![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of the ACT |
Last Updated: 19 September 2008
TECHNO BUILD DEVELOPMENTS PTY LTD v SAYERS AUSTRALIA PTY LTD [2007] ACTSC 60 (4 July 2007)
PRACTICE AND PROCEDURE – application for leave to appeal against award of arbitrator.
Commercial Arbitration Act 1986 (ACT), s 38
Hoyts Pty Ltd v Spencer [1919] HCA 64; (1919) 27 CLR 133
Equuscorp Pty Ltd v
Glengallon Investments Pty Ltd & Ors [2004] HCA 55; (2004) 218 CLR 471
Natoli v
Walker (1994) 217 ALR 201
No. SC 273 of 2007
Judge: Crispin J
Supreme Court of the ACT
Date: 4 July 2007
IN THE SUPREME COURT OF THE )
) No. SC 273 of
2007
AUSTRALIAN CAPITAL TERRITORY )
BETWEEN: TECHNO BUILD DEVELOPMENTS PTY LTD
Plaintiff
AND: SAYERS AUSTRALIA PTY LTD
Defendant
REASONS FOR JUDGMENT
Judge: Crispin J
Date: 4 July 2007
Place: Canberra
1. On 4 July 2007 I granted leave for the plaintiff to appeal against an award
of an arbitrator. I now provide my reasons for that
decision.
2. By a
written contract dated 12 February 2004, the defendant agreed to construct
various works for the plaintiff in accordance with
attached specifications.
Clause 11 of the contract provided that any disputes between the parties
were to be referred to arbitration.
3. A number of disputes subsequently
arose and by letter dated 29 March 2006 the parties appointed Mr Brian Farmer as
arbitrator.
A preliminary conference was convened on 11 April 2006 and
agreement was reached concerning various procedural matters. The arbitration
was conducted on 13 and 14 June 2006 after the parties had agreed upon a series
of 12 specific questions for determination. The
arbitrator delivered an interim
report on 11 December 2006, addressing the issues so identified and finding that
the plaintiff was
liable to the defendant for the sum of $232,268.68 plus
interest and costs.
2. The application was brought in reliance upon
provisions of s 38 of the Commercial Arbitration Act 1986 (ACT), the relevant
portions of which are in the following terms:
(2) Subject to subsection (4), an appeal shall lie to the Supreme Court on any question of law arising out of an award.
. . .
(4) An appeal under subsection (2) may be brought by any of the parties to an arbitration agreement -
(a) with the consent of all the other parties to the arbitration agreement; or
(b) subject to section 40, with the leave of the Supreme Court.
(5) The Supreme Court shall not grant leave under subsection (4) (b) unless it considers that -
(a) having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of 1 or more parties to the arbitration agreement; and
(b) there is –
(i) a manifest error of law on the face of the award; or
(ii) strong evidence that the arbitrator or umpire made an error of law and that the determination of the question may add, or may be likely to add, substantially to the certainty of commercial law.
(6) The Supreme Court may make any leave which it grants under subsection (4) (b) subject to the applicant complying with any conditions it considers appropriate.
3. Section 40 relates to exclusion agreements and it was not suggested that it
was of any relevance to the present case.
4. The defendant does not consent
to the plaintiff bringing the contemplated appeal and it may therefore be
brought only if leave
is granted pursuant to subs 38(4). Hence, it is incumbent
upon the plaintiff to demonstrate that the condition in subsection (5)(a)
and
either of the conditions in subs (5)(b) have been satisfied and to show that the
discretion to grant leave pursuant to subs (4)
should be exercised in its
favour.
5. The plaintiff seeks leave to appeal against the arbitrator’s
findings on two issues; namely, whether the contract price should
have been
taken to have included the Goods and Services Tax (“GST”), and
whether the plaintiff had been entitled to damages
for breach of a contractual
term relating to the provision of fencing.
6. The provisions for payment of
fees to the defendant is contained in cl 8.1 of the contract, which provides
that:
Subject to the proper performance of the Services, the (plaintiff) shall pay the (defendant) the balance of the fee payable for the Services as set out in Annexure C. The parties acknowledge that the fee is deemed to include all costs and expenses (including and without limitation all incidental disbursements and expenses) of providing the Services and complying with all of the terms of this Contract.
7. Annexure C bears the heading “The Fee” and this is followed by
the words “Amount of Fee (Clause 8.1)”.
The annexure then sets out
a series of amounts, described as “Provisional sums”, with a total
figure of $177,000 and
further series of amounts, described as
“Provisional Quantities (allowances in the lump sum contract)”, with
a total
figure of $134,825. The Annexure concludes with the words “the
Lump Sum Contracts” and specifies a further amount of
$1,723,816.
8. The arbitrator noted that in the absence of any express
exclusion of GST it is normally taken to be included. This proposition
was not
disputed. The GST is, of course, simply a tax levied upon the supplier of goods
and/or services. Like sales tax, excise
or the various State and Commonwealth
taxes on petrol, it may be effectively recouped by the supplier increasing
prices charged to
customers. However, in the absence of a contractual term to
that effect, a customer does not assume any obligation to pay more than
the
agreed price. Hence, a customer at a service station is not obliged to add to
the amount shown on the bowser some further percentage
in order to reimburse the
supplier for the tax it is obliged to pay on the petrol.
9. The arbitrator
suggested that there were, however, other issues. He said that, whilst the
heading of Annexure C was immediately
followed by the words “Amount of Fee
(Clause 8.1)”, there was in fact no item in that Annexure that was
identified as
a fee. If, by this comment, he was intending to suggest that the
total of the amounts set out in Annexure C did not constitute the
fee payable
pursuant to cl 8.1 of the contract, then he was, in my opinion, clearly wrong.
He went on to refer to a revised quotation
made on 11 February 2004 which had
referred to a revised price of $1,723,816 “excluding GST” and
suggested that the fact
that the exclusion was not carried through to Annexure C
“would likely be treated as an oversight in the contract
administration”.
He noted that this had been disputed by Mr Aghili, a
director of the plaintiff company, but said that he did not accept his claim
that the changed basis for the fee had been discussed and agreed. The
arbitrator referred to the plaintiff’s letter of acceptance
of 12 February
2004, suggesting that it had been unusual though “not impossible” to
list two items with the same label
and that the reference to one clause in the
contract seemed “odd”. He also noted that Annexure A contained the
words:
“Total (excluding work in provisional sum items) (excluding GST)
$1,723,816”.
10. The arbitrator concluded with the following
statements:
Given the circumstances and the audit trail that existed at the time of offer and acceptance of the contract, I believe it is clear as to the intended meaning of the parties.
I go further, and on the basis of the contra proferentem rule, the parties’ arguments based on mistake or misrepresentation would result in a ruling against the party who had prepared such documentation, in this case, Techno Build.
Either way, I came to the same conclusion.
Accordingly, I rule that the proper interpretation of the contract sum included in Annexure C is that it excludes GST.
11. Mr Hausfeld, who appeared for the plaintiff, submitted that, in these
circumstances, there was a manifest error of law on the
face of the award.
Clause 8.1 of the contract provided for payment of the amounts listed in
Annexure C. The relevant provisions
were clear and unambiguous. Whilst there
was no express reference to the inclusion of GST in those amounts, the
arbitrator had rightly
observed that “by ATO advice and common
practice” the clause should be construed to include GST. Furthermore, Mr
Hausfeld
submitted that, in fact, the terms of cl 8.1 were quite incompatible
with the suggestion that a further unspecified charge should
be added to the fee
so specified. The arbitrator should simply have applied the terms of the
contract without advertence to the
course of pre-contractual negotiations or
other extrinsic material. It was true that Annexure A contained a reference to
the sum
of $1,723,816 “excluding GST” but this reference was on one
of a number of pages that were expressly stated not to be
part of the contract.
Hence, this reference, like the antecedent correspondence, was merely extrinsic
material that might properly
have been taken into account had there been some
real ambiguity in the contract itself. Since that situation had not arisen, the
approach adopted by the arbitrator had been contrary to the parol evidence rule:
see, for example Hoyts Pty Ltd v Spencer [1919] HCA 64; (1919) 27 CLR 133 at 143; Equuscorp Pty
Ltd v Glengallon Investments Pty Ltd & Ors [2004] HCA 55; (2004) 218 CLR 471 at 483. The
contra proferentem rule is merely one guide to construction that might be
invoked in cases of real ambiguity but that
this had not arisen. The suggestion
that it had been invoked in relation to “the parties’ arguments
based on mistake
or misrepresentation” merely revealed a misconception as
to the issues the arbitrator had been required to address.
12. In answer to
these contentions Ms Olsson SC, who appeared for the defendant, submitted that
the arbitrator had approached the
matter correctly. He had begun by attempting
to construe clause 8.1 and Annexure C. He had correctly noted that, in the
absence
of any indication to the contrary, it would have been appropriate to
construe those provisions as requiring payments of the stipulated
sum inclusive
of GST. Ms Olsson maintained, however, that he had been entitled to take into
account the words “excluding GST”
that qualified the total sum
referred to in Annexure A. This gave rise to an ambiguity in the contract and
the arbitrator had been
entitled to consider extrinsic evidence in order to
resolve it.
13. The obvious difficulty with this argument is that it
ignores the fact that the words relied upon do not form part of the contract
and
hence do not create the suggested ambiguity in its terms, though they may have
provided significant evidence in a suit for rectification
had one been
instituted.
14. Ms Olsson also submitted that I should take into account the
fact that the party complaining of the arbitrator’s reliance
upon the
evidence of pre-contractual negotiations had been the party who had introduced
such evidence at the hearing. That fact
may lend a tinge of irony to the
application but, at least in the absence of waiver or estoppel, I am unable to
see how the mere
adducing of such evidence could deprive a party of the right to
insist upon adherence to the parol evidence rule.
15. The arbitrator seems to
have examined the evidence carefully and he clearly identified real issues as to
the intention and understanding
of the parties. Those issues may have raised
questions about the implications of mutual or unilateral mistake or even about
whether
the contract should be rectified. However, the terms of clause 8.1 and
the Appendix C are, in my view, clear and unambiguous. It
was not open to the
arbitrator to effectively re-write the relevant portions of the contract by
purporting to adopt a “proper
interpretation” of them based upon his
opinion that they did not reflect antecedent negotiations or an annexed document
that
was not part of the contract. The extrinsic material may have provided an
arguable case for rectification of the contract so as
to make the amounts
payable pursuant to clause 8.1 exclusive of GST. However, no such claim was
ever articulated or referred to
the arbitrator for determination. He was merely
asked to determine the question, “what is the contract price including
GST?”
That question clearly required him to consider the price payable
pursuant to the contract in its current form. It did not authorise
him to
rectify it.
16. Ms Olsson stressed that it was incumbent upon the plaintiff
to demonstrate that any errors of law were manifest and not merely
arguable.
She cited the observations of Kirby P in Natoli v Walker (1994) 217 ALR 201 at
215 that:
This will seem a harsh decision to those who can show error in an arbitrator’s award . . . But that is the choice which parliament has deliberately taken. Judges must be faithful to that choice. They must obey it, even where their inclinations suggest that a detailed and painstaking review of the facts and the law might ultimately persuade them that the arbitrator has erred.
17. In the present case, however, it is clear from the face of the record
that the arbitrator departed from the parol evidence rule.
It is also clear
that he failed to provide any reasons for doing so or, indeed, even acknowledge
its existence.
18. In the circumstances, I am satisfied that the
arbitrator’s finding that the contract sum outlined in Annexure C excludes
GST, as founded on a manifest error of law on the fact of the award.
19. The
arbitrator appears to have adopted a somewhat similar approach in relation to
the counter claim by the plaintiff relating
to the fencing that it contends,
should have become its property at the completion of the works. In dealing with
this issue, the
arbitrator first turned to discussions that had allegedly
occurred during the tender/negotiation period before citing the relevant
provision in the contract that was in the following terms:
Fencing: Erect pre cast panels with concrete base 2.1 meter high (1050m approx) all around entire site.
On completion of civil work relocate the fencing to new site boundaries for building construction with four gates which will become TBD’s property.
20. The arbitrator suggested that the description of the fencing was strange
and that, read literally, the wording required precast
panels (or their bases)
2.1 meters high. It had been conceded that this had not been intended. During
the hearing Mr Aghili
had said that he had expected pre cast concrete
stabiliser bases with pipe posts and chain wire mesh. The arbitrator referred
to
what he described as “the Hughes Trueman fax dated 30 January
2004” and noted that it had referred only to an entry gate
rather than the
gates specified in the contract.
21. He also noted that the requirement for
relocation mentioned in that fax had not been an “ownership
requirement”.
After adverting to the contractual term providing for the
relocated fence to “become TBD’s property”, the arbitrator
said that: “If Aghili wants to enforce others strict compliance with what
is written, one need only remind him of his own words
used in Techno
Build’s letter of acceptance dated 11 February 2004, ie that the scope of
Sayer’s work was as briefed
by Hughes Trueman 9 December 2003”.
With due respect to the arbitrator, this statement seemed to reflect a view that
if one
wished to avoid compliance with a term of a written agreement one
“need only” advert to earlier correspondence in which
the other
party had taken a different approach. That is incorrect. The arbitrator
asserted that there had clearly been no such
ownership requirement as on 9
December 2003 and he went on to say that Mr Aghili had not explained why the
requirement specified
in the contract had differed from prior discussions
between Sayers and Hughes Trueman and from the documentation at item F9 within
the bill of quantities. He also suggested that Mr McMillan had not been aware
of the requirements in the opening text to Annexure
A when he executed the
contract. He added that item F9 within the bill of quantities was not priced at
a sufficient amount of money
to allow for “precast panels with concrete
base 2.1 metres high” to become the plaintiff’s property upon
completion
of civil work or, on the evidence presented, for even precast
stabiliser bases with chain wire mesh above. The arbitrator concluded:
If I were generous, I would rule a mistake with the insertion of words in Annexure A that were not intended.
If I were less generous, I would rule a deliberate insertion of words in Annexure A not documented, agreed or intended between the parties.
Either way, I believe that what was intended by the parties and what should have been documented in the 12 February 2004 contract were words giving effect to the provision of temporary fencing and upon which, in the absence of any qualifications in its tender, Sayers submitted its tender of 11 February 2004.
It is that tender and that scope to which Techno Build’s acceptance of tender dated 12 February 2004 applies.
...
I rule that Techno Build has no claim to ownership of the fencing provided by Sayers as of the date of Practical Completion and accordingly its counter claim fails.
22. Ms Olsson maintained that this approach had been defensible because the
relevant clause had specified a type of fencing that
the parties had not
intended. Given the concession made by Mr Aghili to this effect, I accept that
the arbitrator did not fall into
error in finding that there had been an
unintended misdescription of the fencing and in treating the clause as requiring
the construction
of a chain wire fence with concrete stabiliser
boxes.
23. There was, however, no legal justification for ignoring the
plaintiff’s contractual entitlement to acquire ownership of
the
fence.
24. Mr Hausfeld challenged the finding that Mr McMillan had not been
aware of this requirement, pointing out that Mr McMillan had
initialled the very
page upon which the clause was contained. That may be so, but this finding was,
of course, one of fact rather
than law, and for present purposes may be
disregarded.
25. More fundamentally, it is clear that the arbitrator did not
seek to construe the relevant contractual clause but rather to deduce
“what should have been documented” in the contract. It was
incumbent upon the arbitrator to adjudicate upon the rights
and obligations of
the parties as they arose under the contract as it stood. It was, of course,
open to him to seek to resolve any
ambiguity in its terms and, had such an issue
arisen, he would have been entitled to consider the course of pre-contractual
negotiations
and other extrinsic material for that purpose. In my view that
situation did not arise. He did not find the relevant contractual
provision
ambiguous. He merely declined to apply it. He proceeded to treat the contract
as if it had been rectified by the exclusion
of the relevant provision on the
ground that there was either a unilateral mistake by Mr McMillan or mutual
mistake. These findings
would not have supported a plea of non est factum had
one been made or, so far as I could see from the available material, provided
an
adequate basis for rectification of the relevant clause had such an issue been
identified and referred for arbitration.
26. In essence, the arbitrator was
asked to resolve a number of differences that had arisen under a commercial
contract between two
companies that were bound by its terms. In respect of the
two issues raised by the plaintiff, he ignored the parol evidence rule
and
purported to construe the contract in a manner that essentially involved
re-writing its terms.
27. In each case, I am satisfied that the determination
of the question of law concerned could substantially affect the rights of
both
parties to the arbitration agreement and that there is a manifest error of law
on the face of the award. I am also satisfied
that it would be appropriate to
exercise my discretion to grant leave to appeal.
28. Ms Olson submitted that,
if leave were to be granted, it should be subject to a condition that at least
some of the amount awarded
by the arbitrator be paid into court. In the
circumstances, I do not think that this would be appropriate. On the other hand
any
appeal should be pursued with expedition and I see no reason why it should
not be instituted within 7 days.
29. The defendant has applied in separate
proceedings for an order that would enable that judgment be entered in
accordance with the
award and it is appropriate for that application to be
stayed pending the appeal.
30. I will hear counsel as to costs.
I certify that the preceding thirty-two (32) numbered paragraphs are a true copy of the Reasons for Judgment herein of his Honour, Justice Crispin.
Associate:
Date: 8 August 2007
Counsel for the plaintiff: Mr S Hausfeld
Solicitor for the plaintiff: J S
O’Connor Harris & Co
Counsel for the defendant: Ms E Olsson
SC
Solicitor for the defendant: Meyer Vandenberg
Date of hearing: 11 May
2007
Date of judgment: 4 July 2007
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/act/ACTSC/2007/60.html