You are here:
AustLII >>
Databases >>
Supreme Court of the ACT >>
2012 >>
[2012] ACTSC 1
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Detheridge as Executrix of the Estate of the late Brian Leslie Wells v Chubb Fire Safety Limited and Perisher Blue Pty Limited [2012] ACTSC 1 (13 January 2012)
Last Updated: 13 January 2012
VICKI DETHERIDGE AS EXECUTRIX OF THE ESTATE OF THE LATE
BRIAN LESLIE WELLS v CHUBB FIRE SAFETY LIMITED AND PERISHER BLUE PTY
LIMITED
[2012] ACTSC 1 (13 January 2012)
PRACTICE AND PROCEDURE – pleadings – particulars
– sought after lengthy delay and after filing of certificate of readiness
– application
for particulars refused.
PRACTICE AND PROCEDURE
– pleadings – party seeking order requiring another party to amend
its pleading – whether power to order –
lengthy delay in applying
– after filing of certificate of readiness – application
refused.
Court Procedures Rules 2006, rr, 21, 53,
425
Workers Compensation Act 1951
Canberra Data Centres
Pty Limited v Vibe Constructions (ACT) Pty Limited [2010] ACTSC
20
No. SC 311 of 2009
Judge: Master
Harper
Supreme Court of the ACT
Date: 13 January 2012
IN
THE SUPREME COURT OF THE )
) No. SC 311 of
2009
AUSTRALIAN CAPITAL TERRITORY )
BETWEEN: VICKI DETHERIDGE AS EXECUTRIX OF THE ESTATE OF THE LATE BRIAN
LESLIE WELLS
Plaintiff
AND: CHUBB FIRE SAFETY LIMITED
Defendant
AND: PERISHER BLUE PTY LIMITED
Second
Defendant
ORDER
Judge: Master Harper
Date: 13 January
2012
Place: Canberra
THE COURT ORDERS THAT:
1. the first defendant’s application dated 29 April 2011 be
dismissed.
2. the second defendant’s application dated 2 May 2011 be
dismissed.
3. the costs of both applications be the plaintiff’s costs
in the cause.
- There
are before the court applications by each of the defendants seeking orders
against the other, in this action for damages for
personal injury. The action
is listed for hearing on 20 February 2012.
- The
first defendant’s application seeks an order that the second defendant
provide further and better particulars of the statement
of claim accompanying
the second defendant’s notice claiming contribution or indemnity from the
first defendant. The second
defendant in its application asks the court to
order the first defendant to file and serve a further amended statement of its
claim
for contribution or indemnity against the second defendant. Neither
application involves the plaintiff. The applications were heard
together, and
the plaintiff did not participate in the hearing.
- The
man who allegedly suffered personal injury died before proceedings were
commenced. The plaintiff sues as executrix of his estate.
- The
plaintiff does not allege that the death of the deceased was caused by the
injury. The allegation is that whilst the plaintiff
was working in the
sprinkler valve room at the Bullocks Flat railway station, a battery exploded,
causing damage to the plaintiff’s
hearing. No direct physical impact
injury is claimed.
- The
plaintiff was employed by the first defendant. The second defendant was the
owner and occupier of the Skitube railway, the Bullocks
Flat Station, the
sprinkler valve room and its contents including the battery.
- Pursuant
to a contractual arrangement between the defendants, it was the responsibility
of the first defendant to provide security
and fire safety services. These
included periodic checking of the working of the sprinkler system. Although it
is not clear from
the pleadings or particulars, or the evidence on the
applications, I take it that the purpose of the sprinkler system was to spray
water from the ceilings of the various buildings constituting the railway
station in the event of a fire. I also take it that the
sprinkler system was
principally powered by electricity and that the battery which exploded was part
of a fallback system in the
event of an electrical failure. The purpose of the
battery was to provide power to a starter motor for a diesel engine which, I
take it, was to provide power to the sprinkler system in the event of failure of
the mains electricity supply.
- The
plaintiff commenced the present action, against the first defendant only, in
March 2009. As required by the Court Procedures Rules 2006, rule 53, the
plaintiff’s statement of claim followed a prescribed form rather than
being in the style of a traditional pleading. The
plaintiff asserted that the
first defendant operated a security and fire safety business from premises in
Fyshwick in the Australian
Capital Territory, and that the deceased was employed
by the defendant as a fire safety mechanic. It was asserted that he was based
in Canberra and was a worker of the Territory for the purposes of the Workers
Compensation Act 1951. He was required as part of his job to attend the
Perisher Blue Ski Resort, including the Bullocks Flat Station, about once a
month,
in connection with maintenance of the fire sprinklers. Part of this task
was the starting of a motor driving a pump. As the deceased
started the pump,
suddenly and without warning the battery exploded causing him acoustic
trauma.
- In
the originating claim the plaintiff claimed damages for breach of contract. He
did not make any claim in negligence. The plaintiff
pleaded that it was a term
of the contract of employment between the deceased and the first defendant that
the first defendant would
take all reasonable precautions for his safety, and
would not expose him to a risk of injury of which it knew or should have known.
It was a further term that the first defendant would take all reasonable
measures to ensure that the deceased’s workplace
was safe, that it would
provide and maintain suitable and safe plant and equipment for him, and that it
would provide and maintain
a proper and safe system of work. The plaintiff then
asserted that the first defendant committed breaches of those terms of the
contract of employment. Further particulars of breach of contract included
failure to carry out a risk assessment, failure to implement
risk control
strategies, and failure to train the deceased adequately for his work.
- In
May 2009 the first defendant joined the present second defendant as a third
party. The third party claim was framed in contract
and in negligence. It
asserted an agreement to provide fire safety services, including services in the
sprinkler valve room. It
is asserted that the third party owned, controlled,
occupied and was responsible for the room and for the diesel pump and battery
in
it, and responsible for ensuring that persons using the room were not exposed to
danger resulting from operation of the pump.
The third party was in addition
responsible for ensuring that the battery was adequate, suitable and the correct
size (any claim
based on the inadequacy of the size of the battery has since
been abandoned). Particulars of the negligence and breach of contract
of the
present second defendant included failure to inspect the battery, failure to
undertake a risk assessment and failure to ensure
that the battery was not
liable to explode.
- The
third party, now the second defendant, filed a defence to the third party claim
saying that it was the first defendant which was
responsible for regular
inspection and maintenance of the battery and reporting of any defects to the
second defendant, and that
it was the first defendant rather than the second
defendant which was relevantly responsible for the instruction and supervision
of the deceased.
- In
December 2009 the third party was on the plaintiff’s application joined as
second defendant. In January 2010 the plaintiff
filed an amended originating
claim and statement of claim adding a count in negligence against the second
defendant (though still
not against the first defendant). The amended statement
of claim effectively added to the original statement of claim the assertions
against the second defendant which had been contained in the third party claim.
Specifically a paragraph was added which, I assume
in error, asserted that the
second defendant owed the plaintiff a duty to take all reasonable care to ensure
that the plaintiff did
not suffer injury. It is clear that the intention of the
drafter was to assert a duty of care by the second defendant to the deceased
rather than to the plaintiff, and all parties have conducted the litigation
subsequently to the filing of the amended originating
claim on that
footing.
- In
April 2010 the second defendant filed a notice claiming contribution or
indemnity from the first defendant, asserting that at all
material times the
first defendant carried on business as a provider of security and fire safety
services and in that capacity contracted
with the second defendant to provide
those services to the second defendant in respect of its fire protection systems
at Bullocks
Flat. The second defendant in the notice asserted that injury to
the deceased had been caused by the negligence of the first defendant.
The
particulars of negligence were set out in virtually identical terms to the
plaintiff’s particulars of breach of contract
alleged against the first
defendant in her statement of claim. Alternatively the notice claimed that the
first defendant had been
in breach of its contractual obligations to maintain
the second defendant’s fire protection systems, specifically the batteries
and chargers.
- The
first defendant filed a defence to the notice claiming contribution or indemnity
in which, inter alia, it admitted the paragraph
asserting that it had contracted
with the second defendant to provide security and fire safety services in
respect of the fire protection
systems at Bullocks Flat.
- In
June 2010 the first defendant filed an amended defence to the plaintiff’s
claim adding a defence of contributory negligence.
Again, the defence asserted
contributory negligence by the plaintiff, when what was intended was clearly to
allege contributory
negligence by the deceased. No one seems to have taken any
point about this.
- On
26 November 2010 the first defendant filed an amended statement of its claim for
contribution or indemnity against the second defendant,
adding further
particulars of negligence or breach of contract. In brief the fresh allegations
were that the second defendant had
negligently installed the battery, or
permitted it to be installed, in the sprinkler room in circumstances where it
was to be trickle-feed
charged on a constant basis, and was not enclosed in any
way, and where the room was subject to significant heating, particularly
during
the winter. It was further asserted that the second defendant had undertaken
responsibility for weekly checks of the battery
required to be undertaken
pursuant to a specified Australian Standard (additionally to the monthly checks
undertaken by the first
defendant) and had failed to conduct adequate checks to
ensure that the electrolyte in the battery did not evaporate to a point where
the battery was at risk of exploding. Finally, it was said that the second
defendant had failed to respond adequately to a note
by one of its maintenance
staff on 7 August 2006 that “batteries in the sprinkler room need some
work”.
- In
December 2010 a certificate of readiness was prepared by the plaintiff’s
solicitors. The certificate, in the prescribed
form, contained three columns
for comments by each of the parties on twenty-two items. The columns for the
defendants were completed
in handwriting. The certificate was signed by the
solicitor for the plaintiff on 14 December 2010, the solicitor for the first
defendant
on 17 December 2010 and the solicitor for the second defendant on 24
December 2010. It was filed on 11 January 2011. The solicitors,
as required by
the prescribed form, certified that the action was ready for trial, and that
pleadings had been completed and filed,
and pleadings had closed. Somewhat
unusually, the solicitor for the second defendant in relation to the second item
(“all
particulars requested have been provided”) commented in the
negative. The sixth item (“all required answers to interrogatories
have
been provided”) was answered in the affirmative only by the first
defendant. The plaintiff and the second defendant both
answered in the
negative. I would not have expected, and solicitors should generally not
expect, registry staff to check each item
of a certificate of readiness to make
sure that it really is what it purports to be. Registry staff should not, and
cannot, be expected
to go beyond the certification at the commencement of the
certificate of readiness by the solicitors that the action is ready for
trial.
- On
12 January 2011, the day after the certificate of readiness was filed, the
solicitors for the second defendant made an application
for further answers to
interrogatories of the first defendant. Notwithstanding the assurance by the
second defendant in the certificate
that all pleadings had been completed and
filed, on the following day, 12 January, the solicitors for the second defendant
filed
a document headed “Defence to amended statement of claim”. It
is apparent only from a detailed scrutiny of the document
that it is intended to
be a defence to the first defendant’s amended notice claiming contribution
and indemnity, rather than
a defence to the plaintiff’s claim.
- The
only amendment made by the first defendant in its amended notice claiming
contribution or indemnity of 26 November 2010 was the
addition of the
particulars of negligence (particulars 10, 11 and 12 in that document) about the
installation of the battery with
constant trickle feed, failure to enclose it,
and subjecting it to significant heating in the winter; failing to conduct
weekly checks
of the battery; and failing to respond to the note by maintenance
staff in August 2006 about the batteries needing some work. All
of the rest of
the notice had been included in the original third party notice in May 2009, a
defence to which had been filed in
October 2009. The second defendant did not
seek leave to amend, and should not in my opinion be permitted to amend, its
defence
to the claim by the first defendant, other than in relation to
paragraphs 10, 11 and 12 of the particulars of negligence, which were
indeed
fresh allegations. To the extent that the document filed on 12 January 2011
purports to go beyond that, it should not be
permitted to do so.
- The
second defendant’s application about answers to interrogatories came
before me on 4 February and 11 February 2011. After
a lengthy hearing I made
orders ex tempore that certain further answers be provided, and this was
subsequently done.
- On
23 February 2011 the matter came before the Deputy Registrar and was listed for
hearing before me on 20 February 2012 with an estimate
of four days.
Regrettably at the time of preparation of these reasons, it appears that there
are two other actions listed for hearing
ahead of it on that day, each with
four-day estimates, so that its prospects of being reached do not appear
high.
- On
29 April 2011 the first defendant made the application presently before the
court for particulars of the second defendant’s
notice claiming
contribution or indemnity of 20 April 2010. The particulars sought may be
described as the usual further and better
particulars of the making of a
contract.
- The
paragraph of the notice claiming contribution or indemnity in which the contract
was asserted reads as follows:
- At
all material times the first defendant carried on business as a provider of
security and fire safety services and in that capacity
contracted with the
second defendant to provide those services to the second defendant in respect of
its fire protection systems
located within the Premises.
- In
its defence to the notice dated 4 May 2010, the first defendant admitted the
contents of paragraph four of the notice. With the
benefit of hindsight, it is
now apparent that the solicitors for the first defendant should have sought
particulars of the contract
before pleading to the paragraph. However, the fact
is that they chose not to do so. It was almost a year before they sought the
particulars and made the application, after the filing of a certificate of
readiness and a fixing of a date for hearing of the action.
- It
is plain from the limited evidence, and the documents on the court file, that
neither defendant is going to be in a position to
produce a written contract
which sets out precisely what each party agreed to do in relation to the fire
safety services. It seems
clear enough that there was some agreement between
the parties and that its terms would have to be gleaned from a combination of
fragments of documentation, and oral evidence of the recollections of employees
or former employees of both companies about discussions
and happenings many
years ago. In the circumstances it does not seem to me that any injustice will
be done to the first defendant
by refusing the application at this stage. It
was after all the first defendant which brought the second defendant into the
action
in the first place. The first defendant can expect that it will be
required to adduce its evidence before the second defendant does
so: those
advising the second defendant may make a decision at the appropriate time that
it need not go into evidence. There is
no suggestion that either defendant has
failed in its duty to discover all the relevant documents in its possession or
control.
- Accordingly
I am not persuaded that the second defendant should be required to provide the
particulars which the first defendant seeks.
- On
2 May 2011 the second defendant filed its application now before the court,
seeking an order that the first defendant file and
serve a further amended
statement of claim against the second defendant. The application is really
based on a recognition that both
defendants have fallen short of what they
should have done in pleading what each of them says is the contract with the
other.
- Counsel
for the second defendant has not taken me to any authority for the proposition
that the court will, in an appropriate case,
on the application of a party,
oblige another party to file an amended pleading. A party which is served with
a pleading which is
bad has the right to apply to the court under rule 425 for
an order that the pleading or part of it be struck out. The second defendant,
then the third party, was served with a third party notice during 2009, and
chose to file a defence to it, rather than applying to
have it, or any part or
it, struck out. The first defendant filed an amended notice claiming
contribution or indemnity in November
2010. The only amendments of any
substance were the addition of the three particulars of negligence I have
mentioned previously.
Again, the second defendant chose to file a defence to
this document, rather than apply to have it, or part of it, struck out.
The
second defendant has still not asked that the amended notice claiming
contribution or indemnity, or any part of it, be struck
out.
- The
first defendant does not, as presently advised, seek to amend the notice any
further.
- It
does not seem to me that the court has a power to order a party to amend a
pleading on the application of another party. However,
it is unnecessary for me
to determine that question for the purpose of deciding the present application
by the second defendant.
Whether or not such a power exists, this is not an
appropriate case, or an appropriate stage, for such a power to be exercised.
The parties have pleaded the case in the manner they have chosen to do, and have
certified to the court that the pleadings are complete
and closed, and that the
action is ready for trial. It should go to trial on those pleadings,
notwithstanding that they may not
be as elegant or as admirable as might be
achieved in a perfect world. The functions of pleadings and particulars were
analysed
in considerable detail by Refshauge J in Canberra Data Centres Pty
Limited v Vibe Constructions (ACT) Pty Limited [2010] ACTSC 20 commencing at
[24]. His Honour referred in particular to pleading a contract at [57] and
following. Notwithstanding some shortcomings
in the present pleadings, I am
reasonably satisfied that they will enable the court to achieve the just
resolution of the real issues
in the proceedings (see rule 21), and that it is
best if the action goes to trial as soon as the court is able to hear it,
without
further interlocutory sparring.
- The
general expectation should be that leave will be granted to amend a pleading
after the filing of a certificate of readiness only
in exceptional
circumstances.
- Neither
defendant has had any real measure of success on either application. It seems
to me that the costs of the applications should
lie where they fall except that
the plaintiff, who has admirably stayed out of this fight and kept her costs to
a minimum, should
have such costs as she may have incurred in relation to the
applications in the event that she ultimately achieves an order for costs
of the
action. The appropriate order, then, is that the costs of both applications are
to be the plaintiff’s costs in the
cause. Both applications will be
dismissed.
I certify that the preceding thirty-one (31) numbered paragraphs are a true
copy of the Reasons for Judgment herein of the Master.
Associate:
Date: 13 January 2012
Solicitors for the plaintiff: Slater & Gordon
Counsel for
the first defendant: Mr RL Crowe SC
Solicitors for the first
defendant: Sparke Helmore
Counsel for the second defendant: Mr RE
Montgomery
Solicitors for the second defendant: Dibbs Barker
Date of
hearing: 20 May 2011
Date of judgment: 13 January 2012
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/act/ACTSC/2012/1.html