AustLII [Home] [Databases] [WorldLII] [Search] [Feedback]

Supreme Court of the ACT Decisions

You are here:  AustLII >> Databases >> Supreme Court of the ACT Decisions >> 1998 >> [1998] ACTSC 179

[Database Search] [Name Search] [Recent Decisions] [Noteup] [Download] [Help]

Commonwealth of Australia v Silverton Limited, Commonwealth Banking Corporation, Peabody Resources Limited, W L Meinhardt & Partners Pty Limited, Dowell Australia Limited, C.C.N. Pty Limited (trading as Cameron Chisholm & Nicol) and Bond James Laron and Murtagh Pty Limited (in Liquidation) [1998] ACTSC 179 (20 March 1998)


  
  
  
  
  

  
   Downlaod RTF

  

   IN THE SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY

   HIGGINS J

  

  

   DAMAGES
- Quantum - Where no admissible evidence as to cost of item
properly claimed - Reasonable amount allowed - Interest on residual value
of
fitout - Where defendant liable for cost of temporary accommodation - Interest
payable from date of vacation of premises.

  

   ACT v Vucetic (Supreme Court of the Australian Capital Territory, Higgins
J, 29 November 1991, unreported); referred to

   Arnall
v Cheminees Phillippe Australia Pty Limited (Supreme Court of the
Australian Capital Territory, Higgins J, 18 August 1995, unreported);
referred
to

   Collin v Botany Crane & Fork Hire Pty Limited and Anor [1993] ACTSC 9;  (1993) 113 FLR
83; referred to

  

  

   CANBERRA, 9, 10 March 1998 (hearing), 20 March 1998 (decision)

   #DATE 20:03:1998

  

   Appearances

   Counsel for the Plaintiff: Mr D Shavin QC with Mr R Vivekananda

   Instructing Solicitors: Australian Government
Solicitor

  

   Counsel for the Defendant: Mr M F Adams QC with Mr R J Weber

   Instructing Solicitors: Blake Dawson Waldron

  

  

  

   Order:

   The parties have leave to make further submissions as to the calculation of
interest and costs.

  

 
 1. On 2 October 1997 I made certain rulings concerning the claim for
damages by the plaintiff against the second defendant. Those
rulings were
intended to enable the second defendant to agree with the plaintiff as to the
quantum of damages to be awarded. That
agreement was not designed to affect
the right of either party to challenge those rulings on appeal. It was
intended to enable consensus
to be reached on the quantum of damages if the
rulings I made were to be accepted as correct.

  

   Regrettably, not all matters
have been so resolved. Happily, most have
been. Further, during the hearing concerning those matters on 9 and 10 March
1998, further
matters became agreed subject, of course, to the reservation I
have mentioned.

  

   I will now refer to those items not now the
subject of agreement.

  

  "ANAO Expenses"

  

  ""Item 3. Damage to Safe $1520 4. The plaintiff sought leave to point to a
document
reporting to its solicitors that the "damage to safe" was, in fact,
the accidental triggering of an anti-theft device which necessitated
work to
replace and reset the device. The device was triggered by the movement of the
safe. Even allowing for the weight which can
be attached to business records,
this statement, made only to the plaintiff's solicitors, was not from a
contemporaneous source.
There was no invoice or record of payment nor even any
secondary documentation supporting the instructions given to the solicitors.

  

   There is, therefore, no evidence supporting this claim. However, even so,
it is not clear to me why ANAO, the owner of the
safe, could not have arranged
for the safe to be moved without triggering the device in question.

  

   Item 5. Storage Charges
$2911

  

   Unfortunately, the question raised in the judgment, namely, the reason for
such expense was not addressed. Consequently,
there is no further material
enabling the expense to be allowed, even assuming that it has been proved that
it was incurred.

  

   Item 36. Storage Charges $9181

  

   These charges were no better supported than Item 5 (supra). They cannot be
allowed.


 

   Item 39. Carpet Charge $2832 8. The nature of the claim has now been better
explained. It was, in fact, not "cleaning" but
rather treatment to prevent
static electricity build-up. Why that was necessary or relevant to ANAO's
occupation of Medibank House
is not clear. The plaintiff cannot locate or
point to any contemporaneous record to support this claim and it must
therefore be rejected."DSS
Expenses"

  

  ""Item 27. D&N Floor Coverings $35,176

  

   That carpet was supplied and laid may be accepted. The cost of
it, however,
is supported only by a memorandum to the plaintiffs solicitors making a claim
in that sum. There is a report supporting
the need for carpet replacement.

  

   I am, therefore, left in a position where I can conclude, and I do, that
carpet replacement
was necessary but I have no admissible evidence as to cost.

  

   11. It is not the law that, as a result, the plaintiff must fail
to recover
any damages for this item. The difficulty of assessment does not justify a
refusal to award anything, see ACT v Vucetic
(Supreme Court of the Australian
Capital Territory, Higgins J, 29 November 1991, unreported), Arnall v
Cheminees Phillippe Australia
Pty Limited (Supreme Court of the Australian
Capital Territory, Higgins J, 18 August 1995, unreported). Some expense must
have been
incurred. The carpet must have been at least of fair average quality
suitable for a reasonably busy office. The carpet supplier and
layer, whoever
it was, could not be regarded as being so charitably inclined as to make a
gift of a substantial area of good quality
new carpet to the Commonwealth. I
must not award more than is claimed. I have the advantage of having inspected
the place where the
carpet was laid. Bearing in mind that reasonable carpeting
would be needed, DSS being a high traffic operation, I think $30,000 is
a fair
estimate of the reasonable cost of new carpeting. Item 35. Atlas Air -
Computer Room air conditioning unit $11,869 12. During
the course of this
hearing, those representing the plaintiff were able to locate documentary
support for this expense. I will therefore,
allow $11,869. That allowance was
conceded as appropriate by those representing the second defendant, at least
as a matter of calculation.
Legal - Lease Renewal Expenses $4500""13. This claim concerned the allowance which should be conceded for legal fees
for the exercise
of the option to renew the Silverton Centre Sublease. The
plaintiff says that the sum should be nothing or close to it. Only a letter
would be required. The second defendant says the sum referred to above is more
realistic.

  

   Not only is there no evidence of
the usual legal cost of commercial lease
renewals pursuant to an option but necessarily, the expense to be anticipated
must be, to
a degree, uncertain.

  

   15. If there is no dispute between the parties a minimal cost may be
expected. However, drawing on judicial
notice of the realities of legal
practice, I cannot see less than $1,000 being charged by solicitors for a
tenant seeking to exercise
an option. I think it likely there would be some
negotiation, at least upon the subject of future rental. Further, given APG's
attitude
to improving accommodation standards, I think it reasonable to
suppose that there would have been some attempt to improve the lease
conditions. The probabilities are that considerably more than $1000 in then
current dollar values (ie at date of breach) would have
been both anticipated
and warranted.

  

   I would therefore, as a matter of impression, allow $2,500.

  

   Pre-commitment Lease
fees $81,471 17. This represents expenses, originally
assessed at $88,106, claimed for negotiating new leases for the Silverton
departments,
principally in relation to Centenary House. This is after
allowance for the chance that new leases might need to be negotiated before
the end of the sublease and its optional further term in any event.

  

   The plaintiff argues that although it may be that this
claim is for a
greater expense than would be incurred in respect of a building already set
up, like Sir Keith Campbell Building,
the negotiations saved money on the
eventual fitout of Centenary House.

  

   19. All that may well be so. However, it seems to
me that, in reality, no
more than a reasonable fee should be allowed. There is nothing to suggest that
the claimed expense is "reasonable"
by comparison with the other options
reasonably open to accommodate ANAO.

  

   Although some search expense may be accepted as
inevitable, I would not
allow more than the $22,733 conceded by the second defendant.

  

   Projected Cost of General Refurbishment
- offset of $1,052,382

  

   The plaintiff contended that to allow an offset for this sum would,
effectively, give a windfall benefit
to the second defendant. It would give an
offset for refurbishment without an allowance for the new fitout required to
replace the
old one.

  

   I agree. I think the second defendant ultimately conceded that to be so, at
least implicitly.

  

   23. The analogy
is with a motor vehicle negligently damaged and written
off. If the owner is entitled to the then lost value of it, the defendant
cannot claim an offset for maintenance which should have been expended upon it
in the future. Conversely, the owner cannot claim
the cost of a new but
similar motor vehicle if it exceeds the lost value.

  

  "Interest on Residual Value of Fitout"

  

   24.
This is to some extent related to the previous contention. The second
defendant argued that, whilst the plaintiff is entitled to
the value of the
fitout at the Silverton Centre lost because of the vacation of the Centre, it
should not have interest on that lost
value from that date. The reason
advanced was that the second defendant has been held liable to pay for the
temporary accommodation
of the Silverton departments pending their removal to
permanent (at least to 2003) accommodation to the extent that those expenses
exceeded the ongoing cost of continuing at the Centre.

  

   25. It seemed to me, however, that the reason advanced does not affect
the
entitlement of the plaintiff to pre-judgment interest. A party is, subject to
the Court's discretion, prima facie entitled to
pre-judgment interest, not
only for monies expended, but also upon the value of an asset from the date of
its destruction (see, eg.
Collin v Botany Fork & Crane Hire Pty Limited
and Anor [1993] ACTSC 9;  (1993) 113 FLR 83. If, for example, stores are utilised to replace
goods damaged or destroyed, the result is no different, in principle,
from the
payment of money to purchase replacement goods for such use. The owner of the
stores, in running down stock, loses the current
market value of that stock.
That loss occurs on utilisation.

   26. It is no different when loss of a fitout is considered. The
fitout had
a current value. It was, notionally, "destroyed" (less salvage) on vacation of
the Centre. That was when the value of
it was lost. The claim for compensation
for that loss, agreed as a matter of calculation at $1,388,198, represents a
sum to which
the plaintiff became immediately entitled.

   The plaintiff did temporarily relocate the Silverton departments. It has
been held
entitled to receive compensation for the additional expenditure
reasonably and proportionately incurred, less any salvage able to
be obtained.

   28. It is analogous to the situation where a chattel, used to further the
commercial interests of the owner, is
wrongfully destroyed. The owner, as I
have explained previously in my Reasons dated 2 October 1997, is entitled not
only to the value
of the chattel at the date of its loss, but also the cost of
the temporary hire of a replacement "chattel" so far as is reasonably
necessary and proportionate. That is simply a mitigation of loss otherwise
likely to be greater. The value of the destroyed chattel,
however, should
notionally remain available to the owner to invest in a permanent replacement
chattel.

  

   29. However, the owner
is neither entitled to the cost of the replacement
chattel whether or not it exceeds that value foregone nor obliged to expend
the
"lost value" on it. It follows that if judgment for the lost value is to
be given, prima facie the owner is entitled to interest
pre-judgment on the
lost value from the date of that loss. The temporary accommodation compensates
for loss flowing from lack of
availability of the income producing asset, not
loss of its value.

  

   30. Interest is, nevertheless, discretionary. For example,
a party who has
unreasonably delayed taking proceedings may be denied a full award of
interest. I pointed out in my Reasons of 2
October 1997 (at 45-54) that the
rate of interest allowable is, though subject to a practice direction
specifying a usual commercial
rate, still discretionary.

  

   31. Further, as Miles CJ pointed out in Collin v Botany Fork & Crane
Hire Pty Limited, supra,
at 91, delay in bringing proceedings may make it fair
to reduce the sum otherwise payable for interest.

  

   32. In the present
case, it is not alleged that the plaintiff failed to
seek redress as soon as practicable. It is not alleged that it unreasonably
delayed relocating the Silverton departments to permanent accommodation.

  

   33. It seems to me that interest on the residual
value of the fitout should
be allowed from the date of the vacation of the Centre until judgment at the
rate I decided in my previous
Reasons to be the applicable rate."Conclusion" It follows from the above that there will be a verdict for the
plaintiff against the
second defendant, calculated as follows:

  

  
TABLE

   Residual fitout $1,388,198.00
   ANAO expenses 619,867.00
   DSS expenses
278,494.00
   DASETT expenses 33,851.00
   APG expenses 149,326.00
   Valuation 6,580.00
   Legal ($2,500 for future) 9,465.00
 
 Make Good 129,000.00
   Advertising for Permanent Accommodation 3,021.00
   Precommitment Lease fees 22,733.00
   ____________

 
   $2,640,535.00
   ____________
  
   Allowances
   Electricity $64,168.00
   Security 22,478.00
   Outgoings 3,806.00
   __________
   90,452.00 less $90.452.00
   ____________
  
   Net sum for judgment $2,550,083.00
   ____________
   34. It seems to me that
sum is the appropriate figure for judgment. I will,
before ordering judgment, hear the parties as to the calculation of interest.
That calculation will be somewhat complex in view of the differing dates of
the accrual of allowances and incurring of expenses.
   I will hear the parties further as to costs.
  
  
  




AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.austlii.edu.au/au/cases/act/ACTSC/1998/179.html