![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of the ACT |
Last Updated: 22 September 2009
MATKEN CONSTRUCTIONS PTY LTD v TREVOR JAMES & ANOR
[2009] ACTSC 100 (27August 2009)
CAVEATS – Land Titles Act 1925 – circumstances in which Court will order removal of caveat conditionally upon payment into Court – building dispute – action by builder – standard building contract – charge under contract giving rise to caveatable interest – extent of charge – whether payment into Court should include interest – whether should include estimated costs of action
Court Procedures Rules 2006 (ACT)
Land Titles Act 1925, s 105
Gibson v Co-ordinated Building Services Pty Ltd (unreported, Supreme
Court of New South Wales, Young J, 20 July 1989)
Griffith v Hodge
(1979) 2 BPR 9474
Commercial Bank of Australia Ltd v Schierholter
[1981] VR 292
Renascent Interiors & Refurbishers Pty Limited v
ASEL Property Group Pty Limited [2002] NSWSC 345
No. SC 5 of 2009
Judge: Master Harper
Supreme Court of the ACT
Date: 27 August 2009
IN THE SUPREME COURT OF THE )
) No. SC 5 of 2009
AUSTRALIAN CAPITAL TERRITORY )
BETWEEN: MATKEN CONSTRUCTIONS PTY LTD
Plaintiff
AND: TREVOR JAMES
First Defendant
DIANNE JAMES
Second Defendant
ORDER
Judge: Master Harper
Date: 27 August 2009
Place: Canberra
THE COURT ORDERS THAT:
The application be stood over to 3 September 2009 for submissions as to the orders which should be made in the light of these reasons.
1. This is an application by the defendants in a building case for an order
that, upon their paying into Court an appropriate amount,
a caveat lodged by the
plaintiff over their residential property be removed.
2. The defendants
engaged the plaintiff company to build a house on their land at Gungahlin. The
parties signed a standard Master
Builders Association home building contract on
27 June 2005.
3. The property is a standard residential suburban block. A
ninety-nine-year Crown lease was granted to the defendants in June 2002.
In May
2003 a mortgage was registered. The mortgagee is Perpetual Limited. The
plaintiff lodged a caveat in August 2007. It is
common ground that the
plaintiff was entitled to lodge a caveat pursuant to clause 31 of the contract,
which provides:
31 CHARGE ON LAND
The owner charges the Site with the
payment to the Builder of all monies payable to the Builder under this Contract
or otherwise from
the carrying out of the Works.
4. The house has been built.
The plaintiff’s case is that it has carried out the work it contracted to
perform. The defendants
have made some progress payments but there remains an
amount due under the contract of $47,722.58. The plaintiff also claims interest
and costs. Item A15 in appendix A to the contract reads as follows:
A15
INTEREST RATE APPLICABLE TO LATE PAYMENTS
Annual Interest Rate applicable to
Late Payments (Adjusted Weekly Compounding) 20 percent (if nothing stated, 20
percent).
In other words, the Master Builders form provides for twenty
percent to be the default rate, but in this case the parties agreed on
twenty
percent anyway.
5. On 19 December 2008, the Registrar General gave notice to
the plaintiff that the defendants had applied for a lapsing notice in
relating
to the caveat. The notice informed the plaintiff that the caveat would lapse at
the end of fourteen days from service of
the notice, in the absence of a court
order to the contrary.
6. It seems that the service of the notice was the
trigger for the commencement of these proceedings. On 6 January 2009, the
plaintiff’s
solicitors lodged the originating claim, statement of claim
and application for extension of the caveat, accompanied by a supporting
affidavit by Mr Kennedy, a director of the plaintiff company.
7. The
application came before Penfold J on 7 January 2009. None of the documents had
been served on the defendants. Her Honour
made an order temporarily extending
the caveat, with the application to come back before the Court on 4 February.
On that date the
defendants were represented. Her Honour left the extension
order in place and referred the matter to the Registrar for further directions.
The matter has since been before the Registrar on ten occasions.
8. On 3
April 2009 the defendants filed a defence and counterclaim. In the defence they
say that part of the amount claimed is not
owing under the contract. They also
say that they have not been given a proper accounting in respect of work done.
They assert
that the interest rate of twenty percent constitutes a penalty.
They make a counterclaim for the cost of remedial work, which they
say was made
necessary because the plaintiff did not carry out the building work properly or
in accordance with the approved plans.
They further claim that the plaintiff
contracted to complete the works by March 2006 but failed to do so, putting the
defendants
to additional expense arising from the fact that they continued to
reside in their existing home from March 2006, and to pay interest
on borrowed
money secured by mortgage over that home. The amount of the counterclaim is not
precisely quantified.
9. On 16 April 2009 the defendants made the present
application. They sought orders that the caveat be removed, that the plaintiff
“issue a certificate of completion with respect to the property” and
that they, the defendants, pay into Court an amount
by way of security for the
plaintiff’s claim. Perhaps surprisingly, they did not ask for security
for costs from the plaintiff.
10. The first defendant has affirmed an
affidavit in support of the application. He says that he and his wife believe
that works
under the contract have been finalised, and that the issue of a
certificate of completion has been held up by the plaintiff. He
says that he
believes that the plaintiff holds various certificates in relation to particular
trades, and that so far as he is aware
there is no impediment to the issue of a
certificate of completion. He says that he is “prepared to pay into Court
any amount
which might be ordered by the Court to provide security for the
plaintiff’s claim.”
11. The evidence from the plaintiff in
relation to the application is contained in an affidavit by Mr J. C. McN.
Ronald, the plaintiff’s
solicitor. Mr Ronald’s affidavit is
directed to the likely cost to the plaintiff of the action proceeding to
hearing. He
anticipates that the plaintiff will call seven witnesses, one being
a building expert who has not yet been qualified but whose expenses
are likely
to be between $4,000.00 and $6,000.00. He estimates that the hearing will take
four or five days. He has instructions
to brief junior counsel at $2,750.00 per
day. He estimates the solicitors’ costs of preparing for hearing, based
on his own
experience and information he has obtained from an experienced costs
assessor, at $20,000.00, with the solicitors’ costs and
counsel’s
fees for a hearing of four to five days ranging from $18,665.20 to
$22,644.00.
12. Counsel for the plaintiff submits that, if the caveat is to
be removed, the defendants should be ordered to pay into Court an
amount
calculated as follows:
|
Claim |
$47,722.58 |
|
Interest |
$37,844.81 |
|
Costs |
$47,000.00 |
|
|
$132,567.39 |
13. Counsel for the defendants submits that the amount his clients should be
required to pay into Court as a condition of removal
of the caveat is:
|
Claim |
$47,722.58 |
|
Interest |
$9,780.00 |
|
Costs |
$13,750.00 |
|
|
$71,252.58 |
14. Notwithstanding the reference in the contract to compound interest, my
understanding is that the solicitors for the plaintiff
have calculated simple
interest at 20% per annum on the outstanding amount, from the dates when its
various components became due
for payment according to their instructions. They
have calculated interest up to 1 February 2011, being the likely date of payment
of the amount due to their client, assuming that the action goes to trial and
their client is successful.
15. Counsel for the defendants has calculated
interest at the rate prescribed by the Court Procedures Rules 2006 for interest
before judgment, 9% per annum, to date and for something less than a year into
the future. He submits that the defendant
should not be penalised as to
interest, in circumstances where the plaintiff left it until the beginning of
this year to commence
proceedings, the defendant having pleaded in the statement
of claim that practical completion was achieved in December 2006, two
years
earlier.
16. The defendants have not put on any evidence about legal costs.
Counsel for the defendants in written submissions has calculated
figures on the
basis of a two-day hearing, with much lower allowances for preparation. Counsel
also submits that the counterclaim
by the defendants is a separate claim and
should not be taken into account when arriving at a figure for costs for the
purposes of
the present application.
17. The power to order the removal of a
caveat is conferred on the Court by section 105 of the Land Titles Act 1925.
That section provides that the registered proprietor against whose title a
caveat has been lodged may apply to the Court on notice
to the caveator for an
order that the caveat be removed. The Court may make such order “as to
the Court or judge seems fit”.
18. I was referred during submissions to
two decisions of the Supreme Court of New South Wales which are of assistance.
In Gibson
v Co-ordinated Building Services Pty Ltd (unreported, Supreme Court of
New South Wales, Young J, 20 July 1989) Young J permitted
the removal of a
caveat provided that a substitute security by way of bank guarantee was provided
by the registered proprietors,
with liberty to apply in the event of delay in
the action proceeding to a hearing. The application arose out of a building
dispute
which had resulted in litigation in the NSW District Court. The builder
had sued for work done and materials provided, and the owners
had counterclaimed
for expenses in a substantially greater amount. The applicable clause of the
building contract was in similar
terms to that in the present case. The owners
wanted to remove the caveat: the value of their house was much greater than the
claim
by the builder, and they wanted to use the house as security for
borrowings for an unrelated purpose. Young J cited Griffith v Hodge
(1979) 2
BPR 9474 as authority for the builder’s caveatable interest in the
property based upon the standard clause. The Court would permit
such a caveat
to be maintained only so long as it was just and convenient to do so. The
question whether the caveat should be maintained
depended on the balance of
convenience between the parties.
19. Young J noted a 1984 Western Australian
Full Court decision to the effect that the Court should not remove a caveat in
such circumstances,
but preferred a decision of the Full Court of the Supreme
Court of Victoria, Commercial Bank of Australia Ltd v Schierholter [1981] VR
292, and earlier single-judge decisions of the Supreme Court of New South Wales,
to the contrary. Counsel for the plaintiff does not
seek to persuade me that I
should do otherwise.
20. In Gibson, there was a disagreement between the
parties as to whether the amount to be secured was simply the amount claimed by
the builder, or whether it should extend to the costs of the action in the
District Court. Young J referred to earlier authority
and concluded that the
builder’s charge over the land was limited to the amount of the claim, but
held that the caveat should
not be removed by order simply on payment by the
owners of that amount. The builder had been given a contractual right to
maintain
a caveat. If it were maintained until the hearing, it would give the
builder a considerable advantage even though his security was
limited to the
amount claimed. In those circumstances it was only conscionable that the owner
ensure that the builder was not disadvantaged
by the Court giving the owner the
indulgence of providing a substitute security. Therefore the builder was
entitled, if there was
to be a substitute security, to such security as would
secure him not only for the claim but for the reasonable costs of
litigation.
21. This decision was followed by Barrett J in Renascent
Interiors & Refurbishers Pty Limited v ASEL Property Group Pty Limited
Limited [2002] NSWSC 345. This also related to a building case in the District
Court. Barrett J was satisfied that the contract created an equitable charge
affecting the defendant’s property, or at least that there was a
sufficiently arguable case to that effect. His Honour was
also satisfied that
the plaintiff had a sufficiently arguable case that moneys of some amount were
secured by the charge. This being
so, the builder was entitled to maintain its
caveat subject to factors relevant to the balance of convenience. The chief
factor
was the defendant’s willingness to give appropriate substitute
security by payment of moneys into Court. The real issue was
as to the
appropriate amount. The defendant did not wish to nominate a sum, and his
Honour thought that that was an appropriate
response. The plaintiff had
provided some calculations. The amount put forward by the plaintiff was the
amount claimed in the District
Court, plus the estimated plaintiff’s costs
in the District Court, plus interest, plus “a contingency for risk from
the
unsecured position” (the last component is not sought by the
plaintiff in the present action).
22. His Honour expressed the view that
there was no need for the Court to go into fine details of calculation. The
defendant had
asked for an order that the money paid into Court be invested.
Barrett J thought it appropriate to order investment in an interest-bearing
deposit with a bank. His Honour generally accepted the figures put forward by
the plaintiff. I note that this was in circumstances
where the total security
ordered by his Honour was $137,800.00, and that the value of the building
against which the caveat had been
lodged was over $25,000,000.00. It may also
be seen as relevant that the defendant had declined to put figures before the
Court,
or to challenge the figures put forward by the plaintiff in any
detail.
23. In the present case, both parties agree that the amount to be
paid by the defendants should include the plaintiff’s claim
of
$47,722.58.
24. As to interest, I am of the view that the amount to be paid
should be calculated at 20% simple interest as claimed in the plaintiff’s
figures, certainly to date, though perhaps not for quite so far into the future
as claimed. In this regard I note Barrett J’s
remark in Renascent
Interiors that there is no need for the Court to go into fine details of
calculation. My reason for allowing
interest at 20% rather than 9% is that the
plaintiff has an arguable case that if successful in the action it should
recover interest
at 20%, a figure after all to which the defendants agreed in
the contract, and the plaintiff should not be placed, by my orders,
in a
position of disadvantage by comparison with its present position as
caveator.
25. As to costs, I am satisfied that the defendants should be
required to pay an amount which ought to be enough to cover party and
party
costs recoverable by the plaintiff in the event that the plaintiff succeeds in
the action. I take the view that the plaintiff’s
figures are
pessimistically high as to the length of time the hearing is likely to take and
the amount it is likely to cost. I also
take account of the fact that
solicitors’ costs are likely to be limited to those laid down by the
Supreme Court scale, and
counsel’s fees to those allowed as between party
and party as published by the Registrar. At the same time, I take the view
that
the defendant’s figures are much too optimistic, both as to length of
hearing and as to quantum.
26. I am minded to reduce the allowance for
interest to something of the order of $32,000.00 to $35,000.00, and costs to
something
of the same order. Rounding the total, I fix $115,000.00 as the
amount the defendants would be required to pay into Court, or otherwise
secure
to my satisfaction, as a condition of the removal of the caveat. Subject to
payment or other acceptable security, I would
be disposed to order the removal
of the caveat.
27. Counsel for the defendants seeks a consequential order
that on payment of the sum, the plaintiff deliver up to the defendants
all
certificates issued relating to the construction work done on the land, and do
all things necessary to procure and hand over
a certificate for the plumbing
works. Counsel for the plaintiff submits that the contract gives his client the
right to retain any
such documents until payment. It must be recognised that
the orders I am making will not result in any payment being made to the
plaintiff immediately.
28. The defendants have not put on any evidence as to
any prejudice to them if the caveat is not removed, or if the orders about the
certificates are not made. It is apparent that the defendants would not be able
to sell their house, or to offer it as security
for a further mortgage, without
removal of the caveat and the issue by the relevant authorities of a certificate
of completion of
the building works, but they have not given evidence that they
have any intention of doing so.
29. In the circumstances I am disposed to
provide the defendants with an opportunity to put evidence on of any such
intention, if
they wish to do so. I would at the same time need to be persuaded
that there is a power to make the orders about the certificates
as interlocutory
orders in a building case of this kind.
30. I shall also provide the parties
with an opportunity to be heard about the costs of the application.
I certify that the preceding thirty (30) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Master.
Associate:
Date: 27 August 2009
Counsel for the plaintiff: Mr RS Dearn
Solicitors for the
plaintiff: Colquhoun Murphy
Counsel for the defendant: Mr GJ
Blank
Solicitors for the defendant: Rod J Barnett & Associates
Date of
hearing: 29 May 2009
Date of judgment: 27 August 2009
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/act/ACTSC/2009/100.html