to be ordained by the terms of the Sub-Contract.
686 Because this submission does raise a recurrent issue in this proceeding I
will, as a matter of convenience, deal with it in this
particular setting.
However, as I will later indicate, I consider that there is a short answer in
any event to GEC Marconi's claim.
Before turning to the "entire obligation"
submission it is necessary to refer at a little length to the terms of the
Sub-Contract.
(a) The Contractual Setting
687 A significant number of provisions of the Sub-Contract bear on the question
of construction raised by BHP-IT's submissions.
Some have already been
referred to at some length and will only be repeated here in précis
form.
688 The Sub-Contract contained a definition of "Contract Price". It was:
" "Contract Price", means the total amount payable by the Customer to the Contractor under this Contract for CSE supplied by the Contractor up to the [Actual Acceptance Date ("AAD")] of the Developed Software and specified in Schedule 4 and includes any price variations as a result of amendments to this Contract."
Schedule 4 cl 7 specified the "Contract Price" for the CSE by reference to
a table (Table 4.2) that replicated three of the
six columns of Table 8.1 of
Schedule 8 ("The Implementation Plan") that is set out (partially) below. The
three columns of Table
4.2 were headed respectively "Deliverable Reference
Ident", "Deliverable Description" and "Payment Amount (AUD)". The items
referred
to under these headings were respectively, the seven milestones
(Milestone 1000 to 7000), the descriptions of the seven milestone
deliverables
and the price to be paid for each of those seven deliverables.
689 Clause 3 of the Sub-Contract made the prices set out in Schedule 4 firm for
the delivery period set out in Schedule 8. Clause
1.1 of Schedule 8 was in the
following terms:
"1. DELIVERABLES SCHEDULE AND PAYMENT PLAN
1.1 Table 8.1 below sets out the planned Contract Acceptance Dates for the project deliverable's (as described in the Scope of Work contained in Schedule 9), and the payment plan."
690 Table 8.1 has been set out in full above: see "Non-Payment for Milestone 4000". It is necessary to refer again to its format, though only in part. It is sufficient that I refer only to the first two milestones:
Deliverable Reference Ident |
Deliverable Description |
Customer's Responsibility |
Date Submitted to Customer |
Contract Acceptance Date |
Payment Amount (AUD) |
1000 |
Project Mobilisation |
Nil |
Not Applicable |
Contract Signature |
1 250 000 |
2000 |
Preliminary Design Review |
08/11/94 |
Subject
to acceptance on achievement of milestone 5000 |
1 250 000 |
Milestones 3000 ("Critical Design Review") and 4000 ("TRR") each had the same
typed entry under the heading "Contract Acceptance
Date" as that emphasised
above. Those entries are crucial to BHP-IT's submission.
691 I would note in passing that the interpretation clause of the Sub-Contract
stated that:
"Contract Acceptance Date" in relation to the Developed Software means the date set out in the Project Plan and the Implementation Plan by which the Acceptance Tests for the Developed Software are to have been completed."
692 Clause 10.1 required BHP-IT and GEC Marconi to perform their obligations
in accordance with (inter alia) the Schedule 8 Implementation
Plan.
693 When dealing with "Non-Payment of Milestone 4000" I set out the relevant
provisions of cl 16 that dealt with the making
of "progress payments in
accordance with the milestone payment schedule". I have already indicated my
view that the clear contemplation
of cl 16, when read in light of Schedule
8, was that a contracted milestone became due when the requirements of that
milestone
had been met. The additional comment I would make is that there is
nothing on the face of cl 16 to indicate that a payment
made in accordance
with its procedures might nonetheless be conditional or refundable: cf
Hyundai Heavy Industries Co Ltd v Papadopoulos [1980] 1 WLR 1129 at
1131.
694 There are three additional contractual matters to which I should refer.
The first relates to liquidated damages. By virtue of
cl 39 and of
Schedule 8, where Acceptance Tests were not successfully completed for
Milestone 5000, liquidated damages were
payable at the rate of $2000 per day.
No liquidated damages were payable for delay in relation to any of the earlier
milestones.
695 Secondly, the Financial Security. Sub-clauses 17.2 and 17.5 provided:
"17.2 The Contractor shall provide security in the form of an unconditional and irrevocable financial undertaking ("the Financial Security") from a guarantor approved by the Delegate. The Financial Security provided shall be in a form acceptable to the Delegate and substantially in the form appearing in Schedule 13 and shall be provided in accordance with Table 8.3 of Schedule 8.
...
17.5 Upon the issue of the Certificate of Acceptance for the Canberra system the Delegate shall release the Financial Security within 7 days by notifying the Contractor that the Financial Security is no longer required."
696 Schedule 3 of the Sub-Contract carried forward the provisions of cl 17. It was in the following terms:
"Unconditional Financial Undertaking (subclause 17.1)
The Contractor is required to provide Unconditional Financial Undertakings in respect of progress payments made. The amounts and the timing of the undertakings shall be determined in accordance with Table 8.3 of Schedule 8."
697 Table 8.3 of Schedule 8 required four financial guarantees to be given.
One was for each of the first four milestones and was
to be given at the time
the respective milestone was achieved and in the sum of that milestone's
payment.
698 Clause 41 of the Sub-Contract stipulated:
"Any damages, liquidated damages, losses, costs and expenses recoverable by the Customer from the Contractor in consequence of the Contractor's breach of this Contract may be deducted from the Financial Security or money then due to the Contractor under this Contract and if that Financial Security or money is insufficient for that purpose, the balance remaining unpaid shall be a debt due by the Contractor to the Customer and may be:
(a) set off against any other money due to the Contractor by the Customer under this Contract; or
(b) recovered from the Contractor by the Customer in any Court of competent jurisdiction."
699 The Financial Securities given by Banque Nationale de Paris in this case were in the form of the deed prescribed by Schedule 13. That form included the following clauses:
"1. The Guarantor unconditionally undertakes and covenants to pay to the Customer on demand without reference to the Contractor and notwithstanding any notice given by the Contractor to the Guarantor not to pay same, any sum or sums which may from time to time be demanded in writing by the Customer to a maximum aggregate sum of $
2. The Guarantor's liability under this Undertaking shall be a continuing liability and shall continue until payment is made under this Undertaking of the said maximum aggregate sum or the Customer notifies the Guarantor that this Undertaking is no longer required."
700 Thirdly, cl 18 of the Sub-Contract required that an approved third
party provide a guarantee for the performance of GEC Marconi's
obligations and
the discharge of its liabilities under the contract. Such a performance
guarantee was given by GEC Marconi Australia
Pty Ltd. As will be seen, it is a
subject of BHP-IT's first cross-claim.
(b) Applicable Principles: an Entire Contract/Entire Obligation
701 The drafting of modern contracts dealing with projects of any size and
complexity has diminished the significance of the question
whether a contract
is an entire one. The principles that bear on that question are of quite some
antiquity: see eg Hyundai Heavy Industries Co Ltd v Papadopoulos [1980]
1 WLR 1129 at 1131. For present purposes I would note the following.
702 (i) An entire contract, or an entire obligation, is one in which, or in
relation to which, the consideration for the payment
of money or the rendering
of some other counter performance is entire, indivisible and not severable:
Baltic Shipping Co v Dillon, above, at 350; Steele v Tardiani [1946] HCA 21;
(1946) 72 CLR 386 at 401; Phillips v Ellinson Brothers Pty Ltd [1941] HCA 35;
(1941) 65 CLR 221 at 233ff.
703 (ii) If a contract or an obligation is entire its complete performance is a
condition precedent to payment or counter performance:
Phillips v Ellinson
Brothers Pty Ltd, above; Hoenig v Isaacs [1952] 2 All ER 176 at
181; see Cheshire and Fifoot, Law of Contract, para 26.13
(8th Aust ed). The court has no power to apportion the
consideration which, in the case of money, is thus regarded as a "lump sum":
see
generally Chitty on Contracts, vol 1, para 22-030 (28th
ed).
704 (iii) The question whether a contract or an obligation is entire or is, in
contrast, divisible, is a question of construction:
Ownit Homes Pty Ltd v
Batchelor [1983] 2 Qd R 124; Hoenig v Isaacs, above. While
building contracts (which have significant similarities with the present type
of contract) have commonly been regarded,
prima facie, as entire or "lump sum"
contracts: see Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol)
Ltd [1974] AC 689 at 717; Chitty on Contracts, vol 2, para 37-139
(28th ed); and see Halsbury's Laws of Australia, vol 3(2)
"Building and Construction", 65-1255; such contracts commonly provide to the
contrary by, for example, apportioning the
consideration: eg Walsh v
Kinnear (1876) SCR(NSW) 434; but cf Hyundai Heavy Industries Co Ltd v
Papadopoulos [1980] 1 WLR 1229 where the contract provided both for the
payment of instalments and for their refund if the contract was cancelled
in
specified circumstances. As was said in the first edition of Halsbury's
Laws of England, vol 3, §458-459:
"458. The large expenditure which builders and contractors have to incur in carrying out the works which they have undertaken to construct renders it usual for the contract to provide for payments on account of the price during the construction of the works. The manner in which these payments on account are regulated varies according to the terms of the contract. Sometimes the several instalments become due on the completion of particular stages of the work ... ; sometimes the interim payments are to be not less than a fixed sum .. ; or, again, at fixed periods, irrespective of amount ... .
...
459. Whichever method is agreed upon as that in accordance with which payment is to be made, nothing becomes due to the contractor until he has done everything to entitle him to receive payment. Each certificate for an instalment creates a debt due, and the contractor is entitled to immediate payment thereof subject to the terms of the contract and any right of the employer to any set-off or counterclaim damages."
705 (iv) The usual rule in relation to instalment payments is as stated above: see also Brooking on Building Contracts, [4-16] (3rd ed); Keating on Building Contracts, 4-06, 4-17 (7th ed); Unidroit, Principles of International Commercial Contracts, Art 6.1.4, Comment 2; Farnsworth, Contracts, 564 (3rd ed). Once the right to payment has accrued it is enforceable as a debt: Pickering v Ilfracombe Railway Co (1868) LR 3CP 235; and that right is not lost notwithstanding that the contract is subsequently terminated because of the default of the party possessing the right to payment: McLachlan v Nourse [1928] SASR 230 at 233-234; see also Markham v Bernales (1906) 8 WAR 208 (a quantum meruit case). Again as was stated in the first edition of Halsbury (above, at §460):
"Where, after the payment of money to the contractor on account, he fails to complete owing to his own default or abandons the contract without good cause, the employer may be entitled to recover back the instalments paid on the ground that the consideration has wholly failed; but at all events the employer would have a ground of action for a breach of the contract to complete, in which the damages recovered might equal or exceed the amount paid on account."
706 (v) If a contract or obligation is to be found to be entire
notwithstanding that the contract or obligation provides for payment
by
instalments, the contract on its proper construction must indicate that the
instalments are nonetheless conditional upon complete
performance of the
contract or obligation, ie that they are refundable if this does not occur
because of the default of the party
that is to render the performance: cf
Hyundai Heavy Industries Co Ltd v Papadopoulous, above, at 1131.
707 The final comment I would make is that, while I have persisted in using the
term "entire contract", as a matter of convenience,
I recognise the criticisms
that can be made of it: see Chitty on Contracts, vol 1, para 22-027
(28th ed); Corbin on Contracts, vol 3A, §694 ("Entire
and Divisible are Terms of Confusion").
(c) The Obligation to Achieve Milestone 5000
708 The short question raised by BHP-IT's submission is whether all milestones
up to Milestone 5000 had to be achieved before payments
made in respect of any
of those milestones became unconditional, ie were no longer refundable. The
linchpins of the argument that
there was an entire obligation to be performed
by GEC Marconi are (i) the notation in Table 8.1 of Schedule 8 under the
heading "Contract
Acceptance Date" which said "Subject to acceptance on
achievement of milestone (sic) 5000", in relation to Milestones 2000, 3000
and
4000; (ii) the statement in Schedule 3 that the securities are required to be
provided "in respect of progress payments made";
and (iii) the release of the
securities on acceptance of the Canberra System at Milestone 5000.
709 In common with GEC Marconi in its submissions on the like argument of the
Commonwealth in relation to the delay and prolongation
claim, I am satisfied
that this reference in Table 8.1 was a reference to the acceptance date of the
contract deliverables for Milestones
2000 to 4000. It did not relate to, or
precondition in any way, the payments made in respect of those milestones. The
structure
of the Sub-Contract was such that the payments for Milestones 1000 to
4000 were apportioned to particular phases of the work to be
performed. The
"Contract Price" was the aggregate of those payments as apportioned in Schedule
4 (subject to price variations resulting
from contract amendments). Table 8.1
for its part, had two distinct purposes. One was to prescribe planned
"Contract Acceptance
Dates for the project deliverable's (sic)". The other was
to prescribe the "payment plan", Schedule 4 having indicated the amount
of each
of the seven milestone payments but not their respective times of payment.
710 I do not consider that the statement in Schedule 3 linking the financial
securities to the progress payments made assists in
illuminating the present
question. It reflects a convenient device for augmenting the security given as
the contract progressed
and provided protection for cl 41 purposes to that
extent. BHP-IT seeks to make a deal of what is said to be the commercial
reason for that linkage, ie that the progress payments are recoverable if the
Canberra system is not delivered at Milestone 5000.
I am not satisfied that so
significant a commercial reason can be found in the fact of that linkage. The
Schedule 3 statement no
less so than the language of Table 8.1 provides a most
oblique way of achieving a most important effect for the contractors if its
purpose was to evidence an intention to make the obligation an entire one.
711 There has been a desultory debate in this proceeding as to whether the
milestone payments, though made on achievement of designated
work, were in fact
payments in advance. The Commonwealth contends that they were while BHP-IT and
GEC Marconi contend to the contrary.
Whether they were or were not prepayments
is a question of construction that I need not answer, though I would suggest
that the
Schedule 3 statement lends some support for the prepayment
contention.
712 The release of the securities after acceptance of the Developed Software on
achievement of Milestone 5000 did no more than reflect
that the principal
burden of the contract has been performed successfully. The achievement of
Milestone 5000 provided an appropriate
time for the release of the securities
and cl 17(5) said no more than that.
713 The devices employed in the Sub-Contract to protect BHP-IT against the
contingencies of GEC Marconi's delay in, or failure to,
achieve Milestone 5000
were threefold: first, there was the liquidated damages clause that was
activated when the Milestone 5000
Acceptance Tests were not successfully
completed by the relevant "Contract Acceptance Date" specified in Schedule 8;
secondly, there
were the financial securities that were required to be given in
respect of Milestones 1000 to 4000 which could be called upon in
the
circumstances envisaged by cl 41 of the Sub-Contract, and which were to be
released on acceptance of the Canberra System
at Milestone 5000; and thirdly,
there was the performance guarantee obtained from GEC Marconi Australia Pty Ltd
under cl 18
of the Sub-Contract.
714 When one has regard (a) to the payment provisions of cl 16 of the
Sub-Contract which, as I have found, presupposed that
a milestone payment was
due when the requirements of that milestone had been met; and (b) to the
various devices used in the Sub-Contract
to protect BHP-IT against GEC
Marconi's possible delay or default in achieving Milestone 5000, I am satisfied
that, in the absence
of a clear and unambiguous provision to the contrary: cf
Hyundai Heavy Industries Co Ltd v Papadopoulos, above; The Tergeste
[1903] P 26 at 34; the right to be paid for achievement of a milestone
prior to Milestone 5000 was an unconditional right and the
payment so received
was not refundable. The reason I consider a clear and unambiguous provision to
the contrary would be necessary
is because I consider the actual terms and
tenor of the Sub-Contract were quite inconsistent with the obligation of entire
performance
proposed by BHP-IT and the Commonwealth.
715 I am satisfied that, while performance of each particular milestone up to
Milestone 5000, was the condition precedent to the
payment for that milestone
(ie each milestone embodied an entire obligation), performance of all
milestones including Milestone 5000
was not a condition precedent to being paid
unconditionally for achievement of each of Milestones 1000 to 4000. And I
would note
in passing that, given the terms in which Table 8.1 refer to
Milestone 1000, it is not easy to divine the basis upon which achievement
of
that milestone was supposedly made subject to achievement of Milestone 5000.
716 The CSE for Milestones 2000 to 4000 had to satisfy the requirements for
their respective milestone on the dates specified in
Table 8.1. Though the
Contract Acceptance Dates for those deliverables may all have been on the same
date, the matched performance
and payment for each deliverable was separate and
divisible from the matched performance and payment of the other milestones.
The
parties themselves had apportioned payment and, having regard to the
variations in the apportionment, seemingly had done so for agreed
equivalents
as between the performance to be rendered for each milestone and the payment to
be made for that performance: cf Restatement of Contracts, Second,
§240; Farnsworth, Contracts, §8.13 (3rd ed).
717 I reject the submission that Milestones 1000 to 4000 were not earned until
achievement of Milestone 5000. In the present case
GEC Marconi had the right
to receive payment for Milestones 1000 to Milestone 3000 and, on being paid for
them (as it was), it was
not obliged to refund those payments merely because,
by wrongfully terminating the contract, it prevented itself from achieving
Milestone
5000. The milestone payments had been earned.
(d) The Call on the Financial Securities: Principles and Conclusions
718 The financial security that GEC Marconi was obliged by cl 17 of the
Sub-Contract to provide, and the security in fact provided,
was an
unconditional and irrevocable one that was payable on demand to BHP-IT. There
being no question of fraud; cf Edward Owen Engineering Ltd v Barclays Bank
International Ltd [1978] QB 159; and, in my view, no arguable case
of unconscionable conduct on BHP-IT's part, the only limitation on its right to
demand payment would be a contractual provision in the Sub-Contract limiting
that right in some way: see Wood Hall Ltd v Pipeline Authority [1979] HCA 21; (1979)
141 CLR 443 at 459; Hortico (Australia) Pty Ltd v Energy Equipment Co
(Australia) Pty Ltd (1985) 1 NSWLR 545 at 552-553; Reid Construction
Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158; see
also Washington Constructions Co Pty Ltd v Westpac Banking Corporation
[1983] 1 Qd R 179.
719 The Sub-Contract is singularly bereft of any such limiting provision,
though cl 41 does make specific provision as to when recourse may be had
to the security. Simply by demanding payment from the Bank, BHP-IT did not as
such have recourse to the security. It
merely changed its form "from security
by way of a bank document to a cash security": Malaysia Hotel (Australia)
Pty Ltd v Sabemo Pty Ltd (1995) 11 BCL 50 at 58; Australasian
Conference Association Ltd v Mainline Constructions Pty Ltd (in liq) [1978] HCA 45; (1978)
141 CLR 335 at 351. I do not consider that the provisions of cl 17.5
relating to the release of the financial security
requires any qualification of
the view I have expressed. That clause was concerned with the duration of the
obligation to provide
the security. It did not address the form it took:
cf Malaysia Hotel (Aust) Pty Ltd v Sabermo Pty Ltd, above, at 56-57. I
should add that a consequence of the view I take is that, absent proof that
BHP-IT's demand was made in breach
of the duty of good faith and fair dealing,
GEC Marconi had no possible ground for complaint against BHP-IT arising from
its demand
for payment from the bank. No such breach as, in my view been
demonstrated. For this reason I reject GEC Marconi's claim for interest
foregone in consequence of the demand.
720 The sole issue is whether the recourse had by BHP-IT to the security in its
cash form was authorised by cl 41 of the Sub-Contract.
BHP-IT's purported
justification of it was that the three milestone payments were recoverable as
of right by BHP-IT as liquidated
sums because those payments only became
unconditional on achievement of Milestone 5000. I have already rejected
BHP-IT's entire
obligation submission. Nonetheless at the time of recourse to
the cash security, GEC Marconi was in breach of its contract and damages,
etc
were recoverable from it - albeit in a to-be-ascertained amount. Circumstances
thus existed in which the cash security had a
continuing role to play under the
Sub-Contract. The consequence of this is that, if BHP-IT's recourse to the
security was improper
and in breach of contract, the best that GEC Marconi
could expect by way of relief would be an order restoring the security. I do
not need to enter on the question whether it would be held by BHP-IT as a trust
fund.
721 In the circumstances any such order would be futile. As will be seen later
in these reasons, the amount of the three milestone
payments made to GEC
Marconi were recoverable by BHP-IT as wasted expenditure. That amount would in
turn then be able to be deducted
from the "restored cash security" as
recoverable damages. For this reason I do not consider it appropriate to make
any order in
relation to this claim though I should note that in assessing
BHP-IT's damages in its cross-claim against GEC Marconi I treat the
recourse to
the securities as if it had been effective.
722 There is one final matter to which I would draw attention. It has not been
suggested that, as a result of GEC Marconi's repudiation,
there was a total
failure of consideration for the Sub-Contract that would, of itself, have
entitled BHP-IT to claim the return of
the milestone payments made: cf
Roxborough v Rothmans of Pall Mall Australia Ltd [2001] HCA 68; (2001) 185 ALR 335.
723 I reject GEC Marconi's claim in relation to the financial securities.
12. THE CONVERSION OF THE STUBS EMULATOR
724 This claim is premised upon the proposition that, as copyright owner, GEC
Marconi had and retained property in the emulator it
built under CR3049.
Whether this was so depended first and foremost on the terms of the
Sub-Contract.
725 Sub-clauses 27(1) and 27(2) provided:
"27.1 Subject to this clause, the title to and Intellectual Property Rights in all Contract Material created by the Contractor and funded by the Commonwealth shall vest in the Commonwealth in accordance with the provisions of subclauses 27.2 and 27.3.
27.2 Copyright (including future copyright) in all Contract Material created by the Contractor and funded by the Commonwealth, including each and every stage of design and construction thereof, is hereby assigned to the Commonwealth."
726 The Sub-Contract defined "Intellectual Property Rights" to include copyright. And it defined "Contract Materials", insofar as is relevant for present purposes, as follows:
" "Contract Material" means, ...:
(a) all material including the Developed Software brought into existence after the date of this Contract; and
(b) all material existing at the date of this Contract to be incorporated with the material referred to in paragraph (a) above,
for the purpose of performing this Contract, including but not limited to documents, equipment, information and data stored by any means (whether specifically envisaged by this Contract or otherwise), but does not include any tools or methodologies used by the Contractor in performing this Contract except where they are specified in Schedule 3." Emphasis added.
727 Schedule 3 stipulated that there would be no tools or methodologies
contained in the "Contract Material". To reiterate, the Sub-Contract
defined
"Developed Software" to mean software that was to be developed and supplied in
accordance with the Sub-Contract and included
"any associated integration
services". One of the "systems integration services" to be supplied under the
Sub-Contract as executed
was the provision of "STUBS devices": Schedule 4, cl
1.1.
728 In light of the findings I have made in relation to the Emulation Variation
Agreement, the conclusion is inevitable that the
emulation software was part of
the "Contract Material", and was not a "tool or methodology". The use of
emulation, doubtless, can
be said to embody a method, ie a "procedure for
attaining an object": Shorter Oxford English Dictionary, "method". So
also can the use of sealers and gateways to achieve boundary security.
Nonetheless the vehicles so employed for these
respective ends would, in each
instance, be a substantive work product in its own right. Whatever its
shortcomings, the emulator
was designed and built in the light of the STUBS SIS
and the SDD prepared by GEC Marconi, and in accordance with the API
Specifications.
In consequence of the Emulation Variation Agreement it had an
important independent function to perform "for the purpose of performing
[the
Sub-Contract]". It was to be used for acceptance testing. In light of the
implied term I have found requiring the amendment
of the contractual
documentation to permit acceptance testing with the emulator, the emulator was,
in all probability, to be regarded
as an "systems integration service" for the
purposes of Schedule 4.
729 Having rejected GEC Marconi's contention, I should indicate that there
clearly was a variety of "tools and methodologies" used
by GEC Marconi in
performing the Sub-Contract which clearly were not "Contract Material". These
were in the nature of techniques,
processes and practices employed in the
production of contract material. One example of these was the methodology
employed in producing
the emulation software. It was that of "rapid
prototyping": see Mr Wishart's 23 October letter.
730 I do not regard the evidence of the experts, Dr Lewis and Professor Offen,
as being of any assistance to GEC Marconi. Their
opinions illuminate the
process of emulation and their respective appreciations of the purpose of the
emulator in the present case.
Their views on the latter matter are of no
relevance at all.
731 My conclusion is reinforced by the clear intent of CR3049 itself. It was a
contract to develop emulation software for acceptance
testing. For the purpose
of that contract and of the Sub-Contract it was a deliverable, copyright in
which vested in the Commonwealth.
GEC Marconi neither owned nor had an
immediate right to possession of the emulation software. It could not complain
that BHP-IT
had converted it.
732 I do not intend formally to assess damages against the contingency that my
conclusion is incorrect. I would observe, though,
that in its original form
the damages claim bordered on the astonishing. It embodied claims both for
prolongation costs and for
exemplary damages - claims now abandoned.
13. THE TERMINATION OF THE STANDING OFFER AGREEMENT
733 To understand GEC Marconi's claim in this particular matter, it is
necessary to refer in some detail to the purpose and the terms
of the Standing
Offer Agreement.
734 BHP-IT had been selected to be a member of a panel to supply integration,
support and consultancy services to the Department
of Defence. That panel was
known as the "Defence Preferred Systems Integrator (DPSI) Panel". To
facilitate its meeting its obligations
to the Commonwealth in respect of any
contracts it might obtain from Defence, BHP-IT in turn constituted a panel of
service providers
from which it could seek quotations for the provision of
services. The instruments used to establish the panel were standing offer
agreements between BHP-IT and what were referred to as Base Team Members (or
"BTMs").
735 On 6 February 1995 BHP-IT and GEC Marconi entered into such a Standing
Offer Agreement (or "SO"). It was to run from 1 December
1994 to 30 November
1997 but could be extended, by agreement, for a further two years.
736 The parties' SO did not confer any right on GEC Marconi to receive any work
from BHP-IT or impose any obligation on BHP-IT to
offer to GEC Marconi (or any
other BTM) any work it might have received as a member of the DPSI Panel.
Several clauses of the SO
accentuate this. I will refer only to cl 11.1.1
which provided:
"Quotations may be obtained from any BTM by BHP IT for work to be carried out under this SO, but nothing in this SO shall require BHP IT to award work to any BTM in respect of a Contract awarded to BHP IT under the DPSI Agreement. However BHP IT will act in a fair and reasonable manner to ensure that, where it is reasonable to do so, the tendered project team undertakes the work share applicable under the Contract."
737 Importantly the SO provided four principal bases upon which the SO itself could be terminated by BHP-IT. The first, which is not presently relevant, was if the BTM failed to carry out to BHP-IT's satisfaction its obligations under any contract entered into with BHP-IT pursuant to the SO: cl 4.1. The second, relating to poor performance, was contained in cl 4.3 and 4.4. These provided:
"4.3 The performance of the BTM will be formally reviewed jointly by BHP IT, Defence and the BTM every six (6) months for the first two (2) years and every twelve (12) months thereafter for the period of this SO. BHP IT and Defence shall conduct informal reviews on a monthly basis for the first 12 months or at any other such time that BHP IT or Defence considers appropriate to verify the performance of the BTM. It is BHP IT's intention that the informal reviews should have minimal administrative impact upon the BTM.
4.4 Performance by the BTM will be assessed against the record of the BTM's performance of all Contracts awarded pursuant to this SO and other BHP IT and Defence contracts considered relevant for the purpose of assessing the BTM's performance. Where the BTM is considered to have performed poorly (over a minimum period of twelve (12) months) BHP IT shall have the right to terminate this SO in accordance with Clause 27.1."
738 I would note in passing that cl 27.1 empowered BHP-IT, in
accordance with cl 4, to terminate the SO or whole or in part
immediately
by notice in writing to the BTM without prejudice to any other right of action
or remedy which has accrued or might accrue
to either party.
739 The third basis for termination was for convenience. Clause 27.5 provided,
insofar as presently relevant:
"Termination for Convenience
a. In addition to any other rights it has under this SO, BHP IT may terminate this SO in whole or in part, by notifying the BTM in writing that this SO or a part of this SO is terminated from the date specified in the notice (which date shall not be a date earlier than the date on which the notice is received by the BTM), and in that event, BHP IT may give to the BTM such directions as it thinks fit in relation to subsequent performance of this SO."
The clause went on to provide for mitigation of the BTM's losses arising in
consequence of termination, and BHP-IT's provision of
an indemnity against
liabilities and expenditure resulting from unavoidable losses by the BTM.
740 The fourth basis - which again is not relevant - provided for termination
of the SO if BHP-IT's DPSI Agreement was terminated.
741 I should note that the principal issues upon which this case turns relate
first and foremost to the construction and interrelationship
of
sub-cll 4.3 and 4.4 and to the relationship of those provisions with
cl 27.5. The latter of these raises the subject
of what in the United
States is known as "constructive termination for convenience": 64 AmJur 2d,
"Public Works and Contracts",
§165.
742 The final provision of the SO to which I should refer for the sake of
completeness is cl 27.3 which permitted GEC Marconi
to terminate the SO in
whole or in part by giving thirty days notice in writing to BHP-IT.
(a) The construction and interrelationship of sub-clauses 4.3 and 4.4
743 There is significant disagreement between the parties on the burden of
these sub-clauses. GEC Marconi submits that (i) they
both contemplated jointly
conducted formal and informal reviews and not severally conducted reviews; and
(ii) the appraisal of the
BTM's performance of contracts envisaged by sub-cl
4.4 was of contracts awarded under the SO or of contracts to which both
BHP-IT and Defence were parties. BHP-IT, in contrast, contends that cl 4.4
permitted it to conduct a review of GEC Marconi's performance
without the
participation of Defence and that in appraising GEC Marconi's contract
performance it could consider a contract between
GEC Marconi and BHP-IT
alone.
744 The meaning of the two sub clauses is, in my view, plain enough and does
not wholly accord with either party's submissions.
The reviews contemplated by
sub-cl 4.3 were joint reviews, whether formal or informal. Sub
cl 4.4 did not create a separate
reviewing power. It merely identified
the focus of a performance review. On its proper construction it permitted
appraisal of all
contracts awarded pursuant to the SO and, subject to the
important limitation of the "considered relevant" requirement, any other
contract GEC Marconi had with either BHP-IT or Defence. I consider this to be
the natural meaning of the terms used in the sub-clause.
And it effectuates in
comprehensible fashion the obvious purpose of the performance appraisal regime
created in cl 4: appropriate
levels of performance were to be expected of
contractors involved in Defence procurement. I do not regard the limitation
GEC Marconi
seeks to put on the contracts that could be considered in the
review as either reasonable or required by the terms of the sub-clause.
(b) "Constructive Termination for Convenience": Applicable
Principles
745 The following extract from American Jurisprudence 2d sufficiently
identifies the purpose and burden of the constructive termination doctrine in
procurement law in the United States (64
AmJur 2d, Public Works and Contracts,
§165):
"If a contract contains a termination for convenience clause allowing the government to terminate a contract in whole or in part and the contracting officer could have invoked that clause instead of terminating, rescinding, or repudiating the contract on some other invalid basis, the court will constructively invoke the clause to retroactively justify the government's actions, avoid a breach, and limit liability. Courts apply the doctrine of constructive termination for convenience on government contract cases when the basis upon which a contract was actually terminated is legally inadequate to justify the action taken."
746 The reason this is of present interest is that GEC Marconi contends that
BHP-IT purported to terminate under cl 27.1 for
poor performance and that
that termination was ineffective and improper. BHP-IT has sought to counter
this by contending that, even
if the poor performance termination was
ineffective, it could have relied in any event on termination for convenience
and it can
now seek to justify its termination by reference to its cl 27.5
power.
747 Neither party adverted to the United States doctrine to which I have
referred, BHP-IT merely asserting its entitlement to avail
of cl 27.5.
However, its submissions refer, though for other purposes, to a long accepted
principle of contract law which, in
turn, provided the underpinning for the
constructive termination doctrine. It is that when a party terminates a
contract and an
ineffectual reason or basis is assigned at the time, another
reason or basis may afterwards be relied upon to justify the termination,
the
question being whether, in the circumstances, the party was actually entitled
to do what it did even if unaware of all of the
circumstances at the time it
terminated the contract; Shepherd v Felt and Textiles of Australia Ltd [1931] HCA 21;
(1931) 45 CLR 359; Rawson v Hobbs [1961] HCA 72; (1961) 107 CLR 466; Concut
Pty Ltd v Worrell (2000) 176 ALR 693; Carter, Breach of Contract,
[1006]-[1014] (2nd ed); Chitty on Contracts, vol 1, para
25-013 (28th ed).
748 In the United States termination for convenience seems to have developed
originally in government contracting as "a tool to avoid
enormous procurements
upon completion of a war effort": Krygoski Construction Co Inc v The United
States 94 F 3d 1537 at 1540 (1996). Though its province is no longer so
limited, it was in a defence procurement setting that the Supreme
Court of the
United States formulated the constructive termination for convenience doctrine.
In College Point Boat Corporation v The United States 267 US 12 (1925),
the United States was sued for loss of profit under a contract of which the
Naval Department had committed an anticipatory
breach. The United States in
fact had an unconditional contractual right to cancel the contract, but neither
party was aware of
that right at the time and no attempt was made at the time
of the anticipatory breach to terminate the contract.
749 On the issue of whether the contractor could claim damages for loss of
profits flowing from the breach, Brandeis J for the Court,
observed (at
15-16):
"The question remains whether the measure of damages recoverable for this breach is the same as it would have been if the Government had not possessed the right of cancellation. A party to a contract who is sued for its breach may ordinarily defend on the ground that there existed, at the time, a legal excuse for non performance by him, although he was then ignorant of the fact. He may, likewise, justify an asserted termination, rescission, or repudiation, of a contract by proving that there was, at the time, an adequate cause, although it did not become known to him until later. An unconditional right to cancel can be availed of for the purpose of terminating a contract, even after suit brought, unless some intervening change in the position of the other party renders that course inequitable. Compare Clough v London & Northwestern Ry Co, LR 7 Exch 26, 33 et seq. Ignorance of its right doubtless prevented the Navy Department from taking, shortly after the Armistice, the course which would have resulted legally in cancelling the contract at that time. But the right to cancel was not lost by mere delay in exercising it ... The right remained effective as a limitation upon the Corporation's right to have the Government accept and pay for the mats. This continuing right of cancellation, which was asserted later, in court, operated to curtail the damages recoverable. It limited the value of the plaintiff's right to require performance, and hence the amount and character of the loss for which compensation must be made. Prospective profits were not recoverable."
750 This decision has subsequently been applied in the manner indicated in the above quotation from American Jurisprudence to preclude a damages claim of the type advanced by GEC Marconi in this case: see eg John Reiner & Co v The United States 325 F 2d 438 (1963). As was said in Hancock Electronics Corp v Washington Metropolitan Area Transit Authority 81 F 3d 451 at 454 (1996):
"Under settled law, whether [the government] breaches or wrongfully terminates a contract, the event is treated as a constructive termination under the Termination for Convenience Clause. See eg , General Builders Supply Co v United States, 187 Ct Cl 477, 409 F 2d 246, 249 (Ct Cl 1969). The law thus recognises that, in entering into a contract, the government limits its potential liability to the value of the performance rendered at the time it terminates the contract for convenience."
751 The evolution of this doctrine in the United States has clearly been
influenced by considerations of public policy and it has
been said to be
"unique to government contracts": ibid.
752 Termination for convenience clauses have received little attention in
Australian legal writing: but for a helpful discussion
see Seddon,
Government Contracts, [5.4]ff (2nd ed). And I am unaware of
any consideration being given at all to the constructive termination doctrine.
It is not necessary, though,
that I consider in any detail the scope and
operation of termination for convenience clauses or that I comment further on
the United
States doctrine.
753 Subject to a pleading point I will refer to later, the only issue I need
determine here is whether a party, by relying on one
basis for terminating a
contract, is for that reason alone precluded from later relying upon a
termination for convenience clause
to justify the termination. Subject to what
I later have to say about compliance with the requirements of the termination
for convenience
clause itself and about the relationship of cl 27.1 and
cl 27.5; see "Submissions and Conclusions" below; I can see no
reason in
principle for such a preclusion. It would be inconsistent with the orthodox
general principle that, while a termination
must be justified by reference to a
legal right to terminate, the party terminating may rely on any ground
available for termination
existing at the time of termination whether or not it
was then aware of it: see also Butterworths, The Law of Contract,
§7.28 (1999). And I see no reason not to apply that principle in a new
setting which would permit later reliance on a termination
for convenience
clause. In so doing, I adopt with respect the opinion of Brandeis J on this
very question in the College Point Boat Corporation case. I acknowledge
that the SO was not itself a government contract (an important feature of the
College Point Boat Corporation case), though it was entered into as part
of the antecedent arrangement put in place for Defence contracting. I am also
influenced
in my conclusion by the distinctive nature of a termination for
convenience clause. Though I accept that the exercise of such a
clause would,
as of course, be subject to a duty of good faith and fair dealing: Hughes
Aircraft Systems International v Airservices Australia (1997) 76 FCR 151;
cf Claybrook, "Good Faith in the Termination and Formation of Federal
Contracts" (1997) 56 Md L Rev 555; the clause
itself, unlike a termination for
convenience clause, seems otherwise unconditioned and unconstrained save for
its notice requirement.
(c) Additional Factual Material
754 Prior to termination of the Sub-Contract, it seems that on only one
occasion was a quotation submitted by GEC Marconi for inclusion
by BHP-IT in a
DPSI Panel member tender. That occurred on 27 November 1995. The quotation
was included in BHP-IT's Best and Final
Offer that was submitted on 25 November
1996. On the same day as it sent GEC Marconi the notice terminating the SO,
BHP-IT informed
GEC Marconi that it had removed it from this tender. The
reason it assigned for its action was that GEC Marconi had "performed very
poorly on the ADCNET project". The Commonwealth did not proceed with the
project in question and did not let a tender for it.
755 The SO was terminated by notice on 24 January 1997. Omitting formal parts
the Notice stated:
"TAKE NOTICE THAT BHP IT considers that EASAMS has performed poorly on the contract between BHP IT and EASAMS dated 14 September 1994 (Contract Agreement No ADC-001) for the software development and systems integration on the ADCNET project as a result of which BHP IT HEREBY notifies EASAMS that the Standing Offer is terminated with immediate effect in accordance with Clause 27.1 of the Standing Offer." Emphasis added.
The accompanying letter was in similar though less formal terms. I note in
passing that that termination was expressly linked to
cl 27.1 and not
cl 27.5 (termination for convenience). Roger Cooke's evidence is that GEC
Marconi received the notice
on or about the date of the notice.
756 The only communication between the parties that is in evidence which
relates performance of the ADCNET contract to the SO was
a letter from Mr
Haddad to Mr Sharp of 17 April 1996. Insofar as presently relevant, it
stated:
"Please find enclosed BHP IT's response to the alleged Notice of Breach issued by EASAMS.
BHP IT's Group General Manager, Ian Dart, has asked me to pass onto you his extreme concern and disappointment at EASAMS' position which will also impact BHP IT's approach on DPSI. BHP IT is astonished that you have adopted this aggressive stance at this very late stage given BHP IT's and DFAT's repeated attempts to accommodate EASAMS' delays and some 18 months of apologetic representations by EASAMS' executive regarding the delays to the project resulting from your admitted lack of adequate resourcing."
757 BHP-IT further relies upon what it says is evidence demonstrating GEC
Marconi's poor performance of the ADCNET Sub-Contract in
1995 and 1996 to
justify its belief. That evidence is dealt with in detail later in these
reasons: Part III, The Repudiation Claim.
758 Finally, there is no evidence to suggest that prior to the Notice, BHP-IT
and Defence had conducted a review of GEC Marconi's
performance of (inter alia)
the ADCNET contract.
(d) Submissions and Conclusions on Liability
759 There is, in my view, no doubt that the termination on 24 January was made
in reliance on the power given by cl 27.1. And
the reason for it was an
alleged judgment of poor performance made under cl 4.4 after a review
under cl 4.3. A termination
relying on that power for that reason would
clearly be ineffective. On the view I take of the proper construction of
cll 4.3
and 4.4, I am not satisfied (and there is no evidence suggesting
otherwise) that a joint review (formal or informal) was undertaken
with Defence
that encompassed GEC Marconi's performance of the ADCNET contract and that led
to the agreed view that it had "performed
poorly ... over a ... period of
twelve ... months": cl 4.4. Unless the termination is able to be
justified on other grounds,
it was clearly wrongful.
760 BHP-IT submits the termination was justifiable by reference to its power to
terminate for convenience. That clause, it is said,
required no more than the
communication of an intention to terminate, and the letter and Notice of 24
January 1997 sufficiently communicated
that, albeit it referred to
cl 27.1.
761 GEC Marconi contends, first, that BHP-IT did not plead cl 27.5 in its
defence to GEC Marconi's claim and should not now
be entitled to rely upon it.
My response to this is that while raised for the first time in written
submissions, GEC Marconi has
not claimed to be prejudiced by this defence.
Given the nature of this defence and the general invitation I have given the
parties
to put in further submissions on matters that arose during submissions,
I reject GEC Marconi's pleading argument.
762 Secondly, it is submitted that having referred to cl 27.1, BHP-IT
should not be allowed "to rewrite history" in the way
it proposes by relying on
cl 27.5. The parties have agreed specific mechanisms having different
consequences for terminating
the SO in whole or in part. A party was entitled
to know which termination ground was being relied upon so that it could adopt a
position accordingly. Further, it is said, there is no evidence that BHP-IT
intended to terminate for convenience. Finally, in
contesting BHP-IT's
reliance upon evidence of poor performance, GEC Marconi has contended that
BHP-IT was not so much concerned with
GEC Marconi's performance as with the
fact that it had terminated the ADCNET contract.
763 My own view is that BHP-IT was entitled to invoke cl 27.5 and, perhaps
fortuitously, it has satisfied the requirements of
that subclause. A notice to
terminate either under cl 27.1 or cl 27.5 did not require that it
state the ground on which
the termination was based. The notice requirements
were (a) in the case of a cl 27.1 notice, the stipulation as to writing
and the communication that the SO was terminated "immediately"; and (b) in the
case of a cl 27.5 notice, a like stipulation
as to writing and the
communication that the SO was terminated from a date specified in the notice
than was no earlier than the date
the BTM received the notice.
764 In the present case, the notice was in writing and, while the notice was to
take immediate effect, the notice of termination
was received on the date of
the notice. Though Roger Cooke's evidence on the latter matter referred only
to receipt of the notice
"[o]n or about 24 January 1997", this was a matter
that I raised with GEC Marconi during oral submissions and it was not suggested
that it was received otherwise than on 24 January. I note in passing, though
the parties have not relied on this and therefore I
do not, that the letter and
notice appear to be part of a composite facsimile communication of 24 January
that indicated that the,
presently relevant, accompanying material was to be
hand delivered "in the next hour". I am, though, prepared to infer from Mr
Cooke's
evidence and the response made in oral submissions that the notice was
received on the date it bore.
765 Clause 27.5 refers to a date being specified in the notice on which the
termination is to take effect. I am satisfied, nonetheless,
that the apparent
failure formally to specify a date in circumstances in which the notice was
intended to take "immediate effect"
and was received on the date it bore, did
not constitute an operative failure to comply with the requirements of
cl 27.5. Both
the notice and the accompanying letter conveyed to GEC
Marconi that the SO was terminated on and from the date of the notice. Given
it was received on that date, the sub-clause had been complied with: see the
observations of Kirby J on construction in Pan Foods Company Importers and
Distributors Pty Ltd v Australia and New Zealand Banking Group Ltd [2000] HCA 20; (2000)
74 ALJR 791 at [23]- [25].
766 The reference in the notice to cl 27.1 does not preclude BHP-IT from
relying upon cl 27.5. BHP-IT was asserting unequivocally
that it was
ending the parties' contractual relationship - it had already done likewise
with the Sub-Contract - and this was all
that it otherwise was required to do
to satisfy cl 27.5. Having regard to the saving of other rights and
remedies in cl 27.1,
that sub-clause did not purport to have an
exclusionary effect in relation to termination such that other grounds could
not be relied
upon to justify a termination that was ineffective on
cl 27.1 grounds: see Carter, Breach of Contract, [1014]
(2nd ed).
767 Though the consequences of terminating under cl 27.1 and cl 27.5
could differ (because of the mitigation and indemnity
provisions of
cl 27.5), I do not consider that those consequences precluded the use of
cl 27.5 in the manner I have indicated.
There was no operative difference
in fact between the two in the circumstances, given that GEC Marconi had been
removed from the
DPSI Panel tender.
768 Considered simply as a termination for convenience, the notice was, I
consider, an effective notice. Notwithstanding that GEC
Marconi had quoted
for, and been included in, a tender under the SO, BHP-IT had indicated to GEC
Marconi after the first notice of
breach had been served that its conduct in
the Sub-Contract relationship could affect BHP-IT's approach to it in the SO
relationship.
I do not consider that there was anything impermissible in
BHP-IT's giving this indication or, in fact, in acting upon it. After
GEC
Marconi's wrongful termination of the Sub-Contract with its consequential
effect on BHP-IT (because of its own contract with
the Commonwealth), it was
understandable that BHP-IT might wish to terminate its business relationships
with GEC Marconi. The SO
embodied one of these. The circumstances are far
removed from those capable of suggesting a breach of the duty of good faith and
fair dealing in effecting the termination on cl 27.5 grounds.
769 I reject GEC Marconi's claim of wrongful termination.
(e) Other matters
770 I do not intend to proceed to assess damages against the contingency that
my conclusions on liability are incorrect. I would
say, though, that on the
twin assumptions that GEC Marconi's termination of the ADCNET contract was
wrongful as was BHP-IT's termination
of the SO, GEC Marconi's claim for damages
seems a particularly weak one. It had no right to receive work from BHP-IT;
the likelihood
of it being offered work in fact was highly questionable; and
there are very real question marks over how realistic the chances
were of GEC
Marconi possibly securing the three lost opportunities it identifies.
771 Even if GEC Marconi's termination of the ADCNET contract was lawful, I
rather doubt that this would have strengthened in any
way its damages claim for
breach of the SO.
16. THE DELAY AND PROLONGATION CLAIM
772 Prior to the termination of the Sub-Contract by GEC Marconi a number of
events had occurred which it alleges entitled it to make
claims under the
contract, first, for extensions of time to perform contractual obligations on
account of delays not of its own making
and, then, for costs and expenses
unavoidably sustained as a result of those delays. GEC Marconi alleges that
BHP-IT has failed
to reimburse it for such costs and expenses and these are now
claimed in this proceeding.
773 This claim has been a lurking presence in this proceeding since the
commencement of the hearing. If each and every one of the
individual delay
claims made had to be examined and decided separately the cost of so doing
would have been considerable. While
the particular claims in issue are made
formally against BHP-IT, they are in substance claims which are alleged to have
resulted
directly from acts or omissions of the Commonwealth and for which it
ultimately will bear responsibility, a responsibility acknowledged
in the 1997
Variation Agreement between the Commonwealth and BHP-IT. For this reason the
Commonwealth and GEC Marconi have assumed
responsibility for the presentation
of this claim in a fashion designed to limit both the scope of the inquiry I
have to undertake
and the material that needed to be tendered.
774 The individual claims advanced have been made in respect of nineteen
specific entries made in a diary kept by GEC Marconi. I
will refer to these as
the "diary entry claims". GEC Marconi and the Commonwealth have agreed facts
relating to each such claim
as also the issue of quantum of each claim. It is
further agreed that each of the delays the subject of these diary entries were
from a cause beyond the reasonable control of GEC Marconi.
775 The following are illustrative of the format of the agreed diary entry
facts:
"Diary Entries 6 & 7
1. The R3 team was split across widely separated areas in the accommodation provided by DFAT for a period of 6 months.
2. As a result, the efficiency of the R3 team was reduced.
3. The reduced efficiency:
(a) extended the project by 28.5 hours;
(b) resulted in delay costs of $25,000.00; and
(c) resulted in prolongation costs of $25,000.00.
Diary Entry 10
1. There was a fire that affected the availability of the accommodation provided by DFAT.
2. The fire damage:
(a) extended the project by 13 hours;
(b) resulted in delay costs of $11,520.00; and
(d) resulted in prolongation costs of $11,405.00."
There are ten such agreed statements covering nineteen actual diary entries.
776 I should add, lest there be any mistake about the matter, that the relevant
diary entries do not take anything like the form
suggested above. What has
been quoted is what has been agreed for present purposes in relation to them.
Diary Entry No 6, for example,
was in the following form:
DIARY ENTRY
ENTRY NO: 006 DATE: Oct 31-Nov 6, 1994
RAISED BY: P. Wishart
DETAILS OF ENTRY: The split of R3 team members across widely separated areas in the building is continuing to cause communication problems.
ASSESSMENT OF IMPACT: Communications difficulties are resulting the need for more document rework than necessary.
ACTION REQUIRED: Relocate all R3 staff to areas in close proximity.
RESPONSIBILITY: DFAT DATE REQUIRED: ASAP
AUTHORISATION:
CONTRACTOR: signature signature
DELEGATE: signature
On its top it had a handwritten notation in capital letters "Approved in
accordance with R3 contract" and a received stamp bearing
the date 9 November
1994. On its bottom it had an "Approved" stamp. The three signatures on the
form are, on the top line, Mr Wishart
and Mr Brent, and on the bottom, Les
Cook. The form used was a standard form for diary entries.
777 The diary claims have been the subject of written submissions only, the
issues they raise being of an essentially legal character.
Before turning to
those issues, it is necessary to refer first to the provisions of the
Sub-Contract.
(a) The Contractual Setting
778 I need to refer to three separate subjects dealt with in the Sub-Contract.
The first related to the keeping of a diary. Clause
12.1 and Schedule 2
required GEC Marconi to maintain a diary of events "that affect the
Contractor's ability to work in accordance
with the Project Plan contained in
Schedule 7". Clauses 12.2 and 12.3 provided:
"12.2 The Contractor shall forward to the Delegate at the end of each calendar week unless otherwise agreed between the Parties a copy of the diary entries for that week. If the Delegate agrees with the statement of facts recorded by the Contractor the Delegate shall sign the Diary within 8 days of receiving a copy of the entry.
12.3 If the Delegate disagrees with the statement of facts recorded by the Contractor the Delegate shall record its version of facts in the Diary. If the Delegate does not record a disagreement with the facts stated in the Diary within 8 days, the Diary shall be prima facie evidence of the facts recorded therein." Emphasis added.
779 The second subject was the granting of extensions of time on account of delay. It is necessary, unfortunately, to set out this wordy provision in full. Clause 46 provided:
"46.1 Where in the Contractor's reasonable opinion there is likely to be a delay of no less than one day in the Contractor discharging an obligation under this Contract because of a cause beyond the reasonable control of the Contractor (except a cause arising out of any act or omission on the part of the Contractor's employees, agents or sub-contractors or their employees or agents) which the Contractor considers justifies an extension of the time specified in this Contract, the Contractor shall:
(a) notify the Customer in writing as soon as possible after the Contractor has formed that opinion of the facts which the Contractor considers give rise to such a delay, develop strategies to manage the consequences of the delay and submit to the Customer a copy of the proposed variations to the Contract pursuant to clause 11; and
(b) immediately after the Contractor is aware that the circumstances causing the delay have ceased, notify the Customer in writing of the period of delay so caused, give details of the likely effect on this Contract and request an extension of time which the Contractor considers reasonable in all the circumstances.
46.2 The Customer shall give consideration to the Contractor's request and shall, within 11 days after receiving a notice under paragraph 46.1(b), notify the Contractor of its decision. Where the delay has arisen from a cause beyond the reasonable control of the Contractor the Customer shall not refuse a request for extension of time without reasonable grounds for doing so. In the event that the Customer does not respond within 15 days of receiving a notice pursuant to clause 46.1(b) the extension of time requested by the Contractor shall be deemed to be granted.
46.3 Notwithstanding that the Contractor has not given notice under subclause 46.1, where the Customer considers that a delay has arisen, in whole or in part, because of an act or omission on the part of the Customer or its employees or agents then the Customer may, by notice in writing to the Contractor, extend the time for performance of the relevant obligation of the Contractor by nominating in the notice a date for such performance and the date so specified shall, for the purposes of this Contract, be the date for performance of that obligation." Emphasis added.
780 The third subject related to delay costs. Clause 47 - again wordy - provided:
"47.1 Subject to compliance with all of the provisions of subclause 47.2, the Contractor shall be entitled to recover from the Customer reasonably foreseeable costs and expenses unavoidably sustained and incurred by it as a result of delay in the integration of the System by any cause or causes beyond the control of the Contractor being an act, default or omission on the part of the Customer in the performance by the Customer of its obligations under this Contract: emphasis added.
47.2 The entitlement of the Contractor to recovery of costs and expenses incurred by it as a result of delay in the integration of the System referred to in subclause 47.1 shall be subject to compliance with the following conditions:
(a) an extension of time has been granted or should properly have been granted pursuant to clause 46;
(b) the Contractor has taken all practicable steps to keep any such damages to a minimum; and
(c) the Contractor has given to the Delegate details in writing of the nature of the claim under subclause 47.1 as soon as practicable after commencement of the delay giving rise to the claim and at a time when those details are capable of being adequately checked by the Delegate, such details being given progressively where necessary.
47.3 This clause 47 does not derogate from any right of the Contractor to recover damages for delay not recovered under this clause."
781 I have emphasised the reference to "delay in the integration of the System" for this reason. The interpretation provision of the Sub-Contract defines both "System" and "Integration". I have referred to these definitions over 200 pages ago. I will repeat them. They are as follows:
" `System' means the working system which complies with this Contract and comprises the [Contractor Supplied Equipment] and [Customer Supplied Items].
`Integration' in respect of the System includes the integration services as set out in Schedule 4."
The Schedule 4 services cover amongst other things the design, development,
integration and testing of the Developed Software.
782 The reason I focus on this particular matter is that the Commonwealth, in
the interpretation it seeks to place on the reference
to "the integration of
the System" in cl 47.1, contends that the word "System" is used in the narrow
sense conveyed by the definition
of that word. GEC Marconi for its part
contends that the entire phrase as used in cl 47.1 reference conveys no less
than what is
conveyed by the definition of "Integration" above.
(b) The Basis of the Claims Made
783 GEC Marconi, as I have indicated, has founded its claim first and foremost
on the diary entries it made. It notes that, by virtue
of cl 12.3, if Mr
Brent did not record disagreement with the statement of facts contained in an
entry, then the entry was "prima
facie evidence" of those facts. Thirteen of
the nineteen diary entries in issue have the stamp "approved" on them.
784 It then contends that no particular formality for an extension of time was
required other than that there be a written request
for an extension. The
diary entry was sufficient for that purpose, as it was for the purposes of
cl 47. Alternatively it is
said that the relevant notifications were
provided in correspondence to which I will refer below, or else BHP-IT is
estopped from
asserting there was no adequate notifications.
785 The Commonwealth defends these claims on three bases. The first is that
GEC Marconi failed to fulfil the requirements of cl 46
and cl 47 of
the Sub-Contract and that the Commonwealth was not estopped from setting up
this failure ("Non-compliance with
cl 46 and cl 47"). Secondly, as
delay costs could only be recovered where "integration of the System" was
delayed, GEC
Marconi could not seek payment for delay and prolongation as it
had not reached that stage of contractual progress under the Sub-Contract
("the
integration defence"). Thirdly, it was a condition precedent to the right to
be paid for a delay and prolongation claim that
the software to be developed be
completed and delivered at Milestone 5000 ("the entire obligation defence").
786 Given the agreed facts for each diary entry, the approach I intend to take
is to consider first the defences raised by the Commonwealth.
If any of these
can be maintained, GEC Marconi's claim must fail.
(c) The Defences
(i) Non-compliance with cl 46 and cl 47: The Diary Entries
787 GEC Marconi's submission on this matter can be put in the following general
terms. The burden of Clauses 46 and 47 was to:
(a) identify the particular fact, matter or circumstance causing a delay;
(b) identify, as far as was possible, the period of that delay;
(c) enable BHP-IT/the Commonwealth to assess the cause and period of delay; and
(d) allow for an appropriate extension of time.
The relevant diary entries:
(a) identified the facts or the circumstances causing the delay;
(b) identified, so far as it was able to do so, the period of delay;
(c) enabled BHP-IT/the Commonwealth the assess the cause and period of delay; and
(d) notified a request for an extension of time.
In consequence the diary entries and their communication to BHP-IT/the
Commonwealth satisfied each of the requirements of clauses
46 and 47.
788 I should preface my own consideration of this matter by making the
following comments on cl 46. The two step procedure
envisaged by
cl 46.1 - ie notification that there was likely to be a delay of no less
than one day (cl 46.1(a)) and notification
after the circumstances causing
the delay have ceased with a request for an extension (cl 46.1(b)) - must
be construed and applied
in light of the myriad of contingencies which the
extension of time provision was clearly intended to accommodate. I do not
consider,
for example, that reasonable parties standing in the shoes of BHP-IT
and GEC Marconi would have intended that there be strict compliance
in all
cases with the requirements of cl 46.1(a), although that provision
manifests a clear intent to deter the making of extension
claims for delays
anticipated to be of short duration.
789 I am satisfied, though, that the parties would have intended that there be
compliance with the provisions of cl 46.1(b).
My reasons for this view
are as follows. First, given the back-to-back nature of the ADCNET contracts,
the administration of the
mechanism for the granting of extensions was
obviously intended to be uniform and to be complied with according to its
terms. The
parties clearly would not have countenanced cl 46.1(b) being
administered in a fashion that could give rise to the possibility
of the same
delay event having differing consequences as between the two contracts - a
matter to which I later return. Moreover,
given the significance of the
subject matter of an extension request, I consider that they would have
intended that the formalised
procedure prescribed would be adhered to as this
would be conducive to maintaining reliable and accurate contract documentation:
cf McMahon Constructions Pty Ltd v Crestwood Estates [1971] WAR 162.
Finally, as an extension may be deemed to be granted if no response to it was
made within 15 days of receipt of the
cl 46.1(b) notice, it is unlikely
that parties would have agreed to such an effect unless an identifiable
"notice" of the prescribed
variety was in fact received.
790 GEC Marconi has submitted that cl 46.1(b) did not prescribe any
particular formality other than that there be written notification
of the
period of the relevant delay and a request for an extension.
791 This, in my view, understates what cl 46 requires. While no
particular form was prescribed for its "notice", cl 46
envisaged a
document created (i) specifically for the purpose of an extension claim, (ii)
at a particular time (ie "immediately after"
etc) and (iii) with a particular
content that included not only notification of the period of the delay but
also a request for an extension of time which the Contractor considered to
be reasonable in all the circumstances. I emphasise the "but
also" for this
reason. Clause 46 was not concerned merely with delay as such. Its focus was
on delay which justifies an extension
of time. Delay in a particular activity
need not necessarily have delayed completion of the contract: cf Halsbury's
Laws of Australia, vol 3(2) "Building and Construction", 65-1035. As will
be seen, Les Cook was alert to this in his letter to BHP-IT of 12 October
1995.
792 Contrary to GEC Marconi's submission, I am not satisfied that the diary
entries which were created and which were required to
be submitted to BHP-IT in
compliance with the distinct contractual regime imposed on GEC Marconi by
cl 12 of the Sub-Contract,
could serve as well as surrogate notices for
cl 46 purposes in the absence of agreement between them that such could be
the
case.
793 It is the case that a diary properly maintained under the Sub-Contract
would record delaying events and their impact. Schedule
2 required the
recording of "events that effect the Contractor's ability to work in accordance
with the Project Plan". It was equally
open to GEC Marconi to develop a diary
containing further information. Its diary in fact contained an "Action
Required" heading.
BHP-IT was required to review the diary on a weekly basis
and to record whether or not it agreed with "the statement of facts" recorded
by GEC Marconi. Thirteen of the diary entries in issue here had an "approved"
stamp on them. That agreement, though, went no further
than an agreement with
such facts as were stated. Where, as in Diary Entry 17, the "Action Required"
was stated to be (inter alia)
"1. Extend project schedule by 0.5 day" that
agreement did not extend to this such that a contract variation was then and
there
agreed. A "fact" was not being agreed to. Moreover, as cl 12.4 of
the Sub-Contract stated the diary did "not operate as a
modification, variation
or amendment to" the contract.
794 When one has regard to the particular diary entries in question here, it
can reasonably be said that some do contain information
of the type to be
expected of a cl 46.1(b) notice. Such entries, though, were not brought
into existence for cl 46.1 purposes
- though they clearly could have been
the heralds thereof - and they did not reflect its purposes. When agreed to by
BHP-IT (or
when agreement was deemed), that agreement was for no purpose other
than the purposes of cl 12 of the Sub-Contract.
795 Unless the parties agreed to the contrary, if an extension request was to
be made, it needed to be a request separate from the
making of a diary entry
for cl 12 purposes. Though this may well have required some duplication
in the communications made,
it reflected what I consider to be the regime
prescribed in the Sub-Contract.
796 For this reason alone GEC Marconi's claim must fail to the extent that it
is based on the diary entries. I would add, though,
that even if diary entries
were capable as well as serving the purpose of a request under cl 46.1(b),
I do not consider that
any of the entries in issue would reasonably have
brought home to BHP-IT that when it was conducting its prescribed review of the
diary it was also being asked to consider a cl 46 request for an extension
of time. Some number of the entries made no estimate
of the extension of time
requested at all. Others stated that the impact of the delay was yet to be
determined. This said, many
of the diary entries would have suggested to
BHP-IT the real likelihood of an extension request and a cl 47 delay claim
being
made in light of the event (and its impact) described in the diary
entry.
797 Fundamental to a delay cost claim under cl 47 was the grant or deemed
grant of an extension under cl 46.2 and cl 46.3.
The lack of such an
extension would in turn be fatal to the delay cost claim made by GEC Marconi.
For the reasons I have given,
the diary entries themselves were incapable of
bringing cl 47 into play because they did not enliven cl 46.2.
(ii) Non-compliance with cl 46 and cl 47: Estoppel
798 GEC Marconi have submitted that, if the diary entries were not of
themselves sufficient notification of extension requests under
cl 46.1(b)
as a matter of construction of the Sub-Contract, nonetheless GEC Marconi and
BHP-IT conducted themselves as if they
were, such that BHP-IT is estopped from
contending that they were insufficient for that purpose.
799 This submission related to communications made between August and December
1995 involving Diary Entries 1 to 25 to which it is
necessary to make brief
reference.
800 (1) By August 1995 both BHP-IT and GEC Marconi were pushing for a schedule
extension to the ADCNET contracts and negotiations
to that end were on foot.
On 4 August Mr Brent wrote a letter to Mr Pears that included the following:
"Further to our discussions I wish to confirm that in order to progress negotiations on the proposed schedule extension I require the following information from EASAMS:
. formal agreement that all EASAMS claims for schedule extension and delay costs would be formally waived when agreement is reached on current negotiations for schedule extension;
. formal presentation of a schedule establishing the new baseline and demonstrating the capacity/capability of the ADCNET team to meet the new schedule;
. a consolidated list of pending claims itemising description of the claim, impact in no of days from the overall project schedule and cost."
801 Les Cook had by then clearly acknowledged that some level of claims for schedule extension and for delay costs were justified. On 10 August he wrote to Mr Brent in (inter alia) the following terms:
"This minute provides the Department's requirements for agreement on an extension to the Release 3 firm price contract schedule." Emphasis added.
BALANCE OF EFFECTS ON THE RELEASE 3 PRICE
From our analysis of the diary entries we believe that any claim for 8 weeks extension in time or for $800,000 in costs would be excessive. Any such claim would be accompanied by detailed justification, but we do not accept that claims exceeding $250,000 could possibly be justified.
...
DELAY CLAIMS
It will be agreed that all events occurring prior to the date of the contract change will not be subject to claims under contract clauses 46 and 47."
802 GEC Marconi supplied BHP-IT with a proposal for the way forward in the schedule amendment negotiations which was prefaced by the following summary of the situation relating to delay claims:
"1. Delay Claims
The consolidated delay claim for the Diary entries up to entry 25 and the claim for lack of CSI supplied staff results in a seven week schedule extension and a cost reimbursement of $285000. Details of the delays can be made available should you so require. This does not include any impact for lack of STUBS delivery which was contracted to be supplied in 1 August 1995 and will become critical from 28 August 1995. The cost for delay in STUBS delivery will be about $1300 per hour with, as a minimum, a corresponding schedule extension on an hour by hour basis."
803 Subsequent discussions were held with DFAT concerning the delay proposals which led Mr Brent to make the following request of GEC Marconi on 29 August 1995.
"1. EASAMS will, as a matter of high priority, prepare a detailed submission to BHP-IT setting out;
- separate details for each delay incurred by EASAMS on the current fixed-price project. This will include the reasons for the delay, the party to which EASAMS considers the cause of delay is attributable as well as the cost and time associated with each delay. The time effect of each delay occasioned by EASAMS is also required."
804 On 11 September 1995 GEC Marconi wrote to BHP-IT to submit its "detailed
proposal to amend the ADCNET Contract". The letter indicated
that the proposal
took into account a number of matters including delay claims up to Diary Entry
25. It proposed that the "delay
costs" be offset against GEC Marconi's
exposure to potential damages so that "[t]his would not result in a change in
the contract
price".
805 The proposal itself was contained in Appendix A which in turn referred to,
and had attached to it, Attachment 1 relating to delay
claims. The Appendix
stated that the total impact of the claims as detailed in the Diary to Entry 25
and/or inadequate supply of
CSI personnel was "between 7 and 8 weeks". The
Attachment opened with the following:
"Delay claims - Diary entries and CSI personnel
The following constitutes the delay claims for Diary Entries 1 to 25 and for lack of CSI personnel to date.
The delay can be estimated in two components. Firstly the cost of effort which was in our view wasted. In most cases we were able to redeploy some of the staff on other activities, however this was not possible for all staff or for all diary entries. Secondly the cost of extending the project schedule by the number of hours impacted for each entry. The cost of extending the project is limited to the Project Management/Administrative functions only. These are made up of the Project Manager; Project Controller; Development, T&I and Systems Engineering managers; Admin staff; Systems Administrator; ten percent of the team leader effort."
Under the headings "Entry No. Rational (sic) for Claim" it referred
sequentially to Diary Entries 1 to 25 and gave brief (usually
less than one
line) descriptions of the basis of the claim. Many of the claims so noted were
for schedule extensions of four hours
or less.
806 On 12 September Mr Haddad of BHP-IT wrote to Mr Pears outlining the
arrangements that had been agreed between the parties regarding
the contract
amendment proposal. His letter included the following:
"(c) any claims for delays and associated costs that EASAMS, BHP-IT or the Department may have with respect to any events which occurred prior to the date of the amendment shall become void at the date of its issue.
...
We will advise you of our progress and address with you any amendments to the preceding which may become necessary as a result of our discussions with the Department, prior to our reaching any formal agreement with the Department."
807 BHP-IT then wrote to Mr Skinner on 15 September concerning the proposal for a contract amendment. In this letter it stated:
"Following your request BHP-IT has reviewed all aspects of delays [occasioned by the parties involved] and shares the Department's view that the matter is best dealt with in two stages:
1. A detailed review of both claims for delay and any associated cost effects, and costings for additional work as a result of change of scope; and
2. Provided that the Department is not financially disadvantaged the matter be resolved by way of one major contract amendment which offsets additional Contractor costs against money that would be payable to the Department in respect of the delays."
It then went on to state its own view of what those delays and costs were. It
gave as its own view that of an overall expected delay
of 11 weeks to
completion date, 7 weeks were attributable to DFAT, of which 5 were "clearly
demonstrable while the remaining two
were a matter of debate.
808 In his 26 September letter formally notifying the cancellation of STUBS Les
Cook observed:
"As explained to the PSI on a number of occasions, the Department is not yet convinced of the validity of several of the claims for excusable delay. In particular, it is not clear that any reasonable delay mitigation strategy was applied as is required by the contract. If an overall agreement can be reached which is fair to both sides, then further detailed examination of these claims, probably by an independent arbitrator, may not be necessary. The Department considers that any such agreement must include a strategy for STUBS replacement. If the PSI will not accept this approach, it should proceed with formal claims for excusable delay immediately. I note that no such claim has yet been received despite the contractual requirements that they be lodged immediately after the cause has ceased."
809 Replying to this on 4 October 1995 Mr Brent stated:
"... I believe that consideration of our proposal by the Department should not be predicated on work associated with the development of the STUBS replacement strategy. In this context the Department should be aware that our proposal for contract extension is also our claim for delay costs and schedule impact."
810 Les Cook responded on 12 October 1995 in terms that included the following:
"The Department does not accept that the PSI's proposal for contract amendment constitutes a valid claim for excusable delay. The only formal communication of this proposal is in your letter KB-697 of 15 September 1995 (note: BHP-IT has informed me that the date on the letter was in error and should be 15 September). That letter and its attachment do not provide any detail of individual events for which claims may be made, indeed the letter contains two quite different estimates of the total delay which might be claimed. The attachment to the letter states that `substantiating detail has been made available to the Department's ADCNET project manager'. Whilst some spreadsheets were provided separately and informally, these certainly did not amount to a justification of a claim in each instance and there were major errors which the Department brought to your notice. No corrected and augmented data has been received. The situation remains that no formal claims have been made as required by the contract, despite the fact that some of the events occurred and ceased more than a year ago.
If formal claims are made, they must include details adequate to demonstrate that the contractor performed `all practical steps to keep any such damages to a minimum'. Vague statements about overtime, redeployment etc. will not meet the requirement for substantiation. The information in the draft spreadsheets clearly indicates that no such steps can have been taken in most instances. As one typical example, there is the claim that a delay of 40 hours affecting only one technical author caused a 40 hour schedule delay. This would be the effect if the entire project team were sent on leave for the whole 40 hour period: any delay mitigation strategy would have reduced the effect from this worst case.
The Department remains willing to avoid a protracted examination of the details of each claim, provided that an overall position can be reached which both sides consider to be fair and which allows the project to move forward to a successful completion."
811 On 1 December Mr Sharp wrote a letter to Mr Brent which concluded with the following:
"It is noted that the EASAMS contract currently requires delivery of the Canberra system on the 15th January 1996, plus some minor extension arising from CCPs. I do however believe that it is jointly recognised by both BHP and DFAT that this date was to be extended to the 7th June 1996 as a result of previous negotiations. Given the agreement from these past negotiations and the recent requirement to develop an alternative to the STUBS device, we seek your support of a contract change formally amending the Contract delivery dates."
The source of that belief has not been revealed in evidence.
812 On 5 December 1995 Les Cook reiterated to Mr Brent DFAT's view that it was
not prepared to agree to an extension of the project
schedule outside the
contract mechanisms of change requests and claims for excusable delay except in
the case of a comprehensive
agreement.
813 In January 1996 BHP-IT and GEC Marconi agreed CR30 which amended Schedule 8
Table 8.1 of the Contract to add 15 days to all milestones
commencing with
TRR.
814 Finally there are in evidence BHP-IT internal communications of September
1996 which record the "delay claims" made in Diary
entries since Diary Entry
25. The primary record was a "Diary Entry Filing Register" indicating that in
each case no cost of any
claim was made.
815 GEC Marconi's submission would seem to be that Appendix A and Attachment 1
to its 11 September 1995 letter to BHP-IT constituted
notification of a claim
for delay for between 7 and 8 weeks. As this letter was not responded to there
was a deemed extension under
cl 46.2. In the alternative it is submitted
that if BHP-IT's response about schedule extension proposals being put to DFAT
constituted a sufficient response, the 11 September letter was at least a
sufficient notification for cl 46.1(b) purposes.
816 GEC Marconi goes on to submit that in making its 15 September proposal to
DFAT, BHP-IT accepted that GEC Marconi was entitled
to prolongation of between
5 and 7 weeks. At no time, it is said, did BHP-IT ever indicate that it
required any further or different
documentation in order for GEC Marconi to
advance any of its diarised delay claims or any claims the subject of the
consolidated
claim.
817 In this proceeding there have been many counterfactuals with which I have
had to deal. I would have to say that, to treat the
documentation prepared by
GEC Marconi for the purposes of the ongoing contract schedule negotiations as
if it embodied notifications
under cl 46.1(b) of the Sub-Contract when
provided to BHP-IT on 11 September, would merely add to those counterfactuals.
The
documentation was not prepared for that purpose. It was one part of a
composite proposal to be used by BHP-IT in negotiations with
DFAT for a general
contract extension. That proposal came to nothing. No extension was agreed.
818 There is nothing in the correspondence to indicate reasonably to BHP-IT
that a request for a contract extension which GEC Marconi
considered was
reasonable in the circumstances was being made of it and required its separate
response. The object of the exercise,
as was well understood both by BHP-IT
and GEC Marconi, was that they were attempting to contrive a favourable
extension to the ADCNET
contracts. And what was being proposed would, if
agreed, result in any claims for delay and associated costs relating to events
occurring prior to the extension becoming "void". Independent resolution of
requests for extensions and delay cost claims was neither
expected by GEC
Marconi or by BHP-IT nor sought by GEC Marconi. Clauses 46 and 47 were not
being activated. The tenor of the documentation
in its setting was that GEC
Marconi had delay claims available to it - but claims it had not as yet made
under the Sub-Contract.
819 Even if, contrary to my view, the 11 September communication could be
contorted into a cl 46.1(b) notification and request,
I do not accept that
there has been a deemed agreement to the extension under cl 46.2. No
certain period of extension was sought
or could be deemed to have been agreed
to. And BHP-IT made plain to GEC Marconi that it was DFAT's response to the
proposal being
put that would ordain such project extension outcome from the
negotiations as there might be. Such was the rationale of BHP-IT's
initial
solicitation of documentation from GEC Marconi from 4 August 1995 onwards.
820 I am unable to accept that BHP-IT and GEC Marconi either understood, or
intended, that the 11 September documentation would enliven
cl 46.1(b) of
the Sub-Contract. The consolidated claim was clearly inapt for the purpose in
any event. Nor do I consider that
the communications between the parties were
capable of founding an estoppel which could preclude BHP-IT from setting up the
requirement
of cl 46.1(b).
821 I would add that the submission GEC Marconi has put on the correspondence
merely reinforces the view I earlier expressed that
parties in the position of
the Commonwealth, BHP-IT and GEC Marconi would have intended that there would
be adherence to the formalised
procedure of cl 46.1(b). If acceded to,
GEC Marconi's submission could well have resulted in an extension occurring in
the
Sub-Contract on account of conduct for which the Commonwealth was
responsible, but which was not replicated in the Head Contract.
This was not
something the parties would either have envisaged or countenanced.
822 GEC Marconi has advanced the alternative submission that, because BHP-IT
had reached the view that delays attributable to DFAT
of 5 to 7 weeks had
occurred and were reflected in Diary Entries 1 to 25, it could have exercised
its discretion to grant an extension
under cl 46.3. Because it was
obliged by cl 5.6 of the Sub-Contract to exercise powers conferred on it
in a reasonable
manner, BHP-IT and, ultimately, the Commonwealth were obliged
to grant an extension of time.
823 The short answer to this is that any response to be made by BHP-IT
presupposed a parallel response by the Commonwealth - and
GEC Marconi well
understood this. Once the Commonwealth contested the validity of the "claim
for excusable delay" made in BHP-IT's
15 September 1995 letter (it did this in
its 12 October letter), BHP-IT could not be said to be acting unfairly and
unreasonably
in "failing" unilaterally to grant an extension.
824 I should add that I refrain in any event from expressing a view on whether
the cl 46.3 power could be converted in any circumstances
into a duty by
virtue of the cl 5.6 obligation such that GEC Marconi could complain of a
failure to exercise that "duty".
(iii)
The Integration Defence
825 I have already foreshadowed this defence. The Commonwealth's contention is
that the phrase delay "in the integration of the
System" means delay in
integration of the Developed Software with the CSI. If the Developed Software
was not in existence and was
not available for integration, there could not be
a recoverable delay cost for the purposes of cl 47 of the Sub-Contract.
The
construction so advanced turns critically, as I have earlier indicated, on
the meaning given by interpretation provision of the Sub-Contract
to
"System".
826 For its part GEC Marconi submits that "in the integration of the System"
must be read in its setting and particularly in light
of cl 46 with which
cl 47 is related. An extension of time under cl 46 could be granted
in respect of delay in each
step of the process of software development leading
up to the integration of the Developed Software with the CSI. A delay giving
rise to such an extension of time would necessarily involve a delay in the
integration of the System itself and, as such, would be
compensable under
cl 47. Particular emphasis in this submission is placed, as I have
indicated, on the interpretation given
by the Sub-Contract to the term
"Integration". To reiterate, it provides that " `Integration' in respect of
the System includes
the integration services as set out in Schedule 4". Those
services in turn include software design, development, etc.
827 For my own part, I consider that the interpretation placed by GEC Marconi
on cl 47 is that which was intended in the ADCNET
contracts. I do not
consider that the parties intended to isolate only a very limited phase of the
contract in which to allow recovery
of delay costs under the contracts leaving
most of the delay costs incurred in the contract period to a common law claim
under cl 47.3.
Such an intention becomes the less probable given that
cl 46 deals with delay across the period of the contracts and cl 47
delay costs were conditioned on a cl 46 extension of time. I consider the
phrase "in the integration of the System" was intended
as a shorthand reference
that included the System Integration Services of Schedule 4.
828 The Commonwealth's submission invites me to attribute to the parties what I
consider to be an improbable intention and one, moreover,
without obvious
commercial justification.
(iv) The "Entire Obligation" Defence
829 I can deal with this matter briefly as it is without merit. In dealing
with GEC Marconi's claim that BHP-IT wrongfully called
on the financial
guarantees I rejected BHP-IT's submission that the payments to GEC Marconi for
Milestones 1000 to 3000 were conditional
upon its achievement of Milestone
5000. The Commonwealth's "entire obligation" defence here does no more than
recycle the submission
made by BHP-IT on the financial guarantees.
(d) Conclusion
830 I have rejected GEC Marconi's claim for delay and prolongation costs under
cl 47.2 of the Sub-Contract. Such right as it
has to claim damages on
account of culpable delay by BHP-IT exists at common law. The "agreed facts"
do not address this matter.
Neither do the submissions that have been made.
This claim will be stood over for further hearing on a date to be fixed.
PART III: BHP-IT'S FIRST CROSS-CLAIM
831 This cross-claim encompasses distinct claims, first, against GEC Marconi
and, secondly, against GEC Marconi Australia Pty Ltd.
The principal claim made
against GEC Marconi is that it repudiated the Sub-Contract when it purported to
terminate that contract
on 10 December 1996 and that BHP-IT, having accepted
that repudiation on 21 January 1997, suffered loss and damage in consequence:
"the Repudiation Claim". A subsidiary claim made is that GEC Marconi's conduct
fell within a provision of the Sub-Contract that
entitled BHP-IT to an
indemnity in respect of any liability it may have had to the Commonwealth under
the Head Contract that resulted
from the repudiation of the Sub-Contract: "the
Indemnity Claim".
832 The claim against GEC Marconi Australia Pty Ltd was for an indemnity under
a performance guarantee given by GEC Marconi Australia
for costs and expenses
incurred by reason of its failure to cause to be completed GEC Marconi's
undertakings under the Sub-Contract:
"the Performance Guarantee".
1. THE REPUDIATION CLAIM
833 The general character of this claim can be put shortly as follows. Against
the background of an emerging realisation of the
loss it was facing under the
Sub-Contract, and of its British parent company's objection to that loss, GEC
Marconi adopted a new
strategy in February 1996 which was designed to secure
either a renegotiation of the Sub-Contract that would have minimised its
prospective
losses, or else a termination for convenience which would allow GEC
Marconi to be paid for Milestone 4000 but which would relieve
it of any further
obligation to perform the Sub-Contract. The instruments employed to contrive
one or other outcome were (i) the
complaints of breach based on the
non-provision of STUBS (despite the Emulation Variation Agreement) and on the
non-payment of Milestone
4000 (though TRR was not completed) and (ii) the $8
million offer for performing CR3057. In implementing this strategy from
February
1996 onwards, GEC Marconi evinced an intention no longer to be bound
by the Sub-Contract. Its attempts to secure re-negotiation
having failed, GEC
Marconi's only option was to terminate the Sub-Contract. That termination was
wrongful and repudiatory.
834 To emphasise the impropriety of the repudiatory conduct, BHP-IT also
alleged that GEC Marconi breached its duty of good faith
and fair dealing in
giving the notice of termination. This is considered separately below: see
"Breach of the Implied Term".
(a) The Factual Setting
835 I have previously set out in detail both the circumstances leading to GEC
Marconi's entry into the Emulation Variation Agreement
with BHP-IT on 1
November 1995 and the evidence concerning the alleged achievement of Milestone
4000. Here I will only make passing
reference to aspects of that evidence.
836 Virtually from the inception of the Sub-Contract, GEC Marconi experienced
difficulties in reaching the stipulated milestones
(2000 and 3000) and in
advancing software development. By early 1995 it had become apparent that the
estimates of cost GEC Marconi
had made for Code and Unit Test activities
("CUT") were insufficient to meet the process commitments required by the SDP.
The "blow
out" in the CUT phase progressively lengthened anticipated delays and
progressively eroded GEC Marconi's margin for the project.
837 On 29 September Mr Wishart initiated a process of reassessing CUT effort
estimates. By early October he was reporting that "current
estimates" to
complete the Sub-Contract "show an increase of around 1640 person days".
838 A facsimile of Lindsay Pears to Roger Cooke of 18 October 1995 reported
that "the projected loss on ADCNET is causing a lot of
heartache for EASAMS
Division, GMS Directors, and the UK". Pears directed Roger Cooke (inter alia)
to "[a]ccelerate the hire or
contracting of a Project Manager" while retaining
the services of Peter Wishart in a technical capacity and to complete the
estimation
process "using a sound estimating methodology, independent internal
and external consultants ... to validate estimates, and prepare
a contract
review by 27Oct1995". The facsimile concluded:
". I want to know why the sudden announcement of increase in costs of this magnitude, and an understanding of lessons learnt by the team (I suspect I already know what they will be).
. What assurance will I have that we do not end up with a $2M loss?
The bottom line is that the company is not prepared to carry a potential loss of $1M or greater. There will be no place for adversarial views about the ... input from independent reviewers.
Please discuss as soon as possible. Since the stakes are so high, we expect a prompt response from the Canberra team and strong sense of commitment to control the damage and reverse the situation where practical. As recently discussed, there are no soft landings with this overrun, but you will receive the support required to resolve this problem. Let me know what help or support you need."
839 The Emulation Variation Agreement was entered into on 1 November 1995.
Shortly afterwards, Mr Pears was replaced by Mr Sharp as
General Manager.
840 A Project Overview report of 9 November 1995 showed (inter alia) that "the
Contract had deteriorated by $1164K and now shows
a loss of $657K" and that
project completion was to be extended from July 1996 to November 1996. The
principal cause of these results
was the underestimation of the CUTS phase.
841 On 27 November 1995, Mr Sharp had a meeting with Mr Brent. Brent recorded
the matters discussed in a letter to Mr Sharp of 5
December. Though I have
referred to this letter earlier in these reasons, I need to restate part of
it:
". EASAMS schedule - you indicated that EASAMS was moving it's ADCNET project control mechanisms to a more rigorous project control regime. We agreed that EASAMS will provide a month-end schedule of the ADCNET project each month to BHP IT beginning with the month of November, 1995;
. EASAMS estimate to complete - you indicated that EASAMS propose to have an independent estimator conduct a full re-estimate of the work remaining. These estimates will be calibrated against work completed to determine the accuracy of the estimate;
...
. STUBS - you indicated that EASAMS would produce a formal priced proposal for the replacement of STUBS by 22 January, 1996. In this context we discussed options for ensuring smooth passage to the proposal. We agreed that full visibility of the following elements of the proposal would be made available to DFAT:
- full rationale supporting the estimates including levels of effort, impact on CSC's, development status of CSC's etc, etc;
- full description of identified risks.
I found the meeting to be productive and propose that we continue to meet on a regular basis - I suggest once a month - to review the position on the ADCNET program."
842 To move ahead somewhat, according to Roger Cooke, the independent
estimation foreshadowed in the letter was completed during December
1995 or
possibly January 1996. That re-estimation concluded that there was a schedule
slip of 12-18 months and a cost deterioration
in the order of $4.335
million.
843 I would note in passing that across December 1995-January 1996 preparations
were in train for, and comments were being made on
draft documents for, TRR
which was scheduled for January and then rescheduled to occur in February 1996.
I would equally note that
the STUBS emulator was demonstrated and then paid for
in the first half of February 1996.
844 Following a transitional period in late January 1996, Mr Goldsmith replaced
Peter Wishart as GEC Marconi's Project Manager.
845 Some time in February 1996 Mr Sharp had prepared an "ADCNET Project
Overview" for the English parent company. Its Executive
Summary referred
(inter alia) to the schedule slip and cost deterioration noted above and
continued:
"In an attempt to mitigate the forecast cost and schedule exposure, EASAMS is negotiating with BHP-IT and DFAT a proposed amendment to the Contract, whereby the Contract is essentially terminated at this time and a time and material rate set for a 3-4 month period to allow an agreed and new technical baseline to be established. After this period EASAMS would then consider a new fixed price contract which recognised the understood technical scope, risk and schedule constraints at that time.
Given the current state of negotiations a best case scenario for the contract would be a break-even and a worst case a loss of $4317K with the potential under a delay claim to negotiate a settlement to break-even or a small margin. The business is looking to provide a firmer view by the 12th April for inclusion in year end accounts."
846 In mid-February a series of communications passed between Mr Wishart and
then Mr Goldsmith on the one hand and (ultimately) Les
Cook on the other
concerning proposed amendments to the FRS for the purposes of CR3057 and the
STUBS replacement. On 19 February
Mr Goldsmith wrote to Mr Brent indicating
that GEC Marconi's analysis of DFAT's comments on the draft FRS changes, "has
shown that
DFAT has introduced a significant new requirement at FRS
4.1.4 which may have a major impact upon the design architecture": emphasis in
original. It said this requirement
"effectively alter[ed] the scope of the CR
scoping task" and that the agreed timetable for completing the CR3057 scoping
could not
be adhered to.
847 On 20 February 1996 Les Cook wrote to Mr Brent responding to GEC Marconi's
assertion that DFAT had introduced a new requirement
into the FRS. He disputed
that assertion; he noted that he raised the need for this change in paragraphs
8 and 9 of his minute
"STUBS Replacement - Design Principles" of 8 November
1995 (which was an attachment to CR3057); but to avoid further delay he
requested
that that proposed change to the FRS be deleted.
848 On 19 February 1996 Mr Goldsmith sent a facsimile to Mr Sharp (which was
copied to Roger Cooke) that was headed "Recent Developments
ADCNET". It was as
follows:
"There have been a couple of developments which impact our strategy since Friday.
STUBS Change Request - Late Friday, discovered a significant change to requirements as a result of comments from DFAT. This impacts the scope of the CR by 10% to 30% over previous estimates. In addition, it also adds further to the uncertainty. Kyrill is pushing real hard for our formal input by tomorrow. He expects a fully costed proposal with a new schedule.
TRR - After discussions with Kyrill and DFAT on Friday, I had our team front up this morning for the TRR we had scheduled. I made statement that our Contract, being the superior document in the case of conflict, called for a TRR consisting only of review of 3 documents. That whilst we were late with the TRR according to the original schedule, we had done our best and had given proper notice of the TRR to be held today. Made the point that until Contract amended to resolve conflict with SDP and to split document reviews from TRR, the Contract and the Milestone payment had to be observed for formal contractual purposes. Then having made contractual point, stated that we would co-operate in defining what docs should be reviewed and when so as to fit in with our schedule whilst easing DFAT's task.
...
I hope that this has preserved our position with respect to being in a position to claim the milestone payment.
ACTION
I don't know how much longer I can keep the lid on this volcano! I recommend that we blow the whistle rather than any of the other players ... it should strengthen our position at BHP IT's expense.
I suggest we should advise Kyrill today that the comments on STUBBS received from DFAT have a significant impact which is yet to be assessed. This could bye us a couple of days.
We can provoke a showdown via STUBBS if and when you wish by simply going back to Kyrill with a ROM price of say $2.5M and a schedule impact of say 9 months above our latest estimates.
This however offers to put the initiative back to BHPIT who could blow the whistle. I still think that it is to our advantage to take that action once it is cleared. I think it would put us in a better light with senior management of DFAT and make BHPIT look worse. With the election looming, the DFAT senior management cannot be feeling too complacent." Emphasis added.
849 It was Roger Cooke's evidence that he thought that "this volcano" was a
reference to the price of CR3057. Mr Sharp could not
recall seeing the
facsimile at the time. Mr Goldsmith did not give evidence.
850 On 22 February 1996 Mr Goldsmith provided Mr Sharp with briefing
information for the meeting to be held the next day with BHP-IT.
Mr Goldsmith
indicated that the then proposed "minimum selling price" for CR3057 was
$3,665,171. In arriving at this figure a "200%
factor" was applied to the CSU
Test Estimates "as a result of a sanity check after the fashion requested by
Samy". I will refer
below to the escalation of the estimates for CR3057.
"Samy" appears to have been a GEC Marconi software engineer. The briefing
information
concluded with the observation:
"BHPIT and DFAT have to be made to realise that the current contract was not ever practical it did not have a sound base. This is not earth shattering. Such mistakes do happen and at least it has been recognised fairly early. The problem needs to be addressed professionally and maturely."
851 It was at the 23 February meeting that Mr Sharp first indicated to Mr
Brent (i) that the non-provision of STUBS might constitute
a default under the
Sub-Contract; and (ii) that GEC Marconi was proposing renegotiation of the
basis of the Sub-Contract. This
meeting, according to Mr Sharp, constituted
the "negotiations with BHP-IT" referred to in his overview paper to the British
parent
company.
852 Sometime after this meeting but before the end of February, Mr Goldsmith
was requested by Mr Sharp to search for documents concerning
the STUBS
emulation agreement. He found Mr Wishart's 16 October 1995 memorandum to Mr
Breden and his 22 November 1995 response to
Mr Cook's comments on the API
Specifications for the STUBS emulator (on these documents, see Part II: The
Emulation Variation Agreement,
(a) Additional Factual Material). These
communications both envisaged the use of emulation for acceptance testing. In
drawing these
to Mr Sharp's attention in a facsimile of 1 March 1996, he went
on to express the view:
"Basically I don't think you have a viable case to say that the system wont work if it is tested against the emulator. I also don't think that you can make much of a case that DFAT can't use the system without STUBS. It is their risk."
853 Mr Goldsmith again communicated with Mr Sharp by facsimile on 4 March 1996 concerning the FRS. The opening paragraph was as follows:
"The original RFT has many references to the need for gateways to other networks. However, the contract has the usual `this agreement supercedes all previous ...' clause. The FRS also has many references to the same requirement and to it being effected by STUBS. Tim can provide a list of FRS Para references. Thus you have good grounds to make your point regarding the thrust of the contract." Emphasis added.
After indicating that he assumed "one of the players in this affaire will get hurt" and that "on the theory of the sacrificial lamb [GEC Marconi] might be advised to side with DFAT", Mr Goldsmith went on to set out a lengthy list of key issues demonstrating (amongst other things) that the contract was unworkable and required significant change and that a T and M contract was to be preferred as "DFAT takes all the risk". He concluded:
"4. If DFAT/BHPIT still refuse to accept that there is a severe problem then we can raise a heap of questions on the FRS and link delay claims to each one basically claiming 100% delay for each item.
5. You should be aware that testing of Build 2 has yet to commence. There appears to be a non trivial incompatibility between what the developers produced and what the testers expected. I have discussed organisational and process changes which would mitigate against this occurring again. However, I have yet to commence instigating radical change. Basically, I'm adopting a business as usual approach but I guess that will only remain viable for a matter of days. After which we will be exposed if BHP IT blow the whistle first."
854 On 8 March 1996 Mr Goldsmith wrote to Mr Brent concerning CR3057. It said in part:
"Because of the very high risks identified in the [accompanying] risk analysis, EASAMS is not prepared to offer a price for this CR in isolation. As previously discussed, EASAMS will wish to offer a price recognising Customer induced delays and frustrations of the Contract suffered by EASAMS to date."
855 The invoice for Milestone 4000 was issued on 12 March 1996. As I earlier indicated, Mr Sharp had no belief at the time that all of the money was due and he accepted that the issuing of the invoice was a ploy to increase commercial pressure on BHP-IT and the Commonwealth. Mr Goldsmith, who forwarded the invoice to BHP-IT, was later to write to Mr Breden (8 May 1996):
"1. The main reason I suggested the invoice was to provide a vehicle for payment in the case BHP IT/DFAT did want to take up our original offer to determine the contract and move to a T&M phase. That payment would have brought us out about square and would have provided an easier mechanism than having to negotiate a termination settlement.
2. Nonetheless, there is some logic in the assertion that as the Contract takes precedence, the TRR as loosely defined in the contract was met by the documentation reviews and is applicable over the tighter definition in the SDP which does not appear to be a formal deliverable itself and therefore has less standing."
856 On the same day in a report prepared for Mr Sharp for transmission to the British parent company, it was stated under the heading "Opportunities":
"The cancellation of the STUBS device and the central importance of STUBS to the "raison d'etre" of ADCNET provides the opportunity to renegotiate the contract. Rectification of Contract input documents eg the FRS and adoption of realistic schedules will reduce risk to acceptable levels (we are effectively sole source) and more equitable Terms and Conditions.
High risk elements of the project will be moved outside the fixed price activities.
The project duration and price will be significantly increased." Emphasis added.
857 Again on 12 March Mr Sharp sent Mr Brent GEC Marconi's proposals in relation to the non-provision of STUBS and DFAT's replacement strategy. The proposal document rehearsed GEC Marconi's arguments that were to loom large across the ensuing months. I refer to two matters in particular. These were:
"d. The Customer can not unilaterally remove from the Contract the requirement of the Customer to provide STUBS CSI.
e. The Customer's view that "STUBS Emulation" as developed by EASAMS under CR3049, is sufficient to allow completion and deployment of ADCNET is not accepted by EASAMS. STUBS Emulation was intended to be used to enable Code and Unit Testing and Integration to proceed until the STUBS replacement strategy was completed. The enclosed two engineering papers raised internally by EASAMS engineers outlining the shortfall in proceeding the Contract to conclusion with STUBS Emulation (Ref 10) support this view from an engineering perspective."
The alternative ways forward remained termination or renegotiation on
payment of Milestone 4000.
858 I have already referred to the "minimum selling price" of CR3057 on 22
February as being $3,665,171. By 27 March that price
had increased to
$5,229,803. Each of the two calculations was made by reference to spreadsheets
that set out base figures referring
to days for particular activities to which,
in both instances, were applied additional percentage increases reflecting (i)
an "80%
confidence level for the estimate" and (ii) the "200% Samy sanity
check". I would note in passing that BHP-IT has made much of the
additional
percentages and the compounding effect of their use in both spreadsheets.
859 On either 27 or 28 March a review meeting for the CR3057 costings was held.
It was attended by Mr Sharp, Mr Becker and "Samy".
I would note in passing
that the evidence of Samy's role both in this meeting and in relation to the
evolution of the CR3057 estimates
is quite unsatisfactory. While I accept that
at some period prior to the February estimates Samy suggested a "200% sanity
check"
in relation to the base figures then being used, I do not consider it
safe to rely upon any of the evidence given by Mr Becker or
Mr Sharp concerning
Samy's involvement in this matter.
860 At the review meeting, a further uplift factor of 20% was applied to the
cost price. Mr Becker said this was necessary because
there were still "a
number of unknowns in regard to KIV-7". Additionally he and Mr Sharp agreed to
add a further million dollars
- an "off-the-top-of-the-head" figure according
to Mr Sharp - to produce a rough order of magnitude figure of $8 million. Mr
Sharp
acknowledged that figure was a "rough order of magnitude guess",
estimates coming in various guises.
861 On 28 March 1996 GEC Marconi sent its CR3057 proposal to BHP-IT. It did
not offer a firm price. Rather it merely advanced its
rough order of magnitude
figure of $8 million to complete the contract. It indicated that it regarded
the non-provision of STUBS
and the proposed use of KIV-7 as involving an
attempt to pass significant and additional risk to GEC Marconi. It also noted
that
the clarity and integrity of the FRS was questionable. It proposed that
the contract be terminated at Milestone 4000 and that a
Critical Design Review
then be held to achieve a new baseline.
862 Mr Brent indicated to Mr Haddad on 28 March that the GEC Marconi proposal
was unacceptable to either BHP-IT or the Commonwealth.
On 1 April in further
commenting to Mr Haddad on the proposal he indicated:
"The indicative value of $8 million is 150% of their contract and is grossly exaggerated in my view. I do accept that significant rework is required associated with STUBS replacement but not of that order of magnitude.
I can find no rational basis for the estimate."
863 At a tri-partite meeting held on 2 April to discuss GEC Marconi's
proposal, the Commonwealth indicated (according to Mr Skinner's
email of the
same day) that the proposal appeared unacceptable but would formally respond
when it received GEC Marconi's formal offer.
It did indicate, though, that if
it did not proceed with CR3057 DFAT would complete the contract "as it was
currently written" using
the emulator and then replacing the emulation software
at a later date.
864 On 2 April GEC Marconi sent two "lawyers letters" to BHP-IT formally
stating its position on a number of matters. On 3 April
the first Notice of
Breach was served. On 11 April BHP-IT in turn served a Notice of Breach on the
Commonwealth. BHP-IT responded
to GEC Marconi's Notice on 17 April.
865 As earlier indicated, in his 12 March proposal document to BHP-IT Mr Sharp
referred to technical difficulties in the way of using
the emulator for
acceptance testing. It seems that around this time he had requested two
members of GEC Marconi's project team -
Mr Harris and Mr Varatharajan - to
identify deficiencies in the emulator built by GEC Marconi. In the event, a
document which came
to be entitled "Summary Review of STUBS Alternatives" was
produced in final form around 30 May 1996, after going through at least
one
(and probably two) previous iterations. A 14 May version is also in evidence.
I do not intend to outline the contents of these
documents other than to note
that both the 14 May and the 30 May documents contain an explicit reference to
waiver of FRS requirements.
The 14 May version was in terms that:
"It has been verbally stated by the Department that they will waiver any requirements that cannot be tested using the emulator. Until we see the requirements that will be waived we cannot make a reasonable judgement."
The 30 May version was in substantially similar terms. I would emphasise the
14 May version as it predated a meeting of 20 May with
BHP-IT and DFAT to which
reference is made below.
866 Both Mr Harris and Mr Varatharajan accepted that there was no technical
reason why the ADCNET contract could not be completed
using the emulator
provided the documentary requirements that were obstacles to completion were
either changed or waived.
867 On 17 May, Mr Vile of BHP-IT had a telephone conversation with Les Cook
following a talk he had had with GEC Marconi management.
Mr Cook's note of
that conversation, though of some length, warrants quotation in almost its
entirety. It reads:
"2. Mr Vile stated that he had talked further with EASAMS management. EASAMS were no longer planning to provide a document claiming that, with only STUBS emulation, the developed software would be unusable and that the Functional Requirements Specification was unbuildable. EASAMS had agreed that the issues were now only `money and principle'.
3. Mr Vile considered that the `principle' was that DFAT had failed to provide STUBS and that this had or would in some way cause harm to EASAMS.
4. Mr Vile asked whether DFAT had decided that it will use the developed software, with STUBS emulation, together with the existing IBM system when deploying release 3.
5. Mr Cook stated that there would be a two stage cutover. The first stage would be as has always been intended, including both ADCNET and the IBM system running in parallel. Communications lines to posts, regional offices, other agencies will be transferred progressively to the ADCNET message switch and the 800 or so ADCNET users in DFAT Canberra will be progressively transferred from Release 1 systems to the Release 3 Canberra node. At the end of the first stage, the role of the IBM will have been reduced to providing connection to the few external communication lines to non-secure systems and to X400 and NNS networks. The second stage would be to replace the IBM with an implementation of sealing and gateways, replacing STUBS emulation. DFAT will decide when and how to achieve this, but it will not be in the scope of the current contract.
6. Mr Vile asked whether DFAT is prepared to state formally that this is its intended plan. Mr Cook said that DFAT would probably agree to this, subject to legal advice.
7. Mr Vile proposed that a meeting be sought with EASAMS management to attempt to resolve any outstanding technical issues. Mr Cook replied that DFAT would probably agree to such a meeting."
868 The proposed meeting occurred on 20 May. The two principal discussion
items for the meeting were, according to its agenda (i)
DFAT's strategy for
deployment of ADCNET without STUBS and (ii) GEC Marconi's problems in
interpreting the FRS. Les Cook did not
keep notes of the meeting but he used
three overheads to illustrate DFAT's deployment strategy.
869 Mr Sharp gave evidence that at this meeting Les Cook said something along
the lines that he was prepared to discuss the potential
waiver of FRS
requirements. Mr Brent's evidence was that "waivers" were referred to at the
meeting.
870 On 21 May 1996 a GEC Marconi engineer, Ian Otto, prepared a memorandum
concerning the STUBS emulator. That memorandum, apparently
unlike the "Summary
Review" paper, was prepared with knowledge of Les Cook's 13 November 1995 and
Mr Wishart's 22 November 1995 exchange
concerning the emulator. I would note
in passing that Mr Varatharajan conceded in cross-examination that he had never
been shown
Mr Wishart's letter of 22 November while Mr Harris said he believed
he would have seen it some time in 1996. The conclusion arrived
at by Mr Otto
was that:
"The STUBS emulator as specified is an incomplete solution to the problem of emulating the STUBS device and does not allow us to test all code paths without either changing our software (which defeats the purpose of the emulator) or making substantial modifications to the emulator."
Mr Sharp gave evidence that he saw this memorandum about the time it was prepared. For completeness I would add Mr Otto prepared a further memorandum on 15 July 1996 giving "a software engineer's view" of the ADCNET project. In it he made the observation:
"5. The Impact of STUBS
Non-delivery of the STUBS device and use of the STUBS emulator does have an impact on the project. It will cause us to rework a number of documents and make a number of code changes. Compared to the other problems on the project however, it is fairly minor."
Again Mr Sharp acknowledged he had seen this memorandum around the time it
was prepared. Mr Otto did not give evidence in this proceeding.
871 On 22 May 1996 the Commonwealth formally indicated to BHP-IT that it did
not consider the CR3057 proposal to be acceptable and
it would not approve it.
872 On 28 May 1996 Mr Brent wrote to Les Cook seeking his advice on, amongst
other things, what DFAT intended to do about obligations
defined in the
contract and the subsidiary documentation which still depended on the delivery
of STUBS. Mr Skinner of DFAT replied
on 30 May proposing a list of document
changes "to remove any ambiguity arising from the use of STUBS emulation". I
would note,
as it has been relied upon by GEC Marconi , that the letter
contained the following sentence:
"DFAT requires BHP IT to deliver software in accordance with the existing contract, including the use of the STUBS emulation software to perform the functions which were to have been performed by STUBS equipment and software."
BHP-IT forwarded this letter to GEC Marconi on 3 June.
873 On 18 June GEC Marconi responded to Mr Skinner's proposed document changes.
It regarded these as a proposal to vary the contract
and it rejected this,
though indicating that it was "prepared to use reasonable endeavours to reach
agreement". It then set out
at length its reasons for rejecting the proposal
which it said would by now be "well-known to you having regard to the range and
depth of correspondence passing between us on the failure of BHP IT to supply
STUBS as CSI". Attached to the response was a copy
of the "Summary Review of
STUBS Alternatives". On the same day the second Notice of Breach was served on
BHP-IT.
874 The response and the attachment were forwarded to DFAT on 25 June 1996.
DFAT responded by letter to BHP-IT of 18 July rejecting
the arguments advanced
in the "Summary Review" paper which it described as "irrelevant, invalid or
both". It provided by way of
attachment an eight-page commentary on the paper
and its alleged errors. There is a dispute between the parties as to whether
DFAT's
18 July comments on the "Summary Review" paper was ever forwarded to GEC
Marconi.
875 BHP-IT provided its own response on 22 July 1996. It reasserted it had no
contractual obligation to provide STUBS and that GEC
Marconi was obliged to use
the emulator for acceptance testing. It went on to observe:
"Candidly we regard the allegations concerning STUBS as a diversionary tactic. You have stated that GEC's real concern is that it has lost money on Phase 2 work and that you believe this will continue when the project progresses.
We confirm that we expect GEC to meet its contractual obligations and we have taken extensive legal advice to the effect that this is a reasonable expectation."
876 The final document to which I need refer is a report in September 1996, from GEC Marconi to its British parent. It contained the following:
"The current instruction/position of BHP-IT and supported by DFAT is:
(a) GMS Pty to complete development of software as contracted and where necessary BHP-IT/DFAT will provide waivers for testing aspects associated with STUBS." Emphasis added.
877 The only additional factual material to which I need refer - contained
primarily in oral and written evidence of witnesses - relates
(a) to whether Mr
Sharp received Les Cook's 18 July comments on the "Summary Review" paper; and
(b) to the issue of waivers of FRS
requirements.
878 First, Les Cook's 18 July comments. Mr Brent, who was the addressee of the
Skinner letter enclosing the comments, had no recollection
of passing the
document on to GEC Marconi. Mr Sharp's original oral evidence was that he
received and read the comments and that
he believed he asked Mr Harris and Mr
Varatharajan to review their original report in light of Mr Cook's response.
He later indicated
he could not recall forwarding the comments to them or
receiving a response. During a luncheon adjournment in re-examination he
was
asked by GEC Marconi's legal representatives to read the comments document and
to consider when and in what circumstances he
first read it. His evidence is
that in so doing he realised he was mistaken and that he had not seen the
document but rather the
document he had in mind was the attachment to Ms
Beattie's letter of 3 June (which was Mr Skinner's letter of 30 May which
outlined
the documentation changes proposed by DFAT). On the resumption of his
re-examination he was again asked about the comments document
and he said he
believed it was a document that came under cover of a letter from Ms
Beattie.
879 Mr Sharp later prepared a witness statement concerning the above. He was
permitted to be recalled and gave further like evidence
concerning the
comments. For reasons I give below, I do not intend to outline his further
evidence in any detail other than to note
two matters: (i) He acknowledged
that he had read the Skinner 30 May letter many times in 1996 and "up until
now"; and (ii) In
relation to the comments paper, he accepted he may have seen
it but could not now remember.
880 Secondly, the evidence on waiver of FRS requirements. By way of background
to this I simply note (a) the references to waiver
in the 14 and 30 May
versions of the "Summary Review" paper and (b) the September 1996 GEC Marconi
document that indicated that "BHP-IT/DFAT
will provide waivers for testing
aspects associated with STUBS".
881 Les Cook's evidence is that he would not have taken the decision to waive
FRS requirements on his own. He would have made a
recommendation to the
Department. But he had no recollection of discussing possible waivers in 1996.
I would note in passing that
the 30 May 1996 DFAT letter on documentation
changes was signed for DFAT by Mr Skinner. In cross-examination by Mr Simpkins
SC,
Les Cook gave the following answers:
"Q. And you never sought, did you, to engage in a process of identification of appropriate amendments [of the FRS] with BHP-IT or GEC; isn't that right?
A. I think my original 1996 response to the [Summary Review] paper made it clear that the emulation should have been sufficient to do acceptance testing. Had I been asked for waivers, as were later agreed, I believe I would have agreed to them.
Q. I just want to ask you about the position you adopted in 1996. Your position in 1996 was that you were personally not prepared to entertain amendments or waivers because of the view you held that the emulator, as constructed, ought properly be sufficient to take this project to acceptance testing completion?
A. I thought no waivers were essential."
I would note, additionally, that when he prepared his witness statement for
this proceeding Mr Cook had no recollection of producing
the 18 July comments
paper and in fact he prepared a paper in 2000 in reply to the Summary Review
paper.
882 Mr Brent's evidence was that at the 20 May meeting Les Cook referred to
waiver of FRS requirements for acceptance testing using
the emulator. That
evidence was more unequivocal as to timing than was his witness statement which
referred to the 20 May meeting
"or at another discussion ... about this time".
He equally gave evidence that the concept of waiving was mentioned in other
forums
and was "an established precedent on the project" but he could not
recall any discussions about waiving requirements for acceptance
testing prior
to 20 May 1996.
883 As to his 28 May 1996 letter and its request of Mr Cook concerning what was
intended to be done about obligations in the contract
and subsidiary documents
that depended on the delivery of STUBS, Mr Brent said that the sentence in
question did not necessarily
address the waiving issue and probably addressed
contractual issues. I would interpolate I regard this and related evidence on
this
letter as involving no more than reconstruction on Mr Brent's part as he
acknowledged.
884 Mr Harris' initial evidence was that he did not know by May 1996 that Les
Cook had made clear that DFAT was prepared to waive
or amend any requirements
that could not be tested with the emulator. He was aware that Les Cook knew he
had the option of change
requests and waivers open to him but not that the
Commonwealth intended "to do such a thing". At the end of his
cross-examination
he accepted that Les Cook verbally said to him that DFAT
could waive FRS requirements. While he could not recall exactly what was
said
it would have been something along the lines of that "the Department would
waive any requirement in the FRS that could not be
tested using the
emulator".
885 Mr Varatharajan's evidence on the matter is contained in the following
exchanges:
"Q. You knew that the position of the Department of Foreign Affairs & Trade was that either it was prepared to change requirements that could not be met by the emulator or, alternatively, that it would waive requirements that could not be met by the emulator, didn't you?
A. That would have been the only way to proceed with the contract. But I did not know that DFAT made any proposal to do either. I know that there were a number of things in train at that time. There was nothing that was agreed, to my knowledge, at that time."
He was then taken to the "waiver paragraph" of the "Summary Review" paper and
he accepted he knew to be the case what was stated
there. He went on, though,
to indicate that it would be difficult to work out what requirements needed to
be waived up front. He
accepted that what needed to be waived would become
apparent at systems integration. He also accepted that insofar as he knew, no
one on GEC Marconi's side followed up with DFAT what was going to be waived.
886 Mr Sharp's evidence on waiver fell into several parts. The first related
to the 20 May 1996 meeting. He accepted that Les Cook
said something "along
the lines that he was prepared to discuss the potential waivers" of
requirements in the FRS that might be obstacles
to completion using emulation.
He refused to accept an unequivocal offer of waiver was made in "black and
white terms". Secondly,
in reference to the September GEC Marconi document
referred to above, Mr Sharp accepted that he knew well before September 1996
that
BHP-IT/DFAT had offered to provide waivers for testing aspects associated
with STUBS emulation, if necessary, but that what were
to be the matters waived
had not been agreed. Thirdly, he said he believed on the basis of advice from
the project team that it
was not technically feasible to complete the contract
using the emulator as-built, although he had accepted that he was not told
this
by Mr Goldsmith, Mr Otto, Mr Varatharajan or Mr Harris. Fifthly on the issue
of agreed waivers, he accepted he did not once
go back to DFAT to ask
specifically what requirements it was prepared to change. He did suggest,
though, that he followed up this
matter with BHP-IT at meetings in the latter
part of 1996. The following passages are emblematic of this part of his
evidence in
cross-examination by Mr Marks (which I do not set out in full for
reasons I give below):
"Q. And you followed up with them, did you, as to whether these offers were still open?
A. I followed up with respect to aiming to have discussion with BHP and Foreign Affairs & Trade as to what could be achieved with respect to bringing the Contract forward.
Q. With some future - sorry?
A. Sorry, including what they aimed for us to do with respect to the use of the emulator to complete the Contract.
Q. But what I am really putting to you is this: you didn't endeavour to ascertain what requirements might be the subject of or could be the subject of waivers for testing aspects associated with STUBS; did you?
A. Not in simple terms.
Q. No. And in that sense you never sought to progress the matter to try and find out what waivers for testing purposes associated with STUBS might be eventually provided?
A. We were at a point in our understanding of the offer, as you call it, which was far more encompassing than some simple waivers. We had to further understand, and requested further meetings with Foreign Affairs through BHP, which were not forthcoming.
...
Q. Did you write to BHP asking BHP to clarify what requirements, if any, BHP or DFAT was prepared to waive for testing purposes associated with STUBS emulation?
A. I did not.
Q. Did anyone else, to the best of your knowledge, write such a letter?
A. I cannot recall."
He later gave evidence that he had advice from his "technical people" that
"the waivers needed further clarification and understanding
on our part to
understand how we could proceed with the contract".
887 On the related question of acceptance testing with the emulator, Mr
Becker's evidence is that there never was any plan to complete
the contract
using the emulation software because he understood from the technical people
that it could not be done. Roger Cooke's
evidence was that the emulator that
was built could not be used for acceptance testing. As I have already noted
both Mr Harris and
Mr Varatharajan accepted that, with appropriate documentary
changes, there was not technical reason why the Sub-Contract could not
have
been completed using the emulator.
(b) Applicable Principles
888 I need say little on the principles governing repudiation of a contract.
They are not in issue between the parties. I would
note the following.
889 (i) A party will have repudiated a contract if, by words or conduct, it
evinces an intention no longer to be bound by it or if
that party shows it
intends to fulfil the contract only in a manner substantially inconsistent with
its obligations and not in any
other way: Shevill v Builders Licensing
Board [1982] HCA 47; (1982) 149 CLR 620 at 625-626; Laurinda Pty Ltd v Capalaba Park
Shopping Centre Pty Ltd [1989] HCA 23; (1989) 166 CLR 623.
890 (ii) The party's conduct is to be judged objectively by reference to the
effect it would be reasonably calculated to have upon
a reasonable person:
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd, at 658;
Satellite Estate Pty Ltd v Jaquet (1968) 71 SR(NSW) 126 at 150.
891 (iii) A party that acts on a genuine but erroneous view of its obligations
under the contract will not for that reason alone
have repudiated it. That
party may still be willing to perform the contract according to its tenor; to
recognise its heresy; or
to accept an authoritative exposition of the
contract: DTR Nominees Pty Ltd v Mona Homes Pty Ltd [1978] HCA 12; (1978) 138 CLR 423
at 431-432; Woodar Investment Development Ltd v Wimpey Construction UK Ltd [1980] UKHL 11;
[1980] 1 WLR 277. But persistence in an untenable construction will
ordinarily be regarded as repudiatory: Summers v The Commonwealth [1918] HCA 33;
(1918) 25 CLR 144 at 152; and see Chitty on Contracts, vol 1, para
25-018 (28th ed).
(c) Submissions and Conclusions
892 I should indicate at the outset that I consider the present to be a clear
instance of repudiation. In light of my previous findings,
GEC Marconi had
contractually agreed both to the non-provision of STUBS and to acceptance
testing using the emulation software.
Equally, its claim to have achieved
Milestone 4000 was not only incorrect, it was colourable. GEC Marconi kept the
Sub-Contract
on foot with the objects in mind of securing either a favourable
renegotiation or a termination for convenience. When these proved
unachievable
it staged its own termination. Its conduct was not that of one adhering
genuinely to a mistaken interpretation of the
contract. Rather it manipulated
and knowingly misinterpreted contractual obligations and engaged in
disingenuous conduct to avoid
having to complete the then Sub-Contract which,
from at least July 1996, it had no intention of doing.
893 The starting point of GEC Marconi's submissions is that it is not enough
simply to show that it improperly terminated. If it
is shown to have acted on
a bona fide construction of the Sub-Contract, it must be asked whether the
termination was nonetheless
repudiatory.
894 Central to its submissions is the claim that it did nothing illegitimate in
availing of the opportunity CR3057 offered to renegotiate
the contract
self-interestedly to avoid apprehended losses. For this reason it attacks both
the concentration of BHP-IT and the
Commonwealth on the "strategy" adopted in
relation to CR3057 and the assertion that its CR3057 response was overpriced
and an attempt
either improperly to recoup losses or to escape the
Sub-Contract.
895 Its submissions go on to point to what it alleges was the importance to the
ADCNET project of replacing the IBM message switch.
As I understand the burden
of this part of the submissions, it relates to GEC Marconi's good faith in
erroneously insisting upon
the requirement that STUBS or a replacement be
provided. It characterised BHP-IT's insistence on use of the emulator as
involving
the non-fulfilment of the most important commercial objective
intended to be achieved by the ADCNET project.
896 Again inconsistently with my finding of an implied term in the Emulation
Variation Agreement that the parties would amend all
contractual documentation
to enable emulation to be used for acceptance testing, it submitted that the
contract would only be completed
by agreed variations to, or waivers of, the
FRS. It attacks both the manner in which "waivers" were said to have been
offered and
the lack of agreed waivers.
897 It relies upon the reasonableness of its own belief about technical
difficulties in acceptance testing with the emulator to rebut
the contention
that it acted unreasonably in terminating. In this it invites me to find that
GEC Marconi never received Les Cook's
18 July comments paper on the Summary
Review and in so doing to accept Mr Sharp's retraction of his evidence that he
had seen and
read that paper.
898 Before expressing my own view on GEC Marconi's submissions, it is
appropriate that I make reference to the witnesses who gave
evidence on matters
relevant to those submissions. First, I have derived little assistance from
Les Cook's evidence. I am not satisfied
that he has sufficient recollection of
any of the matters in question as would make it safe to rely on his oral or
written testimony.
He had no recollection of actions that he did take (eg
writing the 18 July comments) while he gave positive evidence on matters
of
which he had no recollection. Secondly, I again regard Mr Brent's evidence as
unreliable because of the danger that it reflected
no more than reconstruction,
although I have accepted his evidence on the offer of waivers. Thirdly, I have
serious reserve about
Mr Sharp's evidence on most matters for reasons of
credibility. He was often evasive. He was self-contradictory. And in
significant
respects his evidence was contrived. I consider it unlikely that
he had any actual recollection of some of the matters on which
he gave
evidence. I regard this as accounting for the difficulty he got himself into
in relation to Les Cook's 18 July comments
paper. Fourthly, I am not prepared
for reasons of credibility to rely upon Mr Becker's evidence particularly
as it related
to the pricing of CR3057. Finally, and importantly, I attribute
obvious significance to the failure to call Mr Goldsmith. He was
the author of
important documents the precise signification of parts of which was not always
apparent (eg the "volcano" facsimile).
He was a significant actor in events
from February to at least April 1996 and was capable of throwing light upon
them.
899 Turning to my own conclusions, I consider that the events which occurred
from early February 1996 onwards need to be viewed in
light of the changes in
GEC Marconi's management that immediately preceded them. Mr Wishart and Mr
Pears had been replaced by Mr
Goldsmith and Mr Sharp, neither of whom had had
any involvement in CR3049 and the agreements and understandings engendered at
that
time.
900 It is not open to doubt that, faced with the prospect of a ballooning loss
on the Sub-Contract, GEC Marconi management evolved
a strategy in February 1996
to protect its own interests - a strategy which appears, moreover, to have been
developed with little
understanding of the commitments and representations made
by GEC Marconi in November 1995 (and acted on thereafter) in consequence
of the
cancellation of STUBS. Its focus was securing the renegotiation of the
Sub-Contract and the establishment of a new technical
baseline. To induce such
a renegotiation GEC Marconi needed to be in a position to be able to exert
pressure on BHP-IT and DFAT.
For this reason, I infer, GEC Marconi sought to
exploit opportunities (available to it or manufactured by it) to create an
environment
favourable to its end. I am satisfied that for the purpose of
giving itself the apparent capacity to terminate the contract it raised
both
the issue of the non-provision of STUBS and the non-payment of Milestone 4000 -
although I do not consider that GEC Marconi's
commercial objective or intention
initially envisaged termination, notwithstanding this was one of the way
forward options put in
its 12 March proposal to BHP-IT.
901 Insofar as concerns the non-provision of STUBS, I do not consider that when
this matter was first raised in February 1996, it
was done so in the genuine
and reasonable belief that the obligation to supply STUBS remained. Whatever
might have been the understanding
of individual members of the project team, I
am satisfied that it was a contrivance sanctioned by Mr Sharp for his own
strategic
purposes. It is unsurprising that the February "negotiations" with
BHP-IT he reported to his British parent company were no more
than the meetings
in late February in which the STUBS "announcement" was made to BHP-IT and the
Commonwealth.
902 I equally am satisfied that Mr Sharp sought to provide apparent
justifications for his stand on STUBS and he appears to have
used Mr
Goldsmith's services to provide such evidentiary support as could be garnered
to this end - as witness Mr Goldsmith's facsimile
of 1 March 1996 (on the
search for documents relating to the partial emulation of STUBS) and of 4 March
(on the "thrust of the contract").
I am not satisfied that the view taken by
GEC Marconi as to the purpose of the STUBS emulation reflected a considered
appraisal
of its intended and agreed purpose. Rather it was an expedient one
to be exploited in the circumstances whether or not it was correct.
Nor am I
satisfied that the importance Mr Sharp sought to attribute STUBS in the ADCNET
project was inspired by a genuine belief
that such was the case. GEC Marconi
itself had offered in 1995 to complete the contract without STUBS.
903 By his own admission, Mr Sharp used the invoicing for Milestone 4000 as a
ploy to increase commercial pressure on BHP-IT while
not believing that all of
the milestone money was due.
904 Steps which I consider were taken or contemplated for the purpose of
inducing a renegotiation were (i) the refusal to put forward
a firm price for
CR3057 and the provision of a rough order of magnitude figure of $8 million to
complete the contract; (ii) the
advancing of technical arguments to
demonstrate that the emulator could not be used to complete acceptance testing;
and (iii) the
accentuation of the deficiencies of the FRS as evidenced in Mr
Goldsmith's 4 March facsimile foreshadowing the raising of "a heap
of questions
on the FRS" each linked to 100% delay claims, "if DFAT/BHP-IT still refuse to
accept there is a severe problem".
905 The response to CR3057 was, I consider, clearly tactical. All that was
offered was a renegotiation proposal and a rough order
of magnitude figure to
complete the contract in the way proposed. I accept that the introduction of
KIV-7 into the ADCNET project
via CR3057 would have involved a significant new
risk and that GEC Marconi, if conscientiously preparing a costing, would have
made
provision for potential risks as best it could as a matter of professional
judgment. I equally accept that GEC Marconi's previous
estimating for the
Sub-Contract provided a salutary warning to it. While I have no reason to
conclude that the individuals who compiled
the raw figures for the estimates
were acting other than conscientiously in what they were doing, I am not
satisfied that the process
engaged in by Mr Sharp, Mr Becker and Samy on 27
March 1996 represented a bona fide attempt at estimation of cost to complete.
The
evidence of Mr Sharp and Mr Becker, which was on occasion inconsistent and
which was unsupported by documentary proof, was quite
unconvincing. It was
made the more so by the roles they assigned in the matter to "Samy" (he was
never graced with a surname).
I consider that the sum arrived at was
considerably and designedly inflated in GEC Marconi's favour for the purpose of
later possible
loss recoupment; that it was not expected that it would be
accepted in principle - the first Notice of Breach was served within
days of
the CR3057 response being sent to BHP-IT; and that it was advanced in
furtherance of the strategy of securing a contract
renegotiation. I do not
find it at all surprising that it was found to be unacceptable by BHP-IT and
the Commonwealth. It is noteworthy
that, at the 2 April 1996 meeting where GEC
Marconi explained its proposal, the Commonwealth apparently indicated that if
it did
not proceed with CR3057 it would proceed with the contract "as written"
accepting the software with the emulation and then replacing
the emulation
software at a later date.
906 The raising of technical objections to the use of the emulator for
acceptance testing was, I consider, a tactical move by GEC
Marconi aimed at
accentuating the need for further agreement between the parties before the
contract could be completed. But it
was an unusual move. GEC Marconi had
agreed to build an emulator for acceptance testing. Mr Wishart had twice
confirmed this, most
importantly for present purposes in his 22 November 1995
response to Les Cook's 13 November 1995 letter. Neither Mr Varatharajan,
nor,
probably, Mr Harris were aware of this response at the time they prepared their
Summary Review on which GEC Marconi has placed
considerable reliance. Both,
though, considered that with appropriate waivers or amendments, the emulator
could be used for acceptance
testing. The Summary Review paper has been
accorded a status in this proceeding that it does not warrant. Given what GEC
Marconi
contracted to, and represented it would, do with emulation in November
1995, the paper sits oddly to say the least both with the
responsibility it
then assumed and with its own action in building the emulator. Furthermore the
paper acknowledged explicitly the
offer of waiver of requirements that could
not be tested using the emulator.
907 I am satisfied that Mr Sharp, having commissioned the development of the
paper, was content to exploit its conclusions for his
own purposes. I do not
consider that he was relying upon the paper to justify some personal belief
that there was a significant
obstacle to the completion of the Sub-Contract.
He was aware of Mr Otto's contrary view that with modifications the emulator
as-built
could be used for acceptance testing. And he was aware prior to the
final version of the paper of 30 May 1996, that the Commonwealth
was offering
waivers - a subject to which I will return below. I likewise do not consider
the question whether GEC Marconi received
Les Cook's 18 July comments paper to
be of particular moment. I am satisfied that by mid-July, if not considerably
earlier, GEC
Marconi had decided it would not complete the contract using the
emulator and was acting accordingly.
908 I accept Mr Sharp's evidence that he could not recall whether or not he
received the comments paper. However, I do not accept
the reason he gave for
mistakenly agreeing he had received it. This said, I am unprepared to find
that the Cook paper was forwarded
to GEC Marconi. Mr Brent had no recollection
of passing it on. By mid-July, Ms Beattie and Mr Haddad were also
communicating with
GEC Marconi on BHP-IT's behalf. There was in this
arrangement the prospect for oversight. The comments paper was not amongst the
documents produced by GEC Marconi on discovery. In this state of affairs one
can only speculate.
909 One additional matter in relation to emulation should be noted. In his 30
May 1996 letter Mr Skinner used a sentence which could
be taken as suggesting
that the emulation software was to perform the functions which were to have
been performed by STUBS equipment
and software. Considered against a
background of the 26 September 1995 letter, CR3049 and the building of the
emulator, I do not
consider it would have been reasonable for GEC Marconi to
have assumed from this alone that the long understood purpose of the emulator
had been changed. If it had any doubt on this matter it could have sought
clarification. Mr Sharp's attempt to exploit the sentence
in question in his
18 June response to the 30 May letter was disingenuous.
910 With the formal rejection of the CR3057 proposal by the Commonwealth in
late May an important outstanding matter was that of
amendments to, and waivers
of requirements in, the contractual documentation to permit acceptance testing
with the emulator. Putting
to one side what I have found to be the actual
contractual obligation of the parties in relation to the documentation and
focussing
solely on their respective stances and actions, I consider it to be
clear that, from the end of May onwards, GEC Marconi was seeking
to avoid
having matters clarified in a way which would facilitate acceptance testing
using the emulator.
911 GEC Marconi's response of 18 June 1996 to the Skinner 30 May
document-change letter was a rejection out of hand of what was proposed.
Though the letter carried the comment that GEC Marconi was prepared to use
reasonable endeavours to reach agreement (cf cl 11.3 of
the Sub-Contract), the
tenor of the letter was quite to the contrary. It is again unsurprising that
the second Notice of Breach
was served on the same day. In its submissions the
Commonwealth has considered at length this letter and Mr Sharp's evidence in
relation to it. I am in general agreement with those submissions. GEC Marconi
was by then unwilling to cooperate to complete the
existing Sub-Contract.
912 It revealed a like attitude in relation to waivers. I find on the basis of
the documentary evidence that waivers to permit acceptance
testing had been
offered by the Commonwealth prior to at least 14 May 1996 and this was well
understood by GEC Marconi and by Mr
Sharp by at least the end of May 1996. I
reject Mr Sharp's evidence that he subsequently followed up the subject of
waivers with
BHP-IT, though "not in simple terms". There is no documentation
to support his assertion. I do not consider that that follow up
occurred at
all or that Mr Sharp wanted to agree waivers to permit completion of the
Sub-Contract.
913 I should add in passing that I do not regard Mr Brent's 28 May letter to Mr
Cook in which he sought advice on the STUBS dependent
references in the
contractual documentation as having any bearing on the question of whether
waivers had been offered. That letter
acknowledged that there was to be
emulation, and addressed the inconsistent state of the documentation as a
formal contractual matter.
914 GEC Marconi has submitted that the true impediment to acceptance of the
System was not any perceived inadequacy in the emulator
but the unwillingness
on the part of DFAT and BHP-IT to vary the Contract and to agree waivers. I am
satisfied that the contrary
was the case. The fault lay with GEC Marconi. Its
response to the 30 May letter was uncompromising. It did not seek to ascertain
the requirements that DFAT would waive. The inference is irresistible that by
mid-year it had no intention of performing the Sub-Contract.
Its strategy had
failed. When it purported to terminate the contract it merely confirmed what
its conduct reasonably conveyed for
quite some time. It had repudiated the
Sub-Contract.
(d) Breach of the Implied Term ("Good Faith and Fair Dealing")
915 BHP-IT has pleaded that GEC Marconi breached an implied term of the
Sub-Contract which required it to act honestly, fairly and
reasonably in giving
any notice under cl 40.8 and cl 40.9 (the termination provisions).
As I understand it, this term applied
to the exercise of the termination
provisions what is now commonly referred to as the duty of good faith and fair
dealing. The term
itself is said in the circumstances to be implied both by
law and ad hoc: on the difference see Renard Constructions (ME) Pty Ltd v
Minister for Public Works (1992) 26 NSWLR 234 at 256ff; Hughes Aircraft
Systems International v Airservices Australia (1997) 76 FCR 151 at
190ff.
916 GEC Marconi resists the implication. To the extent that the implication
was said to be one of law, it is contended that this
is precluded by cl 50
of the Sub-Contract (an "entire agreement" clause): Castlemaine Tooheys Ltd
v Carlton & United Breweries Ltd (1987) 10 NSWLR 468 at 490-493;
Byrne v Australian Airlines Ltd [1995] HCA 24; (1995) 185 CLR 410 at 449-450. The
entire agreement clause, it is said, either expressly excludes or is
inconsistent with the good
faith term to be implied by law. It is equally said
that, as the parties had addressed issues of good faith in specific provisions
it would be inconsistent with their stated intention to imply a further such
obligation. To the extent that the implication is said
to arise ad hoc, GEC
Marconi accepts that the entire agreement clause will not, of itself, defeat
such an implication: Etna v Arif [1999] VSCA 99; [1999] 2 VR 353 at 371. Nonetheless
it contends that the good faith implication is not necessary to give business
efficacy to the
contract.
917 Given my finding on repudiation, I do not intend dealing with these
submissions at length. There are, though, several comments
I would wish to
make.
918 It has been said that "[i]t is very easy to criticise the use of implied
terms to incorporate an obligation of good faith":
Peden, "The Meaning of
Contractual Good Faith" (2002) 22 Aust Bar Rev 235 at 245. There is some
justice in this. The principles
stated in BP Refinery (Westernport) Pty Ltd
v Shire of Hastings [1977] HCA 40; (1977) 180 CLR 266 at 283 that are to be applied in
making an implication ad hoc are not particularly apt to identify what are the
standards of conduct that the parties are reasonably entitled to expect of each
other in the performance and enforcement of their
contract. And if it be the
case that terms implied by law had their origins in implications based on the
intentions of the parties
that thereafter became so much a part of the common
understanding as to be imported into transactions of the type to which the
particular
implication relates: Byrne's case, above, at 449; this form
of implication likewise provides a not altogether happy vehicle for justifying
the modern good
faith implication.
919 Part of our difficulty arises from the fact that, express or implied term
apart, we have no other available common law device
for imposing obligations on
parties that are contractual in character. We do not have the facility, for
example, to treat the duty
as simply a mandatory rule of contract law as do
many European legal systems: see Principles of European Contract Law,
Art 1.201 and see n5; Principles of International Commercial Contract,
Art 1.7; see also Uniform Commercial Code §1-102(3).
920 This in turn exposes another difficulty. There is not yet agreement in
this country as to the province of good faith in contract
law. Some, myself
included: see Hughes Aircraft Systems International, above, at 192-193;
consider that the duty of good faith and fair dealing should apply to all
contracts. Others are prepared for the moment to see it as a legal
incident of particular classes of contract: Alcatel Australia Ltd v
Scarcella (1988) 44 NSWLR 349; Gary Rogers Motors (Aust) Pty Ltd v
Subaru (Aust) Pty Ltd (1999) ATPR 41-703; and see Central Exchange Ltd
v Anaconda Nickel Ltd (2001) 24 WAR 382. This uncertainty, in my view,
reflects an uncertainty about the very purpose of the duty itself in regulating
contractual behaviour. It also exposes a difficulty of a distinctly doctrinal
character: Is the duty one that can be excluded by
agreement? On one view,
reflected in civilian legal systems and §1-102(3) of the Uniform
Commercial Code, the very rationale of the duty in contract law precludes
its exclusion. But as a matter of legal doctrine in this country it must
be
accepted that, as an implied term, it is capable of being excluded by express
or by inconsistent provision - although it is, perhaps,
difficult to envisage
an express provision authorising dishonesty. We clearly have not reached the
point where it can be said:
"Although ... a covenant of good faith is implied in every contract, an action for its breach is really no different from a tort action, because the duty of good faith is imposed by law and is not a contractual term that the parties are free to bargain in or out as they see fit.":
Carmichael v Adirondack Bottled Gas Corporation of Vermont 635 A2d
1211 at 1216 (1993). There are, nonetheless, real questions still to answer in
Australian law as to the proper approach
to be taken where the issue is, not
whether a duty of good faith should be implied, but rather whether it should be
excluded in circumstances
where it would otherwise be implied but for some
alleged inconsistency with, or preclusion by, the terms of the contract: see
Farnsworth,
"Good Faith in Contract", [6], in (2002) AMPLA Yearbook,
(forthcoming).
921 I have mentioned the above because of the way GEC Marconi has framed its
defence to BHP-IT's claim. While I refrain from expressing
a concluded view on
the matter, I consider this to be a case in which cogent grounds exist for
making the implication sought. I
would simply note that the Sub-Contract was a
long term relational one in which cooperation and trust were to be expected
because
of the back-to-back nature of the ADCNET contracts. And it was one in
which BHP-IT was in a position of vulnerability vis à
vis GEC Marconi
given its parallel obligations under the Head Contract.
922 The final comments I would make are to indicate that (i) I consider the law
in this country to be that an "entire agreement"
clause does not preclude
implications ad hoc: see Etna v Arif, above; so that I cannot, with
respect, agree with the view to the contrary expressed in NT Power
Generation Pty Ltd v Power and Water Authority (2001) 184 ALR 481 at [387];
and (ii) I find arresting the suggestion that an entire agreement clause is of
itself sufficient to constitute
an "express exclusion" of an implied duty of
good faith and fair dealing where that implication would otherwise have been
made by
law.
2. DAMAGES
923 Before outlining the various heads of damages claimed by BHP-IT, it is
useful to provide a brief chronological narrative of the
principal events that
bear on the damages claim. Most of what follows merely reiterates matters
already considered in detail, or
to be considered later in these reasons in
relation to the Commonwealth's cross-claim against BHP-IT.
(a) A Brief Chronology
924 (1) The respective contract prices of the ADCNET Head Contract and
Sub-Contract were $9,609,569 and $6,218,260. These were payable
by instalments
on the achievement of seven milestones. By the time BHP-IT accepted GEC
Marconi's repudiation of the Sub-Contract,
Milestone 3000 had been achieved and
milestone payments of $5,575,000 and $3,875,000 had been received by BHP-IT
from the Commonwealth
and by GEC Marconi from BHP-IT respectively.
925 (2) In the period from the execution of the two contracts in September 1994
until GEC Marconi's purported termination of the
contract, BHP-IT had incurred
project management expenses that were referable to both contracts.
926 (3) On 29 January 1997 BHP-IT called on the financial securities provided
by GEC Marconi and, by so doing, received a sum equivalent
to that received by
GEC Marconi by way of milestone payments (ie $3,875,000).
927 (4) Though GEC Marconi's repudiation resulted in BHP-IT's being further in
breach of the Head Contract, the Commonwealth did
not terminate the Head
Contract for breach. BHP-IT itself assumed the responsibility actually to
perform the software development
and integration formally required by the Head
Contract but which, in fact, was previously being performed by GEC Marconi for
BHP-IT
under the Sub-Contract. This was a significant change of role for
BHP-IT in the Head Contract from that envisaged when both contracts
were
entered into in 1994.
928 (5) The process that led to BHP-IT committing itself to this performance
involved protracted discussions between the parties
in 1997 that resulted in
(a) a review of, and significant amendments to, the FRS; (b) changes to the
CIS and, in this, a greater
use of off-the-shelf-products; and (c) the
execution of the Variation Agreement. A new project team was to be assembled
by BHP-IT
for the purpose.
929 (6) Under the Variation Agreement (which took effect as an amendment to the
Head Contract) BHP-IT agreed to perform the amended
Head Contract for the
previously agreed contract price but according to a new schedule. In
performing the contract BHP-IT and Commonwealth
agreed that BHP-IT would "start
from scratch", making no use of any materials previously provided by GEC
Marconi. As a new regime
of milestones was specified in the amended contract,
BHP-IT refunded the Milestone payments 2000 and 3000 it had received under the
original contract. It nonetheless retained a sum equivalent to the original
Milestone 1000 as a "mobilisation payment" under the
amended contract.
930 (7) In 1998 the Head Contract was further amended to develop the Expedited
Release 3 ("ER3") software which would provide a message
switching facility and
would enable an earlier decommissioning of the IBM system than was envisaged
under the Head Contract. This
work was separately costed and charged for.
931 (8) Work on the amended Head Contract was suspended by agreement in
September 2000. By that time BHP-IT had been paid $7,109,769
in the form of
Milestone payments and had incurred performance costs of $5,136,122. BHP-IT's
earned value calculation was that 55%
of the work under the Head Contract had
been completed. BHP-IT in consequence returned $503,803 to the Commonwealth
and retained
$6,605,966 (being 55% of the Milestones payable). As I indicate
below, the suspension reflected the abandonment of the ADCNET project,
for
practical purposes.
932 It needs to be emphasised that BHP-IT's damages claim is for breach of the
Sub-Contract. The reason for this emphasis is because
quite significant
effects of that breach flowed into the Head Contract and are reflected in
particular heads of damages claimed.
(b) Applicable Principles
933 There is no real dispute between the parties as to the principles governing
the proper measure of contractual damages. Such
controversy as there is
relates to the application of those principles and the methodology used in
quantification of the damages
claimed. Those principles I would state for
present purposes, as follows.
934 (1) The general principle governing the measure of damages for breach of
contract is that where a party sustains a loss by reason
of such a breach that
party is, so far as money can do it, to be placed in the same situation with
respect to damages as if the contract
had been performed: Robinson v Harman
(1848) 1 Ex 850 at 855; Wenham v Ella [1972] HCA 43; (1972) 127 CLR 454 at 471;
The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64.
935 (2) The usual rule is that damages for breach of contract are assessed as
at the date of the breach: Amann Aviation, above, at 161-162; Cheshire
and Fifoot, Law of Contract, para 23.24 (8th Aust ed).
"[T]his rule is not universal": Johnson v Perez [1988] HCA 64; (1988) 166 CLR 351 at
355; and if following it would give rise to injustice, the court may fix such
other date as is appropriate
in the circumstances to give the innocent party
the amount in damages which will most fairly compensate that party for the
wrong
suffered: Johnson v Agnew [1980] AC 367 at 400-401; Johnson v
Perez, above, at 355-356. A common example of another date being fixed is
where, after one party fails to provide goods or services, the
other party
thereafter seeks or proposes to seek substitute performance and claims damages
for the cost of so doing: eg: Radford v De Froberville [1977] 1 WLR
1262; Cormier Enterprises Ltd v Costello (1980) 108 DLR (3d) 472;
Conquest v Ebbetts [1896] AC 490; Chitty on Contracts, vol 1,
paras 27-014, 27-052 (28th ed).
936 (3) If a contract was a profitable one (proof of the likelihood of which
rests on the innocent party: Amann Aviation, at 80), but was terminated
for breach or repudiation, the profits lost and the costs actually and
reasonably incurred in performance
are proper subjects of compensation:
Amann Aviation, at 81, 99, 134-135. If the contract was a loss making
one, the innocent party's recovery will be limited to the extent (if at all)
to
which expenditure would have been recouped through continued performance:
Amann Aviation, at 99.
937 (4) If the innocent party can establish expenditures which would not have
been sustained, or other detriments which would not
have been suffered, but
for the breach or repudiation, damages for those losses will be recoverable
(subject to the remoteness rule):
Amann Aviation, at 128; Carr v J
A Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327; TC Industrial Plant Pty Ltd v
Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180 CLR 130. As was said in Tito v
Waddell (No 2) [1977] Ch 106 at 332:
"if the plaintiff can establish that his loss consists of or includes the cost of doing work which in breach of contract the defendant has failed to do, then he can recover as damages a sum equivalent to that cost."
938 (5) Loss or damage will not be recoverable if it is too remote, the tests of remoteness being those stated in what are described as the two limbs of Hadley v Baxendale (1854) 9 Ex 341 at 354. For present purposes those tests can be expressed in the statement of principle formulated by Lord Reid in C Czarnikow Ltd v Koufos [1967] UKHL 4; [1969] 1 AC 350 at 385 and which has been adopted in this country: see Baltic Shipping Co v Dillon [1993] HCA 4; (1993) 176 CLR 344 at 368:
"The crucial question is whether, on the information available to the defendant when the contract was made, he should, or the reasonable man in his position would, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation."
939 (6) The question whether a loss was of a kind that should have been within the contemplation of the party in breach commonly arises where property or services the subject of a contract is/are being acquired for a particular use or for resale by the innocent party and loss is suffered because that use or resale is prevented, delayed or can only reasonably be secured by substituted performance. In such cases the contract can give rise to two separate expectations, the one being receipt of the promised performance, the other being the putting of that performance to some particular use: see Trietel, Law of Contract, 831 (8th ed); Greig and Davis, The Law of Contract, 1379; McGregor on Damages, paras 279-280 (16th ed); and see eg Alucraft Pty Ltd (in liq) v Grocon Ltd (No 2) [1996] 2 VR 386 at 389ff. As McHugh J observed in Amann Aviation, at 163:
"In such a case, a plaintiff may be able to recover for both moneys expended and loss of profit, although great care needs to be taken that double counting does not occur."
On the rule against "double recovery" see generally Tilbury, Civil
Remedies, vol 2 [13027]ff.
940 (7) In cases of back-to-back or relational contracts, one particular
species of damages is of some importance. It is that which
arises where one
party's breach of, for example, a sub-contract puts the other party to that
contract in breach of the head contract
as, for example, for breach of warranty
or for delayed delivery: see eg Agius v Great Western Colliery Company
[1899] 1 QB 413. Where legal proceedings are taken under the head contract
against the party so put in breach and damages and costs
are recovered against
it, that party may in turn (subject to considerations of remoteness) recover
those damages and costs in proceedings
under the sub-contract against the party
in breach as part of its damages occasioned by the breach: Hammond & Co
v Bussey (1887) 20 QBD 79; see generally, McGregor on Damages, para
758ff, para 769ff (16th ed); Jacobs, Damages in a Commercial
Context, [6.54]; Burrows, Remedies for Torts and Breach of
Contract, 154-155 (2nd ed); for the quite different situation
that obtains where earlier proceedings are brought between the same
parties, see Avenhouse v Hornsby Shire Council (1998) 44 NSWLR 1.
941 (8) I will refer below to one particular head of damages claim advanced by
BHP-IT. That is a claim for $1,132,396 for costs
of managing the dispute
raised by GEC Marconi. All I would note here is that current Australian
authority would suggest that a loss
is not to be presumed from the mere fact of
incurring dispute management costs as such: see Christmas Island Resort Pty
Ltd v Geraldton Building Co Ltd (No 4) (1995) 16 WAR 277; see also Tate
& Lyle Food and Distribution Ltd v Greater London Council [1982] 1 WLR
149 at 152.
942 When considering BHP-IT's claim for losses in performing the amended Head
Contract from 1997, I will refer separately to the
principles governing
recovery of damages (a) for loss of use of an asset, and (b) for remuneration
for using one's own resources
to remedy damage sustained as a result of
another's wrong.
3. THE HEADS OF CLAIM
943 BHP-IT first described its various losses in the following way, although it
has recast them somewhat in the course of submissions
to facilitate computation
of its damages. In that process there has been some variation in the amount
claimed under some of the
following heads.
(1) It lost entirely the benefit of the Sub-Contract, namely the "Developed
Software" which EASAMS had promised to deliver to it,
and which BHP-IT had in
turn promised to deliver to the Commonwealth pursuant to the Head Contract.
(2) It lost entirely the benefit of the Head Contract, compromising:
(a) the Milestone payments 1000 to 3000 which it had already been paid to it
under the Head Contract for undertaking project management
work associated with
the attainment of those Milestones, but which it had agreed to repay as a term
or condition of the 1997 Variation
Agreement.
(b) the profit which it would have earned for carrying out the remainder of
its obligations under the Head Contract (ie for performing
work other than
project management work associated with the attainment of Milestones 1000 to
3000). The actual loss ascribed to
this head is $3.391 million, being the
difference between the milestone payments payable to BHP-IT under the original
Head Contract
($9,609,569) and the amount payable by BHP-IT to GEC Marconi for
performance of the Sub-Contract ($6,218,260).
(3) It incurred costs and expenses in undertaking work on the ADCNET project
between June 1995 (following payment for Milestone 3000)
and 10 December 1996,
(the date GEC Marconi terminated the Sub-Contract). The sum claimed is
$1,123,844.
(4) It incurred costs and expenses managing the dispute that had arisen between
the parties as a consequence of GEC Marconi threatening
to terminate the
Sub-Contract. The sum claimed is $1,132,396 comprising $851297 actual costs
together with a margin or $281,009
to recoup overheads and BHP-IT's standard
return on the labour component of these extra costs.
(5) It incurred additional costs and expenses in respect of the Head Contract
throughout 1997, leading to the entry into the December
1997 Variation
Agreement. The sum claimed is $174,902 being the actual extra costs incurred
in investigating a way forward for the
project.
(6) It incurred costs and expenses in performing the December 1997 Variation
Agreement. It was forced to enter into the December
1997 Variation Agreement
at the same price as provided for in the 1994 Head Contract, and consequently
lost entirely the profit which
it would have earned on the 1997 Variation
Agreement had it been able to negotiate that agreement at arms length and upon
commercial
terms. The sum claimed is $6,522,284, being the burden associated
with BHP-IT having to undertake the December 1997 Variation Agreement,
measured
by the contribution which would have been earned for performance of the
Agreement, had the agreement been negotiated upon
commercial terms, employing
BHP-IT's standard pricing methodology.
(7) It is exposed to a liability to the Commonwealth in respect of the claims
which are now the subject of the Commonwealth cross-claim
against BHP-IT in the
proceeding (the Commonwealth's Cross-Claim). To the extent to which the Part
V: Commonwealth succeeds in
proving its cross-claim against BHP-IT, BHP-IT
will suffer loss and damage.
(8) It lost the opportunity to earn a return on moneys which it would have
earned had it enjoyed the use of those moneys from the
time at which they
became due and payable, at the time they were expended or at the time the loss
was sustained. The sum claimed
is $2,763,001 (alternatively, $2,460,318),
being the amount required to compensate BHP-IT for the lost use of moneys which
BHP-IT
should have been paid under the Head Contract, calculated by reference
to BHP's weighted average cost of capital ("WACC") for the
period 1996 to
2001.
944 Additionally, BHP-IT claims $489,684 for the amount outstanding on unpaid
invoices for the provision by BHP-IT under the Sub-Contract
of its own staff to
assist GEC Marconi in the performance of the Sub-Contract.
945 BHP-IT contends that none of the items of loss and damages claimed offends
the rule against remoteness.
946 I would note in passing that BHP-IT has not brought any claim against GEC
Marconi to enforce any accrued rights that it might
have had that pre-dated the
termination of the Sub-Contract.
947 Before dealing with these heads of claim it is necessary to refer briefly
to how BHP-IT (a) allocated and recorded costs incurred
by its staff engaged on
the ADCNET project; and (b) the internal margins BHP-IT applied to base costs
to produce a contract price
that recovered divisional overheads, corporate
overheads and the minimum profit targets set by BHP-IT.
(i) The recording of costs
948 To determine labour costs associated with work performed on any project,
BHP-IT divided its labour resources into "skill pools". These skill
pools grouped together personnel with similar capabilities. Each skill pool
was then divided into 15 levels reflecting
the potential range of experience
and seniority of the people within each skill pool. BHP-IT then determined an
hourly rate for
each of these levels to reflect the actual cost to BHP-IT
associated with a person within that pool or level performing one hour
of work.
This rate was called an "hourly cross charge rate". These rates were
reviewed by the finance department on a six monthly basis.
949 The hourly rate was determined by reference to the actual salary costs of
each person within a level. Added to these costs were
overheads which would be
directly incurred by the skill pool itself, such as office space, stationery
and computers. In circumstances
where employees worked off site and thus
consumed less direct overhead costs, this would be reflected in the budget set
for these
items. The hourly cross charge rates for each skill level were
loaded into BHP-IT's accounting system.
950 BHP-IT's employees would assign their time to the project code applicable
to the work that they had undertaken on their timesheet:
see below on "project
codes". Those timesheets would then be entered into BHP-IT's time recording
system. Once the time so entered
had been authorised, it would then be
transferred to BHP-IT's accounting system. A cost would then be allocated to
the relevant
project code by multiplying the time assigned to the code by the
particular cross charge rate relevant to the employee in question.
BHP-IT used
cross charge rates to determine as accurately as possible the actual labour
costs associated with the deployment of
labour on any particular project. This
in turn enabled it to employ a standard cost plus pricing methodology to
determine prices
to be charged for work quoted or undertaken on all BHP-IT
projects.
951 All costs incurred in performing work under the rubric of the Head and
Sub-Contracts were collected by a group of project codes.
These codes, for
present purposes, were project specific, so that there was a discrete group of
codes for the ADCNET project. It
is unnecessary to set out the codes employed
in any detail other than to say that they identified (a) costs and revenues
associated
with the fixed-price part of the ADCNET contract; (b)
differentiated between, for example, labour costs incurred, management costs,
and costs for time and material work; and (c) sub-categorised packages of
work. The purpose of the hierarchical structure of the
codes was that it
allowed BHP-IT to track the costs associated with the ADCNET project.
952 As will be seen, BHP-IT relies upon specific project codes as being
relevant to its damages claim.
(ii) BHP-IT's Internal Margin
953 BHP-IT's management had set an internal margin for the company's activities
which was a rate applied to the actual base costs
to be incurred in performing
a contract so as to recover for costs not directly allocated to projects and so
as to generate the minimum
profit that BHP-IT was expected to return. This
internal margin was the minimum percentage by which all base costs were
adjusted
internally before a price was submitted so as to reflect:
(a) recovery of the divisional overheads attached to the provision of the
service such as use of company resources like the divisional
management;
(b) recovery of the corporate overheads attached to the provision of the
service such as administrative costs, sales and marketing
resources, and use of
company equipment; and
(c) the inclusion of the specific minimum profit targets that were set
internally by BHP-IT.
954 The total internal margin for the division of BHP-IT's having
responsibility for the ADCNET project was 49%. This required the
expected cost
base of a project to be multiplied by a factor of 1.49. The margin for
divisional overheads was 12% until the 1997-1998
financial year when it was
revised to 7.2%. The margin for corporate overheads was 22%.
4. LOST BENEFIT OF THE SUB-CONTRACT
5. LOST BENEFIT OF THE HEAD CONTRACT
6. COSTS INCURRED BETWEEN JUNE 1995 AND DECEMBER 1996.
7. COSTS OF PERFORMING THE VARIATION AGREEMENT
955 I have grouped these four heads of damage together because, in applying the
principle in Robinson v Harman, they constitute a family of claims
bearing on the position BHP-IT contends it would have been in had the contract
been performed.
To explain this briefly, and considering the matter as at
the date of acceptance of GEC Marconi's repudiation, if the Sub-Contract
had been performed BHP-IT would in turn have been able to deliver the Developed
Software to the Commonwealth.
The Developed Software was the benefit it lost
from the Sub-Contract. That loss provides, as it were, the trigger to the
monetary
claims made, all of which relate to the Head Contract.
956 By the time GEC Marconi repudiated the Sub-Contract, BHP-IT had a net
receipt of $1,700,000 from the Commonwealth for milestone
payments, but had
incurred the following costs (a) of $3,875,000 being milestone payments of GEC
Marconi and (b) of between about
$1.8 million and $2.5 million in project
management costs. If the Sub-Contract had been performed BHP-IT would have
derived a further
net receipt from milestone payments of $1,691,309. The
claims for lost benefit of the Head Contract and for costs incurred up to
December 1996 are founded on these receipts and expenses.
957 The Head Contract, though, could not be performed unless and until BHP-IT
was in a position to deliver the Developed Software.
Given the repudiation of
the Sub-Contract, it could only be in such a position if either it engaged a
new sub-contractor for this
purpose or it did the work itself. It took the
latter course. This was the "substituted performance" of the Head Contract.
Whatever
the Commonwealth's obligation to BHP-IT in respect of the price to be
paid for that performance, BHP-IT was, it is claimed, entitled
to be
compensated by GEC Marconi for its loss of return on that performance.
(a) Additional Factual Material
958 Before committing itself to the Head Contract and Sub-Contract in September
1994, BHP-IT made its own estimate of costs and returns
of the two contracts.
A Financial Approval Summary that was signed off by senior officers of BHP-IT
(including McDart) estimated
that, if GEC Marconi performed the Sub-Contract,
BHP-IT's own direct costs for management, etc, would be $2,094.111. Provision
of
$461,381 was made for "Contingency and Risk" of $461,381, the estimated
gross profit was $835,912 and the estimated net profit was
$820,912.
959 A BHP-IT Marketing and Operations Report for the ADCNET project of December
1995 recorded that expenditure was below budget,
revenue and profit were "ahead
of budget" and that the risk and contingency was "intact".
960 Documents prepared on the ADCNET project for BHP-IT's quarterly financial
reviews of August and November 1996 both indicated
(in overhead slides) that
while the reported status of the project was 68% complete its actual status was
probably 20-40%. Documents
in each of those reviews contained project
financial estimates which, as the following table for the November review
indicates reproduced
the 1994 estimates with variations. Those variations were
attributable, it would seem, to contract variations resulting in additional
costs, allowances for risk and profit. The substance of the November Table was
as follows:
At Contract Signoff |
August 96 Review |
November 96 | |
BHP direct costs |
$2,094,111 |
$2,160,102 |
$2,160,102 |
Oncharge costs |
$6,218,260 |
$6,554,233 |
$6,554,233 |
Risk & Contingency |
$461,381 |
$488,260 |
$488,260 |
Project Total Cost |
$8,773,752 |
$9,202,595 |
$9,202,595 |
Total Revenue |
$9,609,663 |
$10,254,414 |
$10,254,414 |
Gross Contribution |
$820,912 |
$1,036,819 |
$1,036,819 |
GCM % (excl oncharge) |
26.6% |
32.3% |
32.3% |
The reference GCM at the foot of the Table was to "Gross Contribution Margin".
While the quarterly review documents contained detailed
slides dealing with
risks of various varieties (eg technical, schedule, etc), the probability of
their eventuating and the allowance
that should be made for them, the schedules
do not indicate clearly which, if any, of these risks were ones to which the
risk and
contingency allowance in the 1994 estimates related.
961 One of the documents contained in the November review bundle does appear on
its face to refer to the contingency provision contained
in the November
estimates. It was entitled "Additional Costs Due to Dispute As At 10/11/96".
It is as follows:
ADDITIONAL
COSTS DUE TO DISPUTE AS AT 10/11/96 | |||
Project Costs Incurred Since June |
|||
Management |
$132,407 |
||
Software, Testing & Review |
$119,213 |
||
Subtotal |
$251,620 |
||
Risk & Contingency Provision as per Financial Summary |
$488,259 | ||
Risk and Contingency Provision Remaining |
$236,839 | ||
Commercial and Legal Cost to 10/11/96 |
|||
Commercial (from SAP) |
$154,986 |
||
Legal (from SAP) |
$29,333 |
||
TOTAL |
$184,319 | ||
Risk Contingency Provision Remaining |
$52,520 |
This document was not explained by any witness. It was relied upon by the
Commonwealth in submissions.
962 In giving evidence on the November documents Mr Brent said that his
recollection was that whilst the profit position of the project
looked good at
that time, "the risk position did not".
963 By the time GEC Marconi had repudiated the Sub-Contract, BHP-IT had
received milestone payments of $5,575,000 and had in turn
paid GEC Marconi
$3,875,000 for its achievement of the same milestones. Mr Hammond, who was
BHP-IT's Vice-President of Finance at
the time, accepted that the actual costs
for obtaining these milestones were probably in excess of $900,000. This
figure was based
on labour costs and project expenses of $706,200 which were
charged to ADCNET project codes for the period 1 June 1994 to 31 May
1995 and
to which he said the usual internal margin had to be applied.
964 Between June 1995 and December 1996 BHP-IT had incurred expenses as well in
relation to Milestone 4000 though that milestone,
as I have found, was never
achieved. The payment to be made to BHP-IT for Milestone 4000 was $2,390,000
of which $1,250,000 was
to be paid in turn by BHP-IT to GEC Marconi leaving
BHP-IT with $1,140,000.
965 Mr Hammond's evidence, again based on costs charged to ADCNET project codes
for the period 1 June 1995 to 31 December 1996, was
that BHP-IT had incurred
costs (made up of labour costs and project expenses) of $1,123,844 on the
ADCNET project. After applying
BHP-IT's internal margin to this figure, Mr
Hammond's evidence is that the cost incurred by BHP-IT in this period was
$1,616,551
- a sum greater (by almost $0.5 million) than what have been
retained from Milestone 4000.
966 Mr Hammond gave the following additional evidence in cross-examination:
"Q. So whereas looking at the first stage of the project through to milestone 3,000 there was apparently a profit earned in relation to those milestone payments, your calculations would suggest in relation to milestone 4,000 there was a loss?
A. That would suggest that.
Q. Do I understand that what you haven't attempted to do is look beyond milestone 4,000 to see whether or not this contract would have been loss making or profit making to BHP-IT if GEC Marconi had carried on with it; you just don't know?
A. No, I don't.
Q. Is this right: because you haven't done that exercise you can't say whether the financial consequence to BHP-IT of performing the varied contract is any better or worse than the financial consequence to BHP-IT of performing the original contract?
A. No, I couldn't say that."
The remaining three milestones after Milestone 4000, would have resulted in
payments of $1,644,569 and $1,093,260 to BHP-IT and GEC
Marconi, leaving BHP-IT
with a net return from the payments of $551,309.
967 When GEC Marconi purportedly terminated the Sub-Contract on 10 December
1996, it withdrew all of its staff from the ADCNET project.
It sought as well
to recover a range of data which it said was, variously, (a) non-project
related; (b) its own copy of project-related
material; (c) its own software;
and (d) its own commercial-in-confidence material.
968 By that time meetings had taken place between BHP-IT and DFAT to discuss
options for resolving the dispute with GEC Marconi.
A minute of Les Cook of 23
September 1996 recording one such meeting commented that:
"It seems clear that BHP-IT could continue the project without EASAMS only by starting from scratch or by purchasing intellectual property rights in work done to date from EASAMS. The same options face DFAT if its contract with BHP-IT is terminated."
969 GEC Marconi's performance of the Sub-Contract had been such that, of the
five builds to be undertaken in the software development
process, it is not
clear on the evidence whether Build 2 was ever completed. It had failed
integration testing in early 1996 and
had had corrective work done on it during
the first half of 1996. There is no evidence that any of the other three
remaining builds
were completed before GEC Marconi terminated.
970 GEC Marconi had experienced considerable difficulties with the FRS. A
letter of Mr Brent to Mr Goldsmith of 23 May 1996 recorded
(inter alia) advice
given by Mr Goldsmith at a project management meeting that "53% of the ADCNET
Functional Requirements Specification
... is invalid/unworkable".
971 Mr Brent's evidence is that after 10 December 1996 BHP-IT began to work on
the "resurrection of the program" and to "rebuild
the system from scratch".
Explaining why it was begun "from scratch". Mr Brent said in oral evidence:
"A. In my assessment at the time, the picking up a project of this level of complexity after the bulk of the people involved in the project were no longer available to us was very difficult, because with the people goes the [domain] knowledge. Also I was of the view by that time that in terms of work value there wasn't very much there. And I think I expressed those reservations in some letters."
972 Les Cook similarly gave evidence that his view as at September 1996 was
that the only way of proceeding with ADCNET was to start
from scratch. He was
concerned about the value of the work that had been done to that date.
973 By December 1996 Les Cook was expressing his concern that if the existing
ADCNET contract was performed several problems were
foreseeable which were
attributable, largely, to the estimated 3-year delay before delivery of release
3. One of these was that
the development was based on versions of COTS
software which were already outdated.
974 An ADCNET Project Status Report of 16 April 1997 recorded that from 10
December 1996 the project team (made up of twelve persons
from BHP-IT and DFAT)
had been engaged in a review of the ADCNET project and its requirements. A
significant element in that review
was an analysis of the entire FRS. By the
end of April 1997 BHP-IT considered itself to be in a position to propose a
basis for
resuming the development of the project. Though that proposal was
not accepted and negotiations continued in consequence, the review
of the FRS
continued leading to an agreement in August/September 1997 to adopt a new
version of the FRS.
975 By November 1997 BHP-IT and the Commonwealth were exchanging proposed
drafts of an amended Head Contract and Schedules. On 24
December the Variation
Agreement was signed. Its terms and effect are considered later in these
reasons: see Part V: The Commonwealth's
Cross-Claim: The 1997 Variation
Agreement. For present purposes all that need be said of that agreement is (a)
it amended the Head
Contract and its schedules; (b) under it, BHP-IT agreed to
perform the amended contract itself for the original contract price but
according to a new schedule; (c) in so doing, BHP-IT would start from scratch
with all work previously done by GEC Marconi being
abandoned; (d) new and
fewer milestones were agreed; and (e) BHP-IT was to return to the Commonwealth
the second and third of the
milestone payments it had already received, but was
to retain a sum equivalent to the first milestone it had received as a
mobilisation
payment (ie Milestone 1000) under the newly agreed schedule.
976 Mr Brent was succeeded by Manfred Rentz as BHP-IT's Project Manager in July
1997. In November/December 1997 along with other
members of BHP-IT's project
team, he prepared the Proposal Approval Form ("PAF") for the 1997 Variation
Agreement. This was a standard
form used by BHP-IT to determine prices for
projects for which approval for quotation would be sought.
977 This PAF was not prepared using BHP-IT's usual cost plus methodology as the
price was set by the Variation Agreement itself,
being the original Head
Contract price of $9,609,663. Nonetheless Mr Rentz had a BHP-IT employee
conduct what is described as a
"Function Point Count" to evaluate the size of
job that was to be undertaken and to enable an estimate to be made of labour
needed
to complete it. That form of analysis permitted an estimate to be made
of the labour costs of the project.
978 In his witness statement Mr Rentz explained the bases upon which the other
estimates in the PAF were made. I have set out below
three of the columns in
the PAF. The one matter to which I would draw attention is the risk allowance
of $2,962,151. The manner
in which the figures making up this sum were
calculated was explained by Mr Rentz in his witness statement. The
documentation used
in their calculation was tendered.
979 The PAF produced in November/December 1997 - and signed off by Mr Dart on
23 January 1998 - was, in part as follows:
FINANCIAL DETAILS |
BEST CASE COST |
RISK ALLOWANCE |
BID PRICE |
CONTRIBUTION |
% |
Oncharges |
|||||
. Forte Software License |
$337,000 |
$0 |
$337,000 |
$0 |
0.00% |
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Subtotal: |
$337,000 |
$0 |
$337,000 |
$0 |
0.00% |
Direct Costs |
|||||
. Labour (based on cross-charge rates) |
1.84% | ||||
. Project Management |
$2,510,057 |
$276,584 |
$9,143,780 |
$6,357,139 |
69.52% |
. Software Dev |
$2,498,214 |
$2,685,567 |
$0 |
-$5,183,781 |
|
. Total Negotiation |
$587,608 |
$0 |
$0 |
-$587,608 |
|
. Training & Documentation |
$125,000 |
$0 |
$0 |
-$125,000 |
|
. Consultants |
$235,000 |
$0 |
$0 |
-$235,000 |
|
. Warranty |
$57,750 |
$0 |
$0 |
-$57,750 |
|
. |
$0 |
$0 |
$0 |
||
. |
$0 |
$0 |
$0 |
||
Service Products (based on unit charges) |
|||||
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Expenses |
0.00% | ||||
. Hardware leasing |
$24,989 |
$0 |
$24,989 |
$0 |
0.00% |
. Materials |
$10,000 |
$0 |
$10,000 |
$0 |
0.00% |
. Travel & Accommodation |
$93,800 |
$0 |
$93,800 |
$0 |
0.00% |
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Admin & Finance Charges |
|||||
. Hardware purchases |
$0 |
$0 |
$0 |
$0 |
|
. Corp/Bank Guarantee |
$60,000 |
$0 |
$0 |
-$60,000 |
|
. Prof Indemnity Insurance |
$108,000 |
$0 |
$0 |
-$108,000 |
|
. Cost of Working Capital (if applic) |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Subtotal: |
$6,310,418 |
$2,962,151 |
$9,272,569 |
$0 |
0.00% |
PROPOSAL TOTAL: |
$6,647,418 |
$2,962,151 |
$9,609,569 |
$0 |
0.00% |
PROPOSAL GROSS OPERATING MARGIN = 0.00% TARGET = 31.75% |
980 In May 1999 a revised version of the above PAF was prepared internally by
BHP-IT. It reflected labour prices, divisional and
corporate overheads and
profit margins that BHP-IT was using in projects for 1998 but also included
some of the known extra costs
incurred on the project in 1998 such as the Forte
license and consultancy. It was, in part, as follows:
FINANCIAL DETAILS |
BEST CASE COST |
RISK ALLOWANCE |
BID PRICE |
CONTRIBUTION |
% |
Oncharges |
|||||
. Forte Software License |
$337,000 |
$0 |
$337,000 |
$0 |
0.00% |
. Development Software |
$65,793 |
$0 |
$65,793 |
$0 |
0.00% |
. Forte Consultancy |
$421,388 |
$0 |
$442,457.40 |
$21,069 |
4.76% |
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Subtotal: |
$824,181 |
$0 |
$845,250 |
$21,069 |
2.49% |
Direct Costs |
|||||
. Labour (based on cross-charge rates) |
32.85% | ||||
. Project Management |
$2,510,057 |
$276,584 |
$4,152,096 |
$1,365,454 |
32.89% |
. Software Dev |
$2,498,214 |
$2,198,386 |
$6,997,933 |
$2,301,334 |
32.89% |
. Total Negotiation |
$587,608 |
$0 |
$875,536 |
$287,928 |
32.89% |
. Training & Documentation |
$125,000 |
$0 |
$186,250 |
$61,250 |
32.89% |
. Consultants |
$235,000 |
$0 |
$350,150 |
$115,150 |
32.89% |
. Warranty |
$57,750 |
$0 |
$86,048 |
$28,298 |
32.89% |
. Message Switch CR |
$542,668 |
$34,622 |
$853,891 |
$276,601 |
32.39% |
. |
$0 |
$0 |
$0 |
||
Service Products (based on unit charges) |
|||||
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Expenses |
0.00% | ||||
. Hardware leasing |
$24,989 |
$0 |
$24,989 |
$0 |
0.00% |
. Materials |
$10,000 |
$0 |
$10,000 |
$0 |
0.00% |
. Travel & Accommodation |
$93,800 |
$0 |
$93,800 |
$0 |
0.00% |
. |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Admin & Finance Charges |
|||||
. Hardware purchases |
$0 |
$0 |
$0 |
$0 |
|
. Corp/Bank Guarantee |
$60,000 |
$0 |
$0 |
-$60,000 |
|
. Prof Indemnity Insurance |
$108,000 |
$0 |
$0 |
-$108,000 |
|
. Cost of Working Capital (if applic) |
$0 |
$0 |
$0 |
$0 |
|
. |
$0 |
$0 |
$0 |
$0 |
|
Subtotal: |
$6,853,086 |
$2,509,592 |
$13,630,692 |
$4,268,014 |
31.31% |
PROPOSAL TOTAL: |
$7,677,267 |
$2,509,592 |
$14,475,943 |
$4,289,084 |
29.63% |
PROPOSAL GROSS OPERATING MARGIN = 29.63% TARGET = 30.76% |
981 Mr Hammond, who was BHP-IT's Vice-President of Finance, gave evidence that
this Revised Summary demonstrated that the total contract
price or "bid price"
which BHP-IT would have required for this project in and around December 1997
was $14,475,943, had the agreement
been made on a fair and commercial basis and
had BHP-IT been made aware of the true circumstances and conduct of the other
parties.
982 One amount in the "Best Case Cost" which should be noted is the sum for the
"Message Switch CR" of $853,891. That sum related
to CR007 which was agreed to
in August 1998 and the purpose of which was to develop the expedited Release 3
software so as to facilitate
the early decommissioning of the IBM system: see
"The Commonwealth Cross-claim: Retention of the IBM Classified Message Switch
System". It represents the actual contract price of the change request and
includes an actual contribution of 32.39 per cent.
983 After the signing of the Variation Agreement, BHP-IT assembled its own
project team and proceeded to perform the amended Head
Contract and later some
number of agreed Change Requests.
984 In September 2000 discussions were held between BHP-IT and the Commonwealth
concerning a suspension of work on the ADCNET project.
A deed of termination
had previously been proposed, but not agreed. On 22 September agreement was
reached to suspend work on the
ADCNET contract pending the resolution of the
present litigation.
985 Mr John Crighton, at the time an Assistant Secretary in DFAT, with
responsibility for the IM Branch, indicated in his evidence
that in mid-1999 he
had formed the view that, apart from the ER3 software, further expenditure by
DFAT on the ADCNET contract would
be a waste of public money and that the
contract should otherwise be terminated.
986 Mr Rentz gave evidence that as far as he knew his company (which had been
taken over by Computer Services Corporation ("CSC"))
would have been happy to
have been released from the contract.
987 Mr Crighton's oral evidence was that by 1999 DFAT had committed itself to
the SATIN project on which the future technology requirement
for DFAT was to be
based. In late December 1999 a CR was raised to investigate the feasibility of
amending any aspect of the R3
software so as to make it usable and to bring it
into conformity with the SATIN system. The advice Mr Crighton received was
that
there were better, smarter ways of DFAT achieving the result it wanted
than by trying to bring the remainder of the R3 contract into
conformity with
the SATIN approach. He considered that the balance of the ADCNET software was
in 1999, and remained, completely
redundant. Up until his retirement from DFAT
in February 2001 BHP-IT had not approached him seeking to complete the
contract.
988 There are two additional matters to which reference should be made. The
first relates to the financial status of ADCNET project
at the end of September
2000. Mr Rentz's summary was that:
(a) the agreed Contract price was $10,463,461.00 representing the original
fixed price, plus the cost of Change Requests approved
by the Commonwealth;
(b) the forecast cost was $10,186,978.00;
(c) the project was estimated to be 51.28% complete and the software
development 55% complete;
(d) actual revenue received as at September 2000 was $7,109,769.00;
(e) actual cost of the project as at September 2000 was $5,136,122.00;
(f) the estimated earned value for work up to September 2000 was $6,605,966;
(g) the calculated earned value revenue adjustment as at September 2000 was
$1,743,086.00 in deficit, indicating that BHP-IT had
received greater milestone
payments than the estimate work completed by reason of the fact that milestone
payments were paid in advance;
and
(h) using the estimated value and actual revenue figures, a sum of $503,803
(the difference between $7,109,769 and $6,605,966) was
to be refunded to the
Commonwealth as that amount represented a prepayment for work not yet
completed.
In oral evidence he explained by reference to contemporary documentation that,
as at September 2000, it had been estimated that for
a Contract price of
$10,463,461.00, the project would have earned a contributional profit of
$276,483.00, assuming that risk allowances
allowed of $1,774,834 were fully
exhausted. By September 2002 only $17,865 had been expended and he accepted
that if those risk
allowances were not exhausted, there would have been an
additional contribution.
989 The second matter concerns oral evidence of a very general character given
by Mr Dart and Mr Hammond as to BHP-IT's business
in the period from the end of
1997 to 1999. Mr Dart indicated that in the latter part of that period the
company enjoyed eighteen
months of growth outside of the domain of BHP, at an
annual rate of 40 per cent. It was a period for BHP-IT of `reasonable
buoyancy'
in the market place. It was also a period of substantial demand for
software engineers. For his part Mr Hammond indicated that
in the period 1996
to 1999 BHP-IT had high turnover rates of staff. There was strong growth in
the IT industry across all sectors.
As a result, there were considerable
shortages of skills in this area. Accordingly, in this period, all risk
analyses undertaken
by project managers involved assessments of costs involved
with turnover or potential turnover of key project personnel.
(b) Submissions and Conclusions
990 I should indicate at the outset that two matters have added considerably to
the complexity of the issues raised by these claims.
The first is the 1997
Variation Agreement and in particular its requirement for the repayment of the
sums received for achievement
of Milestones 1000 to 3000 under the original
Head Contract. The second is the Suspension Agreement in September 2000. They
rob
the claims of the relatively straightforward character they would otherwise
possess.
991 As I understand it BHP-IT characterises the lost benefit of the
Sub-Contract as being the Developed Software itself which GEC
Marconi had
contracted, but failed, to deliver to it.
992 The lost benefit of the Head Contract it contends is the difference between
the respective contract prices of the Head Contract
and the Sub-Contract, ie
the sum of $3,391,309 (or else that sum less $264,067 which were performance
costs it did not have to incur
to complete the Head Contract because of GEC
Marconi's repudiation). It arrives at this sum, notwithstanding that BHP-IT
had received
$5,575,000 under the Head Contract, because BHP-IT was obliged to
repay that amount under the Variation Agreement. In consequence
of that
repayment it is said that the revenue received by BHP-IT from the Commonwealth
and the payments it made to the Commonwealth
were "cash neutral". BHP-IT
disputes the contention of both GEC Marconi and of the Commonwealth that the
Milestone 1000 payment
was not repaid but was retained by BHP-IT. The sum in
question ($1,250,000), it says, was and was intended to be the agreed
"Mobilisation"
payment under Schedule 8 of the amended Head Contract for
"Formal resumption of project work".
993 BHP-IT's most contentious claim of the three presently under consideration
relates to the cost of performing the Variation Agreement.
The loss that is
claimed under this head is said to fall squarely within both limbs of Hadley
v Baxendale (a matter to which I will return below). The premises of this
claim are that in the circumstances BHP-IT had no real choice but
to perform
the software development itself but at no change to the original contract
price. It was in consequence obliged to complete
the work GEC Marconi was
engaged to perform, but without reasonable remuneration for the deployment of
its resources in so doing.
It claims it is entitled to claim that loss from
GEC Marconi and it seeks to establish it by reference to the 1999 Revised
Version
of the PAF. Had BHP-IT been able to charge a reasonable price for the
services it actually performed using its standard cost plus
methodology, BHP-IT
contends that the return it would have expected to earn was $6,798,767 (being
made up of the projected contribution
of $4,289,084 and the total risk
allowance of $2,509,592). From that sum $276,483 was to be deducted (being the
forecast contribution
for completing the ADCNET project) leaving a loss for
present purposes of $6,522,284. I would note in passing that there is an
obvious
inaccuracy in the calculations so made, though in respect of less than
$100.
994 Alternatively it is said that, if BHP-IT was relieved of its obligation to
perform the balance of the amended Head Contract in
consequence of the
Suspension Agreement in September 2000, it should nonetheless be entitled to
receive 55% of the estimated contribution
of $6,798,767. This would be
$3,739,322. But as it had been paid $1,469,844 more for the 55% per cent of
the work completed than
had actually been earned, it must account for that sum
so reducing its actual loss to $2,269,478.
995 For its part GEC Marconi has attacked the claims made on a number of broad
fronts. The criticism in the round is made of BHP-IT's
damages claims that
there is an absence of any evidence showing:
(a) what financial position BHP-IT would have occupied had GEC Marconi fully
performed the Sub-Contract;
(b) what expenses would have been incurred by BHP-IT in any event had the
Sub-Contract been fully performed; and
(c) a comparison between the financial outcome to BHP-IT had the Sub-Contract
been fully performed and the financial outcome actually
achieved in performing
and completing the software development work.
A more specific criticism is then made of the evidence provided by Mr Hammond
and of the documentation relied upon to support the
individual claims. It is
contended that Mr Hammond was not a person able to present any reliable
analysis of actual loss and damage
suffered and that he did not attempt to
ascertain the actual loss suffered by BHP-IT as distinct from the actual costs
incurred by
BHP-IT. The reliance placed on the costing methods used by BHP-IT
is attacked on the same ground. The mere allocation of a cost
to a project
code, it is said, does not of itself identify a recoverable loss consequent on
a breach of contract.
996 In relation to the claim for profits that would have been derived if BHP-IT
had been able to negotiate the Variation Agreement
at arm's length, it is
contended that such a claim is based on a fallacy. There would have been no
scope to enter into the Variation
Agreement had GEC Marconi performed the
Sub-Contract.
997 It also is submitted that the 1999 Revised PAF ought not be relied upon as
an accurate reflection of BHP-IT's bid price would
have been and it is entitled
to little weight as it clearly was brought into existence for the purpose of
these proceedings.
998 Before indicating my own conclusions on the claims, there are three
preliminary matters that need to be addressed. The first
relates to the
September 2000 Suspension Agreement, the second, to Hadley v Baxendale;
and the third, to the agreement to start from scratch.
999 First, the Suspension Agreement. The evidence concerning this agreement,
when considered in the context of the direction that
was by then being taken by
DFAT in relation to the SATIN project, leads inexorably to the conclusion that
there was no practical
likelihood at all of the remainder of the amended Head
Contract being completed or of BHP-IT being required to do so. I find
accordingly.
To adapt an answer given by Mr Crighton, DFAT would not meet its
future needs "by continuing to develop a dinosaur". The ADCNET
project's time
had passed.
1000 Secondly, Hadley v Baxendale. As I have indicated, BHP-IT contends
that the losses claimed fall squarely within both limbs of Hadley v
Baxendale. I do not set out its submissions (with which I am in general
agreement) because I consider this to be a clear case in which, save
in one
possible respect noted below, remoteness of damage is not a significant issue.
As back-to-back contracts, the performance
of the Head Contract and the
Sub-Contract were, and were known from the time of their execution to be,
mutually interdependent:
Hydraulic Engineering Co Ltd v McHaffie, Goslett
& Co (1878) 4 QBD 670; R and H Hall Ltd v W H Pim (Junior) and Co
Ltd (1928) 33 Com Cas 324; Brooking on Building Contracts, [14.11]
(3rd ed); 22 Am Jur 2d "Damages", §469ff. Equally the
respective practical roles of the parties to the two contracts were well
known
and understood - the real customer was the Commonwealth; BHP-IT was the
project manager; and GEC Marconi, the builder. It
necessarily would have been
apparent to all parties at the time that (i) a repudiation by GEC Marconi would
have put BHP-IT in breach
of its obligations to the Commonwealth; (ii) if the
Commonwealth elected to affirm the Head Contract despite such a breach, BHP-IT
would be confronted with the choice either of engaging a fresh sub-contractor
without any domain knowledge at commercial rates, or
of using its own
resources, to perform the work that GEC Marconi had failed to do; and (iii)
given that the price for the Head Contract
was a fixed one, and fixed on the
assumption that BHP-IT's role in it was not that of builder, whichever choice
was made by BHP-IT
it was likely to result in it incurring a loss in performing
its obligations under the Head Contract. Equally, a reasonable person
in GEC
Marconi's position would have realised that, if BHP-IT had to make such a
choice because of GEC Marconi's action and chose
to do the work itself, it
would result in an actual performance of the Head Contract quite different from
that envisaged at the time
of execution of the two contracts. I am satisfied
that in light of what it knew at the time of entry into the Sub-Contract, GEC
Marconi would have realised that, if it had repudiated the contract at a time
significantly downstream in the contract's life, the
likelihood would be that
BHP-IT would be compelled to undertake further performance itself and at
significant cost to itself. I
am equally satisfied that these consequences
were sufficiently likely to result from the breach of contract as makes it
proper to
hold that they flowed naturally from it.
1001 In one respect, though, I consider the Hadley v Baxendale issue to
be possibly somewhat more problematic. BHP-IT has made a claim for loss
incurred in performing the amended Head Contract
which included loss of return
made up of loss of overheads and profit. Both, it is said, resulted from its
having to use its own
personnel and resources in what was in fact a non-profit
making activity and having to do so because of GEC Marconi's default.
Consistent
with what I have held above, no issue of remoteness could arise in
relation to the loss of overheads, there being a reasonable likelihood
of such
costs if BHP-IT were to perform the work itself. Somewhat more problematic is
the claim for loss of profits.
1002 GEC Marconi had no notice at the time of entry into the Sub-Contract of
any particular profit-making activities in which BHP-IT
was likely to deploy
its labour and resources in the future. At best GEC Marconi's reasonable
realisation would have been that,
if BHP-IT deployed its own labour and
resources in performing the amended Head Contract, it would in consequence have
been unable
to use that labour and resources in the pursuit of the trading
activities carried on by BHP-IT in the ordinary course of its business.
1003 There, doubtless, are cases in which the nature of the business conducted
by the innocent party is such that a loss of profits
is an almost inevitable
consequence of the diversion of labour and resources to do the work not done by
the party in breach: cf
Royal Pioneer Paper Box Manufacturing Co Inc v
Dejonge 115A 2d 837 (1955). I do not consider the present to be such a
case.
1004 However, I am satisfied that the dimensions of the work that GEC Marconi
left to be done and the length of time likely to be
needed to do it were such
that, on the information it had at the time the Sub-Contract was entered into,
it should have realised
that, if BHP-IT deployed its own labour and resources
to do that work, a loss of profits in BHP-IT's trading activities was likely
to
result as a natural consequence of that deployment. I do not consider the loss
of profits claim to be too remote.
1005 Thirdly, the agreement "to start from scratch". I begin by emphasising
the obvious. When BHP-IT agreed to develop the ADCNET
software itself, it was
performing its own obligation under the Head Contract, it was not purporting to
complete the Sub-Contract.
The "start from scratch" agreement has to be seen
in that context. I have referred to the evidence concerning the need for
revision
of the FRS, and the contemporary understanding that if BHP-IT was to
perform the Head Contract itself it would probably need to start
from scratch.
I have also referred to Mr Brent's explanation as to why there was a "start
from scratch".
1006 For my own part I am satisfied that the agreement to do this was a
reasonable one that was justified in the circumstances.
Given the need for
revision of the FRS, the loss of team members with domain knowledge consequent
upon the departure of GEC Marconi's
project team, the state of development of
the builds and, most importantly, the risk that BHP-IT was assuming in
consequence of the
breach, the agreement to start from scratch was in the
circumstances "a reasonable course to adopt": Bellgrove v Eldridge [1954] HCA 36;
(1954) 90 CLR 613 at 618; see also S & D Mechanical Contractors Inc
v Enting Water Conditioning Systems Inc 593 NE 2d 354, at 361 (1991).
Furthermore, I do not consider that BHP-IT could properly have been expected to
have negotiated with
GEC Marconi to acquire such intellectual property rights,
etc it derived from the project as might have been of assistance in BHP-IT's
own performance of the Head Contract. It has not been suggested that
assistance of that variety was available.
1007 Turning now to my own conclusions, I should first indicate what I consider
to be the bearing the 1997 Variation Agreement has
on the losses claimed.
First, the Variation Agreement obliged BHP-IT to repay the Commonwealth not
only the net receipt that BHP-IT
had from the Milestone payments (ie
$1,700,000) but also the amount paid over to GEC Marconi ($3,875,000). That
repayment had two
consequences. The return of the $1,700,000 eliminated the
advantage BHP-IT had enjoyed in being able to recoup costs already incurred.
In consequence the repayment ensured that all of those costs (which I later
find to be $1,830,044) were actual wasted expenditure.
The payment of
$3,875,000 to GEC Marconi, likewise, had the character of wasted expenditure.
The repayment of it to the Commonwealth
merely accentuated that for the
Commonwealth the amount in question had a like character vis-à-vis
BHP-IT. This repayment,
though, did not then represent a loss to BHP-IT at GEC
Marconi's hands as it had already recouped its payment to GEC Marconi by having
recourse to the financial securities: see Part II: The Call on Financial
Securities.
1008 Secondly, the effect of the Variation Agreement on the claim for the loss
of the benefit of the Head Contract was that it rendered
impossible the actual
performance by, and the return to, BHP-IT that was envisaged under the original
Head Contract/Sub-Contract
arrangements. The milestones had been changed as
had BHP-IT's actual role in the new arrangement. BHP-IT could no longer render
such performance as would secure the payments from the Commonwealth to which it
previously would have been entitled on the basis
contemplated under the
original arrangement with GEC Marconi.
1009 It is important to appreciate the character of the actual claims made by
BHP-IT. The claims for the lost benefit of the original
Head Contract and for
costs incurred until December 1996 are really claims in the alternative, as I
will indicate. Both relate to
the performance of the original Head Contract,
the former being for expectation damages, the latter, for wasted
expenditure.
1010 The claim for costs incurred in performing the amended Head Contract is in
the nature of a claim for additional costs incurred
- hence a consequential
loss sustained - which would not otherwise have been incurred but for GEC
Marconi's repudiation. Though,
as will be seen, the costs claimed are
constituted in part by a loss of profits in consequence of the performance
BHP-IT actually
rendered, the claim itself is not for any expectation loss as
such. Nor is it a conventional claim for damages for loss of an opportunity.
It is for an actual consequential loss suffered as a result of having to
perform the amended Head Contract consequent on GEC Marconi's
failure to
perform the Sub-Contract.
1011 Each of the two types of claim - the one relating to the performance of
the original Head Contract, the other relating to performance
of the amended
Head Contract - represent separate and distinct heads of damage that BHP-IT is
entitled to claim. They do, though,
overlap in one respect that does give rise
to the possibility of double recovery. The claim for the lost benefit of the
original
Head Contract as put takes no account at all of BHP-IT's later
performance of the amended Head Contract. That later performance
does not of
itself preclude the making of this claim. It stands apart from it for the
following reason. I have found that the Variation
Agreement amended, but did
not discharge, the Head Contract. BHP-IT's obligation to perform that contract
remained, albeit it was
amended in significant respects. However, considered
from the standpoint of the parties to the Sub-Contract, and bearing in mind
that the present claim is for breach of the Sub-Contract, the effects of the
Variation Agreement were of a profoundly different character.
As I have
indicated above, that agreement rendered impossible the actual performance by,
and the return to, BHP-IT that was envisaged
under the original Head
Contract/Sub-Contract arrangement. The milestones had been changed as had
BHP-IT's actual role in the arrangement.
BHP-IT could no longer obtain the
payments from the Commonwealth to which it previously would have been entitled.
A different performance
was being rendered and was being paid for differently,
albeit for an unchanged price overall. BHP-IT was, in consequence, entitled
to
claim expectation damages resulting from loss of the benefit of the original
Head Contract as it would have been performed had
GEC Marconi not repudiated.
The hypothetical situation to be considered in such a claim would not involve
any consideration of BHP-IT's
subsequent actual performance of the amended Head
Contract. That performance was simply not envisaged by the scheme of the
Sub-Contract
and the original Head Contract.
1012 However, to the extent that the subsequent actual performance resulted in
a net profit to BHP-IT that net profit had to be brought
into account. Whether
in its original or in its amended form it was on the Head Contract that BHP-IT
expected to make its profit.
To the extent it actually did so, notwithstanding
GEC Marconi's default, it could not claim the full extent of its loss of net
profits
in the action against GEC Marconi on the Sub-Contract. If a profit was
actually derived, it diminished to that extent the expectation
loss suffered.
That such a profit was derived in changed circumstances (ie by BHP-IT's own
performance of the work) did not alter
the character of that return. That it
was earned in changed circumstances, though, gave greater significance to the
consequential
loss claim. It was that claim that dealt with the costs to
BHP-IT of its own performance.
(i) The claims for the lost benefit of the Head Contract/costs incurred
until December 1996.
1013 The second of these claims is in the alternative to the first, given the
way in which BHP-IT has put its primary claim. The
claim for loss of the
benefit of the Head Contract is a claim for the difference between the amounts
payable under the Head Contract
and the Sub-Contract (ie $3,391,000). The
basis on which that sum is claimed (or else that sum minus performance costs of
$264,067
which it did not have to incur in consequence of the breach) is that
if GEC Marconi had performed the Sub-Contract, BHP-IT would
have received that
sum and the assessment of what portion was cost and what was profit was
irrelevant. It was always going to receive
that sum. For reasons I give below
I am unable to accept this simple and obviously abbreviated way of dealing with
an expectation
damages claim: and cf Hydraulic Engineering Co Ltd v
McHaffir, Goshett & Co, above.
1014 The alternative claim for costs incurred to December 1996 were
recoverable, if at all, as wasted expenditure.
1015 By way of preface to my consideration of the claims I should indicate that
I consider that the sum of $1,250,000 in fact retained
by BHP-IT on account of
Milestone 1000 of the amended Head Contract was, and was intended by the
parties to be, a bona fide "Mobilisation"
payment for the "Formal resumption of
the project work" under Schedule 8 of the contract. It was a sum from which
costs incurred
in anticipation of, and in the performance of, the amended Head
Contract were intended to be recouped.
1016 The difficulty I have with the abbreviated method employed by BHP-IT to
ascribe a value to the lost benefit of the amended Head
Contract, is that it
does not adequately identify the costs which BHP-IT was likely to have incurred
"as and from [the date of the
breach], in performing its own contractual
obligations": Amann Aviation Pty Ltd, at 161. Those saved performance
costs are to be deducted from the value of the benefits BHP-IT was still to
receive under the Head
Contract: ibid, 161-162. For this reason it will be
necessary to plot a rather tortured path through the expenses, receipts and
benefits (actual and estimated) of the original Head Contract.
1017 The figures relied upon by BHP-IT to establish the costs it actually
incurred in the performance of the Head Contract up until
GEC Marconi's
repudiation are the raw project cost expenses that have been recorded
internally by BHP-IT in project cost enquiry
reports as having been incurred on
the ADCNET project over the relevant period. They amount to $1,830,044. This
is the aggregate
of the costs (labour costs plus project expenses) recorded by
BHP-IT for two periods (1 June 1994-31 May 1995 and 1 June 1995-31
December
1996) and which coincided with its achieving, in the first period, Milestones
1000 to 3000 ($706,200) and then, in the second,
with its pursuing Milestone
4000 (ie $1,123,844). These figures do not include a sum for the internal
margin that Mr Hammond purported
to apply to them in his evidence. In light of
its submissions, I do not understand BHP-IT to be now claiming that margin. In
any
event, I do not consider it likely that the figures containing the margins
used by Mr Hammond reflected either BHP-IT's actual costs
at the time or any
contemporary appreciation that they were the actual costs incurred. The 1996
Quarterly reviews and Mr Brent's
evidence of his recollection at the time
suggest to the contrary.
1018 GEC Marconi has invited me to reject the evidence relied upon by BHP-IT to
establish the actual costs "reasonably incurred by
it in the discharge of its
contractual obligations": Amann Aviation Pty Ltd, 81. To the extent
that these costs were recorded as "Project Expenses", it is contended there was
no evidence led as to their nature
and to the reason for their having been
incurred. As to the recorded labour costs, while at best demonstrating costs
incurred, they
do not demonstrate any actual loss And no provision has been
made by way of discount for the likelihood that non-chargeable time
was
recorded. Additionally, it is said, some of the cost claimed in the first of
the two periods mentioned above predated the signing
of the ADCNET contracts.
There is no evidence explaining what those "pre-contract" costs were.
1019 For its part BHP-IT contends that the relevant project cost enquiry
reports upon which its calculations were based, though summary
in form, were
primary accounting records comprising extracts from the accounting ledgers of
BHP-IT that utilised the methods of recording
costs I have described earlier in
these reasons. The discontinuance and replacement of BHP-IT's accounting
system in 2000 prevented
access to detailed cost data for every BHP-IT person
who performed work on the project. BHP-IT submits that, given the evidence
as
to how the cost enquiry reports were prepared and used by BHP-IT to record its
actual costs - I have not reproduced it here -
they can be relied upon as the
best primary evidence of the actual costs incurred by BHP-IT or else as
evidence from which to make
the best estimate of the damages sustained by
BHP-IT.
1020 The raw figures as to costs that are relied upon by BHP-IT were booked by
it to the ADCNET project when they were incurred.
Though a deal more
explanation of the nature of, and reason for, them would have been helpful, I
am prepared to accept them as establishing
the actual costs incurred by BHP-IT
in performing the ADCNET contracts notwithstanding the level of generality at
which they were
presented in evidence. It would have been quite unreasonable
to have expected, and quite oppressive to have required, a detailed
explanation
of the myriad of items recorded in the project reports and time sheets that
have been tendered.
1021 I recognise that, because the initial recording of costs by BHP-IT
employees involved a manual process, there was scope for
error in that
non-chargeable time or expenses could have been recorded or that time could
have been wrongly recorded. I consider
that recording errors were as likely to
be wrongly disadvantageous to BHP-IT as they were to be wrongly advantageous,
if such errors
occurred in any measurable number. For this reason if the
project cost inquiry reports do not record with absolute accuracy the
actual
costs incurred those reports are the best estimate of those costs. And I
accept those estimates as being reliable for present
purposes.
1022 I should add that if these actual costs include costs incurred on account
of the contract, though prior to its execution, they
would be recoverable in a
claim for wasted expenditure (which is the alternative claim advanced): see
Amann Aviation Pty Ltd, at 100; Lloyd v Stanbury [1971] 2 All ER
267. I am in any event not satisfied that the cost inquiry report demonstrates
there was pre-contract expenditure.
It merely records expenditure in the
relevant financial year of BHP-IT without ascribing a time to when it was
incurred.
1023 I am satisfied then that in earning Milestones 1000 to 3000, BHP-IT
incurred expenses of $706,200 although, importantly, it
obtained the sum of
$1,700,000 by way of net receipt for those milestones. I am likewise satisfied
that BHP-IT incurred expenses
of $1,123,844 on account of Milestone 4000 but
that that milestone was never achieved and thus never paid for.
1024 BHP-IT's contention is that the actual costs incurred by it were the sum
of these two sets of expenses and amounted to $1,830,044.
Its September 1994
estimate of the costs it would incur in performing the ADCNET contracts was
$2,094,111 and it estimated it would
in consequence have earned a return of
$1,297,293. The effect of GEC Marconi's repudiation was to have relieved
BHP-IT of the need
to incur the further expenditure of $264,067 (being the
difference between its 1994 costs estimate and the actual costs incurred).
Therefore it was entitled to receive by way of damages the sum of $1,830,044
(its actual costs) and $1,297,293 (the return to be
earned) minus $264,067 (the
costs saved by not having to perform the balance of the Head Contract).
1025 In my view, this claim too readily assumes an important component in what
has to be proved. As was said in Amann Aviation Pty Ltd (at 80), when
expectation damages are sought:
"[t]he onus of proving damages sustained lies on a plaintiff and the amount of damages awarded will be commensurate with the plaintiff's expectation, objectively determined, rather than subjectively ascertained. That is to say, a plaintiff must prove, on the balance of probabilities, that his or her expectation of a certain outcome, as a result of performance of the contract, had a likelihood of attainment rather than being mere expectation": emphasis added.
1026 BHP-IT's September 1994 estimate was that its gross profit would be
$835,912 producing a net profit before tax of $820,912.
A separate estimate
was made for contingency and risk for which an allowance of $461,381 was made,
this figure being referable (as
to $156,686) to BHP-IT's own performance and
(as to $304,695) to non BHP-IT costs.
1027 I am satisfied that these estimates were reasonable estimates when made
and they continued to be relied upon by BHP-IT for at
least certain of its
internal purposes up until the Sub-Contract was repudiated, as witness the 1996
quarterly review reports. I
should add, though, that I do not regard the
actual "estimates" Tables used in those reviews (an example of which I
reproduced above)
as being particularly helpful for present purposes as they
seem to do no more than show the effects of contract variations on the
estimates as originally made. They do not, for example, record actual costs
incurred though one can infer that, if the known actual
costs had diverged so
significantly and adversely from the original estimates as to call them into
serious question, this would have
been reflected in the quarterly reviews.
1028 Accepting the original estimates for profit and for contingency and risk
were reasonable, the questions that arise are whether
the former (ie for
profit) remained reasonable and realistic, and whether the latter (ie for
contingency and risk) was likely to
have been unnecessary in light of
subsequent events. I have already indicated that Mr Hammond conceded (a) that
he did not attempt
to see whether the Head Contract would have been loss-making
or profit-making if GEC Marconi had fully performed; and (b) that it
would
have been possible for someone within BHP-IT to determine what further work
BHP-IT would need to have done with GEC Marconi
to achieve Milestones 4000 to
7000.
1029 BHP-IT in its final reply submissions accepts it can still recover its
anticipated profits "provided expectation of such profits
remained reasonable
at the time of repudiation". It then contends GEC Marconi's repudiation made
it impossible to establish what
its actual profits would have been, therefore
the only available evidence would be evidence of anticipated profits and the
best evidence
of that was the estimate in its 1994 costing for the project. It
submits that the reasonableness of that costing is borne out by
subsequent
events, with only $1,830,044 of the projected cost of $2,094,111 having been
incurred notwithstanding that the project
had already overrun by ten months.
1030 Save for what I have to say below on contingency and risk, I would have
accepted that the net profit figure of $820,912 was
one of which there was some
likelihood of attainment. In achieving Milestones 1000 to 3000, BHP-IT
retained a cash benefit of about
$1 million over its expenditure (circa
$700,000). It is unsurprising that Mr Brent's Marketing and Operations Report
of December
1995 had its optimistic note - "Expenditure is below budget,
revenue and profit ahead of budget".
1031 Achieving Milestone 4000 would not have been so bountiful. The evidence
suggests that, at best, the outcome would have been
a break-even one for costs
and receipts for that milestone. Expenses so far incurred on account of that
milestone were $1,123,844
while the net payment to be retained by BHP-IT from
the Commonwealth's payment on achievement of it was $1,140,000.
1032 There is no explicit evidence of the likely estimated cost of achieving
the remaining three milestones, though the effect of
BHP-IT's alternate
submission is that its figure for the expenditure saved of $264,067 would in
large degree provide that estimate.
The net receipt BHP-IT would have derived
from the payment of the remaining milestones after paying GEC Marconi would
have been
$551,309.
1033 When Milestone 4000 would have been achieved, BHP-IT would have received
80% of the total Head Contract price. It seems reasonably
clear from the
Schedule 8 Implementation Plan and from the state of progress the SDP envisaged
would have been achieved by the time
of Test Readiness Review at that
milestone: see "Part I: Non-Payment for Milestone 4000"; that the
preponderance of the development
work to be performed would have occurred by
that stage.
1034 It is also clear that such was not actually the case with the work done
under the Sub-Contract. I have referred earlier to
the state of the builds.
There equally is no doubt that delays had occurred for reasons related both to
the non-provision of STUBS
and otherwise. The FRS posed its own problems. And
there was the on-going dispute. I do not consider it surprising that in the
August and November quarterly reviews of the ADCNET project, an overhead
indicated that while the "reported status" of the project
was 68% complete, the
"[a]ctual status is probably 20-40%". Mr Brent confirmed that that was his
view at the time. In May of 1996
he had already expressed the view to GEC
Marconi that "the overall earned value of the IPD Component ... can only be
somewhere below
20% complete".
1035 While the costs of the delayed progress would have sounded in claims for
liquidated damages (though this had a low ceiling for
the total that could be
claimed: Schedule 8, cl 2.1) or in a possible common law claim, they would in
my view also have had some
reflection in BHP-IT's own performance costs.
1036 This brings me to the question of contingency and risk. The 1994 estimate
envisaged (not unexpectedly given its purpose) that
the allowance for
contingency and risk would be expended. BHP-IT's claim here is based on it
being entirely unexpended and therefore
as constituting a component of the
"contribution" it would have received for performing the Head Contract.
1037 I am not satisfied that such would have been the case. And given the
supposition in the 1994 estimate of the risk allowance
that it would be
exhausted, I would have expected evidence to have been given that it had not
been called upon at all up until the
time of termination if such was the case.
The only document of which I am aware which refers to possible use of the
allowance is
that set out above which relates to additional costs due to the
dispute with GEC Marconi as at 10 November 1996 and which suggested
that the
unexpended provision for risk remaining at that date was only $52,520. This
document has not been explained by any witness.
And it is only evidence of the
accounting adjustments that BHP-IT chose to make for its own purposes. What it
does suggest, though,
is that BHP-IT was incurring unenvisaged costs in
consequence of the dispute with GEC Marconi for which specific provision had
not
otherwise been made. Unless those costs were recoverable from GEC Marconi
- and, as will be seen, BHP-IT has made a significant
dispute management claim
against GEC Marconi which I reject later in these reasons: see "Dispute
Management Costs" - they stood
to dilute the contribution BHP-IT could
reasonably have expected to have derived from the Sub-Contract's performance.
It is on this
basis that Commonwealth relies upon this particular document. I
will refer separately below to particular submissions made in relation
to it by
BHP-IT.
1038 Given (a) what I said earlier both about the actual status of the project
and about the contractual environment in which BHP-IT
was to render its
performance, (b) Mr Brent's stated concern that while the "profit position
looked good ... the risk position did
not", and (c) the original estimate that
the contingency and risk allowance would be consumed, I am not satisfied that
on the balance
of probabilities that this allowance would have made any
contribution to the profit BHP-IT would have made had the Sub-Contract been
performed. In reaching this conclusion, I am estimating that BHP-IT would at
least have incurred costs in the order of about $800,000
to have completed the
Head Contract. I accept that the Sub-Contract and the Head Contract contained
mechanisms that protected BHP-IT
from the financial consequences of many of the
risks to which it was exposed because of the delayed progress of the project,
though
as I have indicated, the liquidated damages provision set a low ceiling
to the total that could be claimed under it. This said,
I consider the figure
of $800,000 to be a more than conservative one.
1039 The Sub-Contract was dramatically improvident for GEC Marconi and it posed
technical impediments because of the FRS. Even assuming
that the contract
proceeded to completion using the emulator, it would in my view have remained a
challenging one not only for GEC
Marconi, but also for BHP-IT. As past
performance had shown, GEC Marconi had been and would have been unable to keep
to the contract
schedule. Delays and negotiations for contract extensions
would have remained the hallmarks of the project. Yet the aggregate of
liquidated damages payable was 5% of the contract price, although it was open
to BHP-IT to claim damages at common law for losses
flowing from delays caused
by GEC Marconi.
1040 It was inevitable in my view that BHP-IT would have had to absorb some of
the costs of delay. I likewise consider that the
state of the FRS would have
had to be addressed. Management of the contracts to completion would have been
more burdensome than
was envisaged in the 1994 estimates and that burden would
have been reflected in BHP-IT's costs.
1041 Before indicating what I consider would be an appropriate award for profit
in the circumstances, I should first refer to the
separate submissions made by
BHP-IT on how I should treat both risk and the costs associated with the
dispute with GEC Marconi prior
to BHP-IT's acceptance of the latter's
repudiation of the Sub-Contract. The submissions are premised upon the
propositions that
GEC Marconi had both breached the Sub-Contract from early
1996 and had repudiated it by at least June 1996. The latter submission
in
particular is consistent with my finding on repudiation: "The Repudiation
Claim". It is likewise possible to point to non-compliance
with timetable
requirements that manifested breaches of the Sub-Contract. It is unnecessary
that I identify the latter or that I
consider such issues as whether any such
breaches had been "waived", etc.
1042 As I understand them, BHP-IT's submissions are, first, that the costs
associated with the dispute are losses suffered in consequence
of breaches that
had occurred up to and including June 1996 and were recoverable as such because
the right to claim them had accrued
prior to termination; secondly, those
losses should thus not be taken into account for risk and contingency purposes
with the consequence
that I should regard the provision made for risk as
unaffected by the dispute costs and I should treat the risk allocation as
unexpended
notwithstanding the 10 November 1996 document; and, thirdly, in any
event, as GEC Marconi repudiated the contract by June 1996,
I should assess
BHP-IT's damages for expectation loss from that time and at that time the risk
allowance was intact and as such should
be treated in its entirety as
contribution.
1043 These submissions can be dealt with briefly. Later in these reasons I
reject BHP-IT's claim for damages for dispute management
costs. Those costs in
consequence would have diluted the contribution BHP-IT stood to derive from the
Sub-Contract's performance,
as I have earlier indicated.
1044 As to the submission that BHP-IT's expectation losses should be assessed
as at June 1996, I need only note that (i) "[l]oss
of bargain damages are
recoverable only if the contract is at an end": Sunbird Plaza Pty Ltd v
Maloney [1988] HCA 11; (1988) 166 CLR 245 at 260; and (ii) "there can be no breach for
loss of bargain following repudiation until that repudiation is accepted.
Only
then is the contract terminated and damages able to be calculated as at that
date": Ronnoc Finance v Spectrum Network Systems Ltd (1997) 45 NSWLR
624 at 636. In the present matter the appropriate time to calculate loss of
bargain damages is at the time the bargain
was lost, ie at the date repudiation
was accepted. On its own case BHP-IT could have accepted GEC Marconi's
repudiation by at least
June 1996. It chose not to do so and incurred
unprovided for costs in consequence. The incurring of those costs provides no
reason
for manufacturing a loss of bargain at an earlier date than when that
loss actually occurred.
1045 I turn now to the question of the measure of relief to which BHP-IT is
entitled. It has often enough been recognised that difficulties
of estimation
do not relieve a court of the responsibility to arrive at an assessment of
damages: eg Fink v Fink [1946] HCA 54; (1947) 74 CLR 127 at 143. In light both of the
performance rendered up until the time of repudiation and of the contingencies
to
which I have referred, I am satisfied that the Head Contract would have
remained profitable for BHP-IT and that that profit, while
not reaching the
level estimated in 1994, would have not fallen significantly short of it. An
award for profit of $700,000 would
be appropriate in the circumstances.
1046 Subject to the question whether any actual net profit was achieved on its
actual performance of the amended Head Contract -
and I later find there was
not - BHP-IT is entitled to be compensated for the loss of the benefit of the
Head Contract in the sum
of $2,530,044, that sum being made up of $1,830,044
for wasted expenditure and $700,000 for loss of net profit.
(ii)
Costs of Performing the Variation Agreement
1047 The central issue raised by this claim is encapsulated in the statement of
principle made by Megarry V-C in Tito v Waddell (No 2) [1997] Ch 106 at
332:
"if the plaintiff can establish that his loss consists of or includes the cost of doing work which in breach of contract the defendant has failed to do, then he can recover as damages a sum equivalent to that cost. It is for the plaintiff to establish this: the essential question is what his loss is." Emphasis added.
It is no answer to such a claim that, as in the present case, the plaintiff is
in turn contractually obliged to do the work the defendant
has failed to do.
Such is the commonplace, in a claim by a lessee against a sub-lessee for breach
of the covenant to repair: see
eg Conquest v Ebbetts [1896] AC 490;
McGregor on Damages, para 1077ff (16th ed); and, as
illustrated in case law in United States jurisdictions, in claims by a head
contractor against a sub-contractor on
account of the latter's failure to
perform, or adequately to perform, the contracted for work: S & D
Mechanical Contractors Inc v Enting Water Conditioning Systems Inc 593NE 2d
354 (1991): US v Curtis T Bedwell & Sons Inc 506 F Supp 1324
(1981); see also "Comment Note: Overhead Expense as Recoverable Element of
Damages" 3 ALR 3d 689 at [8] (US). However,
that the plaintiff may be
remunerated in turn for doing that work does bear directly on the question of
"what his loss is".
1048 The way BHP-IT put its case originally in submissions was, in effect, as a
claim for damages for a form of "lost opportunity
to bargain" (cf Sharpe and
Waddams, "Damages for Lost Opportunity to Bargain" (1982) 2 OxJLS 290) a
realistic commercial price with
the Commonwealth for the actual performance it
had to render after GEC Marconi's repudiation. As later developed, the claim
was
put as one for compensation for the actual cost to BHP-IT of being forced
by GEC Marconi's repudiation to utilise its own labour
and other resources for
a long period and with no return, in performing the work GEC Marconi had
contracted with it to perform.
In its ordinary course of dealings BHP-IT would
have expected a return for having to render its services. That lost return in
this
case - the "opportunity cost" - was a loss suffered by BHP-IT.
1049 While the latter approach avoids the risk of the claim being seen as
simply a claim for loss of an opportunity to make a profit
of the type
exemplified by Sellars v Adelaide Petroleum NL [1994] HCA 4; (1994) 179 CLR 332 - a
risk GEC Marconi has sought to exploit - the two approaches outlined above are
in substance indistinguishable.
They both focus on the loss of a reasonable
commercial return for the services rendered as an actual cost to BHP-IT.
1050 Put shortly the actual claim is that in having to perform the amended Head
Contract at a predetermined price, BHP-IT was unlikely
to obtain any return by
way of profits or contribution to overheads for the work done. If it had been
done in the ordinary course
of BHP-IT's commercial dealings (on its usual costs
plus basis) it would have been done at a price that incorporated profit and a
contribution in the order of $6,798,767. It is this sum, or else a proportion
of it (to reflect the suspension decision with 55%
of the work completed), that
BHP-IT claims as its loss.
1051 While BHP-IT relies upon orthodox principles governing contractual damages
to support the loss claimed, it does seek support
for the "loss of return"
component of the claim from somewhat analogous situations in which such damages
are awarded. The first
of these relates to cases, illustrated by
Hungerfords v Walker [1989] HCA 8; (1990) 171 CLR 125, in which damages have been
awarded for loss of use of money. The second is where a party has been allowed
the
reasonable cost of repairs effected by it personally to remedy damage to
its own property that was sustained by another's tortious
act: Price v
Commissioner of Highways [1968] SASR 329 at 332-333; Commonwealth
Railways Commissioner v Hodson (1970) 16 FLR 437; Trindade and Cane,
The Law of Torts in Australia, 553 (3rd ed). The third and more
distant analogy relied upon, again from tortious damages, is that where a
person loses the use of a profit-earning
asset through the wrong of another.
In such a case the aggrieved party is entitled to recover as damages flowing
naturally from the
wrong, either loss of profits during the period in which the
asset is unavailable where there was otherwise a reasonable certainty
of their
having been earned or else general damages for the loss of such profits which
it must reasonably have been anticipated would
have ensued during that period:
The Argentino (1888) 13 PD 191; affd (1889) 14 App Cas 519; The
Hebridean Coast [1961] AC 545 at 562-565; McGregor on Damages, para
1336ff (16th ed); and see also Oldcastle v Guinea Airways Ltd
[1956] SASR 325. Finally, BHP-IT it is said, was obliged because of GEC
Marconi's wrong to commit substantial resources of its own
to performing the
Head Contract and thus had to forgo the deployment of those resources on other
profitable contracts. It should
in consequence be compensated for the loss of
such profits. For the purposes of showing there were profit-making
opportunities available,
it relies upon the evidence of Mr Dart relating to
BHP-IT's growth in the period from the end of 1997 to 1999 and to the demand
for
software development skills in the market place.
1052 In my view there can be no doubt that GEC Marconi's repudiation cast on
BHP-IT a burden that was unanticipated and unbargained
for by BHP-IT. GEC
Marconi was to perform the actual work in question for BHP-IT. It failed to do
so. It then had to be done by
BHP-IT deploying its own resources for the
purpose. As GEC Marconi well understood, BHP-IT contracted with the
Commonwealth on one
basis (ie the actual work would be performed by a
sub-contractor). It was being required to perform on another. Subject to its
bringing into account payments received from the Commonwealth for its
performance of the amended Head Contract, BHP-IT is entitled
to claim as
damages its costs in doing the work GEC Marconi failed to do: Tito v
Waddell (No 2), at 332. The real issue is whether the costs actually
incurred by BHP-IT can properly be said to include a component representing
the
loss of return (or sacrifice of profit) for doing the work.
1053 The principal way in which BHP-IT now puts its case is premised upon the
proposition that a commercial enterprise will not in
the ordinary course agree
to supply goods or to render services for no return, although on occasion it
may be forced to do so. In
support of this it draws on the observations of
Mason CJ and Dawson J in Amann Aviation Pty Ltd, at 81 that:
"In the ordinary course of commercial dealings, a party supplying goods or rendering services will enter into a contract with a view to securing a profit, that is to say, that party will expect a certain margin of gain to be achieved in addition to the recouping of any expenses reasonably incurred by it in the discharge of its contractual obligations."
1054 Having so identified the expectation of a business enterprise, BHP-IT
then contends that the sacrifice of profit unavoidably
entailed in an activity
carried on by a business is a cost associated with the conduct of that
business. That is a real and identifiable
cost that is measured by the
difference between the price charged by the supplier in the particular case and
the price necessary
to compensate the supplier for the profit it is forced to
sacrifice because of the supply: Telecom Corporation of New Zealand v Clear
Communications Ltd (1995) 32 IPR 573 at 593-594. In this BHP-IT seeks to
pray in aid the economists' conception of "opportunity cost": cf Dart
Industries Inc v Décor Corporation Pty Ltd [1993] HCA 54; (1993) 179 CLR 101 at
123. BHP-IT thus contends that GEC Marconi's repudiation obliged it to
complete the Head Contract itself
and in so doing to tie up its own personnel
and resources for a lengthy period and for no return. To so use its personnel
and resources
involved the relevant sacrifice of profit. It is entitled to be
compensated for that sacrifice.
1055 BHP-IT enlarged upon this "opportunity cost" claim in supplementary
submissions responding to questions I had asked. It noted
that the concept of
opportunity cost is well recognised in Australasian Law: see Hungerfords v
Walker [1989] HCA 8; (1990) 171 CLR 125 at 143-4, I & L Securities Pty Ltd v HTW
Valuers (Brisbane) Pty Ltd [2002] HCA 41 (2 October 2002) at para 123;
Dart Industries Inc v The Décor Corporation Pty Ltd [1993] HCA 54; (1994) 179
CLR 101 at 114 and 123-5; Apand Pty Ltd v Kettle Chip Company Pty Ltd [1999] FCA 483;
(1999) 162 ALR 505 at 520.
1056 The concept has been applied to the expenditure of funds and to an
investment in capital assets. BHP-IT contends there is no
reason why it ought
not to be applied to the forced deployment of skilled staff to complete a
software development project that was
the subject of a repudiated obligation
owed by a sub-contractor, in circumstances where the expenditure of funds will
not otherwise
derive any commercial return. There is no logical difference
between monies invested in plant and equipment, such as a ship or crane,
and
monies invested in retaining and deploying skilled software developers.
1057 Despite its allure I am unable to accept the contention as put. I am
satisfied that, subject to its bringing to account its
receipts from the
Commonwealth, BHP-IT is entitled to claim its actual costs in performing the
amended Head Contract. Those costs
include its direct costs, expenses and
charges and, importantly, loss of overheads. It does not include that
component of loss of
return attributable to loss of profits. The reason for
that exclusion is that no presumption, special or default rule entitles BHP-IT
to claim such a loss in circumstances such as the present without proof of it.
I am not satisfied that BHP-IT has proved it suffered
such a loss: cf
Sunley (B) & Co Ltd v Cunard White Star Ltd [1940] 1 KB 740 at 747;
S & D Mechanical Contractors Inc v Enting Water Conditioning Systems
Inc, at 362ff; see also Ellis-Don Ltd v The Parking Authority of
Toronto (1978) 28 BLR 98 at 124ff; Keating on Building Contracts,
8-67, 8-68 (7th ed).
1058 I equally am not satisfied that the law has yet developed to the point at
which it is open to BHP-IT to make such a generalised
claim for "opportunity
cost" as it does. No single idea (other than compensating actual losses), let
alone a single rule, encompasses
the range of circumstances in which, and the
bases on which, damages can properly be awarded for what, for convenience I
will call,
"loss of use of resources or diversion of resources" consequent upon
a tort or a breach of contract. To illustrate this obvious
point I refer to
two common examples.
1059 The first is where a person (a) has used his or her own time (which would
not otherwise have been used for profit making purposes)
to remedy damage or
loss caused by another's tort or breach of contract; or (b) has lost the use
of a non-profit earning or a loss-making
chattel that has been damaged by
another's tort or breach of contract - and then claims damages for that lost
time so expended:
cf Price v Commissioner of Highways [1968] SASR 399,
or for that loss of use: cf The Mediana [1900] AC 113: Nauru Local
Government Council v New Zealand Seamen's Industrial Union of Workers,
above, at 477 (ll 6-16). Though no loss of return in the nature of a profit
could be claimed in such cases, in each instance a
compensable loss has been
sustained. And in both cases default rules have been employed, as appropriate
in the circumstances, to
provide recompense for what is recognised to be an
actual loss, the monetary expression of which is often difficult to calculate
-
hence the resort to measures based on rates of hire, labour rates, interest on
capital etc: for the variations in relation to
loss of use of chattels see
generally McGregor on Damages, para 1349(a)ff (16th ed);
Waddams, The Law of Damages, 1.2030ff (3rd ed).
1060 The second illustrative case is that in which a loss of profits can so
reasonably be anticipated to have ensued from a tort
or breach of contract that
resort properly be had to some standardised formula to assess that anticipated
loss given what was reasonably
to be expected in the circumstances in the
particular sphere of economic activity in which the alleged loss has been
sustained:
in the case of shipping, see eg The Argentino (1889) 14 App
Cas 524-524 and the explanation of "demurrage" in this context in McGregor
on Damages, paras 1336-1337 (16th ed). I would note in passing
that the evidence in this case does not throw light upon the nature of the
workings of this particular
industry or upon the losses that might reasonably
be anticipated to have ensued from a breach of contract such as in this
case.
1061 What is common to both illustrations is proof that an actual loss has been
sustained. They differ significantly in the manner
in which, and the bases on
which, that loss is translated into a damages award.
1062 BHP-IT cannot be awarded damages to compensate it "for some kind of harm
which [it] cannot prove that [it] ever sustained":
The Hebridean Coast
[1961] AC 545 at 578. The monetary expression of an actual loss or harm
suffered may be difficult to estimate where precise evidence
is not available:
Amann Aviation Pty Ltd, at 83. But the fact of the loss itself is not
to be presumed. As was said by the English Court of Appeal in Sunley (B)
& Co v Cunard White Star Ltd, at 747, of a claim (inter alia) for loss
of profits said to have been occasioned by a breach of contract resulting in
delayed delivery
of a machine used for income producing purposes:
"In [the] circumstances, the plaintiffs really failed to prove any facts on which their damages could be estimated. In the absence of evidence they relied on the law. And the learned judge unfortunately succumbed to the invitation to discuss a variety of cases like The Mediana (I) at great length. Those cases establish that when a plaintiff is deprived of the use of a chattel which he does not use for making profit he is not to be debarred from claiming as damages what during that time its use would have been worth to him, had he not been prevented from using it. But those cases are no authority for the proposition that, if the owner of a profit-earning chattel does not prove the loss he has sustained, the judge may make a guess in the dark and award him some arbitrary sum."
1063 I would note in passing that in the United States where a loss of
profits is claimed in consequence of a tort or of a breach
of contract, a
similar requirement of proof of the loss is imposed: see generally 22 Am Jur
2d "Damages", §624ff. This has
been notably so where, as in the present
case, the loss claimed was of profits foregone because a head contractor was
forced to use
its own employees and plant when doing, or supervising the doing
of, work which in breach of contract a sub-contractor had failed
to do: see eg
US v Curtis T Bedwell & Sons Inc 506F Supp 1324 (1981); S &
D Mechanical Contractors Inc v Enting Water Conditioning Systems Inc,
above. I would, though, acknowledge that the usual requirement in United
States jurisdictions that a loss of profits be proved
with "reasonable
certainty": cf Farnsworth, Contracts, §12.15 (3rd ed);
may well impose a more exacting proof than is the case in this country: cf
Amann Aviation Pty Ltd, at 83-84.
1064 BHP-IT has not sought in its claim to differentiate for any operative
purpose between its alleged loss of overheads and its
loss of profit. The
claim advanced has been a global one embodying both of these elements. As a
matter of principle in a case such
as the present, where there is no issue of
remoteness: cf Parta Industries Ltd v Canadian Pacific Ltd (1974) 48
DLR (3d) 463; there is probably "no logical distinction to be drawn between a
claim for lost profit and a claim for lost
overhead:; Ellis-Don Ltd,
above, at 127; although, importantly, the loss of each does require separate
proof: cf S & D Mechanical Contractors Inc, above, at 362ff.
1065 Considering first the claim for lost profits, for BHP-IT to succeed in its
claim it was necessary for it to demonstrate that,
but for its having to deploy
its labour and resources as it did there was a reasonable likelihood that the
profit it claims was thus
foregone would have been available to it. The
Commonwealth could not have been the source of that profit. The price of the
Head
Contract had long since been fixed. BHP-IT has not pointed to any
particular profit making activity in which there was a "reasonable
certainty"
of it otherwise deploying its labour and resources: The Hebridean Coast
[1961] AC 545 at 562; but which was forsaken because it was required to
divert its own resources to correct the problem created by
GEC Marconi: S
& D Mechanical Contractors Inc, at 363; and which resulted in a "loss
of profits which could reasonably be expected to have been derived": Nauru
Local Government Council, above, at 477.
1066 Apart from several observations of a most generalised character in the
evidence of Mr Dart and Mr Hammond to the effect (a)
that the rate of growth of
BHP-IT in an eighteen month period between 1997 and 1999 was 40 per cent
outside the domain of BHP (ie
the parent company) whatever that might have
signified; (b) that the period was one of "reasonable buoyancy" for BHP-IT;
(c) that
there was a strong growth in the IT industry across all sectors; and
(d) that there was a substantial demand for software engineers,
there was
little in the evidence to illuminate in any satisfactory way how profits such
as claimed by BHP-IT could reasonably have
been earned by it in the then IT
market - a market, moreover, the workings and profitability of which has not
been the subject of
evidence. I do not regard the observations to which I have
referred above as assisting in any way in laying the foundation for proof
of
the loss claimed.
1067 BHP-IT's loss of profits case has not really been advanced (save as a
faint alternative) on the basis that its actual loss had
to be proved by
demonstrating that, in consequence of its diversion of labour and resources,
other actual opportunities were foregone.
This explains the state of the
evidence on this matter. The case, as finally put, was that the loss inhered
in having to do GEC
Marconi's work without return or contribution. As I have
indicated, an alleged loss of profits cannot be assumed. I am not satisfied
that it has been proved that this was a loss sustained by BHP-IT.
1068 Turning to the loss of contribution to overheads, I note again that BHP-IT
has not sought operatively to distinguish this form
of loss from its loss of
profits. This said, and subject to any question of recoupment from moneys paid
by the Commonwealth, BHP-IT's
overhead expenses to the extent that they were
reasonable and were properly allocated to its performance of the Head Contract
were
recoverable by way of damages as an actual cost incurred by BHP-IT: see
eg Commonwealth Railways Commissioner v Hodson (1970) 16 FLR 437; see
also 22 Am Jur 2d, "Damages", §607; "Comment Note: Overhead Expense as
Recoverable Element of Damages",
above; Homes By Calkens Inc v Fisher
634 NE 2d 1039 at 1045-1046 (1993).
1069 I accept the evidence (reflected in the 1997 Proposal Approval Form
("PAF") estimate for the labour costs of performing the
amended Head Contract),
that the expenses incurred by BHP-IT in performing that contract included
overhead expenses for which no
allowance was able to be made because of the
predetermined contract price. I would note in passing that it is Mr Hammond's
evidence
that BHP-IT's internal margin for recovery of divisional and corporate
overheads for the 1997-1998 financial year was 29.2%. The
margin to generate
profit was 13.6%.
1070 Specific submissions were not made initially by any of the parties (a) on
whether or not the separate claim for contribution
for overheads could properly
be made in its own right and (b) on whether or not the claim made is
justifiable in its own terms.
And it has not been separately quantified.
Again in response to questions asked of the parties, BHP-IT later accepted the
propositions
(i) that, on the evidence, BHP-IT has been shown to have separate
divisional overhead rates for each of its three divisions and a
common
corporate overhead rate, the former being subject to periodic review and (ii)
that this evidence should be regarded as reasonable
evidence of what its actual
overhead costs were in its contracting activities. BHP-IT then contended that
its own rates provided
sensible and appropriate basis for proving its overhead
costs in any event.
1071 I would have to say that the claim for overheads brings into sharp focus
the difficulties with the evidence advanced by BHP-IT
in support of its damages
claim generally.
1072 The 1999 rework of the 1997 PAF (that was prepared internally by BHP-IT
under the shadow of this litigation) purported to give
prices that reflected
labour costs, risk allowances, and BHP-IT's internal margin for divisional and
corporate overheads and for
profit. The margin was not disaggregated. For
most items to which it was applied it was in the order of 32.9% (approx) and
produced
an overall contribution of $4,289,084 in a total estimated price of
$14, 475,943.
1073 I have held BHP-IT has not proved its loss of profit and, accordingly, the
total estimate must be abated to reflect this. Furthermore,
the amended Head
Contract that BHP-IT proceeded to perform contained work that GEC Marconi never
undertook to perform (eg the ER3
software for the message switch). It cannot
be required to compensate BHP-IT for losses (if any) on the performance of such
work.
The cost of that work also has not been disaggregated in the claim made.
There is, though, no evidence to suggest it was loss making.
1074 I agree with GEC Marconi's submission that the 1997 reworked PAF is a
document to be treated with considerable circumspection.
But in the
circumstances it does not avail BHP-IT in any event in its claim for actual
costs, whether by way of overheads or otherwise.
1075 I have already found that the ADCNET project had, for practical purposes,
been abandoned after the September 2000 Suspension
Agreement. At that time on
BHP-IT's own case, it has incurred performance costs of $5,136,122 but retained
payments from the Commonwealth
of $6,609,966. Those figures are based on a
financial status report prepared by Mr Rentz which is in evidence. They
resulted
in a net benefit to BHP-IT of $1,469,844. I would note in passing
that the figures contain performance costs that were referable
to, and payments
on account of, CR007 (the Expedited Release 3 ("ER3") amendment). ER3
represented different work agreed to by BHP-IT
after the termination of the
Sub-Contract. The CR007 amendment was designed to secure to BHP-IT an actual
contribution (overheads
and profit) of $276,601 on a contract price of
$853,891. As I indicate below, it is probably the case that the sum of
$1,469,844
contains all or some part of that contribution which BHP-IT would be
entitled to retain without bringing it into account for the
purposes of this
claim.
1076 It is Mr Rentz's evidence that, because the amended Head Contract had to
be performed at the original contract price no provision
could be made for
contribution given his cost estimates to perform at that price. It is likewise
his evidence that his September
2000 figure for the actual costs of performance
to date was based on records of project costs for labour and materials. In
consequence
that cost figure did not include any contribution for corporate and
divisional overheads.
1077 Mr Hammond's evidence is that not all of the categories of cost referred
to both in Mr Rentz's financial status report and in
the 1997 reworked PAF
would have had a margin for contribution applied to them. Applying Mr
Hammond's exclusions to costs listed
in the financial status report would lead
to the result that actual costs in the order of $700,000 would not have been
expected to
make any contribution to overheads.
1078 The principal evidence on contribution to overheads was given by Mr
Hammond. He accepted that the 49 per cent margin that was
at the relevant time
applied to base contract prices was applied prospectively as a matter of
budgeting by BHP-IT. What he had done
in his calculations for the purposes of
BHP-IT's loss claims was simply to apply that figure retrospectively to actual
costs incurred.
He further accepted that in applying a percentage figure to
estimated work there might, depending upon the way expenses or receipts
varied,
be either an under recovery or an over recovery of overheads. He gave the
following evidence that related to the period
which included that of the
Variation Agreement:
"Q. Have you gone back to any financial period after December 1996 to determine for yourself what actually happened in relation to the recoupment of corporate and divisional overheads?
A. No, I haven't.
Q. And you can't, therefore, tell his Honour, do I understand, that contributions from projects other than the ADCNET project did or did not fully recoup to BHP-IT its overhead and divisional expenses?
A. No, I cannot.
Q. You have just relied, have you, on the fact that there was an estimate which was produced [ie in 1997] and if events turned out as the estimate projected, there would have been an insufficient recovery?
A. That's correct."
1079 The actual rates applied to overheads in BHP-IT at the relevant period
were 29.2 per cent (being 22 per cent for corporate overheads
and 7.2 per cent
for divisional overheads). These figures were apparently the products, first,
of a review of the company's internal
margin conducted in the months prior to
December 1997 and, then, of a revision in the 1997-1998 financial year which
effected an
almost 5 per cent reduction in the percentage for divisional
overheads.
1080 As is apparent from the cross-examination of Mr Hammond, BHP-IT has not
sought to adduce evidence of its actual overhead costs
in the period December
1997-September 2000 that were attributable to performance of the amended Head
Contract and which were as such
an actual cost incurred in that performance.
For my own part, I do not consider a failure to do so as being fatal to
BHP-IT's claim.
1081 Notwithstanding that, from year to year, there may in fact have been
variously an over-recovery or an under-recovery of the
overhead costs for the
company as a whole from its various projects, the methodology BHP-IT applied to
secure its overheads, the
allocation made across projects and the reviews of
these made its overhead margins a reasonable and proper basis for estimating
the
likely overhead costs attributable to work performed by it on a particular
project: McCarty Corp v Industrial Scaffolding Inc 413 So 2d 1322 at
1324 (1981). For this reason, though it represents a form of generalised
estimation of cost: cf the description
of the loss in the Nauru Local
Government Council case, above, at 473 (point viii); I am prepared to
accept it as an appropriate substitute for the necessarily burdensome and in
any
event quite inexact proof BHP-IT would otherwise have had to bear of
establishing its actual loss on account of overhead contribution
foregone on
this one of its projects in circumstances such as the present: see generally
"Comment Note: Overhead Expense as Recoverable
Element of Damages" 3 ALR 3d
689 (US). It is clear on the evidence that it rendered performance for that
period on the basis of
a costing that made no contribution to overheads and its
actual cost figure as at September 2000 likewise took no account of overhead
costs. It was appropriate for BHP-IT in the circumstances to rely upon the
margin rates it had set for the recoupment of overheads
as providing a
reasonable basis on which to estimate the likely cost. There was a reasonable
certainty that such costs were incurred
and I am satisfied in light of BHP-IT's
own review and revision of its margin percentages that the overheads margin
represented the
best reasonably available basis for calculating what those
overheads were likely to have been.
1082 Bearing in mind, though, that not all estimated or actual costs were
expected to or did produce a return by way of contribution
to overheads, the
figure for actual costs incurred to September 2002 does not itself provide a
reliable base figure to which to apply
the overheads percentage. I would
reduce that sum by a figure of $700,000 representing costs which, in light of
Mr Hammond's evidence,
were not expected to be return producing. Applying the
29.2 per cent figure to the actual cost figure so reduced produces a figure
for
overhead costs of roughly $1,300,000. I do not consider this to be an unlikely
sum in the circumstances and find, in consequence,
that there was a reasonable
likelihood of a loss in that amount having been suffered by BHP-IT.
1083 BHP-IT has, though, received payments from the Commonwealth amounts
producing a net benefit to it of $1,469,844. It has, in
consequence, been
fully recouped for such overhead expenses as I consider it was likely to have
incurred and it still retains a net
balance of about $170,000. I am not
satisfied, though, that that net balance should be brought into account by
BHP-IT as profit
made on performance of the Head Contract.
1084 Once ER7 was agreed in September 1998 the entire BHP-IT team was, on Mr
Rentz's evidence, then devoted to work on ER3 tasks
which continued until
mid-1999. In February 1999 BHP-IT received a milestone payment of $1,500,000
(for Milestone 3000A). It received
a further milestone payment in September
1999 of $2,009,769 (Milestone 3000B) of which $509,769 was attributable to ER3.
The projected
profit component of the contribution charged in the ER3 contract
was over $100,000. With earned value by September 2000 being significantly
ahead of actual cost, I am prepared to infer that a sum somewhere near the
$170,000 net balance figure I referred to above was likely
to represent return
by way of profit on the ER3 component of the Head Contract.
1085 In the event then I conclude that BHP-IT recouped from the Commonwealth
under the amended Head Contract all of the costs it
would otherwise have been
able to claim against GEC Marconi. I also conclude that it made no actual
profit up to September 2000
in its performance of that contract for which it
would have to account in relation to its claim for profits lost when it lost
the
benefit of the Head Contract.
1086 By a somewhat more circuitous route than that relied upon by GEC Marconi
and the Commonwealth, I have arrived at the same conclusion
for which they each
contended. BHP-IT has not proved it suffered any compensable loss in
performing the amended Head Contract.
8 PROJECT COSTS INCURRED FROM JANUARY-MAY 1997
1087 The sum claimed here for work done on the project after GEC Marconi's
repudiation is $246,607, this sum being made up of costs
of $174,902 which were
charged to project codes during the relevant period and $71,705 representing
the internal margin of 49% applied
to the labour component of the costs
incurred (ie $146,337).
1088 The costs are said to have been incurred in the early stages of the
process of preparing for BHP-IT's own actual performance
of the Head Contract.
BHP-IT claims that they represent a loss that was the immediate consequence of
BHP-IT and the Commonwealth
agreeing to complete the ADCNET development
following GEC Marconi's repudiation of the Sub-Contract. It was not a loss
that was
too remote.
1089 For similar reasons to those given above in relation to losses incurred in
performing the Variation Agreement, I am satisfied
that BHP-IT suffered both
the loss represented by the sum of $174,902 and some loss by way of overheads.
No attempt has been made
separately to quantify those costs, BHP-IT relying
instead on the internal margin figure of 49% which includes a component not
only
for overheads but also for profit, the sum so claimed (limited to labour
costs) being $71,705. Again for the reasons I gave above,
BHP-IT is not
entitled to include a claim for a loss of profit as a head of damages in this
manner. I am prepared, though, to award
a sum at the overhead margin rate of
29.2 per cent. This results in a figure in the order of $42,500. Damages will
be ordered in
this sum in addition to the sum of $174,902 giving a total for
this head of $217,402.
9 DISPUTE MANAGEMENT COSTS
1090 This claim is for costs and expenses incurred by BHP-IT between June 1996
and 24 December 1997 (the date of the Variation Agreement)
in managing and
attempting to resolve the dispute in relation to the Sub-Contract and the Head
Contract which had arisen in consequence
of GEC Marconi's refusing to complete
the ADCNET software. There are said to be two phases to the dispute. The
first ran from June
1996 until 10 December 1996 (when GEC Marconi repudiated
the Sub-Contract) and involved all three parties. The second phase ran
thereafter until the execution of the variation agreement and related to the
resolution of ongoing issues between the Commonwealth
and BHP-IT concerning the
performance of the Head Contract.
1091 It is BHP-IT's evidence that a separate ADCNET charge code (entitled
"Contractual") was established to track the costs associated
with the dispute
with GEC Marconi; that only senior members of the project team charged their
time to this code; and that the total
costs recorded by this code were
$1,132,396. This figure was made up of labour costs of $573,625, expenses of
$277,625 and overheads
and standard margin on labour costs of $281,099. I
simply note in passing that some part of these costs and expenses on Mr
Hammond's
evidence, are referable to the period 24 December 1997 - May 1998.
That period post-dates the dispute.
1092 It is Mr Hammond's evidence that but for the dispute, BHP-IT would have
been in a position to apply the labour resources it
did in incurring these
costs to other profit generating activities for the company. Cross-examined on
this assertion, the following
evidence was given:
"Q. Are you aware of any work which was offered to BHP that it wished to do from late 1996 to 1997 that it was unable to do?
A. I'm not aware of any specific examples.
...
Q. Do I understand that so far as you are aware all those jobs BHP were offered in which it thought it commercially appropriate to undertake it completed and earned whatever profit was available to be earned?
A. Well, what I mean by "commercially" is where it made commercial sense, obviously, to the extent that we had the capability, the skills and the resources available to us to apply and the particular task or the job made commercial sense, then I would see no reason why we would not proceed with it.
Q. But let me be plainer about it, You are not suggesting, are you, that you are actually aware of any instance in late 1996 or 1997 where BHP was offered some work which was commercially attractive and it said to the person offering the work, "Very sorry, we can't do it. We have got some people tied up in dispute management"?
A. No, I am not aware of any specific situation.
...
Q. As I understand what you are telling his Honour, and please correct me if I misunderstand the opinion that you are advancing, you say that the persons who were associated with ADCNET working on dispute management might have been allocated to some other jobs which BHP-IT then had on the books?
A. That's correct. There would have been a probability of that.
Q. That's not a matter that you have investigated?
A. No."
He accepted he had no knowledge of additional persons being contracted to do
work because BHP-IT personnel had been diverted to dispute
management.
1093 A significant proportion of the sums claimed by way of expenses incurred
related to legal expenses. No evidence was given of
the nature of the legal
work performed nor of the extent to which it related in an anticipatory way to
this proceeding.
1094 GEC Marconi challenges this claim on two broad grounds. The first relates
to the sums charged to the charge code. It contends
that the nature of, and
actual reason for, these charges are not explained. The second ground of
challenge is that BHP-IT has not
led any evidence to suggest that the persons
charging time to this charge code would otherwise have been engaged in profit
or income
generating activities were it not for the dispute with GEC
Marconi.
1095 In my own view, it must be accepted (though the case law is slender
indeed) that management expenses incurred in dealing with
or remedying problems
created by tortious conduct: eg Tate & Lyle Food and Distribution Ltd v
Greater London Council [1982] 1 WLR 149 at 152; Nauru Local Government
Council v New Zealand Seamen's Industrial Union of Workers [1986] 1 NZLR
466; or by a breach of contract: Christmas Island Resort Pty Ltd v
Geraldton Building Co Pty Ltd (No 4) 277; Keating on Building
Contracts, 8-38 (7th ed); can be recovered in a damages award.
As was said in the Tate & Lyle case (at 152):
"the expenditure of managerial time in remedying an actionable wrong done to a trading concern can properly form the subject matter of a head of special damage."
1096 In the very few instances of which I am aware in which claims for such
expenses have been made, the principal difficulties encountered
had been ones
of causation and of proof of the loss actually suffered: see eg Tate &
Lyle, above; Christmas Island Resort Pty Ltd, above. In the
Nauru Council case in a tort claim against a maritime union for inducing
a breach of contract which resulted in a ship not being able to be used
for
over 100 days, and in which management time was expended in dealing with the
resultant problems created (especially in relation
to the release of the ship),
the proof problem appears to have been overcome by the award of general damages
that represented a proportionate
part of the administration and general
overhead expenses referable to the vessel and for the period: see [1986] 1
NZLR 466 at 472
(ll 15-20), 473 (viii), 477 (ll 35-38).
1097 In the present matter, I am satisfied that BHP-IT incurred management
costs and expenses in consequence of GEC Marconi's repudiation
of the
Sub-Contract. For accounting purposes BHP-IT created a charge code for costs
it contends were referable to its dispute with
GEC Marconi. The costs recorded
against the charge code are advanced as representing its loss.
1098 The difficulty I have with this is that while BHP-IT may, for its own
book-keeping purposes, have been able so to assign a cost to its
management of the GEC Marconi dispute and its aftermath it has not by so doing
proved that it has thereby suffered an actual
loss. To the extent that
Mr Hammond's evidence has been relied upon to provide the nexus between cost
incurred and loss suffered, it
has been unavailing.
1099 Despite objection, I admitted Mr Hammond's evidence that the labour
resources committed to dispute management would otherwise
have been able to be
deployed in other profit generating activities of the company. I am satisfied
that this amounted to no more
than a speculative assertion on his part, as his
cross-examination revealed. He was not a witness who could give the evidence
needed
to translate these costs into a recoverable loss.
1100 There is no evidence to suggest that BHP-IT would not still have employed
the persons whose labour costs were charged to the
relevant code over the
period in question. There is no evidence that "other remunerative work would
have been undertaken by any
one of the persons concerned if they had been free
to undertake such work, nor what remuneration would have been derived ... as a
consequence of then having undertaken that work": Christmas Island Resort
Pty Ltd v Geraldton Building Co Pty Ltd (No 4) (1995) 16 WAR 277 at 280.
There is no evidence indicating (a) disturbance to the trading activities of
BHP-IT cf Tate & Lyle, at 152; (b) consequential effects on the
performance of other contracts; or (c) any need otherwise to engage staff
because of
the use of personnel on dispute management. This is not a matter in
which a loss is to be, or can be, presumed.
1101 Likewise, in relation to the costs and expenses claimed, I am not prepared
to infer, without explanation of their actual character
and purpose, that those
costs and expenses properly can be characterised as a loss flowing from GEC
Marconi's breach of the Sub-Contract.
I make this comment in particular of the
costs said to be referable to "legal expenses". These costs are not said to
have been
incurred on account of possible proceedings by the Commonwealth
against BHP-IT in consequence of GEC Marconi's repudiation. Such
costs,
arguably, would be recoverable (subject to considerations of remoteness): cf
Hammond v Bussey (1888) 20 QBD 79; McGregor on Damages, paras
768-772 (16th ed). No evidence has been given of the reason these
costs were incurred, the nature of the legal work performed, the connection
between that work and GEC Marconi's repudiation or the possible extent to which
it was done in anticipation of this proceeding.
1102 In my view, given the particular nature of this particular head of damage,
I consider the creation of the separate charge code
is only the first step in
proof of the loss claimed. Given the basis on which BHP-IT has advanced this
claim, and the manner in
which it has calculated its "loss", there is no
foundation for an award of damages under this head: cf Tate & Lyle,
at 152.
10 MONEYS OWING FOR PERSONNEL PROVIDED
1103 This is a claim for $489,684 by way of charges for the services of BHP-IT
personnel provided to GEC Marconi under the Sub-Contract.
(a) Background Setting
1104 In accordance with cl 19A.1 of the Sub-Contract and cl 9.1 of
Schedule 6, BHP-IT provided GEC Marconi with certain
members of its own staff
to undertake work pursuant to the Sub-Contract. These persons were described
in the Sub-Contract as "Customer's
Specified Personnel". Table 6.2 of Schedule
6 specified the period for which each such person was to be provided to GEC
Marconi.
1105 Clause 12.1 of Schedule 6 stipulated, in part, that:
"Where it is necessary for the Customer's personnel to work outside normal hours at the Contractor's request or in the case of the Customer's Specified Personnel for a period greater than that specified in Table 6.2, the Customer shall be entitled to charge the Contractor for such services. For those personnel specified in Table 6.2 the charges shall be in accordance with the time and materials rate specified in Table 6.2. Such charges would be deducted from the next invoice payable by the Customer and be substantiated by details on the personnel undertaking the work and the hours worked."
1106 The documentary evidence relating to this matter commenced on 13 February 1996. Mr Brent had sometime previously turned his mind to the question of CSI personnel and the length of time they had worked for GEC Marconi. His letter to Mr Wishart of that date enclosed spreadsheets which he said indicated that most BHP-IT personnel had worked in excess of the contracted commitment. It went on:
"Days worked in excess of the contracted number of days are chargeable at the rates defined in schedule 6. Accordingly, I would appreciate it if you would:
- check the enclosed spreadsheet and advise me of any perceived discrepancies;
- indicate whether you require any of the BHP IT personnel to continue working on the EASAMS team;
- confirm the amounts owing to BHP IT at the contracted rates stated in schedule 6."
1107 Mr Goldsmith replied to this on 11 March 1996. He indicated that a number of errors had been found in the hours claimed for BHP-IT staff. He then contended that every time a contract extension had been approved, it was reasonable to expect that the hours to be provided under the contract by BHP-IT staff should have been extended at no cost to GEC Marconi. The letter concluded with the following:
"In the meantime, EASAMS considers that since a number of the BHPIT staff engaged on the IPD project are occupying key positions, BHPIT should not change their assignments in order to minimise the impact of the changes currently under negotiation."
1108 On 14 March Mr Brent replied rejecting outright the contention that contract amendments had the effect of amending the number of contracted days for customer personnel. The letter continued:
"Any hours in excess of the contracted obligation are chargeable to EASAMS at rates specified in the contract at schedule 9 table 6.2. Services have been rendered, payment is now due.
The final paragraph of Reference B states that BHP IT should not change the assignments of its staff on the EASAMS IPD team in view of possible impact on the ADCNET project. Continuing deployment of BHP IT staff on the EASAMS team depends on EASAMS ability to pay for services rendered in excess of the contracted number of days.
In the context I require thirty days notice to discontinue the deployment of BHP IT staff on the EASAMS IPD team, should you decide that the services of BHP IT staff are no longer required."
1109 On 22 March 1996 BHP-IT invoiced GEC Marconi in the sum of $157,036.81
an account of excess time worked for the period 25 August
1994 to 11 February
1996. I note in passing this period predates the commencement of the
sequence of correspondence to which I am referring.
1110 Mr Goldsmith replied on 26 March 1996 to Mr Brent's letters of 14 ("Ref
A") and 22 March ("Ref B"). That letter stated:
"In response to reference `A', EASAMS has reviewed the Contract requirements for the supply of Customer Personnel and confirms your findings that specific customer personnel, some by name, are required to be provided for varying specified periods. I also note the provisions regarding any shortfall by the Customer in the supply for such personnel.
Other than these obligations, the Customer has no requirement to provide additional personnel or personnel for extended periods and the Contractor has no right to expect such provision.
Further, I am unable to locate any request under the Contract by EASAMS for the provision by BHP IT of additional Customer Personnel services and the conditions of such supply. It is reasonable to expect that failing such a request BHP IT would withdraw its Customer Personnel once its obligations under the Contract were complete unless it was to BHP IT's benefit to continue such provision absent any agreement as to compensation, if any, by EASAMS.
In view of the above and the concerns expressed in Reference `A', please insure EASAMS is given reasonable notice of BHP IT's intention to withdraw Customer personnel where the Contract requirements have been met, so that EASAMS can make suitable alternative arrangements without further jeopardising the Project schedule.
Further, the invoice submitted under cover of Reference `B' is inappropriate and is therefore rejected."
1111 A letter of 16 April from Mr Sharp to Mr Haddad linked customer personnel to the non-provision of STUBS. The letter stated in part:
"The purpose of this letter is to inform you that "Customers Personnel", both specified and non-specified, are largely unable to undertake work in respect of this contract in accordance with the contract, the fundamental reason being that by reason of the breaches by BHP IT in not supplying Stubs, EASAMS is unable to properly advance the contract.
EASAMS is aware of its obligations to take reasonable steps to minimise damage flowing by reason of the breaches of contract by BHP IT.
Accordingly we hereby give, so far as it is relevant and/or needed, our consent for Customers Personnel, both specified and non-specified, to be absent from undertaking work in respect of this contract - refer Clause 19A.4 of the agreement.
Would you please contact me upon receipt of this letter to discuss suitable arrangements for the redeployment of Customers Personnel from this Contract."
The letter went on to dispute BHP-IT's entitlement to charge for the
provision of services by customer personnel. It relied both
on alleged delays
caused by BHP-IT and on the lack of a request from GEC Marconi. It also
pointed out that Mr Brent's "30 day notice"
requirement had no foundation in
the contract.
1112 On 30 May Mr Brent wrote to his superior in BHP-IT, Mr Higginbotham. That
letter was in the following terms:
"I have indicated in previous correspondence that BHP IT are incurring costs through continued deployment of BHP IT personnel on the project.
Our contractual obligation vis-à-vis EASAMS in this respect is complete and we have been invoicing EASAMS for use of our personnel in excess of the contracted obligation. This is specifically provided for under schedule 6 of our contract with EASAMS.
EASAMS are disputing liability for these costs although they have indicated that their preference would be if we continued to deploy our personnel on the project.
In the current circumstances withdrawal of our personnel at this juncture would seriously impact the viability of the project now and in the future.
Further representations by Margaret Beattie have elicited the request from EASAMS to remove our personnel and DFAT personnel from the project.
In my view we need to continue to deploy our people on the project in the short term as an "insurance policy" but we cannot do it indefinitely. Hence the reason for my concern that we resolve the matter more quickly.
Where possible I will re-deploy personnel to other projects in consultation with Andy Weatherhead.
If you have any concerns regarding this issue, please let me know.": Emphasis added.
1113 Between March and November 1996 BHP-IT issued eight invoices for
charges for customer's personnel. The total sum ultimately
claimed, but not
paid, was $489,684.
1114 Mr Brent's evidence in cross-examination was to the effect that (i) he did
not turn his attention to charging for customer personnel
until early 1996;
(ii) there had not to his knowledge been any actual request by GEC Marconi that
the CSI personnel stay beyond their
nominated periods, but he thought he
implied a request from their continuing to work beyond the stipulated period,
and he did not
ask about a request; (iii) he accepted that by March 1996 there
was a problem with timely performance of the contract and that if
staff were
taken away that problem might become a greater difficulty; (iv) if GEC Marconi
said that the customer personnel were
to be taken away he would cease to be
entitled to raise invoices; (v) he accepted that by April 1996 he appreciated
it would have
been quite inappropriate to raise further invoices for CSI
personnel and he added "we probably should have withdrawn our people and
we
didn't"; (vi) by the time of his letter to Mr Higginbotham he had decided to
let people remain with GEC Marconi; (vii) he continued
to render invoices
because "[o]ur people were delivering work value to the EASAMS team ... and,
therefore, in the sense of services
having been rendered and accepted, I felt
that invoicing was a reasonable thing to do"; and (viii) he acknowledged that
by mid-1996
there was no longer any implied request to extend CSI personnel.
(b) Submissions and Conclusions
1115 BHP-IT's claim for the entirety of the sums invoiced is based upon GEC
Marconi's letter of 11 March in which Mr Goldsmith stated
that while delay
claim negotiations were outstanding BHP-IT should not change the assignment of
its staff as they "are occupying
key positions". It goes on to assert that at
no time subsequently did GEC Marconi indicate it wanted those "key members"
removed
and, on the contrary, GEC Marconi continued to utilise these staff.
1116 GEC Marconi's contention is that BHP-IT has simply not proved that its
personnel worked for an extended period at GEC Marconi's
request nor has it
proved that its personnel in fact worked outside the contracted period.
1117 BHP-IT's claim as pleaded is founded directly upon the provisions of the
Sub-Contract and, in particular, upon cl 12.1
of Schedule 6. I emphasise
this for the following reasons. It has not been suggested that the parties by
their conduct had effected
a variation to the Sub-Contract and to Schedule 6 to
remove any of the stipulated requirements relating to extending the time and/or
charging for CSI personnel. It has not been suggested that BHP-IT can rely
upon an estoppel to prevent GEC Marconi insisting on
its strict legal rights.
And it has not been suggested that BHP-IT's claim could be brought in some
fashion on restitutionary grounds.
1118 For my own part, I am satisfied that BHP-IT has not made out its claim for
payment. My reasons for this conclusion are as follows.
1119 It is reasonable to infer that at the time Mr Brent first turned his mind
in early February 1996 to charging for CSI personnel,
neither party had given
explicit consideration to how the Sub-Contract regulated this dimension of what
they had been doing. It
is equally reasonable to infer that as, first, Mr
Brent and, then, Mr Goldsmith awakened to the possible contractual implications
of what they had been doing in relation to customer personnel, their respective
appreciations of what the Sub-Contract and Schedule
G in fact required were
slow in coming.
1120 Mr Brent's 11 February letter appears to have proceeded on the premise
that days worked in excess of the contractual commitment
were chargeable as of
right. The same view was reiterated in his 14 March letter. Mr Goldsmith
seems only to have turned his mind
to the contractual requirements in mid-March
and, in light of that he raised the issue of there being no request to provide
additional
customer personnel services.
1121 Mr Brent acknowledged that no actual request for the provision of customer
personnel services had ever been made. He did say,
though, that he thought he
implied a request from the fact that BHP-IT's continued working beyond their
specified periods. Consistent
with the view I have taken of Mr Brent's oral
evidence, I do not consider it would be safe to rely upon this recollection as
representing
any view he entertained at the time. His conduct was, in my view,
consistent with the view he accepted he later entertained when
continuing to
invoice GEC Marconi ie if the work was done and accepted it should be paid for.
And he accepted in any event that by
mid-1996 there was no longer any implied
request.
1122 Once the need for a request was squarely raised by Mr Goldsmith in his 26
March letter - and it was reiterated subsequently
by Mr Sharp in his 16 April
letter - any possible basis for a claim thereafter based on cl 12.1 of
Schedule 6 evaporated (if
it had existed at all previously). Mr Goldsmith's 26
March letter acknowledged that BHP-IT might consider it to be to its benefit
to
continue to provide personnel without compensation from GEC Marconi, otherwise
it was reasonable to expect BHP-IT to withdraw
its personnel. BHP-IT's conduct
thereafter was consistent with its acting on the assumption that it was in its
interests not to
withdraw its personnel - as witness the emphasised statements
in the 30 May letter to Mr Higginbotham, above. In the face of the
stand being
taken by GEC Marconi, it continued to provide services at its own risk. It had
no automatic entitlement to be compensated
for the services it chose to
continue to render. There had been no contract variation dispensing with the
request requirement and
no submission has been made to the contrary.
1123 BHP-IT has sought to circumvent this conclusion by relying upon Mr
Goldsmith's first (ie 11 March) reply to Mr Brent in the
sequence of
correspondence I have set out above. In that letter, having attempted to link
the CSI personnel issue to contract extensions
(including from delay claims),
Mr Goldsmith made the observation which I here repeat:
"EASAMS cannot confirm the amounts owing to BHPIT or the hours still due to EASAMS from BHPIT until all claims for delay have been resolved.
In the meantime, EASAMS considers that since a number of the BHPIT staff engaged on the IPD project are occupying key positions, BHPIT should not change their assignments in order to minimise the impact of the changes currently under negotiation": emphasis added.
1124 This letter may properly be able to be interpreted as embodying a
request to continue to supply personnel (whether or not this
would involve an
extension of time) because of the delay claim negotiations. The difficulty
BHP-IT has in relying upon such a request
is that it rejected outright the
premise of it (ie the link to the delay claims). And, in its 14 March letter,
it adhered to the
view Mr Brent had espoused in his 11 February letter: excess
hours were chargeable to GEC Marconi and, as the services had been
rendered,
payment was due.
1125 There is, in my view, no evidentiary foundation at all for the claim
pleaded and prosecuted by BHP-IT. I agree entirely with
GEC Marconi's
submission in this regard. I express no view on whether a differently framed
claim may have fared better.
11 LOSS OF USE OF MONEYS
1126 This claim is a variant on that mandated by Hungerfords v Walker [1989] HCA 8;
(1989) 171 CLR 125; see also Bank of America Canada v Clarica Trust Co
(2002) 211 DLR (4th) 385; Jacobs, Damages in a Commercial
Context, Ch 16. Put shortly, BHP-IT claims $2,457,413.83 as the cost to it
of being deprived of money either withheld from it by GEC Marconi
in breach of
contract or paid away by it in consequence of GEC Marconi's breach. The cost
claimed was based on BHP's "Weighted Average
Cost of Capital" ("WACC"), being a
varying percentage which the parent company, BHP, required each dollar of
capital deployed by
it or its subsidiaries (including BHP-IT) to return and
which represented what was said to be the cost of capital to BHP. The WACC
varied between 12.5% and 9% over the period of this claim.
1127 The breakdown of the WACC claim and the "losses" in respect of which the
claims are made can be represented in tabular form
as follows:
1. Lost Benefit of the Sub-Contract ($3,391,309) |
WACC |
$1,537,912.58 |
2. Cost Jan 1997-May 1997 ($246,607) |
WACC |
$111,832,93 |
3. Dispute Management Costs ($1,132,396) |
WACC |
$513,526.21 |
4. Labour Services invoiced ($489,684) |
WACC |
$265,239.86 |
5. T & M Services ($45,503) |
WACC |
$28,902.24 |
Total: |
$2,457,413.83 |
1128
As I understand it, the claim as finally put is that, if BHP-IT were to have
invested the moneys so expended by it or withheld
from it, it would have been
by way of intercompany loan to its parent BHP at the intercompany rate of
interest.
1129 There is a short answer to almost all of the claim. Save in relation to
the second of the above categories, the losses upon
which the WACC has been
claimed are simply not losses I have found were sustained by BHP-IT. I would
note, though, that the loss
referred to in the fifth category above ("T & M
Services") relates in fact to a claim by BHP-IT that has been accepted by the
Commonwealth for non-payment for work performed. I would also note that the
first category of loss could be recast in a different
sum to represent the loss
I have found flowed from the lost benefit of the original Head Contract.
1130 The basic difficulty with the claim, to the extent that it can be related
to losses actually sustained, lies in the way in which
it is advanced. The
particular loss claimed is, in my view, a contrived one which, moreover, is
measured in substance by its impact,
not on BHP-IT, but upon its parent,
BHP.
1131 Mr Hammond of BHP-IT gave the evidence upon which this claim is based. In
his witness statement he described the WACC and its
purpose in the following
way:
"BHP sources its capital from two (2) sources, equity and debt providers. Both providers require a return for the provision of such capital and the risk taken. The delivery of these returns by BHP's businesses to the equity and debt providers is the "cost of capital" to BHP. The level of equity used by BHP relative to the level of debt (usually referred to as gearing) will determine the weighted average cost of capital ("WACC"). By "equity used" I mean shareholders funds as reported in the Balance Sheet of BHP. BHP requires that each dollar of capital deployed must return the cost of that capital as an absolute minimum.
The rate of the weighted average cost of capital was determined by BHP annually. This rate was then published to BHP and all of its subsidiaries including BHP-IT."
1132 In cross-examination he accepted that (i) the cost of equity was not an
actual cost to a company other than in terms of "the
longevity of the company"
and it was not a figure recorded in BHP-IT's accounts; (ii) he looked at the
WACC from the perspective
of BHP and had not done any calculation of the WACC
of BHP-IT; and (iii) when it was suggested that the WACC figure had nothing
at
all to do with any cost which was in fact incurred by BHP-IT, he replied that
"[t]he way I've presented this is really the impact
on BHP".
1133 In cross-examination he explained the circumstances in which "in the
ordinary course of [his] professional life" he would customarily
use the WACC.
He said:
"A. The weighted average cost of capital is something that would be used in the company to evaluate investments, capital expenditure programs, et cetera, and, indeed, would also be a benchmark figure for key performance criteria for the businesses in terms of their own returns and ensuring that the businesses financial performance were sufficient to recover the corporations cost of capital."
1134 Importantly, he indicated that BHP ran a central treasury. Whenever
BHP-IT had cash reserves these were automatically transferred
to BHP accounts
by way of intercompany loan at the prevailing intercompany rate. It was the
central treasury that effected borrowings
in the market. BHP-IT did not have
any debt funding arrangements in place. He also suggested that, if BHP-IT had
the use of the
moneys it claims as losses, it would have had that use prior to
BHP-IT's sale in 2000 and so it "lost the opportunity of being able
to reinvest
that in other BHP-IT projects".
1135 GEC Marconi has submitted that the WACC cannot be regarded as a comparable
loss to BHP-IT whatever its significance may have
been for BHP. I agree with
this submission. The WACC was imposed on the BHP group for the apparent
benefit of BHP. It does not
reflect the weighted average cost of capital to
BHP-IT. The evidence is that, if BHP-IT had cash reserves, these passed
automatically
to central treasury, BHP-IT having, it would seem, no discretion
in the matter. This "investment" was recorded as a loan at the
inter-company
loan rate. I put to one side, for the moment, the issue whether that rate was
the WACC rate. The point to be made
is that I do not consider that BHP-IT has
suffered an opportunity cost on its loss of use of moneys in the Hungerford
sense. BHP has imposed its desiderata on BHP-IT as to the return it should
make on its monies. I do not accept that a failure to
earn that return can be
said as of course to reflect a loss at that rate by BHP-IT. Vis-à-vis
BHP-IT the WACC rate is an
artificial figure. The matter is not advanced by
suggesting that BHP-IT was deprived of the "opportunity to invest in other BHP
projects". The evidence relating to BHP's central treasury system does not
suggest that this was an opportunity of BHP-IT as distinct
from that of BHP.
1136 Finally, I would note that, insofar as I have been invited to infer that
the inter-company interest rate was set at the WACC
rate, I am not prepared to
do so. Mr Hammond's evidence on that rate so far as it went is contained in
the following passage of
cross-examination:
"Q. So if BHP-IT had received this money it would have made a loan to BHP parent company?
A. Correct.
Q. That would have been your decision, would it, or someone else's decision?
A. No, that was an automatic process that was in place within BHP.
Q. So whenever there were cash reserves within BHP-IT, there would be an automatic deposit of those funds into the bank account or bank accounts of the BHP parent?
A. Correct.
Q. Who then paid some interest rate on those funds, presumably?
A. There would have been an intercompany interest rate.
Q. That intercompany interest rate is something which is recorded from time to time on documents which are business records of BHP-IT, is it?
A. Yes, that's correct."
I was not taken to any business record of BHP-IT which betrayed what that
interest rate might be. Even if it was a requirement of
BHP-IT that "each
dollar of capital deployed must return the cost of that capital as an absolute
minimum", and even if the WACC was
"customarily used" in the way Mr Hammond
described (see above), this would not satisfy me that the inference that I am
asked to draw
was the most probable deduction which may reasonably be drawn
from the established facts: Holloway v McFeeters [1956] HCA 25; (1956) 94 CLR 470 at
477.
1137 I reject the claim made under this head. BHP-IT has, though, foreshadowed
an application for statutory interest up to judgment
under s 51A of the
Federal Court of Australia Act 1976 (Cth).
12 THIRD PARTY LIABILITY COSTS
1138 This claim is based upon the premise that, to the extent that the
Commonwealth is entitled to recover any damages from BHP-IT
in this proceeding,
BHP-IT's liability will have arisen as a direct consequence of GEC Marconi's
failure to perform the Sub-Contract.
Those damages in consequence are
recoverable from GEC Marconi.
1139 The damages I have found relate as, will be seen, (a) to additional
project management costs incurred and (b) to the Commonwealth's
losses flowing
from the need to relocate BHP-IT's project team to the Edmund Barton Building
and then, until December 1997, the R
G Casey Building. BHP-IT is entitled to
recover these costs from GEC Marconi.
13. THE INDEMNITY CLAIM
1140 The claim for an indemnity under cl 36.1 is advanced for
precautionary reasons. If BHP-IT is found to be liable to the
Commonwealth,
but if not all of the claims brought by the Commonwealth are recoverable in
turn by BHP-IT from GEC Marconi as damages
arising from its breach of contract,
then cl 36.1 is relied upon for indemnification against those
"unrecoverable" claims.
1141 Sub-clause 36.1 provided:
"Subject to the provisions of this Contract the Contractor shall at all times indemnify, hold harmless and defend the Customer and its officers, employees and agents (in this clause 36 referred to as "those indemnified") from and against any loss (including legal costs and expenses) or liability reasonably incurred or suffered by any of those indemnified arising from any claim, suit, demand, action or proceeding by any person against any of those indemnified where such loss or liability was caused by any wilful, unlawful or negligent act or omission of the Contractor, its employees, agents or sub-contractors in connection with this Contract."
By sub-clause 36.1A the customer provided a reciprocal indemnity to the
Contractor.
1142 Put shortly, BHP-IT's claim is that it is entitled to be indemnified
against any liability it had to the Commonwealth. It is
contended that GEC
Marconi's actions in terminating the Sub-Contract were wilful and unlawful
within the terms of cl 36.1 -
"wilful", because it acted intentionally and
deliberately in pursuing the strategy it did; and "unlawful" because those
actions
were engaged in for the purpose or intention of compromising BHP-IT's
position under its contract with the Commonwealth, thereby
forcing BHP-IT to
negotiate an outcome which favoured GEC Marconi by minimising its exposure to
loss under the Sub-Contract.
1143 GEC Marconi both disputes the above factual assertion, but more generally
challenges BHP-IT's construction of the sub-clause.
It contends that the
relevant "act or omission of the Contractor ... in connection with this
Contract" means an act or omission
in the actual performance of work under the
Sub-Contract.
1144 For my own part, I am not satisfied that BHP-IT is entitled to the
indemnity it claims. For present purposes the sub-clause
has two requirements.
The first is that BHP-IT is liable to a third party (here the Commonwealth).
The second is that that liability
was caused by a wilful, unlawful, or
negligent act or omission of GEC Marconi in connection with the Sub-Contract.
I am prepared
to assume that GEC Marconi's conduct (a) in seeking to have the
Head Contract and the Sub-Contract renegotiated and in exerting commercial
pressure to that end and (b) in repudiating the Sub-Contract when that strategy
failed, was conduct engaged in deliberately, intentionally,
purposefully. Its
object was to minimise loss to GEC Marconi from the continuing performance of
the Sub-Contract. Having failed
to secure the desired renegotiation, the
effectuation of GEC Marconi's object required it to terminate the Sub-Contract,
albeit unjustifiably.
Such loss as this occasioned BHP-IT in terms of exposure
to the Commonwealth under the Head Contract was not relevantly a loss caused
by
a wilful act or omission in connection with the contract. It was caused by a
breach of contract and, as I indicate below, I do
not consider that cl 36
was directed at liabilities to the Commonwealth arising in such a fashion.
1145 Similarly, I am not satisfied that, in pursuing the course it did, GEC
Marconi engaged in "unlawful" conduct. BHP-IT has sought
to analogise the use
of the term "unlawful" here to its usage in cases involving interference with
contractual relations by indirect
and "unlawful means": see Davies v Nyland
(1975) 10 SASR 76 at 98; Trindade and Cane, The Law of Torts in
Australia, 215 (3rd ed); Todd (ed), The Law of Torts in New
Zealand, §12.2 (3rd ed). GEC Marconi's attempt to have the
two contracts renegotiated failed without subjecting BHP-IT to any liability to
the Commonwealth.
If it is said to have engaged thereafter in an "unlawful"
action which resulted in BHP-IT's becoming liable to the Commonwealth,
that
action could only be the wrongful termination of the contract. This was not,
in my view, such an unlawful action occasioning
loss to BHP-IT as subclause
36.1 envisaged. It was a wrong to BHP-IT for which the law provided redress in
a contractual action
for damages - and that redress could include damages in
respect of a liability incurred to the Commonwealth by reason of GEC Marconi's
repudiation of the Sub-Contract.
1146 As between BHP-IT and GEC Marconi, subclause 36.1 was not directed at
losses or liabilities incurred under the Head Contract
that could flow from a
repudiation of the Sub-Contract as such or from breaches as such. The ADCNET
contracts were back-to-back
contracts, with defaults in one having, or likely
to have, direct and parallel consequences in the other. If the parties had
wished
to utilise an indemnity procedure to make a loss sustained in one of the
two contracts recoverable from the wrongdoer in the other
whose actions
occasioned the dual defaults, it is to be expected that they would have done so
directly. They did not. I regard
that omission as significant given the range
of provisions governing ceilings, performance guarantees, indemnities (eg cl
28.4) etc,
contained in the contracts which regulated the respective
liabilities of the parties in each of the contracts.
1147 Clause 36.1 is a quite inappropriate vehicle for dealing with losses and
liabilities flowing from the Sub-Contract to the Head
Contract in consequence
of breaches of contract. It is hardly likely that commercial parties, aware of
the interrelationship of
the ADCNET contracts, would have singled out for
indemnification losses etc resulting from breaches of contract occasioned by "a
wilful, unlawful or negligent act or omission", while leaving outside of the
indemnification regime all other (though quite predictable
losses) flowing from
a breach of the Sub-Contract. The sub clause was not designed to, nor is its
language apt to, deal with contractual
disputes between members of the "ADCNET
family" that had their genesis in a breach of the Sub-Contract by "the
Contractor". It would
be to give it an unreasonable and uncommercial
construction to hold that it provides the indemnification BHP-IT seeks. In
consequence
I reject BHP-IT's claim.
1148 As will be seen later in these reasons, my conclusion relates to what is
in reality a hypothetical. As I indicated above the
indemnity claim was a
precautionary one. The need for that precaution has not arisen.
14. THE PERFORMANCE GUARANTEE
1149 Sub-clause 18.2 of the Sub-Contract obliged GEC Marconi to lodge with
BHP-IT a Deed of Guarantee for the performance of its
obligations and the
discharge of its liabilities under the Sub-Contract. The performance guarantee
was provided by GEC Marconi Australia
on 31 October 1994 and was in the form
specified in Schedule 14 of the Sub-Contract. The operative provisions of that
guarantee
for present purposes were that:
"The Guarantor hereby guarantees to the Customer the performance of the obligations undertaken by the Contractor under the Contract on the following terms and conditions:
(1) If the Contractor (unless relieved from the performance of the Contract by the Customer or by statute or by a decision of a tribunal of competent jurisdiction) shall fail to execute and perform its undertakings under the Contract the Guarantor will, if required to do so by the Customer, complete or cause to be completed the undertakings set forth in, and in accordance with the conditions of, the Contract. If the Contractor should commit any breach of its obligations, and such breach is not remedied by the Guarantor pursuant to the foregoing sentence, and the Contract is then terminated for default, the Guarantor shall indemnify the Customer against costs and expenses directly incurred by reason of such default."
1150 The circumstances giving rise to the present claim can be stated shortly by reference to three letters. On 24 December 1996 BHP-IT wrote a letter to GEC Marconi Australia that included the following:
"EASAMS recently served upon BHP IT a notice purporting to terminate the Contract. BHP IT hereby calls on the Guarantee and requires GEC to complete or cause to be completed the undertakings set forth in, and in accordance with the conditions of, the Contract. BHP IT requires your written agreement within twenty-one days to complete or cause to complete these undertakings. If by that date, you have failed to remedy the breaches by EASAMS, then BHP IT will treat EASAMS as being in repudiation of the Contract, and BHP IT will accept such repudiation as terminating the Contract. BHP IT will then call upon the indemnity given by GEC under the Guarantee."
1151 GEC Marconi Australia's reply of 13 January 1997, signed by Mr Sharp in
his capacity as a director of that company, denied there
had been any failure
by GEC Marconi to perform its obligations and asserted that there was no
occasion for BHP-IT to call on the
Guarantee.
1152 On 21 January 1997 BHP-IT responded in a letter the operative part of
which stated:
"The Notice of Termination is wrongful, and constitutes a breach of the Contract and a repudiation in that EASAMS has wrongfully refused to perform its undertakings under the Contract. Consequently the Notice under the Performance Guarantee dated 24 December 1996 is valid. GEC's failure to complete or cause to be completed EASAMS' undertakings provided for in the Contract, is a breach of GEC's obligations under the Performance Guarantee. BHP IT hereby requires GEC to indemnify BHP IT against costs and expenses directly incurred by reason of such defaults, as provided for in the Performance Guarantee."
1153 BHP-IT continues to assert its demand under the Guarantee was valid and
claims the following "costs and expenses [were] incurred"
by reason of GEC
Marconi's repudiation:
(1) costs incurred in performing the Head and Sub-Contracts after Milestone
3000;
(2) costs incurred as a result of the dispute raised by GEC Marconi;
(3) costs incurred in performing the Head Contract in 1997;
(4) any liability owed to the Commonwealth;
(5) the legal costs of this proceeding.
To the extent that these are not recovered from GEC Marconi, it is claimed that
GEC Marconi Australia must indemnify BHP-IT for them.
1154 GEC Marconi Australia defends this claim on two grounds. The first is
that the focus of cl 1 of the performance guarantee is
on an actual breach or
breaches of the Sub-Contract by GEC Marconi; the letter of 24 December was
highly ambiguous and failed to
identify any actual breach; the breach
identified in the 21 January 1997 letter (ie GEC Marconi's serving of the
Notice of Termination)
was itself not a matter capable of being remedied and,
thus, of being the subject of a notice under the performance guarantee; and,
in any event, the time of 21 days given by the 24 December letter was not such
as gave GEC Marconi Australia a reasonable opportunity
to comply.
1155 The second of GEC Marconi's contentions is that the expression "costs and
expenses directly incurred" in cl 1 of the guarantee
should be narrowly
construed. It contrasts with expressions used in other provisions of the
Sub-Contract (eg cl 36.1 "any loss (including
legal costs and expenses")) and
cl 41 ("any damages ... losses, costs and expenses"). And while it extends to
moneys paid and obligations
incurred, it cannot be given an extended meaning to
include loss of profits, fixed overheads, a margin charged on overheads,
damages,
or one's own cost of providing services.
1156 BHP-IT's contention is that GEC Marconi abandoned performance of the
contract when it repudiated it so that there was in consequence
a repudiatory
breach of the contract itself; the letter of 24 December called on GEC
Marconi Australia to perform the obligations
abandoned by GEC Marconi; it
failed to do so; the Sub-Contract was then terminated on acceptance of the
repudiatory breach; and
the indemnity became payable.
1157 In common with other parts of the Sub-Contract, the terms of the Schedule
14 performance guarantees are not a model of clarity.
One need only point to
the apparently random usage made of the terms "obligations" and "undertakings"
to illustrate this. In these
circumstances, and having regard to the "settled
principle governing the interpretation of contracts of guarantee": Chan v
Cresdon Pty Ltd [1989] HCA 63; (1989) 168 CLR 242 at 256; I am obliged to construe
ambiguous contractual provisions in favour of the surety: Ankar Pty Ltd v
National Westminster Finance (Australia) Ltd [1987] HCA 15; (1987) 162 CLR 549 at 561.
1158 It is agreed by the parties, correctly in my view, that the term
"undertakings" is synonymous with "obligations" and that `a
failure to perform'
and a "default" approximate to a breach of contract in this setting: cf
cl 40.2 of the Sub-Contract.
1159 The primary obligation undertaken by GEC Marconi Australia was to
guarantee "the performance of the obligations undertaken by
[GEC Marconi]".
That guarantee though was not unconditional. It was given on "terms and
conditions". First and foremost GEC Marconi
Australia's obligation to perform
arose only if, on GEC Marconi's breach of its obligation(s), it was required by
BHP-IT to complete
or cause to be completed GEC Marconi's contractual
obligations. The important point to be emphasised is that the guarantee did
not
merely require that GEC Marconi Australia remedy the breach or breaches
leading to the call. It required that GEC Marconi Australia
complete the
contractual obligations assumed by GEC Marconi.
1160 The second "term" of the guarantee was that, if GEC Marconi Australia did
not remedy the actual breach or breaches that triggered
BHP-IT's right to
trigger the call, and if BHP-IT then terminated for breach, the obligation
arose to indemnify for costs and expenses
directly incurred by reason of that
breach.
1161 BHP-IT's call took place in a setting in which GEC Marconi had abandoned
the further performance of the Sub-Contract in its
entirety (including
remedying past breaches). Its conduct was clearly repudiatory. Having regard
to the continuing character of
many of its obligations under the Sub-Contract
(see eg cl 4(g) and (j)), that repudiation itself clearly put it in
further breach
of the Sub-Contract. That was sufficient to justify BHP-IT's
call on the guarantee even though GEC Marconi's renunciation of the
contract
involved as well anticipatory breaches that only became legally inevitable on
acceptance of the repudiation: Universal Cargo Carriers Corp v Citati
[1957] 2 QB 401 at 438.
1162 In a setting in which further performance of the Sub-Contract had been
abandoned, it was in my view unnecessary for BHP-IT to
particularise the
individual obligations which had actually been breached by GEC Marconi. Given
that GEC Marconi Australia was being
required to take over and perform the
remainder of the Sub-Contract, and that that performance would require
remedying such breaches
as the repudiation occasioned, it was sufficient for
BHP-IT (a) to call on GEC Marconi Australia to perform the Sub-Contract or to
cause to have it performed and (b) to require it to remedy GEC Marconi's
breaches without further specification. While the lack
of specification might
have some bearing on the reasonableness of the time given to comply with the 24
December letter: cf Bunbury Foods Pty Ltd v National Bank of Australasia
Ltd [1984] HCA 10; (1984) 153 CLR 491 at 503-504; it did not effect the efficacy of the
call on the guarantee itself. GEC Marconi had "fail[ed] to
execute and perform
its undertakings under the Contract". The precondition to a call on the
guarantee had been fulfilled.
1163 I do not consider that the subsequent correspondence between BHP-IT and
GEC Marconi in January 1997 was of any particular significance
in relation to
the validity of the call on the performance guarantee. It merely
reflected well understood positions about the significance of GEC Marconi's
purported termination. Subject to what I say below, I consider that BHP-IT's
21 January letter was effective as a call upon the
indemnity obligation even if
it be the case that the first sentence is a model of inaccuracy. The 24
December letter was, or was
not, valid according to its terms. I have held it
was valid. The 21 January letter, written after the 21 days foreshadowed by
the
earlier letter could have no effect on its efficacy.
1164 The 24 December letter insofar as it related to the indemnity embodied a
requirement that GEC Marconi's breaches be remedied,
and if they were not
BHP-IT would accept GEC Marconi's repudiation as terminating the contract. One
can distinguish between repudiation
and termination for breach: see the
helpful discussion in Byrnes v Jokona Pty Ltd [2002] FCA 41 at [72] ff.
While the language of cl 1 of the performance guarantee appears to have
envisaged termination for breach - and in light
of cl 40.1 and
cl 40.2 that breach may have been quite minor - I do not consider that the
manner in which BHP-IT terminated
the Sub-Contract (ie by acceptance of
repudiation) was such as would deny it the benefit of the indemnity. The
essential matters,
in my view, were that the breaches were not remedied as
required and that the contract was terminated in consequence of GEC Marconi's
conduct in relation to the performance of the Sub-Contract which entailed
actual breaches of the Sub-Contract as well as anticipatory
ones.
1165 I consider that the indemnity part of cl 1 would not have been
intended by reasonable commercial persons in the position
of the parties to
differentiate between types of termination such as would leave BHP-IT in the
position, variously, of being able
to call on the indemnity (if the termination
was for a breach) or of having to sue for breach of the Deed itself (if it was
terminated
for repudiation), after GEC Marconi Australia had failed to agree to
remedy GEC Marconi's breaches. I am satisfied that the reference
to
"terminated for default" would have been intended in this setting to indicate
that, after the guarantor's failure to agree to
remedy breaches, the contract
was in consequence terminated on whatever basis was available to BHP-IT at the
time - be this for default
under cl 40.1, or for breach at common law, or
for repudiation. The significant matters in my view are the failure to agree
to remedy the breaches (which is itself a breach of the performance guarantee)
and the consequent termination of the Sub-Contract
(which made the resultant
cost and expense (if any) of the breaches irreversible by remedial action). It
is these matters together
which gave the indemnity its vitality and reasonable
commercial parties would have recognised this. I am in consequence satisfied
that BHP-IT's termination was one envisaged by cl 1 of the performance
guarantee.
1166 The final matter as to the efficacy of the call itself was whether, in the
circumstances, BHP-IT's letter gave GEC Marconi Australia
"a reasonable
opportunity to comply". It was requiring "written agreement" to perform the
Sub-Contract. Given the relationship
of GEC Marconi Australia and GEC Marconi
and Mr Sharp's role in both, I am satisfied that GEC Marconi was itself well
familiar with
the circumstances leading to the call and the nature of the call
being made. Its 13 January 1997 letter was predictable. GEC Marconi
Australia
was not going to render the performance its subsidiary would not. I am
satisfied that the time given was reasonable for
GEC Marconi Australia to
determine its course of action and to comply with BHP-IT's call if it was so
minded.
1167 The final matter raised by GEC Marconi relates to the scope of the
indemnity. What was encompassed by the expression "costs
and expenses directly
incurred by reason of such default"? GEC Marconi has referred to some number
of cases in which courts have
had to consider the meaning of the terms
"expenses" or "costs and expenses" in particular settings (statutory or
otherwise) in which
they have been used: see eg Parr v Australasian Asiatic
Trading & Engineering Co Pty Ltd [1958] VR 198; Maritime Services
Board of New South Wales v Posiden Navigation Incorporated [1982] 1 NSWLR
72. Apart from yielding up the conclusions that these terms are not terms of
art, that they can be ambiguous and uncertain,
and that their meaning is
affected by the context in which they are used, the cases to which I have been
referred are not of any
particular assistance to me.
1168 Importantly, the expression is used in the context of indemnifying against
consequences resulting from a breach of contract.
The contracting parties in
agreeing the terms to be used in the Schedule 14 deed must be taken as being
cognisant of the financial
consequences to the innocent party that could flow
from the other party's breach of contract. The meaning is to be ascertained
accordingly.
1169 In this particular setting I do not consider that the terms "costs" and
"expenses" are used synonymously. The term "costs"
here is sufficiently wide
to encompass "losses" incurred and I am satisfied that reasonable commercial
parties would have intended
that this be so. An indemnity in this setting that
did not extend to losses directly incurred by reason of a breach seems a most
unlikely one to have been sought in a performance guarantee of the present
variety.
1170 If, then, the expression can be taken as referring to "losses and expenses
incurred directly by reason of the default", the
scope of the indemnity seems
relatively straightforward and familiar. As has been recognised in some number
of English decisions
particularly in the context of construction contracts,
"direct loss and expense" (or "damage"), has been equated with loss and expense
which flows naturally from the breach and as such are to be equated with losses
and expenses falling within the first limb of the
rule in Hadley v Baxendale
(1854) 9 Ex 341: see F G Minter Ltd v Welsh Health Technical Services
Organisation (1980) 13 BLR 1 and the cases referred to therein. That
equation, in my view, is one properly to be made in this setting given the
obvious purpose of the indemnity. I would construe it accordingly.
1171 Later in these reasons I have held all of the losses that I find BHP-IT
actually to have suffered in consequence of GEC Marconi's
repudiation, were, in
fact, losses falling within the first limb of Hadley v Baxendale.
Accordingly I am satisfied that consequent upon termination of the Sub-Contract
the costs and expenses that flowed from GEC Marconi's
breaches were the proper
subject of indemnification by GEC Marconi Australia.
15 CONCLUSION ON DAMAGES
1172 I have found that BHP-IT is entitled to an award of damages under the
following heads and in the amounts indicated:
(i) lost benefit of the Head Contract - $2,530,044
(ii) project costs incurred from January -May 1997 - $217,402
(iii) third party liability costs - still to be calculated.
PART IV: BHP-IT'S SECOND CROSS-CLAIM
(1) Introduction
1173 The cross-claim BHP-IT brings against the Commonwealth has an essentially
defensive rationale. If BHP-IT is found liable to
GEC Marconi for breach of
the Sub-Contract, it seeks in its cross-claim to pass on to the Commonwealth
the burden of any damages
awarded against it. The cross-claim has three
independent foundations - breach of contract, contravention of s 52 of the
Trade Practices Act 1974 (Cth) ("the TP Act") and negligent
misrepresentation - although the damages claimed in respect of each of these
are identical.
1174 While the purpose of the cross-claim may have been defensive, the manner
in which it has been formulated in each of its above
three manifestations is
such that, formally at least, those claims are not wholly contingent upon
BHP-IT being found liable to GEC
Marconi. This creates a state of affairs
which, I venture, was unanticipated when the cross-claim was made. Account of
it has not
been taken in the relief sought. The most that BHP-IT can say of
its position is that, even if it is successful against GEC Marconi,
it may
still be able to recover from the Commonwealth losses which resulted from its
dispute with GEC Marconi but which it could
not recover from GEC Marconi (by
reason of the damages ceiling or otherwise). Beyond this it says that, without
the benefit of my
findings, it is not possible to identify with further
precision the circumstances in which its cross-claim would still have an
operation
in the event that it succeeds against GEC Marconi.
1175 The course I intend to take in light of my findings and conclusions on GEC
Marconi's claim and BHP-IT's first cross-claim, is
to consider only the issue
of liability in this cross-claim. It does not appear from what has been put so
far in submissions that
my assessment of damages would serve any useful
purpose. If this cross-claim has remaining independent life, the losses so far
suggested
that may be able to be recovered under it arise out of unrecovered
losses sustained in the BHP-IT - GEC Marconi dispute.
1176 One major part of the cross-claim relates to whether the Commonwealth and
BHP-IT were in breach, respectively, of the Head Contract
and of the
Sub-Contract (a) in failing to provide STUBS and (b) in not paying for
Milestone 4000. I have already dealt with these
matters as they relate to the
Sub-Contract. I need only indicate that my conclusions there are similarly
applicable to the Head
Contact as well.
1177 To put the matter generally but somewhat inaccurately, the balance of the
cross-claim relates to the circumstances leading up
to the cancellation of
STUBS and to alleged misrepresentations and non-disclosures made by the
Commonwealth to BHP-IT concerning
both its intention to provide STUBS and the
reasons for its cancelling STUBS.
1178 As I have indicated the cross-claim is advanced, variously, as a claim for
breach of contract, for contravention of s 52 of the TP Act, and for
negligent misrepresentation. I will describe these briefly. The breach of
contract claim, it is contended, resulted from
the failure of DFAT to keep
BHP-IT fully and accurately informed about STUBS and about DFAT's increasingly
firm intention from early
1995 to abandon STUBS. BHP-IT was in consequence led
to adopt an approach to the non-supply of STUBS and to the negotiation of the
Emulation Variation Agreement in November 1995 which was quite different from
the approach it would have adopted had it been aware
that the cancellation and
the circumstances leading to it had been engineered.
1179 The TP Act and negligent misrepresentation claims are founded on common
facts. BHP-IT contends that from the date of execution of the Head
Contract
until mid-September 1995, the Commonwealth represented to BHP-IT that it was
willing and able to supply STUBS as CSI and
would purchase STUBS from AWADI for
the purpose. When the Commonwealth informed BHP-IT that it had cancelled STUBS
in September
1995 it represented that it had done so through no fault of its
own but as a consequence of the conduct of AWADI. The above representations
were false and were never remedied. Equally they were made in circumstances in
which a duty of care was owed to BHP-IT. BHP-IT
acted in reliance upon them.
I should add in relation to the tort claim that, in light of the conclusion at
which I have arrived
on the contract claim, I do not intend to consider, in the
alternative, whether a duty of care was owed to BHP-IT.
The principal actors and bodies
1180 Before turning to the general factual setting of these claims I should
refer to the principal actors and bodies involved in
the events to be narrated.
The cross-claim focuses primarily on the decisions and actions, first, of
officers and committees in DFAT
and to a lesser extent of the Department of
Defence ("DoD") and, secondly, of AWADI. Dealing first with DFAT, Les Cook
apart, the
relevant officers were -
(i) Robert Nichols, who was an officer in the IT Branch who assisted Les Cook
and who conducted negotiations with AWADI for the proposed
procurement of
STUBS;
(ii) Anthony Skinner, who was an Assistant Secretary and head of the IT Branch
which was responsible for the ADCNET project;
(iii) Geoff Allen, who was an Assistant Secretary and head of the Diplomatic
Security and Countermeasures Branch of DFAT, this branch
being responsible for
the computer security requirements of the Department;
(iv) Robert Cotton, who was the First Assistant Secretary of the Corporate
Services Division of the Department and the person to
whom Mr Skinner
reported; and
(v) Clive (Kim) Jones, who was Deputy Secretary of DFAT who had oversight
responsibility for three Divisions of the Department including
Mr Cotton's and
the person to whom Mr Cotton reported.
The relevant DFAT committees for present purposes were:
(a) the Senior Executive ("the SE") - a body made up of the Secretary and
Deputy Secretary of the Department;
(b) the Systems Policy Committee ("the SPC") - a committee chaired by Mr Cotton
(or by Kim Jones when he attended) that had the oversight
of strategic policy
directions concerning information technology, which had Department-wide
membership and which made recommendations
(where appropriate) to the SE;
(c) the IT Executive - a body formed by Kim Jones to keep him informed on IT
related issues facing the Department, and at the meetings
of which Les Cook was
a regular attendee; and
(d) the ADCNET Security Sub-Committee - a committee chaired by Mr Allen and the
membership of which included Mr Skinner, Les Cook
and DSD (see below)
representatives.
1181 Within the DoD, which was also considering procuring STUBS, there were two
units of present significance. The first was the
Defence Signals Directorate
("DSD"). This was the national authority responsible for signals intelligence
and information security.
Its functions included providing information
security products and services to the Australian Government. It was the body
that
evaluated security devices and made recommendations on their acquisition.
The second DoD unit to be noted was the Defence Science
and Technology
Organisation ("DSTO"). Its role was to ensure the expert and innovative
application of science and technology to
Australia's defence.
Matters of weight and credit
1182 A sharp attack has been made by BHP-IT on the credit of Les Cook and on
the weight to be attributed to the evidence of most
of the principal
Commonwealth witnesses.
1183 Before referring to specific individuals I should say that, in relation to
the cross-claim as in relation to GEC Marconi's claim,
I had derived little
assistance from the oral and much of the written evidence of most of the
witnesses, be they for the Commonwealth
or, in Mr Brent's case, for BHP-IT.
The reason for this is that most demonstrated little, if any, useful recall of
events and conversations
that are said to be germane to the cross-claim. Given
the lapse of time since the events in question this is unsurprising. That
lack
of recall, though, has had two consequences. First, it has fostered
significant attempts at reconstruction from documentation
- a phenomenon that
has left witnesses sadly exposed to obvious inaccuracy in the face of
conflicting documentary material. Les
Cook was a victim of this. Secondly,
the lack of recall led some number of witnesses to state forthrightly that they
had no recall
of the matters about which they were being questioned. This has
led to the predictable, but not necessarily inappropriate, submissions
(a) that
lack of recall has been used as a refuge to deflect questioning and (b) that
clear recall when other matters have not been
recalled, demonstrated
reconstruction or recent invention.
1184 My concern about the selectivity of recall and about the prevalence of
reconstruction in this part of this proceeding has accentuated
my general view
that the oral evidence of some number of the witnesses on matters of detail - I
instance principally Mr Cook, Mr
Brent and Mr Skinner - ought not be treated as
reliable in the absence of support from contemporary documentary evidence.
1185 I turn now to particular witnesses. First Les Cook. I do not regard his
evidence as reliable save when I expressly indicate
to the contrary. It was
marked by a high degree of reconstruction - and he did concede he had
reconstructed portions of his witness
statement. My problems with his evidence
were exaggerated by his tendency to be argumentative (on occasion to the point
of being
counter-suggestive) and by his regular and manipulative advocacy for
his own point of view. The latter quality is on display in
documents he
prepared relating to STUBS. While I acquit Mr Cook of deliberate dishonesty in
some of the evidence he gave, his advocacy
and his argumentativeness resulted
in his giving evidence that was on occasion misleading.
1186 Mr Skinner's oral evidence reflected the problems of lack of recall and
selective memory to which I referred above. Instances
of the latter tended to
be partisan in character and dubious in quality. While not suggesting that he
resorted to untruth, I nonetheless
do not regard his evidence as reliable.
1187 Kim Jones' evidence was strongly marked by a lack of recall of events,
meetings, etc. While he clearly participated in significant
discussions in
May-July 1995 concerning STUBS, I am not surprised at his lack of memory of
these. Though formally responsible for
that area of DFAT engaged in the ADCNET
project - and he was the Department's signatory to the Head Contract with
BHP-IT - his involvement
in the matter was particular and strategic. It
reflected the hierarchical structure and delegation of responsibilities then
characteristic
of the Australian Public Service. His departmental role and the
diversity of his responsibilities in an administrative structure
of this type
go far to explaining his lack of memory. As can be the case in other types of
position, forgetting what it is no longer
necessary to remember can be a
positive attribute. This said, I do not consider that his oral evidence added
to the documents tendered
in this matter.
1188 The one general comment I would make about the evidence of DFAT officers -
and it is reflected in responses given by most of
them to questions of mine -
is that they betrayed a lack of understanding of the ADCNET contracts and of
their significance. The
ADCNET project and the interests of DFAT, rather than
the ADCNET contract and their responsibilities under it, seem to have been
their principal preoccupation. I was left wondering on a number of occasions
whether, on the Department's side, anyone was actually
managing the contract as
such and was attentive to its demands. It is Kim Jones' evidence that this
contract was an early and the
biggest IT contract that by then had been done by
DFAT. The evidence in this proceeding clearly reflected inexperience in
contract
management.
(2) Factual Setting
1189 The oral and documentary evidence relevant to the cross-claim runs into
thousands of pages. The written and oral submissions
on it, to many hundreds
of pages. In an attempt to render this material manageable I intend (a) to
deal synoptically with the evidence
on such issues as I consider to be of real
significance in the cross-claim and (b) to deal cursorily or not at all with
issues I
consider to be of no particular moment. Because of the nature of the
claims made it will be necessary, though, to refer verbatim
to some number of
letters and minutes.
1190 Put generally the relevant evidence falls into four loose phases. The
first ran from that time in 1993 when STUBS became the
preferred option to
provide boundary security for the ADCNET system, until shortly after the
execution of the ADCNET contracts in
September 1994. The second phase was that
in which the process of exploring alternative strategies to STUBS began. The
third was
the period in which official endorsement was sought for an alternate
strategy. And the fourth was the period leading up to the communication
to
BHP-IT and GEC Marconi in September 1995 that STUBS had been cancelled. I do
not assign dates for these phases (other than the
first) as they are not
agreed. The phases themselves merely provide easy but inexact vehicles for
ordering the evidence.
1191 Before dealing with them in turn and so as to give some focus to the
ensuing narrative, I would note the following about the
STUBS procurement
generally and issues to which it gave rise. First, there was over time a
decrease in the number of STUBS devices
likely to be ordered by DFAT and an
increase in the projected price of the devices. Price did at some (disputed)
time become an
issue. With DoD also being interested in procuring STUBS, there
was a related question as to the significance of each Department's
projected
procurement to AWADI's commitment to STUBS and its pricing of the devices.
Secondly, there were two significant risks associated
with the STUBS
procurement. One was that the STUBS devices were required to achieve what was
described as an ITSEC Evaluation of
E5. This evaluation involved an assessment
by DSD of the security of the system according to criteria endorsed by DSD. No
security
device previously used by DFAT had reached the E5 standard. DFAT
insisted that AWADI bore the risk of not reaching that standard.
The other
risk related to whether DSD would be able to perform its ITSEC evaluation
within the timeframe required for the ADCNET
project. Thirdly, the ADCNET
contracts provided only for the use of STUBS devices in Canberra and not at
overseas posts. This limitation
on its use gave rise to what was known as the
"trade-off between security and functionality", a matter that attained
prominence in
mid-1995.
8. 1993 - end of 1994
1192 Discussions between DFAT and AWADI for the possible purchase of STUBS were
initiated in March 1993. At a meeting with James
Armstrong of AWADI on 9 March
1993 Les Cook estimated that the ADCNET requirement would for "some 1000 ...
equipments". At a subsequent
meeting in April 1993 involving Mr Brent, Roger
Cooke and Mr Skinner, amongst others, Mr Skinner indicated that the contracted
for
numbers would be for "300 or so".
1193 By the end of April 1993 an ADCNET Coordination Group had met involving
representatives of DFAT, BHP-IT and EASAMS. The minutes
of that meeting noted
that the "STUBS solution is now considered as the likely solution" and that a
team was being formed to evaluate
its use in ADCNET.
1194 On 22 October 1993 AWADI provided DFAT with a firm price schedule valid
until 30 November 1993. It was in part:
"Device Unit Price $A
STUBS Sealer $12,864
STUBS Gateway $13,520
STUBS Key Distribution Centre $16,965"
1195 Les Cook prepared a minute for the Systems Policy Committee meeting of 4 November 1993. In it he outlined the proposal for deploying STUBS in ADCNET; the procurement of 70 devices at a cost of about $950,000; and the use of STUBS only in Canberra for communications analysts and corrective operators and for some general user's work stations. Approval in principle for STUBS was sought. Among the "major problems" identified with using STUBS, he noted the following:
"a. STUBS is at present available only as a prototype and that will require modification to work within ADCNET. The first production batch is planned to be available by December 1993;
9. AWA do not yet have any firm orders for STUBS. If no orders materialise from Defence, it is possible that a DFAT order might not be sufficient to justify completion of development of the device, leaving DFAT unable to complete ADCNET."
1196 On 8 November 1993 he wrote to Mr Brent in terms that presupposed that
DFAT would acquire STUBS. That letter raised, amongst
other things, that the
proposed fixed-price contract should allow acceptance testing of the software
by emulation should "STUBS or
other DFAT-provided components ... not [be]
delivered to the agreed schedule".
1197 By April 1994 the parties were addressing the issues (inter alia) of AWADI
being unable to provide STUBS devices (described
as a "Low probability") and
AWADI being unable to deliver production STUBS devices on time ("High
probability"). As to the latter,
a risk analysis document of 7 April 1994 from
Mr Nichols to, amongst others, Mr Brent and Roger Cooke, stated the
following:
"GITC Safeguards
R3 acceptance tests will be carried out on the prototype Stubs devices if available or, if the prototype is not available, a test harness will be used to demonstrate the interface has been developed in accordance with the Stubs specification.
Risk Abatement
The PSI will develop their Stubs interface software in accordance with agreed detailed specification to be provided by AWADI after signing of the AWADI contract. AWADI are to provide prototype Stubs devices well before R3 acceptance testing is to begin."
1198 By May of 1994 a draft contract had been prepared for the purchase of
STUBS equipment and services by the Commonwealth from AWADI.
Mr Vile of BHP-IT
assisted Mr Nichols in the preparation of that draft. Schedule 2 to that draft
indicated that it was proposed
to buy 50 STUBS devices. That figure is
consistent with AWADI internal documents for later in 1994.
1199 The ADCNET contracts were executed on 14 September 1994. The Commonwealth
did not then have a contract with AWADI for the supply
to it of STUBS-related
equipment and software though it (and BHP-IT in turn) had entered into
obligations to supply that equipment
and software under the ADCNET contracts.
On 26 September Les Cook wrote to Peter George, the AWADI STUBS Project
Manager, informing
him of the obligations so incurred to BHP-IT and asking for
confirmation that AWADI could meet the timetable for delivery of STUBS
CSI
specified in the ADCNET contracts.
1200 The FRS to the Head Contract indicated that STUBS was only to be deployed
in Canberra and not at overseas missions. This was
later to be recognised
within the Department as "a major weakness of the ADCNET project". AWADI notes
of a meeting with Mr Nichols
of 15 November 1994 indicated that the reason
given for STUBS not being envisaged for overseas posts in the foreseeable
future, was
"lack of money".
1201 The negotiations with AWADI for STUBS were conducted on the basis that it
would achieve an ITSEC evaluation of E5. On 30 November
1994 Mr Nichols wrote
to AWADI on, amongst other things, this matter. The letter stated:
"DSD Evaluation
The main issue as I see it is that Stubs equipment which cannot be evaluated to E5 is of no use whatsoever to DFAT. We have been advised by Attorney General's Department that any progress payments made by the Commonwealth must be fully protected by financial guarantees. In the event that E5 cannot be obtained because of a defect in the design of Stubs (not because of any delay on the part of the evaluator) then all payments must be recoverable.
An issue raised with AWADI (I believe it was with Mr Smith) was that given that AWADI are dependent on DSD (or possibly a commercially licensed evaluation facility) to evaluate Stubs, there will need to be an agreed date after which a procedure will commence which may lead to the enforcement of the financial guarantee if E5 accreditation has not been or cannot be achieved. That procedure may include seeking advice from DSD on whether Stubs can be used with ADCNET prior to completion of evaluation.
It would be advisable for AWADI to obtain formal agreement from DSD that the evaluation will be performed within a timeframe acceptable to DFAT. DSD are aware that ADCNET is unlikely to be commissioned without their approval.
In summary, DFAT may be willing to share the risk that the evaluation cannot be completed by January/February 1996, but we would not be willing to share the financial risk of evaluation not being able to be achieved because of a defective or incorrectly designed product."
1202 By letter of 6 December 1994 AWADI accepted "with gratitude" the offer to share the risk that evaluation could not be completed by February 1996 because of delay on the evaluator's part. On the issue of accepting sole risk for the ITSEC evaluation, AWADI's view was:
"DFAT position is understood, nevertheless there are a number of aspects of STUBS development which necessitate the risks to be understood and appropriately shared between AWADI and Commonwealth. This may necessitate a resolution at a high level meeting between DSD, DSTO, DoD (Business Development), DID, DFAT and AWADI."
1203 DFAT in turn responded to this by letter of 19 December 1994 in which
it outlined three options it was considering as to the
manner and timing of the
purchase of STUBS software and equipment. Its stated preference was to
purchase both the software and equipment
under a single contract rather than to
defer ordering until ITSEC evaluation was completed or nearly so. I would note
that there
had in the above sequence of correspondence been discussions on the
provision of, and use of, prototypes for acceptance testing.
1204 AWADI's view of the progress of negotiations was stated in an internal
memorandum of 18 January 1995.
"For many months now we have been progressing the STUBS DFAT contract which, as you are aware, is vital to the future credibility of our STUBS investment.
The draft Contract Agreement provided to us by Bob Nichols of DFAT in December has been updated by the inclusion of all known changes required by Katrina and ourselves.
It lacks only agreed pricing for the units, to enable us to progress this Contract further.
Please provide or generate cost estimates and arrange a pricing review meeting to finalise the prices to be offered.
...
Please let me know your plans. This project has been hanging around for far too long and the ball is firmly in our court."
1205 On 22 December 1994 Les Cook wrote directly to Mr Harris of GEC Marconi
- the letter was not copied to Mr Brent - raising the
prospect of developing
software for STUBS emulation. It stated that "[t]he purpose of this would be
to avoid dependence on supply
of equipment and software by AWADI to allow PSI
to meet its commitments". In cross-examination Les Cook agreed that this
letter
was directed to the possibility that the Department might move away from
STUBS altogether and finish R3 using an emulator. It appears
from a minute
from Les Cook to a Mr Spiller also of DFAT on 22 December 1994 that he was
keeping abreast of testing of KIV-7 and
that he was giving consideration to its
use as a replacement for STUBS. The minute itself bore the heading "STUBS
REPLACEMENT -
USE OF KIV-7 GATEWAY".
1206 To put the evidence outlined above in context for the purposes of the
cross-claim, BHP-IT has submitted that, in late 1994,
there was little chance
of a purchase contract for STUBS devices being executed in time to enable DFAT
to comply with its obligations
under the Head Contract. It did not reveal this
to BHP-IT. The reason for this was that Les Cook and Mr Nichols were giving
serious
consideration to completing the contract with an emulator and they
induced BHP-IT over time to agree to this.
1207 This submission is strongly contested by the Commonwealth.
10. Exploring alternative strategies
1208 The minutes of an SPC meeting for 17 January 1995 record that:
"Mr Cotton sought an update on the STUBBS project. Mr Cook advised that the matter was still under negotiation and as DFAT seems to be the only buyer at this time the costs and contractual arrangements are not to our liking. Mr Cotton asked for a paper for the next meeting to advance discussion on this matter including fall back options should the contract not proceed."
1209 In cross-examination Les Cook accepted that from February 1995 he
believed, on balance, that DFAT would be better off if it abandoned
STUBS and
went to the alternative he was proposing. That proposal was foreshadowed in
the minute he sent on 14 February to Mr Jones
and Mr Cotton in response to the
latter's SPC meeting request.
1210 That minute noted preliminary DSD agreement concerning an alternative
implementation of the ADCNET security mechanisms should
STUBS not be available.
It noted the high security assurance of STUBS but its "inflexibility" because
STUBS was only to be deployed
in Canberra. It went on to state that:
"AWADI is delaying the completion of a contract with DFAT for STUBS. This has caused us to examine, with DSD, alternatives should the STUBS project not proceed. One alternative is considered to be implementable with minimal delay to the schedule."
The minute outlined the use of an encryption device (KIV-7) as the security
gateway. Although it would only be accredited to E3
rather than E5, it would
be able to be deployed at posts as well as in Canberra. It concluded:
"Decisions Required
9. The Department has two options:
a. implement with STUBS unless AWADI abandon it or seek to increase the price or delay delivery by unacceptable amounts; or
b. accept a slightly higher risk that classified material might be sent to the NNS environment because of a programming error or deliberately introduced hostile program, but implement much improved ADCNET to NNS connectivity at all posts.
10. DSD are likely to advise that an alternative to STUBS should be used only as an interim solution should STUBS not be available. DSD will confirm that the level of assurance which could be achieved with option (b) would be superior to that of comparable systems in allied countries.
11. Guidance is sought as to whether option (b) should be developed into a formal proposal to the Systems Policy Committee through the ADCNET Security subcommittee."
1211 Kim Jones wrote a note on the minute which said that "the functionality
advantages would be considerable". This notation led
Les Cook to develop his
March option papers (below) for the SPC.
1212 A meeting of the ADCNET Security Sub-Committee was held on 17 February
1995. Its minutes record the following:
"STUBS
28. Mr Allen said that the STUBS device was causing him some concern. Mr Cook said that STUBS still existed but that the manufacturer was showing little interest in developing the device further. Part of the problem was the drastically reduced demand for the device. DFAT had reduced its requirement from 1,000 to 50 and DoD, while still interested, had not made any commitments. Mr Nichols said that DFAT was also causing some delays by varying its required specifications. He thought that the manufacturer wanted us to share financially in the risk of development whereas we want to buy a fully evaluated product ...
29. Mr Allen asked whether it was possible to form an alliance of potential users who could bring pressure to bear ... Mr Cook said that we were nearly at the stage where we had to be sure of having STUBS available otherwise we would have to change the direction of our development of ADCNET. Mr Nichols said that we should hear something from AWADI soon. He expected that they might provide us with a pricing and payment schedule."
1213 On 20 February 1995 a Project Management committee meeting was held that was attended by, amongst others, Les Cook, Mr Brent and Mr Wishart. Mr Wishart's report of that meeting noted:
"DFAT getting even more concerned with STUBS. Very high possibility that STUBS will not be available in any quantities for testing. Some possibility that STUBS may never be available. [Les Cook] considering other options, will keep us informally advised and raise CR's for any work to build emulators or (worst case) rework of security policy."
1214 On 3 March a proposed board submission was prepared within AWADI seeking additional funding for the STUBS project. An accompanying handwritten note stated:
"I'm not going to ask the board for a further $1.6m; we need to try to get from our customers:
. a further major cash input; or
. guaranteed orders for up to 1000 units; or
. a combination of cash and orders."
The submission had indicative selling prices for the sealer, gateway and KDC
as $28,223, $28,637 and $29,977 respectively. It indicated
that current sales
forecasts for DFAT for the years 95/96 and 96/97 were "50 Sealers, 2 Gateways,
2 KDCs".
1215 On 2 March Les Cook prepared a paper for the ADCNET Steering Committee.
The opening paragraphs stated the paper's objectives:
"1. It is becoming increasingly likely that STUBS will not be available in time for the deployment of ADCNET release 3 in Canberra. This requires DFAT to decide whether ADCNET can be deployed to replace the IBM message switch and, if so, what will be used to substitute for STUBS as a security gateway between ADCNET and NNS systems.
2. This minute proposes two alternative gateway strategies which would allow deployment of ADCNET to proceed, subject to acceptance of a lower level of security assurance than that which would be achieved with STUBS (although possibly not less than that approved in the original ADCNET System Security Policy). Implementation with STUBS is termed option A. The alternative strategies are termed options B and C. Option B will achieve the highest level of assurance possible without STUBS, but will retain the limitations that documents and electronic mail may be exported from ADCNET to NNS systems only in Canberra. Option C will allow exporting to be initiated from any ADCNET terminal and to be performed at any post, providing ADCNET - NNS communication at posts; this will remove a major area of weakness in the functionality of ADCNET but will achieve a somewhat lower level of assurance."
1216 It went on to outline three options (A, B and C). Option A was to use
STUBS; Option C, to use an encryption device. It considered
the "Delays,
Costs and Risk" on the assumption (a) that STUBS would not be available on time
and (b) that it would be available.
On the first assumption all three options
were open (though with differing delays, costs and risks). On the second
assumption Options
A and C were available. The paper concluded: "Option C is
recommended as providing the highest level of functionality and a balanced
approach".
1217 To anticipate matters, on 27 March a similar paper with a like conclusion
was prepared by Les Cook for the SPC.
1218 To return to 3 March 1995, Les Cook prepared a briefing note for projected
discussions with AWADI and Defence regarding STUBS.
It attached a chronology
of communications between DFAT and AWADI concerning negotiations for STUBS,
that chronology finishing with
the observations (a) that AWADI wished to
arrange a meeting with DFAT's senior management "to discuss the way forward"
and (b) that
Mr Nichols advised Les Cook and Mr Skinner of "his suspicions that
AWADI may be having difficulties in financing the project and
in meeting DFAT's
requirements". The briefing note took the form of questions to be asked of
AWADI and Defence respectively. The
questions to AWADI were:
". does AWADI intend to proceed with the development of STUBS to the production stage?
. if so, do they expect to achieve the availability dates previously indicated to DFAT?
. will the production models meet the functional specification agreed between the company and DFAT, or will a more limited capability model be substituted?
. will AWADI enter into a contract with DFAT to provide the required number of devices at a fixed price, without requirements for DFAT to make non-refundable payments in advance of receipt of the devices?"
One of the questions to DSTO was:
". What are the likely prospects of DSD completing the evaluation of STUBS within a reasonable timescale (mid 1996)?"
1219 Kim Jones sought Mr Cotton's view on 6 March on whether he thought it
would be useful to take up Les Cook's questions with AWADI
and DoD. He thought
himself that "we need to stir this along somehow". Mr Cotton strongly
supported the proposal and indicated
that the sooner the time picture was known
"we will then be better placed to take whatever alternative decisions we decide
are necessary".
(iii) Decision Making in DFAT
1220 On 29 March an ADCNET firm price management meeting was held involving
amongst others Les Cook, Mr Nichols, Mr Brent and Mr
Wishart. A handwritten
note of the meeting recorded the following:
"Kim Jones (Acting Secretary - DFAT) to talk to DSTO and AWADI this week.
DFAT may raise a CR to conduct acceptance tests without STUBS devices.
DFAT to make a judgment on whether STUBS is in the project or not within the next 4 weeks."
The minutes of this meeting recorded that "[t]he status of STUBS requires
constant monitoring. STUBS to be a standard subject item
for all Project
Management Meetings".
1221 On 30 March 1995 Kim Jones, Les Cook and Mr Nichols met with Dr Sinnott
and Ms Thorpe of DSTO. Les Cook prepared a minute for
Mr Skinner that
discussed the meeting. Ms Thorpe sent to Dr Sinnott her notes of it. Both are
in evidence. Ms Thorpe's notes indicated
that DFAT was concerned as to whether
STUBS would be available within DFAT's timeframe (March 96) or otherwise they
would need to
consider alternatives now. DFAT indicated that it was now
intending to purchase around 50 "because no overseas capabilities and
because
so expensive". DFAT also sought DSTO opinion on the "window of opportunity"
for STUBS before superior technology became
available. DSTO expected its own
new technology "to be available in 1-2 years".
1222 Les Cook's minute of the meeting indicated that Dr Sinnott would not state
an opinion on whether STUBS would proceed nor whether
DoD would act if DFAT
"pulled the plug". The minute included the comment that "DSTO seems to be
searching for a scapegoat for the
lack of success of STUBS ... [and] [i]t seems
very likely that DFAT will be the chosen scapegoat".
1223 On 3 April Dr Sinnott prepared a DSTO minute on the "FUTURE OF AUSTRALIAN
INFOSEC CAPABILITY". He expressed the view that there
was a high likelihood of
AWADI cancelling further STUBS development within the next few months on
account of mounting development
costs, uncertainty as to timescale for STUBS'
evaluation and absence of any DoD commitment for purchase of STUBS.
1224 On 4 April both Mr Nichols and Les Cook prepared minutes for Mr Jones (and
others) relating to the proposed meeting with AWADI.
Mr Nichols sought answers
to questions concerning (inter alia) the "new pricing structure ... to DFAT"
and whether STUBS could be
delivered in accordance with ADCNET's schedule. Les
Cook's minute related to the minimum requirements for a contract. It
reiterated
that STUBS should be supplied "in the quantities and schedule (sic)
previously defined by DFAT" and that E5 accreditation was a requirement
for
delivery of production units.
1225 An AWADI memorandum of 12 April 1995 reported a meeting with DoD. It
indicated that DoD was informed that "significant capital
[was] required to
complete STUBS"; "that Defence [was] the primary customer for STUBS as it now
stands"; and that "AWADI [saw]
the investment risk as too large to proceed
with the STUBS development unless there [was] a clear commitment from Defence
for future
purchases".
1226 A special meeting of the SPC occurred on 26 April 1995 to consider
"Security and Functionality Tradeoffs". There are various
notes of this
meeting. A draft minute of that meeting was prepared by Mr Holly of ITB.
Because of the importance attributed to the
minute by BHP-IT it is necessary to
set out one lengthy extract from it. It appears under the heading
"Discussion".
"As it is not sure whether Stubs will be available, two sets of questions arise. On the assumption Stubs is available, do we stick with it? Discussion looked at options for capping ADCNET at confidential or restricted and whether a change could be made at this point of time, ... Lowering the overall classification of ADCNET to allow for greater connectivity would require the setting up of a separate backroom system for highly classified traffic ... The meeting agreed that the level of classification planned for the ADCNET system should remain at Secret, Austeo. Mr Cook explained that [DFAT], in the person of the Secretary, accredits a system and decides whether or not it is prepared to use that system for its data and classification levels. The DSD role is advisory ...
With greater connectivity between systems DSD advice would be that the system should not be used for information classified higher than Restricted. With STUBS available to us the classification could remain at Secret. It was agreed that if STUBS became available we should probably persevere with it. ...
Agreed that we continue to develop ADCNET software in anticipation that Stubs will become available.
Mr Jones summarised discussion by suggesting that we leave the Stubs aspect unresolved as there is doubt about whether it will eventuate in the immediate time frame of the move to the new building.
On the assumption STUBS is not available what do we do then?
The trend of opinion is to go for the more functional version (Option C) of the Stubs alternatives outlined Paragraph 26 of Mr Cook's paper. Option C enables posts to have inter activity between ADCNET and NNS while Option B does not. ...
The meeting agreed that Option C should be adopted recognising the questions that flow from that decision and also agreed that we look very seriously at any system that is available subsequently to improve the security assurance rating." Emphasis added.
1227 To anticipate matters again, a minute of the 26 April SPC meeting was prepared on 21 May 1995 for consideration at an SPC meeting on 25 May 1995. That minute stated in part that the SPC:
"(i) did not achieve consensus on whether the functionality of option (c) ... justified not using STUBS were it available under acceptable contractual terms. It was argued that the proposed implementation of option (c) included adequate measures to counter the major threat of external penetration into ADCNET. Moreover those areas most vulnerable to threats of attack were assessed as having a very low probability of occurrence. It was also argued that the inflexibility of the STUBS approach would tempt staff to use insecure systems to bypass the ADCNET security controls, such as using NNS systems for material which should be classified. The counter argument was that without STUBS it will not be possible to provide an objective assessment of the significance of the security risks.
(j) concluded that if STUBS were not available, then the advantages to the Department of option (c) of the paper, including deployment of gateways at posts, outweighed the more constraining approach described in the paper as option (b);
(k) concluded that if Stubbs was confirmed as a viable security alternative, then the Department will needed to determine whether it should be used given the arguments for and against security assurance and user functionality."
1228 I would note in passing that Les Cook's evidence was that he could
confidently recall a conversation in which he told Mr Brent
of the 26 April SPC
meeting. I would also note that a variant (unexplained) of the 21 May version
of the minutes were annexed to
an Administrative Circular of 17 July 1995 a
copy of which was distributed to Mr Brent.
1229 Reverting to earlier in May, on 10 May 1995 a meeting was held involving
representatives from DoD, AWADI and DFAT (Mr Nichols).
Mr Nichols prepared a
minute for Mr Skinner on 17 May 1995. It read in part:
"2. AWA revealed that the original pricing was based on expected sales of 2,000 units. Defence and DFAT requirements will amount to the sale of only some 400 units at a cost per unit of $29,500 to Defence and $34,000 to DFAT. (The higher cost to DFAT is because of royalties to be paid to DSTO. Defence indicated, however, that this cost could be paid directly by Defence to DSTO to reduce DFAT's price to around $30,000 per unit.)
3. AWA also indicated that they have spent $2M so far in R&D and will need to spend another $3.45M ($0.6M for evaluation by Admiral, $1.3M for further R&D, $0.75M for manufacturing, $0.5M for licensing and $0.3M for trials).
4. AWA still expect to be able to produce a prototype by 3rd quarter 1995 and some production units by 1st quarter 1996. There were still some technical issues outstanding which needed to be resolved by DSTO.
5. Defence suggested that it would be in AWA's interest to not cancel the project, but to find ways of bringing the price down (eg by reducing functionality, not using milspec development techniques, accepting an overall loss which would be less than the $2M spent so far). AWA said that it was too close to finishing Stubs to radically reduce the functionality. Also AWA wish to recover full costs rather than accept a loss.
6. Defence also suggested that Stubs would not have a long life span and that they were looking at other options (presumably what Don Synot (sic) of DSTO had described). They implied that a 3 year contract period (including maintenance) would be appropriate. I said that DFAT would want certainty of support for Stubs for at least 10 years.
...
9. AWA admitted that the timing of the evaluation of Stubs by Admiral was not clear, but that it could take as long as 1 year.
...
11. AWA agreed to try to provide Defence (copied to DFAT) a proposal with revised prices by the end of next week. The pricing would be scaled based on the volume of units to be purchased (eg 300 units, 350 units, 400 units) allowing Defence to see what the pricing would be if DFAT withdrew."
1230 In an internal BHP-IT email of 15 May, Mr Brent recounted that he had
been informed STUBS issues were due to be resolved that
week. AWADI was to
make a decision whether or not to proceed with the program or cancel it
following discussions with DoD. He indicated
this would provide "a further
opportunity" to extend the ADCNET contract schedule. The same email made
reference to a recent "regular
(fortnightly) management meeting".
1231 On 18 May 1995 Mr Brent wrote to Les Cook a letter that addressed directly
the issue of STUBS. It is set out at length in Part II: Emulation Variation
Agreement (a)(i). I would note here that the letter was prefaced by the
observation that "[d]uring the course
of recent project management meetings
there has been a lot of discussion concerning the status of STUBS". It noted
the following
in dot point fashion:
". STUBS Software Interface Specification is delayed 4 months;
. STUBS delivery is likely to be delayed;
. STUBS may not be delivered at all;
. the Department does not have a contract for the delivery of STUBS;
. high level discussions between AWA, DFAT, Defence are imminent and will decide the outcome. This may well be that the STUBS program is cancelled within AWA."
It later observed that "[w]hatever the outcome of STUBS availability we need
to move quickly ... to contain significant and costly
delays".
1232 Les Cook was away at the time of this letter and it was received by
Nichols who left it to Les Cook to reply. This occurred
on 6 June 1995: see
Part II: Emulation Variation Agreement (a)(i).
1233 On 19 May AWADI wrote a letter to DSTO which read in part:
"At a discussion with Jim Noble AS JPM Defence Materiel Division, 19 May, AWADI committed to the following schedule for the STUBS program.
. Sealer demonstration: July 1995 (full working prototype less encryption algorithms
. Defence contract: September 1995
. Hardware designs complete: December 1995
. First prototype system: January 1996
. System integration commences: January 1996
. Formal system acceptance testing complete: June 1996
. First production units available following DSD approval of field use of STUBS
This schedule assumes an early `Letter of Comfort' from DEF Material, a Contract for near 400 units by end August 1995, contract provision which satisfactorily manage the remaining risks and an acceptable price."
1234 The SPC meeting of 25 May 1995 was not attended by Kim Jones or by Les
Cook. Again there are several versions of this meeting.
The minutes recorded
discussion and comment on the 21 May version of the 26 April 1995 SPC meeting.
They indicated that when in
final form those minutes would be forwarded to the
Senior Executive ("the SE") with recommendations. They noted Mr
Nichols' report of his recent meeting with AWADI. It also was indicated that
DSD had undertaken to provide advice to the Department
on Les Cook's Options B
and C. A handwritten note of the meeting additionally had Mr Nichols reporting
that the evaluation of STUBS
would be a further twelve months after its
installation. The minutes recorded that the timeframe for building an
alternative to
STUBS into ADCNET had passed. The handwritten notes also
recorded comments attributed to Mr Cotton. They referred (inter alia)
to
"Final cut-off date" and "can't drag on we need to drop out".
1235 On 26 May 1995 Mr Nichols in an email to Mr Skinner expressed the view
that "[o]n cost grounds ... a decision could be taken
to abandon STUBS
provided: (a) the 3 month delay to project is acceptable (b) DSD are not
insistent that we use STUBS no matter
what the cost and risks".
1236 Prior to receiving a reply to his 18 May letter to Les Cook (who was
overseas at the time) Mr Brent sent a further letter to
Les Cook on 1 June
enclosing a newspaper article concerning AWADI's financial difficulties. The
letter stated that "[i]n view of
the situation we need to consider alternatives
to STUBS". Les Cook responded on 2 June 1995 in a letter that stated in
part:
"The Department was aware of the article and shares your concern as to whether dependence on the STUBS device is likely to lead to problems.
I note that there is presently no proposal from AWADI to change the schedule for STUBS development, but I also note that AWADI has still not entered into an agreement with DFAT. We have been advised that the price of STUBS devices is likely to increase by a factor of more than two. DFAT is in the process of determining its response to this advice.
We do not believe that there is any practical alternative to an implementation of ADCNET based on the concepts of sealing and gateways ...
The Department's Executive is scheduled to meet in the week commencing 12 June to consider whether to proceed with STUBS or to return to an approach in which sealing and gateways are implemented by PSI-developed functions operating on ADCNET-compatible equipment.
To date we have been reluctant to involve the PSI in examination of design options in order to avoid work which may prove to be unnecessary. Until a decision is taken that STUBS is not practical or economic, this remains the case. We have, however, been active in examining contingency measures should the use of STUBS not be possible. This work has involved DSD, whose advice as to the adequacy of any approach will be important to its acceptance. At this stage it does appear that there is an approach which could be implemented without major change to the current ADCNET design, although it will require some additional development by the PSI. An outline of this approach is attached for your examination. Please note that the document is a draft at this stage and is intended to form the basis of a proper examination leading to a change request should this be necessary."
1237 The attached document, entitled "STUBS Alternatives - Design Criteria
and a Proposal" was dated 25 March 1995. Mr Brent had
no recollection of this
letter or its attachment.
1238 On 6 June, as noted earlier, Les Cook replied to Kyrill Brent's 18 May
1995 letter. I merely note that in it he (i) outlined
the Option C proposal
which was being taken to the DFAT executive; (ii) he indicated that "the
Department intends to make a decision
on the use of STUBS or this approach
within the next two weeks"; and (iii) stated he would inform BHP-IT "as soon
as such a decision
is reached".
1239 AWADI's foreshadowed pricing proposal for STUBS was provided to DFAT and
DoD on 5 June. The letter to DFAT acknowledged the
delay in providing a
response. It costed the STUBS sealers, gateways and KDC by reference to
quantity ordered, the unit prices decreasing
as the orders grew in units of 50
from 200 to 400. The 200 unit prices were respectively sealer - $42,403,
gateway - $41,632 and
KDC - $42,537. The letter to DoD which was annexed to
DFAT's letter indicated that "Production (assuming a total purchase by Defence
and DFAT of 400 units) will take place in two batches of 200 units over a
period of approximately 18 months".
1240 When Mr Skinner was informed of the pricing proposals, he sent an email to
the members of the IT Executive indicating that on
the new prices DFAT was
"faced with massive cost overruns". He stated that draft DSD advice was
positive and would not discourage
DFAT from implementing Option C. He
continued that "this all appears good news and would support a decision to not
proceed with
STUBS". The email concluded:
"We need to agree on and put to the Executive for formal approval -
. whether to proceed without Stubs
. how to terminate Awadi negotiations
. whether Option B or Option C
. paper to go to Executive and when
. briefing to Ministers to counter possible reps from Awadi."
1241 A draft minute for submission by the IT Executive to the Senior Executive was prepared by Les Cook on 6 June 1995. It related to the use of STUBS. The minute referred to (a) AWADI's revised prices and the likely timetable for the availability of devices; (b) the cost increase for the Department and the need for augmentation of funds in the order of $1.25 million to $2.25 million in 1995/96; (c):
"AWADI advise that prototype units will be available in 1st quarter 1996, too late to be included in ADCNET Release 3 software testing. Production units will be available over a period of 18 months, the earliest possible availability of sufficient units for DFAT being September 1996. AWADI will not commence production unless orders for at least 200 units are received, Defence are currently considering a proposal to order STUBS devices in September 1995;"
(d) DSD's opinion that Option C would protect against perceived threats; (e) the need to negotiate changes to the ADCNET software specification if the Department decided to proceed with Option C; and (f) the uncertain effect on the schedule for completion of development but by late July it should be predictable whether development would be completed in time to avoid the need to transfer the IBM message switch to the new building. The draft recommendations to the Senior Executive included the following:
"a. advise AWADI that procurement of STUBS devices for ADCNET will not proceed because of high costs, uncertain date of availability of production devices, uncertainty about long term support and inability to deploy sealing and gateway functions at posts;
b. adopt the security architecture outlined in Attachment 1 as `option C', accepting that independent evaluation of ADCNET security will certainly identify the potential security weaknesses described in that document and confirmed by DSD;
c. commence negotiation with the PSI for changes in the ADCNET Release 3 software specifications in order to implement the architecture described as option C in Attachment 1, with a view to defining a new project price and schedule by end July 1995."
I would note in passing that the first quotation in the body of this
paragraph is the subject of an attack by BHP-IT on the credibility
of Les Cook.
Mr Nichols gave evidence in which he accepted that statements made in the
quoted paragraph were inconsistent with correspondence
of which he was aware or
which he had composed.
1242 Kim Jones had written a note on the version of the draft he had received
stating: "what will be their [ie AWADI's] reaction?
Can they sue us?" That
note led to a request for legal advice on 19 June 1995 from DFAT's in-house
lawyers.
1243 The draft paper was scheduled for discussion in the IT Executive on 9
June. The evidence on whether it occurred on that day
or some day soon
thereafter is inconclusive. It is unnecessary to recount it. It is clear that
when notice of the meeting was given
(ie 8 June 1995) the formal advice of DSD
had not been received. It was provided in a document dated 9 June 1995. The
recommendations
made were that:
"a. if STUBS is available and it is practical to deploy it in sufficient numbers it be used;
otherwise
b. Option C be adopted but replaced when STUBS or a similarly strong alternative can be acquired; and
c. precautions of the sort described in para 9 above be adopted in addition to those proposed in the reference.": emphasis in original.
1244 By a Minute of the same day Mr Allen of DFAT's Diplomatic Security and
Countermeasures Branch wrote to all members of the IT
Executive concerning the
proposed STUBS alternative. His paper was critical of the level of security
offered by Option C; it noted
that DSD advised its use as an interim solution
"pending availability of STUBS or a similarly strong alternative"; and he
asked
whether other (indicated) options should be explored.
1245 Mr Campbell, who was Assistant Secretary, Corporate Services Division in
the Department appears to have been given the task
of redrafting Les Cook's 6
June draft in light of comments made at the IT Executive meeting that
considered it. The redraft also
took obvious account of Mr Allen's comments.
It formulated the options available as follows:
". to continue to plan for the use of STUBS and provide the necessary funding, while being aware that if Defence does not proceed to order STUBS we may have to move later in the year to one of the other options and it will cost more at that stage to do so.
. decide now to change to use of option C, on the basis that it will be cost neutral but we should keep looking for a more secure gateway system. Also bearing in mind that, even with this option, it may be necessary to move the mainframe to York Park because time may now be insufficient to have option C operating at the time of the move."
1246 The Campbell paper noted that the Legal Office still had to confirm
that there would be no financial or legal obligations on
DFAT were it not to
proceed with STUBS. Kim Jones request for legal advice was forwarded by the
Department's own lawyers to an officer
of the Attorney-General's Department on
19 June 1995. Advice was sought on DFAT's possible liability arising out of
its contract
negotiations with AWADI. The letter to the Attorney-General's
Department noted that "DFAT officers will be discussing a proposed
course of
action regarding this matter with Deputy Secretary Jones on Monday 26 June
1995". The advice was sought prior to that
date.
1247 A meeting of the Department's Senior Executive was also held on 19 June.
Mr Jones and Mr Cotton were present. Insofar as presently
relevant, the
minutes of that meeting noted:
"IT security and functionality tradeoffs
. The Executive discussed the issues raised in the minute prepared by CSD, covering the minutes of the special meeting of the Systems Policy Committee on 26 April 1995
- and took note of the matters on which a decision would be required in the near future (separate papers to be submitted)."
Neither Mr Jones nor Mr Cotton had a recollection of this meeting. The
Commonwealth has been unable to identify or find the CSD
minute referred to in
the above minutes. I have, though, referred earlier to the differing minutes
of the 26 April SPC meeting including
those prepared on 21 May 1995.
1248 Also on 19 June Mr Nichols sent an email to Les Cook and Mr Skinner
recounting a conversation with Mr Noble from DoD. Mr Noble
had indicated that
Defence was still serious about STUBS; and work was being done on a paper to
go to a committee which would meet
in September/October to make a decision.
1249 It is necessary now to revert to a minute prepared by Les Cook on 17 June
1995 and sent to Mr Skinner. It has been described
as the "Change of Tactics"
minute for such was what was proposed in it by Les Cook and Mr Nichols "with
regard to the STUBS decision".
It needs to be referred to at some length. It
said in part:
"3. If the decision to adopt option C is taken at this stage, we are concerned that a change request of this type will give the PSI a lever to prise open a large extension of schedule and consequent cost increase. I believe that the actual amount of change required will not be large but at this stage it will be difficult to argue with PSI estimates and these will inevitably be very conservative. The alternative is to allow the development to complete as if STUBS is to be used, with an agreed mechanism to emulate the STUBS devices for acceptance testing (the latter will certainly be required if STUBS is to be retained, as it will not be available in time for testing). A new contract might then be negotiated with the PSI for the required set of changes to the delivered Canberra system, including the Option C changes, porting to HP/UX 10 and possibly inclusion of new versions of Applixware and other COTS packages. These changes may be performed as a new fixed price or on time and materials.
4. By the time of such a contract, it will be more clear how option C will be implemented and risks (to the PSI) of delays to the rest of the schedule will be eliminated as a cost factor. Although a small amount of development and testing will have been performed unnecessarily, the overall cost is likely to be lower and the option of retrofitting STUBS or a similar device later will be retained ...
5. If the approach of delaying the change to the functional specification is adopted in the case of option C, then it becomes less urgent to make the basic decision as to whether or not to use STUBS. The Executive will probably be more comfortable making this decision when the firm intentions of Defence are known. This means that we should consider changing previous advice to Kim Jones that it is imperative to make a decision as soon as possible. The options open to the Executive would be:
(i) decide firmly on option A (STUBS) now, with deployment of 70 devices;
(ii) decide firmly on option A (STUBS) now, with deployment of 20 devices in the Comms centre and help desk only;
(iii) decide firmly on option C now;
(iv) delay the decision until Defence's intentions are firm, which will probably be September/October 1995. A decision at that time to use any of the above options should not be significantly more expensive than an immediate decision.
6. In the cases of options (i), (ii) and (iv) it is likely to be the end of 1996 before any STUBS devices are available; this will necessitate moving the IBM to York Park. In the case of option (iii) it is possible, but not certain, that this could be avoided."
1250 I would again note in passing that the submission made by BHP-IT is
that by the time of this minute the IT Executive had determined
to cancel STUBS
and replace it with Option C. The change of tactics only affected the timing
of that decision so as to place DFAT
in a position of advantage in subsequent
contractual negotiations with BHP-IT.
1251 On 22 June 1995 Les Cook sent what was in effect the "change of tactics"
proposal to Mr Jones and the other members of the IT
Executive. It was in a
minute entitled "ADCNET Gateway - Timing of Decision". I need refer to four
paragraphs of the minute because
BHP-IT and the Commonwealth have sought in
submissions to exploit different aspects of them:
"2. At the time of writing we still do not have a formal reply from Defence concerning firm intentions to purchase STUBS. Neither do we have formal advice concerning possible liability to AWADI should we not purchase STUBS. Defence have promised a reply this week. The ALD section has passed all the relevant papers to Attorney General's Department, which has not yet responded. These factors may make it difficult for the Executive to make a firm decision.
3. The ADCNET project team has re-examined the cost and schedule impacts likely to arise from a decision to adopt option C. We believe that the stage has now been reached at which it would be less costly to allow the PSI to complete work according to the current requirement specification and to perform the work necessary to implement option C following acceptance of the Canberra system, scheduled for February 1996. The main reason for this belief is that the PSI would take advantage of a significant change request at this late stage to attempt to recoup some of the delays which have occurred in their development to date; at the very least they will be very conservative in estimating the effects of a change and the cost of delays will be quoted in terms of the expense of the entire project team. Our currently strong contractual position on delays (including penalty payments) would be lost.
4. The effect on the overall schedule should also be reduced. This is because it is possible to perform the major parts of the cutover of the Canberra message switching function prior to the completion of option C changes (or receipt of STUBS). During this period, all communication with non-secure systems will remain via the IBM system. A side benefit of completing development of the original specification would be the ability to retrofit STUBS or a similar device into ADCNET at a later date should this be decided.
...
6. These considerations lead us to suggest that we have reached the point at which it is less urgent to make a final decision as to whether or not to use STUBS. An indication of the likely decision would be helpful, however, in determining the degree of DFAT effort to be expended in testing the STUBS interface software or defining the changes required for option C." Emphasis added.
1252 On the minute sent to Mr Jones, Les Cook made a notation that Mr Skinner had suggested that, if Kim Jones decided to request a decision from the Senior Executive on 26 June, he might wish a brief discussion of this minute first. Kim Jones in turn added the notation:
"This is a helpful suggestion but we should discuss somehow on Friday where to steer next. My preference would be to delay if that is not a problem, as we would then know more about STUBS."
Mr Jones had no recollection of discussing the minute with anyone on 22 June
or subsequently.
1253 I should interpolate at this point that there were a considerable number
of occasions in cross-examination in which it was made
plain that both Les Cook
and Mr Nichols had for at least several months held to the view that the best
approach for DFAT to adopt
was to drop STUBS and substitute Option C. They
both denied repeatedly, though, that a decision had been taken by the IT
Executive,
the SPC or the Senior Executive to that effect. They equally denied
they had received a "nod and a wink" to the effect that Option
C would be
adopted whatever the known availability of STUBS.
1254 On 22 June 1995 a meeting was held of the ADCNET Security Sub-Committee.
This body was chaired by Mr Allen (to whom the 22 June
"Timing of Decision"
minute had been sent). The minutes record Mr Allen asking Les Cook about "the
current state of STUBS". Les
Cook is recorded as saying that they were still
awaiting confirmation from DoD about their intentions and about how many they
planned
to order; that AWADI would not sign a contract with anyone; that DFAT
had not firmly decided to continue with STUBS and was examining
several
options; and that:
"ITB are about to advise the Executive that we have reached the stage of development of Release 3 where even if they decide to move away from STUBS we will complete the development of the software based on the current specification of the software which assumes the use of STUBS."
1255 The Senior Executive met on 26 June. The minutes of that meeting are
unyielding of reliable information of present relevance.
While there is
contradictory evidence from Mr Jones as to whether he took the 22 June minute
to the 26 June meeting, the proper
inference to be drawn in the circumstances
is it is probable it was mentioned at that meeting. I will return to this
matter when
I make my findings.
1256 In late June Mr Hender of AWADI was expressing to DoD his concern that he
would not be able to get board approval to continue
the development of STUBS
but he believed he could get it if he had some commitment from DoD as to
numbers and price, even if this
was to be subject to later endorsement.
Defence was unprepared to make this conditional commitment.
1257 Mr Noble of DoD informed DFAT on 3 July that it was putting forward a
capability submission (that encompassed STUBS) for formal
consideration in
September 1995. On the following day in a DoD internal memorandum Mr Hammond
recorded that DFAT was "maintaining
an interest in the [STUBS] proposal but is
not showing significant commitment. Informal advice indicates that they are
pursuing
a less functional solution." Mr Skinner responded to DoD's 3 July
letter on 6 July indicating that DFAT would delay its decision
on the purchase
of STUBS "until Defence's plans are firm and AWADI's terms and conditions are
known." He also indicated that BHP-IT
had been instructed to proceed with the
development of ADCNET on the basis that STUBS would be acquired.
1258 Sometime prior to this 6 July letter but after 22 June, the IT Executive
agreed to the proposal in Les Cook's 22 June minute.
Les Cook was away during
this period. Mr Skinner sent an undated email at least to Mr Cook and probably
to Mr Nichols. The email
stated:
"As mentioned to LC, [IT Executive] agreed with your suggestion that we proceed with R3 as if Stubs will be available and keep tabs on Awadi and DoD positions in the interim.
When R3 is available,
if Stubs is available then we have BHP add additional features that we want;
if STUBS is not available, we do above and add software gateways as well.
KJ would like you to informally keep DoD informed of our plans.
AS"
Les Cook annotated a hard copy of this email which he went to Mr Nichols. The annotation read:
"AS asks that you inform Defence of our intention to delay final decision on purchase of STUBS until Defence's plans and AWADI's Ts & Cs are firm."
I note in passing that this annotation is in almost identical terms to those
used by Mr Skinner in his 6 July 1995 letter to DoD.
It is Mr Nichols evidence
that he drafted that letter. Mr Skinner had no independent recollection of
it.
1259 Again I note in passing that it is BHP-IT's submission that DFAT had made
a decision to complete the R3 contract without STUBS.
It was not going to
perform its contractual obligations in accordance with the provisions of the
Head Contract.
1260 On 6 July the Attorney-General's Department provided the legal advice
sought of it concerning DFAT's possible liability if it
decided to cancel
negotiations with AWADI. It was advised that the risk was "very small".
1261 Before passing to the next phase in the evidence I should indicate that
there was significant cross-examination of Commonwealth
witnesses on the
meaning of the phrase "if STUBS is available". Illustrative of this was the
following cross-examination of Kim
Jones:
"Young QC: If you were to finish the R3 contract without STUBS part of that alternative was to leave the door open to use or not use STUBS at the other end f the R3 contract; do you agree with that?
Jones: Yes.
Q. So the final decision as to whether you use STUBS or some alternative is going to be addressed again on completion of the R3 contract?
A. If STUBS became available.
Q. If STUBS became available, right? What does `available' mean in your answer you just gave me?
A. It means available in time to be deployed after the software is implemented.
Q. Does it mean as well, available to be deployed in sufficient numbers to suit DFAT's purposes?
A. Well, yes, clearly it means more than one device being available, or something like that.
Q. Does it mean available to be deployed at a cost that is palatable to DFAT?
A. Yes. Well, clearly cost would inevitably be a factor within certain parameters.
Q. And your first element of your definition of available was `available in time to be deployed'; what does that mean?
A. It means being put in action in the ADCNET system when the Release 3 software was put into operation.
Q. But in terms of concrete dates what does that mean?
A. Well, that was uncertain at the time because the Release 3 contract was running behind schedule, as was STUBS.
Q. But, Mr Jones, you must have had in mind in your concept of `available' some time by which the deployment would have to be completed?
A. Well, that would - at that stage it was in time to enable us to move to the new building without taking the IBM with us.
Q. But if a decision about use of STUBS was delayed until completion of the R3 contract, that was never going to be an option, was it?
A. Depending on when the R3 contract was completed."
1262 I will refer to this further below when dealing with submission.
(iv) Communicating decisions to BHP-IT and GEC Marconi
1263 On 7 July there was a meeting of the ADCNET Acceptance Test Team. The
minutes of that meeting contains an item concerning issues
arising from the
lack of STUBS. It was there recorded:
"Status: PSI is still unaware of DFAT official position on STUBS. RN to provide PSI with advice in relation to the go ahead with the emulation of STUBS for testing. R Nichols to speak to L Cook regarding contract variations and will then advise."
Mr Nichols could not recall in evidence what he told BHP-IT at this
meeting.
1264 On 12 July a handwritten note of a project meeting between BHP-IT and GEC
Marconi recorded that, at a meeting held "last Friday"
(ie 7 July) with Mr
Skinner and Les Cook, they were informed that "PSI to go ahead on assumption
STUBS is available".
1265 Mr Cotton, who was then acting as Deputy Secretary in Kim Jones' absence,
distributed an "Administrative Circular" on 17 July
1995. This went to all
divisions, branches, posts and regional offices. The copy in evidence has a
handwritten annotation "Kyrill,
FYI, DMcG 21/7". The word "Kyrill"
has a line through it in the fashion of a cross - off. Mr Brent, I
should add, had no recall
of ever having seen the circular or of having crossed
off his name.
1266 The subject of the circular was "IT Security and Functionality
Trade-Offs". It referred to the SPC meeting of 26 April and
annexed the 21 May
version of the minutes of that meeting. It noted (inter alia) that (a) there
were some doubts about the availability
and affordability of STUBS; (b)
"Subsequent to the SPC, the Executive has agreed that ADCNET Release 3 development will proceed incorporating usage of the Stubs device with its high level of security assurance; the Executive has deferred a decision on the long term usage of Stubs until the availability and affordability of Stubs becomes clearer later this year";
and (c) if there was "a decision not to use STUBS", software gateways would
have to be incorporated after the acceptance of R3 from
the developer.
1267 On 21 July a prototype of STUBS was demonstrated. Mr Nichols attended
that demonstration with DoD officials. A contemporary
note of his indicated he
asked if DFAT could "acquire [from AWADI] the `untrusted software' and any
STUBS simulation software which
may have been developed". He also recorded
that "the performance of STUBS was generally good" and that "AWADI now see DFAT
as being
a minor customer".
1268 On the same day a meeting was held between DoD and AWADI officials ("the
STUBS Advisory Board"). The minutes (para 4.2) noted
a further program
slippage of five months and that prototypes would be available by mid-1996.
Under the heading "AWADI's view of
the Future" it was indicated that if AWADI
did not receive a contract from Defence then the board was likely to cancel the
project.
1269 An internal AWADI Project Status Report prepared in early July stated
(inter alia): "DFAT contract has not been progressed;
awaiting agreeable
resolution of ADF situation [the reference to the ADF was for a contract with
DoD for 343 devices]; ... Draft
contract has not been agreed or accepted by
AWADI".
1270 It is clear that, both from rumour and from notes of a meeting of the
ADCNET Acceptance Test Team, the expectation was being
entertained in the
project team that "STUBS is now a goer", but that DFAT's official position was
to be provided to BHP-IT. DFAT
wrote to BHP-IT on 25 July 1995. This letter
is set out in Part II: Emulation Variation Agreement (a)(i). It raised the
issue of a Change Request to allow emulation to be used for acceptance testing.
It referred to it not being "possible to provide sufficient STUBS devices
to meet the requirements of the Acceptance Test Plan": emphasis added.
When taxed in cross-examination with this comment Mr Cook
said: "Zero is an
insufficiency. I'm not sure why I phrased it that way".
1271 The 10 August 1995 letter from Les Cook to Mr Brent dealing with the
subject of schedule extension contained references to STUBS.
Referring to the
use of emulation for acceptance testing it indicated that "any defect in the
PSI's Developed Software which may
be encountered when STUBS is implemented
will be remedied under the warranty for the Developed Software".
1272 It is unnecessary to repeat here the later correspondence prior to the
announcement in September that STUBS had been cancelled
which related to
emulation of STUBS, other than to reiterate (i) that it was STUBS that was
being emulated; but (ii) that the contracted
date for the delivery of STUBS
(ie 1 August 1995) had passed.
1273 Reference has been made above to DoD finalising a major capability
submission ("MCS") for formal consideration in September.
An August draft of
that submission noted (inter alia) that recent advice indicated that DFAT
considered STUBS to be too expensive
and was pursuing alternative options. A
DoD meeting was held on 29 August to consider issues raised and to ratify the
approach taken
in the draft submission prior to formal consideration of it in
September. Notes of that meeting are in evidence and include the
following:
". After discussion, option generally supported (FDA quiet) to pay AWADI for IP (seen as appeasement) on the grounds that Defence would be hard put to defend against a charge that AWADI was justified in believing a contract was forthcoming. DFAT viewed bitterly as more culpable - had continually promised contract.
. MCS to be modified (due with FDA 31 Aug!) to the above effect - no Stubs purchase.
...
. [First Assistant Secretary Defence Material] asked for guidance - what to tell AWADI? Agreed by [Vice Chief of the Defence Force] that words should be `unlikely that [September committee] will support acquisition of Stubs.' [Has since told them - AWADI in shock!]"
1274 In its submissions the Commonwealth made lengthy reference to ensuing correspondence between AWADI and DoD and internal minutes of AWADI. That correspondence dealt, initially, with the foreshadowed purchase or licensing by DoD of AWADI's intellectual property for STUBS and the approximate cost and delivery availability of working STUBS prototypes that were available or which could be made available without substantial additional work. Attention within AWADI turned to the future of the STUBS development in light of DoD's interest in acquiring the STUBS prototypes. On 11 September 1995 a proposal was raised by AWADI's Managing Director to develop the prototypes to full functionality but without accreditation. In that context it was stated:
"We need to make DFAT aware of the current situation and get feedback on their likely future STUBS plans (if any), either in isolation or in conjunction with limited DOD procurement."
On 12 September Mr Noble of DoD informed Mr Nichols of Defence's decision not to proceed with STUBS. Mr Nichols sent a note of that meeting, as also of a phone call he made to AWADI on the following day, to Les Cook. Insofar as presently relevant that note stated:
"2. Defence are now negotiating with AWADI for the purchase of the STUBS Intellectual Property Rights and prototypes. This will mean that AWADI will effectively be paid for their development effort to date.
...
4. On 13/9/95 I contacted Mark Hender of AWADI (General Manager, Business Operations and Planning) who confirmed that Defence will not proceed with STUBS. AWADI will now not proceed with:
(a) unfinished development work (estimated at $0.5M)
(b) the acquisition and installation of cryptos into the devices
(c) the independent evaluation of STUBS (estimated at $0.6M)
5. AWADI may be willing to manufacture 50 units for DFAT provided that the additional cost (estimated at more than $1.1M) is amortised over the purchase price of STUBS. This would raise the price of a STUBS sealer to an estimated $50K. AWADI has agreed to advise DFAT of indicative new pricing."
1275 An AWADI memorandum recounting the latter conversation referred to the
price of "$50K per unit" and said "I think this shows
that we are unlikely to
get an order from DFAT unless we also get an order for at least 50 units from
Defence".
1276 At a 13 September meeting between Mr Hender of AWADI and Mr Noble of
Defence AWADI's proposal was raised. Whatever expectations
may have been
generated there an AWADI memorandum of the following day from its managing
director, entitled "STUBS Closedown Plan"
indicated that:
"Unfortunately, the latest message from Jim Noble to Mark Hender contradicts his earlier indications, and his direction to us is to minimise further expenditure on STUBS.
In preparation for the meeting with Defence on STUBS next Thursday 21 September, would you please take the following actions:
1. Assume a closedown date for the STUBS project of 30 September 1995.
4. Instruct Nick Davias to initiate no new work, and to restrict existing activities to completion of logical sub-tasks.
5. Prepare a plan for recording and parcelling up the hardware and software for provision to Defence as soon as formal agreement on compensation is reached."
1277 Negotiations ensued for the licensing of STUBS intellectual property
and for the delivery of prototypes etc to DoD.
1278 On 13 or 14 September 1995, Les Cook announced to Kyrill Brent and Roger
Cook that STUBS had been cancelled. I will refer below
to the evidence on that
matter as also on the meeting of 15 September 1995.
1279 There was a meeting of the ADCNET Security Sub-Committee on 22 September
1995. The minutes record the following:
"Availability of STUBS
Mr Allen suggested that this topic could be dealt with very quickly. Mr Cook said that there was unofficial word from DoD that they would not buy STUBS. We have asked AWADI to provide DFAT with a letter that they no longer wish to supply STUBS to us."
1280 In answer to a question of mine Mr Cook said he thought the last
sentence referred to the request by Mr Jones to check whether
AWADI believed
that DFAT had any obligation to it. Such a letter was in fact provided by
AWADI on 17 October 1995 (see below).
It was suggested to Mr Cook in
cross-examination that the above minuted request was a quite different matter
and was sought to fit
with the explanation BHP-IT alleges he had given to Mr
Brent concerning the cancellation of STUBS (ie it was cancelled by AWADI).
Les
Cook insisted there was only one request made.
1281 Mr Nichols, who was the person who actually made the request of AWADI,
said in re-examination in evidence I accept that the
request was made at the
behest of Mr Jones at a meeting shortly after 13 September. Mr Jones gave
evidence after he became aware
DoD had decided not to proceed that he requested
Mr Nichols to contact AWADI to see whether it would give written confirmation
that
DFAT had no obligation to it in relation to STUBS.
1282 The 17 October 1995 letter was in the following terms:
"I refer to your telephone call concerning your Department's legal obligation to proceed with the subject contract.
AWA Defence Industries hereby advises that we do not consider the DFAT are under any legal obligation to continue negotiations on the subject contract. Both parties participated in negotiating the draft contract in good faith, however no agreement was reached in relation to the subject document. Your response of 19 Dec 94 to our suggested options (dated 6/12/94 ref A9/512/1) to resolve the way forward indicated we were only able to agree on the purchase of the Untrusted Software. AWADI is therefore of the opinion that DFAT are under no legal obligation to proceed with finalising the subject order.
We appreciate your efforts in attempting to resolve the outstanding issues. It is unfortunate that the DoD has decided not to support the development of STUBS. However, AWADI can not support the development unaided. We appreciate your business and look forward to being able to provide solutions for any future needs you may have."
1283 Mr Brent indicated to Mr Cook by letter of 25 September in the context of extension to the contract schedule that BHP-IT had not received "any formal notification of the demise of the STUBS program". That notification was provided by Mr Cook's 26 September letter, the opening sentence of which was that:
"I confirm my informal advice to you of 15 September 1995 that AWADI will not continue with the development and supply of the STUBS security devices."
1284 Finally the meetings of 13, 14 and 15 September. I should state at the
outset that on the material before me the precise detail
of how many meetings
there were, who attended them, and what actually was said at them, remains
elusive. It is clear that it was
communicated to Mr Brent and Roger Cooke that
STUBS had been cancelled and that an alternative strategy was outlined. The
best evidence
I have on the matter is contained in a memorandum of Roger Cooke
of 15 September 1995. It does not record Les Cook attributing the
cancellation
to AWADI.
1285 In cross-examination Roger Cooke conceded, quite properly in my view, that
he could not recall accurately whether Les Cook simply
said STUBS was
cancelled, or whether he explained more fully that AWADI had cancelled STUBS.
Mr Brent's evidence was that the cancellation
was attributed to AWADI though
accepted in cross-examination that he could be wrong on this - as he
demonstrably was on other matters
relating to the meetings. Les Cook's
recollection of the meetings could not descend to detail. He accepted in
cross-examination
that he could have said something like AWADI had cancelled
STUBS and therefore DFAT could no longer supply it.
1286 I should note that Mr Cotton was absent from Australia from 9 to 26
September 1995. The only evidence given by Kim Jones concerning
events in
September related to his request of Mr Nichols to get a letter from AWADI after
he had been advised that DoD had decided
not to proceed with STUBS and that
AWADI "had decided it would no longer continue with the STUB devices project".
And no particular
evidence was sought from Mr Skinner about events in September
1995. No witnesses were called from AWADI.
1. THE CONTRACT CLAIM
1287 I intend to refer here only to those claims made for breaches other than
those arising from the non-provision of STUBS and the
non-payment of Milestone
4000.
(a) Relevant contractual provisions
1288 Clause 5.1 of the Head Contract required the Commonwealth to take all
reasonable measures to maintain the processing environment
as constituted by
the elements of the CSI.
1289 Clause 5.4 required the Commonwealth to manage the project risks that were
identified as its responsibility under the Contract.
A variety of provisions
in the Head Contract and its Schedules, as has been seen, made the provision of
STUBS the Commonwealth's
responsibility.
1290 Clause 5.6(a) - which is said to be a specific manifestation of the duty
of good faith and fair dealing - provided:
"Except where otherwise provided in the Contract the Customer, ... agree[s] that in the exercise of any obligation, function or power imposed or conferred on them under this Contract they will:
(a) act in a fair and reasonable manner."
Clause 10.3 provided:
"Where a Party identifies a risk which may have a significant effect on the implementation of the Implementation Plan that Party shall immediately report the identified risk to the other Party and the Party responsible under this Contract for managing the identified risk shall inform the other Party of how it will manage that risk and shall forthwith undertake management of that risk."
BHP-IT contends that, in light of these provisions, the Commonwealth was
subject to at least the following obligations:
(1) in circumstances where at the time it executed the Head Contract the
Commonwealth had not entered into any contract with AWADI
to enable it to
supply STUBS to BHP-IT as CSI, an obligation to keep BHP-IT fully and
accurately informed:
(a) as to its progress in negotiating such a contract;
(b) as to any matters which may present obstacles to the execution of a
contract between AWADI and the Commonwealth and which therefore
may have given
rise to a risk that the Commonwealth may be unable or unwilling to adhere to
its obligations to supply STUBS to BHP-IT
in accordance with its obligations
under the Head Contract;
(c) as to any change in the Commonwealth's intentions concerning the supply
of STUBS to BHP-IT for the purposes of performing the
ADCNET contract.
(2) in the event it became necessary or desirable for the Commonwealth to
negotiate an amendment to the Head Contract to relieve
it from its obligations
in relation to STUBS, an obligation to act fairly and reasonably towards BHP-IT
in the carrying out of its
obligations under the Head Contract, so that BHP-IT
was fully and accurately informed of all material matters so that such
amendment
could be negotiated fairly, at arms length and in a way which would
not later disadvantage, or operate unfairly or unjustly against,
BHP-IT.
(3) to carry out its responsibilities and duties under the Head Contract and
to act toward BHP-IT, fairly, reasonably, and in good
faith.
1291 The alleged breaches of these obligations resulted from the view BHP-IT
invites me to take of what are said to be the improper
decisions and actions
taken, and the misrepresentations and non-disclosures made, during the period
covered in the Factual Setting
above. It is for this reason, as I earlier
foreshadowed, there are hundreds of pages of submissions advancing rival
interpretations
of the events, etc, I have narrated.
(b) Factual findings
1292 My own findings on what are said to be key decisions and actions can be
stated relatively shortly. By way of preliminary comment,
I should indicate
that the level of confidence one can have about the accuracy, veracity, or
contemporary significance of statements
made in documents that have been put in
issue is obviously affected by a number of phenomena. The first is that there
clearly was
a significant degree of personal interaction between personnel of
the three principal parties to this proceeding. They were located
in the same
building; they met regularly; there were obvious professional bonds between
some of them; and their relationship had,
at least amongst some of the more
significant actors - Les Cook, Roger Cooke and Kyrill Brent - extended over
some number of years.
Though documents are the bricks and mortar of this
proceeding, they obviously reflected only a part of the communications between
the parties. And they were only one source of their contemporary
understandings. Further, the correspondence between the parties
reflected, on
occasion, requests for, or the making of, formal communications in respect of
matters already known or else prompted
by prior discussion. The Commonwealth,
in particular, has emphasised the importance that should be attributed to this
informal process
of communication.
1293 What was true of communications between the parties was also evident but
to a much more uncertain degree in communications with
third parties and, in
particular, between DFAT, DoD and AWADI. There is a number of DoD documents,
for example, that refer to "informal
advice" etc about DFAT's intentions.
1294 The difficulties the above phenomenon raised in this proceeding are
compounded by the almost total lack of ordered recall by
key actors of much
that transpired in the period of present concern. While, for example, there
may well have been a simple explanation
for an apparent inconsistency between
two documents - eg additional oral advice or information was acquired before
the latter of
the two was composed - the evidence in this proceeding usually
goes no further than establishing the inconsistency itself. The concern
for me
in this is that in some instances in this proceeding that inconsistency is used
to attack credit particularly in relation
to Les Cook.
1295 I turn to three matters which are, in my view, of general significance to
my findings. The first is that both Les Cook and
Mr Nichols were champions of
Option C and they did not disavow this. From shortly after the entry into the
ADCNET contracts, they
came to the view that the better outcome for DFAT was
that STUBS be abandoned in favour of Option C. Given the opportunity so to
do
by Mr Cotton's 17 January 1995 request for a paper on "fall back options", Les
Cook was enabled to publicise his views in the
papers on alternative strategies
he was asked to or did prepare.
1296 I am satisfied that in the various papers he wrote he was acting in what
he considered were the best interests of the Department.
I imply no
professional criticism in saying that some significant degree of advocacy is
discernible in some of them. I will return
below to the criticism made of him
that he used information manipulatively to achieve his ends.
1297 This brings me to the second general point I wish to make. Les Cook was
not a strategic decision-maker in DFAT. He was a consultant.
While he
obviously took decisions at the implementation level of the ADCNET contracts,
the decisions such as whether STUBS should
be adopted or should be abandoned in
favour of Option C were not decisions he - or for that matter Mr Skinner -
could take and he
was aware of this. At best he could influence
decision-making, which he did decisively, for example, in relation to the
"change
of tactics" decision of the IT Executive.
1298 I am satisfied that it was understood at the time that if a decision was
to be taken to abandon STUBS in favour of Option B
or C, that decision would
ultimately be taken by the Senior Executive after recommendation from the IT
Executive and the SPC. An
important actor in that decision making, as I will
indicate, was Kim Jones.
1299 The significance of the Senior Executive being the organ that was to
decide whether to adopt an alternative is twofold. First,
it alone represented
the Commonwealth for the purposes of that decision. But, secondly, that
decision apart, it was not the only
organ of the Department whose actions could
put the Commonwealth in breach of its contract with BHP-IT. I emphasise this
because
I am satisfied that the Senior Executive did not formally, or
informally (ie "by a nod and a wink"), resolve to abandon STUBS in
favour of
Option C. For this reason the actions of others within DFAT are what are
relevant for the purposes of determining whether
it committed breaches of
contract in the manner in which it performed the Head Contract up until the
cancellation of STUBS and the
entry into the CR3049 Emulation Variation
Agreement.
1300 The third general point I need make is to re-emphasise something I
mentioned earlier in this Part. I am satisfied that the
principal matter of
concern for all relevant DFAT officers in 1995 was the ADCNET project
and not the ADCNET contracts. Mr Skinner, for example, agreed with my
proposition that, so far as he was concerned, his fundamental responsibility
was to administer
the ADCNET project and it happened to be that the contract
was within it. Mr Nichols agreed that he differentiated between the project
and the contract so that he differentiated decisions or action he was taking in
relation to DFAT's overall needs (and that applied
to what the Department
required in the longer term), from those he took in relation to progressing the
BHP-IT contract. He did not
think that the two were "that tightly intertwined"
or that he had "an obligation to advise BHP-IT as to the Department's long-term
plans with respect to STUBS, or any other gateway the Department may wish to
use". For his part Les Cook saw his "major role as being one relating to the
technical work being done and managing the interface to BHP, but not really
being managing the contract". It was for other people within DFAT to be more
concerned with the contract. Kim Jones, again in response
to a question of
mine, accepted that he had no useful knowledge of the contents of the ADCNET
contract; he was unaware of the obligation
in relation to the delivery of
STUBS; and that he was not really aware of any of the contractual
obligations.
1301 I will comment further on contract management later in these reasons. For
present purposes I should indicate that I consider
that the attitude to the
contract displayed by DFAT officials helps explain their greater concern for
what was to be the system they
were going to get, than with the system they had
contracted with BHP-IT to integrate and which required the purchase of STUBS
from
AWADI.
1302 Turning to the evidence I should indicate I do not intend to deal with
each and every submission made on a document by document
basis. Rather I will
state findings in the form of conclusions in light of those submissions.
1303 First, some matters have been put in issue on which the evidence is clear
and requires the following findings.
1304 1. Though Les Cook indicated in March 1993 that he estimated the number of
STUBS devices required would be 1000, that estimate
had been reduced
dramatically prior to the execution of the ADCNET contracts. I am satisfied
that BHP-IT had some appreciation that
there had been a reduction, though I do
not consider that the evidence justifies a finding on my part that prior to the
execution
of the ADCNET contract it had precise knowledge of the number which
DFAT then contemplated purchasing. I am satisfied, though, that
for reasons
given in the next paragraph in relation to deployment only in Canberra, BHP-IT
could not reasonably have expected that
that number would be large.
1305 2. It had been decided well before September 1994 that the STUBS devices
would not be used at overseas posts. It is probable
that that decision was
taken for reasons of cost and that of itself reduced significantly the possible
number of STUBS devices DFAT
would need to acquire. This decision was
reflected in the relevant FRS requirements.
1306 3. Prior to the execution of the ADCNET contracts the parties were
addressing the issues of whether AWADI would be able to provide
STUBS devices
at all, or (production devices) on time. By February of 1995, BHP-IT and GEC
Marconi were informed by Les Cook that
STUBS might never be available; that he
was "considering other options" and would keep them "informally advised and
raise CR's for
any work to build emulators or (worst case) rework of security
policy": Mr Wishart's 20 February 1995 report. Discussions about
the
availability of STUBS (late or at all) were recurrent in project management
meetings prior to mid-June: Mr Brent's 18 May 1995
letter; and the status of
STUBS had been a standard subject item for those meetings since 29 March
1995.
1307 4. By mid-May 1995 BHP-IT was aware that there were meetings to be held
involving discussions between AWADI, DFAT and DoD about
STUBS which could lead
to the STUBS program being "cancelled within AWA": Mr Brent's 15 May email and
18 May letter. By mid-June
1995 Mr Brent had been informed that DFAT was
itself considering whether to proceed with STUBS or to return to an approach in
which
the PSI implemented boundary security and that DFAT might decide that
"STUBS [was] not practical or economic": Les Cook's 2 June
and 6 June 1995
letters.
1308 5. I am in consequence satisfied that BHP-IT had been made aware by
mid-June 1995 (and probably much earlier) that either AWADI
or DFAT might
decide not to proceed with STUBS and that the Commonwealth still did not have a
contract with AWADI. I deal further
with this matter below as bears on the
expectation BHP-IT could reasonably have entertained of a cancellation by
DFAT.
1309 By way of comment, in circumstances in which there was no contract with
AWADI and in which price per unit was escalating ($34,000
in May: Nichol's 17
May minute; circa $42,000 in June: AWADI letter of 5 June), it is
unsurprising that DFAT had flagged at least
possible cancellation by it on
affordability grounds. STUBS was CSI and the ADCNET contracts envisaged the
possibility of changes
to CSI.
1310 A central part of BHP-IT's case is that in late June or early July the
Senior Executive endorsed the IT Executive's "change
of tactics" decision and
that the IT Executive then put that decision into effect. The evidence, it is
alleged, demonstrated that
in early June 1995 and prior to the "change of
tactics" decision, the IT Executive had determined to cancel STUBS and to
replace
it with Option C but between 17 and 22 June it decided to adopt the
change of tactics for the reason given by Les Cook, ie so that
DFAT would not
lose its strong contractual position in relation to contract negotiations.
1311 I am then asked to find (i) that on 22 or 23 June 1995, the IT Executive
resolved to recommend to DFAT Senior Executive on 26
June, 1995, that:
(a) for practical reasons associated with the maintenance of DFAT's strong
contractual position vis-à-vis BHP-IT, it was preferable
for the Senior
Executive to defer a final decision to replace STUBS with Option C until after
the completion of the Release 3 Head
Contract, or, alternatively until after
Defence had made a formal decision whether or not to purchase STUBS from
AWADI;
(b) in the meantime, no steps would be taken to commit to the purchase of STUBS
for the purposes of the Head Contract, regardless
of the provisions of the Head
Contract;
(c) BHP-IT should be told to proceed with completion of the ADCNET contract on
the basis that STUBS would be supplied, albeit late,
and should be held to
delivering under the current timetable and to the current functionality
specified in the Head Contract;
(d) the Senior Executive informally communicate to the IT Executive its
intention to endorse Option C (or a derivative thereof) as
the security device
for use in conjunction with the ADCNET software, in preference to STUBS, so
that future DFAT time and effort
could be allocated appropriately.
(ii) that on 26 June 1995, (or possibly at a meeting of the Senior Executive
held between 26 June and 17 July) the Senior Executive
was informed of the
matters referred to in the preceding sub-paragraph and endorsed the approach
therein set out; and (iii) that
on 5 July 1995, and following the 26 June
meeting of the Senior Executive, the IT Executive resolved to implement the
decision of
the Senior Executive by:
(a) proceeding with completion of the Head Contract without STUBS but as if
STUBS were available (ie would be supplied to BHP-IT);
(b) telling BHP-IT that the DFAT intended to use STUBS and that STUBS was
coming;
(c) keeping tabs on AWADI and Defence in the interim.
1312 For my own part I do not consider that the evidence quite accords with
BHP-IT's contention. I make the following findings.
1313 (a) Prior to the "change of tactics" decision in late June/early July
1995, neither the Senior Executive nor the SPC had determined
that Option C be
adopted irrespective of whether STUBS would be available. The SPC had taken up
the issue of "the security-functionality
trade off" at its special meeting of
26 April 1995. While expressing the view that, if STUBS was available, it
probably should be
persevered with, the SPC confirmed that DFAT would
nonetheless need to determine whether STUBS should be used given the arguments
for and against security assurance and user functionality. The 25 May SPC
meeting did not materially change the 26 April "decision".
It was noted though
that the time frame for building an alternative to STUBS into ADCNET had passed
and that the design of STUBS
had gone too far to abandon the project. I do not
think that particular significance can be attributed to either of these two
matters
but particularly the first. It is not clear whether what was being
referred to was that it was too late to build in an alternative
during the
currency of the ADCNET contract, or, in contrast, for the ADCNET project
itself. The former seems the more likely. The
19 June Senior Executive
meeting which discussed (inter alia) matters raised in the minutes of the SPC
26 April meeting simply noted
the matters on which decision would be required
in the near future.
1314 (b) The IT Executive's function in relation to the abandonment of STUBS
from 6 June 1995 was, like the SPC's, that of making
recommendations. Until
the change of tactics was endorsed it was probably moving towards recommending
STUBS be abandoned. I am
not satisfied that it ever formally reached or was
required to reach, that position. Its evolving view was overtaken by the
change
of tactics proposal.
1315 (c) There were two other significant events in early June. They were (i)
the DSD advice that STUBS be used if it was available
and it was practical to
deploy it in sufficient numbers, and (ii) Mr Jones' request for legal advice on
the Commonwealth's possible
liability to AWADI.
1316 (d) The 22 June change of tactics proposal to the IT Executive was not a
happily crafted document. I am not satisfied that
it evidenced a proposed
decision by the IT Executive that STUBS be abandoned in favour of Option C.
The requested legal advice from
the Attorney-General's Department had not been
obtained and DoD's intentions in relation to the purchase of STUBS had not been
formally
provided to DFAT. While the proposal was cast in the form of four
options, its intention was to secure the deferral of any decision
until
September when Defence's intentions were "firm".
1317 (e) The change of tactics proposal sought an "indication [from the Senior
Executive] of the likely decision [as it] would be
helpful ... in determining
the degree of DFAT effort to be expended in testing the STUBS interface
software or defining the changes
required for option C". If this was to be
understood as soliciting an informal communication of an intention to endorse
Option C,
I am not satisfied that such a communication was made by the Senior
Executive.
1318 (f) I have already indicated that I infer Mr Jones mentioned the change of
tactics proposal at the Senior Executive meeting
on 26 June. Whether or not
the Senior Executive took a decision in light of the proposal at that meeting
is not a matter upon which
a positive finding can be made. What is clear is
that at some time between 26 June and when the Administrative Circular was
issued
on 17 July 1995, the Senior Executive acted consistently with the
proposal to the extent at least of deferring "a decision on the
long term usage
of Stubs until the availability and affordability becomes clearer later this
year": the 17 July Administrative Circular.
Mr Cotton, while having no clear
recollection of any Senior Executive meeting where the proposal was acted upon,
gave evidence as
to his state of mind at the time that was consistent with such
a deferral decision being made.
1319 (g) I consider it improbable that a positive decision was taken, even on
an informal basis, to adopt Option C whether or not
STUBS was available. The
change of tactics proposal itself and the tenor of the DSD advice (on the
premise that STUBS was available)
were both calculated to induce deferring a
decision cancelling STUBS from the ADCNET project until September when
DoD's intentions were known. (I will return below to why I have emphasised
"project" and not "contract" here.)
The lack of formal legal advice until 6
July 1995 on possible liability to AWADI is another influence which I consider
would have
been likely to have induced real caution in taking a cancellation
decision prior to that date. I equally am satisfied that actions
taken by, and
inter - and infra - departmental communications made by, DFAT officials
subsequent to 17 July 1995 are inconsistent
with a cancellation decision having
been taken: eg Mr Nichols 21 July exploration of the purchase of AWADI
prototypes; and the
18 July ADCNET Security Sub-Committee meeting. I find,
then, that in late June/early July no decision was either taken or was
foreshadowed
(i) that STUBS was to be cancelled; or (ii) that Option C would
be adopted in any event. The decision taken was the deferral of
a decision
either to approve or to cancel STUBS from the project. That decision had a
number of practical consequences. The first
was that there was no possibility
of STUBS devices (or even prototypes) being available for delivery on 1 August
1995 as required
by the contracts. The second was that it created a positive
incentive not to commit to a procurement contract with AWADI until DoD's
intentions were known even if the opportunity to do so was there. Mr Skinner's
6 July letter to DoD reflected this. Thirdly, it
allowed for the possibility
of STUBS being either implemented during the ADCNET contracts (depending on
both schedule extensions
and STUBS availability) or retrofitted after
acceptance testing, if it actually became available.
1320 Insofar as the immediate performance of the contracts was concerned, the
course endorsed by the IT Executive and taken by DFAT
vis-à-vis BHP-IT
was to proceed with the ADCNET contract "as if" STUBS would be available. In
so doing it pursued a course
of conduct that kept BHP-IT uninformed of what
DFAT's actual intentions were in relation to the procurement of STUBS from
early July
until STUBS was cancelled on 13-15 September.
1321 This brings me to the second major factual matter in the contract claim.
It relates to how DFAT conducted itself in the performance
of the ADCNET
contract in relation to its obligation to provide STUBS. The background fact
is that the Commonwealth did not meet
any of its contractual obligations in
relation to STUBS CSI either on time or, save for the STUBS SIS, at all.
1322 Turning first to the period from the execution of the ADCNET contracts
until the "change of tactics" decision, I have already
found that (i) DFAT had
made the parties aware from early in the life of the contracts that there was
an issue as to whether AWADI
would be able to supply STUBS on time or at all;
and (ii) by mid-June, BHP-IT had been informed that AWADI or DFAT might
decide not to proceed with STUBS and affordability was a possible reason for
DFAT so doing. I would add to this that,
as the minutes of the Project
Management Committee meeting of 29 March 1995 record, the status of STUBS was
considered to require
"constant monitoring" and was made a "standard subject
item" at future meetings. That this in fact occurred is reflected in the
opening observations of Mr Brent's 18 May 1995 letter.
1323 Notwithstanding the disclosure I have found was so made, BHP-IT has
alleged that from January 1995 DFAT was not, in its negotiations
with AWADI,
taking any real steps to conclude a contract for the supply of STUBS. Insofar
as this allegation relies upon DFAT having
acted in late November-early
December in a way that created an impasse in negotiations (arising in
particular from its demands in
relation to risk allocation for E5 accreditation
and late accreditation), the alleged state of affairs is not borne out by the
evidence.
AWADI's own appreciation of the state of negotiations on 18 January
1995 was that the "ball [was] firmly in [its] court", and that
it had to
"finalise the prices to be offered". Those prices were not supplied until 5
June 1995 although indicative prices were
supplied to DFAT on 10 May at a
meeting involving AWADI, DFAT and DoD.
1324 It may be said that DFAT was not solicitous in attempting to extract a
pricing response from AWADI. It cannot be said that
it had, in reality, ceased
to negotiate from December 1994 - though doubtless the IT Branch was not
displeased at the rate at which
AWADI was proceeding. However, after the
change of tactics decision a quite different state of affairs obtained. AWADI
had by then
provided its price schedule to DFAT but, as I have found, DFAT had
now determined not to commit itself to the purchase of STUBS until
DoD's plans
were firm and AWADI's terms and conditions were known. The former of these
contingencies was not expected to occur until
September 1995.
1325 From early in the ADCNET contracts the use of emulation for acceptance
testing of the R3 software had been raised. The change
of tactics decision, as
implemented by DFAT, necessitated the formalisation of emulation as part of the
ADCNET contractual arrangements.
I am satisfied that this was done by DFAT in
a way calculated to create the impression that for its part DFAT intended to
use STUBS in the ADCNET project. I equally am satisfied that when
presented with opportunities to reveal DFAT's actual intentions in relation to
the STUBS procurement
(ie deferral of any decision), DFAT officers avoided
doing so.
1326 The minutes of the ADCNET Acceptance Test Status meeting of 7 July
recorded that "PSI is still unaware of DFAT official position
on STUBS. [Mr
Nichols] to provide PSI with advice in relation to the go ahead with the
emulation of STUBS for testing". The latter
advice was given on or before 12
July, BHP-IT having been instructed to go ahead "on [the] assumption STUBS is
available": note
of BHP-IT/GEC Marconi meeting of 12 July 1995. The 24 July
minutes of the Acceptance Test Status meeting note that DFAT still had
not
indicated its official position on STUBS.
1327 Contemporary notes, or communications, made by GEC employees provide
reliable indications of what was being communicated unofficially
by Mr Nichols.
An email from Mr Cartwright to Mr Harris of 25 July 1995 reporting on the 24
July meeting (above) stated: "The issue
regarding the STUBS device is
apparently resolved and the device itself will be used". Mr Wishart, who was
not an attendee at the
24 July meeting, reported to his project management team
on 24 July that "rumour from R [Nichols] that STUBS is now a goer". It
will be
recalled that on 21 July 1995 Mr Nichols saw the demonstration of the STUBS
prototype.
1328 Mr Nichols had no actual recollection of what he said at the 24 July
Acceptance Test Status meeting but he denied that at that
time he would have
said that it was DFAT's intention to use STUBS devices in the ADCNET project.
I do not accept this disavowal.
I accept that statements of the type
attributed by Mr Cartwright and Mr Wishart to Mr Nichols were made by him.
1329 The minutes of the 31 July 1995 Acceptance Test Status meeting note that
DFAT's official position had by then been given, though
the minutes do not
describe it. I am satisfied that Les Cook's letter to Mr Brent of 25 July 1995
under the heading "Supply of Stubs
Devices for Acceptance Tests" was, and was
intended to be, DFAT's communication of that official position on STUBS.
1330 In advising in that letter that emulation was to be used for acceptance
testing and a change request would be raised accordingly,
Les Cook clearly
conveyed that it was only because it was "not possible to provide sufficient
STUB devices" that emulation was necessary.
This was a colourable
representation and he must have appreciated that at the time. It suggested
that the Commonwealth had affirmed
its intention at that time to acquire STUBS
and would have reasonably been so understood by BHP-IT. I do not consider the
representations
so conveyed were undercut by the 17 July Administrative
Circular which was provided to Mr Brent. Whatever Mr Brent derived (if
anything)
from that general communication, this letter was a direct
communication to him as project manager from DFAT's project manager. It
was
the awaited statement of "official position". And it confirmed what was being
said unofficially at the time.
1331 There was no documentary communication to BHP-IT thereafter until the 26
September letter that qualified or negatived the representations
made in this
letter. The formal communications made on schedule extension and on emulation
on 10 and 24 August 1995 are quite consistent
with the continuation of the
representations I have noted.
1332 Mr Skinner gave the following oral evidence - not reflected in any
contemporary document notwithstanding its contractual significance
- of
meetings with BHP-IT personnel (Mr Brent and Mr Dean) between July and
September 1995:
"A. I recall clearly advising BHP that the Department was taking the best steps it could to ensure that it met its contractual requirements, but that in relation to the STUBS deliverables we were dependent upon entering into a contract with AWADI which, in turn, was dependent upon Defence making a decision about whether it would proceed with STUBS.
We had been pushing Defence for a decision for some time, as had AWADI and Defence had promised us that they would be making a decision at some point in time and that date had changed a little - August, September, October."
1333 I have already indicated my view of the reliability of Mr Skinner's
evidence generally. I consider the above wholly unreliable.
I agree with
BHP-IT's submission that the clarity of recall here is in complete contrast
with his evidence generally. While I acquit
him of being deliberately
untruthful, I regard this evidence as an invention.
1334 Finally, the cancellation of STUBS. I should state that the evidence is
remarkably slender on DFAT's decision-making on this
matter after DoD's
indication it would not be proceeding with a STUBS procurement. I accept that
Kim Jones was not involved in any
decision to cancel in September and that he
had been advised (inter alia) that AWADI had decided to cancel STUBS. I also
accept
that the letter he directed Mr Nichols to obtain from AWADI that DFAT
had no legal obligation to it was the only letter sought from
AWADI at that
time. I consider no weight should be given to the minute of the ADCNET
Security Sub-Committee of 22 September 1995
which might in its language suggest
that a further letter was sought.
1335 I have already noted that Mr Cotton was overseas at all relevant times in
September. Whatever was the decision that was made
within DFAT, it was made by
persons in the IT Branch. The Commonwealth has not sought to demonstrate the
contrary. I should add
I do not accept the suggestion in Mr Cook's evidence in
cross-examination that the decision to cancel was taken at an IT Executive
meeting held sometime shortly prior to the 26 September letter, that decision
being that the Department had no choice after DoD's
decision not to proceed.
Mr Cook later conceded he had no clear recollection of this meeting and its
occurrence is not otherwise
supported by documentary evidence.
1336 I am satisfied that Mr Skinner, Mr Nichols and Les Cook did not
collectively or individually take a positive decision to cancel
STUBS from the
ADCNET project simply because DoD had decided not to proceed. Given the
history of the "deferral decision" and the
known responsibility of the Senior
Executive to make a decision once DoD's intentions were known, I find it wholly
improbable that
these officers would have presumed to arrogate to themselves a
decision they knew belonged to the Senior Executive. I regard evidence
given
by Les Cook disputing the Senior Executive's continuing role in the matter at
the time as being illustrative of his argumentativeness
in cross-examination
and as being entitled to no weight.
1337 Given that all relevant communications were made by Les Cook, the bases of
his actions are of no little importance. However,
his oral evidence concerning
his state of mind at the time is both contradictory and confused. This
difficulty is overarched by
his lack of recall of the detail of the 13-15
September meetings. I do not intend to recount that evidence other than to say
that
he did indicate that STUBS was cancelled on 13-14 September and that he
stated in cross-examination that (i) the "no STUBS" decision
was made later
than those dates; (ii) on those dates STUBS was still just possibly available
to DFAT; and (iii) he personally did
not have the power to decide whether DFAT
would pursue the procurement of STUBS, DoD's decision notwithstanding.
1338 DoD's decision, as I indicate below, was of significance in evaluating
just how "live" was the possibility of STUBS remaining
available to DFAT. Les
Cook's view was that at 13-15 September there was "a slight possibility it was
not dead". This view, which
probably reflected his own appreciation of the
matter at the time, is also reflected in my conclusions on his actions on 13-15
September.
1339 I make the following findings. (i) Les Cook did tell both Mr Brent and
Roger Cooke at the 13-14 September meeting that STUBS
had been cancelled. The
most reliable evidence of this fact is Roger Cooke's 15 September memorandum.
(ii) I infer that in so doing
he presented as a fait accompli what he
appreciated would be the predictable outcome of DoD's decision, and he did so
while aware
of AWADI's provisional offer to DFAT of 13 September 1995. (iii) I
infer that he made some reference to AWADI and that what he said
was reasonably
capable of creating the understanding that it was AWADI that had cancelled
STUBS; (iv) I also infer that he felt
confident in making the cancellation
communication because he was taking no positive decision in the matter. He was
merely voicing
what he considered was an inevitable outcome, ie DFAT would not
have to make a cancellation decision. (v) A reason this communication
was made
was so that the "STUBS replacement" issue could be included in the contract
negotiations for a schedule extension: Roger
Cooke's memorandum. The schedule
extension negotiations were of real moment in August/September 1995. It is a
moot point whether,
consistent with the reasons underlying the change of
tactics decision, the secretiveness demonstrated by DFAT about disclosing that
decision to BHP-IT was related in any way to those negotiations. I make no
finding on that matter.
1340 The 26 September letter confirmed Les Cook's "informal advice ... of 15
September that AWADI will not continue with the development
and supply of the
STUBS security devices". This letter was a response to Mr Brent's 25 September
request for "formal notification
of the demise of the STUBS program".
1341 It is clear that between the 13-15 September meetings and the 26 September
letter the appreciation developed, and was acted
upon, within DFAT that STUBS
was no longer part of the ADCNET project. For example, the ADCNET Security
Sub-Committee meeting of
22 September addressed the issue of boundary security
as involving a choice between Option C and a new option, Option D. And Kim
Jones' evidence is that after being told both of DoD's decision and of AWADI's
decision to cancel STUBS, he sought the "no legal
obligation letter" from
AWADI. How the above appreciation developed and why DFAT officials acted
confidently upon it is by no means
clear.
1342 One can reasonably infer that after its communication to DFAT on 12
September, the DoD decision was made known to, amongst others,
Kim Jones, Mr
Skinner and Mr Allen. The knowledge that was possessed in DFAT of AWADI's
intention and circumstances prior to the
26 September letter is far from clear.
1343 On 13 September AWADI indicated to DFAT that it would advise it of
"indicative new pricing" for the 50 units it "may be willing
to manufacture ...
for DFAT". No such advice was given. No later manifestation of such
willingness occurred. On 14 September,
the "STUBS Closedown Plan" was directed
to be put into effect, 30 September being the close down date. This, I infer,
explains why
the pricing advice was never forthcoming. While between 11 and 13
September, AWADI may have been acting with some little optimism
about achieving
a "return" on STUBS (as is evidenced in its managing director's proposals
memorandum of 11 September and the "offer"
to DFAT), its conduct from 14
September was consistent with its seeking to procure recoupment from DoD of
costs incurred on the STUBS
project.
1344 I am satisfied that from or shortly after 14 September AWADI had in fact
cancelled STUBS. However, I am not prepared to infer
that such a decision was
conveyed explicitly by AWADI to DFAT. In the absence of evidence of how any
actual decision was made by
DFAT that STUBS was no longer to be used in the
ADCNET, the reasonable inference to be drawn is that it was assumed within DFAT
that
DoD's decision spelled the end of the STUBS project for all practical
purposes and DFAT officials acted accordingly. When Les Cook
wrote the 26
September letter, AWADI was not continuing with the STUBS project.
(c) Conclusions: Contract Claim
1345 I have already rejected those essentially defensive claims made by BHP-IT
that are based on the non-provision of STUBS and the
non-payment of Milestone
4000. My concern here is with whether, in light of my findings, the
Commonwealth acted in breach of cl 5.6(a)
and cl 10.3 of the Head
Contract. The former provision obliged the Commonwealth to act in a fair and
reasonable manner in the
exercise of any obligation, function or power it had
under the contract; the latter required it to report to BHP-IT "immediately"
any risk which might have a significant effect on the Implementation Plan and
to inform BHP-IT of how it would manage that risk.
1346 I am satisfied that, in the manner in which it conducted itself from
around the time of the change of tactics decision in June
1995 until its formal
notice of the demise of STUBS in the 26 September letter, the Commonwealth
acted in breach of both obligations.
However, I am not satisfied that its
conduct prior to June 1995 was similarly wrongful.
1347 First, the period to June 1995. The disclosures DFAT made to BHP-IT
concerning the status of STUBS, the possibility of its
cancellation by either
AWADI or DFAT and the need to make a decision whether it was to proceed with
STUBS, were sufficient in the
circumstances to protect it from falling foul of
the above provisions.
1348 A duty to act fairly and reasonably in performing one's functions is not
breached simply because it can be shown that something
could have been done
more openly, more expeditiously or in a more effective way. Clearly the
Commonwealth could have so acted and
most obviously so (a) in pursuing AWADI
about the price of STUBS prior to June 1995 and (b) in reaching a decision on
proceeding
with STUBS, such a decision being foreshadowed on a number of
occasions from as early as 29 March (the representations were that
it would be
made within "two" or "four" weeks). What is required to be shown is that it
acted unfairly or unreasonably.
1349 If it had been made out that the Commonwealth had in its performance of
the contract in this period acted in a manner other
than that which BHP-IT was
entitled to expect of it, I would have found it to have been in breach of
cl 5.6(a). In formulating
the matter in terms of reasonable expectations,
I wish to draw attention to the important roles that the nature and purpose of
the
contract itself and the evolving relationship of the parties can have on
setting the standard by which to judge whether one party's
conduct can properly
be characterised at a particular point in time as unfair or unreasonable.
1350 Whatever the Commonwealth's sins of commission and omission in this period
I do not consider that its conduct had been so unfaithful
to the parties'
bargain as to be unfair. Neither do I consider that the Commonwealth acted
unreasonably.
1351 I am similarly of the view that it sufficiently identified the "STUBS
availability" risk during this period - so much so that
from the end of March
1995 the status of STUBS was a standard item at project management meetings.
Its dilatoriness in taking its
foreshadowed decisions about STUBS probably
reflected DFAT's primary concern with the ADCNET project not the ADCNET
contract. Nonetheless,
I consider that so far it had sufficiently complied
with the requirements of cl 10.3 in the circumstances. In saying this,
I
do not overlook that in his 18 May letter, Mr Brent foreshadowed the need for
action "to contain significant and costly delays".
By the end of May the time
for action to manage the "STUBS availability" risk had arrived. That is a
matter relevant to my finding
of a breach of cl 10.3 in the period from
June 1995 to September 1995.
1352 Turning now to that period, the change of tactics proposal and its
implementation crystallised a change in the relationship
of the parties. To
avoid having to raise a change request for a replacement for STUBS so giving
"the PSI a lever to prise open a
large extension of schedule and consequent
cost increase", a course was taken which resulted in deception being practised
on BHP-IT.
It involved, first, deferring any decision until September - this
was quite contrary to the expectation Les Cook created in correspondence
that a
decision was soon to be taken (eg in his 6 June letter to Mr Brent); secondly,
not then disclosing that such a deferral decision
was taken; thirdly, securing
the agreement of BHP-IT to the use of emulation for acceptance testing; and
fourthly, later fostering
the expectation that it was DFAT's intention to
acquire STUBS. While different DFAT officials participated in different parts
of
this process - and those who participated in the first (eg Kim Jones and Mr
Cotton) may well have been unaware of the later steps
taken - the outcome of
their collective actions was as I have put in précis form above.
1353 BHP-IT was, in light of communications made from 29 March 1995 onwards but
particularly in light of the 6 June letter, entitled
to expect that DFAT would
take a decision on the use of STUBS or an alternative in June and that this
would be communicated to it.
It was equally entitled to expect that, if DFAT
decided to defer a decision on whether it would even acquire the CSI it had
contracted
to provide, it would be informed of that decision because of its
possible effects on GEC Marconi's performance of the Sub-Contract
hence its own
performance of the Head Contract.
1354 Emblematic of the reason for the latter entitlement was the request made
in Les Cook's 22 June own minute to Kim Jones that
an indication be given of
the likely decision to be taken as that "would be helpful ... in determining
the degree of DFAT effort
to be expended in testing the STUBS interface" etc.
He was seeking what was being denied to BHP-IT. It was being committed to a
course that was likely to result in significant and costly delay and it was
neither informed of this or given the opportunity to
engage in discussions with
DFAT and GEC Marconi about how the deferral decision should be managed.
1355 Consistent with what I have earlier said, I attribute DFAT's conduct in
part to a mentality quite unattuned to contract management
- hence Mr Nichol's
view that he had no obligation to advise BHP-IT of DFAT's long-term plans with
respect to STUBS. However, I
also attribute the conduct of those in IT Branch
and particularly Les Cook to an apprehension that openness with BHP-IT could
prove
costly to the Department. Covert action was engaged in in relation to
its own contractual obligation so as to maintain what was
perceived to be a
contractual advantage in not having to engage in negotiations for a replacement
for STUBS. BHP-IT was being dealt
with unfairly. The Commonwealth was acting
without regard to the interests of BHP-IT in the matter. Fair dealing required
otherwise.
There is a real curiosity in the course of secretiveness taken by
DFAT. If STUBS was later to be cancelled before acceptance testing
of the R3
software - as in fact transpired - a deferral decision would be likely in any
event to lead to consideration of another
option and the raising of a change
request - as in fact happened. This would result in the very event occurring
that the change
of tactics was designed to avert. And so CR 3057 was
raised.
1356 In the manner in which the change of tactics was put into effect, the
Commonwealth breached cl 5.6(a). It misrepresented
its own intentions in
relation to its contractual performance (ie the acquisition of STUBS); in the
deferral decision, it falsified
expectations it had created in relation to the
taking of a decision concerning the STUBS acquisition without informing BHP-IT
of
this; and it acted improperly to advance its own interests without regard
to the interests of BHP-IT and to which, as a matter of
fair dealing, it was
obliged to have regard. The Commonwealth's actions related to the manner in
which it would perform its functions
under the Head Contract and they were
unfair.
1357 I would add that, though the case has not been put on the basis of a
breach of the implied duty of good faith and fair dealing,
the Commonwealth's
action would clearly have fallen foul of that duty.
1358 Secondly, as the deferral decision bore on whether STUBS would be acquired
or another option be pursued, it related to a risk
that might have a
significant effect on implementation of the Implementation Plan. The
Commonwealth did not immediately notify BHP-IT
of that risk. It acted in
breach of cl 10.3 of the Head Contract.
1359 Distinctly, Les Cook's 26 September 1995 letter confirming that AWADI
would not supply STUBS was, on my findings, true as far
as it went. It did not
on its face indicate the reason why AWADI had so acted, ie that DoD was not
proceeding with STUBS. Against
the background of the continuing
misrepresentation that had been made concerning DFAT's intention in relation to
STUBS, it may be
said that there was a distinct lack of candour in Les Cook's
communication if he created the impression that the cancellation decision
was
AWADI's alone and that it was uninfluenced by DoD's decision.
1360 I am not satisfied, though, that such lack of candour would have had
independent contractual significance for present purposes.
All parties were
aware that the Commonwealth in two different manifestations, ie DFAT and DoD,
was interested in procuring STUBS.
Those two departments furthered differing
aspects of the public interests served by the Commonwealth, ie foreign affairs
and defence.
Though BHP-IT was formally dealing with the Commonwealth in the
ADCNET contract, it was perfectly well aware that it was dealing
with the
Commonwealth in the discharge of its foreign affairs responsibilities. It was
for this reason that the intentions of DFAT
were the operative intentions of
the Commonwealth in relation to matters affecting the ADCNET contract.
1361 The furtherance of the Commonwealth's defence responsibility was no part
of the ADCNET contract. Though a bona fide defence-related
decision may (as
here) have impacted upon the Commonwealth's ability to perform some part of the
ADCNET contract, BHP-IT in dealing
with the Commonwealth was not reasonably
entitled to expect that the Commonwealth would not so act in discharging its
defence-related
responsibilities - even if this put the Commonwealth in a
breach of the ADCNET contract or rendered part of its performance impossible.
BHP-IT equally was not entitled to expect that in the conduct of its defence
responsibility the Commonwealth would have regard to
an aspect of its foreign
affairs responsibility, ie the performance of the ADCNET contract.
1362 The DoD decision may have been the practical cause of AWADI's cancellation
of STUBS. However, for the reasons I have given
above, I do not consider that
its taking rendered the conduct of the Commonwealth unfair or unreasonable in
relation to its obligation
to supply STUBS under the Head Contract. That
decision ensured that the Commonwealth remained in breach of its obligation to
supply
STUBS. But the obligation in cl 5.6(a) of the Head Contract did
not disable the Commonwealth from taking that decision. In
that sense, the
decision was a risk born by BHP-IT. Les Cook's communication of the
consequence of the decision was, in contractual
terms, no more than the
communication of a fait accompli. Whether or not it was misleading or
deceptive, it did not attract the
operation of cl 5.6(a). The
communication did not relate to the exercise of a contractual function. It
reported a fact whether
or not Les Cook actually knew that STUBS had been
cancelled by AWADI. For the same reason it did not attract the operation of
cl 10.3
of the Head Contract.
1363 It is unnecessary to consider the consequences that flow from the breaches
that I have found. As I earlier indicated, BHP-IT
has not sought to identify
any loss of damage attributable to them alone.
2. THE TRADE PRACTICES ACT CLAIM
1364 The misleading or deceptive conduct said to found this claim is the same
conduct BHP-IT has relied upon to make out its breach
of contract claim. As
pleaded, the misrepresentations alleged to have been made were (i) in the
period up to September 1995, the
Commonwealth continuously represented that it
remained willing and able to supply STUBS under the Head Contract; and (ii) it
was
unable to supply STUBS because AWADI had chosen not to continue with the
development and supply of STUBS devices.
1365 In light of my findings in the contract claim, I am satisfied that the
Commonwealth calculatedly misrepresented its own intentions
in relation to the
acquisition of STUBS from about the time of the change of tactics decision.
Implicit in this conclusion is the
finding of an additional misrepresentation
involving non-disclosure of the deferral decision in late June/early July 1995.
I should
note, though, that it was unnecessary for the purposes of the contract
claim to make any finding as to whether the formal response
made by Les Cook on
26 September 1995 concerning the cancellation of STUBS embodied a
misrepresentation. I did conclude that by
that time STUBS had been cancelled
by AWADI, whether or not Les Cook knew this to be the case.
1366 For present purposes I need only say that the Commonwealth did engage in
conduct that was misleading or deceptive. However,
the real issues raised by
BHP-IT's TP Act claim lie elsewhere. The TP Act applies to the Commonwealth in
a quite particular way.
1367 Section 2A of that Act provides, insofar as presently relevant, that:
"(1) ... this Act binds the Crown in right of the Commonwealth in so far as the Crown in right of the Commonwealth carries on a business, either directly or by an authority of the Commonwealth."
The section goes on to provide that, where the Commonwealth is carrying on a
business (otherwise than by an authority of the Commonwealth),
the Act applies
to it as if it were itself a corporation. By way of qualification
s 2C(1)(c)(i) provides insofar as presently relevant that, for the
purposes of s 2A, a transaction involving only persons who are all acting
for the Commonwealth does not amount to carrying on a business. I would
also
note in passing that the definition of "business" in s 4 of the Act
includes "a business not carried on for profit". The Commonwealth's principal
defence to this claim is that it was not
relevantly "carrying on a
business".
1368 The Commonwealth's second line of defence is that, assuming the TP Act did
apply in the circumstances, I should not find that BHP-IT relied upon the
misrepresentations made, or suffered loss thereby.
(1) "Carrying on a Business"
1369 BHP-IT's contention is that, by entering into the ADCNET contracts to
obtain the ADCNET software, the Commonwealth was engaged
in the systematic
commercial activity of developing, obtaining, supplying and marketing a secure
communication system and the intellectual
property that was integral to it.
(a) Applicable Principles
1370 The volume of recent case law on s 2A's "carrying on a business"
requirement, and the binding character of the decision in NT Power
Generation v Power & Water Authority [2002] FCAFC 302, relieve me of
the need to consider this matter at any length: see also Sirway Asia
Pacific Pty Ltd v The Commonwealth of Australia [2002] FCA 1152. I need
only note the following:
1371 (1) In the context of the TP Act, "carrying on a business" is intended to
refer to activities undertaken in a commercial enterprise or as a going
concern: Corrections Corporation of Australia Pty Ltd v Commonwealth of
Australia [2000] FCA 1280; (2000) 104 FCR 448 at [12]; NT Power Generation, above at
[85], [88].
1372 (2) While repetition, system and regularity are indicia of carrying on a
business, they are not on their own sufficient to compel
a conclusion that such
is the case: Sirway Asia Pacific Pty Ltd, above, at [60]; there must
be present some element of commerce or trade such as a private citizen or
trader might undertake: RT & YE Falls Investments Pty Ltd v State of
New South Wales [2001] NSWSC 1027 at [78]. "What is a sufficient degree of
commerciality is a question of fact": ibid; Paramedical Services Pty Ltd v
The Ambulance Service of New South Wales [1999] FCA 548 at [86].
1373 (3) Engaging in an activity on a single occasion or only as an ad hoc
response to an infrequent occurrence or circumstances,
will not normally
indicate that a business is being carried on: RT & YE Falls Investments
Pty Ltd, above, at [78]: JS McMillan Pty Ltd v The Commonwealth
(1997) 77 FCR 337.
1374 (4) Where particular activities of the Commonwealth constitute the
carrying on of a business, the ambit of those activities
must be examined to
see whether the impugned conduct was engaged in as part of, or in the course
of, the carrying on of that business:
JS McMillan Pty Ltd, above,
356-357; NT Power Generation, above, at [87].
1375 I would merely add that it is not now open to me to countenance the
suggestion that s 2A should be construed expansively in favour of those
dealing with the Commonwealth, so limiting the immunity that would otherwise be
enjoyed by the Commonwealth: see generally Seddon, Government
Contracts, [6.11]ff (2nd ed); Seddon "Crown Immunity and the
Unlevel Playing Field" (1998) 5 Agenda 467. It is appropriate, though, to note
again the obvious
anomaly of the s 2A requirement. Government contracting
(in procurement and otherwise) is of major significance in the economic life of
this country,
as it is in most countries: Arrowsmith et al, Regulating
Public Procurement, 7. It is somewhat surprising, that when the State
enters the market place to acquire goods or services, it should exempt itself
from those norms of conduct considered appropriate to the conduct of trade and
commerce that it has imposed upon the private sector
as of course - the more so
given the "business-like" manner in which the Executive government commonly
professes it conducts its
affairs both internally and in its dealings with the
community.
(b) Factual Setting
1376 The evidence on this matter is particularly sparse.
1377 I have referred both to the origins of the Diplomatic Communications
Network and of the ADCNET project in the "General Chronology"
in Part I. I
will not repeat what I said there.
1378 On 30 April 1992, the then CEO of BHP-IT wrote to the Minister for Trade
and Overseas Development concerning the anticipated
issue by the Canadian
Government of a Request for Tenders for the development of a global diplomatic
communications network similar
to that of DFAT. The letter went on to say:
"We seek your endorsement to the concept that we, together with the Department of Foreign Affairs and Trade, examine whether it is sensible for us to tender jointly for the Canadian opportunity on the basis that:
. on a commercial basis the Department would assign licencing rights for intellectual property which has been derived from the ADCNET project and which is not prejudicial to Australia's national security interests;
. the Department would contribute other material and human resources as agreed; and
. BHP Information Technology would provide Prime Systems Integration services in a manner similar to that for ADCNET."
1379 The Minister's reply of 16 June 1992 stated, in part:
"As part of the ADCNET Project, the Department has conceived and, with the assistance of BHPIT, is developing several secure Information Technology products which may have a market with agencies of friendly governments. While these products will not be in operation for some time, it would be prudent to keep potential markets informed of the capabilities and availabilities of the products. It is also important to advise potential markets of the added value that Australian industry, such as BHPIT, can provide in the form of Prime Systems Integrator and other services.
I am advised that discussions, along the lines you suggested, have occurred between staff of my Department and BHP staff and as a result a combined presentation will be made to the Canadian Department of External Affairs in Ottawa on 25 June. I support this initiative by the Department and BHPIT in marketing Australian technology overseas and wish you well in your venture."
1380 In mid-1993 DFAT undertook to show ADCNET to Defence International
Projects Branch. Mr Skinner's evidence was that, while not
recalling having
dealings with that Branch, he could recall that demonstrations were given to
DoD in the early 1990s.
1381 On 11 May 1994 DFAT sent a memorandum to all Government Organisations
using ADCNET. The object of the memorandum was to explain
the changes to be
wrought by the ADCNET redevelopment project. It indicated that several new
services would be offered to users
"at charging rates lower than those
available from commercial suppliers". It also indicated what its "charging
policy" would be.
1382 In March 1995 Australia co-hosted the CeBIT Hanover Computer Fair. DFAT
was to have a stand at it demonstrating, with reference
to ADCNET, that
Australia had the capability to develop and implement large, complex IT systems
through partnerships between government
and industry.
1383 In April 1996 BHP-IT made a request to DFAT to demonstrate "ADCNET
functions" at the Australian High Commission in Malaysia.
The purpose of this
was to allow the Malaysian Foreign Ministry and BHP-IT to explore the
possibility for a contract under which
BHP-IT would provide to the Malaysian
Government services similar to those it provided to DFAT in the ADCNET project.
1384 The evidence as it related to STUBS was as follows. The STUBS concept was
developed in 1989 and research and development into
it was then undertaken by
DSTO. In February 1993 the Commonwealth entered into an agreement under which
it licensed STUBS intellectual
property to AWADI. The recitals to the
agreement indicated that AWADI would use its best endeavours to further
develop, manufacture
and market STUBS "to the Australian Defence Forces and
other markets": emphasis added. The Commonwealth had previously filed
a provisional specification for a patent for such STUBS technology as it
had
developed.
1385 In late 1996, the Commonwealth entered into a similar licensing agreement
with Vision Abell Pty Ltd in relation to information
security technology
("Starlight") it had developed after STUBS. The background to this agreement
was that the Commonwealth wished
to develop an Australian based industry
capability in the area of information security. The Commonwealth at the time
foreshadowed
that it might itself need to purchase information security
equipment based on Starlight. Vision Abell Pty Ltd was the vehicle of
a
consortium that included BHP-IT.
1386 The Commonwealth acquired the intellectual property rights to STUBS and
the STUBS prototypes, etc from AWADI in June 1996 for
$2.6 million. There is
no evidence that anything further was done in relation to STUBS thereafter.
(c) Findings and Conclusions
1387 BHP-IT has sought to make far more of the scant evidence of the
Commonwealth's "commercial behaviour" than it is capable of
bearing. It has
been submitted that the Commonwealth "sought to commercialise ADCNET" from an
early date, as witness the BHP-IT
communications with the Minister for Trade
and Overseas Development concerning the possible Canadian tender; that it
"consistently
sought to demonstrate" the ADCNET system to outside interests so
that it could further potential commercial opportunities (eg the
CeBIT Hanover
Fair and the Malaysian exhibition); that it was "commercialising" its network
services in relation to infra-governmental
users; and that it commercialised
STUBS and Starlight technology.
1388 For my own part I am satisfied that the ADCNET project was designed to
enhance the Commonwealth's Diplomatic Communications Network. Though I do not
find the distinction sometimes drawn between "governmental" and
"non-governmental" activities a particularly illuminating one, in
this instance
it is appropriate to describe the nature and purpose of the project as
distinctively governmental in character. The
project and its resultant product
were driven by governmental imperatives.
1389 Of its nature, though, the project resulted in the development of a
product and to which the Commonwealth had intellectual property
rights may have
been of potential interest to third parties. It is unsurprising that the
Commonwealth might consider taking steps
to utilise that intellectual property
(or parts thereof) so as to obtain some return, or cost-offset, on its own
investment in the
project. The evidence of its so doing can only be said to
illustrate action of a sporadic and distinctly desultory character amounting
to
little more than a few instances of approaches, demonstrations, etc over a five
year period with some number of these, in fact,
being instigated by BHP-IT for
its own purposes.
1390 It equally is unsurprising that, as a service provider to other
infra-governmental entities, DFAT should seek to enhance the
"services" it
provided and the "charges" it made to other governmental users when enhancing
ADCNET. Later in these reasons I refer
to the true character of "charges" made
by one government agency to another when considering "rentals" paid by
departments for the
"lease" of government owned buildings: Part V: The
Commonwealth's Cross-Claim: The Edmund Barton Building Expenses; see also
Corrections Corporation of Australia Pty Ltd, above, at 450-451.
Neither the imposition of such charges, nor the provision of services which
might as well be available from the
private sector, would amount to the
carrying on of a business. It simply was not commercial activity for the
Commonwealth to organise
its own activities in ways designed to secure its cost
effective and efficient use of its own resources: cf TP Act
s 2C(1)(c)(i).
1391 If it had been the case that the Commonwealth, as a matter of "whole of
government policy", had ordained that Commonwealth departments
and agencies
were to exploit commercially technological innovations resulting from
activities undertaken by or for those departments
and agencies, it might be
that the aggregate of the actions taken by the departments and agencies could
evidence the carrying on
of a business of exploiting such innovation. The
present is far removed from such a case.
1392 Insofar as the development of the ADCNET software was concerned, the
evidence does not warrant a finding that this occurred
as part of, or for the
purpose of, a business being carried on by the Commonwealth. Whether or not
the resultant product and its
intellectual property could later be turned to
account in some way, the software itself was developed for the Commonwealth's
own
use and purposes and not as well or at all for a business purpose. This
conclusion would itself require the dismissal of the TP Act claim. The
Commonwealth's conduct could only be impugned under s 52 of the TP Act if
that conduct occurred in the course of, or as a part of, carrying on a
business. This limitation has been said to arise from
the wording of
s 2A(1)as the Act applies only "in so far as" the Commonwealth carries on
a business: NT Power Generation, above, at [87]. The ADCNET project
was not part of a business.
1393 If there was a potential business being carried on at all in this case, it
was the commercial exploitation of the product of
the ADCNET project, but that
business would not have encompassed the project itself. Having said this, I am
equally not satisfied
that such a business was carried on by the Commonwealth.
Such steps as were taken to exploit the ADCNET product were, as I have said,
sporadic and desultory. There is little to suggest actions were taken
regularly, systematically, methodically to achieve a desired
commercial end.
The evidence suggests that, if some return were to be made on the ADCNET
project, it would result from an adventitious
occurrence and not from the
concerted pursuit of business opportunities by the Commonwealth.
1394 I should add I do not regard the actions taken by the Commonwealth in
relation to STUBS and Starlight as being of any relevance
to the question
whether, in the conduct of the ADCNET project, the Commonwealth was carrying on
a business. That evidence did no
more than illustrate the Commonwealth's
intent to develop a private sector capability in information security
technology - a capability
the need for which was demonstrated in the ADCNET
project itself - and the Commonwealth's entry into licensing agreements to that
end. Whether or not its so doing had a business character because of
activities engaged in by units within DoD (eg DSTO) is not
a matter before
me.
1395 I conclude that, as the misrepresentations made by the Commonwealth were
not made in the course of carrying on a business, BHP-IT's
claim under the TP
Act must be dismissed.
(d) Other Matters
1396 I have already indicated that this and the contract claim have a marginal
- but unexplored - significance in light of my rejection
of GEC Marconi's
claims against BHP-IT relating to the non-provision of STUBS and the
non-payment of Milestone 4000. Despite this,
I have dealt at some length with
the contract claim.
1397 However, I do not intend here to go on to consider whether, if my
conclusion on s 2A is incorrect, BHP-IT has made out (i) that Les Cook's
formal response of 26 September 1995 was misleading or deceptive; and (ii)
that BHP-IT relied upon, and in consequence was caused loss by, such
misrepresentations as were made by the Commonwealth. The state
of this claim
does not warrant the giving of further attention to over 100 pages of
submissions against the contingency of error
in my s 2A finding.
PART V: THE COMMONWEALTH'S CROSS-CLAIM
1398 The Head Contract (as amended) required BHP-IT to achieve Milestone 5000
by 9 February 1997. That Milestone provided for the
delivery on that date of
the "Canberra System Developed Software". The Commonwealth's claim for damages
is for losses incurred as
a result of late delivery of this software. The
software itself was that part of the ADCNET software which provided the
"Message
Switch" function. If used with a security gateway mechanism, this
software would have enabled the IBM Classified Message Switch
System ("the IBM
System") to have been decommissioned. That System was not in fact
decommissioned until 23 June 2000 when it was
replaced by a new security
gateway system, UNCLGUARD, which had been developed by DFAT and endorsed by
DSD.
1399 The damages claimed are of two broad varieties. The first relates to the
costs and expenses incurred by the continuing need
to use and to maintain the
IBM System until June 2000. The second was of various additional costs
incurred by the Commonwealth up
to July 2000 as a result of BHP-IT's delayed
performance of the Head Contract.
1400 BHP-IT's first line of defence to this claim is that in December 1997 it
entered into the Variation Agreement with the Commonwealth
which had the
effect, it is claimed, of extinguishing the Commonwealth's right to claim
damages. Alternatively it is said that right
was extinguished in respect of
damages arising from breach of the Milestone 5000 requirement but suffered
after the date of execution
of the 1997 Variation Agreement. BHP-IT goes on to
say that if the Variation Agreement had neither of the above effects, it was
an
implied term of the Variation Agreement that, upon BHP-IT's performance of the
Amended Contract, it would be discharged from all
obligations under the Head
Contract.
1401 The second general defence relates to the IBM System claims. BHP-IT
contends that none of the costs associated with its retention
until 2000 were
caused by its breach of the Head Contract. Rather they were the immediate
consequence of the Commonwealth's decision
in 1995 to cancel STUBS and to rely
upon the IBM System pending the development of its own sealer and gateway
mechanism.
1402 Distinctly BHP-IT has made specific challenges to each of the various
heads of damage advanced by the Commonwealth.
1403 GEC Marconi has also put in detailed submissions challenging the
Commonwealth's cross-claim. Its interest in the matter is
that if the
cross-claim is successful the resultant liability will be passed on to it by
BHP-IT.
1404 Because of the significance the 1997 Variation Agreement has to the
cross-claim in its entirety I intend to consider it before
dealing with the
substance of the Commonwealth's various claims.
1. THE 1997 VARIATION AGREEMENT
(a) Background
1405 To recapitulate, after GEC Marconi terminated the Sub-Contract in December
1996, neither BHP-IT nor the Commonwealth sought
to terminate the contract.
Over the next year they engaged in negotiations which led to the December 1997
Variation Agreement. Though
the formal legal relationship between the parties
remained substantially the same, BHP-IT's role in the performance of its
contract
with the Commonwealth changed totally. It did not engage a
sub-contractor to develop the R3 software. It performed the contract
itself.
1406 During the negotiation period (ie in September 1997) GEC Marconi commenced
these proceedings against BHP-IT. Shortly prior
to the execution of the
Variation Agreement, BHP-IT filed its cross-claims against (inter alia) the
Commonwealth.
1407 In October 1997 the Commonwealth issued a Notice of Breach to BHP-IT. The
breach notified was the failure to deliver the Developed
Software as specified
in the Schedule 8 Implementation Plan.
(b) The Terms of the Variation Agreement
1408 The Agreement professed on its face to have been made as a variation under
cl 45 of the Head Contract. It described its
purpose as being to amend
that Contract "following the actions of [GEC Marconi] ... to frustrate the
performance of [the Head Contract]".
And it amended both provisions in the
Head Contract and the requirements of the Schedules to it.
1409 These amendments made plain the performance to be expected of BHP-IT. A
new FRS (Version 4) had been prepared in late 1997
after agreement was reached
in August/September 1997 on changes to the existing version after a
comprehensive review of the FRS over
several months. Schedule 1 of the Head
Contract was amended accordingly. An entirely new Implementation Plan was
prescribed in
Schedule 8, that Plan being premised upon a new manner of
performance of the Contract by BHP-IT. There were to be five milestones,
the
first of which, Milestone 1000 ("Project Mobilisation"), was to occur on 19
December 1997 this being the agreed date for "project
resumption". The four
subsequent milestones were quite different in character from the six they
replaced.
1410 As has been seen, the Variation Agreement did not alter the agreed
contract price. Nonetheless, the creation of new milestones
in place of the
old required that new arrangements be made for the Milestone payments. BHP-IT
could retain what it had been paid
for Milestone 1000 (which was earned on the
date the Variation Agreement took effect). The two further milestones it had
already
received (Milestones 2000 and 3000), were, in effect, returned to the
Commonwealth. BHP-IT was to be paid under the amended Contract
as and when it
met the new milestones.
1411 In describing the amendments made by the Variation Agreement to the Head
Contract and its Schedules, cl 3.3 of the Variation
agreement stated that
these amendments were:
"to facilitate the completion of the project and do not make use of any of the material provided by EASAMS following the actions of EASAMS, and do not result from or constitute a decision by BHPIT not to complete the works under the original contract in the manner contemplated under the original contract." Emphasis added.
BHP-IT was, in other words, committing itself "to start again from scratch"
without the benefit of any work undertaken by GEC Marconi.
Equally, the
amendments were not necessitated by a decision by BHP-IT not to perform the
unamended Contract in the manner contemplated
by it.
1412 Apart from effecting amendments to the Head Contract and its Schedules,
the Variation Agreement contained substantive provisions
of its own. They are
the source of the present controversy.
1413 Though clauses 4, 5 and 6 are central to the controversy between the
parties, there are several other clauses (cll 2, 7, 8 and
11) to which it is
necessary to refer. The relevant clauses are as follows:
"2. Effect
This Amendment will take effect from 19 December 1997.
...
4. Reservation of Rights
4.1 The Commonwealth and BHPIT both reserve any rights that they may have under the original contract in relation to any claim that EASAMS, BHPIT or the Commonwealth may bring against the other. In particular, the Commonwealth and BHPIT agree that except as specifically provided for in this Amendment they have not waived any claim against each other.
5. Release from Further Work
The Commonwealth hereby release BHPIT from any further obligation to perform the work as required under the original contract.
6. Work still to be Performed
The Parties agree that BHPIT will perform the work under the Agreement as amended.
7. Undertaking by The Broken Hill Proprietary Company Limited
The Commonwealth agrees that it will not take any action in respect of the original contract against The Broken Hill Proprietary Company Limited (BHP).
8. Liquidated Damages
The Commonwealth waives all rights to liquidated damages under the original contract.
...
12. Excusable Delay
BHPIT agrees to waive all claims against the Commonwealth under the original contract for delay costs except those that are found by a court or as a result of arbitration or mediation to which the Commonwealth is a party to have arisen from a claim by EASAMS on BHPIT and to have been the direct result of an action or omission of the Commonwealth."
1414 I would add that it was cl 3 that amended the terms and conditions
of the Head Contract and the Schedules in the ways that
were shown in versions
of the Head Contract and the Schedules annexed to the Variation Agreement.
1415 In consequence of the response made by BHP-IT to supplementary questions
asked of the parties it is necessary to refer to the
liquidated damages
provisions of the Head Contract. Clause 39 provided:
"39. LIQUIDATED DAMAGES
39.1 Where, through the fault of the Contractor, the Acceptance Tests are not successfully completed by the relevant Contract Acceptance Date or extension thereof, then:
(a) if it is specified at Schedule 3 that liquidated damages are payable and an amount has been specified in Schedule 8 against a Contract Acceptance Date as the amount (the "liquidated damages amount") that is to be payable by the Contractor as and by way of liquidated damages to the Customer for the loss suffered by the Customer as a result of the delay commencing on the expiration of the relevant Contract Acceptance Date, and the Customer notifies the Contractor that it intends to rely on the remedy set out in this paragraph - the Contractor shall pay that liquidated damages amount as set out in Schedule 8; or
(b) if no amount has been specified in Schedule 8 against a Contract Acceptance Date as the liquidated damages amount or no notice has been sent by the Customer under paragraph (a) - the liability of the Contractor shall, in respect of the delay that occurs after the expiration of the Contract Acceptance Date, be determined in accordance with clause 38."
1416 Schedule 3 ordained that liquidated damages were payable in accordance with Schedule 8. And that Schedule provided, insofar as presently relevant, that:
"2. LIQUIDATED DAMAGES
2.1 The Contractor shall pay liquidated damages to the Customer for delays incurred in delivery of the Deliverables in accordance with the Contract Acceptance Date as specified in Table 8.1 and the amounts specified in Table 8.2. The aggregated liquidated damages payable under this Contract and damages for any subsequent loss suffered by the Commonwealth for further delay in completing the Acceptance Tests which would be incurred before termination of the Contract by the Commonwealth shall be limited to 5% of the Contract Price.
Deliverable Reference Ident |
Deliverable Description |
Liquidated Damages Amount |
1000 |
Project Mobilisation |
Not applicable |
2000 |
Preliminary Design Review |
Nil |
3000 |
Critical Design Review |
Nil |
4000 |
Test Readiness Review |
Nil |
5000 |
Canberra system Developed Software |
$2,000 per day |
..."
(c) The Construction Dispute
1417 The difference between the parties can be simply put. When BHP-IT failed
to deliver the Developed Software in accordance with
Schedule 8 of the
unamended Head Contract it breached several provisions of that contract (eg
cl 9D, cl 10.1). The Commonwealth,
having elected not to terminate
the unamended Head Contract, BHP-IT's obligation to perform (albeit late)
remained and the Commonwealth
was entitled "to sue for any damage suffered ...
through the delay": Carr v J A Berriman Pty Ltd, above, at 349; see
also Farnsworth, Contracts, 852 (3rd ed). That was the
position at the time the Variation Agreement was entered into.
1418 The Commonwealth contends that that right remained unaffected by the
Variation Agreement and was expressly preserved by cl 4.1
of that
agreement. All that the Variation Agreement relevantly did was fix a new date
for delivery of the Developed Software.
1419 BHP-IT's first contention is that, properly construed, cl 5 operated
retrospectively to release it of its past obligation
to perform. This included
the release of such rights as the Commonwealth had to make claims in respect of
those obligations. Alternatively
it is said, if the reservation of rights in
cl 4 had a subsisting operation, no damages could be claimed from the time
of execution
of the Variation Agreement as BHP-IT was not thereafter guilty of
any delay in performing its obligation to deliver the Developed
Software. It
was performing the Head Contract as amended according to its terms. For
convenience this second contention will be
referred to as the "cap
construction".
1420 GEC Marconi, likewise, advance the cap construction. But its principal
submission is that such were the dimensions of the changes
the Variation
Agreement made to the Head Contract and the Schedules, that an intention was
manifest to rescind that Contract and
to bring into existence a new contract
consisting of the Variation Agreement with its annexed amended versions of the
Head Contract
and the Schedules.
1421 The further submission raised by BHP-IT in response to supplementary
questions was that the cl 8 waiver of "liquidated
damages" was intended to
refer to all Commonwealth contractual rights under cl 39.1 to damages
associated with delay in performance
of the Head Contract by the designated
"Contract Acceptance Date". It is contended that it would make no commercial
sense to waive
damages under cl 39.1(a) (which limited recovery to 5
percent of the contract price - approximately $460,000) while retaining
an
unrestricted right to damages up to the limited in the cl 38 damages cap
of $8.6 million): cf Schenker & Co (Aust) Pty Ltd v Maplas Equipment
and Services Pty Ltd [1990] VR 834 at 837, 840-845.
1422 The Commonwealth's short answer to this submission is that cl 39.1
embodied distinct rights. Sub clause (a) gave a right
to liquidated damages to
be calculated at a designated daily rate up to a fixed maximum sum. Sub-clause
(b) acknowledged the Commonwealth's
independent right to claim unliquidated
damages at common law but that right was subjected to the cl 38 "damages
cap". Clear
express words would have been required to rebut the presumption
that the Commonwealth did not intend to abandon the latter right:
Mancorp
Pty Ltd v Baulderstone Pty Ltd (No 2) (1992) 60 SASR 120 at 126-127. The
Variation Agreement was executed after this litigation had been initiated
(including the cross-claim
against the Commonwealth), and as the 5% liquidated
damages ceiling was by that time unlikely to represent the true measure of loss
to the Commonwealth, the waiver of the cl 39.1(a) right alone had a
sensible explanation.
(d) Applicable Principles
1423 I have referred earlier in these reasons to the canons of construction to
be applied in construing commercial contracts: see
Part II: The Proper
Construction and the Applicability of Sub-Clauses 40.8 and 40.9. I will not
repeat what I there said, other than to
note (i) that, where there are
competing interpretations, an interpretation that best serves the commercial
purpose of the contract
is to be favoured: see Lewison, The Interpretation
of Contracts, paras 1.06-1.07 (2nd ed); Spunwill Pty Ltd v
BAB Pty Ltd (1994) 36 NSWLR 290 at 299; Di Dio Nominees Pty Ltd v Brian
Mark Real Estate Pty Ltd [1992] 2 VR 732 at 740-741; Concut Pty Ltd v
Worrell (2000) 176 ALR 693 at [54], [56]; and (ii) that, as the whole of a
written instrument is to be considered in the process of construction,
there is
a presumption against surplusage: Big River Timbers Pty Ltd v Stewart
(1999) 9 BPR 16, 605 at 16,606.
1424 I have also made reference earlier to aspects of the law on contract
variation: see Part II: The Emulation Variation Agreement. It is appropriate
that I make the following additional observations here. The principles
governing
the effect a contract of variation may have on the contract it varies
are settled, even if they do some violence to "strict logic":
Tallerman
& Co Pty Ltd v Nathan's Merchandise (Victoria) Pty Ltd [1957] HCA 10; (1957) 98 CLR 93
at 135; Wilken and Villiers, Waiver, Variation and Estoppel, paras
2.26-2.36. The variation contract may effect (i) a complete discharge of the
original contract and the substitution of a
new contract in its stead; (ii) a
partial discharge of the original contract with or without new terms for those
discharged; or
(iii) the addition of new terms without any partial discharge.
The determining factor is the intention of the parties as disclosed
in the
variation agreement: Tallerman & Co Pty Ltd, above, at 145;
Federal Commissioner of Taxation v Sara Lee Household & Body Care (Aust)
Pty Ltd [2000] HCA 35; (2000) 172 ALR 346; Concut Pty Ltd v Worrell, above, at
698-699.
(e) Conclusions
1425 Before considering the principal controversy between the parties as to the
effect of the Variation Agreement, I should refer
to the discrete supplementary
submission made by BHP-IT concerning the cl 8 waiver of rights to
liquidated damages. I am in
general agreement with the submission made by the
Commonwealth. Clause 39.1 and the Schedules do maintain the liquidated
damages/unliquidated
damages distinction. I can see no justification in
contriving the cl 8 reference to "rights to liquidated damages" as if it
embodied the parties own dictionary meaning of the description - a meaning that
encompassed "unliquidated damages". Moreover, I
am of the view the
Commonwealth's retention of its right to claim unliquidated damages can
properly be said to reflect a reasonable
commercial judgment at the time. This
litigation had been initiated. As I will indicate below, if BHP-IT was found
liable to the
Commonwealth for delay occurring after the expiration of the
Contract Acceptance Date, any such liability could be passed on in turn
to GEC
Marconi. The Variation Agreement itself acknowledged GEC Marconi as the party
responsible for frustrating the performance
of the original Head Contract.
1426 I turn now to the principal controversy. Notwithstanding the significant
differences between the original Head Contract and
the amended Head Contract
(most particularly in relation to the manner of performance of each under their
respective Implementation
Plans) I am satisfied that the parties intended in
the Variation Agreement to partially discharge the original Head Contract and
to substitute new terms, and not to discharge it totally and to substitute a
new contract for it.
1427 The textual indications of this intention in the Variation Agreement
itself are clear enough as both the Commonwealth and BHP-IT
have pointed out in
their submissions. Its declared purpose was to amend; not to discharge.
1428 Much more problematic is the question of the extent of the variation of
the parties' rights and obligations it intended to make.
1429 It probably was the case that cl 3 of the Variation Agreement (which
varied the original Head Contract and Schedules) was
itself sufficient to bring
about a varied contractual relationship in which BHP-IT was no longer required
to perform in accordance
with the unamended Head Contract and Schedules but was
now obliged to perform in accordance with the amended Contract and Schedules.
These were the inexorable consequences of the parties agreeing to cl 3.
1430 But the Variation Agreement left nothing to doubt. The Commonwealth
expressly released BHP-IT from any further obligation to
perform as required
under the unamended Head Contract: cl 5. And it was agreed that BHP-IT
would perform as required by the
amended Head Contract and Schedules:
cl 6. Considered simply in light of cl 3, one could conclude readily
enough that
cl 5 and cl 6 did no more than emphasise unequivocally
what was the effect of cl 3 in any event. But does the Variation
Agreement construed as a whole require a different conclusion? In my view, it
does not.
1431 The Agreement on its face had two principal purposes. One was the
prospective one of providing for the future performance of the Head
Contract - ie "to facilitate the completion of the project". As what was
proposed cut across what had already been done (most notably in relation to
Milestone payments already made), provision needed to
be made to harmonise what
had been done with the performance that was proposed. For this reason the
Variation Agreement made express
provision both to recover milestone payments
2000 and 3000 (which were inconsistent with the new milestones 2000 and 3000)
and to
relieve BHP-IT of obligations it had under the Financial Undertakings it
had given in respect of those two milestone payments.
1432 The second and quite separate purpose of the Variation Agreement was the
retrospective one of addressing the rights which had arisen under the
original Variation Agreement in consequence both of its performance and of
GEC
Marconi's actions in "frustrat[ing] its performance". It is not surprising
that it did this. Though it was entered into after
almost a year of
negotiations, the Variation Agreement was executed under the shadow of the
litigation initiated by GEC Marconi.
The Commonwealth had only recently served
a Notice of Breach on BHP-IT. And BHP-IT had made its cross-claim against the
Commonwealth.
As BHP-IT rightly submits, the tone and tenor of the Variation
Agreement portrays GEC Marconi as the party whose wrongful conduct
created the
need for the agreement, and BHP-IT as a party that had not sought to escape
from the commitment it made under the original
Head Contract.
1433 It is noteworthy, as a matter of emphasis that cl 4.1 of the
Variation Agreement (the Reservation of Rights clause), in
fact, preceded
cl 5 and cl 6. Like those two clauses, it was probably strictly
unnecessary: see Mancorp Pty Ltd v Baulderstone Pty Ltd (No 2), above,
at 126-127. But it emphasised that existing rights were being preserved. Each
party reserved any rights it might have under
the contract in relation to any
claim that GEC Marconi or the other party might bring. And no claim between
"the Commonwealth and
BHP-IT ... [was] waived" except as specifically provided
for in the Variation Agreement. Several such claims were specifically provided
for (eg in cl 8 and cl 12). The Commonwealth's accrued right to sue
BHP-IT for damages for delay in delivery of the Developed
Software was not one
of these.
1434 Given the litigation climate to which I have referred, I consider the
failure to waive this claim as being intentional and,
contrary to BHP-IT's
submission, as not being contrary to business common sense. When the Variation
Agreement was executed there
had been an almost two year delay in the
performance of the Head Contract. That occasioned loss to the Commonwealth and
it was a
consequence of what were perceived to be the wrongful actions of GEC
Marconi. The Commonwealth's retention of its right permitted
that loss
ultimately to be passed on by BHP-IT to GEC Marconi if it was found to be the
wrongdoer in the legal proceedings it had
initiated. And as I will indicate
below, the Variation Agreement necessarily limited the period of the delay
claim to that which
ran from the time of breach until the execution of the
Variation Agreement. The loss from this delay could only be sheeted home
to
GEC Marconi if, first, it was sheeted home to BHP-IT. I merely note in passing
that GEC Marconi has taken a live interest in
this proceeding in challenging
the actual damages sought by the Commonwealth.
1435 To conclude then, I consider that cl 4 on the one hand, and cl 5
and cl 6 on the other, addressed quite different
subjects. The latter
addressed BHP-IT's performance obligation for the future; the former, rights
arising from what has already
transpired. I see no reasonable basis for
construing the clear words of cl 5 in the manner proposed by BHP-IT. They
simply
do not, and were not intended to, address the question of acquired
rights.
1436 I am satisfied, then, that BHP-IT's primary submission must be
rejected.
1437 I have already foreshadowed my conclusion on the "cap construction". The
Variation Agreement can properly be characterised
in BHP-IT's terms as
requiring a "starting from scratch" performance of the amended Head Contract by
BHP-IT. It did much more than
extend the time at which BHP-IT was to deliver
the Developed Software. It recognised that a new state of affairs existed and
it
created a new mode of performance in conformity with which BHP-IT was to
develop and deliver the software. BHP-IT's performance
was no longer to be in
accordance with the terms of the unamended Head Contract. From the date of the
Variation Agreement, that
contract was no longer to be performed according to
its terms and BHP-IT could not be held liable in damages for not so doing or
for delay in so doing.
1438 BHP-IT's alternative submission is that, until it delivered the Developed
Software under the amended Head Contract, it continued
to incur liability for
the loss suffered from its failure to perform the unamended Head Contract
according to its terms. I do not
agree. From the date the Variation Agreement
took effect, it was not open to BHP-IT to perform the unamended contract. The
parties
had agreed otherwise. And by so doing they brought to an end the
period in which BHP-IT's liability for delay in performance ran.
BHP-IT was
now engaged in a different performance albeit the ultimate deliverable - the
Developed Software - was substantially the
same as under the original
contract.
1439 This conclusion is, in my view, in accord with the commercial purpose of
the Variation Agreement. The Agreement marked the
"resumption" of the ADCNET
project (cf the amended Schedule 8, Milestone 1000) and the end of the period
of delay in it. It is unlikely,
in my view, that reasonable parties in the
position of the Commonwealth and BHP-IT, having negotiated an agreement for the
renewed
performance of the ADCNET contract with changed milestones but an
unchanged contract price, would nonetheless have intended that
each and every
minute of the performance of that contract could sound in damages for delay for
BHP-IT's not having performed the
original Head Contract according to its
terms. If this was to be the case notwithstanding this particular Variation
Agreement, it
would have required an express term to that effect.
1440 I should add that I do not regard the cl 4 preservation of rights as
requiring me to arrive at a different conclusion.
The Commonwealth's right to
sue BHP-IT for breach of the original contract was an accrued right which was
preserved by cl 4.
What the Variation Agreement did was not to destroy
that right but, rather, to limit the damages that could be claimed in reliance
on it. This it did by bringing to an end the period of delay in performance of
the original head contract for which damages would
accrue. It put it beyond
BHP-IT's power to complete performance of the original Head Contract. BHP-IT
was thereafter to enter upon
the performance of the amended Head Contract.
1441 My conclusion, then, is that the alleged losses suffered on and from the
date the Variation Agreement took effect are not recoverable
by the
Commonwealth. Those that began to be incurred prior to that date (eg in
relation to continued project management) but which
continued thereafter lost
their compensable character on and from that date.
2. THE INDIVIDUAL HEADS OF CLAIM
(1) Retention of the IBM Classified Message Switch System
1442 This claim is based on a counterfactual. At the time of the ADCNET
contracts the IBM System provided both the message switch
and the boundary
security functions for the Department's communications network. The ADCNET R3
message switch software was to provide
the former but not the latter of these
functions. In consequence, even if it had been delivered on time before the
IBM System could
be decommissioned, a replacement boundary security mechanism
would have had to have been obtained.
1443 The IBM System was decommissioned on 23 June 2000. The new message switch
function was performed by what was known as the Expedited
Release 3 software
("ER3"). This software, which was a subset of the ADCNET R3 software, was
developed by BHP-IT pursuant to Change
Request 7 ("CR007") which was agreed to
on 5 September 1998. ER3 was delivered to DFAT on 31 August 1999. The new
boundary security
function in turn was performed by UNCLGUARD, a software
gateway, which was developed by DFAT. Its use was endorsed by DSD on 15
May
2000 shortly prior to the decommissioning of the IBM system.
1444 DFAT's claim is that, if the Canberra System Developed Software had been
delivered on 9 February 1996, it would have developed
a security gateway
mechanism that would have enabled the IBM System to be decommissioned prior to
November 1996 when it was in fact
moved to the RG Casey Building.
1445 The counterfactual with which I am concerned is whether, and if so when,
prior to 23 June 2000 the Commonwealth would have developed
or procured and
then implemented an alternative boundary security mechanism to the IBM System.
If it was after the execution of the
December 1997 Variation Agreement, this
claim must fail for the reasons I gave above. The assumption I am required to
make in this
is that the Commonwealth obtained the R3 software on 9 February
1996.
1446 To appreciate the basis of the submissions of BHP-IT and GEC Marconi it is
necessary to refer at some little length to the actions
taken by DFAT between
1996 and 2000 to implement an alternative mechanism. Before doing so there is
one concept to which reference
will be made which should be explained. It is
the concept of "cutover of software".
1447 Les Cook explained it in the following passage of evidence when discussing
the actual decommissioning of the IBM message switch.
"The IBM message switch was connected via communication lines to a large number of other computing systems in all of the Department of Foreign Affairs & Trade's overseas posts and to quite a number of other government organisations in Australia. The main part of the cutover was progressively to reconnect each of those lines from the old message switch to the new one, which, in each case, entailed some changes to the system at the other end of the communication line - at the post or at the other government organisation. The task of preparing for, performing and then checking the results of those reconnections is time consuming and took - it in fact took some six months from the start of the process of using the new software to the point at which all of the external systems and all of the internal processing was now being done using the new message switch rather than the old one. In the interim both systems were performing their tasks connected to - each connected to a subset of the total external environment."
(a) Factual Setting
1448 Since at least August 1992, DFAT had planned to move from its then home in
the Administration Building to the RG Casey Building
in around mid-August 1996.
The ADCNET contracts when executed in September 1994 provided for the delivery
of the R3 software integrated
with the STUBS devices within a timeframe that
would allow the IBM System to be decommissioned prior to the move in 1996.
1449 Les Cook's 27 March 1995 "STUBS Alternative" paper that was prepared for
the SPC suggested that to implement Option C would
occasion a delay of "perhaps
3 months" although it went on to acknowledge the "possibility that delays will
cause the IBM not to
have been replaced before the move to the new
building".
1450 The minutes of the SPC meeting of 25 May recorded that "[t]he time frame
for building an alternative to STUBS into ADCNET has
passed".
1451 In his change of tactics memoranda of 17 and 22 June Les Cook expressed
the views that if Option C was "firmly" decided on at
that time "it [was]
possible, but not certain" that moving the IBM to York Park could be avoided.
He expressed a like view in relation
to the "deferral" option (ie deferring a
decision until September/October 1995).
1452 By the time CR3049 was raised DFAT was envisaging that the R3 software be
completed and tested using STUBS emulation. The cancellation
of STUBS did not
change that. What it did do was raise the need for "a strategy to replace
these devices". It now envisaged that
this would "be agreed by all parties
including the Department's security authorities and DSD": Les Cook's 26
September 1995 letter.
CR3052 was raised the same day. It related to the
feasibility of the STUBS replacement strategy.
1453 By this time a further option, Option D, was being advanced by Les Cook
and Mr Nichols. This was an enhanced version of Option
C, the enhancement
being "the encryption of unclassified documents ... from ADCNET": Nichol's
minute of 25 September 1995.
1454 The use of Option D had previously been raised by Les Cook with the ADCNET
Security Sub-Committee on 22 September 1995. The
minutes of that meeting
record the following:
"4. Mr Cook said they had commenced work on deciding how to build Option D. ... We will work with the PSI to see how to change the contract. But until we work out how it will fit into ADCNET we cannot estimate the cost impact, at the moment Option D is the only alternative we have and the committee should endorse that as we will quickly locked into this option. Emphasis added.
5. Mr Allen said there was a disposition with the Executive to go with Option C. If Option D, using the KG84s, can better protect us from external attack then we should go with that option. We need DSD's assistance with this too. Mr Cook said he and Mr Rogers had been through this and he is full aware of the proposal, for which Mr Cook will provide documentation for DSD. Mr Allen asked if it would protect against software errors. Mr Cook said it was about E3 protection against hostile software and better than E3 against the hacker. All the normal paths of attack are certainly closed. Mr Allen suggested we go ahead with the development and testing as soon as possible."
1455 On 25 September 1995 Les Cook sent a minute to both the ADCNET Sub-Committee and DSD providing the advice of the IT Branch and the ADCNET Project Management Team on Option D. That minute noted (inter alia) that the "major vulnerability of option C was considered to be the possibility of attack via the gateway, judged to be the most probable form of attack". The advice given was (inter alia) that:
"Option D is recommended as providing the required level of functionality and the highest level of security which is considered practical in the ADCNET environment, particularly with regard to prevention of external attack."
1456 On 21 November 1995 the ADCNET Security Sub-Committee again considered
Option D. At that meeting Les Cook (who had no recollection
of the meeting) is
recorded as having said that he saw the use of Option D as a better means of
boundary security for ADCNET than
any other system that was currently
available.
1457 The minuted record of discussion of Option D included the following:
"Mr Allen asked if DSD had had a chance to look at Option D. Mr Rogers said DSD were happy with Option D as it was substantially stronger than previously proposed options. It doesn't answer all the questions, only a STUBS could do that, and so it would only reach an E2 level. However it's difficult to say when a better proposal will come along in the foreseeable future. Mr Skinner said that Option D would be in place for at least four years. Even if a new solution were to come to the fore, it would take that long to find the funds and retrofit throughout ADCNET. Mr Allen asked if there would be a problem getting DSD endorsement of Option D. Mr Rogers said they would suggest the level of residual risk and it was up to the department to accept that. At the moment, Option D looks like the best available."
1458 The committee agreed to endorse Option D on the basis proposed by Mr Skinner:
". We will proceed with Option D after advising Executive that the committee has endorsed the option.
. Advise Executive that it is the best level of security currently available.
. E3 is the best level of security we can deliver. Should better technology come along then the department should again consider its options.
. We inform Executive that DSD, as part of the committee, has concurred with this decision."
The "Executive" referred to is, I infer, the Senior Executive.
1459 On 7 December 1995 approval was given for scoping CR3057, the STUBS
replacement change request using KIV-7 (Option D).
1460 By the end of December 1995 it was apparent that progress on using
encryption for boundary security purposes had "not been as
smooth as hoped or
anticipated". KIV-7 by then was known (from work done by DFAT officers) to
have several problems associated with
its use and in particular with its
reliability at higher speeds of operation. It is Les Cook's evidence that he
was aware of these
problems in September 1995 when he issued CR3052. In
January of 1996 he was still confident that KIV-7 was a suitable substitute
for
STUBS and was "the best option we had". KIV-7 retained his "strong support" in
1996, 1997 and 1998.
1461 On 6 February 1996, following on discussions it had with Les Cook in late
January, a company, Compucat Pty Ltd, sent proposals
to DFAT for the joint
development of a `trusted' gateway for ADCNET. Les Cook's evidence is that
these discussions were the product
of an approach by Compucat and did not
reflect his looking elsewhere because of concerns about KIV-7.
1462 9 February 1996 was the date on which the Canberra System Developed
Software was required to be delivered under the Head Contract.
1463 DFAT's move to the RG Casey Building was completed in November 1996. The
IBM System was one of the last items to be relocated.
1464 It is now necessary to turn to two separate developments, one relating to
the development of ER3; the other, to the development
of UNCLGUARD.
1465 First ER3. To anticipate matters, the purpose of the ER3 was to replace
the IBM message switch (but not the use of the IBM
system as a secured
gateway).
1466 By August 1997 Mr Brent wrote in an Exit Brief he prepared - Mr Rentz was
taking over as BHP-IT's project manager - that DFAT
had a "sense of urgency
about [the] issues" of building a new minimal message switch and of developing
a secure messaging gateway.
He described the background to these issues in
that brief in the following way:
"DFAT are incurring significant costs due to delays in the delivery of Release 3 under the contracted schedule DFAT were to de-commission the IBM message switch following formal acceptance of the ADCNET system.
In the event DFAT are required to continue the operation of the IBM message switch until such time as ADCNET becomes available.
In the absence of STUBS there is another reason for maintaining the IBM and that is that DSD have approved the use of the IBM as a secure gateway. ...
Thus DFAT are keen to replace the IBM but are not in a position to do so until a secure messaging gateway is available.
Following the demise of STUBS, DFAT embarked on the development of a sealer and a messaging gateway based on military grade encryption devices.
This project titled `SMOG' has been in progress for about 18 months and a proof of concept prototype has been developed by DFAT with assistance from BHPIT (Richard Elliott).
There are still some issues associated with SMOG, which need to be resolved and the project taken from a proof of concept prototype to a working production model.
Therefore DFAT would like BHPIT to build:
. the minimal message switch which represents about 63% of the total requirements for the Canberra switch;
. the secure messaging gateway to enable the minimal switch to operate.
The BHP-IT position is that:
. BHP-IT is currently reviewing the DFAT definition of the minimal message switch;
. BHP-IT is currently reviewing the concept of the secure messaging gateway - which, if accepted would represent an additional scope of work to be performed on a Time and Materials basis."
1467 Early in 1998 the person in DFAT responsible for the modification and
maintenance of the IBM message switch suffered a serious
illness. It would
seem he was the only person who possessed a detailed knowledge of how to repair
the message switch when it failed.
His illness caused the Information
Management Branch ("IMB") - the successor to the IT Branch - to develop a new
"Contingency Approach".
The final version of the recommendations of a working
party established for this purpose reported to Kim Jones on 17 April 1998.
It
proposed the development of ER3 and made a recommendation that this be accepted
by the IT Executive. On 14 May 1998 the Senior
Executive approved the ER3
Contingency Plan and authorised negotiation for a change request.
1468 On 29 April 1998 Mr Rentz raised CR007 which related to the replacement
message switch. After the approval given by the Senior
Executive negotiations
for the ER3 development were entered into and led to the signing of CR007 on 2
September 1998.
1469 BHP-IT commenced work on ER3 related tasks in anticipation of formal
agreement. Work continued on ER3 until mid-1999. On 6
August 1999 DFAT was
informed that all acceptance tests for the ER3 Developed Software had been
completed. A certificate of acceptance
for delivery of the software was issued
by BHP-IT on 31 August 1999.
1470 Secondly, the secure message gateway: UNCLGUARD. After rejecting GEC
Marconi's CR3078 $8 million proposal, DFAT advised BHP-IT
and GEC Marconi on 20
May 1996 that it would deploy the ADCNET software using the IBM System to meet
its security requirements.
By letter of 30 May 1996 it informed BHP-IT
that:
"DFAT will bear the cost of developing additional equipment and/or software to increase boundary security so that the IBM can be removed from the configuration; this work will be performed outside the scope of contract ITB/002."
1471 Consistent with the proposal in CR3057, it continued thereafter until
at least mid-1998 to investigate and evaluate versions
of KIV-7. I need not
detail the evidence of this other than to note that a version of KIV-7
("SMOG"), was noted to be a possible
future substitute for STUBS when the FRS
changes were agreed in August/September 1997.
1472 The issue of the level of ITSEC assurance required for boundary security
was a matter considered by the ADCNET Security Sub-Committee
in 1997. Minutes
of the Sub-Committee's 17 December 1997 meeting contain the following:
"6. It was suggested that the next meeting should also consider the fact that "Boundary Security" is still required, and that a secure gateway is necessary. However, it was also noted that this is still probably several years away.
7. Noted also that if we move away from E3 then it is probably impossible to achieve a secure gateway, which another organisation needs to build. This work is currently in the hands of DSTO. Also noted that if we don't have a secure gateway there are only two alternatives:
i. continue to keep the old IBM mainframe running, or
ii. keep the unclassified material on NNS and the classified on ADCNET (which creates user problems with revisable documents)."
1473 After the Senior Executive had approved the ER3 Contingency Plan, Les Cook took BHP-IT's ER3 proposals to the ADCNET Steering Committee on 14 August 1998. The minutes record, amongst other things:
"ER3, as specified by the BHPIT proposal, will not provide an assured security gateway to allow delivery of cables to non-Secret environments. For reasons relating to the Release 3 litigation, it will be delivered with the STUBS emulation of sealing and gateways. DFAT has not yet determined its strategy for implementing a fully assured gateway. DFAT and BHPIT will need to negotiate the addition of the selected gateway to ER3. Prior to this being completed, cutover to ER3 can commence with the retention of the IBM message switch in the role of security gateway. This will delay the reduction in operational costs resulting from decommissioning of the IBM but will still reduce the level of dependence on it compared to its present role."
1474 By 12 February 1999 internal DFAT documentation was recording that DFAT would decide "longer term gateway configuration soon". A DFAT minute of 29 July 1999 that was concerned with the tasks remaining to be performed to allow the decommissioning of the IBM System noted under the heading "Security Gateway" that:
"The urgent need is for a decision on what to build/buy. Several options are on the table, including UNCLGUARD as proposed by Hugh Kellow and refined with Kannan and myself. The key action is to decide how much to involve DSD, given that they are likely to have (valid) reservations about each."
1475 DFAT minutes of 2 August (and later 30 August 1999) contain recommendations for the use of UNCLGUARD as the "most practical solution". The minute concluded:
"That the proposed method of implementing a security gateway for the cables service be approved, subject to it being replaced at some time when a more secure and operationally acceptable solution becomes commercially available;
That a competent independent company be contracted to perform a security audit of the gateway design and implementation, but not a formal evaluation to the ITSEC criteria;
That DSD be asked to advise on the level of residual risk if the gateway is implemented and audited as proposed;
That the residual risk be accepted provided that it is not greater than that currently accepted."
1476 A "Cut-Over Plan" of 5 August now included planning for the use of
UNCLGUARD as the security gateway.
1477 A memorandum prepared by the Australian Government Solicitor in late
August 1998 to accompany instructions to an expert who
was to be engaged to
quantify the Commonwealth's losses arising from the BHP-IT's failure to provide
the Developed Software in February
1996, expressed the view that:
"[i]f the Commonwealth wishes to recoup its expenditure for maintaining the Classified IBM System the implementation of the secure gateway should be completed within six months of the delivery of the rescheduled and accelerated ADCNET software. The establishment of an alternative (to the STUBS devices) gateway later than six months will throw into doubt the causal link between the keeping of the Classified IBM System operational and the failure of BHP Information Technology to deliver the ADCNET software under Contract ITB 002."
1478 I note the above as BHP-IT have relied on it in submissions as
indicating why UNCLGUARD was adopted.
1479 There is no evidence before me as to how, and by whom, the decision to
implement UNCLGUARD was taken.
1480 An independent consultant, Damian Farrell was engaged by DFAT to project
manage the implementation of ER3 and the development
of UNCLGUARD. In that
role he produced a "Gantt Chart" entitled "ER3 Cut-over - Security Gateway -
Decommission Classified Mainframe
Project". That document identified
activities undertaken in the development of UNCLGUARD and the periods of time
when they were
undertaken. The chart suggests that systematic development
commenced in early August 1999 although a Table he prepared for his witness
statement has several persons devoting 100 per cent of their time to UNCLGUARD
from July 1999 - or in Les Cook's case, 20 per cent
of his time.
1481 In cross-examination Mr Farrell indicated that the project he was managing
had to finish before the end of the financial year.
His "critical deadline"
was 30 June 2000. "That was when the [IBM] mainframe lease was to run out".
He accepted that this was the
imperative behind completing the development of
UNCLGUARD by that date. He was then asked whether DFAT would take shortcuts
for
the purpose of developing UNCLGUARD with accepted risks, and he replied:
"It took shortcuts. We tried to come up with a system that could in fact be developed within the time. That's true. Some of the other proposals looked at could not be completed within time. One of the big issues was to make sure we had DSD approve the system because they also had to test it. They were also the ones who had to give us accreditation."
1482 As the 2 August 1999 UNCLGUARD recommendations indicated it was not
intended that the gateway be evaluated in accordance with
ITSEC criteria. The
"independent company evaluation" that was envisaged was provided by Admiral
Management Services ("Admiral")
in early May 2000. Admiral believed that
UNCLGUARD should meet the security requirements documented in its
specification, provided
that DoD gave a favourable report on a particular
matter and DFAT was willing to accept a stated risk.
1483 On 15 May 2000 DSD provided its assessment of the security architecture
and design. It commented:
"a. Our policy is to recommend that gateways between SECRET level networks and IN-CONFIDENCE networks connected to the Internet should be AISEP evaluated to ITSEC E5 assurance. However, it is accepted this is not practicable within the implementation timeframe: emphasis added.
b. Given the practical constraint that the gateway is based on COTS products with no formal level of assurance, then DSD considers the overall security architecture to be acceptable. This opinion is in agreement with the Admiral assessment (reference A)."
1484 UNCLGUARD was accredited by DFAT as its security gateway.
1485 Before turning to several matters raised in oral evidence and witness
statements, I would note:
(i) from September to December 2000 the ER3 software was modified so as to
operate with UNCLGUARD the original software having been
developed with STUBS
in mind;
(ii) the "cut-over" of the ER3 software commenced in January 2000 and finished
in March 2000;
(iii) UNCLGUARD commenced operation in parallel with the IBM System at the
beginning of June 2000; and
(iv) The IBM System was decommissioned on 23 June 2000.
1486 Les Cook's evidence in chief was that, with adequate resources, the
UNCLGUARD gateway could have been developed and approved
within six months
allowing the cutover of functions from the IBM classified to be finished before
completion of the move to the RG
Casey Building.
1487 As to the time of actual development of UNCLGUARD, Les Cook expressed the
view that the development of the security gateway
could have started at any
time a decision was taken but that it would have been preferable to perform the
security gateway either
after the ADCNET software was delivered or at least at
a later point in the development of that software.
1488 On the same subject, John Crighton (who was head of the IBM Branch from
May 1999), gave the following evidence:
"When I took up the position of AS IMB there was active discussion amongst my staff, and with security advisers within the department and the Department of Defence, of alternative approaches to implementing a secure gateway that would work in conjunction with the new message switch software. The decision on which approach to take in relation to the secure gateway was not made until the new message switch software had been developed and is delivery reasonably assured. In or around July 1999 I decided that the Department should proceed on the basis of a security gateway developed "in-house"."
1489 Finally, Mr Farrell gave evidence that detailed design of UNCLGUARD
could not be undertaken until ER3 was completed but conceptual
design could
have been undertaken prior to then.
(b) Findings and Conclusions
1490 The Commonwealth's primary submission is that in the nine months between
when BHP-IT should have delivered the Canberra System
Developed Software and
when DFAT had to move the IBM Classified System in November 1996, Les Cook's
Option C could have been developed,
approved and made operational. This was
achievable. In 1999, when the development of UNCLGUARD commenced, there was no
pressing
urgency to have completed the task by a certain date. Such a need
did, however, exist in 1996 and, in the Commonwealth's submission,
had DFAT
been required to develop a security gateway mechanism at that time, it would
have devoted more resources to ensure the task
was completed by the time the
DFAT had to vacate the Administrative Building.
1491 For its part BHP-IT contends that any damage the subject of the
Commonwealth claims associated with the continued use of the
IBM, including of
its relocation from the Administration Building to the RG Casey building (also
referred to as "York Park") in late
1996, and its subsequent use as the interim
security gateway for the ADCNET software, was incurred as a direct result of
the Commonwealth's
conduct in:
(i) cancelling the procurement of STUBS for the ADCNET project;
(ii) failing to procure or provide an alternative security, or gateway, device
within the timeframe of the Head Contract;
(iii) implementing its deliberate strategy to rely upon the IBM in the absence
of a security gateway device (be it STUBS or some
other device in lieu of
STUBS).
Those losses, it is said, continued up until the time the IBM was
decommissioned by the Commonwealth on 23 June 2000. BHP-IT submits
the
evidence shows that, even if BHP-IT had delivered the Release 3 software in
February 1996, the Commonwealth would not have implemented
an alternative
security gateway any earlier than the time it actually did.
1492 GEC Marconi's submissions reflect those of BHP-IT. The claim that DFAT
could have decommissioned the IBM System by November
1996 is challenged,
though, on a separate ground. It is contended that the delivery date was not
in fact 9 February, but that DFAT
was obliged to grant a further eleven weeks
extension for delay. This delay is the subject of the delay claim made by GEC
Marconi
against BHP-IT which has been considered earlier in these reasons: see
Part II: The Delay and Prolongation Claim. My findings in relation to that
claim are fatal to this separate submission of GEC Marconi.
1493 In my view, there are two critical dates that bear on the Commonwealth's
claim. The first is the end of November 1996 when
the IBM System was
relocated. The second is the date of execution of the December 1997 Variation
Agreement.
1494 The significance of the first of these two dates is that if DFAT could not
have selected, developed and implemented an alternative
security gateway by
then, then it was inevitable that the IBM System be relocated to the RG Casey
Building to perform the boundary
security function for the ADCNET system. Such
a relocation would, in my view, be likely to have affected significantly DFAT's
decision-making
in relation to the selection of an alternative to STUBS.
1495 The significance of the date of the Variation Agreement flows from my
earlier holding. From that date such losses as flowed
from the non-delivery of
the Canberra System Developed Software were not compensable in any event. For
this reason it is important
to determine whether, on the counterfactual
assumption upon which this claim is based, DFAT would have developed and
implemented
a security gateway before or after that date (assuming it would not
have done so by the end of November 1996).
1496 Before indicating my own conclusions I should make this comment upon the
nature of the hypothetical "factual" inquiry raised
by this claim. I am
required to make the counterfactual assumption that BHP-IT delivered the
relevant software on 9 February while
disregarding the improbability of earlier
events having occurred as and when they did. I would merely instance that if
BHP-IT had
been ready to deliver the software on that date, the story of the
cancellation of STUBS and of its timing could well have been very
different.
Be this as it may.
1497 As to the first of my critical dates - November 1996 - I am satisfied that
there would have been simply no prospect of an alternative
security gateway
having been implemented by that date. I accept that DFAT had long cherished
the ambition of decommissioning the
IBM System before the move to the RG Casey
Building and it had set its contractual delivery dates with this in mind. What
would
have prevented it achieving its ambition was the timing of its
cancellation of STUBS and the course it then committed itself to in
developing
an alternative to STUBS.
1498 At the time of the STUBS cancellation it was not simply a matter of
adopting Option C. Before the formal notice of cancellation
was given on 26
September 1995, Option D was being proposed both to the ADCNET Security
Sub-Committee and to DSD. DSD, it will be
recalled, only endorsed Option C as
an interim measure in its minute of 9 June 1995. A clear reason assigned for
the change to Option
D was that it provided a better means of boundary security
for ADCNET than any other system that was then available. Option D was
designed to retain the flexibility of Option C while strengthening against the
threat of attack considered the most probable and
which was the "major
vulnerability of option C".
1499 I now refer to what I regard as a characteristic of decision-making in
DFAT revealed in this proceeding. At its best it could
be described as
measured; at its worst dilatory. Four weeks after it was first canvassed with
it, the Option D proposal was accepted
by the ADCNET Security Sub-Committee on
21 November 1995. The Senior Executive was to be notified of this. Discussion
of that acceptance
noted that DSD was of the view that Option D was
"substantially stronger than previously proposed options". And Mr Skinner
stated
that it would be in place "for at least four years". And so CR3057 was
raised.
1500 In its submissions the Commonwealth describes Option D as being simply
Option C with encryption. It goes on to ask me to infer
that, if the Developed
Software had been delivered in February 1995, DFAT's Senior Executive would
there and then have dropped the
use of encryption and would have chosen Option
C without hesitation. The pursuit of Option D would not have been allowed to
interfere
with the imperative of developing a security gateway to enable the
IBM System to be decommissioned before the move to the RG Casey
Building.
1501 I do not accept this. Without pausing to consider how, in the
hypothetical world of present interest, DFAT would have dealt
with BHP-IT over
CR3057 and the offered participation in the development of a STUBS replacement,
I would say that the Commonwealth's
submission assumes too much.
1502 I preface the following with the observation that no officer of DFAT at
the time was asked to proffer a view on how, in that
person's opinion, DFAT
might have acted including in relation to resource allocation if the Developed
Software had been delivered.
It was left to Les Cook, a consultant, to venture
views on this matter. I agree with the criticism made by GEC Marconi of Les
Cook's
evidence in this regard.
1503 DFAT had sound reasons for committing itself to Option D. I do not accept
that those reasons would have been considered to
have been of such marginal
importance as would have justified the abandonment of Option D in favour of
Option C for some temporal
advantage and cost saving relating to the timing of
the IBM System's decommissioning. The weakness exposed in Option C was
represented
in a way that would have made going back on the Option D decision,
without more, difficult to defend - especially in light of DSD's
earlier
recommendation that Option C be regarded as an interim measure and the nature
of its support for Option D.
1504 My impression of the senior decision makers in DFAT, typified by Kim
Jones, is that they were cautious and, on occasion, somewhat
risk averse. I
imply no criticism in this. They had a responsibility that Les Cook did not.
If it had crossed anyone's mind at
the time to reconsider the Option D
decision, I do not consider that the ADCNET Security Sub-Committee or the
Senior Executive would
have hastened to a decision to abandon Option D. I
agree with GEC Marconi's submission that Option C (or UNCLGUARD) was not
something
that DFAT would have had in its mind in February 1996 if the ADCNET
system had been delivered. Even assuming to the contrary, I
consider that
considerable deliberation would have occurred and consultation would have been
had with DSD, before any decision to
abandon Option D without further
investigation was taken in favour of Option C. The hierarchical pattern of
recommendation and decision
would have been followed. Option C had its
sceptics even before the advent of Option D.
1505 I am satisfied that, having committed itself with DSD blessing to the
investigation of Option D, DFAT would have persevered
in that course
notwithstanding what would have been its obvious implication for the
decommissioning of the IBM System.
1506 Distinctly, I accept, as the Commonwealth has submitted, that not all of
the various steps that were required to be taken to
implement a security
gateway and to decommission the IBM System, needed to be taken sequentially.
Some (but only some) could be done
in tandem (eg the development of the gateway
and the cutover of the message switch software). This said, I do not consider
that
the development of a security gateway (even of an UNCLGUARD variety) would
have been attempted in the time then available. I do
not consider that,
viewing the matter prospectively, DFAT would have run the risk that it would be
able to meet a November decommissioning
deadline even if it took "short-cuts".
Even if it be accepted that UNCLGUARD could in fact have been developed in
about nine months
(which I do not), I am not satisfied that the course taken in
its actual development would have been replicated in the development
of a
security gateway in 1996. By 1999 DFAT had considered, and had sought DSD
advice on, a considerable number of options for gateways.
Though I am unable
to make a positive finding as to how the decision to proceed with UNCLGUARD was
made - I do not accept it was
as a result of Mr Creighton's fiat - it was made
(a) against a background of far greater familiarity with what was available;
(b)
in a setting in which DFAT's IT security policy had been extensively
examined in early 1998; and (c) after a long period of involvement
of DSD in
its consideration of the various approaches to the security gateway
implementation. This may help explain both why an
Option C type gateway could
have been adopted in 1999 and why an ITSEC evaluation was dispensed with then.
A similar confidence in
pursuing an UNCLGUARD type option in the manner in
which it did in 1999-2000 could not have been expected in 1996.
1507 I would add that, contrary to DFAT's submission, I consider that there was
a far greater perceived urgency to build the gateway
and decommission the IBM
System in 1999-2000 than there would have been in 1996. Three converging
forces contrived that urgency.
They were the ill health of the person who
maintained the IBM message switch; the views expressed by the Australian
Government
Solicitor on the Commonwealth's damages claim in the GEC Marconi
litigation; and, most importantly, the "critical deadline" set
by the expiry
of the lease of the IBM mainframe in June 2000.
1508 I thus far reject the Commonwealth's submissions.
1509 The next critical date in the Commonwealth's claim is the date of
execution of the Variation Agreement in December 1997. Given
the manner in
which the parties have framed their submissions - essentially extreme positions
have been taken up - it is more problematic
to make a confident finding as to
when, if at all, before June 2000, the IBM System would have been
decommissioned (on the assumption
being made).
1510 As I will indicate I do not accept the position taken by both BHP-IT and
GEC Marconi that UNCLGUARD would not have been developed
earlier than it was.
However, I consider that the prospects were negligible of that development
occurring prior to December 1997.
1511 It must be borne in mind that the twin assumptions on which I am now
proceeding are that (i) the IBM System had been relocated
to the RG Casey
Building but (ii) it was only being used to supply boundary security, the
message switch function being performed
by the ADCNET software.
1512 The decision having been taken to pursue Option D in November 1995, I am
satisfied that DFAT would have persisted in that course
in much the manner that
it did, while at the same time remaining open to new possibilities as in fact
it was. Les Cook continued
to participate in the investigation of encryption
and versions of KIV-7 as also other possible gateways up until mid-1999. A
letter
from DSD to him of 21 July 1999 illustrated that search as it did DSD's
appreciation by then of the urgent need to replace the IBM
message switch.
1513 Having said this, I consider it quite likely that a decision on a gateway
would have been likely to have been taken at a date
earlier than in mid-1999.
My reason for this view is that, in the events which in fact happened, DFAT
needed both a gateway (its
responsibility) and a message switch (BHP-IT's)
before it could decommission the IBM System. The lack of the latter provided
DFAT
with time in which the options for the former could be explored. In
saying this I am not expressing a view on the question whether
a gateway could
have been selected and developed in advance of, or in tandem with, the
development of the ER3 software. All I am
indicating is that DFAT was not the
master of its own destiny because of its dependence on BHP-IT.
1514 If DFAT had its ADCNET message switch from February 1996, I am satisfied
that it would have been likely to have acted with greater
expedition than it in
fact did. However, I am not satisfied that this would have resulted in the
decommissioning of the IBM system
prior to Variation Agreement notwithstanding
that in 1997 DFAT would not have been diverted (as it in fact was) by contract
negotiations
with BHP-IT.
1515 There is nothing in the evidence before me to suggest that the IBM System
did not operate to DFAT's satisfaction as a boundary
security mechanism.
Nonetheless I am satisfied that DFAT considered that its decommissioning was a
matter of some urgency (as Mr
Brent's August 1997 Exit Brief recognised) - an
urgency that became the more pressing with the illness of the person who
maintained
the IBM System and the approach of June 2000 when the lease of the
IBM mainframe ran out.
1516 I do not consider, though, that that sense of urgency would, in 1996 and
1997, have compromised DFAT's investigation of STUBS
replacement options in
cooperation with DSD. The evidence of Mr Cook's activities up until mid-1999
in this regard does not suggest
that a decision would have been made on an
alternative in 1996-1997. Option D was, as seen from the vantage point of DSD
in September
1995, the best available solution and it was then "difficult to
say when a better proposal will come along". DFAT had every reason
to persist
with Option D variants as Les Cook in fact did for three and a half years. I
am satisfied that even if it had the ADCNET
message switch it would have done
so.
1517 The evidence does not suggest that an Option D variant could have been
adopted in 1996-1997. The only question is when, if
at all, pressure would
have been put on the IT Branch to abandon Option D in favour of a new solution.
If that occurred at all, it
would in my view, have been in early 1998 at the
time of the illness of the person who maintained the IBM. That event was a
clear
spur to action in DFAT. It led to ER3. I consider it probable that it
would have led sooner rather than later to a new security
gateway - the more so
as the limitations of the available options were becoming more apparent by that
time.
1518 It is unnecessary, because of my view of the effect of the Variation
Agreement, for me to reach a concluded view on when I consider
an alternate
gateway would have been likely to have been selected and then implemented after
December 1997. This said, I consider
it more probable than not that resort
would have been had to an Option C strategy in 1998. The same forces that led
DFAT to adopt
ER3 as a contingency plan, would have led to consideration of a
replacement of the IBM System as a matter of urgency. The product
of that, I
venture, would have been the implementation of an UNCLGUARD type gateway
sometime in early 1999.
1519 Because I am satisfied that no STUBS replacement would have been in place
prior to the Variation Agreement, I find that such
loss as was suffered by the
Commonwealth in having to retain the IBM System in operation after 9 February
1996 and until December
1997 was attributable, not to BHP-IT's failure to
deliver the Canberra System Developed Software, but to its own failure to
develop
an alternative to STUBS. The Variation Agreement relieved BHP-IT of
any liability it might have incurred thereafter.
1520 Accordingly I reject this head of claim.
(2) Project Management Costs
1521 The cross-claim describes this head of damages as being the additional
costs for the further engagement of the Project Manager,
Les Cook, beyond the
delivery date of the Head Contract of 29 May 1996, to the projected delivery
date of 19 December 2000.
1522 Evidence was adduced at the hearing in support of this claim. It is fair
to say that it was quite problematic for, while it
showed that Les Cook was
engaged and paid as a consultant by DFAT over that period, it is clear that
some, and probably a considerable,
portion of his activities in that period
were quite unrelated to any possible loss flowing from the breach. Les Cook
was, for example,
engaged (inter alia) in the investigation of boundary
security options over this period and Mr Farrell in his evidence, for example,
attributed 20 per cent of the cost of Les Cook to DFAT from July 1999 to March
2000 to his work on UNCLGUARD.
1523 Needless to say the submissions both of BHP-IT and of GEC Marconi have
focussed on what Les Cook was doing in the relevant period.
It is claimed that
the evidence shows (a) that he was providing services to DFAT in matters
unconnected with project management
of the Head Contract; and (b) that to the
extent that his services had some connection to project management of the Head
Contract
and the development of software, these were services it was always
contemplated he would provide. They were not additional services
consequent on
the late delivery of ADCNET Release 3 software. I have been invited to dismiss
this claim in its entirety.
1524 In its Reply Submissions the Commonwealth appears to have abandoned the
head of damage that it pleaded and which it addressed
both in evidence and in
its written submissions. It now says that the claim that the Commonwealth
should have made for Les Cook's
time should have been for the period 14
September 1994 to 19 December 1997 (the date of the Variation Agreement). The
expenses relating
to Les Cook for project management services that DFAT paid
were wasted in this period as the contract had to be re-performed. The
Commonwealth had erroneously claimed the period from 29 May 1996, when the
ADCNET software ought to have been delivered to 31 August
1999 when the
Expedited Release 3 software was in fact delivered. In the event $375,733 is
now claimed as wasted expenditure for
the period 29 May 1996 to 19 December
1997.
1525 BHP-IT contends that it would be quite unfair for the Commonwealth to
attempt fundamentally to change the claim in the manner
proposed. I agree.
The change is not one of form and a quite different cross-examination could
well have been undertaken given the
way the claim is now sought to be put.
1526 I will consider this claim on the basis on which it was put. Before
referring to the evidence (such as it is) that bears on
this claim, I should
note that my earlier conclusion on the effect of the Variation Agreement
entails the consequence that this head
of claim ceased to run on and from the
date of that agreement. Thereafter, such project management costs as were
incurred were incurred
in the performance of the amended Head Contract and were
referable thereto. While that contract did not expressly provide for the
appointment of a project manager by the Commonwealth, the parties at the time
clearly contemplated that such a function would be
performed by a person acting
for the Commonwealth.
(a) Additional Factual Material
1527 The evidence on this matter is relatively sparse.
(1) On 2 February 1990 the company, L G Cook and Associates Pty Ltd, entered
into a consultancy agreement with the Commonwealth to
provide designated
services to DFAT in relation to Stage I of the ADCNET project. Les Cook was to
be the actual service provider.
This consultancy was extended regularly with
changes being made to the services to be supplied reflecting the evolution of
the ADCNET
project itself.
(2) In February 1993 the responsibilities assumed included that of "the role of
ADCNET Project Manager": letter to Mr Skinner of
1 February 1993. That role
carried with it responsibilities that travelled well beyond management of the
ADCNET contract at the time. In a letter of 16 February 1993 to Mr
Cook, Mr Skinner described the position in the following terms:
"The duties of the ADCNET Project Manager are as directed by the Department's Systems Policy Committee (SPC) and its subcommittee, the ADCNET Steering Committee. ... In brief the duties can be summarised as managing the development of ADCNET Information Technology (IT) initiatives, both Stage 1 and Stage 2.
Together with the Deputy Secretary, the FAS CSD and the AS ITB, you will be expected to regularly contribute to formulation of both strategic and tactical IT policy initiatives for the whole Department. You will be expected to form a close working relationship with the AS ITB who will continue to manage your contract and provide administrative, line management and delegation support": emphasis added.
(3) A proposal was prepared by Mr Nichols in September 1994 for Mr Skinner's approval (later provided) that would continue Mr Cook's services until the finalisation of the ADCNET project which was then scheduled to be May 1996. That proposal again described Mr Cook as "ADCNET Project Manager". The tasks it envisaged included:
"3 (i) provide technical advice on related projects (eg the move to the new building), design of Release 1.3.20, Release 3 implementation/upgrade strategies, cutover of the secure IBM to ADCNET.
(j) provide advice to the Department on computer security, connectivity between ADCNET and NNS system and the connection of OGOs to ADCNET.
4. Mr Cook would be a member of the Release 3 Project Management Committee and would continue to be a member of the ADCNET Steering Committee, ADCNET Security Committee, Systems Policy Committee and IT Executive."
(4) Later communications extended the time and the hourly rate of the
consultancy.
(5) It was Mr Cook's practice to lodge a standard form invoice fortnightly for
services performed which listed dates and hours of
work but which did not
provide any indication of the work done for which payment was sought.
(6) During the period May 1996-December 1997 Mr Cook provided a range of
services to DFAT which were unrelated to the performance
of the ADCNET
contract. The fact of such services is evidenced (somewhat oracularly) in
electronic diary entries and is reflected
in the following passage of his
cross-examination:
"MR YOUNG: Q. Mr Cook, let me just put the substance of it to you. What I put to you is you wrote a detailed 19-page document addressing security gateway design principles dated 9 January 1997; do you recall that?
A. I'm afraid I don't.
Q. Do you recall this, that on 31 January 1997 you wrote a detailed paper dealing with convergence issues in the security area to Mr Woodhouse and copied to Mr Bagley, Higgins and others?
A. I do remember some work on what was called convergence of technologies, yes.
Q. Convergence of technologies was part of your wider security advisory role, wasn't it?
A. No. Convergence of technology is related to trying to make the Department's secret level and non-secure networks similar in terms of their technology. And my involvement was providing advice on what the secure network did.
Q. And, I suggest to you, commented on convergence issues, right, Mr Cook?
A. Issues relating to convergence, yes.
Q. You attended a meeting with SMS consultants dealing with convergence issues?
A. Yes.
Q. In July 1997, didn't you?
A. I don't remember the date.
Q. Mr Cook, in July of 1997 you wrote on 16 July another memorandum to Mr Nichols dealing with convergence issues; do you recall that?
A. I don't recall the document, I'm afraid, no. I'm not saying I doubt it.
Q. In August of 1997 you wrote a detailed minute to the steering committee copying Mr Jones dealing with convergence issues; do you recall that?
A. I don't recall details of any of these documents, Mr Young, but I do recall I had involvement in the convergence examination, yes.
Q. Right through July, August, September, October, November 1997, Mr Cook, didn't you?
A. Again, I can't - I don't remember the dates.
Q. Mr Cook, on 17 October 1997 you wrote a document about convergence strategy; do you recall that?
A. No, I don't.
Q. In November of 1997, Mr Cook, do you recall you wrote a paper dealing with email and the applicability of COTS packages and DFAT level of security?
A. I'm afraid I don't remember any of the details of these documents, not without seeing them.
Q. What about generally, Mr Cook? You were working heavily on convergence strategies and issues between July and November 1997, were you not?
A. I was being consulted by the people who were.
Q. And you were writing reports about those matters to your superiors in the Department?
A. On subjects that I was asked to comment on, yes.
Q. Mr Cook, do you recall on 8 August 1997 you made a visit to South Australia? Do you recall that?
A. I'm afraid I don't. Who was it to?
Q. You made a visit to South Australia ... to see DSTO and Vision Abell --
A. Oh, yes.
Q. -- seeking information in relation to the STARLIGHT product; do you recall that?
A. I recall that.
Q. You wrote a report about it?
A. I did.
Q. You wrote a report to Mr Nichols, Ms Bagley and others?
A. I did write a report."
It is also apparent through the above period that he was engaged in pursuing
a suitable replacement for STUBS (a matter outside the
scope of the Head
Contract) and in attending meetings of the IT Executive, etc.
(7) By the time of the "change of tactics" proposal in mid June 1995, Les Cook
was proposing that new (or new versions of) hardware
and software packages
might be added to the ADCNET system. The 1997 revisions of the FRS and
discussions with BHP-IT (referred to
earlier in these reasons) evidenced Mr
Cook's concern at the time with obsolescence and his desire to avail further of
available
COTS products. His concern with obsolescence was further manifest in
a minute to Mr Skinner of 28 August 1996 which, in giving a
prognosis of the
ADCNET contract, stated:
"even if it is completed within, say, two years the delivered software will be based on standard software and equipment which is then obsolete, requiring effort to upgrade before it can be used."
(8) Mr Skinner made the following observation in his witness statement concerning the continuing use of Les Cook's services:
"It was my opinion in 1996 that the continued involvement of Mr Cook as the ADCNET Project Manager representing the Department of Foreign Affairs and Trade was essential to the Department's interests. Mr Cook provided the Department with the technical, security and corporate expertise necessary for the viability of the project that was not otherwise available."
(9) The total amount paid to L G Cook & Associates for the period 29 May
1996-19 December 1997 was $375,733.
(b) Submissions and Conclusions
1528 As pleaded and as originally put this head of damage was in the nature of
a delay claim pending the performance of the original
Head Contract: cf
Farnsworth, Contracts, 582 (3rd ed). It was for the
additional costs of engaging Les Cook beyond the 29 May 1996 delivery date
under the Head Contract. To the
extent that the presupposition of this claim
is that, but for BHP-IT's breach, the Commonwealth would not have continued to
engage
the services of Les Cook after the delivery date, the claim is
manifestly untenable. It fails to differentiate between the ADCNET
project for
which Les Cook was the manager, and the ADCNET contract which represented a
part of his project management responsibility.
1529 In its submissions GEC Marconi notes that the Commonwealth has not led any
evidence indicating that Les Cook would not have
been required to provide
services to DFAT beyond 26 May 1996 had the Release 3 software been developed.
The submission went on to
point out - correctly - that logically Les Cook was
required by DFAT for as long as boundary security for ADCNET required
implementation.
1530 My own view is that irrespective of the breach DFAT would have retained
Les Cook's services for the period 26 May 1996 - 19
December 1997 at least. I
set out above Mr Skinner's evidence on why he considered Mr Cook's continued
involvement as ADCNET Project
Manager from 1996 onwards as necessary. Those
same considerations of "the Department's interests", "the viability of the
project"
and Les Cook's "technical, security and corporate expertise" would
have told heavily in favour of retaining his services after May
1996. There
was to be the move to R G Casey; there was the emerging problem of
obsolescence and the need to update COTS packages;
and, most importantly, a
boundary security device was needed before the IBM system could be
decommissioned. These were all ADCNET
project, but not ADCNET
contract, matters that required attention at the time.
1531 I need not repeat here my earlier findings in relation to when a
replacement for STUBS would have been likely to have been developed
had the
software been delivered on time. It would, in my view, have post-dated the
Variation Agreement. I am satisfied that there
would have been more than
sufficient life remaining in the ADCNET project during the period of present
concern to have made it likely
that Les Cook's services would have been
retained for that time at least. In consequence the global claim made for his
services
for that period must be rejected.
1532 It is clear, though, that some proportion of Les Cook's time in the
relevant period was related to the, then, still unperformed
Head Contract. It
is equally clear that a proportion of his time was unrelated to contract
matters, even if it related to the ADCNET
project as such. And beyond this, Mr
Cook provided services that were not ADCNET related at all.
1533 The Commonwealth has not led evidence positively to identify, as best it
could, the respective proportions of time spent on
contract-related and
non-contract related work (ie ADCNET and otherwise) work. It has been
acknowledged that some part of Les Cook's
time could not be attributed to
BHP-IT's breach. Initially the Commonwealth proffered a 20 per cent reduction
of its claim to account
for this. This was later reduced to 10 per cent, a
figure that is described as "more than adequate and reasonable, if not
generous".
1534 BHP-IT has submitted that the 10 per cent figure is out of all proportion
to the amount of non-contract related work done.
It goes on to contend that,
given the Commonwealth's failure, or inability, to lead evidence as to Mr
Cook's involvement in contract-related
matters and given the considerable
non-contract work done, the claim should be dismissed in its entirety.
1535 For my own part, while I consider that the Commonwealth is entitled to be
compensated for having to incur expenditure by way
of contract management in
consequence of non-delivery of the Developed Software, the level of
compensation awarded should be far
less advantageous to the Commonwealth than
it suggests.
1536 Les Cook's own evidence on how he spent his time was quite unhelpful and
in some degree disingenuous. His invoices are unrevealing
and his electronic
diary entries are largely unexplained.
1537 There is no adequate evidentiary basis before me to provide a remotely
accurate quantification of the actual time he spent in
providing services to
DFAT at the time that were unrelated at all to ADCNET. I am satisfied that he
provided such services and that
they were not insignificant in character and in
time demands. In the relevant period they are exemplified by his work on
convergence
issues. I am also satisfied that he performed significant ADCNET
project related services that were not also ADCNET contract-related.
GEC
Marconi have rightly pointed to STUBS replacement activities, although I accept
that concentration on a STUBS replacement probably
became more intense in 1998
after the need to decommission the IBM system became the more pressing. I
consider services in this
category to have been likely to have been of greater
volume than those unrelated at all to ADCNET in the period of present
concern.
1538 The evidence does indicate some level of continuing activity on Les Cook's
part in relation to the ADCNET contracts prior to
GEC Marconi's termination in
December and, after the decision by the Commonwealth not to terminate, a
process both of ongoing dealing
with BHP-IT over (a) the FRS and COTS products
and (b) contract negotiations for the Variation Agreement. Distinctly, there
were
internal communications within DFAT concerning the prognosis for the
ADCNET contract.
1539 As I earlier indicated, the Commonwealth has invited me to attribute 10
per cent to the non-contract related work and 90 per
cent to that which was
contract related. I cannot accept this proposition. Far from being "more than
adequate and reasonable",
it would in all probability dramatically
over-compensate the Commonwealth. Given the state of the evidence, I am left
almost completely
in the realm of "guestimation" - save that the evidence of
non-contract related work does satisfy me that it was of considerable
dimensions. In these circumstances, I consider it necessary to err on the side
of caution. I am not satisfied that it would be
appropriate to attribute more
than forty per cent of Les Cook's time in this period to compensable
contract-related activities.
I would in consequence award damages under this
head in the sum of $150,000.
1540 The final comment I would make is that I reject a separate argument
advanced by GEC Marconi that to the extent that Les Cook
was performing
services (albeit late) for the Commonwealth that were envisaged by the
consultancy agreement, the only loss suffered
was the increased cost to the
Commonwealth resulting from the increase in Les Cook's rates over what they
were prior to May 1996.
It may well be the case that had the contract been
performed on time, the Commonwealth might not have enjoyed the benefit of Les
Cook's non-contract related services to the extent it did. Nonetheless the
breach occurred and actual expenditure was incurred in
consequence. That
expenditure up to the execution of the Variation Agreement is a proper subject
of compensatory damages.
(3) The Edmund Barton Building Expenses
1541 By way of preface I should note that in its reply submissions, the
Commonwealth again ´has sought to change entirely the
basis upon which
this head of damage is claimed. The change reflects that made in relation to
the claim for "Project Management
Cost" referred to above. As originally made,
the claim was for loss flowing from breach of the original Head Contract. It
is now
sought to be explained as wasted expenditure in the performance of the
original Head Contract. I do not consider that the change
made here would be
likely to have had any significant prejudicial effect upon BHP-IT's conduct of
its case. As a matter of convenience,
I have dealt with the claim on the basis
originally advanced and responded to by BHP-IT and GEC Marconi. Whichever way
the claim
is put, it would seem that the same issue of principle (considered
below) arises and the claim covers the same period in each instance.
1542 Under the Head Contract the Commonwealth was obliged to provide (a) office
accommodation for BHP-IT's project team and (b) a
Test and Integration Facility
("TIF") for the development, integration and acceptance testing of the ADCNET
software. When DFAT
relocated to the RG Casey Building in November 1996, the
BHP-IT and GEC Marconi project teams were relocated to the Edmund Barton
Building. The Commonwealth paid the costs of construction of the TIF at that
site as also the fitout of office accommodation for
BHP-IT and GEC Marconi
staff. When GEC Marconi left the project on 10 December 1996, DFAT decided to
move the BHP-IT team to the
RG Casey Building and to provide it accommodation
and a TIF in that building.
1543 The present head of damages claims the cost of constructing the TIF and
the office fitout at the Edmund Barton Building and
costs associated with the
leasing of office accommodation for BHP-IT personnel and for the TIF from
November 1996 to April 1997.
1544 The basis of the claim is that, if the Head Contract had been performed to
schedule (ie by May 1996), the need would not have
arisen from the Commonwealth
to continue to supply accommodation and a TIF to the BHP-IT project team.
(a) Contractual Setting
1545 Clauses 7.1 and 7.2 of the Head Contract obliged the Commonwealth to
supply the CSI prescribed in Schedule 6. That Schedule
in turn required it to
provide BHP-IT with reasonable office accommodation and support facilities,
reasonable furniture and fittings
and necessary accommodation for testing
facilities: Schedule 6, cl 2-cl 6. Clause 9E.2 of the Head Contract required
the Commonwealth
to provide the necessary testing facilities.
1546 I merely note the obvious that in incurring the costs of construction of
the TIF and of fitout at the Edmund Barton building
and in providing
accommodation for the BHP-IT project team and the TIF at that building, the
Commonwealth was acting in furtherance
of its contractual obligations to BHP-IT.
(b) Factual Setting
1547 In April 1994 (well prior to the execution of the Head Contract) a risk
analysis was undertaken by Mr Nichols of the proposed
R3 contract and copies
were supplied to Mr Brent and Mr Vile of BHP-IT. The first of the "High Impact
Risks", specified though categorised
as a "Low probability" was that the PSI
would be unable to complete the project before the move of DFAT to its new
building.
1548 While Mr Brent in cross-examination said he had no recollection of
receiving and reading the document, I am prepared to infer
that he did receive
and read it.
1549 It had become apparent by the beginning of 1996 that the Head Contract
would not be completed by the time fixed for the move
to the RG Casey Building
and DFAT then began to explore alternate office accommodation for the ADCNET
project team. That survey
involved consideration both of Commonwealth owned
and commercial properties.
1550 By mid-1996 papers had been prepared evaluating the various options (six
in number) and a recommendation was made that the ADCNET
team be relocated to
the Edmund Barton Building. I would note in passing that the costing for this
for a 23-month period was calculated
at $767,600 while the costing for the same
period in commercial offices (at a considerable distance from York Park) was
$744,500.
The recommendation to relocate to the Edmund Barton Building was
agreed on 9 August.
1551 In September 1996 Mr Brent raised CR2081 requesting two person days of
effort for the provision of "advice/consultation/assistance
in planning the
relocation of IPD from Admin Building to EBB". The Commonwealth approved that
CR on 9 September.
1552 Mr Graeme Nichols of DFAT arranged for the management of construction of
the fitout for office accommodation and for the TIF.
His witness statement
contains a table identifying the contractors and suppliers that were involved
in relocating BHP-IT's project
team to the Edmund Barton Building and
thereafter to the RG Casey Building, and the costs thereby incurred by the
Commonwealth.
Those costs were in the sum of $215,287.15. Of this, the sum
$35,000 was recovered by DFAT from the Department of Primary Industries
and
Energy ("DPIE"), leaving the claim made in respect of relocation expenses at
$180,287.
1553 I would note the following of the above costs and expenses incurred.
First, much the greater part of them were attributable
to work done by what was
then an administrative entity of the Commonwealth, Asset Services. That work,
in other words, was done
by the Commonwealth itself. Secondly, the sum
credited from DPIE was on account of facilities left by DFAT in the Edmund
Barton
Building on its departure to the RG Casey Building. DPIE was the
"lessee" of the building and the DFAT occupation of it was by way
of
"sub-lease" from DPIE.
1554 The area occupied by the BHP-IT team in the Edmund Barton Building was
office accommodation (628m2), the TIF (189m2) and storage
(77m2). The building
itself was owned by the Commonwealth. The Commonwealth claims $104,238 on
account of "rental paid" for leasing
the above space. The rent payable was
$295/m2 for the office accommodation and the TIF and $105m2 for the storage.
There were as
well payments made for security and cleaning: see Mr Down's DFAT
minute of 9 December 1996.
1555 It would seem that the space so occupied was previously occupied by DFAT.
(c) Submissions, Findings and Conclusions
1556 BHP-IT contests what I will generically call the "relocation costs claim"
(ie fitout, TIF, etc) on the basis that the Commonwealth
waived this claim when
it agreed to CR2081. It challenges the "rental claim" on the basis that the
Commonwealth had no obligation
to pay rent to itself and suffered no actual
loss in the circumstances.
1557 GEC Marconi submits that both claims are too remote. It likewise submits
in relation to the rental claim that no actual additional
cost was incurred by
the Commonwealth and that there is no proper analogy to be drawn between this
claim for breach of contract and
those rules of tort law that entitled a person
to an award of general damages for loss of use of, or damage to, property and
which
are typified in the holding in The Mediana [1900] AC 113.
1558 Before considering these defences in turn I should indicate the following.
First, I am satisfied that the Commonwealth properly
can be said to have
incurred the relocation costs it claims. While only a relatively small part of
these costs were reflected in
payments made to independent contractors - the
bulk being attributable to work done by Asset Services - I consider that the
Commonwealth
is entitled to claim the reasonable cost of those services. No
challenge having been made to the sums claimed on account of them,
I am
prepared to accept the figures provided by the Commonwealth.
1559 Secondly, despite the apparently formal ritual of entering into what were
described as "leases" and "sub leases" and of invoicing
for, and pay, rent, the
"rental" charged DFAT was merely an infra-governmental accounting arrangement.
I need not speculate upon
the reason for this practice (it has not been the
subject of evidence). However, I do infer that such "leases" were required to
be entered into as a result of Government policy at the time.
1560 BHP-IT's waiver defence can be dispensed with shortly. CR2081 was raised
for the purpose of properly managing the office relocation,
and it sought
payment to BHP-IT for the advice and assistance it might render in planning the
move to the Edmund Barton Building.
Whether or not that advice resulted in the
Commonwealth incurring less cost than it might otherwise have done so - there
is no evidence
on this matter - giving BHP-IT the opportunity to proffer it
without cost to itself, in no way suggests that the Commonwealth intended
to
waive, or could be taken as having waived, its rights against BHP-IT for delay
costs that were reflected in the need to make the
move. I do not pause to
discuss what the term "waive" might be intended to signify in BHP-IT's
submission. I can see no basis for
suggesting that CR2081 grounded an
estoppel, involved an election between alternative and inconsistent rights, or
involved in some
other fashion the intentional relinquishment of a known
right.
1561 I need only consider the remoteness defence in relation to BHP-IT. I am
satisfied that BHP-IT was made aware of, and understood
the significance of,
the timing of completion of the Head Contract relative to the projected move to
the RG Casey Building. From
early in 1994 both parties were well aware from
communications inter se of the risk late delivery posed because of the
projected
move and they contracted in that knowledge. And BHP-IT knew what
were the Commonwealth's obligations in relation to the provision
of
accommodation and of a TIF. BHP-IT in consequence accepted that if, because of
its delay, DFAT moved to the RG Casey building
before the actual completion of
the Head Contract but after the agreed completion date, it bore the risk of
damages arising from
the Commonwealth's continuing need to perform its
obligations in these changed circumstances.
1562 The common defence put by BHP-IT and GEC Marconi appears at first blush to
be unanswerable if the Commonwealth's claim is seen
simply as a claim for
reimbursement of a rent paid, ie, as a claim for an actual cost incurred. What
is clear, notwithstanding the
modern practice in public administration of
treating the departments and agencies of the Executive Government as separate
and independent
entities, is that no loss was incurred by the Commonwealth
resulting from its having made a rental payment to itself. Whatever the
reason
for requiring it, the rental payment was no more than an infra-governmental
accounting device. It had no legal reality.
Neither did the alleged lease in
respect of which the "rent" was paid.
1563 As originally put, the claim was analogised to that arising in tort when a
person loses the use of a non-profit earning chattel
through the tortious act
of another. As was said by Lord Halsbury LC in The Mediana [1900] AC
113 at 116:
"where by the wrongful act of one man something belonging to another is either itself so injured as not to be capable of being used or is taken away so that it cannot be used at all, that of itself is a ground for damages."
1564 I have referred to the analogical use of this principle in considering
BHP-IT's damages claim in its cross-claim against GEC
Marconi. I will not
repeat here what I said there: BHP-IT's First Cross Claim: Costs of
Performing the Variation Agreement, (b)
Submissions and Conclusions.
1565 As finally put, the Commonwealth's submission is that the principle to be
derived from the case law is that where a party is
wrongfully deprived of its
property and uses its own resources to remedy the wrong it is entitled to an
award of general damages
for the use of its resources. I should add that
particular reliance in this was placed upon the decisions of Higgins J in
Commonwealth of Australia v Silverton Ltd (1997) 130 ACTR 1.
1566 It is, in my view, unnecessary to consider whether the Commonwealth's
submission accurately describes the law of this country.
My reason for this is
that the principle advanced is itself inapt to describe the claim actually
being made by the Commonwealth.
1567 Put at its most general that claim is for loss suffered by the
Commonwealth in having to perform its contractual obligation
for a period
greater than that originally contracted for under the Head Contract because of
delay in BHP-IT's performance of its
obligation. It was the manner in which
the Commonwealth elected to discharge that continuing contractual obligation to
BHP-IT (ie
by continuing to use its own property rather than commercially
rented offices) that deprived it of the use of its own property.
Nonetheless,
it was because of BHP-IT's breach and the delay it occasioned, that that
contractual performance needed to be rendered
at all. The Commonwealth was
being obliged to commit its resources beyond the period originally contracted
for in the Head Contract,
because of BHP-IT's breach.
1568 The questions raised by this are, first, whether having so to commit its
resources is properly to be characterised as a loss
for the purposes of an
award of damages for breach of contract; and, secondly, if it is, how are
those damages to be assessed.
1569 As to the first of these questions, I am satisfied that a compensable loss
was suffered. The Commonwealth had to continue performing
obligations owed to
BHP-IT requiring a continuing commitment of resources because, and only
because, of BHP-IT's breach. This involved
a loss of use of property, not
because of some wrong or injury to the property itself: cf The Mediana,
above; Anthanasopoulos v Moseley [2001] NSWCA 266; Nauru Local
Government Council v New Zealand Seamen's Industrial Union of Workers
[1986] 1 NZLR 466; and see generally McGregor on Damages, para
1349ff (16th ed); Tilbury, Civil Remedies, vol 2, [12028];
nor because it was actually kept out of that property by reason of delay in the
other party's performance: cf Restatement of Contracts, Second
§348 and Comment (b); Dobbs, Law of Remedies, vol 3, 443ff
(2nd ed); but because of the continuing need to commit its property
in consequence of the other party's breach. In the immediate circumstances
it
is more than coincidental that BHP-IT, because of its breach, obtained the
advantage of an extended performance at the Commonwealth's
expense. In saying
this I am not suggesting that the Commonwealth's loss is the benefit derived by
BHP-IT as such: Alucraft Pty Ltd (In liq) v Grocon Ltd (No 2) [1996] 2
VR 386 at 400-4001; or for that matter, that a claim in restitution
independent of contract was available to the Commonwealth
(such being clearly
not the case: see Trimis v Mina [1999] NSWCA 140 at [55]). I am merely
emphasising that the benefit or advantage provided to BHP-IT was a
manifestation of the loss suffered by the Commonwealth.
1570 When one turns to the quantification of that loss, problems become
immediately apparent. The present case is not one of an
actual expenditure
made by the Commonwealth in providing accommodation. Nor is it one in which
there is any evidence of an opportunity
otherwise to use the Edmund Barton
Building profitably which was lost to the Commonwealth. And the Commonwealth
was not, on the
evidence, using this building for income earning purposes. Can
it be said, then, that it suffered no pecuniary loss?
1571 I referred above to Lord Halsbury's statement of principle in The
Mediana that establishes loss of use of property from a wrongful act as
being itself a ground for damages. Where such property is not income
producing
or for that matter is not capable of being used for income producing purposes,
or where a substitute is not hired, leased
etc during a period of repair, a
like problem in quantification of loss can arise for reasons similar to those I
have noted above.
This, no doubt, explains the Commonwealth's resort to The
Mediana principle in this setting as that principle has been used to
justify the award of general damages for loss of use of non-profit earning
property: see generally McGregor on Damages, para 1349 (16th
ed); see also Westwood v Cordell [1983] Qd R 276 at 278-279.
1572 The Mediana principle is clearly part of Australian law: see
Tilbury, above, at 205 and the cases there referred to; Price v
Commissioner of Highways [1960] SASR 329; Commissioner for Railways v
Luya, Julius Ltd [1977] Qd R 395. Nonetheless, it has been commented
fairly that there is uncertainty about the appropriate method of calculation
of
damages in cases to which it applies: see Waddams, The Law of Damages,
§1.2050 (3rd ed). A variety of methods have been used in
different contexts and include the rental value of the property concerned; the
costs
of maintenance and the depreciation of the property for the period in
question; and interest upon capital value. These different
methods are
probably justified, as Professor Waddams suggests, "on the basis of convenience
of assessment": above, at §1.2140.
I do not consider it necessary to
enlarge upon them here.
1573 I was not taken to, and I have not been able to discover, a decided case
similar to the present. Such reported loss of use
of property cases as there
are, are of two general varieties: the first, where the loss arises from a
tort occasioning damage to
the property itself; the second, where a breach of
contract delays the use of property (eg because of delay in completion of a
building
on the innocent party's land). It has been said of English law in the
latter class of case that the delay damages should, in principle,
generally be
the rental value for the use of the premises for the period of delay: see
McGregor on Damages, para 1146 (16th ed).
1574 In American jurisdictions the rule commonly adopted in breach of contract
cases where the damage caused by a delay in performance
takes the form of loss
of use of an item of property, is that the damages are generally measured by
the rental value of the property
involved: 22 Am Jur 2d, "Damages", §70.
Restatement of Contracts, Second, §348(1) and Comment (a); for the
parallel tort law measure, see 22 Am Jur 2d, above, §444, §447;
Dobbs, above, §5.15;
see also Westwood v Cordell, above. In
Dobbs, Law of Remedies, the operation of the rental value approach in a
building contract setting has been described in the following way: (vol 3,
443):
"When the contractor breaches by delay in delivering the completed work, the owner is entitled to damages for the delay. Those damages are usually measured by the rental value of the land during the period of delay. The rental value is the value of the land with the building in its completed state as contracted for, not the value of the unimproved or partly improved lot. Rental value is the proper measure even though the owner would not in fact have rented the land and did not in fact need the building on the date called for. Like many other damages awards, the rental value measure may be considered a "default" measure, a kind of liquidated damages to be used unless the parties provide something they prefer. It is close enough to accurate compensation, easy to use, and far preferable to an unlimited award based on subjective guesses about the worth of delay to particular plaintiffs."
1575 In the present case resort to a "default measure" is inescapable. In
the circumstances, I consider a variant on the fair rental
measure is
appropriate. In saying this I recognise (a) that the contractual principle
referred to above was not designed to deal
explicitly with the unusual
circumstances of a case such as the present; and (b) that the Edmund Barton
Building, as Commonwealth
property, may not have had a rental value as such,
but it did have a usable value to the Commonwealth.
1576 If the Commonwealth had accommodated the BHP-IT project team in
commercially rented premises, it would have been entitled to
claim the rental
paid as damages: cf United States v Wyckoff Co 271 US 263 at 267
(1926). It had its own offices instead. Those offices clearly had a usable
value to the Commonwealth. Both before
and after their occupation by BHP-IT,
they were used by the Government departments.
1577 The decision to use the Edmund Barton Building was taken after evaluating
other options including a commercial option. An aspect
of that evaluation
related to the actual rental charged for commercial accommodation and the
"notional rentals" the Commonwealth
charged itself for its use of its own
buildings. Where the Commonwealth has taken the step of placing a cost to
itself upon its
use of its own premises - a cost which is apparently comparable
to rentals charged in the private sector (and it has not been suggested
otherwise in this proceeding) and which I infer is related to the efficient use
of public resources - that cost (not having been
challenged in its amount) can
properly be taken to represent usable value of that property to the
Commonwealth. As such, it provides
an appropriate measure of the damages that
are recoverable by the Commonwealth.
1578 I am satisfied then that the sum of $104,238 is recoverable by the
Commonwealth on account of its having to provide accommodation
and the TIF to
BHP-IT in the Edmund Barton Building. That sum is recoverable, not on account
of rental actually paid for that accommodation,
but as damages for the loss of
use of the premises concerned because it was obliged to provide such
accommodation by reason, and
only by reason, of BHP-IT's breach of contract.
1579 I am similarly satisfied that the relocation costs for fitout etc of the
Edmund Barton Building of $180,287.00 would not have
been incurred but for
BHP-IT's breach, even though the need to make that expenditure was necessary if
the Commonwealth was to perform
its continuing obligation to BHP-IT.
(4) The RG Casey Building Expenses
1580 Given my conclusion in relation to the effect of the Variation Agreement,
damages under this head could only run from May 1997
(when the BHP-IT project
was relocated from the Edmund Barton Building) until 19 December 1997 (the date
of the Variation Agreement).
(a) Additional Factual Material
1581 The "Core Occupancy Agreement" between Australian Estate Management (a
part of the Department of Administrative Services) and
DFAT for the RG Casey
Building was, on Graeme Nichols' evidence, executed on 14 June 1996. That
document was not in evidence, though
an agreement purporting to be a "Core
Occupancy Agreement" that was signed by the Secretary of DFAT on 18 December
1995 was tendered.
The latter document does not have annexed to it the
Schedule that dealt with rents payable.
1582 The evidence concerning the "rental" paid is in a less than satisfactory
state. I have no actual document before me prescribing
either the rent to be
paid for the building itself, or that which was attributable to the BHP-IT
project team's accommodation and
to the TIF. The "invoices" for the rent were
not put in evidence. I imply no criticism in this as to have required that all
relevant
invoices for all claims be tendered would have been both burdensome
and profligate given the volume in question. At best I have
hearsay evidence
of the rentals although there is accurate evidence of the areas occupied by the
BHP-IT project team and the TIF
and of their locations. The rate said to have
been charged was $388 per square metre. This may well have been less than the
actual
rate for the period in question but I am prepared to accept that such
was the rate for present purposes.
1583 The space in respect of which DFAT was paying rent was an area for which
it would have had to pay rent in any event.
(b) Findings and Conclusions
1584 In light of my conclusion in relation to the Edmund Barton Building rental
claim, a like conclusion follows in relation to this
claim for the period May
to December 1997. The actual amount paid for the period in question is still
to be calculated in respect
of the areas occupied by the BHP-IT project
team.
1585 I note that in its submissions BHP-IT has contested whether the area in
respect of which the claim was made was occupied solely
by members of the
BHP-IT (or ADCNET) project team. There is no evidence that such was not the
case and I allow no offset on account
of it.
(5) The Cost of Expedited Release 3 Software
1586 This head of claim is for the $509,796 paid to BHP-IT under CR007 for the
development of the ER3 software. CR007 was entered
into after the 1997
Variation Agreement. For that reason alone the claim is not maintainable.
(6) CONCLUSION
1587 I find that the Commonwealth is entitled to an award of damages under the
following heads and in the amounts indicated:
(i) project management costs - $150,000
(ii) Edmund Barton Building expenses - $284,525
(iii) R G Casey Building expenses - still to be calculated.
PART VI: CONCLUSION
1588 The burden of this proceeding cannot be encapsulated satisfactorily in
précis form. Accordingly, I will do no more than
record here the
outcomes of the various claims and cross-claims. First, I have rejected all of
the claims made by GEC Marconi save
that relating to delay and prolongation
which will be stood over for further hearing on a date to be fixed.
1589 Secondly, I have found that BHP-IT has made out its claim that GEC Marconi
repudiated its contract with BHP-IT. However, I
have not accepted significant
parts of the damages claims advanced by BHP-IT. I also have found that BHP-IT
is entitled to call
upon the performance guarantee given it by GEC Marconi's
parent company, GEC Marconi Australia.
1590 Thirdly, BHP-IT has made out a claim of breach of contract by the
Commonwealth, though not to the extent that it has claimed.
I have not been
asked and have not attempted to assess damages for the breach found. I have
rejected its claim against the Commonwealth
based on the Trade Practices Act
1974 on technical grounds, though I am satisfied that the Commonwealth did
engage in misleading and deceptive conduct in an aspect of
its dealing with
BHP-IT.
1591 Fourthly, I have found that the Commonwealth is entitled to claim damages
from BHP-IT on account of its failure to perform its
contract on time. Those
damages, though, are claimable only for a limited period and are relatively
small in amount.
1592 The only order I propose to make at this stage is to direct the parties to
bring in short minutes of order to give effect to
these reasons. I will
adjourn to a date to be fixed consideration of the question of costs.
I certify that the preceding one thousand five hundred and ninety-two (1592) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Finn. |
Associate:
Dated: 10 February 2003
A |
|
Acceptance Testing |
Process to determine whether a configuration item of computer software complies with its allocated requirements in the Functional Requirements Specification. In the case of ADCNET, also referred to as Formal Qualification Testing. |
ADCNET |
Australian
Diplomatic Communications Network |
ADD |
Architecture
Design Document |
API |
Application Program Interface |
API Specifications |
Specifications for the Cut-down STUBS Emulator. |
Applixware |
COTS software package. |
ATD |
1.
Acceptance Test Data |
2.
Acceptance Test Description | |
ATP |
Acceptance
Test Plan |
AWADI |
AWA
Defence Industries Pty Ltd |
AWADI Untrusted Software |
STUBS software component. |
B |
|
BHP-IT |
BHP Information Technology Pty Ltd |
BTM |
Base Team Member |
Build |
Installable subset of software, usually at CSC or CSCI level, that can be separately developed and tested. |
C |
|
CA |
Contract Amendment Form |
CDR |
Critical
Design Review |
CFS |
Customer's
Functional Specifications |
Contractor |
In the ADCNET Contracts, GEC Marconi was the Contractor in the Sub-Contract, and BHP-IT was the Contractor in the Head Contract (cf Customer) |
COTS |
Commercial Off The Shelf |
CR |
Change
Request |
CR001; CR3049 etc |
Particular change requests identified sequentially by number. |
CSC |
Computer
Software Component |
CSCI |
Computer
Software Configuration Item |
CSE |
Contractor
Supplied Equipment |
CSD |
Corporate Services Division of DFAT (see Schedule 4). |
CSI |
Customer
Supplied Items |
CSU |
Computer
Software Unit |
Customer |
In the ADCNET Contracts, the Commonwealth was the Customer in the Head Contract, and BHP-IT was the Customer in the Sub-Contract (cf Contractor). |
CUT |
Code and Unit Test |
Cut-down STUBS Emulator |
Partial Surface Emulation that was ultimately developed under CR 3049 |
Cutover |
Process of progressively switching from an old computer system to a new computer system while maintaining contact with the external environment. |
D |
|
Deep Emulation |
Emulation that represents the full functionality of the emulated hardware or software (cf Emulation; Surface Emulation). |
Deliverable |
Product or document to be supplied by the Contractor under the Head or Sub-Contract. |
DFAT |
Department of Foreign Affairs and Trade |
DoD |
Department of Defence |
DPSI |
Defence Preferred Systems Integrator |
DSB |
Diplomatic Security & Countermeasures Branch of DFAT (see Schedule 4). |
DSD |
Defence
Signals Directorate |
DSTO |
Defence
Science and Technology Organisation |
E |
|
EASAMS Australia |
The original sub-contractor on the ADCNET project; subsequently taken over by GEC Marconi. |
E2/E3/E5/E6 etc |
Scale of ITSEC Evaluation/Accreditation (see ITSEC Evaluation). |
Emulation |
Hardware and/or software that imitates the functional capability of other hardware/software. |
ER3 |
Expedited
Release 3 |
F |
|
Fixed Price Contracts |
The Head Contract and Sub-Contract signed in September 1994 providing for the development and integration of Release 3. |
FQT |
Formal
Qualification Testing |
FRS |
Functional
Requirements Specification |
Full Surface Emulation |
Emulation that represents all functionality at the interface of a piece of software or hardware. Distinct from Partial Surface Emulation which represents only a subset of interface functionality, and Deep Emulation which represents all functionality. |
Function Point Analysis |
Software estimation model. |
G |
|
Gateway (Trusted) |
Equipment and/or software processes that allow computers or networks with dissimilar characteristics to exchange information. In the case of ADCNET, trusted gateways allow (a) information exchange between ADCNET subsystems processing differently classified material and (b) between ADCNET subsystems and external systems. |
GEC Marconi Systems Pty Ltd |
Company that took over EASAMS Australia. |
GEC Marconi Australia Pty Ltd |
Parent company of GEC Marconi Systems Pty Ltd. |
GMS |
GEC Marconi Systems Pty Ltd |
H |
|
Head Contract |
Contract ITB/002 between BHP-IT and the Commonwealth; one of the back-to-back fixed-price contracts signed on 14 September 1994 for the development and integration of Release 3. |
HP |
Hewlett
Packard |
I |
|
IBM message switch |
Computer System located in DFAT, Canberra, that performed tasks of transmitting, queuing and disseminating diplomatic `cables'. Original IBM message switch was implemented in 1979 and replaced by the ER3 message switch in June 2000. The system controlled the dissemination of cables according to attributes such as addressee, classification and subject identifiers. |
IMB |
Information Management Branch of STUBS (see Schedule 4) |
Interface Emulation |
See Surface Emulation. |
Integration Testing |
The phase in which all constituents of the IPD deliverable are brought together for integration, along with the BND component. |
IPD |
Information
Processing Domain |
ITB |
Information Technology Branch of STUBS (see Schedule 4). |
ITB/002 |
Head Contract between BHP-IT and the Commonwealth. |
ITD |
Integration Test Description |
ITSEC |
Information
Technology Security Evaluation Criteria |
K |
|
KDC |
Key
Distribution Centre |
KG84 |
A military-standard encryption device. |
KIV-7 |
A military-standard encryption device; part of the STUBS replacement proposal under CR 3057. |
L, M, O |
|
LAN |
Local
Area Network |
Milestone |
A contractually designated stage in the performance of the contracted work, on the achievement of which a progress payment was made. There were 7 such Milestones in the Head and Sub-Contracts. |
Operating System |
Master control program that manages a computer's internal functions, such as accepting keyboard input, and that provides a means to control the computer's operations and file system. |
P |
|
Partial Surface Emulation |
Emulation that represents only a subset of the interface functionality of a piece of software/hardware. |
PDR |
Preliminary
Design Review |
PMT |
Project Management Team |
PMR |
Project Management Report |
PSI |
Prime
Systems Integrator |
R |
|
Release 1 |
The original release of ADCNET software, which predated the Fixed Price Contracts. |
R3 |
Release
3 |
ROM |
rough order of magnitude |
S |
|
SATIN |
Secure Australian Telecommunications Information Network |
SDD |
Software Design Document |
Systems Design Document | |
SDP |
Software Development Plan |
SDSDD |
Software Development System Design Document |
Sealing |
A trusted process which converts an unsealed object into a sealed object. |
Senior Executive |
See Schedule 4. |
SIS |
Software Interface Specification |
SMOG |
Single Message Outgoing Gateway |
SO |
Standing Offer Agreement |
SPC |
Systems Policy Committee (see Schedule 4) |
SPME |
STUBS Project Management Executive (see Schedule 4) |
SRS |
Software Requirements Specification |
STARLIGHT |
Security technology developed by DSTO after STUBS. |
STD |
Software Test Description |
STUBS |
Electronic security gateway devices invented by DSTO and licensed for commercial exploitation by AWADI. Hardware components of the STUBS Technology include Sealers, Gateways and Key Distribution Centres. The technology also included Trusted and Untrusted software components. |
Sub-Contract |
Contract ADC/001 between GEC Marconi and BHP-IT; one of the back-to-back fixed-price contracts signed on 14 September 1994 for the development and integration of Release 3. |
Surface Emulation |
Emulation of that part of a piece of software or hardware which interfaces with other elements of a system. |
System |
All components of ADCNET, including computers, network equipment, software and procedures processing all levels of classified and unclassified information. |
System Security Policy |
A top level statement of the risks faced by an electronic information system or collection of systems, the counter measures to be applied within and outside of the systems, and the responsibility for those measures. |
T |
|
TASDD |
Test & Acceptance System Design Document |
TDP |
Test Description Procedure |
Test Harness |
A type of emulation, being a set of scripts/short programs that exercise various files or calls from a database to act as input to, and collect output from, the software being tested - see Contract Schedule 9 Cl 2.2.4.1. |
Testable `Shall' |
Requirement defined in the FRS which must be demonstrated for completion of Formal Qualification Testing. |
TIF |
Test & Integration Facility |
TRR |
Test
Readiness Review |
Trusted |
Any component of the system that was `trusted' could be relied upon to uphold the System Security Policy. |
U |
|
Unit Test |
Test of a CSU to determine whether it meets the capability requirements established in the SDD. |
UNCLGUARD |
Unclassified
Guard |
W |
|
WACC |
Weighted Average Cost of Capital |
WAN |
Wide
Area Network |
*Roger Cooke |
GEC Marconi Project Manager; originally in charge of the ADCNET project team prior to Release 3; later became Canberra Branch Manager of GEC Marconi Systems from 1994 to 1997. |
*Tim Harris |
GEC Marconi Systems Engineering Manager and Integration & Acceptance Test Manager; a software engineer whose principal responsibility was the integration and acceptance testing of the ADCNET Software. |
*MuraliVaratharajan |
GEC Marconi Systems Engineer and later IPD Development Manager; a software engineer whose principal role in the development of the ADCNET Software was to manage of a team of GEC Marconi software engineers/programmers. |
*Peter Wishart |
GEC Marconi Project Manager for the ADCNET project from September 1994 until January/February 1996. Also Technical Manager. |
*Ron Becker |
General Manager (Commercial) of GEC Marconi from April 1990 to March 1999. |
*Ian Sharp |
GEC Marconi General Manager, appointed in November 1995 (replacing Lindsay Pears); subsequently Managing Director of GEC Marconi from July 1996. |
*Howard Breden |
Commercial Manager of GEC MARCONI and then Commercial Manager for C3I Division of GEC Marconi Systems. |
*Peter Newton |
Consultant engaged by GEC Marconi to develop and build the STUBS Emulation Software pursuant to Change Request 3049. |
Edward Goldsmith |
GEC Marconi Project Manager for the ADCNET project; succeeded Peter Wishart in January/February 1996 and left the project in August 1996. |
Samy |
Software engineer/programmer involved in the costing of Change Request 3057 for the development of an alternative security gateway mechanism for ADCNET. |
*Professor Raymond Offen |
Expert in software development called by GEC Marconi to give expert opinion and to comment on Dr Lewis' report. |
Lindsay Pears |
GEC Marconi General Manager up to November 1995 (replaced by Ian Sharp). |
Chris Skinner |
Managing Director of GEC Marconi from April 1996 to June 1996 (replaced by Ian Sharp). |
Ian Otto |
GEC Marconi Systems Architect |
*Daryl Dorfan |
Accountant retained by GEC Marconi. |
BHP Information Technology
*Kyrill Brent |
BHP-IT's ADCNET Project Manager from pre-1994 to May 1997. |
*Ian Dart |
National Manager for Systems Integration Services (SIS) from 1994 to 1995. Appointed Group General Manager of BHP-IT in 1996. |
Mike Haddad |
Senior Commercial Manager of BHP Information Technology. |
Glenn Vile |
Contract Manager for BHP Information Technology; assisted Robert Nichols of DFAT with the drafting of the proposed contract with AWA Defence Industries for the proposed purchase of the STUBS devices. |
Margaret Beattie |
BHP-IT Corporate Legal Counsel |
Ramanathan Vishwanathan ("Vish") |
Software systems architect responsible for the development of the ADCNET software after GEC Marconi terminated the Sub-Contract with BHP-IT (Consultant to BHP-IT). |
*Manfred Rentz |
Project Manager of the ADCNET project taking over from Kyrill Brent in May 1997; with Vishwanathan was responsible for the development of the ADCNET software, in particular the Expedited Release 3 software |
*Ian Fenwick |
System Support Manager responsible for BHP-IT's accounting systems. |
Nick Brazil |
BHP-IT testing engineer |
David McGregor |
BHP-IT test and integration engineer |
*Gerard Hammond |
BHP-IT Vice President (Finance) from June 1996 to May 2000. |
Commonwealth (DFAT)
*Les Cook |
ADCNET Project Manager contracted by DFAT to help oversee the project. |
*Robert (Bob) Nichols |
DFAT officer; Director of section responsible for the development of the ADCNET software between 1994 and 1998; conducted negotiations with AWA Defence Industries on behalf of DFAT for the proposed procurement of the STUBS devices. |
*Kim Jones |
Deputy Secretary of DFAT from 1993 to 1998; the ADCNET project fell within his sphere of departmental responsibility. |
Geoff Allen |
Assistant Secretary of the Diplomatic Security and Countermeasures Branch of DFAT - the Branch responsible for the computer security requirements of the Department, between 1993 and 1996. |
*Anthony Skinner |
Assistant Secretary of the Information Technology Branch of DFAT - the Branch responsible for the ADC Network and the development of the ADCNET software, between 1990 and 1996. |
*John Crighton |
First Assistant Secretary of the Information Management and Property Division of DFAT from 2000 to 2001. |
*Robert Cotton |
First Assistant Secretary of the Corporate Services Division of DFAT from 1993 to 1997. |
*Damian Farrell |
DFAT consultant responsible for project managing the development and implementation of the UNCLGUARD security gateway mechanisms. |
*Graeme Tinney |
DFAT officer, who in conjunction with others, conducted and oversaw the acceptance testing of the Expedited Release 3 software. |
*Graeme Nicholls |
DFAT officer who arranged for the fitout and relocation of the BHP Information Technology/GEC Marconi ADCNET project team from the Administrative (now known as the Sir John Gorton) Building to the Edmund Barton Building. |
*Denis Johnston |
DFAT officer whose prime responsibility was the continued operation and management of the IBM Classified System; also made arrangements to relocate the IBM Classified System to the RG Casey Building. |
*Joseph Bracher |
Professional accountant retained by the Commonwealth to assist in quantifying its damages claim. |
*John Nothdurft |
DFAT Officer responsible for overseeing cable analysis and producing statistics in relation to cable printing and dissemination. |
*Peter Sams |
DFAT Officer responsible for the procurement of paper and certifying invoices for payment. |
*Dr Edward Lewis |
Expert in software development called by the Commonwealth to give expert opinion and to comment on Dr Offen's report. |
John Campbell |
Assistant Secretary of Corporate Services Division. Member of the IT Executive. |
Commonwealth (DoD)
Dr Don Sinnott |
DSTO
Scientist |
AWADI
Nick Davias |
AWADI STUBS Project Manager; responsible for the technical development and eventual manufacture of the STUBS devices. |
Mark Hender |
Marketing officer in AWADI; responsible for the sale of the STUBS devices to DoD and DFAT. |
Name |
Parties/Description |
Acceptance Test Team |
DFAT,
BHP-IT, GEC |
ADCNET Security Sub-Committee |
DFAT,
DSD |
ADCNET Steering Committee |
DFAT;
BHP-IT |
CSD (Corporate Services Division) |
DFAT |
DSB (Diplomatic Security and Countermeasures Branch) |
DFAT |
IMB (Information Management Branch) (Formerly ITB (Information Technology Branch)) |
DFAT |
STUBS Advisory Board |
DoD,
AWADI |
STUBS Project Management Executive |
AWADI,
DoD, DSTO |
Systems Policy Committee |
DFAT |
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/cth/FCA/2003/50.html