![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of the ACT Decisions |
IN THE SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY MILES CJ CORPORATIONS - application under sub-s.459G(1) to set aside a statutory demand - whether bona fide dispute relating to amount claimed in demand - power to make an order to set aside/vary statutory demand subject to conditions, s.459M - set off or counter claim, ss.459H, 459J - demand varied to allow for dispute over rectification already carried out to alleged faulty paintwork but not to allow for further alleged counter-claiming. Corporations Law, sub-s.459G(1) Fleming on Torts (8th ed) (1992) at 637 Mibor Investments Pty Ltd v. Commonwealth Bank of Australia (1993) 11 ACSR 362 Chadwick Industries (South Coast) Pty Ltd v. Condensing Vaporisers Pty Ltd (1994) 13 ACSR 37 CANBERRA, 7 and 12 November 1997 (hearing), 20 March 1998 (decision) #DATE 20:03:1998 Appearances Counsel for the applicant: Mr. C.M. Erskine Solicitors for the applicant: Colquhoun Murphy Counsel for the respondents: Mr. I. Byrne Solicitors for the respondents: Hill & Rummery THE COURT ORDERS THAT: The statutory demand dated 25 August 1997 served on the applicant by the respondents be varied by inserting into the Schedule thereto immediately above the line marked Balance the words and figures "Less claimed by the company for rectification of faulty paintwork $10,000" and further by deleting the figure 64,459 wherever appearing and substituting the figure 54,459.00 subject to the following conditions: (1) The applicant within 21 days file and serve upon the respondents' solicitors a statement of claim setting out the particulars of its claim against the respondents for alleged faulty workmanship in respect of the Dowling contract limited to a total claim of $10,000. (2) The respondents within a further 21 days file and serve their statement of defence. (3) The applicant within a further 14 days file and serve any reply. (4) The matter be listed for further directions on Friday, 8 May 1998 at 9.30 a.m. MILES CJ 1. On 12 September 1997 the applicant filed an application under sub-s.459G(1) of the Corporations Law seeking an order to set aside a statutory demand served upon it by the respondents dated 25 August 1997. The application came before the Court for hearing on 7 November 1997. Evidence was taken and limited submissions were made. On 12 November 1997 I indicated that I was minded to make an order to set aside or vary the statutory demand, but only upon condition that the applicant proceed forthwith to prosecute a counter-claim against the respondents; possibly, upon further condition that the parties accept mediation; alternatively, instead of making an order to set aside or vary the statutory demand, ordering that the proceedings on the statutory demand be stayed pending formulation of issues in the ordinary way by the filing and exchange of pleadings. Being unsure of the power to make orders in the nature of those proposed, I gave leave to the parties to file further submissions in writing in accordance with a time-table limited to the nature and terms of the orders to be made. The submissions in writing have been received, not all of them within the time-table laid down. 2. For the purpose of the application to set aside the statutory demand I make the following findings of fact and I state the issues for determination on that application. 3. The applicant was engaged in construction work on separate parcels of land in Torrens Street, Braddon. There was to be a block of apartments on each parcel of land. One block was called "The Dowling". The other was called "The Vail". 4. The applicant and the respondents entered into two separate contracts in which the respondents agreed to paint certain areas in the respective apartment blocks. (In the language of the construction industry the applicant was probably the head contractor and the respondents were the painting sub-contractors.) According to the applicant, the undated Dowling contract was entered into on or about 14 May 1996. The Vail contract was dated 22 November 1996. The respondents carried out painting work in accordance with their obligations under the two contracts. They claim that they completed the work contracted for and that they did it properly. After allowing for payments on both contracts, the respondents are owed $64,459.00 by the applicant for the work they did. 5. The applicant raises by way of defence that the work was not completed within the times set by the contracts, that the work done on each building, or some of it, was not carried out to the standard required by the contract and that some of the work was not completed. Those are familiar enough defences to a claim for work done in the construction industry. In addition, the applicant claims that the respondents colluded with the applicant's then project manager to render false invoices for the work done and that this collusion has resulted in loss and damage to the applicant. The applicant claims in summary that there has at all times been a bona fide dispute between the parties which disentitled the respondent from issuing a statutory demand. 6. The relevant evidence on affidavit establishes the following: _ In or about the middle of June 1996 Malcolm Naylor, the applicant's project manager approached Mr Trussler, the site foreman on the Dowling project, and told Mr Trussler that he was worried about budget over-runs, that the expected profit on the Dowling project was "disappearing fast" and that he needed to "transfer some of the costs to the Vail". _ On or about 20 September 1996 Mr Naylor told Mr Trussler to transfer $50,000 of the Colour Our World contract "from the Dowling to the Vail". _ On or about 27 September 1996 Mr Stipancic, the first respondent, Mr Naylor and Mr Trussler met. Mr Naylor said to Mr Stipancic that he wanted to "transfer some funds from the Dowling to the Vail" that this would not affect Mr Stipancic's prices for the "overall contract on the Dowling" and that the only difference would be that the "payment advice will have a different job name on it". Mr Stipancic agreed with the proposal. _ On or about 1 October 1996 Mr Trussler advised Mr Stipancic that if he did what Mr Naylor wanted he would get his "money from the Dowling". _ On 5 October 1996 in response to Invoice 108 received from Mr Stipancic, Mr Trussler prepared and sent to the applicant's office a progress payment certificate number 8 bearing that date and marked "The Dowling". The certificate bore a column of figures at the bottom of which and alongside a box marked "This Payment" appeared the figure of $28,500. _ On the same day Mr Naylor asked Mr Trussler to "transfer Invoice 108 to the Vail". Mr Naylor prepared a new and different progress payment certificate in similar form to the one dated 5 October 1996 and marked "the Dowling", but dated 4 October 1996 and marked "Vail Apart". This latter progress payment certificate contained a column of figures different from those in the previous progress payment certificate, but at the bottom the figure for "This Payment" is the same, namely $28,500. There is no evidence that Mr Stipancic had anything to do with the latter certificate. _ On or about 19 October 1996 Mr Trussler received an invoice numbered 109 from Mr Stipancic. This invoice was dated 18 October 1998. It was marked "Vail units" and bore a figure of $20,000. In response Mr Trussler sent invoice 109 together with a memorandum to the applicant's site administrator for the Dowling contract. The documents were accompanied with a written request as follows: "Would you process Colour Our World for 20,000 this should complete the transfer to 50,000". 7. From this evidence the conclusion is open that the applicant paid the respondents $50,000 less than what was owed for the Dowling project and $50,000 more than what was owed for the Vail project, but with the net result that the applicant paid to the respondents no more and no less than what was owed for the total painting work carried out on both projects. 8. There is nothing in the evidence to indicate any fraudulent intent on the part of the respondents or any loss accruing to the applicant as a result of anything done by Mr Stipancic. If there was any loss to the applicant there is no evidence that Mr Stipancic knew that it was likely. There is no evidence that Mr Naylor was acting other than in accordance with what he understood to be the interests of the applicant and in accordance with his authority. There is no arguable basis for any claim that the applicant has a set-off or counterclaim against the respondents in the nature of a tortious claim, whether in deceit, conspiracy or anything else. 9. There is no evidence of any loss to the applicant as a result of Mr Stipancic acceding to Mr Naylor's request to render an invoice claiming payment for work on the Vail contract which was in truth for work done on the Dowling contract. Damage is "of the gist" of the tort of deceit: Fleming on Torts (8th ed) (1992) at 637. Actual damage may not be necessary in an action for conspiracy but proof of intent to injure is necessary: see Fleming on Torts at 705-707. The applicant does not have an arguable claim in deceit or conspiracy against the respondents. 10. The applicant has not shown that it could recover more than nominal damages even if it was successful in a claim in tort against the respondents. However, the dispute that the applicant seeks to rely upon in order to avoid the consequence of non-compliance with the statutory demand, extends to an assertion that the paintwork was neither completed, nor carried out satisfactorily. 11. A complaint about lack of completion of "rectification work" to the ceilings, corridor walls and unit entrance doors of the Dowling was made by the applicant by an undated letter following a meeting of 23 April 1997. A list of alleged defects was prepared by Alliance Properties Limited, apparently the proprietor on whose behalf the Dowling was being constructed. It was dated 17 July 1997. A copy of the list of alleged defects was sent to the respondent on 3 September 1997. The alleged defects were rectified by Katrina Menzies Painting at a cost of $10,000. Another painting contractor submitted a quotation presumably for the same work at a total of $17,850, and another contractor at $34,280. Katrina Menzies has submitted a quotation for $31,850 for further work. There is evidence in the form of a letter (undated and marked "without prejudice") from Master Painters Australia that the painting overall has been carried out in an acceptable manner and that there has been considerable damage to painted surfaces by tradespersons and also some bubbling of paintwork due to moisture. The applicant's case has not been presented with sufficient clarity for me to be satisfied that there is a bona fide claim by the applicant that the further work quoted for at $31,850 or any further rectification is required as a result of any failure on the part of the respondents. 12. On the evidence as it stands, I am not satisfied that there is a bona fide dispute about the completion of the paintwork on the Vail project. The applicant claims that the respondents did not complete the painting of the basement of the car park of the Vail project. Mr Stipancic's affidavit deposes that conversations about possibly painting the car parks on both projects came to nothing. I see no reason to reject that evidence for the purposes of the application. 13. The provisions of the Corporations Law relating to statutory demands were examined by Hayne J. in Mibor Investments Pty Ltd v. Commonwealth Bank of Australia (1993) 11 ACSR 362. At 366 his Honour concluded as follows: "First, any application to set aside a statutory demand must be made very quickly: it must be made within 21 days. Second, the statute contemplates a summary procedure, the only outcome of which will be an order affecting the statutory demand, not any order or judgment declaring a debt to be owing or not to be owing or ordering payment of any money sum. Third, the only significance that the statutory demand has is that if there is failure to comply with it then the company is deemed to be insolvent. Thus the demand is no more than a precursor to an application for winding up in insolvency. Fourth, an application to wind up in insolvency must be determined within six months (unless the court is satisfied that special circumstances justify an extension of that time): s.459R. Fifth, on the hearing of the application to wind up, the company may not oppose the application on grounds that it might have taken in any application to set aside the demand, unless those grounds are material to proving that the company is solvent. 14. These matters, taken in combination, suggest that at least in most cases, it is not expected that the court will embark upon any extended inquiry in order to determine whether there is a genuine dispute between the parties and certainly will not attempt to weigh the merits of that dispute. All that the legislation requires is that the court conclude that there is a dispute and that it is a genuine dispute." On p.368 his Honour further observed: "If the demand stands, the consequences are serious but there is no final determination of any right. All that follows from the demand not being set aside is that the company will have a further perhaps short period within which it must meet the demand, or face a conclusion that it is to be presumed insolvent (unless it proves the contrary). No order can be made under s.459G which finally determines the rights of parties." 15. In the later case of Chadwick Industries (South Coast) Pty Ltd v. Condensing Vaporisers Pty Ltd (1994) 13 ACSR 37, Lockhart J. surveyed some of the case law and commented as follows (at 39): "Certainly the court will not examine the merits of the dispute other than to see if there is in fact a genuine dispute. The notion of a "genuine dispute" in this context suggests to me that the court must be satisfied that there is a dispute that is not plainly vexatious or frivolous. It must be satisfied that there is a claim that may have some substance. On the other hand the court must be careful, because if all an applicant has to do is to assert both a claim and some basis for it, without more, it would mean in almost every case that the court would set aside statutory demands where application is made to that effect. Plainly that is not what the legislature intended by introducing this new regime." 16. On the principles enunciated by their Honours, with which I respectfully agree, I come to the conclusion in this case that there is a genuine dispute between the parties limited to the matter of the standard of workmanship of the painting work carried out by the respondents on the Dowling project which was rectified at a cost of $10,000. I am not convinced that there is any genuine dispute at all between the applicant and the respondents in relation to what the applicant asserts to have been fraudulent or unauthorised conduct on the part of one or more of its own employees or officers conspiring with Mr Stipancic. Nor am I convinced that the claim made on behalf of the applicant in relation to the alleged failure of the respondents to paint part of the parking area of the Vail project is a genuine claim. The claim that the work was not completed in time may have some substance but it does not give rise to a dispute in any relevant sense as no arguable case has been made out to show that delay in completion caused financial loss to the applicant. 17. It is conceded by counsel for the applicant that there is a power to make an order setting aside a statutory demand subject to conditions. The concession appears proper. Section 459M to which I was referred by counsel for the respondents in written submissions provides that an order under s.459H or 459J may be made subject to conditions. Further, as Hayne J observed, "if there is a genuine dispute or an offsetting claim, the court must calculate the substantiated amount of the claim in accordance with a statutory formula". 18. Certain consequences follow relating to the Court's power to set aside or vary the demand. The submissions of counsel did not condescend to touch on this aspect. For the purposes of s.459H, doing the best I can for myself, I find, in accordance with the formula, that the "admitted total" of the debt owing by the applicant is $64,459.00 and that the "offsetting total" claimed by the applicant is $10,000. The substantiated amount is therefore $54,459. That amount is "at least as great as the statutory minimum" fixed by s.9 at $2,000. The Court, therefore, has the power under sub-s.459H(4) to vary the statutory demand. I propose to exercise that power. 19. As far as the demand is concerned, it is varied by reducing the claim by the disputed $10,000 and subject to the following conditions: (1) That the applicant within 21 days file and serve upon the respondents' solicitors a statement of claim setting out the particulars of its claim against the respondents for alleged faulty workmanship in respect of the Dowling contract limited to a total claim of $10,000. (2) That the respondents within a further 21 days file and serve its statement of defence. (3) That the applicant within a further 14 days file and serve any reply. (4) That the matter be listed for further directions on Friday, 8 May 1998 at 9.30 a.m.
AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.austlii.edu.au/au/cases/act/ACTSC/1998/276.html