![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Federal Court of Australia |
COURT
IN THE FEDERAL COURT OF AUSTRALIACATCHWORDS
Practice and Procedure - pleadings - application for summary dismissal of proceedings - application for striking out.Federal Court Rules Order 11 Rule 23, Order 20 Rule 2, Order 11 Rule 16.
Trade Practices Act 1974 (Cth.) s.47(6), s.59(2) and s.87.
Dey v. Victorian Railway Commissioners [1949] HCA 1; (1949) 78 CLR 62
General Steel Industries Inc. v. Commissioner for Railways (NSW) [1964] HCA 69; (1964) 112 CLR 125
Global Sportsman Pty. Ltd. v. Mirror Newspapers Pty. Ltd. [1984] FCA 180; (1984) 2 FCR 82
HEARING
MELBOURNECounsel for the applicants: Mr. T. Bathurst Q.C. Mr. D. Conti
Solicitor for the applicants: Clayton Utz
Counsel for the respondent: Mr. M. Tobias Q.C., Mr. B. Walker
Solicitor for the respondent: Freehill, Hollingdale and Page as agents for Morris, Fletcher and Cross.
ORDER
Paras 22, 23, 47 and 51 and the word "untrue" in para 51b, be struck out, in each case with leave to replead. Leave is also granted to replead para 31b, so that it will be consistent with para 51 as repleaded.Note: Settlement and entry of orders is dealt with in Order 36 DECISION 2. The principles governing the consideration of a motion such as this are
well known.
3. In Dey v.Victorian Railway Commissioners [1949] HCA 1; (1949) 78 CLR 62, Dixon J. said
at 91:
"A case must be very clear indeed to justify the
At times the test has been put as high as saying
As I have said, some of these expressions occur in
6. The material parts of the Amended Application, dated 8 April 1988 read as
follows:
1. The First Applicant claims:
(a) an Order pursuant to Section 87 of the
(b) alternatively to (a) a declaration that
(c) an Order that the Respondent account to
2. The First to Fourth Applicants claim:
(a) damages;
(b) interest on such damages;
(c) costs; and
(d) such further or other relief as the Court
7. On 17 November 1982 the Northern Territory of
8. In about July 1982 the First Applicant called
9. The tender documents provided:
(a) for the basis of payment to the
(b) the contract entered into pursuant to the
10. On or about 30 September 1982 the Respondent
11. On 17 November 1982 the First Applicant
12. On 18 November 1982 the Respondent accepted
13. In the premises the Applicants say and the
14. It was a term and conditon of the agreement
16. It was a further term and condition of the
8. The Further Amended Statement of Claim continued as follows (the
underlined portions being the sum of all the amendments made
from time to time
to the Statement of Claim):
17A.On or about 18 August 1983 the agreement was
PARTICULARS
The variation was oral and was made at a
10. Paragraph 18(a), as it had been pleaded in the Amended Statement of
Claim, read as follows:
(i) Express and made orally by the Respondent
(ii)Implied from
(a) The tender documents:
(b) The letter dated 4 October 1982 from
(c) A statement by Mr. Satchell that a
13. Counsel for the applicant expressly disavowed any application to add the
express representation contained in paragraph 18A(i)
to the grounds of the
implication set out in sub-paragraph (ii).
14. The tender documents set out the basis upon which interested parties were
invited to tender. The letter dated 4 October 1982
read:
Rise and Fall to apply only to those nominated
For any further information, please direct all
15. The respondent contended that the statement in the letter "rise and fall
to apply only to those nominated suppliers and/or Sub-Contractors
as approved
by yourselves" is in its terms inconsistent with a representation that the
respondent would construct the Darwin Centre
for a price in the vicinity of
$36,000,000. The number of suppliers or sub-contractors to whose work rise
and fall would apply was,
it was said, left to the determination of the
applicant. The statement said to have been made by Mr. Satchell one week
later than
the date of the letter that "a further lump sum offer would be made
if the Respondent was granted the contract" did not, the Respondent
submitted,
lend any support to the suggested implication.
16. These submissions of the respondent are not without force, but it is
arguable that at the trial a close study of the tender documents
and a full
knowledge of the circumstances surrounding the letter and the statement by Mr.
Satchell may give rise to the implication
pleaded. The facts relied upon to
support it will be before the trial judge in any event. I would not strike
out para 18A(ii).
17. Paragraph 18(b) and 18B read as follows:
(b) That the Respondent had formed a bona fide
"18B.The representations referred to in paragraph 18(b)
(i) The tender documents:
(ii) The letter of 4 October 1982 from the
(iii)From the statement by Mr. Satchell at a
19. As paragraph 18B now stands, it relies upon the statement alleged in
sub-para (iii), and the documents described in sub-paras
(i) and (ii). In my
opinion, one would not be justified in striking out paras 18(b) and 18B. It
will be for later decision whether
the alleged statement is established by
evidence, and if so, the precise form in which it is found to have been made,
and the inferences
which should be drawn from it.
20. Paras 18(c) and 18C now read as follows:
"18C. The representation referred to in paragraph
(i) Express and made by the Respondent by its
(ii) Implied from the tender documents.".
22. It is not easy at the present stage of these proceedings to see how the
representation referred to in paragraph 18(c) could be
implied from the tender
documents, but for reasons similar to those expressed in relation to para
18A(ii), I would not strike out
para 18C(ii).
23. Paragraph 22 now reads:
(a) The Darwin Centre was not constructed by
(b) The Respondent was not able to complete
25. A similar attack was made upon the pleading in paras 18(c) of a
representation that the respondent "was able to complete the
contract in
accordance with its terms within a period of two years" and the allegation in
para 22(b) that "the respondent was not
able to complete the project within
two years but rather did not complete it until 2 May 1986" (para 22(b)).
26. In my opinion, these criticisms are well founded. I would strike out
para 22(a), and, for similar reasons, para 22(b) and 23
which seeks to rely
upon the matters pleaded in para 22 to found the allegation that the
representations referred to in para 18 were
made "with reckless indifference
to their accuracy".
27. My impression is that the applicants desire to make the allegation that
there was in fact a sufficient resemblance between the
work required under the
original contract and the work as finally completed to found the allegations
in paras 22 and 23. I think
that they should have an opportunity to replead
paragraphs 22 and 23 and I give them leave to do so.
28. If para 23 is repleaded I would see no harm in the applicants putting
the respondent on notice that "further and better particulars
will be given
after discovery and interrogatories".
29. It is to be observed that para 22(a) speaks of "the sum of $36m", whereas
para 18(a) refers to "a price in the vicinity of $36,000,00.".
30. To be consistent with para 18, para 22 should have used the words "in the
vicinity of $36,000,000".
31. In para 18(c) there is alleged a representation that "the Respondent was
able to complete the contract in accordance with its
terms within a period of
two years". In para 22(b) it is alleged that "the Respondent was not able to
complete the project within
two years but rather did not complete it until 2
May 1986", which involves substituting the phrase "the project" for the phrase
"the
contract in accordance with its terms". When para 22 is repleaded,
consideration will no doubt be given to those discrepancies.
32. In paras 25-28 the applicants seek to allege a cause of action under
s.59(2) of the Trade Practices Act 1974, ("the Act") which provides as
follows:
(2) Where a corporation, in trade or commerce,
PARTICULARS OF WORK TO BE PERFORMED
(i) The appointment of the superintendent;
(ii) The provision of certain information (Clause
(iii) The nomination of sub-contractors (Clause
(iv) The supply of materials (Clause 17 of the
35. It may be doubted whether s.59(2) was specifically drafted to cover a
situation such as that alleged in the present case. However, it appears to me
to be arguable
that its language is effective to do so, and I do not think it
appropriate to strike out paragraphs 25-28.
"30. Further and in addition to paragraphs 5 to 29
31. After Westpac made the Offer, Westpac
31A. At all times between 29 October 1984 and 17
37. Paragraph 38 reads as follows:
(a) supplies, or offers to supply, goods or
(b) supplies, or offers to supply, goods or
(c) gives or allows, or offers to give or allow, a
on the condition that the person to whom the
(a) that The Darwin Centre could be
(b) that the construction of the Hotel
(c) that the practical completion date of the
46B.Acting upon and in reliance upon the
47. The representations pleaded in paragraph 46
(a) The actual total construction cost of the
(b) The Respondent was not able to complete
(c) Practical completion did not occur by 5
47A.Additionally or alternatively to paragraph 47
(a) That by reason of the matters pleaded in
(b) That by reason of the fact that the
the said representations were made with
43. In para 51 the applicants allege:
(a) The sum of $200,000 for legal costs in
(b) The sum of $300,000 purportedly being a
(c) The sum of $1.2m. such sum asserted by
(d) The sum of $350,000 being a prospective
45. In para 51B the applicants allege:
(a) Part of the claim referred to comprised
(b) Part of the claim referred to comprised
(c) Part of the claim referred to comprised
(d) Part of the claim referred to comprised
47. To summarise, I would strike out paras 22, 23, 47 and 51 and the word
"untrue" in para 51B,in each case with leave to replead.
I would also grant
leave to replead para 31B, so that it will be consistent with para 51 as
repleaded.
48. For the convenience of the Court and the parties I direct that the
applicants file and serve a Further Amended Statement of Claim,
which may be
headed "Further Amended Statement of Claim of July 1988". It would be helpful
if, in addition to the underlining in
the present Further Amended Statement of
Claim, any words introduced after the delivery of these reasons be underlined
in red.
49. After counsel have had an opportunity to read these reasons, I will hear
them on the costs of the motion and the form of directions,
including the
question of the exchange of expert reports.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
summary intervention of the court to prevent a
4. In General Steel Industries Inc. v. Commissioner for Railways (NSW) [1964] HCA 69; (1964)
112 CLR 125, Barwick C.J. said at 129:
plaintiff submitting his case for determination in
the appointed manner by the court with or without a
jury. The fact that a transaction is intricate may
not disentitle the court to examine a cause of
action alleged to grow out of it for the purpose of
seeing whether the proceeding amounts to an abuse
of process or is vexatious. But once it appears
that there is a real question to be determined
whether of fact or law and that the rights of the
parties depend upon it, then it is not competent
for the court to dismiss the action as frivolous
and vexatious and an abuse of process.".
"It is sufficient for me to say that these cases
5. At p.130, Barwick C.J. described the relevant test as being whether the
plaintiff's case: "... is so clearly untenable that
it cannot possibly
succeed".
uniformly adhere to the view that the plaintiff
ought not to be denied access to the customary
tribunal which deals with actions of the kind he
brings, unless his lack of a cause of action - if
that be the ground on which the court is invited,
as in this case, to exercise its powers of summary
dismissal - is clearly demonstrated. The test to
be applied has been variously expressed; 'so
obviously untenable that it cannot possibly
succeed'; 'manifestly groundless'; 'so manifestly
faulty that it does not admit of argument';
'discloses a case which the court is satisfied
cannot succeed'; 'under no possibility can there be
a good cause of action'; 'be manifest that to allow
them', (the pleadings) 'to stand would involve
useless expense'.
that the case must be so plain and obvious that the
court can say at once that the statement of claim,
even if proved, cannot succeed; or 'so manifest on
the view of the pleadings, merely reading through
them, that it is a case that does not admit of
reasonable argument'; 'so to speak apparent at a
glance'.
cases in which the inherent jurisdiction was
invoked and others in cases founded on statutory
rules of court but although the material available
to the court in either type of case may be
different the need for exceptional caution in
exercising the power whether it be inherent or
under statutory rules is the same.".
"On the grounds appearing in the accompanying Amended
7. In the Further Amended Statement of Claim dated 30 May 1988 the applicants
allege, amongst other things, that:
Statement of Claim.
Trade Practices Act 1974 declaring the
whole of the Agreement between it and the
Respondent dated 17 November 1984 ('the
Agreement") void ab initio;
on the grounds appearing in paragraphs 43
to 45 (inclusive) of the accompanying
Amended Statement of Claim it is entitled
to avoid the Agreement; and
the First Applicant for the sum of $5.5m
paid pursuant to the Agreement together
with interest thereon.
deems fit.".
"6. On or about 9 April 1981 the First Applicant
PARTICULARS
entered into an agreement with the Northern
Territory of Australia and the Northern
Territory Development Corporation relating to
the construction and operation of a complex
comprising a theatre and performing space
(together called 'the Performing Arts Centre')
convention centre, international hotel,
concourse, public gallery and car park ('the
Hotel Complex'), the total complex being
described as The Darwin Centre. The said
Centre was to be constructed on the land
comprised in Lot 5335 Town of Darwin being the
whole of the land comprised in Crown Lease
Term No. 115 ('the land').
Australia leased the land to the First
Applicant for the purpose of construction of
The Darwin Centre.
for tenders for the construction of The Darwin
Centre.
successful tenderer to be by way of lump
sum subject to adjustment for rise and
fall in cost; and
acceptance of any tender and all work
performed thereunder would be performed
in accordance with General Conditions of
Contract NPWC Edition 3 (1981) as varied
or modified by the tender documents.
The provisions were contained in the tender
PARTICULARS
documents issued by the First Applicant in
July 1982. These documents comprised the form
of tender, General Conditions of Contract NPWC
Edition 3 (1981) (including annexures and
variations thereto), the conditions of
tendering, the Schedule of Rates and Schedule
of Prices.
submitted a lump sum tender for The Darwin
Centre in the sum of $32,800,000 subject to
the terms and conditions contained in the
tender form, the Respondent's letter to the
First Applicant of 30 September 1982 and the
attachments thereto.
Letter from the Respondent to the First
PARTICULARS
Applicant dated 30 September 1982 together
with attachments thereto.
accepted the tender of the Respondent subject
to the variations contained in its letter of
acceptance and the attachments thereto.
Letter dated 17 November 1982 from the First
PARTICULARS
Applicant to the Respondent and attachments
thereto.
the variations contained in the First
Applicant's letter of 17 November 1982 and
subsequently entered into possession of the
site.
On 18 November 1982 the Respondent
PARTICULARS
countersigned and delivered to the First
Applicant a copy of the letter of 17 November
1982. The Respondent entered into possession
of the site on or about 22 November 1982.
fact is that on 18 November 1982 the
Respondent agreed with the First Applicant to
construct The Darwin Centre on the terms and
conditions contained in the Applicants' letter
of 17 November 1982 the documents incorporated
by reference therein and the attachments
thereto.
that practical completion of the Centre would
take place within 101 weeks from 17 November
1982, that is by the 16 November 1984.
Annexure C to the letter of 17 November 1982
PARTICULARS
from the First Applicant to the Respondent.
15. It was a further term and condition of the
agreement that in the event that practical
completion did not take place by 16 November
1984 the Respondent would pay to the First
Applicant by way of liquidated damages the sum
of $158,550 per week.
Annexure C to the letter of 17 November 1982.
The respondent no longer presses an attack upon any of these paragraphs.
agreement that the Respondent would within 14
days of being requested to do so sign a formal
instrument of agreement.".
"17.It was a further term and condition of the
PARTICULARS
agreement that if the Respondent failed to
sign the aforesaid formal instrument of
agreement within the time specified, the First
Applicant was entitled to suspend payment
under the agreement.
Clauses 6 & 44 of NPWC Edition 3 (1981).
9. The respondent's attack upon paragraph 17A is that it is superfluous,
because no claim for relief depends upon it. It was rightly
conceded that
this attack was "a minor matter" and I do not propose to base any order upon
it.
varied to provide for the payment of interest
on unpaid progress payments at a rate of 15%.
meeting between Mr. Clark on behalf of the
First Applicant and Mr. Lambert on behalf of
the Respondent.".
"(a) that the Darwin Centre could be constructed
In this form the Respondent challenged it on a number of grounds, which ceased
to be relevant when the allegation was amended to
read:
for a price in the vicinity of $36,000,000 adjusted
in accordance with the terms of the contract.".
"(a) That if awarded the Tender it would construct
11. Paragraph 18A, added by the Further Amended Statement of Claim reads:
the Darwin Centre for a price in the vicinity of
$36,000,000.".
"18A. The representation referred to in paragraph
12. Counsel have agreed that the pleading of an express oral representation
in paragraph 18A(i) is not open to attack, but the respondent
maintained its
challenge to sub-paragraph (ii).
18(a) was:
by its servant or agent Mr. Satchell at a
meeting between him and Mr. V. Keneally
and Mr. Pascoe on behalf of the
Applicants on 4 October 1982.
the Respondent to the First
Applicant:
further lump sum offer would be made
if the Respondent was granted the
contract. This statement was made
at a meeting on 11 October 1982.".
"As an alternative to our Tender for the above on
The letter was signed by Mr. Satchell.
the 30th September, 1982, we offer our firm lump
sum price of $36,000,000-00 (Thirty Six Million
Dollars).
suppliers and/or Sub-Contractors as approved by
yourselves.
enquiries to Myself.".
"18(b) Between 30 September 1982 and 17 November
18. Paragraph 18(b) had included, in the Amended Statement of Claim, the
words "that the Darwin Centre could be constructed", which
have now been
replaced by the words "that it (the respondent) could construct the Darwin
Centre". This amendment overcomes the objections
to the earlier form of words
which were encapsulated in the rhetorical question "constructed by whom?".
1982 the Respondent represented to the Applicants
opinion on reasonable grounds and after
application of due care and skill that it
could construct The Darwin Centre for the
price set out in its tender adjusted in
accordance with the contract annexed to the
tender documents.".
were implied from:
Respondent to the First Applicant.
meeting on 11 October 1982 that in preparing
the lump sum offer of 4 October 1982 the
Respondent had assessed the risk.".
"18(c) That the Respondent was able to complete the
21. The respondent complains that the relationship between sub-paragraphs (i)
and (ii) remains obscure, as to whether they are alternative
or cumulative.
In the absence of the word "or", I would construe them as being cumulative. I
see no reason to strike out the allegation
in sub-paragraph (i) of the express
representation.
contract in accordance with its terms within a
period of two years.".
18(c) was:
servant and agent Mr. Phillips to Mr. Keneally
and Mr. Pascoe on 26 October 1982.
"22.The representations pleaded in paragraph 18
24. The respondent submitted that paras 18 and 22 were not based upon a
comparison of like with like. For all that appeared in
the pleading, it
submitted, there may have been such differences between the original 1982
project and the work as finally completed
as to make it impossible to treat
the difference between the "price in the vicinity of $36,000,000" (para 18(a))
and the sum of $73,000,000
which "the respondent has sought to claim as the
cost of construction" (para 22(a)) as leading to the conclusion that the
representations
alleged in para 18 were, as claimed in para 22, "untrue
misleading and deceptive and were made without any or any adequate
foundation".
were made in trade and commerce and were
untrue, misleading and deceptive and were made
without any or any adequate foundation in
that:
the Respondent for the sum of $36m but
the Respondent has sought to claim as the
cost of construction the sum of
approximately $73m.
the project within two years but rather
did not complete it until 2 May 1986.".
"59(1) ...
33. Para 25 reads as follows:
invites, whether by advertisement or otherwise,
persons to engage or participate, or to offer or
apply to engage or participate, in a business
activity requiring the performance by the persons
concerned of work, or the investment of moneys by
the persons concerned and the performance by them
of work associated with the investment, the
corporation shall not make, with respect to the
profitability or risk or any other material aspect
of the business activity, a representation that is
false or misleading in a material particular.".
"25. The submission by the respondent of the tender
34. The respondent's criticism of the paragraph was that the tender cannot be
an invitation to the firstnamed applicant to engage
in or participate in a
business activity. Nor did it require the investment of money and the
performance of work by it associated
with any "investment". The
particularized examples of "work" did not, it was submitted, arguably amount
to work within the meaning
of s.59(2).
referred to in paragraph 10 of the Further Amended
Statement of Claim constituted an invitation by the
Respondent to the First Applicant in trade and
commerce to engage in or participate in a business
activity, namely the construction of the Darwin
Centre, requiring the investment of monies by the
First Applicant and the performance of work by the
First Applicant associated with the investment.
8.3 of the Standard Conditions of Contract);
10.1 of the Standard Conditions);
Standard Conditions).".
In paras 30, 31 and 31A the applicants alleged:
PARTICULARS
hereof the Applicants say that on or about 24
July 1984 Westpac Banking Corporation
('Westpac') made an offer to advance to the
First Applicant the sum of $23,500,000 (the
Offer) to enable construction of the Centre to
be completed.
purported to vary the Offer and in particular
to make the grant of the loan conditional on
the First Applicant continuing to obtain from
the Respondent building services in relation
to The Darwin Centre.
Telex dated 29 October 1984 from Westpac to
36. When these three paragraphs are read together, there is, in my opinion,
no justification for striking out para 31A.
the Applicants' solicitors, Messrs. Clark and
Partners.
November 1984, Westpac made the said grant of
loan conditional upon the First Applicant
continuing to obtain such building services.".
"The conduct of the Westpac Banking Corporation in
38. Section 47(6) is in the following terms:
seeking to impose the condition referred to in
paragraphs 31 and 31A was in contravention of
S.47(6) of the Trade Practices Act 1974.".
"(6) A corporation also engages in the practice of
39. The respondent challenged para 38 on the ground that the firstnamed
applicant had already acquired the respondent's building
services before
Westpac's alleged imposition of a condition. Having para 31A especially in
mind, I do not consider this criticism
to be valid. Likewise, I would not
strike out para 39 which reads as follows:
exclusive dealing if the corporation -
services;
services at a particular price; or
discount, allowance, rebate or credit in
relation to the supply or proposed supply of
goods or services by the corporation,
corporation supplies or offers or proposes to
supply the goods or services or, if that person is
a body corporate, a body corporate related to that
body corporate will acquire goods or services of a
particular kind or description directly or
indirectly from another person.".
"By reason of its conduct referred to in paragraphs
40. In paras 46, 46B, 47, and 47A the applicants alleged:
32, 33, 34, 35 and 36 the Respondent aided,
abetted, counselled or procured or induced the
contravention by Westpac Banking Corporation of
S.47(6) of Trade Practices Act 1984.".
"46. Further and in the alternative to paragraphs
41. The respondent challenged the words in para 47 "and were made without any
or any adequate foundation of fact". In my opinion,
the applicants are
entitled to plead the allegation in these terms, which are based upon the
words of the Full Court in Global Sportsman
Pty. Ltd. v. Mirror Newspapers
Pty. Ltd. [1984] FCA 180; (1984) 2 FCR 82 at p 88:
30 and 45 the Applicants say on or about 15
November 1984 the Respondent represented to
the Applicants:
constructed for a total cost of $45
million;
complex in The Darwin Centre would be
completed so as to allow formal opening
of the Hotel by 15 August 1985;
Darwin Centre would take place by 5
November 1985.
representations and induced thereby, the First
Applicant entered into the agreement referred
to in paragraph 34 hereof.
were misleading, deceptive and untrue and were
made without any or any adequate foundation in
that:
Darwin Centre was not $45 million, but
the Respondent now claims $73 million in
respect thereof.
the Hotel Complex so as to allow formal
opening of the Hotel Complex by 15 August
1985 and in fact the Hotel Complex was
not completed until March 1986.
November 1985 and in fact did not occur
until 2 May 1986.
the Applicants say:
paragraph 47, and
Respondent had been in possession of the
site since the end of 1982 and was aware
of the cost and time required to complete
the Darwin Centre.
reckless indifference to their accuracy.".
"The non-fulfilment of a promise when the time for
42. The respondent also contended that a discrepancy between prediction and
outcome can never amount to such a case as that pleaded
in para 47. In my
opinion, the reasons which justify striking out para 22 justify a similar
conclusion in relation to paras 47 and
47A. If the pleading were amended to
allege a sufficient resemblance between the project in November 1984 and the
work as finally
completed this would become a question of fact, inference and
opinion appropriate to be decided at the trial in the light of all
the
evidence. Accordingly, I would give leave to replead paras 47 and 47A.
performance arrives does not of itself establish
that the promisor did not intend to perform it when
it was made or that the promisor's intention lacked
any, or any adequate, foundation.".
"51 Further and in the alternative to paragraphs
44. The respondent criticises the allegation that it "represented to Westpac
that it was entitled to make a claim against the First
Applicant for extra
costs" and submits that it should be expressed so as to convey an entitlement
to succeed in such a claim. This
criticism appears to be well founded and I
would strike out para 51, with leave to replead.
30 to 50, the Applicants say that on or about
14, 15 and 16 November 1984 the Respondent
represented to Westpac that it was entitled to
make a claim against the First Applicant for
extra costs incurred as a result of delays and
for legal costs and other costs associated
with the construction of the Darwin Centre,
namely:
respect of proceedings between the First
Applicant and the Respondent.
variation arising out of the introduction
in the Northern Territory of a 38 hour
week.
Mr. Woods to be a productivity loss.
loss that Mr. Woods asserted the
Respondent would incur for delays due to
rain.".
"51B.The representation pleaded in paragraph 51 was
46. Paragraph 51B, as it stands, is open to the criticism that it is not
sufficient to allege that the representation was untrue,
but the applicant
must allege that it was untrue to the knowledge of the respondent at the time
it was said to have been made. I
would strike out the word "untrue" but give
leave to the applicants to replead to allege untruth to the knowledge of the
respondent
at that time. As leave has been granted to replead paragraph 51, I
would also give leave to replead para 51B so that the allegations
of breach
may be pleaded consistently with the repleaded paragraph 51.
made in trade and commerce and was untrue,
misleading and deceptive in that:
the sum of $200,000 for legal costs in
respect of proceedings between the First
Applicant and the Respondent for which
the Respondent was not entitled to make a
claim under the contract or otherwise.
the sum of $300,000 purportedly being a
variation arising out of the introduction
in the Northern Territory of a 38 hour
week, for which the Respondent was not
entitled to make a claim under the
contract or otherwise.
the sum of $1.2m., such sum purportedly
being a productivity loss, for which the
Respondent was not entitled to make a
claim under the contract or otherwise.
the sum of $350,000, purportedly being a
prospective loss that the Respondent
would incur for delay due to rain, for
which the Respondent was not entitled to
make a claim under the contract or
otherwise.".
URL: http://www.austlii.edu.au/au/cases/cth/FCA/1988/229.html